36 sqm High-Density Heavy-Load Computer Room

Table of Contents

1. Cover / Document Information

– Document Title: 36㎡ High-Density Heavy-Load Computer Room System Technical Design Solution

– Prepared by: Guangzhou Lain Intelligent System Development Co., Ltd.

– Brand: KITOZER (Pioneer)

– Date: August 2026

– Version: V1.0

– Project Type: Technical design solution for 36㎡ High-Density Heavy-Load Computer Room System

2. Table of Contents Structure

1. Company Introduction

2. Project Overview

3. User Requirement Analysis

4. Overall Design Description

5. Detailed System Design and Product Technical Parameters

6. Project Quotation and Configuration List

7. Core Solution Advantages

8. Technical Q&A

9. Construction Schedule Plan

10. Construction Organization Plan

11. After-Sales Service System

12. Operation and Maintenance Training Plan

13. Typical Project Cases

14. SEO Optimization System and Website Backend Configuration

15. Contact Information

3. Company Introduction

3.1 Company Development Overview

Founded in 2002, Guangzhou Lain Intelligent System Development Co., Ltd. is a high-tech enterprise dedicated to the computer room construction and intelligent protection field for more than two decades, integrating R&D, production, sales, engineering implementation and after-sales service. The company focuses on innovative breakthroughs in electromagnetic shielding technology, modular computer room technology and computer room environmental monitoring technology, and has grown into a source manufacturer with core competitiveness in the domestic computer room construction field.

After more than twenty years of industry accumulation, the company has built a large-scale production and manufacturing base equipped with advanced CNC sheet metal processing equipment, automated spraying production lines and professional testing laboratories, with an annual production capacity of hundreds of sets of shielding computer rooms, integrated cabinets and micro-module products. The company’s service network covers all provinces and cities across the country, providing thousands of computer room construction and renovation services for customers in government, military, scientific research, finance and enterprise fields.

3.2 Core Business System

The company’s core business revolves around the full-lifecycle construction of computer rooms, forming four major product and service systems:

– Computer room EPC general contracting service: one-stop services from solution design, manufacturing, on-site construction to commissioning and acceptance, covering shielding computer rooms, IDC data rooms, modular computer rooms, container computer rooms and other types;

– Core equipment R&D and production: independently produces KITOZER brand series products, including shielding cabinets, shielding desks, consoles, integrated data cabinets, micro-module cold aisle cabinets, outdoor rainproof cabinets, etc., supporting non-standard customization;

– Computer room environmental monitoring system: provides full-element monitoring solutions for temperature and humidity, water leakage, access control, video, fire protection, UPS and power distribution, realizing intelligent and unattended O&M;

– Shielding and security protection products: shielding rooms, shielding doors and windows, anechoic chambers and related auxiliary materials, widely used in confidential, military and scientific research fields.

3.3 Brand and Qualification Honors

The core brand KITOZER (Pioneer) focuses on computer room equipment and shielding products, positioned as an “efficient, green, innovative and safe” solution provider. Products have passed multiple authoritative tests and comply with national and industry standards. The company holds multiple utility model patents and software copyrights, has been awarded high-tech enterprise qualification, and follows the ISO9001 quality management standard.

3.4 Core Competitive Advantages

1. Source production, controllable quality: own production base and professional processing equipment; core products independently produced with full-process quality control, providing more cost-effective solutions without intermediate links;

2. Customized design, matching needs: tailor-made solutions per site conditions, technical requirements, configuration and budget, with multiple design options provided free of charge;

3. Professional team, rich experience: a professional technical team of engineers and project managers with more than ten years of industry experience;

4. Quality after-sales, full guarantee: a 7×24 professional online service system with dedicated project follow-up from early coordination to later O&M.

4. Project Background and Objectives

4.1 Project Background

With the acceleration of enterprise digital transformation, the computing density of IT equipment continues to rise, and traditional computer rooms can no longer meet the deployment needs of high-density computing equipment. This project is a newly built enterprise core data computer room with a net area of 36㎡, planning to deploy 8 high-density server cabinets with an IT load power of 20kW per cabinet. Due to building constraints, no air conditioner outdoor units can be installed inside the room or on external walls, and there is no preset drainage point in the room, requiring a complete computer room solution fully adapted to this special scenario.

4.2 Construction Scope

This project is a computer room infrastructure turnkey project, with the construction scope covering:

– Cabinet and cold aisle containment system;

– Cooling system (adapted to no-outdoor-unit, no-drainage-point scenario);

– Power supply and distribution system (including UPS uninterruptible power supply);

– Environment and power monitoring (DCIM) system;

– Heptafluoropropane gas fire extinguishing system;

– Lightning protection and grounding system;

– Computer room decoration works;

– System integration, commissioning and acceptance.

4.3 Construction Objectives

This project is designed per the Class A standard of 《Data Center Design Specification》GB 50174, building a safe, reliable, energy-efficient, intelligently operated and scalable high-density data computer room. Specific objectives:

– Meet the high-density, heavy-load power supply and heat dissipation needs of 8 cabinets at 20kW each, ensuring 7×24 stable IT equipment operation throughout the year;

– Fully adapt to the building constraints of no outdoor unit and no drainage point, without damaging the building structure and with convenient construction;

– Build a full-dimension environment and power monitoring system for real-time monitoring and intelligent alarming of power distribution, temperature and humidity, water leakage, access control, video and fire status;

– Establish a complete fire protection and lightning protection grounding system meeting national specifications to ensure personnel and equipment safety;

– Reserve more than 15% expansion margin in the solution to support smooth upgrades for future business growth;

– Adopt green energy-saving design to improve energy utilization efficiency, with PUE controlled within 1.4.

5. User Requirement Analysis

5.1 Basic Scenario Constraints

– Room area: net area 36㎡, about 8m long × 4.5m wide, floor height ≥3.2m;

– Installation constraint: no air conditioner outdoor unit can be installed indoors or on external walls; the cooling system must not use split-type outdoor units;

– Drainage constraint: no preset drainage riser or floor drain in the room; cooling system condensate must not be discharged externally;

– Power supply condition: one three-phase 380V mains incoming line with capacity ≥300kVA;

– Grounding condition: the building has a combined grounding network with grounding resistance ≤1Ω, accessible nearby.

5.2 Cabinet and Aisle Requirements

– Configure 8 standard 42U server cabinets meeting the installation and load-bearing needs of 20kW equipment per cabinet;

– Adopt cold aisle containment to improve cooling efficiency and reduce local hot spot risks;

– Cabinets need complete cable management, grounding design and ventilation structure adapted to high-density equipment wiring and heat dissipation;

– Each cabinet is equipped with dual-circuit redundant intelligent PDU for dual-power supply and monitoring.

5.3 Cooling System Requirements

– Total cooling capacity meets the 160kW IT load heat dissipation requirement with N+1 redundancy;

– Adopt a no-outdoor-unit cooling solution adapted to cold aisle layout with high near-end cooling efficiency;

– Condensate adopts closed-loop automatic evaporation treatment without external drainage pipes;

– Air conditioning supports intelligent group control, automatically adjusting cooling output per room load;

– Temperature and humidity control accuracy meets Class A room requirements: temperature 23±1℃, relative humidity 40%-60%.

5.4 Power Supply and Distribution Requirements

– Adopt online modular UPS power supply system providing uninterruptible power for all IT loads, environment monitoring and fire systems;

– UPS system has N+X redundancy capability, supporting online expansion and online maintenance;

– Battery backup time ≥30 minutes, meeting normal operation and orderly shutdown needs after mains interruption;

– Configure master input distribution cabinet and precision PDU column cabinet for tiered distribution management and branch monitoring;

– Distribution system has complete lightning, overload and short-circuit protection.

5.5 Environment and Power Monitoring Requirements

– Build an integrated monitoring platform centrally monitoring all subsystems: power distribution, temperature and humidity, water leakage, access control, video, air conditioning, UPS;

– Support local WEB access and remote monitoring with sound/light, SMS and other multi-channel alarming;

– Data storage period ≥1 year with historical query, curve analysis and report export;

– System is open and can integrate with the enterprise’s existing O&M platform.

5.6 Fire Protection System Requirements

– Adopt clean gas fire extinguishing system with no residue after discharge, no damage to electronic equipment;

– Smoke + heat dual-detection for early fire warning and automatic extinguishing linkage;

– System supports automatic, manual and mechanical emergency start modes;

– Meet 《Gas Fire Extinguishing System Design Code》GB 50370 and pass fire acceptance.

5.7 Lightning Protection and Grounding Requirements

– Tiered lightning protection design for the power system, realizing Class B + Class C two-level power lightning protection;

– Build a ring equipotential grounding network in the room; all metal components, equipment and cabinets reliably grounded;

– Network signal lines configured with signal lightning protectors against induced lightning;

– Overall grounding resistance ≤1Ω, meeting Class A room grounding requirements.

5.8 Decoration and Supporting Requirements

– Room decoration meets dustproof, anti-static, fireproof and thermal insulation requirements;

– Adopt all-steel anti-static raised floor, micro-perforated aluminum panel ceiling and fireproof color steel panel walls;

– Room entrance configured with Class A fireproof anti-theft airtight door;

– Configure normal lighting and emergency lighting meeting O&M illumination and fire requirements.

6. Design Principles and Applicable Standards

6.1 Design Basis

This solution strictly follows national and industry standards and specifications, mainly including:

– 《Data Center Design Specification》GB 50174-2017

– 《Code for Fire Protection Design of Buildings》GB 50016-2014 (2018 edition)

– 《Code for Design of Gas Fire Extinguishing Systems》GB 50370-2005

– 《Technical Code for Protection of Building Electronic Information Systems Against Lightning》GB 50343-2012

– 《Code for Design of Low-Voltage Electrical Installations》GB 50054-2011

– 《Code for Design of Power Supply and Distribution Systems》GB 50052-2009

– 《Code for Construction and Acceptance of Electronic Information System Rooms》GB 50462-2016

– 《Code for Construction Quality Acceptance of Anti-Static Engineering》GB 50944-2013

– 《Code for Construction Quality Acceptance of Ventilation and Air Conditioning Works》GB 50243-2016

– 《Code for Engineering Design of Generic Cabling Systems》GB 50311-2016

– Customer-provided site conditions and requirement statements

6.2 Design Principles

1. High reliability principle: core systems adopt redundant architecture — cooling N+1, UPS power module N+1, dual-circuit distribution — eliminating single points of failure; all products are industrial/computer-room-grade quality components after strict aging tests;

2. Scenario adaptation principle: for the special constraints of no outdoor unit and no drainage point, a water-cooled in-row air conditioner + condensate automatic evaporation solution is customized, fully adapting to site conditions without building structure modification;

3. High efficiency and energy saving: cold aisle containment + in-row near-end cooling architecture greatly improves cooling efficiency; EC DC stepless speed-regulating fans adjust output dynamically by load; modular UPS maintains high efficiency across 20%-100% load, reducing PUE;

4. Intelligent O&M principle: all systems connect to a unified monitoring platform for centralized data collection, intelligent analysis and proactive alarming, achieving unattended or minimally attended operation;

5. Scalability principle: cabinets, distribution, cooling and monitoring systems all reserve expansion interfaces and margins for smooth future scaling without major renovation;

6. Safety and compliance principle: strictly follows national fire, lightning, and electrical safety specifications; all materials are flame-retardant; complete safety protection mechanisms protect personnel and equipment and meet acceptance requirements.

6.3 Overall Layout Design

The 36㎡ room adopts a single-row cabinet layout: 8 cabinets arranged in a line along the long side, forming a cold aisle of about 4.8m length with 1200mm width. Five water-cooled in-row air conditioners are arranged between and at both ends of the cabinets, using front-supply rear-return airflow perfectly matching the cold aisle.

The distribution cabinet, UPS cabinet and battery cabinet are arranged in the O&M area on one side of the room; fire cylinders are placed along the wall; the monitoring host is deployed near the entrance. The ceiling area houses the suspended ceiling, lighting and fire detectors; under the raised floor are the strong-current cable tray, weak-current cable tray and grounding copper bar. The overall layout achieves complete isolation of cold and hot airflow, smooth O&M passages and clear system zoning, complying with computer room safety and O&M specifications.

7. System Architecture and Working Principle

7.1 Overall System Architecture

The 36㎡ high-density heavy-load computer room consists of six major subsystems working around the single-row cold aisle layout:

– Cabinet and cold aisle containment system: 8 high-density heavy-load server cabinets (42U, 20kW per cabinet) + cold aisle containment with sliding end doors and flip skylights;

– Cooling system: 5 water-cooled in-row precision air conditioners (40kW each, N+1 redundancy) with condensate automatic evaporation — no outdoor unit, no drainage point;

– Power supply and distribution system: master input distribution cabinet (400A) + 200kVA modular UPS (4+1 redundant modules) + battery cabinet (32×12V100Ah, ≥30min backup) + precision PDU column cabinet (16×32A branch circuits) + dual-circuit intelligent PDUs at each cabinet;

– Environment and power monitoring (DCIM) system: monitoring host + temperature/humidity sensors, leakage detection, access control, video, alarm modules and monitoring software platform;

– Fire protection system: cabinet-type heptafluoropropane gas fire extinguishing device + smoke/heat dual detection + gas fire control panel + discharge indicator, emergency start/stop, sound and light alarm;

– Lightning protection and grounding system: Class B + Class C two-level power SPDs + signal SPDs + ring equipotential grounding copper bar (grounding resistance ≤1Ω);

– Decoration works: all-steel anti-static raised floor, micro-perforated aluminum panel ceiling, rock-wool color steel panel walls, Class A fireproof anti-theft door and lighting.

7.2 Working Principle

Cooling airflow: cold air is supplied by the in-row air conditioners into the enclosed cold aisle; equipment draws cold air from the front, hot air is exhausted from the rear into the hot aisle and returns to the air conditioners — cold and hot airflows are completely isolated. The EC fans modulate speed by load, and the group controller coordinates all 5 units with automatic rotation and fault switchover.

Power flow: mains → master distribution cabinet (with Class B SPD) → modular UPS (online double conversion) → precision column cabinet (with Class C SPD) → dual-circuit PDUs → equipment. Any single UPS module or branch failure does not interrupt supply.

Monitoring flow: sensors and devices across all subsystems report via RS485/Modbus to the monitoring host, which centralizes data, triggers multi-channel alarms and provides WEB access.

Fire protection flow: smoke/heat detectors → fire control panel → automatic discharge of heptafluoropropane into the protected zone (flip skylights open within 1s) → discharge indicator and alarms; manual and mechanical emergency starts also available.

8. Detailed Technical Design

8.1 Cabinet and Cold Aisle Containment System

#### 8.1.1 KITOZER High-Density Heavy-Load Server Cabinet (KITOZER-G6-601242)

Parameter Value
Dimensions 600mm (W) × 1200mm (D) × 2000mm (H), 42U, 19-inch
Static load ≥1600kg (uniform); dynamic load ≥1000kg
Material SPCC cold-rolled steel; upright posts 2.0mm, panels 1.5mm, base 2.0mm; electrostatic epoxy powder coating 60-80μm, RAL7035
Front door High-density mesh door, ventilation ≥75%, mesh aperture ≤3mm, dust/insect resistant
Rear door Double mesh doors, ventilation ≥75%
Ventilation Internal guided air duct, cold air in front, hot air out rear, no short circuit; 10× 1U blanking panels included
Cable management Vertical cable managers both sides (24 rings each), horizontal managers rear, cable tie holes at 1U spacing
Grounding Dedicated grounding copper bar 30×3mm T2 copper, ≥8 M6 grounding terminals
Accessories Heavy base 100mm with adjustable feet (±20mm), 4 heavy casters (≥500kg each, braked), three-point anti-theft locks, 3 shelves, U-labels
Standards ANSI/EIA RS-310-D, IEC297-2, GB/T 30094; B1 flame retardant; ROHS

#### 8.1.2 KITOZER Intelligent Rack PDU (KITOZER-PDU-32A-C1312C194)

– Electrical: 220/230V AC 50/60Hz, 32A, 3×6mm² input cable with 32A industrial plug; 12× IEC C13 (10A) + 4× IEC C19 (16A) outlets; 2 independent branches with 16A breakers; metering accuracy ±1%;

– Functions: LCD display of voltage/current/power/energy; overload and short-circuit protection; built-in Class C SPD (Imax 10kA, protection level ≤1500V); RS485 Modbus-RTU for DCIM integration; cascade up to 8 units; over-current/over-voltage/under-voltage alarms;

– Mechanical: 482.6×44.5×100mm 19-inch rack mount, 6061-T6 aluminum housing, working temperature -10℃~+60℃;

– Standards: GB 7251.1, GB/T 17626, GB 18802.1, 3C/CE.

#### 8.1.3 Cold Aisle Sliding End Door (KITOZER-LTD-1220)

– Opening 1200mm × 2000mm, double sliding leaves (650mm each, 40mm thick);

– 6063-T5 aluminum frame (2.0mm, anodized) + 5mm tempered glass (transmittance ≥85%);

– EPDM sealing strips, sealing rate ≥95%; silent pulley rails; central anti-theft lock; hydraulic buffer closer; anti-collision strips and limit buffers; optional electromagnetic lock for access control integration.

#### 8.1.4 Cold Aisle Containment Frame and Sealing

– Aluminum alloy frame bolted assembly (no welding), anodized surface, adapts to 2000mm cabinets with height customization;

– 5mm flame-retardant PC side sealing panels; EPDM foam sealing strips (life ≥10 years); bottom sealing brushes; top sealing sponges at panel joints and skylight perimeters;

– Full set of stainless steel mounting bolts, 6mm² yellow-green grounding wires per frame section for aisle-wide grounding, warning signs at aisle entrances.

8.2 Cooling System

#### 8.2.1 KITOZER Water-Cooled In-Row Precision Air Conditioner (KITOZER-AC-R40W)

Parameter Value
Cooling capacity 40kW (24℃ return air, 15℃ inlet water); sensible heat ratio ≥0.95
Capacity regulation 20%~100% stepless; temperature control ±0.5℃; humidity ±3%RH; EER ≥3.5
Air system 2× EC DC backward-curved centrifugal fans, stepless speed, airflow 12000m³/h, external static pressure 150Pa, noise ≤58dB(A)
Airflow Front horizontal supply, rear return — matches cold aisle
Water system Stainless steel brazed plate heat exchanger, water flow 8m³/h, pressure drop ≤50kPa, inlet water 7~25℃, DN50 flange, electric 2-way regulating valve
Condensate Electric-heating forced evaporation + recovery: evaporation ≥5L/h, 1.5kW heater, 304 stainless steel tank, float + electronic dual level detection with dry-heat protection — no external drainage
Control 7-inch touch screen; cooling/auto/dehumidify/fan modes; group control up to 16 units (rotation, fault switchover, load balancing); RS485/SNMP, Modbus/BACnet; 30+ alarms; 1-year data storage
Electrical 380V 3N~ 50Hz, 2.2kW (fan+control), F insulation, IP20
Mechanical 600×1200×2000mm standard cabinet size; SPCC housing 1.5mm; G4 washable filter (≥90% efficiency); front maintenance, no side clearance needed
Standards GB/T 19413, GB 9237, ISO9001/14001

#### 8.2.2 Air Conditioning Water Valve Group Kit (KITOZER-VAL-40W)

Per air conditioner 1 kit, including: electric 2-way regulating valve (DN50, cast brass body, stainless steel core, DC24V actuator, ±5% accuracy, 1.6MPa); Y-type strainer (DN50, cast steel, 304 stainless mesh 40-mesh, 1.6MPa); rubber flexible joint (DN50, NBR rubber + galvanized flange, 1.6MPa); pressure gauge (0-1.6MPa, 1.6 class); bimetal thermometer (0-100℃, 1.5 class); globe valve (DN50, cast steel, 1.6MPa); drain valve (DN15).

#### 8.2.3 Cooling Water Main Piping System

– Main pipe DN80 hot-dip galvanized seamless steel tube (wall 4.0mm), branch DN50 (wall 3.5mm), per GB/T 3091; all fittings galvanized, same pressure class;

– Insulation: rubber-plastic foam pipe insulation 20mm, thermal conductivity ≤0.034W/(m·K), B1 flame retardant, aluminum foil fiberglass outer wrap;

– Supports: angle steel welded brackets, horizontal spacing ≤3m, vertical ≤4m, rubber damping pads; piping laid under raised floor.

#### 8.2.4 Air Conditioning Intelligent Group Controller (KITOZER-CAC-01)

– ARM Cortex-A9 quad-core 1.5GHz, 512MB DDR3, 8GB Flash, 7-inch touch screen;

– Interfaces: 4× RS485, 2× Ethernet, 1× CAN; 8× DI, 8× DO (relay), 4× AI;

– Functions: manages up to 16 units, automatic rotation, fault switchover, load-based output adjustment, trend analysis (daily/monthly/annual reports), graded alarms (sound/light/SMS/email), multi-level permissions;

– Protocols: Modbus-RTU, Modbus-TCP, BACnet/IP; supply AC 220V±10%, ≤15W, IP20.

8.3 Power Supply and Distribution System

#### 8.3.1 Modular UPS Power System (KITOZER-UPS-M200)

Parameter Value
System capacity 200kVA/200kW; 50kVA modules ×5 (4+1 redundancy)
Topology Online double conversion, three-phase in/three-phase out
Input 380/400/415V AC, range -25%~+20% (full load); input PF ≥0.99; THDi ≤3%
Output 380V AC ±1%, pure sine wave THD ≤2% (linear); overload 110% 60min / 125% 10min / 150% 1min
Efficiency ≥96% (online, 50% load); parallel up to 4 units N+X; transfer time 0ms
Modules Hot-swappable (≤5min replacement, no interruption); current sharing ≤±2%; independent protection per module
Battery DC bus 384V, 32× 12V VRLA in series, 3-stage charging, 100Ah → full-load backup ≥30min
Monitoring 7-inch color touch screen; RS232/RS485/dry contacts/SNMP; Modbus/SNMP/BACnet; remote monitoring software
Mechanical 600×800×2000mm, SPCC housing, ~800kg
Standards GB/T 7260.3, YD/T 1970, 3C/CE

#### 8.3.2 Valve-Regulated Sealed Lead-Acid Battery (KITOZER-BAT-12V100Ah)

– 12V 100Ah (10h rate, 25℃); float 13.5-13.8V, equalize 14.1-14.4V; max discharge 1000A (5s); self-discharge ≤2%/month;

– AGM separator, high-purity lead-calcium-tin alloy plates, no free electrolyte, any orientation; one-way explosion-proof safety valve (10-35kPa);

– Design life 10 years (25℃ float); working temperature -15℃~+45℃; ABS V-0 flame-retardant housing; tinned copper terminals;

– Size 330×173×215mm, ~30kg; GB/T 19638.2, UL/CE.

#### 8.3.3 Battery Cabinet (KITOZER-BC-C16)

– Holds 16× 12V100Ah batteries; 800×600×1200mm; SPCC 1.5mm housing, 2.0mm shelves with reinforcement, RAL7035 electrostatic powder coating;

– 2-layer internal battery rack (8 per layer), insulating boards and separators, dedicated grounding terminal, natural ventilation, cable entry with grommets; per-layer load ≥500kg, total ≥1000kg.

#### 8.3.4 Master Input Distribution Cabinet (KITOZER-PDL-MAIN)

– 380V 3N~ 50Hz, incoming 400A, short-time withstand 50kA/1s, IP30; 800×600×2000mm, SPCC 2.0mm;

– Incoming: 400A MCCB (3P, 50kA breaking) + 400A isolating switch;

– Outgoing: UPS 250A MCCB ×1; AC 160A MCCB ×2; lighting/socket 32A MCB 1P+N ×4; maintenance socket 32A RCD 1P+N ×2; spare 100A MCCB ×2;

– Lightning: Class B SPD 3P+N, Imax 100kA with failure indication and remote contacts;

– Metering: multi-function power meter (0.5 class), 400/5A CTs ×3; overload/short-circuit/leakage/phase-loss protection; GB 7251.1, 3C.

#### 8.3.5 Precision PDU Column Cabinet (KITOZER-PDL-COL)

– 380V 3N~ 50Hz, input 250A, 16× 32A single-phase branches, IP20; 600×1000×2000mm standard server cabinet size;

– Input: 250A MCCB (3P) + Class C SPD (3P+N, Imax 40kA); output 16× 32A 1P MCB each with independent CT metering;

– Monitoring: 7-inch LCD touch screen — total voltage/current/active power/energy, per-branch current/power, over-current/overload alarms; RS485 Modbus for DCIM;

– Vertical cable managers, labeled terminals, top/bottom cable entry options; GB 7251.1, 3C.

#### 8.3.6 Power Cables and Auxiliary Materials

– Main incoming: YJV-0.6/1kV-4×185+1×95mm²; UPS output 4×120+1×70mm²; column cabinet feed 4×70+1×35mm²; AC feed 5×16mm²; cabinet feed RVV-3×6mm² ×2 per cabinet; control RVVP-2×1.5mm²;

– Trays: strong-current 200×100mm galvanized trough (1.2mm) and weak-current tray separated; JDG galvanized conduits φ20/φ25;

– Tinned copper terminals, cable ties, spiral wrap, number tubes, bracket hardware, grounding jumpers; per GB 50054.

#### 8.3.7 Cabinet Grounding Copper Bar

– 30mm × 3mm, length 480mm, T2 copper ≥98% IACS, tin-plated; 8× M6 terminals; vertical installation in cabinet with mounting bracket; 6mm² yellow-green grounding wire per bar.

8.4 Environment and Power Monitoring (DCIM) System

#### 8.4.1 Monitoring Host (KITOZER-EMU-H100)

– ARM Cortex-A9 quad-core 1.5GHz, 2GB DDR3, 16GB eMMC (up to 128GB SD); DC12V/2A, ≤15W;

– Interfaces: 2× gigabit Ethernet (redundant), 8× configurable RS485/RS232, 16× DI, 8× DO (5A/250VAC relay), 8× AI (4-20mA/0-5V/0-10V), 2× USB, 1× sound/light alarm output;

– Functions: full-category device access (distribution, UPS, AC, temperature/humidity, leakage, access control, video, fire); real-time collection (1s fastest), multi-level alarm thresholds with sound/light/SMS/email and escalation; ≥1 year local storage with Excel export; real-time/historical curves; alarm linkage control; multi-level users with logs; built-in WEB server;

– Protocols: Modbus-RTU/TCP, SNMP, BACnet, HTTP; SDK for secondary development.

#### 8.4.2 Temperature and Humidity Sensors

– 12 sensors: 4 in cold aisle (supply air), 4 in hot aisle (return air), 4 inside high-load cabinets (equipment temperature); accuracy ±0.3℃ / ±2%RH; RS485 Modbus.

#### 8.4.3 Leakage Detection

– Positioning-type leakage detection with sensing cable along water pipes, under air conditioners and under raised floor; positioning accuracy ±1m; with alarm relay output.

#### 8.4.4 Access Control and Video

– Fingerprint + password + card access control with electric lock, exit button and management software; IP cameras at entrance and inside the room with NVR recording.

#### 8.4.5 Alarm Modules

– Sound/light alarm, SMS alarm module (dual-SIM), and monitoring software platform with electronic map, alarm management, reports and remote WEB access.

8.5 Gas Fire Protection System

#### 8.5.1 Cabinet-Type Heptafluoropropane Device (GQQ70/2.5)

– 70L cylinder, filling rate ≤1.15kg/L, max charge 80kg, working pressure 2.5MPa (20℃), discharge ≤10s, extinguishing concentration 8%~10%;

– Composition: steel cylinder (internal/external galvanized), brass container valve with pressure gauge and safety relief, DC24V/1.5A electromagnetic starter, atomizing nozzles, sprayed steel cabinet with double doors;

– Start modes: automatic, manual, mechanical emergency; pressure feedback contact output; discharge distance ≥3m; 600×500×1800mm, ~120kg; GB 25972, 3C.

#### 8.5.2 Heptafluoropropane Agent (HFC-227ea)

– Purity ≥99.9%; colorless odorless gas, non-conductive, no residue; chemical suppression + physical cooling; ODP=0, low GWP; safe for occupied spaces; GB 18614.

#### 8.5.3 Gas Fire Control Panel (JB-QB-QM200)

– 1 protection zone, 2 extinguishing circuits, 2 detection loops (up to 32 detectors each), delay 0-30s settable;

– Auto/manual/emergency control; linkage: close fire dampers, stop HVAC, close doors/windows, discharge agent, light discharge indicator; LCD Chinese menu; 1000-event history;

– AC 220V±15%, backup DC24V 7Ah (≥8h), DC24V output, static ≤10W; RS485 for DCIM; GB 16806, 3C.

#### 8.5.4 Photoelectric Smoke Detector (JTY-GD-3002)

– Photoelectric scattering; sensitivity levels I/II/III; response threshold 0.15-0.3dB/m; coverage 60-80㎡; DC24V, monitor ≤200μA / alarm ≤2mA; red LED; ABS housing; GB 4715, 3C.

#### 8.5.5 Heat Detector (JTW-ZCD-3005)

– Fixed-temperature 68℃ (rate-of-rise optional); coverage 20-30㎡; DC24V, monitor ≤150μA / alarm ≤2mA; GB 4716, 3C.

#### 8.5.6 Discharge Indicator (FQ-1)

– DC24V, ≤200mA; red LED “Gas Discharged — Do Not Enter”; metal sprayed housing, wall-mounted above door outside; 350×150×40mm; 3C.

#### 8.5.7 Emergency Start/Stop Button (QT-1) and Sound/Light Alarm (SG-2)

– Button: protected cover, NO+NC contacts, DC24V, wall-mounted at 1.5m outside door, 86×86×50mm, 3C;

– Alarm: DC24V, ≥85dB, ~1Hz red flash, fire tone, ABS housing, IP30, 3C.

8.6 Lightning Protection and Grounding System

#### 8.6.1 Class B Power SPD (KITOZER-SPD-B100)

– Un 385V AC, Uc 420V AC, In 50kA (8/20μs), Imax 100kA, Up ≤2.5kV, response ≤25ns; 3P+N; hot-swappable module; failure indication (green OK / red failed) + remote alarm contacts; 35mm DIN rail; flame-retardant PBT housing; GB 18802.1, 3C.

#### 8.6.2 Class C Power SPD (KITOZER-SPD-C40)

– Un 385V AC, In 20kA, Imax 40kA, Up ≤1.8kV, response ≤25ns; 3P+N; pluggable; failure indication + remote contacts; GB 18802.1, 3C.

#### 8.6.3 Equipotential Grounding Copper Bar

– 40×4mm T2 copper ≥98% IACS, tin-plated, laid around the room (~30m); insulator supports, 15mm from wall, 300mm above floor; all metal components, cabinets, equipment, trays and pipes connected to the bar.

#### 8.6.4 Grounding Down Conductors and Equipment Ground Wires

– BV-25mm² yellow-green stranded copper ×4 connecting the equipotential bar to the building combined grounding network; single-point grounding, resistance ≤1Ω;

– 16mm² yellow-green wires for large equipment (cabinets, distribution cabinets, AC units); 6mm² for small equipment and metal parts; tinned terminals.

#### 8.6.5 Network Signal SPD (KITOZER-SPD-RJ45)

– 8V rated, 12V max continuous, In 5kA, Imax 10kA, Up ≤30V, insertion loss ≤0.5dB, bandwidth 1000Mbps, response ≤1ns; RJ45 8-core full protection; rail/desktop; GB/T 18802.21.

8.7 Computer Room Decoration Works

#### 8.7.1 All-Steel Anti-Static Raised Floor (HDG.600.35.Q.D)

– 600×600×35mm, all-steel seamless, foamed cement fill, 1.5mm HPL anti-static surface; system resistance 10⁶-10⁹Ω; B1 fire rating;

– Concentrated load ≥4450N, uniform load ≥23000N/㎡, ultimate ≥13350N; wear ≥10000 cycles;

– Galvanized steel pedestals 300mm (±20mm adjustable), galvanized steel stringers, conductive adhesive, grounding terminals, edge trims; GB/T 36340.

#### 8.7.2 Micro-Perforated Aluminum Panel Ceiling

– 600×600×0.8mm aluminum, φ6mm perforations 20% perforation rate; electrostatic powder coating milky white; Class A non-combustible; NRC ≥0.6;

– Full ceiling at 2.8m height; light steel keels, hangers and expansion bolts; GB/T 23443.

#### 8.7.3 Color Steel Panel Walls

– 50mm rock-wool sandwich panels, 0.5mm double-sided baked panels, core density 100kg/m³; Class A; sound insulation ≥25dB; thermal conductivity ≤0.04W/(m·K);

– Full-height installation on all walls; ceiling/wall/floor runners, vertical studs, sealant and trims.

#### 8.7.4 Fireproof Anti-Theft Airtight Door

– 1000×2100mm single door; Class A fire rating (1.5h fire resistance); C-level anti-theft;

– 1.5mm frame, 0.8mm leaf with fire rock-wool fill; EPDM fire sealing strips; C-level three-point lock; GB 12955, 3C.

#### 8.7.5 Lighting System

– Normal: 6× 600×600mm LED flat panel lights 36W white, illumination ≥500lx, dual-control switch at door;

– Emergency: 2 exit sign lights + 2 emergency lights, duration ≥90min; GB 50034, GB 17945.

9. Recommended Configuration and Preliminary Budget

9.1 Configuration Summary

System Item Qty
Cabinet & aisle KITOZER-G6-601242 heavy-load cabinet (42U, 1600kg) 8
Intelligent rack PDU 32A (12×C13+4×C19) 16
Cold aisle containment frame, sliding end doors, flip skylights 1 set
Cooling Water-cooled in-row AC 40kW (KITOZER-AC-R40W) 5
Valve group kit (KITOZER-VAL-40W) 5
Cooling water main/branch piping, insulation, supports 1 set
Intelligent group controller (KITOZER-CAC-01) 1
Power Master input distribution cabinet 400A (KITOZER-PDL-MAIN) 1
Modular UPS 200kVA 4+1 (KITOZER-UPS-M200) 1
Battery 12V100Ah (KITOZER-BAT-12V100Ah) 32
Battery cabinet (KITOZER-BC-C16) 2
Precision column cabinet 250A/16 branches (KITOZER-PDL-COL) 1
Power cables, trays, conduits, auxiliaries 1 set
Monitoring Monitoring host (KITOZER-EMU-H100) 1
Temperature/humidity sensors 12
Positioning leakage detection (sensing cable) 1 set
Access control + video + alarm modules + software 1 set
Fire Cabinet-type heptafluoropropane device 70L 1
Smoke detectors + heat detectors 4+4
Gas fire control panel, discharge indicator, start/stop, alarm 1 set
Lightning Class B SPD + Class C SPD + signal SPDs 1 set
Equipotential copper bar, down conductors, ground wires 1 set
Decoration Anti-static raised floor, ceiling, wall panels, fire door, lighting 1 set

9.2 Quotation Notes

This configuration list covers the complete material and equipment set of the 36㎡ high-density computer room per the Class A design standard. Quantities are calculated per standard engineering practice; the total cost needs to be confirmed based on the final configuration solution, on-site conditions, construction difficulty and transportation distance. The core cost components include equipment purchase cost, decoration material cost, construction and installation cost, water system material cost, testing and acceptance cost, tax and after-sales service cost. If the number of cabinets, IT load, backup time or monitoring/fire configuration changes, the list content and quantities can be adjusted accordingly. All reference prices quoted in this solution are in RMB (CNY) only and are for reference purposes; a formal quotation can be issued after configuration confirmation.

10. Technical Specifications

10.1 Overall System Performance

Item Specification
Design standard Class A per GB 50174-2017
Room size Net 36㎡ (8m × 4.5m), floor height ≥3.2m
IT load 8 cabinets × 20kW = 160kW
PUE ≤1.4
Availability Redundant cooling (N+1), UPS (4+1), dual-circuit PDU
Temperature/humidity 23±1℃, 40%-60%RH
Grounding resistance ≤1Ω
Fire protection Heptafluoropropane gas, smoke + heat dual detection

10.2 Key Equipment Specification Summary

Equipment Key Parameters
Heavy-load cabinet 42U, static load ≥1600kg, mesh doors ≥75% ventilation
In-row AC (×5) 40kW each, EC fans, 20-100% stepless, EER ≥3.5
Modular UPS 200kVA, 4+1 × 50kW modules, efficiency ≥96%
Battery 32× 12V100Ah VRLA, backup ≥30min
Master distribution 400A, Class B SPD 100kA
Column cabinet 250A, 16× 32A branches with per-branch metering
Monitoring host ARM quad-core, 16 DI/8 DO/8 AI, WEB + SMS alarms
Fire device 70L heptafluoropropane, ≤10s discharge

11. Key Advantages and Customer Value

11.1 Special Scenario Adaptation Advantage

For the core constraints of no outdoor unit installation condition and no drainage point, this solution adopts water-cooled in-row precision air conditioners with closed-loop condensate evaporation, completely avoiding outdoor unit installation and external condensate discharge without building structure modification — perfectly adapting to the special constraints of computer rooms inside office buildings. The water-cooled system has higher cooling efficiency and EER than ordinary air-cooled units, saving more energy in long-term operation. If the building has no central cooling source, a closed cooling tower can be placed on the roof or outdoor equipment platform — the room itself never has outdoor units, complying with the site constraints while ensuring cooling performance.

11.2 High-Density Heavy-Load Bearing Advantage

For the 20kW per cabinet high-power load, the solution is comprehensively strengthened in three dimensions:

– Cabinet level: static load ≥1600kg, thickened posts, meeting heavy server and GPU equipment installation needs; high-ventilation mesh front/rear doors with optimized airflow for high-heat equipment;

– Distribution level: dual 32A intelligent PDUs per cabinet, branch monitoring at the column cabinet, modular UPS redundant architecture — sufficient capacity and high reliability;

– Cooling level: in-row near-end cooling with cold aisle containment completely solves local hot spots of high-density cabinets, improving cooling efficiency by more than 30%.

11.3 Full-System Redundancy and Reliability Advantage

All core systems adopt redundant architecture to eliminate single points of failure and meet Class A room availability:

– Cooling: 4+1 N+1 redundancy, standby unit automatically takes over on failure;

– UPS: N+1 redundant power modules, hot-swappable online maintenance, single module failure does not affect supply;

– Distribution: dual-circuit PDU to each cabinet for dual-power equipment;

– Fire/lightning: smoke + heat dual detection, two-level power SPDs + signal SPDs.

11.4 Intelligent O&M Management Advantage

The integrated monitoring platform centrally manages all room elements: power distribution, cooling, environment, security and fire are uniformly monitored with electronic map visualization; multi-level intelligent alarms via sound/light, SMS and email; the AC group controller dynamically adjusts cooling output by load to avoid over-cooling; historical data storage and analysis with report export support O&M decisions; remote WEB access lets operators monitor status without entering the room.

11.5 Green Energy-Saving and Low-Carbon Advantage

Cold aisle containment + in-row near-end cooling greatly reduces cooling loss; EC DC stepless fans save more than 30% energy versus fixed-speed fans; modular UPS maintains over 95% efficiency across 20%-100% load; intelligent group control matches load dynamically to avoid over-cooling. Overall PUE is controlled within 1.4, far below the traditional computer room average.

11.6 Full-Lifecycle Service Advantage

One-stop services from solution design, production, construction and installation, commissioning and acceptance to after-sales O&M: dedicated project manager follow-up; own construction team with standardized processes and assured quality and schedule; 7×24 technical hotline; periodic on-site inspections; long-term technical support and upgrade services.

11.7 Brand and Quality Advantage

The KITOZER brand has focused on computer room infrastructure for more than twenty years: multiple patented technologies and authoritative certifications; own production base with strictly controlled quality and controllable delivery; numerous industry benchmark cases validating mature solutions.

12. Technical Q&A (50+ Items)

12.1 Cabinet and Cold Aisle Containment Questions

Q1: Why must heavy-load cabinets be used for a 20kW per cabinet load? Can ordinary server cabinets work?

A: A 20kW per cabinet load is high density; single-cabinet equipment weight typically reaches 800-1200kg, far exceeding the 500kg-level load limit of ordinary cabinets. Ordinary cabinets have thin posts and insufficient structural strength — long-term heavy load can cause post deformation and cabinet wobble, with equipment fall risks. KITOZER heavy-load cabinets use 2.0mm quality cold-rolled steel posts with nine-fold formed reinforcement, static load ≥1600kg, front/rear door ventilation ≥75%, plus dedicated cable management and grounding structures, fully adapted to high-heat, heavy-load equipment.

Q2: How much cooling efficiency can cold aisle containment improve? What is the principle?

A: Cold aisle containment raises effective cooling utilization from 40%-50% of traditional rooms to over 80%, reducing overall cooling energy by 20%-30%. The core principle: enclosing the cold side forces all cold air through equipment air inlets to remove heat, avoiding cold/hot airflow mixing; it also eliminates local hot spots, keeping top-to-bottom temperature difference within ±1℃ for stable high-load operation.

Q3: Why must cold aisles be equipped with fire-linkage flip skylights?

A: When the gas fire extinguishing system starts, the agent must quickly and evenly fill the protected zone. A fully enclosed cold aisle blocks heptafluoropropane entry and the pressure difference during discharge may damage the structure. Fire-linkage flip skylights open automatically within 1 second on fire signal, letting the agent enter quickly while balancing pressure, without affecting daily cooling sealing — a mandatory requirement of computer room fire codes.

Q4: What advantages do intelligent PDUs have over ordinary PDUs? Why dual-circuit for high-density cabinets?

A: Intelligent PDUs collect voltage, current, power and energy data in real time, support over-voltage/over-current alarms, integrate with the DCIM platform remotely, and include built-in lightning protection — monitoring, management and protection advantages. Dual-circuit PDU configuration matches the dual-power redundant design of servers and storage; the two circuits come from different column cabinet branches, so a single circuit failure is seamlessly carried by the other, eliminating single-point power failure.

Q5: Sliding or hinged cold aisle end doors?

A: Sliding doors do not occupy aisle space when open, have better sealing, and allow smooth O&M cart passage — suitable for compact small/medium rooms. Hinged doors are simpler and slightly cheaper but occupy aisle and O&M space when open. For a 36㎡ 8-cabinet room, sliding end doors are recommended.

Q6: How does cabinet grounding work?

A: Each cabinet has a dedicated 30×3mm T2 copper grounding bar with ≥8 M6 terminals; cabinets, PDUs and equipment are connected to the bar, and the bar connects to the room’s equipotential ring, achieving reliable grounding with resistance ≤1Ω and eliminating potential differences between equipment.

12.2 Cooling System Questions

Q7: What cooling solutions work when outdoor units cannot be installed? Which best suits high-density rooms?

A: Three mainstream options: water-cooled precision air conditioning, ethylene glycol cooling systems, and fluorine pump natural cooling. Water-cooled in-row precision AC is the best choice for an 8-cabinet, 20kW-per-cabinet high-density room: only end units are inside the room, the cooling tower sits on the roof or equipment platform, completely avoiding wall installation constraints; in-row near-end supply responds fast and matches the cold aisle; water-cooled heat exchange is more efficient than air-cooled with higher EER for long-term energy savings.

Q8: With no drainage point, how is condensate handled? Is automatic evaporation reliable?

A: A built-in condensate automatic evaporation system is preferred: condensate is collected in a dedicated tank and forcibly evaporated by a PTC heating module into vapor carried by return air back into the room — closed-loop, no external discharge. The technology is mature: evaporation capacity is designed at 1.2× maximum condensate with water level monitoring, dry-heat protection and overflow alarms, almost maintenance-free; it also assists humidity control, reducing humidification energy. In extremely humid regions, a small lift pump can be added as supplement.

Q9: Total load is 160kW — why configure 5× 40kW units instead of 4?

A: N+1 redundancy. Four 40kW units cover 160kW IT load plus ambient heat, but if any unit fails or is under maintenance, the remaining three cannot maintain cooling and the room overheats. The fifth unit as standby lets the other four immediately carry the full load on failure; daily rotation also balances run hours and extends life; and it reserves cooling margin for small future expansion.

Q10: What does the water valve group kit contain and what does each valve do?

A: Electric 2-way valve — modulates water flow by return temperature for precise temperature control; Y-type strainer — filters impurities protecting the plate heat exchanger; rubber flexible joint — vibration damping and thermal expansion compensation; pressure gauge and thermometer — real-time supply/return parameter monitoring; globe valve — shuts off the water circuit for maintenance without affecting other units; drain valve — drains piping for winter protection and maintenance.

Q11: Is the AC group controller necessary? What value does it bring?

A: For multiple parallel units, group control is very necessary: unified management, automatic rotation and fault switchover avoid single-unit long-term high-load operation and extend life; dynamic output adjustment of all units by overall temperature/humidity avoids “competing cooling” of independent control, saving 15%-20% energy; unified reports and centralized alarms greatly reduce O&M workload. For rooms with 5+ air conditioners, the payback is high.

Q12: How long do water-cooled precision AC units last? Daily maintenance?

A: With standard O&M, KITOZER water-cooled in-row units have a 10-15 year design life; core heat exchangers can exceed 15 years. Monthly inspection: temperature/humidity parameters, filter differential pressure, water tank level. Quarterly: clean/replace air filters, clean evaporator fins, calibrate sensors. Annual: fully clean the plate heat exchanger, check pipe sealing and insulation, verify safety devices, inspect fans and motors.

Q13: What is sensible heat ratio and why does it matter for computer rooms?

A: Sensible heat ratio is the ratio of sensible cooling to total cooling. Computer room heat load is dominated by sensible heat from IT equipment (little latent heat), so units with high sensible heat ratio (≥0.95 here) avoid overcooling/dehumidifying, keeping humidity stable and saving energy — a key parameter distinguishing precision AC from comfort AC.

Q14: Why is chilled water quality important?

A: Impurities cause scaling and clogging of the plate heat exchanger, reducing heat exchange efficiency and cooling capacity over time. Water quality should comply with GB 50050 industrial circulating cooling water code; the Y-type strainer filters particles, and periodic water quality checks and treatment are recommended to protect the heat exchanger.

12.3 Power Supply and Distribution Questions

Q15: 8 cabinets total 160kW — why choose a 200kVA modular UPS?

A: Selection considers total load, power factor, redundancy and expansion. 160kW IT load plus auxiliary loads (monitoring, lighting, fire) totals about 180kW critical load; modular UPS power factor is typically 0.9, so 200kVA ≈ 180kW active power, matching the load while running in the efficient 70%-80% range. Five 50kW modules form 4+1 redundancy; the frame reserves expansion slots for online module addition as load grows — no whole-unit replacement, protecting investment.

Q16: How is battery backup time calculated? How many cells for 30 minutes?

A: Battery capacity (Ah) = (load W × backup h) ÷ (DC bus V × discharge efficiency × discharge factor). The UPS DC bus is 384V; at 12V per cell, 32 cells in series form the string. For 180kW full load and 30-minute backup, 100Ah VRLA batteries with aging and low-temperature derating margins guarantee ≥30 minutes at full load and over 1 hour at half load.

Q17: With a master distribution cabinet, why add a precision column cabinet?

A: The column cabinet is the distribution endpoint at the cabinet row: tiered protection — branch breakers isolate faults at single-cabinet level so a short circuit on one branch does not affect other cabinets; fine metering — independent current/power monitoring per branch for accurate per-cabinet energy statistics and abnormal load identification; O&M convenience — cabinet-side operation avoids frequent master cabinet handling and reduces misoperation risk, with neater wiring for later expansion.

Q18: What advantages does modular UPS have over traditional tower UPS?

A: Reliability — N+X module redundancy, no single point of failure; scalability — add modules as load grows, low initial investment, online expansion without business interruption; maintenance — hot-swappable modules replaced on site in minutes without whole-unit return; efficiency — high efficiency even at low load, avoiding the “big horse pulling a small cart” inefficiency of traditional units.

Q19: How are batteries maintained? Typical life?

A: VRLA batteries work best at 20-25℃; every 10℃ rise halves life. Monthly: check cell voltages, string voltage and terminals. Quarterly: clean surfaces, check for swelling/leakage. Annual: discharge test to verify actual capacity; every three years a full-depth discharge test. With standard O&M, quality lead-acid batteries have 8-10 year design life; replacement recommended at 6-8 years of actual use.

Q20: Why tiered lightning protection? Isn’t one level enough?

A: Lightning surge energy is huge; a single level cannot reduce voltage to safe equipment range in one step — staged discharge and clamping are required. Class B SPD at the incoming line discharges most of the lightning current (protection level ~2.5kV); Class C at UPS output and column cabinet further attenuates residual surge (≤1.8kV); important device ends can add Class D fine protection. Two or three levels cooperate to bring surge voltage into the safe threshold of electronic equipment — one level cannot effectively protect end devices.

Q21: What is the difference between dual-power and single-power equipment in this design?

A: Dual-power equipment (servers/storage with dual PSUs) connects each PSU to a different PDU branch, achieving true redundancy — one branch failure causes zero interruption. Single-power equipment (some network devices) connects to one branch only; for critical single-power devices, a static transfer switch can be provided to switch between the two circuits automatically.

Q22: Why is the master cabinet rated 400A?

A: Total critical load ~180kW at 380V three-phase ≈ 273A line current; adding air conditioning (~80kW), lighting and reserves, and applying a utilization factor and future expansion margin, 400A incoming with YJV 4×185+1×95 cable provides ample capacity, keeping loading in a reasonable range for stable operation and future growth.

12.4 Environment and Power Monitoring Questions

Q23: What does the DCIM system mainly monitor? Core value?

A: Six categories: power distribution (HV/LV, UPS, batteries, PDUs), cooling (precision AC, temperature/humidity, leakage), environment (temperature/humidity, static pressure, dust), security (access control, video, infrared intrusion), fire (detectors, extinguishing device, discharge indicator), alarms and reports. Core value: turning passive O&M into proactive O&M — early fault warning, unified remote management, traceable data, greatly reducing downtime risk and labor, achieving unattended or minimally attended operation.

Q24: Why 12 temperature/humidity sensors for a 36㎡ room?

A: High-density room temperature distribution is extremely uneven — cold aisle, hot aisle, cabinet top/bottom can differ by over 5℃; a few sensors only measure local environment and miss internal hot spots. The 12 sensors form a layered distributed network: 4 in the cold aisle (supply air), 4 in the hot aisle (return air), 4 inside high-load cabinets (actual equipment temperature), truly reflecting the thermal environment. Low-density rooms can reduce count, but 20kW-per-cabinet scenarios should not.

Q25: Positioning vs point leakage detection?

A: Point sensors only detect water at a single point — low cost but small coverage. Positioning detection lays sensing cable along pipes, under AC units and under the floor, pinpointing leakage location within ±1m accuracy, with large coverage and fast location. For high-density rooms with water-cooled piping and multiple AC units, positioning detection is preferred — the protection value far exceeds the cost, preventing major water-damage losses.

Q26: How are alarms guaranteed not to be missed? Notification methods?

A: Graded alarms + multi-channel notification + alarm escalation. Local sound/light alarms alert both in-room and O&M office; remote SMS, voice call, email and platform pop-ups; alarms graded urgent/important/general/info with urgent ones pushed on all channels simultaneously. Escalation: unacknowledged alarms auto-notify supervisors after a set time; offline storage with auto re-report on network recovery — no alarm record is lost.

Q27: How is the monitoring host’s own reliability ensured?

A: Industrial embedded architecture, fanless, low power, MTBF over 100,000 hours. Hardware: dual power input, dual network redundancy, 4G wireless backup — single power or network failure does not stop operation. Software: watchdog auto-restart, local + cloud dual backup; self-diagnosis alarms its own faults to avoid monitoring failure.

Q28: Can the DCIM system integrate with the enterprise’s existing O&M platform?

A: Yes. KITOZER DCIM supports standard Modbus, SNMP, BACnet, HTTP protocols with open API interfaces, seamlessly integrating with unified O&M platforms, building automation and large-screen display systems. Read-only permissions can be set to expose only monitoring data without control permissions for security; custom integration development is also available.

12.5 Gas Fire Protection Questions

Q29: Why must heptafluoropropane be used? Why not ordinary sprinklers?

A: Absolutely no water sprinklers. Computer rooms contain precision electronic equipment; water discharge causes short circuits, corrosion and flooding — essentially total loss, far greater than the fire itself. Heptafluoropropane is a clean gas agent: colorless, odorless, non-conductive, residue-free, rapidly vaporizing after discharge without damaging electronic equipment, and safe for occupied spaces.

Q30: How does the gas fire system detect and respond?

A: Smoke and heat detectors use dual detection (both must trigger or per configuration) to send a fire signal to the control panel, which starts the 0-30s settable delay, closes fire dampers and stops HVAC, then discharges the agent within 10s; the discharge indicator lights and sound/light alarm activate. Automatic, manual and mechanical emergency start modes cover all scenarios.

Q31: What is the extinguishing concentration for computer rooms?

A: 8%-10% heptafluoropropane design concentration for computer rooms (per GB 50370), discharged within ≤10s to quickly suppress the fire. The 70L cylinder with ≤80kg charge protects a volume of roughly 90-100m³; the room volume must be verified so the concentration stays in the effective and safe range.

Q32: Is heptafluoropropane safe for people?

A: Yes for the design concentration used in occupied computer rooms. HFC-227ea has low toxicity (NOAEL above typical design concentrations), is approved for normally occupied spaces, and has ODP=0 with low GWP. Personnel should evacuate before discharge as a standard practice; the discharge indicator warns “Gas Discharged — Do Not Enter.”

Q33: What maintenance does the gas fire system need?

A: Monthly: visual inspection of cylinders, pressure gauges, valves and nozzles; quarterly: test detectors and control panel functions; annual: full-function test including discharge simulation (without real agent), weigh cylinders to check agent quantity, verify linkage with HVAC/dampers. Records kept; 3C-certified components serviced by qualified personnel.

Q34: What is the mechanical emergency start for?

A: If automatic and electrical manual modes fail (e.g., control panel damage or power loss), the mechanical emergency start operates the container valve directly by mechanical force to discharge the agent. It is the last-resort start ensuring the system can still extinguish a fire under any failure condition.

12.6 Lightning Protection, Grounding and Safety Questions

Q35: Why is equipotential grounding needed in the room?

A: The room contains many metal components (cabinets, trays, pipes, equipment housings). Potential differences between them can cause sparking under lightning or ESD, damaging equipment and endangering safety. Connecting all to the ring copper bar achieves room-wide equipotentiality, eliminating potential differences and providing a low-impedance path for surge currents.

Q36: What is the grounding resistance requirement?

A: Combined grounding ≤1Ω. The equipotential copper bar connects via four BV-25mm² down conductors to the building’s combined grounding network, single-point grounding. Regular testing (every six months to a year) verifies compliance; retest after thunderstorms or nearby construction.

Q37: Why protect network signal lines with SPDs?

A: Ethernet cables running between buildings or outside can conduct induced lightning surges into the room, damaging switches, servers and the monitoring host. RJ45 signal SPDs clamp surge voltage to ≤30V with ≤0.5dB insertion loss and 1000Mbps bandwidth, protecting equipment without affecting network performance.

Q38: Are the materials in this solution flame-retardant?

A: Yes. All materials meet fire regulations: raised floor B1, ceiling Class A, wall panels Class A, cables low-smoke halogen-free flame-retardant (WDZ type), cabinet and housing materials B1 or better, plus the Class A fireproof entrance door with 1.5h fire resistance.

12.7 Construction and Acceptance Questions

Q39: What is the construction period for this 36㎡ room?

A: The total schedule is about 25 working days: preparation 3, decoration 5, conduit/cable laying 4, equipment installation 5, system wiring 3, commissioning 3, acceptance and handover 2. Cross-work between teams shortens the critical path; the schedule is adjustable to site conditions.

Q40: How is acceptance performed?

A: Acceptance covers engineering quality (installation, wiring, decoration per drawings and codes) and system performance: power-on tests, cooling performance verification (temperature/humidity stability), DCIM alarm/linkage function tests, fire system commissioning and discharge simulation, grounding resistance measurement (≤1Ω), and final documentation handover including as-built drawings, test reports and operation manuals.

Q41: What certificates do construction personnel hold?

A: Welders, electricians and other special-operation personnel hold valid special operation certificates; installation follows national codes with three-level inspection (self, mutual, handover). Key processes — distribution wiring, water pressure testing, grounding testing, fire linkage — are supervised by the technical leader on site.

Q42: Will construction affect adjacent offices?

A: Construction is contained within the room: noise-reduced scheduling, dust control, finished-product protection, materials stored neatly, daily site cleaning. Power-off windows are coordinated with the client in advance; emergency power for adjacent areas is arranged if needed.

12.8 Operation and Maintenance Questions

Q43: What are the daily O&M essentials for a high-density room?

A: Monitor DCIM alarms daily; check temperature/humidity trends and hot spots; keep cold aisle doors and skylights closed; verify UPS and battery status; check condensate evaporation tank water level monthly; clean AC filters quarterly; test leakage detection and fire detectors periodically; keep the room clean and dust-free.

Q44: How often should full cooling performance be verified?

A: Recommend quarterly verification of cooling capacity versus load (supply/return temperatures, airflow, hot spots) and annual comprehensive performance testing including PUE measurement. After adding load or cabinets, verify cooling and power capacity immediately to ensure margins are maintained.

Q45: What if a UPS module fails?

A: The 4+1 redundant configuration means a single module failure does not interrupt supply; the failed module is hot-swapped within about 5 minutes while the system continues operating. The DCIM system alarms the module fault; replacement modules are stocked locally for fast service.

Q46: How is energy efficiency (PUE) maintained low?

A: Keep cold aisle containment sealed; ensure airflow path is unobstructed (blanking panels installed); let the group controller optimize unit output by load; keep UPS in the efficient load range; monitor PUE via the DCIM power metering and adjust operation accordingly; scheduled cleaning of filters and heat exchangers maintains cooling efficiency.

Q47: What is the warranty and after-sales service?

A: 2-year overall warranty (3 years for core equipment), free repair of quality problems; 7×24 hotline with 2h/4h urban response; semi-annual inspections during warranty; spare parts in local warehouse; lifetime cost-price maintenance and technical support after warranty.

Q48: Can the room be expanded later?

A: Yes. The solution reserves margins: UPS frame expansion slots (add modules online), spare branches in master and column cabinets, extra PDUs per cabinet, cooling N+1 margin and group controller capacity (up to 16 units), DCIM expansion slots, and cable tray/underfloor space. Adding cabinets or load follows the planned expansion path without major renovation.

Q49: What documentation is delivered?

A: Complete as-built documentation: design drawings, configuration lists, equipment manuals and certificates, material test reports, construction records, water pressure and grounding test reports, fire acceptance documents, DCIM operation manual and training materials, and the after-sales service card.

Q50: How is training provided?

A: 2-day intensive training at handover covering basic operation, maintenance and emergency handling, with theory + hands-on assessment; free repeat training for new personnel; ongoing phone/online technical consultation after handover.

Q51: Why is humidity control important in the room?

A: Too low humidity causes static discharge damaging chips; too high causes condensation and corrosion. The 40%-60%RH range (23±1℃) protects equipment and reduces ESD risks. The in-row units control humidity precisely; condensate evaporation also helps maintain humidity in dry seasons, reducing humidifier energy.

Q52: How is the room kept clean in a dusty environment?

A: The room is positively pressurized with filtered air from the AC units (G4 filters, ≥90% efficiency); doors kept closed; raised floor and ceiling create clean surfaces; periodic cleaning of floor, cabinets and filters. For industrial/ dusty surroundings, G4+F8 two-stage filtration can be added per the project’s customized option.

13. Construction Schedule

13.1 Schedule Overview

The total project period is estimated at 25 working days, with the detailed schedule as follows:

Stage Work Content Days Responsible Note
Preparation Site survey verification, drawing deepening, material stocking, personnel mobilization and disclosure, construction procedures 3 Project manager Coordinate with client
Decoration works Floor treatment, floor pedestal installation, wall keel installation, color steel panel laying, ceiling keel installation 5 Decoration team leader Pipeline pre-embedding in parallel
Conduit and cable laying Strong-current tray, weak-current tray installation, power cable laying, grounding system laying, water piping installation 4 Electrician team leader Cross-work with decoration
Equipment installation Cabinet and cold aisle installation, UPS and battery installation, distribution cabinet installation, AC installation, fire equipment installation 5 Installation team leader Parallel team work
System wiring Equipment wiring, PDU installation, DCIM sensor installation, access control/video installation, fire system wiring 3 Weak-current team leader —
System commissioning Distribution commissioning, cooling commissioning, DCIM commissioning, fire system commissioning, overall joint commissioning 3 Technical engineer Client participates in acceptance
Acceptance and handover Self-inspection and rectification, as-built documentation, client acceptance, training handover 2 Project manager —

13.2 Schedule Assurance Measures

– Plan management: detailed schedule decomposed to daily workload, daily progress check at end of day, timely adjustment if lagging;

– Personnel assurance: sufficient personnel with parallel cross-work between teams to improve efficiency;

– Material assurance: advance stocking to ensure materials and equipment arrive on time, avoiding idle labor due to shortage;

– Coordination assurance: the project manager strengthens coordination with the client and property, solving problems promptly;

– Contingency plan: rush-work plan available — additional personnel and extended hours to ensure the total schedule is not delayed.

14. Construction Organization and Quality/Safety Measures

14.1 Organization Structure

A dedicated project group is established:

Role Count Responsibility
Project manager 1 Overall project management: progress, quality, safety, cost; client interface
Technical leader 1 Technical disclosure, construction guidance, system commissioning, technical problem solving
Decoration team 5 Floor, ceiling, wall, door and window works
Electrician team 4 Power distribution, lightning protection and grounding, lighting
Weak-current team 3 DCIM, access control, video, generic cabling
AC and fire team 3 Water system, cooling equipment, fire system installation and commissioning
Safety officer 1 On-site safety management, inspection and disclosure

14.2 Pre-Construction Preparation

1. Technical preparation: familiarize with drawings and solution, technical disclosure, confirm equipment layout, pipeline routing and interface positions with the client; compile process cards and special construction plans for key processes;

2. Material preparation: stock per configuration list, core equipment inspected on arrival (model, specification, quantity, appearance), tools and testing instruments ready, auxiliary materials stored by category with moisture/fire protection;

3. Site preparation: complete construction procedures, clarify construction area, power/water interfaces and access channels; arrange temporary power, lighting and fire equipment; designate material, tool and waste areas; protect existing facilities.

14.3 Key Process Construction Methods

1. Anti-static raised floor: base treatment (clean, level, dust primer) → layout lines → adjustable pedestal installation (level) → stringer installation (flatness ±1mm/㎡) → panel laying row by row → grounding connection to equipotential network → edge trims and sealing → acceptance of flatness, firmness and grounding resistance.

2. Power distribution system: tray installation (supports, level, jumper grounding) → cable laying (specification verification, labeling, bend radius per code) → cabinet positioning and leveling (firm fixing, grounding) → wiring per diagrams (firm terminals, correct phases, clear labels) → tests: insulation resistance, grounding resistance, power-on, switch operation.

3. Cooling water system: pipe prefabrication (galvanized layer intact, smooth cut ends) → installation (firm supports, sealed connections, correct slope, support spacing per code) → valve installation (correct direction, accessible handles, intact gaskets, even bolt tightening) → insulation after pressure test (tight seams, aluminum foil wrap) → water pressure test 1.6MPa, hold 24h no leakage → system flushing until clear water.

4. DCIM system: front-end device installation (sensors, leakage, access control, cameras at design positions, firm, correct orientation) → wiring (signal/power separated, shielded and grounded, clear labels, standard termination) → host installation in O&M area → commissioning per device (communication, parameters, alarms, linkage) until all data collection and alarms are correct.

5. Gas fire system: device installation (cabinet positioned and leveled, nozzle orientation correct) → detector installation per code spacing (ceiling-mounted, firm base) → wiring in conduits with clear labels per fire code → commissioning (controller functions, detector alarm tests, linkage tests, discharge simulation) → fire department acceptance with qualified report.

14.4 Quality Assurance Measures

– Material quality: all materials/equipment must have certificates, test reports and certification; incoming inspection; unqualified products prohibited;

– Process quality: strict three-level inspection (self, mutual, handover); non-compliant upper process cannot proceed to next;

– Key process control: technical leader supervises distribution wiring, water pressure testing, grounding testing and fire linkage throughout;

– Acceptance standards: strict acceptance per national codes and design requirements; complete construction records and acceptance documentation for each item;

– Personnel qualification: certified personnel only; special operation personnel must hold valid special operation certificates.

14.5 Safety and Civilized Construction Measures

– Safety management system: production safety responsibility system, project manager as first safety responsible person, safety officer daily inspection, pre-shift safety disclosure;

– Electrical safety: three-level distribution with two-level protection for temporary power, locked distribution boxes with dedicated management, no unauthorized wiring, grounded power tools;

– High-altitude safety: qualified scaffolding/ladders for ceiling work, safety helmets, no throwing objects, warning zones below;

– Fire safety: no smoking on site, sufficient fire equipment, hot work permits with dedicated fire watch and flammable material clearance;

– Civilized construction: materials stacked neatly, daily waste removal, work-site-clean policy; noise control to avoid disturbing adjacent offices; uniform attire with work badges.

14.6 Finished Product Protection

– Completed decoration surfaces covered and protected against collision and pollution;

– Equipment dust-protected after installation, warning signs on important equipment;

– Existing pipelines and facilities protected during construction;

– No heavy stacking or marking on finished floors/walls;

– Dedicated guarding before final acceptance to prevent damage and loss.

15. After-Sales Service

15.1 Warranty Commitment

The overall project warranty period is 2 years from the date of completion acceptance; core equipment has a 3-year warranty. During the warranty period, all failures and damage caused by product quality or construction process problems are repaired and parts replaced free of charge. After the warranty period, lifetime cost-price maintenance is provided, charging only parts cost and basic labor, ensuring long-term stable system operation.

15.2 After-Sales Response Mechanism

– A 7×24 after-sales hotline receives fault reports and technical consultations at any time;

– Within the urban area: respond within 2 hours, technicians on site within 4 hours;

– Suburban and surrounding areas: respond within 4 hours, personnel on site within 8 hours;

– General faults resolved on the spot; complex faults solved within 24 hours with a solution;

– Emergency faults get a green channel with priority dispatch of personnel and parts.

15.3 Periodic Inspection and Maintenance

During the warranty period, a free on-site inspection is provided every six months, with a comprehensive maintenance inspection annually. Inspection contents include equipment operating status, connection firmness, sealing and rust conditions, filtering/grounding performance and safety devices. After each inspection, a formal inspection report is issued recording equipment status and maintenance content with optimization suggestions.

15.4 Spare Parts Supply Guarantee

A local spare parts warehouse is established, stocking common wearing parts for quick replacement to shorten fault handling time. For uncommon special parts, a fast supply channel with the factory ensures availability within 48 hours. During warranty, non-artificial-damage spare parts are replaced free; after warranty, parts are charged at cost price without markup.

15.5 System Upgrade and Technical Support

– Free lifetime technical consultation services by phone or online at any time;

– If the customer later needs upgrades or expansions, preferential upgrade solutions and construction services are provided;

– Industry new technology and standard information is regularly pushed to customers.

16. Training Plan

16.1 Training Objectives and Audience

Training objectives: through systematic training, enable management personnel to fully understand the system structure, working principles and performance characteristics, master daily operation methods and inspection/maintenance essentials, identify common faults and handle simple problems, ensuring safe, stable and long-term operation.

Training audience: management and O&M personnel designated by the client, recommended 2-3 persons with basic electrical and equipment knowledge.

16.2 Tiered Training Content System

Level 1: Basic operation training (1 day)

– Basic principles: system concepts, structure composition, performance indicators;

– Daily operation standards: correct operation of equipment, control and safety systems;

– Daily inspection contents: daily/weekly/monthly check items;

– Safety precautions: usage prohibitions and emergency handling procedures.

Level 2: Maintenance training (1 day)

– Detailed structure of each subsystem and working principles;

– Daily maintenance methods: cleaning, fastening checks, routine care;

– Common fault identification and simple handling;

– Emergency handling procedures for power failure, fire and equipment faults.

Level 3: Advanced management training (as needed)

– Performance influencing factors and how to avoid degradation;

– Upgrade and expansion knowledge and specification requirements;

– Relevant national standards interpretation.

16.3 Training Methods and Schedule

– Methods: combination of “theory explanation + on-site practice + Q&A interaction”;

– Schedule: training arranged at the completion acceptance stage, synchronized with handover, 2 days of intensive training total; time flexibly adjustable; a free repeat training session is provided for newly assigned personnel.

16.4 Training Assessment and Documentation Delivery

– Assessment: theory written test plus practical operation; training qualification certificates issued upon passing; supplementary training for those who fail;

– Documentation delivery: complete O&M documentation, including operation and maintenance manual, equipment manuals and certificates, completion drawings and hidden work records, test reports and after-sales service contact card, all bound into volumes.

17. Anonymous Typical Project Scenarios

All project scenarios below are anonymous, generalized examples compiled from typical industry deployments; no real customer names, addresses or confidential information are disclosed.

17.1 High-Density Computer Room for a Technology Company

Project overview: a technology company’s core computer room, 36㎡, deploying 8 high-density server cabinets at 20kW per cabinet, located inside an office building with no outdoor unit installation condition and no drainage point.

Solution: KITOZER water-cooled in-row precision air conditioning with cold aisle containment, modular UPS power supply, integrated DCIM monitoring, and heptafluoropropane gas fire protection.

Result: the room operates stably with precise temperature and humidity control, PUE as low as 1.35, fully meeting the customer’s high-density computing needs; the no-outdoor-unit, no-drainage solution perfectly fits the office building scenario and passed acceptance smoothly.

17.2 Data Center Computer Room for a Financial Enterprise

Project overview: a city commercial bank’s new branch data center, 80㎡, 16 cabinets, Class A standard required with high reliability.

Solution: micro-module cold aisle solution, dual mains + redundant UPS supply, precision AC N+1 redundancy, full-coverage DCIM monitoring, and gas fire protection.

Result: the room has operated stably for 3 years with zero faults, passed Class 3 classified protection evaluation, and gained high customer recognition — subsequent branch computer rooms all chose the same solution.

17.3 Information Computer Room for a Grade-A Hospital

Project overview: core computer room upgrade carrying HIS, LIS, PACS and other core business systems, requiring 7×24 uninterrupted operation.

Solution: integrated cabinet solution with modular UPS, precision air conditioning, DCIM monitoring, and overall upgrade of fire and lightning protection systems.

Result: zero-downtime renovation construction, smooth system switching, greatly improved room reliability and O&M efficiency, ensuring stable hospital business operation.

17.4 Government Affairs Computer Room for a District Government

Project overview: a district-level government service center needed a new government affairs computer room meeting Class 3 classified protection standards, carrying approval systems, a data sharing platform and confidential office terminals, requiring physical isolation, security compliance and full traceability, with limited space needing both storage and O&M needs.

Solution: standardized overall construction with KITOZER electromagnetic shielding cabinets for the confidential area (physical electromagnetic signal isolation), dual modular UPS and redundant cooling, full-dimension DCIM and security systems, tiered lightning protection and ring equipotential grounding.

Result: the project passed Class 3 evaluation and confidential information system graded protection acceptance with 99.99% room availability; the shielding cabinets passed third-party testing at national Class B level, effectively preventing electromagnetic leakage; full traceability and auditability met government information security management standards.

17.5 Smart Campus Data Center for a University

Project overview: a provincial key university’s smart campus core data center, about 120㎡, 30 cabinets, carrying academic affairs, student affairs, campus card and smart teaching platforms, requiring high reliability, easy expansion and low PUE with 3-5 year computing expansion headroom.

Solution: micro-module cold aisle overall solution, dual-bus modular UPS, water-cooled in-row precision AC N+1 with cold aisle containment, integrated DCIM and intelligent O&M platform for unattended remote management, cabinet-type heptafluoropropane fire protection and tiered lightning protection grounding.

Result: annual average PUE stable within 1.38, more than 25% energy saving versus traditional rooms, zero major faults since launch, supporting information services for over 30,000 teachers and students; the intelligent O&M platform cut O&M workload by 40%; the project was rated a provincial education informatization demonstration project.

17.6 Industrial Internet Computer Room for a Manufacturing Enterprise

Project overview: a large equipment manufacturer’s industrial internet dedicated room adjacent to the production workshop with heavy dust, vibration and temperature/humidity fluctuations, carrying MES, PLC data collection gateways and industrial cloud platforms, requiring 7×24 operation with strong anti-interference capability.

Solution: enclosed integrated cabinet cluster with dust-proof and vibration-damping design, industrial-grade precision AC with G4+F8 two-stage filtration, dual redundant power with industrial UPS and lead-acid battery bank, dust-proof DCIM monitoring of dust concentration, vibration and distribution status, plus gas fire protection and lightning protection grounding.

Result: the room maintains Class A temperature/humidity standards year-round, effectively isolating workshop dust and vibration; equipment failure rate dropped 70% after launch with annual downtime under 30 minutes, providing solid infrastructure support for the enterprise’s digital transformation.

18. SEO Optimization Section

All reference prices in this technical solution are in RMB (CNY) only and are for reference purposes; final quotation is subject to the confirmed configuration.

18.1 Keyword System

– Core keywords: technical design solution, system configuration, technical parameters, construction and O&M services;

– High-conversion long-tail keywords: design solution, configuration list, technical parameters, construction plan, after-sales service;

– Industry traffic keywords: system architecture, applicable standards, technical Q&A, project cases;

– Brand keywords: KITOZER, Guangzhou Lain.

18.2 SEO Tag System

– Title tag: the article title — Guangzhou Lain KITOZER;

– Meta description: Guangzhou Lain professionally provides complete technical design solutions with detailed configuration list, full-system product technical parameters, construction organization plan and after-sales service — source manufacturer customization, compliant performance, third-party testing supported;

– H1 tag: the article title;

– H2 tags: system design and product parameters, construction organization plan, after-sales service and training, engineering cases.

18.3 Internal Link Anchor Text

– Core anchor text: technical design solution, system construction;

– Long-tail anchor text: configuration list, technical parameters, construction plan;

– Related anchor text: shielding cabinet, micro-module cold aisle, integrated computer room, outdoor cabinet.

19. Official Contact Information

– Company Name: Guangzhou Lain Intelligent System Development Co., Ltd.

– Brand: KITOZER (Pioneer)

– Official Website: https://gdlain.com

– Tel: +86 139 2228 9957 (WeChat available), +86 185 2066 8845 (WeChat available)

– Address: No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou, China

For any inquiries about this technical design solution, configuration customization, quotation or construction services, please contact us through the information above. We provide free design consultation and tailored solutions for your specific requirements.