Energy Storage Constant Temperature and Humidity Container HVAC Piping Installation Specification

Table of Contents

Weld Quality Requirements

Welds shall be full and smooth, free from porosity, slag inclusion, false welding, and missed welding defects. Weld formation shall be uniform. After welding, clean weld slag and oxide layer, and perform 100% visual inspection. After welding is completed, the piping must be purged with nitrogen. Use 0.8MPa dry high-purity nitrogen injected from the high-pressure end and discharged from the low-pressure end, continuously purging for 5-10 minutes to thoroughly remove residual copper chips, oxide scale, dust, oil, and other impurities from the piping. This prevents impurities from entering the compressor and causing irreversible damage such as cylinder seizure and wear. After purging, seal the pipe openings to prevent secondary contamination.

Piping Fixation and Layout Specification

Refrigerant piping shall be laid horizontally level and vertically straight, with neat and aesthetically pleasing arrangement and reasonable routing, minimizing unnecessary elbows and length to reduce refrigerant resistance loss. Use dedicated galvanized pipe clamps for fixation, with horizontal piping clamp spacing no greater than 1.2m and vertical piping clamp spacing no greater than 1.5m. Additional fixed pipe clamps must be installed 100-200mm on both sides of bends. Reserve no less than 20mm expansion clearance between piping and container structure or other pipelines to prevent stress deformation caused by thermal expansion and contraction of piping due to refrigerant temperature changes, or even cracking of joints.

High-pressure and low-pressure piping shall be laid separately with parallel spacing no less than 50mm. Bundling, wrapping, or intertwining in the same channel is strictly prohibited to prevent mutual interference between cold and hot piping that could affect heat exchange efficiency. Where piping passes through walls or panels, install steel protective sleeves, and fill the gap between the sleeve and piping with flame-retardant sealant—this prevents air leakage loss and blocks rodent and insect intrusion. At expansion joints and deformation joints, install flexible compensation bends to absorb structural deformation.

All piping shall have identification labels posted along the route, indicating medium name, flow direction, and pipe diameter. Valves shall be marked with opening/closing direction and functional name for easy later maintenance and inspection. Piping routing shall avoid maintenance access aisles and operation areas, and it is strictly prohibited to block electrical boxes, inspection openings, valves, and other components.

Piping Insulation Construction Process

All refrigerant piping must be fully wrapped with flame-retardant rubber-plastic insulation. Insulation thickness shall be no less than 20mm, and increased to 30mm for low-temperature suction piping. Flame retardancy shall reach Class B1, with thermal conductivity ≤0.034W/(m·K), meeting energy efficiency and fire protection requirements. Insulation material shall be cut to precise dimensions, with joints bonded using dedicated environmentally friendly adhesive. Joints shall be staggered to avoid forming continuous seams. After bonding, the surface shall be spirally sealed with aluminum foil tape, with overlap width no less than 1/3 of the tape width, ensuring no exposed metal areas to prevent condensation and dripping on piping.

Insulation at valves, joints, sight glasses, and other components shall use removable insulation jackets for easy maintenance access, with insulation and sealing restored promptly after maintenance. After insulation layer construction is complete, perform visual inspection—the surface shall be smooth, free from cracking, peeling, and hollowing, with no obvious deformation under hand pressure. Low-temperature piping requires condensation testing: after 2 hours of system operation, no surface condensation on the insulation layer indicates a pass.

Energy storage constant temperature and humidity containers are often exposed to outdoor high-temperature, high-humidity environments. Piping insulation quality directly affects system energy efficiency and anti-condensation performance. All construction projects by Guangzhou Lain implement enterprise internal control standards that exceed national standards, eliminating common quality issues such as thin insulation layers, leaking seams, and condensation dripping.

System Air Tightness Pressure Holding Test

After piping connection is complete, an air tightness pressure holding test must be performed. This is the core process for verifying piping installation quality and must never be omitted or simplified. The test medium shall be dry high-purity nitrogen. Oxygen, compressed air, or flammable gases are strictly prohibited as substitutes to prevent explosion and piping oxidation.

Test pressure shall be set separately by side: high-pressure side (discharge pipe, condenser side, liquid line) test pressure is 2.8MPa; low-pressure side (suction pipe, evaporator side) test pressure is 1.6MPa. The pressurization process shall be carried out in three stepped stages: first pressurize to 30% of test pressure, hold for 10 minutes, and conduct preliminary leak inspection; if no abnormality, pressurize to 60%, hold for 10 minutes and inspect again; finally pressurize to 100% of test pressure, close the gas source valve, and record initial pressure and ambient temperature.

After reaching test pressure, hold for 24 hours. Pressure drop in the first 6 hours shall not exceed 0.03MPa, and in the following 18 hours shall not exceed 0.02MPa. After temperature correction, no obvious pressure drop indicates a pass. During the holding period, use soapy water to inspect all welds, joints, valves, and flared connections one by one for leaks. If bubbles are found, mark the location immediately, perform corrective action after pressure release, and re-test after correction until completely leak-free.

After passing the pressure holding test, slowly release pressure, maintaining approximately 0.2MPa micro positive pressure to protect the piping from air and moisture ingress until the vacuuming process. Maintain detailed records throughout the test process, including pressurization time, pressure values, ambient temperature, and leak point handling situations, to be included in project acceptance documentation.

System Vacuuming Process

After the air tightness test passes, perform deep vacuuming of the refrigeration system to remove air, moisture, and non-condensable gases from the system. This is a critical process for ensuring system operating efficiency, preventing ice blockage, and extending compressor service life.

Select a rotary vane vacuum pump with a pumping speed of no less than 4L/s, capable of achieving ultimate vacuum of -0.1MPa. Connect the vacuum pump simultaneously to the system’s high and low pressure service valves through charging hoses for two-way evacuation, improving vacuuming efficiency. Before vacuuming, confirm all system valves are in the open position, with compressor suction and discharge valves closed.

Total vacuuming duration shall be no less than 2 hours. After system vacuum reaches -0.098MPa (755mmHg or above), continue vacuuming for an additional 30 minutes for deep dehydration. Then close the vacuum pump valve, stop the vacuum pump, and maintain the vacuum state for 1 hour. A pressure rise not exceeding 0.005MPa indicates a pass. If vacuum requirements cannot be met or pressure rises too quickly, this indicates micro-leaks or high moisture content in the system—re-inspect for leaks, and continue only after passing.

During vacuuming, it is strictly prohibited to start the compressor, start the vacuum pump while the system is pressurized, or allow vacuum pump oil to backflow into the refrigeration system. Vacuuming operations must be performed by certified refrigeration technicians, strictly following refrigeration safety operating procedures.

Refrigerant Charging and Calibration

According to the refrigerant type and rated charge quantity indicated on the unit nameplate, use precise metered charging method for refrigerant charging. Refrigerant must be high-purity original factory refrigerant conforming to national standards. Use of inferior recycled refrigerant is strictly prohibited, and mixing different refrigerant types is strictly prohibited to avoid damaging the compressor and heat exchange components.

Use liquid charging method from the high-pressure side. Before charging, connect the refrigerant cylinder to the charging hose, open the cylinder valve to purge air from the hose, preventing air from entering the system. Place the refrigerant cylinder on an electronic scale, zero the tare weight, slowly open the valve, control the charging rate, observe the electronic scale reading, and precisely control the charge quantity with an error not exceeding ±5%.

During charging, monitor system pressure changes. If charging rate slows, the compressor can be started to supplement from the low-pressure side in gaseous state, but liquid refrigerant directly entering the low-pressure side is strictly prohibited to prevent liquid slugging damage to the compressor. After charging is complete, close the valve, remove the charging hose, perform soapy water leak inspection on the service valve port, and install the dust cap and protective cover after confirming no leaks.

When charging at low temperatures, the refrigerant cylinder can be heated with warm water below 40°C to increase charging rate. Open flame heating of cylinders is strictly prohibited, and overpressure filling is strictly prohibited. After charging is complete, run the unit for 30 minutes, observe operating pressure, current, superheat, and subcooling, and fine-tune the refrigerant quantity to achieve optimal operating conditions.

After refrigerant piping construction is complete, the technical manager shall conduct dedicated quality acceptance, verifying construction records and test reports, spot-checking key node quality, and proceeding to the next process only after passing. Industrial constant temperature and humidity container refrigeration systems operate continuously for long periods. Piping installation quality directly determines the equipment’s trouble-free operating cycle. Guangzhou Lain has established a three-tier quality inspection mechanism to ensure every system meets factory quality standards.

11.7 Condensate Drainage System Installation

Constant temperature and humidity air conditioning systems continuously generate condensate during cooling and dehumidification operation. Although the condensate drainage system is an auxiliary system, blockage, leakage, or backflow failures can directly cause water damage to internal equipment and stored materials. Construction quality must be strictly controlled.

System Composition and Design Requirements

The condensate drainage system consists of the evaporator drain pan, water level switch, drain hose, U-trap, main drain pipe, expansion joint, support hangers, and sewage outlet, relying on gravity self-flow drainage without power requirements. System drainage capacity shall be configured at 1.5 times the condensate volume under maximum dehumidification conditions, reserving sufficient margin.

The drain pan shall be made of stainless steel, with a depth of no less than 50mm, and a volume sufficient to hold 10 minutes of condensate at full-load operation, preventing overflow from instantaneous large volumes of condensate. The drain pan shall have a 1%-2% slope toward the drain outlet, ensuring condensate naturally flows to the drain outlet without dead zones for water accumulation. A float-type or electrode-type high water level switch shall be installed in the drain pan. When poor drainage causes the water level to rise to the alarm value, it automatically triggers an alarm and shutdown protection to prevent water overflow into the container.

Drainage Piping Installation Specification

Condensate piping shall use national standard UPVC or PPR pipe materials. Standard 20-foot units use DN25 pipe diameter; 40-foot and high-capacity units use DN32 pipe diameter. Pipe interior walls shall be smooth, resistant to scaling and blockage. Piping shall maintain a 2‰-5‰ slope throughout its routing. Reverse slopes and level sections are strictly prohibited to ensure smooth drainage. Horizontal piping shall have a support hanger installed every 3m to prevent piping deformation and sagging that creates water accumulation sections.

Pipe connections shall use dedicated adhesive bonding or thermal fusion connection, with firm and tight joints. Before bonding, clean oil and dust from pipe ends, apply adhesive evenly, insert to position and rotate half a turn to distribute the adhesive layer evenly, then allow to cure before moving the piping. A removable sewage plug shall be installed at the lowest point of the piping for later unclogging and cleaning of sediment.

The connection between the air conditioning unit drain outlet and rigid piping shall use transparent PVC flexible hose, 100-150mm in length, secured with hose clamps. This both absorbs unit vibration (avoiding stress damage to the drain pan from piping) and allows visual observation of drainage status.

U-Trap Installation Requirements

A U-trap must be installed at the unit’s condensate outlet. Water seal height shall be determined based on the unit’s internal static pressure. Standard unit water seal height is 50-80mm; the greater the negative pressure, the higher the required water seal height. The U-trap’s function is to use the water seal to block air, preventing negative pressure in the air duct from drawing air back in during unit operation, which would impede normal condensate drainage. It also blocks sewer odors and insect backflow into the container.

The U-trap shall have a removable union structure for easy disassembly and cleaning when blocked. Before restarting after extended shutdown, water must be added to the U-trap to form an effective water seal, avoiding air leakage and poor drainage during initial discharge. A vent hole shall be provided on the outlet side of the U-trap to balance air pressure in the drainage piping for smoother drainage.

Water Flow and Leakage Prevention Testing

After drainage piping installation is complete, perform water flow testing and full water testing. Water flow test: slowly pour room-temperature clean water into the drain pan, with flow rate simulating maximum condensate volume, and observe whether drainage is smooth, whether pipe joints leak, and whether the U-trap water seal forms properly. Full water test: plug the drain outlet, fill the drain pan and piping completely with water, and let stand for 2 hours. Check all joints and welds for leakage. No obvious water level drop indicates a pass.

Simultaneously test the high water level switch function: manually raise the water level to the alarm position, verify the alarm signal triggers normally and the unit executes the shutdown protection action, ensuring timely warning during faults.

Piping Insulation and Protection

Condensate piping inside the container shall be fully wrapped with 15mm thick flame-retardant rubber-plastic insulation to prevent condensation when the pipe surface temperature falls below the dew point, which would cause dripping and wetting of equipment and cargo below. Insulation joints shall be tight, with the surface wrapped in aluminum foil tape for a neat appearance. Outdoor drainage piping shall be insulated and freeze-protected, with electric heat tracing installed for winter low-temperature environments to prevent pipe freezing, cracking, and blockage.

Condensate shall ultimately be routed to the site’s municipal drainage system or collection well. Random discharge causing ground water accumulation is strictly prohibited. The drainage outlet shall be equipped with an insect screen and water seal to prevent rodents and insects from entering the container along the piping.

Energy storage containers house batteries, electrical equipment, and other high-value assets. Water leakage can cause enormous economic losses. Guangzhou Lain’s constant temperature and humidity containers not only feature dual drainage protection design but are also equipped with a leak detection system, achieving second-level early warning of leakage hazards and providing comprehensive operational safety protection.

11.8 Air Conditioning System Individual Unit Test Run

After air conditioning system installation is complete, individual unit test runs must be performed before overall integrated commissioning. Each core component—including fans, compressors, and heaters—must be verified individually to identify installation defects and equipment faults early, clearing obstacles for system integration commissioning.

Pre-Test Run Inspection

Before test run, the commissioning engineer shall inspect item by item to confirm start conditions are met:

Electrical inspection: Verify power supply voltage and phase sequence are correct, within ±10% deviation; all wiring is secure and correct with clear wire numbers; circuit breakers, thermal relays, and other protective devices are set according to rated parameters; equipment grounding is reliable; insulation resistance meets requirements.

Piping inspection: Refrigerant piping pressure is normal with no leaks; condensate piping is clear and U-trap is filled with water; all valves are in correct open/closed positions, with service valves fully open.

Unit body inspection: No tools or debris left inside the unit; fan impeller rotates freely by hand with no binding or friction noise; compressor mounting bolts are tight, anti-vibration pads are intact; heat exchanger fins are not bent or blocked.

Environment inspection: Supply and return air paths are clear with no obstructions or blockages; no flammable, explosive, or volatile corrosive materials inside the container; fire extinguishing equipment and emergency tools are available on site.

After inspection is complete, fill out the individual unit test run inspection record. Equipment may only be started after all items are confirmed qualified.

Fan System Test Run

First start the supply air fan and return air fan individually. Use jog start method—briefly start and stop to observe whether fan rotation direction is correct and whether there are abnormal impact sounds. If rotation direction is wrong, stop immediately and swap two phases of the three-phase power supply.

After rotation direction is confirmed correct, run continuously for 2 hours, monitoring operating parameters throughout:

  • Fan operating current and voltage are stable within rated range, with three-phase current unbalance no greater than 5%;
  • Fan bearing temperature rise does not exceed 40°C, maximum temperature does not exceed 70°C, with no abnormal heating;
  • Unit operates smoothly, vibration velocity RMS value does not exceed 2.8mm/s, with no resonance phenomenon;
  • Noise value at 1m from the unit does not exceed the nameplate rated value, with no sharp abnormal sounds or friction noise.

During operation, check fan belt tension (belt-driven type)—belt deflection when pressed shall meet manual requirements. Belts that are too loose (slipping) or too tight (bearing wear) both require adjustment. Check all connecting bolts for looseness, and flexible connections for pulling or deformation. After test run completion, record all parameters and fill out the fan test run record form.

Refrigeration Compressor Test Run

After fans operate normally, start the refrigeration compressor. First use jog start to confirm compressor rotation direction is correct and there are no abnormal impact sounds from liquid slugging or cylinder seizure. After formal start, first run unloaded for 30 minutes, gradually observing operating status:

  • Monitor suction pressure and discharge pressure, stable within the unit’s normal operating range, discharge temperature not exceeding 90°C;
  • Check compressor operating current, not exceeding 1.1 times rated current, three-phase current balanced;
  • Observe compressor oil sight glass oil level, maintained at 1/2-2/3 position, with normal oil return and no oil carryover;
  • Listen to compressor operating sound—stable and uniform, no liquid slugging sound, metal friction sound, or abnormal vibration sound;
  • Check compressor housing temperature, no localized overheating, piping frosting and condensation status normal.

If abnormal pressure, current exceeding limits, abnormal sounds, or other situations occur during operation, stop immediately to investigate the cause. Restart only after fault elimination. Operating with faults is strictly prohibited. After first start, run for 1 hour then stop to check compressor oil level and system status. If no abnormality, proceed with extended operation testing.

Heating System Test Run

For heat pump type units, switch to heating mode and run for 30 minutes. Check whether the four-way valve reverses correctly and whether there is abnormal reversal noise. Monitor high/low pressure under heating conditions and supply air temperature, confirming heating capacity meets design requirements. Check defrost function is normal—simulate defrost logic under low-temperature high-humidity conditions, verifying the defrost process is stable with no excessive condensed water splashing.

For electric heating type units, start electric heaters in stages by group. Check each heater group’s operating current meets rated values, and overheat protection and fuse protection functions are effective. Supply air temperature rises uniformly with no localized overheating. Electric heating and fan interlock is normal—electric heating cannot be enabled when the fan is not running, preventing dry-burn damage.

Test Run Safety and Recording Requirements

Individual unit test runs involve live electrical and pressurized operations. Operators must hold valid certification. At least two people are required for operations—one operator and one supervisor. Solo operation is strictly prohibited. During test runs, do not leave the post without authorization. Closely monitor operating parameters. If any abnormality is found, press the emergency stop button immediately. High-pressure piping and high-temperature components must never be touched by hand to prevent burns or frostbite.

Detailed records shall be maintained throughout the test run process, including test run time, ambient temperature and humidity, operating voltage and current, high/low pressure values, supply/return air temperatures, vibration and noise values, fault handling situations, etc. Records shall be jointly signed by the commissioning personnel and supervisor and archived as essential documentation for project acceptance.

Individual unit test run is a critical connecting process in the constant temperature and humidity container installation and commissioning workflow. Guangzhou Lain strictly implements the quality principle of “no integrated commissioning until individual units pass,” ensuring every component reaches optimal condition and guaranteeing long-term reliability of the complete system.

The uniformity, stability, and control accuracy of temperature and humidity inside constant temperature and humidity containers depend not only on air conditioning unit performance but also on air duct system design and installation quality. Proper air distribution enables uniform temperature and humidity coverage throughout the entire working area, eliminates local dead zones, improves control accuracy, and reduces operating energy consumption.

12.1 Air Duct System Design Principles

Container-type constant temperature and humidity system air duct design must integrate container structure, internal equipment layout, and temperature/humidity accuracy requirements for comprehensive planning, following these core principles:

Uniform air distribution: Prioritize the top-supply bottom-return air distribution pattern, forming a top-down piston flow covering the entire working area to avoid temperature and humidity dead zones. When battery racks are arranged inside energy storage constant temperature and humidity containers, use precision supply air ducts with supply air outlets corresponding to each battery module layer, ensuring the temperature difference between the top and bottom of battery clusters does not exceed 2°C.

Air resistance optimization: Optimize duct routing, reduce 90° sharp elbows, use large-radius elbows and gradually tapered ducts to reduce total system air resistance, improve fan energy efficiency, and lower operating noise. Main duct air velocity controlled at 6-8m/s, branch duct velocity 3-5m/s, working area supply air velocity 0.2-0.3m/s.

Integrated sealing and insulation: Ducts fully sealed with air leakage rate ≤2%, reducing heating/cooling losses; duct exterior walls insulated to prevent condensation and reduce supply air temperature rise/drop.

Maintenance convenience: Ducts equipped with inspection openings. Filters, silencers, and other wear-prone components positioned for easy disassembly and replacement. Duct interiors accessible for regular cleaning and dust removal.

Fire safety compliance: Ducts made of non-combustible Class A materials. Fire dampers rated at 70°C installed where ducts pass through equipment partition zones, interlocked with the fire protection system to automatically close and block airflow during fires, in compliance with GB 50243 requirements.

12.2 Air Duct Fabrication and Installation Process

Duct Material and Fabrication Requirements

Galvanized steel sheet is preferred for interior ducts in industrial constant temperature and humidity containers. Sheet thickness is determined by duct long-side dimension: long side ≤400mm—0.5mm thickness; 400mm < long side ≤1000mm—0.75mm thickness; long side > 1000mm—1.0mm thickness. For high-humidity, high-corrosion scenarios, use 304 stainless steel ducts. For clean scenarios, lightweight insulated ducts such as phenolic composite ducts or fiberglass composite ducts may be used.

Ducts shall use Pittsburgh lock seam or button punch snap lock connections. Lock seams must be tight and smooth, with uniform width, free from holes, half-locked seams, or splitting defects. For rectangular ducts with long side greater than 630mm and section length greater than 1250mm, install angle steel reinforcement frames and threaded rod reinforcement ribs to prevent duct collapse under negative pressure, bulging under positive pressure, and resonance noise during operation.

Duct elbows shall use inside-outside curved elbows with curvature radius of 1-1.5 times the duct side dimension, reducing airflow resistance and eddy current noise. Duct transitions shall use gradually expanding/contracting sections with expansion angle not greater than 30° and contraction angle not greater than 45°, ensuring smooth airflow transition and reduced local resistance. After duct fabrication, clean oil and dust from interior surfaces and seal both ends to prevent secondary contamination.

Duct Installation Construction Process

Before duct installation, re-verify elevation and routing against design drawings. Ducts shall be fixed with galvanized threaded rod hangers. Hanger spacing: for horizontal ducts with long side ≤400mm, spacing no greater than 4m; for long side > 400mm, no greater than 3m. Vertical duct spacing no greater than 4m, with no fewer than 2 fixings per vertical riser. Hanger expansion bolts shall be secured to the container’s top beam steel structure. Securing directly to insulation layers or decorative panels is strictly prohibited to prevent falling.

For flanged duct connections, use 3mm thick closed-cell sponge rubber sealing strips between flanges, with temperature resistance range of -30°C to 120°C. Bolts shall be tightened evenly with nuts oriented consistently, ensuring tight and leak-free joints. At connections between ducts and air conditioning units or air outlets, use fire-resistant canvas flexible connections, 150-200mm in length, with appropriate tension and no twisting or deformation—these both isolate fan vibration transmission to ducts and compensate for installation tolerances.

During duct installation, maintain levelness and verticality with horizontal deviation no greater than 3‰ and vertical deviation no greater than 2‰. Valves and adjustment mechanisms on ducts shall be positioned for convenient operation with clearly marked opening/closing directions. Volume control dampers shall be installed on main and branch ducts for later air volume balancing.

Duct Insulation and Sealing

Duct exterior shall be wrapped with 20mm thick flame-retardant rubber-plastic insulation, increased to 30mm for low-temperature supply air ducts. Insulation layer shall be smooth and tight, with joints bonded using dedicated adhesive and spirally sealed with aluminum foil tape, free from cracking, peeling, or hollowing. An aluminum foil protective layer may be added over the insulation to prevent mechanical damage and dust accumulation.

After duct installation, perform light leak detection: in a dark environment, place a 100W safety lamp with protective cover inside the duct, slowly move along duct seams and joints, observing from outside for light leak points. For low-pressure systems, no more than 2 light leak points per 10m of seam, with an average of no more than 16 points per 100m of seam, indicates a pass. Medium and high-pressure systems also require air leakage rate testing, with leakage rates meeting GB 50243-2016 standard requirements.

12.3 Supply/Return Air Outlet Installation and Air Volume Balancing

Outlet Selection and Layout

Supply air outlets shall use square diffusers or slot-type adjustable outlets with good supply air diffusion and uniform airflow attenuation, avoiding direct blowing that creates local temperature differences. Return air outlets shall use louver-type return grilles with built-in G4 grade primary filters to block large particles from being drawn into the fan, protecting the heat exchanger and fan impeller. Outlet materials may be aluminum alloy with electrostatic powder coating or flame-retardant ABS, with colors coordinated with the container interior finish.

Supply air outlets shall be evenly arranged along the longitudinal direction at the top of the container with 2-3m spacing, ensuring supply air covers the entire working area. Return air outlets shall be arranged on both sides at the lower portion or at the lower end of one side, forming a top-supply bottom-return vertical air distribution pattern to improve temperature and humidity uniformity. Outlet placement shall avoid positioning directly above large equipment to prevent supply air from directly blowing onto equipment surfaces, causing sudden local temperature changes that affect stored material performance.

Outlet Installation Requirements

Outlets shall be installed level and securely, with tight connection to ducts, flush against ceiling decorative surfaces without gaps, and sealed around the perimeter with neutral sealant. Outlet blade angles shall be adjustable, with blade angles adjusted based on airflow test results after installation to optimize air distribution. Within the same space, outlets shall be neatly arranged with consistent elevations, uniform spacing, horizontally level and vertically straight, aesthetically coordinated.

Return air outlet filter screens shall be firmly installed with drawer-type structure for easy removal, cleaning, and replacement. Outlet surfaces shall be free from scratches and deformation, with uniform blade spacing and smooth opening/closing operation.

Air Volume Balancing

After outlet installation, use a thermal anemometer to measure the air volume at each supply and return outlet point by point. Balance air volumes by adjusting duct volume control dampers and outlet blade angles. Balancing standard: deviation between actual and design air volume at each outlet shall not exceed ±10%, and deviation between total system air volume and design total shall not exceed ±5%.

Air volume balancing is a prerequisite for ensuring uniform temperature and humidity inside the container. Each point must be adjusted and repeatedly calibrated to ensure reasonable air volume distribution in every zone. For complex scenarios with internal shelving or equipment obstructions, fine-tune outlet angles and air volumes based on actual airflow conditions to eliminate air short-circuiting and supply air dead zones.

12.4 Air Distribution Verification and Optimization

After duct installation, on-site air distribution testing and optimization must be performed to ensure uniform internal temperature and humidity fields.

Airflow pattern testing: Use a smoke generator to release visible smoke and observe the airflow pattern inside the container, confirming whether airflow spreads uniformly and whether there are short-circuiting, dead zone, or eddy current areas. Focus on corners, behind equipment, between shelf layers, and other locations prone to dead zones.

Air velocity distribution testing: Within the working area, use a 1m×1m grid layout to measure air velocity at three heights—0.5m, 1.5m, and 2.0m. Average air velocity in the working area shall be controlled at 0.2-0.3m/s. Excessive air velocity accelerates moisture loss from materials; insufficient air velocity results in poor temperature and humidity uniformity.

Preliminary temperature field testing: After the system operates stably under no-load conditions, arrange temperature and humidity measurement points at different positions and heights inside the container, continuously monitoring for 1 hour to preliminarily identify areas with significant temperature or humidity differences.

Targeted optimization: For issues identified in testing, adjust outlet angles and air volume distribution. If necessary, add air deflectors and flow equalizers to optimize air distribution. For scenarios with large equipment obstructions, add side supply outlets or inter-layer supply air branch ducts to ensure airflow reaches every corner.

Good air distribution can significantly improve the temperature and humidity uniformity of constant temperature and humidity containers with equivalent equipment configuration while reducing system energy consumption. Guangzhou Lain uses CFD fluid simulation to preview airflow effects during the product design phase, and performs on-site measurement and optimization after construction completion—dual assurance of uniform and stable internal environment.

12.5 Air Filtration System Installation

The air filtration system not only ensures indoor air quality inside the container but also protects internal precision equipment and stored materials from dust contamination, while extending the service life of air conditioning heat exchangers. It is an important component of industrial constant temperature and humidity containers.

Filtration Grade Configuration

Standard configuration uses G4 grade primary filters, capable of filtering dust particles ≥5μm with 90% filtration efficiency, suitable for ordinary energy storage and industrial warehousing scenarios. For electronic and pharmaceutical scenarios with higher cleanliness requirements, add F8 grade medium filters for particles ≥0.5μm with 95% efficiency. For ultra-high cleanliness requirements, H13 grade HEPA high-efficiency filters can be configured, with filtration efficiency ≥99.97% for 0.3μm particles, achieving Class 10,000 cleanliness.

Filter Installation Requirements

Primary filters shall be installed at the return air outlets and the return air section of the air conditioning unit. Medium filters shall be installed in the supply air section of the unit. High-efficiency filters shall be installed at the terminal supply air outlets. Differential pressure transmitters shall be installed before and after each filter stage to monitor filter resistance in real time. When resistance reaches 2 times the initial resistance, the control system automatically issues a cleaning or replacement reminder.

Filters shall be installed level and securely, with closed-cell sponge sealing strips between the filter and frame to prevent side leakage, ensuring all air passes through the filter media. Filter installation direction shall match airflow direction, with the upstream face corresponding to the marking. Reverse installation is strictly prohibited. Drawer-type filters shall slide smoothly with secure latches for quick replacement.

Before high-efficiency filter installation, perform visual inspection—filter media free from damage and adhesive leakage, frames free from deformation. After installation, perform leak testing using the particle counter scanning method with scanning speed ≤5cm/s. Leak point penetration rate ≤0.01% indicates a pass. Obvious leak points are strictly prohibited.

Maintenance Documentation Delivery

Upon completion of installation, deliver a filter maintenance manual to the user, specifying cleaning and replacement cycles for different filter grades. Under normal outdoor environments: primary filters cleaned every 1-2 months and replaced every 6-12 months; medium filters replaced every 3-6 months; high-efficiency filters tested annually, replaced when resistance exceeds limits or leaks are detected. In high-dust or chemical environments, shorten cycles accordingly.

Battery modules and electrical components inside energy storage containers are sensitive to dust. Dust accumulation affects heat dissipation performance and reduces insulation strength. A reliable air filtration system can effectively reduce equipment failure rates and extend overall system service life.

The humidity control system is the core function distinguishing constant temperature and humidity containers from ordinary air conditioning containers. Through bidirectional adjustment of humidification and dehumidification, relative humidity inside the container is stabilized within the set range, meeting the humidity requirements of different material storage and equipment operation.

13.1 Electrode Steam Humidifier Installation

Electrode steam humidifiers are the standard humidification configuration for small and medium constant temperature and humidity containers, featuring simple structure, fast response, high control accuracy, and convenient maintenance.

Operating Principle and Structure

Electrode steam humidifiers work by inserting electrode rods into water in the humidification cylinder. Using water’s electrical conductivity, current passes through the water body generating Joule heat, heating the water to boiling to produce clean steam, which is carried into the container air by the supply airflow for humidification. Humidification output is regulated by controlling electrode energization time and water level height, combined with PID control algorithms for precise humidity control.

The equipment mainly consists of the humidification cylinder, electrode rods, inlet water solenoid valve, drain solenoid valve, water level sensor, and control module, integrated into the humidification section of the air conditioning unit with compact structure. The humidification cylinder is removable for regular scale cleaning and replacement.

Water Supply System Connection

The humidifier water supply connects to municipal tap water, requiring inlet water pressure of 0.1-0.4MPa. A Y-type strainer (40 mesh) shall be installed on the inlet water line to filter sediment and impurities from water, preventing solenoid valve blockage and accelerating scale formation. A manual service valve shall be installed upstream of the inlet for shutting off the water source during maintenance.

Water quality requirement is ordinary municipal tap water with resistivity of 100-1000Ω·cm. Ultra-pure water (such as distilled water or RO water) has poor conductivity and cannot operate properly. Water with excessive hardness accelerates electrode scaling and shortens humidification cylinder life. In high-hardness water scenarios, an optional water softener can be installed to reduce inlet water hardness and extend consumable life by 3-5 times.

Steam Delivery and Installation

Steam is delivered through high-temperature resistant steam tubing into the air conditioning supply air duct. Steam tubing shall use food-grade silicone tubing or stainless steel tubing. Piping shall maintain an upward slope to prevent steam condensate from flowing back into the humidifier main unit. The steam outlet shall be positioned in the fan’s positive pressure section, using high-velocity supply air to rapidly disperse and mix steam, avoiding localized condensation and dripping.

The humidifier body shall be installed vertically with tilt no greater than 5°, ensuring accurate water level detection. Insulation isolation shall be provided between the humidification cylinder and unit body to prevent water-borne current from conducting to the unit housing. Equipment grounding shall be reliable, and the power supply circuit shall be equipped with residual current protection devices for electrical safety.

Functional Testing

After installation, perform power-on testing:

Water inlet test: Open the inlet valve, check water inlet speed is normal, high and low water level switches operate accurately, and water supply automatically stops when water level reaches set value;

Heating test: Start the heating function, observe normal steam production, humidification output reaches rated value, with no water leakage or electrical leakage;

Drain test: Activate the blowdown function, drain solenoid valve opens smoothly, drainage is thorough, and no blockage occurs;

Protection test: Simulate water shortage, overcurrent, and over-temperature faults, verify protection functions trigger normally, and alarm signals upload accurately to the main controller.

Electrode steam humidifiers produce clean steam with precise control, making them very suitable for industrial constant temperature and humidity containers requiring high humidity accuracy. All Guangzhou Lain product series come standard with branded humidification components, providing stable operation, universal spare parts, and low later-stage maintenance costs.

13.2 High-Pressure Micro-Mist Humidification System Installation (Optional)

For energy storage containers larger than 40 feet with high humidification volume requirements, high-pressure micro-mist humidification systems can be selected, offering higher humidification efficiency, lower energy consumption, and greater humidification output.

System Composition and Principle

The high-pressure micro-mist humidification system consists of a high-pressure plunger pump, stainless steel high-pressure piping, ceramic atomizing nozzles, water treatment unit, water softener, and control unit. The high-pressure plunger pump pressurizes purified water to 7-10MPa, which is sprayed through dedicated atomizing nozzles into ultra-fine mist particles of 5-10μm. The mist rapidly evaporates in the air, absorbing heat and achieving dual humidification and cooling effects. Humidification efficiency can reach above 95%, with energy consumption only 1/10 of electrode steam humidifiers.

Main Unit and Piping Installation

The high-pressure main unit shall be installed in the equipment room at the container end or a corner, on a level foundation with anti-vibration pads installed at the bottom to reduce operating noise and vibration. The main unit shall be installed horizontally with tilt no greater than 1°, ensuring normal pump head lubrication and extended service life. Reserve more than 400mm of maintenance space around the main unit for filter cartridge replacement and pump maintenance.

High-pressure piping shall use 304 stainless steel high-pressure tubing or nylon high-pressure tubing. Pipe connections shall use dedicated ferrule-type fittings with reliable sealing, high pressure resistance, and corrosion resistance. Piping shall be neatly arranged and fixed with dedicated pipe clamps at 1-1.5m spacing to prevent vibration wear during operation. Large-radius elbows shall be used at pipe bends to reduce resistance.

After piping installation, perform a pressure test at 1.5 times working pressure (15MPa), holding for 30 minutes. No obvious pressure drop and no joint leakage indicate a pass. Using low-pressure piping to replace high-pressure piping is strictly prohibited to prevent pipe burst risk.

Nozzle Arrangement and Commissioning

Atomizing nozzles shall be evenly arranged in the supply air duct or in the top supply air outlets based on space size and humidification volume requirements, using supply airflow to fully disperse and rapidly completely evaporate the mist. Nozzle direction shall align with airflow direction. Directing mist toward electrical equipment, walls, or materials is strictly prohibited to prevent condensation and dripping.

Single nozzle flow rate is 2-5L/h depending on model. Total nozzle quantity shall be configured per design humidification output with 10%-20% margin. Nozzles use quick-connect installation for easy removal, cleaning, and replacement.

During system commissioning, first run water through at low pressure to flush the piping, removing impurities from the piping to prevent nozzle blockage. Then start the high-pressure system, gradually increasing pressure to working pressure of 7MPa. Check atomization effect of each nozzle—mist particles shall be uniform and fine, with no dripping, off-angle spraying, or blockage. Adjust system working pressure and nozzle quantity so total humidification output meets design requirements.

Water Treatment and Safety Protection

The high-pressure micro-mist system has high water quality requirements. Inlet water must undergo softening treatment with total hardness ≤50mg/L to prevent nozzle scaling and blockage. Inlet water shall be configured with three-stage filtration: 50μm pre-filter, 5μm precision filter, and activated carbon filter to remove impurities, residual chlorine, and odors. Replace filter cartridges regularly to ensure outlet water quality.

The system is equipped with multiple safety protections: water shortage protection, overpressure protection, overload protection, and water leakage protection. Faults trigger automatic shutdown and alarm with audible and visual indication. After extended shutdown, the system automatically executes the drain program to empty piping water, preventing bacterial growth and winter freeze cracking.

13.3 Refrigeration Dehumidification System Installation

Refrigeration dehumidification is the basic dehumidification function of constant temperature and humidity containers, integrated within the refrigeration system—simple in structure, reliable in operation, and capable of meeting most humidity requirements above 30%RH.

Dehumidification Principle and Structure

When humid air passes over the low-temperature evaporator coil, the air temperature rapidly drops below the dew point. Water vapor in the air condenses into water droplets on the surface of hydrophilic aluminum foil fins, flowing along the fins into the drain pan and being discharged, thereby reducing air moisture content and achieving dehumidification. Dehumidification capacity is related to evaporator temperature, airflow volume, and air humidity.

The evaporator coil uses inner-grooved copper tubes with hydrophilic aluminum foil fins for high heat exchange efficiency and easy condensate runoff. Fin spacing is 2.0-2.5mm, balancing heat exchange efficiency with anti-clogging performance—resistant to dust accumulation and easy to clean and maintain.

Dehumidification Reheat System

Pure refrigeration dehumidification simultaneously lowers air temperature. To maintain stable temperature, a reheat system is required. Standard models use electric heating reheat with staged control for flexible adjustment. High-efficiency models use heat pump heat recovery reheat, utilizing condensation heat to reheat the dehumidified cold air without additional power consumption, improving energy efficiency by more than 30%.

The reheater is installed downstream of the evaporator. Dehumidified cold air passes through the reheater, rises to the set temperature, and is delivered into the container, achieving constant temperature dehumidification and avoiding temperature fluctuations inside the container. The reheater surface temperature shall be uniform with no localized overheating, equipped with overheat thermal fuse protection to prevent dry-burn fire in case of fan failure.

Eliminator and Drain Pan

A baffle-type eliminator shall be installed on the evaporator outlet side, made of ABS or 304 stainless steel, with multi-fold angle structure to effectively intercept water droplets carried in the air, preventing moisture carryover into the air duct that could wet internal materials. The eliminator shall be installed tightly with no gaps at the frame, with the bottom connected to the drain pan so all intercepted droplets flow into the drainage system.

Under dehumidification conditions, condensate volume is large. The drain pan volume shall be designed at 1.5 times maximum dehumidification capacity with depth no less than 60mm. The drain pan bottom shall slope at 5° toward the drain outlet with no water accumulation dead zones. Dual drain outlets shall be provided—one in use, one as backup—preventing overflow from debris blockage.

Dehumidification Performance Verification

During system commissioning, perform dehumidification performance testing: create a high-humidity environment inside the container, start dehumidification mode, and after stable operation, measure supply and return air temperature and relative humidity. Calculate the air moisture content difference and combined with airflow volume, calculate total dehumidification output. Reaching 90% or more of rated dehumidification capacity indicates a pass.

Simultaneously check for moisture carryover at supply air outlets, condensation or dripping on the interior ceiling and walls, and water accumulation in the air duct. If moisture carryover issues exist, adjust air velocity, add eliminators, or optimize the air duct to thoroughly resolve the issue.

13.4 Rotor Dehumidification System Installation (Optional)

When scenarios require low-humidity environments with relative humidity ≤30%RH, refrigeration dehumidification cannot meet requirements. A rotor dehumidification system must be added to achieve deep dehumidification, with minimum dew point temperature reaching -40°C and relative humidity as low as 10%RH.

System Composition and Principle

The core component of the rotor dehumidification system is the desiccant rotor. The rotor substrate is ceramic fiber with a surface coating of silica gel or molecular sieve desiccant material. The rotor rotates slowly at 10-15 revolutions per hour, divided into process zone and regeneration zone: when humid air passes through the process zone, moisture is adsorbed by the rotor and dry air is delivered into the room; simultaneously, high-temperature regeneration air passes through the regeneration zone, desorbing the moisture adsorbed by the rotor and exhausting it outdoors. The rotor rotates continuously, achieving continuous and stable deep dehumidification.

The system mainly consists of the desiccant rotor, drive motor, regeneration fan, regeneration heater, filters, heat exchanger, and control system.

Equipment Installation and Duct Connection

The rotor dehumidification unit is generally installed upstream of the air conditioning unit as a fresh air pre-treatment section. It first deeply dehumidifies fresh air, then mixes with return air entering the temperature control section for temperature adjustment, achieving low-temperature low-humidity environment control.

The unit shall be installed horizontally with a leveled base and complete anti-vibration pad configuration. Ducts are divided into the process air side and regeneration air side, strictly separated—cross-airflow is strictly prohibited. Process air inlet connects to air conditioning return air, process air outlet connects to the air conditioning unit inlet section. Regeneration air inlet connects to outdoor fresh air, regeneration air outlet connects to outdoor exhaust. Duct connections shall be tight with leakage rate ≤2%. Regeneration ducts shall be insulated to reduce heat loss.

The regeneration heater shall use PTC electric heating or stainless steel finned electric heating with multi-stage power adjustment, precisely controlling regeneration temperature at 120-140°C. An over-temperature protector shall be installed at the heater outlet, automatically cutting power when temperature exceeds 160°C to prevent overheating and fire.

Sealing and Drive Commissioning

High-temperature resistant silicone sealing strips shall be used between the rotor and housing to separate the process zone and regeneration zone. Sealing shall be tight to minimize cross-airflow and ensure dehumidification efficiency. Sealing strips are wear-prone components, installed with clip-on structure for quick replacement when worn.

The rotor drive mechanism uses a reduction motor with chain/belt drive, operating smoothly with precise rotation speed. After installation, manually rotate the rotor to confirm free rotation without binding or friction. Power on and commission the drive motor, verifying rotor speed matches design values, with no abnormal noise or vibration during operation. Transmission belt tension shall be appropriate with regular tensioning maintenance.

Performance Testing and Protection

Run the system continuously for 2 hours. Test process air inlet and outlet dew point temperatures, confirming dehumidification effect meets design parameters. Check regeneration temperature stability, rotor operating status, fan currents, and other parameters—all within normal ranges.

The system is equipped with multiple protections: rotor stoppage protection, regeneration over-temperature protection, fan fault protection, and low airflow protection. Abnormal conditions trigger automatic shutdown and alarm to prevent equipment damage.

Rotor dehumidification systems can achieve extreme low-humidity environments, widely applied in lithium battery storage, precision electronic component warehousing, military munitions storage, and other scenarios with extremely high humidity requirements. This is the core optional function of high-end energy storage constant temperature and humidity containers.

13.5 Water Supply and Drainage Piping Connection and Testing

The water supply and drainage system is the foundational support for humidification and dehumidification functions. Although it is an auxiliary system, water leakage faults can cause serious economic losses—construction quality must be strictly controlled.

Water Supply Piping Construction

Humidification system water supply piping shall use food-grade PPR pipe or 304 stainless steel pipe—hygienic, non-toxic, and corrosion-resistant. Main pipe DN20, branch pipe DN15, meeting maximum inlet water flow requirements. Piping shall be horizontally level and vertically straight, fixed securely with pipe clamps at 1.2-1.5m spacing.

Before equipment water inlet, install a main service valve, Y-type strainer, and pressure reducing valve. The main valve is used to shut off the water source during maintenance. The Y-type strainer intercepts sediment and impurities to protect solenoid valves. When inlet water pressure exceeds 0.4MPa, install a pressure reducing valve to stabilize at 0.2-0.3MPa, protecting seals and diaphragms.

After piping connection is complete, perform a hydrostatic test at 0.6MPa, holding for 1 hour. Pressure drop not exceeding 0.05MPa with no joint leakage indicates a pass. After passing the test, flush the piping to discharge sand and debris, preventing equipment blockage.

Drainage Piping Construction

Condensate water, dehumidification water, and humidifier blowdown water shall each flow through branch pipes into the main drainage pipe for unified discharge outdoors. Drainage piping shall use UPVC pipe—corrosion-resistant, smooth interior walls, and resistant to scaling. Piping shall maintain a 3‰-5‰ slope throughout with reverse slopes strictly prohibited, relying on gravity self-flow drainage.

Drainage risers shall have a vent pipe extending upward to balance air pressure in the piping and ensure smooth drainage. The drainage outlet shall connect to the site drainage network, with a water seal pit or U-trap at the outlet to prevent sewer odors and insect backflow into the container. Outdoor drainage piping shall be insulated and freeze-protected, with electric heat tracing added in cold northern regions to prevent winter pipe freezing, cracking, and blockage.

After drainage piping installation, perform water flow and ball passage tests—drainage shall be smooth with no blockage or leakage. Clean the drainage outlet filter screen regularly to prevent debris blockage.

Leak Detection System Integration

Positioning-type leak detection cable shall be arranged in leak-prone areas such as the bottom of constant temperature and humidity containers, under air conditioning units, and at piping joints, interlocked with the control system. Upon leak detection, an audible and visual alarm is immediately issued, uploaded to the remote monitoring platform, while the main water inlet valve is simultaneously closed to prevent leak expansion.

Positioning-type leak detection can accurately locate the leak position with error ≤1m, facilitating rapid troubleshooting by maintenance personnel. All Guangzhou Lain constant temperature and humidity container series come standard with leak detection systems, providing comprehensive leak risk prevention and control from design and construction to monitoring.

For constant temperature and humidity containers where personnel operate and volatile materials are stored, the fresh air and purification system is a critical component ensuring internal air quality, maintaining indoor positive pressure, and protecting both personnel and material safety.

14.1 Fresh Air System Design Principles

The core function of the fresh air system is to supply fresh air, exhaust contaminated air, maintain indoor positive pressure, and prevent unfiltered outdoor air from infiltrating. The design must adhere to the following principles:

Proper Air Volume Matching: For occupied scenarios, calculate fresh air volume at 30 m³/(h·person); for unoccupied scenarios, calculate based on 0.5–1 air changes per hour and maintain indoor positive pressure of 5–10 Pa; for scenarios with hazardous gas emissions, calculate ventilation volume based on pollutant concentration to ensure concentrations comply with occupational health standards.

Efficient Energy Control: Fresh air is a major source of temperature and humidity load on the air conditioning system; excessive fresh air volume significantly increases energy consumption. Prioritize total heat exchange fresh air ventilators to recover temperature and humidity energy from exhaust air, with heat recovery efficiency ≥70%, substantially reducing fresh air load.

Multi-Stage Filtration: Fresh air must pass through multi-stage filtration before being supplied indoors, blocking outdoor dust, PM2.5, and pollutants to protect the internal environment and equipment.

Intelligent Adjustable Control: Fresh air volume can be adjusted based on usage requirements, automatically reducing fresh air or switching to internal circulation during unoccupied periods for energy-efficient operation. Configure CO₂ and VOC sensors to automatically adjust fresh air volume based on air quality.

Fire Protection Integration Compliance: The fresh air system must be interlocked with the fire alarm system, automatically closing fresh air dampers and stopping fresh air fans during a fire to prevent smoke spread and combustion support.

14.2 Total Heat Exchange Fresh Air Ventilator Installation

The total heat exchange fresh air ventilator is the preferred fresh air solution for constant temperature and humidity containers, minimizing energy consumption while ensuring ventilation.

Equipment Selection and Installation

Select the appropriate unit model based on required fresh air volume, with 10%–15% capacity margin reserved to compensate for airflow decay caused by increased filter resistance. The unit must achieve enthalpy efficiency ≥60%, airflow resistance ≤150 Pa, and noise ≤55 dB(A), meeting energy-saving and quiet operation requirements.

The unit is installed via suspension mounting in the container ceiling plenum or end equipment area, using 4 suspension rods with spring vibration isolation hooks to reduce vibration and noise transmission. The unit must be installed level with a tilt of no more than 1° to ensure proper condensate drainage. Reserve a maintenance clearance of no less than 400 mm around the unit for filter replacement and core maintenance.

Duct Connection and Insulation

The fresh air intake connects to the outdoors, equipped with a rain-proof louver and insect screen, with the opening angled downward to prevent rainwater ingress. The exhaust outlet connects to the outdoors, with the exhaust direction avoiding the intake, maintaining a separation of no less than 2 m to prevent exhaust short-circuiting and re-entrainment.

The supply air side connects to the air conditioning return air section or indoor supply air system; the return air side connects to indoor return air. Use canvas flexible connections between ducts and the unit, 150 mm in length, with appropriate tightness for vibration damping and noise reduction. Both fresh air and exhaust ducts must be wrapped with 20 mm thick rubber-plastic insulation foam to prevent condensation on duct walls and reduce thermal losses. Outdoor duct sections shall be coated with waterproof and anti-corrosion paint, with weatherproof sealant applied at joints to prevent rainwater ingress.

Filtration and Control

Both the fresh air intake side and indoor return air side shall be equipped with G4 grade primary filters, with F8 medium filters added in highly polluted areas. Filters shall be drawer-mounted for easy replacement. Differential pressure detection shall be provided before and after filters, alerting for filter replacement when resistance exceeds limits.

The fresh air ventilator connects to the main control system, supporting manual, timed, and automatic control. When a CO₂ sensor is configured, fresh air volume automatically adjusts based on indoor CO₂ concentration: reduce fresh air volume for energy saving when concentration is below 1000 ppm, and increase fresh air volume when above 1500 ppm. Interlocked with the fire protection system, the unit automatically shuts down and closes the fresh air damper upon fire alarm signal.

Performance Testing

After installation, perform performance testing: measure fresh air and exhaust air volumes with an anemometer to verify design values; measure indoor positive pressure with a differential pressure gauge, maintaining 5–10 Pa; verify unit heat recovery efficiency, operating power, and noise levels, all conforming to product standards and design requirements.

With the total heat exchange fresh air system, the containerized constant temperature and humidity system ensures internal air quality while effectively reducing air conditioning energy consumption, improving overall energy efficiency by more than 20%. It is the standard configuration for attended scenarios.

14.3 Air Purification System Installation

For special industry requirements in pharmaceutical, electronics, and chemical sectors, constant temperature and humidity containers can be customized with multi-stage air purification systems to meet cleanliness, deodorization, and sterilization requirements.

Three-Stage Filtration Purification System

Scenarios with high cleanliness requirements are equipped with a primary + medium + high-efficiency three-stage filtration system:

  • Primary Filtration (G4): Captures large dust particles, hair, and fibers, protecting downstream equipment and filters;
  • Medium Filtration (F8): Filters fine particulate matter and most microorganisms, protecting high-efficiency filters and extending their service life;
  • High-Efficiency Filtration (H13 HEPA): Filtration efficiency ≥99.97% for 0.3 μm particles, capable of removing bacteria, viruses, and ultra-fine dust, achieving Class 10,000 cleanliness.

High-efficiency filters are installed at supply air terminal outlets, with individual scan leak testing performed on each filter. A leak rate of ≤0.01% qualifies as acceptable. Filter frames are constructed of aluminum alloy, installed level, with evenly compressed sealing gaskets and no side leakage.

Gas Phase Purification System

For scenarios with odors, VOC, and corrosive gases, activated carbon chemical filtration modules are configured. Honeycomb columnar activated carbon is used, featuring large specific surface area and high adsorption capacity, effectively adsorbing gaseous pollutants such as toluene, formaldehyde, hydrogen sulfide, and odors.

Select specialized activated carbon formulations based on pollutant type: impregnated alkaline activated carbon for acid gases, impregnated acid activated carbon for alkaline gases, and coal-based granular activated carbon for general deodorization. Filter modules adopt drawer-type construction for convenient periodic replacement of activated carbon media.

Sterilization and Disinfection System

UV-C Sterilization: Install 254 nm wavelength UV-C germicidal lamps within the supply air duct to irradiate circulating air, destroying microorganism DNA structure with sterilization efficiency ≥99%. Equipped with timers for scheduled operation, avoiding direct human exposure. Lamp life is 8000 hours, with automatic replacement reminders upon expiration.

Photohydroionization Purification: Uses photocatalytic technology to generate hydroxyl radicals and negative ions, decomposing harmful gases, killing bacteria and viruses, while settling micro-dust. No secondary pollution, suitable for continuous purification in occupied scenarios.

Installation and Effectiveness Verification

Each purification module must be securely installed, tightly sealed, with no bypass air leakage. Module frames shall be constructed of galvanized steel sheet or 304 stainless steel for corrosion resistance. Provide access doors and quick-release clasps for convenient consumable replacement.

After installation, perform effectiveness testing: cleanliness testing uses a particle counter to measure 0.5 μm particle concentration, verifying compliance with the designed cleanliness class; TVOC concentration is tested by gas chromatography, conforming to standard requirements; total bacterial count is tested using the sedimentation method, conforming to hygiene standards.

The customized air purification system significantly expands the application scenarios of constant temperature and humidity containers. Guangzhou Lain can provide one-on-one dedicated purification solutions based on customer industry characteristics and pollutant types, meeting all special environmental requirements.

The electrical system is the power core of the constant temperature and humidity container. The reliability and safety of the power supply directly determine whether the entire system can operate stably. Power supply and distribution construction must strictly comply with GB 50303-2015 “Code for Acceptance of Quality of Construction of Building Electrical Engineering”, achieving standardized wiring, complete protection, and reliable grounding.

15.1 Power Distribution Cabinet Installation

Cabinet Selection and Configuration

The distribution cabinet uses an outdoor-type cold-rolled steel plate with plastic spray coating, with protection rating IP54, corrosion-resistant, dust-proof, and splash-proof. All internal components shall be from first-tier brands such as CHINT, Schneider, or ABB, with complete 3C certification and reliable quality.

The cabinet is configured with a main circuit breaker, branch circuit breakers, residual current circuit breakers, AC contactors, thermal relays, surge protectors, terminal blocks, and other components. The main switch provides overload and short-circuit protection. Each power circuit (compressor, fan, heater, humidifier, etc.) is independently controlled and protected with individual protective devices. The control circuit has a dedicated switch and fuse, separated from power circuits to prevent power faults from affecting control.

Internal component layout is rational, with power and low-voltage wiring separated at distances complying with safety codes. Circuit identification is clear, with circuit names and numbers labeled for convenient operation and maintenance. An electrical system diagram and circuit cross-reference table are affixed to the inside of the cabinet door.

Cabinet Installation Procedure

The distribution cabinet is installed on the inside of the box door or on the wall of the end equipment room, at a mounting height of 1.5 m from floor to cabinet center for convenient operation and observation. Secure with expansion bolts, firmly installed, with verticality deviation not exceeding 1.5‰. The cabinet is reliably grounded, with the grounding terminal having good continuity with the cabinet metal enclosure.

Cabinet incoming and outgoing cables use a bottom-in/bottom-out configuration, with rubber grommets installed at the bottom to prevent cable insulation damage. After cable installation, seal the grommets to prevent dust, insects, and rodents from entering the cabinet. Internal wiring is neat, with power and low-voltage wiring routed in separate channels, securely tied, with clear and complete wire numbers.

When multiple devices are jointly controlled, configure a main distribution cabinet and sub-distribution boxes with hierarchical power distribution. The main distribution cabinet is equipped with an energy meter, power factor meter, and voltage/current meters for real-time power consumption monitoring.

Component Wiring Requirements

Component wiring uses copper lug crimping, firmly crimped, with tinned contact surfaces to reduce contact resistance. Stranded copper wires are strictly prohibited from direct insertion into terminals; terminal lugs must be crimped before connection. Each terminal point accepts no more than 2 wires, and wires of different diameters shall not be connected to the same terminal point.

Secondary control wires use 0.75–1.5 mm² stranded copper flexible wire, clearly numbered with wire number sleeves oriented uniformly for easy tracing. Wiring is neatly arranged, bundled, and routed along internal wiring ducts. All connections are secure and pass pull testing without loosening.

After wiring completion, verify wire numbers against the drawings point by point to ensure correct connections. Use a multimeter to measure continuity and insulation of each circuit, confirming no short circuits or misconnections before energizing.

15.2 Power Cable Installation

Cable Selection Standards

All cables use national-standard copper-core flame-retardant cables. Power circuit conductor sizes are selected based on power ratings, ensuring current-carrying capacity meets rated current requirements with more than 20% margin. High-current circuits such as compressors and electric heaters require individual conductor size calculations to avoid overload and overheating.

Load Copper Core Wire Size
Below 3 kW 2.5 mm²
3–10 kW 4 mm²
10–20 kW 6–10 mm²
Above 20 kW 16–25 mm²

Control signal wires use shielded twisted pair cable; analog signal cables use shielded cable to prevent electromagnetic interference. Communication cables use Cat-5e or better network cable or fiber optic cable to ensure stable signal transmission.

Cable Installation Procedure

Cables are routed along metal cable trays or galvanized steel conduits, neatly arranged, straight and level. Cable trays and conduits are securely fastened with support hangers spaced per code requirements. Conduit bends are made with a conduit bender for cold bending, with bend radius not less than 6 times the conduit diameter, free of crimps, flattening, or cracks.

Cable routing avoids crossing where possible. Cables of different voltage levels and different circuits are routed separately, with a spacing of no less than 200 mm between power and low-voltage cables; where unavoidable, use metal partition plates for shielding. Appropriate slack is reserved at cable bends and ends for maintenance access.

When pulling cables through conduits, install protective bushings at conduit openings to prevent insulation damage. No more than 8 cables per conduit, with total cross-sectional area not exceeding 40% of the conduit interior area. Cables of different voltages and different circuits shall not be installed in the same conduit.

After cable installation, apply identification labels at both ends indicating circuit number, origin, and destination for future maintenance.

Wiring Safety Requirements

Cable routing avoids high-temperature components, rotating parts, and sharp edges; where unavoidable, install thermal insulation or protective sleeves. Cables in moving parts use high-flexibility drag chain cables with sufficient travel allowance to prevent pull-out and breakage.

Outdoor cables are routed through galvanized steel conduits with anti-corrosion treatment and waterproof sealing at joints. Direct-buried cables have a burial depth of no less than 0.7 m, with fine sand and red brick protection above and below, and warning signs along the route.

Splices in cables are strictly prohibited. Where splices are unavoidable, install junction boxes with proper insulation and waterproofing. High-voltage power cable splices use dedicated cold-press or heat-shrink connectors to ensure insulation and mechanical strength.

15.3 Grounding System Construction

The grounding system is the last line of defense for electrical safety. For constant temperature and humidity containers, working grounding, protective grounding, lightning protection grounding, and anti-static grounding are established jointly, forming an equipotential grounding system.

Ground Electrodes and Grounding Busbar

An artificial ground electrode is installed outdoors using 50×50×5 mm galvanized angle steel, 2.5 m in length, driven vertically into the ground, with the top 0.8 m below ground surface. Ground electrode spacing is no less than 5 m; the quantity is determined by grounding resistance requirements, with a minimum of 3 electrodes. Electrodes are interconnected with 40×4 mm galvanized flat steel welded into a closed grounding grid.

Welding uses lap welding with a lap length of 2 times the flat steel width, welded on three sides; for round steel, lap length is 6 times the diameter, welded on both sides. Weld slag is removed and asphalt anti-corrosion coating is applied. The grounding busbar is routed into the container and reliably connected to the main grounding terminal block.

Equipotential Bonding

All exposed conductive parts including the container metal shell, distribution cabinet enclosure, air conditioning unit enclosures, metal piping, metal cable trays, and equipment racks are reliably connected to the grounding terminal block via grounding wires, forming an equipotential body to prevent potential differences between different equipment.

Grounding wires use yellow-green dual-color dedicated grounding wire, with cross-sectional area no less than 1/2 of the phase conductor, and minimum 2.5 mm². Each equipment is individually connected with its own grounding wire; series grounding is prohibited. Grounding terminals use bolted connections with spring washers to prevent loosening, ensuring good contact.

Grounding Resistance Testing

After grounding system construction, measure grounding resistance with a ground resistance tester. Combined grounding resistance shall be no greater than 4 Ω; where low-voltage and communication systems are present, no greater than 1 Ω. If grounding resistance does not meet requirements, increase the number of ground electrodes or add ground resistance reducing agents until requirements are satisfied.

Test records are archived, and grounding resistance is re-measured annually before the rainy season to ensure reliable grounding.

Lightning and Surge Protection

Install Class I/II power surge protective devices (SPD) at the power incoming line to protect equipment from induced lightning strikes and switching overvoltages. Install signal surge protective devices on signal circuits and communication lines to protect automation and communication equipment.

Surge protectors are installed downstream of the incoming switch, with short and straight connection wires not exceeding 0.5 m in length to minimize lead inductance effects. SPD grounding is reliable with a grounding wire cross-section of no less than 4 mm². Periodically inspect the SPD status indicator window and replace promptly upon failure.

Energy storage constant temperature and humidity containers are often deployed in open outdoor areas with high lightning risk. A complete lightning protection and grounding system is an important guarantee for safe equipment operation. All outdoor products from Guangzhou Lain are designed and constructed to Class II lightning protection standards, comprehensively mitigating lightning risks.

15.4 Electrical System Testing and Inspection

After electrical installation is complete, comprehensive electrical testing must be performed before energizing and commissioning.

Insulation Resistance Testing

Use a 500V megohmmeter to measure insulation resistance of each power and control circuit: between phase conductors, phase-to-ground, and neutral-to-ground. Power circuit insulation resistance ≥0.5 MΩ and control circuit ≥1 MΩ qualify as acceptable.

Before testing, disconnect all electronic components, sensors, and controllers to prevent high voltage breakdown damage to low-voltage components. After testing, fully discharge to avoid electric shock. Under humid conditions, insulation resistance values may be appropriately lower, but shall not be below 0.25 MΩ; otherwise, investigate moisture points, dry, and retest.

Continuity and Phase Sequence Testing

Use the multimeter continuity mode to test each circuit’s continuity, verifying wire numbers, confirming correct wiring with no short circuits, open circuits, or misconnections. Test protective grounding continuity: all equipment enclosures show good continuity with grounding terminals, resistance ≤0.1 Ω.

For three-phase power circuits, measure phase sequence with a phase sequence indicator to ensure positive sequence, preventing reverse rotation damage to fans and compressors. If phase sequence is incorrect, swap any two phase conductors to correct.

Protection Device Verification

Verify circuit breaker and thermal relay settings match load rated current, with reliable overload and short-circuit protection operation. Test residual current circuit breakers using the test button, confirming tripping within 0.1 seconds at 30 mA leakage.

Simulate overload, short-circuit, and leakage faults to verify accurate protection device operation, correct selective coordination of protection levels, and no nuisance upstream tripping.

After all electrical tests pass, complete the electrical insulation test records, grounding resistance test records, and circuit verification records for inclusion in as-built documentation. Before energizing, re-inspect the site to confirm no personnel working, no tools left behind, and post warning signs before staged energization.

The intelligent control system is the “brain” of the constant temperature and humidity container, responsible for precise temperature and humidity control, equipment operation management, data acquisition and storage, abnormal alarms, and remote communication. The stability and precision of the control system directly determine the user experience and control effectiveness of the entire equipment.

16.1 Main Controller Installation

Controller Selection

The main controller uses an industrial-grade PLC (Programmable Logic Controller), with brands selected from Siemens, Mitsubishi, or Delta, providing stable operation and strong anti-interference capability suitable for industrial outdoor scenarios. The CPU module is configured with sufficient I/O points, reserving 15%–20% spare points for future functional expansion.

Analog modules use 12-bit or higher high-precision AD conversion to ensure accurate acquisition of analog signals such as temperature and humidity. Communication modules support RS485, Ethernet, 4G, and other communication methods, compatible with common protocols such as Modbus and MQTT for integration with third-party platforms.

Installation and Wiring

The controller is installed on dedicated mounting rails inside the electrical control cabinet, vertically mounted with tilt not exceeding 5°, at a height convenient for observation and operation. The controller maintains appropriate distance from power components, away from strong electromagnetic interference sources, with shielding partition plates installed where necessary.

The controller power supply circuit is equipped with a dedicated switching power supply providing stable DC24V output, with filtering and surge protection to ensure supply stability. An UPS (Uninterruptible Power Supply) is installed upstream of the power supply, providing more than 30 minutes of continuous power after mains failure, ensuring data is not lost and alarm information is transmitted normally.

Control cables use shielded cable with single-ended grounding of the shield layer to reduce electromagnetic interference. Analog signal wires are routed in dedicated channels, away from power cables, avoiding parallel routing; crossings are made at right angles. All connections are secure with terminal tightening torque meeting requirements to prevent poor contact causing signal fluctuation.

Program Download and Configuration

Download the completed control program to the PLC. The program includes temperature and humidity PID control logic, equipment start/stop logic, protection interlock logic, alarm logic, and data acquisition logic. The program is written in modular structure with clear organization for convenient future modification and maintenance.

Configure the controller IP address, communication parameters, and device addresses to ensure normal communication with the touch screen and remote modules. Set administrator passwords and operation permissions to prevent unauthorized parameter modification.

16.2 Temperature and Humidity Sensor Layout

Sensor Selection

Temperature and humidity sensors use Swiss-imported sensing elements, with temperature accuracy of ±0.1°C and humidity accuracy of ±1.5%RH, with measurement range covering full operating conditions of the equipment. Output signals are 4–20 mA or RS485, providing strong anti-interference capability and long transmission distance.

Sensor housings are made of ABS engineering plastic, moisture-proof and dust-proof, suitable for high-humidity environments. Certain points are configured with protective filter screens to prevent dust contamination of sensing elements affecting accuracy.

Sensor Point Layout Principles

Sensor placement follows the principle of “multi-point distribution, representing the true environment”:

Container Size Number of Test Points Placement
Standard 20-foot 4 points Both ends, center, return air outlet
40-foot 6–8 points Evenly distributed across different areas and heights
  • Reference measurement point at return air outlet, serving as the primary control feedback point;
  • Operating layer measurement points in work areas, reflecting temperature and humidity in actual usage areas;
  • Auxiliary measurement points in dead zones, near doors/windows, and near equipment to monitor local temperature and humidity deviations.

Sensors are installed at approximately 1.5 m height, representing the typical height for personnel operation and material storage. Sensors are positioned away from supply air outlets, return air outlets, doors/windows, and heat sources to avoid local airflow affecting measurement accuracy.

Installation and Calibration

Sensors are wall-mounted using expansion screws, securely installed with sensing probes facing downward to prevent water and dust accumulation. Signal wires are connected to controller analog modules. After wiring, configure range and calibration coefficients.

Before system commissioning, perform on-site comparison calibration of sensors using a standard temperature and humidity calibrator to correct systematic errors, ensuring accurate and reliable measurement values. Calibration records are archived, with annual periodic calibration to maintain measurement accuracy.

16.3 Human-Machine Interface Touch Screen Installation

Equipment Configuration

Use a 10-inch color industrial touch screen, resolution 1024×600, capacitive touch, smooth operation, dust-proof and waterproof. Installed on the inside of the box door or on the operation panel at a height of 1.4–1.6 m for convenient standing operation.

The touch screen interface is fully featured, including:

  • Real-time monitoring screen: Displays internal temperature/humidity, equipment operating status, operating time, and alarm information;
  • Parameter setting screen: Allows setting temperature/humidity setpoints, PID parameters, alarm thresholds, and scheduled on/off times;
  • Trend curve screen: Displays temperature/humidity historical curves, supporting query of historical data within 1 year;
  • Alarm record screen: Records all alarm information including time, type, and processing status;
  • Equipment status screen: Displays operating current, operating time, and accumulated running hours of each component;
  • Permission management screen: Hierarchical permission management — regular users can only view, administrators can modify parameters.

Installation and Communication

The touch screen is flush-mounted on the control cabinet panel with sealant applied around the perimeter for waterproofing and dust protection. Communication with the main controller is via Ethernet or RS485, providing fast communication speed and timely data refresh.

The interface operation logic is clear with simple hierarchy, enabling rapid operator proficiency. Configure screen saver and automatic screen lock, automatically locking after extended periods of inactivity to prevent accidental operation.

16.4 Remote Communication and Monitoring System

Communication Module Installation

Configure a 4G full-network communication module or Ethernet module to upload equipment data to the cloud platform for remote monitoring. The module is installed inside the electrical control cabinet, with antenna routed to the exterior of the container for good signal reception, avoiding metal shielding.

Use MQTT IoT protocol for stable data transmission with low data consumption. Support breakpoint continuation — automatically resend data after network interruption recovery, ensuring data integrity.

Cloud Monitoring Functions

Users can view equipment operating status anytime, anywhere through PC web pages and mobile apps, including:

  • Real-time temperature and humidity data and curves;
  • Equipment operating status and fault alarm information;
  • Historical data query and report export;
  • Remote modification of temperature/humidity setpoints and on/off control;
  • Centralized management of multiple devices with project overview;
  • Alarm notifications via SMS, WeChat, and APP push with multi-channel notification.

The cloud platform supports multi-level user permissions with encrypted data storage for data security. Supports integration with customer-owned SCADA systems and energy management platforms through standard protocol interfaces.

Remote monitoring functionality enables unattended operation of constant temperature and humidity containers, significantly reducing operation and maintenance costs. Guangzhou Lain provides free cloud platform access service and 1 year of data traffic, with low subsequent renewal costs and excellent cost-effectiveness.

16.5 Control Circuit Verification and Simulation Testing

After all control circuit installation is complete, verify each wire against the drawings one by one, confirming correct wiring, clear wire numbers, and no short or open circuits. Then perform de-energized simulation testing:

  • Input signal testing: Simulate temperature/humidity signals and digital signals, confirming accurate controller acquisition with values consistent with actual conditions;
  • Output action testing: Force outputs through the controller, verifying correct operation of contactors, relays, and valves, with corresponding equipment starting and stopping normally;
  • Interlock logic testing: Simulate fault conditions to verify protection interlock actions, such as electric heater prohibited when fan is stopped, humidifier stopped at high water level, compressor shutdown on over-temperature;
  • Alarm function testing: Simulate over-temperature, over-humidity, water leak, and fan fault alarms, confirming audible/visual alarm triggering and correct alarm information upload.

Energized integrated commissioning may proceed only after all simulation tests pass.

The constant temperature and humidity container integrates electrical, HVAC, energy storage, and other systems, storing high-value assets. A comprehensive safety protection system is an essential configuration ensuring personnel, equipment, and asset safety.

17.1 Fire Alarm and Suppression System

Fire Detection System

The container is equipped with photoelectric smoke detectors and heat detectors, multi-point arranged to cover the entire space. Smoke detector sensitivity complies with GB 4715 standard, with obscuration rate adjustable from 2%–10%; heat detectors use a combination rate-of-rise/fixed-temperature type, triggering alarms when temperature rise rate exceeds 5°C/min or temperature reaches 57°C.

Detectors are ceiling-mounted with spacing no greater than 6 m, distance from walls no greater than 3 m, avoiding supply air outlets and light fixtures. Detector bases are securely fastened with reliable wiring.

The fire alarm controller is independently powered with backup batteries providing ≥24 hours of standby power upon mains failure. Upon alarm, the audible/visual alarm device inside the container is triggered, alarm signals are uploaded to the remote platform, and actions are coordinated to close fresh air dampers, cut non-fire-fighting power, and activate the suppression system.

Fire Suppression System Configuration

Select the suppression system based on stored material type:

Heptafluoropropane (FM200) Gas Suppression System: Suitable for electrical equipment, batteries, and precision instruments. Clean and residue-free, high extinguishing efficiency, no damage to equipment. Available in cabinet type or piped type, with design extinguishing concentration of 8% and discharge time ≤10 seconds. Provides audible/visual pre-warning before discharge with 30-second delay for personnel evacuation.

Aerosol Suppression Device: Suitable for small spaces and unattended scenarios. Simple installation, no piping required, fast activation, high extinguishing efficiency.

Dry Powder Extinguishers: Configure 2 units of 4 kg ABC dry powder extinguishers inside the container, placed at easily accessible locations near the door as backup for initial fire suppression.

Suppression system installation is performed by qualified professional fire protection contractors, complying with GB 50370 “Code for Design of Gas Fire Extinguishing Systems”. After installation, conduct simulated discharge testing to verify accurate and reliable system operation.

17.2 Water Leak Detection System

System Composition and Principle

Use a locating-type water leak detection system consisting of a leak controller, locating detection cable, terminating end, and lead wires. The detection cable contains two sensing wires; upon exposure to water, resistance changes occur, and the controller calculates resistance values to precisely locate the leak position with positioning accuracy ≤1 m.

The controller is interlocked with the main control system. Upon water detection, it immediately triggers audible/visual alarms, uploads alarm information, and can coordinate closing of the main water supply valve to prevent leak expansion.

Detection Cable Layout

Detection cable is laid along the perimeter of the container floor, beneath air conditioners, at pipe joints, and below water supply/drainage pipes, covering all leak-prone areas. The detection cable is installed flat against the floor, secured with dedicated mounting clips spaced at 50 cm intervals. The cable avoids sharp objects to prevent damage.

Detection cable joints are waterproofed. The controller is installed in a dry, elevated location for convenient alarm status observation. After system installation, perform simulated leak testing by dripping water at different locations to verify alarm and positioning accuracy.

17.3 Access Control and Security System

Access Control System Configuration

The container is equipped with an electromagnetic access control system supporting multiple entry methods including password, card, fingerprint, and facial recognition, selectable based on requirements. The access controller stores entry records, allowing query of historical entry personnel and times for personnel access management.

Access control is interlocked with fire protection — doors automatically unlock upon fire alarm to facilitate personnel escape and rescue entry. The access control system features tamper alarm and forced-entry alarm functions, with abnormal conditions uploaded to the monitoring platform.

Video Surveillance (Optional)

Network HD cameras can be configured inside and outside the container, providing 24-hour recording with storage period ≥30 days. Cameras support night vision, motion detection, and remote viewing; users can view live footage in real time via mobile app.

Video surveillance is integrated with the alarm system — automatic snapshot recording upon alarm to preserve evidence. For remote-area unattended energy storage constant temperature and humidity containers, video surveillance significantly enhances security levels.

17.4 Emergency Lighting and Evacuation System

Emergency Lighting

The container is equipped with fire emergency lighting fixtures, battery-backed type, charging under normal conditions and automatically illuminating upon power failure, with ≥90 minutes of endurance. Fixtures are installed on the ceiling, above aisles, and at exits, with illumination meeting evacuation requirements.

Additionally configure safety exit indicators and evacuation direction indicators, automatically illuminating upon power failure to guide evacuation routes. Emergency lighting fixtures comply with GB 17945 standard with complete 3C certification.

Evacuation Devices

Escape doors are equipped with push-bar emergency exit devices — pressing the push bar from inside opens the door immediately without keys for rapid escape in emergencies. External access requires a key to maintain security. Escape door opening direction is outward, consistent with evacuation direction.

Evacuation routes remain clear with width ≥800 mm; stacking of debris blocking routes is strictly prohibited. Evacuation diagrams are posted inside the container indicating escape exits, extinguisher locations, and alarm button positions.

17.5 Other Safety Protection

Emergency Stop Button: Red mushroom-head emergency stop buttons are installed inside and outside the container. Pressing in an emergency cuts off the entire machine’s power supply, stopping all equipment operation. Emergency stop buttons are conspicuous, easy to operate, with clear identification.

Safety Warning Signs: Safety signs such as “DANGER — Electric Shock Risk,” “CAUTION — High Temperature,” “Authorized Personnel Only,” and “Fire Lane — Do Not Block” are posted inside and outside the container, complying with national safety color standards.

Insulation Protection: Insulation rubber matting with 5 mm thickness and 10 kV withstand voltage is laid in operating areas for electric shock protection. High-voltage parts are fitted with insulation protective covers to prevent accidental contact.

A comprehensive safety protection system is the foundation for reliable operation of industrial constant temperature and humidity containers. From design and production to installation, all Guangzhou Lain products implement safety concepts throughout the entire process, comprehensively safeguarding personnel and asset safety.

System commissioning is the final stage of constant temperature and humidity container installation and the core process for verifying equipment performance and ensuring subsequent stable operation. Commissioning must be conducted in an orderly manner based on completion of all sub-project installations and successful individual equipment trial operation. Comprehensive condition verification and preparation must be completed before commissioning, eliminating the risks of commissioning with defects or in haste.

18.1 Installation Completion Verification

Before commissioning, the project technical leader organizes construction team leaders and commissioning engineers to conduct overall installation completion verification, checking item by item against design drawings and construction specifications:

HVAC System Verification: Indoor and outdoor air conditioning units securely installed with levelness meeting standards; refrigerant piping connected with successful pressure holding and vacuum levels achieved; condensate drainage piping unobstructed with water seal traps filled; duct system installed with flexible damper adjustment and preliminary airflow balancing completed; humidification/dehumidification system piping correctly connected with unobstructed water supply and drainage.

Electrical System Verification: Distribution cabinet installed, component wiring secure, circuit identification clear; power and control cables installed with insulation resistance and grounding resistance tests passed; sensors and actuators correctly wired with complete wire numbers; surge protection and grounding systems completed and tested to standards.

Control System Verification: PLC main controller, touch screen, and communication modules installed with program downloaded; all I/O point wiring verified; remote monitoring system hardware connected with normal network signal.

Safety System Verification: Fire alarm, water leak detection, access control, and emergency devices installed in place; emergency stop buttons, emergency lighting, and evacuation devices functional; safety warning signs complete.

Site Environment Verification: Construction debris, tools, and miscellaneous items completely cleaned from the container; supply/return air paths unobstructed with maintenance access clear; on-site water and power supplies stable, meeting continuous operation requirements.

Problems found during verification are logged item by item, corrected within specified timeframes, and re-inspected. Only after all items pass and the commissioning commencement confirmation form is signed may the formal system commissioning phase begin. Energy storage constant temperature and humidity container commissioning involves multiple risks including high voltage, live electrical work, and refrigerant media. Guangzhou Lain strictly implements the “no qualifications, no commissioning” principle, eliminating commissioning safety hazards at the source.

18.2 Commissioning Instruments and Tools Preparation

Prepare all testing instruments and specialized tools before commissioning, ensuring measuring instruments are within calibration validity and accuracy meets testing requirements:

Category Instruments
Temperature/Humidity Testing High-precision temperature/humidity calibrator (±0.1°C/±1%RH), multi-point temperature/humidity recorder, handheld thermohygrometer
Airflow/Velocity Testing Thermal anemometer, air volume hood, micro differential pressure gauge
Electrical Testing Digital multimeter, clamp ammeter, megohmmeter, ground resistance tester, power analyzer
Refrigeration System Testing Refrigerant manifold gauge set, electronic refrigerant scale, vacuum pump, leak detector
Other Tools Sound level meter, vibration tester, stopwatch, two-way radios, logbook

Commissioning instruments are managed centrally by the commissioning engineer, with zero-point calibration performed before use to ensure accurate and reliable measurement data.

18.3 Commissioning Personnel and Plan Confirmation

Personnel Configuration: Establish a dedicated commissioning team led by a senior commissioning engineer, with one HVAC commissioning technician, one electrical commissioning technician, and one recorder, with clear division of duties. All commissioning personnel are certified for their positions and familiar with the principles and commissioning procedures of this equipment model.

Plan Preparation: Prepare a dedicated commissioning plan for the specific project configuration, defining commissioning steps, test items, acceptance criteria, operating points, safety precautions, and emergency response plans. The plan is executed after approval by the technical leader.

Technical Briefing: Conduct a plan briefing for all participants before commissioning, ensuring familiarity with commissioning procedures, parameter standards, risk points, and emergency response methods.

18.4 Initial Parameter Presets

Before energizing, preset basic operating parameters in the controller to avoid equipment shock from abnormal parameters during initial startup:

  • Temperature/Humidity Setpoints: Default temperature 25°C, relative humidity 50%RH, adjustable per user requirements;
  • PID Parameters: Preset empirical values with proportional band, integral time, and derivative time set for normal operating conditions, progressively optimized during commissioning;
  • Protection Thresholds: Set over-temperature, over-humidity, low-temperature, and low-humidity alarm thresholds, as well as compressor high/low pressure protection, fan overload protection, and electric heater over-temperature protection setpoints;
  • Sequencing Logic: Set compressor start/stop delays, fan startup sequence, electric heater interlock, and other protection logic to avoid frequent equipment cycling and false operation.

System integrated commissioning is the key process for verifying collaborative operation capabilities of all subsystems, progressing step by step following the principle of “local before overall, manual before automatic.”

19.1 Supply Air System Integrated Commissioning

  • Manually start the supply fan, return fan, and fresh air fan, confirming correct rotation direction, speed, and current, with smooth operation and no abnormal noise;
  • Adjust duct damper openings for system airflow balancing, achieving deviations between supply/return air outlet volumes and design values within ±10%;
  • Test indoor air distribution: uniform airflow velocity in the work area, without noticeable drafts or airflow dead zones;
  • Verify fan and damper interlock logic: fans cannot start with dampers closed; when a fan faults, the corresponding damper automatically closes;
  • Test fan speed adjustment functions: for variable frequency fans, test airflow and current changes at different frequencies, confirming smooth speed regulation without impact.

19.2 Refrigeration System Integrated Commissioning

  • After fans operate normally, switch to cooling mode and manually start the compressor, observing stable starting current without liquid slugging or abnormal noise;
  • Monitor system high/low pressures, discharge temperature, return gas temperature, and operating current, gradually stabilizing within normal operating ranges;
  • Observe even evaporator condensation, proper condenser heat dissipation, and no abnormal frost or condensation on piping;
  • Test compressor loading/unloading logic: for variable frequency compressors, test operating status at different frequencies with smooth regulation and minimal pressure fluctuation;
  • Verify refrigeration system protection functions: simulate high pressure, low pressure, overload, and discharge over-temperature faults, confirming accurate protection device operation and normal alarm information upload;
  • Test defrost logic (low-temperature conditions): simulate frost formation conditions and verify defrost cycle, defrost temperature, and defrost recovery time meet design requirements.

During refrigeration system commissioning, closely monitor compressor operating status. Prolonged operation outside the operating envelope is strictly prohibited. Industrial constant temperature and humidity containers operate continuously year-round; thorough refrigeration system break-in during commissioning significantly extends compressor service life.

19.3 Heating System Integrated Commissioning

  • Switch to heating mode: for heat pump units, verify proper four-way valve reversal with normal heating operating pressures and supply air temperatures;
  • For electric heating units, stage-start each group of electric heaters, testing each stage’s heating power and current, with supply air temperature rising steadily;
  • Verify heating and fan interlock logic: electric heaters cannot be enabled with fan stopped, and electric heaters are immediately cut off when the fan stops;
  • Test over-temperature protection: simulate over-temperature conditions, confirming accurate and reliable operation of over-temperature protectors and thermal fuses;
  • Test temperature regulation accuracy in heating mode: under PID control, temperature fluctuation is minimal, with automatic maintenance upon reaching setpoint.

19.4 Humidification/Dehumidification System Integrated Commissioning

Humidification Commissioning: Manually start the humidification system, observing normal steam generation, stable humidification output, no water leakage, and no abnormal noise; test output capacity at different humidification levels with response speed meeting design requirements; verify low-water protection and overcurrent protection functions.

Dehumidification Commissioning: Start dehumidification mode, observing normal evaporator condensation, smooth condensate drainage, and no water carryover at supply air outlets; test dehumidification capacity with indoor humidity declining smoothly without significant temperature fluctuation.

Constant Humidity Integration: Switch to automatic constant humidity mode, simulate humidity fluctuations, verify automatic humidification/dehumidification switching logic with smooth transitions without impact, and humidity progressively converging toward setpoint.

Test humidity protection thresholds: Over-humidity and low-humidity alarms trigger accurately with normal coordinated protection actions.

19.5 Fresh Air and Purification System Integrated Commissioning

  • Start the fresh air ventilator, testing fresh air and exhaust air volumes meeting design values, with indoor positive pressure maintained at 5–10 Pa;
  • Verify fresh air and air conditioning coordination: fresh air follows air conditioning start/stop, with automatic fresh air volume adjustment based on indoor air quality;
  • Test heat recovery function, calculating fresh air heat recovery efficiency to meet product rated values;
  • Test purification system operating status: filter differential pressure readings normal, sterilization and purification devices operating normally;
  • Verify fire protection interlock logic: upon fire alarm signal, the fresh air system automatically shuts down and fresh air dampers close.

19.6 Full System Automatic Mode Integrated Commissioning

After all subsystem manual commissioning passes, switch to full automatic operation mode for overall integrated operation testing:

  • Set target temperature and humidity values; the system automatically starts corresponding functional units. Observe temperature and humidity curves smoothly approaching setpoints without overshoot or oscillation;
  • Introduce artificial disturbance to temperature/humidity (e.g., opening doors, placing wet objects), testing system response speed and recovery capability, verifying control algorithm stability;
  • Operate continuously for 4 hours, observing collaborative operation of all systems without frequent cycling, logic conflicts, or false alarms;
  • Test mode switching: transitions between cooling/heating/humidification/dehumidification/automatic modes are smooth with stable transitions and no equipment shock.

After integrated commissioning, conduct formal performance testing and accuracy calibration to comprehensively verify whether all technical specifications of the constant temperature and humidity container meet design and contractual requirements.

20.1 Test Environment and Sensor Layout Requirements

Test Conditions: Empty-load condition, doors and vents closed, outdoor ambient temperature within normal equipment operating range, stable power supply voltage, free from strong electromagnetic interference and vibration effects.

Sensor Layout: Per GB/T 5170.2 standard, evenly distribute measurement points in the working area using a three-dimensional grid layout method:

Container Size Layout Total Points
20-foot 3 layers (upper/middle/lower) × 9 points per layer 27 points
40-foot 3 layers (upper/middle/lower) × 15 points per layer 45 points

Measurement points are located at distances of no less than 100 mm from container walls, at heights of 0.5 m, 1.5 m, and 2.0 m above the floor, avoiding areas directly blown by supply and return air outlets.

Test Instruments: All measurement points use metrologically calibrated high-precision temperature/humidity sensors, with sampling interval of 1 minute and automatic data recording.

20.2 Temperature Performance Testing

Temperature Stability Test: Set the standard temperature point to 25°C. After the system reaches stable operation, continuously record data for 2 hours and calculate temperature fluctuation, defined as 1/2 of the difference between the maximum and minimum values at the center point. Temperature fluctuation for standard equipment shall be ≤±0.5°C, and for high-precision equipment ≤±0.3°C.

Temperature Uniformity Test: Under stable conditions, the difference between the maximum and minimum temperature values across all measurement points at the same moment represents the temperature uniformity. Temperature uniformity for standard equipment shall be ≤±2°C, which can reach ≤±1.5°C after optimizing airflow distribution.

Temperature Deviation Test: The difference between the measured average temperature at each measurement point and the set temperature. A temperature deviation of ≤±1°C is considered qualified.

Heating/Cooling Rate Test: From ambient temperature to the maximum set temperature, and down to the minimum set temperature, calculate the average heating/cooling rate to verify compliance with design requirements.

Extreme Condition Test: Test the temperature control capability inside the container under extreme outdoor high-temperature and low-temperature environments, verifying that the set temperature can still be maintained under extreme conditions.

Batteries inside energy storage containers are extremely sensitive to temperature. Poor temperature uniformity can cause inconsistent degradation among battery modules, affecting the overall service life. Through CFD simulation optimization plus on-site precision commissioning, Guangzhou Lain’s energy storage constant temperature and humidity containers ensure the temperature difference in the battery area is controlled within ±1.5°C, significantly improving battery system consistency and service life.

20.3 Humidity Performance Testing

Humidity Stability Test: Set the standard humidity point to 50%RH and temperature to 25°C. After system stabilization, continuously record for 2 hours and calculate humidity fluctuation. Humidity fluctuation for standard equipment shall be ≤±2%RH, and for high-precision equipment ≤±1%RH.

Humidity Uniformity Test: The difference between the maximum and minimum relative humidity values across all measurement points at the same moment. Humidity uniformity for standard equipment shall be ≤±5%RH.

Humidity Deviation Test: The difference between the measured average humidity at each measurement point and the set humidity. A deviation of ≤±3%RH is considered qualified.

Humidification/Dehumidification Rate Test: From low humidity to the set high humidity, and from high humidity to the set low humidity, calculate the average humidification/dehumidification rate to verify response speed.

Low-Humidity Condition Test: Test the minimum achievable humidity to verify that deep dehumidification functions such as desiccant wheel dehumidification meet design specifications.

20.4 Energy Efficiency and Noise Testing

Energy Efficiency Test: After stable system operation, use a power analyzer to measure the total input power of the unit. Calculate the energy efficiency ratio EER/COP based on cooling/heating capacity, ensuring compliance with product nameplate values and the national Grade 1 energy efficiency standard.

Energy Consumption Test: Run continuously for 24 hours, record total power consumption, calculate daily average operating energy consumption, and evaluate operating costs.

Noise Test: Measure operating noise at four points — front, rear, left, and right — at a distance of 1m from the container body and a height of 1.5m. Take the average value. Noise for standard equipment shall be ≤60dB(A), and for noise-reduced equipment ≤55dB(A), complying with environmental requirements for residential and office areas.

Vibration Test: Measure vibration velocity at the unit base and container frame. Vibration intensity shall be ≤2.8mm/s, with no resonance phenomena.

20.5 PID Parameter Optimization and Tuning

During the performance testing process, optimize and tune PID control parameters based on temperature and humidity response curves. Using the critical proportionality method or decay curve method, gradually adjust the proportional coefficient, integral time, and derivative time to achieve the optimal control effect of “fast, stable, and accurate”:

  • Proportional coefficient: Ensure response speed while avoiding overshoot and oscillation;
  • Integral time: Eliminate static error while balancing adjustment speed and stability;
  • Derivative time: Predict change trends in advance and suppress fluctuations.

Optimize parameters separately for different operating conditions — such as high-temperature, low-temperature, high-humidity, and low-humidity conditions — storing a separate set of PID parameters for each. The system automatically switches between parameter sets to achieve precise control across the full operating range. After parameter optimization is completed, parameters are locked in the controller and cannot be modified arbitrarily by ordinary users, ensuring long-term stable system operation.

20.6 Final Control Precision Calibration

After all parameter optimization is completed, perform the final precision verification test. Run continuously for 8 hours, recording data every 10 minutes. Calculate all performance indicators. After all indicators meet the contracted technical specifications, sign the performance test report. If any indicator fails to meet specifications, analyze the cause, implement targeted rectification and optimization, and retest until qualified.

After performance testing is qualified, conduct a 72-hour uninterrupted continuous trial operation to comprehensively assess the long-term operational stability and reliability of the equipment. This is the final quality checkpoint before project delivery.

21.1 Trial Operation Preparation and Requirements

  • Before trial operation, conduct a comprehensive inspection of equipment status once again, confirm that all protection devices are engaged, parameter settings are correct, and there are no safety hazards on site;
  • Arrange commissioning personnel to work in two shifts for round-the-clock monitoring, tracking operating status throughout the process. Trial operation without supervision is strictly prohibited;
  • Develop a trial operation record sheet, specifying parameters to be recorded hourly: ambient temperature/humidity, internal temperature/humidity, operating current, high/low pressure readings, equipment operating status, alarm information, etc.;
  • Maintain normal operating conditions during the trial operation period. Do not make large-scale parameter adjustments or perform equipment maintenance, simulating real usage scenarios.

21.2 Full-Process Operating Parameter Monitoring

Record key parameters once per hour during the trial operation, with focus on:

Temperature Stability: Internal temperature continuously stable within ±1°C of the set value, with no significant fluctuation or drift;

Humidity Stability: Relative humidity stable within ±3%RH of the set value, with no abnormal rises or falls;

Compressor Status: Suction pressure, discharge pressure, operating current, and oil level normal; reasonable number of start/stop cycles; no frequent start-stop;

Fan Status: Operating current stable, no abnormal bearing temperature rise, no abnormal changes in noise or vibration;

Humidification/Dehumidification System: Normal operation, unobstructed water supply and drainage, no leakage or blockage;

Electrical System: No abnormal heating of components, normal cable temperatures, no circuit breaker trips.

Conduct a comprehensive inspection every 8 hours, checking for pipe joint leaks, condensation on insulation layers, loose connections, and unobstructed drainage.

21.3 Common Trial Operation Fault Handling

Common problems and treatment methods that may occur during trial operation:

Large Temperature Fluctuation: Check whether PID parameters are appropriate, whether supply air volume is uniform, whether door seals are tight, and whether there are air leaks;

Humidity Cannot Be Reduced: Check whether fresh air volume is excessive, whether door seals are leaking moisture, whether dehumidification capacity is matched, and whether condensate drainage is unobstructed;

Frequent Compressor Start-Stop: Check whether the temperature differential setting is too small, whether the system is low or overcharged with refrigerant, and whether pressure protection is triggering falsely;

Humidifier Fault Alarm: Check whether water intake is unobstructed, whether water quality is too hard causing scaling, whether electrodes have reached service life, and whether the water level sensor is malfunctioning;

False Alarms: Check whether sensors are damp or displaced, whether wiring is loose, and whether alarm threshold settings are reasonable.

Immediately analyze the cause of any fault. For minor faults that do not affect operation, keep records and handle them uniformly after the trial operation ends. For serious faults, stop the equipment immediately for troubleshooting, then restart the trial operation countdown after resolution.

21.4 Trial Operation Effectiveness Evaluation

After the 72-hour trial operation ends, compile all operating records and conduct a comprehensive evaluation:

  • Equipment operates continuously without major faults; protection devices act accurately; operating status is stable;
  • Temperature and humidity indicators meet specifications throughout the entire period; control precision meets requirements;
  • All systems work together normally without logic conflicts or abnormal start-stop;
  • No safety hazards such as water leakage, electrical leakage, or gas leakage;
  • Energy consumption, noise, vibration, and other indicators comply with design standards.

After all requirements are met, sign the 72-hour trial operation qualification record, and the equipment is ready for acceptance and delivery. If problems affecting long-term operation exist, rectify them and conduct another 72-hour trial operation until qualified.

Container-type constant temperature and humidity systems are mostly used in unattended outdoor energy storage sites, where long-term operational reliability is of paramount importance. Every unit shipped from Guangzhou Lain undergoes a 48-hour factory trial run, followed by a 72-hour loaded trial run after on-site installation. This dual verification ensures stable operation upon delivery and reduces later-stage operation and maintenance costs.

On the basis of completed local system commissioning, complete the integration and commissioning of the remote monitoring system to achieve cloud-based and intelligent equipment management.

22.1 Communication Link Commissioning

  • Check that 4G/Ethernet communication module power supply is normal, SIM card is activated with sufficient data, and network signal is good;
  • Configure communication parameters; complete handshake connection between the equipment end and cloud platform; ensure the data transmission link is unobstructed;
  • Test data upload frequency — default is data upload every 5 minutes; alarm information is uploaded in real-time; adjustable according to requirements;
  • Test breakpoint resume function — data is cached locally during network disconnection and automatically retransmitted when the network recovers, with no data loss.

22.2 Cloud Function Verification

Real-Time Monitoring: Computer and mobile APP can view temperature, humidity, equipment status, and operating parameters in real-time; data refreshes promptly and is consistent with local display;

Remote Control: Remote modification of temperature/humidity set points, power on/off, and operating mode switching; commands are issued accurately and executed properly;

Alarm Push: Simulate various fault alarms to verify that SMS, WeChat, and APP multi-channel alarms arrive in a timely manner; alarm information is complete and accurate;

Historical Data: Historical data curves can be queried, supporting daily, weekly, monthly, and yearly views; data reports can be exported in Excel format;

Equipment Management: Centralized management of multiple devices; clear project grouping; complete equipment information; comprehensive operational overview at a glance.

22.3 Third-Party Platform Integration (Optional)

If integration with the user’s own SCADA system, energy management platform, or smart campus platform is required, standard Modbus RTU/TCP and MQTT protocol interfaces are provided. Cooperate with users to complete data integration and functional commissioning, achieving data connectivity and unified management.

Engineering acceptance is the final stage of the constant temperature and humidity container installation project and represents a comprehensive assessment of the entire project’s design, construction, quality, and performance. Acceptance work is strictly carried out in accordance with national specifications and contract agreements.

23.1 Acceptance Basis and Standards

Acceptance work is based on the following documents and standards:

  • Purchase contract, technical agreement, and design drawings signed by both supply and demand parties;
  • GB 50243-2016 “Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works”;
  • GB 50303-2015 “Code for Acceptance of Construction Quality of Building Electrical Engineering”;
  • GB 50166-2019 “Standard for Construction and Acceptance of Fire Alarm System”;
  • JB/T 12076-2014 “Constant Temperature and Humidity Chambers”;
  • Product factory inspection standards and enterprise construction specifications.

23.2 Acceptance Organization and Participants

Acceptance is organized by Party A, presided over by the supervision unit (if any), with the construction unit (Guangzhou Lain) providing support. Personnel from the user and operations/maintenance parties are invited to participate. The acceptance team has one team leader responsible for overall coordination of acceptance work and signing of final conclusions.

The construction unit must prepare a complete set of acceptance documents in advance, organize the site, and cooperate with the acceptance team in conducting various inspections and tests.

23.3 Overall Acceptance Process

Acceptance Application: After completing all construction and commissioning and passing self-inspection, the construction unit submits a completion acceptance application report and a complete set of completion documents to Party A;

Document Review: The acceptance team first reviews the completeness, standardization, and accuracy of completion documents;

On-Site Inspection: After document review passes, conduct on-site appearance inspection, functional spot checks, and performance re-testing;

Problem Rectification: Issue a rectification notice for problems found during acceptance, specifying rectification content and deadlines;

Re-Inspection and Certification: After rectification is completed, apply for re-inspection. After all items pass, all parties sign the completion acceptance report and the equipment is formally handed over for use.

24.1 Container Body and Structural Engineering Acceptance

Appearance Inspection: Container surface coating is intact, free of scratches, rust, and deformation; doors and windows open/close flexibly with tight sealing; hardware fittings are complete and in good condition; identification labels and signs are complete and clear.

Structural Inspection: Container is securely installed with levelness meeting requirements; anchor bolts are complete and tightened; splicing parts are flat and firm with intact sealing and waterproofing; auxiliary structures such as ladders, guardrails, and platforms are secure and comply with safety specifications.

Foundation Inspection: Foundation is flat and intact, free of cracks and settlement; surrounding drainage is unobstructed with no standing water; apron and waterproofing are intact.

Dimension Verification: Verify internal and external dimensions of the container, door opening dimensions, and internal clear height, meeting design requirements.

24.2 HVAC System Acceptance

Equipment Acceptance: Indoor/outdoor air conditioning units, humidifiers, dehumidification wheels, and other equipment models, specifications, and quantities comply with contract requirements; installation is secure with correct orientation;

Piping Acceptance: Refrigerant pipes, water pipes, and condensate drain pipes are neatly arranged, securely fixed, with intact insulation and clear labeling; valves open/close flexibly with no leakage;

Air System Acceptance: Air ducts are manufactured and installed to specification with good sealing and intact insulation; air outlets are installed flush and neatly arranged with flexible airflow adjustment;

Functional Acceptance: Cooling, heating, humidification, and dehumidification modes operate normally with smooth switching; air volume and velocity meet design requirements; airflow distribution is uniform with no obvious dead zones.

24.3 Electrical and Control System Acceptance

Power Distribution System: Distribution box is installed to specification; component brands and specifications comply with contract requirements; wiring is neat with clear labeling and secure connections; insulation resistance and grounding resistance tests pass; protection devices are correctly set and operate reliably.

Control System: Controller, touch screen, and sensor models and specifications meet requirements; interface functions are complete with smooth operation; temperature/humidity display is accurate; control logic is correct; all protection and interlock functions are effective.

Remote Monitoring: Remote monitoring functions operate normally with stable data upload; alarm push is timely and accurate; historical data is complete and queryable.

Document Verification: Electrical schematic diagrams and wiring diagrams match actual site conditions; component certificates of conformity and 3C certification documents are complete.

24.4 Safety Protection System Acceptance

Fire Protection System: Smoke and heat detectors operate normally with accurate alarms; audible and visual alarm devices are fully functional; fire suppression system configuration meets requirements and is in normal standby status; fire linkage logic is correct.

Water Leakage Detection: Water leakage detection system is responsive with accurate positioning; alarm and linkage functions operate normally.

Access Control and Security: Access control system operates normally with complete door opening records; fire linkage unlock function is effective; video surveillance images are clear with normal storage.

Emergency Systems: Emergency lighting and evacuation signs automatically illuminate upon power failure with battery life meeting standards; emergency escape door locks function normally; emergency stop buttons operate reliably.

25.1 Comprehensive Performance Spot Testing

Based on the performance indicators agreed in the technical agreement, the acceptance team conducts on-site spot testing of key indicators:

  • Spot testing of temperature/humidity control precision, uniformity, and fluctuation;
  • Spot testing of cooling capacity, heating capacity, humidification capacity, and dehumidification capacity;
  • Spot testing of noise, vibration, and energy consumption;
  • Verification of operational stability under extreme conditions.

If spot test results deviate from the commissioning report within the allowable range, the item is considered qualified. If deviations are excessive, comprehensive re-testing is required.

25.2 Completion Document Handover

After acceptance passes, the construction unit hands over a complete set of completion documents to Party A. Two copies are prepared — one for Party A’s archive and one for the operations/maintenance department. The handover document list includes:

  • Project completion report and completion acceptance certificate;
  • Product factory certificate of conformity and factory inspection report;
  • Installation and commissioning instructions, operation and maintenance manuals;
  • Completion drawings: container structure drawings, HVAC system drawings, electrical schematic diagrams, wiring diagrams, automation control schematic diagrams, and general layout drawings;
  • Certificates of conformity, instruction manuals, warranty cards, and test reports for major components;
  • Construction records: hidden project acceptance records, pressure test records, insulation test records, and grounding test records;
  • Commissioning records: single-unit test run records, system integrated commissioning records, performance test reports, and 72-hour trial operation records;
  • Spare parts list and special tools list;
  • After-sales service commitment letter and warranty card.

All documents are bound into volumes with clear tables of contents for easy reference. Electronic versions of documents are simultaneously handed over, including editable drawings, electronic manuals, monitoring software installation packages, etc.

25.3 Spare Parts and Tools Handover

Hand over spare parts and special tools according to contract agreements. Both parties verify items one by one against the list and sign for confirmation:

  • Consumable spare parts: Air filters, humidification cylinders, fuse links, sealing strips, sensor protective covers, etc.;
  • Special tools: Refrigerant gauge manifolds, hex key sets, special wrenches, leak detection tools, etc.;
  • Consumable samples: Insulation cotton, sealant, cable ties, and other commonly used consumable samples.

Handed-over spare parts are properly stored for later replacement during operation and maintenance.

During the delivery phase, provide systematic operation and maintenance training for Party A’s operations personnel to ensure users can independently, correctly, and safely use and manage the equipment.

26.1 Training Targets and Objectives

Training targets are Party A’s equipment management personnel and operations/maintenance operators, with no limit on participant numbers. Training objectives:

  • Understand the working principles, system composition, and performance characteristics of constant temperature and humidity containers;
  • Master daily power on/off operations, parameter setting, mode switching, and other basic operations;
  • Master daily inspection contents, periodic maintenance methods, and precautions;
  • Be able to identify common faults and master troubleshooting and handling methods for simple faults;
  • Be familiar with safety operating procedures and emergency response processes.

26.2 Theoretical Training Content

Product Overview: Structural composition, working principles, technical parameters, and application scenarios of constant temperature and humidity containers;

System Principles: Working principles of the refrigeration system, heating system, humidification system, dehumidification system, control system, and safety system;

Operating Procedures: Power on/off procedures, parameter setting methods, operating mode switching, and daily inspection key points;

Maintenance: Content and cycles of daily maintenance, weekly maintenance, monthly maintenance, quarterly maintenance, and annual maintenance;

Safety Knowledge: Electrical safety, refrigeration safety, operational safety precautions, and emergency handling methods;

Common Faults: Common fault phenomena, cause analysis, simple handling methods, and repair request procedures.

26.3 On-Site Practical Training

Conduct hands-on practical teaching at the equipment site. Each trainee independently performs the following operations:

  • Power on/off operations, manual/automatic mode switching;
  • Temperature/humidity parameter setting, PID parameter viewing, alarm threshold viewing;
  • Historical data query and alarm record viewing;
  • Air filter cleaning and replacement, humidification cylinder disassembly and cleaning;
  • Daily inspection operations and key inspection points for each component;
  • Common fault simulation and reset operations;
  • Emergency stop button use and emergency shutdown procedures;
  • Remote monitoring platform operation and mobile APP usage.

26.4 Training Assessment and Q&A

After training, conduct simple theoretical and practical assessments to verify training effectiveness. Address questions raised by trainees one by one until all trainees can operate independently. Issue training certificates and training materials for future reference.

Guangzhou Lain provides lifetime free technical consultation services. Free retraining can be provided when operations personnel change, ensuring the equipment always has qualified personnel managing it. As a professional constant temperature and humidity container manufacturer, we deliver not only equipment but also complete usage and maintenance capabilities.

Correct daily operation and maintenance are key to ensuring long-term stable operation of constant temperature and humidity containers, extending service life, and reducing failure rates. Establishing a standardized operation and maintenance management system and conducting regular inspection and maintenance can increase equipment fault-free operating time by more than 30%.

27.1 Daily Inspection Content

Daily routine inspection is conducted once per day by the duty personnel, focusing on the following items and filling in the inspection record:

Operating Status Check: View temperature and humidity displayed on the touch screen to confirm they are within the set range without significant fluctuation; check equipment operating status indicators — compressor, fans, humidification, etc. operate normally with no fault alarms.

Appearance and Environment Check: Check the container body for deformation and rust; confirm doors and windows are closed tightly; check for debris accumulation around the container and whether ventilation and heat dissipation channels are unobstructed; check for obstructions around the outdoor unit and whether heat dissipation is good.

Sound and Vibration Check: Listen for smooth equipment operation sounds, checking for abnormal noises, friction sounds, and impact sounds; touch the container frame to feel whether vibration is normal and not abnormally increased.

Drainage Check: Check whether condensate drainage is unobstructed and whether the drain outlet is blocked; check the ground for standing water or signs of leakage.

Alarm Check: Check for alarm information, whether audible and visual alarms are normal, and whether fault indicator lights are illuminated.

Record Keeping: Record current temperature/humidity, voltage, operating mode, inspection time, and abnormal conditions, then sign for confirmation.

27.2 Weekly Inspection Content

Perform a deeper inspection once per week, adding the following items based on daily inspection:

Air Filter Check: Check the dust accumulation on the return air filter mesh surface; clean promptly when dust accumulation is significant; check the fresh air filter status.

Electrical Check: Check the distribution box for unusual odors and heating; check cables for aging and loosening; check indicator lights and instrument displays for normal operation.

Piping Check: Check refrigerant pipes and water pipes for leakage, abnormal frosting, and condensation; check insulation for damage or shedding.

Humidification System Check: Check whether the water level in the humidification cylinder is normal and whether scaling is present; check whether the water intake filter is blocked.

Safety Equipment Check: Check whether emergency lighting, emergency stop buttons, fire extinguishers, and escape locks are intact and effective.

27.3 Operation Management Regulations

  • Designate dedicated personnel responsible for equipment management; unauthorized personnel shall not arbitrarily operate the equipment or modify parameters;
  • Minimize the frequency and duration of door opening; open doors quickly when placing or retrieving materials to avoid large temperature/humidity fluctuations and increased energy consumption;
  • Do not arbitrarily modify equipment, add loads, or block air outlets; do not store flammable, explosive, or strongly corrosive items inside the container;
  • Check and handle alarms promptly when they occur; contact the manufacturer’s technical support promptly if issues cannot be resolved; strictly prohibit forced operation of faulty equipment;
  • Establish an equipment operation ledger, recording operating hours, fault conditions, maintenance contents, and consumable replacement times, enabling full lifecycle traceability;
  • During long-term shutdown, drain water from the humidification cylinder and piping, turn off water and electricity, implement dust and moisture protection, and periodically energize for dehumidification.

28.1 Monthly Maintenance

Comprehensive maintenance is performed once per month by professional operations/maintenance personnel:

Air System Maintenance: Clean the primary air filter and dry before reinstalling; check fan belt tension and adjust as needed; tighten fan bolts and add grease to bearings.

Water System Maintenance: Clean the Y-type water intake filter; check the humidification cylinder for scaling — clean and descale for light scaling; clear the condensate drain pipe and clean debris from the drain pan.

Electrical Maintenance: Tighten all electrical wiring terminals to eliminate loose-connection heating hazards; clean dust inside the distribution box and check components for aging; test grounding resistance and check surge protector status.

Cleaning Maintenance: Clean the interior and exterior walls of the container, air outlets, and evaporator surface dust; clear debris around the container to ensure ventilation and heat dissipation.

28.2 Quarterly Maintenance

Deep maintenance is performed once per quarter:

Heat Exchanger Cleaning: Use compressed air or clean water to flush dust from condenser and evaporator fins to maintain heat exchange efficiency; straighten any bent fins.

Piping Inspection: Comprehensively check refrigerant piping for minor leaks using a leak detector at key joints; check insulation integrity and repair any damaged areas.

Control System Maintenance: Calibrate temperature/humidity sensors and correct deviations; back up controller programs and parameters; check communication module signals and clear data caches.

Safety System Testing: Test smoke alarms, water leakage detection, access control, and emergency lighting functions; check fire extinguisher pressure and expiration dates.

28.3 Annual Maintenance

Comprehensive annual maintenance is performed once per year. It is recommended to contact the manufacturer’s professional engineers for on-site service:

Refrigeration System Deep Maintenance: Check refrigerant pressure and purity — replenish if low, replace if deteriorated; check compressor oil level and quality, replacing refrigeration oil if necessary; clean the dryer filter and replace vulnerable valve components.

Fan Motor Maintenance: Disassemble fan motors, clean bearings, and replace grease; test motor insulation and check winding condition; replace aged belts and seals.

Humidification/Dehumidification System Maintenance: Replace humidification cylinders and electrode rods; clean the dehumidification wheel and check seals; replace aged piping and solenoid valve diaphragms.

Electrical System Comprehensive Testing: Comprehensively test the performance of all electrical components and replace aged parts; test the operational reliability of all protection devices; calibrate all instruments and sensors.

Container Structure Maintenance: Check the container’s anti-corrosion coating and touch up any chipped paint; check door seal elasticity and replace hardened or aged seals; tighten all structural bolts.

Performance Comprehensive Re-Testing: After maintenance is completed, conduct comprehensive performance testing, calibrate control precision, and restore the equipment to factory performance condition.

Industrial constant temperature and humidity containers operate outdoors for long periods. Regular professional maintenance can effectively slow aging, extending equipment service life from 10 years to more than 15 years, with lower full-lifecycle costs.

29.1 Air Filters

  • Replacement Cycle: Primary filters — clean every 1–2 months, replace every 6–12 months; medium-efficiency filters — replace every 3–6 months; high-efficiency filters — replace every 1–2 years, or when resistance reaches 2 times the initial resistance;
  • Replacement Method: Open the filter frame latch, remove the old filter media, install a new filter media of the same specification, pay attention to airflow direction, and secure the latch;
  • Precautions: Avoid secondary dust dispersion during replacement; reset the differential pressure counter after replacement.

29.2 Humidification Cylinders and Electrodes

  • Replacement Cycle: 3–6 months under normal tap water quality; 6–12 months under softened water quality;
  • Replacement Method: Close the water intake valve and cut off power, drain accumulated water from the cylinder, disconnect wiring and release mounting clips, remove the old cylinder, install the new cylinder, reconnect wiring, and open the water intake valve;
  • Precautions: After replacement, purge air once, check for leaks, and confirm normal water level.

29.3 Sealing Strips

  • Replacement Cycle: Door seal strips — replace every 3–5 years, or promptly when elasticity decreases, cracking occurs, or air leakage is detected;
  • Replacement Method: Peel off the old strip, clean the channel, embed the new strip into the channel, make 45° miter joints at corners, and apply a small amount of sealant for fixing;
  • Precautions: After replacement, check sealing performance — no light-transmitting gaps after closing.

29.4 Temperature and Humidity Sensors

  • Replacement Cycle: 5–8 years under normal use; calibrate once per year; replace in advance if deviation exceeds limits;
  • Replacement Method: Remove the old sensor, connect the new sensor wiring, secure installation, and re-calibrate the zero point in the controller;
  • Precautions: After replacement, precision comparison calibration is required; direct replacement without calibration is not permitted.

30.1 Temperature-Related Faults

Fault Phenomenon Possible Causes Handling Methods
Internal temperature cannot be lowered 1. Insufficient refrigeration capacity, low refrigerant 2. Condenser dusty, poor heat dissipation 3. Compressor fault, not starting 4. Door seal leaking or frequent door opening 5. Excessive internal heat load 1. Leak check and recharge refrigerant 2. Clean condenser fins 3. Check compressor power supply and protection 4. Repair door seal, reduce door opening 5. Calculate load, add unit capacity if necessary
Internal temperature cannot be raised 1. Electric heater damaged or contactor fault 2. Heat pump four-way valve reversing fault 3. Temperature sensor deviation 4. Excessive fresh air volume 1. Replace heater or contactor 2. Repair four-way valve coil and valve body 3. Calibrate or replace sensor 4. Reduce fresh air damper opening
Large temperature fluctuation 1. Inappropriate PID parameters 2. Uneven supply air volume 3. Frequent compressor start-stop 4. Door seal air leakage 1. Re-tune PID parameters 2. Adjust air outlet balance 3. Check start-stop differential and refrigerant charge 4. Repair or replace door seal

30.2 Humidity-Related Faults

Fault Phenomenon Possible Causes Handling Methods
Humidity cannot be raised 1. Humidifier not working, water intake blocked 2. Severe scaling in humidification cylinder 3. Excessive fresh air volume removing moisture 4. Temperature too high pulling humidity down 1. Clean water intake filter, check solenoid valve 2. Clean or replace humidification cylinder 3. Reduce fresh air volume 4. Stabilize temperature first, then adjust humidity
Humidity cannot be lowered 1. Dehumidification system fault, compressor not cooling 2. Fresh air humidity too high 3. Door seal leaking moisture, internal moisture source 4. Poor drainage, evaporator carrying water 1. Repair refrigeration dehumidification system 2. Enable fresh air pre-dehumidification 3. Repair door seal, remove moisture sources 4. Clear drainage, check baffle plate
Abnormal humidity display 1. Humidity sensor damp or dusty 2. Sensor wiring loose 3. Controller analog channel fault 1. Clean or replace sensor 2. Tighten wiring terminals 3. Repair controller module

30.3 Equipment Start-Stop Related Faults

Fault Phenomenon Possible Causes Handling Methods
Unit cannot be powered on 1. External power supply failure 2. Main switch tripped or burnt out 3. Emergency stop button pressed 4. Residual current device tripped 1. Check upstream power supply 2. Close or replace switch 3. Reset emergency stop button 4. Investigate leakage point, reset RCD
Compressor does not start 1. Temperature has not reached start condition 2. High/low pressure protection tripped 3. Contactor or thermal relay fault 4. Compressor motor burnt out 1. Check set temperature 2. Investigate abnormal pressure cause, reset protection 3. Replace contactor or thermal relay 4. Repair or replace compressor
Fan does not rotate 1. Fan switch not turned on 2. Fan capacitor burnt out 3. Motor winding burnt out 4. Belt broken or detached 1. Turn on fan switch 2. Replace start capacitor 3. Repair or replace motor 4. Replace or reinstall belt

30.4 Alarm-Related Faults

Over-Temperature Alarm: Check whether refrigeration is normal, whether the load is excessive, whether the set value is reasonable, and whether the sensor is malfunctioning;

Water Leakage Alarm: Immediately check the leak location, close the water intake valve, investigate the leak point, handle and dry the area, then reset the alarm;

Smoke Alarm: Immediately stop the equipment and inspect the site to confirm whether there is an actual fire. If it is a false alarm, reset after confirming; clean the detector if dusty;

Fan Fault Alarm: Check whether the fan has tripped or burnt out, whether the belt is broken, and whether the feedback signal is normal;

Filter Blockage Alarm: Clean or replace the air filter, then reset the differential pressure switch.

When troubleshooting, always comply with safety regulations: cut off power before disassembly and repair; discharge high-voltage components before operation; refrigerant systems must be handled by certified refrigeration technicians. For faults that cannot be diagnosed or handled, promptly contact Guangzhou Lain technical support hotline +86 13538869979 for professional engineer guidance or on-site service.

31.1 Summer High-Temperature Season Maintenance

Summer ambient temperatures are high and the equipment operates under heavy load. Focus on ensuring heat dissipation and cooling stability:

  • Clean the outdoor unit condenser in advance to ensure heat dissipation efficiency;
  • Check the compressor high-pressure protection setting to ensure it does not frequently trip on high pressure in high temperatures;
  • Check that condenser fans operate normally with unobstructed exhaust;
  • Increase inspection frequency, paying attention to discharge temperature and operating current;
  • Provide sun protection for the container; install a sunshade canopy if necessary to reduce solar radiant heat.

31.2 Winter Low-Temperature Season Maintenance

In low-temperature winter environments, focus on freeze protection and heating assurance:

  • Install electric heat tracing and insulation on outdoor water pipes and condensate drain pipes to prevent freezing and cracking;
  • Check that low-temperature heating kits and defrost functions operate normally;
  • Drain all pipe water during long-term shutdown to prevent equipment freeze damage;
  • Check door seal tightness to reduce cold air infiltration and lower heating energy consumption;
  • Check batteries and UPS for low-temperature performance to ensure reliable backup power.

31.3 Plum Rain Season Maintenance

During the plum rain season with high humidity, focus on dehumidification and condensation prevention:

  • Check that the dehumidification system operates normally with unobstructed drainage;
  • Check the container insulation layer for localized condensation;
  • Check the electrical cabinet for moisture; turn on the cabinet heater;
  • Increase internal dehumidification operating time to prevent internal materials from becoming damp and moldy;
  • Check metal components for rust and apply touch-up paint for corrosion protection.

Energy storage containers are deployed across the country, and maintenance priorities differ by climate region. Guangzhou Lain can customize exclusive operation and maintenance plans based on the project location’s climate characteristics, ensuring stable equipment operation throughout the year.

Constant temperature and humidity containers involve multiple risks including electrical, refrigeration, and pressure vessel hazards. Operation and maintenance must strictly comply with safety regulations to prevent safety accidents.

32.1 Personnel Qualification Requirements

  • Equipment operators and daily inspection personnel must undergo specialized training and pass assessments before being permitted to work;
  • Electrical repairs must be performed by certified electricians, strictly implementing the procedures of power isolation, voltage testing, tagging, and locking;
  • Refrigeration system repairs must be performed by certified refrigeration technicians familiar with refrigerant characteristics and safety protection;
  • Work at heights must be performed by certified height-work personnel wearing safety harnesses with proper protection;
  • Hot work must be conducted with a hot work permit, clearing surrounding combustibles, equipping fire extinguishing equipment, and under dedicated supervision.

32.2 General Operating Safety Rules

  • Strictly follow the operating manual procedures; violations of work discipline and unauthorized operations are prohibited;
  • Before starting, confirm that no personnel or debris are inside the equipment and that all safety protection devices are intact;
  • Do not remove protective covers during equipment operation; do not reach hands into fan or moving parts areas;
  • Do not operate electrical switches and equipment with wet hands to prevent electric shock;
  • When leaving the equipment, confirm normal operation and close the container door properly;
  • Children and unauthorized personnel must not approach or operate the equipment.

32.3 Repair Safety Regulations

  • Equipment repair must be performed with power off and equipment stopped, with a “Under Repair — Do Not Close Circuit Breaker” warning sign posted and dedicated supervision;
  • Before disassembly, confirm that capacitors have been discharged and pipes have no pressure to prevent electric shock and refrigerant spray;
  • Use qualified tools; using defective or non-standard tools is prohibited;
  • Repairs in enclosed spaces require adequate ventilation, at least two persons working together, with external supervision;
  • After repair, count tools to prevent leaving them inside the equipment and causing faults;
  • Before test operation after repair, conduct a comprehensive inspection and confirm no abnormalities before energizing.

33.1 Electrical Safety

  • All electrical equipment metal housings must be reliably grounded with periodic grounding resistance testing;
  • Unauthorized wiring, overload use, and replacing fuses with copper wire are strictly prohibited;
  • No debris shall be stored in the distribution box; keep it clean and dry with the cabinet door closed and locked;
  • In case of electrical fire, immediately cut off the power supply and use dry powder or gas fire extinguishers; never use water;
  • If cable heating, insulation damage, or unusual odors are found, stop the equipment immediately, cut off power, and investigate.

33.2 Refrigeration System Safety

  • Refrigerant cylinders shall be stored upright, away from fire and heat sources, protected from direct sunlight, and never struck or impacted;
  • Wear protective goggles and gloves when charging refrigerant to prevent skin contact and frostbite;
  • Never discharge large amounts of refrigerant in enclosed spaces to prevent asphyxiation; maintain good ventilation;
  • Never disassemble pipes or components while the refrigeration system is under pressure; depressurize before operation;
  • Never close the discharge valve while the compressor is running to prevent overpressure pipe rupture.

33.3 Fire Safety

  • Flammable and explosive items are strictly prohibited inside the container; open flame work is strictly prohibited;
  • Regularly inspect fire equipment; replace expired items promptly;
  • Keep fire escape routes clear; never block escape doors and passageways;
  • Regularly test the fire alarm system to ensure normal function;
  • All personnel must be familiar with fire extinguisher usage and escape routes.

34.1 Power Outage Emergency Plan

After a sudden power outage, the equipment automatically stops. Check whether the UPS is supplying power to the control system and save data; close the main power switch to prevent surge damage when power is restored; no special handling is needed for short outages — restart the equipment according to procedures after power returns. For extended outages, if stored items are sensitive to temperature and humidity, take temporary measures such as transferring materials or starting the backup generator. Record the outage time and cause. After power returns, check equipment status and start up gradually after confirming normal operation.

34.2 Water Leakage Emergency Plan

Upon discovering a leak or receiving a water leakage alarm, immediately close the main water intake valve and cut off power to the humidification system. Locate the leak point, use containers to catch water, and clean up floor water to prevent damage to equipment and materials. Determine the cause of the leak — pipe rupture, drain blockage, humidifier overflow, etc. — and handle accordingly. For severe leaks, cut off the main power supply to prevent short circuits and electric shock. After handling, dry the affected areas, ventilate, check electrical insulation, and resume operation after confirming safety.

34.3 Fire Emergency Plan

Upon discovering a fire, immediately press the emergency stop button, cut off the main power supply, and call the fire department at 119. For incipient fires, use fire extinguishers to fight the fire. When the gas fire suppression system activates, personnel must evacuate immediately to prevent asphyxiation. Personnel should evacuate orderly through the nearest escape door, count heads, and never risk lives for property. Cooperate with fire rescue personnel and inform them of the types of equipment and stored items and their hazardous characteristics. After the fire is extinguished, conduct a comprehensive inspection. Only after confirming no re-ignition risks and completing full equipment repair may operations resume.

34.4 Personnel Injury Emergency

Electric Shock First Aid: Immediately cut off the power supply or use insulating objects to separate the victim from the power source; never pull with bare hands. If the victim is unconscious, immediately perform CPR and call 120 for medical transport.

Frostbite First Aid: If refrigerant contacts skin causing frostbite, immediately rinse with large amounts of warm water at approximately 40°C; never rub the area or use high-temperature baking; seek medical attention for severe cases.

Mechanical Injury: Stop the equipment immediately, stop bleeding and bandage wounds; send seriously injured persons to medical facilities promptly to prevent infection.

All emergency procedures shall be posted in prominent locations at the equipment site. Conduct regular emergency drills to ensure relevant personnel are proficient. Energy storage constant temperature and humidity containers are mostly deployed in remote outdoor sites; comprehensive emergency plans can minimize losses during unexpected situations.

Guangzhou Lain Intelligent System Development Co., Ltd., as a professional energy storage container manufacturer, has deep experience in the constant temperature and humidity container field and possesses strong custom R&D and production capabilities, able to meet the differentiated needs of various industries and operating conditions.

35.1 Size and Specification Customization

Standard Specifications: 20-foot, 40-foot, and 45-foot standard shipping container dimensions, available from stock;

Non-Standard Customization: Full-size customization with length from 3m to 18m, width from 2.2m to 3.5m, and height from 2.6m to 3.5m;

Multi-Container Combinations: Parallel, series, and multi-layer stacking of multiple containers, usable to form large constant temperature and humidity warehouses;

Special Structures: Shelter-type, vehicle-mounted, foldable, and rapid-deployment special structure customization.

35.2 Performance Parameter Customization

Temperature Customization: Full temperature range from -60°C to +100°C; ultra-low temperature, high temperature, and wide temperature range types customized as needed;

Humidity Customization: Full humidity range from 1%RH to 98%RH; ultra-low humidity, high humidity, and high-precision types customized as needed;

Precision Customization: Standard grade (±1°C/±5%RH), precision grade (±0.5°C/±3%RH), and high-precision grade (±0.3°C/±1.5%RH) available;

Energy Efficiency Customization: Grade 1 energy efficiency, ultra-high efficiency, solar-powered, and waste heat recovery energy-saving solutions customized.

35.3 Industry Scenario Customization

Energy Storage Industry: Adapting to different energy storage technologies including lithium batteries, flow batteries, and flywheel energy storage; integrating BMS connectivity, fire protection systems, and thermal management optimization; providing complete energy storage constant temperature and humidity container solutions;

Electronics Manufacturing Industry: Anti-static, clean-grade constant temperature and humidity warehousing, suitable for SMT materials, chips, and component storage;

Pharmaceutical and Biotechnology Industry: GMP-grade constant temperature and humidity cold storage, suitable for pharmaceuticals, reagents, vaccines, and biological sample storage;

Military and Aerospace Industry: Explosion-proof, anti-corrosion, and anti-interference types, suitable for ammunition, precision instruments, and aviation component storage;

Agriculture and Food Industry: Specialized temperature and humidity environment customization for seed storage, edible fungus cultivation, and food preservation.

35.4 Functional Configuration Customization

Intelligent Upgrades: AI energy efficiency optimization, digital twin, unattended operation, and edge computing intelligent functions;

Security Upgrades: Fingerprint access control, facial recognition, video surveillance, and perimeter protection security systems;

Power Support: UPS uninterruptible power supply, diesel generators, and photovoltaic off-grid power supply configurations;

Internal Configuration: Shelving, workstations, anti-static flooring, observation windows, and pass-through windows internal facility customization.

Guangzhou Lain adheres to the “one customer, one solution” customization service model, with dedicated personnel managing the entire process from requirements research, solution design, production and manufacturing, to installation and commissioning, ensuring the final product fully matches the customer’s actual usage needs. We provide four core services — customization, OEM manufacturing, confidentiality, and stock supply — whether for batch standardized procurement or personalized customization, we can provide the optimal solution.

36.1 Warranty Service Commitment

  • Whole machine warranty of 1 year; core components (compressor, controller) warranty of 2 years; lifetime maintenance;
  • Equipment failures during the warranty period not caused by human damage receive free on-site repair and parts replacement;
  • The warranty period commences from the date of equipment acceptance;
  • After the warranty period ends, provide lifetime cost-price maintenance services, charging only for parts costs and labor/travel expenses, with no hidden charges.

36.2 Response and On-Site Service

  • Establish a 7×24-hour technical support hotline at +86 13538869979, available to answer technical questions and fault consultations at any time;
  • On-site service within 24 hours for provincial projects, 48 hours for out-of-province projects, and 72 hours for remote areas;
  • Establish exclusive customer service files, track service progress throughout the process, and conduct satisfaction follow-up calls after service completion;
  • Proactively conduct regular follow-up visits to understand equipment operating status, provide maintenance recommendations, and proactively reduce fault probability.

36.3 Maintenance Service Packages

Provide multiple annual maintenance packages for customer selection:

Basic Maintenance: 2 on-site inspection and maintenance visits per year, discounts on consumable parts, and no labor charges for fault on-site visits;

Comprehensive Maintenance: 4 on-site deep maintenance visits per year, including all consumable part replacements, and free repair of all faults throughout the year;

Full-Service Maintenance: All-inclusive service — all repairs, parts, maintenance, and labor fully covered — worry-free and convenient.

36.4 Technical Support Channels

  • Service Hotline: +86 13538869979 (also on WeChat), for business consultation and order coordination;
  • Technical Support: +86 13538869979, for technical issues and fault reporting;
  • Official Website: https://gdlain.com, for product documentation download and online consultation;
  • Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou, welcome for on-site visits and discussions.

Guangzhou Lain adheres to the business philosophy of “Quality First, Customer Supreme,” earning customer trust with quality products, professional technology, and complete services. Choosing Guangzhou Lain constant temperature and humidity containers means choosing a stable and reliable environmental control solution.

Manufacturer: Guangzhou Lain Intelligent System Development Co., Ltd.

Service Hotline: +86 13538869979 (also on WeChat)

Technical Support: +86 13538869979

Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou

Official Website: https://gdlain.com

Scroll to Top