Title Tag: Packaged Container Installation and Commissioning Manual_General Scenario Container Installation Guide – Guangzhou Lain Intelligent System Development Co., Ltd.
Meta Keywords: Packaged container, packaged container installation and commissioning, general scenario container, packaged container installation manual, Lain container, container commissioning method, prefabricated container installation, packaged container construction specification, Guangdong packaged container manufacturer, container acceptance standard
Meta Description: Guangzhou Lain Intelligent System Development Co., Ltd. provides the complete version of the packaged container installation and commissioning manual, covering the full-process guide of general scenario packaged container installation steps, system commissioning methods, completion acceptance standards, daily maintenance, and fault troubleshooting. Original factory technical support: +86 13538869979, service hotline: +86 13538869979, official website: https://gdlain.com.
H1 Tag: Packaged Container Installation and Commissioning Manual (General Scenarios)
H2 Tags: Product Overview and Technical Parameters, Pre-installation Preparation Work, Main Installation Construction Process, System Commissioning and Performance Testing, Engineering Acceptance and Delivery, Daily Maintenance and Periodic Maintenance, Common Faults and Solutions, Safe Construction and Emergency Regulations
Internal Link Optimization Anchor Text System
Core Anchor Text: Packaged container, packaged container installation and commissioning
Long-tail Anchor Text: General scenario packaged container installation method, packaged container system commissioning steps, packaged container acceptance standard
Related Anchor Text: Modular container construction, prefabricated container operation and maintenance, container housing installation technical specification
Manufacturer Information
Manufacturer: Guangzhou Lain Intelligent System Development Co., Ltd.
Service Hotline: +86 13538869979 (WeChat same number)
Technical Support: +86 13538869979
Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou
Official Website: https://gdlain.com
Preface
This manual addresses packaged container products for general scenarios, systematically elaborating the technical requirements and operational specifications covering the full process from site entry preparation, installation construction, system commissioning, acceptance, to operation and maintenance. This manual is compiled in accordance with current national standards for building structures, electromechanical installation, fire safety, and other relevant regulations, and is applicable to packaged container installation and commissioning operations in general scenarios such as office temporary construction, warehousing and turnover, emergency command, supporting equipment rooms, commercial displays, and temporary accommodation.
As a professional packaged container manufacturer, Guangzhou Lain Intelligent System Development Co., Ltd. possesses integrated full-process capabilities in design, production, installation, and after-sales service. All products are manufactured in strict compliance with the ISO9001 quality management system. Construction units and user units should strictly follow this manual during operations. For technical questions, please call the technical support hotline +86 13538869979 at any time for original factory guidance.
This manual is version V2.0. Future technical upgrades will be synchronized with updates. The latest version can be downloaded from the official website https://gdlain.com.
Chapter 1 Product Overview and Technical Parameters
1.1 Definition of Packaged Container Product
Packaged containers, also known as container cabins or prefabricated packaged boxes, are prefabricated building products with a steel structure as the main frame, featuring modular design, factory prefabrication, and rapid on-site assembly. General scenario packaged containers can be flexibly combined according to usage requirements, achieving single-story or multi-story stacking, as well as various layout forms such as horizontal splicing and longitudinal extension, with core characteristics of convenient disassembly and assembly, recyclability, and strong site adaptability.
Compared with traditional fixed buildings, packaged containers do not require complex civil construction, have low foundation requirements, short installation cycles, and the entire unit can be relocated and reused. They are widely used in numerous general scenarios such as engineering camps, industrial park supporting facilities, emergency resettlement, commercial pop-up stores, warehousing and logistics, and equipment room support, making them one of the most widely applied categories in the prefabricated building field.
Lain packaged containers manufactured by Guangzhou Lain Intelligent System Development Co., Ltd. adopt standardized modular design, with all core components prefabricated at the factory. On-site assembly only requires bolted connections and sealing treatment, greatly reducing on-site construction difficulty and labor costs.
1.2 Core Application Areas of General Scenario Packaged Containers
Engineering Temporary Construction Scenarios: Construction site project departments, worker dormitories, canteens, meeting rooms, guard rooms, material storage rooms, etc., which can be quickly erected and put into use, and after project completion, can be dismantled and relocated to the next project for reuse.
Warehousing and Logistics Scenarios: Temporary park warehouses, equipment transit warehouses, tool storage rooms, material sorting rooms, etc., where the number of containers can be flexibly increased or decreased according to cargo volume, adapting to warehousing needs of different durations.
Office Support Scenarios: Temporary office areas in industrial parks, entrepreneurial incubation workstations, park service stations, property duty rooms, etc., which can be paired with decorated interiors to achieve a modern office environment.
Emergency Support Scenarios: Disaster-relief temporary resettlement points, epidemic prevention checkpoints, emergency command rooms, temporary medical stations, etc., which can be rapidly transported and erected to meet the timeliness requirements of emergency scenarios.
Commercial Service Scenarios: Pop-up stores, market stalls, tourist service centers, scenic area support buildings, outdoor stations, etc., which can be flexibly deployed and removed according to activity cycles.
Equipment Room Support Scenarios: Small data equipment rooms, equipment rooms, monitoring rooms, weak-current rooms, etc., which can be retrofitted with thermal insulation, fire protection, and anti-static measures to meet the operating environment requirements of electromechanical equipment.
Other General Scenarios: Temporary school classrooms, sports event support buildings, outdoor work camps, breeding support buildings, etc., suitable for the vast majority of non-specialized industrial general usage scenarios.
1.3 Core Advantages of Packaged Containers
1.3.1 Modular Design, Efficient Installation
Packaged containers adopt standardized modular design. All main structural components are prefabricated at the factory, with no on-site welding required. Assembly is completed solely through bolted connections. A standard single container can be fully assembled by only 2-3 workers in half a day, greatly shortening the construction period and achieving rapid deployment of “site entry and use on the same day.”
1.3.2 Recyclable, Superior Economics
The product adopts an overall steel structure with a service life of over 15 years under normal use conditions. It can be dismantled, relocated, and reassembled multiple times, with a reuse rate exceeding 90%. Compared with traditional mobile prefab houses, packaged containers have extremely low disassembly and assembly losses, significantly reducing long-term comprehensive usage costs and aligning with the concept of green and low-carbon development.
1.3.3 Sturdy Structure, Safe and Reliable
The main frame of Lain packaged containers is formed by welded galvanized section steel, providing excellent wind resistance, seismic resistance, and compression resistance. Standard products can withstand Force 10 winds, with seismic fortification intensity up to 7 degrees and roof uniformly distributed load up to 1.5kN/m², meeting the natural environment usage requirements of most regions. The container body uses fire-resistant panel materials, with a core fireproof rating up to Class A, complying with building fire safety codes.
1.3.4 Strong Site Adaptability
Packaged containers have low foundation requirements and can adapt to various site conditions including cement floors, hardened sites, lawns, and slopes. Only simple leveling or simple strip foundations are needed for installation. No complex civil construction approval processes are required, enabling rapid implementation, particularly suitable for temporary land use and short-term usage scenarios.
1.3.5 Flexible Layout, Strong Scalability
Each single container is an independent unit that can be combined through horizontal splicing, longitudinal extension, and multi-story stacking to form building spaces of different areas and configurations. The number of containers can be increased or decreased at any time according to usage requirements, and units can also be relocated to new sites and rearranged, flexibly adapting to changes in business scale.
1.3.6 Thermal Insulation, Comfortable Living
The envelope panel adopts a double-layer color steel sandwich insulation structure. The core material can be selected from rock wool, glass wool, polyurethane, and other insulation materials, offering excellent thermal insulation, heat insulation, and sound insulation performance. In summer, outdoor heat can be effectively blocked; in winter, indoor heat loss is reduced. When paired with air conditioning equipment, a comfortable indoor environment can be achieved, meeting office and residential usage needs.
1.4 Product Structure Composition of Packaged Containers
General scenario packaged containers consist of seven core systems: the main frame system, envelope wall system, roof system, floor system, door and window system, electromechanical support system, and sealing and waterproofing system. All system components are standardized prefabricated parts that are universally interchangeable.
1.4.1 Main Frame System
The main frame is the load-bearing core of the packaged container, comprising three main parts: the bottom frame, columns, and top beams. All are made of Q235B carbon structural steel with hot-dip galvanized surface anti-corrosion treatment for long service life.
Bottom Frame: The main beams, secondary beams, and peripheral frame are welded into an integral frame, with ground connection holes at the bottom for fixing to the foundation. The bottom frame has reserved pipe and cable pass-through holes to facilitate water and electrical conduit installation. Main beams use No. 8/No. 10 channel steel, secondary beams use No. 5 angle steel, with spacing designed according to load-bearing requirements to ensure uniform floor plate load distribution.
Columns: Made of square steel tubes, with connection flange plates welded at both upper and lower ends, rigidly connected to the bottom frame and top beams via high-strength bolts. The columns have prefabricated wall panel fixing slots and screw holes, eliminating the need for on-site drilling. Standard column heights are 2.8m and 3.0m, with custom height extension available upon request.
Top Beams: Welded from main beams, secondary beams, and peripheral frame corresponding to the bottom frame structure, used to bear roof loads and upper container loads (when stacked). The top beams have reserved roof connection holes and lifting holes to accommodate both installation and hoisting requirements.
1.4.2 Envelope Wall System
The wall system comprises three parts: exterior wall panels, interior wall panels, and insulation layer, with interlocking installation for tight joints and good sealing.
Exterior Wall Panels: Double-sided color steel sandwich panels with 0.4-0.6mm thick color-coated steel sheets on both faces. The core material is Class A fire-resistant rock wool or glass wool, with a typical thickness of 50mm, 75mm, or 100mm. The panel edges feature male-female groove interlocking structures that fit tightly during installation, providing multiple functions of insulation, fire protection, sound insulation, and waterproofing.
Interior Wall Panels: Available in color steel sandwich panels, calcium silicate boards, decorative integrated panels, and other materials for the interior decorative surface. The surface is flat and aesthetically pleasing, ready for use without secondary decoration.
Insulation Layer: The sandwich panel core material serves as the insulation layer. For special low-temperature/high-temperature scenarios, an additional interior insulation layer can be added to enhance thermal insulation effectiveness.
Corner Components: Dedicated galvanized steel internal and external corner components are provided at wall corners, ensuring both structural strength and enhanced overall appearance.
1.4.3 Roof System
The roof system consists of roof panels, roof beams, gutters, and sealing strips, featuring organized drainage design to ensure smooth rainwater drainage with no leakage risks.
Roof Panels: Double-layer color steel sandwich roof panels with profiled color steel surface, featuring self-waterproofing with dedicated waterproof sealing strips at lap joints. The roof has a built-in 2%-3% drainage slope directing rainwater toward the gutters.
Gutters: Formed by bending galvanized steel sheets, installed on both sides of the top beams to collect roof rainwater, with outlet ports at the ends connected to downspouts. Weather-resistant sealant is applied at gutter joints to ensure no leakage.
Downspouts: Made of PVC or galvanized steel pipe, fixed along the columns, directing rainwater from the gutters to the ground drainage system.
1.4.4 Floor System
The floor system consists of three parts: the load-bearing base layer, moisture barrier layer, and surface floor, featuring load-bearing, moisture-proof, and wear-resistant properties.
Load-bearing Base Plate: Typically 15-18mm thick fiber cement board or magnesium oxide board, laid on the bottom frame secondary beams as the base load-bearing layer, with excellent fire resistance and moisture resistance.
Moisture Barrier Layer: A PE moisture barrier film is laid beneath the base plate to isolate ground moisture and prevent floor deformation due to dampness.
Surface Flooring: For general scenarios, PVC flooring, laminate flooring, anti-static flooring, etc., can be selected according to usage requirements. The standard configuration includes PVC flooring, which is wear-resistant, slip-resistant, and easy to clean.
1.4.5 Door and Window System
Doors and windows are factory-prefabricated finished products, directly installed and fixed on site with excellent sealing performance.
Doors: Standard configuration is a steel anti-theft door measuring 900×2100mm, equipped with locks, hinges, and a door closer. Fire doors, glass doors, roller shutter doors, etc., can be added upon request.
Windows: Standard configuration is a uPVC sliding window or aluminum alloy sliding window measuring 1200×1200mm, equipped with screen mesh, handles, and locking mechanisms. Glass is 5mm thick tempered glass, providing good safety and light transmission. Additional windows or custom floor-to-ceiling windows can be provided upon request.
1.4.6 Electromechanical Support System
General scenario packaged containers can be pre-installed with a basic electromechanical system, ready for use upon connecting utilities on site.
Electrical System: Standard equipment includes a distribution box, lighting fixtures, switches and outlets, and wiring conduits. Circuit design complies with civil electrical codes and can meet daily office, lighting, and general equipment power demands.
Water Supply and Drainage System: Water supply and drainage interfaces can be pre-installed, with matching installation of faucets, wash basins, floor drains, etc., to meet water usage requirements.
Ventilation System: Standard exhaust fans or ventilation louvers are provided to ensure indoor air circulation. Air conditioning and fresh air systems are optional.
1.4.7 Sealing and Waterproofing System
All component joints are provided with dedicated sealing strips and weather-resistant sealant to form a complete sealing and waterproofing system, including wall panel joint strips, roof lap joint strips, door and window perimeter sealant, and pipe through-wall waterproof sealant, ensuring overall water tightness and air tightness of the container.
1.5 Core Technical Parameters of General Scenario Packaged Containers
1.5.1 Standard Single Container Dimensional Parameters
| Parameter Item | Standard Model (3m×6m) | Wide Model (3.6m×6m) | Small Model (3m×4m) | Remarks |
|---|---|---|---|---|
| External Length | 6000mm | 6000mm | 4000mm | Including frame dimensions |
| External Width | 3000mm | 3600mm | 3000mm | Including frame dimensions |
| External Height | 2896mm | 2896mm | 2896mm | From outdoor ground level to highest point of roof |
| Internal Net Length | 5840mm | 5840mm | 3840mm | Interior wall spacing |
| Internal Net Width | 2840mm | 3440mm | 2840mm | Interior wall spacing |
| Internal Net Height | 2600mm | 2600mm | 2600mm | From floor to ceiling lower surface |
| Single Container Floor Area | 18m² | 21.6m² | 12m² | Calculated per exterior wall perimeter |
| Single Container Usable Area | Approx. 16.6m² | Approx. 20m² | Approx. 10.9m² | Indoor net usable area |
1.5.2 Structural Performance Parameters
- Main frame material: Q235B carbon structural steel, hot-dip galvanized anti-corrosion, galvanized layer thickness ≥80μm
- Design service life: 15 years (under normal use and regular maintenance conditions)
- Seismic fortification intensity: 7 degrees
- Wind resistance rating: Level 10 (wind speed 28m/s), up to Level 12 with reinforcement
- Roof uniformly distributed live load: 1.5kN/m²
- Floor uniformly distributed live load: 2.0kN/m²
- Wall wind pressure resistance: ≥1.0kPa
- Multi-story stacking: maximum 3 stories; second and third stories must satisfy load verification requirements
1.5.3 Envelope Performance Parameters
- Exterior wall panel thickness: 50mm/75mm/100mm optional
- Core material fireproof rating: Class A (non-combustible)
- Wall heat transfer coefficient: ≤0.6W/(m²·K) (75mm rock wool core material)
- Airborne sound insulation: ≥30dB
- Roof waterproofing rating: Class II, waterproof durability 10 years
- Wall water tightness: Meets Class 6 requirements of GB/T 7106-2019
1.5.4 Electrical System Parameters
- Rated voltage: AC220V/380V, 50Hz
- Standard main switch capacity: 32A/63A
- Standard circuit count: 1 lighting circuit, 2 outlet circuits, 1 air conditioning circuit
- Outlet specifications: 10A five-hole outlet, 16A air conditioning outlet
- Lighting power: LED flat panel light, 2-4 per container, total power 40-80W
- Earthing method: TN-S system, earth resistance ≤4Ω
- Cable specifications: lighting 1.5mm² copper wire, outlets 2.5mm² copper wire, air conditioning 4mm² copper wire
1.6 Product Applicable Standards and Specifications
The design, production, installation, and acceptance of this product strictly comply with the following national and industry standards:
- “Unified Standard for Reliability Design of Building Structures” GB 50068-2018
- “Standard for Design of Steel Structures” GB 50017-2017
- “Technical Code of Cold-Formed Thin-Wall Steel Structures” GB 50018-2002
- “Standard for Quality Acceptance of Steel Structure Engineering Construction” GB 50205-2020
- “Code for Seismic Design of Buildings” GB 50011-2010 (2016 Edition)
- “Code for Fire Protection Design of Buildings” GB 50016-2014 (2018 Edition)
- “Metal-Faced Sandwich Panels for Building Insulation” GB/T 23932-2009
- “Graduations and Test Methods of Air Permeability, Water Tightness and Wind Load Resistance Performance for Building External Windows and Doors” GB/T 7106-2019
- “Code for Acceptance of Quality of Construction of Building Electrical Engineering” GB 50303-2015
- “Code for Acceptance of Construction Quality of Building Water Supply, Drainage and Heating Works” GB 50242-2002
- “Technical Standard for Assembled Steel Structure Buildings” GB/T 51232-2016
- “Technical Standard for Modular Assembled Monolithic Buildings” JGJ/T 469-2019
1.7 Manufacturer Introduction
Guangzhou Lain Intelligent System Development Co., Ltd. is headquartered at Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou. It is a high-tech enterprise specializing in the research and development, production, sales, and installation services of modular buildings, smart machine room equipment, and shielding security products. The company possesses a modern production base and a professional technical team, with an annual production capacity of over ten thousand sets of packaged containers. Products are widely used in construction, communications, electric power, medical, emergency, and other industrial sectors.
Adhering to the business philosophy of “Quality First, Customer Foremost,” all packaged container products are manufactured through standardized, modularized, and intelligent production. From raw material procurement, production and processing to finished product delivery, a strict quality control system is implemented to ensure that every product meets national standards and customer requirements.
The company provides full-process services from solution design, manufacturing, transportation and delivery, installation and commissioning, to after-sales maintenance. On-site installation and technical support are available nationwide. Service hotline: +86 13538869979 (WeChat same number), technical support: +86 13538869979. For more product information, please visit the official website https://gdlain.com.
Chapter 2 Pre-installation Preparation Work
2.1 Pre-arrival Site Survey
Before the packaged container arrives on site for installation, a complete on-site survey must be conducted to confirm that site conditions meet installation requirements, avoiding situations where construction cannot proceed after arrival. The survey should be led by the project technical director, conducted in conjunction with construction drawings and actual site conditions, and a formal site survey report should be produced.
2.1.1 Core Survey Content
Site Topography and Dimensions
- Measure the actual usable dimensions of the site to confirm sufficient space for container placement, hoisting operations, and material stacking. A single container installation requires a minimum of 2m of surrounding operational space. Hoisting operations require reserved radius space based on crane parameters.
- Survey site flatness, record elevation differences, and determine whether site leveling or foundation leveling is required.
- Confirm whether there are obstacles around the site, such as overhead power lines, trees, buildings, etc., and assess whether they affect hoisting operations and container transport into the site.
Geological and Foundation Conditions
- Determine the foundation bearing capacity. Ordinary hardened cement ground and compacted plain soil foundations must have bearing capacity ≥80kPa. Soft foundations, sandy ground, and backfilled soil require additional foundation reinforcement treatment.
- Survey underground pipeline distribution to confirm whether gas, power, communication, water supply, and drainage pipelines are buried beneath the installation area to avoid damaging underground utilities during construction.
- Survey groundwater level conditions. Sites with excessively high groundwater levels require proper waterproofing, moisture protection, and drainage treatment.
Surrounding Environmental Conditions
- Confirm site drainage conditions and whether there is a risk of water accumulation. Plan drainage slopes and drainage paths to prevent rainwater from flowing backward into the container.
- Confirm the location and distance of water and power connection points, plan the routing of pipes and cables, and confirm whether connection capacity meets usage requirements.
- Survey site traffic conditions to confirm whether transport vehicles can directly access the installation site, and whether road turning radius, height limits, and weight limits meet container transport requirements.
- Confirm whether the surrounding environment has special requirements, such as noise restrictions, construction time limits, and fire protection requirements.
Climate and Environmental Factors
- Understand the climate characteristics of the project location, such as rainy season duration, winter minimum temperature, year-round wind speed, and snowfall, to determine whether special reinforced configurations of the product are required.
- For coastal areas, confirm salt spray corrosion conditions and assess whether additional anti-corrosion treatment is needed. For high-altitude areas, confirm UV intensity and assess the aging resistance of sealants and panels.
2.1.2 Survey Results Output
Upon completion of the survey, a “Site Survey Report” must be compiled, including: site plan diagram, dimensional annotations, foundation condition description, obstacle annotations, water and power connection point locations, hoisting operation plan, foundation treatment recommendations, risk points and response measures, etc. The report must be reviewed and confirmed by the technical director and serve as the basis for subsequent foundation construction and installation operations.
2.2 Foundation Construction Technical Requirements
Packaged containers have lower foundation requirements than traditional buildings, but foundation quality directly affects container installation accuracy, structural stability, and service life, and must be constructed in strict accordance with technical requirements. For general scenarios, four foundation types may be selected based on site conditions: concrete strip foundation, monolithic concrete slab foundation, point foundation, and hardened ground direct installation.
2.2.1 General Foundation Design Requirements
- The foundation top elevation shall be 100-150mm above the outdoor ground level to prevent rainwater backflow.
- Foundation top surface flatness deviation ≤3mm/m, overall elevation deviation ≤5mm, ensuring uniform horizontal load distribution on the bottom frame after installation.
- The foundation shall have sufficient bearing capacity to avoid uneven settlement causing container deformation.
- The foundation shall have reserved earthing electrode embedded positions, with earth resistance meeting electrical system requirements.
- Drainage slopes shall be provided around the foundation, with a slope ≥3‰, directing rainwater away from the foundation.
2.2.2 Common Foundation Types and Construction Requirements
Concrete Strip Foundation
- Applicable scenarios: Long-term use, multi-story stacking, and general foundation conditions; it is the most commonly used foundation type.
- Construction requirements: Strip foundations shall be placed along the bottom frame perimeter, with width of 240-300mm, height of 200-300mm, poured with C20 concrete, and containing a Φ8@200 bidirectional steel mesh.
- M12 expansion bolts or embedded steel plates shall be embedded on the foundation top surface for fixed connection with the container bottom frame. Bolt spacing ≤1500mm, and each corner point must have a fixing point.
- Strip foundations shall be poured on the original soil layer. Weak soil layers require replacement and compaction, with a replacement depth ≥300mm.
Monolithic Concrete Slab Foundation
- Applicable scenarios: Multi-container splicing, indoor floor level with outdoor ground level, and scenarios requiring high floor flatness.
- Construction requirements: A monolithic C20 concrete slab shall be poured with a thickness of ≥100mm, containing a Φ6@200 steel mesh. The slab surface shall be troweled and leveled to meet flatness requirements.
- Fixing bolts may be embedded at container positions, or expansion bolts may be installed after concrete curing.
- The slab shall be provided with expansion joints at intervals of ≤6m to prevent concrete cracking.
Point Foundation
- Applicable scenarios: Temporary use, single-story containers, and sites with good foundation conditions; fast construction and low cost.
- Construction requirements: Concrete foundation piers shall be placed at positions corresponding to container columns, with dimensions of 300×300×300mm, poured with C20 concrete, with embedded steel plates on the top surface.
- Top elevations of all foundation piers must be consistent, with elevation difference ≤3mm, ensuring uniform column load distribution.
- Point foundations are only suitable for single-story, short-term use scenarios. Point foundations are strictly prohibited for multi-story stacking.
Hardened Ground Direct Installation
- Applicable scenarios: Sites with existing hardened cement floors, thickness ≥150mm, and meeting bearing capacity requirements, such as factory workshops and park hardened roads.
- Construction requirements: After verifying floor flatness and bearing capacity, directly mark positioning lines and use expansion bolts to fix the bottom frame to the floor.
- Areas with cracks, hollowing, or settlement in the floor must be repaired and reinforced first; direct installation is not permitted.
2.2.3 Foundation Acceptance
After foundation construction is completed, acceptance inspection must be organized, covering: foundation dimensions, elevation, flatness, bearing capacity, fixing bolt positions, earthing embedment, drainage slope, etc. Container installation may proceed only after acceptance is passed. Foundations that fail acceptance must be rectified and re-inspected.
Container installation may only commence after the foundation concrete strength reaches 75% of the design strength. Under normal temperature conditions, curing typically requires 7 days or more. Winter construction requires extended curing time or anti-freezing measures.
2.3 Construction Personnel Organization and Job Responsibilities
Packaged container installation requires the formation of a professional construction team with clearly defined job responsibilities to ensure construction safety and installation quality. A standard single container installation requires 2-3 workers. Multi-container combinations and multi-story stacking require proportionally additional personnel.
2.3.1 Personnel Allocation Standard
| Position | Quantity | Qualification Requirements |
|---|---|---|
| Project Manager | 1 | Experience in prefabricated building construction management; safety officer certificate preferred |
| Technical Director | 1 | Familiar with packaged container installation processes; capable of drawing interpretation and technical guidance |
| Installation Foreman | 1 | 3+ years of packaged container installation experience; proficient in all installation procedures |
| Installation Workers | 2-4 | Trained in installation; familiar with operating procedures; capable of working at heights |
| Electrician | 1 | Hold low-voltage electrician operation certificate; responsible for electrical system installation and commissioning |
| Welder | 1 | Hold welder operation certificate; responsible for miscellaneous welding and earthing welding (configured as needed) |
| Safety Officer | 1 | Hold safety officer certificate; responsible for on-site safety management and supervision |
2.3.2 Job Responsibility Descriptions
Project Manager
- Overall responsibility for project construction management, coordinating the full process of site entry, construction, and acceptance.
- Responsible for communication and coordination with the client and supervision units, implementing construction requirements.
- Responsible for construction schedule control, ensuring installation tasks are completed as planned.
- Responsible for overall control of on-site safety, quality, and cost.
- Liaison with factory technical support to coordinate and resolve major issues during construction. Technical support hotline: +86 13538869979.
Technical Director
- Responsible for construction drawing review and technical briefing, preparing construction plans.
- Guides on-site construction, resolving technical issues during installation.
- Responsible for installation quality inspection and acceptance, completing construction records.
- Prepares commissioning plans and organizes system commissioning work.
- Consolidates completion documentation and participates in final acceptance.
Installation Foreman
- Leads the installation crew in installation operations per drawings and specifications.
- Rationally arranges work sequences, controlling installation progress and quality.
- Responsible for the management and maintenance of construction tools and materials.
- Implements crew safety briefings and supervises crew compliance with safe operating procedures.
- Holds daily pre-shift meetings to assign daily tasks and emphasize safety precautions.
Installation Workers
- Strictly perform construction operations in accordance with installation specifications and technical requirements.
- Correctly use construction tools and safety protective equipment.
- Cooperate in completing installation procedures and self-inspection tasks.
- Promptly report quality issues and safety hazards to the foreman.
Dedicated Electrician
- Responsible for on-site temporary electrical distribution layout and management.
- Responsible for container electrical system installation, wiring, and commissioning.
- Responsible for earthing system construction and testing.
- Strictly implement electrical safety codes and prohibit non-compliant electrical use.
Safety Officer
- Responsible for on-site safety management and supervision of safety code compliance.
- Conducts safety education and safety technical briefings.
- Patrols the site for safety hazards and urges rectification.
- Manages on-site fire-fighting equipment and implements hot work approval procedures.
- Participates in safety accident emergency response.
2.4 Installation Tools and Equipment Preparation
All installation tools and equipment must be prepared and checked for performance status before construction to ensure normal use during the construction process. Tools are divided into five categories: hoisting equipment, manual tools, power tools, measurement and testing tools, and safety protective equipment.
2.4.1 Hoisting Equipment
| Equipment Name | Specification/Model | Purpose | Remarks |
|---|---|---|---|
| Truck Crane | 8-25 ton | Hoisting of large components such as container frames and roof panels | Selected per container weight and hoisting height |
| Forklift | 3-5 ton | On-site material transfer, short-distance handling of bottom frames | Used when site has good hardened surface conditions |
| Manual Chain Hoist | 2 ton | Small component hoisting, fine positioning adjustment | Used with scaffolding or temporary supports |
| Lifting Slings | 3 ton/5 ton | Component hoisting slings | Wire ropes are strictly prohibited for direct bundling of components |
| Shackles | M16/M20 | Hoisting connection accessories | Inspect regularly for wear |
2.4.2 Manual Tools
| Tool Name | Specification | Purpose | Quantity |
|---|---|---|---|
| Adjustable Wrench | 8″, 12″, 15″ | Bolt tightening | 2 each |
| Socket Wrench Set | 8-24mm set | High-strength bolt tightening | 2 sets |
| Torque Wrench | 50-200N·m | Bolt torque verification | 1 |
| Screwdrivers | Phillips and flat head, various sizes | Screw fastening, panel installation | 4 each |
| Rubber Mallet | 16oz | Wall panel adjustment, component seating | 2 |
| Hammer | 1.5lb, 3lb | Driving, chiseling | 1 each |
| Steel Tape Measure | 5m, 7.5m, 30m | Dimension measurement, layout marking | 2 each |
| Feeler Gauge | 1-15mm | Gap inspection | 1 set |
| Utility Knife | Large | Panel cutting, gasket trimming | 5 |
| Caulking Gun | Manual | Sealant application | 4 |
| Plumb Bob | 0.5kg | Verticality inspection | 2 |
| Electrician Tool Set | Includes wire strippers, voltage tester, etc. | Electrical installation | 1 set |
2.4.3 Power Tools
| Tool Name | Specification | Purpose | Remarks |
|---|---|---|---|
| Electric Drill | Cordless/plug-in | Drilling, screw fastening | Equipped with various drill bits and driver bits |
| Impact Drill | Type 26 | Concrete drilling, expansion bolt installation | Equipped with impact drill bits |
| Angle Grinder | 100mm | Metal cutting, grinding | Equipped with cutting discs and grinding discs |
| Cut-off Saw | Section cutting saw | Section steel and panel cutting | Fixed workstation usage |
| Welding Machine | 220V/380V DC | Miscellaneous welding, earthing welding | Operators must be certified |
| Electric Impact Wrench | Impact type | Rapid tightening of large bolts | Equipped with appropriate sockets |
| Electric Caulking Gun | Electric | Uniform sealant application | Optional, improves efficiency |
2.4.4 Measurement and Testing Tools
| Tool Name | Accuracy | Purpose |
|---|---|---|
| Laser Level | ±2mm/10m | Horizontal elevation and verticality measurement |
| Theodolite | 2″ | Axis positioning, verticality inspection |
| Straightedge | 2m | Wall and floor flatness inspection |
| Earth Resistance Tester | 0.01Ω | Earth resistance testing |
| Insulation Resistance Tester (Megger) | 500V | Electrical insulation resistance testing |
| Multimeter | Digital | Electrical parameter measurement |
| Vernier Caliper | 0.02mm | Component dimension and thickness inspection |
2.4.5 Safety Protective Equipment
Personal Protection: Safety helmets, safety harnesses, anti-slip safety shoes, protective gloves, safety goggles, dust masks
On-site Protection: Safety warning tape, warning signs, scaffolding, safety ladders, fire extinguishers, first aid kits
Temporary Electrical: Residual current devices, earthing rods, insulated cables, distribution boxes
All tools and equipment must be inspected and calibrated before entering the site. Measurement tools must be within their calibration validity period. Power tools must have sound insulation. Hoisting equipment must be reliable in performance. Operation of defective equipment is strictly prohibited.
2.5 Material Arrival and Acceptance
2.5.1 Material Transportation
Packaged containers are transported in component-separated form, with frames, panels, doors and windows, and accessories packed separately by category and transported to the site by truck. During transportation, protective measures must be taken to prevent component deformation, paint surface scratches, and panel moisture damage.
- Steel structure frames must be stacked neatly with timber spacers between layers to prevent collision deformation during transport.
- Sandwich panels must be stored vertically with the bottom supported evenly. Heavy objects must not be placed on top, and the surface should be covered with a rainproof tarp.
- Doors, windows, hardware accessories, and electrical components must be boxed for protection to avoid impact damage.
- Sealants, adhesives, and similar materials must be protected from direct sunlight and high-temperature storage to ensure performance stability.
2.5.2 Unloading and Stacking
- Materials should be sorted and stacked in designated areas upon arrival. Stacking areas must be flat, dry, and free of standing water.
- Use gentle lifting and lowering during unloading. Throwing and dragging are strictly prohibited to avoid component deformation and surface finish damage.
- Steel structural components shall be stacked to a height of ≤1.5m, with timber spacers aligned between layers to prevent bending deformation from compression.
- Sandwich panels shall be stacked at a 5°-10° incline to facilitate drainage, with a height of ≤1.5m, covered with a rainproof tarp.
- Hardware accessories and electrical components shall be stored in a warehouse, protected from moisture and dust, and labeled by category for convenient retrieval.
- Flammable and explosive materials shall be stored separately, away from ignition sources, with fire-fighting equipment provided.
2.5.3 Arrival Acceptance
Materials must undergo joint arrival acceptance with the client and supervision units upon arrival. Acceptance contents include:
- Verify the shipping list against delivered components and accessories, confirming quantities and that specification models match the contract.
- Inspect the appearance quality of components: steel structure frames must be free of deformation, galvanized layer free of peeling; panels free of damage and scratches; doors and windows free of glass breakage and profile deformation.
- Check quality certification documents including product certificates, material test reports, and factory inspection reports.
- Perform sampling inspection of critical dimensions: frame dimensions, panel thickness, bolt specifications, etc., must meet design requirements.
- Non-conforming materials must be clearly marked and promptly returned to the manufacturer for replacement. Non-conforming products are strictly prohibited for use in construction.
- After acceptance is passed, complete the “Material Arrival Acceptance Record” with signatures from all parties. All factory-outgoing products from Guangzhou Lain Intelligent System Development Co., Ltd. are accompanied by complete quality certification documents. If any are missing, contact the service hotline +86 13538869979 for reissuance.
2.6 Construction Technical and Safety Briefing
Technical briefing and safety briefing must be conducted before formal construction to ensure that all construction personnel understand construction requirements, operating specifications, and safety precautions. Briefings must be conducted in writing, signed by all personnel, and records retained.
2.6.1 Technical Briefing Content
- Project overview and construction scope, clearly defining the number of containers to be installed, layout, and schedule requirements.
- Construction drawing explanation, including plan layout, joint construction details, installation sequence, and quality standards.
- Key process operation points, such as bottom frame leveling, wall panel interlocking, waterproof sealing, and electrical wiring.
- Quality acceptance standards, sub-item quality requirements, and acceptance methods.
- Common quality issues and preventive measures, such as leakage, uneven gaps, and frame inclination.
- Finished product protection requirements, including protection measures during and after installation.
2.6.2 Safety Briefing Content
- On-site safety management system, operational discipline, attendance system, and violation penalty regulations.
- Safety operating procedures for each trade, including safety requirements for hoisting, working at heights, electrical work, and hot work.
- Personal protective equipment wearing requirements: safety helmets must be worn upon site entry, and safety harnesses must be worn for work at heights.
- On-site hazard identification and preventive measures, such as falls from height, object strikes, electric shock, and mechanical injury.
- Emergency response procedures, including reporting, first aid, and emergency handling steps after an accident.
- On-site fire safety requirements, hot work approval system, and fire extinguisher usage methods.
2.7 Construction Schedule Planning
Construction schedules shall be compiled according to project scale and site conditions, defining the time nodes for each process to ensure orderly installation progress. The reference installation schedule for a general scenario single container is as follows:
- Foundation construction and curing: 7 days
- Material transportation and arrival: 1 day
- Main frame installation: 0.5 day
- Envelope wall installation: 1 day
- Roof, door, and window installation: 0.5 day
- Electromechanical system installation: 1 day
- Sealing and finishing: 0.5 day
- System commissioning and self-inspection: 1 day
- Completion acceptance: 0.5 day
Multi-container splicing and multi-story stacking projects require correspondingly extended schedules, determined based on the number of containers and layout. The schedule must account for weather factors. Outdoor installation work should not be performed on rainy or high-wind days, and buffer time should be reserved.
Chapter 3 Main Installation Construction Process
3.1 Foundation Setting Out and Positioning
After foundation acceptance is passed, on-site setting out and positioning is performed according to the construction drawings to determine the precise installation position of the container. This is the first process that ensures installation accuracy.
3.1.1 Setting Out Preparation
- Confirm Reference Points: Obtain the site reference axes and elevation control points provided by the client. After verification, use them as the basis for setting out.
- Tool Preparation: 30m steel tape measure, laser level, theodolite, ink line, chalk, wooden stakes, iron nails, etc.
- Clean the foundation surface, removing debris and dust to facilitate line marking and installation operations.
3.1.2 Planar Positioning Setting Out
- According to the container coordinates indicated on the drawings, first establish the longitudinal and transverse main axes of the container, marking them on the foundation surface with an ink line.
- Based on the main axes, mark the bottom frame outer outline, and mark the center point position of each column.
- Mark the drilling positions for fixing bolts to ensure correspondence with the bottom frame bolt holes.
- For multi-container splicing, mark the joint seam positions to ensure alignment and tight splicing of the containers.
- After setting out is complete, perform verification by measuring diagonal lengths. Diagonal deviation ≤5mm is acceptable.
3.1.3 Elevation Control
- Transfer the elevation control point to the installation area and mark the elevation control line on the foundation sides.
- Inspect the foundation top surface elevation, and perform leveling treatment at positions where elevation deviation exceeds tolerance.
- Place adjustment shims at each support point before bottom frame installation, pre-adjusting to the design elevation.
3.1.4 Setting Out Acceptance
After setting out is complete, the technical director shall perform joint review and acceptance, focusing on checking axis positions, dimensional deviations, diagonal deviations, and elevation deviations. Only after confirmation of accuracy may the next process proceed.
3.2 Bottom Frame Installation and Leveling
The bottom frame is the load-bearing foundation of the container. Its installation levelness directly affects overall structural stability and the installation accuracy of subsequent wall panels, and installation quality must be strictly controlled.
3.2.1 Bottom Frame Positioning
- Use a crane or forklift to lift the bottom frame to the marked position, lowering it slowly, initially aligning with the outline lines.
- Manually fine-adjust the bottom frame position so that the frame perimeter precisely coincides with the setting-out lines, and bolt holes align with the foundation marks.
- Preliminarily secure the bottom frame after positioning to prevent displacement.
3.2.2 Levelness Adjustment
- Use a laser level to measure the elevations of the four corner points of the bottom frame, recording elevation difference data.
- Adjust elevations by adding or removing steel adjustment shims beneath the bottom frame. Shim thicknesses available include 1mm, 2mm, 5mm, and 10mm.
- Adjustment sequence: first adjust the four corner points, then the midpoint of each side, and finally verify overall levelness.
- Quality standard: bottom frame top surface levelness deviation ≤2mm/m, overall maximum elevation difference ≤3mm.
- After levelness adjustment is qualified, tighten fixing bolts symmetrically and evenly to avoid bottom frame deformation caused by single-sided tightening.
3.2.3 Bottom Frame Fixation to Foundation
- Use expansion bolts to fix the bottom frame to the foundation. Bolt specifications are M12-M16, with embedment depth ≥100mm.
- Fixing point placement: 1 at each of the four corners, 1 at every 1500mm interval along the long sides, and 1 at every 1000mm interval along the short sides.
- Bolt tightening torque ≥40N·m, with bolts protruding 2-3 threads beyond the nut.
- After fixation is complete, re-verify levelness and re-adjust if any changes have occurred.
3.2.4 Bottom Frame Treatment for Multi-container Splicing
- Adjacent container bottom frames shall be aligned for splicing, with joint seam width ≤2mm.
- Use connection bolts to securely connect the two bottom frames at the splice, with bolt spacing ≤500mm.
- Apply sealant at the bottom of the joint seam to prevent moisture and insects from entering from below.
- After splicing is complete, re-verify overall flatness and straightness to ensure smooth overall appearance after multi-container splicing.
3.2.5 Bottom Frame Moisture Protection Treatment
- Lay a moisture-proof sealing strip between the bottom frame and the foundation contact surface to block capillary water rise.
- Lay PE moisture barrier film on the inner bottom of the bottom frame, with overlap width ≥100mm and edges turned up 50mm.
- Seal pipe pass-through openings in the bottom frame with waterproof sealant to prevent water seepage.
3.3 Column and Main Frame Installation
3.3.1 Column Installation Preparation
- Inspect the column appearance, confirming no deformation, no galvanized layer damage, and no debris in threaded holes.
- Apply sealing gaskets to the upper and lower flange plates of the columns to ensure sealing at connection joints.
- Prepare connection bolts, washers, and nuts. Bolt specifications are typically M16 high-strength bolts.
3.3.2 Column Installation Procedure
- Install the four corner columns first. Align the lower flange of each column with the bottom frame corner bolt holes, insert bolts, and tighten nuts temporarily without final tightening.
- Use a plumb bob or laser level to check column verticality, adjusting the column to a plumb state.
- Temporary fixation: use diagonal braces to temporarily secure the column and prevent tipping.
- Install the remaining columns in sequence, performing the same verticality correction and temporary fixation.
- After all columns are installed, re-verify column spacing and diagonal dimensions. Deviation ≤3mm.
3.3.3 Top Beam Installation
- Hoist the top beam frame and lower it slowly, aligning it with the column upper flanges.
- Insert connection bolts and initially tighten nuts.
- Check the overall diagonal dimensions of the frame and adjust until deviation ≤5mm.
- Check column verticality; if deviation is present, correct by fine-adjusting the top beam position.
- Tighten all connection bolts in diagonal sequence. Bolt tightening torque ≥80N·m.
- After tightening is complete, remove temporary diagonal braces and re-verify overall verticality and diagonal dimensions.
3.3.4 Overall Frame Verification
- Column verticality: deviation ≤H/1000, with total deviation ≤5mm (H is column height).
- Frame diagonal: length deviation ≤5mm.
- Top beam levelness: deviation ≤3mm.
- All bolt connections are firm and free of loosening, with all washers in place.
- Frame joint seams are uniform, with sealing gaskets compressed and free of gaps.
3.3.5 Multi-story Stacking Frame Installation
- Before installing a second-story container, mark the second-story container positioning lines on the first-story top beams.
- Hoist the second-story bottom frame, align it with the positioning lines, and connect it to the first-story top beams using dedicated connection brackets and bolts.
- Second-story columns and top beams follow the same process as the first story, with installation and verification performed story by story.
- Three or more stories of stacking require structural verification and, where necessary, additional reinforcement measures.
- Multi-story stacked containers require the installation of stairs, corridors, and other auxiliary structures, which should be installed in coordination.
3.4 Enclosure Wall System Installation
Wall installation is a critical process that determines the exterior appearance and thermal insulation/waterproofing performance of the prefabricated container. Strict control of panel joint quality and sealing effectiveness is required.
3.4.1 Pre-Installation Preparation
- Clean debris from the frame slots to ensure smooth insertion of wall panels.
- Inspect wall panels for damage, deformation, or paint peeling; verify dimensions meet requirements.
- Prepare self-tapping screws, sealing rubber strips, waterproof sealant, internal/external corner bead strips, and other accessories.
- Pre-adhere sealing rubber strips in the panel joint grooves, with strip joints cut at a 45° bevel.
3.4.2 Exterior Wall Panel Installation Sequence
1. Begin from one corner of the wall and install panels sequentially toward both sides, finishing at the opposite side or at door/window openings.
2. First panel positioning: Insert the bottom edge of the panel into the bottom frame slot, press the side edge against the column, and snap the top edge into the top beam slot.
3. Adjust panel plumbness and flatness; once verified, secure the panel to columns, bottom frame, and top beam using self-tapping screws.
4. Self-tapping screw spacing: Vertical spacing ≤ 300 mm, horizontal spacing ≤ 400 mm. Apply sealant over screw heads for corrosion protection and waterproofing.
5. Align the male groove of the second panel with the female groove of the first panel, push in slowly for a tight joint. Joint gap ≤ 1 mm.
6. Continue installing remaining panels sequentially — check flatness and plumbness after each panel installation, and correct cumulative deviations promptly.
3.4.3 Wall Panel Treatment at Door/Window Openings
- When encountering door/window openings, first measure the opening dimensions, then cut the wall panel to size.
- Install reinforcing columns on the sides of the opening to ensure structural strength.
- Edge-seal the cut panel sections to prevent core material exposure to moisture.
- Secure panels above and below the opening firmly, and reinforce the four corners of the opening to prevent cracking.
3.4.4 Internal/External Corner Treatment
- Install dedicated internal/external corner bead strips at wall corners, made of galvanized steel sheet.
- Apply sealant between the bead strip and wall panels, secure with self-tapping screws at spacing ≤ 300 mm.
- Verticality deviation of corner bead strips ≤ 3 mm/m; surface must be flat with no warping.
3.4.5 Interior Wall Panel Installation
- After exterior wall panels are installed, install interior wall panels (if required) from the interior side.
- Interior panel joints use the same tongue-and-groove insertion method, with uniform gaps and flat surfaces.
- Interior panels must be securely connected to the steel structure frame — no looseness or hollow areas.
- For acoustic insulation requirements, fill soundproofing cotton between interior and exterior wall panels to enhance sound insulation performance.
3.4.6 Wall Installation Quality Standards
| Inspection Item | Standard |
|---|---|
| Wall flatness | ≤ 3 mm / 2 m straightedge |
| Wall verticality | ≤ 3 mm/m |
| Joint gap width | ≤ 1 mm, uniformly consistent |
| Self-tapping screw alignment | Neat, level and plumb, deviation ≤ 2 mm |
| Panel surface | No scratches, dents, or color difference; paint intact |
| Sealing rubber strip | Continuously compressed, no breaks or debonding |
3.5 Roof System Installation
The roof system directly affects waterproofing performance and is a key control point for installation quality. Overlap joints must be tight and waterproofing reliable.
3.5.1 Roof Panel Installation Preparation
- Clean debris from top beam surfaces; check top beam flatness.
- Adhere roof sealing rubber strips onto the top beams, laid continuously along the roof overlap direction.
- Inspect roof panels for deformation or paint damage; verify overlap edges are regular.
3.5.2 Roof Panel Installation Procedure
1. Lay roof panels sequentially from one end of the roof to the other, with overlap direction following the prevailing wind direction.
2. Position the first roof panel, aligning to the frame edge line; adjust flatness.
3. Secure roof panels to roof beams with self-tapping screws — screws installed at the crest positions, complete with waterproof rubber washers.
4. Overlap the second panel onto the first panel, with an overlap width of ≥ 150 mm, embedding waterproof rubber strip into the overlap groove.
5. Compact the overlap seam to ensure tight strip contact, then secure the second roof panel.
6. Continue laying all remaining roof panels; finally install the ridge cap and end edge trim.
3.5.3 Gutter and Downspout Installation
- Install gutters on both sides of top beams, secured with rivets or self-tapping screws at spacing ≤ 300 mm.
- Gutter joint overlap ≥ 50 mm; apply weather-resistant sealant to ensure no leakage.
- Install downspout outlets at gutter ends, with waterproof sealant around the outlet perimeter.
- Install downspouts vertically along columns, with pipe clamps at spacing ≤ 1000 mm, bottom 150 mm above ground.
- Connect downspouts to the ground drainage system, directing rainwater to designated discharge points.
3.5.4 Roof Waterproofing Detail Treatment
- All self-tapping screw locations fitted with waterproof rubber washers; apply sealant over screw heads after tightening.
- Apply sealant at ridge cap overlap joints; install flashing at ridge-to-gable wall intersections.
- Install waterproof sleeves at roof penetrations (e.g., ventilation pipes, chimneys), with weather-resistant sealant applied around the perimeter.
- Apply sealant at gable wall-to-roof intersections for waterproof edge finishing.
3.5.5 Roof Installation Quality Standards
| Inspection Item | Standard |
|---|---|
| Roof panel laying | Flat, no warping or deformation |
| Overlap seams | Straight, consistent overlap width, deviation ≤ 5 mm |
| Gutter installation | Straight, correct slope, no ponding or reverse slope |
| Waterproofing details | Sealed tightly, sealant layer continuous and full, no breaks or bubbles |
| Roof cleanliness | No construction debris, kept clean |
3.6 Door and Window System Installation
3.6.1 Door/Window Installation Preparation
- Check door/window opening dimensions; rectify if deviations exceed tolerance.
- Inspect finished door/window products — frames/sashes free from deformation, glass unbroken, hardware complete.
- Prepare expansion bolts, foam sealant, sealant, wooden wedges, and other installation accessories.
3.6.2 Door Frame/Window Frame Installation
1. Place the door/window frame into the opening, adjusting position for uniform gaps on all sides.
2. Temporarily secure the frame with wooden wedges; adjust verticality and levelness.
3. Check verticality of frame front and side faces — deviation ≤ 2 mm/m; levelness deviation ≤ 2 mm.
4. Secure the frame to the wall frame using expansion bolts, with no fewer than 3 fixing points per side, spacing ≤ 500 mm.
5. Remove wooden wedges after fixing; re-verify installation accuracy.
3.6.3 Gap Filling and Sealing
- Fill gaps between the door/window frame and wall with polyurethane foam sealant — continuous and full.
- After foam cures, trim excess; apply weather-resistant sealant on both interior and exterior sides.
- Apply architectural sealant on the interior side and weather-resistant waterproof sealant on the exterior side, with smooth, straight sealant lines.
- Sealant width ≥ 10 mm, continuous with no breaks, bubbles, or cracking.
3.6.4 Door/Window Sashes and Hardware Installation
- Install door/window sashes; adjust hinges to ensure smooth opening/closing with no binding or abnormal noise.
- Install locks, handles, rollers, wind braces, and other hardware; adjust until smooth operation.
- Install glass and rubber strips — glass evenly supported on all sides, rubber strips seated flat.
- Install screens; verify smooth screen operation and intact mesh.
3.6.5 Door/Window Installation Quality Standards
| Inspection Item | Standard |
|---|---|
| Frame verticality | ≤ 2 mm/m |
| Frame levelness | ≤ 2 mm |
| Sash operation | Smooth opening/closing; airtight when closed, no light or draft penetration |
| Lock operation | Smooth, securely locked |
| Glass/rubber strips | No scratches or bubbles on glass; rubber strips flat, no shedding |
| Sealant | Straight and smooth, firmly bonded to wall |
3.7 Floor System Installation
3.7.1 Substrate Preparation
- Clean debris from the bottom frame; check flatness of bottom frame joists.
- Lay PE moisture barrier — film surface flat, overlap width ≥ 100 mm, seams taped.
- Turn up the moisture barrier 50 mm at the perimeter, pressed against the bottom edge of wall panels.
3.7.2 Load-Bearing Subfloor Installation
- Lay cement fiber subfloor panels, with panel joints aligned to joist centers.
- Secure subfloor to joists with self-tapping screws at 200 – 300 mm spacing; countersink screw heads below the board surface.
- Leave 3 – 5 mm expansion gaps at panel joints; fill gaps with sealant.
- Check flatness after subfloor installation — deviation ≤ 2 mm / 2 m.
3.7.3 Surface Flooring Installation
- Lay PVC flooring or other surface flooring over the subfloor, cut to floor dimensions.
- Flooring joints tight, gap ≤ 0.5 mm, surface flat without blistering.
- Cut flooring neatly at walls and columns with uniform gaps; apply sealant at edges for finishing.
- For anti-static requirements, install anti-static flooring with proper grounding connections.
3.7.4 Floor Installation Quality Standards
| Inspection Item | Standard |
|---|---|
| Floor flatness | ≤ 2 mm / 2 m |
| Flooring condition | No blistering, cracking, or curling edges |
| Joint seams | Straight and uniform, no obvious height difference |
| Surface | Clean, no stains or scratches |
3.8 Interior Partition and Decoration Installation
Based on usage requirements, the container can be fitted with interior partitions, suspended ceilings, decorative moldings, etc., to enhance comfort and aesthetics.
3.8.1 Interior Partition Installation
1. Lay out partition position lines per drawings; ensure accurate positioning.
2. Install partition framing — top and bottom secured to floor and top beam; vertical stud spacing ≤ 600 mm.
3. Install partition wall panels using the same method as interior wall panels; ensure flat and secure.
4. Install door frames at partition door openings, then install door leaves and hardware.
5. Seal the gap between partition top and top beam with sealant.
3.8.2 Suspended Ceiling Installation
1. Install ceiling hanger rods, securely connected to top beams, spacing ≤ 1000 mm.
2. Install main runners and furring channels; adjust for flatness and levelness.
3. Lay ceiling panels with joints aligned to runners; surface flat.
4. Reserve cutouts for light fixtures and ventilation openings with neat cut edges.
5. Install trim molding at ceiling-to-wall junctions for a neat appearance.
3.8.3 Decorative Finishing
- Install skirting boards, crown molding, door/window casings, and other decorative trim.
- Touch up all nail holes with matching paint to the panel surface color.
- Clean interior construction debris; wipe down wall panels, flooring, and glass surfaces.
3.9 Water Supply and Drainage System Installation
Standard-purpose prefabricated containers can be equipped with water supply and drainage systems as required, to meet handwashing, sanitation, and cleaning water needs.
3.9.1 Water Supply System Installation
- Supply pipes use PPR pipe or galvanized steel pipe; pipe diameter designed per water demand.
- Route pipes along the bottom frame or walls; secure firmly with neat arrangement.
- Pipe connections use heat-fusion or threaded connections; joints tight with no leakage.
- Install faucets, angle valves, and inlet flexible hoses at positions meeting usage requirements.
- Install a main shutoff valve on the main supply line for maintenance control.
- Conduct hydrostatic pressure test after installation — test pressure is 1.5× working pressure; hold for 30 minutes; pass criteria: pressure drop ≤ 0.05 MPa.
3.9.2 Drainage System Installation
- Drain pipes use PVC-U drainage pipe, diameter ≥ 50 mm; floor drain pipe diameter ≥ 75 mm.
- Drainage pipe installation slope ≥ 3‰, sloping toward the drainage outlet; no reverse slope.
- Pipe joints bonded with dedicated PVC adhesive; secure and watertight.
- Install floor drains, basin traps, and P-traps; trap seal height ≥ 50 mm to prevent odor backflow.
- Connect drainage outlet to the external drainage system; seal the connection point.
- Conduct water flow test after installation; pass criteria: smooth drainage with no leakage.
3.9.3 Waterproofing Treatment
- Apply waterproofing treatment to wet-area floors, with 2 – 3 coats of waterproof coating.
- Reinforce waterproofing around floor drains and pipe wall penetrations.
- Wall waterproofing upstand height ≥ 300 mm to prevent moisture migration through walls.
3.10 Electrical System Installation
Electrical system installation must be performed by a certified electrician, strictly following electrical construction codes to ensure electrical safety.
3.10.1 Distribution Board Installation
- Install the distribution board on the wall near the entrance, at height 1.4 m, positioned for convenient operation and maintenance.
- Secure the board firmly; verticality deviation ≤ 3 mm.
- All components present: main breaker, branch circuit breakers, and RCDs configured per design.
- Internal wiring neat, circuit labels clear, connections secure.
- Protective earth connection made to the distribution board enclosure.
3.10.2 Conduit and Cable Installation
- Electrical circuits routed through conduits — PVC conduit or galvanized steel conduit.
- Route conduit along walls, ceilings, and under floors; secure firmly with supports at spacing ≤ 1000 mm.
- Use bends or junction boxes at conduit turns; sharp bends strictly prohibited to allow cable pulling and maintenance.
- Circuits of different types or voltage levels must not share the same conduit.
- Seal conduit connections to prevent moisture and dust ingress.
3.10.3 Switch and Socket Installation
- Switch mounting height 1.3 m; socket mounting height 0.3 m; consistent heights within the same premises.
- Socket wiring follows the “left neutral, right live, top earth” principle; connections secure.
- Switches control the phase conductor; lamps are de-energized when switched off.
- High-power equipment (air conditioners, water heaters, etc.) use dedicated 16 A sockets on independent circuits.
- Outdoor sockets are weatherproof type with waterproof boxes.
3.10.4 Lighting System Installation
- Interior lighting uses LED flat panel lights, surface-mounted or recessed into ceiling, with uniform illumination.
- Fixtures securely fixed, wiring correct, switch control mapping accurate.
- Exterior wall lamps and entrance lamps may be added, using weatherproof fixtures.
- Emergency lighting configured as required — automatically illuminates on power failure, duration ≥ 30 minutes.
3.10.5 Earthing System Installation
- The container steel frame structure is reliably connected to the foundation earth electrode, forming an integrated earth system.
- Electrical system protective earth conductors connect to the earth grid; earth resistance ≤ 4 Ω.
- All metal enclosures, distribution boards, and metal conduits are equipotentially bonded.
- Earth main conductors use ≥ 4 mm² copper wire or galvanized flat steel; connections secure.
- Verify earth resistance after installation; add additional earth electrodes if requirements are not met.
3.10.6 Insulation Testing
- Conduct insulation resistance testing after cable installation and before energization.
- Insulation resistance between phase-neutral, phase-earth, and neutral-earth ≥ 0.5 MΩ.
- Only proceed with energization and commissioning after tests pass; rectify any failures identified.
3.11 Ventilation and Air Conditioning System Installation
3.11.1 Natural Ventilation System
- Install ventilation louvers or exhaust fans in walls to create air convection.
- Install insect screens at ventilation openings to prevent insect entry.
- Install exhaust fans at high wall positions or on ceilings; wiring secure, operation stable.
3.11.2 Air Conditioning System Installation
- Install wall-mounted air conditioners at suitable wall positions; drill penetrations clear of structural columns.
- Waterproof-seal wall penetrations for AC piping; install protective sleeves.
- Install outdoor units on outdoor platforms or dedicated brackets; secure firmly.
- Route condensate drainage into the drainage system — uncontrolled dripping prohibited.
- After installation, energize and test cooling and heating performance.
3.11.3 Fresh Air System (Optional)
- Install fresh air unit in the ceiling void or corner; secure firmly with vibration isolation for noise reduction.
- Route fresh air ducting through ceiling space; supply and return air outlets arranged logically.
- Install filters that can be periodically replaced or cleaned.
- Commission fresh air volume to ensure air change rate meets requirements.
3.12 Sealing and Waterproofing System Construction
Sealing and waterproofing are critical processes for preventing leakage and preserving thermal insulation in prefabricated containers. These must be performed throughout the installation process — comprehensively, meticulously, and without omission.
3.12.1 Sealant Selection Requirements
- Exterior joints: neutral silicone weather-resistant sealant — high/low temperature resistance, aging resistance, and excellent waterproofing.
- Interior joints: architectural sealant — environmentally friendly, no odor.
- Sealant must be used within its shelf life; expired product is strictly prohibited.
- Use dedicated sealants for different material contact surfaces to ensure bond strength.
3.12.2 Key Sealing Locations
| Location | Details |
|---|---|
| Wall panel vertical joints | Between wall panels |
| Wall-to-frame horizontal joints | Wall panels to bottom frame / top beam |
| Roof panel overlap seams | Between roof panels |
| Ridge seams | At ridge cap |
| Gutter joints | Gutter sections |
| Door/window frame perimeter | Frame to wall gaps |
| Pipe penetrations | Through walls/floors |
| Internal/external corners | Corner transitions |
| Screw/rivet holes | All fastening points |
| Floor-to-wall junctions | Perimeter sealing |
3.12.3 Sealant Application Procedure
1. Clean joint surfaces of dust, oil, and debris; keep dry and clean before application.
2. For joints ≥ 5 mm wide, insert backing rod to 0.5 – 0.7× joint depth.
3. Apply masking tape along both sides of the joint to ensure straight, neat sealant lines.
4. Extrude sealant continuously and evenly — bead full, no breaks or bubbles.
5. After application, tool the sealant surface smooth and compact to form a smooth rounded profile.
6. Remove masking tape before the sealant cures; avoid touching or water exposure during curing.
7. Sealant width ≥ 8 mm, thickness ≥ 3 mm to ensure effective sealing.
3.12.4 Seal Quality Inspection
- Sealant bead continuous and full — no missed areas, breaks, or bubbles.
- Sealant firmly bonded to both substrate surfaces — no debonding or cracking.
- Sealant surface smooth and straight, aesthetically acceptable.
- For critical locations, conduct water spray testing to verify no leakage.
3.13 Ancillary Structure Installation
3.13.1 Outdoor Corridor and Platform
- Corridor frame bolted to the container bottom frame/columns — secure and reliable.
- Lay corridor flooring — options include checkered steel plate, treated wood, cement board, etc.
- Install corridor guardrails, height ≥ 1.1 m, vertical baluster spacing ≤ 110 mm.
- Corridor floor sloped for drainage to prevent ponding.
3.13.2 Staircase Installation
- Multi-story containers require outdoor staircases; stair tread rise 150 – 170 mm, tread width ≥ 250 mm.
- Staircase reliably connected to container frame and ground foundation — overall stable with no sway.
- Install handrails on both sides of stairs, height ≥ 0.9 m.
- Treat treads with anti-slip finish to prevent slipping in rain or snow.
3.13.3 Canopy/Awning Installation
- Entrance canopy connected to container top beams, projection length 600 – 1000 mm.
- Canopy top sloped for drainage, directing rainwater to both sides.
- Canopy underside flat with neat, tidy edges.
3.13.4 Ladder and Access Platform
- Roof access ladder installed along columns, fixed securely with rung spacing of 300 mm.
- Ladders exceeding 2 m in height require safety hoops for climbing safety.
3.14 Finished Product Protection During Installation
- Avoid impacts and scratches to panels, doors, and windows during transport and installation; keep protective film on surfaces until handover.
- Personnel must not walk or step on installed roof panels; lay walk boards where access is required.
- Protect electrical and plumbing fittings after installation from dust and cement ingress.
- Protect uncured sealant from dust contamination and external damage.
- Keep interior clean after decorating; smoking and littering strictly prohibited inside.
- Coordinate processes during concurrent operations to prevent damage to completed work by subsequent trades.
Chapter 4 System Commissioning and Performance Testing
4.1 Pre-Commissioning Preparation
4.1.1 Commissioning Team Organization
Form a commissioning team led by the technical director as team leader, with members comprising installation foreman, electrician, plumber, and quality inspector. All commissioning personnel must be familiar with system principles and commissioning methods, with clearly defined responsibilities.
4.1.2 Commissioning Tools Preparation
Prepare required tools and instruments: multimeter, megger, earth resistance tester, clamp meter, water pressure gauge, tape measure, straightedge, feeler gauge, flashlight, water testing container, thermometer, anemometer, etc. Verify instrument calibration accuracy and validity periods.
4.1.3 Site Condition Confirmation
- Main installation 100% complete, all processes self-inspected and accepted.
- Site cleaned of construction debris; access paths unobstructed.
- Utilities connected — stable supply voltage, normal water pressure.
- Doors and windows operating normally; passageways clear; emergency exits unobstructed.
- Commissioning area marked with warning signs; unauthorized personnel prohibited.
4.1.4 Technical Documentation Verification
Verify construction drawings, product manuals, equipment certificates, and installation records to confirm system configuration matches design. Contact factory technical support at +86 13538869979 for confirmation if questions arise.
4.2 Structural Stability Commissioning and Testing
4.2.1 Frame Dimension Re-Verification
- Re-measure overall container length, width, and height; compare with design values — deviation ≤ 10 mm.
- Measure wall and roof diagonals — diagonal difference ≤ 5 mm.
- Inspect all connection bolts — spot-check 10% for torque; bolt torque meets design requirements, no loosening.
4.2.2 Verticality and Levelness Testing
| Item | Standard |
|---|---|
| Column verticality | Theodolite or laser plumb — deviation ≤ H/1000, and ≤ 5 mm |
| Overall wall verticality | ≤ 5 mm full height |
| Bottom frame and top beam levelness | ≤ 3 mm |
| Floor flatness | ≤ 3 mm / 2 m |
4.2.3 Structural Connection Inspection
- All bolted connections complete with washers and nuts — no missing items.
- Welded joints full — no porosity, slag inclusion, or cracks; anti-corrosion treatment in place.
- No significant deformation, bending, or denting of members; structure carries loads normally.
- Container-to-foundation connections secure; anchor bolts not loose.
- Multi-story stacked containers properly connected top-to-bottom; no deformation of connection hardware.
4.2.4 Static Load Test (Optional)
- When required for important projects or by design, conduct floor/roof static load testing.
- Evenly distribute ballast per design load; hold for 24 hours.
- Observe structural deflection; verify rebound meets requirements after unloading.
- Pass criteria: no permanent deformation, connection loosening, or member cracking.
4.3 Waterproofing and Sealing Commissioning Testing
Waterproofing performance is a core performance indicator for prefabricated containers. Every unit must be tested to ensure there are no leakage risks.
4.3.1 Roof Water Spray Test
- Use artificial water spray or natural rainfall to test roof waterproofing.
- Spray duration no less than 2 hours, with spray intensity simulating moderate to heavy rain.
- During spraying and within 1 hour after completion, inspect interior ceiling, wall panel tops, and door/window tops for any leakage or water stains.
- Focus on ridge, overlap seams, gutters, downspout outlets, penetration perimeters, and other detail locations.
4.3.2 Wall Water Spray Test
- Conduct water spray testing on exterior wall joints and around doors/windows for no less than 1 hour.
- Inspect corresponding interior locations for water penetration or dampness.
- Focus on wall panel vertical joints, internal/external corners, door/window frame perimeters, and pipe wall penetrations.
4.3.3 Gutter Water Retention Test
- Plug gutter downspout outlets; fill gutter with water to submerge the gutter bottom.
- After 24-hour retention, inspect gutter joints and gutter-to-wall connections for leakage.
- Inspect downspout connections for leakage; verify drainage flows freely.
4.3.4 Wet Area Water Retention Test
- Conduct water retention tests in wet areas (bathrooms, pantry areas, etc.); water depth 20 – 30 mm.
- After 24-hour retention, inspect below and surrounding walls for leakage.
- Verify floor drains drain freely with no ponding.
4.3.5 Leak Remediation Requirements
- Mark leak points; analyze leakage causes and formulate remediation plans.
- Common leakage causes: missed sealant application, sealant cracking, inadequate overlap, unsealed screw holes, etc.
- Re-test with water spray/retention after remediation until no leakage.
- All leak remediation records filed into as-built documentation.
4.4 Electrical System Commissioning
Electrical system commissioning must be performed by a certified electrician, strictly observing electrical safety regulations. Always test de-energized first, then energize for commissioning.
4.4.1 Pre-Energization Testing
- Insulation resistance test: Measure insulation resistance between phase, neutral, and earth conductors of each circuit using 500 V megger — resistance ≥ 0.5 MΩ.
- Earth resistance test: Measure system earth resistance with earth resistance tester — resistance ≤ 4 Ω.
- Circuit continuity test: Verify each circuit for normal continuity; no short circuits or open circuits.
- Component inspection: Verify distribution board breakers and RCDs match specified models and ratings; connections secure.
- Phase sequence check: For three-phase supply systems, verify correct phase sequence.
4.4.2 Distribution Board Commissioning
1. Close main breaker; verify incoming voltage normal — 220 V system within ±10% tolerance.
2. Close each branch circuit breaker sequentially; verify output voltage at outgoing terminals normal.
3. Test RCDs: press test button — RCD must trip immediately; trip current ≤ 30 mA; trip time ≤ 0.1 s.
4. Verify breaker labels correspond correctly to circuits; labels clear.
4.4.3 Lighting System Commissioning
- Energize lighting circuits; test each luminaire switch individually — all fixtures illuminate normally.
- Check lighting uniformity; no flickering or abnormal noise.
- Test switch-to-fixture control mapping; switches control phase conductors — fixtures de-energized when off.
- Emergency lighting test: disconnect main supply — emergency lighting automatically illuminates for required duration.
4.4.4 Socket Circuit Commissioning
- Test each socket with socket tester — correct wiring (left neutral, right live, top earth); no reversed or missing earth.
- Connect test load; socket supplies power normally, voltage stable.
- Test high-power sockets with load — normal operation, no conductor heating.
- Test outdoor weatherproof sockets — waterproof covers intact, power supply normal.
4.4.5 No-Load and Loaded Operation
- Energize all circuits no-load for 2 hours; inspect distribution board and conductors for abnormal heating.
- Gradually add load to design rated load; operate for 4 hours; verify conductor and breaker temperatures normal.
- Measure each circuit current with clamp meter — current not exceeding rated value.
- No tripping, abnormal noise, or odor during operation.
4.4.6 Electrical Commissioning Acceptance Standards
- All luminaires, sockets, and switches operate normally with accurate control.
- Insulation and earth resistance meet code requirements.
- RCDs operate sensitively and reliably.
- Stable operation under load; no abnormal heating of conductors or components.
- Distribution board labels clear; wiring neat.
4.5 Water Supply and Drainage System Commissioning
4.5.1 Water Supply System Commissioning
1. Open the main inlet valve; fill slowly to purge air from pipes.
2. Inspect all connections, valves, and faucets for leakage.
3. Verify outlet pressure; smooth water flow meeting usage requirements.
4. Operate each faucet and angle valve individually — smooth opening/closing, no dripping.
5. Hydrostatic pressure test re-verification: hold at system working pressure for 2 hours — pressure drop ≤ 0.02 MPa, no leakage.
4.5.2 Drainage System Commissioning
- Introduce water to each drainage point; verify drainage speed — smooth flow with no blockage.
- Check P-trap seals intact; no odor backflow.
- Inspect all pipe joints and floor drain perimeters for leakage.
- Verify outdoor drain discharge is clear with no backflow.
- Continuous water flow test for 30 minutes; pass criteria: no blockage or leakage.
4.5.3 Water-Using Equipment Commissioning
- For units with water heaters, wash basins, toilets, etc., commission each item individually.
- Equipment water inlet/outlet functioning normally; features operating correctly.
- Equipment grounding connections reliable; electrical safety confirmed.
4.6 Door/Window and Ventilation System Commissioning
4.6.1 Door/Window Commissioning
- Operate door/window sashes at least 10 times — smooth operation, no binding or abnormal noise.
- When closed, check sealing — uniform gaps, no obvious light penetration.
- Test locks and handles — smooth operation, secure locking.
- For sliding windows: test rollers run smoothly; limit stops effective.
- For casement windows: test wind braces hold firmly; opening angle appropriate.
4.6.2 Ventilation System Commissioning
- Operate exhaust fans — stable running, no abnormal noise or vibration.
- Measure outlet air velocity; air volume meets design requirements.
- Check louvers operate freely with smooth adjustment.
- For fresh air systems: verify balanced air volume at each outlet; air change rate meets requirements.
4.6.3 Air Conditioning System Commissioning
- Operate cooling and heating modes separately for 30 minutes.
- Verify indoor temperature changes; cooling/heating performance normal.
- Check AC operating noise meets requirements; no abnormal vibration.
- Condensate drains freely with no dripping.
4.7 Overall Performance Testing
4.7.1 Thermal Insulation Performance Testing
- In winter or summer, conduct indoor/outdoor temperature differential testing to evaluate insulation effectiveness.
- With doors/windows closed and AC off, indoor temperature change rate meets thermal insulation design requirements.
- Inspect wall panels, roof, and doors/windows for cold bridge condensation.
4.7.2 Acoustic Insulation Performance Testing
- Play fixed noise outdoors; measure indoor noise levels; calculate sound insulation value.
- Wall airborne sound insulation ≥ 30 dB for acceptance.
- Good sound insulation with doors/windows closed; no obvious sound transmission gaps.
4.7.3 Fire Performance Verification
- Verify fire rating certificates for wall panels, ceiling materials, etc.; conform to design requirements.
- Check electrical conductors are conduit-protected — no exposed wiring.
- Verify fire-fighting equipment is complete; extinguisher types and quantities meet requirements.
- Emergency exits clear; evacuation signage legible.
4.8 Comprehensive Safety Inspection
| Category | Requirements |
|---|---|
| Structural safety | Overall stability; no loosening or deformation; edge protection in place |
| Electrical safety | Standard wiring; RCD effective; earthing reliable; no unauthorized connections |
| Fire safety | Fire-rated materials compliant; fire-fighting equipment available; access unobstructed |
| Use safety | Door/window hardware secure; glass unbroken; floor slip-resistant; no sharp protrusions |
| Lightning protection | Tall containers have lightning protection earthing compliant; earth resistance qualified |
4.9 Commissioning Records and Documentation Filing
- Fill in all commissioning records truthfully during commissioning; data accurate.
- Record issues identified during commissioning and rectification status, with before/after comparison.
- Compile all commissioning documentation after completion, including structural test records, waterproofing test records, electrical commissioning records, water supply/drainage commissioning records, etc.
- Commissioning records signed by commissioning personnel and quality inspector; included in completion acceptance documentation.
- Issue commissioning acceptance report after passing; submit acceptance application.
- For on-site commissioning guidance from factory technicians, call KITOZER (Guangdong Lain Intelligent System Development Co., Ltd.) technical support hotline +86 13538869979 to schedule service.
Chapter 5 Engineering Acceptance and Handover for Use
5.1 Acceptance Basis and Standards
Prefabricated container installation engineering acceptance is performed strictly in accordance with relevant national codes, construction drawings, contract requirements, and the standards of this manual. Primary acceptance basis includes:
- 《Standard for Quality Acceptance of Steel Structure Engineering》GB 50205-2020 (Standard for Quality Acceptance of Steel Structure Engineering)
- 《Code for Acceptance of Construction Quality of Building Electrical Engineering》GB 50303-2015 (Code for Acceptance of Construction Quality of Building Electrical Engineering)
- 《Code for Acceptance of Construction Quality of Water Supply, Drainage and Heating Engineering》GB 50242-2002 (Code for Acceptance of Construction Quality of Water Supply, Drainage and Heating Engineering)
- 《Standard for Quality Acceptance of Building Decoration Engineering》GB 50210-2018 (Standard for Quality Acceptance of Building Decoration Engineering)
- 《Technical Standard for Prefabricated Steel Structure Buildings》GB/T 51232-2016 (Technical Standard for Prefabricated Steel Structure Buildings)
- Construction drawings, design changes, technical consultation documents
- Product factory certificates, material test reports
- Quality requirements specified in this installation and commissioning manual
5.2 Acceptance Classification and Procedure
Acceptance is conducted at three levels: sub-item engineering acceptance, sub-division engineering acceptance, and completion acceptance. Each level must pass before proceeding to the next.
5.2.1 Sub-Item Engineering Acceptance
Upon completion of each sub-item work, the construction unit performs self-inspection, then submits for acceptance to the supervisor/owner. Sub-items include: foundation works, frame installation, wall installation, roof installation, door/window installation, floor installation, electrical installation, water supply/drainage installation, waterproofing works, etc.
Sub-item acceptance content:
- All inspection batches within the sub-item pass
- Quality control documentation complete
- Visual quality meets requirements
- Safety and function tests pass
5.2.2 Sub-Division Engineering Acceptance
After all sub-item acceptances pass, conduct sub-division engineering acceptance — the overall prefabricated container installation sub-division acceptance. Organized by the project chief supervision engineer or owner’s project manager, attended by the construction unit project manager and technical director.
Sub-division acceptance content:
- All sub-items passed
- Quality control documentation complete
- Safety and function test documentation complete
- Visual quality acceptance passed
5.2.3 Completion Acceptance
After all work is completed, the construction unit self-inspection passes, and the completion report with complete as-built documentation is submitted, organize completion acceptance. Organized by the owner, with design, supervision, construction, and factory units jointly participating.
Completion acceptance procedure:
1. Construction unit submits completion acceptance application and as-built documentation
2. Acceptance team reviews as-built documentation for completeness
3. On-site physical inspection — groups inspect quality of each section
4. Compile acceptance opinions; propose issues requiring rectification
5. Construction unit rectifies issues and undergoes re-inspection
6. Acceptance passed; sign completion acceptance form
5.3 On-Site Physical Acceptance Key Points
5.3.1 Appearance and Structure Acceptance
- Container overall level and plumb; clean appearance; uniform color.
- Wall panels free of scratches, dents, or deformation; joints uniform and straight.
- Roof flat; corrugations straight; no warping or damage.
- Door/window surfaces clean; glass intact; hardware complete.
- Floor flat; no blistering, cracking, or stains.
- Internal/external corners straight; decorative trim aesthetically acceptable.
- Bolts and screws neatly arranged with anti-corrosion treatment in place.
5.3.2 Waterproofing Acceptance
- Review water spray and retention test records — tests passed.
- On-site inspection: no water penetration traces on interior ceilings, walls, or around doors/windows.
- Gutters and downspouts drain freely; no ponding or leakage.
- Sealant continuous and full; firmly bonded; no cracking.
- Wet areas free of leakage; floor drains drain freely.
5.3.3 Electrical Acceptance
- Distribution boards securely mounted; wiring neat; labels clear.
- All luminaires, switches, and sockets operate normally; positions accurate.
- RCD and earth protection reliable; tests passed.
- Conductor installation compliant; no exposed or unauthorized wiring.
- Insulation resistance and earth resistance test records passed.
5.3.4 Water Supply/Drainage Acceptance
- Water supply flow smooth; pressure normal; no leakage.
- Drainage smooth; no blockage or leakage.
- Valves operate freely; no dripping.
- Sanitary fixtures securely installed; functions normal.
- Hydrostatic pressure test and water flow test records passed.
5.3.5 Usage Function Acceptance
- Doors/windows open and close freely; good sealing; locks function normally.
- Ventilation and AC equipment operate normally with effective performance.
- Interior partitions and ceilings secure and flat.
- Ancillary structures (stairs, corridors, canopies) stable and safe.
- Overall usage function meets design and contract requirements.
5.4 As-Built Documentation Checklist
Complete as-built documentation must be submitted for acceptance, including but not limited to:
- Project completion report
- Construction organization design and construction plan
- Drawing review and technical disclosure records
- Material/equipment factory certificates, test reports, incoming inspection records
- Sub-item and sub-division engineering acceptance records
- Concealed works acceptance records
- Structural test records, commissioning test records
- Waterproofing test records, electrical commissioning records, water supply/drainage commissioning records
- Design change and technical consultation documents
- As-built drawings
- Quality accident handling records
- After-sales service and warranty documents
5.5 Handover and Usage Training
After acceptance passes, conduct handover training to the user unit to ensure operating personnel can correctly use and maintain the container.
5.5.1 Training Content
| Topic | Details |
|---|---|
| Container structure and system overview | Basic configuration and components |
| Door/window usage | Correct operation and precautions |
| Electrical system usage | Distribution board operation, electrical safety requirements |
| Water supply/drainage usage | Winter freeze protection, routine drain clearing |
| AC/ventilation equipment | Operation and simple maintenance |
| Daily inspection points | Routine checks and common minor issue handling |
| Prohibited actions | No unauthorized structural modification, no overload, no heavy impact on walls, etc. |
| After-sales service | Process and contact information |
5.5.2 Training Format
Use a combination of on-site explanation and hands-on demonstration to train the user’s management and maintenance personnel until they are proficient in basic operations and routine maintenance. Sign a training confirmation form after training.
5.6 Warranty and After-Sales Service
5.6.1 Warranty Period
For prefabricated containers manufactured by Guangzhou Lain Intelligent System Development Co., Ltd.:
| Item | Warranty Period |
|---|---|
| Main steel structure | 1 year — free repair for non-artificial quality issues |
| Wearing parts (sealant, hardware, electrical components) | 6 months |
| Technical support and repair services | Lifetime |
5.6.2 Warranty Coverage
Covered: Failures and damage caused by inherent product quality issues during the warranty period — free repair and replacement.
Not covered by warranty:
- Damage from human misuse or improper use
- Damage from unauthorized structural or system modification
- Damage from natural disasters or accidents
- Normal wear and appearance aging from regular use
- Damage from repairs by non-factory personnel
5.6.3 Service Response
| Service | Details |
|---|---|
| Service hotline | +86 13538869979 (WeChat same number), weekdays 8:00 – 18:00 |
| Technical support | +86 13538869979, 24-hour technical consultation |
| Response time | Solution within 2 hours of repair request; on-site service within 24 hours in Pearl River Delta region, within 48 hours in other regions |
| Website | https://gdlain.com — online service requests and product documentation download |
5.6.4 Value-Added Services
- Regular return visits and inspection services to proactively identify issues.
- Relocation, disassembly, and reinstallation services.
- Upgrade and modification services — adding partitions, replacing doors/windows, adding equipment, etc.
- Genuine parts supply services — factory components ensure compatibility.
Chapter 6 Routine Maintenance and Periodic Servicing
6.1 General Maintenance Principles
Good routine maintenance and periodic servicing effectively extend the service life of prefabricated containers, maintain good performance, and reduce failure rates. The user unit should establish a maintenance system, designate responsible personnel, and carry out regular inspections and servicing.
Maintenance should follow the principle of “prevention first, regular inspection, timely repair, safety foremost.” Address problems promptly to prevent minor issues from escalating. Structural and electrical repairs must be performed by qualified professionals; unauthorized modification is strictly prohibited.
6.2 Routine Inspection Content and Frequency
Establish a tiered inspection mechanism with five levels: daily, weekly, monthly, quarterly, and annual inspections.
6.2.1 Daily Inspection (Performed by User Personnel)
- Check doors/windows intact; verify normal opening/closing; locks undamaged.
- Check interior for water leakage or seepage traces — especially after rainy days.
- Check lighting and sockets function normally; no odor or abnormal noise.
- Check floors for standing water or debris; keep interior clean.
- Check fire-fighting equipment in place and functional.
- Close doors/windows and cut non-essential power before leaving at end of day.
6.2.2 Weekly Inspection (Performed by Maintenance Personnel)
- Check roof for debris accumulation; gutters and downspouts for blockage.
- Check exterior wall panels for damage or deformation; sealant for cracking.
- Check distribution board operation; no heating or abnormal noise.
- Check water supply/drainage for leakage; drainage flowing freely.
- Check staircases, corridors, guardrails, and other ancillary structures for loosening.
- Clean roof and surrounding debris; maintain drainage paths.
6.2.3 Monthly Inspection (Performed by Maintenance Supervisor)
- Check structural connection bolts for loosening — focus on corners and joints.
- Check steel structure anti-corrosion condition; rust or galvanizing loss.
- Comprehensively inspect all sealant; repair cracked or detached areas promptly.
- Test earth resistance and RCD function to ensure electrical safety.
- Inspect door/window hardware; lubricate and adjust opening/closing smoothness.
- Check ventilation equipment operation; clean filters.
6.2.4 Quarterly Inspection (Performed by Qualified Professionals)
- Comprehensively inspect structural stability; measure verticality and settlement.
- Inspect overall roof waterproofing condition; perform water spray sampling tests at critical joints.
- Check electrical conductor aging; tighten terminal connections.
- Check water supply/drainage pipes for scaling or blockage; clear as needed.
- Check insulation for moisture damage or detachment; wall panels for hollow areas.
- Verify fire-fighting equipment effectiveness; replace expired extinguishers.
6.2.5 Annual Comprehensive Overhaul (Performed by Factory or Professional Team)
- Comprehensive structural inspection — full bolt re-tightening, structural deformation assessment.
- Comprehensive steel anti-corrosion inspection — rust removal and touch-up painting.
- Comprehensive roof and wall waterproofing inspection — replace all aged sealant.
- Comprehensive electrical system testing — insulation test, earth test, replacement of aged wiring.
- Comprehensive door/window adjustment and servicing — replace aged rubber strips and hardware.
- Comprehensive water supply/drainage cleaning and pressure testing — replace aged seals.
- Issue annual inspection report with maintenance recommendations for the following year.
6.3 Main Structure System Maintenance
6.3.1 Bolt Tightening
Periodically inspect all connecting bolts and promptly retighten any that are found loose.
High-strength bolts shall be tightened to the specified torque; do not overtighten or undertighten.
Bolts with severe corrosion shall be replaced promptly, and anti-rust grease shall be applied during replacement.
A comprehensive bolt retightening inspection shall be performed at least once a year.
6.3.2 Steel Structure Anti-Corrosion Maintenance
Periodically inspect the galvanized coating or paint finish on the steel structure surface; promptly address any damage or corrosion found.
Minor corrosion: remove rust, apply two coats of anti-rust primer, then apply finish paint.
Small areas of damaged galvanized coating: apply galvanizing repair paint.
Areas with severe corrosion require structural strength assessment; reinforcement or replacement shall be carried out as necessary.
In coastal or highly corrosive environments, increase the frequency of anti-corrosion inspections and perform anti-corrosion treatment every six months.
6.3.3 Structural Deformation Monitoring
Periodically observe the overall unit for any tilting or deformation; promptly investigate the cause if any abnormality is found.
For multi-layer stacked units, pay particular attention to the deformation of the bottom frame structure.
After extreme weather events such as strong winds, heavy rain, or blizzards, conduct a special inspection of structural safety.
If abnormal structural deformation, weld cracking, or other issues are found, immediately cease use and contact professionals for evaluation and handling. Technical consultation: +86 13538869979.
6.3.4 Foundation Maintenance
Periodically inspect the foundation for settlement or cracking; promptly address any uneven settlement found.
Maintain proper drainage around the foundation to avoid prolonged water accumulation soaking the foundation.
Periodically derust and oil foundation anchoring bolts to prevent them from seizing.
6.4 Enclosure Wall and Roof System Maintenance
6.4.1 Wall Panel Maintenance
Keep wall panel surfaces clean; wipe off dust and stains with a neutral cleaning agent. The use of strong acids or alkalis for cleaning is strictly prohibited.
Avoid impact from hard objects on wall panels; promptly repair small areas of denting or paint peeling.
Periodically inspect the sealant at wall panel joint seams; reapply sealant promptly where aging or cracking is found.
Avoid moisture soaking on interior wall panels; if water stains or mold appear, promptly identify the water source and address it.
The core material of sandwich panels must never be exposed to water ingress. Once water enters, the thermal insulation and fire resistance performance will degrade, and the panels must be replaced promptly.
6.4.2 Roof Maintenance
Periodically clear debris, leaves, and dust from the roof to keep it clean and prevent corrosion of the paint finish.
It is strictly prohibited to stack heavy objects on the roof, and frequent foot traffic on the roof is forbidden.
Periodically inspect waterproofing details such as roof panel lap joints, ridges, and gutters; promptly repair any leaks found.
Clear snow from the roof promptly during the snow season to avoid structural deformation caused by excessive load.
Before the rainy season each year, conduct a comprehensive roof waterproofing inspection, clear gutters and downspouts, and ensure proper drainage.
6.4.3 Door and Window System Maintenance
Keep doors and windows clean; clean glass with glass cleaner and avoid scratching with hard objects.
Periodically inspect door and window sealing strips; replace promptly when aging, hardening, or cracking is found to ensure sealing performance.
Periodically apply lubricating oil to hardware such as hinges, rollers, and locks to maintain smooth opening and closing.
Periodically clean debris from sliding window tracks to maintain smooth sliding operation.
Close and lock doors and windows promptly during strong wind weather to prevent wind damage.
Replace glass promptly when cracks appear to prevent injury from shattering.
6.4.4 Floor System Maintenance
Keep the floor clean and dry; wipe up standing water promptly to avoid prolonged soaking.
Avoid scratching the floor with sharp objects; avoid dragging heavy items during transport.
PVC flooring shall be waxed and maintained periodically to maintain gloss and wear resistance.
Repair or replace floor sections promptly when bubbling or cracking occurs.
Hot work directly on the floor is strictly prohibited to prevent burning the floor.
6.5 Electromechanical System Maintenance and Servicing
6.5.1 Electrical System Maintenance
Routine Maintenance
Keep the distribution box clean and dry; stacking of debris or obstruction around it is strictly prohibited.
Overloading is strictly prohibited; the unauthorized addition of high-power equipment is strictly prohibited.
Periodically check switches and sockets for heating or abnormal noise; promptly cut off power and perform repairs if any issue is found.
Press the test button on the residual current circuit breaker once a month to confirm normal operation.
Periodic Servicing
Tighten wiring terminals once per quarter to prevent loosening and heating.
Test insulation resistance and grounding resistance once per year to ensure electrical safety.
Inspect wiring for aging; replace aging wiring promptly.
Replace damaged lamps and switches promptly with accessories of the same specification.
Safety Precautions
Electrical repairs must be carried out by a certified electrician; cut off power before performing any work.
Take precautions against electric shock when using electricity in humid environments.
During thunderstorms, turn off the main power supply and unplug electrical appliances.
6.5.2 Water Supply and Drainage System Maintenance
Routine Maintenance
Take anti-freeze precautions in winter; drain water from pipelines when the unit is out of service in low-temperature environments.
Dumping debris or grease into drainage outlets is strictly prohibited to prevent clogging.
Periodically check faucets and valves; promptly replace seals when dripping or leaking is found.
Periodic Servicing
Inspect pipe connections once per quarter; promptly address any leaks found.
Clear drainage lines once every six months to prevent siltation and clogging.
Flush the water supply pipes once per year to maintain water quality.
Drain all water from the pipes and close the main water inlet valve before prolonged shutdown.
6.5.3 Ventilation and Air Conditioning System Maintenance
Clean the filters of exhaust fans and fresh air systems periodically; excessive dust accumulation will affect airflow.
Clean air conditioning filters once per month to maintain cooling and heating performance.
Perform comprehensive servicing on the air conditioner once each season change, including cleaning the heat exchanger.
If abnormal noise or odor occurs during equipment operation, stop the unit promptly and contact professionals for repair.
When equipment is not in use for extended periods, provide dust protection and power on periodically for dehumidification.
6.6 Seasonal Maintenance Points
6.6.1 Rainy Season Maintenance
Before the rainy season, conduct a comprehensive waterproofing inspection, reapply sealant, and clear gutters and downspouts.
Strengthen inspections during rainy weather, focusing on the roof, doors, windows, and walls for any leaks.
After rain, promptly clear standing water and debris from the roof to maintain proper drainage.
Check the moisture protection of electrical wiring to prevent short circuits caused by dampness.
6.6.2 Winter Maintenance
Take anti-freeze measures before winter; wrap insulation material around water supply and drainage pipes.
In low-temperature environments, maintain an appropriate indoor temperature when the unit is unoccupied to prevent pipe freezing and cracking.
Drain all water from pipes for units that will be out of service for extended periods.
Clear snow from the roof promptly after snowfall to reduce structural load.
Check door and window sealing; replace strips where drafts are found to improve insulation.
6.6.3 Summer High-Temperature Maintenance
Check ventilation and air conditioning equipment to ensure normal operation and prevent excessive indoor heat.
Check heat dissipation of electrical equipment to avoid high-temperature overload and tripping.
Check sealant for melting or cracking under high temperatures; reapply promptly.
Provide sun protection to avoid accelerated aging of wall panels, doors, and windows from prolonged exposure.
6.6.4 Strong Wind Weather Maintenance
Before a strong wind warning, close and lock doors and windows and retrieve any outdoor items that could be blown away.
Check the unit anchoring and connection of auxiliary structures for security.
After strong winds, conduct a comprehensive inspection of the structure, roof, doors, and windows for any damage.
6.7 Common Wear and Tear Repair Methods
6.7.1 Minor Paint Finish Damage Repair
Sand the damaged area to remove rust and loose paint.
Wipe clean and apply one coat of anti-rust primer.
After the primer dries, apply two coats of finish paint with color as close to the original as possible.
For small areas, spray paint may be used for convenient touch-up.
6.7.2 Minor Wall Panel Dent Repair
For minor dents, gently tap from the interior side with a rubber mallet to restore the shape.
Repair damaged paint finish using the method described above.
For deeper dents or panel damage, replace the wall panel locally or apply decorative panels to cover.
6.7.3 Sealant Cracking Repair
Use a utility knife to remove aged and cracked old sealant.
Clean dust and grease from the joint surface, keeping it dry and clean.
Apply new weather-resistant sealant, smooth and compact it.
Avoid touching or exposure to water before the sealant cures.
6.7.4 Minor Leak Repair
Locate the leak point and clean the surface.
For roof leaks, apply waterproof membrane or brush on waterproof coating.
For joint leaks, reapply sealant.
After treatment, perform a water spray test to verify the repair effectiveness.
6.8 Long-Term Storage and Relocation Precautions
6.8.1 Long-Term Storage Requirements
The storage site shall be level, dry, well-ventilated, with good surrounding drainage.
Raise the unit off the ground with supports to avoid direct contact with the ground and moisture.
Close doors and windows; protect against dust, moisture, and pests.
Cut off the main water and power supply; drain all water from the pipes.
Perform a monthly inspection; promptly address any issues found.
Storing flammable or explosive materials around the stored unit is strictly prohibited.
6.8.2 Relocation and Disassembly Precautions
Relocation and disassembly shall be carried out by a professional team, following the reverse order of installation.
Disconnect all water and electrical connections and drain all pipes before disassembly.
Protect components during disassembly to avoid collision and deformation.
Sort and package components by category; pack hardware fittings in separate boxes to avoid loss.
Protect the units during transport; place panels vertically and use timber spacers between frames.
For reinstallation, follow the specifications in this manual; replace aged sealant and sealing strips.
For professional relocation and installation services, contact our service hotline: +86 13538869979.
Chapter 7 Common Faults and Solutions
7.1 Structural Common Faults
7.1.1 Loose Connecting Bolts
Fault Symptom: Slight wobbling of the frame, enlarged joint gaps, bolts can be turned by hand.
Causes: Long-term vibration, temperature fluctuations, inadequate initial tightening.
Solution: Retighten bolts to the specified torque with a wrench, tightening diagonally and evenly; perform a comprehensive retightening once per year; install anti-loosening washers in frequently vibrating environments.
Precautions: Loose bolts in multi-layer units must be addressed promptly to avoid compromising overall structural safety.
7.1.2 Slight Column Tilting
Fault Symptom: Column verticality exceeds tolerance, unit appears tilted.
Causes: Uneven foundation settlement, inadequate alignment during installation, excessive lateral force.
Solution: Check foundation settlement conditions; if a foundation issue exists, first reinforce the foundation; adjust the bottom frame shims to correct verticality; add diagonal bracing for lateral reinforcement; severe tilting requires evaluation and handling by professionals.
7.1.3 Steel Structure Corrosion
Fault Symptom: Rust spots and patches on steel structure surfaces, paint blistering and peeling.
Causes: Damaged anti-corrosion coating, humid environment, coastal salt spray corrosion.
Solution: For minor corrosion, derust and apply anti-rust paint; for severe corrosion, replace the affected components; in coastal environments, increase anti-corrosion coating thickness and perform regular anti-corrosion maintenance.
7.1.4 Floor Noise and Indentation
Fault Symptom: Floor makes noise when walked on, local indentations appear.
Causes: Excessive spacing between floor supports, floor deformation due to moisture, excessive local loading.
Solution: Add secondary support beams underneath; replace moisture-deformed floor panels; avoid excessive concentrated loads; ensure the floor substrate is level.
7.2 Waterproofing and Leakage Common Faults
7.2.1 Roof Leakage
Fault Symptom: Dripping or dampness on the interior ceiling on rainy days, typically at lap joints and gutters.
Causes: Sealant aging and cracking, stripped sealing tape at lap joints, failed screw hole waterproofing, clogged gutters with standing water.
Solution: Clear debris from gutters and unclog downspout openings; remove and reapply sealant at cracked joints; reapply sealant at screw holes; for large-area leaks, apply a layer of waterproof membrane.
7.2.2 Wall Panel Joint Leakage
Fault Symptom: Water intrusion and dampness at vertical wall panel joints on rainy days.
Causes: Poor panel joint fit, missing or cracked sealant, detached sealing strips.
Solution: Adjust wall panel gaps to be even; apply sealant from the interior side; reapply weather-resistant sealant from the exterior; replace damaged sealing strips.
7.2.3 Door and Window Perimeter Leakage
Fault Symptom: Rainwater penetrates around door and window frames into the interior.
Causes: Cracked perimeter sealant, inadequate foam filling, reverse slope on window sills.
Solution: Remove old sealant and reapply weather-resistant sealant; apply construction sealant on the interior side; create a slope on window sills to direct water outward.
7.2.4 Pipe Penetration Leakage
Fault Symptom: Water leaks where pipes pass through walls or the roof.
Causes: Inadequate waterproof sealing, aged sealant.
Solution: Install waterproof pipe sleeves; reapply sealant around penetrations; install flashing caps at roof openings.
7.2.5 Floor Water Seepage in Wet Areas
Fault Symptom: Water seeps from bathroom or pantry floors to surrounding areas or floors below.
Causes: Damaged waterproofing layer, failed sealing around floor drains.
Solution: Locally redo the waterproofing layer; reapply waterproof sealant around floor drains; for severe cases, remove floor tiles and redo the full waterproofing.
7.3 Electrical Common Faults
7.3.1 Main Breaker Tripping
Fault Symptom: Main breaker trips immediately when closed, or trips suddenly during use.
Causes: Short circuit, overload, leakage, or faulty breaker.
Solution:
First disconnect all branch circuits and close them one by one to identify the faulty circuit.
Short circuit: inspect for damaged wiring or short circuits at connections; repair before closing the breaker.
Overload: reduce electrical load or replace with a higher-capacity breaker and wiring.
Leakage: use a megger to locate the leakage point, focusing on damp areas.
Faulty breaker: replace with a breaker of the same specification.
Precautions: Electrical faults shall be diagnosed by a certified electrician. Forcibly closing the breaker is strictly prohibited.
7.3.2 No Power at Socket
Fault Symptom: One or multiple sockets have no power while other circuits work normally.
Causes: Corresponding branch circuit breaker tripped, loose socket wiring, damaged socket.
Solution: Check the corresponding branch breaker in the distribution box and reset if tripped; open the socket and check wiring, retighten if loose; replace the socket if damaged.
7.3.3 Light Not Working
Fault Symptom: Light does not illuminate or flickers.
Causes: Burnt-out bulb/LED module, faulty switch, loose wiring, circuit power failure.
Solution: First check whether the switch is working and whether the circuit is energized; replace the damaged light source; reconnect loose wiring; replace the ballast/driver if damaged.
7.3.4 Residual Current Device Tripping Frequently
Fault Symptom: Residual current device trips when using appliances; after resetting, it trips again.
Causes: Appliance leakage, damp wiring causing leakage, faulty protective device.
Solution: Unplug appliances one by one to identify the leaking device; check wiring insulation and dry or replace damp sections; replace the residual current device with one of the same specification if faulty.
7.3.5 Distribution Box Noise and Overheating
Fault Symptom: Humming sound inside the distribution box, heating of switches and terminals.
Causes: Loose wiring with poor contact, overload operation, aged switch contacts.
Solution: After cutting off power, tighten all wiring terminals; reduce load to avoid overload; replace switches that show severe aging and overheating; immediately cut off power and inspect if any abnormal heating occurs to prevent fire.
7.4 Door and Window Hardware Common Faults
7.4.1 Stiff Door/Window Operation
Fault Symptom: Sliding or casement doors/windows do not open and close smoothly, with sticking or noise.
Causes: Dirt in tracks, worn rollers, dry hinges, seal friction.
Solution: Clean debris and dust from tracks; replace worn rollers; lubricate hinges; adjust seal position to reduce friction.
7.4.2 Door/Window Not Sealing Properly
Fault Symptom: Gaps after closing, allowing drafts, light penetration, and poor sound insulation.
Causes: Aged and shrunk sealing strips, loose hinges, sagging door leaf.
Solution: Replace aged sealing strips; adjust hinge positions to correct the door leaf; adjust locking points to increase locking force.
7.4.3 Stiff Lock Operation
Fault Symptom: Key insertion and removal difficulty, bolt does not extend smoothly.
Causes: Dry lock cylinder, dust accumulation, misaligned lock bolt.
Solution: Inject pencil graphite powder or specialized lock lubricant into the cylinder; adjust the lock bolt position to align with the strike plate; replace the lock if severely damaged.
7.4.4 Glass Fogging and Water Ingress
Fault Symptom: Condensation and water droplets inside insulated glass units.
Causes: Failed airtight seal on insulated glass, moisture entering the glass cavity.
Solution: For minor fogging, ventilate and observe; for severe cases, replace the insulated glass unit; avoid prolonged water accumulation at glass edges.
7.5 Plumbing Common Faults
7.5.1 Faucet Dripping and Leaking
Fault Symptom: Faucet continues to drip after closing; seepage at connections.
Causes: Worn valve cartridge, aged sealing ring, loose connections.
Solution: Close the angle valve, disassemble and replace the valve cartridge or sealing ring; wrap PTFE tape on threads and retighten; replace the faucet if severely damaged.
7.5.2 Drain Clogging and Slow Drainage
Fault Symptom: Slow drainage from floor drains and basins, even water backup and overflow.
Causes: Debris, hair, and grease clogging the pipes.
Solution: Use a drain unclogging tool or chemical drain cleaner; use a drain auger for severe clogs; periodically clean drain inlet strainers to prevent debris from entering the pipes.
7.5.3 Pipe Joint Leakage
Fault Symptom: Water droplets or dripping at pipe connections.
Causes: Loose connections, aged seals, inadequate hot-melt or adhesive bonding.
Solution: Rewrap threaded connections with PTFE tape and retighten; for PPR pipe joint leaks, cut off and redo the hot-melt joint; for PVC joints, reapply adhesive.
7.5.4 Winter Pipe Freezing and Cracking
Fault Symptom: Pipes crack and leak after low winter temperatures.
Causes: Water in pipes freezes and expands, bursting the pipes.
Solution: Replace cracked pipes; provide adequate insulation in winter; drain water when out of service for extended periods; maintain a minimal trickle of water flow in low temperatures to prevent freezing.
7.6 Fault Reporting and Service
For faults that cannot be diagnosed and resolved independently, contact Guangdong Lain Smart Equipment Room Co., Ltd. for professional repair services.
Service Hotline: +86 13538869979 (also available via WeChat)
Technical Support: +86 13538869979
When reporting a fault, please provide the product model, years of service, fault description, and location to facilitate prompt repair arrangements.
Chapter 8 Safety Construction and Emergency Standards
8.1 General Safety Construction Principles
The installation and construction of modular container units must adhere to the safety production policy of “Safety First, Prevention Oriented, Comprehensive Management,” and strictly comply with national safety production laws, regulations, and on-site safety management systems. All construction personnel must undergo safety education and training, and special operation personnel must hold valid certificates.
Before project commencement, a dedicated safety construction plan must be prepared, safety protection measures implemented, and dedicated safety officers assigned to ensure the entire construction process remains safe and controllable, eliminating safety accidents.
8.2 High-Altitude Work Safety Standards
All work performed at a falling height of 2m or more above the reference surface constitutes high-altitude work and must comply with high-altitude safety regulations.
High-altitude workers must pass physical examinations and have no contraindicated conditions such as hypertension, heart disease, or acrophobia.
Workers must wear safety harnesses with the lanyard anchored above the work position at a secure and reliable point.
Qualified scaffolding or work platforms must be erected for high-altitude work. Scaffold planks shall be fully laid and secured, with guardrails and toe boards installed.
Tools used at height must be secured with lanyards to prevent falling and causing injury. Throwing tools or materials up or down is strictly prohibited.
Work at exposed heights shall be suspended in adverse weather conditions including winds of Beaufort scale 6 or above, heavy rain, or dense fog.
A warning zone shall be established below high-altitude work areas with warning signs posted. Unauthorized personnel are prohibited from entering, and a dedicated lookout shall be assigned.
When working on roofs, edge protection shall be provided along the roof perimeter. Personnel shall watch their footing to prevent stepping off and falling.
8.3 Hoisting Operation Safety Standards
Hoisting operations must be performed by a certified crane operator with a dedicated signal person using unified and clear hand signals.
Before hoisting, inspect slings, rigging, and shackles. Any showing excessive wear or broken wires are strictly prohibited from use.
Lifted components shall be securely lashed with protective padding at sharp edges. Lifting shall be smooth and steady to avoid swinging and collision.
No personnel shall be permitted within the lifting radius. A warning zone shall be established with a dedicated lookout.
A trial lift shall be performed by raising the load 20–30cm above the ground to check lashing, rigging, and crane stability before proceeding with the full lift.
Personnel are strictly prohibited from standing on loads during hoisting, and the crane shall not be used to lift personnel.
All crane outriggers shall be fully extended with timber pads placed underneath to ensure crane stability. Overloading the crane is strictly prohibited.
Hoisting operations shall cease when wind reaches Beaufort scale 6 or above. Hoisting is prohibited during rain or fog when visibility is poor.
Slings and hooks shall only be released after the component is securely fixed in place.
8.4 Construction Electrical Safety Standards
On-site temporary power supply must comply with the “three-level distribution, two-level protection” system and use the TN-S grounded neutral system.
Temporary electrical installations shall be set up and maintained by certified electricians. Unauthorized wiring is strictly prohibited.
Distribution boxes and switch boxes shall comply with specifications, be rainproof and dustproof, have complete locks, and follow the “one machine, one switch, one RCD, one box” principle.
All power tools must have proper insulation, be equipped with residual current devices, and have insulation tested periodically.
Cables shall be installed overhead or in conduits. Dragging cables on the ground, running them over, or submerging them in water is strictly prohibited.
Safe voltage shall be used in damp environments. Hand-held lighting shall use 36V or lower.
Before repairing electrical equipment, power must be cut off, a “Do Not Close” warning sign posted, and a dedicated lookout assigned.
Insulated fire extinguishing equipment shall be provided on site. For electrical fires, cut off power first before extinguishing. Never use water to extinguish electrical fires.
8.5 Hot Work Safety Standards
Hot work on site requires an approved hot work permit before operations may begin.
Hot work shall be supervised by a dedicated fire watch with fire extinguishing equipment available. Flammable and explosive materials shall be cleared from the surrounding area.
Welders must hold valid certificates and wear protective face shields, gloves, and other protective equipment.
Catch trays shall be placed below hot work points to prevent welding spatter from igniting combustible materials.
Hot work near sandwich panels is strictly prohibited to prevent igniting the core material and causing fire.
After hot work is completed, inspect and confirm no smoldering embers remain before leaving the area.
Oxygen and acetylene cylinders shall maintain a minimum separation distance of ≥5m, and at least ≥10m from naked flames. Cylinders shall be stored upright and protected from direct sunlight.
8.6 Personal Protective Equipment Requirements
Proper safety helmets must be worn when entering the construction site, with chin straps fastened.
Workers shall wear slip-resistant safety shoes. Wearing slippers, high-heeled shoes, or working barefoot is strictly prohibited.
Safety harnesses required for high-altitude work; welding work requires face shields and goggles; grinding work requires goggles and dust masks.
The correct protective equipment shall be worn according to the specific work type. Damaged protective equipment shall be replaced promptly.
Working under the influence of alcohol is strictly prohibited. Working while fatigued or ill is strictly prohibited.
Stay focused during work. Horseplay is strictly prohibited. Work discipline shall be observed.
8.7 On-Site Fire Safety Standards
The construction site shall be equipped with firefighting equipment as required, properly arranged, with periodic effectiveness inspections.
Smoking is strictly prohibited on site. Unauthorized use of open flames is strictly prohibited.
Flammable materials shall be stored separately, away from ignition sources, in well-ventilated areas.
Electrical wiring and equipment shall maintain a safe distance from combustible materials to prevent ignition from overheating.
Fire access routes shall be kept clear at all times. Blocking or occupying them is strictly prohibited.
Conduct regular fire safety inspections, eliminate fire hazards, and organize fire safety training and emergency drills.
8.8 Emergency Response Plans
8.8.1 Fall Accident Emergency Response
In the event of a fall accident, immediately stop work and call the emergency hotline 120.
Carefully move mildly injured personnel to a safe area and provide initial treatment such as stopping bleeding and dressing wounds.
Seriously injured personnel must not be moved casually. Keep their airway open and wait for professional medical personnel.
Protect the accident scene, report to the relevant authorities, and cooperate with accident investigation.
Immediately identify and rectify safety hazards on site. Construction shall only resume after rectification passes inspection.
8.8.2 Electric Shock Accident Emergency Response
Upon discovering an electric shock incident, first cut off the power supply, or use a dry insulating object to separate the victim from the power source.
Never pull the victim directly with bare hands to prevent rescuers from also being shocked.
After the victim is separated from the power source, check consciousness and breathing. If cardiac or respiratory arrest has occurred, begin CPR immediately.
Simultaneously call 120 and continue first aid until medical personnel arrive.
Investigate the cause of the electric shock, eliminate the hazard, and strengthen electrical safety management.
8.8.3 Fire Accident Emergency Response
Upon discovering a fire, immediately raise the alarm, call 119, and provide the location, fire size, and burning materials.
For incipient fires, use nearby fire extinguishers to suppress the fire, cut off power, and move nearby flammable and explosive materials away.
If the fire cannot be controlled, immediately organize personnel evacuation along safe routes. Never use elevators.
During evacuation, cover the mouth and nose with a wet towel and stay low while moving.
After the fire is extinguished, protect the scene and cooperate with the accident investigation.
8.8.4 Struck-by-Object Accident Emergency Response
When someone is struck by a falling object, immediately stop work and assess the victim’s condition.
For minor injuries, disinfect and dress the wound; for head or torso injuries, keep the victim lying flat and avoid moving them.
For severe injuries, call 120 and provide necessary first aid while waiting.
Clean up loose items in the area, identify falling object hazards, and post warning signs.
8.8.5 Emergency Contact Information
Emergency Medical: 120
Fire: 119
Police: 110
Manufacturer Technical Support: +86 13538869979
Manufacturer Service Hotline: +86 13538869979
8.9 Usage Phase Safety Requirements
Unauthorized modification of the unit structure or removal of load-bearing components is strictly prohibited. Random drilling or welding on beams and columns is strictly prohibited.
Overloading is strictly prohibited. Heavy items stacked on floors or roofs shall not exceed the design load.
Storage of flammable, explosive, toxic, or hazardous materials inside the unit is strictly prohibited.
Use electricity safely. No unauthorized wiring, no use of non-compliant electrical appliances. Cut off power when leaving.
Pay attention to fire prevention. Open-flame heating indoors is strictly prohibited. Firefighting equipment shall be provided and inspected regularly.
Take protective measures before extreme weather events such as typhoons, heavy rain, or blizzards. Evacuate personnel when necessary.
Periodically inspect the structure and facilities for safety. Address hazards promptly. Never use the unit when it is in a defective condition.
Children must be supervised by adults, and climbing on windowsills or stairs shall be avoided to prevent accidents.
Appendices
Appendix A Installation Quality Acceptance Record Form (Template)
Appendix B Commissioning and Testing Record Form (Template)
Appendix C Routine Inspection Record Form (Template)
Appendix D Product Warranty Card
Appendix E Parts List and Specification Parameter Table
Prepared by: Guangdong Lain Smart Equipment Room Co., Ltd.
Version: V2.0
Release Date: July 2026
Service Hotline: +86 13538869979 (also available via WeChat)
Technical Support: +86 13538869979
Address: China Resources Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou
Official Website: https://gdlain.com
Guangdong Lain Smart Equipment Room Co., Ltd. reserves the final right of interpretation of this manual. Product technical upgrades will be reflected in synchronized updates to this manual. Please refer to the latest version on the official website.
For additional technical information on modular container installation and commissioning, or for inquiries about Lain modular container product details, please feel free to contact us. We will be pleased to provide professional products and services.