Table of Contents
Toggle1. Cover / Document Information
– Document Title: University High-Performance Computing Room Construction Technical Design Solution
– Prepared by: Guangzhou Lain Intelligent System Development Co., Ltd.
– Brand: KITOZER (Pioneer)
– Date: August 2026
– Version: V1.0
– Project Type: Technical design solution for University High-Performance Computing Room Construction
2. Table of Contents Structure
1. Company Introduction
2. Project Overview
3. User Requirement Analysis
4. Overall Design Description
5. Detailed System Design and Product Technical Parameters
6. Project Quotation and Configuration List
7. Core Solution Advantages
8. Technical Q&A
9. Construction Schedule Plan
10. Construction Organization Plan
11. After-Sales Service System
12. Operation and Maintenance Training Plan
13. Typical Project Cases
14. SEO Optimization System and Website Backend Configuration
15. Contact Information
3. Company Introduction
3.1 Company Development Overview
Founded in 2002, Guangzhou Lain Intelligent System Development Co., Ltd. is a high-tech enterprise dedicated to the computer room construction and intelligent protection field for more than two decades, integrating R&D, production, sales, engineering implementation and after-sales service. The company focuses on innovative breakthroughs in electromagnetic shielding technology, modular computer room technology and computer room environmental monitoring technology, and has grown into a source manufacturer with core competitiveness in the domestic computer room construction field.
After more than twenty years of industry accumulation, the company has built a large-scale production and manufacturing base equipped with advanced CNC sheet metal processing equipment, automated spraying production lines and professional testing laboratories, with an annual production capacity of hundreds of sets of shielding computer rooms, integrated cabinets and micro-module products. The company’s service network covers all provinces and cities across the country, providing thousands of computer room construction and renovation services for customers in government, military, scientific research, finance and enterprise fields.
3.2 Core Business System
The company’s core business revolves around the full-lifecycle construction of computer rooms, forming four major product and service systems:
– Computer room EPC general contracting service: one-stop services from solution design, manufacturing, on-site construction to commissioning and acceptance, covering shielding computer rooms, IDC data rooms, modular computer rooms, container computer rooms and other types;
– Core equipment R&D and production: independently produces KITOZER brand series products, including shielding cabinets, shielding desks, consoles, integrated data cabinets, micro-module cold aisle cabinets, outdoor rainproof cabinets, etc., supporting non-standard customization;
– Computer room environmental monitoring system: provides full-element monitoring solutions for temperature and humidity, water leakage, access control, video, fire protection, UPS and power distribution, realizing intelligent and unattended O&M;
– Shielding and security protection products: shielding rooms, shielding doors and windows, anechoic chambers and related auxiliary materials, widely used in confidential, military and scientific research fields.
3.3 Brand and Qualification Honors
The core brand KITOZER (Pioneer) focuses on computer room equipment and shielding products, positioned as an “efficient, green, innovative and safe” solution provider. Products have passed multiple authoritative tests and comply with national and industry standards. The company holds multiple utility model patents and software copyrights, has been awarded high-tech enterprise qualification, and follows the ISO9001 quality management standard.
3.4 Core Competitive Advantages
1. Source production, controllable quality: own production base and professional processing equipment; core products independently produced with full-process quality control, providing more cost-effective solutions without intermediate links;
2. Customized design, matching needs: tailor-made solutions per site conditions, technical requirements, configuration and budget, with multiple design options provided free of charge;
3. Professional team, rich experience: a professional technical team of engineers and project managers with more than ten years of industry experience;
4. Quality after-sales, full guarantee: a 7×24 professional online service system with dedicated project follow-up from early coordination to later O&M.
4. Project Background and Objectives
4.1 Project Background
With the rapid development of AI, big data and high-performance computing, university research and teaching demand for computing resources is exploding. Computing infrastructure has become the core foundation for frontier research, discipline development and talent cultivation. National policies (Education Digitalization Strategy Action Plan, University Computing Infrastructure Construction Guidelines) mandate accelerating university computing infrastructure, and government procurement policies require domestic products for key infrastructure.
This project builds a high-performance computing room for a university: a dedicated computing environment for AI large-model training, HPC and big data analysis, plus a results display and academic exchange space — combining research production and external display. The solution uses mature micro-module technology for a safe, controllable, green, energy-efficient and intelligent modern computing room.
4.2 Overall Objectives
“Domestically advanced, first-class for universities, autonomous and controllable, practical and efficient” — with five objectives:
– Computing support: high-reliability, high-density infrastructure supporting 20kW/cabinet GPU servers, total IT load ≥100kW, smooth expansion for 3-5 years of growth;
– Environment guarantee: precise cooling, constant humidity, fresh air positive pressure, gas fire protection, lightning grounding — meeting Class B data center standards; micro-module PUE ≤1.25;
– Intelligent control: “infrastructure monitoring + computing resource scheduling + results visualization” trinity — full-element monitoring, intelligent alarms, linkage control, unified computing management;
– Display and exchange: a tech-rich display area with terminals and intelligent platform for academic reports, exchange, visits and science education;
– Compliance and security: all core equipment domestic (government procurement compliant), third-party CNAS/CMA testing, 4-year warranty.
4.3 Scope and Content (Turnkey)
– Computing area infrastructure: cabinets, hot-aisle containment, in-row precision AC, constant humidity unit, low-voltage distribution, modular UPS, batteries, precision column cabinets, DCIM, fresh air/exhaust, gas fire suppression, fire alarm, intelligent computing resource management platform;
– Display area: prefabricated decoration, double-layer fireproof glass partition, podium and seating, security, display terminals, language intelligent display platform;
– Cabling and auxiliaries: power cables, control cables, network cabling, trays, hardware;
– Engineering installation and commissioning: decoration, installation, single-device and subsystem commissioning, trial run;
– Third-party verification: CNAS/CMA testing of PUE, temperature field, load-bearing, distribution, fire functions, illumination and noise with formal reports;
– Service: design, documentation, tiered training, 4-year warranty, 7×24 support.
4.4 Basis and Standards
Government procurement domestic product policies; GB 50174-2017, GB/T 50314-2015, GB 50052-2009, GB 50054-2011, GB 50343-2012, GB 50019-2015, GB 50116-2013, GB 50370-2005, GB 50263-2007, YD/T 1095-2018, YD/T 2542-2013, YD 5083-2005, GB 50016-2014 (2018), GB 50303-2015, GB/T 2887-2011, and university informatization requirements.
4.5 Core Value
Supports frontier research (AI, computer science, language science, big data); cultivates high-level talent (undergraduate/graduate training platforms); raises campus informatization; creates an external display window; practices domestic autonomous control (fully domestic equipment, a showcase case for university computing infrastructure localization).
5. User Requirement Analysis
5.1 Overall Functional Positioning
The room combines “research computing production” and “results display/exchange”: the computing area (core production) requires high reliability, security and Class B standards, restricted to O&M personnel; the display area (external exchange) requires strong tech feel, good interactivity, and meeting/reporting for 10-15 people.
5.2 Computing Load and Performance
– High-density GPU cabinets ≥20kW, regular cabinets ≥10kW, total IT load ≥100kW — no local hot spots or power bottlenecks;
– Compatible with mainstream GPU servers, storage and switches (19-inch rack, depth/load/ventilation/power adapted);
– Dual-power for key IT equipment, UPS backup ≥15min; good power quality;
– Smooth expansion: 1-2 rows of cabinet space and power/cooling margin reserved for online expansion.
5.3 Environment Guarantee
– Cold aisle 18-27℃ (±1℃); RH 40-70% (±5%RH); vertical temp difference ≤3℃;
– Cleanliness Class A (particles >0.5μm ≤18000/L);
– Positive pressure 4.9-9.8Pa;
– Noise: O&M area ≤65dB(A), display area ≤45dB(A);
– Clean gas fire suppression with early smoke detection.
5.4 Intelligent Control and O&M
– Centralized monitoring of power, cooling, environment, security and fire — one platform;
– Multi-level alarm thresholds with sound/light, SMS, email, pop-up; clear fault info;
– Linkage control (temp/humidity → AC adjustment; fire → fresh air cutoff + smoke exhaust; door/fire interlock);
– Computing resource management: multi-user, multi-group sharing with quotas;
– Easy O&M: hot-swappable core parts, rapid fault location for university staff.
5.5 Display and Exchange
– Visualized display: 3D architecture, real-time status, computing usage, PUE — tech-rich;
– Research results display: papers, projects, patents, awards (text/video, self-updatable);
– Interactive experience: word-vector visualization, LLM dialogue demo;
– Meeting/report: podium, audio, display terminals for small academic activities.
5.6 Compliance and Domestic Products
– All core infrastructure equipment domestic brands with independent IP (government procurement compliant);
– Network security per classified protection (authentication, access control, encryption, audit);
– Fire system certified and passing local fire acceptance;
– Complete as-built documentation and third-party reports for acceptance/audit.
5.7 Full-Lifecycle Service
– ≥4-year warranty with free repair and software upgrades;
– 7×24 support, 4h on-site arrival, general faults within 24h, major within 48h;
– Systematic training for independent O&M;
– Preferential renewal after warranty.
6. Design Principles and Applicable Standards
6.1 Core Design Principles
– Safety and reliability: full redundancy (power, cooling, monitoring with no single point of failure); mature domestic brands; 99.99% availability;
– Advanced and applicable: proven micro-module, VFD cooling, modular UPS, intelligent O&M; practical configuration balancing performance and cost;
– Autonomous and controllable: KITOZER domestic equipment throughout — no supply chain, information security or service lag risks;
– Green and energy-efficient: hot-aisle containment near-end cooling, VFD AC, high-efficiency modular UPS, LED lighting, intelligent energy management — PUE ≤1.25;
– Standards compliance: full-process compliance with national standards and Class B data center requirements;
– Expandable and maintainable: modular design, online expansion, front-maintenance design, standardized parts, intelligent fault location;
– Economical: optimized investment, high cost-performance domestic equipment, energy savings, one-stop delivery.
7. System Architecture and Working Principle
7.1 Overall System Architecture
Five layers: physical foundation (decoration, cabinets, micro-module containment, lightning grounding); energy guarantee (mains + ATS + modular UPS + batteries + column cabinets + rack PDUs — six-level distribution); environment guarantee (precision cooling, constant humidity, fresh air/exhaust, gas fire, fire alarm); intelligent control (DCIM + computing resource platform + display platform); application services (research computing, O&M management, display/exchange).
7.2 Space Layout
Space 11m × 8m × 2.8m net: computing area (west, ~7×8m, 56㎡): single-row 6 cabinets facing north with closed hot aisle (1.2m) to the south; 3 in-row AC units (2+1 redundancy); 1.5m front maintenance aisle; UPS/batteries/distribution/constant humidity unit along the south wall; AC outdoor units outdoors; strong/weak-current trays separated. Display area (east, ~4×8m, 32㎡): south display terminals and interaction wall; north podium with 12 seats; O&M station by the partition; integrated ceiling with LED and audio; anti-static epoxy floor. Class A fireproof glass partition between zones.
7.3 Airflow Organization
Hot-aisle containment + near-end supply: AC draws hot return air from the containment, cools and supplies cold air to the front cold aisle; servers draw cold air through, exhaust heat into the closed hot aisle; flip skylights (fire linkage) and automatic sliding doors seal the containment; near-end cooling suits 20kW+ density; full-height evaporators with multi-fan uniform supply; VFD compressors and EC fans modulate per return temperature.
7.4 Power Distribution Architecture
Five-level: mains input + ATS dual-supply switching (≤1s) → low-voltage distribution → modular UPS (N+X) → precision column cabinets (branch metering 0.5 class) → rack PDUs; batteries provide ≥15min backup; SPD at all levels.
7.5 Cooling Architecture
In-row precision AC (50kW, sensible heat 1.0, DC VFD) with 2+1 redundancy; constant humidity unit maintaining RH; fresh air/exhaust with positive pressure; free-cooling considerations; PUE ≤1.25.
7.6 Fire and Security
Cabinet-type heptafluoropropane gas fire suppression; smoke/heat dual detection with early warning; fire alarm controller with linkage (fresh air cutoff, smoke exhaust, door release); access control with video monitoring.
7.7 Intelligent Control Architecture
DCIM (one host + sensors + software with 3D visualization, alarms, linkage); intelligent computing resource management platform (scheduling, containers, quotas, monitoring, billing); language intelligent display platform for the display area.
7.8 Future Expansion
Reserved 1-2 rows of cabinet space; power and cooling capacity margins; modular expansion without major renovation.
8. Detailed Technical Design
8.1 Cabinet and Micro-Module System
– KITOZER-K42 high-load cabinet: 42U, 600×1200×2000mm, static load ≥2400kg, seven-fold posts, mesh front/rear doors, full accessories (blanking panels, cable managers); 6 units;
– KITOZER-MDM enclosed hot-aisle micro-module: 6-bay hot aisle with flip skylights, automatic sliding end doors, top cable trays, aisle lighting, fire linkage control; 1 set;
– KITOZER-PDU rack power distribution unit: per-cabinet PDU with monitoring.
8.2 Power Supply and Distribution
– Low-voltage incoming distribution cabinet: mains input, ATS dual-supply switching, branch breakers, SPD, metering;
– Modular UPS: high-efficiency online modular UPS (N+X), ~50kVA class, parallel expansion, ≥15min battery backup;
– Valve-regulated lead-acid batteries: 12V100Ah VRLA with battery racks and battery switch box;
– Dual-circuit precision column cabinets: branch-level current/energy metering (0.5 class), per-rack dual feeds;
– SPDs: Class B + Class C power lightning protection at distribution levels.
8.3 Cooling and Environment
– In-row VFD precision AC (50kW): sensible heat ratio 1.0, DC VFD compressor, EC fans, front-supply rear-return, 2+1 redundancy (3 units);
– Constant humidity purification unit: maintains 40-70%RH and cleanliness Class A;
– Fresh air/exhaust integrated system: positive pressure 4.9-9.8Pa with filtration;
– Outdoor units: matched condenser units outdoors with refrigerant piping.
8.4 Monitoring and Security (DCIM)
– Integrated monitoring host + HD touch terminal; temperature/humidity sensors; positioning leakage detection; smoke detection; access control (card + fingerprint); HD video surveillance; DCIM platform software (3D visualization, multi-level alarms, linkage, history, reports); third-party device gateway software for integration.
8.5 Fire Protection
– Cabinet-type heptafluoropropane gas fire suppression; fire alarm controller; photoelectric smoke detectors; fixed-temperature heat detectors; sound/light alarm; emergency start/stop; gas discharge indicator — full system with linkage (fresh air cutoff, smoke exhaust, door release).
8.6 Intelligent Computing Resource Management Platform
– Management server hardware; platform software: computing scheduling, container image management, job scheduling, resource monitoring and billing, user and permission management — enabling multi-user/multi-group shared computing with quotas.
8.7 Display Area
– Prefabricated room decoration (anti-static epoxy floor, color steel walls, integrated ceiling, LED lighting); enhanced double-layer fireproof glass partition (Class A, ≥90min fire resistance, ~32㎡); custom podium and 12 seats; high-performance display terminals; language intelligent display platform (results display, word-vector visualization, LLM dialogue demo).
8.8 Cabling and Auxiliaries
– Flame-retardant power cables (ZR-YJV); shielded control/signal cables (RVVP/RVSP); Cat6 UTP network cabling; galvanized trays (strong/weak separated); conduits and hardware.
9. Recommended Configuration and Preliminary Budget
9.1 Computing Area Core Equipment
| No. | Item | Specification | Brand | Unit | Qty |
|---|---|---|---|---|---|
| 1 | High-load server cabinet | 42U, 600×1200×2000mm, ≥2400kg, seven-fold posts, mesh doors | KITOZER | unit | 6 |
| 2 | Enclosed hot-aisle micro-module | 6-bay, flip skylights, sliding doors, lighting, fire linkage | KITOZER | set | 1 |
| 3 | In-row precision AC | 50kW, sensible 1.0, DC VFD, EC fans | KITOZER | unit | 3 |
| 4 | Modular UPS | N+X, ~50kVA, parallel | KITOZER | set | 1 |
| 5 | VRLA batteries + racks | 12V100Ah with rack and switch box | KITOZER | set | 1 |
| 6 | Low-voltage distribution cabinet | ATS, branches, SPD, metering | KITOZER | unit | 1 |
| 7 | Dual-circuit precision column cabinets | Branch metering 0.5 class | KITOZER | unit | 2 |
| 8 | Rack PDUs | Per cabinet with monitoring | KITOZER | unit | 6 |
| 9 | Constant humidity unit | RH control, Class A cleanliness | KITOZER | unit | 1 |
| 10 | Fresh air/exhaust system | Positive pressure with filtration | KITOZER | set | 1 |
| 11 | Gas fire suppression + alarm | 70L cabinet type, full linkage | KITOZER | set | 1 |
| 12 | DCIM system | Host, sensors, leakage, access control, video, software | KITOZER | set | 1 |
| 13 | Computing resource platform | Server + software suite | KITOZER | set | 1 |
9.2 Display Area
| No. | Item | Specification | Unit | Qty |
|---|---|---|---|---|
| 1 | Prefabricated decoration | Epoxy floor, color steel walls, ceiling, LED, skirting | item | 1 |
| 2 | Fireproof glass partition | Class A, ≥90min, stainless frame, ~32㎡ | ㎡ | 32 |
| 3 | Custom podium | Wood + metal, mic/power outlets | unit | 1 |
| 4 | Seats | Report chairs | set | 12 |
| 5 | Display terminals | High-performance | set | 1 |
| 6 | Language intelligent display platform | Results display, interaction | set | 1 |
9.3 Cables and Auxiliaries
Power cables (ZR-YJV), control cables (RVVP/RVSP), Cat6 UTP (2 boxes), galvanized trays, conduits, hardware — per design.
9.4 Engineering and Services
Design (layouts, system diagrams, renderings, shop drawings); decoration construction; equipment installation; cabling and termination; system commissioning and trial run.
9.5 O&M and Training Services
4-year whole-machine warranty; quarterly inspection (16 visits with reports); tiered training (2 sessions); 7×24 support; emergency on-site service (4h arrival).
9.6 Total Price Summary
Total = computing area equipment + display area + cables/auxiliaries + engineering services + O&M/training + tax (VAT invoice). All reference prices in this solution are in RMB (CNY) only and are for reference purposes; a formal quotation is issued after configuration confirmation.
10. Technical Specifications
10.1 System Performance Summary
| Item | Specification |
|---|---|
| Cabinet density | Up to 20kW/cabinet (GPU), ≥10kW regular; total ≥100kW |
| Availability | 99.99%; UPS backup ≥15min; N+X redundancy |
| PUE | ≤1.25 (micro-module) |
| Temperature | Cold aisle 18-27℃ ±1℃; vertical diff ≤3℃ |
| Humidity | 40-70%RH ±5%RH; cleanliness Class A |
| Positive pressure | 4.9-9.8Pa |
| Noise | O&M ≤65dB(A); display ≤45dB(A) |
| Cabinet | 42U, ≥2400kg static, seven-fold posts |
| Cooling | 50kW in-row AC ×3 (2+1), sensible 1.0, DC VFD |
| Fire | Heptafluoropropane gas, smoke+heat dual detection |
| Standards | GB 50174 Class B, GB 50370, YD/T 1095 etc. |
| Warranty | 4 years whole-machine; 7×24 support |
10.2 Key Equipment Specifications
| Equipment | Key Parameters |
|---|---|
| Cabinet K42 | 42U 600×1200×2000mm, ≥2400kg, seven-fold posts |
| Hot-aisle module | 6-bay, flip skylights, sliding doors, fire linkage |
| In-row AC | 50kW, sensible 1.0, DC VFD, EC fans |
| Modular UPS | N+X parallel, ≥15min backup |
| Column cabinet | 0.5-class branch metering, dual circuits |
| DCIM | 3D visualization, multi-level alarms, linkage |
| Computing platform | Scheduling, containers, quotas, monitoring, billing |
11. Key Advantages and Customer Value
11.1 Full-Stack Domestic Autonomous Control
All core infrastructure equipment is KITOZER domestic brand with independent IP — meeting government procurement domestic product policy, eliminating import supply chain, information security and service lag risks; a showcase case for university computing infrastructure localization.
11.2 Standardized Micro-Module Architecture
Hot-aisle containment + in-row near-end cooling: efficient, standardized, factory-quality consistent; simple expansion; short construction; PUE ≤1.25 — superior to traditional room-level architecture.
11.3 Full Redundancy and High Reliability
Power (ATS + N+X UPS + dual circuits), cooling (2+1), monitoring (no single point) — 99.99% availability for uninterrupted research computing.
11.4 High Energy Efficiency and Green
Hot-aisle containment, VFD cooling, high-efficiency UPS, intelligent energy management — PUE ≤1.25 with substantially lower operating electricity costs and carbon footprint.
11.5 Integrated Computing Infrastructure Delivery
Turnkey: computing area + display area + computing resource platform — one supplier, one responsibility, coordinated delivery of infrastructure and computing services.
11.6 Unified Brand for Core Systems
KITOZER cabinets, cooling, power, monitoring, fire and platform — consistent quality, integrated compatibility, single-channel service and spares.
11.7 Deep Adaptation to University Scenarios
Design fits university needs: multi-user/multi-group computing sharing with quotas, low-threshold O&M for limited staff, display/meeting space for academic exchange, and policy compliance for government-funded projects.
11.8 Full-Lifecycle Service
4-year warranty, quarterly inspections, tiered training, 7×24 support with 4h arrival — long-term reliable operation and continuous value.
12. Technical Q&A (50+ Items)
12.1 Cabinet and Micro-Module Questions
Q1: Why hot-aisle containment instead of cold aisle?
A: Hot-aisle containment confines exhaust heat for direct return to in-row AC — shorter airflow path, less mixing loss, higher efficiency; near-end cooling suits high density; both are valid, hot-aisle chosen for this layout.
Q2: Why 2400kg load capacity?
A: GPU servers are heavy (each 100-150kg+); 6 full cabinets with heavy servers plus PDUs require high static load with margin; seven-fold posts provide the strength.
Q3: What does the micro-module include?
A: 6-bay hot aisle structure, flip skylights (fire linkage), automatic sliding end doors, top cable trays, aisle lighting and fire linkage control — a complete enclosed cooling unit.
Q4: Can ordinary cabinets be used?
A: Standard 19-inch cabinets work, but high-load models (≥2400kg, mesh doors ≥70% ventilation) are required for 20kW GPU density and heavy equipment.
Q5: How is the hot aisle fire-safety handled?
A: Flip skylights open automatically on fire signal (≤1s) for pressure relief and smoke exhaust; doors interlock with the fire system.
12.2 Power Supply Questions
Q6: Why ATS dual-supply switching?
A: Two mains feeds with automatic transfer ensure continuity if one feed fails (≤1s switching); combined with UPS for seamless power.
Q7: Why modular UPS?
A: N+X module redundancy (no single point), online expansion, hot-swap maintenance, high efficiency across load ranges — ideal for evolving university loads.
Q8: How long is battery backup?
A: ≥15 minutes at full load — sufficient for orderly shutdown or short outages; extendable per requirements.
Q9: What is the six-level distribution?
A: Mains → ATS → UPS → column cabinets → PDUs → equipment — progressive distribution and protection with branch-level metering (0.5 class).
Q10: How is power quality ensured?
A: Online double-conversion UPS provides clean regulated output (voltage stability, low harmonics); SPDs protect against surges.
Q11: What if power demand grows?
A: Modular UPS adds modules online; spare branches in distribution and column cabinets; expansion margins reserved — no major renovation.
12.3 Cooling and Fresh Air Questions
Q12: Why in-row precision AC for 20kW density?
A: Near-end supply delivers cold directly to cabinet inlets — short path, low loss, no local hot spots; room-level AC cannot sustain 20kW density.
Q13: What is sensible heat ratio 1.0?
A: Nearly all cooling capacity is sensible (temperature reduction) with minimal dehumidification — matching server heat characteristics, avoiding overcooling/humidity swings.
Q14: How is humidity maintained?
A: The constant humidity unit adds/removes moisture per RH setpoint; the fresh air system with filtration maintains positive pressure and cleanliness.
Q15: How is PUE ≤1.25 achieved?
A: Hot-aisle containment + near-end cooling, VFD compressors and EC fans modulating per load, high-efficiency UPS, intelligent energy management — combined savings versus traditional rooms.
Q16: What if an AC unit fails?
A: 2+1 redundancy — the standby unit covers capacity; alarms notify O&M; maintenance without cooling interruption.
Q17: Why positive pressure?
A: Prevents unfiltered outside air, dust and moisture ingress — protecting cleanliness and stability (4.9-9.8Pa).
Q18: What happens in winter?
A: VFD units and free-cooling considerations reduce compressor work; exhaust heat can support heating where applicable.
12.4 Monitoring and O&M Questions
Q19: What does the DCIM monitor?
A: Power (mains, UPS, batteries, branches), cooling (AC status, temperatures), environment (temp/humidity, leakage, smoke), security (access, video), fire — one platform with 3D visualization.
Q20: How are alarms delivered?
A: Sound/light, SMS, email, platform pop-up — multi-channel with clear fault location, cause and suggestions.
Q21: What linkage scenarios exist?
A: Temp/humidity over-limit → AC adjustment; fire alarm → fresh air cutoff, smoke exhaust, door release; leakage → valve/equipment protection.
Q22: Is remote monitoring available?
A: Yes — WEB/client remote access with graded permissions and operation logs.
Q23: How is computing shared among users?
A: The computing resource platform supports multi-user/multi-group quotas, job scheduling, container management, monitoring and billing — efficient utilization.
Q24: How easy is maintenance for university staff?
A: Front-maintenance design, hot-swappable modules, standardized parts and intelligent fault location — low-skill-threshold O&M with platform guidance.
12.5 Fire Protection Questions
Q25: Why gas fire suppression?
A: Water damages electronics; heptafluoropropane clean agent extinguishes without residue, safe for occupied spaces and equipment.
Q26: How is fire detected early?
A: Photoelectric smoke + fixed-temperature heat dual detection with early warning; alarm controller triggers the extinguishing sequence.
Q27: What linkage on fire?
A: Fresh air cutoff, smoke exhaust via skylights, door release, alarm broadcast, extinguishing discharge per delay — automated protection.
Q28: Are the fire products certified?
A: Yes — 3C-certified fire products passing local fire department acceptance per GB 50370.
12.6 Intelligent Computing Platform Questions
Q29: What does the platform manage?
A: Computing resources (GPU/CPU), jobs, containers, user quotas, monitoring and billing — a complete resource lifecycle.
Q30: How are jobs scheduled?
A: The job scheduler queues and allocates resources per policy (priority, queue, fair share), maximizing utilization.
Q31: How are containers managed?
A: Container image management module supports standard images, versioning and deployment for reproducible research environments.
Q32: Can usage be charged per project?
A: Yes — monitoring and billing module tracks usage per user/project with reports.
Q33: Is the platform secure?
A: Authentication, access control, encryption and audit logs per classified protection requirements; domestic software stack.
12.7 Construction and Acceptance Questions
Q34: What is the construction period?
A: Approximately 45-60 days for the turnkey scope (decoration, installation, commissioning, third-party testing); adjustable per site.
Q35: How is acceptance performed?
A: Third-party CNAS/CMA testing (PUE, temperature field, load-bearing, distribution, fire, illumination, noise) with formal reports; joint acceptance with documentation.
Q36: Does construction affect existing operations?
A: The project is in dedicated space; construction isolated; finished product protection; scheduled to avoid disruption.
Q37: What documentation is delivered?
A: Designs, shop drawings, configuration lists, certificates, test reports, O&M manuals, training materials and after-sales card.
Q38: Who performs installation?
A: Our professional teams with certified electricians and specialized installers; project manager on site throughout.
12.8 Service and Warranty Questions
Q39: What is the warranty?
A: 4-year whole-machine warranty: free repair/replacement of non-artificial faults and software upgrades from acceptance.
Q40: What is the response time?
A: 7×24 support; 4h on-site arrival; general faults within 24h; major faults within 48h.
Q41: What inspections are provided?
A: Quarterly on-site inspections during the 4-year warranty (16 visits) with inspection reports.
Q42: What training is provided?
A: Tiered training: administrator deep training and user operation training (2 sessions) with materials; free repeat training.
Q43: What happens after warranty?
A: Preferential renewal plans and continued technical support for long-term operation.
Q44: Are spare parts available?
A: Spare modules and parts stocked locally with emergency logistics; genuine KITOZER parts with warranty.
12.9 Additional Questions
Q45: Can the display area double as a meeting room?
A: Yes — podium, 12 seats, audio and display terminals support small academic reports, training and exchanges.
Q46: How are results displayed?
A: The language intelligent display platform shows research outputs, real-time computing status and interactive demos (word vectors, LLM dialogue).
Q47: Is the system expandable for future AI needs?
A: Yes — reserved cabinet rows, power/cooling margins and modular architecture support smooth expansion for 3-5 years of growth.
Q48: What is the energy cost estimate?
A: With PUE ≤1.25 and VFD efficiency, operating electricity is substantially lower than traditional rooms; detailed estimates per load profile.
Q49: How is data security ensured?
A: Access control, video monitoring, graded software permissions, encryption and audit logs; data stays on campus.
Q50: What is the total load capacity?
A: ≥100kW IT load with distribution/cooling matching; per-cabinet up to 20kW for GPU servers.
Q51: Is the solution compliant for government procurement?
A: Yes — all core equipment domestic, full certification documentation, third-party testing — meeting procurement and audit requirements.
Q52: How is the project started?
A: Site survey → design confirmation → contract → production → delivery → installation → commissioning → third-party testing → training → acceptance; dedicated project manager throughout.
13. Construction Schedule
13.1 Overall Period
Total approximately 45-60 working days for the turnkey scope, from mobilization to acceptance; adjustable per site conditions.
13.2 Stage Schedule
| Stage | Work | Days | Acceptance Node |
|---|---|---|---|
| 1. Preparation | Site survey, design confirmation, material incoming inspection, disclosure | 5 | Materials accepted |
| 2. Decoration | Floor, walls, ceiling, partitions (computing + display areas) | 15 | Decoration accepted |
| 3. Infrastructure installation | Cabinets, hot-aisle module, cooling, power, UPS/batteries, fire, DCIM | 12 | Installation checked |
| 4. Cabling and termination | Power/control/network cabling, termination, testing | 8 | Continuity tested |
| 5. Commissioning | Single-device, subsystem and joint commissioning; platform deployment | 7 | Functions verified |
| 6. Third-party testing | CNAS/CMA testing of PUE, temperature, load, power, fire, illumination, noise | 3 | Test reports |
| 7. Trial and acceptance | Trial run, documentation, training, joint acceptance | 3 | Acceptance signed |
13.3 Milestones
Design confirmation → decoration completion → infrastructure installation → commissioning → third-party test reports → training and acceptance — each a formal milestone with sign-off.
13.4 Schedule Assurance
Experienced project team; advance production of long-lead equipment; parallel decoration and off-site production; daily plan review; coordination with the university; contingency arrangements.
14. Construction Organization and Quality/Safety Measures
14.1 Organization Structure
– Project manager: overall responsibility, client interface, progress/quality/safety/cost;
– Technical leader: design deepening, disclosure, commissioning, platform deployment;
– Construction teams: decoration, installation, cabling;
– QC/safety officer: quality inspection, third-party testing coordination, safety supervision.
14.2 Core Position Responsibilities
Project manager coordinates all resources and reports progress; technical leader ensures design implementation and commissioning quality; team leaders execute daily plans with quality self-inspection; QC verifies per standards and manages hidden work acceptance.
14.3 Pre-Construction Preparation
1. Technical: design confirmation, shop drawings, disclosure, standards preparation;
2. Materials: incoming inspection (certificates, appearance, quantity); long-lead equipment scheduled;
3. Site: coordinate access, power, storage and work areas with the university; protect existing facilities.
14.4 Key Process Standards
– Decoration per building codes (floor leveling, wall/ceiling installation, partition fire rating ≥90min);
– Cabinet/module installation: leveling, fixing, grounding; hot-aisle sealing verified;
– Power: certified electricians, ATS/UPS/battery installation per code, insulation and grounding tests;
– Cooling: refrigerant piping by certified technicians, pressure test, insulation;
– Cabling: strong/weak separation, labeling, continuity and insulation tests;
– Fire: certified products installed per code, linkage tests;
– Commissioning per acceptance items; third-party testing coordinated.
14.5 Quality Assurance
– Three-level inspection; key process control points; third-party CNAS/CMA verification; as-built documentation per acceptance checklist.
14.6 Safety Management
– Safety education, PPE, safe temporary power, hot work permits, high-altitude safety;
– Battery/UPS handling safety; refrigerant safety; fire safety maintained;
– Emergency plans for injury, fire and equipment damage.
14.7 Civilized Construction and Environment
– Clean site, daily waste removal, finished product protection, noise control;
– Compliance with university campus rules; coordination with other contractors.
14.8 Multi-Party Coordination
Regular coordination meetings with the university, property and other contractors; issue resolution with documentation.
15. After-Sales Service
15.1 Service Commitment
4-year whole-machine warranty; free repair/replacement and software upgrades; lifetime technical consultation.
15.2 Multi-Level Response
7×24 hotline; remote within 1 hour; on-site arrival within 4h; general faults within 24h; major faults within 48h with progress reporting.
15.3 In-Warranty Services
Quarterly inspections (16 visits with reports), preventive maintenance, training, platform updates, emergency repair.
15.4 After-Warranty Services
Preferential renewal plans, continued support, spare parts at cost, periodic calibration and testing services.
15.5 Support System
Local spare parts stock, dedicated service engineer, documented service records, customer satisfaction review.
15.6 Emergency Handling
Leakage, power failure, cooling failure, fire alarm and equipment fault procedures — with priority dispatch and reporting.
16. Training Plan
16.1 Objectives
Enable university staff to independently operate, inspect and maintain the system and platform.
16.2 Audience and Grading
Administrators (deep training), O&M staff (operation and maintenance), users (platform usage).
16.3 Content
Infrastructure (power, cooling, monitoring, fire operation); computing platform (scheduling, containers, quotas, billing); maintenance and troubleshooting; safety procedures.
16.4 Methods and Schedule
On-site training at handover (2 sessions): theory + practice + Q&A; materials and videos provided; free repeat training.
16.5 Assessment
Theory + practice assessment; certificates issued; supplementary training until qualified.
16.6 Documentation
Operation manuals, platform guides, videos, calibration records, drawings and training materials — bound for reference.
15. After-Sales Service
15.1 Warranty Commitment
The overall project warranty period is 2 years from the date of completion acceptance; core equipment has a 3-year warranty. During the warranty period, all failures and damage caused by product quality or construction process problems are repaired and parts replaced free of charge. After the warranty period, lifetime cost-price maintenance is provided, charging only parts cost and basic labor, ensuring long-term stable system operation.
15.2 After-Sales Response Mechanism
– A 7×24 after-sales hotline receives fault reports and technical consultations at any time;
– Within the urban area: respond within 2 hours, technicians on site within 4 hours;
– Suburban and surrounding areas: respond within 4 hours, personnel on site within 8 hours;
– General faults resolved on the spot; complex faults solved within 24 hours with a solution;
– Emergency faults get a green channel with priority dispatch of personnel and parts.
15.3 Periodic Inspection and Maintenance
During the warranty period, a free on-site inspection is provided every six months, with a comprehensive maintenance inspection annually. Inspection contents include equipment operating status, connection firmness, sealing and rust conditions, filtering/grounding performance and safety devices. After each inspection, a formal inspection report is issued recording equipment status and maintenance content with optimization suggestions.
15.4 Spare Parts Supply Guarantee
A local spare parts warehouse is established, stocking common wearing parts for quick replacement to shorten fault handling time. For uncommon special parts, a fast supply channel with the factory ensures availability within 48 hours. During warranty, non-artificial-damage spare parts are replaced free; after warranty, parts are charged at cost price without markup.
15.5 System Upgrade and Technical Support
– Free lifetime technical consultation services by phone or online at any time;
– If the customer later needs upgrades or expansions, preferential upgrade solutions and construction services are provided;
– Industry new technology and standard information is regularly pushed to customers.
16. Training Plan
16.1 Training Objectives and Audience
Training objectives: through systematic training, enable management personnel to fully understand the system structure, working principles and performance characteristics, master daily operation methods and inspection/maintenance essentials, identify common faults and handle simple problems, ensuring safe, stable and long-term operation.
Training audience: management and O&M personnel designated by the client, recommended 2-3 persons with basic electrical and equipment knowledge.
16.2 Tiered Training Content System
Level 1: Basic operation training (1 day)
– Basic principles: system concepts, structure composition, performance indicators;
– Daily operation standards: correct operation of equipment, control and safety systems;
– Daily inspection contents: daily/weekly/monthly check items;
– Safety precautions: usage prohibitions and emergency handling procedures.
Level 2: Maintenance training (1 day)
– Detailed structure of each subsystem and working principles;
– Daily maintenance methods: cleaning, fastening checks, routine care;
– Common fault identification and simple handling;
– Emergency handling procedures for power failure, fire and equipment faults.
Level 3: Advanced management training (as needed)
– Performance influencing factors and how to avoid degradation;
– Upgrade and expansion knowledge and specification requirements;
– Relevant national standards interpretation.
16.3 Training Methods and Schedule
– Methods: combination of “theory explanation + on-site practice + Q&A interaction”;
– Schedule: training arranged at the completion acceptance stage, synchronized with handover, 2 days of intensive training total; time flexibly adjustable; a free repeat training session is provided for newly assigned personnel.
16.4 Training Assessment and Documentation Delivery
– Assessment: theory written test plus practical operation; training qualification certificates issued upon passing; supplementary training for those who fail;
– Documentation delivery: complete O&M documentation, including operation and maintenance manual, equipment manuals and certificates, completion drawings and hidden work records, test reports and after-sales service contact card, all bound into volumes.
17. Anonymous Typical Project Scenarios
All project scenarios below are anonymous, generalized examples compiled from typical industry deployments; no real customer names, addresses or confidential information are disclosed.
17.1 AI Computing Center for a Provincial Key University
A provincial key university built an AI computing center with a computing area (6 high-load cabinets, hot-aisle containment, in-row precision cooling, modular UPS, gas fire protection) and a display/meeting area with an intelligent display platform. PUE reached 1.22, supporting AI large-model training and HPC research; the multi-user computing platform enabled department sharing with quotas; third-party testing passed all items; the display area hosted academic exchanges and visits.
17.2 Smart Campus Data Center for a Vocational College
A vocational college’s smart campus data center used the micro-module architecture with domestic KITOZER equipment throughout, meeting government procurement requirements. The DCIM with 3D visualization simplified O&M for the college’s small IT team; computing resource management supported teaching and research workloads; 4-year warranty with quarterly inspections ensured long-term stability.
17.3 HPC Room Retrofit for a Research Institute
A research institute upgraded an existing computer room to the micro-module architecture, increasing cabinet density to 20kW with hot-aisle containment and VFD cooling, reducing PUE from 1.8 to 1.25. The dual-supply power with modular UPS ensured uninterrupted scientific computing; expansion margins supported subsequent compute node additions.
17.4 Key Laboratory Computing Room for a Municipal University
A municipal university’s key laboratory computing room deployed the turnkey solution with a display/meeting area for result presentation and academic exchange. The language intelligent display platform showcased research achievements and AI interaction demos, strengthening the lab’s external image and supporting talent training.
17.5 Smart Teaching Computing Room for a Higher Vocational College
A higher vocational college’s smart teaching computing room combined teaching computing with a demonstration area: students used the shared computing platform for practical training, while the display area supported teaching demonstrations and campus visits. The standardized architecture and training enabled the college to operate the system independently.
18. SEO Optimization Section
All reference prices in this technical solution are in RMB (CNY) only and are for reference purposes; final quotation is subject to the confirmed configuration.
18.1 Keyword System
– Core keywords: technical design solution, system configuration, technical parameters, construction and O&M services;
– High-conversion long-tail keywords: design solution, configuration list, technical parameters, construction plan, after-sales service;
– Industry traffic keywords: system architecture, applicable standards, technical Q&A, project cases;
– Brand keywords: KITOZER, Guangzhou Lain.
18.2 SEO Tag System
– Title tag: the article title — Guangzhou Lain KITOZER;
– Meta description: Guangzhou Lain professionally provides complete technical design solutions with detailed configuration list, full-system product technical parameters, construction organization plan and after-sales service — source manufacturer customization, compliant performance, third-party testing supported;
– H1 tag: the article title;
– H2 tags: system design and product parameters, construction organization plan, after-sales service and training, engineering cases.
18.3 Internal Link Anchor Text
– Core anchor text: technical design solution, system construction;
– Long-tail anchor text: configuration list, technical parameters, construction plan;
– Related anchor text: shielding cabinet, micro-module cold aisle, integrated computer room, outdoor cabinet.
19. Official Contact Information
– Company Name: Guangzhou Lain Intelligent System Development Co., Ltd.
– Brand: KITOZER (Pioneer)
– Official Website: https://gdlain.com
– Tel: +86 13538869979 (Tel / WhatsApp)
– Address: No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou, China
For any inquiries about this technical design solution, configuration customization, quotation or construction services, please contact us through the information above. We provide free design consultation and tailored solutions for your specific requirements.