Table of Contents
Toggle1. Cover / Document Information
– Document Title: Computer Room Power Distribution System Technical Design Solution
– Prepared by: Guangzhou Lain Intelligent System Development Co., Ltd.
– Brand: KITOZER (Pioneer)
– Date: August 2026
– Version: V1.0
– Project Type: Technical design solution for Computer Room Power Distribution System
2. Table of Contents Structure
1. Company Introduction
2. Project Overview
3. User Requirement Analysis
4. Overall Design Description
5. Detailed System Design and Product Technical Parameters
6. Project Quotation and Configuration List
7. Core Solution Advantages
8. Technical Q&A
9. Construction Schedule Plan
10. Construction Organization Plan
11. After-Sales Service System
12. Operation and Maintenance Training Plan
13. Typical Project Cases
14. SEO Optimization System and Website Backend Configuration
15. Contact Information
3. Company Introduction
3.1 Company Development Overview
Founded in 2002, Guangzhou Lain Intelligent System Development Co., Ltd. is a high-tech enterprise dedicated to the computer room construction and intelligent protection field for more than two decades, integrating R&D, production, sales, engineering implementation and after-sales service. The company focuses on innovative breakthroughs in electromagnetic shielding technology, modular computer room technology and computer room environmental monitoring technology, and has grown into a source manufacturer with core competitiveness in the domestic computer room construction field.
After more than twenty years of industry accumulation, the company has built a large-scale production and manufacturing base equipped with advanced CNC sheet metal processing equipment, automated spraying production lines and professional testing laboratories, with an annual production capacity of hundreds of sets of shielding computer rooms, integrated cabinets and micro-module products. The company’s service network covers all provinces and cities across the country, providing thousands of computer room construction and renovation services for customers in government, military, scientific research, finance and enterprise fields.
3.2 Core Business System
The company’s core business revolves around the full-lifecycle construction of computer rooms, forming four major product and service systems:
– Computer room EPC general contracting service: one-stop services from solution design, manufacturing, on-site construction to commissioning and acceptance, covering shielding computer rooms, IDC data rooms, modular computer rooms, container computer rooms and other types;
– Core equipment R&D and production: independently produces KITOZER brand series products, including shielding cabinets, shielding desks, consoles, integrated data cabinets, micro-module cold aisle cabinets, outdoor rainproof cabinets, etc., supporting non-standard customization;
– Computer room environmental monitoring system: provides full-element monitoring solutions for temperature and humidity, water leakage, access control, video, fire protection, UPS and power distribution, realizing intelligent and unattended O&M;
– Shielding and security protection products: shielding rooms, shielding doors and windows, anechoic chambers and related auxiliary materials, widely used in confidential, military and scientific research fields.
3.3 Brand and Qualification Honors
The core brand KITOZER (Pioneer) focuses on computer room equipment and shielding products, positioned as an “efficient, green, innovative and safe” solution provider. Products have passed multiple authoritative tests and comply with national and industry standards. The company holds multiple utility model patents and software copyrights, has been awarded high-tech enterprise qualification, and follows the ISO9001 quality management standard.
3.4 Core Competitive Advantages
1. Source production, controllable quality: own production base and professional processing equipment; core products independently produced with full-process quality control, providing more cost-effective solutions without intermediate links;
2. Customized design, matching needs: tailor-made solutions per site conditions, technical requirements, configuration and budget, with multiple design options provided free of charge;
3. Professional team, rich experience: a professional technical team of engineers and project managers with more than ten years of industry experience;
4. Quality after-sales, full guarantee: a 7×24 professional online service system with dedicated project follow-up from early coordination to later O&M.
4. Project Background and Objectives
4.1 Project Background
With the rapid development of the digital economy and computing industry, the data center — as the core carrier of computing infrastructure — depends directly on the reliability and stability of its power supply for business continuity. The room power distribution system is the “energy artery” of data center infrastructure, providing safe, continuous, high-quality power to all room loads — IT equipment, power equipment, lighting, security and fire systems. A scientifically designed, reasonably configured distribution system effectively reduces supply-fault risk, improves room operational safety, and supports energy saving and later expansion.
This solution is specially designed for full-scenario room distribution needs, building a complete supply chain of “mains input — dual-power transfer — UPS uninterruptible supply — graded end distribution”, covering six core distribution units: the mains distribution cabinet, intelligent row (column) distribution cabinet, ATS dual-power automatic transfer cabinet, UPS output distribution cabinet, power distribution cabinet and lighting distribution cabinet — fully covering IT, power, lighting and security loads. The solution strictly follows national data center construction standards and combines over 20 years of room construction experience to deliver a highly reliable, safe, expandable and manageable modern room power distribution system for small/medium data centers, enterprise rooms, government rooms, shielded rooms, micro-module rooms and container rooms.
4.2 Project Objectives
Continuous reliable supply: 7×24 uninterruptible power for core IT equipment; seamless ATS transfer and UPS energy storage bridge mains interruptions and voltage anomalies, avoiding business interruption and data loss and meeting high-grade room availability requirements.
Graded distribution management: independent, graded, per-circuit and per-zone distribution for different load types and importance levels; IT, power and lighting loads managed separately for easier fault finding and power dispatch, preventing single-point faults from spreading globally.
Comprehensive safety protection: multi-level electrical protection (overload, short circuit, leakage, overvoltage, undervoltage, surge), complete grounding and lightning design protecting equipment and personnel, compliant with national electrical safety codes.
Intelligent monitoring: real-time acquisition of voltage, current, power, energy and power factor at the main feed and branch circuits, with anomaly alarms and fault positioning; DCIM integration for visualized management and reduced manual patrol cost.
Flexible expansion: sufficient capacity and circuit-count redundancy, modular cabinet structure — later growth needs only additional modules, protecting prior investment without large-scale system modification.
4.3 Applicable Scope
The solution adapts to conventional indoor rooms, shielded rooms, micro-module cold aisles and container rooms, with customizable cabinet sizes and mounting per site conditions; meets different load-level supply needs — dual-path redundant supply for critical IT loads and motor-characteristic protection for power loads; and is compatible with mainstream environment-monitoring and building automation systems for unified management.
4.4 Compilation Basis
The design strictly follows current national and industry standards, mainly: GB 50174-2017 (data center design), GB 50054-2011 (low-voltage distribution design), GB 50052-2009 (power supply and distribution system design), GB 50057-2010 (building lightning protection design), GB 50055-2011 (general electrical equipment distribution design), GB 50217-2018 (power engineering cable design), GB 50462-2016 (data center infrastructure construction and acceptance), GB 7251.1-2013 (low-voltage switchgear and controlgear), GB/T 7260.3-2003 (UPS), plus enterprise standards and practical experience.
5. User Requirement Analysis
5.1 Core Functional Requirements
Continuous reliable supply: 7×24 uninterruptible power for core IT equipment; ATS transfer and UPS storage provide seamless bridging on mains interruption and voltage anomalies, preventing business interruption and data loss and meeting high-grade availability requirements.
Graded distribution management: independent graded, per-circuit, per-zone distribution for loads of different types and importance; IT, power and lighting loads independently managed for fault finding and dispatch, preventing single-point fault spread.
Comprehensive safety: multi-level protection (overload, short circuit, leakage, over/undervoltage, surge), complete grounding and lightning design, compliant with national electrical safety codes.
Intelligent O&M monitoring: real-time acquisition of voltage, current, power, energy and power factor at main and branch circuits, anomaly alarms and fault positioning, DCIM integration for visualized management and lower patrol cost.
Flexible expansion: 20-30% capacity and circuit redundancy, modular cabinet structure — later expansion by adding modules without large-scale retrofit, protecting investment.
5.2 Scenario Adaptation Requirements
Adapt to conventional rooms, shielded rooms, micro-module cold aisles and container rooms with customizable cabinet sizes and mounting; meet different load-level needs — dual-path redundant supply for critical IT loads, motor-protection characteristics for power loads; compatible with mainstream environment-monitoring and building automation systems.
5.3 Quality and Service Requirements
Core components from first-line brands, high-standard cabinet workmanship, full outgoing inspection and third-party certification; one-stop service from design, production and installation to after-sales O&M; fast after-sales response with timely on-site handling to keep the room power system stable.
6. Design Principles and Applicable Standards
6.1 Applicable Standards
GB 50174-2017, GB 50054-2011, GB 50052-2009, GB 50057-2010, GB 50055-2011, GB 50217-2018, GB 50462-2016, GB 7251.1-2013, GB/T 7260.3-2003, plus national construction acceptance codes for building electrical engineering and the manufacturer’s enterprise standards.
6.2 Design Principles
Reliability first: mature technology and high-quality components, redundant core supply paths, layered multiple protections reducing single-point risk; all equipment passes strict factory power-on tests per national electrical safety standards.
Full-dimension safety: a multi-level electrical protection system from incoming lightning protection and main-circuit protection to branch protection with selective coordination; cabinets with good insulation and mechanical strength, standardized grounding, and isolation/interlocking devices against misoperation.
Expandable compatibility: 20-30% capacity and circuit-count redundancy, standardized modular cabinets, generic communication protocols compatible with different UPS and DCIM brands for future upgrades.
Intelligent O&M: multi-dimension monitoring modules with real-time electrical parameter acquisition, remote status monitoring, active alarm and energy data statistics — visualized, digital management, higher efficiency, lower difficulty.
Green and energy-saving: low-loss components, optimized distribution paths reducing line loss and voltage drop; smart monitoring enables refined energy management supporting green data center concepts.
High cost-performance: optimized configuration balancing initial and O&M cost, source-factory advantage removing intermediate links.
7. System Architecture and Working Principle
7.1 Mains Distribution Cabinet (KITOZER-SPD-AC)
The total entrance hub of the room distribution system — receives external mains, performs total energy metering and total electrical protection, and distributes power to downstream units.
Structure: cold-rolled steel, frame ≥2.0 mm, doors/panels ≥1.5 mm, acid-washed/phosphated/electrostatic powder coated, RAL7035 (custom colors available); IP30 indoor (IP40/IP54 optional); floor-standing with bottom cable entry, top/bottom entry options; 2200×800×600 mm standard (width/depth customizable per current and circuit count); fixed compartment structure with separate incoming, outgoing and metering compartments and separated power/weak-current wiring; double-leaf front door with lock, optional glass observation window; T2 tin-plated copper neutral/earth bars, adjustable mounting rails, reserved positions for monitoring modules and SPDs.
Electrical: AC 380V/220V three-phase four/five-wire, 50 Hz; main incoming current 250A/400A/630A/800A/1000A/1250A/1600A; breaking ≥50 kA (≥630A) / ≥36 kA (≤400A); outgoing circuits 10-400A configurable, standard 12/24/36 circuits, up to 60, ≥15% spare; insulation class B, clearance ≥12 mm, creepage ≥20 mm, 2500V/min withstand, temperature rise ≤70K per GB 7251.1.
Configuration: incoming molded-case or air breaker with three-stage protection (long-delay overload, short-delay short circuit, instantaneous) with adjustable settings for selective coordination, optional isolation switch for a visible break; Class B SPD at the incoming side (In ≥40 kA, Imax ≥80 kA, response ≤25 ns, degradation indicator and remote alarm contact); three-phase multi-function smart meter (voltage, current, active/reactive/apparent power, PF, frequency, active/reactive energy, harmonics; active energy 0.5 class; RS485 Modbus-RTU for energy management); outgoing circuits with D-curve breakers for power loads and C-curve for lighting/general loads, clear labels, DIN-rail mounting for easy change; digital panel meter, status and fault indicators, optional audible/visual alarm module with remote signal; internal LED lighting (auto-on with door), locks and anti-touch shields.
7.2 Intelligent Row Distribution Cabinet (KITOZER-CRC)
Deployed at the head of server cabinet rows, downstream of the UPS output — the end distribution core for IT loads, enabling precise per-rack power management, energy statistics and fault positioning.
Structure: cold-rolled steel ≥1.5 mm, electrostatic powder coated, RAL7035 matching server cabinets; IP20; floor-standing side-by-side with standard server cabinets; 2000×600×1000 mm (42U height), customizable; modular assembled structure with front/rear doors, internal cable channels, power/weak-current separation; standard 42U space compatible with monitoring modules, PDUs and small switches; top/bottom cable entry with large openings and cable retainers.
Electrical: AC 380V/220V three-phase five-wire, 50 Hz; incoming 100A/160A/250A/400A, dual-infeed redundancy optional; breaking ≥36 kA; branch outputs 10A/16A/32A standard (max 63A per circuit); standard 24/36/48 single-phase or 12/18 three-phase circuits, customizable with spare circuits; branch monitoring accuracy voltage ±0.5%, current ±0.5%, active energy class 1; insulation ≥10 MΩ, 2000V/min withstand.
Configuration: incoming molded-case breaker with overload/short protection; dual-infeed models with interlock against paralleling; Class C SPD at the incoming side (In ≥20 kA); per-branch current transformers and monitoring modules collecting voltage, current, active/reactive power, energy and PF in real time, aggregated by an ARM-based concentrator with local storage and precise fault-circuit positioning; branch switches as high-breaking miniature C-curve breakers; output terminals or industrial connectors; clear labels with rack number and phase; modular hot-swap branch units for no-downtime expansion and repair; 7-inch color touchscreen showing total and per-branch parameters, status and alarms with local settings and history; RS485 + Ethernet dual communication (Modbus-RTU, SNMP) integrating with DCIM/BMS; email, SMS and audible/visual alarms; front operation/rear wiring; optional busbar plug-in structure for high-density racks.
7.3 ATS Dual-Power Automatic Transfer Cabinet (KITOZER-ATS)
Automatically transfers between two independent power sources (normal/standby mains, mains/generator), keeping loads powered when one source fails.
Structure: cold-rolled steel ≥2.0 mm, electrostatic powder coated, RAL7035; IP30 indoor (IP54 outdoor optional); floor-standing, top/bottom entry; 2200×800×600 mm standard, wider/deeper for large currents; integral cabinet with independent transfer compartment and separated dual infeed.
Electrical: AC 380V/220V three-phase four/five-wire, 50/60 Hz adaptive; rated current 100A-2000A full range; 3P/4P; PC-class (isolation) or CB-class (breaker) transfer switch; transfer time standard ≤2 s (power/general loads), intelligent fast type ≤0.2 s optional (sensitive loads); mechanical life ≥10,000 operations, electrical ≥1,000 at rated current; breaking ≥50 kA; 2500V/min withstand; dual mechanical + electrical interlock absolutely preventing parallel operation of the two sources.
Configuration: first-line brand transfer switch with silver-alloy contacts; microcomputer intelligent controller with LCD showing voltage, frequency, phase and switch status of both sources; fault detection (overvoltage, undervoltage, phase loss, loss of voltage, frequency anomaly) with adjustable thresholds; adjustable transfer delay avoiding false transfer from voltage fluctuation; auto/manual modes; breakers or isolation switches on both infeeds with overload/short protection and maintenance isolation; Class B SPD on the incoming side; T2 tin-plated neutral/earth bars; source/status/fault indicators; audible/visual alarm with dry contacts for remote monitoring; maintenance lighting; fire linkage input cutting non-fire loads; optional energy metering and generator start contacts.
7.4 UPS Output Distribution Cabinet (KITOZER-UPS-PD)
Distributes UPS output to IT load circuits, important power circuits and security circuits — the hub ensuring uninterruptible supply to critical loads, deeply matched to the UPS system.
Structure: cold-rolled steel ≥1.5 mm, phosphated and powder coated, RAL7035; IP30; floor-standing; 2200×800×600 mm standard, customizable; compartment structure (incoming, outgoing, bypass, monitoring); double-leaf front door with lock, optional observation window.
Electrical: AC 380V/220V three-phase five-wire, 50 Hz; incoming 100A-800A matching UPS output; breaking ≥50 kA; outgoing 16A/32A/63A/100A/160A/250A; standard 12/24/36/48 circuits, customizable, ≥15% spare; insulation class B, 2500V/min withstand.
Configuration: incoming molded-case breaker with three-stage protection matching the UPS output protection for selective coordination; standard manual maintenance bypass (load-break isolation switch with interlock) allowing load transfer to mains bypass during UPS fault, maintenance or upgrade without interruption; outgoing circuits with C-curve for IT loads and D-curve for power loads; dual-power transfer modules for important loads (UPS + mains redundant); clear labels; spare circuits for expansion; three-phase multi-function meter at the incoming side; optional branch monitoring; Class C SPD at the output side (In ≥20 kA); neutral-earth voltage suppression device; over/undervoltage, overload and short protections; digital meter, UPS/bypass/loop/fault indicators, remote alarm signals.
7.5 Power Distribution Cabinet (KITOZER-PWR)
Supplies power loads — precision AC, in-row AC, fresh-air and exhaust systems, chillers, chilled/cooling water pumps, fire fans — meeting large-current and motor-load start/protection needs.
Structure: cold-rolled steel ≥2.0 mm, powder coated; IP30 (IP54 outdoor optional); floor-standing; 2200×800×600 mm standard; fixed structure with generous internal space, top/bottom ventilation openings; double-leaf front door with lock.
Electrical: AC 380V/220V three-phase five-wire, 50 Hz; main incoming 250A-1250A; breaking ≥50 kA; outgoing circuits 16A-630A for different power equipment; standard 8/12/16 power circuits, customizable with spares; mechanical life ≥10,000; 2500V/min withstand; motor-protection characteristics with start delay avoiding nuisance trips from motor starting current.
Configuration: incoming molded-case/frame breaker with three-stage protection and adjustable settings; Class B SPD; optional isolation switch; motor-protection breakers per circuit (overload, short circuit, phase loss, motor-start adapted); contactor + thermal relay combinations for large equipment with remote start/stop; clear labels; multi-function power meter; optional per-circuit metering for energy analysis; per-circuit status indicators; integration with HVAC and building automation for linked control; grille ventilation for natural heat dissipation; safety locks, large T2 tin-plated neutral/earth bars, insulation shields.
7.6 Lighting Distribution Cabinet (KITOZER-LT)
Controls normal lighting, emergency lighting and evacuation indication lighting in the room, meeting operational illumination and emergency evacuation needs per fire codes.
Structure: cold-rolled steel ≥1.2 mm, powder coated; IP30; wall-mounted (800×600×200 mm) or floor-standing (1800×600×400 mm); modular structure on standard DIN rails; single door with lock.
Electrical: AC 220V/380V single/three-phase, 50 Hz; incoming 32A/63A/100A/160A; outgoing 6A/10A/16A/20A/32A; standard 12/24/36 lighting circuits, customizable with spares; breaking ≥6 kA; insulation ≥10 MΩ, 2000V/min withstand.
Configuration: normal and emergency lighting fed separately (normal from mains, emergency from UPS/emergency power); incoming breakers with overload/short protection; main isolation switch; zone-based control by room function (main hall, auxiliary, O&M, corridor); optional intelligent lighting control (timed switching, occupancy sensing, scene modes — O&M/duty/full-bright), emergency circuits with forced lighting on fire or outage per fire codes; independent evacuation indication circuit in continuous mode with independent protection; status indicators and clear labels; spare circuits; optional lux sensors for automatic brightness adjustment.
8. Detailed Technical Design
8.1 Overall Supply Chain Design
The four-level supply chain “dual mains input — ATS transfer — UPS uninterruptible supply — graded end distribution” provides: dual mains feeds via ATS for source redundancy; UPS output feeding IT loads through the UPS output cabinet; row cabinets at each server row head for end distribution with branch monitoring; power cabinets for HVAC and power loads; lighting cabinets for normal/emergency/evacuation lighting. Selective protection is coordinated from the main feed down through each level.
8.2 Protection and Selective Coordination Design
Breaker settings coordinate upstream and downstream: the mains cabinet main breaker (long-delay/short-delay/instantaneous adjustable), downstream distribution breakers and end branch breakers graded so a fault trips only the nearest upstream breaker, preventing cascade trips and limiting the outage to the faulted circuit.
8.3 Monitoring and Management Design
Multi-function meters at each main feed (0.5 class) plus branch-level monitoring at row cabinets (V/I ±0.5%, energy class 1); data aggregated via RS485/Modbus-RTU and Ethernet/SNMP to the DCIM platform; alarms (overcurrent, undervoltage, trip) pushed via email/SMS/audible-visual; energy statistics for PUE calculation, tenant billing and load-balance analysis.
8.4 Grounding and Lightning Protection Design
Three-level lightning protection (Class B at mains/ATS/power cabinet infeeds In ≥40 kA; Class C at UPS/row cabinet infeeds In ≥20 kA; Class D at critical loads); equipotential bonding with a grounding bus; all enclosures grounded with resistance ≤4 Ω; neutral and earth separated with neutral-earth voltage suppression at UPS output; dedicated grounding design for shielded rooms with filters maintaining shielding performance.
8.5 Customization Design
Cabinet dimensions, circuit counts, monitoring functions and colors customized per site (narrow cabinets for tight spaces, low cabinets for limited ceiling height, shielded cabinets with filters for classified rooms); busbar plug-in structures for high-density racks; dual-infeed and maintenance bypass options per reliability grade.
9. Recommended Configuration and Preliminary Budget
9.1 Configuration Summary
The following table lists the recommended configuration for a standard medium room power distribution system (equipment main materials):
| No. | Equipment | Model / Specification | Qty | Unit |
|---|---|---|---|---|
| 1 | Mains distribution cabinet | KITOZER-SPD-AC-630A, 630A incoming, 24 outgoing circuits, multi-function metering + Class B SPD | 1 | pc |
| 2 | ATS dual-power cabinet | KITOZER-ATS-630A, 4P PC-class, intelligent controller, surge protection | 1 | pc |
| 3 | UPS output distribution cabinet | KITOZER-UPS-PD-400A, 400A incoming, 36 circuits, maintenance bypass + metering | 1 | pc |
| 4 | Intelligent row cabinet | KITOZER-CRC-250A, 250A incoming, 48 monitored branches, touchscreen, communication | 2 | pcs |
| 5 | Power distribution cabinet | KITOZER-PWR-630A, 630A incoming, 12 power circuits, motor protection | 1 | pc |
| 6 | Lighting distribution cabinet | KITOZER-LT-100A, 24 lighting circuits, zone control, wall-mounted | 1 | pc |
| 7 | Class B surge protector | In 40 kA, Imax 80 kA, 3P+N | 3 | pcs |
| 8 | Class C surge protector | In 20 kA, Imax 40 kA, 3P+N | 2 | pcs |
| 9 | Three-phase multi-function meter | 0.5 class, RS485 communication | 4 | pcs |
| 10 | Branch monitoring module set | 48 single-phase circuits, with concentrator and CTs | 2 | sets |
| 11 | In-cabinet copper busbars | T2 tin-plated copper | 1 | set |
| 12 | Grounding materials | Ground flat steel, cables, terminals | 1 | lot |
| 13 | Cable and wiring auxiliaries | Terminals, number tubes, ties, fixings | 1 | lot |
| 14 | Transport | City delivery to site | 1 | item |
| 15 | Installation and commissioning | Cabinet installation, wiring, system commissioning, joint tests | 1 | item |
9.2 Quotation Notes
This quotation is a standard-configuration reference; the final price is calculated per actual configuration, project scale and customization. It excludes main power cables, cable trays and civil works, settled per actual site quantities. The quotation includes a 2-year equipment warranty, free on-site installation and commissioning, and free technical training. All prices are indicative and quoted in RMB (CNY) only — no foreign-currency conversion is provided; the final quotation is subject to a formal quotation document.
10. Technical Specifications
10.1 System Performance Summary
| Item | Specification |
|---|---|
| Supply chain | Dual mains → ATS → UPS → graded end distribution |
| System voltage | AC 380V/220V, three-phase four/five-wire, 50 Hz |
| Main incoming current | 250A-1600A (mains), 100A-2000A (ATS), 100A-800A (UPS output) |
| Breaking capacity | ≥50 kA (≥630A), ≥36 kA (≤400A) |
| Outgoing circuits | 10A-630A per circuit, 12-60 circuits per cabinet, ≥15% spare |
| ATS transfer time | ≤2 s standard; ≤0.2 s fast type optional |
| ATS interlock | Mechanical + electrical dual interlock, no parallel operation |
| Monitoring accuracy | V/I ±0.5% (branch), active energy class 1 / 0.5 (feed) |
| Communication | RS485 Modbus-RTU, Ethernet SNMP, dry contacts |
| Lightning protection | Class B In ≥40 kA / Class C In ≥20 kA / Class D at loads |
| Insulation | Class B, clearance ≥12 mm, 2500V/min withstand |
| Temperature rise | ≤70K conductive parts per GB 7251.1 |
| Cabinet finish | Cold-rolled steel, electrostatic powder coating, RAL7035 (custom) |
| Protection rating | IP30 standard (IP40/IP54 options) |
| Warranty | 2 years, free quarterly patrol during warranty |
10.2 Key Component Specifications
| Unit | Key Parameters |
|---|---|
| Mains cabinet SPD-AC | 630A incoming, 24 circuits, 3-stage breaker, Class B SPD, 0.5-class meter |
| Row cabinet CRC | 250A incoming, 48 monitored branches, ±0.5% accuracy, 7-in touchscreen, hot-swap branches |
| ATS cabinet | 630A 4P PC-class, ≤2 s transfer, dual interlock, LCD controller, 10,000 mechanical cycles |
| UPS output cabinet UPS-PD | 400A incoming, 36 circuits, maintenance bypass with interlock, Class C SPD, N-E suppression |
| Power cabinet PWR | 630A incoming, 12 motor-protection circuits, start delay, contactor+relay options |
| Lighting cabinet LT | 100A incoming, 24 circuits, zone control, emergency forced lighting, evacuation circuit |
| Class B SPD | In 40 kA, Imax 80 kA, ≤25 ns, 3+1 mode, pluggable |
| Class C SPD | In 20 kA, Imax 40 kA, ≤25 ns, 3+1 mode, pluggable |
| Multi-function meter | 0.5 class active energy, RS485 Modbus-RTU, full electrical parameters |
11. Key Advantages and Customer Value
11.1 Full-Chain Redundant Architecture — High Supply Reliability
The four-level reliable supply chain “dual mains input — ATS transfer — UPS uninterruptible supply — graded end distribution” applies redundancy at every core link, with multi-level electrical protections selectively coordinated, effectively avoiding single-point-failure risk, ensuring load supply continuity and meeting Class A data center availability requirements.
11.2 Refined Graded Distribution — Higher Management Efficiency
Dedicated distribution units per load type and importance level — IT, power and lighting loads independently distributed with precisely matched protection characteristics, avoiding electromagnetic interference and fault impact between loads while enabling refined, zone-based energy management and greatly improving O&M efficiency.
11.3 Full-Dimension Intelligent Monitoring — Visualized O&M
Multi-dimension monitoring from the main feed to end branches collects electrical parameters and status in real time with active alarms and precise fault positioning; DCIM integration provides visualized distribution data and energy statistics, replacing traditional manual patrol, lowering O&M cost and speeding up fault response.
11.4 Flexible Customization — Full Scenario Coverage
With the source factory’s flexible customization capability, all distribution equipment is customizable per room dimensions, load capacity and functional needs — cabinet size, circuit count, monitoring functions and colors all adjustable, highly adapted to conventional rooms, shielded rooms, micro-module rooms and container rooms.
11.5 Source-Factory Quality — Higher Cost-Performance
As a source manufacturer, the company enforces a strict quality system — fine cabinet workmanship, first-line-brand core components, full factory power-on testing of every unit plus third-party quality monitoring; removing intermediate distributors delivers high cost-performance products and services.
11.6 Full-Lifecycle Service — Worry-Free After-Sales
One-stop service from design, production and installation to after-sales O&M; 24-hour technical hotline with 4-hour on-site response in urban areas; free patrol and repair during warranty and lifetime technical support after warranty.
12. Technical Q&A (50+ Items)
12.1 System Basics
Q1: What does a room power distribution system consist of?
A: A complete system typically comprises the incoming distribution unit (mains cabinet), dual-power transfer unit (ATS cabinet), UPS unit, UPS output distribution cabinet, end row cabinets, power distribution cabinet, lighting distribution cabinet, lightning/grounding system and distribution monitoring system — jointly realizing power input, conversion, distribution, protection and monitoring for all room loads.
Q2: Why a dedicated row cabinet instead of feeding racks directly from the UPS cabinet?
A: The row cabinet enables refined end distribution and management: it shortens feeder distance, reducing line loss and voltage drop; it provides branch-level current/power monitoring and fault positioning down to the specific rack circuit, greatly improving O&M efficiency; centralized distribution also tidies cabling and supports later rack expansion.
Q3: What is the role of the ATS cabinet? Can it be omitted?
A: The ATS (automatic transfer switch) cabinet automatically transfers between two independent sources — when normal mains fails (outage, undervoltage, phase loss), it switches to the standby source (another mains feed or a generator) keeping loads powered. For high-reliability rooms the ATS is critical: without it, a mains fault requires manual transfer — slow and error-prone, causing load outage.
Q4: What is the difference between the mains cabinet and the power cabinet?
A: The mains cabinet is the room’s total incoming cabinet — receives external mains and distributes/metres power for all load types across the room. The power cabinet is a dedicated unit for power loads (AC, pumps, fans), using motor-protection breakers adapted to motor start current to avoid nuisance trips, and generally does not feed IT loads.
Q5: What special designs does the UPS output cabinet have vs. ordinary cabinets?
A: Three core designs: protection parameters deeply matched with the UPS host for selective coordination (no cascade trips shutting down the UPS); a standard manual maintenance bypass so loads transfer to mains bypass during UPS fault/maintenance without interruption; higher power-quality requirements — neutral-earth voltage suppression and higher-grade surge protection for sensitive IT loads.
Q6: What monitoring accuracy does the intelligent row cabinet achieve? Can it be used for energy statistics?
A: Branch monitoring achieves V/I ±0.5% and active energy class 1 — fully meeting room energy-statistics accuracy. It counts total row consumption and per-rack, per-circuit consumption for PUE calculation, tenant billing and load-balance analysis.
Q7: Does the ATS switching interrupt power? Will servers be affected?
A: Standard ATS transfer takes about 1-2 s; sensitive loads like servers are backed by UPS, whose battery bridges the transfer gap seamlessly — servers are unaffected. Second-level gaps also do not affect power loads; high-speed ATS (≤0.2 s) is available for special needs.
Q8: What loads does the power cabinet serve?
A: Precision and in-row AC units, fresh-air and exhaust systems, chillers, chilled/cooling water pumps and fire fans — high-current motor loads requiring start protection and sometimes remote start/stop and linkage with HVAC/BMS systems.
Q9: How is the lighting cabinet designed for fire compliance?
A: Normal and emergency lighting are fed separately (emergency from UPS/emergency power); emergency circuits have forced lighting on fire or outage; an independent evacuation indication circuit operates in continuous mode; all per fire codes.
Q10: What is selective protection and why does it matter?
A: Graded breaker settings so a fault trips only the nearest upstream breaker, isolating the faulted circuit while other circuits keep running — preventing cascade trips that would black out the whole room.
12.2 Product Technology
Q11: What are the protection functions of the mains cabinet main breaker?
A: Three-stage protection — long-delay overload, short-delay short circuit and instantaneous short circuit — with adjustable settings for selective coordination with upstream/downstream breakers; an optional isolation switch provides a visible break for maintenance safety.
Q12: What do the SPD grades mean?
A: Class B (In ≥40 kA, Imax ≥80 kA) discharges large lightning/surge energy at the mains entry; Class C (In ≥20 kA) cleans residual surges at UPS/row inputs; Class D protects critical loads at the socket level — a three-level cascade reducing surge energy step by step.
Q13: What is PC-class vs. CB-class ATS?
A: PC-class is an isolation-type transfer switch — higher reliability, faster, no short-circuit protection built in (upstream breaker provides it); CB-class integrates breaker protection. PC-class is preferred for critical room applications; CB-class suits space-saving needs.
Q14: How does the ATS prevent two sources from paralleling?
A: Dual interlock — mechanical interlock physically prevents simultaneous closure, and electrical interlock logically blocks it — absolutely preventing parallel operation and back-feed accidents.
Q15: What is the neutral-earth voltage suppression device for?
A: High neutral-earth voltage can disturb server power supplies and cause data errors; the device at the UPS output suppresses it (keeping N-E voltage low) for stable IT equipment operation.
Q16: Why do power circuits use D-curve breakers?
A: D-curve breakers tolerate higher inrush (10-20× rated) without tripping, matching motor starting current; C-curve (5-10×) suits lighting/general loads; matching characteristics avoids nuisance trips.
Q17: What parameters does the multi-function meter measure?
A: Three-phase voltage and current, active/reactive/apparent power, power factor, frequency, active/reactive energy and harmonics — with RS485 Modbus-RTU upload for energy management and remote monitoring.
Q18: How does branch monitoring locate faults?
A: Each branch has a CT and monitoring module; the concentrator compares thresholds in real time; an overcurrent or trip alarm identifies the exact circuit and rack, displayed on the touchscreen and pushed remotely — cutting troubleshooting from hours to minutes.
Q19: Can row cabinet branches be expanded without downtime?
A: Yes — modular branch units are hot-swappable; add or replace a branch while other circuits keep running, no power interruption for expansion or repair.
Q20: What is the maintenance bypass and how does it work?
A: A load-break isolation switch with mechanical interlock in the UPS output cabinet; close it to feed loads from mains bypass, then isolate the UPS for maintenance/upgrade — the load never loses power; interlocking prevents misoperation.
12.3 Installation and Environment
Q21: What are the environment requirements for distribution equipment?
A: Dry, ventilated indoor space without corrosive gas or strong magnetic interference; ambient temperature -5℃ to +40℃ recommended, humidity ≤90% without condensation; level floor with adequate load capacity; ≥600 mm operation space around cabinets; away from water sources and heat, no direct sunlight.
Q22: What is the cabinet installation process?
A: Position per drawing, level and plumb (verticality deviation within standard), fix with expansion bolts (≥4 points), side-by-side cabinets joined evenly; grounding connected reliably; incoming/outgoing cables dressed and terminated; final inspection before energization.
Q23: What are the wiring standards?
A: Cables sized per current with margin; flame-retardant types; phase colors A yellow / B green / C red / N blue / PE yellow-green; terminals crimped firmly with number tubes and labels; power and weak-current separated; bending radius compliant; insulation and continuity tested before power-on.
Q24: How is grounding done?
A: All cabinet enclosures, busbars and equipment connect to the room equipotential ground bus; ground trunk ≥16 mm² yellow-green copper (branch ≥4 mm²); resistance ≤4 Ω (≤1 Ω for rooms with communication/classified equipment); N and PE separated; periodic measurement.
Q25: How long does a standard medium room distribution project take?
A: About 15 working days: preparation 2, foundation/trays/grounding 3, equipment installation 2, wiring 4, commissioning 2, acceptance and training 2 — adjustable per site conditions.
Q26: Can cabinets be customized for tight spaces?
A: Yes — as a source manufacturer, full-size customization is supported: narrow cabinets for constrained spaces, low cabinets for limited ceiling height, plus customized colors, door styles, observation windows and internal layouts.
Q27: Can the equipment integrate with an existing DCIM system?
A: Yes — standard Modbus-RTU/SNMP protocols with RS485/Ethernet interfaces integrate seamlessly with mainstream environment-monitoring and building automation systems; custom protocol development is available for special requirements.
Q28: What tests are performed at commissioning?
A: Per-device power-on; ATS dual-power transfer tests (both directions, timing); protection parameter verification; insulation/continuity tests; monitoring joint tests with data upload; loaded trial run (24-72 h); documentation handover.
Q29: What safety measures apply during installation?
A: Certified electricians; power-off, verification, tagging and locking for electrical work; live work only with two-person supervision and insulation; RCD-protected temporary power — one machine one switch one RCD; hot-work permits with watchers; helmets, insulating shoes and PPE; warning signs and controlled access.
Q30: How is the room kept running during retrofit?
A: Phased, non-stop construction: new cabinets and cabling installed first, then circuit-by-circuit cutover with UPS bridging; each phase accepted before the next; work scheduled in low-peak windows; the owner’s operations team coordinates throughout.
12.4 O&M
Q31: What daily maintenance is required?
A: Periodic internal dust cleaning (prevent poor heat dissipation and insulation degradation); breaker/switch operation checks; terminal loosening/heating checks; monitoring data verification and alarm function tests; SPD status checks for degradation; periodic ATS transfer tests; grounding system checks.
Q32: How often should the ATS transfer function be tested?
A: Quarterly or semi-annually, manually or by simulated source failure, verifying correct transfer in both directions, timing and interlock — keeping the transfer function reliable for real outages.
Q33: How are SPDs checked and replaced?
A: Check the window indicator (green normal / red fault) and remote alarm contacts; replace degraded modules promptly; pluggable modules replace online without tools; keep spares per the SPD count.
Q34: What does the quarterly patrol include?
A: Full system detection, cleaning and care — breaker status, terminal thermal scan, monitoring accuracy spot checks, alarm tests, ATS function test, SPD status, grounding resistance — with a patrol report identifying hidden risks.
Q35: How is energy data used?
A: Feed meters plus branch monitoring provide total and per-circuit consumption for PUE calculation, tenant billing, capacity planning and load-balance analysis — supporting energy optimization decisions.
Q36: What should be checked on the touchscreen during patrol?
A: Total feed parameters, per-branch current/power status, alarm history, communication status with the DCIM platform, and any threshold settings that need adjustment per load changes.
Q37: How is the spare circuit capacity managed?
A: Record spare circuit positions and ratings; when adding racks, install the matching breaker and label it per the naming convention; update as-built drawings so the spare pool stays accurate.
Q38: What safety rules apply to O&M staff?
A: Authorized access only; verify with a voltage tester before touching; use insulated tools; two-person rule for energized work; follow lockout/tagout for maintenance; keep cabinet doors locked; never bypass interlocks or protections.
Q39: What documentation should be maintained?
A: As-built single-line diagrams, circuit schedules with labels, commissioning records, patrol reports, alarm logs and modification records — kept current and accessible for rapid fault handling.
Q40: Is operator training provided?
A: Yes — at acceptance, on-site training covers theory (architecture, functions, electrical safety) and hands-on (breaker/ATS manual operation, touchscreen use, patrol points, emergency flows for outage and trips), with manuals and a technical hotline for follow-up.
12.5 Fault Handling
Q41: A branch trips — how to handle?
A: Identify the circuit and rack from the alarm/label; check for overload, short circuit or faulty equipment on that branch; isolate, clear the fault, test insulation, then re-close; if it trips again, inspect the downstream equipment and cable before further attempts.
Q42: The main breaker trips — what to do?
A: Do not re-close blindly; check for downstream faults (shorts, heavy overloads, cable damage); measure insulation of the outgoing feeders; clear the cause; verify breaker settings; re-close and monitor — if the cause is unclear, engage a professional survey.
Q43: ATS fails to transfer — causes and handling?
A: Check controller power and settings (thresholds, delay, mode); verify both source availability; check transfer switch mechanism and interlock state; check for fault alarms; test manually; if the mechanism is faulty, arrange service with a bypass plan for the load.
Q44: What if the touchscreen shows communication failure?
A: Check RS485/Ethernet cabling and terminations, device addresses, protocol settings and the DCIM platform configuration; reboot the concentrator if needed; verify data upload after recovery.
Q45: How is a suspected SPD failure detected?
A: Window indicator red or remote alarm contact active indicates degradation; also check for repeated downstream surge damage; replace the module and record the event; verify protection after replacement.
Q46: What does a hot terminal indicate?
A: Loose connection, undersized conductor or overload; measure with a thermal scanner during patrol; tighten or replace the termination, verify load current, and correct the root cause to prevent insulation damage or fire.
Q47: Power quality complaints from IT loads — what to check?
A: Check neutral-earth voltage (should be low at UPS output), voltage balance across phases, harmonics from the meter, and UPS/bypass mode status; verify SPDs and N-E suppression devices; balance single-phase loads across phases.
Q48: What is the emergency flow for a room-wide outage?
A: Confirm ATS/UPS behavior and downstream trip state; isolate the fault, restore non-faulted sections progressively per the single-line diagram; engage standby/generator per plan; record timestamps and events for analysis; inspect before full restoration.
Q49: How are electrical accidents handled?
A: Electric shock — cut power or separate with insulating material, never bare hands; check breathing/consciousness, CPR if needed, call 120; preserve the scene. Fire — cut power, dry-powder extinguishers (never water), call 119 if large, evacuate; inspect and rectify before re-energizing.
Q50: When should the manufacturer be called?
A: For persistent trips without an identified cause, ATS mechanism faults, breaker replacement requiring coordination settings, monitoring system integration issues, or any work on energized distribution — engage certified engineers rather than risk unsafe intervention.
12.6 Customization and Service
Q51: Can the cabinet color and layout be customized?
A: Yes — colors (RAL custom), door styles, observation windows, internal compartment layout, cable entry direction and mounting (floor/wall) are all customizable per room style and space.
Q52: Can shielded rooms use this distribution system?
A: Yes — shielded cabinets with shielding treatment and filters on incoming/outgoing lines maintain electromagnetic shielding while providing distribution, meeting classified room construction and EMC standards.
Q53: What is the warranty and service commitment?
A: 2-year free warranty from acceptance; non-artificial faults repaired/replaced free with standby substitution when needed; free quarterly on-site patrol during warranty; 7×24 hotline; general faults within 24 h, urgent faults on site within 2 h in urban areas and resolved within 4 h; lifetime technical support after warranty at cost-only parts and reasonable service fees.
Q54: Can the system be expanded later?
A: Yes — spare circuits and space are reserved in the cabinets; ordinary additions need only the matching breaker; row cabinet branches hot-swap without downtime; significant capacity growth adds new cabinets within the same architecture.
Q55: What documentation supports acceptance?
A: 3C certificates, type test reports, factory test reports, single-line and wiring diagrams, commissioning and test records, as-built drawings, training records and maintenance manuals — satisfying data center and electrical acceptance filing.
Q56: How is the system designed for high availability (Class A)?
A: Dual mains + ATS + UPS + dual-path row feeds for critical loads; N+1/N+X redundancy at each level; selective protection; monitoring for every link; maintenance bypasses for non-stop servicing — meeting Class A availability requirements.
Q57: What is the delivery time for standard equipment?
A: Standard configurations ship in about 7-10 working days after order confirmation; customized cabinets typically 15-20 working days per configuration; project schedules are coordinated with the construction plan.
Q58: Is on-site measurement provided?
A: Yes — free on-site survey before ordering verifies space, load, cable routes and power entry, producing the customized design; three free design options are provided for selection.
Q59: What are the green features?
A: Low-loss components, optimized paths reducing line loss and voltage drop; smart metering for refined energy management; monitoring supports PUE optimization and load balancing; materials and processes comply with environmental norms.
Q60: How is service quality supervised?
A: A service supervision hotline accepts complaints and suggestions; satisfaction follow-up after every service; a dedicated project service file records the full lifecycle; quarterly patrol reports are delivered to the owner for traceability.
13. Construction Schedule
13.1 Overall Period
For a standard medium room power distribution project, the total construction period is about 15 working days, adjustable per site conditions, owner coordination and force-majeure factors:
| Stage | Work | Days | Responsible | Coordination |
|---|---|---|---|---|
| 1. Preparation | Site survey (positions, cable routes), drawing review and technical disclosure, equipment/material incoming inspection, tools and PPE | 2 | PM, technical lead | Owner confirms site conditions and provides construction power |
| 2. Foundation work | Cabinet base positioning and fixing, tray and conduit installation, grounding system | 3 | Electricians, foreman | Owner coordinates site space |
| 3. Equipment installation | Cabinet/ATS/row cabinet positioning, leveling, fixing; internal component check; appearance and quantity acceptance | 2 | Electricians | Owner joins incoming acceptance |
| 4. Wiring | Power cable laying, dressing and fixing; cabinet wiring, terminal crimping, number labels; control/communication wiring; insulation and continuity tests | 4 | Electricians, engineer | — |
| 5. Commissioning | Per-device power-on; ATS transfer tests; protection parameter verification; monitoring joint tests and data upload; loaded trial run | 2 | Engineer, technical lead | Owner provides mains input |
| 6. Acceptance and handover | 24-hour continuous trial run, as-built documentation, owner acceptance, operation training | 2 | PM, technical lead | Owner organizes acceptance team |
13.2 Schedule Assurance
Material assurance: equipment production and stocking arranged in advance with common models in stock; auxiliary materials purchased ahead to avoid shortages.
Personnel assurance: a fixed experienced crew and commissioning engineers without arbitrary changes; advance technical and safety disclosure improves efficiency.
Process assurance: standardized processes with seamless stage connection; daily progress tracking with same-day issue resolution.
Contingency: emergency plans cover site-condition changes, transport delays and coordination issues with buffer time, keeping the total period controllable.
14. Construction Organization and Quality/Safety Measures
14.1 Organization Structure
Project manager (1): overall management — schedule, quality, safety, coordination with both parties; first responsible person.
Technical lead (1): construction plan review, technical disclosure, commissioning guidance, technical problem solving.
Electrician foreman (1): leads the crew, executes workmanship and safety rules, manages crew members.
Electricians (3-4): certified — cabinet installation, cable laying, wiring.
Commissioning engineers (1-2): power-on, joint commissioning, function tests.
Safety officer (1, may be part-time): site safety management, inspection, disclosure, rule enforcement.
14.2 Quality Control
Material control: all incoming equipment and materials carry certificates, test reports and 3C certification; incoming inspection rejects unqualified products; core components from first-line brands.
Workmanship standards: construction strictly per GB 50462-2016 and building electrical acceptance codes — firm wiring, tidy layout, clear labels, reliable grounding; key processes follow the workmanship-sample system before large-scale execution.
Process acceptance: the “three-inspection” system (self, mutual, special); the previous process must pass before the next; concealed works and key processes require owner side-station confirmation and signature.
Product protection: dust and impact protection after installation; protect existing decoration, floors, walls and equipment; clean the site daily.
14.3 Safety Management
Disclosure: full safety and technical disclosure before work; special-trade personnel certified, no uncertified operation.
Electrical safety: compliant temporary power with RCDs — one machine one switch one RCD; live work only in pairs (one operator, one watcher); power-off work follows “power off, verify, tag, lock”.
Hot work: permits with extinguishers and a designated watcher; confirm no ignition source after completion.
Site protection: helmets, insulating shoes and PPE; harnesses for work at height; warning signs and controlled access.
14.4 Civilized Construction
Materials and tools stacked neatly and labeled; daily waste removal — “work finished, materials consumed, site clean”; noise minimized with high-noise work scheduled outside operational hours; owner site rules observed with entry registration; uniformed, polite staff.
15. After-Sales Service
15.1 Warranty Commitment
All distribution equipment carries a 2-year free warranty from qualified completion acceptance. During warranty, non-artificial quality faults are repaired and parts replaced free; equipment not repairable on site is replaced by standby units to keep the system running. Free quarterly on-site patrol during warranty covers full system inspection, cleaning and care with a patrol report identifying hidden risks.
15.2 Fault Response Mechanism
A 7×24 technical hotline accepts reports and consultation. Graded response: general faults (not affecting normal supply) handled on site within 24 hours; urgent faults (affecting supply safety and system operation) reached within 2 hours in urban areas and resolved within 4 hours or provided with an emergency solution. A dedicated project service file records operation, maintenance and fault handling throughout the lifecycle.
15.3 Post-Warranty Services
Lifetime technical support and repair after warranty at cost-only parts and reasonable service fees; annual maintenance agreements provide patrol, rush repair, system upgrade and technical consultation as full coverage; system software upgraded free for life, hardware upgrades at preferential prices.
15.4 Service Supervision
A service supervision hotline accepts complaints and suggestions; satisfaction follow-up after every service continuously improves quality.
16. Training Plan
16.1 Training Objectives
Through systematic training, enable the owner’s O&M staff to: understand the overall architecture and working principles of the room power distribution system; master the operation methods and status identification of each distribution cabinet; operate the monitoring system — view running data and handle alarms; master daily patrol content and basic maintenance; and master emergency flows for sudden outages and trips.
16.2 Training Audience
Room O&M managers, electrical duty staff and relevant technical leads — unlimited headcount.
16.3 Training Content and Duration
| Module | Content | Duration |
|---|---|---|
| Theory | System architecture and principles; functions, composition and parameters of each cabinet; electrical safety basics and operation rules | 2 h |
| Hands-on | Manual operation of breakers and ATS; local touchscreen operation, data viewing, parameter setting; daily patrol demonstration and key points | 3 h |
| Maintenance and emergency | Daily maintenance content and cycles; common fault judgment and simple handling; emergency flows for outages and trips | 2 h |
16.4 Methods and Materials
On-site training at acceptance with face-to-face theory and hands-on demonstration, one-on-one engineer guidance until mastered; supporting materials — operation manual, maintenance manual and emergency handling guide; continuous technical hotline support after training for any questions.
16. Training Plan
16.1 Training Objectives and Audience
Training objectives: through systematic training, enable management personnel to fully understand the system structure, working principles and performance characteristics, master daily operation methods and inspection/maintenance essentials, identify common faults and handle simple problems, ensuring safe, stable and long-term operation.
Training audience: management and O&M personnel designated by the client, recommended 2-3 persons with basic electrical and equipment knowledge.
16.2 Tiered Training Content System
Level 1: Basic operation training (1 day)
– Basic principles: system concepts, structure composition, performance indicators;
– Daily operation standards: correct operation of equipment, control and safety systems;
– Daily inspection contents: daily/weekly/monthly check items;
– Safety precautions: usage prohibitions and emergency handling procedures.
Level 2: Maintenance training (1 day)
– Detailed structure of each subsystem and working principles;
– Daily maintenance methods: cleaning, fastening checks, routine care;
– Common fault identification and simple handling;
– Emergency handling procedures for power failure, fire and equipment faults.
Level 3: Advanced management training (as needed)
– Performance influencing factors and how to avoid degradation;
– Upgrade and expansion knowledge and specification requirements;
– Relevant national standards interpretation.
16.3 Training Methods and Schedule
– Methods: combination of “theory explanation + on-site practice + Q&A interaction”;
– Schedule: training arranged at the completion acceptance stage, synchronized with handover, 2 days of intensive training total; time flexibly adjustable; a free repeat training session is provided for newly assigned personnel.
16.4 Training Assessment and Documentation Delivery
– Assessment: theory written test plus practical operation; training qualification certificates issued upon passing; supplementary training for those who fail;
– Documentation delivery: complete O&M documentation, including operation and maintenance manual, equipment manuals and certificates, completion drawings and hidden work records, test reports and after-sales service contact card, all bound into volumes.
17. Anonymous Typical Project Scenarios
All project scenarios below are anonymous, generalized examples provided for reference only. No real customer names, addresses or identifiable details are disclosed.
17.1 Technology Enterprise Data Center Distribution Project
Project overview. A complete power distribution system for a new 200 m² medium data center of a technology enterprise: mains distribution cabinet, ATS dual-power cabinet, UPS output cabinet, 4 intelligent row cabinets, power cabinet and lighting cabinet, supporting 80 server racks of IT loads plus supporting power equipment.
Implementation. A three-level redundant supply architecture of dual mains + diesel generator + UPS; branch-level intelligent monitoring achieving visualized management of the full distribution chain; customized cabinets adapted to the room layout for a unified appearance.
Results. Delivered on schedule, passed third-party inspection and acceptance, stable operation with system availability reaching 99.99%, highly recognized by the customer.
17.2 Government Unit Room Retrofit Distribution Project
Project overview. An upgrade retrofit of an aging government unit room distribution system — replacing old cabinets and adding an ATS dual-power transfer system and intelligent row cabinets to improve supply reliability and O&M intelligence.
Implementation. A non-stop construction scheme with phased retrofit keeping government services uninterrupted; customized cabinet sizes adapted to the original room space without large-scale decoration changes; integration with the existing environment-monitoring system for unified management.
Results. Zero-incident delivery; supply reliability greatly improved after the retrofit with significantly higher O&M efficiency.
17.3 Classified Unit Shielded Room Distribution Project
Project overview. A dedicated distribution system designed and constructed for a classified unit’s shielded room: shielded mains cabinet, shielded UPS output cabinet, lighting cabinet, with filtering devices.
Implementation. Cabinets with shielding treatment and dedicated filters on incoming/outgoing lines, combining distribution function with electromagnetic shielding performance, compliant with national classified room construction standards and EMC requirements.
Results. Passed classified-site inspection and acceptance, stable and reliable operation, fully meeting the customer’s usage requirements.
18. SEO Optimization Section
All reference prices in this technical solution are in RMB (CNY) only and are for reference purposes; final quotation is subject to the confirmed configuration.
18.1 Keyword System
– Core keywords: technical design solution, system configuration, technical parameters, construction and O&M services;
– High-conversion long-tail keywords: design solution, configuration list, technical parameters, construction plan, after-sales service;
– Industry traffic keywords: system architecture, applicable standards, technical Q&A, project cases;
– Brand keywords: KITOZER, Guangzhou Lain.
18.2 SEO Tag System
– Title tag: the article title — Guangzhou Lain KITOZER;
– Meta description: Guangzhou Lain professionally provides complete technical design solutions with detailed configuration list, full-system product technical parameters, construction organization plan and after-sales service — source manufacturer customization, compliant performance, third-party testing supported;
– H1 tag: the article title;
– H2 tags: system design and product parameters, construction organization plan, after-sales service and training, engineering cases.
18.3 Internal Link Anchor Text
– Core anchor text: technical design solution, system construction;
– Long-tail anchor text: configuration list, technical parameters, construction plan;
– Related anchor text: shielding cabinet, micro-module cold aisle, integrated computer room, outdoor cabinet.
19. Official Contact Information
– Company Name: Guangzhou Lain Intelligent System Development Co., Ltd.
– Brand: KITOZER (Pioneer)
– Official Website: https://gdlain.com
– Tel: +86 139 2228 9957 (WeChat available), +86 185 2066 8845 (WeChat available)
– Address: No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou, China
For any inquiries about this technical design solution, configuration customization, quotation or construction services, please contact us through the information above. We provide free design consultation and tailored solutions for your specific requirements.