Table of Contents
Toggle1. Cover / Document Information
– Document Title: Computer Room Lead-Acid Battery System Technical Design Solution
– Prepared by: Guangzhou Lain Intelligent System Development Co., Ltd.
– Brand: KITOZER (Pioneer)
– Date: August 2026
– Version: V1.0
– Project Type: Technical design solution for Computer Room Lead-Acid Battery System
2. Table of Contents Structure
1. Company Introduction
2. Project Overview
3. User Requirement Analysis
4. Overall Design Description
5. Detailed System Design and Product Technical Parameters
6. Project Quotation and Configuration List
7. Core Solution Advantages
8. Technical Q&A
9. Construction Schedule Plan
10. Construction Organization Plan
11. After-Sales Service System
12. Operation and Maintenance Training Plan
13. Typical Project Cases
14. SEO Optimization System and Website Backend Configuration
15. Contact Information
3. Company Introduction
3.1 Company Development Overview
Founded in 2002, Guangzhou Lain Intelligent System Development Co., Ltd. is a high-tech enterprise dedicated to the computer room construction and intelligent protection field for more than two decades, integrating R&D, production, sales, engineering implementation and after-sales service. The company focuses on innovative breakthroughs in electromagnetic shielding technology, modular computer room technology and computer room environmental monitoring technology, and has grown into a source manufacturer with core competitiveness in the domestic computer room construction field.
After more than twenty years of industry accumulation, the company has built a large-scale production and manufacturing base equipped with advanced CNC sheet metal processing equipment, automated spraying production lines and professional testing laboratories, with an annual production capacity of hundreds of sets of shielding computer rooms, integrated cabinets and micro-module products. The company’s service network covers all provinces and cities across the country, providing thousands of computer room construction and renovation services for customers in government, military, scientific research, finance and enterprise fields.
3.2 Core Business System
The company’s core business revolves around the full-lifecycle construction of computer rooms, forming four major product and service systems:
– Computer room EPC general contracting service: one-stop services from solution design, manufacturing, on-site construction to commissioning and acceptance, covering shielding computer rooms, IDC data rooms, modular computer rooms, container computer rooms and other types;
– Core equipment R&D and production: independently produces KITOZER brand series products, including shielding cabinets, shielding desks, consoles, integrated data cabinets, micro-module cold aisle cabinets, outdoor rainproof cabinets, etc., supporting non-standard customization;
– Computer room environmental monitoring system: provides full-element monitoring solutions for temperature and humidity, water leakage, access control, video, fire protection, UPS and power distribution, realizing intelligent and unattended O&M;
– Shielding and security protection products: shielding rooms, shielding doors and windows, anechoic chambers and related auxiliary materials, widely used in confidential, military and scientific research fields.
3.3 Brand and Qualification Honors
The core brand KITOZER (Pioneer) focuses on computer room equipment and shielding products, positioned as an “efficient, green, innovative and safe” solution provider. Products have passed multiple authoritative tests and comply with national and industry standards. The company holds multiple utility model patents and software copyrights, has been awarded high-tech enterprise qualification, and follows the ISO9001 quality management standard.
3.4 Core Competitive Advantages
1. Source production, controllable quality: own production base and professional processing equipment; core products independently produced with full-process quality control, providing more cost-effective solutions without intermediate links;
2. Customized design, matching needs: tailor-made solutions per site conditions, technical requirements, configuration and budget, with multiple design options provided free of charge;
3. Professional team, rich experience: a professional technical team of engineers and project managers with more than ten years of industry experience;
4. Quality after-sales, full guarantee: a 7×24 professional online service system with dedicated project follow-up from early coordination to later O&M.
4. Project Background and Objectives
4.1 Project Background
With the rapid development of the digital economy, the data center — as the core carrier of digital infrastructure — depends directly on operational stability for business continuity. In the room power system, the UPS is the core link ensuring supply continuity, and the lead-acid battery group is the backup energy carrier of the UPS — providing sustained power to core loads on mains interruption, the last line of defense of room power safety.
Room loads are increasingly diverse; servers, storage and network equipment demand extremely high supply quality and continuity — even a few seconds of mains interruption can cause data loss, business interruption and major economic and reputational damage. The enclosed, high-density room environment also places higher demands on battery safety, maintenance-free operation and environmental adaptability. Configuring a stable, safe, room-adapted lead-acid battery system is therefore the necessary choice for room power safety.
This solution addresses the UPS lead-acid battery construction needs of computer rooms, combining standardized and customized lead-acid battery system solutions that fully meet room backup power requirements.
4.2 Project Objectives
Supply continuity: on mains interruption or UPS main-path anomaly, the battery group switches seamlessly to discharge, providing continuous backup power to core loads — achieving 30-minute, 1-hour, 2-hour or 4-hour backup per requirements.
System safety: sealed, explosion-proof, flame-retardant lead-acid batteries with standardized electrical design and protective structures eliminate leakage, fire and explosion hazards, adapting to the enclosed room environment.
Lower O&M complexity: maintenance-free VRLA batteries with an intelligent patrol system provide real-time monitoring and early warning, reducing manual O&M workload.
Extended service life: scientific capacity design, standardized installation and professional maintenance guidance keep the battery group running stably long term, lowering the customer’s long-term cost.
Code compliance: the design, product selection and construction fully comply with national data center design, power engineering and fire-safety standards.
4.3 Project Scope
The solution covers the full process from design to delivery: system design (capacity calculation, series/parallel configuration, cabinet layout, wiring design, monitoring design per UPS parameters, load capacity and backup time); equipment supply (batteries, battery cabinets, intelligent patrol system, DC distribution units, connection cables and auxiliaries); engineering construction (cabinet installation, battery assembly, electrical connection, grounding, monitoring deployment, wiring); system commissioning (charge/discharge tests, voltage consistency tests, monitoring joint tests, UPS linkage tests); after-sales and training (warranty service, periodic patrol, technical training for independent daily O&M).
4.4 Design Standards
The design and construction strictly follow national and industry standards, mainly: GB 50174-2017 (data center design), GB/T 19638.2-2014 (stationary VRLA batteries), YD/T 799-2010 (VRLA batteries for telecommunications), DL/T 5044-2014 (power engineering DC power system design), GB 50462-2016 (data center infrastructure construction and acceptance), GB 50057-2010 (lightning protection design), GB 50054-2011 (low-voltage distribution design), YD/T 1970-2009 (battery O&M for communication stations), plus enterprise standards and customer requirements.
5. User Requirement Analysis
5.1 Core Functional Requirements
Backup supply: during normal mains, the battery group float-charges in standby; on mains interruption or rectifier fault, it discharges instantly to feed the UPS inverter, keeping load supply uninterrupted for the preset duration.
Charge/discharge management: float and boost charging modes coordinated with the UPS host for precise voltage/current control, avoiding overcharge and undercharge and protecting battery life.
Status monitoring: real-time monitoring of group voltage, charge/discharge current, and per-cell voltage, internal resistance and surface temperature with anomaly alarms.
Protection: overcurrent, short-circuit, overvoltage, undervoltage and overtemperature protections with flame-retardant structures.
5.2 Performance Requirements
Capacity: rated capacity per nameplate; at 25℃ the 10-hour-rate discharge capacity is no less than 100% of rated; high-current capability meets UPS inverter start and peak-load needs.
Voltage consistency: small per-cell deviation in one group — float deviation ≤±50 mV; discharge deviation kept within reasonable range to avoid single-cell over-discharge damage.
Cycle life: at 80% DOD under standard conditions — 2V series ≥1200 cycles, 12V series ≥500 cycles; float design life — 2V ≥10 years, 12V ≥6 years.
Self-discharge: ≤3%/month at normal temperature for long storage.
Discharge efficiency: charge/discharge energy conversion efficiency ≥90%.
5.3 Environmental Adaptability Requirements
Temperature: conventional VRLA works at -15℃ to +45℃ (best 20-25℃); gel batteries extend to -30℃ to +55℃.
Compatibility: fully sealed, no acid mist — can be installed in the same room as IT equipment without a separate battery room.
Placement: vertical/horizontal mounting, standard battery cabinets, seismic performance meeting room requirements.
Altitude: normal use below 2000 m; derating design above.
5.4 O&M Management Requirements
Maintenance-free: VRLA sealed structure — no water refilling, no electrolyte density measurement, greatly reduced daily O&M.
Intelligent O&M: patrol system with remote status viewing, history storage, trend analysis and fault prediction for unattended operation.
Easy replacement: standardized sizes and terminals — faulty cells replaced quickly without whole-group replacement.
Data integration: standard protocols integrate with the existing environment-monitoring system.
5.5 Safety and Compliance Requirements
Electrical safety: housing insulation ≥100 MΩ; explosion-proof safety valves; fully insulated connections preventing accidental contact.
Fire safety: UL94 V-0 flame-retardant housings; steel cabinets with fire-isolation capability; fire-code-compliant layout.
Environmental compliance: production and use meet national environmental requirements; lead paste and electrolyte sealed and recoverable; RoHS compliant.
Grounding safety: complete grounding design with reliably grounded cabinets for personnel and lightning/ESD safety.
5.6 Expansion and Lifecycle Requirements
Capacity expansion: reserved expansion space — adding parallel battery groups extends backup time for future load growth.
Technical compatibility: parameters fit mainstream UPS brands and models for easy replacement and upgrade.
Lifecycle cost control: long life, low O&M cost, low fault loss — optimal total cost over the lifecycle.
6. Design Principles and Applicable Standards
6.1 Applicable Standards
Per section 4.4: GB 50174-2017, GB/T 19638.2-2014, YD/T 799-2010, DL/T 5044-2014, GB 50462-2016, GB 50057-2010, GB 50054-2011, YD/T 1970-2009 and related mandatory requirements.
6.2 Design Principles
Reliability first: mature, stable VRLA technology, redundant design concepts and strict series/parallel matching — every stage from selection and configuration to installation aims at long-term stable operation.
Safety and compliance: complete overcurrent, short-circuit, overtemperature and overvoltage protection; flame-retardant explosion-proof products; fire-code-compliant layout; lightning/ESD-compliant grounding.
Advancement with practicality: mainstream mature technology with real usability — simple operation, easy maintenance, no pursuit of premature technology.
Economy and lifecycle optimum: optimized configuration controlling initial cost; long-life, low-O&M products reducing lifecycle O&M and replacement cost.
Scalability: reserved capacity expansion space and interfaces for smooth later expansion, protecting investment.
Intelligent O&M: the patrol system provides real-time monitoring, automatic fault warning and automatic data statistics, reducing manual O&M pressure.
6.3 System Architecture
The lead-acid battery system consists of five units working with the UPS host:
Battery group unit: the core energy storage unit — multiple cells in series/parallel per UPS DC bus voltage and backup time, storing sufficient energy.
Cabinet unit: standard or custom battery cabinets provide structural support, heat-dissipation space and physical protection, standardizing placement and improving room aesthetics.
DC distribution unit: DC breakers and fuses provide on/off control between the battery group and UPS, plus overcurrent/short protection and maintenance isolation.
Intelligent patrol unit: patrol host, acquisition modules and sensors collect per-cell voltage, internal resistance and temperature plus group voltage and charge/discharge current, displaying status and issuing audible/visual and remote alarms.
Wiring unit: connection busbars/cables between cells, group-to-distribution cables, grounding and communication cables with standardized workmanship.
Working logic: during normal mains, the UPS rectifier DC powers the inverter and float-charges the battery group; on mains interruption, the battery discharges immediately, feeding the inverter to convert DC to AC for the load — seamless supply switching.
6.4 Capacity Design and Calculation
The industry-standard constant-power method (with amp-hour estimation as a secondary check) is used, considering aging, temperature and consistency coefficients.
Core parameters: load active power P (kW); UPS inverter efficiency η (0.92-0.95); battery group nominal voltage U (per UPS DC bus); required backup time T (h); cell cutoff voltage Vd (1.8V for 2V cells, 10.5V for 12V); temperature correction Kt; aging coefficient Ka (1.1-1.2); redundancy Kr (1.05-1.1).
Constant-power steps: total discharge power W_total = (P × 1000) / η; per-cell power W_cell = W_total / N (N = series cell count); look up the constant-power discharge table for the model at the required time and cutoff voltage; apply temperature, aging and redundancy coefficients.
Example: 100 kW load, 384V DC bus, η 0.93, 1 h backup, 25℃: total ≈ 107,527 W; 2V cells N = 384/2 = 192; per-cell ≈ 560 W — the 1-hour table gives about 1000 AH; with aging 1.15 and redundancy 1.05, select 2V 1200 AH × 192 cells.
Amp-hour estimate: C = (P × T × 1000) / (U × η × Kd), Kd the capacity coefficient at the discharge rate — for small capacity, long backup time.
6.5 Series/Parallel Matching Design
Series: raises total voltage to match the UPS DC bus — total voltage = cell voltage × cell count; cell count = bus voltage / cell voltage. Rules: same brand/model/batch in one string; DC breaker and fuse in the string for short/overcurrent protection; equal-cross-section busbars or cables with code torque and low connection resistance.
Parallel: multiple groups in parallel raise total capacity — total = single-group capacity × group count. Rules: identical brand/model/capacity/age to avoid circulating current and uneven charge/discharge; independent DC breaker per group for maintenance isolation; identical wiring length and cross-section for balanced current; parallel group count ≤4 to avoid uneven current and life reduction.
6.6 Heat Dissipation and Environmental Adaptation
Temperature directly affects performance and life — high temperature accelerates grid corrosion and water loss (even thermal runaway); low temperature reduces capacity. Cabinet design uses top/bottom vents and louvered doors for natural convection; cells spaced 10-20 mm for airflow; large systems add temperature-linked fans (cabinet internal difference ≤3℃). Installation avoids AC direct blow, heat sources and sunlight; gel batteries for non-air-conditioned outdoor rooms; UPS charging with temperature compensation (-3 mV/℃/cell typical) adjusts float voltage with temperature.
6.7 Wiring and Grounding Design
Wiring: cable/busbar current capacity ≥1.5× maximum discharge current; DC loop voltage drop from group to UPS ≤1% of nominal; power and communication cables separated ≥50 mm; tidy, tied, labeled wiring with proper bend radii; flame-retardant cables; all live parts insulated (busbars wrapped, covers fitted).
Grounding: battery cabinet metal enclosures grounded to the room system with resistance ≤4 Ω; DC working ground per UPS requirements — never mixing working and protective grounds; monitoring equipment grounded separately to avoid interference.
6.8 Safety Protection Design
Electrical: each group with DC breaker + fuse dual protection; all terminals and busbars insulated; overvoltage/undervoltage/overtemperature alarms with serious-fault circuit cut-off.
Fire: UL94 V-0 housings, self-extinguishing; cold-rolled steel cabinets with fire isolation; smoke detector mounting positions for fire-system integration; maintenance aisles and fire spacing per code.
Explosion: one-way safety valves vent at threshold pressure and re-seal; normal operation produces minimal gas — hydrogen/oxygen far below the explosion limit for safe indoor use.
7. System Architecture and Working Principle
7.1 2V VRLA Battery Series
KITOZER 2V stationary VRLA batteries use high-purity lead-calcium-tin alloy grids, micro-fiber separators and starved-electrolyte design — long life, low self-discharge, high reliability for room UPS, base stations and power DC systems.
2V 100AH: 10-h rate 100 AH, 3-h 85 AH, 1-h 55 AH; float 2.23-2.27V (recommend 2.25V), boost 2.30-2.35V (recommend 2.32V); max charge 30A; resistance ≤6 mΩ; self-discharge ≤3%/month; float life 10 years; cycle ≥1200 (80% DOD); -15℃~+45℃; 171×71×205 mm, 6.8 kg; ABS UL94 V-0; valve 10-35 kPa; per GB/T 19638.2, YD/T 799; CE/ROHS/TLC.
2V 200AH: 200 AH (10-h), 170 AH (3-h), 120 AH (1-h); max charge 60A; ≤3.2 mΩ; life 10 years; 171×111×330 mm, 13.2 kg.
2V 300AH: 300/255/180 AH; max charge 90A; ≤2.2 mΩ; float life 12 years; cycle ≥1300; 171×151×330 mm, 19.5 kg.
2V 500AH: 500/430/310 AH; max charge 150A; ≤1.3 mΩ; self-discharge ≤2.5%/month; life 12 years; cycle ≥1300; 241×172×330 mm, 32 kg.
2V 600AH: 600/516/372 AH; max charge 180A; ≤1.1 mΩ; life 12 years; cycle ≥1300; 301×172×330 mm, 38.5 kg.
2V 800AH: 800/688/496 AH; max charge 240A; ≤0.85 mΩ; float life 15 years; cycle ≥1500; 411×172×330 mm, 51 kg.
2V 1000AH: 1000/860/620 AH; max charge 300A; ≤0.7 mΩ; self-discharge ≤2%/month; life 15 years; cycle ≥1500; 511×172×330 mm, 64 kg.
2V 1500AH: 1500/1290/930 AH; max charge 450A; ≤0.48 mΩ; life 15 years; cycle ≥1500; 751×172×330 mm, 95 kg.
2V 2000AH: 2000/1720/1240 AH; max charge 600A; ≤0.36 mΩ; float life 18 years; cycle ≥1800; 1001×172×330 mm, 128 kg.
7.2 12V VRLA Battery Series
Six 2V cells integrated in series — compact, easy installation for small/medium UPS, emergency power and fire backup.
12V 24AH: 24/20/13 AH; float 13.5-13.8V (recommend 13.65V), boost 13.8-14.1V; max charge 7.2A; ≤26 mΩ; self-discharge ≤3%/month; float life 6 years; cycle ≥400; 166×125×175 mm, 8.2 kg; blade copper terminals.
12V 38AH: 38/32/21 AH; max charge 11.4A; ≤17 mΩ; life 6 years; 197×165×170 mm, 12.5 kg.
12V 65AH: 65/55/36 AH; max charge 19.5A; ≤10 mΩ; float life 8 years; cycle ≥500; 350×166×175 mm, 21 kg.
12V 100AH: 100/85/55 AH; max charge 30A; ≤6.5 mΩ; self-discharge ≤2.5%/month; life 8 years; cycle ≥500; 407×173×210 mm, 31 kg.
12V 120AH: 120/102/66 AH; max charge 36A; ≤5.5 mΩ; life 8 years; 485×170×240 mm, 37 kg.
12V 150AH: 150/127.5/82.5 AH; max charge 45A; ≤4.5 mΩ; float life 10 years; cycle ≥600; 483×170×240 mm, 45 kg.
12V 200AH: 200/170/110 AH; max charge 60A; ≤3.4 mΩ; self-discharge ≤2%/month; life 10 years; cycle ≥600; 522×240×218 mm, 62 kg.
12V 250AH: 250/212.5/137.5 AH; max charge 75A; ≤2.8 mΩ; life 10 years; cycle ≥600; 520×268×220 mm, 76 kg; M8 copper bolt terminals; per GB/T 19638.2, YD/T 799; CE/ROHS/TLC/fire certification.
7.3 Gel Battery Series
Fumed-silica gel electrolyte fully solidified in a three-dimensional network — no flow, no acid mist; deeper cycle life, wider temperature range and lower self-discharge than AGM; ideal for outdoor base stations, industrial sites with large temperature swings, energy storage and remote unattended stations. No electrolyte stratification (better group consistency, strong deep-discharge recovery); ≥60% rated capacity at -30℃ and low grid corrosion at high temperature; any-angle installation without leakage; float life 30%+ longer than equal AGM.
2V gel: 500AH (420/290 AH; float 2.25-2.30V recommend 2.27V, boost 2.35-2.40V; max charge 125A; ≤1.5 mΩ; self-discharge ≤2%/month; float life 15 years; cycle ≥1800; -30℃~+55℃; -20℃ ≥75% capacity; 243×175×335 mm, 35 kg). 1000AH (840/580 AH; max charge 250A; ≤0.8 mΩ; life 18 years; cycle ≥2000; 515×175×335 mm, 68 kg). 2000AH (1680/1160 AH; max charge 500A; ≤0.4 mΩ; self-discharge ≤1.5%/month; life 20 years; cycle ≥2200; 1005×175×335 mm, 135 kg). Per GB/T 19638.2, DL/T 637.
12V gel: 65AH (54/34 AH; float 13.6-13.9V recommend 13.75V, boost 14.1-14.4V; ≤12 mΩ; life 10 years; cycle ≥800; 350×166×178 mm, 23 kg). 100AH (84/53 AH; ≤7.5 mΩ; life 12 years; cycle ≥1000; 407×173×213 mm, 34 kg). 200AH (168/106 AH; ≤4.0 mΩ; self-discharge ≤1.5%/month; life 15 years; cycle ≥1200; 522×240×222 mm, 68 kg).
7.4 Battery Cabinets
Standard series: DC-16 (16 × 12V cells, 600×600×1200, 1.5 mm, ≥800 kg); DC-24 (24 × 12V, 600×600×1600, 1.5 mm, ≥1200 kg); DC-32 (32 × 12V, 600×600×2000, 2.0 mm, ≥1600 kg); DC-24-2V (24 × 2V, 600×800×1200, 2.0 mm, ≥1500 kg); DC-48-2V (48 × 2V, 600×800×2000, 2.0 mm, ≥3000 kg); DC-64-2V (64 × 2V, 800×800×2000, 2.5 mm, ≥4000 kg). Common: IP20; dedicated ground terminal ≤0.1 Ω; seismic per GB 50260 (stable at intensity 8); concealed locks, double doors; RAL7035 standard.
Custom types: heavy-load reinforced (single-layer 2V placement, 2000 kg per layer, reinforced plates); forced cooling (top axial fans with temperature control, cabinet difference ±2℃); outdoor IP55 (rain/dust/theft resistant, UV coating, optional insulation); shielded (B-class shielding with conductive gaskets and insulated mounting for classified rooms).
Materials/workmanship: Angang/Baosteel cold-rolled steel 1.5-3.0 mm; CO₂ gas-shielded welding; full pretreatment (hot wash → alkaline → acid → phosphating → pure-water rinse); pure polyester electrostatic powder coating 60-80 μm; zinc-alloy locks, reinforced hinges, adjustable shelf brackets.
7.5 Intelligent Patrol System
Main control unit: 32-bit ARM Cortex-M4 120 MHz; 16 MB Flash + 8 MB RAM, SD expansion to 128 GB (>2 years history); 7-inch color touchscreen 800×480; up to 256 per-cell voltage channels per unit (0-16V, ±2 mV), cascade expandable; 2 group-voltage channels (0-600V DC, ±0.2%); 2 current channels with Hall sensors (0-1000A, ±0.5%); 16 NTC temperature channels (-20℃~+80℃, ±0.5℃); online AC-injection internal resistance testing (±5%); RS485/RS232/Ethernet with Modbus-RTU/TCP and SNMP for DCIM integration; 8 dry-contact alarm outputs; DC 48V or AC 220V dual supply, ≤15 W; -10℃~+60℃; 19-inch 2U; MTBF ≥100,000 h.
Cell acquisition module: DIN-rail mounted; 12 or 24 channels per module (2V/12V compatible); 0-16V, 1 mV resolution, ±2 mV accuracy; 2 temperature channels per module; RS485 bus, addressable, up to 1000 m; powered from the battery bus (18-60V DC), ≤1 W; 2000V/1min isolation; EMC level 4 per GB/T 17626.
Software: real-time graphical monitoring (refresh ≤1 s, multi-group); multi-level alarms (over/undervoltage, overtemperature, abnormal resistance, communication fault) with customizable thresholds and popup/sound/SMS/email notification; automatic daily/monthly/annual reports, voltage/temperature/resistance trend charts, capacity-attenuation analysis and remaining-life prediction; remote capacity (discharge) test with automatic recording and professional reports; optional active balancing (max 5A) improving consistency; multi-level user permissions; standard OPC/API interfaces to DCIM platforms.
7.6 DC Distribution and Connection Materials
DC breakers/fuses: molded-case DC breakers (DC 500V, 63-1600A, 50 kA, 2P/3P) for group protection; miniature DC breakers (DC 250V/500V, 6-125A, 10 kA) for branches; DC fuses (DC 500V, 50-1000A, 100 kA) as backup short protection. Dedicated DC arc-extinguishing chambers (arc time ≤10 ms), long-delay + instantaneous characteristics, insulation class high, anti-welding contacts, electrical life ≥10,000, auxiliary/alarm contacts optional, per GB 14048.2 and IEC 60947-2, 3C certified.
Busbars: T2 copper ≥99.95%, tin-plated ≥5 μm; series 20×3 to 120×10 mm, customizable; design 2.5 A/mm² with 1.5× margin; PVC flame-retardant covers, stainless bolts, washers.
Power cables: ZR-YJV flame-retardant XLPE 0.6/1 kV, 10-240 mm²; conductor resistance per GB/T 3956; 3.5 kV/5 min withstand; class B flame retardant; long-term 90℃, short-circuit 250℃ max 5 s.
Terminals and insulation: tin-plated copper DT lugs and SC ferrules, hydraulic-crimped; 2:1 flame-retardant heat-shrink tubing; ABS insulating covers; epoxy insulating separators (≥10¹² Ω); PVC flame-retardant labels with cell numbers, polarity and circuit IDs.
8. Detailed Technical Design
8.1 Configuration Design by Backup Time (100 kW / 384V DC reference)
30 min: 192 × 2V 600AH, 6 standard cabinets, patrol system (192 voltage + current + temperature), DC 500V 630A breaker, 50×5 mm busbars, ZR-YJV 1×185 mm² cables.
1 h: 192 × 2V 1000AH, 8 cabinets, patrol (192 voltage + temperature, audible/visual), DC 500V 1000A breaker, 80×6 mm busbars, 1×240 mm² cables.
2 h: 192 × 2V 1500AH, 10 reinforced cabinets (single-layer), patrol with online resistance, DC 500V 1250A breaker, 100×8 mm busbars, 2×240 mm² parallel cables.
4 h: 384 × 2V 2000AH in two parallel groups, 24 custom forced-cooling cabinets, patrol 384 channels with dual main units and DCIM integration, per-group DC 500V 1600A breakers + 2500A total breaker, 120×10 mm busbars, 4×240 mm² parallel cables.
Warranty options: 1/3/5 years with different patrol frequencies (3-year standard: 2 visits/year; 4 h option: quarterly visits). Additional items (floor reinforcement, battery room retrofit, deep DCIM integration) quoted separately.
8.2 Selection and Matching Design
2V series for core rooms with large capacity, long backup and high reliability (better consistency, smaller failure impact, longer float life, lower replacement cost); 12V series for small/medium UPS with short backup and limited space (integrated, easy installation, lower initial cost); gel series for outdoor, wide-temperature and deep-cycle scenarios. Parallel groups ≤4 with identical cells; per-group breakers; equal wiring.
8.3 Safety and Protection Design
Per-group DC breaker + fuse; insulated terminals/busbars/covers; over/undervoltage and overtemperature alarms with circuit cut-off on serious faults; UL94 V-0 housings; steel cabinets; smoke detector positions; one-way safety valves; grounding ≤4 Ω; ESD wrist straps and insulating tools during O&M.
8.4 Monitoring and Management Design
Patrol system covers per-cell voltage, resistance and temperature plus group voltage and current; alarms via popup/sound/SMS/email; trend analysis and life prediction; remote capacity tests; DCIM/OPC/API integration; active balancing option; multi-level user permissions.
8.5 Commissioning Design
Full wiring/insulation/polarity checks before power-on; float/boost parameter setting; charging monitoring (current, per-cell voltage); alarm function tests (over/undervoltage, overtemperature); capacity verification discharge test; DCIM joint tests; documentation and training.
9. Recommended Configuration and Preliminary Budget
9.1 Configuration Summary
The following tables list reference configurations for 100 kW load / 384V DC bus (customizable per actual load, voltage and backup time):
30-minute backup:
| No. | Equipment | Specification | Qty | Unit |
|---|---|---|---|---|
| 1 | VRLA battery | 2V 600AH | 192 | cells |
| 2 | Standard battery cabinet | C-32 type, for 2V cells | 6 | pcs |
| 3 | Battery patrol system | 192 voltage + current + temperature | 1 | set |
| 4 | DC molded-case breaker | DC500V 630A | 1 | pc |
| 5 | Connection busbar | T2 tin-plated 50×5 mm | 30 | m |
| 6 | DC power cable | ZR-YJV 1×185 mm² | 20 | m |
| 7 | Auxiliary package | Terminals, ties, labels, ground wire | 1 | lot |
| 8 | Installation and commissioning | Includes capacity test | 1 | item |
| 9 | 3-year warranty service | 2 on-site patrols per year | 1 | item |
1-hour backup: 192 × 2V 1000AH; 8 × C-24 cabinets; patrol (192 voltage + temperature, audible/visual); DC500V 1000A breaker; 80×6 mm busbars; ZR-YJV 1×240 mm².
2-hour backup: 192 × 2V 1500AH; 10 reinforced single-layer cabinets; patrol with online resistance; DC500V 1250A breaker; 100×8 mm busbars; 2×240 mm² parallel.
4-hour backup: 384 × 2V 2000AH (two groups); 24 custom forced-cooling cabinets; patrol 384 channels, dual main units, DCIM integration; 2 × DC500V 1600A + 1 × 2500A breakers; 120×10 mm busbars; 4×240 mm² parallel.
9.2 Quotation Notes
The above are reference configurations for standard scenarios; the final price is calculated per actual configuration, construction difficulty and transport distance. Warranty options of 1, 3 and 5 years are available at different fees; additional needs such as floor reinforcement, battery room retrofit and deep DCIM integration are quoted separately. All products are original with complete test reports, certificates and warranty documents. All prices are indicative and quoted in RMB (CNY) only — no foreign-currency conversion is provided; the final quotation is subject to a formal quotation document.
10. Technical Specifications
10.1 System Performance Summary
| Item | Specification |
|---|---|
| Battery types | VRLA (AGM) 2V / 12V; gel 2V / 12V |
| Capacity range | 2V: 100-2000 AH; 12V: 24-250 AH; gel: 65-2000 AH |
| Voltage matching | 2V cells (192 cells @ 384V bus); 12V cells (32 @ 384V, 16 @ 192V) |
| Backup time | 30 min / 1 h / 2 h / 4 h configurations (customizable) |
| Float voltage | 2V: 2.23-2.27V; 12V: 13.5-13.8V; gel: 2.25-2.30V / 13.6-13.9V |
| Boost voltage | 2V: 2.30-2.35V; 12V: 13.8-14.1V; gel: 2.35-2.40V / 14.1-14.4V |
| Self-discharge | ≤1.5-3%/month by model (25℃) |
| Float design life | 2V: 10-18 years; 12V: 6-10 years; gel: 15-20 years (25℃) |
| Cycle life (80% DOD) | 2V ≥1200-1800; 12V ≥400-600; gel ≥800-2200 |
| Working temperature | -15℃~+45℃ (VRLA); -30℃~+55℃ (gel) |
| Monitoring | Per-cell V/R/T, group V/I; Modbus/SNMP; 256+ channels |
| Grounding | Cabinet ≤0.1 Ω terminal; system ≤4 Ω |
| Standards | GB/T 19638.2, YD/T 799, DL/T 637, DL/T 5044 |
| Warranty | 3 years VRLA / 5 years gel (options 1-5 years) |
10.2 Key Component Specifications
| Component | Key Parameters |
|---|---|
| 2V 600AH | 600/516/372 AH, ≤1.1 mΩ, 12-year float life, 38.5 kg |
| 2V 1000AH | 1000/860/620 AH, ≤0.7 mΩ, 15-year life, 64 kg |
| 2V 2000AH | 2000/1720/1240 AH, ≤0.36 mΩ, 18-year life, 128 kg |
| 12V 100AH | 100/85/55 AH, ≤6.5 mΩ, 8-year life, 31 kg |
| 12V 250AH | 250/212.5/137.5 AH, ≤2.8 mΩ, 10-year life, 76 kg |
| Gel 2V 2000AH | 2000 AH, ≤0.4 mΩ, 20-year life, -30~55℃, 135 kg |
| Cabinet DC-64-2V | 64 × 2V cells, 2.5 mm steel, ≥4000 kg, 800×800×2000 |
| Patrol main unit | ARM M4, 256 channels, ±2 mV, 7-in touchscreen, Modbus/SNMP |
| Acquisition module | 12/24 channels, ±2 mV, bus-powered, DIN rail |
| DC breaker | DC500V 63-1600A, 50 kA, arc ≤10 ms, 3C |
| Busbar | T2 copper tin-plated, 20×3 to 120×10 mm, 2.5 A/mm² |
| Power cable | ZR-YJV 0.6/1 kV, 10-240 mm², class B flame retardant |
11. Key Advantages and Customer Value
11.1 Product Performance Advantage
KITOZER lead-acid batteries use high-purity lead-calcium-tin alloy grids, micro-fiber separators and starved-electrolyte sealing — consistency, cycle life and high-current discharge performance at the industry frontier, fully matching UPS inverter instant-start and peak-load supply. The gel series adds wide-temperature adaptability and deep-cycle capability for outdoor and industrial environments. All products pass national authority testing, meeting telecom, power and finance industry admission standards.
11.2 System Design Advantage
The solution strictly follows GB 50174 and DL/T 5044 with high reliability as the core principle, refined design across capacity calculation, series/parallel matching, heat dissipation, wiring and safety. Capacity calculation fully considers temperature correction, aging and redundancy coefficients, guaranteeing backup time throughout the lifecycle; multi-level electrical protection precisely isolates faults; the monitoring system provides full-parameter online monitoring with early warning. Expansion interfaces are reserved for smooth growth, protecting investment.
11.3 Construction and Delivery Advantage
A self-owned professional construction team with certified workers and years of room power experience, familiar with room codes and safety management; dust, fire and electric-shock measures protect running equipment. Standardized processes from survey, confirmation, stocking, transport, installation to commissioning — standard projects delivered in 3-7 working days; urgent projects compress the schedule on demand.
11.4 After-Sales Advantage
A nationwide service network with 24-hour online service provides full-cycle support: free periodic patrol during warranty with formal reports; 7×24 fault response — 4-hour on-site in urban areas, 8 hours suburban; general faults resolved on site; extended warranty and annual maintenance contracts after warranty; a dedicated service specialist follows each customer one-on-one.
11.5 Total Lifecycle Cost Advantage
Long-life series batteries (2V float life 10-15 years) greatly reduce replacement frequency; maintenance-free design reduces manual O&M; the patrol system provides early fault warning, reducing outage risk and loss; professional periodic maintenance and capacity management extend actual service life — total lifecycle cost more than 30% lower than ordinary low-price battery solutions.
12. Technical Q&A (50+ Items)
12.1 Fundamentals
Q1: Why are VRLA batteries maintenance-free?
A: The starved-electrolyte design and oxygen-recombination principle: oxygen generated at the positive plate diffuses through the separator to the negative plate, reacting with lead to form water — water loss is extremely low in normal use, so no periodic water refilling is needed; the one-way safety valve exhausts only minimally at high internal pressure, otherwise fully sealed — achieving long-term maintenance-free operation.
Q2: What do float and boost charging do?
A: Float charging is the normal standby mode — continuous small current at constant low voltage compensating self-discharge and keeping the battery full; the normal state for backup power. Boost charging is equalizing charge at higher constant voltage with current limiting — used to rapidly restore capacity after deep discharge, or to correct per-cell deviation after long float, improving group consistency.
Q3: Under what conditions is rated capacity defined?
A: Rated capacity (usually the 10-hour-rate capacity) is defined at 25℃ ambient, discharging at constant current for 10 hours to the cell cutoff voltage (1.8V for 2V cells) — the total energy delivered. Lower temperature and faster discharge rates reduce actual deliverable capacity, so temperature and rate correction are needed in practice.
Q4: What is the core difference between gel and AGM batteries?
A: The electrolyte form: AGM absorbs liquid sulfuric acid in micro-fiber; gel fixes the electrolyte in a three-dimensional fumed-silica gel network. Gel has no flow (lower leakage risk), deeper cycle life and wider temperature adaptability; AGM has better high-current discharge and lower cost — the conventional choice for standard room backup.
Q5: How does the oxygen-recombination cycle prevent water loss?
A: During charging, oxygen generated at the positive plate migrates through the micro-fiber separator to the negative plate, where it recombines with lead to form lead oxide, then with sulfuric acid back to lead sulfate and water — closing the internal cycle and minimizing water loss, enabling sealed maintenance-free design.
Q6: What is the danger of thermal runaway?
A: At high temperature or overcharge, charging current rises, generating more heat, which further raises current — a self-reinforcing cycle that can deform, vent or ignite the battery. Temperature-compensated charging, correct float voltage and ventilation prevent it.
Q7: Why is voltage consistency important within a group?
A: Cells in series share the same current; inconsistent cells become overcharged or over-discharged, accelerating aging and reducing group capacity and life. Same-brand/batch cells plus equalizing charge keep deviation small (≤±50 mV float).
Q8: What is the sulfation failure mode?
A: Long-term undercharge or deep discharge forms hard lead sulfate crystals on the negative plate that no longer convert back during charging — capacity falls permanently. Periodic full charging and avoiding deep discharge prevent it.
Q9: How is battery capacity affected by temperature?
A: Capacity falls at low temperature (chemical reaction slows; e.g. -20℃ may deliver only ~60% for standard types) and life shortens at high temperature (grid corrosion and water loss accelerate; every +10℃ roughly halves life). Best operation at 20-25℃.
Q10: What is the role of the battery in the UPS system?
A: The battery is the UPS energy storage: it float-charges during normal mains and discharges instantly to feed the inverter on mains interruption, providing backup power for orderly shutdown or generator start — the last line of defense of room power safety.
12.2 Selection and Configuration
Q11: How is UPS battery capacity calculated?
A: The industry-standard constant-power method: total discharge power = load kW × 1000 / inverter efficiency; per-cell power = total / series cell count; look up the constant-power discharge table for the model at the required time and cutoff voltage to find capacity; multiply by temperature, aging (1.1-1.2) and redundancy (1.05-1.1) coefficients. Quick estimate: C(Ah) = (P W × T h) / (bus V × efficiency × capacity coefficient).
Q12: 2V or 12V batteries — how to choose?
A: Core rooms with large capacity, long backup and high reliability prefer 2V: better per-cell consistency, smaller failure impact, longer float life, lower replacement cost. Small/medium UPS with short backup and limited space use 12V: integrated, easy installation, lower initial cost.
Q13: Are more parallel groups always better?
A: No — too many groups worsen current imbalance and circulating current, accelerating aging and raising fault/maintenance complexity. Keep parallel groups ≤4; prefer increasing single-group capacity over adding groups.
Q14: Can different brands/capacities/ages be mixed?
A: No — different internal resistance and charge/discharge characteristics cause uneven charging, overcharge/overdischarge of some cells, rapid damage and safety hazards. One group must be the same brand, model, batch and age.
Q15: How is the series cell count determined?
A: Series cell count = UPS DC bus nominal voltage / cell nominal voltage (e.g. 384V / 2V = 192; 384V / 12V = 32). Use the configured count; wrong counts damage the charger or shorten backup.
Q16: What backup time should be configured?
A: With a generator: 0.5-1 h (generator start/switch). Without: 1-2 h general rooms, 4 h+ for core rooms with poor mains. Balance cost and utilization — over-long backup means high cost and low battery utilization.
Q17: AGM or gel for outdoor/industrial sites?
A: Gel — wider temperature range (-30℃~+55℃), lower self-discharge, deeper cycles, no stratification; AGM for standard indoor rooms where high-current discharge and cost matter more.
Q18: How does the maximum charge current affect charging time?
A: Recommended 0.1-0.2C (e.g. 0.1C = 100A for 1000AH); higher current charges faster but raises temperature and grid corrosion. The UPS charger limits current automatically; oversized chargers should be configured per the battery spec.
Q19: What does the temperature compensation coefficient do?
A: Float voltage adjusts with temperature (-3 mV/℃/cell for 2V) — lower voltage at high temperature prevents overcharge; higher at low temperature prevents undercharge — extending battery life across seasons.
Q20: How is a specific project’s configuration validated?
A: The supplier performs the constant-power calculation per actual load, bus voltage and backup time, then verifies with a capacity (discharge) test at commissioning; documentation includes the calculation basis and test report.
12.3 Installation and Construction
Q21: What are the floor load requirements?
A: Lead-acid batteries are heavy — a 2V 1000AH cell weighs ~64 kg; 192 cells exceed 12 tons plus cabinets. Verify the room floor capacity before installation; use distributed placement, support stands or floor reinforcement if insufficient.
Q22: Where should batteries be installed?
A: Well-ventilated, even-temperature areas away from heat sources, direct sunlight and AC direct blow; ≥500 mm maintenance aisles; no corrosive gas or strong electromagnetic interference; no water/steam pipes above; large groups prefer a dedicated battery room, otherwise same-room installation is acceptable for sealed types.
Q23: Why busbars instead of ordinary cables for connections?
A: At high current, busbars carry more current, dissipate heat better, have lower connection resistance and loss, are structurally stable and reliable long term without loosening or oxidation; cables suit small-current short connections; large series/parallel loops prefer busbars.
Q24: What are the grounding requirements?
A: Battery cabinet metal enclosures connect reliably to the room protective ground (≤4 Ω) for ESD and personnel safety; DC working ground per UPS requirements — never mixing working and protective grounds; monitoring equipment grounded separately to avoid interference.
Q25: What is the installation process?
A: Cabinet positioning and leveling (deviation ≤1 mm/m), grounding; battery inspection (appearance, open-circuit voltage); placement per number order with correct polarity and insulation pads; series connections with torque-controlled bolts; group voltage verification before main-circuit connection; wiring (power/communication separated ≥50 mm, crimped terminals, labels); patrol system deployment; commissioning tests.
Q26: What torque is required for connection bolts?
A: Per the battery manufacturer’s spec (typically 10-20 N·m by terminal size), applied with a torque wrench; ≥10% of connection points are sampled per batch with deviation ≤±10%; proper torque ensures low resistance without terminal damage.
Q27: What are the pre-power checks?
A: Verify all wiring correctness, insulation (power to ground ≥10 MΩ, communication ≥2 MΩ), polarity (100% check, no reverse), connection tightness, and no tools/debris left; then energize the charging circuit.
Q28: How long does a standard project take?
A: About 7 working days for a standard 100 kW/1 h/192-cell project: preparation 1, survey 1, delivery 1, installation 2, commissioning 1, acceptance 1; urgent projects can be compressed to 3 working days.
Q29: What safety measures apply during installation?
A: Certified electricians; temporary power with RCDs; live work in pairs with insulated tools; battery circuit work after de-energizing; helmets, insulating shoes and PPE; correct lifting with multiple workers; electrolyte contact flushed with water immediately; no smoking or open flame.
Q30: Can batteries be installed in the same room as servers?
A: Yes for sealed VRLA/gel types — no acid mist, no electrolyte leakage, flame-retardant housings; ensure ventilation and temperature control; verify the room’s fire code allows it or provide a dedicated battery room for large groups.
12.4 O&M
Q31: What daily maintenance is required?
A: Periodic cleaning of surface dust; terminal checks for loosening, heating and corrosion; per-cell float voltage and group voltage measurement with consistency checks; patrol system data and alarm review; capacity (discharge) verification test every 1-2 years.
Q32: What is the impact of high or low float voltage?
A: High float causes overcharge — grid corrosion, water loss, shortened life, possible thermal runaway; low float causes undercharge — sulfation, falling capacity, eventual failure. Set the correct float voltage and enable temperature compensation.
Q33: Will long-term storage damage batteries?
A: Self-discharge depletes stored batteries; deep depletion causes irreversible sulfation. Recharge every 3 months at room temperature (2 months in high-temperature storage); store fully charged in a dry, ventilated place at 0-25℃.
Q34: When should batteries be replaced?
A: Capacity test below 80% of rated; float deviation exceeding ±100 mV not recoverable by boost; physical damage (swelling, leakage, casing cracks); internal resistance above 1.5× initial and rising; end of design float life — plan replacement to avoid sudden failure.
Q35: What does the capacity verification test involve?
A: A controlled discharge at a defined rate (e.g. to a set SOC or voltage) with per-cell and group data recorded, then recharge; actual capacity is compared with rated and the report documents remaining life; the patrol system supports remote initiation.
Q36: How is the patrol system used daily?
A: View group voltage/current and per-cell data on the touchscreen or remotely; review alarms and trends; export reports; run scheduled battery tests; check communication status with the DCIM platform.
Q37: How are alarms interpreted?
A: Overvoltage/undervoltage — charging settings, cell aging, loose connections; overtemperature — environment, overcharge, internal fault; resistance anomaly — aging cells, loose terminals; communication fault — bus wiring/addresses; each alarm prompts the corresponding check.
Q38: How often should connections be re-tightened?
A: At every patrol (quarterly/semi-annual) check torque and thermal scan; re-tighten per spec if loose; thermal imaging during discharge reveals high-resistance joints.
Q39: What environment conditions should be maintained?
A: Temperature 20-25℃ (best), humidity within range without condensation, clean dust-free space, adequate ventilation; monitor with the room environment system and alarms for deviation.
Q40: Is operator training provided?
A: Yes — 1-day training at acceptance (theory + hands-on): multimeter measurement, thermal scan, patrol procedures, patrol system operation, discharge test flow, alarm handling, emergency drills; written + practical assessment with certification and free retraining.
12.5 Fault Finding
Q41: Group voltage is low — causes?
A: Float voltage set too low (undercharge); frequent outages with insufficient recharge; group at end of life with overall capacity decline; severely degraded lagging cells pulling the group down. Check charging parameters first, then per-cell voltages to locate lagging cells.
Q42: Batteries run hot — what is wrong?
A: Normal float produces slight warmth; obvious heating suggests: float voltage too high (overcharge); high ambient temperature or poor heat dissipation; internal micro-short with high self-discharge; excessive charge current or long boost. Immediately reduce voltage or stop charging and investigate to avoid thermal runaway.
Q43: Per-cell voltage inconsistency — how to fix?
A: Minor deviation — 1-2 equalizing charges usually corrects it; if a lagging cell persists, test its resistance and capacity; replace severely degraded cells with same-spec units; if the whole group is inconsistent with low capacity, the group is at end of life — replace it.
Q44: A cell leaks electrolyte — can it stay in service?
A: No — leakage means seal failure: electrolyte corrodes equipment and cabinets, risks chemical burns, capacity falls fast, resistance rises, and short-circuit/fire risk increases. Isolate and replace the cell immediately, neutralize and clean the spill area.
Q45: The DC breaker trips — what to do?
A: Do not re-close blindly; check for short circuits (loose terminals, insulation damage, water/debris), verify load current, measure insulation; clear the cause, then re-close and monitor; if the cause is unclear, engage a professional survey.
Q46: Backup time is shorter than designed — why?
A: Actual load larger than designed; battery aging (capacity decline); low ambient temperature; long float without discharge (fade); verify load, run a capacity test, and replace aging cells.
Q47: A cell swells — causes and action?
A: Overcharge, high temperature, valve failure or internal short; swelling indicates serious degradation and fire risk — remove from service, isolate the group, replace the cell, and check charging parameters and ventilation.
Q48: The patrol system reports resistance rising — what does it mean?
A: Rising internal resistance indicates grid corrosion, sulfation or terminal issues; compare with initial baseline (1.5× triggers warning); check terminals first, then capacity; plan replacement of cells with confirmed degradation.
Q49: What is the emergency flow for a short-circuit spark?
A: Open the upstream DC breaker immediately; extinguish minor fire with dry-powder extinguisher; locate the short point, repair, test insulation, verify before restoring; assess battery/equipment damage and make a repair plan.
Q50: When should the manufacturer be called?
A: For persistent faults without identified causes, group-level replacement, capacity planning, DCIM integration issues, or any work on energized battery circuits — engage certified engineers rather than risk unsafe intervention.
12.6 Service and Lifecycle
Q51: What is the warranty?
A: 3-year whole-unit warranty on VRLA batteries, 5 years on gel, 2 years on cabinets and patrol systems, from acceptance; quality faults repaired/replaced free (no parts/labor/travel fees); 1/3/5-year extended warranty options.
Q52: What is the response commitment?
A: 7×24 service: engineer call-back within 30 minutes; remote resolution within 2 hours; on-site within 4 hours urban / 8 hours suburban / 24 hours remote; general faults fixed on site in 2 hours; major faults solved within 24 hours with standby equipment and full repair within 72 hours.
Q53: What does the patrol service include?
A: Free periodic on-site patrol during warranty (2/year standard, quarterly for core projects): appearance check (swelling, leakage, corrosion), per-cell/group voltage and float current recording, terminal checks and re-tightening, resistance sampling, cabinet and grounding checks, patrol system calibration, and a formal report with recommendations.
Q54: What value-added services exist?
A: Annual capacity test with professional reports; remaining-life assessment with replacement planning; free lifetime monitoring software upgrades; annual advanced O&M training; free lifetime technical consultation and optimization advice.
Q55: How are spare parts guaranteed?
A: Regional warehouses stock common batteries, breakers and monitoring modules for fast supply; compatible replacements for discontinued models; long-term original parts at preferential prices after warranty without bundled services; optional on-site spare stock.
Q56: Can the system be expanded later?
A: Yes — reserved cabinet space and parallel group positions; add groups in parallel (≤4 total) with per-group breakers and matched cells to extend backup time; verify UPS charger capacity for the added groups.
Q57: What documentation supports acceptance?
A: Test reports, certificates of conformity, type test reports, capacity calculation basis, wiring diagrams, installation and commissioning records, discharge test reports and warranty documents — satisfying room construction and filing requirements.
Q58: What are the green credentials?
A: Lead paste and electrolyte are sealed and recoverable; production complies with national environmental requirements; RoHS compliant; high charge/discharge efficiency (≥90%) reduces charging loss; recycling services are available for retired batteries.
Q59: How is service quality supervised?
A: A service supervision hotline accepts complaints and suggestions; satisfaction follow-up after every service; dedicated project files record the full lifecycle; patrol reports are delivered to the owner for traceability.
Q60: How does the solution reduce total cost?
A: Long-life batteries cut replacement frequency; maintenance-free design cuts labor; early warning prevents outage losses; professional capacity management extends actual life; versus ordinary low-price solutions, total lifecycle cost is reduced by over 30%.
13. Construction Schedule
13.1 Stage Division
The project delivery is divided into six core stages: preparation, site survey, equipment arrival, installation and wiring, commissioning and testing, and acceptance and handover.
13.2 Standard Project Schedule (100 kW / 1 h / 192 × 2V, 7 Working Days)
| Stage | Work | Day | Responsible | Deliverable |
|---|---|---|---|---|
| Preparation | Contract confirmation, technical disclosure, stocking, construction plan | 1 | PM, procurement | Plan, material list, drawings |
| Site survey | Re-measurement, floor load check, position confirmation, power/ground points | 2 | Engineer, foreman | Survey report, layout drawing |
| Equipment arrival | Transport, unpacking inspection, quantity/appearance check, documentation | 3 | Foreman, owner contact | Incoming acceptance, certificates |
| Installation and wiring | Cabinet positioning, battery placement, busbar/cable connection, distribution, grounding, patrol deployment | 4-5 | Crew | Completed installation, wiring records |
| Commissioning | Insulation tests, charge/discharge commissioning, patrol joint tests, alarm tests, capacity verification | 6 | Engineer | Commissioning and test reports |
| Acceptance and handover | As-built documentation, customer acceptance, operation training, project handover | 7 | PM, owner contact | Acceptance report, full documentation |
13.3 Urgent Project Schedule (3 Working Days)
Day 1: solution confirmation + stocking + site survey in parallel, equipment arrives in the evening; Day 2: full-day installation, wiring and grounding; Day 3: commissioning + acceptance + brief training. A dedicated crew and commissioning engineer prioritize material and personnel dispatch, compressing the schedule while maintaining quality and safety.
13.4 Schedule Assurance
Personnel: a dedicated PM coordinates; fixed crew without cross-assignment. Materials: safety stock of common batteries, cabinets and auxiliaries for immediate dispatch. Plan control: daily progress updates with risk prediction and adjustment. Coordination: advance confirmation of entry time, room access and outage windows. Contingency: standby materials and substitute personnel for immediate cover.
14. Construction Organization and Quality/Safety Measures
14.1 Organization Structure
Project manager: overall responsibility for progress, quality, customer liaison and resource coordination. Technical engineer: solution implementation, site guidance, commissioning, technical problem solving. Foreman: crew management, plan execution, workmanship and site safety, daily meetings. Construction staff: certified electricians and installers for installation, wiring and grounding. After-sales specialist: post-delivery liaison, patrol scheduling and fault response.
14.2 Pre-Construction Preparation
Technical: internal review of drawings and solution; work-instruction documents (torque, wiring, grounding details); calibrated instruments (multimeter, resistance meter, torque wrench); technical and safety training with qualification before entry.
Materials: stocking per configuration list with model/quantity verification; appearance and documentation check; auxiliary materials (cables, busbars, terminals, ties, grounding); classified packing with transport protection.
Site: confirm entry time, room access procedures and construction power; verify level floor and load capacity, clear obstacles; confirm UPS DC input positions and ground points, plan cable routes; temporary barriers and warning signs demarcating the work area.
14.3 Core Construction Processes
Cabinet installation: position per layout drawing, level and plumb (deviation ≤1 mm/m); side-by-side cabinets joined evenly; expansion-bolt or counterweight fixing per floor load; grounding connected and tested.
Battery installation: unpack and inspect (no damage, leakage or deformation; normal open-circuit voltage); place per number order with correct polarity, stable and aligned; insulation pads between cells; series busbars/links with code torque; verify group voltage and polarity before main-circuit connection.
Wiring: power and communication cables on planned routes, separated ≥50 mm; crimped terminals with number tubes and clear labels; breakers and UPS terminals connected with code torque and correct polarity; tidy ties with bend radii; insulating covers on all live parts.
Patrol system installation: mount the main unit in the standard cabinet; install acquisition modules with per-cell sampling wires; install temperature and current sensors in accurate positions; power on, configure parameters, test data acquisition and alarms; verify DCIM integration.
Commissioning: full wiring/insulation/polarity check; close the charging circuit, set float/boost parameters, start charging; monitor current and per-cell voltage; alarm function tests (over/undervoltage, overtemperature); loaded or capacity verification discharge test confirming backup duration.
14.4 Quality Control
Three-level inspection: self-inspection per process; foreman daily mutual inspection with rectification; engineer special inspection of key processes with records.
Key process control: connection torque with torque wrench (≥10% sampling, deviation ≤±10%); insulation resistance (power to ground ≥10 MΩ, communication ≥2 MΩ); polarity 100% checked, no reverse; ground resistance ≤4 Ω.
Documentation: full installation, test and rectification records; accurate signed data as as-built documentation; photos of concealed works for traceability.
14.5 Safety and Civilized Construction
Electrical safety: temporary power from designated points with RCDs; live work in pairs (one operator, one watcher); intact insulated tools; battery circuit work after de-energizing; no large-area live work.
Fire safety: no smoking or open flame; extinguishers on site with trained staff; flammable materials stored separately from heat and live parts; daily power cut-off and fire-hazard check after work.
Personnel safety: helmets, protective shoes and PPE; correct lifting with multiple workers; electrolyte contact flushed with water immediately; stable ladders for high work, no cabinet climbing.
Civilized construction: materials stacked neatly without blocking fire/O&M lanes; daily site cleaning with packaging waste removed; dust control protecting room equipment; observe room rules, no touching unrelated equipment, no noise.
14.6 Construction Contingency Plans
Electric shock: cut power or separate with insulating tools; move to ventilated area, check breathing/heartbeat, CPR if needed; call emergency number, report to the PM; preserve the scene and investigate the cause.
Electrolyte leakage: isolate the leaking cell and open the circuit; neutralize with baking soda wearing rubber gloves and goggles; wipe clean and collect waste (never drain); check adjacent equipment for corrosion; replace the cell and investigate the cause.
Short-circuit spark: open the upstream breaker immediately; extinguish minor fire with dry-powder extinguisher; locate and repair the short, test insulation, verify before restoring; assess damage and make a repair plan.
Personnel injury: minor injuries with the first-aid kit; serious injuries sent to hospital and reported; suspend related work, analyze the cause, rectify before resuming.
15. After-Sales Service
15.1 Warranty Commitment
VRLA batteries: 3-year whole-unit warranty; gel batteries: 5 years; battery cabinets and patrol systems: 2 years — from qualified acceptance. During warranty, quality faults under normal use are repaired/replaced free with no parts, labor or travel fees. Artificial damage, misuse and force majeure are excluded. Extended warranty options of 1, 3 and 5 years are available.
15.2 Response Standards
7×24 service: engineer call-back within 30 minutes with remote guidance; remote resolution within 2 hours; on-site within 4 hours urban / 8 hours suburban / 24 hours remote; general faults fixed on site within 2 hours; major faults solved within 24 hours with standby equipment and full repair within 72 hours.
15.3 Periodic Patrol Service
Free periodic on-site patrol during warranty (2/year standard; quarterly for large core rooms): appearance check (swelling, leakage, corrosion); per-cell/group voltage and float current recording; terminal checks with re-tightening; resistance sampling and health assessment; cabinet and grounding checks; patrol system calibration; a formal patrol report with O&M advice and risk prompts.
15.4 Repair Service
Full system detection and precise fault positioning; quality faults within warranty replaced free; out-of-warranty or artificial faults repaired per clear quotation after confirmation; standby batteries/equipment for temporary substitution when core parts cannot be repaired quickly; a fault analysis report after repair with cause, process and prevention.
15.5 Spare Parts Assurance
Regional warehouses stock common batteries, breakers and monitoring modules for fast supply; compatible replacement models for discontinued products; long-term original parts at preferential prices without bundled services; optional on-site spare stock for rapid emergency replacement.
15.6 Value-Added Services
Annual professional capacity (discharge) test with reports; remaining-life assessment with replacement planning; lifetime free monitoring software upgrades and hardware expansion; annual advanced O&M training; lifetime free technical consultation and optimization advice.
16. Training Plan
16.1 Objectives and Audience
Objectives: enable the customer’s O&M staff to fully master the battery system’s working principles, operation, daily maintenance, common fault finding and emergency handling, and independently perform daily O&M.
Audience: the customer’s room O&M staff, electricians and IT center technicians, 2-4 persons with basic electrical knowledge.
16.2 Theory Training Content
Fundamentals: battery working principle, structure and performance; VRLA vs. gel differences and scenarios; charge/discharge principles, float/boost functions and parameter setting; key life factors; the battery’s role in the UPS supply system.
System and products: overall architecture and configuration of this project; technical parameters of each model; cabinet, DC distribution and monitoring system composition and functions; electrical schematic explanation, circuit routing and protection configuration.
O&M standards: patrol content, cycles and methods; normal ranges and anomaly criteria for voltage, resistance and temperature; charge/discharge operation standards; room environment requirements; relevant national and industry O&M codes.
Safety and emergency: battery operation safety; common fault phenomena and emergency flows; handling of leakage, short circuit and overheating; personal protection and first aid.
16.3 Hands-On Training Content
Patrol practice: multimeter measurement of per-cell and group voltage; thermal measurement of cell and terminal temperature; terminal tightness and appearance checks; patrol system operation (data viewing, history, alarm handling).
Charge/discharge practice: UPS battery-mode switching; boost parameter setting and start; capacity verification discharge test flow and precautions; data recording and status observation during discharge.
Fault handling practice: per-cell voltage anomaly troubleshooting; alarm identification and handling; DC breaker trip reset and investigation; lagging-cell identification and temporary handling.
Safety drills: battery handling and installation; correct use of insulated tools; leakage emergency handling; electric-shock rescue simulation.
16.4 Methods and Schedule
Training at acceptance over 1 working day, theory + hands-on with practice first: morning theory and architecture (~3 h); afternoon hands-on practice and Q&A (~4 h). Face-to-face lecture + live demonstration + trainee operation + interactive Q&A; schedule adjustable; online training available.
16.5 Assessment and Certification
Theoretical written test (100 points, 80 pass) plus practical assessment (independent patrol, alarm handling, parameter viewing, scored by standardization and completion). Qualified trainees receive a certificate; those who fail get free retraining until mastered. Full courseware and the O&M manual are delivered for later reference.
16. Training Plan
16.1 Training Objectives and Audience
Training objectives: through systematic training, enable management personnel to fully understand the system structure, working principles and performance characteristics, master daily operation methods and inspection/maintenance essentials, identify common faults and handle simple problems, ensuring safe, stable and long-term operation.
Training audience: management and O&M personnel designated by the client, recommended 2-3 persons with basic electrical and equipment knowledge.
16.2 Tiered Training Content System
Level 1: Basic operation training (1 day)
– Basic principles: system concepts, structure composition, performance indicators;
– Daily operation standards: correct operation of equipment, control and safety systems;
– Daily inspection contents: daily/weekly/monthly check items;
– Safety precautions: usage prohibitions and emergency handling procedures.
Level 2: Maintenance training (1 day)
– Detailed structure of each subsystem and working principles;
– Daily maintenance methods: cleaning, fastening checks, routine care;
– Common fault identification and simple handling;
– Emergency handling procedures for power failure, fire and equipment faults.
Level 3: Advanced management training (as needed)
– Performance influencing factors and how to avoid degradation;
– Upgrade and expansion knowledge and specification requirements;
– Relevant national standards interpretation.
16.3 Training Methods and Schedule
– Methods: combination of “theory explanation + on-site practice + Q&A interaction”;
– Schedule: training arranged at the completion acceptance stage, synchronized with handover, 2 days of intensive training total; time flexibly adjustable; a free repeat training session is provided for newly assigned personnel.
16.4 Training Assessment and Documentation Delivery
– Assessment: theory written test plus practical operation; training qualification certificates issued upon passing; supplementary training for those who fail;
– Documentation delivery: complete O&M documentation, including operation and maintenance manual, equipment manuals and certificates, completion drawings and hidden work records, test reports and after-sales service contact card, all bound into volumes.
17. Anonymous Typical Project Scenarios
All project scenarios below are anonymous, generalized examples provided for reference only. No real customer names, addresses or identifiable details are disclosed.
17.1 Government Data Center Room Battery Project
Project background. A municipal government data center core room upgrade required a highly reliable backup power system keeping government services running and meeting Class-3 classified-protection requirements.
Implementation. 384 × 2V 1200AH VRLA batteries in two parallel groups, with an intelligent patrol system and reinforced battery cabinets, providing 2-hour backup.
Highlights. Designed strictly to Class A data center standards with redundant configuration and full-parameter online monitoring; zero-outage cutover construction without affecting existing business; stable operation after delivery, passing classified-protection assessment and industry acceptance.
Customer evaluation. Stable product quality, professional and standardized construction, timely after-sales response — effectively safeguarding government system power supply.
17.2 Enterprise Headquarters Core Room Battery Project
Project background. A large technology enterprise’s headquarters data center carrying core business systems and data storage demanded extremely high supply reliability and maintainability.
Implementation. 192 × 2V 1000AH long-life batteries (15-year design float life), integrated battery cabinets and environment-monitoring integration, providing 1-hour backup.
Highlights. Long-life series batteries; the patrol system provides online resistance monitoring warning of battery degradation in advance; customized layout adapted to the room space with tidy, standardized wiring meeting high data center standards.
Customer evaluation. Sound design, refined workmanship, convenient O&M, three years of operation without any fault.
17.3 Tertiary Hospital Information Room Battery Project
Project background. A tertiary hospital’s core information room carrying HIS, LIS and PACS systems — power interruption directly affects diagnosis and treatment, with strict reliability and emergency requirements.
Implementation. 64 × 12V 100AH VRLA batteries in two parallel groups, medical-grade power assurance scheme, 30-minute backup.
Highlights. Products passed medical-industry certification, no acid mist — adapted to the hospital’s clean environment; construction strictly followed hospital infection-control requirements with dust-free operation; 7×24 emergency service with 2-hour response.
Customer evaluation. Professional service and rapid response fully meeting hospital power needs — multiple outages switched smoothly, keeping medical services continuous.
18. SEO Optimization Section
All reference prices in this technical solution are in RMB (CNY) only and are for reference purposes; final quotation is subject to the confirmed configuration.
18.1 Keyword System
– Core keywords: technical design solution, system configuration, technical parameters, construction and O&M services;
– High-conversion long-tail keywords: design solution, configuration list, technical parameters, construction plan, after-sales service;
– Industry traffic keywords: system architecture, applicable standards, technical Q&A, project cases;
– Brand keywords: KITOZER, Guangzhou Lain.
18.2 SEO Tag System
– Title tag: the article title — Guangzhou Lain KITOZER;
– Meta description: Guangzhou Lain professionally provides complete technical design solutions with detailed configuration list, full-system product technical parameters, construction organization plan and after-sales service — source manufacturer customization, compliant performance, third-party testing supported;
– H1 tag: the article title;
– H2 tags: system design and product parameters, construction organization plan, after-sales service and training, engineering cases.
18.3 Internal Link Anchor Text
– Core anchor text: technical design solution, system construction;
– Long-tail anchor text: configuration list, technical parameters, construction plan;
– Related anchor text: shielding cabinet, micro-module cold aisle, integrated computer room, outdoor cabinet.
19. Official Contact Information
– Company Name: Guangzhou Lain Intelligent System Development Co., Ltd.
– Brand: KITOZER (Pioneer)
– Official Website: https://gdlain.com
– Tel: +86 13538869979 (Tel / WhatsApp)
– Address: No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou, China
For any inquiries about this technical design solution, configuration customization, quotation or construction services, please contact us through the information above. We provide free design consultation and tailored solutions for your specific requirements.