KITOZER
KITOZER

Water Leakage Monitoring System Hardware Configuration

Table of Contents

1. Cover / Document Information

– Document Title: Water Leakage Monitoring System Hardware Configuration Technical Design Solution

– Prepared by: Guangzhou Lain Intelligent System Development Co., Ltd.

– Brand: KITOZER (Pioneer)

– Date: August 2026

– Version: V1.0

– Project Type: Technical design solution for Water Leakage Monitoring System Hardware Configuration

2. Table of Contents Structure

1. Company Introduction

2. Project Overview

3. User Requirement Analysis

4. Overall Design Description

5. Detailed System Design and Product Technical Parameters

6. Project Quotation and Configuration List

7. Core Solution Advantages

8. Technical Q&A

9. Construction Schedule Plan

10. Construction Organization Plan

11. After-Sales Service System

12. Operation and Maintenance Training Plan

13. Typical Project Cases

14. SEO Optimization System and Website Backend Configuration

15. Contact Information

3. Company Introduction

3.1 Company Development Overview

Founded in 2002, Guangzhou Lain Intelligent System Development Co., Ltd. is a high-tech enterprise dedicated to the computer room construction and intelligent protection field for more than two decades, integrating R&D, production, sales, engineering implementation and after-sales service. The company focuses on innovative breakthroughs in electromagnetic shielding technology, modular computer room technology and computer room environmental monitoring technology, and has grown into a source manufacturer with core competitiveness in the domestic computer room construction field.

After more than twenty years of industry accumulation, the company has built a large-scale production and manufacturing base equipped with advanced CNC sheet metal processing equipment, automated spraying production lines and professional testing laboratories, with an annual production capacity of hundreds of sets of shielding computer rooms, integrated cabinets and micro-module products. The company’s service network covers all provinces and cities across the country, providing thousands of computer room construction and renovation services for customers in government, military, scientific research, finance and enterprise fields.

3.2 Core Business System

The company’s core business revolves around the full-lifecycle construction of computer rooms, forming four major product and service systems:

– Computer room EPC general contracting service: one-stop services from solution design, manufacturing, on-site construction to commissioning and acceptance, covering shielding computer rooms, IDC data rooms, modular computer rooms, container computer rooms and other types;

– Core equipment R&D and production: independently produces KITOZER brand series products, including shielding cabinets, shielding desks, consoles, integrated data cabinets, micro-module cold aisle cabinets, outdoor rainproof cabinets, etc., supporting non-standard customization;

– Computer room environmental monitoring system: provides full-element monitoring solutions for temperature and humidity, water leakage, access control, video, fire protection, UPS and power distribution, realizing intelligent and unattended O&M;

– Shielding and security protection products: shielding rooms, shielding doors and windows, anechoic chambers and related auxiliary materials, widely used in confidential, military and scientific research fields.

3.3 Brand and Qualification Honors

The core brand KITOZER (Pioneer) focuses on computer room equipment and shielding products, positioned as an “efficient, green, innovative and safe” solution provider. Products have passed multiple authoritative tests and comply with national and industry standards. The company holds multiple utility model patents and software copyrights, has been awarded high-tech enterprise qualification, and follows the ISO9001 quality management standard.

3.4 Core Competitive Advantages

1. Source production, controllable quality: own production base and professional processing equipment; core products independently produced with full-process quality control, providing more cost-effective solutions without intermediate links;

2. Customized design, matching needs: tailor-made solutions per site conditions, technical requirements, configuration and budget, with multiple design options provided free of charge;

3. Professional team, rich experience: a professional technical team of engineers and project managers with more than ten years of industry experience;

4. Quality after-sales, full guarantee: a 7×24 professional online service system with dedicated project follow-up from early coordination to later O&M.

4. Project Background and Objectives

4.1 Project Background

With the widespread use of precision air conditioners, chilled-water systems, fire sprinkler piping and water-supply lines in data centers, communication rooms, underground pipe galleries and warehouses, water leakage has become a major hidden threat to equipment and business continuity. Traditional leak response relies on manual patrols and post-incident discovery — slow, costly and often too late.

4.2 Leak Hazards and the Necessity of Monitoring

Equipment damage and business interruption: water intrusion into servers, switches and power equipment causes short circuits, corrosion and total failure. For finance, communication, medical and government sectors, equipment failure interrupts business services — direct revenue loss, brand damage, compliance risk and legal liability.

Safety hazards: water contact with power lines may cause electric shock, short circuit and fire, threatening personnel; long-term water erosion accelerates building and cable degradation.

Difficult tracing, long recovery: traditional post-leak inspection section by section — especially concealed piping and under-floor areas — makes location hard and recovery slow, enlarging losses.

Necessity: a leak monitoring system provides 24-hour monitoring with proactive warning — detection time from “hours” to “seconds”; locating leak-detection cable pinpoints positions within 1m for fast handling; unattended operation cuts labor; relay linkage enables automatic drainage/valve closure and higher safety.

4.3 Project Objectives

Full coverage: 24m of locating leak-detection cable for continuous monitoring along pipelines plus one point-type floor-water sensor at a key low-lying area — a “line + point” full-coverage network with no blind spots.

Precise and reliable: second-level response, meter-level location accuracy, alarm accuracy ≥99%; broken-line self-check and anti-interference prevent false/missed alarms.

Unified control: both monitoring modes connect to one controller — unified acquisition, management and upload; fewer devices, simpler architecture, lower O&M complexity.

Seamless integration: standard RS485 with Modbus RTU protocol connects directly to the customer’s existing central platform without extra monitoring software — protecting existing investment.

Stable and durable: industrial-grade design adapting to site temperature/humidity; anti-interference and corrosion resistant; MTBF ≥100,000h.

4.4 Applicable Scenarios

Data centers/IDC/server rooms/network rooms; communication base stations, optical distribution boxes, communication rooms; museums, archives, libraries, warehouses; underground pipe galleries, metro tunnels, underground parking; hospital clean rooms, pharmaceutical warehouses, laboratories; industrial plants, automation control rooms, distribution rooms; building equipment floors and water-pipe shafts of offices and hotels.

5. User Requirement Analysis

5.1 Core Hardware Requirements

Locating leak monitoring: 24m total of locating leak-detection cable laid along water pipes, AC lines and cabinet bases for continuous monitoring with precise positioning.

Floor-water monitoring: one point-type floor-water monitoring set for fixed-point detection at low-lying areas and entrances.

Control equipment: one leak alarm controller connecting both types, with unified data acquisition/processing and an RS485 interface supporting standard industrial protocols.

5.2 Functional and Performance Requirements

Alarms: immediate alarm on leak detection; local audible/visual alarm and upload to the central platform; multiple alarm types (leak alarm, broken-line fault alarm). Location: meter-level location accuracy showing the distance from the controller. Reliability: strong anti-interference and environmental adaptation; no false/missed alarms in complex industrial EM environments. Maintainability: simple installation, commissioning and maintenance; cable reusable; sensor auto-resets when dry — no sensor replacement.

5.3 Communication and Integration Requirements

RS485 hardware interface with standard Modbus RTU protocol for direct central-platform integration; uploaded signals include leak alarm status, fault status, leak location data and device running status; configurable baud rate and device address.

5.4 Construction and Delivery Requirements

Complete hardware with installation auxiliaries — no extra procurement; multiple mounting options adapting to site conditions; simple quick construction with minimal impact; complete technical documentation (manuals, parameter handbook, wiring drawings) at delivery.

6. Design Principles and Applicable Standards

6.1 Design Principles

Reliability first: industrial-grade components, mature detection technology, multi-layer anti-interference and self-check — no missed alarms, few false alarms. Advancement + practicality: mainstream locating-leak detection and digital communication; practical cost-effective configuration. Openness and compatibility: standard protocols and universal interfaces for direct platform integration and expansion. Expandability: spare I/O channels and cable-length margin for future points/lengths without controller replacement. Easy maintenance: simple architecture, reusable cable, convenient troubleshooting and part replacement. Economy: optimized configuration and integrated design minimizing full-lifecycle cost.

6.2 Applicable Standards

GB 50174-2017 (data center design), GB 51348-2019 (civil building electrical), GB 50093-2013 (industrial automation instrument installation and acceptance), GB 50057-2010 (lightning protection), GB 50054-2011 (low-voltage distribution), YD/T 2164-2010 (communication station water-immersion alarm), Modbus Application Protocol V1.0, GB 50348-2018 (security engineering), GB 4943.1-2022 (IT equipment safety), plus customer requirements.

7. System Architecture and Working Principle

7.1 Overall Architecture

Three-layer architecture: perception layer — locating leak-detection cable (distributed sensing electrodes; resistance change on contact with conductive liquid determines leak position) and electrode point-type water immersion sensors (dual-electrode conduction); control/transmission layer — the locating leak alarm controller acquires, analyzes and processes signals, executes alarm logic, uploads via RS485 and drives relay outputs (siren, drain pump); platform application layer — the customer’s existing central platform receiving data for display, storage, alarm notification, history and statistics (hardware + standard interface only; no platform software included).

7.2 Networking Design

Star topology “one controller + multiple sensing devices”: cable via dedicated lead-in to the leak-detection terminals; point sensors via signal cable to dry-contact inputs, all powered by the controller; controller as Modbus RTU slave on RS485 (RVSP 2×1.0mm² shielded twisted pair, single-end earthed, bus topology hand-in-hand, ≤1200m at 9600bps, TVS + opto-isolation on the port, 120Ω termination resistors at both ends recommended).

Feasibility of sharing one controller: independent isolated hardware channels — no cross-talk; high-performance industrial microprocessor with parallel multi-channel scanning — second-level response unaffected; unified protocol upload with different register addresses distinguishing points.

7.3 Working Principle

Locating monitoring: the cable contains two parallel sensing electrodes and two signal wires; dry state = high insulation; on contact with water the electrodes conduct and loop resistance changes. The controller applies constant detection current, computes resistance from voltage, and converts resistance to distance via linear correspondence — accuracy ≤1m; abnormal total resistance indicates broken line or short circuit → fault alarm.

Point monitoring: two exposed electrodes at the sensor base; water reaching the threshold height bridges them; the internal circuit outputs a relay dry-contact signal; the controller scans the dry-contact channel and triggers the point alarm.

Alarm flow: leak detected → signal to controller → analysis → local indicator + relay action → RS485 upload to platform → platform notifies staff (popup/sound/SMS) → staff handles at the located position → after drying, the system auto-resets.

7.4 Compatibility Design

Protocol: universal Modbus RTU — natively supported by most environment-monitoring platforms, SCADA and PLCs — no driver development. Data: complete register address table with definitions and conversion formulas. Power: DC12-24V wide range, or via the included adapter from 220V mains. Installation: DIN rail or wall mount; cable clips adhesive or screw-fixed for different floor materials.

8. Detailed Technical Design

8.1 Controller Design (KTZ-LS-1000)

ABS V-0 housing, industrial grey; DIN rail + wall mount; 158×88×58mm, ~320g; 5 status LEDs (power, run, leak alarm, fault, communication); plug-in terminals 0.5-2.5mm²; front IP30 / terminal side IP20. DC12-24V wide input; static ≤80mA / max ≤150mA; ≤0.96W / ≤1.8W; reverse protection, self-recovery fuse 2A, overvoltage protection DC30V; ESD ±8kV/±15kV; surge ±2kV. One locating circuit (≤100m cable, accuracy ≤1m, response ≤2s, reset ≤5s, 3 sensitivity levels); 4 dry-contact inputs (NO/NC configurable, DC12V 10mA); 2 relay outputs (AC250V/3A, DC30V/5A; mechanical ≥100,000, electrical ≥50,000); broken-line/short detection; ≥1,000 event storage (non-volatile). RS485 Modbus RTU, 1200-38400bps (default 9600), 8N1, no/odd/even parity, address 1-247 (default 1), ≤1200m, opto-isolated 1500V, TVS. -10℃~+55℃ working; vibration/shock per GB/T 2423; EMC GB/T 17626 industrial level 3.

8.2 Leak-Detection Cable Design (KTZ-RS-06)

4-core (2 sensing electrodes + 2 signal wires); high-purity tin-plated copper stranded; food-grade PE insulation; low-smoke halogen-free flame-retardant braided sheath (V-0); φ6.0±0.2mm; ~12g/m; black; standard male/female connectors, gold contacts, IP65, ≥1,000 matings; DC5-12V; ≤10mA/m; electrode resistance ≤50Ω/m; dry insulation ≥100MΩ; linearity ±1%; max length 100m; accuracy ≤1m; detects water/dilute acid/alkali; film-level detection; response ≤2s; reset ≤5s; reusable with no performance decay; condensation-resistant; bend radius 10mm; tensile ≥100N; ≥5,000 bends; ≥10,000 abrasion cycles; withstands stepping; -20℃~+60℃ working; IP67 submersible; anti-mold; indoor life ≥8 years.

8.3 Accessories Design

Lead-in cable (KTZ-YCX-5M): 4-core shielded (aluminum foil + braid), tinned copper, PVC sheath, φ4.5mm, 5m standard (custom); cable-side standard female connector IP65; controller-side bare terminals; contact resistance ≤5Ω; insulation ≥500MΩ; -20℃~80℃.

Terminator (KTZ-ZJQ-01): standard male connector for φ6mm cable; high-precision low-drift resistor ±0.1%; ABS; IP65; -20℃~60℃; completes the loop, provides reference resistance for accuracy, enables broken-line detection; ≥10-year life.

Fixing clips (KTZ-KZ-01): flame-retardant nylon PA66 V-0; white; fits φ5.5-6.5mm; 20×12×8mm; 3M adhesive + screw hole; elastic openable clip; -30℃~85℃; acid/alkali/oil resistant; one per meter (24 pcs).

8.4 Point Sensor Design (KTZ-DS-01)

Electrode conduction type; ABS housing; 304 stainless electrodes; base-fixed floor mount; body φ35×18mm, base φ45mm; ~25g; 10m shielded signal cable; IP67 long-term submersible; DC9-24V (rated 12V); static ≤5mA / alarm ≤10mA; relay dry contact, 1 NO/NC selectable, AC125V/0.5A, DC24V/1A; ≥100,000 contacts; opto-isolated; detects ≥0.5mm water; response ≤1s; reset ≤3s; electrode surface treatment suppresses dust/condensation false alarms; repeatability ≤5%; -10℃~+60℃.

8.5 Power and Auxiliaries

DC adapter (KTZ-PW-12V2A): AC100-240V 50/60Hz; DC12V 2A 24W; ripple ≤100mVpp; regulation ±1%; DC 5.5×2.1mm plug; 1.2m lead; OCP/OVP/SCP/OTP; Class II; CCC/CE/FCC. Auxiliary kit (KTZ-FC-01): 8× M6×30 expansion bolts, 20× M4×16 self-tapping screws, 50 nylon ties, insulation tape, waterproof putty, number tubes, terminals.

8.6 Installation and Commissioning Design

Survey → confirm paths/positions/wiring → cable and power routing (strong/weak separated, labeled) → controller mounting → cable laying with clips every 1m (S-shape at key points, bend ≥10mm, terminator at end) → sensor mounting at low points with electrodes flush → wiring → continuity/insulation tests → energization → parameter configuration → per-point alarm/location tests → platform integration → trial run → acceptance with full documentation. Total 3-4 working days (5 incl. preparation).

9. Recommended Configuration and Preliminary Budget

9.1 Core Control Unit

No. Device Brand Model Qty
1 Locating leak alarm controller KITOZER KTZ-LS-1000 (1 locating circuit + 4 dry-contact inputs, RS485 Modbus RTU) 1

9.2 Locating Leak Cable Monitoring Unit

No. Device Brand Model Qty
1 Locating leak-detection cable KITOZER KTZ-RS-06, 4-core φ6mm, accuracy 1m, LSZH sheath 24 m
2 Cable lead-in KITOZER KTZ-YCX-5M, 4-core shielded 5m 1
3 Loop terminator KITOZER KTZ-ZJQ-01, IP65 1
4 Fixing clips KITOZER KTZ-KZ-01, one per meter 24

9.3 Point Floor-Water Monitoring Unit

No. Device Brand Model Qty
1 Electrode point water immersion sensor KITOZER KTZ-DS-01 (relay output, DC12V, IP67, base + 10m cable) 1

9.4 Installation Auxiliaries

No. Device Brand Model Qty
1 DC power adapter KITOZER KTZ-PW-12V2A (AC220V in, DC12V/2A) 1
2 General installation kit KITOZER KTZ-FC-01 (anchors, screws, ties, tape, putty, tubes) 1

9.5 Summary

Core control unit 1; locating leak monitoring unit (24m cable + accessories); point water monitoring unit 1; installation auxiliaries 1 set.

9.6 Quotation Notes

The above is the reference configuration for this project; the final quotation is calculated per confirmed configuration and quantities, tax-inclusive. All prices are indicative and quoted in RMB (CNY) only — no foreign-currency conversion is provided. Warranty: 2 years whole system, 7×24 support, lifetime maintenance at cost, free training and protocol documentation.

10. Technical Specifications

10.1 Locating Leak Alarm Controller (KTZ-LS-1000)

Category Item Specification
Physical Housing ABS flame-retardant, UL94-V0, industrial grey
Mounting 35mm DIN rail / wall mount
Size / weight 158×88×58mm / ~320g
Indicators 5 LEDs — power, run, leak alarm, fault, communication
Terminals Plug-in, 0.5-2.5mm²; front IP30, terminal side IP20
Electrical Supply DC12-24V wide input; rated DC12V
Current/power Static ≤80mA ≤0.96W; max ≤150mA ≤1.8W
Protection Reverse protection; self-recovery fuse 2A; overvoltage DC30V; ESD ±8kV/±15kV; surge ±2kV power & comms
Monitoring Locating circuits 1, max cable 100m
Location accuracy ≤1m full range
Leak response ≤2s; reset ≤5s after drying
Sensitivity 3 levels adjustable (high/medium/low)
Dry-contact inputs 4, NO/NC configurable, DC12V 10mA
Relay outputs 2, dry contacts, AC250V/3A, DC30V/5A; mechanical ≥100,000, electrical ≥50,000
Fault detection Cable broken-line and short-circuit detection
Event storage ≥1,000 records, non-volatile
Communication Interface 1× RS485 Modbus RTU
Baud/parity 1200-38400bps (default 9600); 8N1; no/odd/even
Address 1-247 (default 1)
Distance ≤1200m @9600bps; opto-isolated 1500V; TVS
Environment Temperature -10℃~+55℃ working, -20℃~+70℃ storage
Humidity 10-95%RH non-condensing
Vibration/shock GB/T 2423.10 (2g), GB/T 2423.5 (15g 11ms)
EMC GB/T 17626 industrial level 3

10.2 Locating Leak-Detection Cable (KTZ-RS-06)

Category Item Specification
Structure Core structure 4-core: 2 sensing electrodes + 2 signal wires
Electrodes High-purity tin-plated copper, stranded
Insulation / sheath Food-grade PE / low-smoke halogen-free braided (V-0)
Diameter / weight φ6.0±0.2mm / ~12g/m; black
Connectors Standard male/female, gold contacts, IP65, ≥1,000 matings
Electrical Voltage / current DC5-12V / ≤10mA/m
Electrode resistance ≤50Ω/m; dry insulation ≥100MΩ
Linearity / max length ±1% / 100m
Location accuracy ≤1m with controller
Detection Media Water, dilute acid, dilute alkali (conductive liquids)
Min level / response Film-level contact detection / ≤2s
Reset ≤5s after wiping dry; reusable, no performance decay
False-alarm suppression Anti-condensation; no alarm from humidity alone
Mechanics Bend radius / tensile 10mm / ≥100N
Bending / abrasion ≥5,000 bends / ≥10,000 abrasion cycles
Stepping Withstands normal personnel stepping
Environment Temperature -20℃~+60℃ working, -30℃~+70℃ storage
Humidity / waterproof 0-100%RH / IP67 submersible
Corrosion / mold Acid/alkali/oil resistant; anti-mold additives
Life ≥8 years indoors

10.3 Accessories

Lead-in cable (KTZ-YCX-5M): 4-core shielded (foil + braid); tinned copper; PVC sheath φ4.5mm; 5m (custom); female connector IP65 on cable side, bare terminals on controller side; contact resistance ≤5Ω; insulation ≥500MΩ; -20℃~80℃.

Terminator (KTZ-ZJQ-01): male connector for φ6mm cable; high-precision low-drift resistor ±0.1%; ABS; IP65; -20℃~60℃; completes loop, provides reference resistance, enables broken-line alarm; ≥10-year life.

Fixing clips (KTZ-KZ-01): flame-retardant nylon PA66 V-0; white; fits φ5.5-6.5mm; 20×12×8mm; 3M adhesive + screw holes; openable elastic clip; -30℃~85℃; acid/alkali/oil resistant; keeps cable in optimal contact position.

10.4 Electrode Point Water Immersion Sensor (KTZ-DS-01)

Category Item Specification
Basic Principle Dual-electrode conduction
Housing / electrodes ABS flame-retardant / 304 stainless
Mounting Base-fixed floor mount; body φ35×18mm, base φ45mm; ~25g
Cable 10m shielded signal cable
Protection IP67, long-term submersible
Electrical Supply DC9-24V (rated 12V); static ≤5mA, alarm ≤10mA
Output Relay dry contact, 1 NO/NC selectable, AC125V/0.5A, DC24V/1A; ≥100,000 contacts; opto-isolated
Performance Sensitivity Detects ≥0.5mm water height
Response / reset ≤1s / ≤3s after water recedes
Threshold Fixed — contact of electrodes by water triggers alarm
False-alarm suppression Electrode surface treatment prevents dust/condensation false alarms
Repeatability ≤5%
Environment Temperature -10℃~+60℃ working, -20℃~+70℃ storage
Humidity / water 0-100%RH / long-term clean-water immersion
Vibration 10-500Hz, 1g no damage

10.5 Power Adapter and Auxiliary Kit

KTZ-PW-12V2A: AC100-240V 50/60Hz; DC12V 2A 24W; ripple ≤100mVpp; voltage regulation ±1%, load ±2%; DC 5.5×2.1mm plug, 1.2m lead; OCP/OVP/SCP/OTP; Class II; 0℃~40℃; CCC/CE/FCC.

KTZ-FC-01: 8× M6×30 expansion bolts; 20× M4×16 self-tapping screws; 50× 3×150mm nylon ties; insulation tape; waterproof putty; number tubes; terminals — one-stop for regular installation.

11. Key Advantages and Customer Value

11.1 Integrated Architecture

Single-controller integration of locating and point monitoring versus two separate systems — simpler architecture, fewer failure points, higher stability, lower equipment and wiring cost; distributed sensing + centralized processing balances coverage and management; mature resistance-locating and electrode technologies; fully isolated circuits (power, detection, communication) blocking interference and surge damage.

11.2 Product Performance

Meter-level locating (≤1m error) pinpoints leaks for fast handling; second-level response (≤2s) gives early warning; low false-alarm rate (≥99% accuracy) via multi-level sensitivity, temperature compensation and signal filtering; industrial-grade components with high/low-temperature cycling, aging, vibration and EMC tests — MTBF ≥100,000h; 8+ year cable life (tin-plated anti-oxidation electrodes, wear/corrosion/flame-retardant sheath), 10+ year controller/sensor life.

11.3 Cost and O&M Advantage

Source-Manufacturer Supply; integrated design reduces device count; simple wiring installable by ordinary electricians with short schedule; automated unattended operation with low routine maintenance; reusable cable and few wear parts; direct connection to existing platforms without extra software/servers — protecting investment.

11.4 Compatibility and Expansion

Standard Modbus RTU compatible with 99%+ of environment-monitoring, SCADA, PLC and BAS systems — no custom development; spare dry-contact channels and cable-length margin allow direct expansion without controller replacement; adaptable to rooms, warehouses, pipe galleries and outdoor cabinets; relay outputs flexibly link sirens, drain pumps, solenoid valves and cameras for a full monitor-to-handle protection system.

11.5 Service Guarantee

Full-process technical support (design, consultation, installation guidance, commissioning, O&M); 7×24 hotline with 1-hour general response and on-site service; long warranty with free repair/replacement; lifetime maintenance at cost; free operation and maintenance training.

12. Technical Q&A (50+ Items)

12.1 System General

Q1: Locating vs. point monitoring — differences and scenarios?

A: Form — locating is continuous line monitoring along the cable; point is fixed-point detection only. Location — locating pinpoints the meter position (≤1m); point only tells presence of water. Scenarios — locating suits long strip areas (along water pipes, AC lines, cabinet bases) where leak paths are clear and fast location matters; point suits doors, low spots and drain areas for presence judgment. This solution combines both for “line + point” full coverage.

Q2: Do the two monitoring types interfere when sharing one controller?

A: No — the locating circuit and dry-contact channels are independent, electrically isolated hardware; signals processed separately with no cross-talk; the high-performance microprocessor scans all channels in parallel — response and accuracy unaffected.

Q3: Can the system connect to the customer’s own platform?

A: Yes — the controller has RS485 with standard Modbus RTU; any platform with Modbus RTU master and RS485 connects directly without development; complete protocol documentation and register tables provided; Ethernet platforms can use an RS485-to-Ethernet module.

Q4: Does the system work during a power outage?

A: It needs DC supply; connect to a UPS so monitoring continues during outages; DC12-24V wide input suits common DC UPS systems in rooms.

Q5: Will humidity or condensation cause false alarms?

A: Normal humidity (water vapor) cannot conduct the electrodes — no alarm. For condensation-prone low-temperature scenes, lower the sensitivity and the cable’s hydrophobic coating suppresses light condensation; heavy condensation forming a continuous liquid film bridging both electrodes triggers a genuine alarm — a real hidden hazard, not a false one.

12.2 Controller

Q6: How long a cable can one controller take? Multiple cables?

A: One locating circuit supports up to 100m — ample for this 24m project; only one continuous locating loop per controller; independent locating zones need additional controllers, all paralleling on one RS485 bus to the same platform.

Q7: What do the relay outputs do? What can they link?

A: Two dry-contact relays set for leak-alarm, fault-alarm or manual action — linking sirens (on-site alert), drain pumps (auto drainage), inlet solenoid valves (auto shutoff), cameras (turn and record), alarm hosts and access control — within rated contact capacity.

Q8: Does the controller store alarm history?

A: Yes — built-in non-volatile memory stores ≥1,000 leak/fault events (type, time, location); data survives power loss and is readable/exportable via software; longer-term storage lives on the central platform.

Q9: Can the controller be installed outdoors?

A: IP30 — indoor/dry environments (rooms, racks, weak-current boxes); outdoor or dusty/humid sites use an outdoor waterproof enclosure with ventilation; -10℃~+55℃ range applies.

Q10: How are address and baud rate changed?

A: Locally via configuration software over a USB-RS485 adapter; or remotely by Modbus write-register commands on the platform; parameters take effect after auto-restart — record original values first.

Q11: What alarm types are supported?

A: Leak alarm, broken-line fault, short-circuit fault and device anomaly — distinguished by indicators and platform data.

Q12: What is the event response time?

A: Leak response ≤2s; relay action immediate; platform upload depends on polling interval (typically seconds).

12.3 Leak-Detection Cable

Q13: How is location accuracy achieved?

A: Resistance-divider principle: the cable’s two sensing electrodes have uniform per-meter resistance; on water contact the controller applies constant current, measures the voltage at the contact point and computes resistance → length via Ohm’s law — accuracy ≤1m.

Q14: Can the cable be cut or spliced?

A: Locating cable must not be cut (changes total resistance and shifts the reference); extend via standard male/female connectors up to 100m total; connectors are IP65.

Q15: Can a stepped-on or dirty cable still work? How to clean?

A: Normal stepping won’t damage it (wear/compression-resistant sheath); rinse with clean water or wipe — performance unaffected after drying; avoid strong acids/bases; replace damaged sections showing exposed cores.

Q16: Can it be laid under floors?

A: Yes — under anti-static floors or in floor gaps (common in rooms); avoid direct burial in cement (alkaline corrosion, hard maintenance); use PVC duct/soft conduit with inspection openings.

Q17: What is the cable life and when to replace?

A: ≥8 years in dry indoor environments; shorter in humid/dusty/corrosive conditions. Replace on sheath cracking/aging, exposed oxidized electrodes with frequent false/missed alarms, multiple breaks, or corrosive-liquid damage.

Q18: What liquids can it detect?

A: Conductive liquids — water, dilute acids and alkalis; not pure water/deionized water (insufficient conductivity) at the electrode-type point sensor, though the locating cable with its film-level detection handles general coolant leaks.

Q19: Is the cable reusable after alarm?

A: Yes — wipe dry and it auto-resets; reusable indefinitely with no performance decay under normal conditions.

12.4 Point Sensor

Q20: What is the minimum water height detected?

A: 0.5mm — bridging the two electrode tips triggers the alarm; the threshold is fixed; raise the base to increase the triggering height if less sensitivity is desired.

Q21: Can the sensor stay submerged?

A: Yes — IP67 fully sealed, 304 stainless electrodes — long-term clean-water immersion is fine; avoid strong acid/alkali immersion.

Q22: Does it need power? Can it connect to alarm hosts directly?

A: DC9-24V (rated 12V), powered by the controller here; relay dry contact connects directly to alarm hosts, PLCs and controller dry-contact inputs — NO/NC selection only, no polarity concerns.

Q23: Where should it be installed?

A: Low-lying water-collection points — under AC units and pipe joints, at room doors and basement entrances (backflow), around floor drains and low spots, beside tanks/pumps; must be the lowest point, firmly fixed, electrodes flush to the floor, away from direct dripping.

Q24: Electrode vs. photoelectric sensors?

A: Electrode — conductive detection, simple, low cost, reliable, dust-immune; suits rooms/basements; slight electrode corrosion over time; unsuitable for high-resistivity pure water. Photoelectric — infrared refraction, precise, no corrosion, suits pure water; costlier and optical windows can be fouled by dust/oil. Electrode fits this project best.

Q25: Can the sensor output both NO and NC?

A: One relay with selectable NO or NC configuration to match the host’s input logic.

12.5 Installation

Q26: How should the cable be laid?

A: Along the underside of leak-prone lines; S-shape at joints, valves and AC drip pans; clip every 1m (denser at bends/joints); bend radius ≥10mm; keep connectors away from low water spots; terminate the end with the terminator; label start/end/bends.

Q27: RS485 wiring rules?

A: RVSP twisted shielded pair ≥0.5mm² (never parallel wire); bus topology hand-in-hand (no star/tree branches); shield single-end earthed at the control end; ≥30cm separation from power cables, no same duct; 120Ω termination resistors at both ends beyond 100m; A/B polarity correct, terminals tight.

Q28: How long does installation take?

A: Hardware installation and commissioning about half a day for one skilled technician (2 people faster): fixing devices 1-2h; cabling/wiring 1h; commissioning 1h; civil trenching adds time.

Q29: Will installation damage decoration or affect the running room?

A: Minimal — adhesive clips (no drilling), DIN-rail controller or small wall holes, cables along walls/trays with ties; all low-voltage work without live operation — no impact on running equipment; ideal for in-service room retrofits.

Q30: What tools are needed?

A: Impact drill, screwdrivers, strippers, multimeter, cable tester, utility knife, tape — standard electrician tools.

12.6 Communication Integration

Q31: Is Modbus RTU hard to integrate?

A: It is the industry’s “common language” — master/slave query/response with standard registers; with the provided register table, 1-2 hours of integration is typical; remote guidance available.

Q32: What data is uploaded? Can relays be remote-controlled?

A: Device power/communication status, leak alarm status, leak location (meters), fault status (broken line/short), per-channel dry-contact states, device parameters; remote write commands control both relays (pumps, valves) and modify parameters.

Q33: If the communication line breaks, does local alarming still work?

A: Yes — the controller alarms independently (indicators, relays); only platform upload is lost; check communication status regularly; local audible/visual alarms remain a key supplement.

Q34: How many controllers per platform host?

A: Up to 247 slaves per RS485 bus theoretically; ≤32 recommended for stability/response; more via serial-port expansion cards on multiple buses.

Q35: What if the platform is Ethernet-based?

A: Add an RS485-to-Ethernet gateway (Modbus TCP) — the controller side unchanged.

12.7 O&M and Maintenance

Q36: What routine maintenance is needed?

A: Quarterly checks: indicator status; clean cable/sensor surfaces; terminal tightness and cable integrity; function test with a little water (alarm + platform); environment check (dry, ventilated); annual deep maintenance (accuracy calibration, full re-tightening, internal cleaning).

Q37: How to test alarm functionality?

A: Locating cable — wet cloth or a few drops on any position; verify alarm within seconds and location data; wipe dry and verify reset. Point sensor — a few drops on the bottom electrodes; verify alarm. Use tap water, not pure/deionized water; avoid flooding nearby equipment; record test results.

Q38: How are false alarms handled?

A: Check for real water/condensation; clean dust/water/metal debris from cable/sensor; dry and re-tighten terminals; check connector moisture; lower sensitivity for high-humidity scenes; replace a section if persistent.

Q39: Can a damaged cable section be replaced only?

A: Yes — locating cable is sectionalized with connectors; replace the damaged section and rejoin; re-verify location accuracy after replacement.

Q40: What happens after warranty?

A: Lifetime repair service — diagnosis, quotation, repair at component + labor cost only; damaged-beyond-repair units get trade-in preference.

Q41: How long does the battery-free system last?

A: Controller/sensor design life ≥10 years; cable ≥8 years indoors; adapter ~5 years typical; all modular and replaceable.

Q42: Can the system expand later?

A: Yes — spare dry-contact channels for more point sensors; cable length up to 100m per loop; more controllers parallel on the bus — no core replacement.

12.8 Value and Service

Q43: How does this compare with two separate systems?

A: One controller, one bus, one interface — lower hardware, wiring and platform cost; simpler O&M; unified data.

Q44: What documentation is delivered?

A: Manuals, parameter handbook, register address table, wiring drawings, certificates, commissioning records and acceptance documents.

Q45: What training is provided?

A: One-day on-site training (theory + hands-on + alarm drills + fault handling) with manuals and remote refresher support; assessment before independent operation.

Q46: What is the delivery period?

A: Standard configurations ship from stock in 1-3 days; total project including installation and commissioning about 5 working days.

Q47: Can it link drainage and shutoff automatically?

A: Yes — relay outputs drive drain pumps and inlet solenoid valves; leak → auto pump/valve action; optional camera linkage for evidence.

Q48: How is accuracy maintained over time?

A: Temperature-compensated AD sampling; factory calibration; annual verification recommended; the terminator’s low-drift reference resistor keeps location stable.

Q49: Why choose the KITOZER/Lain solution?

A: Source-factory integrated hardware (controller, cable, sensors), standard Modbus compatibility, meter-level locating, 2-year warranty, lifetime service and 20+ years of room/environment-monitoring engineering.

Q50: What makes this system reliable in harsh environments?

A: Industrial-grade components, opto-isolated circuits, TVS surge protection, wide-temperature design, IP67 sensing devices, anti-condensation cable and full factory aging/EMC testing — MTBF ≥100,000h.

13. Construction Schedule

13.1 Stage Division

Five stages: preparation, cable/power routing, equipment installation, system commissioning, acceptance/delivery.

13.2 Detailed Schedule

Stage No. Work Duration Responsible Acceptance
Preparation 1 Site survey — paths, positions, wiring routes 0.5 day PM + engineer Survey record, confirmed drawings
2 Equipment stocking and outbound inspection 0.5 day Warehouse + QC Model/qty correct, intact
3 Tools and PPE 0.5 day Lead Complete
Routing 4 Communication and power routing/fixing 0.5 day Crew Tidy, firm, strong/weak separated
5 Continuity and insulation tests 0.5 day Engineer No short/open/earth, insulation OK
Installation 6 Controller mounting 0.5 day Crew Firm, accessible
7 Locating cable laying and fixing 1 day Crew Per design, firm, flat, joints reliable
8 Point sensor mounting 0.5 day Crew Low spot, firm, electrodes flush
9 All wiring and terminal tightening 0.5 day Engineer Correct, labeled, insulated
Commissioning 10 Energization and parameter configuration 0.5 day Engineer Normal LEDs, parameters set
11 Alarm tests and location calibration 0.5 day Engineer Timely alarm, error ≤1m, reset OK
12 Platform communication integration 0.5 day Engineer + customer Stable, accurate upload, platform alarms
13 Relay linkage tests (if any) 0.5 day Engineer Correct action and logic
Acceptance 14 Trial run 1 day Both No anomaly, no false/missed alarm
15 As-built documentation 0.5 day PM Complete
16 Acceptance signature 0.5 day Both Passed

Total: pure construction/commissioning 3-4 working days; overall project within 5 working days incl. preparation; extended only for site conditions or customer coordination delays.

13.3 Key Node Control

Survey node: confirm all positions, routes, power points and platform interface in writing before work — avoid rework. Line test node: continuity/insulation tests before connecting devices — prevent shorts damaging equipment. Pre-energization check: engineer full wiring check — no reversals, errors or shorts. Function test node: test every point’s alarm, location and upload — 100% pass, no hidden faults. Acceptance node: full documentation and training handover for independent customer operation.

14. Construction Organization and Quality/Safety Measures

14.1 Organization

Project-manager responsibility system: PM (1) — overall coordination, schedule, resources, customer liaison, acceptance. Technical engineer (1) — design, disclosure, commissioning, platform integration, training, support. Construction lead (1) — on-site organization, personnel, safety, quality self-check. Workers (1-2) — installation, cabling, fixing. QC (1, part-time) — outbound inspection, process spot checks, final quality acceptance.

14.2 Personnel Requirements

PM with 3+ years of weak-current project management, familiar with leak and environment-monitoring systems; engineer with electronics/automation background and 2+ years of commissioning, proficient in Modbus and platform integration; lead with 2+ years of weak-current construction; all staff safety/technically trained and certified, observing customer site rules.

14.3 Pre-Construction Preparation

Technical: team familiarization with drawings and requirements; technical disclosure (installation standards, wiring, precautions); drawings, point tables, wiring diagrams and manuals prepared; early communication with customer technicians (power, platform port, schedule window). Materials: inventory check of all devices/auxiliaries; factory energization test of core devices; tools (impact drill, screwdrivers, strippers, multimeter, cable tester, knife, tape); PPE (helmet, insulating gloves, dust mask, signs); labeled case packing. Site: survey and clearance; temporary power confirmed; construction registration with the site manager; warning signs.

14.4 Standard Construction Process

Positioning: mark controller position, cable path, sensor points and cable routes per drawings; confirm with customer before work. Cable works: exposed routing along walls/floors/trays with clips/ties, neat and horizontal/vertical; concealed routing in conduit/duct with no joints inside and slack at bends; strong/weak separated; labeled both ends. Device installation: controller DIN/wall mounted level and accessible; cable laid per marked path with one clip per meter, smooth bends, connectors locked; sensor base fixed with electrodes flush; adapter in dry ventilated place with labeled plug. Termination: wire strictly per wiring diagram; proper strip length; firm crimps, no burrs/shorts; terminals tightened; tidy dressing with labels. Commissioning: megger-check circuits before energization; power on and verify LEDs/no abnormal heat or sound; configure address/baud; per-point alarm, location and fault tests; platform integration; record and rectify issues.

14.5 Quality Control

Three-inspection system (self, lead re-check, QC final) per process; incoming materials with certificates — unqualified prohibited; national weak-current codes and enterprise craft standards; key processes (line test, pre-energization check, commissioning) attended by the engineer; complete quality records — logs, test and commissioning documents — fully traceable.

14.6 Safety Management

Safety training before entry; power from designated panels with qualified tools, live work only by certified electricians; harnesses/helmets for high work, no throwing; no smoking, fire equipment, hot-work permits; protection of customer equipment and décor; room rules observed around running equipment; emergency plan — stop work on incidents, first aid, report.

14.7 Civilized Construction

Uniform attire and badges; tidy materials/tools; daily waste removal — work finished, site clean; noise control outside business hours; care for public facilities; courteous communication with customer personnel.

15. After-Sales Service

15.1 Warranty Commitment

2-year free warranty on the whole system from acceptance — free repair and free part replacement for non-human quality faults; failed units replaced with new equivalents; exclusions: human damage, unauthorized modification, force majeure, consumable wear.

15.2 Fault Response

7×24 hotline; general consultation within 1 hour; general faults within 2 hours (remote guidance); major faults within 4 hours — on-site within 8h urban / 24h suburban; flow: report → register → engineer → remote diagnosis → resolve or dispatch → repair → confirm → follow-up record.

15.3 On-Site Repair

Engineers carry common spares/tools for one-visit resolution; fault cause, plan and cost (out-of-warranty) explained and approved before repair; full tests after repair with explanations; failed parts returned per policy.

15.4 Spare Parts

Common spare stock of controllers, sensors, cable and power units; ≥5-year parts support after phase-out; backup units for core customers during repairs to minimize downtime.

15.5 Lifetime Maintenance

Lifetime service after warranty — annual maintenance agreements (≥2 inspections/year with proactive hazard elimination) or per-visit service; out-of-warranty repairs at component + reasonable labor cost only; free lifetime firmware/software upgrades; free technical consultation, expansion design and remote assistance; free documentation reissue.

16. Training Plan

16.1 Objectives and Audience

Objectives: understand system composition, principles and functions; operate software, view alarms and query history; master daily inspection and common fault handling; cultivate 1-2 system administrators. Audience: customer system administrators, O&M engineers, duty and security staff; 2-3 trainees with basic weak-current/PC skills.

16.2 Training Content

Theory: system overview (composition, principles, value); core devices (controller, cable, sensor functions/parameters); architecture and communication (RS485, Modbus basics); alarm types (leak, broken line, short circuit). Practice: controller panel (indicator recognition, local status); platform operation (monitoring, alarm handling, history, parameter configuration); alarm handling flow (on-site check steps, handling, reset); daily inspection (items, methods, alarm function tests). Maintenance: daily care (cable/sensor cleaning, line checks, dust/moisture prevention); common fault finding (false alarm, no alarm, communication faults); simple fixes (loose wiring, device restart, continuity tests); reporting flow.

16.3 Methods and Schedule

On-site instruction with real equipment; hands-on drills (alarm tests, platform operation, fault simulation) under engineer guidance; paper/electronic manuals (operation, maintenance, courseware); Q&A session. One day at acceptance: 9:00-10:30 theory; 10:40-12:00 operation demonstration; 13:30-15:00 hands-on + alarm drill; 15:10-16:30 maintenance and fault training; 16:40-17:00 Q&A + assessment; flexible or batched per customer.

16.4 Assessment and Certification

Theory questioning (principles, alarm types, inspection) + practical assessment (simulated alarm handling and standard operation); passing = independent daily operation, correct alarm handling and simple fault finding; free retraining until mastery.

16. Training Plan

16.1 Training Objectives and Audience

Training objectives: through systematic training, enable management personnel to fully understand the system structure, working principles and performance characteristics, master daily operation methods and inspection/maintenance essentials, identify common faults and handle simple problems, ensuring safe, stable and long-term operation.

Training audience: management and O&M personnel designated by the client, recommended 2-3 persons with basic electrical and equipment knowledge.

16.2 Tiered Training Content System

Level 1: Basic operation training (1 day)

– Basic principles: system concepts, structure composition, performance indicators;

– Daily operation standards: correct operation of equipment, control and safety systems;

– Daily inspection contents: daily/weekly/monthly check items;

– Safety precautions: usage prohibitions and emergency handling procedures.

Level 2: Maintenance training (1 day)

– Detailed structure of each subsystem and working principles;

– Daily maintenance methods: cleaning, fastening checks, routine care;

– Common fault identification and simple handling;

– Emergency handling procedures for power failure, fire and equipment faults.

Level 3: Advanced management training (as needed)

– Performance influencing factors and how to avoid degradation;

– Upgrade and expansion knowledge and specification requirements;

– Relevant national standards interpretation.

16.3 Training Methods and Schedule

– Methods: combination of “theory explanation + on-site practice + Q&A interaction”;

– Schedule: training arranged at the completion acceptance stage, synchronized with handover, 2 days of intensive training total; time flexibly adjustable; a free repeat training session is provided for newly assigned personnel.

16.4 Training Assessment and Documentation Delivery

– Assessment: theory written test plus practical operation; training qualification certificates issued upon passing; supplementary training for those who fail;

– Documentation delivery: complete O&M documentation, including operation and maintenance manual, equipment manuals and certificates, completion drawings and hidden work records, test reports and after-sales service contact card, all bound into volumes.

17. Anonymous Typical Project Scenarios

All project scenarios below are anonymous, generalized examples provided for reference only. No real customer names, addresses or identifiable details are disclosed.

17.1 Large Data Center Leak Monitoring Project

Project background. A Tier III data center of ~2,000m² with many server racks, precision AC units and extensive water piping; leakage would cause huge economic and business loss. A highly reliable, accurate system covering all zones and integrating with the existing environment-monitoring platform was required.

Implementation. 12 locating leak alarm controllers; 3,600m of locating leak-detection cable along all rack bases, AC perimeters and water lines; 36 point water immersion sensors at doors, floor drains and distribution rooms; auxiliaries and power; integrated into the existing platform over RS485.

Results. Stable since commissioning — repeatedly detected AC condensate leaks and pipe-joint seepage early; staff handled quickly per location data, avoiding major loss; high accuracy, zero false alarms, location precision met design; all new rooms continue using the same products.

17.2 Underground Utility Gallery Environment Monitoring Project

Project background. A ~5km underground utility gallery housing water-supply pipes, power and communication cables — humid environment, water-leak risk and inconvenient manual inspection; automated monitoring with alarms to the gallery control center was needed.

Implementation. 25 industrial leak controllers distributed per fire compartment; 8,000m of locating cable laid continuously along the underside of water-supply lines; waterproof junction boxes and signal repeaters; ring-network communication integrated into the comprehensive monitoring platform.

Results. Stable long-term operation in the humid, high-temperature-differential environment; repeatedly caught pipe-joint seepage with accurate location, greatly shortening repair time and reducing water waste and ponding risk; reliability and environmental adaptability highly rated by the operator.

17.3 Pharmaceutical Enterprise Clean Warehouse Leak Monitoring Project

Project background. A pharmaceutical warehouse storing drugs and biological products required strict temperature/humidity control and water protection; constant T/H AC and fire sprinkler piping inside; the system needed high sensitivity to trace micro-leaks and zero dust contamination for the clean area.

Implementation. 8 high-precision controllers; 1,200m of locating cable along AC piping, sprinkler piping and walls; 16 point sensors at low spots and elevator pits; all devices with clean housings — no shedding or odor, meeting GMP cleanliness.

Results. Stable with high sensitivity, detecting even trace condensate leaks; cleanliness fully compliant with no impact on stored products; integrated with the warehouse environment system for unified temperature/humidity, leak and access monitoring — higher smart-management level.

17.4 Telecom Operator Base-Station Room Leak Monitoring Project

Project background. The operator had over a hundred outdoor base-station rooms, some with roof/AC leak risks; unattended, leaks were found late, often causing equipment faults and service loss; a low-cost, highly reliable remote monitoring solution was needed.

Implementation. One compact controller per station (120 total); 10-20m of locating cable per station along rack bases and under AC units; data backhauled through the existing base-station environment-monitoring channel to the network management center; wide-voltage DC supply and strong anti-interference for station power.

Results. Leak fault discovery time cut from ~12 hours average to under 1 minute; equipment fault/outage rate from leaks down over 90%; simple installation, high stability, low fault rate — ideal for distributed unattended scenarios; highly praised by the operator’s O&M department.

18. SEO Optimization Section

All reference prices in this technical solution are in RMB (CNY) only and are for reference purposes; final quotation is subject to the confirmed configuration.

18.1 Keyword System

– Core keywords: technical design solution, system configuration, technical parameters, construction and O&M services;

– High-conversion long-tail keywords: design solution, configuration list, technical parameters, construction plan, after-sales service;

– Industry traffic keywords: system architecture, applicable standards, technical Q&A, project cases;

– Brand keywords: KITOZER, Guangzhou Lain.

18.2 SEO Tag System

– Title tag: the article title — Guangzhou Lain KITOZER;

– Meta description: Guangzhou Lain professionally provides complete technical design solutions with detailed configuration list, full-system product technical parameters, construction organization plan and after-sales service — source manufacturer customization, compliant performance, third-party testing supported;

– H1 tag: the article title;

– H2 tags: system design and product parameters, construction organization plan, after-sales service and training, engineering cases.

18.3 Internal Link Anchor Text

– Core anchor text: technical design solution, system construction;

– Long-tail anchor text: configuration list, technical parameters, construction plan;

– Related anchor text: shielding cabinet, micro-module cold aisle, integrated computer room, outdoor cabinet.

19. Official Contact Information

– Company Name: Guangzhou Lain Intelligent System Development Co., Ltd.

– Brand: KITOZER (Pioneer)

– Official Website: https://gdlain.com

– Tel: +86 139 2228 9957 (WeChat available), +86 185 2066 8845 (WeChat available)

– Address: No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou, China

For any inquiries about this technical design solution, configuration customization, quotation or construction services, please contact us through the information above. We provide free design consultation and tailored solutions for your specific requirements.