Computer Room Rack-Mounted Gas Fire Suppression

Table of Contents

1. Cover / Document Information

– Document Title: Computer Room Rack-Mounted Gas Fire Suppression Technical Design Solution

– Prepared by: Guangzhou Lain Intelligent System Development Co., Ltd.

– Brand: KITOZER (Pioneer)

– Date: August 2026

– Version: V1.0

– Project Type: Technical design solution for Computer Room Rack-Mounted Gas Fire Suppression

2. Table of Contents Structure

1. Company Introduction

2. Project Overview

3. User Requirement Analysis

4. Overall Design Description

5. Detailed System Design and Product Technical Parameters

6. Project Quotation and Configuration List

7. Core Solution Advantages

8. Technical Q&A

9. Construction Schedule Plan

10. Construction Organization Plan

11. After-Sales Service System

12. Operation and Maintenance Training Plan

13. Typical Project Cases

14. SEO Optimization System and Website Backend Configuration

15. Contact Information

3. Company Introduction

3.1 Company Development Overview

Founded in 2002, Guangzhou Lain Intelligent System Development Co., Ltd. is a high-tech enterprise dedicated to the computer room construction and intelligent protection field for more than two decades, integrating R&D, production, sales, engineering implementation and after-sales service. The company focuses on innovative breakthroughs in electromagnetic shielding technology, modular computer room technology and computer room environmental monitoring technology, and has grown into a source manufacturer with core competitiveness in the domestic computer room construction field.

After more than twenty years of industry accumulation, the company has built a large-scale production and manufacturing base equipped with advanced CNC sheet metal processing equipment, automated spraying production lines and professional testing laboratories, with an annual production capacity of hundreds of sets of shielding computer rooms, integrated cabinets and micro-module products. The company’s service network covers all provinces and cities across the country, providing thousands of computer room construction and renovation services for customers in government, military, scientific research, finance and enterprise fields.

3.2 Core Business System

The company’s core business revolves around the full-lifecycle construction of computer rooms, forming four major product and service systems:

– Computer room EPC general contracting service: one-stop services from solution design, manufacturing, on-site construction to commissioning and acceptance, covering shielding computer rooms, IDC data rooms, modular computer rooms, container computer rooms and other types;

– Core equipment R&D and production: independently produces KITOZER brand series products, including shielding cabinets, shielding desks, consoles, integrated data cabinets, micro-module cold aisle cabinets, outdoor rainproof cabinets, etc., supporting non-standard customization;

– Computer room environmental monitoring system: provides full-element monitoring solutions for temperature and humidity, water leakage, access control, video, fire protection, UPS and power distribution, realizing intelligent and unattended O&M;

– Shielding and security protection products: shielding rooms, shielding doors and windows, anechoic chambers and related auxiliary materials, widely used in confidential, military and scientific research fields.

3.3 Brand and Qualification Honors

The core brand KITOZER (Pioneer) focuses on computer room equipment and shielding products, positioned as an “efficient, green, innovative and safe” solution provider. Products have passed multiple authoritative tests and comply with national and industry standards. The company holds multiple utility model patents and software copyrights, has been awarded high-tech enterprise qualification, and follows the ISO9001 quality management standard.

3.4 Core Competitive Advantages

1. Source production, controllable quality: own production base and professional processing equipment; core products independently produced with full-process quality control, providing more cost-effective solutions without intermediate links;

2. Customized design, matching needs: tailor-made solutions per site conditions, technical requirements, configuration and budget, with multiple design options provided free of charge;

3. Professional team, rich experience: a professional technical team of engineers and project managers with more than ten years of industry experience;

4. Quality after-sales, full guarantee: a 7×24 professional online service system with dedicated project follow-up from early coordination to later O&M.

4. Project Background and Objectives

4.1 Industry Background

With the growth of the digital economy, data rooms and server racks have become core corporate assets. The IT equipment inside a rack is dense, high-value and heat-intensive, making electrical fire risk prominent. Traditional room-level fire protection uses piped or cabinet-type gas suppression covering the whole computer room as one protected zone: once discharged, the entire zone is affected, causing large-scale business interruption and incalculable economic loss.

Rack-mounted gas fire suppression is the new-generation precision fire-protection technology for computer rooms. It takes a single server rack or network cabinet as an independent protected unit, integrating the suppression device and detection system inside the cabinet to achieve “extinguish exactly where the fire is”, greatly narrowing the affected scope and keeping core business running. It has become the mainstream upgrade direction for high-density data rooms and critical business racks.

4.2 Project Objectives

This solution designs a safe, reliable, efficient and intelligent rack-mounted gas fire suppression system for rack-level fire protection, achieving the following objectives:

Precision protection: each cabinet is an independent protected unit; a fire affects only the cabinet of origin while adjacent equipment keeps running.

Rapid suppression: close-range detection and discharge inside the rack detect fire early and reach the extinguishing concentration quickly.

Clean and non-damaging: clean gaseous agents leave no residue after discharge and do not damage precision electronic equipment.

Intelligent management: local and remote monitoring, integration with the computer room environmental (DCIM) system, and visualized O&M.

Compliance: strict adherence to national fire codes and data center standards, satisfying fire acceptance requirements.

Convenient deployment: standard rack-unit (U) design, no computer room structure modification, online installation without business interruption.

4.3 Applicable Scope

The solution applies to fire protection of standard 19-inch server racks, network cabinets, communication cabinets, shielded cabinets, outdoor cabinets and industrial control cabinets, covering data centers, IDC rooms, enterprise rooms, government rooms, communication base stations, power control rooms and medical equipment rooms.

5. User Requirement Analysis

5.1 Core Fire-Safety Requirement

Rack interiors are dense with equipment and cabling; electrical short circuits and equipment overheating can easily cause fire. Fire must be detected and extinguished at the earliest stage to prevent spread that would destroy a whole rack or even the whole computer room, protecting equipment assets.

5.2 Business Continuity Requirement

Core business racks carry critical production systems. Traditional whole-room discharge stops business across the zone with long recovery times and heavy losses. The user needs the fire system to confine the impact to a single rack, minimizing business interruption time and economic loss.

5.3 Intelligent Management Requirement

Computer rooms are moving toward unattended and remote operation. The fire system needs status monitoring, alarm push and remote query, and must integrate with the existing environment-monitoring platform for unified management, reducing manual patrol cost.

5.4 Compliance Requirement

As a mandatory safety installation, the design, products, construction and acceptance must comply with the current national standards *Code for Design of Gas Fire Extinguishing Systems*, *Code for Design of Data Centers*, *Code for Design of Automatic Fire Alarm Systems* and others, passing fire acceptance and routine inspection.

5.5 Installation and O&M Requirement

Deployment must not damage the existing computer room structure or interrupt business operation. Modular design, easy installation and maintenance, readily available spare parts and flexible later expansion are required.

5.6 Green and Environmental Requirement

In line with national green data center and dual-carbon policies, the user prefers environmentally friendly agents with zero ozone depletion potential and low global warming potential, supporting green and low-carbon development.

6. Design Principles and Applicable Standards

6.1 Applicable Standards

– *Code for Design of Gas Fire Extinguishing Systems* — GB 50370-2005

– *Code for Design of Data Centers* — GB 50174-2017

– *Code for Fire Protection Design of Buildings* — GB 50016-2014 (2018 edition)

– *Code for Design of Automatic Fire Alarm Systems* — GB 50116-2013

– *Code for Installation and Acceptance of Gas Fire Extinguishing Systems* — GB 50263-2007

– *Code for Construction and Acceptance of Electronic Information System Computer Rooms* — GB 50462-2008

– *Technical Standard for Fire Emergency Lighting and Evacuate Indication System* — GB 51309-2018

– Current national and local fire regulations and technical codes

6.2 Design Principles

(1) Safety and reliability. Safety comes first: multi-detection logic reduces false alarm/false discharge probability, certified products from authoritative testing bodies are selected, and critical components are redundantly designed for long-term stable operation and reliable suppression.

(2) Technical advancement. Rack-level precision suppression combined with IoT and remote monitoring upgrades protection granularity, response speed and management efficiency compared with traditional room-level systems, providing a forward-looking solution.

(3) Economy. Configuration is optimized to control construction cost while meeting function and safety requirements, and construction/O&M costs are reduced together with fire-loss risk, delivering optimal lifecycle value.

(4) Installation convenience. Modular, prefabricated products require only simple on-site mounting and wiring — no large-scale piping or room modification — with a short construction period and deployment without business interruption.

(5) O&M efficiency. Self-diagnosis, status monitoring and remote management keep daily maintenance simple; high standardization means universal spare parts and easy fault replacement, reducing O&M workload.

(6) Green and environmental. Environmentally friendly clean agents are preferred with no secondary pollution, and production and construction follow environmental norms.

(7) Scalability. The distributed architecture supports gradual expansion by rack count for different room scales; standard communication interfaces connect different environment-monitoring platforms, and functions can be extended as needed.

6.3 System Architecture

The rack-mounted gas fire suppression system consists of four subsystems cooperating to complete the full process of detection, alarm, suppression and feedback:

Suppression execution subsystem: centered on the rack-mounted gas suppression device (agent cylinder, container valve, atomizing nozzle, pressure signal device), it receives commands and discharges agent to extinguish the fire.

Detection and alarm subsystem: point-type photoelectric smoke detectors, point-type rate-of-rise/fixed-temperature detectors, ultraviolet flame detectors and manual alarm call points monitor fire conditions inside the rack in real time.

Control and management subsystem: the gas suppression controller, zone control panel, audible/visual alarm, discharge indicator light and emergency start/stop button perform signal processing, logic judgment, command output and status display.

Auxiliary subsystem: the rack-specific pressure relief device, cabling, terminals and identification plates maintain pressure balance, fixing and standard marking.

6.4 Working Principle and Control Modes

The system supports automatic, manual and mechanical emergency operation to ensure reliable suppression in all scenarios.

Automatic mode. When any single detector (smoke or heat) alarms, the controller issues a pre-alarm and notifies the monitoring platform. When two or more detectors of different types alarm simultaneously, the controller confirms fire, starts a discharge delay countdown (0-30 s adjustable), activates the audible/visual alarm and lights the discharge indicator outside the protected zone. After the delay, the controller outputs the start signal, opens the container valve, and the agent is discharged through the atomizing nozzle into the rack. After discharge, the pressure signal device feeds back the discharge status, and the system records discharge time and state.

Manual mode. Personnel can start the system manually: press the emergency start button outside the protected zone (discharge after a short delay), or start the corresponding zone from the controller panel with a privileged password. If a false alarm is confirmed, the emergency stop button terminates the start procedure before the delay elapses.

Mechanical emergency mode. If the control system loses power or fails, personnel go to the device and press the emergency start button on the container valve to discharge the agent directly.

6.5 Protected-Zone Design and Agent Calculation

Protected unit division. A standard 19-inch server rack is one independent protected unit. A typical 42U rack has an internal net volume of about 1.2-1.8 m³; with doors closed it forms a relatively sealed space meeting gas-immersion requirements.

Design concentration. For electronic computer rooms, the heptafluoropropane (HFC-227ea) design concentration is 8% with immersion time ≥10 min; for electronic equipment, the perfluorohexanone (FK-5-1-12) design concentration is 4.5% with immersion time ≥10 min.

Agent quantity formula. The charge quantity per rack is calculated as W = V × C × ρ × K / 100 (where W = design agent quantity in kg, V = net protected volume in m³, C = design concentration in %, ρ = saturated vapor density, K = altitude/sealing correction factor). For a 1.5 m³ standard rack at 8% heptafluoropropane, the calculated design quantity is about 2.1 kg, matched with a 2.5 L device with ample margin.

Pressure relief area. Gas discharge momentarily raises pressure inside the rack, so a mechanical pressure relief device is fitted which opens automatically when the set pressure is reached and closes after, preventing rack deformation. The relief area is calculated per code; 0.01 m² per standard rack is sufficient.

7. System Architecture and Working Principle

7.1 Rack-Mounted Gas Suppression Device

The rack-mounted device is an integrated, built-in gas suppression unit designed for standard 19-inch racks, integrating the cylinder, valve, nozzle and pressure gauge into a 2U unit installed directly in a free rack U position. No external piping is needed and installation is simple — it is the core equipment of rack-level precision suppression.

Heptafluoropropane series (KITOZER-JQF-4.2/2.5 example): nominal working pressure 4.2 MPa at 20℃ (max 5.3 MPa at 50℃), effective cylinder volume 2.5 L, agent charge 2.875 kg (±2%), charge density ≤1150 kg/m³, design concentration 8% (electronic rooms), discharge time ≤10 s, immersion ≥10 min, protected volume ≤2.5 m³, working temperature -20℃ to +50℃, electrical start (DC 24V, ≥1.2 A/1 ms) plus mechanical emergency start, safety relief 5.8 ±0.5 MPa, 19-inch 2U mounting (482.6 × 88.9 × 500 mm), net weight 12.5 kg, 304 stainless seamless cylinder, HPb59-1 brass container valve, 304 stainless nozzle, NBR/PTFE seals, axial pressure gauge, passive NO/NC feedback contact (DC24V/1A), IP40, per GB 50370-2005 and GA 400-2002 with national type test report; cylinder design life 20 years, agent validity 10 years, MTBF ≥100,000 h. Series: JQF-4.2/1.5 (1U, ≤1.5 m³), /2.5 (2U, ≤2.5 m³), /4.0 (3U, ≤4.0 m³), /6.0 (4U, ≤6.0 m³).

Perfluorohexanone series (KITOZER-JQP-1.6/2.0 example): eco-friendly FK-5-1-12 agent, ODP 0, GWP 1, atmospheric lifetime 0.014 years, low toxicity (NOAEL 10%, above design concentration), nominal pressure 1.6 MPa (nitrogen pressurized), volume 2.0 L, charge 1.6 kg, design concentration 4.5%, discharge ≤8 s, protected volume ≤2.5 m³, working temperature -10℃ to +55℃, 2U mounting (482.6 × 88.9 × 480 mm), net weight 8.2 kg, 6061 aluminum alloy seamless cylinder, 304 stainless valve, IP40, per GB 50370-2005 and ISO 14520, compliant with Montreal Protocol alternatives — suitable for attended rooms, green data centers and high-value precision equipment.

7.2 Detection and Alarm Components

Photoelectric smoke detector (KITOZER-SD-100): light-scattering principle, high sensitivity and fast response with strong anti-interference, providing the first-stage early warning inside the rack. Addressable two-wire, DC 16-28 V, monitoring current ≤350 μA, alarm current ≤2 mA, sensitivity I/II/III adjustable (default II), response threshold 0.10-0.25 dB/m, protection area ≤60 m² (ceiling ≤6 m), protection radius ≤5.8 m, electronic addressing 1-255, per GB 4715-2005, life ≥10 years.

Rate-of-rise/fixed-temperature detector (KITOZER-WD-200): combines fixed-temperature alarm (68℃ default; 57/79/93℃ optional) with rate-of-rise alarm (≥7.5℃/min), providing the second-stage confirmation signal; combined with smoke detection it forms compound judgment logic that greatly reduces false alarms. Two-wire, monitoring ≤300 μA, protection area ≤30 m², working temperature -20℃ to +70℃, per GB 4716-2005.

UV flame detector (KITOZER-UV-300): detects the ultraviolet spectrum of flames (185-260 nm) with millisecond response (≤5 ms), immune to high temperature and dust, serving as third-stage confirmation for scenarios where open flame can appear quickly. Detection angle 120° horizontal/vertical, range ≥15 m (0.1 m² gasoline flame), DC 18-30 V, relay output plus optional 4-20 mA, built-in self-test, IP65, die-cast aluminum housing, per GB 12791-2006.

7.3 Control and Indication Components

Single-zone gas suppression controller (KITOZER-MK-1): the core control unit receives detector signals, executes fire logic judgment, outputs start commands and manages audible/visual and feedback signals, with fault self-test, 1000-event history (power-fail retained), RS485 (Modbus-RTU) communications and optional Ethernet. AC 220V ±15% supply with DC 24V/7Ah standby (≥4 h monitoring endurance), 1 two-wire loop with 32 addresses, 2 fire relay outputs, 2 start outputs (DC24V/2A), 1 fault output, 1 audible/visual output, 128×64 LCD with Chinese menus, three-level password, delay 0-30 s adjustable in 1 s steps, wall-mounted 320×240×80 mm, ABS V0 housing, per GB 4717-2005 and GB 16806-2006. Multi-zone variants: 2/4/8-zone controllers for centralized management of multiple racks.

Audible/visual alarm (KITOZER-SG-1): DC 24V, ≤150 mA, sound pressure ≥85 dB at 3 m, fire-tone variation, red flash 1-2 Hz, visible ≥20 m, IP43, per GB 26851-2011.

Discharge indicator (KITOZER-PD-1): installed above the door outside the protected zone; red light flashes during discharge warning personnel not to enter; DC 24V, 3 W, flash 1±0.5 Hz, visible distance ≥20 m, wall-mounted 300×100×40 mm, IP30, per GB 16806-2006.

Emergency start/stop button (KITOZER-QT-1): installed outside the protected zone; press start to initiate manual suppression, press stop within the delay to terminate; key reset prevents misoperation; DC 24V, contact capacity DC24V/2A, 1 NO (start) + 1 NC (stop), IP65, aluminum housing, 86-box mounting, per GB 16806-2006.

7.4 Auxiliary Components

Rack pressure relief device (KITOZER-XY-0.01): installed on the rack side or rear panel; when discharge pressure reaches the set value the vanes open automatically to relieve pressure, closing after pressure drops to retain agent concentration, preventing rack deformation. Purely mechanical, no power required. Nominal relief area 0.01 m², opening pressure 1000±200 Pa, closing pressure 500±100 Pa, withstand ≥3000 Pa, leakage ≤5 m³/h at 500 Pa, galvanized steel vanes (304 stainless optional), EPDM seals, 120×120×20 mm, life ≥10 years, per GB 50370-2005. Shielded variants with beryllium-copper spring contacts keep electromagnetic shielding continuous.

Pressure signal feedback device (KITOZER-XH-1): installed on the device outlet piping; when discharge pressure reaches the action value the internal micro switch outputs a passive contact signal to the controller. Working pressure 0-6 MPa, action 0.5±0.1 MPa, 1 NO contact (DC24V/1A, AC220V/0.5A), ≥10,000 operations, G1/4″ thread, HPb59-1 brass, IP54, per GA 400-2002.

Cabling and identification: signal bus ZR-RVS-2×1.5 flame-retardant twisted pair, start power line ZR-BV-2×2.5, terminals, ties and identification plates complete the installation.

8. Detailed Technical Design

8.1 Suppression Device Installation Design

The device is installed at a free U position in the upper part of the rack with the nozzle facing downward, so the agent sprays top-down and fills the whole rack space quickly by gravity and diffusion. The position avoids server air outlets and heat-dissipation channels and reserves operation and maintenance space. If no upper U position is free, side or lower mounting with adjusted nozzle angles ensures coverage. Fixing uses standard rack screws at four points, firm and level, with the pressure gauge checked before and after installation. The start and feedback lines are connected firmly with correct polarity and insulated.

8.2 Detection Layout Design

Smoke and heat detectors are installed on the inner top of the rack, away from supply-air outlets and heat sources, ensuring effective smoke and temperature detection. Bases are fixed with screws, wiring is polarity-correct, and each detector is addressed electronically with recorded positions and numbers. The UV flame detector is mounted with an adjustable bracket where open-flame risk exists. Manual call points are installed at accessible positions inside or beside the rack with telephone jack interface.

8.3 Control and Linkage Design

The controller is wall-mounted in the equipment aisle or management area, connected to the two-wire detection loop and the start outputs of the suppression devices. The 0-30 s adjustable delay is set per site (typically 20-30 s for attended rooms). Linkage includes: pre-alarm on single-detector alarm; confirmed alarm activates the audible/visual alarm and discharge indicator; discharge feedback returns via the pressure signal device; fault and status signals upload to the environment-monitoring platform via RS485/Modbus-RTU or Ethernet. Zone division follows the rack layout — one zone per rack or per row of adjacent racks per the controller model.

8.4 Pressure Relief and Sealing Design

Each protected rack is fitted with one mechanical pressure relief device on the side or rear panel (0.01 m² per standard rack, calculated per code), opening at 1000±200 Pa to prevent overpressure deformation and closing at 500±100 Pa to retain agent. For shielded cabinets, shielded relief devices maintain shielding continuity, and control signals are routed through waveguide penetrations without breaking the shield. Cabling holes are sealed with fire-stop material to preserve the immersion environment and fire separation integrity.

9. Recommended Configuration and Preliminary Budget

9.1 Configuration Summary

The following table lists the recommended configuration for one standard rack-mounted gas fire suppression system set (adjustable per actual rack count and requirements):

No. System Product Model / Specification Qty Unit
1 Suppression Rack-mounted heptafluoropropane device KITOZER-JQF-4.2/2.5, 4.2 MPa, 2.5 L, 2U 1 set
2 Suppression Agent cylinder 304 stainless seamless, with container valve and gauge 1 pc
3 Suppression HFC-227ea agent Purity 99.9%, charge density 1150 kg/m³ 2.875 kg
4 Suppression Atomizing nozzle assembly 304 stainless, multi-directional 1 set
5 Suppression Pressure signal feedback Passive contact output 1 pc
6 Detection Photoelectric smoke detector KITOZER-SD-100, addressable two-wire 1 pc
7 Detection Rate-of-rise/fixed-temperature detector KITOZER-WD-200, 68℃ action 1 pc
8 Detection Detector bases Dedicated, ceiling/wall universal 2 pcs
9 Detection Manual alarm call point KITOZER-SB-1, with phone jack 1 pc
10 Control Single-zone gas controller KITOZER-MK-1, wall-mounted, DC24V standby 1 pc
11 Control Audible/visual alarm KITOZER-SG-1, 24V red flash 1 pc
12 Control Discharge indicator KITOZER-PD-1, outside door 1 pc
13 Control Emergency start/stop button KITOZER-QT-1, key reset, IP65 1 pc
14 Auxiliary Rack pressure relief device KITOZER-XY-0.01, mechanical 1 pc
15 Auxiliary Signal bus ZR-RVS-2×1.5 20 m
16 Auxiliary Start power cable ZR-BV-2×2.5 10 m
17 Auxiliary Terminals and accessories Terminals, ties, identification 1 set
18 Service Installation and commissioning Labor, debugging, acceptance guidance 1 item
19 Service Transport and insurance Delivery, loading, insurance 1 item
20 Service Training Operation, maintenance, emergency 1 item

Notes: multi-rack scenarios can use multi-zone controllers for centralized management; optional upgrades include perfluorohexanone eco devices, UV flame detectors, environment-monitoring integration modules and wide-temperature outdoor models.

9.2 Quotation Notes

The preliminary budget covers the suppression device and agent, detection and alarm components, control and indication equipment, auxiliary materials, on-site installation and commissioning, transportation and insurance, and training. All prices are indicative and quoted in RMB (CNY) only — no foreign-currency conversion is provided. The final quotation is confirmed by the sales engineer after the on-site survey according to the actual rack count, cabinet types, selected agent and controller configuration, and is subject to a formal contract. Free design proposals and technical consultation are provided before ordering; online installation is supported for live computer rooms without business interruption.

10. Technical Specifications

10.1 System Performance Summary

Item Specification
Protection granularity Single rack (independent protected unit)
Protected volume ≤2.5 m³ per standard set (up to 6.0 m³ with larger devices)
Agent types HFC-227ea (7-fluoropropane) / FK-5-1-12 (perfluorohexanone)
Design concentration 8% (HFC-227ea, electronic rooms) / 4.5% (FK-5-1-12)
Discharge time ≤10 s (HFC-227ea) / ≤8 s (FK-5-1-12)
Immersion time ≥10 min
Detection logic Smoke + heat compound; optional UV flame triple confirmation
Discharge delay 0-30 s adjustable, 1 s steps
Start modes Automatic / manual / mechanical emergency
Controller standby DC 24V/7Ah, ≥4 h monitoring endurance
Communications RS485 Modbus-RTU, optional Ethernet
Mounting 19-inch standard U positions, no room modification
Working temperature -20℃ ~ +50℃ (standard); -40℃ ~ +60℃ (wide-temperature)
Compliance GB 50370-2005, GB 50116-2013, GA 400-2002, ISO 14520
Device life Cylinder 20 years; agent 10 years; MTBF ≥100,000 h

10.2 Key Component Specifications

Component Key Parameters
Rack device JQF-4.2/2.5 4.2 MPa, 2.5 L, 2.875 kg charge, 2U, 12.5 kg, 304 SS cylinder
Rack device JQP-1.6/2.0 1.6 MPa, 2.0 L, 1.6 kg FK-5-1-12, ODP 0/GWP 1, 2U, 8.2 kg
Controller MK-1 1 zone, 32 addresses, 128×64 LCD, 1000 events, 0-30 s delay
Smoke detector SD-100 Photoelectric, ≤350 μA monitoring, 0.10-0.25 dB/m, addressing 1-255
Heat detector WD-200 Rate-of-rise/fixed 68℃, ≥7.5℃/min trigger, -20℃~+70℃
UV flame detector UV-300 185-260 nm, ≤5 ms response, 120°×120°, ≥15 m range, IP65
Relief device XY-0.01 0.01 m², open 1000±200 Pa, close 500±100 Pa, mechanical
Pressure feedback XH-1 0-6 MPa, action 0.5±0.1 MPa, NO contact DC24V/1A
Discharge indicator PD-1 DC 24V 3 W, red flash 1 Hz, visible ≥20 m
Emergency button QT-1 1 NO + 1 NC, key reset, IP65
Audible/visual alarm SG-1 ≥85 dB at 3 m, red flash 1-2 Hz, ≤150 mA

11. Key Advantages and Customer Value

11.1 Rack-Level Precision Protection — Loss Minimized

Breaking through the limitation of whole-room suppression, each rack is an independent protected unit: a fire affects only the rack of origin while adjacent racks’ business is unaffected, shrinking the business-interruption scope from a whole room to a single device and greatly reducing economic loss and operational risk — especially suitable for critical business racks.

11.2 Ultra-Early Response and Higher Suppression Efficiency

Detectors are deployed directly inside the rack, close to heat sources and ignition points, capturing smoke and temperature-rise signals earlier than room-level detectors. The suppression device is built into the rack with a short discharge path, so the agent fills the protected space in seconds and reaches the extinguishing concentration quickly — truly “detect early, extinguish small” to prevent fire growth.

11.3 Clean, Residue-Free and Zero Equipment Damage

Heptafluoropropane and perfluorohexanone are clean gaseous agents that vaporize rapidly after discharge, leaving no residue; they are non-conductive, non-corrosive and do not contaminate electronic components or circuit boards. After discharge, equipment can resume operation quickly without cleaning, with no secondary damage to precision IT equipment.

11.4 Standard Rack Mounting — Zero Room Modification

The 19-inch standard U-position modular design fixes directly into a free U position inside the rack, requiring no modification of room walls, floors or ceilings and no complex piping or cylinder room. Construction volume is small and the period short; online installation can proceed without stopping business, with almost no impact on the existing room.

11.5 Multi-Detection Logic — No False Discharge Risk

The “smoke + heat” dual-detection compound judgment, with optional flame detector for triple confirmation, starts the suppression program only when two or more detectors of different types alarm simultaneously, fundamentally reducing the false-discharge risk of a single detector — keeping room business stable.

11.6 Intelligent Linkage — Higher O&M Efficiency

Standard RS485/Ethernet interfaces with Modbus and other common protocols integrate seamlessly with room environment-monitoring and building automation systems, providing remote status monitoring, alarm push, history query and remote start/stop. O&M staff can grasp system status without entering the room, improving management efficiency.

11.7 Full-Process Compliance — Acceptance Ready

Design, product selection and construction strictly follow current national fire codes; all core components carry type test reports from national authoritative testing bodies, with complete documentation, meeting fire acceptance and routine inspection requirements and avoiding compliance risk.

11.8 Green Formulation — Dual-Carbon Trend Aligned

The optional perfluorohexanone agent has zero ozone depletion potential, extremely low global warming potential and a short atmospheric lifetime, degrading naturally — fully compliant with national green data center requirements and the dual-carbon strategy, the first choice for next-generation eco-friendly fire protection.

11.9 Flexible Expansion — Adaptable to Different Scenarios

The distributed architecture flexibly configures by rack count, scaling seamlessly from a single rack to hundreds of racks in a whole room; it adapts to standard server racks, network cabinets, shielded cabinets, outdoor cabinets and industrial control cabinets, meeting the protection needs of different industries and scenarios.

11.10 Source-Factory Service — Full-Lifecycle Assurance

As a source manufacturer with 20 years of computer room experience, KITOZER provides self-developed, self-produced, self-installed and self-serviced full-chain capability with fast response, ample spare parts and lower service cost — full-lifecycle support from design, installation and commissioning to later maintenance and upgrade.

12. Technical Q&A (50+ Items)

12.1 System Basics

Q1: What is a rack-mounted gas fire suppression system?

A: It is a miniature gas suppression system designed for single server racks, network cabinets and other rack-mounted equipment. The suppression device, detection components and control unit are highly integrated and installed directly inside the rack, providing single-rack-level precision fire protection. Compared with traditional room-level gas suppression, it has finer protection granularity, faster response and less business impact — the mainstream upgrade for high-density data centers.

Q2: What is the difference between rack-mounted and traditional piped gas suppression?

A: Five core differences: protection granularity — piped systems protect a whole room, rack systems protect a single cabinet; installation — piped systems need piping networks and a cylinder room with heavy engineering, rack systems mount directly in the cabinet without modification; impact scope — piped discharge stops the whole room, rack discharge affects only the rack of origin; construction period — piped systems coordinate with room fit-out and take long, rack systems install online within days; expansion flexibility — piped systems are hard to expand, rack systems are plug-and-use and expand on demand.

Q3: What scenarios is rack-mounted gas suppression suitable for?

A: Very wide: server and network racks in data centers and IDC rooms; core business racks in enterprise and government rooms; outdoor cabinets at communication base stations and edge computing nodes; shielded rooms and shielded cabinets; power control cabinets and industrial automation control cabinets; medical equipment and laboratory precision instrument cabinets; and other high-value rack-mounted equipment that cannot tolerate interruption.

Q4: What agents are commonly used, and what are their features?

A: Two mainstream types: heptafluoropropane (HFC-227ea) — high efficiency, mature technology, moderate cost, good insulation, the most widely used clean gaseous agent, though with some global warming potential; perfluorohexanone (FK-5-1-12) — eco-friendly, ODP 0, GWP 1, low extinguishing concentration, safer for people, ideal for attended rooms and green rooms, at higher cost. Both are clean gases leaving no residue and not damaging electronic equipment.

Q5: What size device does a standard 42U server rack need?

A: A standard 42U server rack has an internal net volume of about 1.5-1.8 m³; at the 8% design concentration for electronic rooms, a 2.5 L device charged with about 2.875 kg of heptafluoropropane meets the requirement with ample margin. For deep or high-density racks, or with perfluorohexanone, re-size per the actual volume.

Q6: Where is the device installed in the rack?

A: Usually at a free U position in the upper part of the rack with the nozzle facing downward, so the agent sprays top-down and fills the rack by gravity and diffusion. The position avoids server air outlets and heat-dissipation paths and reserves operation/inspection space. If no upper U position is free, side or lower mounting with adjusted nozzle angles is possible.

Q7: Does installation require downtime?

A: Normally no. The device fixes with standard U screws, and detection wiring runs along the cable management; construction does not touch running equipment or disconnect power/network, so online installation proceeds while business runs. Only in rare cases involving rack power tapping or existing-line changes is a brief low-peak window arranged.

Q8: Will the system discharge falsely? How is it avoided?

A: Multiple safeguards: “smoke + heat” compound judgment — a single detector alarm only pre-alarms, two different detector types must alarm together to start the sequence; a 0-30 s adjustable delay allows manual confirmation and emergency stop; a manual/automatic switch allows manual mode during maintenance; and the products pass strict reliability testing with extremely low false-action probability.

Q9: Would a false discharge damage equipment?

A: No. Both agents are clean inert gases — non-conductive, non-corrosive, no particle residue — vaporizing rapidly without staining or corroding circuit boards or surfaces. After a false discharge, simply ventilate, reset the system, and equipment runs normally with no hardware damage.

Q10: Does the system need a pressure relief opening? How is it installed?

A: Yes. Gas discharge raises internal pressure quickly; without relief, rack doors could deform or glass break. This solution includes a dedicated mechanical relief device — small, embedded by cutting a matching square hole in the rack side or rear panel; purely mechanical, no wiring, opening automatically on overpressure and closing when pressure drops.

12.2 Integration and Management

Q11: Can the system integrate with the existing environment-monitoring (DCIM) platform?

A: Yes. The controller has a standard RS485 interface with Modbus-RTU, optional Ethernet, integrating with mainstream environment-monitoring and building automation platforms for fire, fault and discharge status upload, remote monitoring and alarm push — no separate management platform needed.

Q12: How many rack devices can one controller manage?

A: It depends on the model: a single-zone controller manages one protected zone (one or several adjacent racks); multi-zone controllers come in 2-, 4- and 8-zone versions, each zone an independent protected unit. For rooms with hundreds of racks, multiple controllers network through the environment-monitoring platform for centralized management without a count limit.

Q13: Can it connect to the building automation or SCADA system?

A: Yes. Besides RS485/Modbus-RTU and optional Ethernet, the controller’s relay outputs can drive building automation inputs; for industrial scenarios it integrates with SCADA for unified monitoring of control cabinets and fire status.

Q14: Can existing old computer rooms be retrofitted?

A: Very suitable. Old rooms usually have room-level fire systems but insufficient single-rack protection; adding rack-mounted suppression creates “overall + local” dual protection for higher safety. Retrofit needs no structure modification, does not affect the existing fire system, is simple and cost-controlled — a high-value upgrade for aging rooms.

Q15: Does it support remote alarm push?

A: Yes. Through the environment-monitoring platform or optional 4G wireless module (for outdoor base stations), fire, fault and discharge alarms push to O&M staff via app/message in real time, enabling unattended operation.

Q16: Can the system be expanded later?

A: Fully. The distributed architecture adds rack devices zone by zone; controllers cascade or network, and the platform centralizes management — from one rack to hundreds without replacing existing equipment.

Q17: Is a dedicated management platform needed?

A: No separate platform is required. The controller operates standalone with local display and history; for centralized management it integrates with the room’s existing environment-monitoring platform.

Q18: What is the monitoring endurance during a power outage?

A: The controller has a built-in DC 24V/7Ah battery that float-charges under normal supply and switches automatically on main power loss, maintaining monitoring for ≥4 hours. The suppression device itself is stored-pressure — no external power needed; once the valve triggers, it discharges regardless of power status.

Q19: How are discharge and fault records viewed?

A: The controller stores 1,000 events (fire, fault, operation) with power-fail retention, viewable on the LCD and exportable via RS485; records can also be queried through the environment-monitoring platform.

Q20: Can the delay time be adjusted after installation?

A: Yes — 0-30 s in 1 s steps, set at commissioning and adjustable on site by an authorized operator with the password, adapting to attended or unattended room policies.

12.3 Safety and Compliance

Q21: Is discharge dangerous to people in the room?

A: Well-designed systems are fully safeguarded: a 0-30 s discharge delay with audible/visual alarm prompts evacuation; the discharge indicator outside the zone prohibits entry; both agents are safe at design concentrations for short exposure; and the emergency stop button terminates start on confirmed false alarm. Evacuation from the protected zone during discharge is still recommended.

Q22: Can the system pass fire acceptance? Does it have certification?

A: Yes. The design strictly follows GB 50370 (gas suppression design) and GB 50116 (fire alarm design); all core products carry type test reports from the National Fire Equipment Quality Supervision and Inspection Center and the National Fire Electronic Product Quality Supervision and Inspection Center, with complete compliant documentation. Fire inspection and acceptance can proceed per code after construction.

Q23: What is the difference between rack-mounted and cabinet-type heptafluoropropane?

A: Cabinet-type (piped-less) suppression is a floor-standing cabinet protecting a whole room — room-level fire protection; rack-mounted devices are small units inside server cabinets protecting a single rack — rack-level protection. They differ clearly in size, protection scope, installation and application.

Q24: Are the cylinder and agent inspected regularly?

A: Yes. Per the national gas cylinder safety regulation, fire-rated seamless stainless cylinders are pressure vessels with a 20-year design life and a hydrostatic test every 5 years by a qualified cylinder inspection body. Agent is sampled and tested every 3-5 years.

Q25: How long is the agent valid? Can it be refilled?

A: Both agents remain valid for about 10 years when sealed and pressure-normal. After discharge or leakage, qualified professionals recover and refill, followed by air-tightness and pressure tests before reuse.

Q26: What fire acceptance checks apply to rack-level systems?

A: Checks cover: product type test reports and certificates; detection and control device functionality; wiring and insulation; discharge logic and delay; emergency start/stop; pressure relief and agent quantity; linkage with the environment-monitoring system; and documentation. The system is designed to pass all.

Q27: Is the device heavy? Can the rack bear it?

A: Very light. A 2.5 L heptafluoropropane device weighs about 12.5 kg including agent — far below the standard rack U static load capacity (usually ≥50 kg per U) — and does not affect rack stability even at the top. Aluminum-alloy perfluorohexanone devices weigh about 8 kg.

Q28: What certifications do the detection devices hold?

A: Smoke, heat and flame detectors comply with GB 4715-2005, GB 4716-2005 and GB 12791-2006 respectively with national inspection reports; the controller complies with GB 4717-2005 and GB 16806-2006; the suppression device complies with GA 400-2002 — all documented for acceptance.

Q29: Does a shielded cabinet affect or get affected by the system?

A: No. The device installs fully inside the shielded cabinet without through-holes; shielded relief devices with shielding gaskets keep electromagnetic shielding continuous, and control signals route through waveguides — shielding performance is preserved, meeting classified and shielded room requirements.

Q30: Can outdoor cabinets use the system?

A: Yes. Wide-temperature models cover -40℃ to +60℃, adapting to outdoor diurnal and seasonal extremes; industrial-grade wide-temperature detectors and controllers ensure stable outdoor operation, with 4G wireless alarm push for unattended base stations.

12.4 Operation and Maintenance

Q31: Does the system require annual inspection? What maintenance is needed?

A: Regular maintenance is required — quarterly routine patrol and annual comprehensive inspection recommended. Daily items: pressure gauge in normal range; detector indicator status; detector dust cover cleaning; controller function and standby battery tests; wiring and terminal tightness; relief device operation. Agent sampling every 3-5 years and cylinder hydrostatic tests per national cycle.

Q32: What does quarterly patrol include?

A: Equipment appearance check and dust cleaning; pressure gauge check for leakage; detector function tests and indicator status; controller power and standby battery tests; line and terminal checks with tightening; basic function tests confirming normal operation; a signed patrol record.

Q33: What does the annual comprehensive inspection include?

A: All quarterly items plus deep function tests, linkage logic verification, grounding and insulation tests, battery capacity test, full agent pressure and sealing check, system operation assessment with maintenance recommendations, and a formal annual report.

Q34: How are the pressure gauge readings judged?

A: The gauge on the device indicates cylinder pressure; the pointer should be in the green normal zone. A reading below the green zone suggests agent leakage; above it suggests overpressure risk. Deviations are reported promptly for inspection.

Q35: What common faults occur, and how are they handled?

A: Typical: detector contamination causing false alarm — clean the dust cover; loose wiring — tighten terminals; standby battery aging — replace; communication interruption — check bus and addressing; pressure deviation — leak check and refill. The controller displays fault types with self-test, guiding targeted handling.

Q36: Can O&M staff perform simple maintenance themselves?

A: Yes. Daily patrol, cleaning, battery checks and simple fault handling follow the maintenance manual and training; operations involving agent, cylinder hydrostatic testing and system logic changes are performed by qualified professionals.

Q37: What about spare parts supply?

A: A local spare-parts warehouse in Guangzhou stocks the full series of complete devices and core components; non-artificial faulty parts are replaced free within warranty; after warranty, parts are supplied at cost; urgent parts can reach site within 4 hours.

Q38: How often should the standby battery be tested?

A: Every quarter during patrol, check charge and capacity; annually test discharge endurance (≥4 h monitoring). Replace the battery when capacity degrades significantly to keep power-fail protection effective.

Q39: Is online installation safe for running equipment?

A: Yes — installation avoids touching running devices, uses existing cable management paths, seals drilling dust, and follows ESD protection (anti-static wrist strap). Operations that could affect power or network are scheduled in low-peak windows with prior approval.

Q40: What documentation is delivered at handover?

A: Complete acceptance documentation: type test reports and certificates of all devices, installation records, wiring diagrams, commissioning test reports, configuration parameters, training materials, maintenance manual and contact information — satisfying fire acceptance and filing.

12.5 Selection and Design

Q41: How do I choose between heptafluoropropane and perfluorohexanone?

A: By priority: for mature, stable and budget-conscious needs, choose heptafluoropropane — long track record, lower cost, large installed base; for environmental performance, attended rooms and higher safety requirements, choose perfluorohexanone — superior eco profile, lower extinguishing concentration, safer for people, aligned with green data center trends, higher long-term value.

Q42: How is the device model selected for a specific rack?

A: Determine the rack’s internal net volume (typical 42U: 1.2-1.8 m³), apply the design concentration (8% HFC-227ea / 4.5% FK-5-1-12) in the quantity formula with altitude/sealing correction, then select the smallest model whose protected volume covers the result with margin — e.g. 2.5 L for standard 42U racks, 4.0-6.0 L for deep or high-density racks, 1.5 L for small network cabinets.

Q43: How is the pressure relief area calculated?

A: Per GB 50370, the relief area is calculated from the agent discharge rate and the allowable internal pressure of the protected enclosure; for a standard 42U rack, 0.01 m² is sufficient. The mechanical relief device opens at 1000±200 Pa and closes at 500±100 Pa, protecting the cabinet while retaining the agent.

Q44: What is the immersion time and why does it matter?

A: Immersion time (≥10 min for electronic equipment) is the period the agent must remain at extinguishing concentration to cool and prevent re-ignition of smoldering materials. The rack enclosure with closed doors and sealed cable openings maintains the concentration during immersion.

Q45: Do multiple racks share one protected zone?

A: Optionally. Adjacent racks can form one zone served by one controller output and one relief design, but the recommended practice is one rack per zone so a discharge affects only one cabinet; multi-zone controllers manage each rack independently.

Q46: Can the system protect a whole row or pod?

A: Yes, by installing per-rack devices under one multi-zone controller or a networked group — each rack still gets rack-level precision while management is centralized by row/pod.

Q47: What if the rack has no free U position?

A: Devices can mount on the rack side rails, rear space or bottom area with adjusted nozzle angles; alternatively use lower-profile models (1U) or external mounting brackets. The survey confirms the available space before selection.

Q48: Are there special requirements for high-density racks?

A: High-density racks (e.g. 20+ kW) have larger internal volumes and higher fire risk; use 4.0 L or 6.0 L devices, dual smoke+heat detection with optional UV flame detection, and verify the relief area for faster agent discharge.

12.6 Service and Support

Q49: What is the warranty period and scope?

A: 24-month free warranty from qualified acceptance. During warranty, non-artificial, non-force-majeure equipment faults and quality issues are repaired, replaced and serviced on site free; firmware upgrades and function optimization are free; quarterly free on-site patrol and annual deep inspection with formal reports are provided.

Q50: What is the fault response commitment?

A: 7×24 support: telephone technical guidance within 30 minutes; remote resolution within 2 hours where possible; on-site arrival within 4 hours in Guangzhou urban area, 8 hours in the Pearl River Delta, 24 hours within Guangdong; general faults repaired within 8 hours; if a major fault cannot be fixed within 24 hours, a standby device substitutes to keep the system running.

Q51: What services are available after the warranty period?

A: Annual maintenance contracts provide patrol, priority response, discounted parts and consumables, free technical consultation and upgrade guidance, and annual fire inspection support; alternatively, per-visit service is available on demand with per-visit settlement.

Q52: What training is provided?

A: Delivery training (4 h: operation, daily patrol, emergency basics) for O&M and management staff; quarterly return-visit training (1 h: common faults, maintenance skills); annual special training (8 h: code updates, deep maintenance, fault finding, emergency drills). Trainees are assessed by written and practical tests before independent operation.

Q53: What does the emergency operation procedure cover?

A: Real-fire emergency flow and role division; false-alarm judgment and handling; emergency start and stop button operation; mechanical emergency operation steps; post-discharge recovery and system reset; drill organization. Training includes a simulated fire drill.

Q54: Can the system be moved when racks relocate?

A: Yes — professional disassembly, relocation, reinstallation and commissioning services are provided, with pressure checks and function tests after reinstallation.

Q55: How is the agent refilled after discharge?

A: Qualified professionals recover the remaining agent, refill per the rated charge with density verification, then perform pressure and air-tightness tests and re-seal; the system is re-commissioned and the discharge record updated.

Q56: Does the company provide acceptance support?

A: Yes — technical staff support fire acceptance and annual fire inspection, preparing documentation, demonstrating functions and answering inspector questions, including remote projects as conditions allow.

Q57: What upgrade options exist?

A: Environment-monitoring integration modules, UV flame detection, perfluorohexanone eco conversion, wide-temperature outdoor models, shielded variants, and firmware/function upgrades — extending system life and capabilities.

Q58: How are spare parts priced after warranty?

A: At cost — only material cost is charged; urgent parts reach site within 4 hours in Guangzhou, keeping fault repair fast and economical.

Q59: Is the system suitable for industrial control cabinets?

A: Yes — with heat-sensing cable plus point-type heat detection, dust-resistant housings and wide-temperature devices, it protects PLC and VFD cabinets in dusty, high-temperature workshops and integrates with SCADA.

Q60: What are the green credentials of the eco option?

A: Perfluorohexanone has ODP 0, GWP 1 and a 0.014-year atmospheric lifetime, degrading naturally — compliant with Montreal Protocol alternatives, green data center standards and dual-carbon policy, with a NOAEL concentration of 10% (above the 4.5% design concentration) for personnel safety.

13. Construction Schedule

13.1 Overall Period

For a standard computer room rack-mounted gas fire suppression system project, the overall construction period is 15 working days (excluding acceptance and training), adjustable by rack count and site conditions. Construction is scheduled in business low-peak periods where possible, with core equipment operations reported in advance, minimizing impact on normal room operation.

13.2 Detailed Schedule

Stage Work Days Responsible Coordination
1. Preparation Site survey (rack sizes, count, positions), detailed drawings and point/wiring plan, material stocking and incoming inspection, technical and safety disclosure, room entry procedures and work-area demarcation 2 PM, technical lead Owner provides room drawings, entry passes, designated contact
2. Cabling Cable management installation, signal bus and start power wiring, labeling, separation of signal/power, continuity and insulation tests, controller wall mounting and terminal fixing 3 Foreman, crew Owner coordinates time windows, confirms drilling positions
3. Front-end installation Mount rack devices at U positions, install and address smoke/heat detectors, install emergency buttons, audible/visual alarms and discharge indicators, cut and install relief devices, appearance and fixing check 4 Crew, QC Owner confirms drilling positions not affecting equipment
4. Wiring Terminate all devices, controller loop and power wiring, grounding and ground-resistance test, full-circuit continuity and polarity check, dressing and labeling 2 Engineer, crew Owner may witness wiring workmanship
5. Commissioning Power-on tests, address registration, detector alarm and fault simulation tests, manual alarm and emergency start/stop tests, linkage logic, delay and start output verification, simulated discharge and feedback test, DCIM integration joint test 2 Commissioning engineer, technical lead Owner O&M staff observe and learn
6. Acceptance and handover Contractor self-inspection and rectification, as-built documentation, owner-organized acceptance with function demonstration, on-site training and documentation handover, project handover and warranty start 2 PM, all Owner organizes acceptance team and O&M training attendance

13.3 Schedule Assurance

Advance stocking: production and stocking start immediately after contract signing; common models are kept in stock to avoid supply delay.

Personnel assurance: a fixed construction crew with certified workers and rich experience avoids schedule impact from personnel changes.

Progress tracking: daily short site meetings check progress; slippage triggers immediate personnel and sequence adjustment.

Cross-operation: piping and equipment installation proceed in parallel zones where safe, compressing the total period.

Contingency: potential site issues are anticipated with backup plans and spare materials for rapid resolution.

14. Construction Organization and Quality/Safety Measures

14.1 Organization Structure

A dedicated project team is formed for the project:

Project manager (1): overall project management, coordinating schedule, quality, safety and cost; first person responsible for the project.

Technical lead (1): solution deepening, technical disclosure, on-site technical guidance, system commissioning and acceptance; resolves technical issues during construction.

Foreman (1): on-site construction organization, personnel dispatch, work sequencing, schedule execution, and implementation of site safety and quality requirements.

Construction crew (3-5): cabling, equipment installation and wiring, certified for their trades.

Safety officer (part-time): site safety supervision, safety inspection and PPE checks.

QC inspector (part-time): quality inspection of each construction step, three-level inspection system, quality records.

14.2 Pre-Construction Preparation

Technical preparation: technicians study the design drawings and relevant codes, conduct drawing review and clarify key points and difficulties; a special construction plan and work instructions are compiled and approved; full technical and safety disclosure covers workmanship, quality standards, safety requirements and precautions; codes, drawings and record forms are prepared.

Material preparation: all equipment and materials are stocked per the bill of materials with certificates of conformity and test reports; incoming inspection verifies model, specification, quantity, appearance and accessories; tools — rotary hammer, hand drill, crimping pliers, multimeter, megger, ladder, tool kit — are ready with measuring instruments within calibration validity; safety and PPE items — helmets, insulating shoes, anti-static wrist straps, dust masks, extinguishers — are prepared.

Site preparation: entry time is coordinated with the owner, room entry passes obtained, and the owner’s room management rules observed; work area and temporary material storage are demarcated with finished-product protection; temporary power is connected safely with reliable grounding; the site environment and installation positions are verified against drawings.

14.3 Core Construction Processes

Cabling: room wiring runs along cable management, straight and neatly tied; signal and power lines are separated by ≥30 mm to avoid interference; signal bus ZR-RVS-2×1.5 and start power ZR-BV-2×2.5 are both flame-retardant; every cable is labeled at both ends with number and endpoints; after wiring, continuity and insulation tests confirm insulation resistance ≥20 MΩ with no short, open or loose joints; controller housing and metal conduit are reliably grounded with ground resistance ≤4 Ω.

Suppression device installation: confirm the U position per drawings, avoiding air outlets and power areas and reserving operation space; fix with standard rack screws at four points, firm and level without loosening or tilting; adjust nozzle angle and direction for full rack coverage without obstruction; check the pressure gauge in the green zone before and after installation; connect start and feedback lines firmly with correct polarity and insulation.

Detector installation: install on the inner top of the rack, away from supply-air outlets and heat sources for effective detection; fix bases firmly with correct, polarity-safe wiring; encode addresses before installation with recorded positions and numbers, no duplicates; rotate detectors into bases, confirm latching and normal LED flashing.

System commissioning: re-check all wiring for shorts and wrong connections before power-on; test each detector, manual call point and audible/visual alarm individually, confirming addresses and status; test fire alarm, fault alarm, self-check, silence and reset functions; simulate dual-detector alarm to verify delay logic, audible/visual activation, discharge indicator and suppression output; test emergency start/stop and mechanical emergency operation; test DCIM communications with accurate upload and status sync; set delay time and sensitivity per site and save configuration.

14.4 Quality Assurance Measures

Three-level inspection: crew self-inspection, QC re-inspection and technical-lead final inspection; unqualified upstream work cannot proceed to the next step.

Material control: all incoming equipment and materials must carry certificates and test reports; unqualified products are prohibited on site.

Workmanship standards: construction strictly follows drawings, national codes and process standards — firm wiring, neat layout, level installation and clear labeling.

Concealed-work acceptance: concealed cabling must be accepted and signed by the owner before covering.

Quality records: construction, test and acceptance records are kept complete and synchronized with progress.

Product protection: existing equipment, racks, floors and walls are protected from impact, contamination and damage.

14.5 Safety and Civilized Construction Measures

Safety disclosure: full safety disclosure before work; room entry complies with the owner’s computer room safety management rules.

Certified operation: electricians, welders and other special-trade personnel must hold valid certificates.

Electrical safety: temporary power is connected per code with qualified sockets; no unauthorized wiring; live work requires two-person cooperation with insulation protection.

Hot-work control: hot work requires a permit, extinguishers, a designated watcher, and confirmation of no ignition source after completion.

ESD protection: anti-static wrist straps are worn when touching in-rack equipment to avoid static damage to electronic components.

Site tidiness: the site is cleaned daily with tools and materials returned to place — work finished, site clean.

Safety patrol: the safety officer patrols daily, identifies hazards and stops violations.

14.6 Finished Product Protection

Dust covers protect existing equipment and racks before drilling; dust control during rack openings with immediate debris removal; equipment and materials handled gently to avoid scratching rack paint or existing equipment; tools and materials stored in designated areas, never on equipment or heat-dissipation paths; personnel must not touch unrelated equipment, switches or cables to prevent misoperation and business interruption; the site is checked for safety hazards before leaving each day.

15. After-Sales Service

15.1 Warranty Commitment

Warranty period: 24 months free warranty from qualified completion acceptance.

Warranty scope: during warranty, non-artificial, non-force-majeure equipment faults and quality issues are repaired, replaced and serviced on site free of charge.

Software upgrade: firmware upgrades and function optimization are free during warranty.

Patrol service: free quarterly on-site patrol during warranty and an annual comprehensive deep inspection with a formal report.

15.2 Fault Response Mechanism

A 7×24 technical support system provides multi-level response: telephone technical guidance within 30 minutes of a report; remote resolution within 2 hours for remotely solvable issues; on-site arrival within 4 hours in Guangzhou urban area, 8 hours in the Pearl River Delta and 24 hours within Guangdong; general faults repaired within 8 hours; for major faults not fixable within 24 hours, a standby device substitutes to keep the system running.

15.3 Regular Patrol Service

Quarterly routine patrol: equipment appearance check and dust cleaning; pressure gauge check for leakage; detector function and indicator tests; controller power and standby battery tests; line and terminal inspection with tightening; basic function tests; a signed patrol record.

Annual comprehensive inspection: all quarterly items plus deep function tests, linkage logic verification, grounding and insulation tests, battery capacity test, full agent pressure and sealing check, system operation assessment with maintenance recommendations, and a formal annual report.

15.4 Repair and Maintenance Service

Agent refill: professional recovery and refill after discharge or leakage, with pressure and air-tightness tests after filling.

Cylinder inspection: hydrostatic tests per the national cycle with test reports.

Consumable replacement: regular replacement of seals, indicator lamps and batteries to maintain reliability.

System upgrade: function extension, firmware upgrades and platform integration to extend system life.

Relocation service: professional disassembly, relocation, reinstallation and commissioning for rack moves.

15.5 Technical Support

A 7×24 technical consultation hotline answers operation, maintenance and fault-finding questions; WeChat/email online support with illustrated guidance; fire-code interpretation, solution optimization and expansion consulting; support for annual fire inspection and acceptance checks.

15.6 Spare Parts Supply

A local warehouse in Guangzhou stocks the full series of complete devices and core components; non-artificial faulty parts are replaced free during warranty; after warranty, parts are supplied at material cost; urgent parts reach site within 4 hours for fast repair.

15.7 Post-Warranty Service

After warranty expiry, annual maintenance contracts provide service equal to the warranty period: regular on-site patrol and care, priority fault response and on-site repair, discounted parts and consumables, free technical consultation and upgrade guidance, and annual fire inspection support. Per-visit service is also available on demand with per-visit settlement.

16. Training Plan

16.1 Training Objectives

Enable O&M personnel to master daily operation, status viewing and alarm handling; enable management to understand system principles, architecture and management points; enable emergency personnel to master fire emergency procedures and emergency operation; and develop O&M personnel capable of daily maintenance and simple fault finding, keeping the system stable over the long term.

16.2 Training Audience

Operation level: room O&M personnel and duty staff.

Management level: room supervisors and department heads.

Emergency level: volunteer firefighters and emergency responders.

16.3 Training Content

Basic theory: gas suppression fundamentals and agent characteristics; rack-mounted system architecture, composition and working process; relevant fire codes and room fire-safety management rules; design approach and protected-zone division.

Operation and use: controller interface, menus and parameter viewing; identification of fire, fault and discharge states; silence, reset and self-check operations; manual/automatic mode switching and applicable scenarios; history query and export.

Daily maintenance: patrol content, cycles and methods; pressure gauge reading and normal-range judgment; detector cleaning and simple fault finding; standby battery check and care; common fault phenomena, causes and handling.

Emergency handling: real-fire emergency flow and role division; false-alarm judgment and handling; emergency start/stop button operation; mechanical emergency operation steps and precautions; post-discharge recovery and system reset; drill organization and methods.

16.4 Training Methods

On-site lecture: engineers explain theory with physical demonstrations.

Hands-on practice: trainees operate the controller and simulate alarms and handling to master practical skills.

Simulated drill: organized fire emergency drills familiarize the handling process.

Material delivery: paper and electronic training manuals, operation instructions, maintenance manuals and emergency plans are provided.

Follow-up Q&A: continuous online support answers questions arising in use.

16.5 Training Schedule

Stage Content Duration Audience Form
Delivery training System operation, daily patrol, emergency basics 4 h O&M, management Lecture + practice
Quarterly return training Common fault handling, maintenance skills 1 h O&M Lecture + Q&A
Annual special training Code updates, deep maintenance, fault finding, emergency drill 8 h All relevant Centralized + drill

16.6 Assessment and Evaluation

Training effectiveness is verified by written and practical tests after training; trainees pass before operating the system independently. Targeted supplementary coaching follows assessment results so all trainees master the required skills. Trainee feedback is collected to continuously optimize content and methods.

16. Training Plan

16.1 Training Objectives and Audience

Training objectives: through systematic training, enable management personnel to fully understand the system structure, working principles and performance characteristics, master daily operation methods and inspection/maintenance essentials, identify common faults and handle simple problems, ensuring safe, stable and long-term operation.

Training audience: management and O&M personnel designated by the client, recommended 2-3 persons with basic electrical and equipment knowledge.

16.2 Tiered Training Content System

Level 1: Basic operation training (1 day)

– Basic principles: system concepts, structure composition, performance indicators;

– Daily operation standards: correct operation of equipment, control and safety systems;

– Daily inspection contents: daily/weekly/monthly check items;

– Safety precautions: usage prohibitions and emergency handling procedures.

Level 2: Maintenance training (1 day)

– Detailed structure of each subsystem and working principles;

– Daily maintenance methods: cleaning, fastening checks, routine care;

– Common fault identification and simple handling;

– Emergency handling procedures for power failure, fire and equipment faults.

Level 3: Advanced management training (as needed)

– Performance influencing factors and how to avoid degradation;

– Upgrade and expansion knowledge and specification requirements;

– Relevant national standards interpretation.

16.3 Training Methods and Schedule

– Methods: combination of “theory explanation + on-site practice + Q&A interaction”;

– Schedule: training arranged at the completion acceptance stage, synchronized with handover, 2 days of intensive training total; time flexibly adjustable; a free repeat training session is provided for newly assigned personnel.

16.4 Training Assessment and Documentation Delivery

– Assessment: theory written test plus practical operation; training qualification certificates issued upon passing; supplementary training for those who fail;

– Documentation delivery: complete O&M documentation, including operation and maintenance manual, equipment manuals and certificates, completion drawings and hidden work records, test reports and after-sales service contact card, all bound into volumes.

17. Anonymous Typical Project Scenarios

All project scenarios below are anonymous, generalized examples provided for reference only. No real customer names, addresses or identifiable details are disclosed.

17.1 Internet Company Data Center Rack-Level Fire Upgrade

Project overview. An internet company in Guangzhou operates a data center with more than 200 standard server racks protected by an existing room-level piped heptafluoropropane system. Once discharged, the room-level system would interrupt business on a large scale with severe losses. The customer wanted a fire upgrade for core business racks with finer protection granularity.

Implementation. KITOZER rack-mounted heptafluoropropane devices were deployed, one 2.5 L device per core rack; single-zone and multi-zone gas suppression controllers were provided; smoke plus heat dual detection was installed inside each rack; and the system was integrated into the customer’s existing environment-monitoring platform for centralized management.

Project scale. 200 rack-mounted suppression devices, 25 eight-zone controllers, plus detection and auxiliary components.

Highlights. Fully online construction without interrupting customer business; all installation and commissioning completed in 20 days; dual-detection logic with extremely low false-alarm rate; dual protection with the original room-level system greatly raised the safety level.

Customer feedback. Stable operation, professional and standardized construction, timely service response, effectively reduced fire-related business interruption risk; subsequent expansion continued with the same solution.

17.2 Government Data Center Green Fire Upgrade

Project overview. A provincial government data center carrying government service systems had extremely high safety and compliance requirements, and responded to green room construction by replacing an aging system with an environmentally friendly fire solution.

Implementation. Rack-mounted perfluorohexanone devices were adopted — green, safe for equipment and personnel; triple detection (smoke + heat + UV flame) with compound judgment further reduced false-discharge risk; shielded zones used dedicated shielded variants to preserve electromagnetic shielding performance.

Project scale. 120 rack-mounted perfluorohexanone devices, 15 controllers, with detection and relief devices.

Highlights. The FK-5-1-12 agent has ODP 0, meeting green data center standards; the system passed fire acceptance and classified information-system security inspection; construction strictly followed government room management rules with zero safety incidents.

Customer evaluation. Strong compliance, met environmental indicators, reliable product quality, professional service team — satisfying the high standards of a government room.

17.3 Communication Operator Outdoor Base Station Cabinet Fire Project

Project overview. An operator’s outdoor communication base stations are numerous, widely distributed and unattended; in-cabinet equipment is high-value and summer heat can trigger electrical fires, while traditional fire protection is difficult to adapt to outdoor scenarios.

Implementation. Industrial wide-temperature rack-mounted heptafluoropropane devices were selected, operating from -40℃ to +60℃; heat plus flame detection adapted to dusty outdoor environments; 4G wireless transmission pushed alarm messages to the O&M platform remotely.

Project scale. First batch of 150 outdoor base station cabinets across multiple Pearl River Delta cities.

Results. Stable operation since commissioning; multiple equipment overheating hazards were successfully warned and handled, avoiding base station fire accidents; remote management greatly reduced patrol cost and improved O&M efficiency.

18. SEO Optimization Section

All reference prices in this technical solution are in RMB (CNY) only and are for reference purposes; final quotation is subject to the confirmed configuration.

18.1 Keyword System

– Core keywords: technical design solution, system configuration, technical parameters, construction and O&M services;

– High-conversion long-tail keywords: design solution, configuration list, technical parameters, construction plan, after-sales service;

– Industry traffic keywords: system architecture, applicable standards, technical Q&A, project cases;

– Brand keywords: KITOZER, Guangzhou Lain.

18.2 SEO Tag System

– Title tag: the article title — Guangzhou Lain KITOZER;

– Meta description: Guangzhou Lain professionally provides complete technical design solutions with detailed configuration list, full-system product technical parameters, construction organization plan and after-sales service — source manufacturer customization, compliant performance, third-party testing supported;

– H1 tag: the article title;

– H2 tags: system design and product parameters, construction organization plan, after-sales service and training, engineering cases.

18.3 Internal Link Anchor Text

– Core anchor text: technical design solution, system construction;

– Long-tail anchor text: configuration list, technical parameters, construction plan;

– Related anchor text: shielding cabinet, micro-module cold aisle, integrated computer room, outdoor cabinet.

19. Official Contact Information

– Company Name: Guangzhou Lain Intelligent System Development Co., Ltd.

– Brand: KITOZER (Pioneer)

– Official Website: https://gdlain.com

– Tel: +86 13538869979 (Tel / WhatsApp)

– Address: No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou, China

For any inquiries about this technical design solution, configuration customization, quotation or construction services, please contact us through the information above. We provide free design consultation and tailored solutions for your specific requirements.