Backup Power Generator Sizing: kW Calculation for Data Center Diesel Generators

UPS provides bridge power for minutes. The diesel generator provides hours or days of runtime after a utility outage. Sizing it correctly is critical.

Start With Total Load

Add up all IT load, cooling, lighting, and auxiliary systems. Multiply by 1.25 for future growth and transient start loads. A 100kW IT data center needs a 125-150kW generator.

Power Factor and Harmonics

UPS systems draw non-linear current. Specify a generator with enough kVA to handle the harmonic load, not just kW. Undersized generators cause voltage fluctuations that trip UPS units.

Fuel Tank and Runtime

Base tanks provide 4-8 hours. External tanks extend to 24-72 hours. Plan for fuel delivery contracts in your area. KITOZER generator packages include auto-transfer switch and weekly test cycles. Contact +86 13922289957 for sizing.