Drone Charging Container Installation and Commissioning Manual

Table of Contents

SEO Optimization Tag System

Page Core Optimization Tags

Title Tag: Drone Charging Container Installation and Commissioning Manual_Industrial Special-Purpose Drone Charging Station Installation Guide – Guangdong Lai’an

Meta Keywords: Drone Charging Container, Industrial Special-Purpose Container, Drone Automatic Charging Container Installation, Drone Charging Container Commissioning Plan, Inspection Drone Charging Container, Lai’an Drone Charging Container, Drone Hangar Container, Intelligent Drone Charging Cabin, Drone Charging Container Manufacturer, Airport Drone Charging Container Customization

Meta Description: Guangdong Lai’an Intelligent Equipment Co., Ltd. professionally researches, develops, and manufactures industrial special-purpose drone charging containers. This manual comprehensively details the drone charging container installation process, commissioning steps, acceptance standards, maintenance, and troubleshooting procedures. It supports multi-scenario drone automatic charging requirements including power inspection, logistics distribution, security monitoring, emergency rescue, and more. Customized solutions are available. Service Hotline: +86 13538869979.

H1 Tag: Drone Charging Container Installation and Commissioning Manual

H2 Tags: Product Overview and Technical Parameters, Pre-Installation Preparation Work, Container Body Main Installation Engineering, Internal Subsystem Installation Specifications, System Commissioning and Functional Verification, Engineering Acceptance and Delivery, Daily Operation Maintenance, Common Fault Troubleshooting and Handling, Safety Operation Specifications, After-Sales Service and Technical Support

Internal Link Optimized Anchor Texts (Natural Integration)

Core Anchor Texts: Drone Charging Container, Industrial Special-Purpose Container

Long-Tail Anchor Texts: Drone Charging Container Installation and Commissioning, Inspection Drone Charging Container Customization, Drone Automatic Charging Station Installation Plan

Related Anchor Texts: Intelligent Drone Hangar, Special-Purpose Container Customization, Drone Charging Cabin Manufacturer

Manufacturer Information

  • Manufacturer: Guangdong Lai’an Intelligent Equipment Co., Ltd.
  • Service Hotline: +86 13538869979 (WeChat same number)
  • Technical Support: +86 13538869979
  • Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou City
  • Official Website: https://gdlain.com

Preface

With the rapid development of the low-altitude economy, the application scale of drones in power inspection, oil and gas pipeline inspection, security monitoring, logistics distribution, emergency rescue, surveying and mapping exploration, agricultural and forestry crop protection, and other industries continues to expand. The contradiction between drone endurance limitations and the demand for operational continuity is becoming increasingly prominent. As an important segmented product in the industrial special-purpose container field, the drone charging container has become key infrastructure supporting all-weather, long-endurance, unattended drone operations, thanks to its core advantages of integrated design, high outdoor protection, fully automatic operation, and flexible deployment.

This manual has been compiled by Guangdong Lai’an Intelligent Equipment Co., Ltd. in accordance with relevant national standards, industry specifications, and product design requirements. It aims to provide users, installation contractors, and operation and maintenance management personnel with complete, standardized, and operable technical guidance for the entire drone charging container installation, commissioning, acceptance, and operation and maintenance process. The manual strictly follows the compilation principles of “Safety First, Standardized Operation, Performance Compliance, Long-Term Reliability,” providing detailed technical descriptions and operational guidance for pre-installation preparation, container positioning, subsystem installation, stand-alone commissioning, system integration testing, acceptance and delivery, daily maintenance, and fault troubleshooting.

This manual is applicable to Guangdong Lai’an’s full series of industrial special-purpose drone charging containers, covering multiple specifications including the 6-foot standard type, 12-foot extended type, and 20-foot multi-drone concurrent type. It is also compatible with container products supporting multiple charging modes including wired contact charging, wireless inductive charging, and automatic battery swap. Relevant construction units and operation and maintenance personnel must carefully study this manual before commencing work and strictly follow the standardized procedures to ensure equipment installation quality, operational safety, and service life.

The content of this manual will be continuously updated with product technology iterations. If you have any questions, please contact our technical support hotline promptly to obtain the latest version of the technical documentation.

Part 1: Product Overview and Technical Parameters

1.1 Product Definition and Core Value

1.1.1 Product Definition

The drone charging container belongs to the segmented category of industrial special-purpose containers. It is a mobile, modularized drone fully automatic charging support facility that uses a standard maritime shipping container as the carrier, highly integrating an intelligent charging system, temperature control environment system, power distribution and protection system, intelligent monitoring system, drone takeoff/landing and positioning system, and fire protection and security system. Unlike traditional fixed machine-room style drone charging stations, container-style charging facilities offer significant advantages including high factory pre-fabrication, minimal on-site installation work, flexible relocation and deployment, and strong outdoor protection capabilities. They can be rapidly deployed in various complex outdoor scenarios such as mountainous areas, wilderness, borders, ports, and along power grid lines.

1.1.2 Core Value

  • Enhanced Operational Efficiency: Enables automatic return, precise landing, and automatic charging after drone missions without manual on-site battery replacement operations, reducing the interval between single-drone sorties by over 80%, supporting 7×24-hour uninterrupted operations.
  • Reduced Operation and Maintenance Costs: Unattended operation mode significantly reduces on-site O&M personnel; centralized charging management reduces per-sortie charging energy consumption and battery degradation.
  • Enhanced Environmental Adaptability: Container structure provides IP54/IP55 level protection; built-in temperature control system operates stably in extreme environments from -40°C to +55°C, suitable for plateau, extreme cold, extreme heat, high humidity, and high salt-spray conditions.
  • Flexible and Convenient Deployment: Fully pre-fabricated and debugged at the factory; on-site only requires foundation pouring, container hoisting, and utility connections before operation. Deployment cycle is reduced from over 30 days for traditional machine rooms to 3-7 days.
  • Safe, Reliable, and Controllable: Multiple electrical safety protections, battery thermal runaway warning, automatic fire suppression, remote monitoring and alarming mechanisms ensure charging process safety and eliminate safety accident risks.

1.2 Industry Application Scenarios

Drone charging containers have achieved large-scale application across multiple industries due to their excellent environmental adaptability and deployment flexibility. Typical scenarios include:

  • Power Inspection Scenario: Deployed along transmission line corridors and around substations, working with inspection drones to achieve routine autonomous line inspection, significantly improving grid inspection frequency and defect detection rates.
  • Oil and Gas Pipeline Inspection: Deployed at intervals along oil and gas pipelines to achieve full-length autonomous inspection of long-distance pipelines, promptly detecting pipeline leaks, illegal construction, and geological disaster risks.
  • Security and Border Patrol: Deployed along borderlines, around industrial parks, and at ports and docks, working with security drones to achieve 24/7 autonomous patrol and monitoring, improving security response speed.
  • Logistics Distribution Scenario: Deployed at logistics transfer nodes and distribution stations to support route-based, routine operations of last-mile delivery drones, ensuring battery supply for delivery drones.
  • Emergency Rescue Scenario: Rapidly and flexibly deployed to disaster sites to provide continuous charging support for emergency reconnaissance and disaster assessment drones, supporting emergency rescue command and decision-making.
  • Surveying and Mapping Exploration Scenario: Deployed in surveying operation areas to support continuous operation of large-area terrain mapping and resource exploration drones, improving field surveying efficiency.
  • Agricultural and Forestry Crop Protection Scenario: Deployed at large farms and forest areas to provide nearby charging supply for crop protection drones, expanding coverage and improving operational efficiency.

1.3 Product Models and Classification

Guangdong Lai’an drone charging containers are divided into three major series based on specifications, dimensions, charging modes, and carrying capacity, meeting the drone operational needs of different industries and scales.

1.3.1 Classification by Container Specification

Product Series Container Specification Compatible Drone Quantity Typical Application Scenarios
LA-W6 Small Series 6-foot standard special-purpose container 1-2 small drones Single-point inspection, temporary operations, emergency deployment
LA-W12 Medium Series 12-foot extended special-purpose container 2-4 small/medium drones Routine line inspection, park security, small/medium logistics nodes
LA-W20 Large Series 20-foot standard industrial special-purpose container 4-8 medium/large drones Large-scale power grid inspection bases, trunk logistics hubs, border patrol stations

1.3.2 Classification by Charging Mode

  • Contact Charging Type: Uses conductive contact point docking for charging. High charging efficiency, low cost, compatible with the majority of industry drones. This is the current mainstream product form.
  • Wireless Charging Type: Uses electromagnetic induction wireless charging. No mechanical contact wear, higher reliability, compatible with specific drone models, suitable for high-frequency operation scenarios.
  • Automatic Battery Swap Type: Built-in robotic arm and spare battery compartment. Automatically replaces batteries after drone landing. Fastest energy replenishment speed, suitable for operations with high time-criticality requirements.

1.4 Overall Technical Parameters

1.4.1 Container Structure Parameters

  • Container Standard: Meets GB/T 1413-2018 “Series 1 Freight Containers – Classification, Dimensions and Ratings”
  • External Dimensions (20-foot standard type): Length 6058mm × Width 2438mm × Height 2896mm (customizable height)
  • Internal Dimensions (20-foot standard type): Length 5898mm × Width 2352mm × Height 2680mm
  • Container Material: Main body uses Q235B high-quality carbon structural steel; side panels ≥2.0mm thickness; roof panels ≥2.5mm thickness; bottom frame crossbeams ≥5.0mm thickness
  • Protection Rating: Overall IP54; key electrical compartments IP55, compliant with GB 4208-2017 “Degrees of Protection Provided by Enclosures (IP Code)”
  • Thermal Insulation: Container walls filled with 50mm thick rock wool insulation layer; thermal conductivity ≤0.040W/(m·K); meets extreme environment temperature control requirements
  • Anti-Corrosion Performance: Entire surface shot-blast derusted, sprayed with epoxy zinc-rich primer + polyurethane topcoat; total film thickness ≥120μm; salt spray test ≥1000 hours
  • Rated Static Load: Floor uniformly distributed load ≥500kg/m²; localized load in key equipment installation areas ≥2000kg/m²
  • Wind Resistance Rating: Can withstand Category 12 hurricane (32.7m/s) in closed state
  • Seismic Rating: Meets 8-degree seismic fortification requirements of GB 50011-2010 “Code for Seismic Design of Buildings”

1.4.2 Electrical System Parameters

  • Rated Input Voltage: AC 380V three-phase five-wire / AC 220V single-phase; voltage fluctuation range ±15%
  • Rated Frequency: 50Hz±2Hz
  • Total Installed Power (20-foot standard type): ≤30kW
  • Standby Power Consumption: ≤0.8kW
  • Insulation Class: B-class insulation for entire electrical system
  • Grounding Resistance: ≤4Ω, compliant with GB 50054-2011 “Code for Design of Low Voltage Electrical Installations”
  • Lightning Protection Rating: Level II lightning protection for power system; Level III for signal system; maximum surge current capacity 40kA
  • Power Factor: ≥0.92

1.4.3 Charging System Parameters

  • Number of Charging Channels: 8 independent charging channels configured for 20-foot standard type; expandable to 16 channels
  • Single Channel Rated Output Power: 200W~3000W configurable, compatible with different drone battery models
  • Output Voltage Range: DC 12V~DC 120V, covering 2S~32S lithium battery charging requirements
  • Charging Modes: Constant current constant voltage charging, trickle float charging, balancing charging, fast charging mode (selectable)
  • Charging Efficiency: ≥93%
  • Voltage Measurement Accuracy: ±0.5%
  • Current Measurement Accuracy: ±1%
  • Battery Compatibility: Supports DJI, Autel, XAG, JOUAV and other mainstream brand drone batteries; supports BMS communication protocol integration
  • Auto-Stop at Full Charge: Automatically cuts off charging output when battery reaches 100%; overcharge protection included
  • Multi-Drone Scheduling: Supports intelligent scheduling strategies including multi-drone sequential charging, priority charging, and scheduled charging

1.4.4 Environmental Control Parameters

  • Internal Operating Temperature Range: 10°C~30°C settable; control accuracy ±2°C
  • External Ambient Temperature Range: -40°C~+55°C
  • Internal Humidity Control Range: 40%RH~60%RH
  • Air Conditioning Configuration: 20-foot standard type configured with 2 units of 3HP industrial inverter air conditioners; total cooling capacity 16kW; total heating capacity 14kW
  • Ventilation System: 4 axial flow ventilation fans; single fan airflow ≥1500m³/h; supports fresh air exchange and forced heat dissipation
  • Dehumidification Capacity: Industrial dehumidifier configured; daily dehumidification capacity ≥20L/D
  • Low-Temperature Heating: PTC electric heaters configured; total heating power 6kW; meets rapid temperature rise requirements in low-temperature environments

1.4.5 Monitoring System Parameters

  • Main Control Unit: Industrial-grade industrial PC; quad-core processor; 8G memory; 256G solid-state drive
  • Data Acquisition: Supports comprehensive data acquisition including voltage, current, temperature/humidity, smoke, water immersion, door magnetic status, wind speed, and rainfall
  • Communication Methods: Supports Ethernet, 4G/5G, WiFi, fiber optic, and other communication methods
  • Video Surveillance: 4 channels of 2-megapixel infrared night vision cameras covering takeoff/landing area, equipment area, and entrances/exits; video storage duration ≥30 days
  • Alarm Methods: Supports audible/visual alarm, SMS alarm, platform popup alarm, WeChat push alarm, and other methods
  • Remote Management: Supports remote monitoring of equipment operating status, charging data, and alarm information via Web and mobile platforms
  • Data Storage: Local storage of ≥1 year operating data; supports cloud synchronized storage

1.4.6 Takeoff/Landing and Positioning System Parameters

  • Landing Platform Dimensions: 2000mm×2000mm (customizable)
  • Positioning Method: Dual positioning with visual positioning + RTK differential positioning
  • Landing Accuracy: Horizontal positioning accuracy ±5cm; altitude positioning accuracy ±3cm
  • Return Guidance: Supports multi-band beacon guidance; guidance distance ≥5km
  • Platform Leveling: Electric automatic leveling; leveling accuracy ±0.5°
  • Door Opening/Closing: Electric automatic door; opening/closing time ≤10s; anti-pinch protection included

1.5 System Composition Architecture

The drone charging container adopts a modular design philosophy, composed of eight core systems that operate independently while working collaboratively to ensure fully automatic, highly reliable equipment operation.

1.5.1 Container Load-Bearing System

The container load-bearing system is the foundational carrier of the entire equipment, consisting of the bottom frame, side panels, roof panels, end doors, internal partitions, and equipment mounting racks. It provides structural load-bearing, protective isolation, thermal insulation, and equipment installation and fixation functions. The container is manufactured strictly according to industrial special-purpose container standards, featuring excellent structural strength, anti-corrosion performance, and environmental adaptability. All internal equipment mounting interfaces are pre-fabricated in the factory to ensure on-site installation consistency and reliability.

1.5.2 Intelligent Charging System

The intelligent charging system is the core functional system of the drone charging container, consisting of charging power supply modules, charging management units, charging docking mechanisms, battery detection modules, and scheduling control software. The system automatically identifies drone battery models and status, matches the optimal charging curve, and achieves full-process intelligent control of constant current, constant voltage, and trickle charging. It also features multiple protection functions including overvoltage, overcurrent, overtemperature, short circuit, and reverse connection protection, ensuring safe and efficient charging. The multi-channel intelligent scheduling function rationally allocates charging power based on battery priority and state of charge, improving charging resource utilization efficiency.

1.5.3 Power Distribution and Safety Protection System

The power distribution system is the energy supply hub of the entire equipment, consisting of the main incoming circuit breaker, distribution cabinet, branch circuit breakers, surge protective devices, metering instruments, UPS backup power supply, and grounding bars. The system adopts a hierarchical distribution architecture with comprehensive electrical protection functions including overload, short circuit, earth leakage, undervoltage, and overvoltage protection. It is also configured with Level II lightning protection modules to effectively withstand lightning surge impacts. The UPS backup power supply provides no less than 4 hours of continuous power to the monitoring system, communication equipment, and emergency lighting during utility power outages, ensuring equipment status monitoring and data security.

1.5.4 Temperature Control and Environmental Regulation System

The temperature control and environmental regulation system provides a suitable temperature and humidity environment for internal equipment and drone batteries, consisting of industrial air conditioners, ventilation fans, dehumidifiers, PTC heaters, temperature/humidity sensors, and control units. The system adopts closed-loop automatic control logic, automatically regulating cooling, heating, dehumidification, and ventilation operation status based on real-time internal temperature and humidity data, ensuring the internal environment remains stable within the set range. For special operating conditions such as extreme high temperature, extreme low temperature, and high humidity, the system features dedicated operating modes to ensure stable equipment operation under various harsh environments.

1.5.5 Intelligent Monitoring and Management System

The intelligent monitoring and management system is the “brain” of the entire equipment, consisting of the industrial control host, data acquisition modules, various sensors, video surveillance equipment, communication modules, local display terminals, and remote management platform. The system handles core functions including equipment operating status monitoring, data acquisition and analysis, fault alarming, remote control, charging scheduling, and log recording, supporting fully automatic unattended operation. Through the remote management platform, management personnel can view the operating status, charging statistics, and alarm information of all station equipment from anywhere, achieving centralized and flat operation and maintenance management.

1.5.6 Drone Takeoff/Landing and Positioning System

The takeoff/landing and positioning system is responsible for precise drone landing, position correction, and charging docking, consisting of the landing platform, door mechanism, visual positioning module, RTK positioning module, return beacon, automatic leveling mechanism, and centering docking mechanism. The system ensures precise drone landing at the designated position on the platform through dual positioning technology, and precisely pushes the drone to the charging docking position through the centering mechanism, achieving reliable charging interface connection. The automatic door opening/closing mechanism automatically opens before drone takeoff and closes after landing, ensuring the container’s internal protection performance.

1.5.7 Fire Protection and Security System

The fire protection and security system is an important guarantee for safe equipment operation, consisting of smoke detectors, temperature detectors, combustible gas detectors, aerosol fire suppression devices, audible/visual alarms, access control systems, video surveillance, and emergency lighting. The system features a multi-level fire warning and response mechanism: early smoke warning, mid-stage temperature warning, and late-stage automatic fire suppression. It can rapidly activate the fire suppression device in the early stages of battery thermal runaway, containing fire spread. The access control system supports multiple door opening methods including card swiping, password, and remote authorization, and records all personnel entry/exit logs, ensuring physical equipment security.

1.5.8 Auxiliary Support Systems

Auxiliary support systems include internal lighting, maintenance outlets, ladders and guardrails, warning signage, and external sunshade canopies. These facilities provide convenience and safety guarantees for equipment maintenance and personnel operations. All auxiliary facilities are designed to industrial-grade standards, featuring high reliability and long service life.

1.6 Compilation Basis and Applicable Standards

The design, manufacturing, installation, commissioning, and acceptance of this manual and corresponding products strictly comply with the following national and industry standards and specifications:

Standard Number Standard Name
GB/T 1413-2018 Series 1 Freight Containers – Classification, Dimensions and Ratings
GB/T 17770-2020 Containers – General Purpose Containers for Air/Land/Water (Intermodal) – Technical Requirements and Test Methods
GB 4208-2017 Degrees of Protection Provided by Enclosures (IP Code)
GB 50054-2011 Code for Design of Low Voltage Electrical Installations
GB 50168-2018 Code for Construction and Acceptance of Cable Lines in Electrical Equipment Installation Engineering
GB 50303-2015 Code for Acceptance of Construction Quality of Building Electrical Engineering
GB 50011-2010 Code for Seismic Design of Buildings
GB 50016-2014 (2018 Edition) Code for Fire Protection Design of Buildings
GB 7251.1-2013 Low-Voltage Switchgear and Controlgear Assemblies – Part 1: General Rules
GB/T 19826-2014 General Specification and Safety Requirements for DC Power Supply Equipment in Power Engineering
T/CPS 1008-2024 Inspection Drone Static Wireless Charging Hangar – Part 1: General Technical Requirements
GB/T 31485-2015 Safety Requirements and Test Methods for Traction Battery of Electric Vehicles
GB 50057-2010 Code for Design Protection of Structures Against Lightning
GB/T 2887-2011 General Specification for Computer Field
IEEE Std 1936.5-2025 Technical Standard for Intelligent Drone Hangars

1.7 Terminology and Abbreviation Definitions

  • BMS: Battery Management System. Responsible for battery status monitoring, protection, and balancing control.
  • RTK: Real-time Kinematic. Real-time dynamic differential positioning, enabling centimeter-level high-precision positioning.
  • UPS: Uninterruptible Power Supply. Provides continuous power supply during utility power outages.
  • IP Rating: Ingress Protection. Enclosure protection rating, consisting of two digits representing dust protection level and water protection level.
  • PTC: Positive Temperature Coefficient. Heater with automatic constant temperature characteristics.
  • SOC: State of Charge. Battery remaining charge percentage.
  • SOH: State of Health. Battery health status, indicating the degree of battery performance degradation.
  • EMC: Electromagnetic Compatibility. The ability of equipment to operate normally in an electromagnetic environment without causing electromagnetic interference to other equipment.
  • PLC: Programmable Logic Controller. Used for industrial field logic control.
  • HMI: Human Machine Interface. Used for local equipment operation and status display.

Part 2: Pre-Installation Preparation Work

2.1 Installation Site Survey and Location Selection Requirements

2.1.1 Basic Principles for Location Selection

The location selection of drone charging containers directly affects equipment operational safety, operational efficiency, and service life. The location selection work must be jointly carried out by the user unit, design unit, and installation unit, determined comprehensively based on drone operational requirements, on-site environmental conditions, and infrastructure availability. Location selection must follow the following basic principles:

  • Operational Coverage Principle: The site should be located at the center of the drone operation area or at a key point on flight routes, ensuring the drone operating radius covers the target area, reducing ineffective flight distance, and improving operational efficiency.
  • Safety and Compliance Principle: The site must comply with relevant local urban and rural planning, land use, production safety, and civil aviation control regulations, avoiding restricted or prohibited construction areas such as airport clearance zones, military control zones, flammable and explosive sites, and areas beneath high-voltage transmission lines.
  • Environmental Suitability Principle: Priority should be given to areas with flat terrain, good geological conditions, and smooth drainage, avoiding low-lying flood-prone areas, soft geological areas, and areas prone to geological disasters such as landslides and debris flows. Also avoid strong electromagnetic interference sources and highly corrosive gas environments.
  • Complete Infrastructure Principle: The site should have reliable utility power supply conditions, network communication conditions, and access routes, facilitating equipment transportation, hoisting, and daily operation and maintenance.
  • Expansion Reserve Principle: The site should reserve certain expansion space to meet future equipment capacity expansion and multi-container combined deployment requirements.

2.1.2 On-Site Environmental Survey Content

Before installation construction, the construction unit must arrange professional technical personnel to conduct detailed on-site surveys and produce a formal site survey report. The survey content must include at least:

  • Topographic and Geological Survey: Measure site elevation and terrain slope; verify soil type and foundation bearing capacity; confirm whether foundation reinforcement is required. Foundation bearing capacity requirement is ≥150kPa. If not satisfied, reinforcement measures such as soil replacement and compaction must be taken.
  • Meteorological and Environmental Survey: Understand local extreme maximum/minimum temperatures, maximum wind speed, annual rainfall, thunderstorm days, salt spray corrosion level, and other meteorological parameters; confirm whether equipment selection is compatible with the local environment.
  • Electromagnetic Environment Survey: Detect on-site ambient electromagnetic interference intensity; confirm whether strong electromagnetic interference sources such as high-power radar, radio stations, or high-voltage substations exist nearby; assess impact on drone navigation and charging equipment.
  • Infrastructure Survey: Verify on-site utility power access point location, supply capacity, voltage level; network access method and bandwidth; on-site access road width, turning radius, height and weight limits; confirm whether equipment transportation and hoisting requirements are met.
  • Surrounding Environment Survey: Measure heights of surrounding buildings, trees, high-voltage lines, and other obstacles; confirm no obstruction of drone takeoff and landing flight paths; confirm whether flammable/explosive, toxic/harmful, or other hazard sources exist nearby.

2.1.3 Site Space Requirements

  • Container Footprint: The 20-foot standard container body occupies approximately 14.8m² of land area. The site must reserve a level area of no less than 1.5 times the container footprint to meet equipment installation and maintenance operation space requirements.
  • Hoisting Operation Space: The container hoisting operation area must meet crane operating radius requirements. A truck crane of 25 tons or above is recommended for 20-foot container hoisting. No high-voltage lines, buildings, or other obstacles within the operating radius.
  • Takeoff/Landing Clearance Requirements: No obstacles within 30m vertically above the landing platform; no obstacles higher than 10m within 50m horizontally. This ensures safe drone takeoff and landing.
  • Maintenance Access Requirements: A maintenance access path of no less than 1.2m width must be reserved around the container for routine equipment inspection and maintenance.
  • Safety Distance Requirements: Distance from container to flammable/explosive sites: not less than 30m; distance to high-voltage transmission lines: not less than 1.5 times the tower height; distance to civil buildings: not less than 5m.

2.2 On-Site Foundation Construction Requirements

Foundation engineering is a critical element in ensuring long-term stable operation of the drone charging container. Foundation construction quality directly affects container structural safety, equipment operational accuracy, and service life. Foundation construction must be strictly executed according to design drawings and relevant specifications. Container installation may only commence after foundation completion acceptance.

2.2.1 Foundation Form Selection

Based on on-site geological conditions and equipment specifications, the commonly used foundation forms are divided into the following three types:

Foundation Form Applicable Conditions Characteristics
Monolithic Concrete Slab Foundation General geological conditions, larger loads for 20-foot large containers Uniform overall stress and settlement; most commonly used foundation form
Concrete Strip Foundation Medium/small containers with better geological conditions Strip foundations along container bottom frame main beams; saves materials and construction costs
Prefabricated Steel Structure Foundation Temporary deployment, frequent relocation scenarios Prefabricated steel base; quick installation and disassembly; reusable

This specification uses the most common monolithic concrete slab foundation as the primary example for detailed explanation. Other foundation forms may be implemented with reference to this specification.

2.2.2 Concrete Foundation Technical Requirements

  • Foundation Dimensions: For the 20-foot standard container: foundation external dimensions Length 6500mm × Width 2900mm; foundation thickness ≥300mm; foundation top surface shall be no less than 200mm above surrounding ground level to prevent ground water accumulation.
  • Concrete Grade: Foundation concrete strength grade no less than C30; cushion layer using C15 concrete with 100mm thickness.
  • Reinforcement Configuration: Foundation to be reinforced with Φ12@200 bidirectional double-layer reinforcing mesh; protective layer thickness 40mm; structural reinforcement ribs at foundation edges.
  • Embedded Parts: 8 sets of M20 anchor bolts pre-embedded in the foundation, positioned to correspond one-to-one with container bottom frame mounting holes; embedded part positioning deviation ≤2mm; embedded part top surface flush with foundation top surface.
  • Grounding Pre-Embedment: Pre-embed grounding flat steel (-40×4 hot-dip galvanized flat steel) in the foundation, reliably welded to anchor bolts; grounding terminals shall be brought out; grounding resistance must be ≤4Ω.
  • Foundation Flatness: Foundation top surface flatness deviation ≤3mm/m; overall levelness deviation ≤5mm.
  • Settlement Requirements: After foundation completion, curing shall be carried out for no less than 7 days. Equipment installation may only proceed after settlement is stable. Total settlement ≤20mm; differential settlement ≤5mm.
  • Waterproofing and Drainage: Drainage slope and drainage channels shall be provided around the foundation to ensure timely rainwater drainage and prevent water accumulation.

2.2.3 Foundation Construction Process

1. Site Leveling and Layout: Clear site debris, level the ground, and mark foundation excavation boundary lines and elevation control points according to design drawings.

2. Foundation Pit Excavation: Excavate the foundation pit according to layout dimensions. Excavation depth is determined based on frost depth and foundation bearing capacity, generally no less than 500mm. The pit bottom must be compacted with compaction coefficient ≥0.93.

3. Cushion Layer Pouring: After foundation pit acceptance, pour a 100mm thick C15 concrete cushion layer with a smooth surface.

4. Reinforcement Binding and Embedded Parts Installation: Bind reinforcement mesh on the cushion layer; install and secure anchor bolts and grounding flat steel; recheck embedded part positions and dimensions to ensure deviations are within allowable range. Embedded parts must be firmly secured to prevent displacement during concrete pouring.

5. Formwork Installation: Install foundation side formwork. Formwork must have sufficient strength and rigidity, with tight joints to prevent grout leakage. Apply release agent to the inner surface of formwork.

6. Concrete Pouring: Pour C30 concrete using immersion vibrators for proper compaction, ensuring the concrete is free of honeycomb, surface voids, and cavities. Continuously monitor embedded part positions during pouring and correct any displacement promptly.

7. Curing and Formwork Removal: Cover and water-cure within 12 hours after concrete pouring. Curing duration no less than 7 days. Side formwork may only be removed after concrete strength reaches 70% or above.

8. Foundation Acceptance: After foundation completion, joint acceptance by the construction unit, supervision unit, and construction owner unit. Inspect foundation dimensions, flatness, embedded part positions, and grounding resistance. Issue acceptance records upon passing.

2.3 Open-Box Inspection and Goods Inventory

After the drone charging container arrives at the site, open-box inspection and goods inventory must be conducted before installation to confirm equipment integrity, complete accessories, and complete documentation, avoiding construction delays caused by missing or damaged parts discovered during installation. Open-box inspection must be jointly conducted by factory technical personnel, the construction unit, and the construction owner unit.

2.3.1 Pre-Opening Inspection

  • Inspect whether the container outer packaging is intact, with no obvious collision deformation, damage, rain exposure, or moisture traces.
  • Verify that the container body identification marks for product model, serial number, and shipping information match the procurement contract.
  • Inspect whether container door locks and seals are intact, with no signs of unauthorized opening.
  • Record any abnormal appearance conditions of the container body and take photos for documentation. If significant transportation damage exists, promptly contact the factory and logistics provider for resolution.

2.3.2 Open-Box Inspection Content

  • Main Structure Inspection: Check for deformation, rust, weld cracking, paint peeling in the container internal structure; check door and window opening/closing smoothness; check sealing rubber strips for damage or detachment.
  • Equipment Completeness Inspection: Verify against the packing list, item by item, the distribution cabinet, charging modules, air conditioners, industrial PC, landing platform, cameras, and all other equipment installed internally. Confirm model, quantity, and specifications match the list. Check equipment exteriors for bruises, damage, or moisture.
  • Accessory Inventory: Count anchor bolts, special tools, consumable parts, connecting cables, terminal blocks, and other accompanying accessories. Confirm complete quantities and correct specifications.
  • Documentation Verification: Verify product certificates of conformance, factory inspection reports, user manuals, electrical schematic diagrams, installation drawings, warranty cards, and other technical documentation are complete.

2.3.3 Inspection Records and Issue Resolution

  • The open-box inspection process requires completion of the “Equipment Open-Box Inspection Record,” detailing inspection results with three-party signatures for confirmation.
  • If equipment damage, missing parts, incorrect shipments, or other issues are found, record details and take photos for evidence. Contact the factory promptly for coordinated resolution. Installation shall not proceed until issues are resolved.
  • After passing inspection, equipment should be protected on-site to prevent dust, rain, and debris from entering equipment interiors. Precision electronic equipment requires moisture-proof and dust-proof protection.

2.4 Installation Tools and Instruments Preparation

Before installation construction, all types of construction tools and testing instruments must be prepared according to the installation content. All tools and instruments must be in good working condition, with measuring instruments within calibration validity.

2.4.1 Hoisting and Structural Installation Tools

  • Truck crane (25 tons), forklift (3 tons), wire ropes, shackles, manual chain hoist (2 tons), hydraulic jacks (5 tons)
  • Rotary hammer drill, electric hammer, angle grinder, cut-off machine, hand drill, electric wrench, torque wrench
  • Spirit level, straightedge, steel tape measure, vernier caliper, feeler gauge, plumb bob, level instrument, theodolite
  • Socket wrench set, open-end wrench, box-end wrench, hex key set, screwdrivers, pliers, hammers

2.4.2 Electrical Installation Tools and Instruments

  • Wire strippers, crimping pliers, electrician’s knife, conduit bender, wire puller, cable tie gun
  • Multimeter, clamp ammeter, insulation resistance tester, ground resistance tester, phase sequence indicator
  • Oscilloscope, power quality analyzer, loop resistance tester, withstand voltage tester
  • Soldering iron, hot air gun, heat shrink tubing, insulating tape, cable number markers

2.4.3 Commissioning Specialized Tools and Software

  • Laptop computer, dedicated commissioning data cables, commissioning software installation packages
  • Drone simulation test batteries, signal generator, temperature/humidity calibration instrument
  • Network tester, fiber optic fusion splicer, optical power meter
  • Two-way radios, safety helmets, insulating shoes, voltage detectors, grounding wires

2.4.4 Safety Protection Equipment

  • Safety helmets, safety belts, insulating gloves, insulating shoes, protective goggles, dust masks
  • Fire extinguishers, first aid kits, safety warning tape, warning signs, night warning lights

2.5 Installation Personnel Qualifications and Safety Training

2.5.1 Personnel Qualification Requirements

Drone charging container installation involves multiple specialized trades including structural hoisting, electrical installation, and low-voltage commissioning. Operating personnel must possess the corresponding qualifications before commencing work:

  • Project Manager: Holds a second-grade or above construction engineer qualification for mechanical and electrical engineering or intermediate-level or above professional title; has experience managing similar industrial special-purpose container installation projects.
  • Hoisting Command Personnel: Holds a special equipment operator certificate (crane commanding); has extensive hoisting operation command experience.
  • Crane Operator: Holds a crane operation certificate for the corresponding tonnage; certified for the position.
  • Electrician: Holds a low-voltage/high-voltage electrician special operation certificate; has 3+ years of electrical installation experience.
  • Low-Voltage Commissioning Engineer: Has a background in automation or electronic information; familiar with drone charging system commissioning procedures.
  • Safety Officer: Holds a safety officer Class C certificate; responsible for on-site safety management and supervision.

2.5.2 Pre-Construction Safety Technical Disclosure

Before construction, a safety technical disclosure meeting must be organized for all construction personnel. Disclosure content includes:

  • Project overview, construction scope, schedule requirements, and quality standards
  • Construction process, key process operation points, and technical parameter requirements
  • On-site hazard source identification and safety precautions
  • Special safety requirements for elevated work, hoisting operations, and electrical operations
  • Emergency response procedures and first aid knowledge
  • On-site civilized construction and environmental protection requirements

After the disclosure is completed, all participating personnel must sign for confirmation. Personnel who have not received the disclosure are prohibited from commencing work.

2.6 Construction Organization and Schedule Plan

2.6.1 Construction Organizational Structure

Establish a dedicated installation project department, clarifying responsibilities and division of labor for each position:

Position Responsibilities
Project Manager Overall responsibility for project schedule, quality, safety, and cost management; coordinates relationships between all parties
Technical Director Responsible for construction technical plan preparation, technical disclosure, technical issue resolution, quality acceptance
Safety Officer Responsible for on-site safety management, safety inspections, hazard rectification, safety education
Construction Team Leader Responsible for on-site construction personnel scheduling, process organization, on-site construction execution
Commissioning Engineer Responsible for equipment commissioning, performance testing, acceptance coordination, personnel training

2.6.2 Construction Schedule Plan

The total on-site installation and commissioning period for a standard 20-foot drone charging container is generally 7 days. The specific schedule is as follows:

No. Construction Stage Duration Main Work Content
1 Construction Preparation 1 day Site survey, foundation acceptance, tools and personnel mobilization, open-box inspection
2 Container Hoisting and Positioning 1 day Container hoisting, level calibration, anchor bolt fastening, grounding connection
3 Electrical System Installation 2 days External power access, internal wiring organization, grounding system completion, equipment wiring
4 Subsystem Commissioning 2 days Power distribution system commissioning, charging system commissioning, temperature control system commissioning, monitoring system commissioning
5 System Integration Testing and Acceptance 1 day Full-system integration testing, functional testing, completion acceptance, personnel training

The schedule may be adjusted based on actual site conditions and project scale, reasonably compressing or extending the duration while ensuring construction quality.

2.7 On-Site Safety Protection and Civilized Construction Requirements

2.7.1 Basic On-Site Safety Requirements

  • The construction site shall be enclosed with barriers and safety warning signs displayed. Non-construction personnel are prohibited from entering.
  • All construction personnel must wear safety helmets. Safety belts must be worn for elevated work. Non-slip shoes required.
  • Adequate fire-fighting equipment shall be provided at the construction site, placed in conspicuous and easily accessible locations, with regular effectiveness checks.
  • On-site electrical usage strictly implements “three-level distribution, two-level protection.” All electrical equipment must be reliably grounded. Temporary electrical wiring shall use qualified cables. Arbitrary wiring is strictly prohibited.
  • Hoisting operation areas shall be marked with warning zones with dedicated personnel on duty. Personnel are strictly prohibited from standing or passing beneath suspended loads.
  • Daily pre-work meetings shall be held before each construction day, emphasizing the day’s operational safety risks and precautions.

2.7.2 Civilized Construction Requirements

  • Construction site materials and tools shall be neatly arranged and orderly, with clear classification labels.
  • Construction waste shall be promptly cleared, achieving “clean site after work completion,” maintaining site tidiness.
  • Construction hours shall be reasonably arranged to avoid nighttime high-noise operations, minimizing impact on the surrounding environment.
  • Protect existing site facilities and landscaping. No arbitrary damage. Restore original conditions after construction completion.
  • Construction personnel shall wear uniform attire, maintain civilized conduct, and comply with site management regulations.

Part 3: Container Body Main Installation Engineering

3.1 Container Hoisting and Positioning Specification

Container hoisting is a high-risk procedure in the installation process. It must strictly comply with crane operation safety regulations and be uniformly commanded by professional command personnel to ensure safe and precise hoisting.

3.1.1 Pre-Hoisting Preparation

  • Re-verify foundation acceptance status, confirming foundation strength, flatness, and embedded part positions meet requirements. Foundation surface shall be cleaned and free of debris and water accumulation.
  • Inspect crane condition, confirming wire ropes, shackles, and lifting accessories are intact and undamaged, with rated lifting capacity meeting hoisting requirements.
  • Clear the hoisting operation area, remove obstacles, set up safety warning tape, and arrange dedicated personnel for guarding.
  • Install dedicated lifting slings at the four hoisting points on the container roof. Confirm secure connection between slings and hoisting points. Check the sling included angle is between 60°~90° to avoid excessive stress on slings.
  • Conduct a trial lift before formal hoisting, lifting the container to 100~200mm height and holding for 30 seconds. Check sling stress, container balance, and crane stability. Only proceed with formal hoisting after confirming no abnormalities.

3.1.2 Hoisting and Positioning Operation Steps

1. Command the crane to slowly lift the container, smoothly raising it to a height of 300~500mm above the foundation.

2. Command the crane to slowly move and adjust the container position so that the container bottom mounting holes align with the foundation anchor bolts. Arrange construction personnel to assist with positioning during the process, avoiding container collision with anchor bolts.

3. After alignment, command the crane to slowly lower the container. Reduce speed as the container approaches the foundation, ensuring the container lands smoothly on the foundation with all four anchor bolts threaded through the mounting holes.

4. After container positioning, initially tighten the anchor bolt nuts. After confirming the container position is approximately correct, the crane may slowly release the hook. Before releasing the hook, confirm there is no risk of container tilting or slipping.

3.1.3 Hoisting Safety Precautions

  • Hoisting operations must be uniformly commanded by certified crane command personnel. Command signals must be clear and unambiguous. All operating personnel must obey commands.
  • Hoisting operations are prohibited when wind force exceeds Level 6. Hoisting operations are prohibited during rain, fog, or other adverse visibility conditions.
  • Standing beneath suspended loads is strictly prohibited. During hoisting, construction personnel must not place hands or feet beneath the container.
  • If abnormal sounds, container tilting, crane malfunction, or other anomalies occur during hoisting, immediately stop operations, smoothly lower the container to a safe position, investigate and resolve the issue before continuing operations.
  • Before the container is secured in position, personnel are strictly prohibited from entering the container interior or climbing on the container.

3.2 Cabinet Leveling and Fixing

After the cabinet is in place, precise leveling and secure fixing must be performed. This is the foundation for ensuring the operational accuracy of internal equipment and long-term structural safety.

3.2.1 Leveling Operation

Set up a level (surveying instrument) at an appropriate position beside the foundation. Place leveling rods (staffs) on the bottom frames at the four corners of the cabinet respectively, and measure the elevation values at the four corners.

Based on the measurement results, adjust the cabinet height using jacks. Install adjustment shims between the anchor bolts and the cabinet bottom frame. The shims shall be made of galvanized steel plate, with thickness determined according to actual deviation. The number of shims shall not exceed 3 pieces.

Repeat measurement and adjustment until the longitudinal and transverse levelness deviations of the cabinet are both ≤2mm/m, and the overall maximum levelness deviation ≤3mm.

After leveling is completed, check that all anchor bolts are in close contact with the bottom frame, with no suspended or virtual contact conditions.

3.2.2 Cabinet Fixing Operation

After levelness calibration is qualified, gradually tighten the anchor bolt nuts in diagonal order. Use a torque wrench for tightening. The tightening torque for M20 bolts is 280~320N·m.

During the tightening process, continuously monitor the cabinet levelness. If deviation is detected, make timely adjustments to avoid cabinet deformation or displacement during tightening.

After all bolts are fully tightened, recheck the cabinet levelness to confirm it remains within the qualified range.

The exposed thread length of anchor bolts shall be 2~3 thread pitches. Apply grease to exposed portions for rust prevention and install bolt protective caps.

After cabinet fixing is completed, fill the gap between the foundation top surface and the cabinet bottom frame using micro-expansion fine aggregate concrete grouting. The grouting shall be dense and flat, with proper curing performed.

3.3 Cabinet Sealing and Waterproofing Treatment

After cabinet installation is completed, sealing and waterproofing treatment must be applied to all joints, openings, and interface locations to ensure the cabinet’s overall protection rating meets requirements, preventing rainwater, dust, and insects from entering the cabinet interior.

3.3.1 Door Frame and Door Panel Sealing Inspection

Check whether the sealing rubber strips on all door panels and hatches are intact, tightly fitted, and free from cracks, aging, or detachment.

Repeatedly open and close door panels to check the locking force of latches. Confirm that after locking, the door panel and door frame fit uniformly without excessive local gaps.

For locations with inadequate sealing, adjust the door lock latching travel or replace the sealing rubber strips to ensure sealing performance.

Check that the drainage holes at the bottom of the door frame are unobstructed, ensuring minimal rainwater ingress can be drained smoothly.

3.3.2 Opening and Interface Sealing Treatment

All openings on the exterior of the cabinet — including power cable entry holes, network cable entry holes, and air conditioning pipeline holes — must be sealed with fire-resistant and waterproof sealant after pipeline installation is completed. The sealant shall be fully filled, with a smooth and even surface.

Check the waterproofing sealant at cabinet splicing seams and weld locations for integrity. Re-apply sealant at locations with cracking or detachment.

Apply sealant to all fasteners and rivets on the cabinet roof to prevent rainwater seepage.

Install waterproof elbows at cable entry/exit locations on the cabinet bottom. Cables shall be routed downward to prevent rainwater from flowing into the cabinet along the cables.

3.3.3 Spray (Water) Test Verification

After sealing treatment is completed, a water spray test may be conducted where conditions permit. Use a fire hose nozzle to spray water on cabinet joints, doors/windows, and opening locations. The duration shall be no less than 15 minutes. After spraying is completed, enter the cabinet interior for inspection — no water seepage or leakage indicates a qualified result.

3.4 Grounding System Installation and Testing

The grounding system is an important safeguard for electrical safety. The drone charging container requires a complete working grounding, protective grounding, and lightning protection grounding system. All grounding systems share a common ground electrode, with grounding resistance ≤4Ω.

3.4.1 Grounding System Composition

External Ground Electrodes: The site shall adopt a vertical ground electrode + horizontal grounding grid configuration. Vertical ground electrodes shall use ∠50×5 hot-dip galvanized angle steel, 2.5m in length, driven into the ground at 5m spacing. Horizontal grounding conductors shall use -40×4 hot-dip galvanized flat steel, welding all vertical ground electrodes into an interconnected network.

Cabinet Grounding: The cabinet bottom frame shall be reliably connected to the external grounding grid via grounding flat steel, with no fewer than 2 connection points, forming a ring-type grounding configuration.

Equipment Grounding: The metal enclosures of all internal electrical equipment, distribution cabinets, racks, metal conduits, etc., shall be reliably connected to the internal grounding busbar, which is then connected to the cabinet grounding system.

Lightning Protection Grounding: The grounding terminals of power surge protective devices (SPDs) and signal surge protective devices shall be directly connected to the grounding busbar. Grounding conductors shall use stranded copper wire with cross-sectional area ≥16mm².

3.4.2 Grounding Installation Technical Requirements

All grounding weld joints shall have full weld penetration, free from insufficient welding, slag inclusion, or undercut. After welding, remove welding slag and apply two coats of anti-rust paint for corrosion protection.

The lap length of grounding flat steel shall be no less than 2 times the width of the flat steel, welded on three sides. The lap length of round steel shall be no less than 6 times the diameter of the round steel, welded on both sides.

When grounding conductors are connected using bolted connections, flat washers and spring washers must be installed. Contact surfaces shall be ground clean to ensure good contact.

The color identification for the grounding main conductor shall be yellow-green dual color. All grounding points shall be provided with clear identification markings.

3.4.3 Grounding Resistance Test

After grounding system construction is completed, measure the grounding resistance value using a ground resistance tester. The test method shall adopt the three-point (fall-of-potential) method.

Perform testing on dry weather days. Avoid testing when the soil is wet after rain to prevent result deviations.

The measured grounding resistance must be ≤4Ω. If the requirement is not met, increase the number of ground electrodes or change the grounding location until compliance is achieved.

After the test passes, fill out the “Grounding Resistance Test Record” and retain it for archiving.

3.5 External Interface Connection

3.5.1 Mains Power Supply Connection

Select the appropriate specification of power supply cable based on the total equipment power. For 20-foot standard type equipment, YJV-0.6/1kV 5×16mm² copper core power cable is recommended.

The cable shall be routed from the site distribution box, run through galvanized steel conduit, and laid underground into the cabinet cable entry. The burial depth shall be no less than 0.7m. When crossing roads, protect the cable with steel conduit.

Connect the cable to the upper terminal of the main incoming circuit breaker inside the cabinet. The wiring phase sequence must be correct, connections must be secure, and phase color markings must be clear.

Before power connection, confirm that the site supply voltage is within the allowable fluctuation range and that the capacity meets the equipment’s full-load operation requirements.

3.5.2 Network Communication Connection

Select Ethernet, fiber optic, 4G/5G, or other communication methods based on site conditions. Wired networks are preferred to ensure communication stability.

Connect network cables to the internal switch or router in the cabinet. Properly terminate RJ45 connectors and perform fiber optic splicing. Test network connectivity and bandwidth.

When using wireless communication, install an external high-gain antenna, fixed at an appropriate position on the cabinet roof. Adjust the antenna direction to ensure signal strength meets requirements.

After network connection is completed, test the communication link between the equipment and the remote management platform to confirm normal data transmission.

3.5.3 Other External Interfaces

For external peripherals such as weather stations and environmental monitoring equipment, connect them to the corresponding signal terminals according to interface specifications.

For fire alarm linkage or security alarm linkage requirements, connect the corresponding dry contact signals or communication interfaces.

All external interfaces shall be provided with identification plates indicating interface purpose, specification, and wiring definitions.

3.6 Cabinet Accessory Installation

3.6.1 Ladder and Guardrail Installation

Install an external ladder at the cabinet end. The ladder shall be made of hot-dip galvanized steel, firmly installed, with uniform step spacing. The distance between the ladder and the cabinet wall surface shall be no less than 150mm.

Install safety guardrails around the perimeter of the cabinet roof. The guardrail height shall be no less than 1100mm, equipped with intermediate horizontal rails and toe boards. Guardrails shall be securely connected and capable of withstanding a horizontal force of no less than 1kN.

The top of the ladder shall transition smoothly with the roof platform. Install handrails to ensure personnel safety when climbing up and down.

3.6.2 Warning Sign Installation

Install equipment name identification plates and manufacturer identification plates at conspicuous positions on the cabinet.

Post “Caution: Electric Shock” and “High Voltage Danger” warning signs in electrical areas.

Post “Fire Extinguisher” and “Fire Exit” signs at fire equipment locations.

Set up warning markings and warning signs around the takeoff/landing area to remind personnel to stay away from the drone takeoff/landing zone.

Install nighttime warning lights around the cabinet that automatically illuminate under low-light conditions to indicate obstacle locations.

3.6.3 Sunshade and Rain Protection Facilities Installation (Optional)

For regions with high temperatures and intense sunlight, a sunshade canopy may be installed on the cabinet roof to reduce the impact of direct sunlight on internal temperatures and reduce air conditioning energy consumption.

Install a rain canopy at the cabinet entrance to prevent rainwater from blowing into the cabinet during door-open maintenance operations.

Install a protective cover over the air conditioning outdoor unit to prevent damage from debris or hail, while not affecting ventilation and heat dissipation.

4.1 Power Distribution System Installation

The power distribution system is the energy supply core for all electrical equipment. Installation quality directly affects the electrical safety and operational reliability of the entire equipment. The power distribution system of the drone charging container has completed main installation and wiring at the factory. On-site work mainly involves external power connection, cable organization, grounding completion, and functional verification.

4.1.1 Distribution Cabinet Installation Verification

Check the installation and fixing condition of the distribution cabinet inside the container. Confirm that the cabinet is securely connected to the mounting frame, without looseness or tilting. Cabinet verticality deviation ≤1.5‰.

Check the installation condition of components inside the distribution cabinet. The model and specification of circuit breakers, contactors, relays, surge protective devices, meters, and other components shall meet design requirements, be firmly installed, and have neat wiring.

Check the tightening condition of terminal blocks inside the cabinet. All wire terminals shall be free from looseness, with secure crimping, clear and complete wire number markings consistent with the drawings.

Check the wiring standards inside the cabinet. Power (strong current) and signal (weak current) wires shall be routed separately, bundled neatly, with clear cable bundle identification. Cables across doors shall have sufficient service loop allowance.

Clean dust and debris from inside the distribution cabinet to ensure the cabinet interior is clean and dry, free from metal shavings or residual wire ends.

4.1.2 Main Cable Routing and Termination

Connect the external main power cable to the upper terminal of the main incoming circuit breaker. The cable stripping length shall be appropriate without damaging the conductor. Wire terminals shall be securely crimped using cold-pressed terminals and tin-dipped (tinned).

Connect the three-phase conductors to circuit breaker terminals L1, L2, and L3 respectively. Connect the neutral conductor to the N busbar and the ground conductor to the PE busbar. Phase color markings shall be correct: A phase — yellow, B phase — green, C phase — red, neutral — light blue, ground — yellow-green dual color.

After cable connection, properly dress the cable termination and secure the cable to prevent pulling stress on the wire terminals.

Measure the insulation resistance between phases and between phase-to-ground on the main incoming side. Use a 1000V insulation resistance tester. Insulation resistance ≥10MΩ is considered qualified.

4.1.3 Branch Circuit Inspection and Completion

Check the power supply targets of each branch circuit against the electrical schematic diagram one by one. Confirm correct circuit division and that circuit breaker rated currents match the loads.

Check the cable routing condition of each branch circuit. Cables shall be run through conduits or cable trays, with no exposed, squeezed, or abraded conditions. Sufficient service loop allowance shall be provided at turns.

All cable ends shall have clear identification labels indicating circuit number, start and end locations, facilitating later maintenance and repair.

Check that all socket and lighting circuit wiring is correct, with no neutral-ground mixing, and reliable grounding.

4.1.4 Surge Protective Device Installation Check

Check the installation position of the power surge protective device (SPD). It shall be located downstream of the main incoming circuit breaker, with wiring as short as possible to reduce the effect of lead inductance.

The phase, neutral, and ground connections of the SPD shall be secure. The ground conductor cross-sectional area ≥16mm², length ≤0.5m.

Check the SPD status indication window. Normal status is green. If red is displayed, the device has failed and must be replaced promptly.

Check the installation of signal line SPDs. Network and communication signal lines shall pass through SPDs before connecting to equipment, with reliable grounding.

4.1.5 Metering Instruments and Indicator Devices Check

Check that voltmeters, ammeters, energy meters, and other metering instruments are firmly installed, with clear displays and correct wiring.

Check that power indicator lights, closing indicator lights, fault indicator lights, and other indicating devices operate normally with clear markings.

Verify that the energy meter multiplier is consistent with the current transformer ratio to ensure accurate metering.

4.2 Charging System Installation

The charging system is the core functional system of the drone charging container. Its installation precision directly determines charging docking reliability and charging performance. The contact-type charging system includes the charging module rack, charging docking mechanism, charging control unit, battery detection module, and other components.

4.2.1 Charging Module Rack Installation

The charging module rack has been prefabricated and installed at the factory. On-site, check the rack fixing condition. The rack shall be securely connected to the container floor, with no loose bolts. Rack verticality and levelness shall meet requirements.

Check the installation of charging modules on the rack. Modules shall insert/remove smoothly, be securely fixed, and ventilation and heat dissipation gaps shall meet requirements.

Check the connection of inter-module power cables and communication cables. Connections shall be secure, identification clear, and wiring neat without obstructing module air channels.

Clean dust and debris from the cooling fan air inlets of the modules to ensure smooth airflow.

4.2.2 Charging Interface and Docking Mechanism Installation

Check the installation of charging contacts on the takeoff/landing platform. Contact surfaces shall be clean and flat, free from oxidation, wear, or deformation, with appropriate spring pressure.

Check the operation of the charging docking centering mechanism. Manually test the centering push rods for smooth operation, free from jamming or abnormal noise, with accurate travel and correct position sensing. After reaching position, contact pressure shall meet design requirements.

Adjust the position of charging contacts to ensure precise alignment with the drone charging contacts. Docking deviation ≤0.5mm.

Check the connection between charging cables and contacts. Welding shall be secure, insulation wrapping intact, with no exposed copper.

For wireless charging type products, check the installation flatness of the wireless charging transmitter coil. The coil shall be securely fixed with reliable shielding layer grounding.

4.2.3 Charging Control Unit Wiring

Check the installation and fixing of the charging control unit (BMS interaction module, charging scheduling controller). Wire terminals shall be free from looseness.

Verify that the communication cables and control cables between the charging modules and control unit are correctly wired, consistent with the drawings.

Check that voltage sampling wires and current sampling wires are securely connected, with accurate sampling point positions to ensure sampling precision.

Check that the communication cable between the control unit and the industrial host computer is properly connected, with matching communication protocol.

4.2.4 Battery Detection Module Installation

Check the installation position of battery temperature detection sensors. Sensors shall be in good contact with batteries for accurate temperature measurement.

Check that battery voltage acquisition terminals are reliably connected, with good insulation and no short-circuit risk.

For automatic battery swapping type products, check that battery compartment detection sensors are installed at accurate positions and can correctly identify battery presence status and model.

4.3 Temperature Control System Installation

The temperature control system maintains stable temperature and humidity inside the container, providing a suitable environment for charging equipment and drone batteries. It includes industrial air conditioning, ventilation fans, dehumidifiers, heaters, temperature/humidity sensors, and other equipment.

4.3.1 Industrial Air Conditioning Unit Installation

Check the installation and fixing of the air conditioning indoor unit and outdoor unit. Brackets shall be sturdy and reliable, with anti-vibration pads properly installed. No obvious vibration or abnormal noise during operation.

Check the refrigerant piping connections. Piping shall be free from deformation or damage, insulation layer intact, and no refrigerant leakage traces at joints.

Check the condensate drain piping connection. Drain pipe slope shall be reasonable, drainage smooth, with no water accumulation or leakage. Condensate water shall be routed to the designated external drain point.

Check that the air conditioner power cable and control cable are correctly wired, terminals tightened, and grounding reliable.

Clean the air conditioner filter, evaporator, and condenser coil fins to ensure heat exchange efficiency.

4.3.2 Ventilation Duct and Fan Installation

Check that axial fans are securely installed, fan blades rotate smoothly, with no scraping, abnormal noise, and correct rotation direction.

Check ventilation duct connections for tightness, with no air leakage. Ducts shall be securely fixed without shaking.

Check that rain-protection louvers at air inlets and outlets are intact, and insect screens are complete without damage.

Check that damper actuators operate normally, can adjust opening degree according to control signals, and reach open/closed positions correctly.

4.3.3 Dehumidifier and Heater Installation

Check that the dehumidifier is installed stably, the water tank is properly positioned, drain hose connection is smooth, and the dehumidifier air inlet and return air openings are unobstructed.

Check that PTC heaters are securely fixed, maintaining sufficient safe distance from surrounding combustible materials, with protective screens intact.

Check that the heater temperature protection switch is correctly installed, and the over-temperature protection function is effective.

Dehumidifier and heater wiring shall be secure, grounding reliable, and control circuit wiring correct.

4.3.4 Temperature/Humidity Sensor Deployment

Check the installation positions of temperature/humidity sensors. They shall be deployed at key locations including the charging area, equipment area, and air inlet/outlet positions. Installation height approximately 1.5m, avoiding locations subject to direct air conditioning airflow or direct sunlight.

Sensors shall be securely fixed, correctly wired, and clearly identified.

Verify that sensor address codes are consistent with monitoring system configuration to ensure accurate data mapping.

4.4 Intelligent Monitoring System Installation

The intelligent monitoring system serves as the “neural center” of the equipment, responsible for full-system data acquisition, status monitoring, logic control, and remote management. It includes the industrial host computer, data acquisition modules, various sensors, cameras, network equipment, etc.

4.4.1 Industrial Host Computer and Display Installation

Check that the industrial control host is installed in the standard equipment rack, securely fixed, with good ventilation and heat dissipation, in a clean and dry environment.

Check that the host power cable, network cable, serial cables, and video cables are securely connected with clear identification.

Check that the local touchscreen display is installed on the operation panel, securely fixed, with responsive touch and clear display.

Check that the host grounding is reliable and the power supply passes through a UPS to ensure data is not lost during power failure.

Power on and check the host operating status. System startup shall be normal, with no error messages, and all device drivers properly installed.

4.4.2 Environmental and Electrical Sensor Installation

Smoke Sensors: Install on the container ceiling, with spacing no greater than 8m, distance from walls no greater than 4m. Securely installed, indicator light blinking normally, self-test function normal.

Water Leakage Sensors: Install at low points on the container floor, beneath the air conditioner, and at cable entry locations. Detection electrodes shall be installed horizontally with reliable contact.

Door Magnetic Sensors: Install at corresponding positions on door leaves and door frames, with accurate alignment, sensing distance meeting requirements, and normal door open/close signals.

Voltage/Current Sensors: Install on each key circuit. Wiring correct, range matching, securely fixed.

Wind Speed and Rainfall Sensors: Install at unobstructed locations on the container roof. Installed vertically and securely, wiring correct, signal transmission normal.

4.4.3 Camera and Security Equipment Installation

Check the installation positions of internal cameras, covering the takeoff/landing platform, equipment racks, and entrances/exits. Installation angles shall be appropriate with comprehensive field coverage and no obstructions.

Check that camera power cables and network cables are securely connected, video images are clear, night vision function is normal, and PTZ control is smooth (for PTZ models).

Check that the DVR (digital video recorder) is securely installed, hard drive capacity meets the requirement of more than 30 days of storage, recording function is normal, and time synchronization is accurate.

Check that audible and visual alarm devices are installed at conspicuous positions on the container roof and interior. Wiring correct, with loud sound and obvious flashing light during alarm activation.

4.4.4 Network Equipment and Antenna Installation

Check that switches, routers, and 4G/5G modules are installed in the equipment rack, securely fixed, with indicator lights operating normally.

Check that external communication antennas and GNSS antennas are installed on the container roof at appropriate heights, with no surrounding obstructions, feeder cables securely connected, and waterproofing properly handled.

Check network wiring standards. Network cable termination shall meet standards, labels clear, and link tests pass.

Check network security configuration. Firewall policies and access permission settings shall be reasonable to ensure equipment network security.

4.5 Takeoff/Landing and Positioning System Installation

The takeoff/landing and positioning system ensures precise drone landing and reliable docking, serving as a key link for achieving fully automatic charging. It includes the takeoff/landing platform, hatch door mechanism, positioning module, and leveling mechanism.

4.5.1 Takeoff/Landing Platform Base Fixing

Check that the takeoff/landing platform base is securely connected to the container floor, with all bolts tightened and no looseness.

Check the platform surface flatness. Platform surface flatness deviation ≤2mm, free from deformation or warping.

Check that platform vibration damping pads are properly installed to effectively absorb drone landing impact forces.

4.5.2 Precision Positioning Module Installation

Visual Positioning Module: Install above the center of the takeoff/landing platform. Camera lens clean, oriented directly downward, focus clear. The identification pattern shall be installed at the center of the platform, with clear and complete pattern.

RTK Positioning Module: GNSS antenna installed at an unobstructed location on the container roof, feeder cable of appropriate length, signal gain meeting requirements. Positioning host installed in the internal equipment rack with correct wiring.

Check that the positioning module power supply is stable, communication connections are normal, and positioning data output is normal.

4.5.3 Homing Beacon Installation and Commissioning

Install the homing beacon antenna at the highest point on the container roof, unobstructed, with signal coverage range meeting design requirements.

Check that the beacon host is securely installed, parameters correctly configured, and communication protocol matches the drone side.

Test beacon signal strength. Signal shall be stable and reliable within the designed guidance distance.

4.5.4 Platform Leveling and Hatch Door Mechanism Inspection

Check that the electric leveling mechanism operates normally. Four support legs extend/retract smoothly with good synchronization. Leveling accuracy reaches ±0.5°.

Check that the electric hatch door mechanism operates smoothly, opening/closing steadily without jamming or abnormal noise. Opening/closing time meets design requirements, and position switch signals are accurate.

Check the hatch door anti-pinch function. Simulate obstacle triggering — the door shall stop and reverse promptly.

Check that the hatch door seals well after closure, with uniform gaps, meeting protection rating requirements.

4.6 Fire Protection and Safety System Installation

4.6.1 Aerosol Fire Extinguishing Device Installation

Install the fire extinguishing device on the ceiling of the charging area, with the spraying direction oriented toward the battery charging position. Securely fixed, with installation angle meeting design requirements.

Connect the device activation line to the fire alarm controller. Wiring correct, polarity correct.

Check the device expiration date and status indication. It shall be within the validity period and in normal status.

The area around the fire extinguishing device shall be free from obstructions to ensure effective spraying of extinguishing agent over the protected area.

4.6.2 Smoke Alarm and Audible/Visual Alarm Installation

Install the fire alarm controller at a position near the door for easy operation. Securely fixed, power supply normal, self-test function normal.

All smoke, temperature, and combustible gas detectors shall be connected to the alarm controller, with correct address codes and clear position identification.

Connect audible/visual alarm devices to the alarm output circuit so they activate simultaneously when alarm is triggered.

Test the alarm linkage logic. After detector alarm activation, the audible/visual alarm shall activate, simultaneously linking to cut off non-fire-fighting power and start the smoke exhaust fan.

4.6.3 Emergency Lighting and Evacuation Sign Installation

Install emergency lighting fixtures at corridor and exit locations. They shall automatically illuminate upon power failure, with illumination duration ≥90 minutes.

Install safety exit signs above exits. Install evacuation direction indicator signs on corridor walls at a height of 30cm from the floor, with correct indication direction.

Emergency lighting power shall be supplied by the UPS to ensure normal operation during mains power interruption.

4.6.4 Access Control System Installation

Install the access control card reader at an appropriate height outside the door. Card swiping shall be responsive and recognition normal.

Install the electric lock securely, with smooth latch bolt extension/retraction and automatic locking after door closure.

Install the access controller inside the container, with normal permission management and door opening log recording functions.

Install a door exit button and emergency escape knob on the inside of the door for one-touch door release in emergency situations.

4.7 Lighting and Auxiliary System Installation

4.7.1 Internal Lighting Fixture Installation

Check that LED lighting fixtures are securely installed and evenly distributed, with illumination brightness meeting O&M operation requirements.

Install light switches at positions near the door for convenient operation. Switch-to-fixture correspondence labels shall be clear.

Lighting fixtures shall have reliable grounding, with intact lamp covers and no damage.

4.7.2 UPS Backup Power Supply Installation

Install the UPS host in the equipment rack, securely fixed with good ventilation.

Battery banks shall be installed stably, connections secure, wiring correct, polarity correct, and insulation protection in place.

Check that UPS input/output wiring is correct, with normal mains, battery, and inverter switching functions.

Verify that UPS capacity meets the design backup time requirement, with full-load backup time ≥4 hours.

4.7.3 Socket and Low-Voltage Panel Installation

Maintenance power sockets shall be distributed throughout the container interior. Securely installed, wiring correct, grounding reliable, equipped with splash-proof covers.

Network panels and telephone panels installed neatly, module termination per standard, tested for connectivity.

All sockets and panels shall have clear labels indicating circuit and purpose.

System commissioning is a key stage for verifying installation quality and validating equipment performance. It must be carried out in an orderly manner following the principle of “single machine first, then system; no-load first, then loaded; local first, then overall.” All commissioning data shall be truthfully recorded to form a complete commissioning report. Commissioning work must be performed by qualified professional technical personnel, strictly observing electrical safety operating procedures.

5.1 Pre-Commissioning Preparation and Safety Inspection

5.1.1 Pre-Commissioning Preparation Work

Confirm that all installation work is fully completed, installation quality acceptance has passed, the site is cleaned up, and there is no debris affecting commissioning.

Prepare the instruments, tools, and recording forms required for commissioning. All measuring instruments shall be verified/calibrated and within validity.

Organize commissioning personnel to familiarize themselves with the drawings, manuals, and commissioning plan. Clarify commissioning steps, technical indicators, and safety precautions.

Confirm that the site power supply is stable, with voltage and frequency within the allowable range for the equipment.

Disconnect all equipment power switches and confirm that all circuits are in the de-energized state.

5.1.2 Safety Inspection Items

Check that all electrical equipment is reliably grounded and that grounding resistance tests have passed.

Check that all exposed live parts have insulation protection, with no exposed electric shock hazards.

Check that the commissioning area is set up with safety warnings, and non-commissioning personnel are prohibited from entering.

Equip insulating gloves, voltage testers, fire extinguishers, and other safety protection items.

Implement the two-person commissioning system — one operator, one supervisor. Working on live equipment by a single person is strictly prohibited.

5.2 Power Distribution System Commissioning

5.2.1 Insulation Resistance Test

Disconnect all load switches and unplug all electronic device plugs to ensure no load on the test circuit.

Use a 1000V insulation resistance tester to measure the insulation resistance between the three-phase conductors, between phases and neutral, between phases and ground, and between neutral and ground.

For low-voltage distribution systems, insulation resistance shall be ≥0.5MΩ. Actual test values should typically be ≥10MΩ. If below standard, investigate the cause and correct before energizing.

Test the insulation resistance of the main circuit and each branch circuit separately. All must pass, with test data recorded.

5.2.2 Grounding Resistance Test

Use a ground resistance tester to re-measure the total system grounding resistance, confirming ≤4Ω.

Spot-check the continuity between major electrical equipment metal enclosures and the grounding busbar. Resistance ≤0.1Ω, ensuring good grounding continuity.

Check that surge protective device grounding connections are reliable, with grounding lead length meeting requirements.

5.2.3 Phase Sequence Check Before Energization

Measure the three-phase voltage at the upper terminal of the main incoming circuit breaker. Confirm three-phase voltage balance, with voltage values within ±10% of rated voltage.

Use a phase sequence meter to check the three-phase phase sequence. Confirm positive sequence. If phase sequence is incorrect, swap phase conductors to correct.

Measure the neutral-to-ground voltage, which shall be ≤5V. If excessively high, check whether the neutral connection is reliable.

5.2.4 Step-by-Step Energization Commissioning

After confirming all downstream circuit breakers are open, close the main incoming circuit breaker. Check that the power indicator light on the distribution cabinet illuminates, and measure the outgoing side voltage for normal values.

Following the sequence from main to secondary and from power circuits to low-voltage circuits, close each branch circuit breaker one by one. After closing each circuit, check whether the corresponding equipment power supply is normal, with no abnormal sounds, odors, or excessive heating.

If any abnormality occurs during energization — such as tripping, arcing, or abnormal noise — immediately de-energize and troubleshoot. Continue only after the fault is resolved.

After all circuits are energized, run for 30 minutes and check that all circuit breakers and cables have no abnormal heating, with temperature not exceeding 60°C.

5.2.5 Protection Function Verification

Overload Protection Test: Verify that the circuit breaker overload protection trip current and trip time match rated values through simulated loads or parameter settings.

Short-Circuit Protection Test: Actual short-circuit testing is strictly prohibited. Verify protection parameters by cross-checking the circuit breaker trip curve and setting values.

Residual Current (RCD) Protection Test: Press the test button on the residual current protective device to verify it trips within the specified time. Trip current ≤30mA, trip time ≤0.1s.

Undervoltage/Overvoltage Protection Test: Use a voltage regulating device to simulate abnormal voltage conditions. Verify that undervoltage and overvoltage protection devices operate accurately, with protection values meeting design requirements.

5.3 Charging System Commissioning

Charging system commissioning shall proceed progressively from loaded testing, functional testing, and protection testing based on a qualified no-load test, ensuring all charging performance and safety protection indicators are met.

5.3.1 Charging Module No-Load Test

Disconnect the charging module output, energize only the module input side, and check whether the module starts up normally, indicator lights display normally, and there are no fault alarms.

Use a multimeter to measure the module no-load output voltage. Confirm the output voltage is within the rated range with no output drift.

Test the module fan activation logic. The fan shall automatically start when temperature rises, with speed adjusting according to temperature, and no abnormal noise during operation.

Test the module communication function. The monitoring system shall be able to read module voltage, current, temperature, status, and other parameters normally.

5.3.2 Charging Protocol Compatibility Test

Connect a compatible drone battery to the charging interface. Confirm that the system can automatically identify battery model, voltage, capacity, SOC, and other information.

Verify that BMS communication handshake is normal, with no communication errors, and real-time reading of battery cell voltages, temperatures, and other data.

Test compatibility with different brands and models of batteries. All shall be correctly identified and charging initiated normally.

5.3.3 Constant Current/Constant Voltage Charging Test

Select a standard test battery, start the charging process, and observe the charging curve.

Constant Current Stage: Charging current shall be stable at the set value, with current fluctuation ≤±2%, and voltage rising steadily.

Constant Voltage Stage: After voltage rises to the set value, it shall remain stable, with current gradually decreasing, and voltage fluctuation ≤±0.5%.

Trickle Stage: After current drops to the set threshold, transition to trickle float charging to replenish remaining battery capacity.

Record the complete charging time. Confirm charging duration meets design targets, with charging efficiency ≥93%.

5.3.4 Full-Charge Auto-Stop Function Verification

When the battery reaches 100% SOC, observe whether the system automatically stops charging output.

After full-charge stop, measure the output terminal voltage to confirm no output voltage and no trickle overcharging phenomenon.

After the battery rests for a period, when voltage drops to the set value, verify whether the system automatically initiates replenishment charging.

5.3.5 Multi-Module Sequential Charging Logic Test

Simultaneously connect multiple batteries, set different priorities, and verify that the system charges them sequentially according to priority.

Test the charging power intelligent allocation function. High-priority batteries are allocated power first, while low-priority batteries are automatically current-limited.

Test the sequential charging logic where a fully charged battery automatically switches to the next battery. The switching process shall be smooth without impact.

Verify intelligent scheduling functions such as scheduled charging and off-peak electricity pricing charging operate normally.

5.3.6 Charging Abnormal Protection Test

Overvoltage Protection: Simulate output overvoltage. Verify that the system immediately stops charging and issues an output overvoltage alarm.

Overcurrent Protection: Simulate output short circuit or overcurrent. Verify that the system cuts off output within milliseconds, protecting the battery and module safety.

Over-temperature Protection: Simulate battery temperature too high and module temperature too high. Verify that the system automatically reduces charging power or stops charging, and automatically resumes after temperature recovers.

Reverse Polarity Protection: Simulate reversed battery positive/negative connection. Verify that the system has no output, does not damage the battery or equipment, and issues a reverse polarity alarm.

Communication Interruption Protection: Disconnect the BMS communication line. Verify that the system immediately stops charging to avoid uncontrolled charging risk.

5.4 Temperature Control System Commissioning

5.4.1 Air Conditioning Cooling and Heating Test

Start the air conditioner in cooling mode, set the temperature below the current ambient temperature. Check that the compressor starts normally and the supply air temperature gradually decreases.

After running for 30 minutes, measure the overall internal temperature. Temperature uniformity ≤±2°C, with cooling rate meeting design requirements.

Switch to heating mode, set the temperature above ambient temperature. Check that electric heating or heat pump heating starts normally, and supply air temperature rises normally.

Test air conditioner fan speed adjustment, mode switching, and timer functions. All shall function normally, with operating noise ≤55dB(A).

5.4.2 Temperature/Humidity Automatic Control Logic Commissioning

Set the target temperature to 25°C and target humidity to 50%RH in the monitoring system.

Simulate temperature rise. Verify that the air conditioner automatically starts cooling, and automatically stops or reduces frequency when temperature drops to the set value.

Simulate temperature drop. Verify that the heater automatically starts heating, and automatically stops when temperature reaches the set value.

Simulate excessive humidity. Verify that the dehumidifier automatically starts dehumidifying and automatically stops when humidity reaches the set value.

Verify the temperature/humidity linkage control logic. Under high temperature and high humidity conditions, cooling and dehumidification shall take priority. Under low temperature and high humidity, heating and dehumidification shall be applied. Control logic must be correct.

Run continuously for 2 hours and record the temperature/humidity variation curves. Confirm control accuracy within ±2°C and ±5%RH.

5.4.3 Ventilation and Air Exchange Function Test

Test the manual ventilation mode. Start all ventilation fans and check that supply and exhaust airflow is smooth, with internal air exchange rate meeting requirements.

Test the automatic ventilation logic. When the indoor-outdoor temperature difference is appropriate and air quality is poor, fresh air ventilation shall automatically activate.

Test the fire alarm linkage exhaust function. Smoke alarm triggers automatic start of the exhaust fan.

Check that fans run smoothly with no abnormal vibration or noise, and correct rotation direction.

5.4.4 Extreme Condition Simulation Test

High Temperature Condition: Simulate an external temperature of 55°C through external heating or summer high-temperature environment. Verify that the temperature control system maintains internal temperature stable within 30°C, with equipment operating normally.

Low Temperature Condition: Simulate an external temperature of -20°C. Verify that the heating system maintains internal temperature above 10°C, with charging functions operating normally.

High Humidity Condition: Simulate a high-humidity environment. Verify that the dehumidification system operates effectively, maintaining internal humidity below 60%RH with no condensation phenomenon.

5.5 Intelligent Monitoring System Commissioning

5.5.1 System Power-On and Self-Test

Energize the industrial host computer, display, switches, and other equipment. Check that the system startup process is normal with no hardware errors.

After system startup, run the monitoring software and execute system self-test. Check the connection status of all hardware modules, communication channels, and sensors.

Record self-test results. Troubleshoot offline or abnormal equipment one by one until all equipment is online and in normal status.

5.5.2 Data Acquisition Function Verification

Verify the acquisition accuracy of all analog and digital/dry-contact data one by one:

Data Type Acceptance Criteria
Voltage, current data vs. multimeter actual measurements Error ≤±1%
Temperature/humidity data vs. calibrated instrument Temperature error ≤±0.5°C, humidity error ≤±3%RH
Digital/dry-contact status vs. actual status Consistent, no false or missed reports

Check the data refresh rate. Real-time data refresh cycle ≤5 seconds.

Verify data storage function. Historical data shall be queryable and exportable, with complete storage and no data loss.

5.5.3 Remote Communication and Backend Integration Test

Test the network connection between the equipment and the remote management platform. Confirm stable communication without frequent disconnections.

Verify the data upload function. All operational data, alarm information, and charging records shall upload to the platform in real time.

Test the remote control function. The platform shall be able to remotely view equipment status, modify operating parameters, remotely restart equipment, and remotely open/close the hatch door. Control commands shall respond promptly.

Test the mobile APP function. The mobile end shall be able to view data, receive alarms, and perform remote operations normally.

5.5.4 Alarm Function Test

Simulate various alarm conditions to verify accurate and timely alarm triggering:

Alarm Category Specific Conditions
Voltage abnormal alarms Overvoltage, undervoltage, phase loss
Temperature abnormal alarms Internal high temperature, low temperature, battery over-temperature, module over-temperature
Equipment fault alarms Charging module fault, air conditioner fault, communication interruption
Security alarms Smoke alarm, water leakage alarm, door magnetic anomaly, unauthorized intrusion

Verify alarm linkage: audible/visual alarm activation, SMS push, platform pop-up, and WeChat notification triggered simultaneously.

Test the alarm classification mechanism. Important alarms and general alarms shall be handled differently, with reasonable alarm level settings.

Verify alarm silencing, acknowledgment, and recording functions. All alarm events shall be fully recorded and traceable for query.

5.5.5 Report and Log Function Test

Test the automatic generation of daily, weekly, and monthly reports. Reports shall include key data such as charging volume, operating hours, alarm statistics, and energy consumption statistics.

Check that operation logs, alarm logs, and charging logs are fully recorded, including time, object, event, operator, and other information.

Test log query, filtering, and export functions, supporting Excel and PDF format export.

5.6 Takeoff/Landing and Positioning System Commissioning

5.6.1 Positioning Accuracy Calibration

Visual Positioning Calibration: Place a calibration board on the takeoff/landing platform. Adjust camera parameters and recognition algorithms to ensure visual positioning planar accuracy ≤±2cm.

RTK Positioning Calibration: Connect to base station differential signals and perform fixed-solution calibration. Positioning accuracy shall reach centimeter level, with stable and reliable positioning.

Test positioning performance under different lighting conditions. Strong light, low light, and nighttime conditions shall all provide stable positioning.

Test landing accuracy under different wind speeds. At 5m/s wind speed, landing accuracy shall still meet requirements.

5.6.2 Drone Homing Guidance Test

Control the drone to fly at different distances from the station. Test the homing beacon guidance function. The drone shall be able to accurately identify the beacon signal and automatically plan the return route.

Test the switching logic between long-distance guidance and short-distance precision landing. The transition shall be smooth.

Test the lost-communication return function. When communication is interrupted, the drone shall automatically return and land precisely.

5.6.3 Takeoff/Landing Platform Automatic Leveling Test

Manually trigger the leveling function. Observe the leveling mechanism operation. The four support legs shall extend/retract automatically, and the platform shall self-level.

After leveling is completed, use a level to measure platform levelness. Confirm ≤±0.5°.

Simulate slight foundation settlement. Verify that the automatic leveling function can self-correct and maintain platform levelness.

5.6.4 Docking Accuracy Verification

Control the drone for simulated landing. Observe the centering mechanism action, precisely pushing the drone to the charging position.

Check the charging contact docking condition. Contact pressure shall be uniform, with contact resistance ≤5mΩ.

Repeat the landing and docking procedure 10 times. Docking success rate shall be 100%, with no docking failures or contact displacement.

5.7 Fire Protection and Security System Commissioning

5.7.1 Smoke Alarm Linkage Test

Use smoke test agent to simulate smoke, triggering the smoke detector. Verify that the alarm controller issues a fire alarm signal within 10 seconds.

Verify the linkage logic: audible/visual alarm activation, internal lighting switches to emergency mode, non-fire-fighting power is cut off, exhaust system starts, fire extinguishing device enters standby status, and alarm information uploads to the platform.

Test the logic for multiple detectors alarming simultaneously. The system shall accurately identify the alarm location.

5.7.2 Fire Extinguishing Device Activation Test

Use a simulated signal to trigger the aerosol fire extinguishing device. Verify that the device activates normally, sprays smoothly, and has no blockage.

Test the extinguishing delay function. After alarm, there shall be a 30-second delay before activation to allow personnel evacuation time. The delay time shall be adjustable.

Test the manual emergency activation function. Press the emergency activation button and the fire extinguishing device shall activate immediately.

5.7.3 Access Control System Function Test

Test multiple door opening methods including card swipe, password, and remote opening. All shall unlock normally.

Test rejection of invalid cards and incorrect passwords. The continuous-error lockout function shall operate normally.

Check that door opening logs are complete, including opening time, card number, and opening method.

Test the fire alarm linkage unlock function. When a fire alarm signal is triggered, the access control shall automatically unlock to facilitate personnel evacuation.

5.7.4 Video Surveillance System Test

Check that all camera images are clear, with no freezing or frame loss, and good night vision performance.

Test PTZ rotation, zoom, and preset position functions. Control shall be precise with timely response.

Test video recording storage. Playback shall be smooth, time accurate, and searchable by time or event.

Test remote video viewing. Both the platform and mobile end shall be able to view surveillance footage in real time.

5.8 Full System Integration Commissioning and Overall Operation Testing

After all individual subsystem commissioning tests pass, full system integrated commissioning shall be carried out to verify inter-system collaborative operation capability and overall performance indicators.

5.8.1 Multi-System Linkage Logic Verification

Full-Automatic Charging Full-Process Linkage: Simulate the complete process of drone return → hangar door automatic opening → drone precision landing → hangar door closing → centering and docking → automatic charging → full charge disconnection → standby waiting, to verify that the action sequence timing of each system is accurate, transitions are smooth, and the full process requires no manual intervention.

Abnormal Condition Linkage: Simulate battery over-temperature during charging, verify the linkage logic that the charging system pauses charging, the temperature control system strengthens cooling, and the monitoring system issues an alarm, all functioning correctly.

Fire Alarm Linkage: Simulate fire alarm trigger, verify the full system emergency response logic that charging cutoff, power cutoff, fire suppression activation, and alarm upload execute synchronously.

Power Outage Linkage: Simulate utility power interruption, verify the UPS automatically switches power supply, critical equipment continues uninterrupted operation, and the monitoring system issues a power outage alarm.

5.8.2 Simulated Drone Full-Process Charging Test

Use a real drone to perform a complete operational cycle test: drone takeoff to execute simulated mission → low battery return → automatic landing and charging → automatic standby after full charge.

Record the time consumed at each stage of the full process, evaluate operational turnaround efficiency, and confirm compliance with design indicators.

Execute 10 complete consecutive cycles to test system operational stability, with no faults, no errors, and 100% docking success rate.

Check that charging data records are complete, battery level statistics are accurate, and battery health status monitoring is normal.

5.8.3 Power Outage and Power Restoration Self-Recovery Test

With equipment in normal operation, disconnect the utility power input to simulate a power outage.

Verify seamless UPS switching, continuous operation of critical monitoring and communication equipment, and no data loss.

After utility power restoration, verify that the system automatically restores power supply, all equipment automatically restarts and returns to normal operation status without requiring manual reset.

Record power outage and power restoration events; the system automatically generates alarms and logs.

5.8.4 Extreme Environment Simulated Operation Test

Simulate extreme environments such as high temperature, low temperature, strong wind, and rainfall to verify overall system operational stability.

Test continuous charging for 8 hours in high temperature environment; equipment temperature remains normal with no over-temperature protection activation or fault shutdown.

Test cold start function in low temperature environment; equipment can warm up normally after power-on and start charging.

Test enclosure sealing performance under rain spray conditions; no internal water seepage or moisture ingress, electrical equipment operates normally.

5.8.5 72-Hour Continuous Operation Stability Test

Set all systems to fully automatic operation mode and conduct a 72-hour uninterrupted continuous operation test.

Arrange personnel for shift duty, periodically record operational data, and observe equipment operating status.

If there are no faults, alarms, or shutdowns within 72 hours and all performance indicators remain stable, the stability test is deemed qualified.

Upon test completion, issue a complete 72-hour operation test report recording all operational data and test conclusions.

Part 6 Engineering Acceptance and Delivery

6.1 Acceptance Basis and Acceptance Organization

6.1.1 Acceptance Basis

  • Purchase contract, technical agreement, and design drawings
  • This installation and commissioning manual and related technical documents
  • Current applicable national and industry standards and specifications
  • Equipment factory inspection reports and certificates of conformity
  • Installation and commissioning records, test reports

6.1.2 Acceptance Organization

Engineering acceptance is organized by the construction unit, with the participation of the construction contractor, equipment manufacturer, and supervision unit, forming an acceptance team. Prior to acceptance, the contractor and manufacturer shall submit complete completion documents. The acceptance team shall inspect and test item by item according to the acceptance procedure, and sign the acceptance report after passing.

6.2 Appearance and Structural Acceptance

6.2.1 Enclosure Appearance Inspection

  • Overall enclosure appearance is clean and tidy, paint finish intact, no obvious impacts, deformation, or corrosion, no coating peeling, runs, or color difference.
  • Doors and windows open and close smoothly, locks are intact, sealing strips are complete, and seal tightly when closed.
  • Labels and nameplates are complete, clear, and correctly positioned; warning signs are complete.
  • Enclosure surrounding area is clean, drainage is unobstructed, no standing water or debris.

6.2.2 Structural Installation Quality Inspection

  • Enclosure positioning is accurate, with deviation from design position ≤ 50 mm.
  • Enclosure levelness meets requirements, anchor bolts are properly tightened, and anti-corrosion treatment is intact.
  • Foundation surface is smooth, free from cracks, honeycomb, or surface voids; grouting treatment is intact.
  • Ladders, guardrails, sunshade awnings, and other accessories are firmly installed and comply with safety regulations.

6.2.3 Internal Wiring and Installation Workmanship Inspection

  • Internal wiring is neat and orderly, power and signal cables are separated, routed through cable trays or conduits, securely tied, and clearly labeled.
  • Equipment is firmly installed, neatly arranged, with reasonable spacing for ease of maintenance and inspection.
  • Wiring terminals are securely crimped, no loose connections or exposed conductors, wire number sleeves are complete and clear.
  • Grounding connections are reliable, with standard yellow-green dual-color identification.

6.3 Electrical Performance Acceptance

6.3.1 Power Supply Quality Testing

  • Measure input voltage and frequency; must be within rated allowable range, three-phase voltage unbalance ≤ 2%.
  • Measure power factor; at full load condition ≥ 0.92.
  • Measure harmonic content; current total harmonic distortion rate ≤ 5%.
  • Test voltage fluctuation and flicker; must comply with power quality standard requirements.

6.3.2 Safety Performance Testing

  • Grounding resistance test ≤ 4 Ω.
  • Insulation resistance test complies with specification requirements.
  • Leakage protection trip test passes.
  • Withstand voltage test: AC 1 kV/1 min without breakdown or flashover (performed at factory; on-site spot check permitted).

6.3.3 Energy Consumption Indicator Testing

  • Test standby-mode overall system power consumption; must comply with design indicators.
  • Test energy consumption per unit of charging capacity under standard charging conditions; energy efficiency indicators must be met.
  • Test temperature control system energy consumption ratio; energy-saving performance meets requirements.

6.4 Functional Performance Acceptance

6.4.1 Charging Function Acceptance

  • Live testing of the full automatic charging process; charging docking success rate 100%.
  • Charging speed and charging efficiency meet technical agreement requirements.
  • All charging protection functions verified qualified, with accurate and reliable operation.
  • Multi-battery rotation charging and intelligent scheduling functions operate normally.

6.4.2 Environmental Control Acceptance

  • Temperature and humidity control accuracy meets design indicators; temperature and humidity inside the enclosure are uniform and stable.
  • Extreme environment adaptability test passes.
  • Air conditioning, ventilation, dehumidification, and heating equipment operate normally without faults.

6.4.3 Intelligent Monitoring Acceptance

  • All data acquisition is accurate, and monitoring functions are complete.
  • Remote communication is stable, and remote control functions operate normally.
  • Alarm functions are comprehensive, notification methods are complete, and response is timely.
  • Data storage, reports, and log functions operate normally.

6.4.4 Takeoff/Landing Positioning Acceptance

  • Drone landing precision meets design standards.
  • Automatic leveling, automatic hangar door, and centering docking functions operate normally.
  • Homing guidance distance and guidance accuracy meet standards.

6.4.5 Fire Protection and Security Acceptance

  • Fire detection is sensitive, alarm is timely, and linkage logic is correct.
  • Fire suppression devices are effective and comply with fire protection regulations.
  • Access control, video surveillance, and intrusion alarm functions operate normally.

6.5 Document Delivery and Acceptance Files

6.5.1 Delivered Documentation List

Upon acceptance, the manufacturer and contractor shall deliver complete technical documentation to the construction unit, including:

  • Product certificate of conformity, factory inspection report
  • Installation and commissioning manual, operation and maintenance manual
  • Electrical schematic diagrams, wiring diagrams, equipment layout drawings
  • Equipment list, spare parts list, wear parts list
  • Foundation construction drawings, concealed engineering acceptance records
  • Installation records, commissioning records, test reports
  • Grounding resistance test records, insulation test records
  • 72-hour continuous operation report
  • Completion acceptance report
  • Warranty card, after-sales service manual

6.5.2 Acceptance Report Signing

After all acceptance items pass, all participating parties shall jointly sign the “Engineering Completion Acceptance Report,” specifying the acceptance conclusion, acceptance date, outstanding issues, and rectification deadlines. Upon signing of the acceptance report, the equipment is officially delivered to the construction unit for operation, and the warranty period commences.

6.6 Personnel Training and Technical Briefing

During the acceptance and delivery phase, manufacturer technical personnel shall conduct systematic technical training for user operations and maintenance management personnel, ensuring that user personnel are capable of independent operation, routine maintenance, and common fault handling.

6.6.1 Training Content

  • Theoretical training: Product structure principles, system composition, workflow, technical parameters, safety regulations
  • Operation training: Power on/off procedures, manual/automatic mode switching, charging operations, parameter settings, alarm handling
  • Maintenance training: Daily inspection items, periodic maintenance items, wear parts replacement methods, cleaning and maintenance requirements
  • Fault handling training: Common fault identification, troubleshooting methods, emergency handling procedures
  • Platform operation training: Remote management platform usage, data query, report export, equipment management

6.6.2 Training Assessment

After training completion, trainees shall be assessed through both theoretical written examination and practical operation assessment. Only those who pass the assessment may operate independently. The manufacturer shall retain training records and assessment results.

Part 7 Daily Operation and Maintenance

Scientific and standardized routine maintenance is key to ensuring long-term stable operation of the drone charging container, extending equipment service life, and reducing fault occurrence rates. Users shall establish a comprehensive operations and maintenance management system, define maintenance responsibilities and cycles, and strictly carry out maintenance work in accordance with specifications.

7.1 Daily Inspection Standards and Inspection Forms

7.1.1 Inspection Frequency and Personnel Requirements

  • Unattended sites: one remote inspection per day, one on-site inspection per week.
  • Attended sites: two on-site inspections per day, once in the morning and once in the evening.
  • Additional special inspections required before and after severe weather (heavy rain, strong wind, high temperature, cold waves).
  • Inspection personnel must be professionally trained and familiar with equipment structure and safety operation procedures.

7.1.2 Daily Remote Inspection Content

  • Log in to the remote management platform, check overall equipment operating status, confirm no offline devices and no major alarms.
  • Check temperature and humidity data inside the enclosure; confirm within normal range.
  • Check charging records and battery status; confirm charging function is normal.
  • Check power supply voltage and current data; confirm power supply is normal.
  • Check alarm records; handle any occurred alarms promptly and record them.
  • Check surveillance footage of key locations; confirm no abnormal conditions on site.

7.1.3 Daily On-Site Inspection Content

  • Enclosure exterior inspection: Check for damage or corrosion on enclosure exterior, debris or standing water in surrounding area, and unobstructed drainage.
  • Power supply inspection: Check distribution cabinet indicator lights are normal, no circuit breaker trips, voltage and current displays are normal.
  • Environmental inspection: Verify internal temperature is normal, no unusual odors or noises, lighting is normal.
  • Equipment status inspection: Check charging module, air conditioning, industrial PC, and other equipment operation indicator lights are normal, no fault alarms.
  • Security inspection: Check access control is intact, surveillance footage is normal, fire protection equipment is in place and intact.
  • Fill out the “Daily Inspection Record Form,” recording inspection data and abnormal conditions.

7.2 Weekly Maintenance Items

Comprehensive on-site maintenance shall be performed weekly, including:

  • Cleaning and dust removal: Clean dust inside the enclosure, wipe equipment surfaces, clean air conditioning filters and ventilation filter screens.
  • Fastener inspection: Check for loose mounting bolts and wiring terminals on main equipment, with emphasis on high-current circuit terminals.
  • Cable inspection: Check cables for wear, aging, heat discoloration, and neat routing.
  • Grounding inspection: Check grounding wire connections are secure, no corrosion or detachment.
  • Sealing inspection: Check door/window sealing strips for aging or deformation, and drainage holes for unobstructed flow.
  • Functional spot check: Spot-check auxiliary functions such as hangar door switching, lighting, and power outlets.
  • Clear weeds and debris around the enclosure to maintain a clean surrounding environment.

7.3 Monthly Maintenance Items

Deep maintenance shall be performed monthly, including:

  • Electrical performance testing: Measure key circuit voltages and currents, record data, and compare with historical data for analysis.
  • Temperature control system maintenance: Check air conditioning operating pressure and refrigerant charge, clean condenser fin dust, and check condensate drainage.
  • Charging system inspection: Check charging contact wear and oxidation, clean contact surfaces, and check contact pressure.
  • Transmission mechanism lubrication: Apply lubricating oil to moving parts of the hangar door mechanism, centering mechanism, and leveling mechanism; check smooth operation.
  • Security system testing: Test smoke alarm, water immersion alarm, door magnetic sensor, and audible/visual alarm functions.
  • Data backup: Back up monitoring system historical data and configuration parameters to ensure data security.
  • UPS inspection: Check UPS battery voltage and perform a discharge test to confirm backup time meets standards.
  • Software inspection: Check system operation logs, clean system junk files, and confirm smooth system operation with no viruses.

7.4 Quarterly Maintenance Items

Comprehensive system maintenance shall be performed quarterly, including:

  • Insulation resistance testing: Measure insulation resistance of main circuits and each branch circuit; confirm good insulation performance.
  • Grounding resistance retest: Retest system grounding resistance; ensure ≤ 4 Ω.
  • Lightning protection system inspection: Check surge protector status and test lightning protection grounding connection reliability.
  • Fan maintenance: Disassemble and clean all ventilation fans, check bearing lubrication, and tighten fan mounting bolts.
  • Battery health testing: Perform capacity testing on backup batteries and UPS batteries; assess battery health status.
  • Landing platform calibration: Calibrate landing platform levelness, calibrate positioning system accuracy, and check docking mechanism wear.
  • Fire protection system inspection: Check fire suppression device expiration dates, test fire linkage logic, and replace expired fire equipment.
  • Overall performance testing: Perform a full-process functional test to verify all performance indicators meet standards.

7.5 Annual Overhaul and Inspection Items

A comprehensive annual overhaul and professional inspection shall be performed each year, recommended to be executed by manufacturer professional technical personnel, including:

  • Overall structural inspection: Check enclosure welds and structural members for corrosion, deformation, or cracking; perform anti-corrosion touch-up painting.
  • Electrical system overhaul: Comprehensively inspect all electrical components, replace aged cables and terminals, and tighten all wiring terminals.
  • Charging module calibration: Calibrate charging module output precision to ensure voltage and current accuracy meets standards.
  • Air conditioning system overhaul: Thoroughly clean evaporator and condenser, replace dryer filter, replenish refrigerant, and check compressor operating condition.
  • Transmission component replacement: Inspect hangar door, centering, and leveling mechanism wear; replace severely worn gears, belts, bearings, and other components.
  • Sensor calibration: Perform professional calibration of all temperature, humidity, voltage, and current sensors to ensure detection accuracy.
  • Software upgrade: Upgrade equipment firmware and monitoring system software to the latest versions, optimizing functionality and performance.
  • Comprehensive performance testing: Conduct complete performance testing and 72-hour continuous operation testing; issue an annual inspection report.

7.6 Wear Parts Replacement Cycle and Replacement Methods

7.6.1 Main Wear Parts Replacement Cycle

Wear Part Recommended Replacement Cycle Remarks
Air conditioning filter screen 1–3 months Adjust based on environmental dust conditions
Air filter element 6 months Ventilation air intake filtration
Charging contacts 1–2 years Adjust based on usage frequency
Sealing strips 3–5 years Replace when aging causes sealing failure
UPS battery 3–5 years Replace when capacity drops below 80%
Cooling fan 3–5 years Replace when abnormal noise or speed drop occurs
Surge protector 5 years Replace when status indicator turns red
Aerosol fire suppression device 5–6 years Replace according to expiration date

7.6.2 Key Wear Parts Replacement Methods

Charging Contact Replacement:

1. Disconnect charging system power supply and confirm power is off.

2. Remove old contact mounting screws, remove old contact, and unplug wiring connectors.

3. Install new contact, connect wiring, and tighten mounting screws.

4. Adjust contact height and levelness to ensure uniform docking pressure.

5. Power on and test charging function to confirm good contact.

Air Conditioning Filter Replacement:

1. Open the air conditioning intake panel and pull out the old filter.

2. Clean dust from the filter surface; washable types can be rinsed with clean water and air-dried, non-washable types should be replaced directly.

3. Install the filter back in place in the correct direction and secure the panel.

4. Note the filter installation direction; ensure the air filtration surface faces the intake side.

UPS Battery Replacement:

1. Turn off UPS output and disconnect utility power input; ensure complete power-off.

2. Disconnect battery pack connecting wires, recording the wiring sequence and polarity.

3. Remove old batteries and install new batteries, ensuring positive and negative terminal directions are consistent.

4. Connect battery wires according to the original wiring sequence, tighten terminals, and provide insulation.

5. Close utility power, start the UPS, and check battery voltage and charging status are normal.

6. Old batteries must be recycled and disposed of in accordance with hazardous waste regulations; do not discard casually.

7.7 Seasonal Maintenance Key Points

7.7.1 Summer High-Temperature Maintenance

  • Comprehensively clean the air conditioning cooling system before summer arrives to ensure cooling efficiency.
  • Check high-temperature protection threshold settings; set temperature control parameters reasonably.
  • Increase inspection frequency, with focus on equipment temperature to prevent over-temperature faults.
  • Check enclosure sunshade facilities are intact to avoid direct sunlight exposure.
  • Check lightning protection facilities and prepare for thunderstorm season.
  • Check drainage system to ensure smooth drainage during heavy rain with no standing water.

7.7.2 Winter Low-Temperature Maintenance

  • Check heating system function before winter arrives to ensure normal startup at low temperatures.
  • Check enclosure insulation and sealing; seal any air leakage gaps.
  • Check pipeline freeze protection measures to prevent condensate pipes and exposed lines from freezing and cracking.
  • Check UPS battery and backup power low-temperature performance to ensure reliable power supply during outages.
  • Promptly clear snow accumulation on the enclosure roof after snowfall to prevent excessive load.
  • Appropriately extend equipment preheating time in low-temperature environments to avoid cold start damage.

7.7.3 Plum Rain (Humid Season) Maintenance

  • Check dehumidifier operating status to ensure internal humidity control meets standards.
  • Check enclosure sealing to prevent rainwater infiltration.
  • Check electrical equipment for condensation; add dehumidification heating if necessary.
  • Check metal parts for corrosion and perform anti-corrosion treatment promptly.
  • Increase insulation testing frequency to prevent moisture-induced insulation degradation.

7.8 Long-Term Shutdown Maintenance Requirements

If equipment requires long-term shutdown (more than 1 month), the following shutdown maintenance requirements shall be followed:

  • Pre-shutdown processing: Charge all batteries to approximately 50% SOC, disconnect charging connections; clean debris and dust inside the enclosure.
  • Power-off procedure: Gradually shut down all equipment according to operating procedures, finally disconnect the main power supply, and close all doors and windows.
  • Moisture protection and anti-corrosion: Place desiccant inside the enclosure and replace periodically to prevent equipment moisture damage and corrosion; precision electronic equipment may use vacuum sealed dust-proof packaging.
  • Periodic inspections: Conduct on-site inspection at least once per month, checking enclosure integrity and internal dryness; power on and operate for more than 2 hours to drive out moisture.
  • Re-commissioning: After long-term shutdown, comprehensive inspection and testing are required before putting back into service; confirm all equipment is normal before operation.

Part 8 Common Fault Diagnosis and Handling

8.1 Basic Fault Diagnosis Principles and Safety Precautions

8.1.1 Basic Fault Diagnosis Principles

  • Power first, then load: When a fault occurs, first check whether the power supply is normal; after eliminating power issues, check load equipment.
  • External first, then internal: First check external wiring, switches, settings, and other external factors, then disassemble to check internal components.
  • Simple first, then complex: First troubleshoot the most common and easily checked fault causes, then investigate complex and difficult faults.
  • Static first, then dynamic: First perform power-off static checks, then power-on dynamic testing to avoid fault escalation.
  • Common first, then individual: When multiple devices fail simultaneously, first check common parts, then check individual devices.

8.1.2 Fault Diagnosis Safety Precautions

  • Live troubleshooting must be performed by certified electricians wearing insulating protective equipment, with dual-person supervision.
  • Before disassembly and repair, power must be disconnected, and energy storage components such as capacitors must be discharged.
  • If dangerous conditions such as smoke, sparking, or unusual odors are discovered during troubleshooting, immediately cut power and evacuate.
  • It is strictly forbidden to arbitrarily bypass protective devices or modify protection parameters, or to replace components with non-specification items.
  • For difficult faults, promptly contact manufacturer technical support; do not blindly disassemble and enlarge the fault.
  • After fault handling is completed, verify the fault is completely eliminated and equipment operates normally before restoring fully automatic operation.

8.2 Power Distribution System Common Faults

Fault Phenomenon Possible Causes Handling Methods
Main circuit breaker trips, cannot power on 1. Short circuit in downstream line or equipment<br>2. Leakage protector activated<br>3. Breaker itself faulty<br>4. Severe overload 1. Disconnect all branch breakers, check each one by closing to locate short circuit<br>2. Press leakage reset button, locate leakage point<br>3. Check breaker body; replace if damaged<br>4. Verify load power, reduce simultaneously operating loads
Single-phase power loss, phase loss operation 1. Upstream supply phase loss<br>2. Main breaker one phase poor contact<br>3. Phase conductor broken<br>4. One-phase fuse blown 1. Measure upstream incoming voltage; confirm utility supply issue and contact power department<br>2. Check breaker terminals, polish contacts or replace breaker<br>3. Check section by section for break point, repair line<br>4. Replace with same specification fuse
Low voltage, equipment cannot start 1. Low utility grid voltage<br>2. Undersized cable, large voltage drop<br>3. Excessive load<br>4. Poor contact, large voltage drop 1. Install voltage stabilizer, verify supply capacity<br>2. Replace with larger cross-section supply cable<br>3. Stagger operation time of high-power equipment<br>4. Check and tighten terminals, treat oxidized contact surfaces
Frequent tripping, no obvious short circuit 1. Breaker setting value too low<br>2. Breaker aging, tripping characteristic deviation<br>3. High inrush current impact<br>4. Intermittent leakage 1. Verify load current, adjust breaker setting value<br>2. Replace with same specification new breaker<br>3. Install soft start or stagger startup<br>4. Locate leakage point, treat insulation damage
Equipment enclosure electrified, tingling sensation 1. Poor grounding or grounding wire disconnected<br>2. Equipment insulation damage causing leakage<br>3. Neutral and ground wires reversed 1. Check and repair grounding connection, ensure reliable grounding<br>2. Locate leaking equipment, repair or replace<br>3. Verify neutral/ground wiring, correct wiring error
Surge protector indicator turns red 1. Lightning surge impact causing module failure<br>2. Overvoltage causing module damage<br>3. Module natural aging 1. Replace with same model surge protector module<br>2. Check upstream voltage, install overvoltage protection<br>3. Inspect periodically, replace when expired

8.3 Charging System Common Faults

Fault Phenomenon Possible Causes Handling Methods
Charging startup fails, no output 1. Charging module not powered<br>2. Charging contacts not docked properly<br>3. BMS communication failure<br>4. Protection function triggered and locked<br>5. Control module fault 1. Check module power switch, close to supply power<br>2. Check docking mechanism, re-center and dock, clean contacts<br>3. Check communication cable, confirm battery BMS is normal<br>4. Investigate over-temperature, overvoltage, reverse connection and other protection triggers; reset fault<br>5. Replace control module, contact manufacturer for repair
Low charging current, slow charging 1. Low battery temperature, low-temperature current limiting<br>2. Charging mode set to slow charge<br>3. Charging contacts oxidized, high contact resistance<br>4. Module output power limited<br>5. Battery aging, high internal resistance 1. Raise internal temperature; fast charge automatically resumes after battery warms up<br>2. Modify charging parameters, set to fast charge mode<br>3. Polish and clean charging contacts, adjust contact pressure<br>4. Check module temperature and current limit settings, remove power limit<br>5. Replace with battery in good health condition
Charging stops midway, fault reported 1. Battery over-temperature protection<br>2. Voltage abnormality protection<br>3. Communication interruption<br>4. Input power fluctuation<br>5. Module over-temperature protection 1. Check temperature control system, lower ambient temperature; automatically resumes after cooling<br>2. Check supply voltage, handle voltage fluctuation<br>3. Check communication cable and BMS, restore communication<br>4. Stabilize power supply, install voltage stabilizer<br>5. Clean module cooling fan dust, improve ventilation
Does not stop at full charge, continuous overcharging 1. Abnormal battery BMS full-charge signal<br>2. Inaccurate voltage sampling<br>3. Incorrect full-charge cutoff threshold setting<br>4. Charging module output out of control 1. Test battery BMS, repair or replace battery<br>2. Calibrate voltage sampling accuracy<br>3. Reconfigure full-charge cutoff parameters<br>4. Immediately cut power, replace faulty charging module
Multi-channel rotation charging not working 1. Scheduling software fault<br>2. Channel address conflict<br>3. Priority setting error<br>4. Some channels faulty and shielded 1. Restart charging scheduling system, upgrade software version<br>2. Modify channel addresses to avoid conflicts<br>3. Reset charging priorities<br>4. Troubleshoot and repair faulty channels, remove shielding
Wireless charging low efficiency 1. Large coil misalignment<br>2. Excessive gap<br>3. Metal foreign objects between coils<br>4. Insufficient transmitter module power 1. Calibrate positioning to ensure precise coil alignment<br>2. Adjust docking height to reduce gap<br>3. Clean foreign objects between coils<br>4. Check transmitter module, repair or replace

8.4 Temperature Control System Common Faults

Fault Phenomenon Possible Causes Handling Methods
Air conditioning not cooling 1. AC not powered or switch off<br>2. Temperature set higher than ambient<br>3. Refrigerant leakage<br>4. Compressor fault<br>5. Filter screen clogged, poor heat dissipation 1. Check power supply and switch, close to supply power<br>2. Lower set temperature, confirm cooling mode<br>3. Locate and repair leak, replenish refrigerant<br>4. Check compressor power and capacitor; replace if damaged<br>5. Clean filter screen and condenser
Internal temperature cannot be lowered 1. Insufficient AC capacity<br>2. Poor enclosure sealing, severe heat leakage<br>3. Direct sunlight, high heat load<br>4. Excessive internal heat-generating equipment<br>5. AC return air short-circuit 1. Add more AC units or replace with larger capacity unit<br>2. Repair enclosure sealing, replace aged sealing strips<br>3. Install sunshade awning to avoid direct sunlight<br>4. Optimize equipment layout, strengthen local heat dissipation<br>5. Straighten air ducts to avoid hot/cold air short-circuit
Air conditioning not heating 1. Heating mode not enabled<br>2. Temperature set lower than ambient<br>3. PTC heater damaged<br>4. Heat pump four-way valve fault<br>5. Over-temperature protection triggered 1. Switch to heating mode<br>2. Raise set temperature<br>3. Check heater and temperature control switch, replace damaged parts<br>4. Repair four-way valve<br>5. Check fan and air duct, eliminate over-temperature cause then reset
Humidity remains high 1. Dehumidifier fault, not started<br>2. Poor enclosure sealing, external moisture entering<br>3. Poor AC cooling/dehumidification performance<br>4. Standing water or moisture source inside enclosure<br>5. Inaccurate humidity sensor 1. Check dehumidifier power and control, repair fault<br>2. Repair enclosure sealing, seal gaps<br>3. Maintain AC, improve dehumidification capability<br>4. Clear standing water, eliminate moisture source<br>5. Calibrate or replace humidity sensor
Fan not rotating or abnormal noise 1. Fan power not connected<br>2. Fan capacitor damaged<br>3. Bearing lacks lubrication or damaged<br>4. Impeller jammed by foreign object<br>5. Mounting bolts loose 1. Check fan power circuit, restore power<br>2. Replace with same specification start capacitor<br>3. Add lubricating oil or replace bearing<br>4. Clean debris from fan interior<br>5. Tighten fan mounting bolts
Abnormal temperature/humidity display 1. Sensor damaged<br>2. Signal wire broken or poor contact<br>3. Acquisition channel fault<br>4. Sensor water ingress or moisture 1. Replace with same model sensor<br>2. Check and repair signal wire<br>3. Replace acquisition module channel<br>4. Dry or replace sensor

8.5 Monitoring System Common Faults

Fault Phenomenon Possible Causes Handling Methods
Industrial PC cannot power on 1. Power supply fault, power not connected<br>2. Power module damaged<br>3. Motherboard fault<br>4. Memory loose<br>5. System crash 1. Check power socket and switch, restore power<br>2. Replace host power supply<br>3. Contact manufacturer to repair motherboard<br>4. Reseat memory, clean gold contacts<br>5. Reinstall system, restore backup configuration
System frequently freezes or restarts 1. Poor heat dissipation, CPU overheating<br>2. Unstable power supply<br>3. Software conflict or virus<br>4. Hard disk fault<br>5. Memory fault 1. Clean host dust, check cooling fan<br>2. Stabilize power supply, check UPS output<br>3. Remove virus, uninstall conflicting software<br>4. Check hard disk for bad sectors, replace hard disk<br>5. Replace memory module for testing
Some sensor data not displaying 1. Sensor damaged<br>2. Wiring disconnected or loose<br>3. Acquisition module channel fault<br>4. Sensor address configuration error<br>5. Communication bus fault 1. Replace sensor<br>2. Check and tighten wiring<br>3. Replace channel or acquisition module<br>4. Verify and modify sensor address configuration<br>5. Troubleshoot bus fault, repair communication line
Remote platform cannot connect 1. On-site network interrupted<br>2. Device IP changed<br>3. Platform server fault<br>4. Firewall blocking<br>5. Communication module fault 1. Check on-site network and carrier signal, restore network<br>2. Set fixed IP and port mapping<br>3. Contact platform operations to confirm server status<br>4. Open corresponding ports, adjust firewall policy<br>5. Replace 4G/5G module or communication network card
Video surveillance no image 1. Camera power fault<br>2. Network cable disconnected or RJ45 connector damaged<br>3. Camera IP conflict<br>4. Recorder channel configuration error<br>5. Camera damaged 1. Check camera power supply<br>2. Remake connector, replace network cable<br>3. Modify camera IP to avoid conflict<br>4. Re-add camera channel<br>5. Replace camera
Alarms not pushing 1. Alarm threshold set too high<br>2. Notification method not configured<br>3. Network disconnected, messages cannot be sent<br>4. Mobile APP notification permission disabled<br>5. Alarm shielded 1. Set alarm threshold reasonably<br>2. Configure SMS, WeChat and other notification methods, test sending<br>3. Restore network connection<br>4. Enable mobile APP notification permission<br>5. Remove alarm shielding

8.6 Takeoff/Landing Positioning System Common Faults

Fault Phenomenon Possible Causes Handling Methods
Hangar door cannot open/close 1. Drive motor power fault<br>2. Transmission mechanism jammed<br>3. Limit switch fault<br>4. Abnormal control signal<br>5. Foreign object jamming door 1. Check motor power circuit, restore power<br>2. Check transmission gears, belts, clear jammed foreign objects<br>3. Check and replace limit switch<br>4. Check control wiring and controller<br>5. Clear foreign objects from door gaps
Large drone landing deviation 1. Poor RTK signal, no fixed solution<br>2. Visual positioning markers dirty<br>3. Camera focus inaccurate<br>4. Excessive wind speed<br>5. Positioning parameter drift 1. Check GNSS antenna, ensure open sky without obstruction, check differential signal<br>2. Clean positioning marker patterns<br>3. Adjust camera focal length, recalibrate<br>4. Disable automatic landing in high wind<br>5. Recalibrate positioning parameters
Centering mechanism not actuating 1. Drive motor or servo fault<br>2. Transmission structure jammed<br>3. Position sensor fault<br>4. Control signal not issued<br>5. Landing detection not triggered 1. Check and replace drive motor/servo<br>2. Clear foreign objects from transmission parts, lubricate moving pairs<br>3. Check and replace position sensor<br>4. Check control wiring and controller output<br>5. Check drone presence detection sensor
Platform leveling failure 1. Leveling motor fault<br>2. Level sensor fault<br>3. Support leg jammed<br>4. Excessive foundation settlement, beyond leveling range<br>5. Leveling algorithm abnormal 1. Check and replace leveling motor<br>2. Calibrate or replace level sensor<br>3. Clean and lubricate support leg screw shaft<br>4. Address foundation settlement, adjust foundation height<br>5. Restart controller, upgrade firmware
Short homing guidance distance 1. Beacon antenna fault<br>2. Severe surrounding obstruction<br>3. Low beacon transmission power<br>4. Abnormal drone-side reception 1. Check antenna and feeder, replace damaged parts<br>2. Raise antenna installation position, avoid obstruction<br>3. Adjust beacon transmission power<br>4. Check drone-side receiving equipment

8.7 Fire Protection and Security System Common Faults

Fault Phenomenon Possible Causes Handling Methods
Smoke detector false alarm 1. Excessive dust triggering false alarm<br>2. Insects entering detector<br>3. High ambient humidity<br>4. Detector sensitivity too high<br>5. Nearby steam or oil smoke 1. Clean detector dust<br>2. Install insect screen, remove insects<br>3. Dehumidify and reduce humidity<br>4. Appropriately lower sensitivity<br>5. Avoid installation near oil smoke/steam environment
Access control card no response 1. Card reader damaged<br>2. Card expired or unauthorized<br>3. Controller fault<br>4. Wiring disconnected<br>5. Power supply fault 1. Replace card reader<br>2. Replace card or re-authorize<br>3. Restart or replace access control controller<br>4. Check and repair access control wiring<br>5. Check access control power supply
Fire suppression device fault light on 1. Device expired or failed<br>2. Activation circuit open circuit<br>3. Device itself faulty<br>4. Controller fault 1. Replace with fire suppression device within validity period<br>2. Check and repair activation circuit<br>3. Replace fire suppression device<br>4. Check fire alarm controller
Water immersion alarm false alarm 1. Condensation at probe<br>2. Probe short circuit<br>3. Wiring moisture causing insulation drop<br>4. Alarm threshold too low 1. Dry probe, improve ventilation to reduce condensation<br>2. Clean probe, eliminate short circuit<br>3. Dry wiring, improve moisture protection<br>4. Appropriately adjust alarm threshold

8.8 Comprehensive Fault Diagnosis Procedures

8.8.1 Equipment Complete Offline Diagnosis Procedure

  • Step 1: Check whether on-site utility power supply is normal, whether there is a power outage.
  • Step 2: Check main switch and UPS output, whether equipment is powered.
  • Step 3: Check network equipment operating status, whether on-site network is interrupted.
  • Step 4: Check whether industrial PC is frozen; restart host for testing.
  • Step 5: Check whether communication module and antenna are faulty.
  • Step 6: Contact manufacturer technical support for remote diagnosis.

8.8.2 Fully Automatic Charging Failure Diagnosis Procedure

  • Step 1: Check whether the drone returned normally and whether battery level reached the return threshold.
  • Step 2: Check whether the hangar door opened normally and the landing platform is ready.
  • Step 3: Check whether drone landing precision is within allowable range.
  • Step 4: Check whether centering mechanism actuated normally and docking is in place.
  • Step 5: Check whether charging system started normally and BMS communication is normal.
  • Step 6: Check whether protection functions were triggered and whether there are any alarm messages.

8.9 Emergency Handling Plans

8.9.1 Fire Emergency Handling

  • Upon discovering a fire, immediately press the emergency stop button and cut off the main equipment power supply.
  • Immediately call the fire emergency number and simultaneously report to the unit supervisor.
  • Personnel shall evacuate to a safe area; do not blindly open the enclosure to extinguish fire.
  • Small initial fires may be extinguished using fire extinguishers; for larger fires, wait for fire department rescue.
  • After fire extinguishing, protect the scene, cooperate with accident investigation, and contact the manufacturer to assess equipment damage.

8.9.2 Electric Shock Emergency Handling

  • Immediately cut off the power supply, or use insulating objects to separate the victim from the power source.
  • Move the victim to a ventilated area, check breathing and heartbeat, and perform CPR if necessary.
  • Immediately call the emergency number and transport the victim to the hospital for treatment.
  • Protect the scene, investigate the cause of electric shock, and implement corrective measures.

8.9.3 Extreme Weather Emergency Handling

  • Upon receiving extreme weather warnings (heavy rain, typhoon, blizzard), check enclosure sealing and reinforce external facilities in advance.
  • If necessary, shut down equipment and disconnect the main power supply to prevent lightning or water damage.
  • After extreme weather passes, comprehensively inspect equipment; only after confirming no water ingress or damage, power on and resume operation.

8.9.4 Drone Forced Landing Emergency Handling

  • Upon monitoring drone loss of signal or abnormality, immediately initiate the emergency handling procedure.
  • Organize on-site search based on last known positioning information and recover the drone.
  • Investigate the cause of signal loss, assess equipment status, and repair before returning to service.

Part 9 Safety Operation Specifications and Precautions

9.1 Electrical Safety Regulations

  • All electrical work must be performed by certified electricians; unauthorized personnel are strictly prohibited fromunauthorized wiring or disassembling electrical equipment.
  • Electrical maintenance must strictly implement the “five-step power-off method”: power off, verify no voltage, discharge, tag, and lock. Live work is strictly prohibited.
  • No debris shall be stored in distribution boxes or cabinets; maintain ventilation and dryness around electrical equipment, and no flammable or explosive items shall be stored.
  • It is strictly forbidden to replace fuses with copper or iron wire, arbitrarily increase breaker settings, or bypass leakage protectors.
  • Do not operate electrical switches or equipment with wet hands; test for leakage before working in moist environments.
  • Regularly check electrical equipment insulation and grounding; promptly handle any identified hazards.
  • Before equipment power-on, confirm all personnel have evacuated the energized area and wiring is correct before energizing.

9.2 Lifting and Installation Safety Regulations

  • Lifting operations must have a special plan, be directed by certified commanding personnel, with the work area barricaded and unauthorized personnel prohibited from entering.
  • Before lifting, check slings, wire ropes, and shackles are in good condition; overloading, angled lifting, and oblique hoisting are strictly prohibited.
  • No standing or passing under suspended loads; no working while standing on suspended loads.
  • For elevated work, safety harnesses must be worn, tool bags carried, tools fitted with fall prevention lanyards; throwing objects from height is strictly prohibited.
  • Before the enclosure is firmly secured, personnel are strictly prohibited from entering the enclosure interior or climbing on the enclosure.
  • When using power tools, insulating gloves must be worn, power cord insulation checked, and leakage protectors installed.
  • Hot work operations must obtain hot work approval, clear combustible materials from surroundings, equip fire extinguishers, and have designated personnel supervise.

9.3 Commissioning and Operation Safety Regulations

  • Before system commissioning, a detailed commissioning plan must be developed, safety measures defined, and supervisory personnel assigned.
  • Live commissioning requires two-person teamwork: one operator and one supervisor. The operator shall inform the supervisor of operations before performing them.
  • When commissioning high-voltage or high-current sections, single-hand operation is mandatory; other body parts shall not contact the equipment enclosure.
  • If abnormalities such as unusual noise, odor, smoke, or overheating are found during equipment operation, immediately stop the machine and disconnect power for inspection.
  • During drone takeoff/landing testing, personnel must evacuate to safe areas; standing under the takeoff/landing flight path is strictly prohibited.
  • Keep test records during commissioning; promptly stop the machine to address problems; operating equipment with faults is strictly prohibited.

9.4 Maintenance Work Safety Regulations

  • Before maintenance work, conduct safety briefing defining work content and safety risks.
  • Before entering equipment interior for maintenance, disconnect the main power supply and hang a “Man at Work, Do Not Close” warning sign.
  • When replacing components, ensure equipment is de-energized and energy storage components are fully discharged.
  • Tools used during maintenance shall be collected promptly after use and not left inside the equipment.
  • Electrical equipment cleaning must use dry compressed air or anti-static brushes; washing with water is strictly prohibited.
  • After maintenance work is completed, count tools and personnel, and only after confirming no items are left behind, close the power supply.

9.5 Fire Safety Regulations

  • Smoking is strictly prohibited inside the enclosure; open flames, flammable, and explosive items are strictly prohibited.
  • Fire equipment shall be inspected regularly to ensure it is intact and effective; misappropriation is strictly prohibited.
  • Blocking fire escape routes is strictly prohibited; ensure emergency evacuation channels are unobstructed.
  • No debris shall be stacked in charging areas; maintain clear heat dissipation channels.
  • Regularly check fire alarm and suppression devices to ensure normal function.
  • Lithium battery charging must be monitored by designated personnel; if bulging, leakage, or abnormal heating is found, immediately stop charging and transfer to a safe area.

9.6 Severe Weather Safety Requirements

  • Outdoor work is prohibited during thunderstorms; disconnect equipment power and network incoming lines to prevent lightning damage.
  • During high winds, check enclosure fixation, reinforce external facilities, and secure loose outdoor items.
  • During heavy rain, check drainage systems to prevent water immersion damage and check enclosure for leaks.
  • During high temperatures, reasonably schedule work hours, avoid midday peak heat, and implement heatstroke prevention measures for personnel.
  • During low temperatures and icy/snowy conditions, implement freeze prevention and anti-slip measures; elevated work requires anti-slip measures to prevent frostbite and falls.

9.7 Personnel Protection and Emergency Rescue

  • All on-site personnel must wear required labor protection equipment as specified, correctly using safety helmets, safety belts, insulating shoes, and other protective gear.
  • The site shall be equipped with a first-aid kit containing common first-aid medications and supplies, inspected and replenished periodically.
  • All operational personnel shall master basic first-aid knowledge, including CPR and bleeding control/bandaging.
  • Emergency contact numbers shall be posted on site; accidents must be immediately reported and emergency rescue plans activated.
  • Regularly organize safety emergency drills to improve personnel emergency response capability.

Part 10 After-Sales Service and Technical Support

10.1 Quality Assurance Commitment

Guangzhou Lain Intelligent System Development Co., Ltd. strictly adheres to the ISO9001 quality management system standard and provides comprehensive quality assurance for its drone charging container products:

  • Products undergo strict full-process inspection and testing before leaving the factory, ensuring product performance and quality comply with standards and contract requirements.
  • All raw materials and components are selected from reputable brands with qualified products; key components adopt imported or first-tier brand products, ensuring product reliability and service life.
  • Strictly designed and manufactured in accordance with national and industry standards. The overall product warranty period is 12 months from acceptance, core components have a 24-month warranty, and lifetime technical support and repair services are provided.
  • During the warranty period, for non-artificial quality issues, the manufacturer provides free repair, component replacement, and free on-site service (except remote areas).
  • Beyond the warranty period, repair services and spare parts are available at cost price, with lifetime free software upgrade services.

10.2 Warranty Scope and Warranty Period

10.2.1 Warranty Scope

Quality issues covered by warranty include:

  • Manufacturing quality defects such as enclosure structural cracking, excessive corrosion, and sealing failure.
  • Performance faults of electrical components and functional modules due to non-artificial damage.
  • Functional abnormalities caused by defects in system software itself.
  • Equipment faults and performance non-compliance occurring under normal use conditions.

10.2.2 Exclusions from Warranty

The following situations are not covered by the free warranty:

  • Equipment damage caused by improper human operation, unauthorized modification, or disassembly.
  • Equipment damage caused by force majeure (earthquake, flood, lightning strike, fire, etc.).
  • Equipment damage or performance degradation caused by failure to maintain and use according to manual requirements.
  • Faults or damage caused by use of non-genuine accessories.
  • Normal wear and replacement of wear parts and consumables.

10.2.3 Warranty Periods

  • Complete machine warranty: 12 months from the date of completion acceptance
  • Enclosure structural warranty: 5 years (non-artificial corrosion, structural deformation)
  • Charging module warranty: 24 months
  • Industrial control system warranty: 24 months
  • Air conditioning equipment warranty: Per manufacturer standards, not less than 12 months
  • Software upgrades: Lifetime free

10.3 After-Sales Service Response Mechanism

  • Service Hotline: 24/7 service hotline +86 13538869979, accepting user repair requests and technical consultations at any time.
  • Response Time: Within 1 hour of receiving a repair request, provide telephone technical response and guide user through troubleshooting.
  • On-Site Service: For problems that cannot be resolved by phone, arrive on site within 24 hours within the province, and within 48 hours outside the province (remote areas may be appropriately extended).
  • Fault Resolution: General faults repaired on site within 24 hours; major faults resolved with a solution plan within 72 hours, restoring equipment operation as soon as possible.
  • Periodic Follow-Up: During the warranty period, telephone follow-up quarterly and on-site inspection semi-annually, proactively understanding equipment operation status and investigating potential hazards.

10.4 Technical Support and Upgrade Services

  • Technical Consultation: Provide lifetime free technical consultation services, answering user technical questions in use and maintenance.
  • Custom Solutions: Provide customized modification, expansion, and upgrade solutions based on user special requirements.
  • Software Upgrades: Continuously optimize system software functions, periodically release upgrade versions; users can upgrade for free.
  • Technical Training: Provide advanced technical training for users to improve operations and maintenance personnel technical capabilities.
  • Remote Support: Provide system commissioning, fault diagnosis, and parameter configuration through remote assistance to improve service efficiency.

10.5 Spare Parts Supply

  • The company maintains a comprehensive spare parts inventory; common spare parts are kept in stock to ensure repair and replacement needs.
  • All spare parts are original manufacturer products with performance parameters fully matching original equipment.
  • During the warranty period, non-artificially damaged spare parts are replaced free of charge; beyond warranty, supplied at cost.
  • Provide spare parts lists and recommended stock quantities based on user needs to support user self-maintenance requirements.
  • For discontinued products, spare parts supply support is guaranteed for more than 5 years.

10.6 Manufacturer Contact Information

  • Manufacturer: Guangdong Lain Intelligent System Development Co., Ltd.
  • Service Hotline: +86 13538869979 (also on WeChat)
  • Technical Support: +86 13538869979
  • Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou
  • Official Website: https://gdlain.com

Guangdong Lain specializes in R&D and manufacturing of industrial special containers. In addition to drone charging containers, the company also provides data center containers, energy storage containers, equipment shelters, shielded room containers, and other full-series special container products, supporting customized design and production. Clients are welcome to inquire and negotiate.

Document Version: V2.0

Release Date: July 2026

Prepared by: Technical Department, Guangdong Lain Intelligent System Development Co., Ltd.