Emergency Support Material Container Installation and Commissioning Manual

Manufacturer: Guangzhou Lain Intelligent System Development Co., Ltd.

Version: V2.0

Release Date: July 2026

Service Hotline: +86 13538869979 (WeChat ID same as phone number)

Technical Support: +86 13538869979

Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou

Official Website: https://gdlain.com

Table of Contents

Copyright Notice

This manual is the exclusive property of Guangzhou Lain Intelligent System Development Co., Ltd. No individual or organization may reproduce, distribute, or alter the contents of this manual in any form without prior written permission. The contents of this manual may be revised as the product undergoes technical upgrades; such revisions will not be announced separately. Please refer to the latest version. This manual serves solely as a guidance document for the installation, commissioning, and maintenance of emergency support material containers. Actual operations must be performed by qualified technical personnel in conjunction with site-specific conditions.

SEO Optimization Tag System

Page Core Optimization Tags

Title Tag: Material Container Installation and Commissioning Manual_Emergency Support Material Container Manufacturer – Guangzhou Lain Intelligent System Development Co., Ltd.

Meta Keywords: material container, emergency support container, material container installation and commissioning, emergency support material container, material storage container, emergency material storage container, Guangzhou Lain material container, material container manufacturer, material container commissioning steps, emergency material container specifications

Meta Description: Guangzhou Lain Intelligent System Development Co., Ltd. provides a professional emergency support material container installation and commissioning manual, covering the full-process guide including material container installation procedures, commissioning steps, acceptance criteria, and maintenance. As a professional material container manufacturer, we provide comprehensive technical support and after-sales service. Service hotline: +86 13538869979.

H1 Tag: Emergency Support Material Container Installation and Commissioning Manual

H2 Tags: Product Overview, Technical Parameters and Performance Indicators, Pre-Installation Preparations, Container Foundation Construction and Positioning Installation, Internal System Installation Process, System Commissioning and Trial Operation, Installation and Commissioning Quality Acceptance Standards, Daily Use and Operating Procedures, Maintenance and Inspection Procedures, Common Fault Diagnosis and Solutions, Safety Operations and Emergency Handling, After-Sales Service and Technical Support

Internal Link Optimization Anchor Text

Three types of anchor text are naturally embedded throughout the full text:

Core Anchor Text: material container

Long-tail Anchor Text: emergency support material container installation and commissioning, material container manufacturer, material container commissioning steps

Related Anchor Text: emergency support container, material storage container, emergency material storage container, emergency support equipment

Preface

With the continuous improvement of China’s emergency management system, emergency material support capability has become one of the core pillars for responding to natural disasters and sudden public events. As modular, rapidly deployable material storage carriers, emergency support containers are widely used in fire rescue, earthquake disaster relief, flood control and drought relief, public health emergencies, and military logistics support, thanks to their flexible deployment, excellent protection performance, and strong environmental adaptability. As the core category within the emergency support container system, material containers are specifically designed for the standardized storage, transfer, and rapid delivery of various emergency materials, and are important equipment for building a modern emergency material support system.

Guangzhou Lain Intelligent System Development Co., Ltd., as a professional domestic material container manufacturer, has deep expertise in the field of modular integrated equipment. Leveraging our technical accumulation in equipment room systems, special-purpose containers, and intelligent integrated systems, we have developed a full series of emergency support material container products. The material storage containers manufactured by our company strictly comply with relevant national standards and industry specifications. From container structure, internal fittings to intelligent systems, all have undergone rigorous testing to meet emergency material storage needs in various scenarios.

To standardize the installation and commissioning process of emergency support material containers, ensure product installation quality and operational stability, and guarantee that material storage environments meet requirements, this “Emergency Support Material Container Installation and Commissioning Manual” has been specially compiled. This manual systematically outlines the complete operational procedures for material containers—from pre-installation preparation, foundation construction, container positioning, internal system installation, to system commissioning and acceptance delivery—while also covering daily use, maintenance, fault diagnosis, and safety management, providing comprehensive technical guidance for installation and commissioning personnel and operations and maintenance managers.

During the preparation of this manual, extensive practical installation experience from numerous emergency material storage container projects has been fully incorporated. Detailed explanations of installation challenges and commissioning key points under different application scenarios are provided, with quality control standards and safety precautions clearly defined for each stage. User units and operators must strictly follow the requirements of this manual to ensure installation quality and operational safety of emergency support containers.

Due to the diversity of application scenarios and differences in site conditions, this manual does not cover installation and commissioning solutions for all special scenarios. In the event of special working conditions or issues not mentioned in this manual, please contact our technical support hotline at +86 13538869979, and we will provide professional technical guidance and solutions.

Guangzhou Lain Intelligent System Development Co., Ltd.

July 2026

Chapter 1 Product Overview

1.1 Product Definition and Classification

1.1.1 Product Definition

A material container is an important branch of emergency support containers. It is a modular piece of equipment that uses a standard container body as the carrier, integrating internal storage shelving, environmental control, safety protection, and intelligent monitoring systems, specifically designed for the standardized storage, transfer, and rapid deployment of emergency materials. Compared with traditional fixed warehouses, emergency support material containers offer advantages such as mobility, rapid deployment, high protection levels, and controllable environments. They can quickly establish material storage sites in scenarios without fixed buildings, providing stable material storage support for emergency rescue and logistics support.

The material containers developed and manufactured by Guangzhou Lain Intelligent System Development Co., Ltd. feature container bodies constructed from high-strength steel, with the interior custom-integrated according to material storage requirements. They enable classified material storage, real-time environmental monitoring, and safety protection, and are widely applicable to various emergency support scenarios.

1.1.2 Product Classification

Based on different classification criteria, material storage containers can be divided into multiple types to suit different application needs:

(1) Classification by Container Size

Type Dimensions Application
20-foot standard material container 6058mm × 2438mm × 2591mm Suitable for small and medium emergency stations, moderate storage capacity, flexible transfer; currently the most widely used specification
20-foot high-cube material container 6058mm × 2438mm × 2896mm Higher interior space for storing larger-volume materials; stronger adaptability
40-foot standard material container 12192mm × 2438mm × 2591mm Large storage capacity, suitable for large emergency support bases, regional material reserve centers
40-foot high-cube material container 12192mm × 2438mm × 2896mm Extra-large storage volume, meeting large-scale material reserve requirements
Non-standard custom material container Custom dimensions per customer requirements Meets storage needs for specific sites and specific materials

(2) Classification by Stored Material Type

  • General-purpose material container: Can store various general emergency materials such as rescue equipment, daily necessities, tools and instruments. Features adjustable internal shelving with strong adaptability.
  • Special-purpose material container: Designed for special material storage needs, such as moisture-proof material containers, constant-temperature material containers, and explosion-proof material containers, with special environmental control and safety protection performance.
  • Medical material container: Specifically for storing medical emergency materials, equipped with disinfection, constant-temperature, and sealing functions to meet medical material storage specification requirements.
  • Flood control material container: Specifically adapted for storing flood control sandbags, assault boats, rescue equipment, and other flood control materials, with internal load-bearing structures configured for heavy materials.

(3) Classification by Functional Configuration

  • Basic material container: Configured with basic shelving, lighting, and ventilation systems, meeting conventional material storage needs at lower cost with simple deployment.
  • Standard material container: Adds dehumidification, temperature/humidity monitoring, and access control systems on the basis of the basic model, enabling controllable management of the material storage environment.
  • Intelligent material container: Integrates IoT monitoring, intelligent access control, fire alarm linkage, and remote management systems, enabling intelligent and visualized management of material storage, suitable for high-standard material support scenarios.

1.2 Core Advantages of Emergency Support Material Containers

As a professional emergency support container manufacturer, Lain’s material containers possess multiple core advantages that comprehensively meet various emergency material storage needs:

1.2.1 Rapid Deployment and High Mobility

Material containers adopt a standardized container body structure and can be transported via highway, railway, sea, and other methods. Upon arrival at the site, no complex construction is required—the container can be positioned quickly and put into service immediately. Compared with traditional fixed warehouse construction, the construction period is reduced by more than 90%, enabling rapid establishment of material support stations during sudden emergency events and achieving rapid delivery and storage of materials.

1.2.2 Sturdy Structure and Excellent Protection Performance

The container body is made of high-strength weather-resistant steel, integrally welded, with excellent wind resistance, seismic resistance, waterproofing, and dustproofing. The protection rating reaches IP65, allowing long-term outdoor use in harsh environments and effectively protecting internal materials from external environmental erosion. The container corners feature reinforced design, capable of withstanding impact forces during lifting and transfer, ensuring transport safety.

1.2.3 Controllable Environment and Safe Material Storage

The interior integrates ventilation, dehumidification, and temperature/humidity monitoring systems, enabling precise regulation of internal temperature and humidity to maintain a stable material storage environment and prevent material damage from moisture, high temperature, mold, and other factors. For special materials, constant-temperature, constant-humidity, and explosion-proof systems can also be configured to meet the storage environment requirements of various materials.

1.2.4 High Space Utilization and Standardized Storage

The interior features a modular shelving design, allowing flexible adjustment of shelving layout according to material dimensions and types, achieving classified, layered, and zoned material storage. This significantly enhances container space utilization while facilitating material inventory, access, and management, improving emergency material dispatch efficiency.

1.2.5 Intelligent Integration and Efficient Management

Intelligent material containers integrate IoT monitoring systems, enabling remote monitoring and data collection of temperature/humidity, access control, fire protection, and power supply systems. Management personnel can monitor real-time container environmental status and material storage conditions through the backend, achieving intelligent material storage management, reducing manual inspection costs, and improving management efficiency.

1.2.6 Flexible Customization and Strong Adaptability

Customized design of container dimensions, internal configuration, and system functions can be provided according to actual customer requirements, adapting to the storage needs of different material types and application scenarios, offering customers personalized emergency material storage solutions.

1.3 Product Application Scenarios

As modular material storage equipment, emergency material storage containers have broad application scenarios covering emergency management, military logistics, industrial production, engineering construction, and other fields. Typical application scenarios include:

1.3.1 Natural Disaster Emergency Rescue Scenarios

During earthquakes, floods, typhoons, mudslides, and other natural disasters, material containers can be rapidly deployed to store rescue equipment, food and medicine, daily necessities, and other emergency materials, providing material support for disaster area rescue operations. They are an important component of the material reserve system for emergency management departments at all levels.

1.3.2 Public Health Emergency Scenarios

During sudden public health events, material containers can serve as epidemic prevention material storage sites for masks, protective clothing, disinfection supplies, testing reagents, and other epidemic prevention materials. Disinfection and constant-temperature systems can be configured to meet the storage specification requirements of epidemic prevention materials, supporting public health emergency response efforts.

1.3.3 Fire Rescue Support Scenarios

Fire rescue teams can deploy material containers at fire stations, duty points, and major event sites to store firefighting equipment, rescue tools, and personal protective equipment, enabling rapid dispatch and nearby support of firefighting materials and improving fire rescue response speed.

1.3.4 Military Logistics Support Scenarios

Material containers can be used in field military training, exercises, border posts, and other scenarios to store logistics materials, equipment and tools, and supplies. They feature strong concealment, flexible transfer, and good protection performance, meeting the mobility and safety requirements of military logistics support.

1.3.5 Engineering Construction Site Support Scenarios

At large infrastructure projects, field engineering sites, and mining operations, material containers can be deployed to store engineering equipment, labor protection supplies, and emergency rescue materials, adapting to complex field environments, reducing temporary warehouse construction costs, and improving material management efficiency.

1.3.6 Enterprise and Institution Emergency Reserve Scenarios

Schools, hospitals, factories, industrial parks, and other enterprises and institutions can deploy material containers as emergency material reserve warehouses to store emergency escape equipment, first-aid supplies, and flood control materials, enhancing their own emergency response capabilities.

1.4 Applicable Standards and Specifications

Material containers manufactured by Guangzhou Lain strictly comply with relevant national and industry standards and specifications from design, production, to installation and commissioning, ensuring product quality and operational safety. The primary applicable standards include:

  • GB/T 1413-2008 “Series 1 freight containers – Classification, dimensions and ratings”
  • GB/T 17770-1999 “Containers – Specifications and testing of general purpose containers for air/land/sea (intermodal) transport”
  • GB 50016-2014 (2018 Edition) “Code for Fire Protection Design of Buildings”
  • GB 50052-2009 “Code for Design of Electric Power Supply Systems”
  • GB 50303-2015 “Code for Acceptance of Construction Quality of Architectural Electrical Engineering”
  • GB 50243-2016 “Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works”
  • GB 50166-2019 “Code for Construction and Acceptance of Fire Automatic Alarm System”
  • GB/T 2887-2011 “General specification for computer field”
  • AQ 3025-2008 “Safety code for working at height in chemical production units”
  • JB/T 10542-2006 “Dehumidifiers”
  • GA/T 394-2002 “Technical requirements for access control systems”

In addition to the national standards listed above, the products also comply with the emergency equipment technical requirements of the Ministry of Emergency Management, and can additionally satisfy industry standards and enterprise standards based on specific customer requirements.

1.5 Product Structure and Composition

The emergency support material container as a whole consists of six major systems: the container body system, internal storage system, environmental control system, electrical power supply system, safety protection system, and intelligent monitoring system. All systems work together to ensure safe, stable, and efficient material storage.

1.5.1 Container Body System

The container body is the basic load-bearing structure of the material container, mainly including:

  • Container frame: Welded from high-strength square steel and channel steel, providing structural support for the entire container and withstanding lifting, stacking, and transfer loads.
  • Wall panels: Including side panels, end panels, and roof panels, made of corrugated steel plate or flat steel plate, with waterproof, dustproof, and impact-resistant performance.
  • Floor: Made of anti-slip patterned steel plate, with anti-corrosion treatment and crossbeam support at the bottom, bearing the weight of materials and shelving, with moisture-proof and anti-corrosion performance.
  • Container doors: Double-leaf swing door design, equipped with anti-theft locks and sealing strips, with a large opening angle for easy entry and exit of large materials, and good sealing and anti-theft performance.
  • Anti-corrosion coating: The entire container body undergoes shot blasting rust removal, with high-performance anti-corrosion topcoat sprayed on the surface, providing excellent weather resistance and corrosion resistance for long-term outdoor use.

1.5.2 Internal Storage System

The internal storage system is the core for achieving classified material storage, mainly including:

  • Heavy-duty shelving: Made of cold-rolled steel with strong load-bearing capacity, capable of layered storage of various materials, with shelf heights flexibly adjustable according to material dimensions.
  • Partition components: Including partition panels, storage boxes, and hanging panels, achieving subdivided material storage, preventing material mixing, and facilitating management.
  • Loading/unloading auxiliary facilities: Such as access ladders, hydraulic pallet truck aisles, and cargo pallet positions, improving material handling efficiency.
  • Identification system: Including zone labels, material labels, and load capacity labels, standardizing material storage management and improving access efficiency.

1.5.3 Environmental Control System

The environmental control system is used to ensure stable storage environment inside the container, mainly including:

  • Ventilation system: Including natural ventilation openings and mechanical ventilation fans, achieving internal air circulation and removing odors and moist air.
  • Dehumidification system: Configured with industrial dehumidifiers to perform air dehumidification inside the container, controlling internal humidity within a reasonable range to prevent material moisture damage and mold.
  • Temperature control system (optional): Configured with air conditioning or heating equipment to achieve internal temperature regulation, meeting the storage requirements of temperature-sensitive materials.

1.5.4 Electrical Power Supply System

The electrical power supply system provides power support for all electrical equipment inside the container, mainly including:

  • Power distribution unit: Including distribution box, circuit breakers, and residual current circuit breakers, achieving power distribution and safety protection.
  • Lighting system: Including main lighting and emergency lighting, ensuring adequate internal illumination for material access and inspection needs.
  • Power supply interfaces: Including external power input ports and internal sockets, meeting equipment power supply and temporary power needs.
  • Backup power supply (optional): Configured with UPS or generator set to provide power support for critical equipment during external power interruptions.

1.5.5 Safety Protection System

The safety protection system is used to ensure the safety of materials and the container, mainly including:

  • Fire protection system: Including smoke detectors, fire extinguishers, and automatic fire suppression devices, achieving fire warning and initial response.
  • Access control system: Including mechanical anti-theft locks, electronic access control, and fingerprint/card access control, controlling personnel entry and exit and ensuring material security.
  • Security surveillance (optional): Configured with cameras and infrared alarms for real-time monitoring and intrusion alarm.
  • Anti-static system (optional): Configured with anti-static flooring and static grounding devices for special materials to eliminate static hazards.

1.5.6 Intelligent Monitoring System

The intelligent monitoring system achieves intelligent management of container conditions, mainly including:

  • Temperature/humidity monitoring terminal: Collects real-time temperature and humidity data inside the container, with over-limit alarm function.
  • Data transmission module: Transmits monitoring data to the backend management platform for remote monitoring.
  • Management platform: Enables data viewing, alarm management, historical data query, and remote device control functions.

1.6 Core Configuration List

Taking the standard 20-foot emergency support material container as an example, the core configuration list is shown in the table below. Specific configurations can be adjusted according to customer requirements.

Table 1-1 Core Configuration List for 20-Foot Standard Material Container

No. System Category Equipment Name Specifications Qty Remarks
1 Container Body Standard container body 20ft high-cube, 6058×2438×2896mm, high-strength steel 1 set Includes anti-corrosion treatment
2 Storage System Heavy-duty storage shelving 2000×600×2500mm, load capacity 300kg per shelf 4 sets Adjustable shelf levels
3 Storage System Cargo pallets 1200×1000mm, wood/plastic 20 pcs Optional
4 Environmental Control Axial flow fan Air volume 2000m³/h, 220V 2 units One inlet, one outlet
5 Environmental Control Industrial dehumidifier Dehumidification capacity 50L/D, 220V 1 unit Automatic humidity control
6 Electrical System LED panel light 40W, cool white 4 pcs Main lighting
7 Electrical System Emergency light 90-minute battery life 2 pcs Auto-illumination on power failure
8 Electrical System Distribution box 8 circuits, with residual current protection 1 set Includes main switch
9 Safety Protection Photoelectric smoke detector Linked audible/visual alarm 2 pcs 3C certified
10 Safety Protection ABC dry chemical fire extinguisher 4kg 2 units Wall-mounted
11 Safety Protection Three-point anti-theft door lock Anti-pry, anti-theft 1 set Container door configuration
12 Intelligent Monitoring Temperature/humidity sensor Accuracy ±0.5℃/±3%RH 2 pcs Data collection
13 Intelligent Monitoring 4G data transmission terminal Includes management platform 1 set Remote monitoring

Chapter 2 Technical Parameters and Performance Indicators

2.1 Container Body Parameters

2.1.1 Dimension Parameters

Material containers adopt the standard container dimension system, while also supporting non-standard customization. Standard specification dimension parameters are as follows:

(1) 20-Foot Standard Material Container (Standard Height)

Parameter Value
External dimensions (L×W×H) 6058mm × 2438mm × 2591mm
Internal dimensions (L×W×H) 5898mm × 2352mm × 2385mm
Door dimensions (W×H) 2340mm × 2280mm
Internal usable volume Approx. 33m³
Rated gross mass 30480kg
Container tare weight Approx. 2100kg (excluding internal equipment)

(2) 20-Foot High-Cube Material Container

Parameter Value
External dimensions (L×W×H) 6058mm × 2438mm × 2896mm
Internal dimensions (L×W×H) 5898mm × 2352mm × 2690mm
Door dimensions (W×H) 2340mm × 2585mm
Internal usable volume Approx. 37m³
Rated gross mass 30480kg
Container tare weight Approx. 2250kg (excluding internal equipment)

(3) 40-Foot Standard Material Container (Standard Height)

Parameter Value
External dimensions (L×W×H) 12192mm × 2438mm × 2591mm
Internal dimensions (L×W×H) 12032mm × 2352mm × 2385mm
Door dimensions (W×H) 2340mm × 2280mm
Internal usable volume Approx. 67m³
Rated gross mass 30480kg
Container tare weight Approx. 3600kg (excluding internal equipment)

(4) 40-Foot High-Cube Material Container

Parameter Value
External dimensions (L×W×H) 12192mm × 2438mm × 2896mm
Internal dimensions (L×W×H) 12032mm × 2352mm × 2690mm
Door dimensions (W×H) 2340mm × 2585mm
Internal usable volume Approx. 76m³
Rated gross mass 30480kg
Container tare weight Approx. 3800kg (excluding internal equipment)

2.1.2 Structural Performance Parameters

Parameter Value
Container frame material Q235B high-strength carbon structural steel
Wall panel material 1.5mm thick weather-resistant cold-rolled steel plate, corrugated structure
Roof panel material 2.0mm thick cold-rolled steel plate, with 2‰ drainage slope
Floor material 3.0mm thick patterned anti-slip steel plate, with transverse load-bearing beams at 600mm spacing
Welding method Frame: full weld process; wall panels: intermittent weld + sealant process
Wind resistance rating Withstands Category 12 typhoon (wind speed 32.7-36.9m/s)
Seismic rating Complies with Grade 8 seismic fortification requirements
Stacking capacity Empty container: 3 tiers; fully loaded: 2 tiers
Lifting method Standard lifting holes at four top corners, compatible with standard container spreaders
Protection rating IP65 for entire container, dustproof and waterproof

2.1.3 Anti-Corrosion and Weather Resistance Parameters

Parameter Value
Surface treatment process Full shot blasting rust removal, achieving Sa2.5 rust removal standard
Primer Epoxy zinc-rich primer, thickness ≥60μm
Intermediate coat Epoxy micaceous iron oxide intermediate coat, thickness ≥40μm
Topcoat Polyurethane anti-corrosion topcoat, thickness ≥60μm
Total coating thickness ≥160μm
Salt spray resistance ≥1000 hours without rusting
Weather resistance ≥8 years outdoor use without significant fading or peeling of coating
Acid/alkali resistance Resistant to weak acid and alkali environmental corrosion

2.2 Internal Supporting System Parameters

2.2.1 Shelving System Parameters

Parameters of the standard heavy-duty storage shelving are as follows:

Parameter Value
Shelving material Q235 cold-rolled steel, electrostatic powder coating
Single shelving unit dimensions (L×W×H) 2000mm × 600mm × 2500mm (customizable)
Upright post specification 80×60×1.5mm C-channel steel
Beam specification 60×40×1.2mm P-type beam
Shelf panel specification 0.8mm thick cold-rolled steel plate, with reinforced rib design
Rated load capacity per shelf 300kg (uniformly distributed)
Number of shelf levels 5 levels (adjustable)
Shelf level adjustment increment 50mm
Surface treatment Electrostatic powder coating, anti-corrosion and wear-resistant
Installation method Bolted assembly, no welding required

2.2.2 Ventilation System Parameters

Parameter Value
Fan type Axial flow fan
Air volume per unit 2000m³/h
Air pressure 120Pa
Power 120W
Rated voltage AC220V/50Hz
Noise ≤55dB(A)
Protection rating IP54
Ventilation method One inlet, one outlet, forming cross-ventilation
Ventilation opening configuration Stainless steel insect screen, aluminum alloy rainproof louver

2.2.3 Dehumidification System Parameters

Parameters of the standard industrial dehumidifier:

Parameter Value
Dehumidification capacity 50L/D (at 30℃, RH80% working conditions)
Suitable space 40-60m³
Rated voltage AC220V/50Hz
Rated power 650W
Humidity control range 30%-80%RH, settable
Control method Microcomputer automatic control, digital humidity display
Water tank capacity 6L, supports external drain hose connection
Compressor Rotary compressor, energy-efficient
Protection rating IP20
Noise ≤52dB(A)
Additional features Automatic defrosting, water-full alarm, fault self-diagnosis

2.3 Environmental Adaptability Parameters

Material containers can adapt to various complex environmental conditions. Specific environmental adaptability parameters are as follows:

2.3.1 Temperature Adaptability

Parameter Value
Storage environment temperature range -20℃ ~ +60℃ (without temperature control configuration)
With temperature control system Constant temperature control of +5℃ ~ +35℃ achievable
Equipment operating temperature range -10℃ ~ +45℃ (electrical equipment)
Low-temperature environment Low-temperature start-up components can be configured per requirements, adaptable to -40℃ extreme cold environments
High-temperature environment Enhanced ventilation and air conditioning systems can be configured, adaptable to +70℃ high-temperature environments

2.3.2 Humidity Adaptability

Parameter Value
External environment humidity ≤95%RH (no condensation)
Internal controllable humidity 40%-70%RH (with dehumidification system configured)
High-humidity environment Dual dehumidifiers can be configured to enhance dehumidification capacity for high-humidity regions
Low-humidity environment Humidification system can be configured to meet special material low-humidity storage requirements

2.3.3 Altitude Adaptability

Parameter Value
Standard applicable altitude ≤2000m
High-altitude adaptation Custom plateau-type electrical equipment available for altitudes above 2000m to ensure stable equipment operation

2.3.4 Special Environment Adaptation

Environment Adaptation Measure
Coastal areas Upgrade to marine-grade anti-corrosion coating to enhance salt spray corrosion resistance
Sandy/dusty areas High-efficiency dust-proof filters configured at ventilation openings to enhance dustproof performance
Flammable/explosive environments Custom explosion-proof configuration available, meeting Exdâ…¡BT4 explosion-proof rating
High-radiation areas Radiation shielding layer can be configured to meet special material storage requirements

2.4 Safety Performance Parameters

2.4.1 Fire Safety Parameters

Parameter Value
Container material combustion performance Non-combustible Class A
Internal decorative materials All use non-combustible or flame-retardant materials
Smoke alarm response time ≤10s
Fire extinguisher configuration Complies with GB 50140-2005 “Code for Design of Configuration of Fire Extinguishers in Buildings”
Automatic fire suppression device (optional) Aerosol fire suppression device, fire suppression response time ≤5s
Electrical fire protection All electrical components are 3C certified, with overload, short circuit, and residual current protection

2.4.2 Anti-Theft Safety Parameters

Parameter Value
Container door locking Three-point anti-theft lock, anti-pry, anti-saw, anti-technical opening
Access control system (optional) Card/fingerprint/password multi-factor authentication, door opening record storage ≥10,000 entries
Container structure Integral steel structure, strong anti-destruction capability
Security surveillance (optional) 2-megapixel high-definition camera, infrared night vision, motion detection alarm

2.4.3 Electrical Safety Parameters

Parameter Value
Distribution system Complies with GB 7251.1-2013 low-voltage switchgear and controlgear assemblies standard
Insulation resistance Power circuit ≥2MΩ, weak current circuit ≥1MΩ
Grounding resistance ≤4Ω
Residual current protection Residual current trip current 30mA, trip time ≤0.1s
Overvoltage protection Equipment operates normally within ±20% input voltage fluctuation range
Electromagnetic compatibility Complies with GB/T 17626 electromagnetic compatibility standard

2.5 Electrical System Parameters

2.5.1 Power Supply Parameters

Parameter Value
Rated input voltage AC220V/50Hz, single-phase three-wire system
Optional input voltage AC380V/50Hz, three-phase five-wire system (high-power configuration)
Rated total power Standard configuration ≤2kW
Maximum load power ≤5kW (customizable expansion)
Power input method Aviation plug/terminal block, rapid external connection

2.5.2 Lighting Parameters

Parameter Value
Main lighting LED panel light, 40W per unit, color temperature 6000K (cool white)
Illuminance Average illuminance at working surface inside container ≥300lx
Emergency lighting LED emergency light, 5W power, battery life ≥90min
Emergency lighting illuminance Evacuation route ≥50lx
Lighting control Toggle switch control, optional human sensor control

2.5.3 Monitoring System Parameters

Parameter Value
Temperature/humidity acquisition accuracy Temperature ±0.5℃, humidity ±3%RH
Data sampling interval 1 minute to 1 hour, settable
Data transmission method 4G/WiFi/Ethernet selectable
Data storage Local storage ≥1 year, cloud storage expandable
Alarm methods Audible/visual alarm, SMS alarm, platform alarm
Management platform Supports PC and mobile access, unified management of multiple devices

Chapter 3 Pre-Installation Preparations

Thorough pre-installation preparation is the prerequisite for smooth installation and commissioning of material containers, effectively improving installation efficiency, reducing installation risks, and ensuring installation quality. The installation and commissioning of emergency support material containers must strictly follow the requirements of this chapter to complete all preparatory work. Site construction may only commence after all conditions are confirmed to be satisfied.

3.1 Installation Site Survey and Requirements

3.1.1 Site Survey Content

Professional technical personnel must be arranged to survey the installation site in advance, comprehensively assessing site conditions and confirming whether the site meets installation requirements. The main survey contents include:

(1) Site Location and Surrounding Environment

  • Confirm the specific location of the installation site and surrounding road conditions; assess whether transport vehicles and lifting equipment can access the site smoothly; determine the container transport route and lifting operation area.
  • Survey the surrounding area for obstacles such as overhead power lines, buildings, and trees; confirm safe lifting operation distances to ensure sufficient lifting workspace. Lifting operations are strictly prohibited beneath overhead power lines. Safe distances from power lines must comply with electrical safety regulations: ≥3m for 10kV lines, ≥4m for 35kV lines.
  • Understand the drainage conditions around the site; confirm whether there are risks of water accumulation or flooding to prevent the container from being submerged after installation.
  • Survey the location of power access points around the site; confirm power supply distance and capacity; formulate the power connection plan.
  • Understand the communication signal conditions around the site; assess the signal transmission quality of the intelligent monitoring system. Signal enhancement plans must be developed for locations with weak signals.

(2) Site Geological and Foundation Conditions

  • Survey the geological conditions of the site; confirm whether the foundation bearing capacity meets requirements to prevent settlement, tilting, and other issues after installation. This can be determined through geological survey reports or on-site simple penetration testing.
  • Measure the flatness of the site; confirm whether the ground slope meets requirements; site leveling treatment is necessary if required.
  • Confirm whether there are underground pipelines, culverts, air-raid shelters, or other underground facilities beneath the site to prevent damage during lifting and foundation construction. This can be confirmed by reviewing underground pipeline drawings, on-site detection, and other methods.

(3) Site Dimensions and Layout

  • Measure the effective dimensions of the installation site; confirm whether the site meets container placement requirements, while reserving door opening space, operating aisles, and equipment maintenance space.
  • For single-container installation, at least 1m of operating space must be reserved around the container, and at least 3m of aisle space on the door side, to meet material handling and personnel passage requirements.
  • For multi-container combined installation, the spacing between containers must be confirmed according to the combined layout, reserving container joining space and pipeline connection channels. The spacing on the container joining side is determined by the joining plan, typically reserving 100-200mm of operating clearance.

3.1.2 Basic Site Requirements

The material container installation site must meet the following basic requirements:

(1) Foundation Bearing Capacity Requirements

Container Type Fully Loaded Gross Weight Unit Area Load Required Foundation Bearing Capacity
Standard 20-foot material container Approx. 30 tons Approx. 2t/㎡ ≥5t/㎡
40-foot material container Approx. 30 tons Approx. 1t/㎡ ≥3t/㎡

If the site has poor geological conditions such as soft soil or backfill soil, foundation reinforcement treatment must be performed, such as pouring a concrete foundation or laying a crushed stone cushion layer.

(2) Site Flatness Requirements

  • Site surface flatness error ≤5mm/m, overall slope ≤1%, to prevent container tilting after installation which could affect door operation and internal equipment operation.
  • The site must be slightly higher than surrounding ground, with a 0.5%-1% drainage slope set, ensuring rainwater can drain smoothly and preventing site water accumulation.

(3) Environmental Condition Requirements

  • The installation site should be far from flammable/explosive locations, corrosive gas sources, and strong electromagnetic interference sources to ensure safe operation of the container and equipment.
  • For outdoor installation, locations with higher elevation and good ventilation should be preferred, avoiding low-lying water accumulation areas and geohazard-prone areas.
  • For indoor installation, confirm that door openings and passage dimensions meet container entry requirements; indoor clear height must meet container height requirements, with at least 200mm of installation allowance reserved at the top.

(4) Power Supply Condition Requirements

  • The installation site must have a stable utility power source, with supply capacity meeting the total power requirements of the container. Standard configuration containers require a single-phase 220V power supply capacity of no less than 5kW.
  • The distance from the power access point to the container should not exceed 50m, with voltage drop controlled within the allowable range to ensure stable equipment power supply.
  • The power supply circuit must have an independent protective switch, a complete grounding system, and grounding resistance ≤4Ω.

3.1.3 Site Pre-Treatment Plans

For sites that do not meet requirements, pre-treatment must be performed. Common pre-treatment plans are as follows:

(1) Site Leveling Treatment

  • Remove debris, rocks, weeds, and other materials from the site; level uneven ground by cutting high spots and filling low spots.
  • After leveling, use a roller or compactor for compaction, ensuring ground compactness reaches above 90%.
  • After leveling is completed, measure flatness and slope to confirm compliance with requirements.

(2) Crushed Stone Cushion Layer Plan

Suitable for temporary deployment and general geological conditions of outdoor sites. Construction process:

1. Lay out the base line according to the container foundation dimensions, with the foundation range extending 200mm beyond the container base edge on each side;

2. Excavate the foundation trench to a depth of 200-300mm, level and compact the trench bottom;

3. Lay a 100mm thick crushed stone cushion layer, aggregate size 20-40mm, well-graded, compacted;

4. Lay a 50mm thick fine sand leveling layer, compacted and leveled, flatness error ≤5mm/m;

5. Anti-slip steel plates or precast concrete slabs may be laid as the container bearing surface as required.

(3) Concrete Foundation Plan

Suitable for long-term fixed installation and scenarios with poor geological conditions. Construction process:

1. Lay out the base line according to container dimensions; excavate the foundation pit to a depth of 300-500mm, adjusted according to geological conditions;

2. Lay a 100mm thick crushed stone cushion layer, compacted;

3. Tie Φ10@200 bidirectional steel mesh, set 40mm thick concrete cover blocks;

4. Pour C25 concrete, thickness 200-400mm, vibrate to achieve full compaction;

5. Trowel and finish the surface, set a 1% drainage slope; the foundation top surface should be 100-150mm above surrounding ground level;

6. Cover and cure for no less than 7 days; container installation may proceed only after strength reaches above 70%.

(4) Elevated Platform Plan

Suitable for low-lying, water-prone, and soft geological areas. A steel structure or concrete structure elevated platform is used to raise the container 300-500mm above ground level, preventing water immersion while improving ventilation and moisture protection. The platform bearing capacity must meet the container’s fully loaded weight requirements, with ladders and operating access configured for personnel entry and exit.

3.2 Tools and Consumables Preparation

3.2.1 Installation Tools Preparation

Based on the installation content and work procedures, prepare all types of installation tools in advance, ensuring tools are in good condition and measuring instruments are accurate. The main tool categories are as follows:

(1) Lifting and Handling Tools

  • Lifting equipment: Mobile crane (select appropriate tonnage based on container weight; 25-ton or above mobile crane is recommended for 20-foot containers), container-specific spreader, lifting slings, shackles, wire ropes
  • Handling tools: Manual hydraulic pallet truck, hand truck, pry bars, rollers, hydraulic jacks
  • Leveling tools: Screw jacks (5-ton or above), flat shims, tapered shims, laser level

(2) Hardware Installation Tools

  • Power tools: Hammer drill, electric drill, angle grinder, cut-off machine, electric wrench, hand drill, heat gun
  • Hand tools: Wrench sets, socket sets, screwdriver sets, pliers, hammers, steel tape measures, spirit levels, plumb bobs, ink line, files, taps
  • Measuring tools: 5m steel tape measure, 50m steel tape measure, laser level, vernier caliper, feeler gauge, ground resistance tester, megohmmeter, clamp meter

(3) Electrical Installation Tools

  • Electrician tools: Wire strippers, crimping pliers, voltage tester, multimeter, insulation resistance tester, insulating tape, heat shrink gun
  • Wiring tools: Wire puller, cable tray cutter, cable tie gun, wire numbering machine, conduit bender

(4) Auxiliary Tools and Safety Protective Equipment

  • Auxiliary tools: Step ladder, elevated work platform, flashlight, marker pen, brushes, wiping cloths, vacuum cleaner
  • Safety protection: Safety helmet, safety harness, anti-slip safety shoes, protective gloves, safety goggles, dust mask, dry powder fire extinguisher, safety warning tape, warning posts

3.2.2 Installation Consumables Preparation

Prepare all types of consumables required during installation in advance, ensuring specifications match and quantities are sufficient. The main consumables include:

(1) Structural Installation Consumables

  • Fasteners: Expansion bolts, hex bolts, self-tapping screws, nuts, flat washers, spring washers (specifications matching installation requirements)
  • Sealing materials: Neutral silicone weather-resistant sealant, EPDM sealing strips, polyurethane foam, waterproof membrane
  • Anti-corrosion materials: Epoxy zinc-rich primer, polyurethane topcoat, anti-corrosion repair paste, anti-rust paint

(2) Electrical Installation Consumables

  • Wire and cable: BV copper conductor wire, RVV control cable, shielded signal cable (specifications conforming to design requirements)
  • Wiring materials: PVC cable trays, galvanized steel conduits, cable clips, nylon cable ties, wiring terminals, insulating tape, heat shrink tubing, corrugated conduit
  • Distribution auxiliary materials: Copper cable lugs, busbars, grounding terminals, cable identification tags, circuit identification labels

(3) Other Consumables

  • Cleaning consumables: Industrial cleaner, lint-free wiping cloths, dust removal equipment
  • Labeling consumables: Label paper, warning sign stickers, material classification labels
  • Commissioning consumables: Commissioning record forms, marker pens, marking paint

3.2.3 Tool and Consumable Management Requirements

  • All measuring tools must be within the validity period of calibration, ensuring measurement data accuracy.
  • Power tools must undergo insulation testing to ensure no leakage hazards, and power cords must be free of damage or exposed conductors.
  • Lifting tools must undergo visual inspection to ensure no cracks, excessive wear, broken wires, and rated load capacity meets usage requirements.
  • Consumables must be stored in categories with proper labeling to avoid mixing and waste. Moisture-sensitive consumables must be protected against moisture.
  • Complete the tool and consumable inventory list before site entry, assign dedicated personnel for management, and conduct inventory verification upon site entry and exit.

3.3 Personnel Allocation and Qualification Requirements

3.3.1 Personnel Allocation Plan

The installation and commissioning of material containers requires a professional construction team. Personnel should be allocated appropriately according to the project scale. The personnel allocation for a standard single-container installation and commissioning project is as follows:

Table 3-1 Single Container Installation and Commissioning Personnel Allocation Table

Position Quantity Main Responsibilities
Project Manager 1 person Overall management of the installation and commissioning project, schedule control, quality supervision, external coordination
Technical Manager 1 person Responsible for technical disclosure, construction plan implementation, technical problem solving, commissioning technical guidance
Hoisting Work Group 2 persons Including 1 lifting commander and 1 crane operator, responsible for container lifting and positioning operations
Structural Installer 2 persons Responsible for container fixing, rack installation, structural component installation, sealing treatment
Electrician 1 person Responsible for electrical system installation, cabling, wiring, power-on commissioning
Low-Voltage Engineer 1 person Responsible for installation and commissioning of low-voltage systems such as surveillance, access control, and fire protection
Safety Officer 1 person Responsible for on-site safety management, safety inspection, safety disclosure, hazard investigation

For multi-container combined installation or complex configuration projects, construction personnel shall be increased correspondingly based on the workload to ensure construction progress and quality.

3.3.2 Personnel Qualification Requirements

All personnel involved in installation and commissioning must possess the corresponding qualifications and capabilities. Specific requirements are as follows:

  • Project Manager: Possess more than 3 years of modular equipment installation project management experience, familiar with emergency support container installation procedures, with good coordination and management capabilities.
  • Technical Manager: Possess a mechatronics or related professional background, familiar with material container system principles, with extensive installation and commissioning experience, capable of solving on-site technical problems.
  • Crane Operator: Hold a Special Equipment Operator Certificate (Crane Operator), possess operating experience with cranes of the corresponding tonnage, familiar with container hoisting operation specifications.
  • Lifting Commander: Hold a Special Equipment Operator Certificate (Hoisting Machinery Commander), familiar with lifting command signals, with extensive on-site hoisting command experience.
  • Electrician: Hold a Low-Voltage Electrician Special Operation Certificate, familiar with electrical installation specifications, with electrical equipment installation and commissioning experience.
  • Low-Voltage Engineer: Possess low-voltage system installation and commissioning experience, familiar with the installation and commissioning of surveillance, access control, and fire protection systems.
  • Safety Officer: Hold a Safety Officer Class C Certificate, familiar with construction site safety management regulations, with on-site safety management capability.
  • Structural Installer: Possess steel structure installation experience, familiar with hardware installation operations, with safety operation awareness.

3.3.3 Pre-Employment Requirements for Personnel

  • All personnel entering the site shall receive pre-employment training and safety technical disclosure, and be familiar with the project content, installation procedures, quality requirements, and safety precautions.
  • Personnel entering the site shall wear the appropriate safety protective equipment, dress in compliance with regulations, and observe the on-site safety management system.
  • Special operations personnel must work with their certificates on site, and carry the certificates with them at all times. Working without a certificate or in violation of regulations is strictly prohibited.
  • Before construction, the division of responsibilities for each position shall be clarified, and responsible persons shall be designated to ensure that each process proceeds in an orderly manner.
  • Health checks shall be conducted before starting work. Personnel under the influence of alcohol, fatigued, or in poor health conditions are strictly prohibited from working.

3.4 Arrival Acceptance and Inventory Checking

3.4.1 Arrival Acceptance Procedure

After the material containers arrive at the site, acceptance and inventory checking work shall be organized promptly to confirm that the products are intact and all accessories are complete. The acceptance work shall be jointly conducted by both the supplier and the purchaser, following the procedures below:

1. Preliminary Visual Inspection: Before unloading, first inspect the container exterior for deformation, impacts, paint peeling, rust, or other damage during transportation. Check whether the container doors and locks are intact. If there is obvious transportation damage, take photos for records and confirm responsibility with the transporter.

2. Quantity Verification: Check the container quantity and accessory box quantity against the shipping list, confirming that the quantity is consistent with the contract agreement and that the container numbers match the factory serial numbers.

3. Unloading and Positioning: After acceptance confirms no major appearance issues, unload the container to the designated position. During unloading, lift and place gently to avoid secondary damage.

4. Open-Box Inventory: Open the accessory boxes and check each internal device, accessory, and consumable item one by one against the packing list for specification and quantity. Check whether the equipment appearance is intact, without damage, moisture, or water ingress. Pay special attention to precision equipment and fragile equipment.

5. Documentation Verification: Verify that the product certificate of conformity, factory inspection report, instruction manual, warranty certificate, packing list, and other technical documents are complete.

6. Acceptance Records: Fill in the arrival acceptance record form, documenting the acceptance status in detail. Any issues found must be clearly marked with the location, extent, and quantity, and both parties shall sign for confirmation.

7. Issue Handling: If product damage, missing accessories, incomplete documentation, or other issues are found, promptly report to the manufacturer and negotiate a resolution. Installation may only proceed after the issues have been resolved.

3.4.2 Acceptance Precautions

  • Acceptance work shall be conducted in a timely manner before or after unloading to avoid later liability disputes.
  • When inspecting the container, all surfaces must be thoroughly checked, including the top, bottom, and corner positions, with special attention to easily damaged areas such as lifting points, container doors, and welds.
  • Electrical equipment shall be checked for intact packaging, no signs of moisture or water ingress, and the equipment nameplate parameters shall be consistent with the design.
  • Fragile and precision equipment shall be handled with care to avoid damage during the acceptance process.
  • After acceptance is passed, properly store the goods and accessories, implement protective measures, and avoid damage or loss during storage.

3.4.3 On-Site Storage Requirements

If installation is not carried out immediately after acceptance, the following on-site storage protection work shall be completed:

  • The container storage site shall be flat and solid, avoiding water accumulation. Place 200mm-high wooden blocks under the container bottom to prevent the bottom plate from directly contacting the ground and being affected by moisture and corrosion.
  • Container doors shall be closed and locked, with sealing strips fitted tightly to prevent rainwater and dust from entering the container and damaging internal equipment and accessories.
  • Accessories and equipment shall be stored in dry, ventilated indoor areas. If no indoor storage conditions exist, rainproof and moisture-proof packaging shall be provided, with storage raised 300mm or more above the ground.
  • Valuable equipment and precision instruments shall be placed under dedicated supervision with anti-theft measures implemented.
  • Weekly inspections shall be conducted during the storage period. Any moisture or damage found shall be promptly addressed.

3.5 Safety Technical Disclosure

3.5.1 Disclosure Organization and Participants

Before installation construction, the project technical manager and safety officer shall jointly organize a safety technical disclosure for all construction personnel, ensuring that all construction personnel are familiar with the construction procedures, technical requirements, and safety risks. Participants in the disclosure include the project manager, technical manager, safety officer, and all construction personnel. If necessary, the Party A on-site management personnel shall be invited to participate.

3.5.2 Technical Disclosure Content

The technical disclosure is primarily aimed at explaining the technical construction requirements to ensure construction quality meets standards. The main contents include:

  • Project overview and the overall installation and commissioning process, including the interface requirements between each process and the schedule arrangement.
  • Technical requirements, quality standards, and acceptance methods for container foundation construction.
  • Operating points, positioning accuracy requirements, and leveling standards for container hoisting and positioning.
  • Construction specifications, installation steps, and quality control points for each internal system installation.
  • System commissioning procedures, commissioning parameters, acceptance standards, and recording requirements.
  • Acceptance standards and procedures, with explanations of key quality control points.
  • Methods for handling common on-site problems and technical requirements.

3.5.3 Safety Disclosure Content

The safety disclosure focuses on explaining the safety risks during construction and preventive measures to ensure construction safety. The main contents include:

  • Construction site safety management system, safety discipline requirements, and penalty regulations for violations.
  • Hoisting operation safety specifications, hoisting operation risk points and preventive measures, and command signal explanations.
  • High-altitude operation safety requirements, safety belt usage specifications, and high-altitude operation protective measures.
  • Electrical operation safety specifications, temporary electrical safety requirements, and electric shock prevention measures.
  • Safe usage requirements for tools and equipment, and the risks and consequences of non-compliant operations.
  • On-site fire safety requirements and hot work operation management regulations.
  • Emergency response procedures, and reporting and handling methods for sudden accidents.
  • On-site hazard source identification and targeted safety precautions.

3.5.4 Disclosure Requirements

  • Safety technical disclosure shall be conducted in written form, with formal disclosure documents prepared. Both the discloser and the disclosees shall sign for confirmation.
  • The disclosure shall be comprehensive and detailed, tailored to the actual on-site conditions, avoiding vague or general content.
  • After the disclosure, construction personnel shall be tested through questions to confirm they have mastered the disclosed content. Personnel who have not mastered the content shall receive the disclosure again.
  • If the construction plan or on-site conditions change during construction, safety technical disclosure shall be re-conducted.
  • Disclosure documents shall be properly archived as part of the project safety technical documentation.

Container foundation construction and positioning installation are the core structural processes of material container installation, directly affecting the structural safety, operational stability, and service life of the container. This chapter details the full-process operation specifications and quality requirements for foundation construction, container hoisting and positioning, fixing and leveling, splicing installation, and sealing and waterproofing. Construction personnel shall strictly follow the requirements in this chapter.

4.1 Foundation Construction Specifications

4.1.1 Foundation Construction Preparation

The following preparatory work shall be completed before foundation construction:

  • Technical Preparation: Familiarize with the foundation construction drawings, clarify technical parameters such as foundation dimensions, elevation, concrete grade, and reinforcement details. Prepare a special foundation construction plan and conduct technical disclosure for construction personnel.
  • Site Preparation: Complete site clearing and leveling, remove debris and obstacles in the construction area, connect construction water and electricity supply, and set up construction safety warning areas to prohibit unauthorized personnel from entering.
  • Material Preparation: Prepare cement, sand and gravel, rebar, formwork, and other construction materials. Confirm the material quality is acceptable and specifications meet the design requirements. Cement shall have a factory certificate of conformity and be retested upon arrival; sand and gravel shall be clean with mud content within specification limits; rebar shall have quality certification documents and undergo mechanical property retesting upon arrival.
  • Equipment Preparation: Prepare excavators, vibrators, troweling machines, rebar cutters, formwork tools, and other construction equipment. Check that the equipment is in good condition and meets construction requirements.
  • Layout and Surveying: Based on the design drawings, use a total station or theodolite to mark out the foundation axis lines, boundary lines, and elevation control points on site. Set up control stakes with protection and marking to ensure accurate foundation positioning.

4.1.2 Gravel Cushion Foundation Construction

The gravel cushion foundation is a simple foundation type suitable for temporary deployment and scenarios with good geological conditions. The construction process and requirements are as follows:

(1) Construction Process

Surveying and layout → Trench excavation → Base compaction → Gravel spreading → Layered compaction → Leveling layer construction → Acceptance

(2) Operation Points

  • Surveying and Layout: Mark out the excavation boundary lines based on the container foundation dimensions. The foundation dimensions shall extend 200mm beyond each side of the container bottom edge to allow for container positioning adjustment.
  • Trench Excavation: Excavate the trench manually or mechanically. The excavation depth shall be determined based on design requirements, typically 200-300mm. Control the excavation depth during the process to avoid over-excavation. If over-excavation occurs, backfill with gravel and compact thoroughly; loose soil shall not be used for backfill.
  • Base Compaction: After excavating to the design elevation, compact the base using a vibratory compactor. Compact at least 3 passes, achieving a compaction density of 90% or above, ensuring the base bearing capacity meets requirements.
  • Gravel Spreading: Spread gravel in layers, with each layer thickness not exceeding 150mm. The gravel particle size should be 20-40mm with good gradation, free from mud and debris.
  • Layered Compaction: After spreading each gravel layer, compact using a vibratory compactor for at least 3 passes to ensure the compaction density meets requirements.
  • Leveling Layer Construction: After the gravel layer is completed, spread a 50mm-thick fine sand or stone powder layer as the leveling layer. Level and lightly compact, then check the surface flatness using a 2m straightedge, with an error of ≤5mm/m.
  • Acceptance: After construction, check the foundation dimensions, elevation, flatness, and compaction density. Fill in the foundation construction acceptance record. Proceed to the next process only after acceptance is passed.

4.1.3 Concrete Foundation Construction

Concrete foundations are suitable for long-term fixed installation, high load conditions, and poor geological conditions. They feature high bearing capacity, good stability, and long service life. The construction process and requirements are as follows:

(1) Construction Process

Surveying and layout → Formwork installation → Rebar tying → Concealed work acceptance → Concrete pouring → Vibration compaction → Surface finishing → Curing → Formwork removal → Acceptance

(2) Operation Points

  • Surveying and Layout: Mark out the foundation axis lines and boundary lines, set elevation control points, and clarify the foundation top surface elevation. The foundation top surface shall be 100-150mm higher than the surrounding ground to prevent rainwater backflow.
  • Formwork Installation: Use steel or wooden formwork. Install formwork according to the layout lines, with steel pipe scaffolding supports. The supports shall be firmly secured to prevent formwork displacement or deformation during pouring. Apply release agent to the inner side of the formwork for easy removal. Formwork joints shall be tight, with sponge strips applied at gaps to prevent slurry leakage.
  • Rebar Tying: Tie the rebar mesh according to design requirements, with rebar specifications, spacing, and concrete cover thickness conforming to design requirements. Splicing lengths shall meet specification requirements, and ties shall be secure without looseness or deformation. Place concrete spacer blocks at the bottom to ensure the rebar cover thickness, typically 40mm.
  • Concealed Work Acceptance: After rebar tying is complete, organize concealed work acceptance to check rebar specifications, quantity, spacing, cover thickness, and splice lengths. Concrete pouring may proceed only after acceptance is passed.
  • Concrete Pouring:
  • The concrete grade shall typically be C25 or C30, adjustable based on load requirements. Ready-mixed concrete is preferred. If mixed on-site, strictly follow the mix ratio, mix thoroughly, with a mixing time of no less than 90 seconds.
  • Before pouring, check whether the formwork and rebar meet requirements, clean debris from the base, and wet the base with water, but without standing water.
  • Concrete shall be poured continuously in layers, with each layer thickness not exceeding 300mm, to avoid cold joints. If construction joints must be left, they shall be handled according to specification requirements.
  • During pouring, continuously check the formwork and support conditions. Address any deformation or slurry leakage promptly.
  • Vibration Compaction: Use an immersion vibrator for compaction. Vibration points shall be evenly distributed with spacing no greater than 1.5 times the vibrator’s effective radius. Vibrate until the concrete surface shows slurry, no further settling, and no air bubbles emerge. Avoid under-vibration and over-vibration. The vibrator shall be inserted quickly and withdrawn slowly, avoiding contact with rebar and formwork.
  • Surface Finishing: After concrete pouring, level and finish the surface. Control the top elevation according to the elevation control points, and check flatness using a 2m straightedge, with an error of ≤3mm/m. A drainage slope shall be created according to design requirements, typically 1%-2%. A second troweling shall be performed after initial setting to reduce surface cracks.
  • Curing: Cover the concrete within 12 hours after pouring, using geotextile fabric or straw mats, and keep it moist by watering. The curing time shall be no less than 7 days. For concrete with admixtures, the curing time shall be no less than 14 days. During the curing period, placing heavy objects on or driving vehicles over the foundation is prohibited.
  • Formwork Removal: Formwork may only be removed after the concrete strength reaches 70% or more of the design strength. Follow the principle of “remove later-installed first, first-installed last” to avoid damaging the concrete edges and corners.
  • Acceptance: After foundation construction, inspect the foundation position, dimensions, elevation, flatness, and concrete strength. Fill in the foundation acceptance record. Container installation may proceed only after acceptance is passed.

4.1.4 Foundation Construction Quality Standards

The following quality standards shall be met after foundation construction:

Inspection Item Standard Value
Foundation position deviation (axis displacement) ≤10mm
Foundation top elevation deviation ±5mm
Surface flatness ≤3mm/m
Foundation dimension deviation ±10mm
Concrete strength Meets design requirements, test block inspection passed
Appearance quality No honeycombing, surface voids, holes, exposed rebar, cracks, or other defects
Drainage slope Meets design requirements, no water accumulation

4.2 Container Hoisting and Positioning

4.2.1 Pre-Hoisting Inspection

Container hoisting is a high-risk operation. A comprehensive inspection must be conducted before hoisting to confirm that all conditions meet the hoisting requirements:

  • Hoisting Equipment Inspection: Check the crane condition, braking system, hoisting wire ropes, hooks, and shackles for integrity. The rated lifting capacity shall meet the hoisting requirements. The crane outrigger area shall be on solid ground, with outrigger pads of no less than 50mm thickness to ensure crane stability.
  • Sling Inspection: Check the container-specific spreader and slings for integrity, free from wear, cracks, broken wire strands, or other defects. The rated load shall be no less than 2 times the container weight.
  • Container Inspection: Check that the container lifting holes are intact, without deformation or cracks. Confirm that there are no loose items inside the container and that the container doors are closed and locked to prevent items from falling during hoisting.
  • Site Inspection: Clear the hoisting work area, set up safety warning tape and security personnel, and prohibit unauthorized personnel from entering. Confirm that there are no obstacles or overhead power lines within the hoisting range and that safety distances meet requirements.
  • Personnel Inspection: Hoisting personnel shall work with their certificates, wear safety protective equipment, have clear division of duties, and the commander and crane operator shall confirm unified command signals in advance.
  • Weather Inspection: Confirm good weather conditions, with wind force not exceeding level 6, and no heavy rain, dense fog, or other weather conditions that could affect hoisting safety.

4.2.2 Hoisting Operation Procedure

Container hoisting shall be performed in strict accordance with the standard operation procedure to ensure hoisting safety and accurate positioning:

1. Sling Connection: Securely connect the special spreader to the four lifting holes on the container top. Confirm that the four lifting points are evenly loaded, the spreader locking mechanism is engaged, and the safety pins are inserted.

2. Test Lift: Command the crane to slowly lift, raising the container 100-200mm above the ground, then stop. Hold for no less than 30 seconds. Check crane stability, sling load conditions, and container balance. Continue lifting only after confirming no abnormalities.

3. Lifting and Slewing: Command the crane to slowly lift the container to an appropriate height above the foundation, then slowly slew the crane to align the container with the foundation installation position. Keep the container stable during slewing to avoid swaying.

4. Slow Descent: Command the crane to slowly lower the hook. When the container is 300mm from the foundation top surface, slow down. Construction personnel assist with positioning on both sides, guiding the container to accurately land at the designed position. Keep the container stable during landing to avoid impacting the foundation.

5. Initial Position Adjustment: After the container lands, initially adjust the container position so that the container axis aligns with the foundation axis, with deviation controlled within the allowable range. After confirming the position is correct, remove the spreader.

4.2.3 Hoisting Safety Precautions

  • Hoisting operations must be uniformly commanded by a certified lifting commander. Command signals shall be clear and accurate, and the crane operator shall strictly follow the command signals. Unsafe command and unsafe operations are strictly prohibited.
  • Standing within the hoisting radius is strictly prohibited. Personnel are strictly prohibited from staying or passing beneath the suspended load.
  • During hoisting, movements shall be smooth, avoiding sudden stops and sharp turns to prevent container swaying and collision.
  • In the event of level 6 or above winds, heavy rain, dense fog, or other severe weather, outdoor hoisting operations are prohibited.
  • Arrange dedicated personnel to observe the crane outriggers, slings, and container during hoisting. If any abnormality is found, stop work immediately and resume only after the issue is resolved.
  • When the container lands, construction personnel shall not extend hands or feet under the container bottom to avoid crushing injuries.
  • Hoisting operations shall have a full-time safety officer supervising throughout, promptly stopping any unsafe behavior.

4.3 Container Fixing and Leveling

4.3.1 Container Leveling

After the container is positioned, leveling shall be performed to ensure the container is in a horizontal state, avoiding tilting that could affect door operation, equipment running, and structural loading. The leveling operation procedure is as follows:

1. Measurement and Inspection: Use a laser level to measure the horizontal level in both the transverse and longitudinal directions across the container top, to determine the container tilt direction and amount. Also measure the elevation of the four container corners to confirm the height differences.

2. Jacking Adjustment: Based on the measurement results, use jacks at the corresponding positions under the container bottom to adjust the container height. Operate jacks slowly, with each jacking increment kept small. Adjust both sides simultaneously to avoid container displacement. Jacks shall be positioned on the container load-bearing beams. Jacking on non-load-bearing parts such as wall panels or roof panels is strictly prohibited.

3. Shimming and Fixing: After leveling is achieved, insert leveling shims or steel plates between the container bottom and the foundation. Place the shims at the container load-bearing beam positions, packed firmly without voids or gaps. The number of shim sets shall be determined by the container size: 20-foot containers require at least 6 sets of shims, distributed at the four corners and middle load-bearing positions; 40-foot containers require at least 8 sets.

4. Verification and Re-check: After shimming, re-measure the container horizontal level to confirm compliance, with the horizontal deviation ≤2mm/m. Also re-check the container position to ensure the position deviation meets requirements.

5. Fixing the Shims: After confirming leveling is qualified, tack-weld the shims to prevent displacement. For concrete foundations, expansion bolts may be used to fix the container bottom beams to the foundation.

4.3.2 Container Fixing

Depending on the installation scenario and usage requirements, different fixing methods may be used for the container. Common fixing methods are as follows:

(1) Expansion Bolt Fixing

Suitable for long-term fixed installation on concrete foundations. Operation procedure:

  • After the container is leveled, mark the drilling positions on the foundation corresponding to the fixing holes on the container bottom beams.
  • Use a rotary hammer drill to drill holes. The drilling depth shall meet the expansion bolt installation requirements, the hole diameter shall match the expansion bolt specification, and the holes shall be perpendicular to the foundation surface.
  • Clean the dust from the drilled holes, insert the expansion bolts, and tighten the nuts to securely connect the container bottom beams to the foundation.
  • Each bottom beam shall have no fewer than 3 fixing points. For a 20-foot container, at least 3 fixing points on each side, with no fewer than 8 total fixing points.
  • After fixing, check the bolt tightening torque to ensure uniform and secure tightening.

(2) Counterweight Fixing

Suitable for temporary deployment and scenarios where drilling is not possible. Use concrete blocks, sandbags, or other heavy objects to press down on the container bottom crossbeams, increasing container stability and preventing container displacement under strong wind conditions. The total counterweight weight shall be no less than 1.5 times the container’s own weight, evenly distributed around the container bottom perimeter to avoid concentrated loading.

(3) Welding Fixing

Suitable for steel structure platform foundations. Weld the container bottom beams to the steel structure platform. Use full welding or intermittent welding, with weld lengths satisfying load-bearing requirements. After welding, remove welding slag, apply anti-corrosion treatment, and coat with anti-rust primer and topcoat.

4.3.3 Leveling and Fixing Quality Standards

Inspection Item Standard Value
Container transverse horizontal deviation ≤2mm/m
Container longitudinal horizontal deviation ≤2mm/m
Container position axis deviation ≤10mm
Container elevation deviation ±5mm
Fixing points Firm and reliable, no looseness or false connection
Shim placement Properly arranged, evenly loaded, no voids

4.4 Container Splicing Installation (Multi-Container Combination Scenarios)

In scenarios with large material storage requirements, multi-container combinations are often used to build large material storage centers. Container splicing installation is required to achieve connectivity between containers and overall coordination.

4.4.1 Pre-Splicing Preparation

  • Confirm the Splicing Plan: Clarify the container combination layout, splicing positions, connection methods, and sealing requirements. Prepare a special splicing construction plan and conduct technical disclosure for construction personnel.
  • Container Positioning: Hoist and position each container according to the combination layout. Adjust the position, elevation, and horizontal level of each container to ensure the splicing surfaces are aligned, with height differences and misalignment meeting requirements.
  • Splicing Surface Treatment: Clean dust, oil, and debris from the container splicing surfaces. Check the flatness of the splicing surfaces, and grind or correct any raised or deformed areas.
  • Prepare Splicing Materials: Prepare connecting bolts, connecting steel plates, sealing strips, neutral silicone sealant, foam filler, waterproof cover plates, waterproof membrane, and other splicing materials. Confirm the specifications are matched.

4.4.2 Container Splicing Operation Procedure

Taking the transverse splicing of two containers as an example, the splicing operation procedure is as follows:

1. Alignment Adjustment: Adjust the splicing surfaces of the two containers so that they align, with consistent container heights, misalignment deviation ≤3mm, uniform gaps, and gap width controlled at 5-10mm.

2. Internal Structure Connection: Personnel enter the container and use connecting steel plates and high-strength bolts to connect and fix at the columns and beams at the splicing position. The spacing between connection points shall not exceed 500mm, ensuring a secure connection and that the containers form an integrated structure. Bolt tightening torque shall meet specification requirements and be tightened evenly.

3. Gap Sealing Treatment:

  • Fill polyurethane foam filler into the splicing gaps, fully filled, to provide sealing, insulation, and cushioning functions.
  • After the foam filler cures, trim off the excess. Apply EPDM sealing strips on both the inner and outer sides of the splicing seams, and apply neutral silicone weather-resistant sealant to ensure a tight seal with no risk of water or air leakage.
  • Install a stainless steel waterproof cover plate at the top splicing seam, lay SBS waterproof membrane, and properly finish the waterproofing ends to prevent rainwater infiltration.

4. Passage Opening: If connectivity between containers is required, open passage door openings on the splicing side panels according to the designed dimensions. Reinforce the perimeter of the openings with structural steel, install door frames and fire doors, and carry out perimeter sealing and waterproofing treatment. The standard door opening size is typically 1800mm × 900mm, customizable as required.

5. Pipeline Connection: Connect the electrical wiring, surveillance cabling, and fire protection cabling of the two containers. Provide wire marking and insulation protection to ensure system connectivity. Install junction boxes at cable connection points with standardized wiring.

6. Inspection and Acceptance: After splicing is complete, check the connection firmness, sealing effectiveness, and passage functionality. Test the connectivity of each system and conduct a water spray test to check the waterproofing effect, confirming that the splicing quality meets requirements.

4.4.3 Splicing Quality Requirements

Inspection Item Standard Value
Container splicing misalignment deviation ≤3mm
Splicing gap width uniformity deviation ≤2mm
Connection points Firm, bolt tightening torque meets requirements, no looseness
Sealing Tight and leak-proof, no leakage after 30-minute water spray test
Passage opening Neatly cut, door opens and closes smoothly, good sealing
Pipeline connections Standardized wiring, clear markings, good insulation

4.5 Sealing and Waterproofing Treatment

4.5.1 Inspection of Container Original Sealing

After the container is installed and positioned, the container’s original sealing structure shall be inspected to ensure sealing performance is intact:

  • Check whether the container door sealing strips are intact, free from detachment, cracking, or aging. After the door is closed, the sealing strips shall be evenly compressed with no gaps.
  • Check whether there are sealing defects at the container welds and rivet points, and whether there are signs of water seepage.
  • Check whether the sealing at vents and pipeline openings is intact, and whether rain hoods and insect screens are properly installed.
  • Check whether the roof drainage slope is normal, whether drain holes are unobstructed, and whether there is water accumulation or rust perforation.

4.5.2 Sealing and Waterproofing Treatment at Openings

If openings need to be cut in the container for cabling or equipment installation, sealing and waterproofing treatment at the openings shall be performed. Operation requirements:

  • Opening positions shall preferably be located on the upper part of the container side walls or at raised positions on the roof, avoiding openings in low-lying areas where water may accumulate.
  • Openings shall be neat and clean, with edges ground smooth and burrs removed. After cutting, apply anti-corrosion treatment to the cut areas, including anti-rust primer and topcoat.
  • Where pipes or cables pass through openings, use waterproof rubber grommets and sealant for sealing. Fill gaps fully to ensure no water seepage risk.
  • Install rain hoods or waterproof elbows at external openings to prevent direct rainwater ingress.
  • For larger openings, install opening cover plates with sealant applied around the perimeter, firmly fixed.

4.5.3 Bottom Moisture-Proofing Treatment

To prevent ground moisture from rising and affecting the container and stored materials, bottom moisture-proofing treatment shall be performed:

  • Place a moisture-proof pad or apply a moisture-proof coating between the container bottom and the foundation to block the moisture rising path.
  • Seal the container bottom perimeter with sealant to prevent rainwater and moisture from entering through bottom gaps.
  • For direct ground placement, lay a polyethylene moisture-proof membrane under the container bottom, extending to the container perimeter and compacted, to enhance the moisture-proofing effect.

4.5.4 Sealing and Waterproofing Quality Inspection

After the sealing and waterproofing construction is completed, quality inspection shall be conducted:

  • Visual Inspection: Sealant shall be applied evenly and continuously, without gaps, bubbles, or cracks. Sealing strips shall be firmly adhered and evenly compressed.
  • Water Spray Test: Use spraying to conduct water spray tests on the container splicing seams, openings, container doors, and other areas for no less than 30 minutes. Check for any leakage inside the container.
  • Post-Rain Inspection: For containers installed outdoors, promptly check after rain for water seepage or moisture inside the container. Repair any leaks found promptly.

After the container is positioned and fixed, installation of the internal systems can begin. The internal systems of a material container include the rack system, lighting system, ventilation and dehumidification system, fire protection system, temperature and humidity monitoring system, access control and security system, power supply and distribution system, and emergency lighting system. Each system installation shall follow the corresponding construction specifications to ensure installation quality and operational safety. This chapter details the installation procedures, operation points, and quality standards for each system.

5.1 Rack System Installation

The rack system is the core of the material container’s internal storage system. Its installation quality directly affects the safety of material storage and space utilization efficiency. The standard configuration is heavy-duty shelf racks, using bolted assembly structure, easy to install and flexibly adjustable.

5.1.1 Pre-Installation Preparation

  • Layout and Marking: Based on the designed rack layout drawing, mark the rack installation position lines on the container floor, and mark the column positions. Confirm the layout meets design requirements, with sufficient aisle space reserved. The main aisle width shall typically not be less than 1000mm, and secondary aisles not less than 800mm.
  • Accessory Inventory: Count the rack accessories, including columns, beams, shelf panels, bolts, foot pads, and safety pins. Check that accessories are complete, free from deformation, paint peeling, cracks, or other defects.
  • Tool Preparation: Prepare wrenches, rubber mallets, tape measures, spirit levels, plumb bobs, and other installation tools.
  • Floor Treatment: Confirm that the installation position floor is level. If the floor is uneven, treat it in advance or use adjustable foot pads for adjustment.

5.1.2 Installation Operation Procedure

1. Column Assembly: Connect the columns to the bottom foot pads, pre-tightening the foot pad bolts for subsequent leveling. Each rack bay consists of a pair of columns. Confirm the column orientation is correct and the holes are aligned.

2. Install Bottom Beams: Erect the two columns, and insert the beam ends into the column slots at the bottom height. Confirm the beams are fully seated, and insert the safety pins to prevent beam detachment. Install the bottom two layers of beams first to give the rack initial shape and stability, preventing tipping.

3. Rack Leveling: Use a plumb bob and spirit level to adjust the vertical and horizontal level of the rack. Adjust the bottom foot pad heights so that the rack is vertical and level, with verticality deviation ≤3mm/m and beam horizontal deviation ≤2mm/m.

4. Install Remaining Beams: Install the beams for each level in sequence according to the designed layer heights. Both ends of each beam at each level shall be firmly seated in the slots with safety pins inserted. Check the layer spacing deviation during installation, with deviation ≤5mm.

5. Install Shelf Panels: Place the shelf panels in sequence on the beams. The panels shall fit tightly against the beams without warping or voids, with uniform gaps between panels.

6. Reinforcement Treatment: For racks exceeding 2m in height or heavy-load racks, install back tie rods or side supports to enhance overall rack stability and prevent swaying.

7. Anti-Collision Corner Guard Installation: Install rubber anti-collision corner guards at the bottom of rack columns near aisles and container doors to prevent material handling operations from impacting the rack columns.

8. Inspection and Adjustment: After all installation is complete, thoroughly check the rack’s verticality, horizontal level, and firmness. Check that all bolts are tightened and pins are fully seated. Adjust any non-compliant areas.

5.1.3 Installation Quality Standards

Inspection Item Standard Value
Rack column verticality deviation ≤3mm/m, full height ≤10mm
Beam horizontal deviation ≤2mm/m
Layer spacing deviation ±5mm
Rack overall position deviation ≤10mm
All connecting bolts Tightened to specification, no looseness
Beam engagement Firm, all safety pins fully installed
Shelf panel placement Flat, no warping, deformation, or voids
Rack surface No paint peeling, scratches, or deformation defects
Rack aisle width Meets design requirements, deviation ≤10mm
Anti-collision corner guards Firmly installed, accurately positioned

5.1.4 Installation Precautions

  • Rack installation shall proceed in a bottom-to-top sequence to ensure rack stability during installation and prevent tipping.
  • Rough handling during installation is prohibited to avoid deformation of columns and beams that would affect load-bearing capacity.
  • After rack installation is complete, unauthorized modification of the rack structure or increasing layer heights is strictly prohibited. Any adjustments shall be performed by qualified personnel.
  • Heavy-duty racks shall undergo load testing after installation, with loads applied layer by layer, to confirm the rack load-bearing capacity meets design requirements.
  • When installing racks, avoid blocking vents, lighting fixtures, sensors, and other equipment to prevent obstruction of equipment functions.

5.2 Lighting System Installation

The lighting system provides illumination for material access, inspection, and maintenance inside the container. It consists of main lighting and emergency lighting, using LED lighting fixtures that are energy-efficient and have a long service life.

5.2.1 Pre-Installation Preparation

  • Layout and Marking: Based on the lighting design plan, mark the lighting fixture installation positions and cable routing lines on the container roof panel. Confirm that the lighting layout is evenly distributed and that illuminance meets requirements. Main lighting fixtures are typically arranged uniformly directly above the aisles to ensure uniform illuminance on the work surface.
  • Equipment and Material Inventory: Count the LED panel lights, emergency lights, switches, wires, conduit, terminal blocks, and other materials. Check that the lighting fixtures are intact, accessories are complete, specifications and parameters meet design requirements, and have 3C certification.
  • Tool Preparation: Prepare electric drills, screwdrivers, wire strippers, crimping pliers, multimeters, ladders, and other installation tools.

5.2.2 Installation Operation Procedure

1. Cabling Work:

  • Install PVC cable trays or galvanized steel conduit according to the cable routing lines. The cable trays/conduits shall be firmly fixed, level and plumb, with fixing point spacing meeting specification requirements: no greater than 1m on straight sections, and no greater than 0.5m at bends.
  • Pull the lighting cables through. Cable specifications shall meet design requirements, typically 2.5mm² copper core wire. Phase wire, neutral wire, and ground wire shall be clearly color-coded (phase wire red, neutral wire blue, ground wire yellow-green).
  • After cable pulling is complete, perform insulation testing, with insulation resistance ≥2MΩ, confirming no short circuits or open circuits.

2. Lighting Fixture Installation:

  • Drill holes in the roof panel according to the marked positions and install the lighting fixture mounting bases, firmly fixed and flush against the roof panel.
  • Connect the fixture power wires, connecting the phase wire to the L terminal, neutral wire to the N terminal, and ground wire to the ground terminal. Connections shall be secure with proper insulation wrapping.
  • Mount the lighting fixtures to the bases and adjust the fixture angles to ensure correct lighting direction. Fixtures shall be installed level without tilting.

3. Switch Installation:

  • Install lighting switches on the wall inside the container door at an appropriate height, typically 1.3m from the floor, for convenient operation.
  • Connect the switch wiring, with the switch controlling the phase wire of the lighting circuit. Wiring shall be correct, and the switch panel shall be fixed level and firmly.
  • Multiple lighting groups may be separately controlled, with multiple switches or a combination of master and individual controls.

4. Power-On Testing:

  • After all lighting fixtures and switches are installed, connect temporary power and test the lighting switches for proper control, that fixtures light up correctly, and that there is no flickering or abnormal noise.
  • Test the emergency lighting function by disconnecting the main power supply, confirming that the emergency lights automatically illuminate with normal brightness.

5.2.3 Installation Quality Standards

Inspection Item Standard Value
Lighting fixture position deviation ≤10mm, neatly arranged, level and plumb
Lighting fixtures Firmly installed, no looseness, flush fit, no gaps
Switch installation height deviation ±5mm, panel level and flush against the wall
Cable routing Standardized, level and plumb, firmly fixed, clearly marked
Wiring connections Secure, good insulation, no exposed wire ends
Lighting control Normal, switches correctly correspond to fixtures, no miscontrol
Emergency lighting activation Normal, automatically lights within 1s of power failure, brightness meets requirements
Average illuminance on interior work surface ≥300lx, illuminance uniformity ≥0.7

5.3 Ventilation and Dehumidification System Installation

The ventilation and dehumidification system regulates the air environment inside the container, maintaining air circulation and controlling humidity within a reasonable range to prevent material moisture damage and mold. It is the core system for material storage environmental protection.

5.3.1 Ventilation System Installation

(1) Pre-Installation Preparation

  • Position Determination: Determine the ventilation fan installation positions on the container side walls, typically arranged diagonally on opposite side walls at both ends of the container — one for air intake and one for exhaust — forming cross-ventilation. The intake vent shall be positioned lower and the exhaust vent higher to facilitate air circulation.
  • Equipment and Material Inventory: Check the axial flow fans, rainproof louvers, insect screens, fixing bolts, sealant, and other materials. Confirm specifications meet design requirements and that fans are undamaged.
  • Tool Preparation: Prepare cutting machines, rotary hammer drills, wrenches, sealant guns, tape measures, and other tools.

(2) Installation Operation Procedure

1. Cutting Work: Mark the opening position on the container side wall according to the fan dimensions. Use a plasma cutter or cutting machine to make the opening. The opening size shall be slightly larger than the fan dimensions. After cutting, grind off edge burrs and apply anti-corrosion treatment to the cut areas, including anti-rust primer.

2. Install Rainproof Louver: Install the aluminum alloy rainproof louver on the outside of the opening. Secure it firmly with the louver vanes facing downward to prevent rainwater ingress. Apply neutral silicone sealant around the perimeter for sealing.

3. Install Insect Screen: Install a 304 stainless steel insect screen on the inner side of the louver to prevent insects and debris from entering the container. The insect screen shall be firmly fixed and easy to remove for cleaning.

4. Install Fan: Install the fan from the inside of the container into the opening. Adjust the fan direction — intake fan airflow direction inward, exhaust fan airflow direction outward. Secure the fan to the side wall with bolts, firmly fixed. Install vibration damping pads between the fan and the side wall to reduce operating vibration.

5. Sealing Treatment: Apply sealing strips at the contact areas between the fan and the container side wall, and apply neutral silicone sealant around the perimeter to ensure a tight seal with no air or water leakage risk.

6. Wiring and Power-On: Connect the fan power cables, configure a dedicated switch, ensure secure wiring with good insulation, and connect power to test fan operation. Check whether the rotation direction is correct and whether there is abnormal noise or severe vibration.

(3) Installation Quality Standards

Inspection Item Standard Value
Fan installation position deviation ≤5mm, installed level and firmly
Opening Neat, smooth edges, proper anti-corrosion treatment
Rainproof louver and insect screen Firmly installed, no looseness
Sealing Tight, no air leakage or water seepage
Fan operation Smooth, no abnormal noise or vibration, correct rotation direction
Fan airflow Meets design requirements, smooth air circulation inside the container
Switch control Normal, standardized cable routing

5.3.2 Dehumidification System Installation

(1) Pre-Installation Preparation

  • Position Determination: Select a position inside the container near the ventilation openings, convenient for drainage and maintenance. Typically placed in a corner at one end of the container, away from the material storage area, to avoid the dehumidifier’s exhaust affecting the stored materials. Reserve no less than 200mm of ventilation space around the dehumidifier.
  • Equipment Inspection: Check the dehumidifier for intact appearance, complete accessories, and no damage to the water tank, filter, drain hose, and other components. Confirm the model and parameters meet design requirements.
  • Power Supply and Drainage Preparation: Confirm that a power outlet is available near the installation position. Reserve a drainage channel. An external drain hose may be used to route condensed water out of the container.

(2) Installation Operation Procedure

1. Placement: Transport the dehumidifier to the designated position, place it stably, and adjust the bottom leveling feet so that the dehumidifier is level, preventing leakage caused by tilting. The distance between the dehumidifier and the wall shall be no less than 200mm to ensure unobstructed air intake and exhaust.

2. Drain Hose Connection: Connect the external drain hose to the dehumidifier’s drain outlet, with the other end routed outside the container to a drainage point. The drain hose shall be laid straight with a slope of no less than 5‰, avoiding kinks and water accumulation to ensure smooth drainage. Install an insect screen at the drain hose outlet to prevent insects from entering in reverse.

3. Power Connection: Plug the dehumidifier’s power cord into a dedicated outlet, confirming that the supply voltage meets the equipment requirements and that grounding is reliable.

4. Filter Inspection: Check whether the dehumidifier’s intake filter is properly installed and undamaged, ensuring the filter is clean.

5. Power-On Testing: Connect power, turn on the dehumidifier, set the target humidity, and test the dehumidifier’s operation. Check that the compressor starts normally, there is no abnormal noise, the exhaust is normal, and drainage is smooth. Test the humidity control function, confirming that the equipment automatically shuts off when the humidity reaches the set value.

(3) Installation Quality Standards

Inspection Item Standard Value
Dehumidifier placement Stable, horizontal deviation ≤2mm/m
Surrounding clearance Sufficient maintenance and ventilation space, no obstruction
Drain hose connection Secure, no leakage, smooth drainage
Power connection Standardized, reliable grounding
Equipment operation Stable, no abnormal noise or vibration
Dehumidification effect Meets requirements, can control container humidity within the set range
Automatic humidity control Functions normally, accurate start/stop

5.4 Fire Protection System Installation

The fire protection system is an important component of material container safety protection, used for fire warning and initial fire response. The standard configuration includes smoke alarms and dry powder fire extinguishers, with the option to upgrade to an automatic fire suppression system as needed.

5.4.1 Smoke Alarm Installation

(1) Pre-Installation Preparation

  • Position Determination: Install smoke alarms on the container roof panel, evenly distributed, with spacing no greater than 8m, and distance from the end wall no greater than 4m. Avoid positioning near vents, lighting fixtures, or other locations to ensure detection sensitivity.
  • Equipment Inspection: Check the smoke alarms, bases, batteries, mounting screws, and other accessories. Confirm the equipment is undamaged, functions correctly, and has 3C certification.

(2) Installation Operation Procedure

1. Positioning and Drilling: Mark the drilling points on the roof panel according to the marked positions. Drill holes and install the mounting bases, ensuring the bases are firmly fixed and flush against the roof panel.

2. Wiring Connection: For standalone smoke alarms, install the battery only. For networked smoke alarms, connect the alarm wiring and power wiring, ensuring correct and secure connections.

3. Detector Installation: Snap the smoke alarm onto the base, rotate to lock, and confirm firm installation.

4. Functional Testing: Press the test button to test the audible and visual alarm function, confirming that the alarm sound is loud and the indicator light flashes normally. For networked types, test the linked alarm function to confirm that alarm signals are transmitted to the monitoring platform correctly.

(3) Installation Quality Standards

Inspection Item Standard Value
Installation position deviation ≤20mm, arrangement meets specification requirements
Installation Firm, no looseness, flush fit against the roof panel
Alarm function Normal, clear audible and visual alarm, volume ≥80dB
Networked alarm signal transmission Accurate, no delay
Cable routing Standardized, clearly marked

5.4.2 Fire Extinguisher Installation

(1) Installation Requirements

  • Fire extinguishers shall be wall-mounted, installed near the container door in a location convenient for quick access. The installation height shall be such that the top of the extinguisher is 1.5m from the floor, and the bottom is no less than 0.08m from the floor.
  • The quantity and specifications of fire extinguishers shall meet design requirements. Typically, a 20-foot container is equipped with 2 units of 4kg ABC dry powder fire extinguishers.
  • The installation position of fire extinguishers shall be visible, clearly marked, and unobstructed for quick access in emergency situations.

(2) Installation Operation Procedure

1. Position Marking: Mark the fire extinguisher bracket installation position on the container interior wall, confirming that the height meets requirements.

2. Bracket Installation: Drill holes and install the fire extinguisher bracket, firmly fixed, capable of withstanding the weight and impact of the extinguisher.

3. Place Fire Extinguisher: Place the fire extinguisher into the bracket, secure it, and check that it is firmly held and convenient to access.

4. Apply Labels: Paste the fire extinguisher usage instruction label and fire safety warning sign next to the extinguisher.

(3) Quality Standards

Inspection Item Standard Value
Installation position Meets specifications, height deviation ≤10mm
Bracket installation Firmly fixed, load-bearing capacity meets requirements
Fire extinguisher access Convenient, unobstructed
Fire extinguisher Within validity period, normal pressure
Labels Clear and complete

5.4.3 Automatic Fire Suppression System Installation (Optional)

For material containers storing valuable materials or flammable materials, an aerosol automatic fire suppression device may be configured. Installation requirements are as follows:

  • The fire suppression device shall be installed at the central position of the container roof, with the discharge direction facing downward, covering the entire interior space of the container.
  • The fire suppression device shall be linked with the smoke alarms and temperature alarms, automatically triggering fire suppression in the event of a fire.
  • Installation shall be firm, wiring standardized, linked function testing normal, and the fire suppression agent within its validity period.
  • The installation position shall avoid areas where personnel frequently stay, with warning signs posted to remind personnel not to touch the device.

5.5 Temperature and Humidity Monitoring System Installation

The temperature and humidity monitoring system is used for real-time monitoring of temperature and humidity status inside the container, with automatic alarm upon exceeding limits. It is an important intelligent system ensuring the material storage environment, capable of local display and remote monitoring.

5.5.1 Pre-Installation Preparation

Point Determination: Temperature and humidity sensors shall be arranged at representative positions inside the container, typically 1 sensor in the middle and 1 at each end of the container body, at a distance of no less than 300mm from racks and walls, avoiding ventilation openings, dehumidifier outlets, lighting fixtures, and other heat/cold sources to ensure accurate monitoring data.

Equipment Check: Check the temperature and humidity sensors, data acquisition terminals, power adapters, communication antennas, mounting brackets, and other equipment. Verify equipment integrity and that model parameters meet requirements.

Tool Preparation: Prepare electric drills, screwdrivers, wire strippers, multimeters, and other tools.

5.5.2 Installation Operation Procedure

Sensor Installation:

  • Install the sensor mounting bracket at the designated position. The bracket shall be firmly secured at a height of approximately 1.5m above the floor, conforming to ergonomic viewing height.
  • Secure the temperature and humidity sensor onto the bracket, adjusting the angle to ensure the sensor sensing head faces the air circulation area.
  • Connect the sensor power supply line and signal line, ensuring firm connections and good insulation.

Acquisition Terminal Installation:

  • Install the acquisition terminal on the interior wall of the container door for convenient operation and viewing, at a mounting height of approximately 1.5m above the floor.
  • Secure the terminal base, connect the power supply and sensor signal lines. Wiring shall be connected according to terminal markings to avoid misconnection.
  • Install the communication antenna in a location with good signal strength, positioned as close to the exterior of the container as possible to enhance signal strength. Antenna cables shall avoid running parallel to high-voltage lines.

System Power-On Commissioning:

  • Connect the system power supply, start the acquisition terminal, and check whether sensor data displays correctly and data refresh functions normally.
  • Set the temperature and humidity upper/lower alarm limits, test the alarm function by simulating limit-exceeding conditions through humidification and heating, and confirm the system can properly issue audible and visual alarms with alarm information correctly uploaded to the monitoring platform.
  • Test the remote monitoring function by viewing real-time data through the computer or mobile platform, confirming normal data transmission and effective remote control functions.

5.5.3 Installation Quality Standards

  • Sensor installation positions are reasonable and can truly reflect the average temperature and humidity inside the container
  • Equipment is firmly installed, free from looseness, and neatly arranged
  • Wiring is properly routed, clearly labeled, and connections are firm and accurate
  • Temperature and humidity monitoring accuracy meets requirements: temperature error ≤ ±0.5°C, humidity error ≤ ±3%RH
  • Data acquisition is stable, refresh is normal, with no packet loss or delay
  • Limit-exceeding alarm function operates correctly, with clear audible and visual alarms and accurate alarm information upload
  • Remote platform data synchronization is normal with complete functionality

5.6 Access Control and Security System Installation

The access control and security system is used to manage personnel entry and exit and ensure material security, including mechanical anti-theft locks and electronic access control systems, with optional video surveillance, infrared alarm, and other security equipment.

5.6.1 Electronic Access Control System Installation

(1) Pre-Installation Preparation

Point Confirmation: The access control host shall be installed on the exterior or interior wall of the container door at a convenient operating position. The card reader shall be installed at a height of 1.3–1.5m above the floor. The electric lock shall be installed at the container door frame. The exit button shall be installed on the interior wall adjacent to the door at the same height as the card reader. Confirm that the installation position avoids strong electromagnetic interference sources and does not affect normal door operation.

Equipment Check: Verify the access control controller, card reader, electric strike/magnetic lock, exit button, access control power supply, access cards, mounting screws, and other accessories. Check equipment appearance integrity, model parameters conforming to design requirements, and functional integrity.

Tool Preparation: Prepare impact drills, screwdrivers, wire strippers, crimping tools, multimeters, soldering irons, heat guns, and other installation tools.

(2) Installation Operation Procedure

Access Control Host and Card Reader Installation: Drill holes in the container wall at the designated positions, secure the access control host base and card reader base, connect the signal lines between the host and card reader, and connect wiring according to the corresponding terminals in the equipment manual. After confirming correct wiring, clip the equipment onto the base and secure firmly. The card reader installation area shall remain clean and flat, avoiding metal shielding that may affect card reading sensitivity.

Electric Lock Installation: Install the electric strike or magnetic lock according to lock type. The lock body is installed on the door frame, and the strike plate is installed at the corresponding position on the container door. Adjust the alignment accuracy between the latch bolt and strike plate to ensure the bolt can properly extend and lock after the door closes. The lock shall be firmly secured with load-bearing capacity meeting anti-theft requirements. Install anti-vibration pads between the electric lock and door frame to reduce closing impact and lower operating noise.

Exit Button and Power Supply Installation: Install the exit button on the interior door side of the container with firm wiring and smooth press-and-return action. Install the dedicated access control power supply in a concealed position inside the container, connected to the mains circuit, with output voltage matching access control equipment requirements and reliable grounding. Reserve maintenance access space beside the power supply for future servicing.

Line Connection: Connect the lines between the access control controller, card reader, electric lock, exit button, and power supply one by one. High-voltage and low-voltage lines shall be routed separately with a spacing of no less than 200mm to avoid electromagnetic interference. All wiring terminals shall be securely crimped, insulation properly applied, and lines labeled with identification numbers.

Functional Testing: Connect the power supply and conduct access control function tests, including card-swipe door opening, password door opening, exit button door opening, lock status feedback, and abnormal alarm functions. Test access control permission management functions to confirm authorized cards can open the door, unauthorized cards cannot, and door opening records can be properly stored and queried.

(3) Installation Quality Standards

  • Equipment installation position deviation ≤ 5mm, height deviation ≤ 10mm, flat and firm installation without looseness or tilting
  • Lock alignment is precise, opening/closing is smooth, locking is reliable, with no jamming or false locking
  • Wiring is properly routed, high/low voltage separated, clearly labeled, and connections are firm and reliable
  • Card reading response time ≤ 0.5s, door opening action is smooth without delay
  • Access control records are completely stored, with capacity for no less than 10,000 door opening records
  • Lock state maintenance or automatic unlocking after power failure conforms to design requirements, and emergency release function operates normally
  • Equipmentenclosure grounding is good, with no electric leakage hazards

5.6.2 Video Surveillance System Installation

(1) Pre-Installation Preparation

Point Planning: Cameras shall typically be installed at diagonal positions on the interior ceiling of the container, covering the entire interior area and the door entrance/exit with no blind spots. Outdoor cameras may be installed on the exterior top of the container to monitor the surrounding environment. Confirm that the installation position has a clear view without obstruction, avoiding direct strong light and heat sources to prevent image overexposure or impact on equipment lifespan.

Equipment Check: Verify network HD cameras, DVR/NVR, surveillance hard drives, power adapters, network cables, mounting brackets, and other equipment. Check equipment integrity, pixel count, night vision function, and other parameters conforming to design requirements. Lenses shall be free from scratches and dust ingress.

Tool Preparation: Prepare electric drills, screwdrivers, network cable crimping tools, cable testers, multimeters, ladders, and other tools.

(2) Installation Operation Procedure

Camera Installation: Secure the camera mounting bracket at the designated position, adjust the bracket angle, install the camera onto the bracket, connect the network cable and power cable, and make preliminary camera angle adjustments to ensure the monitoring view covers the target area. Outdoor cameras shall be fitted with waterproof protective housings, and connections shall be waterproofed and insulated to prevent rainwater ingress.

Recorder Installation: Install the DVR/NVR beside the distribution box inside the container or in a dedicated equipment cabinet. Secure firmly, connect to the mains power supply, install the surveillance hard drive, and connect camera network cables and display equipment (optional). Reserve heat dissipation space around the recorder to prevent equipment overheating.

Cable Routing: Use Cat5e or Cat6 network cables for video signal transmission. Route cables along the container side walls, protected by conduit or cable trays. Label both ends of cables, crimp RJ45 connectors to specification, and test line continuity and transmission rates for normal operation.

System Commissioning: Connect the system power supply, start the recorder and cameras, add devices, adjust camera angles and focal lengths to ensure clear images and complete fields of view. Configure recording parameters, enable motion detection, night vision, recording storage, and other functions. Test remote viewing functions to confirm real-time viewing and playback via mobile and computer platforms.

(3) Installation Quality Standards

  • Cameras are firmly installed, angles are adjustable, without looseness
  • Monitoring images are clear, without obstruction or blind spots, and night vision performance meets requirements
  • Recording storage is normal, capable of storing no less than 30 days of HD recordings
  • Remote access is smooth without lag, and image synchronization is good
  • Cables are neatly routed, clearly labeled, and connections are properly crimped
  • Motion detection alarm function operates normally, with timely and accurate alarm push notifications

5.6.3 Infrared Intrusion Alarm System Installation (Optional)

(1) Pre-Installation Preparation

Point Determination: Infrared detectors shall be installed near doors/windows and passageways inside the container to form an intrusion detection defense line. The host shall be installed in a concealed position, and the alarm siren shall be installed on the exterior of the container for deterrence. Detectors shall avoid heat sources such as ventilation openings and heating equipment, as well as positions with direct airflow, to reduce false alarm probability.

Equipment Check: Verify active/passive infrared detectors, alarm host, audible/visual siren, power supply, remote controls, and other equipment. Check functional integrity and complete accessories.

(2) Installation Operation Procedure

Detector Installation: Secure the detector mounting bracket, adjust the detection angle and sensitivity, and confirm the detection range covers all intrusion passageways with no blind spots. Connect signal lines and power lines with firm connections and good insulation.

Alarm Host and Siren Installation: Install the alarm host, connect the power supply and all detector lines, and install the audible/visual siren on the exterior with firm wiring. Configure zone numbers on the host corresponding to each detection point.

Functional Testing: Set zone parameters and test intrusion detection functions by simulating personnel intrusion. Confirm detectors can accurately identify intrusions, the host triggers audible/visual alarms, and alarm signals can be synchronously uploaded to the monitoring platform. Test arming, disarming, and bypass functions, confirming normal remote control operation and alarm delay times conforming to design requirements.

(3) Installation Quality Standards

  • Detector detection range conforms to design requirements with no blind spots
  • Alarm response time ≤ 2s, audible/visual alarm volume ≥ 100dB
  • Low false alarm rate, strong environmental adaptability
  • Arming/disarming operation is convenient with complete functionality

5.7 Power Supply and Distribution System Installation

The power supply and distribution system is the power source for all electrical equipment. Its installation quality directly affects the electrical safety and operational stability of the entire material container. Construction must strictly follow electrical installation specifications to ensure reliable power supply and adequate protection. As the core supporting system of the emergency supply container, the power distribution design fully considers power supply requirements for emergency scenarios, featuring multiple protections against overload, leakage, and surge, adaptable to complex outdoor power environments.

5.7.1 Distribution Box Installation

(1) Pre-Installation Preparation

Position Confirmation: The distribution box shall be installed on the interior wall adjacent to the container door for convenient operation and maintenance, at a mounting height of 1.5m from the floor to the bottom edge of the box. Avoid damp and collision-prone positions, and reserve no less than 500mm of operating space around the box.

Equipment Check: Verify the distribution box body, circuit breakers, residual current circuit breakers (RCCB), wiring terminals, busbars, and other components. Check that the distribution box housing is intact, electrical component specifications and parameters conform to design requirements, and products carry 3C certification.

Tool Preparation: Prepare impact drills, screwdrivers, wire strippers, crimping tools, multimeters, megohmmeters, voltage testers, and other tools.

(2) Installation Operation Procedure

Box Body Fixing: Drill holes in the container wall at the designated position and secure the distribution box firmly using expansion bolts. The box shall be vertical and level with a verticality deviation ≤ 1.5mm/m. Install an insulating pad between the distribution box and container wall. Apply sealing and waterproofing treatment at openings in the box to prevent moisture and dust ingress.

Component Assembly: Install the main circuit breaker, branch circuit breakers, residual current circuit breakers, surge protective devices, and other components onto the DIN rail inside the distribution box according to the power distribution system diagram. Arrange neatly with uniform spacing, and affix clear circuit identification labels for each circuit.

Wiring Construction:

  • Connect the external mains incoming line, with phase, neutral, and ground wires connected to the main incoming terminals respectively. Phase sequence must be correct, connections firm, wire lugs crimped to specification, and stranded wires tinned.
  • Connect each branch circuit line. Lighting, ventilation, dehumidification, socket, and low-voltage circuits shall be routed separately. Each circuit corresponds to an independent circuit breaker, with circuit labels corresponding one-to-one with end equipment.
  • Install independent grounding busbar and neutral busbar. All ground wires are uniformly connected to the grounding busbar, neutral wires to the neutral busbar, and grounding bolts are tightened securely.
  • Connect the surge protective device to the incoming end, connected in parallel between phase and ground, to protect downstream equipment from lightning surge damage.

Insulation Testing: After wiring is complete, close all circuit breakers and use a 500V megohmmeter to test insulation resistance of each circuit. Power circuits shall have insulation resistance ≥ 2MΩ, low-voltage circuits ≥ 1MΩ. Confirm no short circuit or ground fault.

Power-On Inspection: Close the main switch and sequentially close each branch circuit switch. Check whether the supply voltage of each circuit is normal. Test the residual current circuit breaker trip function by pressing the test button to confirm normal tripping with an operating time ≤ 0.1s.

(3) Installation Quality Standards

  • Distribution box is installed vertically and level, verticality deviation ≤ 1.5mm/m, firmly secured
  • Electrical component specifications conform to design, neatly arranged, with clear and accurate labels
  • Wiring is firm, phase sequence correct, wire numbers clear, and routing neat and aesthetically pleasing
  • Insulation resistance conforms to code requirements, with no short circuit or leakage hazards
  • Residual current protection function operates normally, operating parameters meet requirements
  • Grounding is reliable with grounding resistance ≤ 4Ω
  • Interior of the box is clean, free of debris, and the door lock is functional

5.7.2 Cable Routing

(1) General Routing Requirements

Indoor wiring within the container shall adopt surface-mounted routing, laid in cable trays or galvanized steel conduits. Bare, scattered wiring is strictly prohibited. High-voltage and low-voltage lines shall be routed separately with a spacing of no less than 200mm to avoid electromagnetic interference.

Cable selection shall conform to design requirements. Power circuits shall use BV copper-core wires, lighting circuits no less than 1.5mm², socket and equipment circuits no less than 2.5mm². Low-voltage signal circuits shall use shielded cables or dedicated signal cables with the shield grounded at one end.

No splices are permitted in the middle of cables. All connections shall be made at junction boxes or equipment terminals. Both ends of cables shall be provided with clear circuit identification and numbering.

Cable passage points through container wall panels shall be fitted with protective grommets to prevent damage to cable insulation, and openings shall be sealed and waterproofed.

(2) Construction Operation Procedure

Line Measurement and Pay-out: Measure cable lengths according to routing directions, cut cables with 10%–15% excess allowance for equipment connection and maintenance. Avoid bending or scratching cable insulation during pay-out.

Cable Tray/Conduit Installation: Secure PVC cable trays or galvanized steel conduits horizontally and vertically. Fastener spacing shall comply with codes: straight sections of cable trays ≤ 1m spacing, at bends ≤ 0.5m; conduit fasteners ≤ 1.5m spacing. Use dedicated corner fittings at tray bends to prevent cable damage from sharp bending.

Wire Pulling: Pull cables through cable trays or conduits. Lines of different circuits and voltage levels shall be routed separately. Cables shall run straight without kinking or compression. Apply talc powder for lubrication when pulling wires; do not forcibly stretch cables.

Securing and Dressing: After routing is complete, dress the cables and secure with nylon cable ties for a neat appearance. Affix circuit identification labels on the side facing convenient viewing.

(3) Quality Standards

  • Cable routing is horizontal and vertical, firmly secured, neat and aesthetically pleasing
  • Cable specifications conform to design, without damage or aging
  • High/low voltage lines are separated without parallel winding
  • Line labels are clear and accurate with definite correspondence
  • Conduit and wall penetration protection is adequate without damage hazards
  • Cable excess is moderate, convenient for maintenance, without waste

5.7.3 Socket and Grounding System Installation

(1) Socket Installation

Sockets shall be installed along the interior walls of the container at a height of 0.3m or 1.2m above the floor, determined by usage requirements, with spacing no greater than 3m. Dedicated sockets shall be provided near equipment.

Sockets shall be five-hole safety type with protective shutters, rated current 10A. High-power equipment shall be provided with dedicated 16A sockets.

Socket wiring shall follow the principle of “left neutral, right phase, top ground”. Connections shall be firm, faceplates flat and securely mounted, fitting tightly against the wall without gaps.

Socket circuits shall be provided with independent residual current circuit breakers to ensure temporary power usage safety.

(2) Grounding System Installation

The material container shall be provided with a complete grounding system, including container body grounding, equipment grounding, and lightning protection grounding, adopting a combined grounding method with grounding resistance ≤ 4Ω.

A dedicated grounding terminal shall be installed at the bottom of the container, connected to an external grounding electrode using 40×4mm galvanized flat steel or 16mm² stranded copper grounding wire. The grounding electrode shall use ∠50×5 galvanized angle steel, 2.5m in length, driven vertically into the ground. Connection shall only be made after grounding resistance testing passes.

All electrical equipment metal housings inside the container, distribution box housings, metal cable trays, and metal conduits shall be reliably grounded, forming a complete equipotential grounding network.

Grounding connections shall use bolted compression. Contact surfaces shall be ground and derusted, coated with conductive grease, with firm connections and good contact. Bolts shall be fitted with anti-loosening washers.

5.7.4 Backup Power Supply System Installation (Optional)

For emergency supply containers with high power supply reliability requirements, a UPS or small generator set may be configured as backup power to ensure continuous operation of critical equipment after power failure, suitable for field emergency scenarios without mains power supply.

(1) UPS Installation

Install the UPS host in a dry, ventilated dedicated position with no less than 200mm of heat dissipation space reserved around it. Place stably, secure firmly, and avoid vibration.

The battery bank shall be installed in conjunction with the host, with correct wiring and correct polarity. The battery bank shall be firmly secured with proper insulation protection and ventilation/cooling. Install battery protective barriers to prevent collision.

Connect the mains input and load output lines. Critical equipment such as surveillance systems, fire protection systems, and temperature/humidity monitoring shall be connected to the UPS power supply circuit. Non-critical equipment shall not be connected to the UPS to extend backup time.

After installation, conduct charge/discharge testing to verify backup time meets design requirements. Mains-to-UPS transfer time ≤ 10ms, ensuring uninterrupted power supply after power failure.

(2) Diesel Generator Set Installation

The generator set shall be installed in an independent machine room beside the container or in a dedicated compartment, with proper vibration damping, noise reduction, and exhaust treatment. The exhaust pipe shall be routed to a safe area with a spark arrester installed.

Connect the fuel system, cooling system, and output distribution system. Wiring shall be to code, grounding reliable, and fuel tank capacity sufficient for extended operation requirements.

Commission the automatic start function of the generator set. It shall automatically start and supply power within 15 seconds of mains power interruption, and automatically stop and switch back to mains power after mains restoration.

Chapter 6 System Commissioning and Trial Operation

After all systems are installed, comprehensive system commissioning and trial operation shall be conducted to verify the functionality and performance of each system, ensuring the material container can operate stably and reliably upon delivery. System commissioning follows the principle of “standalone first, system second; individual adjustment first, integrated adjustment second,” carried out in an orderly step-by-step manner. This is the core quality control stage in the installation and commissioning process of the emergency supply container.

6.1 Pre-Commissioning Preparation

6.1.1 Commissioning Condition Confirmation

  • All system installation work is fully completed, installation quality complies with code requirements, installation records are complete, and concealed works acceptance has passed.
  • On-site power supply is stable, mains connection is normal, voltage and frequency conform to equipment rated requirements, and supply capacity meets full-load operation requirements.
  • Container sealing is intact, interior is clean without debris or construction waste, and all equipment appears undamaged without installation damage.
  • Commissioning tools are fully prepared, including multimeters, clamp ammeters, thermohygrometers, anemometers, illuminance meters, sound level meters, grounding resistance testers, and other measuring instruments, all within their calibration validity period.
  • Commissioning personnel are in place, familiar with system principles and commissioning methods, clear on commissioning procedures and acceptance criteria, with safety protection measures implemented.
  • A dedicated commissioning plan is developed, specifying commissioning items, methods, acceptance criteria, and recording requirements, with designated personnel responsible for recording commissioning data.

6.1.2 Pre-Commissioning Inspection

Visual Inspection: Inspect each equipment’s installation position, fixing condition, and appearance integrity one by one. Confirm no looseness, deformation, or damage. Wiring terminals shall have no looseness or exposure, and equipment labels shall be clear.

Line Inspection: Verify the wiring correctness of each system, phase sequence correspondence, label clarity, insulation quality, and grounding reliability. High and low voltage lines shall not be mixed or entangled.

Power Supply Inspection: Measure the input power supply voltage and frequency, confirming they are within the allowable fluctuation range of equipment. Check that the setting values of breakers and protection devices at each level conform to design requirements.

Environmental Inspection: Confirm the container interior is clean, free of flammable and explosive materials, with smooth ventilation. Commissioning environment temperature and humidity shall meet equipment operating requirements, with no obstructions affecting commissioning.

6.2 Individual System Standalone Commissioning

6.2.1 Electrical System Commissioning

(1) Power Distribution System Commissioning

  • Sequentially close the circuit breakers and check whether the voltage of each level of distribution circuit is normal. Three-phase voltage balance meets requirements, single-phase voltage deviation ≤ ±7%.
  • Test residual current protection functions, testing the residual current circuit breaker operation performance circuit by circuit. Operating current 30mA, operating time ≤ 0.1s, conforming to national standard requirements.
  • Test overload and short-circuit protection functions, verifying protection devices can reliably operate, with settings matching line and equipment loads.
  • Measure the no-load current of each circuit, confirming no abnormal no-load losses or abnormal heating.
  • Test grounding resistance using a grounding resistance tester to measure the combined grounding resistance, confirming ≤ 4Ω.

(2) Lighting System Commissioning

  • Turn on all lighting fixtures and check whether all lamps illuminate normally, with no flickering, abnormal noise, or flashing. Lamp color temperature and brightness conform to design requirements.
  • Use an illuminance meter to measure the working surface illuminance inside the container. Select 5–8 measurement points and take the average, confirming average illuminance ≥ 300lx, illuminance uniformity ≥ 0.7, with no obvious dark areas.
  • Test lighting switch control functions, confirming correct correspondence between switches and lamps, flexible control, and no misoperation or lag.
  • Test emergency lighting functions by disconnecting the main power supply. Check whether emergency lights illuminate automatically, measure emergency illuminance, and confirm evacuation passage illuminance ≥ 50lx with a duration ≥ 90 minutes.
  • Operate continuously for 2 hours, checking lamp temperature rise and line heating, confirming no abnormal overheating and conductor temperatures within allowable range.

6.2.2 Ventilation and Dehumidification System Commissioning

(1) Ventilation System Commissioning

  • Start each ventilation fan individually, checking whether the fan rotation direction is correct, operation is stable, with no abnormal noise or severe vibration, and no obvious housing resonance.
  • Measure fan operating current, confirming it is within the rated current range, no overload, and three-phase current balance meets requirements.
  • Use an anemometer to measure airflow velocity at ventilation openings, calculate ventilation volume, and confirm it meets design ventilation requirements. Effective air circulation shall be formed inside the container with air exchange rate ≥ 6 times/hour.
  • Test fan switch control and timer control (if applicable) functions, confirming normal control and no impact during start/stop.
  • Operate continuously for 1 hour, checking fan motor temperature rise and bearing temperature, confirming no abnormal overheating, stable operation, and noise ≤ 55dB(A).

(2) Dehumidification System Commissioning

  • Start the dehumidifier and check whether the equipment starts normally, the compressor and fan operate properly, with no abnormal noise or vibration, and the display operates normally.
  • Set the target humidity to 60%RH, observe equipment operating status, and record humidity data inside the container every 30 minutes. Confirm dehumidification performance is good and humidity can be reduced to the set value within the specified time.
  • Test the automatic humidity control function. The equipment shall automatically stop when humidity reaches the set value and automatically restart after humidity rises by 3%–5%. Start/stop control shall be accurate without frequent cycling.
  • Check the drainage system, confirming condensate drains smoothly without leakage or blockage, and the water tank full alarm function operates normally.
  • Test the defrost function (in low-temperature environments), confirming the equipment can defrost normally without icing faults, and the defrost process does not affect normal operation.
  • Operate continuously for 4 hours, recording equipment operating parameters, confirming stable operation, dehumidification capacity conforming to rated parameters, and uniform humidity inside the container.

6.2.3 Fire Protection System Commissioning

(1) Smoke Alarm System Commissioning

  • Test each smoke detector individually using a dedicated smoke pen to simulate smoke. Check whether the detector triggers an audible/visual alarm within 10 seconds, the alarm indicator flashes normally, and alarm volume ≥ 80dB.
  • Test linkage functions. After alarm triggering, verify whether the actions of the linked audible/visual siren, surveillance system, and access control system (if applicable) conform to the designed logic, with a linkage response time ≤ 3 seconds.
  • Test fault alarm functions by simulating detector faults and line open circuits. Confirm the system can issue fault alarm signals and accurately display the fault location.
  • Test alarm recording functions, confirming alarm time, location, and type can be accurately stored and queried, with record capacity meeting design requirements.

(2) Fire Extinguisher and Automatic Fire Suppression System Commissioning

  • Check fire extinguisher pressure, validity period, and installation position. Confirm the pressure gauge needle is in the green zone, the cylinder is free from rust and deformation, and accessories are complete.
  • For systems configured with automatic fire suppression, simulate fire signals to test the fire suppression device activation function. Confirm timely activation, normal discharge, correct linkage logic, and full coverage of extinguishing agent discharge without dead corners.

6.2.4 Intelligent Monitoring System Commissioning

(1) Temperature and Humidity Monitoring System Commissioning

  • View real-time data from each temperature and humidity sensor, compare with calibrated standard thermohygrometers, and confirm measurement accuracy meets requirements: temperature error ≤ ±0.5°C, humidity error ≤ ±3%RH.
  • Test data refresh frequency, confirming timely data updates without lag or packet loss, and data sampling intervals conform to configuration requirements.
  • Set temperature and humidity upper/lower limits, simulate limit-exceeding environments through humidification and heating, and test audible/visual alarm, SMS alarm, and platform alarm functions. Confirm timely and accurate alarms with complete alarm information.
  • Test historical data storage, query, and export functions, confirming complete data storage, query capability by time and point, and Excel format export support.
  • Test remote monitoring functions by accessing the platform via PC and mobile devices. Confirm normal data synchronization, effective remote parameter configuration, and unified management of multiple devices.

(2) Access Control and Security System Commissioning

  • Test card swipe, password, fingerprint, and other door opening methods. Confirm rapid response, smooth lock release, and effective permission management, with different permission levels corresponding to different operational scopes.
  • Test exit button and fire alarm linkage door opening functions, confirming normal operation and automatic door unlocking during fire conditions.
  • Test access control record storage and query functions, confirming complete records of door opening time, personnel, and method, with filtering and query capability by personnel and time.
  • Commission the video surveillance system, adjusting camera angles and focal lengths. Confirm clear images, no blind spots, good night vision performance, and pixel count conforming to design requirements.
  • Test recording storage, playback, and remote viewing functions. Confirm complete recordings, smooth playback, no lag during seeking, and stable remote access.
  • Test the infrared alarm system, confirming sensitive detection, accurate alarms, low false alarm rate, and convenient arming/disarming operation.

6.3 System Integrated Commissioning

After each subsystem passes standalone commissioning, overall system integrated commissioning shall be conducted to verify the collaborative operation capability and overall performance of all systems, simulating real operating conditions to test overall system compatibility.

6.3.1 Electrical Linkage Commissioning

  • Simulate mains power failure scenarios to test the backup power automatic transfer function. Confirm uninterrupted power supply to critical equipment, transfer time meets requirements, and load equipment does not restart or shut down.
  • Test fire alarm linked power shutdown. After fire alarm triggering, non-fire-fighting power is automatically cut off, and emergency power is automatically engaged to ensure power supply for emergency lighting and fire-fighting equipment.
  • Test the distribution load condition during simultaneous operation of all systems. Measure total current and voltage drop, confirming the distribution system can carry the full load without overload or low voltage, with normal temperature rise of conductors and circuit breakers.
  • Test the surge protection function by simulating surge voltage. Confirm the surge protective device can effectively operate to protect downstream equipment from damage.

6.3.2 Environmental Control Linkage Commissioning

  • Set temperature and humidity linkage logic. The ventilation system, dehumidification system, and temperature/humidity monitoring system shall operate in linkage, automatically starting and stopping equipment based on temperature and humidity inside the container for unattended environmental control.
  • Simulate high-humidity conditions by humidifying the container interior. Verify the logic of automatic dehumidifier startup and ventilation fan linked operation, and whether environmental control performance meets standards.
  • Simulate high-temperature conditions to test the logic and performance of automatic ventilation system startup for cooling. Confirm temperature can be controlled within a reasonable range.
  • Operate continuously for 24 hours, recording the temperature and humidity variation curves inside the container. Confirm environmental parameters can be stably controlled within the set range, fluctuation amplitude meets requirements, and equipment start/stop frequency is reasonable.

6.3.3 Security and Fire Protection Linkage Commissioning

  • Test fire alarm and access control system linkage. After fire alarm triggering, the container door access control shall automatically unlock to facilitate personnel evacuation and rescue entry, while emergency lighting is activated.
  • Test fire alarm and video surveillance linkage. After alarm triggering, the surveillance system shall automatically record, display the alarm area image in a pop-up window, and save video footage before and after the alarm.
  • Test intrusion alarm and surveillance linkage. After infrared alarm triggering, cameras shall automatically pan to the alarm area, start recording, and push alarms to management personnel’s mobile phones.
  • Test security system and platform linkage, confirming all alarm information can be synchronized to the remote management platform with accurate and timely push notifications.

6.3.4 Integrated Commissioning Acceptance Criteria

  • All systems operate normally in coordination, linkage logic is accurate, with no conflicts or false operations
  • Overall operation is stable with no fault alarms for 24 consecutive hours
  • Environmental parameters inside the container are stable within the design range, satisfying material storage requirements
  • Safety protection system linkage is effective with timely emergency response
  • Distribution system load is balanced, power supply is stable, with no abnormal heating or tripping
  • Intelligent system data transmission is stable with complete platform management functions
  • Operating noise conforms to environmental requirements, with no abnormal noise pollution

6.4 Trial Operation

After passing integrated commissioning, the 72-hour continuous trial operation phase shall commence to comprehensively verify the long-term operational stability and reliability of the systems, simulating actual operating conditions to expose potential hidden issues.

6.4.1 Trial Operation Requirements

  • During the trial operation period, all systems shall be fully operational, maintaining normal working status. Simulate actual operating conditions and periodically simulate material access, equipment start/stop, and other operations.
  • Designate personnel for inspection every 2 hours, recording system operating parameters including voltage, current, temperature, humidity, equipment operating status, and alarm conditions. Fill in trial operation records with true and accurate data.
  • Equipment parameters shall not be arbitrarily adjusted during trial operation. If faults occur requiring shutdown for handling, detailed records of fault phenomena, occurrence time, handling process, and handling results shall be made. Trial operation timing shall restart after fault resolution.
  • During trial operation, simulate various extreme operations, including frequent start/stop, full-load operation, and parameter adjustments, to verify system reliability and fault tolerance.

6.4.2 Trial Operation Inspection Items

  • Electrical System: Distribution box temperature, circuit breaker status, voltage and current, grounding conditions, lighting operating status, socket power supply conditions
  • Environmental System: Temperature and humidity values, dehumidifier operating status, fan operating status, drainage conditions, filter cleanliness
  • Security and Fire Protection: Access control status, surveillance images, alarm system status, fire-fighting equipment status, detector operating status
  • Structural Components: Container sealing condition, door opening/closing smoothness, rack stability, any leakage or abnormal noise
  • Intelligent System: Data transmission status, platform online status, alarm function status

6.4.3 Trial Operation Acceptance Determination

  • Continuous 72-hour trial operation without faults, all operating parameters within normal ranges, all functions conforming to design requirements, and material storage environment meeting standards constitutes a pass.
  • Minor issues occurring during trial operation that have been rectified and verified as acceptable, without affecting overall operation, may be judged as passing.
  • Trial operation records shall be organized and archived as one of the core bases for completion acceptance.

Chapter 7 Installation and Commissioning Quality Acceptance Standards

After the material container installation and commissioning is completed and passes trial operation, formal quality acceptance shall be organized. Acceptance shall be jointly conducted by the construction unit, construction organization, and supervision unit (if applicable), strictly in accordance with the standards in this chapter. The container may only be formally delivered after passing acceptance. These standards are developed based on relevant national codes and the container manufacturer’s enterprise standards, comprehensively covering structural, electrical, environmental, safety, and intelligent dimensions.

7.1 Acceptance Basis and Procedure

7.1.1 Acceptance Basis

  • This installation and commissioning manual, product design drawings, technical agreement, and contract requirements
  • GB 50303-2015 Code for Acceptance of Quality of Construction of Building Electrical Engineering
  • GB 50243-2016 Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works
  • GB 50166-2019 Standard for Construction and Acceptance of Fire Alarm System
  • GB 50140-2005 Code for Design of Extinguisher Distribution in Buildings
  • GB/T 1413-2008 Series 1 Freight Containers — Classification, Dimensions and Ratings
  • Relevant national and industry construction acceptance codes and quality evaluation standards

7.1.2 Acceptance Procedure

Acceptance Application: The construction organization shall, upon completion of installation, commissioning, and trial operation, confirm quality compliance and complete documentation, and submit an acceptance application and complete set of completion documents to the construction unit.

Documentation Review: The acceptance team shall first review completion documents, including construction records, commissioning records, trial operation records, equipment certificates of conformity, test reports, qualification documents, etc., confirming the documents are complete, authentic, and standardized.

On-Site Acceptance: The acceptance team shall conduct on-site physical quality inspection, testing and measuring items one by one according to the acceptance checklist, recording acceptance results, and conducting sampling tests on key items.

Issue Rectification: For issues identified during acceptance, a rectification notice shall be issued specifying the rectification period and requirements. The construction organization shall rectify within the specified period and apply for re-inspection after completion.

Acceptance Conclusion: After all items pass acceptance and documents are complete, an acceptance report shall be issued, signed and confirmed by all parties, and the container shall be formally delivered for use.

7.2 Container Structure and Foundation Acceptance

7.2.1 Foundation Acceptance

  • Foundation position, dimensions, and elevation conform to design requirements: axis deviation ≤ 10mm, elevation deviation ±5mm
  • Foundation surface is level with flatness ≤ 3mm/m, drainage slope meets requirements, with no water accumulation or cracks
  • Concrete foundation strength reaches design requirements, with no honeycombing, pitting, cracks, or exposed reinforcement
  • Foundation grounding is reliable, grounding resistance conforms to design requirements, and grounding terminal labels are clear
  • Gravel cushion foundation compaction meets standards, with no settlement or collapse

7.2.2 Container Installation Acceptance

  • Container position is accurate: axis deviation ≤ 10mm, elevation deviation ±5mm
  • Container levelness is good: horizontal and longitudinal levelness deviation ≤ 2mm/m
  • Container is firmly secured, with fastener quantity and specifications conforming to requirements, bolt tightening torque meeting standards, and no looseness
  • Container exterior is intact, without deformation, impact damage, paint peeling, or rust. Coating is complete, and scratch depth does not exceed coating thickness
  • Container door opens and closes smoothly, locks are reliable, sealing strips are intact with uniform compression, without cracking or adhesive failure
  • Container sealing and waterproofing pass: 30-minute water spray test without leakage, no water infiltration traces in the interior
  • Assembled containers have firm connections, intact sealing, misalignment deviation ≤ 3mm, and passage doors open and close smoothly

7.2.3 Rack System Acceptance

  • Rack layout conforms to design, passageway widths meet requirements: main passageway ≥ 1000mm, secondary passageway ≥ 800mm
  • Racks are firmly installed with verticality ≤ 3mm/m and beam levelness ≤ 2mm/m
  • Shelf spacing is uniform with deviation ≤ 5mm, shelf boards are level without warping or deformation, fitting tightly against beams
  • All connectors are properly tightened, safety pins are complete without missing items
  • Rack surfaces are intact without paint peeling, scratches, or deformation. Columns and beams are free from cracks
  • Load-bearing tests pass: no obvious deformation or abnormal noise under full load, deflection ≤ 1/200

7.3 Electrical System Acceptance

7.3.1 Power Distribution System Acceptance

  • Distribution box installation is standardized, components are complete, parameters conform to design, and labels are clear
  • Cable routing is neat, labels are clear, connections are firm, and insulation resistance meets standards
  • Protection devices at each level are correctly set, operate reliably, and residual current protection functions normally
  • Phase sequence is correct, voltage is stable, and voltage drop during full-load operation is within the allowable range
  • Box interior is clean, wiring is aesthetically pleasing, grounding is reliable, grounding resistance ≤ 4Ω
  • Surge protection devices are complete, correctly wired, and conform to lightning protection code requirements

7.3.2 Lighting and Socket Acceptance

  • Lighting fixtures are neatly installed and operate normally, average illuminance ≥ 300lx, illumination is uniform
  • Emergency lighting functions are normal, duration ≥ 90 minutes, evacuation illuminance meets standards
  • Sockets are installed to specification, correctly wired, reliably grounded, and protective shutters are effective
  • Switches operate flexibly and correspond accurately, installation heights are uniform with deviation ≤ 5mm

7.4 Environmental Control System Acceptance

7.4.1 Ventilation System Acceptance

  • Fans are firmly installed, operate stably, without abnormal noise or vibration
  • Air volume and velocity conform to design requirements, ventilation air exchange rate meets standards
  • Rainproof louvers and insect screens are complete, intact, and firmly installed
  • Control functions operate normally, start/stop is flexible, and operating current is within rated range
  • Noise meets requirements with operating noise ≤ 55dB(A)

7.4.2 Dehumidification System Acceptance

  • Dehumidifier is stably installed, drainage is smooth without leakage, and drainage piping is reasonably arranged
  • Dehumidification capacity meets standards, capable of controlling humidity within the set range within the specified time
  • Automatic humidity control function is accurate, start/stop operates normally, without frequent cycling
  • Operating noise meets requirements, without abnormal noise or vibration
  • All equipment protection functions operate normally, operation is stable, and compressor temperature rise is normal

7.5 Safety Protection System Acceptance

7.5.1 Fire Protection System Acceptance

  • Smoke detectors are installed to specification, detection is sensitive, response time ≤ 10 seconds
  • Fire extinguishers are configured to code with quantity, specification, and position meeting requirements, intact and effective
  • Automatic fire suppression system linkage operates normally, activation is reliable, and discharge range provides full coverage
  • Fire protection wiring is routed to specification, clearly labeled, and fire resistance rating meets requirements
  • Linkage logic is correct, response is timely, and fault alarm functions operate normally

7.5.2 Access Control and Security Acceptance

  • Access control system functions are complete, door release is smooth, and permission management is effective
  • Door opening records are complete, query is convenient, and storage capacity meets standards
  • Surveillance images are clear, coverage is comprehensive without blind spots, and recording storage is normal
  • Infrared alarms are accurate with low false alarm rate, and linkage functions operate normally
  • Equipment is firmly installed, wiring is to specification, and grounding is reliable

7.6 Intelligent Monitoring System Acceptance

  • Temperature and humidity monitoring accuracy meets requirements, data is accurate, and errors are within the allowable range
  • Data transmission is stable, remote monitoring functions are complete, and platform access is smooth
  • Alarm functions are complete, and multi-channel alarm push notifications are timely and accurate
  • Historical data storage is complete and traceable, supporting export and analysis
  • Management platform operation is convenient, functions meet usage requirements, and multi-device management is supported

7.7 Completion Documentation Acceptance

Complete completion documentation shall be submitted for acceptance, primarily including:

  • Product certificate of conformity, factory test reports, equipment instruction manuals
  • Foundation construction records, concealed works acceptance records, foundation test reports
  • Container installation records, leveling and fixing records, sealing and waterproofing inspection records
  • Installation construction records and concealed works acceptance records for each system
  • System commissioning records, standalone commissioning reports, integrated commissioning reports
  • 72-hour continuous trial operation records
  • Equipment lists, accessory lists, and spare parts lists
  • Construction organization qualification documents, special operation personnel qualification certificates
  • Design change approvals, engineering consultation records
  • Sub-item works acceptance records, completion acceptance reports

Documents shall be compiled into volumes, with complete signatures and seals, authentic and complete, traceable, and prepared in multiple copies with separate archiving by the construction unit and construction organization.

Chapter 8 Daily Use and Operating Procedures

To ensure the long-term stable operation of the emergency supply material container, standardize daily use and operation, and prevent equipment damage or safety accidents caused by improper operation, this chapter establishes operating procedures that management personnel and operators of the using unit shall strictly follow. Standardized operation not only ensures the safe use of the material storage container but also effectively extends equipment service life and reduces operation and maintenance costs.

Chapter 8 Personnel Management and Operational Specifications

8.1 Personnel Management Requirements

8.1.1 Operator Qualifications

Operators must undergo professional training and be familiar with the working principles, operating methods, and safety precautions of each system of the material container. They may only commence operations after passing the assessment.

Electrical operations and equipment maintenance must be performed by certified electricians or professional technical personnel. It is strictly prohibited for uncertified personnel to disassemble, assemble, or repair electrical equipment without authorization.

Management personnel must master material storage management requirements and basic system operations, be responsible for daily inspections and material management, and master basic fault diagnosis and emergency handling methods.

8.1.2 Job Responsibilities

Administrator: Responsible for the daily management of the material storage container, material inbound/outbound registration, environmental monitoring, daily inspections, and issue reporting; regularly verifies material ledgers to ensure accounts match physical inventory.

Operations and Maintenance Personnel: Responsible for regular equipment maintenance, fault troubleshooting, inspection and repair, ensuring normal system operation, maintaining maintenance records, and developing maintenance plans.

Safety Officer: Responsible for container safety management, implementing fire prevention, theft prevention, and flood prevention safety measures; conducting regular safety inspections, eliminating safety hazards, and organizing emergency drills.

8.2 Container and Door Operation Specifications

8.2.1 Container Door Opening and Closing Operations

Opening the door: First unlock the door lock, slowly push the door open, and secure the door on the door catch to prevent free swinging and collision. When opening the door in windy weather, protective measures must be taken, with designated personnel holding the door to prevent it from being blown and causing injury.

Closing the door: Slowly close the door, confirm the door is fully seated, lock all locking points, check that the sealing gasket is properly seated, confirm all locks are fully engaged, and ensure the door has no looseness.

Precautions: Violent opening/closing of the door is strictly prohibited. Hanging heavy objects on the door is strictly prohibited. Regularly inspect door hinges and locks, apply lubricating oil in a timely manner, and maintain smooth operation. After the door is opened, it must be firmly secured to prevent wind from closing it and causing injury. When leaving for extended periods, the door must be locked with anti-theft measures in place.

8.2.2 Material Storage and Retrieval Specifications

Material storage must follow the principle of “classified storage, light items on top, heavy items on bottom, neat and orderly,” stored by layer and zone on shelves with clear material identification labels for easy locating and retrieval.

Shelf load capacity must comply with rated requirements. Overloading is strictly prohibited. Loads must be evenly distributed on each level to avoid concentrated stress. Heavy materials must be placed on the bottom levels, and light materials on the upper levels.

Handle materials gently during storage and retrieval. Throwing, tossing, or impacting shelves and container walls is strictly prohibited. Climbing on shelves to retrieve items is strictly prohibited. Use a ladder for retrieving items from high positions.

When storing/retrieving large materials, use dedicated handling equipment with designated personnel directing the operation to avoid collision with the container body, equipment, and shelves, preventing damage to equipment and materials.

After material storage/retrieval is completed, promptly tidy the materials inside the container, maintain cleanliness, turn off lighting and unnecessary equipment, and lock the container door.

8.2.3 Usage Environment Requirements

It is strictly prohibited to store flammable, explosive, toxic, hazardous, or corrosive items in general-purpose emergency material storage containers. Special material containers must store corresponding materials as per design requirements. Use beyond the designed scope is strictly prohibited.

Keep the container interior clean and dry. Regularly remove debris. Smoking and open flame operations inside the container are strictly prohibited. Unauthorized electrical wiring is strictly prohibited. Piling debris that blocks ventilation openings and equipment is strictly prohibited.

Ventilation openings, dehumidifier air intakes, and return air openings must not be blocked by stacked materials. Maintain smooth air circulation to ensure effective environmental control.

Regularly clean dust and debris inside the container, keeping equipment and shelves clean to prevent dust accumulation from affecting equipment operation and material cleanliness.

8.3 Electrical System Operation Specifications

8.3.1 Power Distribution Operations

Closing sequence: First close the main switch, then close each branch circuit switch. Opening sequence: First open each branch circuit switch, then open the main switch. Pulling the main switch under heavy load is strictly prohibited to avoid arc damage to the switch.

When operating electrical switches, wear insulating gloves and stand to the side of the switch, avoiding facing the switch directly to prevent arc injury.

If a trip occurs, the cause must first be identified and the fault cleared before reclosing. Forced reclosure is strictly prohibited. Arbitrarily adjusting circuit breaker settings is strictly prohibited. Frequent tripping requires contacting professional personnel for troubleshooting.

For containers that have been out of service for extended periods, the electrical system must be fully inspected before recommissioning. Power may only be applied after insulation testing passes. After energizing, run with no load for a period of time before connecting loads.

8.3.2 Lighting and Socket Usage

Turn on lighting fixtures as needed and turn them off promptly when unoccupied to save electricity and extend lamp life. The emergency lighting circuit must never be switched off arbitrarily and must remain in a continuously powered state.

When using sockets, ensure plugs are firmly inserted. Overloading sockets is strictly prohibited. Using damaged plugs and cables is strictly prohibited. High-power equipment must use dedicated sockets.

Connecting excessive high-power equipment to a single socket is strictly prohibited to avoid branch circuit overload tripping. Unauthorized use of extension strips for multi-outlet expansion is strictly prohibited.

8.4 Environmental Control System Operation Specifications

8.4.1 Ventilation System Operations

Reasonably operate the ventilation system based on season and weather conditions to maintain fresh air inside the container. During spring and autumn when humidity is suitable, natural ventilation may be used; during high-humidity seasons, operate mechanical ventilation in conjunction with dehumidification.

Ventilation fans should be rotated in operation to avoid prolonged single-unit operation, extending equipment life. Regularly inspect ventilation opening filters and clean dust and debris promptly to maintain smooth ventilation.

During rainy and dusty weather, close ventilation openings and ventilation fans, and close rain-proof louvers to prevent rain and dust from entering the container, contaminating materials, and damaging equipment. Promptly resume ventilation and dehumidification after weather improves.

8.4.2 Dehumidification System Operations

Set reasonable target humidity based on material storage humidity requirements. For general emergency materials, a setting of 50%-65% RH is recommended. Special materials should be adjusted according to their storage requirements.

During prolonged dehumidifier operation, regularly check drainage conditions to prevent drain pipe blockage and overflow. Regularly clean the intake air filter to maintain dehumidification efficiency, generally once every half month.

In low-temperature winter environments, pay attention to equipment freeze protection. If the unit is to be out of service for extended periods, drain accumulated water from the equipment to prevent heat exchanger freeze cracking.

If the dehumidifier triggers a fault alarm, stop the unit promptly for troubleshooting. Operation with existing faults is prohibited. Do not force-start the unit before the fault is resolved.

8.5 Smart and Security System Operation Specifications

8.5.1 Temperature and Humidity Monitoring System

Management personnel must review temperature and humidity data daily to confirm environmental parameters are within normal ranges. Promptly handle over-limit alarms, analyze the cause of over-limit conditions, and take corresponding measures.

Do not arbitrarily change system parameters or remove sensors. Parameter adjustments require professional personnel and must be documented with change records.

Regularly cross-check monitoring data against mechanical thermohygrometers to ensure data accuracy and reliability. Calibrate sensors promptly if deviation is excessive.

8.5.2 Access Control and Security System

Access cards are for individual use only and must not be lent to others. Promptly revoke permissions when personnel leave. Regularly review the permission list and remove invalid permissions.

Regularly review surveillance footage and access control records. Promptly report and handle any abnormalities. Footage records must not be arbitrarily deleted and must be retained per the specified retention period.

Follow proper arming/disarming procedures daily. Conduct regular security system tests to verify alarm functionality and ensure system effectiveness.

Cameras and detectors must be kept clean and unobstructed. Regularly wipe dust from lens and probe surfaces to ensure detection and recording performance.

Chapter 9 Maintenance and Repair Procedures

Regular maintenance is key to ensuring the long-term stable operation of the material container and extending its service life. The user unit must establish a comprehensive maintenance system and carry out daily maintenance, regular inspections, and annual overhaul in accordance with the procedures in this chapter. A professional maintenance system can effectively reduce equipment failure rates, ensuring that emergency support containers are always in a ready-to-use state to meet emergency support needs.

9.1 Maintenance Classification and Cycles

Maintenance Level Cycle Main Content Personnel
Daily Inspection Daily/Weekly Visual inspection, status check, simple cleaning On-site Administrator
Monthly Maintenance Monthly Equipment cleaning, functional checks, tightening and adjustment O&M Personnel
Quarterly Inspection Quarterly Performance testing, hazard inspection, consumable parts check Professional Technical Personnel
Annual Overhaul Annually Comprehensive inspection, deep maintenance, consumable replacement, performance calibration Factory Technical Personnel or Professional Team

9.2 Daily Inspection and Monthly Maintenance

9.2.1 Daily Inspection Content

Daily inspections are conducted by the administrator, focusing on the following:

Container body appearance: Check for deformation, rust, leakage; check door and locks for integrity; check sealing condition; check surrounding drainage for unobstructed flow.

Environmental status: View temperature and humidity display values, confirm they are within normal range; check for unusual odors, abnormal sounds, water accumulation; check materials for signs of moisture.

Equipment status: Check dehumidifier, fans, and lighting for normal operation; check for alarms, abnormal sounds, and normal display panel operation.

Safety status: Check fire equipment for integrity and correct pressure; check security system for normal operation; check for safety hazards.

Fill out inspection records. Report any abnormalities promptly. Minor issues that can be handled on-site should be addressed immediately.

Additional weekly inspection items:

  • Check ventilation opening filters for blockage; clean dust and debris promptly.
  • Check dehumidifier water tank level or drain pipe condition; clean accumulated water.
  • Check shelves for looseness or deformation; verify material storage compliance and check for overloading.
  • Check distribution box for unusual odors or abnormal heating; verify switch positions.

9.2.2 Monthly Maintenance Content

Monthly comprehensive maintenance is performed by O&M personnel:

Container Structure Maintenance

  • Clean dust and debris from the container surface; check anti-corrosion coating for damage or peeling; treat small areas of paint loss with rust removal and touch-up paint.
  • Check door hinges and locks; apply lubricating oil to maintain smooth operation; tighten loose screws; replace worn components.
  • Check sealing gaskets; clean surface dust; apply silicone grease for preservation; replace gaskets that show aging or cracking.
  • Check the container bottom for rust and water accumulation; clean surrounding debris; maintain unobstructed drainage.

Electrical System Maintenance

  • Clean dust from the distribution box and equipment surfaces; tighten loose terminal connections; check wiring for aging, damage, or signs of heating.
  • Test residual current circuit breaker (RCCB) function by pressing the test button to verify tripping reliability; replace defective units promptly.
  • Clean lighting fixtures; check lamp wiring; replace damaged light sources and ballasts.
  • Check the grounding system; test ground resistance; ensure reliable grounding; tighten ground terminals.

Environmental System Maintenance

  • Clean ventilation fan blades and housings; check fan mounting bolts; tighten loose components; apply grease to bearings.
  • Clean the dehumidifier intake filter and evaporator dust; check drain piping; clear blockages; clean the condensate tray.
  • Check dehumidifier refrigerant pressure; replenish refrigerant if low; check compressor operating status and temperature rise.

Safety and Smart System Maintenance

  • Clean dust from smoke detectors and sensor surfaces; test alarm functions to ensure detection sensitivity.
  • Check fire extinguisher pressure; confirm within validity period; replace units approaching expiry in advance.
  • Clean camera lenses; adjust camera angles; check video recording storage; clear outdated recordings to free storage space.
  • Test access control system functions; clean card reader surfaces; check electric lock operation; lubricate the latch bolt.
  • Back up monitoring data and system configurations; check system operation logs; investigate abnormal records.

9.3 Quarterly Inspection Content

Quarterly deep inspections are performed by professional technical personnel to identify potential hazards and prevent failures:

  • Conduct comprehensive insulation testing and ground resistance testing on the electrical system; investigate wiring aging and poor contact hazards; tighten all terminal connections.
  • Perform performance testing on ventilation and dehumidification equipment; measure airflow and dehumidification capacity; evaluate performance degradation; conduct targeted maintenance and clean heat exchangers.
  • Perform load-bearing checks on shelves; tighten all connecting bolts; check posts and beams for deformation or cracks; correct minor deformation.
  • Conduct comprehensive functional testing of the fire protection system; replace consumables approaching expiry; calibrate detector sensitivity.
  • Conduct comprehensive diagnostics on the smart system; upgrade system firmware; optimize operating parameters; investigate communication fault hazards.
  • Check container anti-corrosion condition; perform rust removal and touch-up painting on corroded areas; assess overall anti-corrosion status.
  • Check container sealing and waterproofing performance; focus on seam joints, penetration points, and container doors; promptly repair any leaks found; conduct water spray tests for verification.

9.4 Annual Overhaul Content

An annual comprehensive overhaul is performed by the factory or a professional team to ensure long-term reliable operation and restore equipment performance:

Container body comprehensive inspection: Fully inspect container structural strength, weld condition, and anti-corrosion status; assess the overall anti-corrosion coating; perform full refurbishment and anti-corrosion treatment if necessary; correct minor container deformation.

Electrical system overhaul: Comprehensively inspect wiring aging; replace aged cables; verify circuit breaker and protection device performance; replace degraded electrical components; fully tighten all terminal connections; optimize distribution circuits and organize wiring.

Equipment overhaul: Disassemble and service power equipment such as dehumidifiers and fans; replace wearing parts including bearings and seals; clean compressors and evaporators; replenish refrigerant and lubricating oil; restore rated equipment performance.

Safety system verification: Fully verify fire protection and security system performance; replace expired consumables and wearing parts; calibrate sensor accuracy; ensure systems are reliable and effective and comply with fire protection code requirements.

Smart system upgrade: Upgrade monitoring platform and terminal firmware; optimize system functions; back up historical data; service communication modules; ensure stable data transmission; expand system functions.

Overall performance testing: After all maintenance is completed, conduct full-system integrated testing and performance verification to confirm overall performance meets factory standards; issue an annual inspection report.

9.5 Wearing Parts Replacement and Spare Parts

9.5.1 Common Wearing Parts and Replacement Cycles

Wearing Part Recommended Replacement Cycle Remarks
Air filter 3–6 months Adjust based on ambient dust conditions; shorten cycle in dusty areas
Container door sealing gasket 3–5 years Replace promptly if aged, cracked, or elasticity degraded
Lighting source 2–3 years Replace promptly upon failure; batch replacement is more efficient
Dehumidifier compressor oil 3 years Check and top up regularly; replace during annual overhaul
Fire extinguisher agent Per expiry date Replace/refill promptly upon expiry; dry powder extinguishers require agent replacement every 5 years
Battery (UPS/emergency light) 3–5 years Replace promptly when capacity drops below 80%
Fan bearing 5 years Replace promptly upon abnormal noise or wear
Access control card reader 5–8 years Replace when card reading sensitivity degrades

9.5.2 Recommended Spare Parts

To support daily maintenance and emergency repairs, the following spare parts are recommended to avoid equipment downtime due to parts waiting:

Electrical: Spare circuit breakers, sockets, switches, LED lamp beads, fuses, terminal blocks

Equipment: Fan start capacitors, dehumidifier filters, temperature/humidity sensors, access control card readers

Structural: Door lock components, sealing gaskets, bolts and nuts, anti-corrosion primer and topcoat

Tools: Common electrician tools, test instruments, cleaning tools

9.6 Long-Term Out-of-Service Maintenance

If the emergency support container is to be out of service for an extended period, proper preservation maintenance must be performed to prevent moisture damage, rust, and aging:

  • Remove all materials from the container; comprehensively clean the interior; wipe dry any water stains; maintain dryness.
  • Disconnect the main power supply; unplug all equipment; apply moisture protection to electrical equipment; cover with dust covers.
  • Close all ventilation openings and louvers; place sufficient desiccant inside the container; regularly inspect and replace desiccant to prevent moisture damage.
  • Lock the container door; implement anti-theft measures; open the container monthly for ventilation inspection, checking for moisture and rust; ventilation time should be no less than 2 hours.
  • Before recommissioning after more than 6 months of storage, conduct a comprehensive inspection and insulation test; clean equipment; confirm no issues before applying power; run with no load before connecting loads.

Chapter 10 Common Fault Diagnosis and Solutions

During use, the material container may experience various faults due to environmental factors, improper operation, equipment aging, etc. This chapter summarizes common fault phenomena, possible causes, and solutions for the reference of O&M personnel during troubleshooting. For complex faults or issues that cannot be diagnosed, promptly contact the material container manufacturer’s technical support. Do not blindly disassemble or repair equipment to avoid secondary damage.

10.1 Common Electrical System Faults

10.1.1 Main Switch Tripping

Possible causes:

  • Short circuit in downstream wiring or equipment; insulation damage causing line-to-neutral contact
  • Multiple high-power devices starting simultaneously, causing excessive inrush current
  • Equipment or wiring leakage, triggering residual current protection device
  • Switch malfunction; tripping mechanism damaged; false tripping

Solutions:

  • Open all branch circuit switches, close them one by one to isolate the fault circuit; after power-off, use a multimeter to inspect wiring and equipment; clear the short circuit point; repair damaged insulation.
  • Adopt staggered startup; start equipment sequentially to avoid simultaneous startup of multiple high-power devices, reducing inrush current.
  • Check insulation condition of each piece of equipment; identify leakage points; reset the RCCB after repair.
  • Replace the faulty circuit breaker with a properly rated, quality-certified product.

10.1.2 Lighting Not Working

Possible causes:

  • Lighting branch circuit breaker tripped; circuit overload or short circuit
  • Fixture damaged; light source burned out; driver power supply failure
  • Switch malfunction; poor contact at contacts
  • Open circuit in wiring; loose or disconnected connections

Solutions:

  • Check the lighting branch circuit breaker in the distribution box; restore after identifying the cause.
  • Replace damaged fixtures, light sources, or driver power supplies.
  • Repair or replace the lighting switch; dress contacts or replace entirely.
  • Check wiring connections; tighten loose terminals; locate and repair open circuit points.

10.1.3 Socket Has No Power

Possible causes:

  • Socket circuit tripped; leakage or overload triggered protection
  • Socket wiring loose or disconnected; internal contact plates oxidized
  • Internal socket contact plates making poor contact; spring tension degraded
  • Open circuit in upstream wiring; intermediate connection point disconnected

Solutions:

  • Check the corresponding branch circuit breaker; reset after identifying leakage or overload causes.
  • After power-off, open the socket faceplate; tighten terminal connections; treat oxidized areas.
  • Replace the damaged socket with a qualified safety-type socket.
  • Inspect upstream wiring; locate and reconnect the break point.

10.1.4 Emergency Lighting Not Working

Possible causes:

  • Battery discharged or aged/damaged; insufficient capacity
  • Emergency light control circuit fault; switching mechanism failed
  • Charging circuit fault; battery not charged over extended period

Solutions:

  • Charge for 12 hours and test; if still non-functional, replace with a battery of the same specification.
  • Repair the emergency light control circuit or replace the emergency light fixture.
  • Check the charging circuit and power supply; restore power.

10.2 Common Ventilation and Dehumidification System Faults

10.2.1 Ventilation Fan Does Not Start

Possible causes:

  • Power not connected; switch fault; open circuit in wiring
  • Start capacitor damaged; capacitance degraded
  • Motor burned out; winding open circuit or turn-to-turn short circuit
  • Bearing seized; blades blocked by debris

Solutions:

  • Check power supply and switch; restore power; replace faulty switch; repair open circuit wiring.
  • Replace with a start capacitor of the same specification, ensuring capacitance and voltage rating match.
  • Repair or replace the motor; preferably replace with the same model.
  • Clear blocking debris; service bearings; apply grease; replace bearings if severely worn.

10.2.2 Fan Operating with Abnormal Noise and Excessive Vibration

Possible causes:

  • Fan blades accumulated dust or deformed; dynamic balance imbalance
  • Mounting bolts loose; body vibration
  • Bearing wear or lack of lubrication; abnormal operating noise
  • Fan rubbing against housing or duct

Solutions:

  • Clean blade dust; correct deformed blades; redo dynamic balancing.
  • Tighten all mounting bolts; add lock washers.
  • Replace worn bearings; apply high-temperature grease.
  • Adjust fan position; correct duct alignment; eliminate friction.

10.2.3 Dehumidifier Not Dehumidifying

Possible causes:

  • Ambient temperature too low; evaporator frosting; heat exchange ineffective
  • Intake filter blocked; insufficient airflow; poor air circulation
  • Refrigerant leakage; compressor fault; refrigeration cycle failure
  • Humidity sensor fault; inaccurate detection; misreading humidity
  • Fan not rotating; air cannot circulate through the evaporator

Solutions:

  • Enable auto-defrost function; use auxiliary heating equipment in low-temperature environments; dehumidification efficiency drops significantly when ambient temperature is below 5°C.
  • Clean the intake filter; maintain unobstructed intake; clean filters regularly.
  • Contact professionals for leak detection and repair; recharge refrigerant; repair or replace the compressor.
  • Calibrate or replace the humidity sensor.
  • Service the fan circuit and motor; restore normal fan operation.

10.2.4 Dehumidifier Water Leakage

Possible causes:

  • Drain pipe blocked or kinked; poor drainage
  • Water tank displaced or overflowing; full-tank switch failure
  • Evaporator condensate tray blocked; water overflowing
  • Unit tilted; condensate tray water level offset

Solutions:

  • Clear the drain pipe; straighten the tubing; ensure drainage slope ≥5‰.
  • Reposition the water tank; clear the drain outlet; repair or replace the full-tank switch.
  • Clean debris and dirt from the condensate tray and drain holes.
  • Adjust the dehumidifier leveling feet; keep the unit level.

10.3 Common Fire Protection and Security System Faults

10.3.1 Smoke Detector False Alarm

Possible causes:

  • Excessive dust or moisture inside container entering the detection chamber
  • Insects entering the detector, blocking the optical chamber
  • Detector aging; sensitivity drift
  • Nearby steam, oil smoke, or dust interference

Solutions:

  • Enable ventilation, dust removal, and dehumidification; improve container environment; clean detector surfaces.
  • Clean insects from inside the detector; check insect screen integrity.
  • Calibrate sensitivity or replace with a new detector.
  • Adjust installation position; move away from interference sources.

10.3.2 Access Card Does Not Open Door

Possible causes:

  • Access card invalid, unauthorized, or demagnetized
  • Card reader fault, dirty surface, metal obstruction
  • Electric lock fault; latch bolt seized; insufficient power supply
  • Access control power supply fault; abnormal output; low voltage
  • Open circuit or loose wiring; signal transmission interrupted

Solutions:

  • Reauthorize the card or issue a new card.
  • Clean the card reader surface; remove metal obstructions; repair or replace the card reader.
  • Service the electric lock; clean the latch bolt; adjust alignment; check supply voltage.
  • Check the access control power supply output; replace the faulty power supply.
  • Trace wiring; tighten terminal connections; repair break points.

10.3.3 No Video on Monitor

Possible causes:

  • Camera power supply fault; power interrupted
  • Network cable disconnected; RJ45 connector damaged; network interruption
  • Camera hardware fault; camera module damaged
  • Recorder channel fault; IP conflict; device offline

Solutions:

  • Check camera power supply wiring and power source; restore power.
  • Repair network cable; re-terminate RJ45 connector; test circuit continuity.
  • Repair or replace the camera.
  • Adjust camera IP address; troubleshoot recorder channel faults; re-add the device.

10.4 Common Smart Monitoring System Faults

10.4.1 Abnormal Temperature/Humidity Data

Possible causes:

  • Sensor probe dirty or dust-accumulated, affecting detection accuracy
  • Sensor wiring loose; poor contact
  • Data acquisition terminal fault; abnormal data processing
  • Nearby heat source or cold source interference; readings deviating from actual environment

Solutions:

  • Clean the sensor probe; avoid touching the sensing element directly with hands.
  • Tighten terminal connections to ensure good contact.
  • Repair or replace the acquisition terminal.
  • Adjust installation position; avoid air conditioner outlets, lighting fixtures, and other interference sources.

10.4.2 Remote Platform Inaccessible

Possible causes:

  • On-site network fault or poor signal; device offline
  • Communication module fault; SIM card arrears or damaged
  • Platform server fault; under maintenance or upgrade
  • Device powered off; not reconnected after reboot

Solutions:

  • Check network and signal; install a signal amplifier or switch network method.
  • Check SIM card status; top up or replace; service the communication module.
  • Contact platform O&M personnel to troubleshoot server status.
  • Check device power and network status; restart the device and wait for reconnection.

10.4.3 Alarm Function Failure

Possible causes:

  • Alarm parameter settings incorrect; thresholds set too high or too low
  • Audible/visual alarm device damaged; circuit disconnected
  • Linkage circuit fault; signal cannot be transmitted
  • Notification number set incorrectly; SMS push failed

Solutions:

  • Reset correct alarm thresholds and linkage logic.
  • Replace the audible/visual alarm horn; repair the alarm circuit.
  • Trace the linkage circuit; repair fault points.
  • Verify and reset alarm notification numbers; confirm SMS service is functional.

10.5 Common Container Structure Issues

10.5.1 Container Leakage

Possible causes:

  • Sealing gasket aged, damaged, or insufficient compression
  • Weld cracks, loose rivets, gaps formed
  • Seal failure at penetration points; sealant layer cracked or detached
  • Joint seam sealant detached; waterproof membrane damaged

Solutions:

  • Replace aged sealing gaskets; adjust door compression to increase gasket compression.
  • Re-weld cracked welds; tighten loose rivets; grind and apply sealant.
  • Remove old sealant; reapply neutral silicone weather-resistant sealant; install rain shields.
  • Clean joint seams; refill with foam and sealant; repair waterproof membrane.

10.5.2 Container Door Sticking or Difficult to Operate

Possible causes:

  • Door hinges lack lubrication or rusted; high rotational resistance
  • Container tilted; door misaligned; latch bolt and striker plate misaligned
  • Lock deformed or sticking; latch bolt does not extend smoothly
  • Sealing gasket too thick or displaced, increasing closing resistance

Solutions:

  • Clean hinge rust; apply lubricating oil; cycle the door open/closed to break in.
  • Adjust container leveling; correct door position; realign the lock.
  • Repair or replace the lock; adjust latch bolt position; lubricate the latch bolt.
  • Adjust gasket position; replace with correctly sized gasket.

10.5.3 Shelf Sway or Deformation

Possible causes:

  • Shelf overloaded; load exceeds rated capacity
  • Connecting bolts loose; overall structure unstable
  • Uneven floor; shelf posts suspended; uneven load distribution
  • Impact from materials causing post and beam deformation

Solutions:

  • Rearrange material storage; remove overloaded portions; distribute loads evenly.
  • Tighten all connecting bolts; install safety pins.
  • Adjust shelf feet; shim suspended areas; ensure four-point even load distribution.
  • Replace severely deformed components; prohibit continued heavy-load use of deformed shelves.

Chapter 11 Safety Operations and Emergency Handling

Safety is the foremost principle in the use and maintenance of emergency support material containers. All operations must strictly comply with safety regulations and implement safety protective measures. At the same time, comprehensive emergency plans must be developed to ensure rapid response to emergencies, minimizing losses to the greatest extent possible. This chapter specifies safety operation requirements and emergency handling procedures for various incidents, applicable to all personnel who come into contact with the material container.

11.1 General Safety Operation Principles

All operations must strictly comply with safety operating procedures, adhering to the principle of “Safety First, Prevention Oriented, Comprehensive Management.” Commanding in violation of regulations, operating in violation of regulations, and violating labor discipline are strictly prohibited.

Personnel entering the emergency support container must wear appropriate personal protective equipment. Safety harnesses are required for work at height, insulating shoes for electrical work, and protective gloves for material handling operations.

Smoking and open flame operations inside the container are strictly prohibited. If hot work is required, a hot work permit must be obtained, fire prevention measures implemented, fire extinguishing equipment available, dedicated personnel assigned for monitoring, and all ignition sources cleared after completion.

Unauthorized electrical wiring is strictly prohibited. Arbitrarily changing electrical system and equipment parameters is strictly prohibited. Overloading electrical circuits is strictly prohibited. Use of non-compliant electrical equipment is strictly prohibited.

Conduct regular safety training and emergency drills to enhance operator safety awareness and emergency response capabilities. At least one fire emergency drill must be conducted annually.

11.2 Key Operation Safety Specifications

11.2.1 Work at Height Safety

All work at a falling height of 2m or more above the reference plane constitutes work at height. Safety harnesses must be worn, and a reliable work platform must be erected. Climbing shelves or the container body as support for work at height is strictly prohibited.

Tools for work at height must be placed in tool bags. Throwing tools or materials from height is strictly prohibited. Small tools must be attached with safety lanyards to prevent falling and causing injury.

Set up a warning zone below work-at-height areas, hang warning signs, prohibit personnel passage, and assign personnel for monitoring.

Outdoor work at height is prohibited during rain and windy weather (Beaufort scale 6 and above). Anti-slip measures must be implemented during winter operations.

11.2.2 Electrical Work Safety

Electrical work must be performed by certified electricians. The procedures of power-off, voltage verification, tagging, and locking must be strictly enforced. Live work is strictly prohibited. Special circumstances requiring live work must have dedicated safety measures developed.

Before work, confirm the power supply is disconnected. Use a voltage tester to verify zero voltage before proceeding. Hang a “DO NOT CLOSE — WORK IN PROGRESS” warning sign on the distribution box.

Use insulated tools and wear insulating protective equipment. Work performed by a single person requires a second person on standby. Single-person hazardous electrical work is strictly prohibited.

After work completion, account for all tools, confirm no foreign objects remain in the distribution box, then close the circuit to energize. Test for normal function before leaving.

11.2.3 Lifting and Handling Safety

Material lifting and handling must be directed by designated personnel. Lifting equipment and slings must meet load requirements. Overloading lifts is strictly prohibited.

During lifting operations, no personnel are permitted beneath the suspended load. The signal person must stand in a safe position with good visibility, using clear and uniform signals.

When carrying heavy materials, assess capacity realistically. Multiple-person handling requires unified command and coordinated movements to prevent crushing and pinching injuries.

Inspect hydraulic pallet jacks and hand trucks before use. Push smoothly, avoid sharp turns and sudden braking to prevent tipping.

11.3 Emergency Response Plans

11.3.1 Fire Emergency Response

Upon discovering a fire, immediately press the manual alarm button, call for nearby personnel to evacuate, call 119 without delay, and simultaneously report to the unit supervisor.

Initial fire suppression: Immediately cut off the main power supply inside the container, use the nearest fire extinguisher to fight the fire. Stand upwind, aim at the base of the flame, and protect your own safety.

If the fire grows beyond control, immediately evacuate to a safe area, close the container door to slow fire spread, and wait for fire department rescue. Never blindly return to the container to salvage materials.

After fire suppression, comprehensively check for remaining fire to prevent reignition. Protect the incident scene and cooperate with relevant authorities in the incident investigation.

Note: Electrical fires must never be fought with water. Dry powder or COâ‚‚ extinguishers must be used. Fires involving special materials must be fought according to the specific material characteristics.

11.3.2 Electric Shock Emergency Response

If someone is electrocuted, immediately cut off the nearest power source, or use a dry insulating wooden stick or bamboo pole to separate the wire from the victim. Never pull the victim with bare hands to prevent the rescuer from also being electrocuted.

After the victim is separated from the power source, move them to a well-ventilated flat area, loosen the collar, check consciousness and breathing. If breathing and heartbeat have stopped, immediately perform CPR and call 120 for emergency medical services.

Protect the incident scene, report to relevant departments, investigate the cause of the electric shock, implement corrective measures, and prevent recurrence of similar incidents.

11.3.3 Material Moisture Damage and Mold Emergency

If high humidity inside the container or material moisture damage is detected, immediately activate the dehumidifier and ventilation system to accelerate moisture removal, and investigate the cause of the humidity rise.

Transfer moisture-affected materials to a dry area for classified handling. Items that can be air-dried should be moved for sun-drying promptly. Document damaged quantities and report them.

Investigate the root cause of moisture damage, such as container leakage, dehumidification equipment failure, or poor ventilation. Promptly repair fault points and restore normal environmental conditions.

Conduct comprehensive dehumidification and drying inside the container. After confirming the environment meets standards, return intact materials to storage. Clean and disinfect the affected interior to prevent mold spread.

11.3.4 Container Water Ingress Emergency

When heavy rain or flooding causes water ingress into the container, first cut off the main power supply to prevent electric shock accidents, and transfer valuable materials to higher positions.

Use drainage pumps, mops, water-absorbing equipment, etc. to remove accumulated water from the container. Clean and classify affected materials.

After water recedes, thoroughly clean mud and debris from the container, ventilate and dry. Dry electrical equipment and conduct insulation testing. Power may only be restored after testing passes.

Inspect the container for leakage points and identify the cause of water ingress. Perform waterproofing repairs. If necessary, raise the container or construct flood barrier walls to prevent recurrence.

11.3.5 Theft and Intrusion Emergency

If container theft or signs of intrusion are discovered, immediately protect the scene, prohibit unauthorized personnel from entering, and report to the unit supervisor and public security authorities.

Retrieve surveillance footage and access control records, preserve evidence, and cooperate with police investigation and evidence collection.

Inventory material losses, document damage, and report to relevant departments.

Strengthen security measures; repair damaged locks and security equipment; increase patrol frequency; and enhance anti-theft capability.

Chapter 12 After-Sales Service and Technical Support

Guangzhou Lain Intelligent System Development Co., Ltd., as a professional manufacturer of material containers, consistently upholds the service philosophy of “Quality First, Customer Supreme,” providing comprehensive after-sales service and technical support for all emergency support material container products to ensure worry-free customer operation. Relying on a complete service system and professional technical team, the company provides customers with full-cycle services from pre-sales solutions to after-sales operation and maintenance, helping customers build efficient and reliable emergency material support systems.

12.1 Warranty Service Commitment

12.1.1 Warranty Period

  • The overall warranty period for this product is 12 months, calculated from the date of project acceptance.
  • The container body main structure warranty period is 5 years. Within the warranty period, non-man-made quality issues such as structural weld cracking and large-area anti-corrosion coating peeling are repaired or replaced free of charge.
  • Core equipment such as dehumidifiers, fans, and electrical components are covered per the manufacturer’s warranty policy, not less than 12 months.
  • Within the warranty period, equipment faults and quality issues not caused by man-made damage or force majeure are provided with free repair, parts replacement, and on-site service.

12.1.2 Warranty Scope Exclusions

Within the warranty period, the following situations are not covered by the free warranty:

  • Damage caused by improper operation, unauthorized modification, or non-compliant use
  • Damage caused by force majeure (earthquake, flood, typhoon, lightning strike, and other natural disasters)
  • Damage caused by failure to perform maintenance per the instruction manual
  • Normal wear and replacement of wearing parts and consumables
  • Damage caused by repair, disassembly, or assembly by non-company personnel
  • Faults and damage caused by use of non-genuine parts

12.2 After-Sales Service Response

Item Details
Service Hotline +86 13538869979 (same as WeChat), 7×24-hour service consultation and fault reporting
Technical Support +86 13538869979, senior technical engineers provide professional technical consultation and remote fault guidance
Response Time Response within 30 minutes of fault report; solution within 2 hours; on-site service within 24 hours within the province, within 48 hours outside the province (remote areas may be extended appropriately)
Resolution Time General faults resolved on-site within 4 hours; major faults with a solution within 24 hours

12.3 Service Content

12.3.1 Technical Consultation Services

  • Provide pre-sales technical consultation including product selection, solution design, site planning, and budget preparation; customize personalized material storage container solutions based on customer requirements.
  • Provide after-sales technical support including operation training, maintenance guidance, and technical Q&A; on-site training services can be provided based on customer needs, systematically training operators and O&M personnel.
  • Provide industry policy and standard/regulation consultation to assist customers in building compliant emergency material support systems.

12.3.2 Repair and Maintenance Services

  • Free repair of quality issues within the warranty period; paid repair services outside the warranty period, charging only component costs with no excessive service fees.
  • Provide annual maintenance service with signed annual maintenance agreements; conduct regular on-site comprehensive inspection and maintenance to ensure long-term stable equipment operation and reduce failure rates.
  • Provide genuine factory parts supply, ensuring spec-matched, reliable quality, and transparent pricing; common parts available from stock to shorten repair cycles.

12.3.3 Upgrade and Retrofit Services

  • Based on customer needs, perform functional upgrades and system retrofits on existing emergency material storage containers, such as adding smart monitoring systems, upgrading dehumidification and air conditioning systems, expanding shelving capacity, adding security configurations, etc., to improve product performance and adaptability.
  • Provide container refurbishment, anti-corrosion repair, and structural reinforcement services to extend product service life and reduce customer procurement costs.
  • Support system platform iterative upgrades, continuously optimizing smart management functions and enhancing customers’ digital material management capabilities.

12.4 Contact Information

Item Details
Manufacturer Guangzhou Lain Intelligent System Development Co., Ltd.
Service Hotline +86 13538869979 (same as WeChat)
Technical Support +86 13538869979
Company Address Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou
Official Website https://gdlain.com

Guangzhou Lain Intelligent System Development Co., Ltd. specializes in the R&D, production, and service of various emergency support containers and special integrated enclosures, with extensive project experience and strong technical capability. The company is committed to winning the market with quality and building reputation through service, dedicated to providing customers with high-quality, high-reliability modular emergency support equipment. Customers are welcome to inquire about cooperation. We will provide reliable overall emergency material storage solutions with quality products, professional technology, and comprehensive service.

Appendix

Appendix A: System Commissioning Record Table

Commissioning Item Commissioning Parameter Standard Value Measured Value Pass/Fail Remarks
Power Distribution System Input voltage AC220V±7%
Insulation resistance ≥2MΩ
Ground resistance ≤4Ω
Lighting System Average illuminance ≥300lx
Emergency lighting duration ≥90min
Ventilation System Operating current ≤Rated current
Noise ≤55dB(A)
Dehumidification System Dehumidification capacity Per nameplate rating
Humidity control accuracy ±5%RH
Fire Protection System Alarm response time ≤10s
Temperature/Humidity Monitoring Temperature accuracy ±0.5℃
Humidity accuracy ±3%RH
Access Control System Card reading response time ≤0.5s
Integrated Testing 24-hour operation No faults

Commissioning Personnel: _________________ Commissioning Date: ___________

Appendix B: Daily Inspection Record Table

Inspection Date Container Body Door Status Temp/Humidity Dehumidifier Status Ventilation Fan Status Lighting Status Fire Protection Status Access Control Status Abnormal Conditions Inspector

Appendix C: Annual Maintenance Plan Table

No. Maintenance Item Maintenance Content Scheduled Date Responsible Person Completion Status
1 Container Structure Anti-corrosion inspection, touch-up painting, sealing gasket inspection/replacement, door lubrication
2 Electrical System Insulation testing, terminal tightening, switch verification, wiring inspection
3 Dehumidification System Deep cleaning, refrigerant check, wearing parts replacement, performance calibration
4 Ventilation System Blade cleaning, bearing lubrication, fastening inspection
5 Fire Protection System Function testing, consumable replacement, detector calibration
6 Smart System System upgrade, data backup, function testing
7 Security System Equipment cleaning, function testing, storage cleanup