With the comprehensive advancement of smart city construction in China and the continuous improvement of refined urban lighting management, road lighting systems have upgraded from traditional “illumination projects” to modern systems characterized by “intelligence, energy efficiency, safety, and manageable controllability.” As the core control and power distribution node of road lighting systems, the road lighting cabinet undertakes critical functions including power distribution, switching control, safety protection, and status monitoring. Its performance stability, installation standardization, and commissioning accuracy directly determine the operational reliability and maintenance efficiency of the entire road lighting system.
Guangdong Lain Intelligent System Development Co., Ltd. has been deeply engaged in the field of outdoor cabinets and intelligent power distribution for over a decade. Targeting diverse lighting scenarios including municipal roads, industrial parks, scenic areas, and rural areas, we have developed and manufactured a full series of functional dedicated outdoor road lighting cabinets. Our products strictly comply with national electrical safety standards and outdoor equipment protection specifications, integrating traditional power distribution protection with IoT intelligent control technology. They feature core advantages of high protection, high reliability, easy installation, and easy maintenance, and have been widely applied in hundreds of urban lighting projects nationwide.
To standardize the on-site installation, wiring, and commissioning procedures for road lighting cabinets, ensure the personal safety of construction personnel and long-term stable operation of equipment, and guide operation and maintenance personnel in daily maintenance and fault troubleshooting, our company has organized a joint team of technical R&D, engineering construction, and after-sales service personnel to compile this manual. This manual comprehensively covers the entire chain of content including product introduction, composition structure, working principles, technical parameters, functional features, application scenarios, installation construction, wiring specifications, commissioning procedures, precautions, repair and maintenance, fault troubleshooting, Q&A, and acceptance standards. All operational steps are compiled based on national standards and extensive field engineering experience, combining professionalism with operability.
This manual is applicable to the LA-LD series standard, intelligent, and high-configuration road lighting cabinets manufactured by our company, and may be used for reference by electrical construction personnel, project management personnel, operation and maintenance inspection personnel, and Party A technical staff. Due to continuous product iteration and upgrades, if minor discrepancies exist between the actual product and this manual, the factory qualification certificate and technical drawings shipped with the goods shall prevail. For any technical questions, please contact our technical support team at any time for guidance.
Chapter 1: Road Lighting Cabinet Product Introduction
1.1 Industry Development Background
Urban road lighting is an important component of urban infrastructure, serving multiple functions including ensuring nighttime traffic safety, enhancing city image, and supporting nighttime economic development. China’s urbanization rate has exceeded 65%, urban road mileage continues to grow, and the corresponding number of street lights has surpassed 30 million, increasing at a rate of more than 5% annually. Traditional street light power distribution mostly uses ordinary outdoor distribution boxes with only basic branch circuit power supply functions. These suffer from problems such as crude control methods, high energy consumption, delayed fault detection, high maintenance costs, and insufficient protection capabilities, and can no longer meet the lighting management needs under smart city and dual carbon goals.
Meanwhile, LED lighting technology has been comprehensively adopted, and intelligent control, IoT, and big data technologies are gradually penetrating the lighting field. Road lighting systems are developing toward the intelligent direction of “single-lamp controllability, on-demand lighting, measurable energy consumption, and pre-warning of faults.” As the “brain and heart” of the lighting system, the road lighting cabinet has also been upgraded from a single power distribution unit to an intelligent outdoor node integrating distribution, protection, control, communication, and metering, becoming standard equipment for smart light poles and smart road systems.
At the national level, the “14th Five-Year Plan for National Urban Infrastructure Construction” explicitly proposes promoting intelligent renovation of urban lighting and promoting time-sharing, zone-based, and tiered energy-saving control modes. Various provinces and cities have successively issued urban lighting management regulations requiring that new road lighting must have intelligent control functions, and existing lighting systems must gradually complete intelligent upgrades. Driven by both policy and market demand, professional and intelligent outdoor road lighting cabinets have become essential industry products.
1.2 Product Definition
The road lighting cabinet is a sub-category of functional dedicated outdoor cabinets. It is an outdoor power distribution and control device specifically designed for road lighting systems, installed in outdoor environments along roads, in parks, scenic areas, etc., capable of power distribution, on/off control, operational protection, status monitoring, and data upload for lighting circuits.
Compared with ordinary indoor distribution boxes and general-purpose outdoor distribution cabinets, road lighting cabinets are specially optimized for lighting load characteristics: multiple circuits with moderate per-circuit current, adapted to the distributed load characteristics of street lights; integrated with dedicated lighting control functions such as time control, light control, and longitude/latitude control; possessing stronger outdoor protection capabilities to withstand rain, sand and dust, intense sun exposure, low temperatures, and other harsh environments; and equipped with appropriately selected circuit breakers and contactors tailored to the impact characteristics of lighting loads to extend equipment service life. Intelligent communication modules can be expanded to connect to urban lighting management platforms for remote centralized management and control.
1.3 Product Design Philosophy
Our road lighting cabinets consistently adhere to the design philosophy of “safety first, intelligence as the core, durability as the foundation, and convenience as the priority,” comprehensively meeting the requirements of outdoor lighting scenarios:
Safety First: Strictly comply with national electrical safety standards including GB 7251.1 and GB 50054, equipped with multiple electrical protections and structural safeguards to eliminate risks of electric leakage, short circuit, fire, and electric shock. The cabinet adopts an electric-shock-proof structural design with fully enclosed live parts that cannot be accessed by non-professionals.
Intelligence as the Core: The full series reserves space for intelligent control upgrades, with time control and light control as standard features. Optional intelligent modules include longitude/latitude control, 4G communication, electrical energy metering, and fault alarms. Compatible with mainstream urban lighting management platforms, supporting smooth upgrades to smart lighting systems.
Durability as the Foundation: Targeting harsh outdoor environments such as high temperature, high humidity, corrosion, and lightning strikes, the cabinets use high-protection cabinet structures, anti-corrosion materials, and surface treatment processes. Core electrical components are selected from well-known domestic and international brands, ensuring a Mean Time Between Failures (MTBF) of ≥50,000 hours.
Convenience as the Priority: Internal wiring space and component layout are optimized, reserving ample wiring and operation space. Standardized mounting structures accommodate floor-mounted, wall-mounted, and pole-mounted installation methods. Modular design facilitates component replacement and functional upgrades, reducing construction and maintenance costs.
1.4 Product Implementation Standards
This series of road lighting cabinets strictly complies with current national and industry standards in design, production, and inspection, including but not limited to:
- 《Low-voltage switchgear and controlgear assemblies – Part 1: General rules》 GB 7251.1-2013
- 《Code for design of low voltage electrical installations》 GB 50054-2011
- 《Standard for lighting design of urban road》 CJJ 45-2015
- 《Electrical installations for outdoor sites under heavy conditions – Part 1: Scope and definitions》 GB/T 9089.1-2008
- 《Low-voltage surge protective devices – Part 1: Surge protective devices connected to low-voltage power distribution systems》 GB 18802.1-2011
- 《Installation and operation of residual current operated protective devices》 GB 13955-2017
- 《Degrees of protection provided by enclosures (IP code)》 GB 4208-2017
- 《Electromagnetic compatibility – Testing and measurement techniques》 GB/T 17626 series standards
- 《Technical requirements for intelligent street light control systems》 CJ/T 527-2018
All products pass type tests conducted by third-party testing institutions before leaving the factory. All performance indicators meet national standard requirements, and complete test reports are available.
1.5 Product Development History
Our road lighting cabinet products have undergone three generations of technological iteration, continuously adapting to market demands:
First Generation (Basic Type): Launched in 2015, based on cold-rolled steel plate outdoor cabinet structure, equipped with circuit breakers, contactors, and time switches, achieving manual + timed control. This solved the problems of insufficient protection and single control methods in traditional distribution boxes, and was widely applied in ordinary municipal road projects.
Second Generation (Intelligent Type): Upgraded in 2019, integrating dedicated lighting controllers with new light control, longitude/latitude control, and electrical energy metering functions. Optional RS485 and 4G communication modules support remote monitoring and centralized management, suitable for smart city lighting renovation projects.
Third Generation (IoT Type): Launched in 2023, equipped with edge computing controllers supporting single-lamp control, proactive fault alarm, energy consumption data analysis, and multi-scenario linkage. Compatible with smart light poles, photovoltaic energy storage, security monitoring, and other multi-system integration, suitable for new smart city and zero-carbon park construction needs.
Currently, our company offers a full series of product selections covering all scenarios from simple rural lighting to urban smart roads, supporting customized design and production based on project requirements.
Chapter 2: Road Lighting Cabinet Product Composition
The road lighting cabinet is an integrated packaged equipment consisting of four major parts: cabinet structure system, electrical power distribution system, intelligent control system, and auxiliary accessories. These parts work in coordination to achieve the complete functions of power distribution, control, protection, and communication.
2.1 Cabinet Structure System
The cabinet structure is the physical carrier of the equipment, serving core functions including protection, mounting, sealing, and heat dissipation, directly determining the equipment’s adaptability to outdoor environments. Our road lighting cabinet adopts a layered structural design, from outside to inside: outer protective layer, intermediate skeleton layer, and internal mounting layer.
2.1.1 Cabinet Enclosure
Material Selection
The standard version uses high-quality cold-rolled carbon steel plates with door panel thickness ≥2.0mm, cabinet body thickness ≥1.5mm, and back panel thickness ≥1.2mm, providing sufficient mechanical strength to withstand external impact, wind pressure, and snow loads. For coastal areas, chemical industrial parks, and other high-corrosion environments, 304/316 stainless steel material can be customized with the same thickness as cold-rolled steel plates, offering excellent corrosion resistance.
Surface Treatment Process
Cold-rolled steel plate cabinets undergo a full-process anti-corrosion treatment: first, pre-treatment including degreasing, pickling, phosphating, and passivation to remove surface oil and oxide layers, forming a phosphate protective film; then, electrostatic epoxy powder coating with coating thickness ≥60μm, achieving grade 0 coating adhesion, with excellent anti-corrosion, UV resistance, and scratch resistance. Stainless steel cabinets may be finished with brushed or matte treatment, providing a smooth surface that is easy to clean.
Color Options
Standard colors are RAL7035 light gray and RAL6005 military green. Other colors can be customized according to project requirements to ensure harmony with the surrounding environment.
Rain-proof Structural Design
The cabinet top is designed as an inclined rain-proof roof with the front edge protruding 30mm from the cabinet body, forming a rain shield that guides rainwater to flow down the front and both sides, preventing rainwater from seeping into cabinet door gaps. The cabinet door perimeter uses a recessed stop structure combined with sealing gaskets to form multiple waterproof barriers. The bottom features an upward-protruding cable entry chamber with cable entry holes located at the cabinet base, preventing rainwater from seeping into the cabinet along cables.
Sealing System
The cabinet door perimeter is fitted with integrally molded EPDM (ethylene-propylene-diene monomer) foam sealing gaskets. The gasket cross-section has a porous structure with good compression resilience, resistant to high and low temperatures and aging, with a service life ≥10 years. Gaskets are fixed using a slot-type mounting without adhesive bonding, preventing aging-related detachment. After the cabinet door is closed, gasket compression is ≥30%, achieving IP65 level sealing.
Door Locks and Hinges
Standard configuration includes anti-theft triangular locks with strong versatility, supplied with dedicated keys and certain anti-theft performance. Optional locks include pin tumbler locks, intelligent fingerprint locks, and hasp lugs. Hinges are stainless steel concealed hinges installed inside the cabinet body, cannot be removed from the outside, offering excellent anti-theft performance. Hinges have strong load-bearing capacity, with each door able to bear ≥50kg, and can operate ≥10,000 cycles without loosening.
Cable Entry/Exit Structure
Multiple knockout holes are reserved at the cabinet base, with rubber sealing plugs as standard. On-site, corresponding holes are knocked out according to the number and diameter of cables, paired with waterproof cable glands for sealed cable fixing. A cable fixing beam is provided at the base for lashing and securing incoming cables, preventing cable tension from being transmitted to wiring terminals. For high-current specification cabinets, a bottom cable trench entry method can be customized to accommodate large cross-section multi-circuit cable routing.
2.1.2 Internal Skeleton and Mounting Structure
Mounting Rails and DIN Rails
2-3 galvanized mounting rails are horizontally arranged inside the cabinet, with adjustable positions up and down to accommodate components of different heights. Standard C45 DIN rails are provided for mounting rail-mounted components such as circuit breakers, contactors, and surge protective devices. Rails have thickness ≥1.2mm, galvanized for corrosion protection, and are securely fixed.
Terminal Block Mounting Position
A dedicated terminal block mounting area is reserved in the lower part of the cabinet, equipped with insulated mounting plates for installing wiring terminal blocks, enabling transfer and labeling of incoming and outgoing wires for convenient later maintenance.
Layered Partition Panels
For large-size cabinets, insulated layered partition panels are optional to separate high-voltage areas from low-voltage areas, preventing high-voltage interference with low-voltage signals and improving system stability.
Grounding System
A through-type grounding copper busbar is installed inside the cabinet with thickness ≥3mm and width ≥25mm. The copper busbar is tin-plated with multiple grounding terminals reserved, enabling multi-point grounding of the cabinet body, components, and cable shielding layers. The grounding copper busbar is reliably connected to the cabinet enclosure to ensure grounding continuity.
2.1.3 Heat Dissipation and Temperature Control Structure
Natural Heat Dissipation Design
The standard version uses natural heat dissipation through the cabinet body’s own heat conduction and air convection. Internal component layout reserves sufficient heat dissipation gaps, with heat-generating components (such as contactors and transformers) positioned in locations with better heat dissipation to avoid heat accumulation.
Forced Heat Dissipation Option
For cabinets used in high-current, high-power, or high-temperature environments, a temperature-controlled fan heat dissipation system can be customized: air intake grilles at the lower part, exhaust fans at the upper part, and dust-proof filter screens at air intakes. Paired with a temperature control switch, the fan automatically starts when the internal temperature exceeds the set value (default 40°C) and automatically stops when below the set value, balancing heat dissipation with dust and water protection.
Low-temperature Heating Option
For severe cold regions in the north, PTC heating devices can be customized, paired with temperature controllers. When the internal temperature falls below the set value (default 0°C), heating activates automatically, ensuring reliable operation of electrical components at low temperatures and preventing sealing gaskets from freezing and failing.
2.2 Electrical Power Distribution System
The electrical power distribution system is the core functional unit of the road lighting cabinet, responsible for power distribution, circuit protection, and load switching, consisting of the main incoming line unit, branch distribution unit, protection unit, and outgoing line transfer unit.
2.2.1 Main Incoming Line Unit
Main Circuit Breaker
Serving as the master power switch, it provides on/off control and overall protection for the entire cabinet. Molded case circuit breakers or miniature circuit breakers are selected based on total capacity. It features overload long-delay and short-circuit instantaneous protection with a rated breaking capacity ≥6kA, effectively isolating faults and preventing upstream breaker tripping. Intelligent versions may optionally be equipped with communication-capable intelligent circuit breakers supporting remote opening/closing and parameter collection.
Incoming Line Terminals
High-current specifications are equipped with dedicated incoming line copper busbars or high-current terminals, suitable for large cross-section incoming cables, ensuring reliable contact and preventing heat generation.
2.2.2 Branch Distribution Unit
Branch Circuit Breakers
Each lighting circuit is equipped with one miniature circuit breaker providing overload and short-circuit protection for individual circuits. In the event of a fault, only that single circuit trips without affecting the normal operation of other circuits. The breaker tripping characteristic uses the C curve, adapted to the starting characteristics of LED lamps, high-pressure sodium lamps, and other lighting loads, preventing nuisance tripping caused by starting surge currents. The number of circuits can be customized as required, with common configurations of 6, 8, 12, 16, or 24 circuits.
AC Contactors
Each circuit is equipped with an AC contactor serving as the actuating element that receives control signals and achieves frequent on/off control of the circuit. Contactors are selected from well-known brands with silver alloy contacts for arc resistance and long life, with electrical life ≥1 million operations, meeting the frequent daily switching requirements of lighting. For low-power circuits, breakers may be used for direct control, omitting contactors to reduce cost.
2.2.3 Protection Unit
Surge Protective Device (SPD)
A Type 2 power surge protective device is configured at the incoming end, using a combination structure of metal oxide varistor + gas discharge tube. It diverts lightning-induced overvoltages and switching overvoltages, protecting downstream electrical components and intelligent devices from surge damage. Rated discharge current In ≥20kA, maximum discharge current Imax ≥40kA, voltage protection level Up ≤1.8kV, with failure indication and remote signaling contacts for alarm signal output upon fault.
Residual Current Protective Device (RCD)
Optional total incoming line RCD or branch RCD, operating on the residual current protection principle. When leakage or personnel electric shock occurs in a circuit, power is quickly cut off within 0.1s, ensuring personal and equipment safety. Leakage operating currents can be selected as 30mA/100mA/300mA. Lighting systems commonly use 300mA fire-prevention type, balancing safety and avoidance of nuisance tripping.
Fuses
Fuses may be configured at the front end of control circuits, voltage transformers, and communication modules for short-circuit protection, protecting low-voltage components from damage due to short circuits.
2.2.4 Metering and Indication Unit
Energy Meter (Watt-hour Meter)
A three-phase multifunction energy meter is optional, supporting measurement of voltage, current, power, electrical energy, power factor, and other parameters. Accuracy class 1.0, with RS485 communication for data upload, enabling energy consumption monitoring and statistical analysis.
Indicator Lamps
The cabinet door panel is equipped with power indicator, operation indicator, and fault indicator lamps, visually displaying equipment operating status. Each branch circuit can be equipped with a circuit indicator lamp for quick on-site determination of circuit on/off status.
2.3 Intelligent Control System
The intelligent control system is the “brain” of the road lighting cabinet, implementing lighting logic control, data acquisition, and communication interaction. It is divided into basic control type and intelligent IoT type configurations.
2.3.1 Basic Control Module
Time Switch
Standard configuration includes a microcomputer time switch with a built-in high-precision clock chip, providing accurate timekeeping with annual error ≤5 minutes. Multiple groups of on/off times can be set, supporting weekday/holiday mode switching. With built-in battery, the clock continues running for more than 3 years after power failure without requiring reset.
Light Sensor (Photocell)
An optional light sensor probe can be installed on the cabinet top or in an unobstructed outdoor location, collecting ambient illuminance in real time. The controller automatically switches lights on/off based on the set illumination thresholds. On cloudy or rainy days, lights can automatically switch on earlier, adapting to weather changes and providing greater energy savings than pure time control.
Manual/Auto Selector Switch
A standard transfer switch enables switching between manual control and automatic control. During maintenance, commissioning, or special weather conditions, the system can be switched to manual mode for direct circuit on/off control, and switched back to automatic mode for daily operation.
2.3.2 Intelligent IoT Module
Lighting Main Controller
Uses a 32-bit ARM processor with stable operation and strong computing capability. Integrates multiple control logic functions including time control, light control, longitude/latitude control, holiday control, and scene mode control. Can collect operating parameters including voltage, current, leakage, and temperature. Features fault detection and alarm functions supporting multiple alarm types including circuit faults, overvoltage/undervoltage, leakage, and unauthorized cabinet door opening.
Longitude/Latitude Control Unit
Built-in longitude/latitude algorithm automatically calculates the daily sunrise and sunset times for the project location after inputting the longitude and latitude. Switch on/off times are automatically adjusted according to seasonal changes, eliminating the need for frequent manual time modifications. This achieves “automatic lighting at dusk and automatic extinguishing at dawn,” saving 10%-15% energy compared with fixed time control.
Communication Module
Standard configuration includes RS485 communication interface supporting Modbus-RTU protocol for connection to local monitoring systems. Optional 4G/NB-IoT wireless communication module provides direct cloud platform access without the need for wiring, enabling remote monitoring. Communication uses encrypted transmission to ensure data security.
Antenna and Accessories
Wireless communication versions are supplied with high-gain waterproof antennas installed on the cabinet top for optimal signal reception. The light sensor probe uses a waterproof housing, and cable lengths can be customized to ensure installation in locations with adequate illumination.
Human-Machine Interface
High-configuration versions are equipped with an LCD display and keys, allowing on-site viewing of operating parameters, setting of control parameters, and querying of fault records without the need for a computer to complete on-site commissioning.
2.4 Auxiliary Accessory System
Installation Accessories: Including floor-mounting anchor feet, wall-mounting brackets, pole-mounting clamps, expansion bolts, etc., adapted to different installation methods.
Sealing Accessories: Waterproof cable glands, sealing mastic, fire-stop putty, etc., used for sealing cable entry holes after on-site installation.
Labeling Accessories: Circuit identification labels, warning signs, grounding labels, operation instruction stickers, etc., to standardize on-site labeling.
Spare Parts: Spare fuses, sealing gaskets, keys, special tools, etc., supplied with the equipment for routine maintenance.
Chapter 3: Road Lighting Cabinet Product List
3.1 Product Model Designation
Our road lighting cabinet model naming convention is as follows:
LA – LD – Circuit Number – Control Type – Mounting Method – Material
| Code | Meaning |
|---|---|
| LA | Company code (Lain) |
| LD | Product code (Road Lighting Cabinet) |
| Circuit Number | Number of lighting output circuits, e.g., 06, 08, 12, 16, 24 |
| Control Type | A – Basic time control; B – Light + time control; C – Intelligent longitude/latitude; D – IoT 4G |
| Mounting Method | L – Floor-mounted; G – Wall-mounted; P – Pole-mounted |
| Material | S – Cold-rolled steel plate; B – 304 stainless steel |
Example: LA-LD-12-C-L-S represents a 12-circuit intelligent longitude/latitude type floor-mounted cold-rolled steel plate road lighting cabinet.
3.2 Standard Configuration List (Example: LA-LD-12-C-L-S)
| No. | Component Name | Specification/Model | Qty | Unit | Remarks |
|---|---|---|---|---|---|
| 1 | Cabinet body | 800mm × 1500mm × 400mm (W×H×D), cold-rolled steel 2.0/1.5mm, IP65 | 1 | Unit | RAL7035 light gray |
| 2 | Main molded case circuit breaker | 100A/3P, C curve, breaking capacity 6kA | 1 | Pc | Master power switch |
| 3 | Branch miniature circuit breaker | 16A/1P, C curve, breaking capacity 6kA | 12 | Pc | Individual circuit protection |
| 4 | AC contactor | 18A/220V, AC-3 category | 12 | Pc | Circuit on/off actuation |
| 5 | Power surge protective device | 40kA/3P+N, Type 2 protection | 1 | Pc | Lightning/surge protection |
| 6 | Intelligent lighting controller | 12 circuits, longitude/latitude + time + light control, with LCD display | 1 | Unit | Core control unit |
| 7 | Light sensor | 0-200,000 Lux, waterproof type, 3m cable | 1 | Pc | Illuminance acquisition |
| 8 | Manual/auto transfer switch | 3-position, 16A | 1 | Pc | Control mode switching |
| 9 | Wiring terminal block | 30-position, 10A, screw type | 2 | Pcs | Signal and neutral transfer |
| 10 | Grounding copper busbar | 3mm × 25mm, tin-plated, with 10 terminals | 1 | Pc | Grounding bus |
| 11 | Power indicator lamp | AC220V, green | 1 | Pc | Power status indication |
| 12 | Fault indicator lamp | AC220V, red | 1 | Pc | Fault status indication |
| 13 | Circuit indicator lamp | AC220V, yellow | 12 | Pc | Branch circuit status indication |
| 14 | EPDM sealing gasket | One perimeter of cabinet door, integrally molded | 1 | Set | Waterproof sealing |
| 15 | Anti-theft triangular lock | Stainless steel, with 2 keys | 1 | Set | Cabinet door lock |
| 16 | Stainless steel hinge | Concealed heavy-duty hinge | 2 | Pcs | Cabinet door connection |
| 17 | Mounting anchor feet | Galvanized steel plate, with mounting holes | 4 | Pcs | Floor-mount fixing |
| 18 | Waterproof cable gland | M20/M25, suitable for cable diameter | 15 | Pcs | Cable entry sealing |
| 19 | Product certificate of conformity | / | 1 | Sheet | Factory inspection pass |
| 20 | Product manual | This manual | 1 | Copy | Operating instructions |
| 21 | Warranty card | / | 1 | Sheet | After-sales certificate |
| 22 | Spare key | / | 1 | Pc | Spare |
| 23 | Spare fuse | 2A | 5 | Pcs | Control circuit spare |
3.3 Optional Configuration List
| No. | Component Name | Specification Description | Applicable Scenarios |
|---|---|---|---|
| 1 | 4G communication module | Full network compatibility, supports MQTT protocol, cloud platform access | Projects requiring remote monitoring and centralized management |
| 2 | Three-phase multifunction energy meter | Class 1.0, measures voltage/current/power/energy, with RS485 | Projects requiring energy metering and electricity cost accounting |
| 3 | Residual current protective device | Main incoming 300mA leakage, or branch 30mA leakage | Scenarios with high safety requirements and easy personnel contact |
| 4 | PTC heating device | 50W/100W, with temperature control switch, activates at 0°C | Severe cold regions below -20°C |
| 5 | Temperature-controlled cooling fan | Axial fan, activates at 40°C, with dust screen | High-temperature summer regions, high-current loads |
| 6 | Single-lamp control module | Power line carrier/ZigBee, single-lamp level control and fault detection | Projects requiring refined control and single-lamp fault location |
| 7 | Photovoltaic access module | DC MPPT controller, suitable for photovoltaic power supply | Solar street lighting, off-grid lighting projects |
| 8 | Cabinet door status sensor | Magnetic door switch, door-open alarm | Projects with high anti-theft requirements and remote road sections |
| 9 | Cabinet temperature/humidity sensor | Monitors internal temperature and humidity, alarm on threshold exceedance | High-humidity, high-temperature environment projects |
| 10 | 304 stainless steel cabinet body | Full 304 stainless steel material, higher corrosion protection grade | Coastal areas, chemical industrial parks, high-corrosion environments |
| 11 | Wall-mounting bracket | Heavy-duty galvanized bracket, with expansion bolts | Wall and light pole side mounting |
| 12 | Pole-mounting clamp kit | Double clamp, suitable for φ60-φ200 light poles | Pole-top mounting |
3.4 Spare Parts List (Recommended Purchase)
| No. | Spare Part Name | Recommended Stock Quantity | Replacement Cycle |
|---|---|---|---|
| 1 | Miniature circuit breaker | 10% of total circuit count | Replace upon damage |
| 2 | AC contactor | 5% of total circuit count | 3-5 years or contact damage |
| 3 | Surge protective device | 1 per 10 cabinets | Lightning damage or 3-5 years |
| 4 | Sealing gasket | 1 set per 10 cabinets | 5-8 years or aging failure |
| 5 | Door lock assembly | 1 set per 20 cabinets | Replace upon damage |
| 6 | Light sensor | 1 per 10 cabinets | 2-3 years |
| 7 | Control fuse tube | Several | Replace when blown |
| 8 | Waterproof cable gland | Several | Replace upon damage |
Chapter 4: Road Lighting Cabinet Product Working Principles
4.1 Overall Working Principle Overview
The road lighting cabinet uses three-phase five-wire (TN-S system) AC power as input. Power passes through the main circuit breaker for overall protection and master switching, then is distributed to each lighting branch. Each branch is protected by a circuit breaker for overload and short-circuit protection, with an AC contactor responsible for circuit on/off actuation. The intelligent controller outputs control signals based on preset control logic (timed, light control, longitude/latitude, remote commands), driving the contactor coil to energize/de-energize, thereby controlling the energization and de-energization of lighting circuits to achieve automatic switching of street lights.
Meanwhile, the various protection devices configured inside the cabinet monitor circuit status in real time. When abnormalities such as short circuit, overload, leakage, overvoltage, or surge occur, they quickly operate to cut off the circuit or divert energy, ensuring equipment and line safety. Intelligent models can collect operating data including voltage, current, power, and switch status, upload it to the cloud management platform via the communication module, and receive control commands issued by the platform for remote management and control.
4.2 Power Distribution System Working Principles
4.2.1 Main Circuit Distribution Principle
The road lighting cabinet adopts a three-phase incoming, single-phase branch output distribution method: three-phase AC power (L1, L2, L3) with neutral (N) and protective earth (PE) connects to the cabinet’s main incoming terminals, passes through the main circuit breaker, and enters the busbar system. The three-phase busbars distribute power to each branch circuit breaker. To achieve three-phase load balancing, branch circuits are evenly distributed across the three phases. For example, in a 12-circuit configuration, L1 carries circuits 1-4, L2 carries circuits 5-8, and L3 carries circuits 9-12, with a shared neutral, ensuring the three-phase current imbalance does not exceed 25%.
The live wire of each branch circuit passes through the circuit breaker first, then through the AC contactor main contacts, and finally connects to the outgoing terminal for connection to the corresponding street light load. The neutral wires are connected to a common neutral busbar and then distributed to each circuit. The protective earth wires connect directly to the grounding copper busbar, connecting to the cabinet body and lamp housings to form a complete grounding protection system.
4.2.2 Circuit Breaker Protection Principle
The circuit breaker is the core component of circuit protection, providing both overload protection and short-circuit protection. Its working principle is based on thermal and electromagnetic effects:
Overload Protection (Thermal Trip): The circuit breaker contains a bimetallic strip made of two metals laminated together with different thermal expansion coefficients. When the circuit current exceeds the rated value, the heat generated by the current causes the bimetallic strip to bend. When bent to a certain degree, it pushes the trip mechanism to operate, causing the breaker to trip and cut off the circuit. The larger the overload current, the faster the bimetallic strip heats up, and the shorter the tripping time, achieving inverse-time protection characteristics that prevent line aging or even fire caused by prolonged overload heating.
Short-Circuit Protection (Magnetic Trip): The circuit breaker contains an electromagnetic coil. When a short circuit occurs in the circuit, a large current several to dozens of times the rated value is instantaneously generated. The electromagnetic coil produces a strong electromagnetic attraction force, instantly attracting the armature, pushing the trip mechanism to quickly trip, cutting off the short-circuit current within milliseconds to prevent the short-circuit current from burning out equipment and lines.
The road lighting cabinet uses C-curve trip characteristic circuit breakers with a short-circuit trip current of 5-10 times the rated current. This avoids the starting surge currents of LED lamps and high-pressure sodium lamps, ensuring reliable protection while avoiding nuisance tripping.
4.2.3 AC Contactor Working Principle
The AC contactor is the actuating element for automatic control, using electromagnetic attraction to achieve circuit on/off control. It mainly consists of four parts: electromagnetic system, contact system, arc extinguishing system, and housing:
Electromagnetic System: Includes the coil, static core, and moving core. When rated voltage is applied to the control coil, the static core produces electromagnetic attraction force, attracting the moving core, which drives the moving contacts to operate. When the coil is de-energized, the electromagnetic attraction force disappears, and the moving core resets under spring force, causing the contacts to open.
Contact System: Divided into main contacts and auxiliary contacts. Main contacts are used for switching high currents in the main circuit, made of silver alloy with arc resistance and low contact resistance. Auxiliary contacts are used for signal transmission and self-locking/interlocking in the control circuit, with smaller current capacity.
Arc Extinguishing System: When main contacts open, an arc is generated. The arc extinguishing cover quickly stretches, cools, and extinguishes the arc, preventing the arc from burning the contacts and causing phase-to-phase short circuits.
In the road lighting cabinet, the 220V control voltage output by the controller is connected to the contactor coil. By controlling the energization and de-energization of the coil, the main circuit on/off is indirectly controlled, achieving the purpose of using small current to control large current and low voltage to control high voltage, while providing electrical isolation between the control circuit and main circuit for enhanced safety.
4.2.4 Surge Protection Principle
The surge protective device (SPD) is used to suppress transient overvoltages generated by lightning induction and switching operations, protecting downstream sensitive electrical equipment. Its core components are metal oxide varistors (MOVs) and gas discharge tubes, connected in parallel between the power phase lines and the ground:
Normal Operating State: When the grid voltage is normal, the varistor is in a high-resistance state with extremely low leakage current, equivalent to an open circuit, not affecting normal circuit operation.
When a Surge Arrives: When the transient overvoltage exceeds the varistor’s threshold voltage, the varistor instantly changes to a low-resistance state, diverting the surge current to ground and clamping the voltage across its terminals to a safe range that the equipment can withstand, protecting downstream equipment from overvoltage impact.
Failure Protection: The SPD contains a built-in thermal disconnect device. When surge impacts occur too frequently or aging degradation occurs over time, the thermal disconnect operates, isolating the SPD from the circuit while popping out a red failure indicator window to prompt replacement.
The road lighting cabinet is configured with Type 2 surge protection installed at the rear of the main circuit breaker, effectively protecting against induced lightning and switching overvoltages. In regions with high lightning activity, an additional Type 1 surge protective device can be added at the incoming line end for graded protection.
4.2.5 Residual Current Protection Principle
The residual current protective device operates based on Kirchhoff’s current law, with the core component being a zero-sequence current transformer: the phase and neutral conductors pass through the zero-sequence transformer together. Under normal conditions, the current flowing out through the phase conductor equals the current returning through the neutral conductor, equal in magnitude and opposite in direction. The magnetic fluxes in the transformer core cancel each other out, and no induced current is output on the secondary side.
When leakage occurs in a circuit or personnel are electrocuted, part of the current flows to ground through the leakage point or human body, causing the current returning through the neutral to be less than the current flowing out through the phase. The zero-sequence transformer detects the residual current. When the residual current reaches the operating value, the internal trip mechanism operates, driving the circuit breaker to trip and cut off the power supply.
The residual current protective device operates within ≤0.1s, cutting off the power supply before electric shock can cause harm to the human body, effectively preventing electric shock accidents and leakage fires. Road lighting systems have long outdoor lines, humid environments, and high leakage risks; leakage protection functionality is recommended.
4.3 Lighting Control System Working Principles
4.3.1 Time Control Principle
Time control functionality is implemented by the built-in real-time clock chip and microprocessor: the clock chip operates independently with continuous power supply, running accurately and outputting current time signals. The microprocessor compares the current time with user-preset switch on/off times. When the switch-on time is reached, it outputs a relay close signal, the contactor coil energizes, the circuit is energized and lights turn on. When the switch-off time is reached, it outputs a relay open signal, the contactor de-energizes, and the circuit is de-energized and lights turn off.
Advanced time control functions support multi-period control, such as midnight-light mode settings: full brightness in the first half of the night, and half of the circuits turned off in the second half, achieving significant energy savings while maintaining basic lighting. Different schedules for working days and holidays are supported to meet various scenario needs. The clock chip comes with a spare button battery that operates for more than 3 years after power failure, preventing time reset after blackouts.
4.3.2 Light Control Principle
Light control functionality is achieved through the coordination of light sensors and control logic: the core of the light sensor is a photoresistor whose resistance value changes with ambient light intensity—the stronger the light, the lower the resistance; the weaker the light, the higher the resistance. The controller converts the photoresistor resistance value to a corresponding illuminance value (unit: Lux).
Users can set switch-on and switch-off thresholds, for example, switching on when illuminance drops below 50 Lux and switching off when it rises above 100 Lux (with hysteresis set to avoid critical flicker). In the evening as ambient light gradually dims and illuminance falls below the switch-on threshold, the controller outputs a switch-on signal. In the early morning as light gradually brightens and illuminance rises above the switch-off threshold, it outputs a switch-off signal.
Light control automatically adapts to weather changes. On cloudy, overcast, or hazy days, lights can automatically switch on earlier, avoiding the problem of insufficient lighting in the early evening that pure time control cannot address. To prevent false operation caused by nighttime vehicle headlights, lightning, or strong light exposure, the controller has built-in delay judgment logic—only when illuminance remains below the threshold continuously for 1-5 minutes (configurable) does it operate, enhancing stability.
4.3.3 Longitude/Latitude Control Principle
Longitude/latitude control is an intelligent control method that calculates local sunrise and sunset times through algorithms based on the Earth’s rotation and revolution. After the user inputs the project location’s longitude and latitude, the controller’s built-in astronomical algorithm automatically calculates the sunrise and sunset times for each day without requiring manual setting of specific times.
Due to the Earth’s revolution, sunrise and sunset times change daily. On the summer solstice, sunrise is earliest and sunset is latest; on the winter solstice, sunrise is latest and sunset is earliest. Longitude/latitude control precisely follows these seasonal changes, achieving year-round adaptive light switching. Compared with fixed time control, longitude/latitude control eliminates the maintenance work of frequently modifying times, while avoiding energy waste and insufficient lighting caused by late switch-on in winter and early switch-on in summer, offering better energy-saving results.
Longitude/latitude control can be paired with a light control correction function, using sunset time as the baseline and combining with the actual lighting conditions of the day to appropriately advance or delay switching, balancing seasonal adaptability and weather adaptability.
4.3.4 Remote Control Principle
Intelligent IoT road lighting cabinets achieve remote control through wireless communication modules. The workflow is as follows:
Data Upload: The controller collects data in real time including voltage, current, power, switch status, and fault information for each circuit, and sends it to the cloud server via 4G/NB-IoT networks. The cloud server processes and stores the data, displaying it on the management platform web interface and mobile app.
Command Issuance: Management personnel issue commands such as light switching, parameter modification, and mode switching on the management platform. Commands are sent through the network to the corresponding cabinet’s communication module and then transmitted to the main controller. After executing the command, the controller feeds back the execution result to the platform.
Alarm Push: When equipment faults occur (breaker trip, leakage, overvoltage, offline), the controller immediately generates alarm information and proactively uploads it to the platform. The platform notifies management personnel via SMS, app push, email, and other methods, enabling rapid fault response.
Remote control supports manual remote light switching, timed strategy distribution, batch group control, scene mode switching, and other functions. Management personnel can control all city street lights without being on site, significantly improving operation and maintenance efficiency and reducing costs.
4.4 Grounding System Working Principle
The road lighting cabinet uses the TN-S grounding system, where the protective earth conductor (PE) is completely separated from the neutral conductor (N). The PE conductor carries no current under normal conditions and is dedicated to equipment enclosure grounding protection. Its working principle is: when internal insulation of equipment fails and the phase conductor contacts the metal enclosure, the enclosure becomes live. Current flows back to the transformer neutral point through the PE conductor, forming a short-circuit loop. This generates a large short-circuit current, causing the upstream circuit breaker to trip quickly and cut off the power supply, preventing the enclosure from remaining live for an extended period and causing electric shock to personnel.
Additionally, cabinet grounding diverts static electricity and lightning-induced currents and reduces electromagnetic interference, ensuring stable operation of intelligent equipment. The grounding system requires a grounding resistance of ≤4Ω, ensuring sufficient short-circuit current can be provided during faults for reliable operation of protection devices.
Chapter 5: Road Lighting Cabinet Product Technical Parameters
5.1 Cabinet Structure Parameters
| Parameter Category | Parameter Item | Standard Version | Stainless Steel Version | Remarks |
|---|---|---|---|---|
| Dimensions | 6 circuits | 500 × 800 × 300mm (W×H×D) | Same as left | Dimensional tolerance ±2mm |
| 12 circuits | 600 × 1200 × 350mm | Same as left | Dimensional tolerance ±2mm | |
| 16 circuits | 700 × 1400 × 350mm | Same as left | Dimensional tolerance ±2mm | |
| 24 circuits | 800 × 1600 × 400mm | Same as left | Dimensional tolerance ±2mm | |
| Material Thickness | Door panel | 2.0mm high-quality cold-rolled steel | 2.0mm 304 stainless steel | / |
| Cabinet body | 1.5mm high-quality cold-rolled steel | 1.5mm 304 stainless steel | / | |
| Back panel | 1.2mm high-quality cold-rolled steel | 1.2mm 304 stainless steel | / | |
| Surface Treatment | Coating process | Electrostatic epoxy powder coating | Brushed/matte finish | / |
| Coating thickness | ≥60μm | – | Cross-cut test grade 0 adhesion | |
| Corrosion protection grade | WF1 (medium anti-corrosion) | WF2 (heavy-duty anti-corrosion) | / | |
| Protection Performance | Enclosure protection rating | IP65 | IP65 | GB 4208-2017 |
| Electric shock protection class | Class I | Class I | With protective grounding | |
| Mechanical Performance | Wind resistance rating | Grade 12 (≤35m/s) | Grade 12 (≤35m/s) | Based on solid floor-mount foundation |
| Door load capacity | ≥50kg | ≥50kg | / | |
| Switching life | ≥10,000 cycles | ≥10,000 cycles | Hinges and locks | |
| Weight | 6-circuit empty cabinet | ≈35kg | ≈45kg | Excluding components |
| 12-circuit complete set | ≈65kg | ≈85kg | Including all standard components | |
| 24-circuit complete set | ≈110kg | ≈140kg | Including all standard components | |
| Mounting Method | Standard options | Floor-mounted / Wall-mounted / Pole-mounted | Same as left | Optional |
| Mounting hole spacing | Holes per corresponding dimensions | Same as left | Hole drilling drawing provided with delivery |
*(End of Part 1 of 5)*
5.2 Electrical Performance Parameters
| Parameter Category | Parameter Item | Parameter Specification | Remarks |
|---|---|---|---|
| Rated Parameters | Rated Operating Voltage Ue | AC 380V/220V, Three-phase five-wire | 50Hz |
| Rated Frequency | 50Hz | 60Hz customizable | |
| Main Circuit Rated Current In | 63A/100A/160A/250A | Optional | |
| Branch Circuit Rated Current | 10A/16A/20A/32A | Single circuit, optional | |
| Rated Insulation Voltage Ui | AC 660V | / | |
| Rated Impulse Withstand Voltage Uimp | 6kV | / | |
| Breaking Capacity | Main Circuit Breaker Rated Breaking Capacity | ≥6kA | MCCB up to 25kA |
| Branch Circuit Breaker Rated Breaking Capacity | ≥6kA | C-type trip curve | |
| Protection Parameters | Overload Protection | 1.05In no trip, 1.3In trip within 1h | Complies with GB 10963.1 |
| Short-Circuit Protection | 5-10In instantaneous trip | C-type characteristic | |
| Surge Protection | Imax 40kA (8/20μs), Up≤1.8kV | Level 2 protection | |
| Residual Current Trip Current | 30mA/100mA/300mA optional | Trip time ≤0.1s | |
| Electrical Life | Circuit Breaker Electrical Life | ≥10000 operations | / |
| Contactor Electrical Life | ≥1,000,000 operations | AC-3 category | |
| Metering Accuracy | Voltage Measurement Accuracy | ±0.5% | Smart model |
| Current Measurement Accuracy | ±0.5% | Smart model | |
| Energy Metering Accuracy | Class 1.0 | Optional energy meter | |
| Insulation Performance | Main Circuit Insulation Resistance | ≥10MΩ | 500V Megger |
| Control Circuit Insulation Resistance | ≥2MΩ | 500V Megger | |
| Power Frequency Withstand Voltage | 2kV/1min, no breakdown or flashover | Main circuit to ground |
5.3 Environmental Adaptation Parameters
| Parameter Item | Standard Range | Extended Range (Custom) | Remarks |
|---|---|---|---|
| Operating Ambient Temperature | -25℃ ~ +60℃ | -40℃ ~ +70℃ | Extreme cold/high temp custom model |
| Storage Ambient Temperature | -40℃ ~ +70℃ | -50℃ ~ +80℃ | Transportation and storage state |
| Relative Humidity | ≤95% (non-condensing) | ≤98% (non-condensing) | At 25℃ ambient |
| Altitude | ≤2000m | ≤4000m | Derating required above standard altitude |
| Atmospheric Pressure | 80kPa ~ 110kPa | 70kPa ~ 110kPa | Corresponds to altitude |
| Salt Spray Resistance | No obvious corrosion for 48h | No obvious corrosion for 1000h | Stainless steel model |
| Vibration Resistance | 10-55Hz, 0.5mm amplitude, no damage | / | Complies with GB/T 2423 |
| Shock Resistance | 10g, 11ms, half-sine wave | / | Complies with GB/T 2423 |
5.4 Control Function Parameters
| Parameter Item | Basic Model | Smart Model | IoT Model |
|---|---|---|---|
| Number of Control Circuits | 6-24 circuits | 6-24 circuits | 6-24 circuits |
| Time Control Function | Supported, 2 groups of timers | Supported, 10 groups of timers | Supported, unlimited groups (set via platform) |
| Photocontrol Function | Optional | Standard | Standard |
| Latitude/Longitude Control | Not supported | Standard | Standard |
| Manual Control | Supported | Supported | Supported |
| Scene Modes | None | 3 presets | Unlimited custom |
| Midnight Light Mode | Not supported | Supported | Supported |
| Holiday Mode | Not supported | Supported | Supported |
| Remote Control | Not supported | Optional RS485 | Standard 4G/NB-IoT |
| Data Acquisition | None | Voltage/Current/Switch Status | Full electrical parameters + Faults + Temp/Humidity |
| Fault Alarm | None | Local indicator light | Local + Platform + SMS Push |
| Clock Accuracy | ±5s/day | ±2s/day | Network time sync, ±1s |
| Photocontrol Range | 0-100,000 Lux | 0-200,000 Lux | 0-200,000 Lux, adjustable threshold |
| Control Delay | / | Adjustable 1-600s | Adjustable 1-600s |
5.5 Communication Performance Parameters
| Parameter Item | RS485 Communication | 4G Communication | NB-IoT Communication |
|---|---|---|---|
| Communication Protocol | Modbus-RTU | MQTT/Modbus-TCP | MQTT/CoAP |
| Transmission Rate | 9600bps (default), adjustable | Adaptive | Adaptive |
| Communication Distance | ≤1200m | Nationwide coverage, wherever signal exists | Nationwide coverage, broader reach |
| Data Upload Cycle | Real-time | Adjustable 1min-1h | Adjustable 5min-24h |
| Network Standard | Wired | Mobile/Unicom/Telecom 4G | Mobile/Telecom NB-IoT |
| Antenna Gain | None | 5dBi waterproof antenna | 5dBi waterproof antenna |
| Power Consumption | Low | Medium | Ultra-low |
| Applicable Scenarios | Local monitoring, campus intranet | City-level remote management | Low-frequency data upload, remote areas |
5.6 Parameter Notes and Derating Rules
Temperature Derating: When ambient temperature exceeds 40℃, the rated current-carrying capacity of electrical components such as circuit breakers and contactors must be derated proportionally. For every 10℃ increase in ambient temperature, the rated current should be derated by 5%-10%. Reserve margin should be considered during selection for high-temperature environments.
Altitude Derating: When altitude exceeds 2000m, air density decreases, heat dissipation performance deteriorates, and insulation strength reduces. Electrical equipment requires derating. For every 1000m increase in altitude, the rated current should be derated by 5%-8%.
Circuit Expansion: This parameter table represents standard specifications. More circuits and higher current specifications can be customized based on project requirements. Specific parameters shall be subject to the customized technical agreement.
Parameter Measurement Conditions: All electrical parameters are measured under conditions of 25℃ ambient temperature, rated voltage, and altitude ≤1000m. Reasonable deviations may occur in special environments.
6.1 Core Power Distribution Functions
6.1.1 Multi-Circuit Distribution and Hierarchical Protection
The street lighting cabinet supports power distribution output for 6-24 circuits or more, meeting the branch circuit control requirements for multi-segment lighting on long-distance roads. It adopts a hierarchical protection architecture of “Main Circuit Breaker + Branch Circuit Breakers.” The main switch provides overall fault protection, while branch switches provide individual circuit protection. When a fault occurs in a single circuit, only the corresponding switch trips, without affecting normal power supply to other circuits, thereby minimizing the scope of fault impact and improving overall power supply reliability.
Each circuit is independently equipped with a circuit breaker and contactor, providing electrical isolation between circuits to prevent mutual interference. Three-phase loads are evenly distributed to reduce phase imbalance, minimize neutral current, and reduce line losses and safety hazards.
6.1.2 Multiple Electrical Safety Protections
The product integrates a comprehensive electrical protection system covering various common electrical faults:
- Short-Circuit Protection: Millisecond-level rapid interruption of short-circuit current, preventing fault escalation and avoiding damage to luminaires and wiring.
- Overload Protection: Inverse-time characteristic; the more severe the overload, the faster the trip action, preventing long-term overheating and aging of wiring and preventing electrical fires.
- Surge Protection: Dissipates lightning-induced overvoltage, protecting intelligent control components and reducing lightning damage rates. Suitable for open roads and suburban sections.
- Residual Current Protection: Optional configuration, continuously monitors residual current in the line; rapid power-off when leakage exceeds limits, preventing electric shock and leakage-induced fires.
- Overvoltage/Undervoltage Protection: Standard on smart models; alarms or trips when grid voltage is abnormal, protecting luminaires from damage due to voltage anomalies.
6.2 Intelligent Control Functions
6.2.1 Multi-Mode Control Logic
The product integrates multiple control methods that can be flexibly switched to meet different scenario requirements:
- Manual Control: Used for maintenance and emergency scenarios; directly controls circuit on/off via transfer switches or circuit breakers inside the cabinet. Operation is intuitive and reliable.
- Timed Control: Basic standard function; multiple on/off times can be set to suit fixed-schedule lighting needs. Simple setup, stable operation.
- Photocontrol: Automatically switches lights on/off based on ambient illuminance, adapting to weather changes such as rain, fog, and haze. Enables “lighting on demand,” avoiding energy waste and insufficient lighting associated with fixed schedules.
- Latitude/Longitude Control: Automatically adjusts throughout the year based on local sunrise/sunset times, eliminating the need for manual seasonal parameter modifications. Low maintenance effort, with better energy savings than fixed timed control.
- Remote Control: Remote on/off and parameter adjustment via PC client or mobile APP, suitable for city-level batch management and convenient emergency dispatch.
Multiple control methods can be combined, for example, a “latitude/longitude primary, photocontrol correction, remote intervention” composite mode, balancing automation, energy efficiency, and flexibility.
6.2.2 Refined Energy-Saving Control
- Midnight Light Mode: Can be configured for full illumination in the first half of the night and partial circuit shutdown or brightness reduction in the second half. While meeting minimum lighting standards, this significantly reduces late-night energy consumption, achieving energy savings of over 30%.
- Time-Segmented Brightness Adjustment: When paired with dimmable LED drivers, enables staged brightness adjustment for evening, late night, and early morning periods, further optimizing energy savings.
- Holiday Mode: Presettable special lighting schemes for holidays and major event days, such as extended lighting hours and activating all landscape lighting. Adapts to different management requirements.
- Scene Mode Switching: Built-in daily, energy-saving, holiday, emergency, and other scene modes for one-key switching without modifying individual parameters.
6.2.3 Operational Status Monitoring
Smart models can collect full-dimensional operational data in real-time for transparent management:
- Electrical Parameter Monitoring: Three-phase voltage, current, power, energy, power factor, frequency, etc.
- Switch Status Monitoring: Main switch, branch circuit breaker status, contactor status.
- Environmental Monitoring: Cabinet internal temperature, humidity, external illuminance.
- Fault Status Monitoring: Short-circuit trip, overload alarm, leakage alarm, over/undervoltage, unauthorized cabinet door opening, device offline, etc.
All data is stored locally with cloud backup, allowing historical data and fault records to be queried, providing data support for operations management, energy consumption analysis, and fault tracing.
6.2.4 Proactive Fault Alarming
The product changes the traditional passive model of “manual inspection to detect faults” to achieve proactive fault warning and alarming:
- Alarm Types: Circuit trip fault, luminaire failure fault, over/undervoltage, excessive leakage, cabinet overtemperature, device offline, unauthorized cabinet door opening, etc.
- Alarm Methods: Local audible/visual alarm, platform pop-up alarm, mobile APP push, SMS notification, email notification.
- Alarm Grading: Fault levels can be configured; critical faults are pushed immediately, while general faults are aggregated for batch notification, avoiding information overload.
Fault alarming can shorten fault response time from “days” to “minutes,” significantly improving lighting availability rates and citizen satisfaction.
6.3 Outdoor Protection Features
6.3.1 IP65 High Protection Rating
The cabinet is strictly designed and manufactured to the IP65 protection rating:
- Dust Protection Level 6: Completely prevents dust ingress, suitable for roads and construction site environments with heavy sand and dust, preventing dust from entering the cabinet and causing insulation degradation or poor contact.
- Water Protection Level 5: Resists water jets from any direction without water ingress, withstanding heavy rain and high-pressure water washing. Safe and reliable operation in rainy conditions.
- Multi-Layer Waterproof Structure Design: Rainproof roof + rabbeted cabinet door + foam sealing strip + bottom cable entry + gland sealing, providing layered protection to ensure no water ingress during rain. All exposed fasteners are stainless steel to prevent rust and failure.
6.3.2 Strong Weather Resistance and Anti-Corrosion Capability
- Wide Temperature Adaptation: Standard model operates stably in -25℃~+60℃; custom models cover -40℃~+70℃, adapting to all climate zones from Hainan to Heilongjiang.
- Anti-Corrosion Durability: Cold-rolled steel cabinet body with multi-layer anti-corrosion treatment, service life ≥15 years in general outdoor environments; stainless steel cabinet suitable for coastal and chemical industry park environments with high corrosion, service life ≥20 years.
- UV Resistance: Surface coating resists UV aging, no fading, cracking, or chalking under prolonged sun exposure, maintaining stable appearance and protective performance.
- Wind and Snow Resistance: High mechanical strength cabinet can withstand Force 12 winds and 30cm snow loads. Reinforced structure available for northern heavy snow regions.
6.3.3 Anti-Theft and Vandalism Prevention Design
- Concealed Hinges: Hinges are installed inside the cabinet, cannot be removed externally, preventing door opening by prying hinges.
- Anti-Theft Lock: Standard with dedicated triangle key lock or anti-theft cylinder lock, resisting technical opening and forced prying.
- Sturdy Cabinet Body: Thick steel plate structure, impact-resistant, anti-treading, resistant to deformation and damage.
- Door Open Alarm: Optional door magnetic sensor; immediate alarm on unauthorized cabinet door opening, deterring theft.
6.4 Structure and Maintenance Features
6.4.1 Standardized Flexible Installation
Supports three installation methods: floor-standing, wall-mounted, and pole-mounted, flexibly selectable based on site conditions:
- Floor-Standing: Suitable for large circuit count and high current specifications, stable installation with ample operating space. The mainstream installation method for municipal roads.
- Wall-Mounted: Suitable for small circuit count specifications, installed on walls or building facades, saving space.
- Pole-Mounted: Suitable for scattered points and rural roads, directly fixed to lighting poles, no foundation required, quick construction.
Standardized installation accessories and drilling templates are provided for all installation methods, allowing installation crews to complete installation quickly without secondary processing.
6.4.2 Humanized Maintenance Design
- Large Door Opening: Cabinet door opens to a wide angle (≥120°), exposing all internal components for sufficient maintenance workspace.
- Clear Labeling: Every circuit, terminal, and component has clear identification with clear correspondence, eliminating the need for individual tracing during maintenance.
- Modular Layout: Standardized, modular component arrangement for convenient replacement; common spare parts can be changed without specialized tools.
- Reserved Expansion Space: Internal spare circuits and mounting positions are reserved, allowing future circuit addition or function upgrades without replacing the cabinet, protecting initial investment.
6.4.3 High Reliability and Long Service Life
- Brand Components: Core electrical components are from leading domestic and international brands, strictly screened and aged-tested before shipment, ensuring stable and reliable quality.
- Rigorous Factory Inspection: Every product undergoes power-on testing, insulation testing, withstand voltage testing, protection testing, functional testing, and other processes before shipment, ensuring 100% factory pass rate.
- Mean Time Between Failures: MTBF ≥50,000 hours; calculated at 12 hours of daily operation, stable operation for over 10 years.
- Comprehensive Warranty: Complete unit warranty for 2 years, core components warranty for 3 years, lifetime technical support and spare parts supply.
As a general-purpose outdoor lighting distribution and control device, the street lighting cabinet is widely applicable to various outdoor lighting scenarios. The following are typical application scenarios and corresponding solutions.
7.1 Municipal Road Lighting
Municipal roads are the most core application scenario for street lighting cabinets, covering urban expressways, main roads, secondary roads, branch roads, sidewalks, and other road classes.
- Scenario Characteristics: Long lines, multiple circuits, evenly distributed loads, with high requirements for lighting reliability, energy efficiency, and maintenance efficiency. Requires centralized monitoring under unified city lighting management.
- Selection Recommendations: Recommend 12-24 circuit smart IoT floor-standing street lighting cabinets, configured with latitude/longitude control + 4G communication + energy metering + residual current protection, connected to the city lighting management platform.
- Application Value: Achieves fully automatic switching of road lighting without manual onsite operation; remote monitoring of operational status with proactive fault alarming improves lighting availability rates; latitude/longitude + midnight light modes reduce lighting energy consumption; unified platform management reduces inspection workload and lowers O&M costs.
- Configuration Details: One lighting cabinet every 500-1000 meters; circuits divided based on single/double-sided roads and pole spacing to ensure balanced single-circuit loading; enhanced surge protection in high lightning-prone areas.
7.2 Industrial Park Lighting
Industrial park lighting includes factory main roads, branch roads, storage yards, parking lots, and perimeter boundary lighting, serving as an important guarantee for factory safety in production.
- Scenario Characteristics: Large factory area with dispersed lighting points; some areas require high-brightness lighting for night production while others only require security low-brightness lighting; clear time-segmented control requirements.
- Selection Recommendations: Select 8-16 circuit smart street lighting cabinets based on area size, floor-standing or wall-mounted; can be connected to the factory energy management system.
- Application Value: Area-based and time-segmented control – full illumination during work shifts for production, security lighting retained after shifts, significantly reducing factory lighting energy consumption; unified control eliminates the need for manual security guard switching; residual current protection configuration enhances factory electrical safety and prevents personal electric shock risks.
- Special Configurations: Explosion-proof lighting cabinets for chemical parks and combustible dust hazardous areas; stainless steel anti-corrosion models for coastal industrial zones.
7.3 Scenic Area and Park Lighting
Scenic area and park lighting includes road streetlights, landscape lights, courtyard lights, lawn lights, and decorative lighting, serving both lighting and landscape functions.
- Scenario Characteristics: Diverse lighting types with large load power differences; different lighting schemes for holidays versus regular days; night landscape lighting requires scene mode switching; lush greenery environments with higher humidity.
- Selection Recommendations: Recommend multi-circuit smart latitude/longitude lighting cabinets with photocontrol function; road light circuits and landscape light circuits separately controlled.
- Application Value: One-key switching between regular day mode (basic road lighting) and holiday mode (all landscape lighting activated); automatic switching based on daylight conditions, landscape lights activated earlier on overcast days to enhance visitor experience; high protection rating adapts to humid, vegetation-rich park environments.
- Extended Features: Can be paired with human body sensors – lights on when people are present on remote paths and dim when unoccupied, further saving energy.
7.4 Residential Community Lighting
Residential community lighting includes community roads, plazas, building entrances, underground garage entrances, and perimeter boundary lighting, relating to resident travel safety and living experience.
- Scenario Characteristics: Dense lighting points with low individual luminaire power; long nighttime duration with high energy-saving requirements; property management requires ease of operation.
- Selection Recommendations: 6-8 circuit basic smart wall-mounted/floor-standing lighting cabinets with time control + photocontrol.
- Application Value: Automatic light switching eliminates manual operation by property staff, saving labor; reduced lighting brightness or partial circuit shutdown in the second half of the night lowers shared electricity costs; fault alarms promptly notify property management for rapid repair, ensuring resident travel safety.
- Humanized Design: Low-brightness mode can be set in the early morning hours, balancing safety and energy savings while avoiding light disturbance to residents.
7.5 Tunnel and Bridge Lighting
Tunnels and bridges are special traffic lighting scenarios with extremely high requirements for lighting continuity and reliability.
- Scenario Characteristics: Tunnels require 24-hour lighting with different brightness levels for daytime, nighttime, and emergency conditions; bridges are open environments with high lightning strike risk; humid and dusty conditions require high protection levels.
- Selection Recommendations: High-spec smart IoT lighting cabinets with dual power supply switching, enhanced surge protection, and temperature/humidity monitoring; moisture-proof models with higher protection ratings for tunnel interiors.
- Application Value: Graded brightness control automatically adjusts tunnel interior lighting based on external brightness, improving driving safety and avoiding the “black hole effect”; real-time operational monitoring with immediate fault alarming ensures uninterrupted tunnel lighting; enhanced lightning protection reduces lightning-related failures.
- Safety Redundancy: Important tunnels can be configured with dual power automatic transfer switching – automatic switchover to backup power on primary power failure, ensuring uninterrupted lighting.
7.6 New Rural and Village Road Lighting
Rural road lighting is an important component of rural revitalization infrastructure, with dispersed points, varying power supply conditions, and weak maintenance capacity.
- Scenario Characteristics: Short individual roads with scattered points; unstable power supply in some areas; lack of professional maintenance personnel requiring simple, reliable, maintenance-free equipment; relatively limited budgets.
- Selection Recommendations: 6-circuit basic time-controlled pole-mounted street lighting cabinets with simple structure, affordable price, and quick installation; photovoltaic integration option for solar-powered areas.
- Application Value: Automatic light switching eliminates manual operation by village staff; high-reliability design with low failure rates adapts to weak rural maintenance conditions; pole-mounted installation requires no concrete foundation, reducing construction costs and enabling fast installation.
- Solar Complementary Solution: For remote rural areas without grid access, off-grid lighting cabinets with solar + energy storage + LED can be configured for completely independent operation with flexible installation.
7.7 Other Application Scenarios
In addition to the above mainstream scenarios, street lighting cabinets can also be applied to:
- Parking Lot Lighting: Open-air and public parking lots; zone-based control with partial lighting shutdown during low-traffic periods.
- Plaza Lighting: Civic plazas and sports plazas; supports switching between large event mode and daily mode.
- Campus Lighting: School road and playground lighting; different modes for class periods, after-school, and vacations.
- Logistics Park Lighting: Time-segmented and zone-based control, adapting to logistics operation shifts.
- Airport and Port Lighting: Apron and dock yard lighting; custom high-reliability and high-protection configurations.
Different scenarios can be customized based on actual load conditions, environmental factors, and management requirements. Our company provides free solution design and selection guidance.
8.1 Pre-Installation Preparation
Adequate pre-installation preparation is the prerequisite for ensuring installation quality, construction safety, and schedule. Preparation should be made from five dimensions: technical, personnel, tools, materials, and site.
8.1.1 Technical Preparation
- Drawing Review: Before construction, organize technical personnel to review construction drawings, product installation manuals, and electrical schematics, clarifying key information such as installation location, circuit division, cable routing, and grounding requirements; verify that drawings match product specifications, promptly communicating any issues found with the design party or manufacturer.
- Technical Disclosure: The project technical leader conducts written technical disclosure to the construction crew, clarifying installation standards, operating procedures, quality requirements, and safety precautions. Both parties sign to confirm; emphasis on critical steps such as grounding specifications, protective sealing, and finished product protection.
- Plan Development: For large projects or complex sites, develop a dedicated installation construction plan clarifying construction sequence, personnel assignments, schedule, safety measures, and acceptance criteria, executed after approval.
- Qualification Confirmation: Confirm construction personnel hold valid electrician operation certificates, high-altitude work certificates, and other qualification certificates. Working without certification is strictly prohibited.
8.1.2 Personnel Preparation
Configure construction personnel based on project scale. Standard single floor-standing cabinet installation recommends:
- 1 Electrician: Responsible for electrical wiring, grounding testing, commissioning, and other electrical work.
- 1-2 Assistants: Responsible for foundation construction, cabinet handling, fixing, and auxiliary cable routing.
- 1 On-site Safety Officer: Required for large projects, responsible for on-site safety supervision and hazard identification.
All personnel must undergo safety training, be familiar with on-site safety management systems, and master emergency skills such as electric shock first aid and high-altitude fall rescue.
8.1.3 Tool Preparation
The following tools are required for installation. Check tool integrity and measuring instrument calibration validity before entering the site:
| Tool Category | Tool Name | Specification Requirement | Purpose |
|---|---|---|---|
| Measuring Tools | Steel Tape Measure | 5m | Dimension measurement, positioning and marking |
| Spirit Level | 600mm | Leveling and verticality calibration | |
| Plumb Bob | 0.5kg | Verticality calibration | |
| Earth Resistance Tester | 0-100Ω | Earth resistance measurement | |
| Megger (Insulation Resistance Tester) | 500V | Insulation resistance measurement | |
| Multimeter | Digital | Voltage measurement, continuity testing | |
| Construction Tools | Rotary Hammer Drill | Electric hammer type, with φ12/φ14 bits | Drilling holes in walls and floors |
| Socket Wrench Set | 8-24mm set | Tightening bolts | |
| Adjustable Wrench | 8″, 12″ | Tightening nuts | |
| Screwdrivers | Cross and flat head set | Tightening screws | |
| Wire Strippers | 0.5-6mm² | Stripping cable insulation | |
| Crimping Tool | For cold-pressed terminals | Crimping wire terminals | |
| Hacksaw/Cutting Machine | / | Cutting ground flat steel, conduits | |
| Soldering Iron | 30-60W | Soldering signal wires | |
| Rubber Mallet | / | Tapping cabinet for alignment, avoiding paint damage | |
| Safety Tools | Safety Helmet | Complies with GB 2811 | Head protection |
| Insulated Gloves | High voltage insulation | Live work protection | |
| Insulated Shoes | Electrician insulated shoes | Foot protection | |
| Safety Harness | For high-altitude work | High-altitude work protection | |
| Temporary Distribution Box | With residual current protection | Temporary construction power | |
| Warning Signs | “DANGER – DO NOT CLOSE – MEN AT WORK” | Power-off operation warning | |
| Auxiliary Tools | Cable Ties, Markers, Insulation Tape, Sandpaper, Rags | / | Cable routing, labeling, cleaning |
8.1.4 Material Preparation
Prepare corresponding auxiliary materials based on installation method. Verify specifications and quantities in advance to ensure quality:
- Foundation Construction Materials: Cement (P.O 42.5), river sand, crushed stone, reinforcing bar (φ8-φ12), formwork (wood or steel), anchor bolts (M12/M16, galvanized).
- Fixing Materials: Expansion bolts (M12×100/M16×150, stainless steel or galvanized), chemical anchors (when concrete strength is insufficient).
- Grounding Materials: Earth electrode (∠50×50×5 galvanized angle steel, 2.5m length), grounding flat steel (-40×4 galvanized flat steel), grounding bolts, galvanized nuts, flat washers, spring washers, anti-corrosion asphalt paint.
- Sealing Materials: Waterproof cable glands, sealing putty, fire-stop putty, neutral silicone sealant.
- Cable Routing Materials: Cable ties, wire number sleeves, terminal blocks, cold-pressed terminals, insulation sleeves, identification labels.
8.1.5 Site Survey and Positioning
On-site Environment Inspection:
- Check whether the installation position ground/wall is solid, with no settlement, cracking, or loosening, and whether load-bearing capacity meets requirements.
- Check for flammable/explosive materials, corrosive gases, and strong electromagnetic interference sources nearby.
- Check whether the installation position is prone to water accumulation or vehicle collision; install anti-collision barriers and drainage measures as necessary.
- Check whether the power incoming cable route is clear and cable laying is feasible.
- Check whether the installation position obstructs traffic sight lines or pedestrian passage, ensuring compliance with road safety regulations.
Installation Position Selection Principles:
- Choose elevated, dry, and well-ventilated locations, avoiding low-lying water-prone areas.
- Facilitate cable routing and future maintenance, with sufficient operating space and cabinet door opening angle ≥90°.
- Avoid strong vibration, strong corrosion, and flammable/explosive hazardous areas.
- Position close to the load center as much as possible to reduce outgoing cable length and line losses.
- Comply with municipal planning requirements without affecting aesthetics and passage.
Positioning and Marking:
- Determine the specific cabinet installation position based on drawings and actual site conditions. Use a marker to draw installation reference lines and hole position lines. Mark foundation excavation boundary lines for floor-standing cabinets, and mounting hole positions for wall/pole-mounted cabinets.
8.2 Floor-Standing Installation Construction Process
Floor-standing installation is the most commonly used method for street lighting cabinets, suitable for large cabinets with 12 circuits or more, providing stable installation and convenient maintenance.
8.2.1 Foundation Construction
Foundation Excavation:
- Excavate the foundation pit based on cabinet dimensions. Foundation dimensions should be 100-200mm larger than the cabinet bottom dimensions, with a foundation depth of ≥500mm (northern permafrost areas must exceed the frost depth).
- Compact the pit bottom, with flatness deviation ≤10mm; for soft soil, lay a 100mm thick crushed stone cushion and compact to improve bearing capacity.
Rebar Tying and Formwork Installation:
- Configure φ8@200 bidirectional rebar mesh within the foundation, double layers, with protective layer thickness ≥30mm to improve crack resistance.
- Install wood formwork with accurate dimensions and firm support to prevent deformation during pouring. Apply release agent to the inside of the formwork for easy removal.
Anchor Bolt Embedment:
- Prefabricate anchor bolt positioning plates according to the cabinet base mounting hole dimensions to ensure accurate bolt spacing and verticality.
- Use M16 galvanized bolts with embedment depth into concrete ≥300mm, with bent hooks at the bottom for enhanced anchoring force.
- Bolt protrusion above the foundation top surface: 50-70mm, sufficient for nut tightening. Verify bolt positions before pouring and correct deviations during pouring.
Concrete Pouring:
- Use C20 ready-mix concrete or site-mixed concrete with mix ratio of cement: sand: stone = 1:2:3, water-cement ratio ≤0.5.
- Pour in layers with vibration, using a vibrator to ensure compaction, avoiding honeycombing, surface voids, and voids.
- Level and finish the foundation top surface, with flatness deviation ≤5mm; the top surface should be 100-200mm above ground level to prevent rainwater from entering the cabinet base.
Curing and Formwork Removal:
- Cover and water-cure within 12 hours after pouring, with watering at least 3 times daily under normal temperatures, for a minimum of 7 days.
- Winter construction requires insulation measures, covering with insulation blankets and adding antifreeze admixtures as needed.
- Formwork can be removed when concrete strength reaches 70% (approximately 3 days at normal temperature). Cabinet installation can proceed when strength reaches 100% (approximately 7 days).
8.2.2 Cabinet Handling and Positioning
Handling Precautions:
- Upon delivery of the cabinet to site, check packaging integrity, open the box to inspect for damage, deformation, component displacement, or missing accessories. Promptly contact the manufacturer if damaged.
- Keep the cabinet upright during handling; tipping or laying on sides is strictly prohibited to avoid internal component displacement or damage.
- Use team lifting with careful handling; dragging or rolling is strictly prohibited. When using forklifts or cranes, apply force at the cabinet base, avoiding compression of the door and side panels.
- Protect the cabinet paint surface and sealing strips during handling to avoid scratches and damage.
Positioning and Alignment:
- Place the cabinet gently onto the foundation, aligning anchor bolt holes and lowering slowly.
- Use a spirit level to measure the cabinet top and side surfaces, adjusting levelness and verticality with shims:
- Levelness deviation ≤2mm/m
- Verticality deviation ≤1.5mm/m
- Total cabinet height deviation ≤5mm
- After alignment, tighten anchor bolt nuts sequentially with diagonal uniform force to avoid cabinet deformation.
8.2.3 Grounding System Installation
The grounding system is the core of electrical safety and must be constructed strictly in accordance with specifications to ensure compliant grounding resistance.
Earth Electrode Fabrication and Driving:
- Use ∠50×50×5 galvanized angle steel, 2.5m length, with one end cut to a sharp point for ease of driving.
- Select a location with low soil resistivity 1-2m from the cabinet foundation; drive the electrode vertically with the top 0.8-1m below ground level.
- Drive vertically, using a wooden block when hammering the top to avoid deformation. For multiple electrodes, maintain ≥5m spacing and connect them with grounding flat steel to form a grounding grid.
Grounding Flat Steel Laying:
- Use -40×4 galvanized flat steel for the grounding main conductor, laid along the grounding trench with welded connections.
- Lap connection length should be 2 times the width (≥80mm), welded on three sides (top, bottom, and side), with full and smooth welds, free from slag inclusions, cold welding, and undercut.
- After welding, remove slag and apply two coats of anti-corrosion asphalt paint to the welds to extend service life.
- Weld one end of the flat steel to the earth electrode and route the other end to the cabinet grounding terminal, leaving sufficient connection length.
Cabinet Grounding Connection:
- A dedicated grounding bolt is provided at the cabinet base. Use copper wire of not less than 16mm² cross-section or galvanized flat steel to connect reliably to the grounding main conductor.
- Equip connection bolts with flat washers and spring washers, tightened securely to ensure grounding continuity.
- The internal grounding busbar must be reliably connected to the cabinet enclosure. All components requiring grounding are connected to the grounding busbar via grounding wires.
Grounding Resistance Test:
- After grounding system construction, measure grounding resistance with an earth resistance tester.
- Street lighting system grounding resistance requirement: ≤4Ω. If not met, increase the number of earth electrodes, replace soil, or add resistance-reducing agents until compliant.
- File test records as acceptance documentation.
8.2.4 Cable Entry/Exit Hole Sealing
- After cable laying, install waterproof cable glands on the bottom cable entry holes. Insert cables through the glands and tighten the lock nuts for cable fixation and sealing.
- Unused knock-out holes must retain their sealing plugs. Removing plugs without use is strictly prohibited.
- Fill gaps between cables and the cabinet body with sealing putty to ensure complete sealing, preventing rainwater, insects, and rodents from entering the cabinet.
- Seal the gap between the cabinet base and foundation with waterproof mortar, leveled smoothly, and apply neutral silicone sealant externally as a second layer of waterproofing.
8.3 Wall-Mounted Installation Construction Process
Wall-mounted installation is suitable for small cabinets with 6-8 circuits, installed on solid walls to save ground space.
8.3.1 Wall Inspection and Hole Positioning
- The mounting wall must be solid brick, concrete, or other load-bearing wall. Installation on lightweight partition walls or hollow brick walls is strictly prohibited. Wall load-bearing capacity must be ≥2 times the total cabinet weight.
- Mark mounting hole positions on the wall according to wall-mounting bracket mounting hole dimensions. Recommended mounting height: cabinet bottom 1.2-1.5m above ground for convenient operation and maintenance.
- Ensure hole positions avoid reinforcing bars and embedded piping within the wall. Use a pipe/cable detector before drilling.
8.3.2 Drilling and Bracket Fixing
- Drill holes with a rotary hammer drill, matching hole diameter and depth to expansion bolt specifications. M12 expansion bolts correspond to φ14 drill bits, with drilling depth ≥120mm.
- Clean dust from holes, insert expansion bolts, align wall-mounting bracket to the holes, and tighten nuts to ensure firm, level bracket installation.
- Brackets are made of galvanized or stainless steel for corrosion resistance; rubber pads can be placed between bracket and wall for vibration damping and wall surface protection.
8.3.3 Cabinet Installation and Alignment
- Two people coordinate to lift the cabinet and hang it onto the bracket, securing the cabinet to the bracket with matching bolts.
- Use a spirit level to calibrate cabinet levelness and verticality, with the same deviation requirements as floor-standing installation.
- Route grounding flat steel along the wall, connecting one end to the earth electrode and the other end to the cabinet grounding terminal. Grounding resistance ≤4Ω.
8.4 Pole-Mounted Installation Construction Process
Pole-mounted installation is suitable for rural roads and scattered points, directly installed on street light poles without requiring a foundation for quick construction.
8.4.1 Pole Adaptability Check
- Compatible pole diameter: φ60-φ200mm. Custom mounting clamps required outside this range.
- Poles must be sturdy and free from rust, with adequate load-bearing capacity. Recommended installation height: 2.5-3m above ground to avoid personnel contact and vehicle collision while facilitating maintenance access.
8.4.2 Clamp Installation and Cabinet Fixing
- Use double-clamp fixing method with upper and lower clamps for enhanced stability. Clamps are galvanized, width ≥50mm, thickness ≥3mm.
- Place anti-slip rubber pads between clamps and pole to increase friction, prevent cabinet sliding, and protect the pole paint surface.
- Connect the cabinet mounting backplate to the clamps, adjust level and verticality, then tighten bolts.
- Check cabinet firmness by shaking – no looseness should be felt, ensuring wind resistance compliance.
For grounding, the pole grounding system can be utilized. Reliably connect the cabinet grounding terminal to the pole grounding point and test grounding resistance ≤4Ω.
8.5 Post-Installation Internal Inspection
After cabinet fixation, perform a comprehensive internal inspection before power-on to eliminate issues caused during transportation and installation:
- Component Inspection: Check all circuit breakers, contactors, controllers, terminal blocks, and other components for looseness, displacement, or detachment. Tighten all fixing screws. Check components for damage, moisture, or water ingress traces; address any anomalies promptly.
- Wiring Inspection: Check internal wiring for looseness, detachment, or poor contact, focusing on main circuit high-current terminals. Check wiring labels for clarity and completeness, checking for incorrect connections or short-circuit hazards.
- Debris Cleanup: Clean dust, debris, leftover screws, and wire clippings from inside the cabinet to prevent short circuits. Replace expired desiccant.
- Door Inspection: Check door opening/closing smoothness, sealing strip fit, and lock function. Apply a small amount of lubricating oil to the lock cylinder for smooth operation.
- Label Verification: Verify circuit labels, warning labels, and grounding labels are complete and accurate, consistent with drawings.
8.6 Installation Safety Regulations
- On-site Electrical Safety: Temporary construction power must use three-level distribution with two-level protection, with residual current protection devices in distribution boxes. Check power tools for insulation integrity and cables for damage before use. Unauthorized wiring connections are strictly prohibited.
- High-Altitude Work Safety: Wall-mounted and pole-mounted installations constitute high-altitude work. Workers must wear safety harnesses, hooked from above. Tools must be kept in tool bags. Throwing tools or materials up or down is strictly prohibited. Set up warning zones below to keep personnel clear.
- Foundation Construction Safety: Prevent trench collapse during excavation; support required for depths exceeding 1.5m. Watch for machinery hazards during concrete pouring. Prevent falling injuries during formwork removal.
- Electrical Work Safety: All electrical work must be performed with power disconnected, with “DANGER – DO NOT CLOSE – MEN AT WORK” warning signs hung, and dedicated personnel assigned for supervision. Live work is strictly prohibited. Special safety measures must be developed for exceptional live-work situations.
- Finished Product Protection: After installation, protect the cabinet from subsequent construction scratches and impacts. Keep the cabinet door closed and locked to prevent unauthorized operation.
Wiring is the core phase of street lighting cabinet construction. Wiring quality directly affects equipment operational reliability and safety. Electrical wiring specifications must be strictly followed to achieve “correct connections, reliable contact, clear labeling, and neat cable routing.”
9.1 Pre-Wiring Preparation
9.1.1 Technical and Safety Preparation
- Familiarize with electrical schematics, wiring diagrams, and circuit correspondence tables, clarifying the correspondence, cable specifications, and routing for each circuit.
- Confirm that the upstream power supply has been disconnected, verify zero voltage with testing equipment, hang power-off warning signs, and execute the “power off, verify, ground, tag, supervise” power-off procedure.
- Workers must wear insulated shoes and insulated gloves, use insulated tools, and have dedicated supervision.
9.1.2 Cable Selection and Inspection
Main Circuit Cables:
- Lighting main circuits use copper-core PVC insulated cables (BV) or armored power cables (YJV22); armored cables are preferred for outdoor direct burial or conduit installation.
- Wire gauge is based on circuit rated current, with 1.2-1.5 times safety margin reserved. Reference selection:
| Circuit Rated Current | Copper Cable Cross-Section | Remarks |
|---|---|---|
| ≤10A | 1.5mm² | Small power LED circuits |
| 10-16A | 2.5mm² | Standard street light circuits |
| 16-25A | 4mm² | High-power street lights/landscape lights |
| 25-32A | 6mm² | Multi-luminaire centralized circuits |
- Incoming main cable is selected based on total current: 25mm² copper cable for 100A main switch, 35mm² for 160A, and 70mm² for 250A.
Control Circuit Cables:
- Use 1.0-1.5mm² copper stranded flexible wire (RV); color coding: red for phase/live, blue for neutral, yellow-green for ground, black for signal wires.
- Weak-current signal wires use shielded cable (RVVP) to avoid interference from power circuits.
Grounding Cables:
- Protective ground wire uses yellow-green bicolor copper wire with cross-section not less than 1/2 of the corresponding phase conductor, and not less than 2.5mm².
- Main grounding conductor uses flat steel or copper wire of 16mm² or larger.
Cable Inspection:
- Check for certificate of conformity and CCC certification upon cable delivery; specifications and models must comply with design requirements.
- Visual inspection for insulation damage, aging, and oxidation.
- Measure cable insulation resistance with a Megger; ≥0.5MΩ qualifies. Cables with substandard insulation are strictly prohibited from use.
9.1.3 Tool and Auxiliary Material Preparation
- Tools: Wire strippers, crimping tools, diagonal cutters, screwdrivers, multimeter, soldering iron, heat gun, cable tie gun.
- Auxiliary Materials: Cold-pressed terminals (cable lugs), wire number sleeves, insulation tape, heat shrink tubing, cable ties, identification labels, fire-stop putty, terminal blocks.
9.2 General Wiring Specifications
Phase Sequence and Color Specifications:
- Three-phase conductors: L1 yellow, L2 green, L3 red
- Neutral N: light blue
- Protective ground PE: yellow-green bicolor
- DC positive: brown, negative: blue
- Mixing colors is strictly prohibited. Using the ground wire as neutral or phase wire is strictly prohibited.
Wire Stripping Specifications:
- Stripping length should match the terminal, with copper exposed 0.5-1mm beyond the terminal as appropriate – neither too long nor too short.
- Use dedicated wire strippers; avoid damaging copper strands, and prevent strand breakage or spreading.
- Stranded flexible wires must be terminated with cold-pressed terminals after stripping. Direct insertion of bare stranded wire into screw terminals is strictly prohibited.
Terminal Crimping Specifications:
- Select matching cold-pressed terminals based on wire gauge; tin-plated copper lugs provide good conductivity.
- Ensure firm crimping; wires must not pull out under tension test. After crimping, no copper strands should be exposed and insulation must not be crimped into the terminal.
- Large cross-section cables use hydraulic crimping tools, with indentation count and depth in compliance with specifications.
Screw Tightening Specifications:
- Terminal screws must be fully tightened to minimize contact resistance and prevent operational heating.
- Different wire gauges correspond to different tightening torques; reference values: 2.5mm² correlates to 0.8-1.0N·m, 4mm² to 1.2-1.5N·m, 10mm² to 2.5-3.0N·m.
- After tightening, gently pull the wire to confirm no loosening. Multiple stranded wires must be crimped before terminal insertion; twisting multiple strands directly into a terminal is strictly prohibited.
Cable Routing Specifications:
- Internal wiring should be neat and orderly (horizontal and vertical), with power and control wiring kept separate to avoid crossing.
- Cables are bundled and fixed with cable ties at even intervals (150-200mm), with appropriate tightness that does not damage insulation.
- Cable bends should be smooth arcs with bend radius ≥6 times the cable diameter, avoiding sharp bends that damage insulation.
- Cables for movable parts (cabinet door) should have slack allowance, using stranded flexible wire with corrugated tube protection, not subject to tension during repeated opening/closing.
- All cables should have wire number sleeves with clear, consistently oriented labels for easy maintenance.
Grounding Specifications:
- Cabinet body, doors, all electrical component metal enclosures, and cable shields must all be reliably grounded.
- Grounding connection wires use yellow-green bicolor wire, connected to the dedicated grounding busbar. Each terminal accepts no more than 2 wires.
- Grounding circuits must never be daisy-chained (series-connected); each must connect directly to the grounding busbar.
9.3 Main Circuit Wiring
The main circuit wiring involves high-voltage connections and is the key focus of the wiring work. It must be strictly carried out according to the schematic diagram to ensure correct phase sequence and reliable contact.
9.3.1 Incoming Power Supply Wiring
Route the three-phase incoming cables (L1, L2, L3, N, PE) from the cable entry holes at the bottom of the cabinet and secure them with cable glands;
Connect the PE wire directly to the grounding copper bar inside the cabinet, tighten with bolts to ensure good contact;
Connect the L1, L2, L3 phase wires and the N neutral wire to the incoming terminals of the main circuit breaker, connecting them according to the corresponding phase sequence and tightening the terminal blocks;
For large cross-section cables, crimp lugs and then tin them to increase the contact area and reduce contact resistance;
Reserve a 10-15cm allowance for incoming cables to facilitate future maintenance. Bundle and secure the allowance portion.
9.3.2 Busbar and Branch Circuit Wiring
Connect the outgoing terminals of the main circuit breaker to the busbar or branch circuit incoming wires. Distribute the load evenly across the three phases. For example, for 12 circuits, distribute as follows: L1 supplies circuits 1-4, L2 supplies circuits 5-8, L3 supplies circuits 9-12, ensuring three-phase current balance;
Connect the phase wires to the incoming terminals of branch circuit breakers correspondingly, and connect all neutral wires uniformly to the neutral busbar;
Connect the outgoing terminals of the branch circuit breakers to the incoming terminals of the main contacts of the AC contactors, and connect the outgoing terminals of the contactor main contacts to the outgoing terminal blocks;
Each circuit must be connected strictly according to its circuit number to avoid misconnection. After wiring, verify that the circuit numbers are consistent with the circuit breaker numbers.
9.3.3 Outgoing Circuit Wiring
Route the cables for each lighting circuit out from the cable exit holes at the bottom and secure them with cable glands;
Connect the circuit live wires to the corresponding outgoing terminals, the neutral wires to the neutral busbar, and the PE wires to the grounding copper bar;
Insulate the spare cores of multi-core cables properly, bundle and secure them, reserving them for future expansion;
Leave an appropriate allowance for outgoing cables outside the cabinet to facilitate luminaire connection and maintenance.
9.3.4 Surge Protective Device (SPD) Wiring
Connect the surge protective device in parallel at the outgoing side of the main circuit breaker. Connect the three-phase wires and the neutral wire to the corresponding SPD terminals, and connect the PE terminal to the grounding copper bar;
Keep the wiring as short and straight as possible, length ≤ 0.5m, to reduce lead inductance and improve surge discharge effectiveness;
Use stranded copper wire with a cross-section of not less than 2.5mm² to ensure adequate discharge capacity.
9.4 Control Circuit Wiring
The control circuit acts as the bridge between low-voltage control and high-voltage power. Wiring accuracy directly affects control functions and requires careful verification point by point.
9.4.1 Control Power Supply Wiring
Take one phase wire and the neutral wire from the outgoing terminals of the main circuit breaker as the control circuit power supply. Connect a 2A fuse in series at the front end for short-circuit protection;
Connect the power supply to the intelligent controller power terminals, the time switch power terminals, and the indicator light power terminals;
Verify that the control voltage matches the rated voltage of the components, typically AC220V, to avoid connecting 380V and burning out components.
9.4.2 Contactor Control Wiring
Connect the control live wire output from the controller sequentially to one end of the coil of the corresponding contactor;
Connect the other ends of all contactor coils in parallel and then connect to the control neutral wire;
Connect the manual/auto transfer switch in series in the control circuit. When switched to manual, directly control the contactors; when switched to auto, the controller takes over;
Contactor auxiliary contacts can be connected to indicator lights and feedback signals as required to provide status indication.
9.4.3 Indicator Light and Button Wiring
Connect the power indicator light in parallel across the control power supply terminals. It lights up when the power is switched on;
Connect the circuit indicator lights in parallel at the outgoing terminals of the corresponding contactor main contacts. They light up when the circuit is energized;
Connect the fault indicator light to the fault output contacts of the protector. When a fault occurs, the contacts close and the indicator light illuminates;
Wire the buttons and switches on the cabinet door panel according to the wiring diagram, ensuring the operation direction and logic are consistent.
9.5 Sensor and Communication Circuit Wiring
9.5.1 Photocontrol Sensor Wiring
Use shielded cable for the photocontrol sensor connection. Ground the shield layer at a single end (at the grounding copper bar inside the cabinet);
Connect the sensor power wires and signal wires to the corresponding photocontrol terminals on the controller. Do not reverse the positive and negative poles;
Route the sensor probe outside the cabinet. Install it in a location with direct sunlight, no obstructions, and no interference from artificial light sources. Secure it firmly and provide waterproofing;
If the cable length is insufficient, use an intermediate junction box for connection, ensuring waterproofing and insulation.
9.5.2 Communication Module and Antenna Wiring
Install the 4G/NB-IoT module in the low-voltage area in the upper part of the cabinet. Connect its power supply to the DC output of the controller or a dedicated power supply;
Connect the communication interface (RS485/TTL) to the main controller accordingly, ensuring the A and B wire sequences are correct without reversal;
Route the antenna feeder cable through the waterproof hole on the cabinet top and connect it to the antenna interface on the module. Tighten the connector to ensure good contact;
Install the antenna on the outside of the cabinet top, pointing vertically upward, avoiding metal obstructions to ensure signal strength. Apply sealant around the antenna connector for waterproofing.
9.5.3 Other Sensor Wiring
For auxiliary components such as temperature and humidity sensors, door magnetic switches, and leakage current transformers, connect them according to the corresponding product manuals. Pay attention to separating signal wires from power wires to avoid interference.
9.6 Post-Wiring Inspection and Labeling
9.6.1 Continuity and Insulation Inspection
Visual Inspection: Check each wire one by one for correct connection, ensuring no misconnections, missing connections, or loose connections; check if the wiring is neat and labels are clear;
Continuity Test: With the power off, use the continuity setting on a multimeter to test the continuity of each circuit and verify consistency with the switch states; check for short circuits and ground faults;
Insulation Resistance Test:
Disconnect all low-voltage components. Use a 500V megohmmeter to measure the insulation resistance between phases, phase-to-neutral, and phase-to-ground of the main circuit. A reading of ≥ 0.5MΩ is considered acceptable;
The insulation resistance for control circuits should be ≥ 0.5MΩ, and for low-voltage circuits ≥ 1MΩ;
If insulation resistance fails, investigate the cause point by point. Only proceed with energization after the fault is resolved.
9.6.2 Labeling Improvement
Fit heat-shrink wire markers at both ends of all cables, indicating the circuit number and wire number with clear fonts and consistent orientation;
Affix corresponding circuit labels to each circuit breaker, contactor, and terminal block;
Post a circuit comparison table, electrical schematic diagram, and operation instructions on the inside of the cabinet door;
Affix “Danger – High Voltage” warning signs, grounding signs, and equipment identification plates on the outside of the cabinet;
Attach identification tags to both ends of outgoing cables, specifying the circuit number, destination, and specifications.
9.6.3 Sealing and Tidying
Seal all cable entry and exit holes completely with cable glands and sealing compound, ensuring no gaps are left;
Arrange and bundle the cables inside the cabinet neatly. Coil any excess cable neatly and secure them firmly;
Clean up tools and debris from inside the cabinet. Wipe away dust to keep the cabinet interior clean.
9.7 Typical Wiring Examples
9.7.1 12-Circuit LED Street Light Wiring Example
Main Incoming Cable: 3×16mm² + 1×10mm² + PE10mm² YJV22 armored cable;
Main Circuit Breaker: 100A/3P molded case circuit breaker;
Branch Circuits: Each circuit uses 2.5mm² BV wire, supplying 10 units of 150W LED street lights, with a single circuit current of approximately 7A;
Three-Phase Distribution: L1 supplies circuits 1-4, L2 supplies circuits 5-8, L3 supplies circuits 9-12;
Control: The controller’s 12 outputs control the coils of 12 contactors rated at 18A respectively;
Grounding: The PE wires of all luminaires are connected in series and then connected to the grounding bar inside the cabinet.
9.7.2 Solar-Assisted Street Light Wiring Example
Connect the DC incoming wires from the photovoltaic (PV) modules to the DC input terminals of the MPPT controller;
Connect the battery bank to the energy storage terminals of the controller;
Connect the DC output of the controller to the DC side of the inverter. The inverter outputs 220V AC power, which is connected to the main circuit of the lighting cabinet;
The mains power serves as backup power, connected via a dual power transfer switch. When PV power is insufficient, it automatically switches to mains power;
Pay attention to the positive and negative poles on the DC side. Reversing the connection will burn out the controller. Use dedicated PV cables for DC wiring.
9.8 Wiring Safety Precautions
Strictly implement lockout/tagout procedures. It is strictly forbidden to work on live wires. Before wiring, test for the absence of voltage and confirm zero energy before proceeding;
Pay attention to tool safety when stripping wires and crimping to avoid hand injuries;
When handling and connecting large cross-section cables, use multiple people to coordinate and prevent crushing or pinching injuries;
Temporarily exposed wire ends during wiring must be properly insulated to prevent accidental short circuits;
After completing the wiring, conduct a comprehensive check again. Only after confirming there are no short circuits or misconnections can you apply for energization for commissioning.
Commissioning is a critical step to verify installation and wiring quality, validate product functions, and ensure normal equipment operation. It must follow the principle of “inspect before energizing, test no-load before loaded, test local before global, test function before performance,” and be carried out systematically.
10.1 Pre-Commissioning Preparation
10.1.1 Personnel and Documentation Preparation
Commissioning personnel must be certified electricians familiar with product principles and operating methods, possessing electrical commissioning experience;
Prepare the product manual, electrical schematic diagram, wiring diagram, and commissioning record sheet;
Arrange for 1 assistant to cooperate, responsible for closing switches, observing luminaire status, etc. Designate a dedicated person for safety supervision.
10.1.2 Tool and Instrument Preparation
| Instrument/Tool | Specification | Purpose |
|---|---|---|
| Digital Multimeter | Accuracy 0.5 grade | Measure voltage, current, resistance |
| Clamp Meter | 0-500A | Measure circuit load current |
| 500V Megohmmeter | / | Measure insulation resistance |
| Light Meter | 0-200,000 Lux | Calibrate photocontrol sensor |
| Phase-Volt-Ammeter | / | Detect phase sequence, power factor |
| Voltage Tester | Low voltage | Voltage testing |
| Walkie-talkies | A pair | Communication between cabinet and luminaire end |
| Laptop/Phone | / | Commission smart controller, test remote functions |
| Insulated Tools | Screwdrivers, wrenches, etc. | Live commissioning operations |
| Safety Protection Equipment | Insulated gloves, insulated shoes, safety helmet | Personal protection |
10.1.3 Site and Safety Preparation
Clean the commissioning site, remove unrelated debris, and ensure sufficient operating space;
Confirm all luminaires are installed, load wiring is correct, and there are no short circuits or ground faults;
Verify that the upstream power supply is normal and voltage meets rated requirements;
Ensure all circuit breakers and switches are in the OFF position, and the controller is in its initial state;
Set up a warning area, prohibit unrelated personnel from entering, and hang a “Commissioning in Progress – Do Not Close” warning sign.
10.2 Comprehensive Pre-Power-On Inspection
Before energization, the following checks must be completed to confirm no hazards exist:
Installation Quality Check: Cabinet is installed securely, levelness and verticality meet standards; grounding system is reliably connected and ground resistance test passed; cable entries and exits are properly sealed.
Wiring Quality Check: All wiring is correct, tight, with no misconnections, missing connections, or loose connections; phase sequence is correct, color coding is standard; labels are clear and complete; no exposed live parts.
Component Status Check: All circuit breakers, contactors, and controllers are in good condition, undamaged, and free from moisture; surge protective device indicators are normal; component parameters match design specifications.
Insulation Resistance Re-test: Re-measure the insulation resistance of the main circuit and control circuit to confirm compliance; disconnect all low-voltage modules to prevent insulation testing from damaging microchips.
Load Side Check: Confirm all luminaire switches are OFF, the load side has no short circuits, no ground faults, and no personnel are working on the load side.
10.3 No-Load Energization Commissioning
No-load commissioning means energizing without a load to verify the electrical and control functions of the cabinet itself, avoiding load faults interfering with equipment assessment.
10.3.1 Closing and Powering On
Confirm all branch circuit breakers and contactors are in the OFF position, and the controller power switch is OFF;
Close the upstream power switch. Test the voltage and confirm the incoming voltage is normal, the three-phase voltage is balanced, with a deviation ≤ 5%;
Slowly close the main circuit breaker and observe the cabinet for any abnormal noise, odor, or arcing. If any abnormality is found, immediately de-energize and investigate;
Measure the three-phase voltage at the main circuit breaker outgoing terminals and the neutral-to-ground voltage to confirm normal voltage and no phase loss.
10.3.2 Power Supply and Indicator Check
Observe whether the power indicator lights up with the correct color;
Measure the control circuit power supply voltage. The deviation from the rated value should be ≤ ±10%;
Close the controller power switch and observe whether the controller starts up normally, the display screen lights up, and no error messages are shown;
Check the surge protective device status indicator. Green indicates normal, red indicates failure. If failed, replace it immediately.
10.3.3 Manual Control Commissioning
Switch the transfer switch to the “Manual” mode;
Press the manual control buttons one by one or close the contactors, observing whether the corresponding contactors engage reliably without abnormal noise or chatter;
Verify that the corresponding circuit indicator lights illuminate simultaneously and are consistent with the actual state;
Measure the voltage at the contactor outgoing terminals. The voltage should be normal without phase loss;
Test the manual control functions of all circuits one by one. All functions operating normally constitutes a pass.
10.4 Loaded Energization Commissioning
After no-load commissioning is successful, proceed to loaded commissioning to verify the capability of operation under load.
10.4.1 Single Circuit Loaded Testing
Keep other circuits OFF. Close the circuit breaker for the first circuit, allow the contactor to engage, and energize the first circuit;
Observe whether the luminaires light up normally without flickering or failure to light;
Use a clamp meter to measure the operating current of this circuit and compare it with the theoretical calculated value. If the deviation is excessive, investigate the cause (luminaire power mismatch, poor wiring, abnormal voltage, etc.);
Run for 10 minutes and check the circuit breaker, contactor, and wiring terminals for overheating. A temperature of ≤ 60°C is considered normal;
After a single circuit tests normal, open that circuit and test all branch circuits one by one, troubleshooting faults as they arise.
10.4.2 Full Circuit Loaded Testing
After all single circuit tests are normal, close all circuits one by one and run at full load;
Measure the total three-phase current and check the three-phase balance. An unbalance of ≤ 25% is acceptable; if the unbalance is too large, adjust the circuit distribution;
Measure the total incoming voltage and check whether the voltage drop under load is within the allowable range;
Check the neutral current. Under normal three-phase balance, the neutral current should be very small. An excessively high neutral current indicates severe three-phase unbalance or the presence of harmonics;
Run continuously at full load for 30 minutes. Observe the operating status of all components. No overheating, no abnormal noise, and no tripping constitutes a pass.
10.5 Individual Function Commissioning
10.5.1 Time Control Function Commissioning
Enter the controller’s time control setting interface and set the current accurate time;
Set a set of test on/off times, for example, lights ON in 2 minutes and lights OFF in 5 minutes;
Wait for the set time and observe whether the controller outputs the control signal on time, whether the contactors operate, and whether the luminaires switch on/off synchronously;
Test multiple timing groups, holiday timing, and midnight light mode. Accurate operation of all functions constitutes a pass;
Test the power-off retention function: disconnect the controller power for 1 minute and then restore power. Check whether the time is lost and whether the set parameters are retained.
10.5.2 Photocontrol Function Commissioning
Enter the controller settings, enable photocontrol mode, set the lights-ON threshold and lights-OFF threshold, and set the delay time;
Completely cover the photocontrol sensor with a black cloth to simulate a night environment. After the delay time, observe whether the lights turn on automatically;
Remove the black cloth to simulate a daytime environment and observe whether the lights turn off automatically;
Test the threshold adjustment function. After modifying the threshold, verify whether the operation matches the settings;
Test the anti-flicker function: quickly shine a flashlight at the sensor. It should not operate frequently and erroneously.
Use a light intensity meter to calibrate the sensor accuracy. An error of ≤ 10% is considered acceptable.
10.5.3 Latitude/Longitude Control Commissioning
Enter the latitude/longitude settings interface on the controller and input the accurate latitude and longitude of the project site;
The controller automatically calculates the sunrise and sunset times for the day. Verify that the calculated results are consistent with the actual local sunrise and sunset times. An error of ≤ 5 minutes is acceptable;
Set to latitude/longitude control mode and verify that the lights turn on automatically at sunset and off at sunrise;
Test the latitude/longitude + photocontrol correction mode and verify that the photocontrol adjusts based on the latitude/longitude calculation.
10.5.4 Protection Function Commissioning
Overload Protection Test:
Test by adding load or adjusting circuit breaker parameters to verify that the circuit breaker trips reliably during overload;
Note: Strictly avoid prolonged overload. Restore immediately after testing to avoid burning out equipment.
Leakage Protection Test:
Press the “Test” button on the leakage protector. The protector should trip immediately, verifying the leakage protection function is normal;
After testing, reset the circuit breaker and restore normal power supply;
It is recommended to test the leakage protection function once a month.
Surge Protection Function:
Visually inspect the surge protective device status indicator window. Green indicates normal, red indicates failure;
If conditions permit, use a surge generator for simulated testing. Generally, only visual and status checks are performed on-site.
Overvoltage/Undervoltage Protection:
For smart models, set voltage thresholds and simulate overvoltage/undervoltage conditions to verify the alarm and tripping functions.
10.5.5 Intelligent Communication and Remote Function Commissioning
Communication Network Test:
Check the 4G module signal strength. A signal strength of ≥ -75dBm is considered good. If the signal is poor, adjust the antenna position;
Observe the module’s network connection status. After successful connection, the indicator light should be solid or blink regularly;
Check on the platform end whether the device is online and whether data is uploading correctly.
Remote Control Test:
On the cloud platform or mobile APP, send single-circuit on/off commands remotely. Verify that the commands are issued successfully, the circuits operate accurately, and status feedback is timely;
Test batch group control and scene mode switching functions;
Test the remote parameter modification function. Modify the timing time and check whether the device updates synchronously.
Alarm Function Test:
Simulate a fault (e.g., open a branch circuit breaker) and check whether the platform receives the alarm information and whether the alarm push notification is timely;
Test alarm methods such as SMS and APP push notifications to ensure notification delivery.
Data Upload Test:
Verify that the voltage, current, power, and other data displayed on the platform are consistent with on-site instrument measurements, within the allowable error range;
Test the historical data storage, query, and export functions.
10.6 System Integration Testing and Trial Operation
Multi-Cabinet Integration: For projects with multiple lighting cabinets, test the unified scheduling and centralized management functions. Verify group control, scene mode, and batch timing strategy distribution functions;
Interlocking Test: For projects integrating with smart light poles, security systems, fire protection systems, etc., test whether the interlocking trigger logic is correct;
72-Hour Trial Operation:
After all functions pass commissioning, put the equipment into continuous 72-hour trial operation;
During the trial operation period, record operating parameters and fault conditions. Check component temperature rise and operating reliability;
If there are no faults for 72 hours and all indicators meet the standards, the commissioning is considered complete.
10.7 Commissioning Records and Closure
Fill in Commissioning Records: Accurately fill in the commissioning record sheet, recording all test data, functional status, fault conditions, and handling results. The commissioning personnel and supervisor must sign for confirmation;
Parameter Backup: Back up the controller setting parameters and communication parameters for archival purposes to facilitate future maintenance;
Site Cleanup: After commissioning is complete, clean up commissioning tools and debris, close and lock the cabinet doors;
Operation Training: Provide training to the owner’s operation and maintenance personnel on basic operations, daily precautions, and simple fault handling methods.
10.8 Commissioning Safety Regulations
During energized commissioning, at least two people must cooperate: one operator and one supervisor. It is strictly forbidden for a single person to work on live equipment;
Follow standard operating procedures strictly when closing or opening switches. When closing switches under load, be aware of arc hazards and keep your face away from the front of the switch;
When measuring high-voltage points, ensure the test leads are firmly connected to prevent short circuits. Do not touch the metal part of the test leads with your hands during measurement;
If any abnormal conditions such as arcing, smoke, or unusual noise occur, immediately de-energize. Only continue after investigating and resolving the cause;
For outdoor commissioning, pay attention to weather conditions. It is strictly forbidden to conduct outdoor energized commissioning during rain or thunderstorms.
11.1 Transportation and Storage Precautions
Transportation Requirements
The product must be transported in an upright position, with a tilt angle of ≤ 15°. Overturning or laying the cabinet on its side is strictly prohibited to avoid component displacement or damage;
Take shockproof and rainproof measures during transportation. Use foam, cartons, and wooden frames for packaging to avoid collision, extrusion, and rain exposure;
Handle with care during loading and unloading. Dropping or rolling the cabinet is strictly prohibited. When using a forklift, insert the forks into the base to avoid damaging the cabinet side panels;
Regularly check the packaging during transportation. Address any looseness or water ingress promptly.
Storage Requirements
The storage site should be well-ventilated, dry, rainproof, and moisture-proof. Keep it away from corrosive gases and dust;
Ambient temperature -40°C ~ +70°C, relative humidity ≤ 95%, no condensation;
Place the product on a flat floor or shelves. Stacking height should not exceed 2 layers to avoid deformation from excessive weight;
For long-term storage, inspect every 3 months. Check for moisture, corrosion, and component aging. Energize briefly to dehumidify if necessary;
Store away from flammable and explosive materials and strong electromagnetic interference sources;
Keep the packaging intact during storage. Cabinet doors should be closed and locked to prevent dust, insects, and rodents from entering.
11.2 Installation and Construction Precautions
Selection and Adaptation: Before installation, confirm that the product model, specification, and parameters meet design requirements, and match the on-site load and environment. It is strictly prohibited to use beyond rated parameters.
Environmental Prohibitions
Strictly prohibited to install in flammable and explosive hazardous locations or areas with strong corrosive gases;
Strictly prohibited to install in low-lying areas prone to water accumulation. The installation foundation must be elevated above ground level;
Avoid installing on west-facing walls exposed to direct sunlight. High summer temperatures can cause excessive heat buildup inside the cabinet. Add sunshade measures if necessary.
Foundation and Fixing
The foundation must be solid and sturdy, meeting load-bearing and wind resistance requirements. Installing on soft foundations is strictly prohibited;
Expansion bolts and anchor bolts must be tightened securely. Regularly check for looseness;
For wall-mounted and pole-mounted installations, confirm the load-bearing capacity of the wall or light pole. Installing on non-load-bearing walls is strictly prohibited.
Mandatory Grounding Requirements
Reliable grounding is mandatory. The grounding resistance must be ≤ 4Ω. It is strictly prohibited to operate without grounding;
It is strictly forbidden to connect the ground wire to public utility pipes such as water pipes or gas pipes. It is strictly forbidden to use the neutral wire as a substitute for the ground wire;
After completing the grounding system installation, the resistance must be tested and meet the standard before commissioning.
Sealing and Protection
All cable entry and exit holes must be sealed properly. Open holes are strictly prohibited to prevent rainwater, rodents, and insects from entering;
After installation, check that the cabinet door sealing gaskets fit properly and have not fallen off or been damaged to ensure the protection rating.
Finished Product Protection
From installation until the completion of the final acceptance inspection, protect the finished product from construction contamination and impact damage;
Welding or drilling holes in the cabinet body is strictly prohibited, as this damages the structure and anti-corrosion coating.
11.3 Wiring Operation Precautions
De-energized Operation: Wiring operations must be performed with the power completely disconnected. Test for zero energy, post warning signs, and assign a supervisor. Wiring on live equipment is strictly forbidden.
Wire Gauge Matching: Strictly select cable specifications according to the load current. It is strictly forbidden to use undersized wire gauges for large loads to prevent overheating and fire hazards.
Terminal Tightening: All wiring terminals must be tightened securely to ensure good contact. Re-tighten high-current terminals regularly to prevent loosening due to heat generation during operation.
Correct Phase Sequence: The three-phase sequence must be correct. The neutral wire and ground wire must not be reversed. For single-phase circuits, the live and neutral wires must not be reversed. For screw-type lamp holders, the live wire must be connected to the center contact.
Separation of Power and Control Wires: Keep power wiring and low-voltage signal wiring separated by a distance of ≥ 10cm to avoid interference with low-voltage signals. Use shielded cable for signal wires with single-ended grounding.
Insulation Protection: All exposed live parts must be properly insulated. Exposed copper wires are strictly prohibited. Insulate spare wire ends properly.
Standardized Wiring: Random wiring and unauthorized connections inside the cabinet are strictly prohibited. Adding high-power loads beyond the rated capacity of cabinet components is strictly forbidden.
11.4 Commissioning and Operation Precautions
Energization Sequence: Strictly follow the sequence of “main switch first, then branch switches; no-load first, then loaded.” The de-energization sequence is the reverse.
Prohibition of Switching Under Load: Minimize opening circuit breakers under load to avoid arc erosion of contacts. After a fault trip, investigate and resolve the fault first. Do not force re-close circuit breakers.
Fault Trip Handling: After a circuit breaker trips, first determine the cause of the trip, resolve the fault, and then re-close. It is strictly forbidden to repeatedly force re-energize, as this can worsen the fault.
Parameter Settings: Configure controller parameters reasonably. On/off times and photocontrol thresholds must meet on-site requirements. Avoid faulty settings leading to abnormal lighting operation.
Thunderstorm Weather: During thunderstorms and heavy rain, disconnect the power when possible to prevent lightning damage to equipment. After a thunderstorm, check the status of surge protective devices.
Operation Inspection: Regularly inspect the equipment during operation. If abnormal noise, odor, overheating, or water ingress is found, immediately de-energize and investigate.
11.5 Daily Use Precautions
Designated Personnel: The equipment should be managed and operated by certified electricians. Unauthorized personnel are strictly prohibited from opening the cabinet to prevent electric shock and operational errors.
Cabinet Door Management: During normal operation, the cabinet door must be closed and locked. Running with the door open is strictly prohibited to prevent water ingress, dust, and accidental contact. Close the door promptly after maintenance.
Load Management: Adding circuit loads or replacing luminaires with higher wattage beyond the rated capacity of circuit breakers and cables is strictly prohibited.
No Unauthorized Modifications: Modifying the internal structure of the cabinet, replacing components, or changing wiring without authorization is strictly prohibited. Contact the manufacturer for technical guidance if modifications are required.
Cleaning and Maintenance: Regularly clean the cabinet body and interior. Wiping live parts with wet cloths is strictly prohibited. Washing the inside of the cabinet with water is strictly prohibited.
Emergency Response: In case of emergencies such as electric shock or fire, immediately disconnect the upstream power supply and call the emergency repair hotline. Pouring water on live electrical equipment to extinguish fires is strictly prohibited.
11.6 Special Environment Precautions
Coastal High Salt Spray Environment
Select 316 stainless steel cabinet bodies or enhanced anti-corrosion models;
Inspect the cabinet surface and component corrosion quarterly and wipe off salt deposits regularly;
Use stainless steel fasteners to prevent rusting and seizing.
High-Altitude Cold Environment
Select low-temperature customized models equipped with heating devices;
Check that the heating device works properly in winter to prevent component failure due to low temperatures and hardening of sealing strips;
Clear snow promptly to avoid damaging the cabinet.
High-Temperature and Sun Exposure Environment
Configure sunshades or choose a shaded installation location;
Configure cooling fans and check their operation in summer;
Increase inspection frequency during high-temperature periods and pay attention to component temperature rise.
Dusty Environment
Regularly clean the dust filter at the air inlet to prevent blockage affecting heat dissipation;
Regularly clean accumulated dust inside the cabinet to prevent insulation degradation;
Check sealing performance to prevent dust ingress.
11.7 Safety Warnings
Electric Shock Hazard: The cabinet contains high voltage. Unauthorized personnel are strictly prohibited from opening the cabinet doors and performing maintenance on live equipment;
Fire Risk: Overload operation is strictly prohibited. Blocking heat dissipation channels is strictly prohibited. Regularly clean accumulated dust and debris;
Lightning Risk: Equipment in open areas must be reliably grounded. Surge protective devices should be checked regularly. Disconnect power during thunderstorms when possible;
Mechanical Injury: Be careful not to pinch hands when opening and closing cabinet doors. Be cautious of crushing and pinching when handling the cabinet.
Scientific and standardized maintenance and repair are key to extending equipment service life, reducing failure rates, and ensuring stable operation of the lighting system. Establishing a “prevention first, maintenance combined with repair” maintenance system can effectively improve equipment reliability and reduce life-cycle costs.
12.1 Maintenance System and Cycle
We recommend implementing a four-level maintenance system: “Daily Inspection, Monthly Maintenance, Quarterly Overhaul, and Annual Major Overhaul”. The specific cycles and contents are as follows:
| Maintenance Level | Execution Cycle | Executing Personnel | Core Purpose |
|---|---|---|---|
| Daily Inspection | Daily/Weekly | O&M inspection personnel | Detect appearance and obvious abnormalities, handle minor issues promptly |
| Monthly Maintenance | Once per month | Junior electrician | Cleaning, tightening, visual inspection, eliminate basic hazards |
| Quarterly Overhaul | Once per quarter | Intermediate electrician | Functional testing, protection verification, performance checks |
| Annual Major Overhaul | Once per year | Senior electrician / Manufacturer after-sales | Comprehensive inspection, deep cleaning, replacement of wear parts, performance calibration |
The cycle can be adjusted based on the importance of the project and the severity of the environment. Shorten the maintenance cycle for important road sections and harsh environments.
12.2 Daily Inspection Contents
Daily inspections focus primarily on visual checks without opening the cabinet, judging the operating status through appearance and indicator lights:
Cabinet Body Appearance Check: Check for tilting, deformation, damage, or corrosion; paint peeling or blistering; door lock integrity and whether the cabinet door is tightly closed.
Surrounding Environment Check: Check for standing water or debris accumulation; risks of construction or impact; items blocking heat dissipation or antennas.
Indicator Light Status: Check whether the power indicator is lit normally; whether the fault indicator is lit; whether circuit indicators are consistent with operating status.
Abnormal Noise and Odor Check: Listen near the cabinet for abnormal noises or discharge sounds; smell for burning or ozone odors.
Lighting Effect Check: During night inspections, check the lighting conditions of the corresponding road section for any sections that are completely dark or flickering.
Inspection Records: Fill in inspection records and report any identified abnormalities promptly.
12.3 Monthly Maintenance Contents
Monthly maintenance requires opening the cabinet and working with the power off. Main contents:
Cleaning and Dust Removal
Use a dry brush and blower to clean dust and debris from inside the cabinet;
Wipe down the interior of the cabinet and component surfaces, focusing on circuit breakers, contactors, and heat dissipation channels;
Clean the cabinet door glass and sealing gaskets, removing dust from gasket gaps;
Clean the exterior of the cabinet to maintain a tidy appearance; clear any standing water or debris from the cabinet base.
Tightening Checks
Check and tighten main circuit wiring terminals, focusing on high-current terminals and incoming/outgoing terminals to prevent loosening and overheating;
Tighten component mounting screws and DIN rail mounting screws;
Check whether the grounding connections are secure and corrosion-free.
Structure and Sealing Checks
Check that door locks and hinges operate smoothly and apply a small amount of lubricant;
Check for aging, cracking, or detachment of sealing gaskets and verify sealing integrity;
Check whether the sealing of cable entry and exit holes is intact, without looseness or signs of water ingress;
Check for corrosion points on the cabinet. Remove rust and touch up paint for minor corrosion.
Status Verification
Verify the working status of circuit breakers and contactors, checking for overheating or discoloration;
Check the status indicator of surge protective devices and replace them promptly if failed;
Verify the accuracy of the controller clock and calibrate if deviation is significant.
Simple Functional Tests
Test the manual on/off light function;
Test that all indicator lights illuminate correctly and replace any damaged ones.
12.4 Quarterly Overhaul Contents
Quarterly overhauls are in-depth functional inspections requiring professional electricians to work with instruments:
Electrical Performance Testing
Measure incoming voltage and current of each circuit, checking load balance and overload conditions;
Measure the insulation resistance of main and branch circuits to confirm good insulation performance;
Test ground resistance to ensure it is ≤ 4Ω. Address any poor grounding promptly;
Check wiring terminal temperature rise using a temperature gun. A temperature of ≤ 60°C is normal. Address overheating promptly.
Protection Device Verification
Test the leakage protector by pressing the test button to verify the trip function;
Check the tripping characteristics of circuit breakers. Conduct sampling tests if conditions permit. Replace aging circuit breakers promptly;
Check the performance of surge protective devices, especially after lightning strikes. Replace immediately if failed.
Control Function Calibration
Calibrate the controller clock to ensure accurate timekeeping;
Check photocontrol sensor sensitivity, clean the probe surface dust, and calibrate the photocontrol threshold;
Verify the accuracy of time control and latitude/longitude control functions;
Check communication module signal strength and test whether remote communication is normal;
Test the fault alarm function to ensure timely and accurate alarms.
Component Status Check
Check contactor contacts for burning or oxidation. Polish minor burns; replace if severely damaged;
Check whether the operating mechanism of circuit breakers is flexible without sticking;
Check the controller operating status for crashes or errors. Perform a restart test.
Heat Dissipation and Temperature Control Check
For cabinets with fans, clean the fan and dust filter, and test the temperature control start/stop function;
For cabinets with heaters, test the heating function before winter.
12.5 Annual Major Overhaul Contents
The annual major overhaul is a comprehensive deep maintenance, recommended to be completed before the annual thunderstorm season. It can be combined with planned power outages:
Comprehensive Deep Cleaning
Completely disconnect power. Remove cleanable components for cleaning;
Thoroughly clean dust, grease, and debris from every corner of the cabinet;
Clean cooling fans and filters, replace aging filter media;
Clean busbars and terminal blocks, remove oxidation layers, and apply conductive compound.
Comprehensive Component Inspection and Replacement
Comprehensively test the performance of all circuit breakers and contactors. Replace those with unreliable operation or severely worn contacts;
Replace aging surge protective devices (service life 3-5 years);
Replace aging sealing gaskets (service life 5-8 years);
Replace the controller backup battery (service life 3 years);
Check all indicator lights and buttons, and replace any damaged ones.
Comprehensive Wiring Rectification
Re-tighten all wiring terminals, especially high-current terminals;
Replace aging, cracked, or discolored cables;
Arrange wiring, replace aging cable ties, and re-bundle neatly;
Complete or replace any missing labels and wire numbers.
Comprehensive Performance Testing
Comprehensively test all protection functions, control functions, and communication functions;
Conduct full-load testing, measuring three-phase current, voltage, and temperature rise;
Re-calibrate metering accuracy to ensure accurate energy metering;
Test all fault alarm functions and repair fault points.
Structural Anti-Corrosion Maintenance
Remove rust and touch up paint on the cabinet surface to enhance corrosion resistance;
Remove rust from fasteners and ground flat steel and apply anti-corrosion paint;
Perform deep maintenance on hinges and locks, replacing worn parts.
Documentation Update
Update equipment records, maintenance records, and fault records;
Back up controller parameters and platform configurations;
Assess equipment condition and develop the next year’s maintenance plan and spare parts procurement plan.
12.6 Replacement Methods for Common Components
12.6.1 Miniature Circuit Breaker Replacement
Disconnect the upstream power supply and test for zero voltage;
Remove the incoming and outgoing wires from the circuit breaker, marking their positions and noting the wiring arrangement;
Use a screwdriver to release the clip at the bottom of the circuit breaker and remove it from the DIN rail;
Align the new circuit breaker to the rail and snap it into place, securing the clip;
Connect the incoming and outgoing wires according to the markings and tighten the terminal screws;
Close the switch and test the function. Confirm normal operation before putting into service.
Note: Replace with the same model and specification circuit breaker. It is strictly forbidden to replace with a circuit breaker with a higher rated current.
12.6.2 AC Contactor Replacement
De-energize and test for zero voltage. Remove the main circuit and control circuit wires from the contactor, marking their positions;
Unscrew the mounting screws of the contactor or remove the old contactor from the DIN rail;
Mount the new contactor in the installation position and tighten the screws;
Connect the main circuit and control circuit wires according to the markings and tighten the terminals;
Energize and test for proper engagement, abnormal noise, and whether the circuit energizes correctly.
Note: The coil voltage and rated current must match the original specifications.
12.6.3 Surge Protective Device (SPD) Replacement
De-energize and test for zero voltage. Remove the SPD wiring;
Remove the old SPD from the DIN rail;
Clip the new SPD onto the rail. Connect the wires according to the original phase sequence. Ensure the PE terminal is reliably grounded;
After verifying the wiring, energize. The status indicator window should show green for normal operation.
Note: The phase, neutral, and ground wires must not be reversed. Keep the wiring as short and straight as possible.
12.6.4 Lighting Controller Replacement
De-energize. Record all controller parameters and wiring positions;
Remove all wiring and unplug the communication connectors;
Remove the mounting screws and take out the old controller;
Install the new controller and secure it firmly;
Connect the wires one by one according to the original wiring positions and verify correctness;
After energization, reconfigure parameters and communication settings. Test all functions;
Notify the platform end to update the device configuration and confirm communication is normal.
Note: Pay attention to the positive and negative poles on low-voltage wiring. Do not reverse them to avoid burning out modules.
12.6.5 Sealing Gasket Replacement
Peel off the old gasket and clean residual adhesive and dust from the channel;
Insert the new gasket into the channel. Use 45° mitre joints at corners and bond the joints firmly;
Close the cabinet door and check for proper fit. The gasket should compress evenly around the perimeter with no gaps visible.
12.7 Maintenance Safety Regulations
All maintenance work must be performed with the power off. Follow the lockout/tagout procedure: de-energize, test for zero energy, post warning signs, and assign a supervisor. Maintenance on live equipment is strictly prohibited;
When working at height, wear a safety harness and keep tools in a tool bag to prevent falling objects;
After replacing components, verify the wiring is correct before energizing for testing;
Clean up tools and debris after maintenance to ensure no leftover metal objects cause short circuits;
After major fault repairs, conduct a trial run for a period to confirm normal operation before leaving;
All maintenance must be documented, including the fault phenomenon, cause, replaced components, and handling results. Establish an equipment maintenance archive.
12.8 Spare Parts Management Recommendations
Establish a spare parts ledger. Reasonably stock easily worn spare parts based on the number of equipment and failure rates;
It is recommended to source core spare parts from the original manufacturer to ensure quality matching and avoid substandard parts causing fault escalation;
Store spare parts in a dry, ventilated environment with proper care to prevent moisture and damage;
Regularly take inventory of spare parts and replenish them promptly to avoid extended downtime due to lack of spare parts.
13.1 Electrical Faults
Fault 1: No Power to the Entire Cabinet, All Indicator Lights Off
Possible Causes:
Upstream power outage, no voltage at the incoming terminals;
Upstream circuit breaker tripped or fuse blown;
Main circuit breaker tripped or damaged;
Incoming cable broken, wiring terminal loose or detached;
Main incoming leakage protector tripped.
Troubleshooting Steps:
First check whether other electrical equipment in the surrounding area has power to confirm whether it is a widespread outage;
Open the cabinet door and observe the status of the main circuit breaker to see if it is in the tripped position;
Use a multimeter to measure the voltage at the incoming terminals of the main circuit breaker. If there is no voltage, investigate the upstream power supply and incoming cable;
If there is voltage at the incoming terminals, measure the voltage at the outgoing terminals. If there is no voltage, the main circuit breaker may be damaged or not closed;
Check the incoming terminals for burning, looseness, or detachment;
If there is a main leakage protector, check whether it has tripped due to leakage.
Solutions:
Upstream power outage: Wait for power restoration or switch to backup power;
Upstream breaker tripped: Investigate the cause of the fault and re-close after resolution;
Main breaker tripped: Open all branch circuits first, attempt to close. If it cannot be closed, investigate for short circuits inside the cabinet;
Terminal loose/detached: Re-crimp and tighten;
Breaker damaged: Replace with a main breaker of the same specification;
Leakage trip: Investigate the leakage point, resolve, and reset.
Fault 2: A Single Circuit Does Not Light, Other Circuits Are Normal
Possible Causes:
The corresponding branch circuit breaker has tripped;
The branch circuit breaker is damaged;
The AC contactor is damaged or the coil is open-circuited;
The controller has no output for the corresponding circuit;
The circuit outgoing terminal is loose or the wire is broken;
The circuit cable is short-circuited or open-circuited;
All luminaires on that circuit are damaged.
Troubleshooting Steps:
Check whether the corresponding branch circuit breaker has tripped. If tripped, first disconnect the load;
Manually close the contactor and measure whether there is voltage at the contactor’s outgoing terminals;
If there is no voltage, measure the voltage at the outgoing and incoming terminals of the circuit breaker to locate the fault point;
If there is voltage at the contactor’s outgoing terminals, check the outgoing terminals and the outdoor cable;
Disconnect the load-side cable and measure insulation resistance to determine whether it is a short circuit or open circuit;
Verify whether the controller output is normal and whether the control wiring is broken.
Solutions:
Breaker tripped: Investigate load-side short circuit, overload, or leakage. Re-close after resolving the fault;
Breaker damaged: Replace with a branch circuit breaker of the same specification;
Contactor fault: Replace the contactor or coil;
Controller no output: Check controller settings and replace the corresponding output relay;
Loose wiring: Re-tighten the wiring;
Cable fault: Locate the break or short circuit point, repair or replace the cable;
Damaged luminaires: Replace the faulty luminaires.
Fault 3: Luminaires Flicker or Brightness is Unstable
Possible Causes:
Significant voltage fluctuation in the power grid;
Poor contact in wiring terminals, intermittent connection;
Contactor contacts oxidized or burnt, causing poor contact;
Unstable controller output, frequent operation;
Improper photocontrol threshold settings, resulting in repeated switching at the threshold boundary;
Poor neutral wire contact causing voltage drift;
Faulty LED driver.
Troubleshooting Steps:
Measure the incoming voltage and observe for fluctuations;
Check all wiring terminals, especially the neutral terminal, for looseness, oxidation, or overheating;
Check the main contacts of the contactor for burning or pitting;
Observe the controller output status for frequent jumps;
If in photocontrol mode, check whether the light sensor probe is blocked or affected by strong light interference;
Replace the luminaire to test and rule out luminaire-related faults.
Solutions:
Voltage fluctuation: Investigate the grid cause. For severe cases, consider installing a voltage stabilizer;
Poor contact: Polish oxidized terminals, re-crimp and tighten;
Contactor contact issues: Polish minor contact burns, replace the contactor if severely damaged;
Controller issue: Adjust control parameters. Replace the controller if faulty;
Photocontrol misoperation: Adjust the threshold and delay time, relocate the light sensor;
Neutral wire issue: Tighten the neutral terminal and repair any broken points in the neutral wire;
Luminaire fault: Repair or replace the LED driver.
Fault 4: Circuit Breaker Trips Frequently
Possible Causes:
Circuit load too large, overload;
Short circuit in the wiring or luminaires;
Leakage in the wiring, causing the leakage protector to trip;
Circuit breaker undersized, tripping current too low;
Circuit breaker aging, tripping characteristics shifted;
Ambient temperature too high, derating of the circuit breaker;
High inrush current causing nuisance tripping.
Troubleshooting Steps:
Measure the circuit operating current and compare it with the rated current of the circuit breaker to determine if it is overloaded;
Disconnect all loads and measure the line insulation resistance to determine short circuit or leakage;
Gradually add load and observe the current value at which tripping occurs;
Check whether the circuit breaker specification matches the load;
Check the temperature inside the cabinet for high ambient temperature;
Replace with a new circuit breaker of the same specification to test whether the circuit breaker itself is faulty.
Solutions:
Overload: Reduce the circuit load, or replace with a larger rated circuit breaker and cable;
Short circuit: Find the short circuit point and repair the insulation;
Leakage: Investigate the leakage point and repair insulation damage;
Undersized breaker: Replace with a circuit breaker with an appropriate rated current;
Breaker aging: Replace with a new circuit breaker;
High temperature: Improve heat dissipation and ventilation, derate the breaker;
Inrush current: Replace with a D-type tripping curve circuit breaker, or stagger the start times.
Fault 5: Severe Heat Build-up in Cabinet, Burning Odor
Possible Causes:
Loose high-current terminals with high contact resistance, generating significant heat;
Overload operation causing circuit breakers, contactors, and cables to overheat;
Poor contact of contactor contacts causing high contact resistance and heat;
Blocked heat dissipation channels and poor ventilation;
Severe three-phase unbalance causing high neutral current and heat generation;
Localized short circuit or leakage causing abnormal heat.
Troubleshooting Steps:
After de-energizing, open the cabinet door and visually inspect for any burnt or discolored parts. Identify the source of the burning odor;
Use a temperature gun to measure the temperature of various terminals and components to locate the heat source;
Measure each circuit’s current to check for overload and three-phase unbalance;
Check for loose or oxidized wiring terminals;
Check whether the cooling fan is operating correctly and whether the heat dissipation vents are blocked.
Solutions:
Loose/oxidized terminals: Polish the terminals, re-crimp and tighten, apply conductive compound;
Overload: Reduce the load or upgrade component specifications;
Contactor overheating: Replace the contactor and check the contacts;
Poor heat dissipation: Clean dust, repair the cooling fan, improve ventilation and cooling;
Three-phase unbalance: Adjust the circuit distribution to balance the three-phase loads;
Short circuit/leakage: Immediately de-energize and investigate, then resolve the fault.
13.2 Control Function Faults
Fault 6: Time Control Inaccurate, Switching Times Vary Significantly
Possible Causes:
- The controller’s clock chip has significant time drift.
- The backup battery is depleted, causing the time to reset after a power outage.
- Incorrect settings, such as improperly configured time periods.
- Latitude/longitude or light control correction enabled, causing times to vary seasonally.
- The controller has frozen (locked up), and the clock has stopped.
Troubleshooting Steps:
- Access the controller interface and verify the current time is accurate.
- Check if the timer settings are correct and if there are multiple, conflicting timer groups.
- Power cycle the controller to see if the time is lost.
- Check whether other control modes are enabled that might affect the timer.
Solutions:
- Recalibrate the current time.
- Time lost on power outage: Replace the controller’s backup coin cell battery.
- Incorrect settings: Re-set the correct switching times.
- Latitude/longitude deviation: Verify the latitude and longitude settings are correct.
- Controller freeze: Restart the controller; if it freezes frequently, replace it.
Fault 7: Light Control Not Working, No Automatic Light Switching
Possible Causes:
- Light control mode is not enabled.
- The light sensor probe is incorrectly wired or has a broken wire.
- The light sensor probe is damaged.
- The light control threshold is set unreasonably, outside the ambient light range.
- The light sensor probe is blocked or covered by thick dust, preventing it from detecting light.
- The controller’s light control port is damaged.
Troubleshooting Steps:
- Check the controller settings to confirm light control mode is enabled.
- Inspect the light sensor probe wiring for loose connections, breaks, or reversed polarity.
- Clean the sensor probe surface and remove any obstructions.
- Use a multimeter to measure the light sensor output signal. Check if it changes when the sensor is covered/uncovered.
- Test with a new light sensor probe to determine if the original is faulty.
Solutions:
- Not enabled: Enable light control mode and set reasonable thresholds.
- Wiring error: Re-wire correctly.
- Probe damage: Replace the light sensor.
- Unreasonable threshold: Adjust the switching thresholds based on the site environment.
- Blockage/dust: Clean the probe and install it in an unblocked location.
- Port damage: Replace the controller’s corresponding port or the entire controller.
Fault 8: Latitude/Longitude Control Time Inaccurate
Possible Causes:
- Incorrect latitude and longitude values were entered.
- The controller’s algorithm has significant calculation error.
- Light control correction is enabled, causing a discrepancy between actual and calculated times.
- Incorrect time zone settings.
Troubleshooting Steps:
- Verify the entered latitude/longitude matches the project’s actual location.
- Compare the controller’s calculated sunrise/sunset times with astronomical data.
- Check if the time zone is set to UTC+8 (China Standard Time).
Solutions:
- Input error: Re-input the accurate latitude and longitude.
- Algorithm error: Set a time offset to correct the deviation.
- Light control correction: This is normal; disable or adjust the correction level as needed.
Fault 9: Manual Control Works, Automatic Mode Non-Operational
Possible Causes:
- The Manual/Auto selector switch is in the Manual position.
- The controller’s power supply is disconnected.
- The controller is faulty and has no output.
- The automatic control parameters are set incorrectly.
- The common wire for the control circuit is broken.
Troubleshooting Steps:
- Check the position of the selector switch; ensure it is set to Automatic mode.
- Measure the controller’s power supply voltage to verify it is normal.
- Check the controller’s operational status for errors and whether the output indicator lights are illuminated.
- Force a trigger for automatic output and measure the voltage at the output terminals.
Solutions:
- Wrong switch position: Switch to Automatic mode.
- Power supply issue: Connect the controller’s power supply and check if the fuse is blown.
- Parameter error: Reconfigure the automatic control parameters.
- Controller fault: Repair or replace the controller.
- Broken control wire: Restore the control circuit wiring.
13.3 Structural Protection Faults
Fault 10: Water Intrusion, Dampness, and Condensation Inside the Enclosure
Possible Causes:
- The enclosure door is not fully closed; the sealing gasket is misaligned.
- The sealing gasket is aged, cracked, or has lost its elasticity.
- Cable entry/exit holes are not sealed properly, allowing rainwater to flow along the cables.
- The top weld seam of the enclosure has cracks or leaks.
- The installation site is low-lying, causing water accumulation that submerges the enclosure base.
- Large temperature differences between day and night cause condensation inside the enclosure.
Troubleshooting Steps:
- Check if the enclosure door is closed properly, the gasket is sealing well, and there is no damage.
- Inspect the sealing of cable entry/exit holes for signs of water ingress.
- Check the enclosure top and weld seams for rust, corrosion, or leaks.
- Check the foundation for water accumulation and the bottom of the enclosure for water ingress.
Solutions:
- Door not fully closed: Close and lock the enclosure door properly.
- Aged gasket: Replace the sealing gasket.
- Leaking cable entry: Re-seal using sealing putty or cable glands.
- Enclosure leak point: Weld to repair the leak, touch-up paint for corrosion protection.
- Water accumulation issue: Elevate the foundation and implement drainage measures.
- Condensation issue: Install a dehumidifier or breather valve to improve ventilation.
Fault 11: Door Lock Damaged, Cannot Open or Close
Possible Causes:
- The lock cylinder is rusted or stuck.
- The key is broken or an incorrect key is used.
- The lock bolt is jammed, or the mechanism is deformed.
- The enclosure door is deformed, causing misalignment with the lock bolt.
Troubleshooting Steps:
- Check if the key is correct and if the lock cylinder has foreign objects or rust.
- Inspect if the lock bolt extends and retracts smoothly without jamming.
- Check if the enclosure door is warped and if the hinges are loose or sagging.
Solutions:
- Stuck lock cylinder: Apply lubricating oil and operate the lock repeatedly to free it.
- Broken key: Extract the broken key piece and replace the lock cylinder.
- Damaged lock mechanism: Replace the entire door lock set.
- Warped door: Adjust the hinges and correct the door alignment.
Fault 12: Severe Corrosion of the Enclosure
Possible Causes:
- Highly corrosive environment (e.g., coastal, chemical industrial areas) where standard materials are unsuitable.
- Paint damage not repaired promptly, leading to base metal rusting.
- Prolonged exposure to dampness or standing water, causing bottom corrosion.
- Damage to the galvanized layer and coating during installation.
Troubleshooting Steps:
- Check the location and extent of the corrosion – is it localized or widespread?
- Analyze environmental factors, such as high salt spray or corrosive atmospheres.
Solutions:
- Localized corrosion: Remove rust, apply anti-rust primer, and apply a finishing coat.
- Bottom corrosion: Elevate the foundation and implement waterproofing/corrosion protection.
- Severe widespread corrosion: Replace with a stainless steel enclosure, suitable for highly corrosive environments.
13.4 Communication and Smart Feature Faults
Fault 13: Device Offline, Cannot Connect to Platform
Possible Causes:
- Poor or no mobile network signal at the site.
- The antenna is loose, disconnected, or damaged.
- The communication module’s power supply is faulty or not supplying power correctly.
- The SIM card is out of credit, damaged, or has poor contact.
- Incorrect communication parameter configuration (e.g., server address, port, device ID mismatch).
- Communication module hardware failure or abnormal firmware operation.
- Cloud server failure, or network firewall restricting device access.
- Strong electromagnetic interference nearby suppressing the wireless signal.
Troubleshooting Steps:
- Visual Inspection: First, check if the antenna connection is secure. Inspect the antenna feeder cable for damage or water ingress. Check if the antenna’s installation position is completely blocked by metal structures or walls.
- Indicator Light Check: Observe the communication module’s indicator light. The blinking pattern indicates power status, network search status, and data transmission status. (e.g., Steady ON = Power OK but not networked; Slow Blink = Network Connected; Fast Blink = Data Transmitting).
- Power Supply Test: Disconnect the module wiring and use a multimeter to measure the supply voltage. Verify it is within the module’s rated voltage range. Rule out power circuit faults or blown fuses.
- SIM Card Inspection: Power off the device, remove the SIM card, check for oxidation or rust on the chip surface. Insert the SIM into a phone to test for credit balance and network registration capability.
- Parameter Verification: Access the controller’s parameter settings and verify the communication parameters like server IP address, port number, device ID, and access key to ensure they match the platform configuration.
- Signal Testing: Use a mobile phone with the same carrier at the enclosure installation location to test signal strength. If the signal is ≤ 2 bars, the site’s network coverage is insufficient.
- Platform Side Check: Contact platform operations personnel to confirm the server is running correctly, the specific device account is not disabled, and the firewall is not blocking the device’s access port.
Solutions:
- Weak Field Signal: Extend the antenna to an outdoor, open, and unblocked high location. Replace with a high-gain, waterproof antenna. If one carrier’s signal is poor, switch to a full-network (full-network) module and select the carrier with the strongest signal. In extreme no-signal scenarios, consider wired fiber optic transmission or LoRa relay transmission.
- Antenna Fault: Re-tighten the antenna connector. Replace damaged or water-ingressed feeder cables and antennas. Ensure waterproof sealing at the connectors.
- Abnormal Power Supply: Troubleshoot the control circuit power supply. Replace blown fuses. Repair loose power supply wiring to ensure stable power to the module.
- SIM Card Issue: Recharge the SIM card promptly if out of credit. Clean the oxidized chip surface with an eraser. Replace a damaged card with a new IoT card. Ensure the chip has solid contact during installation.
- Parameter Error: Re-enter the configuration parameters provided by the platform. Save and restart the communication module to re-establish the network connection and registration.
- Module Damage: If firmware is abnormal, try upgrading the firmware or restoring factory settings. If hardware is damaged, replace with the same model of communication module.
- Platform/Network Restrictions: Coordinate with operations personnel to open the corresponding ports, lift access restrictions, or fix server faults.
- Electromagnetic Interference: Move the enclosure away from strong interference sources like transformers, high-voltage lines, or radar. Use shielded cables for signal lines. Add signal filters if necessary.
Fault 14: Significant Deviation Between Platform Displayed Data and Actual On-Site Values
Possible Causes:
- Incorrect voltage/current transformer wiring, or the transformer ratio parameter doesn’t match the actual transducer.
- Reversed phase sequence (3-phase), causing incorrect power/energy calculation logic, leading to reversed or low readings.
- Controller’s metering chip calibration drift, decreasing accuracy over extended operation.
- Data packet loss during communication, causing the platform to display historical cached data instead of real-time updates.
- Poor contact in the front-end sampling wiring, causing distorted sampling signals.
- Controller firmware bug causing data conversion logic errors.
Troubleshooting Steps:
- Baseline Comparison: Use a multimeter or clamp meter with accuracy class 0.5 or higher to measure actual voltage and current on-site. Compare these values with the controller’s local display and the platform’s display to pinpoint the source of deviation.
- Wiring Inspection: Check the direction of the primary and secondary wiring of the transformers. Verify the number of primary turns meets requirements and the secondary side is reliably grounded.
- Parameter Verification: Access the controller parameter interface. Confirm the voltage transformer ratio and current transformer ratio match the actual transducer’s nameplate ratings.
- Phase Sequence Test: Use a phase sequence meter to measure the incoming 3-phase sequence. Confirm the phases are connected in positive sequence (L1-L2-L3) without missing or reversed phases.
- Real-Time Verification: Manually refresh the platform page multiple times and observe if the data updates synchronously with load changes. This rules out cache lag issues.
- Local Comparison: If the controller’s local display is accurate but the platform shows deviation, the issue is likely communication or platform conversion. If the local display also shows deviation, the issue lies within the sampling/measurement end.
Solutions:
- Wiring/Transformer Ratio Error: Correct the transformer wiring direction. Re-set the ratio parameters to match the hardware. Ensure the sampling ratio is correct.
- Phase Sequence Reversed: Adjust the incoming 3-phase sequence to ensure positive phase sequence. Correct the power and energy calculation direction.
- Accuracy Drift: Access the controller calibration interface. Use a standard meter as a reference to recalibrate the metering parameters. If the deviation is severe and cannot be calibrated, replace the main control unit.
- Data Cache Lag: Clear the platform cache. Set a shorter data upload interval to ensure data is real-time.
- Sampling Circuit Fault: Repair loose sampling wiring. Replace aging sampling cables.
- Program Fault: Upgrade the controller to the latest stable firmware version to fix the program bug.
Fault 15: No Response from Device After Remote Control Command is Sent
Possible Causes:
- The device is offline, the network connection is interrupted, and the command cannot be delivered.
- The Manual/Auto selector switch inside the enclosure is in the “Manual” position, blocking remote control permissions.
- The communication module receives abnormally, resulting in command data packet loss or parsing failure.
- The platform account doesn’t have control permissions, only viewing permissions.
- The controller’s output circuit is faulty (e.g., damaged relay), preventing contactor activation.
- Incompatible communication protocol; the device cannot recognize the command format.
- The contactor coil is damaged; it receives a control signal but cannot energize.
Troubleshooting Steps:
- Online Status Confirmation: First, check the device’s online status on the platform. If offline, prioritize network troubleshooting.
- Control Mode Check: On-site, inspect the selector switch position to confirm it’s in “Remote/Auto” mode.
- Command Log Query: Review command send/receive logs on both the controller and the platform to confirm the command was successfully sent and received by the device.
- Local Control Test: Manually test the circuit switching on-site to confirm contactors, breakers, and loads are all functioning correctly. This rules out failures at the execution end.
- Permission Verification: Log in with an administrator account to test the control function. Confirm whether the standard account has control permissions.
Solutions:
- Device Offline: Follow the troubleshooting methods for Fault 13 to restore network connectivity and ensure the device is stable online.
- Mode Error: Switch the selector switch to the “Auto/Remote” position to unlock remote control permissions.
- Command Parsing Failure: Restart the communication module. Upgrade the device and platform protocol versions to ensure compatibility.
- Insufficient Permissions: Contact the platform administrator to grant control permissions for the specific account.
- Output Circuit Fault: Replace the damaged output relay in the controller. Repair control circuit wiring.
- Contactor Fault: Replace the damaged contactor coil or the entire contactor.
- Protocol Incompatibility: Standardize the communication protocol. Develop and install a protocol conversion gateway.
Fault 16: Platform Does Not Receive Alarm Notifications After a Fault Occurs
Possible Causes:
- The corresponding alarm item is disabled in the controller, or the alarm threshold is set outside normal range, preventing triggering.
- The device is offline, so alarm information cannot be uploaded.
- Platform alarm push function is disabled, or SMS/APP notification permissions are off.
- Alarm contact person’s phone number or account is configured incorrectly.
- The alarm detection sensor is damaged and cannot identify the fault state.
- The alarm level is set too low and gets filtered out by the platform’s message filtering rules.
Troubleshooting Steps:
- Function Configuration Check: Access the controller’s alarm settings interface. Confirm alarms such as over-voltage, under-voltage, leakage, and circuit faults are enabled, and thresholds are reasonable.
- Simulated Fault Test: On-site, artificially simulate a minor fault (e.g., disconnect a branch circuit breaker). Check if the controller triggers an alarm locally and if the fault indicator lights up.
- Push Settings Check: Log into the platform backend. Check if alarm push rules are enabled, and SMS, voice call, APP, and email notifications are turned on.
- Contact Verification: Confirm the phone numbers and accounts in the alarm contact list are accurate and have not been blacklisted.
- Network Status Confirmation: Confirm the device is online and data upload is normal, ruling out upload failure due to network interruption.
Solutions:
- Alarm Not Enabled: Enable the required alarm items. Set reasonable alarm thresholds and delays based on site conditions.
- Device Offline: Restore network connectivity to ensure real-time alarm uploads.
- Push Disabled: Enable push notifications for the corresponding alarm levels on the platform. Enable APP notification permissions and SMS notification on the phone.
- Contact Error: Update alarm contact information to ensure phone numbers and accounts are accurate.
- Sensor Fault: Replace damaged detection components like leakage transformers or voltage acquisition modules.
- Information Filtering: Adjust the platform filtering rules to elevate the corresponding alarm level to a push notification level.
13.5 Environmental and Other Faults
Fault 17: Contactor Fails to Close or Equipment Operates Abnormally in Low-Temperature Winter Environments
Possible Causes:
- Ambient temperature is below the minimum operating temperature of components. The contactor coil’s resistance changes significantly, resulting in insufficient closing force.
- Lubricating grease solidifies at low temperatures, causing sticking in contactors or switch mechanisms.
- No heating device configured inside the enclosure. Internal temperature drops below -25°C, outside the operating range of standard components.
- Sealing gaskets harden in the cold, compromising door seals and allowing cold air to enter, further lowering the temperature.
Troubleshooting Steps:
- Measure the actual internal temperature of the enclosure with a thermometer. Compare it with the rated operating temperature range of the components to confirm if it’s an ultra-low temperature operation issue.
- Power off and manually press the contactor armature to determine if the mechanism is stuck or has excessive resistance.
- Measure the contactor coil supply voltage to confirm the voltage is normal, ruling out insufficient power supply issues.
- Check the enclosure door seal for air leaks or frost marks.
Solutions:
- Install Temperature-Controlled Heating: Configure a PTC constant-temperature heater and a temperature controller. Set it to automatically start heating at 0°C to maintain the cabinet temperature above 5°C, ensuring reliable component operation.
- Replace with Wide-Temperature Components: In extremely cold regions, replace standard breakers and contactors with -40°C wide-temperature models suitable for high-altitude cold environments.
- Mechanism Maintenance: Clean off standard grease and apply low-temperature specific silicone grease to ensure smooth operation of mechanisms in cold conditions.
- Enclosure Insulation: Replace seals with low-temperature resistant gaskets. Add insulation cotton to the exterior of the enclosure to reduce heat loss.
- Enable Low-Temperature Protection Logic: Intelligent models can have a low-temperature protection feature enabled to prevent frequent switching operations when temperatures are too low, protecting the components.
Fault 18: Frequent Tripping and Component Overheating in Summer High-Temperature Environments
Possible Causes:
- High ambient temperature with direct sunlight on the enclosure heats the interior. Component rated current-carrying capacity is derated, causing overload trips.
- Cooling fan is damaged or the dust filter is blocked, rendering the forced cooling system ineffective.
- Loose wiring terminals with high contact resistance, generating heat that combines with high ambient temperature, triggering overheat protection.
- Long-term load overload, causing further over-temperature on top of the normal temperature rise.
- Poor internal component layout, concentrating heat-generating components and preventing heat dissipation.
Troubleshooting Steps:
- Temperature Measurement: Use an infrared thermometer to measure the internal ambient temperature, breaker casing, wiring terminals, and contactor coil temperatures to locate overheated parts.
- Cooling Check: For enclosures with fans, check if the fan is operating. Inspect the intake dust filter for blockages from dust, catkins, or debris.
- Load Detection: Use a clamp meter to measure the current in each circuit to confirm if loads exceed the breaker’s rated current.
- Wiring Check: Power off and inspect the terminals in overheated areas for looseness, oxidation, or discoloration.
Solutions:
- Shading and Cooling: Install a sunshade over the enclosure to avoid direct sunlight. During peak heat, the door may be opened briefly to assist cooling (require supervision).
- Repair Cooling System: Clean the dust filter and debris. Replace the damaged cooling fan to ensure proper ventilation. Add insect mesh to the air intake to prevent blockage.
- Derated Usage: In high-temperature environments, derate circuit loads by 10%-20% to avoid full-load operation. Redistribute oversized loads to other circuits or upgrade component specifications.
- Terminal Treatment: Clean and re-tighten oxidized or loose terminals. Apply conductive paste to high-current terminals to reduce contact resistance.
- Optimize Layout: Modify the internal layout, distribute heat-generating components, reserve heat dissipation channels, and add guide vanes or ducts if necessary.
Fault 19: Equipment Malfunctions or Component Damage After Lightning Strikes
Possible Causes:
- The surge protective device (SPD) has failed or degraded and cannot discharge the lightning overvoltage.
- Lightning intensity exceeds the maximum discharge current of the installed Type 2 SPD.
- Poor grounding system (excessive ground resistance), preventing the surge from quickly dissipating to the ground.
- Signal and control lines lack signal surge protection. Induced lightning enters via weak-current lines, damaging control modules.
- Incoming/outgoing cables lack proper shielding/grounding, causing induced coupled overvoltage.
Troubleshooting Steps:
- Visual Inspection: Check the SPD’s status indicator window (Red = failed). Inspect components for signs of burning, cracking, or puncture marks.
- Grounding Test: Re-test the grounding resistance to confirm it is ≤ 4Ω. Check the grounding conductor for breaks or loose connections.
- Functional Test: Test the power distribution, control, and communication functions one by one to identify damaged modules and components.
- Line Check: Inspect signal and power lines for installed surge protection devices and verify compliant installation.
Solutions:
- Replace SPD: Immediately replace failed power SPDs. In high-lightning areas, upgrade to Type 1 + Type 2 cascaded protection to increase discharge capacity.
- Rectify Grounding: Re-do the grounding system, increase ground rods, add resistance-reducing agents, and ensure stable grounding resistance below 4Ω.
- Signal Protection: Install appropriate signal surge protectors on communication lines, sensor signal lines, and control circuits for full-port lightning protection.
- Replace Damaged Components: Replace damaged breakers, controllers, communication modules, etc., one by one. Test fully before putting the system back into service.
- Cable Shielding: Use armored shielded cables for incoming/outgoing lines. Connect both ends of the shield layer reliably to the ground to reduce induced lightning coupling.
Fault 20: Severe Condensation Inside Enclosure, Insulation Degradation Causing Malfunctions
Possible Causes:
- Large temperature differences between day and night. Rapid nighttime cooling causes moist internal air to condense into water droplets.
- Enclosure installed in a low-lying, damp area with high groundwater levels. Moisture intrudes from the bottom.
- Cable entry holes are poorly sealed, allowing moisture to enter along the cables.
- The enclosure’s breather valve is blocked, preventing pressure equalization and moisture exhaust.
- Humid climate (e.g., plum rain season in the south, coastal high-humidity), with long-term saturated air humidity.
Troubleshooting Steps:
- Open the enclosure door and check the inner walls and component surfaces for condensation droplets, damp spots, or mold.
- Check the bottom cable entry holes and enclosure weld seams for signs of moisture intrusion.
- Measure the relative humidity inside the enclosure to confirm if it has been consistently above 90%.
Solutions:
- Install Dehumidifier: Configure a semiconductor dehumidifier or a PTC heating dehumidifier with automatic humidity control to maintain internal humidity below 75%.
- Improve Sealing: Re-seal cable entry holes. Replace aged sealing gaskets to reduce external moisture intrusion.
- Install Breather Valve: Install a waterproof breather valve on the enclosure top to balance internal/external pressure, expel moisture, and prevent liquid water entry.
- Improve Environment: Elevate the installation foundation and ensure proper site drainage to prevent the enclosure from sitting in a perpetually damp location.
- Periodic Drying: During the plum rain season, periodically energize the system in no-load operation, using component self-heating to drive out moisture.
Chapter 14 Product QA – Frequently Asked Questions
This chapter compiles high-frequency questions regarding street lighting control cabinets throughout their lifecycle – from selection and installation to commissioning and maintenance, providing professional answers in a Q&A format for quick reference by project personnel.
14.1 Basic Selection
Q1: How do I choose the number of circuits for a lighting control cabinet? How many circuits are typically needed per road?
A: The number of circuits depends on the road length, pole spacing, luminaire wattage, and control zones. For standard municipal roads with single-side spacing of 30 meters, it is recommended to have 8-12 LED streetlights per circuit, with a single-circuit power controlled within 2 kW (corresponding current is approximately 10A). Use a 16A breaker. For example, a 1 km road with double-side lighting involves approximately 66 luminaires. It is recommended to configure a lighting cabinet with 6-8 circuits, distributing 2-3 circuits per phase to ensure three-phase balance. If separate control is needed for midnight lights and full-night lights, or if there are other loads like landscape lights or advertising light boxes, the number of circuits must be increased accordingly.
Q2: What scenarios are suitable for floor-standing, wall-mounted, and pole-mounted cabinets? How do I choose the installation method?
A: The selection principles for the three installation methods are as follows:
- Floor-standing: Suitable for larger cabinets with ≥12 circuits or total current above 100A. Commonly used for major urban roads, expressways, large industrial parks, etc. It offers stable installation and ample maintenance space and is the mainstream choice for municipal projects. Requires a concrete foundation and a slightly longer construction time.
- Wall-mounted: Suitable for smaller cabinets with 6-8 circuits. Commonly used for branch roads in residential areas, parks, and factories. Mounted on exterior walls or solid boundary walls, saving ground space with convenient installation. Requires the wall to be a solid, load-bearing structure.
- Pole-mounted: Suitable for small capacity cabinets within 6 circuits. Commonly used for rural roads, scattered points, and temporary lighting. Mounted directly on the light pole, eliminating the need for a foundation, offering fast construction and low cost. Limited by the pole’s load-bearing capacity; cannot be used for larger cabinets.
Q3: Is a stainless steel enclosure necessary in ordinary areas? In what situations must stainless steel be used?
A: For ordinary inland cities and standard road environments, a standard cold-rolled steel enclosure with sprayed coating fully meets the requirements, offering a service life of up to 15 years or more and providing better cost-effectiveness. However, a 304/316 stainless steel enclosure is recommended in the following scenarios:
- Coastal areas, seaside roads, or environments with severe salt spray corrosion.
- Chemical industrial parks, sewage treatment plants, metallurgical plants, or other environments with corrosive gases or liquids.
- Hot, humid, rainy southern regions where mold easily grows.
- High-end projects requiring superior aesthetics and corrosion resistance.
- 304 stainless steel is suitable for moderate corrosive environments; 316 stainless steel is suitable for strong corrosive environments and heavy salt spray coastal areas.
Q4: How do I choose between time control, light control, latitude/longitude control, and 4G remote control? Which is the most practical?
A: The four control methods have different applicable scenarios and can be selected based on specific needs:
- Time Control Only: Lowest cost, simple settings. Suitable for small projects with fixed lighting requirements and sufficient maintenance personnel, such as rural roads and small factories. The drawback is that times need manual adjustment with seasonal changes, and it cannot adapt to rainy days.
- Time + Light Control: Best cost-performance ratio. Uses time control as the base with light control for weather correction, automatically turning lights on earlier on cloudy days. Suitable for most standard roads, residential areas, and parks. Avoids the rigidity of time-only control and is cheaper than latitude/longitude control.
- Latitude/Longitude Control: No manual seasonal adjustments needed. Automatically adjusts throughout the year based on sunrise and sunset times. Offers good energy savings and low maintenance requirements. Suitable for major urban roads, long-distance roads, and suburban projects with limited maintenance staff.
- 4G Remote IoT Type: Most feature-rich. Enables remote monitoring, remote control, and fault alarming. Suitable for city-level batch management and smart lighting projects. Although the unit price is slightly higher, it significantly reduces inspection and maintenance costs, offering better long-term returns.
- General recommendation: Prioritize the “Latitude/Longitude + Light Control” combination. If the budget allows, directly go for the 4G IoT type, which is currently the mainstream configuration for smart lighting.
Q5: Is a surge protective device (SPD) standard equipment? Is it necessary to add Type 1 lightning protection?
A: Our standard street lighting control cabinets are equipped with a Type 2 power SPD as standard. This protects against induced surges and switching overvoltages, meeting the lightning protection requirements for the vast majority of scenarios. It is recommended to add an additional Type 1 SPD or upgrade to a high-current capacity SPD in the following scenarios:
- High lightning activity areas (annual thunderstorm days > 40), open rural areas, hilltops, or other high-risk zones.
- Lighting cabinets located in open areas like tunnel entrances, bridges, and elevated roads.
- IoT type cabinets equipped with numerous smart modules and precise control components.
- Scenarios where the power supply line is overhead and directly exposed outdoors.
- The Type 1 SPD should have a nominal discharge current of ≥ 100kA, installed at the main incoming line end. It works with the Type 2 SPD for cascaded protection, providing more reliable lightning protection.
14.2 Installation and Construction
Q6: Is a foundation mandatory for the lighting cabinet? Can it be placed directly on the ground?
A: A concrete foundation is mandatory for floor-standing lighting cabinets. Placing them directly on the ground is strictly prohibited. There are three reasons: First, it prevents ground water from immersing the cabinet bottom, preventing rust and water ingress. Second, it ensures the cabinet is stable, wind-resistant, and collision-proof, preventing tipping. Third, it isolates ground moisture, reducing internal condensation. The foundation should be 100-200mm above ground level, made of C20 or higher grade concrete, with a depth of at least 500mm. In northern regions, it must be deeper than the frost line to prevent frost heave deformation. For temporary use, small cabinets can be placed on precast concrete blocks, but a permanent foundation is mandatory for long-term use.
Q7: What is the required grounding resistance? What if it’s not achieved? How many ground rods are needed?
A: As a low-voltage distribution device, the protective grounding resistance for a lighting cabinet is required to be ≤ 4Ω, as mandated by national regulations. In normal soil resistivity conditions, grounding resistance within 4Ω can typically be achieved by driving 2-3 pieces of 2.5m long ∠50 galvanized angle steel ground rods, spaced 5m apart, and connected with flat steel.
If the measured grounding resistance does not meet the standard, the following measures can be taken:
- Increase the number of ground rods and extend the length of the grounding grid.
- Replace the soil around the ground rods with low-resistivity clay or black soil.
- Add resistance-reducing agents or modules to lower soil contact resistance.
- Utilize natural grounding bodies found nearby, such as metal pipelines or rebar in building foundations.
- It is strictly forbidden to use water pipes or gas pipelines as grounding rods due to safety hazards.
Q8: Should a lighting cabinet installed by the roadside be equipped with anti-collision measures?
A: For cabinets installed next to non-motorized vehicle lanes, pedestrian walkway edges, or parking lots, it is recommended to add anti-collision measures to prevent vehicle damage. Common methods:
- Install Steel Anti-Collision Guardrails: Create a U-shape or box-shape guardrail around the cabinet, 0.5-0.8m high, painted with yellow-black warning stripes for visibility and impact absorption.
- Set Up Anti-Collision Bollards: Pour concrete bollards around the cabinet or place pre-made rubber anti-collision blocks.
- Relocate Installation: Where conditions permit, install the cabinet within the roadside green belt, set back more than 50cm from the curb, to fundamentally avoid collision risks.
- Cabinets located alongside expressways or major roads must have anti-collision protection and reflective markings to improve nighttime visibility.
Q9: Why should cables enter and exit from the bottom of the enclosure? Can they enter from the side or top?
A: Bottom cable entry is the standard design for outdoor enclosures. The core purpose is waterproofing: rainwater flowing down cables will not be directed into the enclosure, and reliable waterproofing can be achieved with cable glands and sealing putty. Side or top entry poses significant water ingress risks, as rainwater can easily flow along the cables into the enclosure, often causing short circuits.
If side or top entry is absolutely necessary, special waterproofing measures must be taken: Create a drip loop in the cable, install waterproof elbows at the entry holes, seal rigorously after entry, and ensure a rain cover shields the area. Side or top entry is not recommended unless absolutely necessary; please contact the manufacturer for custom hole punching if needed.
14.3 Wiring and Commissioning
Q10: How do I balance the three phases for streetlights? What is the impact of imbalance?
A: Three-phase load balancing is a fundamental requirement for low-voltage distribution. The allocation principle is to distribute all lighting circuits evenly across phases L1, L2, and L3, striving for similar total power per phase. For example, with 12 circuits: L1 carries circuits 1, 4, 7, 10; L2 carries 2, 5, 8, 11; L3 carries 3, 6, 9, 12. Cross-distribution avoids having most of the initial circuits on a single phase.
Hazards of Three-Phase Imbalance:
- Excessive neutral current, causing neutral wire heating, increased line losses, and in severe cases, burning out the neutral wire.
- Three-phase voltage shifts, with some phases too high and others too low, leading to uneven luminaire brightness and reduced lifespan.
- Increased transformer losses and degraded power supply quality.
- Regulations require the three-phase current imbalance to be ≤ 25%. If exceeded, circuit allocation must be adjusted.
Q11: Can the neutral and ground wires be connected together? Why should they be separate?
A: In a TN-S system, the neutral (N) wire and the protective earth (PE) wire must be strictly separated, and mixing them is strictly prohibited. The neutral is the working conductor, carrying current under normal operating conditions. The ground wire is the protective conductor, carrying no current under normal conditions, only conducting fault current during a fault.
Mixing neutral and ground leads to the following problems:
- The ground wire becomes live during normal operation, energizing the enclosure casing and posing a serious electric shock hazard.
- Residual current devices (RCDs) may not function properly, failing to trip during earth leakage faults, losing their protective function.
- Interference with weak-current signals, affecting the stable operation of controllers and communication modules.
- Neutral and ground are only connected together at the transformer’s neutral point; they must be fully separated throughout the user-side installation.
Q12: Is it normal to see arcing when closing the breaker during commissioning? Is it a short circuit?
A: A slight arc when closing the breaker is a normal phenomenon, especially when closing with a load connected. A small arc is generated momentarily when the contacts touch. Seeing a small spark and hearing a soft “snap” is normal arcing, which the breaker’s arc extinguishing chamber quickly quenches.
However, if there is violent arcing, an explosive sound, smoke, or immediate tripping, this is abnormal and indicates a short circuit or severe overload. Power must be disconnected immediately for troubleshooting. Common causes: short circuit in the wiring, reversed neutral and ground wires, severe short circuit on the load side, damaged breaker, etc.
It is recommended to minimize closing breakers with load connected. Open all branch circuits first, close the main breaker, and then close the branch circuits one by one to reduce arcing.
Q13: Where is the best location to install the light sensor? Can it be installed inside the enclosure?
A: The light sensor cannot be installed inside the enclosure. The light conditions inside the enclosure differ greatly from the outside environment, rendering the detection data completely inaccurate. The correct installation location requirements:
- Install outdoors in an open, unobstructed area to accurately sense natural light changes.
- Avoid shaded areas that receive no direct sunlight, and avoid being blocked by trees or buildings.
- Keep it away from direct light sources like streetlights, advertising lights, and vehicle headlights to prevent false detection and erroneous switching.
- Avoid low-lying areas prone to water accumulation. Tilt the probe downwards at 15 degrees to prevent rainwater from pooling on the lens.
- Typically installed on the top exterior of the enclosure or on a nearby light pole at a height of 2.5-3 meters.
- After installation, test: lights should turn on automatically at dusk and turn off automatically at dawn, matching local conditions.
14.4 Operation and Maintenance
Q14: What routine maintenance does a lighting cabinet require? How often?
A: Routine maintenance is divided into different levels, with frequencies and content as follows:
- Daily/Weekly Inspection: Visual check for closed doors, damage, and status indicators. No opening required. Performed by inspection personnel.
- Monthly Maintenance: Open the enclosure, clean dust, tighten wiring terminals, check seals and door locks, test manual functions. Performed by junior electricians.
- Quarterly Overhaul: Test insulation resistance and grounding resistance, verify protection functions, calibrate control parameters, check component status. Performed by intermediate electricians.
- Annual Major Service: Comprehensive deep cleaning, replacement of wear parts, full performance testing, and rectification of hazards. Recommended to be completed before the annual thunderstorm season.
- The above cycles apply to normal environments. Coastal, high-humidity, dusty, or highly corrosive environments require shortened maintenance cycles and increased frequency.
Q15: How often should the surge protective device be replaced? How can I tell if it needs replacement?
A: The surge protective device is a consumable component. Under normal conditions, its lifespan is 3-5 years. It must be checked and replaced immediately after a severe lightning strike. Methods to determine if replacement is needed:
- Check Status Window: Green indicates normal, Red indicates failed. Immediate replacement is required if red.
- Check Appearance: Cracks, deformation, charring, or smoke indicate replacement is necessary.
- Post-Lightning Test: After strong thunderstorms, test for leakage current using a surge tester. Replace if leakage current exceeds standards.
- End of Lifecycle: After 5 years of use, replacement is recommended even if the appearance is fine, as the protection capability of aging internal components decreases significantly.
- A failed SPD means no lightning protection. A lightning strike can directly damage expensive downstream control components. Be sure to replace them promptly.
Q16: Can a circuit breaker be directly re-closed after tripping? Why won’t it reset?
A: Absolutely not. Never forcibly reset a circuit breaker after it trips. The cause of the trip must be investigated and the fault cleared before re-closing. Forcibly re-energizing can exacerbate the fault, potentially destroying equipment or even causing a fire.
Common reasons why a breaker won’t reset:
- The fault (short circuit, earth leakage) still exists on the load side; it trips immediately upon resetting.
- The breaker is in a thermal trip state. After an overload trip, the bimetallic strip needs time to cool down and reset (wait a few minutes).
- The breaker’s operating mechanism is damaged and cannot be re-latched.
- After an RCD trips, the reset button may need to be pressed before it can be re-closed.
- Correct procedure: Disconnect all loads first, then attempt to re-close. If it holds, the fault is on the load side. If it still trips, the issue is within the breaker or the enclosure itself, requiring step-by-step investigation.
Q17: What should I do if mice or insects get inside the enclosure? How to prevent pests?
A: Rodents and insects entering the outdoor enclosure can cause short circuits, insulation degradation, and blocked ventilation channels. Prevention and control measures:
- Strictly seal all cable entry/exit holes with fire-stop putty or sealing compound, leaving no gaps.
- Install fine insect mesh over vents to allow airflow while blocking insects and rodents.
- Place glue traps or insect repellent packs in corners of the enclosure, checking and replacing them regularly. Never use highly toxic rodenticides to avoid dead rodents decaying, causing odors and corrosion.
- Clean up weeds, debris, and trash around the enclosure to reduce habitats for pests.
- Inspect the enclosure regularly. If pest traces are found, clean up immediately and check for chewed cables.
14.5 Smart Features
Q18: Does an intelligent lighting cabinet have to be connected to a platform to work? Can it operate independently?
A: Intelligent IoT lighting control cabinets support standalone operation. All basic functions such as time control, light control, latitude/longitude control, and local manual control work normally without a platform connection. A communication module fault does not affect local automatic lighting. Connecting to the platform adds value-added features like remote monitoring, remote management, data statistics, and fault alarming.
The device automatically runs its local control logic upon power-up. If the network is disconnected, it automatically switches to local autonomous mode and resumes data upload upon reconnection, fully ensuring normal lighting operations. This design ensures road lighting functions correctly even if the platform fails or the network is interrupted.
Q19: Is the data traffic cost for 4G communication expensive? How much traffic is used per year?
A: The data transmission volume for lighting cabinets is very small. It mainly uploads small data points like voltage, current, and switch status. With standard settings for a 5-minute upload interval, monthly traffic usage is only 10-30 MB (less than 500 MB per year). IoT cards are billed annually; the annual traffic fee is only a dozen to a few dozen RMB, making the cost extremely low. Even with a 1-minute upload interval, monthly traffic does not exceed 100 MB, keeping operational costs minimal.
- The IoT data card can be provided by our company, or users can purchase one themselves from the three major telecom operators.
Q20: Can it connect to a third-party smart city platform? What conditions are required?
A: Our intelligent lighting cabinets support standard communication protocols like Modbus-RTU and MQTT, allowing integration with third-party smart city, energy management, and smart park platforms. Conditions for integration:
- The third-party platform provides standard protocol interface documents, clearly defining the data point table and communication rules.
- If protocols are incompatible, a protocol conversion gateway can be installed for adaptation.
- Technical personnel from both parties collaborate to complete joint debugging and testing.
- Our company can provide customized integration development services, supporting seamless integration with mainstream domestic smart lighting and municipal management platforms.
14.6 After-Sales and Warranty
Q21: What is the warranty period for the product? Is repair free during the warranty period?
A: Our street lighting cabinets come with a 2-year warranty for the entire unit, a 3-year warranty for core control components, and a 5-year warranty for the enclosure structure. During the warranty period, product failures caused by non-human factors and non-force majeure events are covered by:
- Free repair
- Free replacement parts
- Free technical support
The following situations are not covered by the warranty:
- Human damage
- Unauthorized modification
- Water ingress or rodent entry
- Overload usage
- Force majeure events (floods, lightning strikes, earthquakes, etc.)
- Damage caused by failure to install or use according to the manual.
Lifelong repair services are available after the warranty period, charging only for parts cost and reasonable service fees.
Q22: How quickly can an engineer be dispatched for an on-site fault? What about remote areas?
A: We have established a comprehensive after-sales service system:
- Pearl River Delta Region: On-site response within 24 hours.
- Within the Province (Guangdong): Within 48 hours.
- Other Provinces: Within 72 hours for dispatching a technician.
- For remote areas: Initial troubleshooting will be conducted remotely via phone or video calls. Simple faults can often be resolved remotely. If remote resolution is impossible, technicians from the nearest service point will be dispatched, and spare parts will be shipped simultaneously to minimize fault downtime.
- For bulk projects, an annual operation and maintenance agreement can be signed, providing full-service options like regular inspections, emergency repair, and spare parts backup to ensure system stability.
Q23: Can you provide installation and commissioning services? How are charges applied?
A: We can provide professional installation guidance, on-site commissioning, and personnel training services.
- Small projects in the Pearl River Delta region can receive free phone guidance.
- Large projects can have engineers dispatched for on-site guidance as needed, with fees calculated based on project scale, travel distance, and service duration.
- Turnkey installation and commissioning services are also available, covering everything from foundation work and wiring to commissioning and acceptance, with transparent pricing and a hassle-free process.
- For specific quotes, please contact our sales engineers based on your project requirements.
Chapter 15 Product Acceptance
Product acceptance is a critical step to ensure product quality, construction quality, and operational performance. It is divided into four stages: Factory Acceptance, Site Acceptance, Installation & Commissioning Acceptance, and Final Completion Acceptance. Each stage must be strictly executed according to standards to ensure project delivery quality.
15.1 Factory Acceptance Testing
Factory Acceptance Testing (FAT) is the quality gate before products leave the factory. It is performed by our Quality Control (QC) department. Customers may send representatives to participate in the supervision and testing.
15.1.1 Acceptance Basis
- Product Technical Agreement and Purchase Contract Technical Requirements.
- GB 7251.1 “Low-voltage switchgear and controlgear assemblies – Part 1: General rules”.
- CJJ 45 “Standard for lighting design of urban road”.
- Product enterprise standards and design drawings.
15.1.2 Acceptance Items and Standards
| Category | Inspection Item & Standard |
|---|---|
| Appearance & Structure | – Cabinet paint finish is smooth and uniform, free from runs, bubbles, peeling, or scratches. Color matches the agreement.<br>- Cabinet dimensions within drawing tolerances. Diagonal deviation ≤ 3mm.<br>- Doors open/close smoothly, hinges flexible without jamming, locks engage reliably.<br>- Sealing gaskets securely attached, no breaks or peeling, compress evenly when closed.<br>- Weld seams smooth, no slag, cold lap, or cracks. Anti-corrosion treatment effective.<br>- Labels and nameplates complete and legible. Model and parameters match the contract. |
| Component Configuration | – Verify all electrical components (brand, model, specification, quantity) against the configuration list and contract.<br>- Components installed securely, neatly arranged, spacing meets standards. No looseness or damage.<br>- Component certificates of conformity and test reports are complete and valid. |
| Wiring Craftsmanship | – Internal wiring is horizontal/vertical, neatly bundled. Power and control wiring separated. Identification clear.<br>- Wire number sleeves complete, numbers match drawings, fonts clear and durable.<br>- Terminals crimped securely, no broken strands, excessive exposed copper. Tightening torque meets standards.<br>- Grounding system complete, copper busbar continuous, all ground points connected reliably. |
| Electrical Performance Test | – Insulation Resistance Test: Main circuit to ground ≥ 10MΩ. Control circuit ≥ 2MΩ.<br>- Power Frequency Withstand Voltage Test: Apply 2kV to the main circuit for 1 minute. No breakdown or flashover.<br>- Operational Test: Energize and manually operate each circuit. Contactors close correctly, indicators function correctly.<br>- Protection Function Test: RCDs and SPDs function normally and operate reliably. |
| Functional Test | – Time Control: Set timers and verify switching actions are accurate.<br>- Light Control: Simulate light changes to verify correct light control operation.<br>- Latitude/Longitude Control: Input coordinates and verify sunrise/sunset calculations are accurate.<br>- Communication Function: Test data upload and command sending/receiving via network connection. |
| Documentation & Accessories | – Shipment Documents: Product certificate, manual, warranty card, test report, schematic diagram, wiring diagram – all complete.<br>- Spare Parts & Accessories: Spare keys, spare fuses, installation accessories – complete and quantities accurate. |
15.1.3 Acceptance Process
1. QC department completes full factory inspection and issues the factory inspection report.
2. Notify the customer for on-site acceptance, or provide acceptance videos/photos.
3. Conduct item-by-item inspection according to the acceptance items. Fill out the factory acceptance record.
4. Upon successful acceptance, both parties sign for confirmation, and the product is approved for shipment.
5. For non-conforming items, issue a corrective action notice. Re-inspect after rectification, and only allow shipment after passing.
15.2 Incoming Acceptance Inspection
After the equipment arrives at the project site, the construction unit, supervision unit, and owner’s unit shall jointly conduct the incoming acceptance inspection. Only equipment that passes the inspection may be installed on site.
15.2.1 Acceptance Procedure
- Upon equipment arrival, verify the delivery note against the purchase order to confirm model and quantity consistency;
- Inspect the packaging for integrity, checking for damage, rain exposure, or impact marks;
- Open the case and inspect the equipment appearance for transportation bumps, deformation, paint peeling, or water ingress;
- Check components, accessories, and documentation against the packing list to confirm nothing is missing;
- Complete the equipment incoming acceptance form with signatures from all parties;
- Equipment failing the acceptance inspection shall be returned or exchanged; non-conforming products are strictly prohibited from entering the site for installation.
15.2.2 Key Acceptance Points
- Focus on transportation damage inspection: Check cabinet edges, door panels, and glass for collision deformation; verify internal components for displacement or loosening;
- Verify model and parameters: Confirm that the equipment model, number of circuits, control type, and installation method match the design drawings to avoid incorrect deliveries;
- Document review: Ensure quality certification documents such as 3C certification, factory inspection reports, and certificates of conformity are complete and valid;
- Proper storage: Equipment that passes acceptance shall be protected as finished products and stored in a dry, well-ventilated location to avoid secondary damage.
15.3 Installation Process Acceptance
Installation process acceptance covers concealed works and process-step inspections. The next process step may only proceed after the previous step has passed acceptance, to avoid rework at a later stage.
15.3.1 Foundation Works Acceptance
- Foundation dimensions, elevation, and strength comply with design requirements;
- Anchor bolt positions are accurate, and verticality complies with specifications;
- Embedded steel reinforcement and grounding flat steel within the foundation meet requirements;
- Concrete test cube strength reports are qualified, and the surface is free from honeycombing, pitting, or cracks.
15.3.2 Grounding System Acceptance
- Grounding electrode material, specifications, and driving depth comply with specifications;
- Grounding flat steel lap length and weld quality meet requirements, with proper anti-corrosion treatment;
- Grounding resistance test ≤ 4 Ω, with complete test records;
- Cabinet body is reliably connected to the main grounding busbar, with clear grounding markings.
15.3.3 Cabinet Installation Acceptance
- Cabinet is securely installed with all anchor bolts tightened;
- Cabinet levelness deviation ≤ 2 mm/m, verticality deviation ≤ 1.5 mm/m;
- Cabinet elevation complies with the design, with appropriate cable entry/exit heights;
- Cabinet doors open and close smoothly, locks are intact, and sealing is effective.
15.4 Wiring Process Acceptance
After wiring is completed and before energization, a dedicated wiring quality inspection shall be conducted.
- Cable specifications and models comply with design requirements, with certificates of conformity complete;
- Wiring phase sequence is correct, color coding complies with standards, and neutral and protective earth conductors are strictly separated;
- All wiring terminals are tightened, crimping workmanship is qualified, with no loose connections, exposed copper, or broken strands;
- Cable routing is neat, markings are clear, strong and weak current cables are separated, and shielding is applied at crossing points;
- Cable entry holes are properly sealed with adequate waterproofing measures;
- Insulation resistance tests pass, with no short circuits or ground faults;
- Circuit markings, terminal markings, and equipment markings are complete and accurate.
15.5 Commissioning Acceptance
After commissioning is completed, a dedicated functional and performance acceptance inspection shall be conducted to verify that all equipment indicators meet the design requirements.
15.5.1 Power Distribution Performance Acceptance
- All circuits energize normally, all luminaires illuminate, with no entire section failing to light;
- Three-phase voltage is balanced, deviation ≤ 5%, and three-phase current unbalance ≤ 25%;
- After 1 hour of full-load operation, terminal and component temperature rise ≤ 30 K, maximum temperature ≤ 65 °C;
- All circuit breakers and contactors operate normally, with no abnormal noise or overheating;
- Protection functions such as short circuit, overload, and leakage protection operate accurately and reliably.
15.5.2 Control Function Acceptance
- Manual control: Manual switching of each circuit operates normally, with correct correspondence and synchronized indicator lights;
- Time control: Scheduled on/off times are accurate, with error ≤ 1 minute;
- Light control: Light-level threshold triggering is accurate, delay function operates normally, with no false operation;
- Latitude/longitude control: Sunrise/sunset calculation is accurate, and switching times conform to actual local conditions;
- Scene modes: Midnight lighting, holiday, energy-saving, and other modes switch correctly with proper logic.
15.5.3 Intelligent Communication Acceptance
- Equipment connects to the network normally and is online, with signal strength meeting requirements;
- Data upload is accurate; voltage, current, power, and other data deviate from on-site measurements by ≤ 5%;
- Remote control responds promptly, commands execute accurately, and status feedback is correct;
- Fault alarm functions operate normally; alarm messages are pushed promptly after simulated faults;
- Historical data storage, query, and export functions operate normally.
15.6 Final Completion Acceptance
After the overall project installation and commissioning are complete and the trial run passes, a final completion acceptance shall be conducted as the final stage of project delivery.
15.6.1 Trial Run Requirements
- Equipment operates continuously without fault for more than 72 hours;
- All indicators remain stable during the trial run with no major faults;
- Lighting rate ≥ 98%, complying with municipal road lighting acceptance standards;
- Trial run records are complete with full data.
15.6.2 Acceptance Documentation
The following complete completion documentation shall be submitted for final acceptance, including but not limited to:
- Completion drawings: System diagrams, layout plans, wiring diagrams, foundation drawings, grounding drawings;
- Equipment documentation: Product certificates of conformity, instruction manuals, 3C certification, test reports, factory inspection reports;
- Construction documentation: Construction records, concealed works acceptance records, grounding resistance test records, insulation test records;
- Commissioning documentation: Commissioning records, trial run records, functional test records;
- Management documentation: Commencement report, completion report, bill of quantities, change orders;
- Operation and maintenance documentation: Operation manuals, maintenance procedures, spare parts lists.
15.6.3 Acceptance Conclusion
- If all acceptance items pass and documentation is complete, the project is deemed to have passed acceptance. The completion acceptance form shall be signed, and the project shall be formally handed over for use;
- If general non-conforming items exist that do not affect safety or primary functions, rectification shall be completed within a specified period, followed by re-inspection;
- If major quality issues exist that affect safe operation, the project shall be deemed to have failed acceptance. Work shall be suspended for rectification, and acceptance shall be re-organized.
15.7 Summary of Acceptance Criteria
| Acceptance Item | Acceptance Criterion | Test Method |
|---|---|---|
| Cabinet verticality | ≤ 1.5 mm/m | Plumb bob, steel tape measure |
| Cabinet levelness | ≤ 2 mm/m | Spirit level |
| Grounding resistance | ≤ 4 Ω | Ground resistance tester |
| Main circuit insulation resistance | ≥ 0.5 MΩ | 500 V megger |
| Power frequency withstand voltage | 2 kV/1 min, no breakdown | Withstand voltage tester |
| Three-phase voltage unbalance | ≤ 5% | Multimeter |
| Three-phase current unbalance | ≤ 25% | Clamp meter |
| Terminal temperature rise | ≤ 30 K | Infrared thermometer |
| Time control accuracy | ≤ ±1 min/day | Stopwatch verification |
| Light control accuracy | ≤ ±10% | Illuminance meter calibration |
| Data measurement accuracy | ≤ ±5% | Comparison with standard instruments |
| System lighting rate | ≥ 98% | Night-time statistics |
| Fault response time | ≤ 5 minutes (smart model) | Simulated fault test |
Chapter 16: SEO Keyword System and Optimization Tags
16.1 Search Keyword Classification and Layout
Core Primary Keywords
Road lighting cabinet, outdoor road lighting cabinet, road light control cabinet, road light distribution box, lighting distribution cabinet
High-Conversion Long-Tail Keywords
Road lighting cabinet manufacturer, smart road lighting cabinet price, outdoor road light distribution box manufacturer, municipal road light control cabinet custom, road lighting distribution cabinet installation, LED road light control box, road light time-controlled distribution box, outdoor waterproof road light cabinet, road lighting cabinet price per unit, integrated road light control box
Industry Traffic Keywords
Urban road lighting distribution cabinet, smart street light control cabinet, solar street light control box, municipal lighting distribution box, outdoor lighting control cabinet, street light dedicated distribution box, lighting control cabinet, street light remote control cabinet, latitude/longitude street light controller, street light lightning protection distribution box
Brand-Specific Keywords
Lain road light photoelectric cabinet, Guangdong Lain road lighting cabinet, Lain intelligent lighting cabinet, Lain outdoor equipment cabinet, Lain street light distribution box, Guangzhou Lain street light control cabinet
Dropdown/Related Search Keywords
Road lighting cabinet wiring diagram, road lighting cabinet installation specifications, road lighting cabinet working principle, street light distribution box dimensions and specifications, how to set time on road light control cabinet, road lighting cabinet grounding requirements, outdoor street light distribution box protection rating, street light distribution cabinet technical parameters
16.2 SEO Optimization Tag System
Core Page Optimization Tags
Build a hierarchical optimization system centered on the core theme of “road lighting cabinets,” covering the full path from homepage to detail pages, covering the full user search path to improve keyword rankings and natural traffic conversion.
Title Tag
Road Lighting Cabinet_Outdoor Smart Street Light Control Cabinet_Municipal Lighting Distribution Box Manufacturer — KITOZER Smart Equipment Co., Ltd.
Meta Keywords
Road lighting cabinet, outdoor street light control cabinet, intelligent lighting distribution cabinet, street light distribution box manufacturer, road lighting control box, LED street light cabinet, outdoor waterproof lighting cabinet, Lain road light cabinet
Meta Description
KITOZER (Guangzhou Lain Intelligent System Development Co., Ltd.) is a professional manufacturer of road lighting cabinets, intelligent street light control cabinets, and outdoor lighting distribution boxes. We provide time-controlled/light-controlled/latitude-longitude/4G remote multiple specification products with IP65 protection, suitable for municipal roads, industrial parks, scenic areas, and all scenarios. We offer integrated installation and commissioning services. Service hotline: +86 13538869979.
H1 Tag
Function-Specific Outdoor Equipment Cabinet: Complete Manual for Installation, Wiring, and Commissioning of Road Lighting Cabinets
H2 Tags
Road lighting cabinet product introduction, road lighting cabinet product composition structure, road lighting cabinet configuration list, road lighting cabinet working principle, road lighting cabinet technical parameters, road lighting cabinet functional features, road lighting cabinet application scenarios, road lighting cabinet installation and construction specifications, road lighting cabinet wiring standards, road lighting cabinet commissioning process, road lighting cabinet usage precautions, road lighting cabinet maintenance methods, road lighting cabinet common fault troubleshooting, road lighting cabinet Q&A, road lighting cabinet acceptance standards
Internal Link Optimization Tags (Anchor Text — Natural Placement)
- Core anchor text: Road lighting cabinet, street light control cabinet, lighting distribution box
- Long-tail anchor text: Intelligent road lighting cabinet, outdoor waterproof street light cabinet, municipal road lighting distribution cabinet, street light time/light control box
- Related anchor text: Outdoor equipment cabinet, intelligent lighting control system, low-voltage distribution cabinet, outdoor waterproof cabinet, equipment room cabinet
Copyright Notice
All text, images, and drawings in this document (Manual for Installation, Wiring, and Commissioning of Road Lighting Cabinets) are copyrighted by Guangzhou Lain Intelligent System Development Co., Ltd. and protected by national copyright law.
No individual or organization may reproduce, reprint, modify, or excerpt any part or the entirety of this document for commercial purposes without written authorization from our company. The content of this document may not be used for competitor promotion, product imitation, bid submissions, or other commercial activities.
For non-commercial study or reference reproduction, the original source must be cited as “Source: Guangzhou Lain Intelligent System Development Co., Ltd.,” complete copyright information must be retained, and core content may not be deleted or modified.
Our company reserves the right to pursue legal liability for any infringement. Infringement will be prosecuted.
Contact Information
Manufacturer: Guangzhou Lain Intelligent System Development Co., Ltd. (KITOZER)
Service Hotline: +86 13538869979 (WeChat same number)
Technical Support: +86 13538869979
Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou, China
Official Website: https://gdlain.com