Table of Contents
TogglePreface

With the rapid development of the digital economy, equipment density in critical infrastructure such as data centers, telecommunications equipment rooms, and computing centers continues to rise. Per-cabinet power and equipment weight are growing exponentially, posing severe challenges to building floor load-bearing capacity. In scenarios where existing buildings are converted into equipment rooms, or old equipment rooms are being upgraded and expanded, the original building floor slab load capacity often cannot meet the placement requirements of heavy-duty cabinets, UPS power supplies, battery banks, precision air conditioners and other equipment. Direct deployment may bring safety risks such as floor slab cracking, structural settlement, and even collapse.
As the core solution in the field of equipment room load-bearing reinforcement, the ground load-bearing support bracket employs the mechanical principle of “concentrated load dispersion and uniform stress transmission” to evenly distribute the concentrated weight of equipment through a steel structure frame onto a larger floor slab contact area, keeping the load per unit floor area within the building design allowable range. It is essential infrastructure for ensuring equipment room structural safety and stable equipment operation.
This manual has been compiled by the Technology R&D Center of Guangzhou Lain Intelligent System Development Co., Ltd. based on current national standards and years of engineering practice. It comprehensively covers the entire process of ground load-bearing support brackets, including product definition, structural composition, classification and selection, technical parameters, installation procedures, wiring specifications, commissioning methods, operation and maintenance, fault troubleshooting, and quality acceptance. It aims to provide standardized, professional technical guidance for engineering design units, construction units, and operation and maintenance units, ensuring product installation quality and operational safety.
This manual strictly follows the following national and industry standards: *Code for Design of Data Centers* GB 50174-2017, *Load Code for the Design of Building Structures* GB 50009-2012, *Standard for Design of Steel Structures* GB 50017-2017, *Code for Construction and Acceptance of Data Center Infrastructure* GB 50462-2015, *General Specification for Antistatic Access Floors* GB/T 35665-2017, among others. All technical indicators have been verified by third-party testing institutions and may be directly used as technical basis for engineering construction and acceptance.
Chapter 1 Product Introduction

1.1 Product Definition
A ground load-bearing support bracket, also known as an equipment room load distribution frame, equipment load-bearing base, or floor slab load-bearing reinforcement bracket, is a steel structure load-bearing dispersion device specially developed for heavy-duty equipment in equipment rooms. It forms a rigid load-bearing frame through the combination of vertical support members and horizontal beam members, evenly distributing the concentrated vertical loads of cabinets, battery cabinets, UPS mainframes, precision air conditioners and other equipment onto a larger floor contact area, thereby reducing the pressure per unit area on the floor slab, enabling the floor load to meet building structural design requirements, and preventing floor slab deformation, cracking, or even structural failure caused by excessive local loads.
This product belongs to the category of equipment room structural safety infrastructure. It is the mainstream technical solution for addressing insufficient floor slab load-bearing capacity in existing building conversions, old equipment room expansions, and high-density computing center construction. Compared with traditional reinforcement methods such as concrete thickening, steel plate bonding reinforcement, and carbon fiber reinforcement, it offers significant advantages including shorter construction periods, no need to damage building structures, disassembly and reuse capability, and controllable costs.
1.2 Industry Development Background
Load-Bearing Pressure from Increased Equipment Density
With the widespread adoption of cloud computing, artificial intelligence, and big data technologies, the power of a single server cabinet has increased from 2kW in the early stages to 8kW, 12kW, or even 20kW and above. Correspondingly, equipment weight has grown from the traditional 300-500kg/cabinet to 800-1500kg/cabinet, with some liquid-cooled high-density cabinets weighing more than 2 tons. The traditional office floor design live load of 3.5-5.0kN/㎡ is completely inadequate, making load-bearing reinforcement a prerequisite for equipment room construction.
Surge in Demand for Existing Building Conversions
China has a vast stock of commercial and office buildings, and a large number of data centers and equipment rooms are built through conversion of existing buildings. These buildings were originally designed for office or commercial purposes, with generally low floor slab load capacities that cannot directly accommodate heavy IT equipment. Load-bearing reinforcement is a core part of such conversion projects. According to industry statistics, more than 60% of existing building equipment room conversion projects require dedicated load-bearing reinforcement treatment.
Continuous Improvement of Standards and Specifications
The state has successively issued mandatory standards including the *Code for Design of Data Centers* and the *Code for Construction and Acceptance of Data Center Infrastructure*, which explicitly specify floor load requirements for different levels of equipment rooms. Among them, the live load for Class A data center main computer rooms shall not be less than 8.0kN/㎡, and UPS equipment rooms and battery rooms shall not be less than 16.0kN/㎡, driving the standardization and normalization of load-bearing reinforcement technology.
Popularization of Modular Equipment Rooms
The rapid promotion of modular data centers and micro-module equipment rooms requires load-bearing reinforcement solutions to feature rapid deployment, flexible adjustment, and relocatability and reusability. Prefabricated ground load-bearing support brackets precisely match this development trend and have become the standard supporting product for modular equipment rooms.
1.3 Product Design Philosophy
This series of ground load-bearing support brackets follows the core design philosophy of “safety and compliance, modular design, convenient construction, and full-lifecycle reliability,” specifically reflected as follows:
Safety First, Redundant Design
All products are designed with a safety factor of 1.3-1.5 times the actual load-bearing requirement, reserving sufficient safety margin. Extreme working conditions such as equipment handling impact loads, maintenance personnel live loads, and seismic additional loads are fully considered to ensure structural safety and reliability.
Modular Assembly, Welding-Free Construction
Standardized prefabricated components are used. On-site assembly requires only bolted connections with no hot work welding required, reducing construction safety risks and improving installation efficiency. The design also supports later expansion, adjustment, disassembly, and reuse, adapting to dynamic equipment room operation and maintenance needs.
Height Adjustable, Adapting to Complex Working Conditions
Support columns are equipped with high-precision threaded leveling mechanisms that accommodate various raised floor height requirements and ground flatness deviations, ensuring the levelness of the bracket top surface and equipment installation precision.
Corrosion-Resistant, Long-Life Design
Main components use anti-corrosion treatment processes such as hot-dip galvanizing and Dacromet coating, suitable for the constant temperature, constant humidity, and high cleanliness operating environment of equipment rooms. The design service life is no less than 20 years, synchronous with the equipment room full lifecycle.
System Compatibility, Functional Integration
Compatible with antistatic access floor systems, equipotential grounding systems, cable management systems, seismic reinforcement systems, and other equipment room infrastructure, achieving multi-system integrated consolidation and reducing cross-construction difficulty.
1.4 Applicable Standards and Specifications
The design, production, installation, and acceptance of this product strictly comply with the following national and industry standards:
| Standard No. | Standard Name |
|---|---|
| GB 50174-2017 | Code for Design of Data Centers |
| GB 50009-2012 | Load Code for the Design of Building Structures (2012 Edition) |
| GB 50017-2017 | Standard for Design of Steel Structures |
| GB 50462-2015 | Code for Construction and Acceptance of Data Center Infrastructure |
| GB/T 35665-2017 | General Specification for Antistatic Access Floors |
| GB 50205-2020 | Standard for Acceptance of Construction Quality of Steel Structures |
| GB 50367-2013 | Code for Design of Strengthening Concrete Structure |
| T/CEC 178-2020 | Technical Specification for Modular Construction of Data Centers |
| YD/T 2164-2010 | Environmental Conditions of Communication Data Center Equipment Room |
| GB 50011-2010 | Code for Seismic Design of Buildings (2016 Edition) |
1.5 Product Core Value
Structural Safety Assurance
Effectively disperses concentrated equipment loads, keeping the pressure per unit floor area within the building design allowable range, eliminating risks of floor slab deformation and cracking, and ensuring the safety of building structures and equipment room equipment.
Compliance Support
Meets the mandatory floor load requirements of national data center design codes and equipment room acceptance standards, providing a compliance basis for equipment room level certification and safety acceptance.
Economical and Efficient
Compared with traditional civil engineering reinforcement methods, the construction period is shortened by more than 70%, the comprehensive cost is reduced by 40%-60%, and the product can be repeatedly disassembled and reused, adapting to equipment room upgrade and iteration needs with lower full-lifecycle costs.
Construction Friendly
Prefabricated installation requires no hot work and no wet operations, causes no damage to the original building structure, and features low dust and low noise during construction. Partial renovation can be carried out in operating equipment rooms.
Flexible Layout
Bracket dimensions and layouts can be flexibly customized according to cabinet arrangements, supporting multiple reinforcement forms including single-cabinet, full-row, and full-area configurations. Later equipment relocation and expansion can be quickly adjusted.
Chapter 2 Product Composition

The ground load-bearing support bracket is a modular steel structure system consisting of six core subsystems: the vertical support system, horizontal beam system, leveling and locking system, anchoring and fixation system, equipotential grounding system, and auxiliary accessory system. All system components are produced to standard specifications and quickly assembled on site using bolts, buckles, and other fasteners to form a complete load-bearing unit.
2.1 Vertical Support System
The vertical support system is the core load-bearing structure of the support bracket, responsible for transmitting upper loads vertically to the floor slab. It mainly consists of the following components:
Support Columns
Support columns are the primary load-bearing members for vertical loads. Depending on the load-bearing class, they are manufactured from different specifications of pipe materials, including round steel pipe, square steel pipe, and C-channel steel. The standard version uses Φ32×2.0mm hot-dip galvanized round pipe, the reinforced version uses Φ45×2.5mm hot-dip galvanized round pipe, and the heavy-duty version uses 60×60×3.0mm hot-dip galvanized square pipe. Connection trays are welded to both the top and bottom ends of the columns for connection to the top beams and bottom bases.
Column length is customized according to raised floor height, with a standard height range of 100mm-1000mm. Special scenarios may require custom extended heights of 1000mm-2000mm. Ultra-tall columns require the addition of horizontal ties and diagonal bracing to ensure lateral stability.
Top Load-Bearing Trays
Welded to the top ends of the support columns, these trays receive the horizontal beams. They are typically square steel plates available in three standard sizes: 120×120×5mm, 150×150×6mm, and 200×200×8mm. The tray surfaces are pre-drilled with bolt holes for bolted connection with beams. Certain models include pre-formed slot structures for rapid beam snap-in installation. Tray surfaces receive galvanized anti-corrosion treatment, and edges are ground smooth with no burrs.
Bottom Compression Bases
Welded to the bottom ends of the support columns, these bases expand the contact area with the floor slab, reducing bottom pressure, and are also used for anchoring and fixation. The bases are also square steel plates available in standard sizes of 150×150×5mm, 200×200×6mm, and 250×250×8mm. Each base is pre-drilled with 2-4 expansion bolt mounting holes. Heavy-duty models may include additional stiffening ribs to improve deformation resistance.
Rubber vibration-damping pads may be adhered to the bottom of the bases, providing combined vibration damping, anti-slip, and insulation functions, preventing scratches and abnormal noise from direct metal-to-floor contact.
2.2 Horizontal Beam System
The horizontal beam system forms the upper load-bearing frame of the bracket, directly bearing the equipment weight and uniformly transmitting loads to each vertical support point. It mainly consists of three parts: main beams, secondary beams, and connection nodes.
Main Beams
Load-bearing beams arranged along the primary load direction of the equipment, directly receiving pressure from cabinet bases and equipment bases. Depending on the load-bearing class, main beams may use different profiles:
| Grade | Profile Specification | Application |
|---|---|---|
| Light-duty | 40×40×2.0mm galvanized square steel | Network cabinets, small equipment |
| Standard | 50×50×2.5mm galvanized square steel / 10# national standard channel steel | Standard server cabinets |
| Reinforced | 80×40×3.0mm C-channel / 12# national standard channel steel | High-density cabinets, UPS mainframes |
| Heavy-duty | 16# I-beam / H-beam | Battery banks, precision air conditioners, ultra-heavy equipment |
Main beam length is customized according to equipment dimensions, with standard lengths matching common cabinet widths of 600mm, 800mm, 1000mm, and 1200mm. Both ends are pre-drilled with connection holes for rapid connection with support columns.
Secondary Beams
Also known as tie beams, these are arranged perpendicular to the main beams. Their function is to enhance the overall rigidity of the frame, prevent lateral deformation of main beams, and disperse local loads. Secondary beam profile specifications are generally one grade lower than main beams, with spacing determined by stress calculations, typically 400-600mm. Secondary beams are connected to main beams via bolts or dedicated buckles, forming a “well” (#) shaped or “eye” (目) shaped grid frame.
Connection Node Components
Used for connecting beams to columns and beams to beams, including right-angle connectors, T-type connectors, and cross connectors. These are stamped from 2-5mm thick steel plate, hot-dip galvanized, and pre-drilled with standard bolt holes to achieve precise component alignment. Node components are key components ensuring overall frame stability, and their strength directly affects the overall deformation resistance of the bracket.
2.3 Leveling and Locking System
The leveling and locking system is used to adjust the overall height and levelness of the bracket, adapting to ground flatness deviations and different raised floor height requirements. It mainly consists of three parts: adjusting screw rods, locking nuts, and adjustment nuts.
Adjusting Screw Rods
Manufactured from high-strength carbon steel with galvanized surface treatment, thread precision class 6g. Diameters are divided into four specifications according to load-bearing class: M12, M16, M20, and M24. The lower end of the screw rod connects to the bottom base, and the upper end passes into the interior of the support column, achieving height adjustment through threaded engagement. Adjustment travel is typically ±20mm, ±30mm, or ±50mm, with some large-travel models reaching ±100mm.
Upper Locking Nuts
Used in conjunction with the adjusting screw rod, located at the lower end inside the support column. After height adjustment is completed, the upper nut is tightened to lock the relative position of the screw rod and column, preventing screw rod retraction under compression. Hex thick nuts are used to ensure sufficient thread engagement length and avoid thread stripping failure.
Lower Locking Nuts
Located above the bottom base. After the adjusting screw rod passes through the base, the lower nut is tightened to lock it in place, while also assisting in fine height adjustment and uniformly transmitting column loads to the base plate. The double-nut locking structure effectively prevents thread loosening under vibration conditions, ensuring long-term operational stability.
2.4 Anchoring and Fixation System
The anchoring and fixation system is used to firmly connect the entire bracket to the building floor slab, preventing horizontal displacement and overturning of the bracket, which is especially critical under conditions such as earthquakes and equipment handling impact loads. Main components include:
Expansion Bolts
Ordinary expansion bolts are used for conventional concrete floors, with specifications of M8×80mm, M10×100mm, and M12×120mm, selected according to bracket base size and load-bearing class. Each base is equipped with 2-4 expansion bolts. Bolt embedment depth into concrete shall not be less than 50mm to ensure the pullout resistance meets requirements.
Chemical Anchor Bolts
Suitable for scenarios with lower base material strength, higher anchoring force requirements, and environments where the surface layer should not be damaged, such as antistatic flooring and wear-resistant flooring. Chemical anchor bolts consist of a chemical adhesive cartridge and a threaded rod, bonding the rod and concrete into one unit through resin grouting. They provide stronger pullout resistance and cause less structural damage. Common specifications are M10×130mm and M12×160mm.
Adhesive Fixation Components
Suitable for floors where drilling is not appropriate (such as raised floor base layers, tile floors, and waterproofed floor slabs). High-strength structural adhesive is used to bond the bracket base to the ground. Dedicated primers and structural adhesives are used, and bond strength must be verified through pull-out testing. Suitable for light and medium-duty load-bearing brackets.
2.5 Equipotential Grounding System
All metal components in the equipment room must be connected to the equipotential grounding system to prevent static charge accumulation and potential differences, ensuring the safety of equipment and personnel. The grounding system of the load-bearing bracket includes the following components:
Grounding Connection Terminals
Pre-installed grounding bolt terminals on the bracket frame, typically M6 or M8 copper bolts, used for connecting grounding conductors. Each section of bracket frame shall have at least 2 grounding terminals to ensure redundant and reliable grounding paths.
Grounding Conductors
Multi-strand copper-core insulated conductors with a cross-sectional area of not less than 4mm², with 6mm² conductors for important areas. Both ends of the conductors are crimped with copper lugs and reliably connected to bracket grounding terminals and the equipment room equipotential copper busbar via bolts.
Conductive Washers
Installed at bolted connection nodes to break through the insulating effect of the galvanized layer on component surfaces, ensuring electrical continuity between metal components and forming the entire bracket frame as an equipotential whole. Conductive washers are made of copper (T2 grade) with tin-plated surfaces.
Copper Foil Strips
For bracket systems integrated with antistatic access floors, 20mm wide, 0.1mm thick copper foil strips are used to connect the bracket with the floor grounding system, forming a complete static discharge path.
2.6 Auxiliary Accessory System
Vibration Damping and Buffering Accessories
Including rubber vibration-damping pads and spring vibration isolators, installed between the top of the bracket and the equipment base, or between the bottom of the bracket and the floor. They absorb equipment vibration, reduce noise transmission, and prevent paint wear and abnormal noise from hard contact.
Edge Sealing and Decorative Accessories
Including side sealing panels and decorative cover plates, manufactured from cold-rolled steel plate with spray coating or aluminum alloy. They conceal the bracket sides, enhance overall aesthetics, and prevent cables and debris from falling beneath the bracket. Sealing panels may include ventilation openings and cable entry/exit ports.
Cable Management Accessories
Including cable organizers, cable tie bases, and cable troughs, installed on bracket beams to secure equipment power cables and signal cables, keeping wiring neat and organized for ease of operation and maintenance.
Seismic Reinforcement Accessories
Including lateral diagonal braces, seismic tie rods, and limit blocks, used in regions with high seismic fortification intensity to enhance lateral stability and overturning resistance of the bracket, meeting building seismic design code requirements.
Identification and Labeling
Including product nameplates, load rating labels, and warning signs, fixed at prominent positions on the bracket, indicating rated load capacity, manufacturer, installation date, and other information for ease of operation and maintenance management.
Chapter 3 Product Classification
This series of ground load-bearing support brackets can be classified into multiple categories based on load-bearing class, structural form, installation method, application scenario, material and process, to adapt to the load-bearing requirements, site conditions, and budget requirements of different equipment rooms.
3.1 Classification by Load-Bearing Class
According to the rated uniformly distributed load capacity of a single frame, the brackets are divided into five grades: light-duty, standard, reinforced, heavy-duty, and ultra-heavy-duty, covering all scenarios from weak-current equipment rooms to supercomputing centers.
3.1.1 Light-Duty Load-Bearing Brackets (L Series)
| Parameter | Value |
|---|---|
| Rated uniformly distributed load | ≤5kN/㎡ (approx. 500kg/㎡) |
| Maximum single-cabinet load | ≤800kg |
| Core configuration | Φ25×1.5mm support columns, 40×40×1.5mm square steel beams, M12 adjusting screw rods, 120×120×4mm bases |
| Application scenarios | Ordinary network cabinets, distribution frames, monitoring console desks, small office equipment room equipment, ordinary weak-current equipment room equipment |
| Characteristics | Light weight, low cost, easy installation. Suitable for scenarios with good floor slab load capacity and lighter equipment weights. The main function is to optimize stress distribution rather than substantially increase the load-bearing limit. |
3.1.2 Standard Load-Bearing Brackets (S Series)
| Parameter | Value |
|---|---|
| Rated uniformly distributed load | 5-10kN/㎡ (approx. 500-1000kg/㎡) |
| Maximum single-cabinet load | 800-1500kg |
| Core configuration | Φ32×2.0mm support columns, 50×50×2.0mm square steel / 10# channel steel main beams, M16 adjusting screw rods, 150×150×5mm bases |
| Application scenarios | Standard server cabinets, medium-sized UPS mainframes, ordinary battery cabinets, main computer rooms of small and medium-sized data centers |
| Characteristics | Mainstream market model with high cost-performance ratio and balanced overall performance. Meets the load-bearing requirements of conventional cabinets in the vast majority of Class A and Class B data centers, complying with the 8kN/㎡ floor load requirement for main computer rooms per GB 50174. |
3.1.3 Reinforced Load-Bearing Brackets (H Series)
| Parameter | Value |
|---|---|
| Rated uniformly distributed load | 10-16kN/㎡ (approx. 1000-1600kg/㎡) |
| Maximum single-cabinet load | 1500-2500kg |
| Core configuration | Φ45×2.5mm support columns, 80×40×2.5mm C-channel / 12# channel steel main beams, M20 adjusting screw rods, 200×200×6mm bases, with additional secondary beam ties |
| Application scenarios | High-density server cabinets, high-power UPS mainframes, lead-acid battery banks, precision air conditioner indoor units, UPS battery rooms |
| Characteristics | High structural rigidity, minimal deformation, ample safety margin. Meets the 16kN/㎡ high load requirement for battery rooms and UPS equipment rooms per code. The standard solution for heavy equipment areas. |
3.1.4 Heavy-Duty Load-Bearing Brackets (Z Series)
| Parameter | Value |
|---|---|
| Rated uniformly distributed load | 16-25kN/㎡ (approx. 1600-2500kg/㎡) |
| Maximum single-cabinet load | 2500-4000kg |
| Core configuration | 60×60×3.0mm square pipe columns, 16# I-beam / H-beam main beams, M24 adjusting screw rods, 250×250×8mm bases, well-grid (#) densified support layout |
| Application scenarios | Liquid-cooled high-density cabinets, large diesel generator sets, energy storage battery clusters, heavy precision equipment, extreme reinforcement scenarios for aged floor slabs |
| Characteristics | Uses heavy-duty steel sections and densified support structures with extremely strong deformation resistance. Evenly disperses concentrated loads of several tons. Suitable for extreme heavy-load scenarios and conversions with extremely low floor slab load capacity. |
3.1.5 Ultra-Heavy-Duty Load-Bearing Brackets (CZ Series)
| Parameter | Value |
|---|---|
| Rated uniformly distributed load | ≥25kN/㎡ (approx. 2500kg/㎡ and above) |
| Maximum single-cabinet load | ≥4000kg |
| Core configuration | 80×80×4.0mm square pipe / 100×100 H-beam columns, 20# and above I-beam main beams, enlarged adjusting screw rods, 300×300×10mm and above large-size bases, with additional diagonal braces and transverse reinforcement |
| Application scenarios | Supercomputing center cabinets, large industrial equipment, special equipment room equipment, building structural reinforcement projects |
| Characteristics | Customized design with dedicated mechanical verification for extreme heavy-load scenarios. Typically works in conjunction with building structural beams, transmitting loads to building main beams rather than the floor slab. |
3.2 Classification by Structural Form
3.2.1 Independent Base-Type Load-Bearing Brackets
Structural characteristics: Each cabinet corresponds to an independent rectangular frame base, composed of 4 or more columns and perimeter beams, with each cabinet forming its own load-bearing unit.
Advantages: Flexible layout, individual cabinet installation possible, cabinets are independent of each other, easy to relocate and adjust later; clear load paths, failure of one bracket does not affect other units.
Disadvantages: More connection nodes when installing in full rows, overall integrity slightly lower than continuous-row types.
Application scenarios: Equipment rooms with fewer cabinets, dispersed layouts, rooms where positions may be adjusted later, and reinforcement of individual heavy equipment units.
3.2.2 Full-Row Continuous Load-Bearing Brackets
Structural characteristics: Continuous frame structures arranged along the entire length of the cabinet row. The entire row of cabinets shares one load-bearing bracket, with continuous longitudinal main beams and transverse secondary beams with support columns.
Advantages: Good overall rigidity, uniform stress distribution, strong integrity, high installation efficiency, neat and uniform row appearance.
Disadvantages: High degree of customization, requires precise matching of cabinet row length, less flexible for later adjustment.
Application scenarios: Standardized micro-module equipment rooms, server cabinet areas arranged in full rows, battery cabinet rows, and other scenarios with fixed layouts.
3.2.3 Well-Grid Full-Hall Load-Bearing Brackets
Structural characteristics: Longitudinal and transverse beams with columns are arranged throughout the entire equipment room at fixed spacing, forming a fully covered grid load-bearing platform, similar to a reinforced support system for raised floors.
Advantages: Uniform load-bearing capacity improvement across the entire area, equipment can be placed anywhere, extremely flexible layout; high overall rigidity, good seismic performance.
Disadvantages: Higher cost, larger material consumption, greater installation workload.
Application scenarios: Reserved equipment rooms with undetermined equipment layouts, high-density full-area heavy-load equipment rooms, and core equipment rooms with high seismic fortification intensity.
3.2.4 Cantilever Beam-Type Load-Bearing Brackets
Structural characteristics: Both ends of the main beams are supported on building walls or structural beams, with the middle section suspended, directly transmitting equipment loads to the building load-bearing structure without relying on floor slab load capacity at all.
Advantages: Completely solves the problem of insufficient floor slab load-bearing capacity, suitable for scenarios with extremely low floor slab load capacity.
Disadvantages: Relies on supporting walls or structural beams on both sides, significant site limitations, high installation difficulty.
Application scenarios: Precast slab floors, old brick-wood structures, and extreme weak scenarios where floor slab thickness is less than 100mm.
3.3 Classification by Installation Method
3.3.1 Prefabricated Bolted Brackets
Installation method: All components are factory prefabricated and assembled on site with bolts. No welding or cutting required.
Advantages: Fast construction speed, no open flame risk, controllable installation quality, disassembly and reuse capability.
Disadvantages: High machining precision requirements for components, node strength slightly lower than welded types.
Application scenarios: The vast majority of equipment room scenarios, especially in-use equipment rooms where hot work is prohibited and equipment rooms with high fire protection requirements.
3.3.2 On-Site Welded Brackets
Installation method: Steel sections are cut on site and nodes are connected by welding to form an integrated steel structure.
Advantages: High node strength, good overall integrity, flexible adaptation to complex on-site dimensions.
Disadvantages: Long construction periods, open flame operation risks, welded areas require on-site anti-corrosion treatment, and cannot be reused.
Application scenarios: Heavy-load non-standard custom scenarios, new equipment room construction, and projects with extremely high structural integrity requirements.
3.3.3 Adhesive-Bonded Drill-Free Brackets
Installation method: High-strength structural adhesive is used to bond the bracket base to the floor, eliminating the need for drilling and expansion bolts.
Advantages: No damage to the floor surface layer, dust-free construction, fast installation.
Disadvantages: Anchoring force is highly dependent on base material conditions, not suitable for heavy-load and high-seismic scenarios.
Application scenarios: Finished floors, antistatic flooring, upper layers of raised floors, and scenarios where drilling is not appropriate.
3.4 Classification by Material and Surface Treatment
3.4.1 Ordinary Carbon Steel Hot-Dip Galvanized Brackets
| Parameter | Value |
|---|---|
| Material | Q235B high-quality carbon structural steel |
| Surface treatment | Full hot-dip galvanizing, zinc layer thickness ≥65μm |
| Characteristics | High strength, moderate cost, good anti-corrosion performance. The mainstream product in the market, with a service life of over 20 years in indoor environments. |
3.4.2 Carbon Steel Dacromet-Coated Brackets
| Parameter | Value |
|---|---|
| Material | Q235B carbon steel |
| Surface treatment | Dacromet (zinc-chromium coating), salt spray test ≥1000 hours |
| Characteristics | Anti-corrosion performance far superior to ordinary hot-dip galvanizing, no hydrogen embrittlement risk, uniform coating thickness. Suitable for harsh environments such as high humidity and coastal salt spray. |
3.4.3 Stainless Steel Brackets
| Parameter | Value |
|---|---|
| Material | 304 stainless steel / 316L stainless steel |
| Surface treatment | Brushed or polished finish |
| Characteristics | Excellent anti-corrosion performance, high cleanliness. Suitable for clean equipment rooms, pharmaceutical equipment rooms, chemical corrosion environments, and other special scenarios, but with higher cost. |
3.4.4 Powder-Coated Colored Brackets
| Parameter | Value |
|---|---|
| Material | Carbon steel substrate, electrostatic powder coating |
| Characteristics | Aesthetic appearance, customizable colors (equipment room gray, white, etc.), with a certain degree of anti-corrosion capability. Suitable for showcase equipment rooms with high visual requirements. |
3.5 Classification by Functional Characteristics
3.5.1 Standard Load-Bearing Type
Provides only basic load-bearing and dispersion functions. Standard configuration, suitable for conventional equipment room scenarios.
3.5.2 Seismic Reinforced Type
Equipped with additional lateral diagonal braces, seismic tie rods, and limit devices, meeting seismic fortification intensity requirements of 6-9 degrees. Suitable for core equipment rooms in high seismic intensity regions.
3.5.3 Vibration Damping and Noise Reduction Type
Equipped with rubber vibration-damping pads and spring vibration isolators, effectively isolating equipment vibration transmission and reducing structure-borne sound. Suitable for precision equipment rooms and equipment rooms located within office areas.
3.5.4 Antistatic Integrated Type
Integrates a complete equipotential grounding and static discharge system, seamlessly connected with antistatic access floors, ensuring the static resistance of the entire support system complies with code requirements.
3.5.5 Intelligent Monitoring Type
Pressure sensors, displacement sensors, and inclination sensors are installed at key points of the bracket to monitor the stress state and deformation of the bracket in real time. The system connects to the equipment room environment and monitoring system (DCIM) for online structural safety monitoring. Suitable for ultra-high-grade data centers.
Chapter 4 Product List
4.1 Standard Configuration List (Example: Standard S Series 600×1200mm Single-Cabinet Bracket)
| No. | Component Name | Specification/Model | Material | Unit | Qty | Remarks |
|---|---|---|---|---|---|---|
| 1 | Support column assembly | Φ32×2.0mm, height 300mm | Q235B hot-dip galvanized | pc | 6 | Including top and bottom trays |
| 2 | Main beam | 50×50×2.0mm square steel, length 1200mm | Q235B hot-dip galvanized | pc | 3 | Arranged along width direction |
| 3 | Secondary beam | 40×40×1.5mm square steel, length 600mm | Q235B hot-dip galvanized | pc | 4 | Arranged along depth direction |
| 4 | Adjusting screw rod | M16×100mm | 45# steel galvanized | set | 6 | Including upper and lower locking nuts |
| 5 | Bottom base | 150×150×5mm | Q235B hot-dip galvanized | pc | 6 | With bolt holes |
| 6 | Right-angle connector | 50×50×3mm | Q235B hot-dip galvanized | pc | 12 | Beam-column connection |
| 7 | Connection bolt | M8×20mm hex socket | 8.8 grade galvanized | set | 24 | Including flat washer and spring washer |
| 8 | Expansion bolt | M10×100mm | Carbon steel galvanized | set | 12 | For floor fixation |
| 9 | Grounding terminal | M6 copper | Brass | pc | 2 | For grounding connection |
| 10 | Conductive washer | Φ8 copper | T2 copper | pc | 24 | For node electrical conductivity |
| 11 | Product nameplate | 80×50mm aluminum | Aluminum alloy | pc | 1 | Indicates parameter information |
4.2 Optional Accessory List
| No. | Accessory Name | Specification | Unit | Application Scenario |
|---|---|---|---|---|
| 1 | Rubber vibration-damping pad | 150×150×10mm | pc | Equipment bottom vibration damping, base anti-slip |
| 2 | Spring vibration isolator | Load 100-500kg | pc | Precision equipment vibration damping and noise reduction |
| 3 | Side sealing panel | Cold-rolled steel plate powder-coated | ㎡ | Appearance enhancement, dust protection |
| 4 | Cable organizer | 19-inch standard | pc | Cable arrangement and fixation |
| 5 | Lateral diagonal brace | 40×40×2mm square steel | set | Seismic reinforcement, ultra-tall brackets |
| 6 | Chemical anchor bolt | M12×160mm | set | High-strength anchoring requirement scenarios |
| 7 | Grounding copper foil strip | 20mm×0.1mm | m | Antistatic system connection |
| 8 | Grounding conductor | BV-6mm² | m | Equipotential connection |
| 9 | Displacement sensor | Accuracy 0.01mm | pc | Intelligent deformation monitoring |
| 10 | Pressure sensor | Range 0-5t | pc | Intelligent load monitoring |
| 11 | Warning label sticker | Load warning | pc | Safety identification |
| 12 | Anti-rust grease | 500g/can | can | Thread anti-corrosion and lubrication |
4.3 Dedicated Installation Tool List
| No. | Tool Name | Specification | Purpose |
|---|---|---|---|
| 1 | Laser level | 2-line / 5-line | Elevation marking, levelness inspection |
| 2 | Rotary hammer drill | 13mm / 16mm | Floor drilling for expansion bolt installation |
| 3 | Socket wrench set | 8-24mm | Bolt tightening |
| 4 | Torque wrench | 0-100N·m | Controlling bolt tightening torque |
| 5 | Steel tape measure | 5m / 30m | Dimension measurement, layout marking |
| 6 | Feeler gauge | 0.02-2mm | Gap and flatness inspection |
| 7 | 2m straightedge | Aluminum alloy | Floor and bracket flatness inspection |
| 8 | Angle grinder | 100mm | Section cutting, burr grinding |
| 9 | Multimeter / Ground resistance tester | — | Grounding continuity and resistance testing |
| 10 | Vacuum cleaner | Industrial grade | Drilling dust removal, maintaining equipment room cleanliness |
| 11 | Rubber mallet | 1 lb | Beam seating, fine alignment |
| 12 | Adjustable wrench | 12 inch | Leveling nut adjustment |
4.4 Product Packaging List
Inner packaging: Components are individually wrapped with foam sheeting to prevent scratching of the galvanized layer during transportation. Thread areas are covered with plastic protective caps to prevent thread damage from impacts.
Outer packaging: High-strength corrugated cartons or wooden crates, with foam cushioning material filled inside the crate to ensure components are not deformed or damaged during transportation.
Documents included with shipment:
| Document | Qty |
|---|---|
| Product certificate of conformity | 1 copy |
| Product factory inspection report | 1 copy |
| This installation and operating manual | 1 copy |
| Packing list | 1 copy |
| Warranty card | 1 copy |
Chapter 5 Product Principles
5.1 Core Principle of Mechanical Load Dispersion
The core working principle of the ground load-bearing support bracket is the equivalent uniform distribution of concentrated loads. Based on the equivalent uniformly distributed load calculation method in the *Load Code for the Design of Building Structures*, the concentrated point loads of equipment are converted into large-area uniformly distributed loads by expanding the load-bearing contact area, reducing the pressure per unit area of the floor slab to within the design allowable range.
5.1.1 Load Transmission Path
Equipment weight → Equipment base → Bracket main beams → Bracket secondary beams → Support columns → Bottom bases → Building floor slab → Building beams/columns/foundation
In this transmission path, the most critical stage is the dispersion process from support columns to bottom bases. The concentrated pressure of the equipment is distributed through the beams to each column point, and then through the large-size bases, the concentrated forces are spread onto the floor slab. The larger the base area, the smaller the pressure per unit area on the floor slab.
5.1.2 Equivalent Uniformly Distributed Load Calculation Principle
According to GB 50009-2012 *Load Code for the Design of Building Structures*, the concentrated load acting on a floor slab can be converted to an equivalent uniformly distributed load based on the internal force equivalence principle. The calculation formula is as follows:
qe = 8Mmax / (b·l²)
Where:
- qe = equivalent uniformly distributed load (kN/㎡)
- Mmax = maximum bending moment of the floor slab under concentrated load (kN·m)
- b = calculated width of the floor slab (m)
- l = calculated span of the floor slab (m)
By adding a load-bearing bracket, the load distribution width b is effectively increased, thereby reducing the equivalent uniformly distributed load value. For example, a 1-ton cabinet with a base contact area of approximately 0.6㎡, when placed directly, produces a local equivalent load far exceeding ordinary floor slab limits. By dispersing the load through a load-bearing bracket to a contact area of more than 2㎡, the equivalent uniformly distributed load can be reduced to 1/3-1/4 of its original value, meeting floor slab load-bearing requirements.
5.2 Stress Uniformization Principle
When traditional equipment is placed directly on the floor, loads are concentrated at several support points of the equipment base, causing local stress concentration in the floor slab, which readily produces local deformation and cracking. The load-bearing bracket, through its continuous beam frame and multi-point support structure, evenly disperses concentrated stress to multiple support points, making the floor slab stress distribution more uniform and avoiding local stress exceeding limits.
At the same time, the rigidity of the steel structure frame itself can offset part of the floor slab deformation. When the floor slab has slight deflection, the rigid bracket can perform a secondary load redistribution function, making the forces at each support point more balanced and avoiding excessive load at any single point.
5.3 Horizontal Self-Adaptive Leveling Principle
The bracket uses a threaded pair adjustment mechanism, utilizing the screw drive principle to achieve continuous stepless height adjustment. The adjusting screw rod and support column are engaged through precision threads. Rotating the nut changes the extended length of the screw rod, thereby adjusting the height of a single column to accommodate uneven ground surfaces.
The threaded leveling mechanism has self-locking characteristics and will not retract on its own under vertical loads. When combined with double-nut locking, height precision can be maintained over the long term. Conventional adjustment precision can reach the 0.1mm level, fully meeting the levelness requirements for equipment installation.
5.4 Seismic and Vibration Damping Working Principles
5.4.1 Seismic Principle
Seismic-type load-bearing brackets form a spatial truss structure by adding lateral diagonal braces and longitudinal tie rods, converting horizontal seismic forces into axial forces borne by the members. When an earthquake occurs, horizontal inertial forces are transmitted through the diagonal braces to the floor anchoring points, preventing lateral overturning and sliding of the bracket. At the same time, the bracket adopts a rigid connection design overall, with node strength higher than the members themselves, ensuring that nodes do not fail before members under seismic action.
5.4.2 Vibration Damping Principle
Vibration-damping brackets incorporate elastic damping elements (rubber pads, springs) in series in the load path, using the deformation of elastic materials to absorb vibration energy, reduce vibration acceleration, and block vibration transmission from equipment to the building structure. They also reduce the impact of floor vibration on precision equipment.
Rubber vibration-damping pads are mainly suitable for medium and high-frequency vibration isolation, while spring vibration isolators are suitable for low-frequency vibration isolation. The combination of both achieves broadband vibration damping.
5.5 Static Discharge and Equipotential Principle
Static charge accumulation in equipment rooms can cause interference or even damage to electronic equipment. All metal components must maintain equipotentiality and be reliably grounded. The load-bearing bracket ensures electrical continuity between all metal components through conductive washers, forming a continuous conductive whole. It is then connected to the equipment room equipotential grounding system through grounding conductors, keeping the entire bracket at the same potential as the equipment room and avoiding potential differences that cause electrostatic discharge.
Static electricity is rapidly discharged through the path of “bracket metal frame → grounding terminal → grounding conductor → equipotential copper busbar → equipment room grounding electrode → earth,” ensuring the static voltage always remains within a safe range.
Chapter 6 Product Technical Parameters
6.1 General Technical Parameters
| Parameter Category | Parameter Item | Technical Indicator | Remarks |
|---|---|---|---|
| Basic parameters | Standard installation height | 100-1000mm | Custom extendable to 2000mm |
| Height adjustment travel | ±20mm / ±30mm / ±50mm | Large-travel version optional | |
| Level adjustment precision | ≤0.1mm | Thread adjustment precision | |
| Standard grid module | 600×600mm / 600×1200mm | Compatible with antistatic access floor module | |
| Mechanical parameters | Safety factor | ≥1.5 | Based on rated load |
| Deflection under concentrated load | ≤1/1000 span | Under rated load | |
| Residual deformation | ≤0.25mm | Permanent deformation after unloading | |
| Single column axial load capacity | 8kN / 15kN / 25kN / 40kN | Four grades | |
| Base pullout resistance | ≥15kN | M10 expansion bolt in concrete | |
| Material parameters | Main material | Q235B high-quality carbon steel | 304 stainless steel optional |
| Bolt grade | 8.8 grade high-strength bolts | 10.9 grade for critical nodes | |
| Surface anti-corrosion coating thickness | Hot-dip galvanizing ≥65μm; Dacromet ≥8μm | Per GB/T 13912 | |
| Electrical parameters | System grounding resistance | ≤4Ω | Connected to equipment room grounding system |
| Node transition resistance | ≤0.03Ω | Component connection points | |
| Static discharge resistance | 10⁶-10⁹Ω | Per antistatic code | |
| Environmental parameters | Operating temperature | -20℃ ~ +60℃ | Conventional indoor environment |
| Storage temperature | -40℃ ~ +80℃ | ||
| Relative humidity | ≤95% (non-condensing) | ||
| Seismic fortification intensity | 6-8 degrees | Reinforced type up to 9 degrees | |
| Design service life | ≥20 years | Indoor normal environment |
6.2 Detailed Parameters by Series
6.2.1 L Series Light-Duty Load-Bearing Bracket Parameters
| Model | Single-Cabinet Dimensions (mm) | Rated Single-Cabinet Load (kg) | Column Specification | Beam Specification | Base Dimensions (mm) | Adjusting Screw | Number of Columns |
|---|---|---|---|---|---|---|---|
| LA-6060 | 600×600 | 500 | Φ25×1.5mm | 40×40×1.5mm square steel | 120×120×4 | M12 | 4 |
| LA-6120 | 600×1200 | 800 | Φ25×1.5mm | 40×40×1.5mm square steel | 120×120×4 | M12 | 6 |
| LA-8100 | 800×1000 | 700 | Φ25×1.5mm | 40×40×1.5mm square steel | 120×120×4 | M12 | 6 |
6.2.2 S Series Standard Load-Bearing Bracket Parameters
| Model | Single-Cabinet Dimensions (mm) | Rated Single-Cabinet Load (kg) | Column Specification | Beam Specification | Base Dimensions (mm) | Adjusting Screw | Number of Columns |
|---|---|---|---|---|---|---|---|
| SA-6060 | 600×600 | 1000 | Φ32×2.0mm | 50×50×2.0mm square steel | 150×150×5 | M16 | 4 |
| SA-6120 | 600×1200 | 1500 | Φ32×2.0mm | 50×50×2.0mm square steel | 150×150×5 | M16 | 6 |
| SA-8100 | 800×1000 | 1200 | Φ32×2.0mm | 50×50×2.0mm square steel | 150×150×5 | M16 | 6 |
| SA-8120 | 800×1200 | 1500 | Φ32×2.0mm | 10# channel steel | 150×150×5 | M16 | 8 |
6.2.3 H Series Reinforced Load-Bearing Bracket Parameters
| Model | Single-Cabinet Dimensions (mm) | Rated Single-Cabinet Load (kg) | Column Specification | Beam Specification | Base Dimensions (mm) | Adjusting Screw | Number of Columns |
|---|---|---|---|---|---|---|---|
| HA-6120 | 600×1200 | 2500 | Φ45×2.5mm | 12# channel steel | 200×200×6 | M20 | 8 |
| HA-8120 | 800×1200 | 2500 | Φ45×2.5mm | 12# channel steel | 200×200×6 | M20 | 10 |
| HA-1020 | 1000×2000 | 4000 | Φ45×2.5mm | 16# channel steel | 200×200×6 | M20 | 12 |
6.2.4 Z Series Heavy-Duty Load-Bearing Bracket Parameters
| Model | Single-Cabinet Dimensions (mm) | Rated Single-Cabinet Load (kg) | Column Specification | Beam Specification | Base Dimensions (mm) | Adjusting Screw | Number of Columns |
|---|---|---|---|---|---|---|---|
| ZA-8120 | 800×1200 | 4000 | 60×60×3.0mm square pipe | 16# I-beam | 250×250×8 | M24 | 12 |
| ZA-1020 | 1000×2000 | 6000 | 60×60×3.0mm square pipe | 20# I-beam | 250×250×8 | M24 | 16 |
6.3 Material Performance Parameters
Q235B Steel Mechanical Properties
| Property | Value |
|---|---|
| Yield Strength | ≥235 MPa |
| Tensile Strength | 370-500 MPa |
| Elongation | ≥26% |
| Impact Energy | ≥27 J (20°C) |
Compliant with GB/T 700-2006 standard requirements.
Class 8.8 Bolt Mechanical Properties
| Property | Value |
|---|---|
| Tensile Strength | ≥800 MPa |
| Yield Strength | ≥640 MPa |
| Proof Stress | ≥580 MPa |
Compliant with GB/T 3098.1-2010 standard requirements.
Hot-Dip Galvanizing Anti-Corrosion Performance
| Property | Specification |
|---|---|
| Zinc Coating Thickness | ≥65 μm (for component thickness ≥5 mm) |
| Adhesion | Firm bonding between zinc layer and substrate; no peeling in hammer test |
| Salt Spray Test | ≥480 hours without red rust |
Compliant with GB/T 13912-2002 standard requirements.
6.4 Environmental Adaptability Parameters
Temperature Adaptability
The product can operate normally for extended periods in environments ranging from -20°C to +60°C, and can withstand short-term exposure to -40°C low temperatures and +80°C high temperatures. Dimensional deformation caused by temperature changes is minimal, and its impact on structural loading and levelness is negligible.
Humidity Adaptability
The hot-dip galvanized surface can be used long-term in environments with relative humidity below 95%. Under non-condensing conditions, the anti-corrosion service life can reach over 20 years. In high-humidity coastal areas, Dacromet or stainless steel materials are recommended to further enhance corrosion resistance.
Cleanliness Adaptability
The product surface is smooth and flat, resistant to dust accumulation. The galvanized layer is stable with no volatile emissions, meeting Class A computer room cleanliness requirements. It does not generate particulate contaminants that could affect equipment operation.
Electromagnetic Compatibility
The metal support frame is a good conductor. When connected to the grounding system, it provides a degree of electromagnetic shielding. It does not generate electromagnetic interference to electronic equipment in the computer room, nor does it experience performance changes due to equipment electromagnetic fields.
7.1 Core Functions
7.1.1 Floor Slab Load-Bearing Reinforcement Function
This is the most core function of the product. Through the principle of mechanical load distribution, the concentrated load of heavy equipment is uniformly dispersed, effectively reducing the pressure per unit area on the floor slab. This addresses the problem of insufficient load-bearing capacity of existing building floor slabs, enabling ordinary office buildings and commercial buildings to meet the requirements for housing computer room equipment without the need for large-scale civil structural modification.
7.1.2 Equipment Horizontal Support Function
The support frame features a high-precision leveling mechanism that can adjust equipment to a completely horizontal state, ensuring stable operation of internal mechanical structures of precision equipment such as servers and switches. This reduces hard drive wear, abnormal fan noise, poor connector contact, and other issues caused by tilting, thereby extending equipment service life.
7.1.3 Structural Safety Protection Function
The product is designed with a 1.5x safety factor, capable of withstanding additional loads such as equipment handling impacts, personnel stepping, and earthquakes, preventing structural failure due to accidental overload. Additionally, the rigid frame can enhance the overall stiffness of the floor slab to a certain extent, reducing the impact of floor vibration and deformation on equipment.
7.1.4 Equipotential Grounding Function
The support frame is an integral conductive metal structure that can be connected to the computer room equipotential system, providing an auxiliary grounding path for equipment. It also dissipates static electricity, eliminates potential differences, and ensures electrical safety for both equipment and personnel.
7.1.5 Overhead Cable Routing Compatibility Function
The overhead space created by the support frame is compatible with underfloor air supply and underfloor cable routing requirements. Cables and air ducts can pass beneath the support frame, seamlessly integrating with the anti-static floor system without the need for additional cable tray or air duct modifications.
7.2 Product Features
7.2.1 Safe, Reliable, and Compliant
Strictly developed in accordance with national steel structure design specifications and data center design standards. All models have been verified through professional mechanical calculations, and key indicators have been tested by third-party testing institutions.
- 1.5x safety redundancy design, fully considering various extreme operating conditions, ensuring zero structural risk during long-term operation.
- Fully meets acceptance standards for Class A and Class B data centers, providing compliance support for computer room certification and safety assessment.
7.2.2 Modular Design, Efficient Installation
- Full series of standardized prefabricated components with strong interchangeability. No on-site welding or cutting required; simple tools are sufficient for assembly.
- Compared to traditional concrete reinforcement, the construction period is reduced from 20-30 days to 1-3 days, significantly shortening project timelines.
- Construction involves no wet work, minimal dust, and no open flames, with minimal impact on the surrounding environment. Partial construction can be performed in operating computer rooms without shutdown.
7.2.3 Flexible and Adjustable, Strong Adaptability
- Continuously adjustable height, accommodating various raised floor heights from 100-1000 mm, perfectly matching all specifications of anti-static floors.
- Support frame dimensions and support density can be customized based on equipment size, weight, and layout, precisely adapting to different scenario requirements.
- Supports future expansion and adjustment. When equipment is relocated, the support frame can be disassembled and reused, avoiding duplicate investment.
7.2.4 Corrosion-Resistant and Durable, Long Service Life
- The main body uses hot-dip galvanizing anti-corrosion treatment. The zinc layer is uniform and dense with excellent corrosion resistance, providing a service life of no less than 20 years in normal indoor environments.
- All fasteners are made of galvanized or stainless steel materials, preventing rust seizure and maintaining flexibility for adjustment and disassembly after long-term use.
- No vulnerable or consumable parts. Daily maintenance workload is minimal, resulting in low life-cycle costs.
7.2.5 System-Compatible, Integrated Solution
- Seamlessly interfaces with anti-static floors, grounding systems, cabling systems, seismic resistance systems, and environment monitoring systems, achieving multi-system integration.
- Optional vibration damping, cover plates, cable management, and other accessories to meet personalized requirements in different scenarios.
- Compatible with all mainstream brands of cabinets, UPS systems, air conditioning units, and other equipment. Mounting holes can be flexibly adjusted.
7.2.6 Green, Environmentally Friendly, and Recyclable
- Steel is 100% recyclable, aligning with green building and low-carbon construction concepts.
- Construction process generates no construction waste or harmful gas emissions, making it environmentally friendly.
- Can be repeatedly disassembled and reused, reducing resource waste and adapting to the trend of computer room iterative upgrades.
Floor load-bearing support frames are widely used in various computer rooms and equipment scenarios that require solutions to insufficient floor load-bearing capacity. They can be divided into the following typical application scenarios by industry and function.
8.1 Data Centers and IDC Computer Rooms
This is the primary application scenario for the product, including carrier IDC computer rooms, third-party data centers, and enterprise self-built data centers.
- Main Computer Room Area: Load-bearing reinforcement for server cabinets, network cabinets, and storage cabinets, meeting load requirements of 8 kN/m² or above.
- UPS and Battery Room: Specialized reinforcement for high-power UPS units, lead-acid/lithium battery banks, meeting high load requirements of 16 kN/m².
- Air Conditioning Room: Reinforcement for heavy equipment such as precision air conditioning indoor units and chilled water units.
- Electrical Distribution Room: Reinforcement for high/low voltage distribution cabinets, row-head cabinets, diesel generator sets, and other equipment.
- High-density computing centers, AI training computer rooms, and other scenarios where single-cabinet weight exceeds 1.5 tons must be reinforced with load-bearing support frames; otherwise, structural safety requirements cannot be met.
8.2 Telecommunications Computer Rooms
Includes carrier core computer rooms, base station computer rooms, and transmission computer rooms. Telecommunications computer rooms contain large quantities of communication cabinets, power cabinets, and battery banks that are heavy, and many are located in existing office buildings with limited floor load capacity, generally requiring load-bearing reinforcement.
- Core Switching Room: Reinforcement for core routers and transmission equipment cabinets
- Power Room: Reinforcement for switching power supplies and battery banks
- Base Station Room: Reinforcement for BBU equipment, power supplies, and batteries
8.3 Financial Industry Computer Rooms
Data centers and computer rooms of banks, securities, and insurance companies have extremely high safety requirements. They are mostly located in office buildings in prime urban commercial areas where the original building design load is generally low, making load-bearing reinforcement a mandatory item for computer room construction.
- Bank Data Center: Reinforcement for core business system server cabinets
- Securities Trading Room: Reinforcement for trading servers and market data equipment
- Disaster Recovery Center: Reinforcement for disaster recovery equipment and storage equipment
8.4 Government and Public Institution Computer Rooms
Government cloud computer rooms, e-government computer rooms, public security computer rooms, tax computer rooms, etc. These computer rooms are mostly located in government office buildings designed to office standards, requiring modification through load-bearing support frames to meet computer room standards.
- Government Data Center: Reinforcement for government cloud server cabinets
- Monitoring and Command Center: Reinforcement for large-screen controllers and storage equipment
- Public Security Private Network Room: Reinforcement for public security business equipment
8.5 Healthcare Industry Computer Rooms
Hospital information center computer rooms, imaging department equipment rooms, and laboratory equipment rooms not only have high load-bearing requirements but also very high stability and seismic resistance requirements.
- Hospital IT Department Room: Reinforcement for HIS and PACS system servers
- Imaging Department: Reinforcement for control cabinets supporting large medical equipment such as CT and MRI
- Laboratory Equipment Room: Reinforcement for precision equipment such as large biochemical analyzers and gene sequencers
8.6 Industrial Control Computer Rooms
Central control rooms of manufacturing plants, PLC rooms, industrial server rooms, as well as control rooms for power and rail transit. These computer rooms are often located in industrial facilities with relatively complex environments, heavy equipment, and high reliability requirements.
- Factory Central Control Room: Reinforcement for DCS control systems and PLC control cabinets
- Power Dispatch Room: Reinforcement for grid dispatch equipment and protection devices
- Rail Transit Control Center: Reinforcement for signal systems and ATS system equipment
8.7 Special Scenario Applications
Renovation of Computer Rooms in Old Buildings
For buildings with extremely poor load-bearing capacity such as precast slab floors, brick-concrete structures, and old factory buildings, cantilevered or full-floor load-bearing support frames are used to transfer loads to load-bearing walls and beams of the building, achieving equipment deployment with zero reliance on floor slab load capacity.
Temporary and Mobile Computer Rooms
Temporary computer rooms for exhibitions, sporting events, and emergency command centers use prefabricated load-bearing support frames that can be quickly assembled, quickly dismantled, and reused without damaging the site floor.
Laboratories and Test Centers
Laboratory equipment and test instruments in universities, research institutions, and corporate R&D centers, especially precision measurement equipment, have high requirements for levelness and vibration control. Vibration-damping load-bearing support frames provide a stable installation foundation.
Computer Rooms on Upper Floors of High-Rise Buildings
Computer rooms located on upper floors of office buildings typically have lower floor load capacity and are inconvenient for civil reinforcement. Prefabricated load-bearing support frames are the optimal solution.
9.1 Pre-Installation Preparation
9.1.1 Technical Preparation
Drawing Review and Technical Disclosure
Before construction, organize drawing review involving design personnel, construction personnel, and supervision personnel to familiarize with construction drawings and technical requirements, and clarify key parameters such as support frame layout, elevation, load rating, and grounding requirements. Provide detailed technical disclosure to the construction crew, including construction procedures, process standards, and safety precautions, ensuring all construction personnel understand the work requirements.
Site Survey and Verification
Technical personnel conduct an on-site survey to verify that on-site dimensions, floor elevations, beam and column positions, and equipment layout match the drawings. Key verification items include:
- Actual floor slab thickness and concrete strength grade, confirming original design load values
- Floor flatness, measured with a 2m straightedge, recording elevation difference data
- Whether there are pipelines or waterproofing layers beneath the floor, determining safe drilling zones
- Positions of walls and structural beams, determining whether heavy-load support frames can utilize structural support
- Computer room grounding system location, confirming grounding points
Preparation of Construction Plan
Prepare a specialized construction plan based on actual site conditions, clarifying construction schedule, personnel allocation, tool and material plans, quality control points, and safety assurance measures. For heavy-load support frames, extra-high support frames, and seismic support frames, separate load calculation reports and specialized construction plans must be prepared.
9.1.2 Personnel Preparation
Personnel Allocation
Standard construction crew configuration: 1 construction supervisor, 1 technical supervisor, 3-5 installation technicians, and 2 assistants. The construction supervisor must have more than 3 years of computer room engineering construction management experience. The technical supervisor must be familiar with steel structure construction and computer room specifications.
Qualification Requirements
- Construction personnel must receive professional training and be familiar with product structure and installation procedures
- Welders must hold special operation permits (welding operations); welding must only be performed by certified personnel
- Personnel working at height must hold high-altitude operation certificates; safety harnesses must be worn when working above 2 meters
- All personnel must receive safety education and safety technical disclosure before entering the site
9.1.3 Material and Tool Preparation
Material Incoming Inspection
Products must undergo unpacking inspection upon arrival, verifying that models, specifications, and quantities match the contract. Inspect components for deformation, galvanized layer peeling, impact damage, and other defects, and verify thread integrity. Also inspect product certificates of conformity, factory inspection reports, and other quality documentation. Non-conforming products are strictly prohibited from being used on site.
Tool Preparation
Prepare all construction tools and testing instruments according to the tool list, verify tools are in good condition, and ensure measuring instruments are within their calibration validity period. Pay particular attention to laser level accuracy, torque wrench calibration status, and impact drill working condition.
Auxiliary Material Preparation
Prepare expansion bolts, conductive adhesive, anti-rust paint, structural adhesive, cable ties, markers, and other auxiliary materials, ensuring specifications and quality meet requirements.
9.1.4 Site Condition Preparation
Base Conditions
The installation area floor must be completed, with concrete strength reaching C20 or above and the floor essentially level. Clean the floor of debris and dust, and set up isolation and warning signs in the construction area. If floor flatness deviation is excessive, leveling treatment must be performed first.
Environmental Conditions
Construction site temperature should be between 5°C and 40°C, relative humidity ≤85%, with no rain or snow exposure. Indoor construction must ensure adequate lighting and good ventilation. When working in operating computer rooms, dust protection measures must be implemented, equipped with industrial vacuum cleaners to prevent dust from affecting equipment operation.
Safety Conditions
Set up warning signs in the construction area; unauthorized personnel are prohibited from entering. Check electrical safety before using power tools. Temporary electrical installations must comply with regulations. Hot work operations require a hot work permit and fire extinguishing equipment.
9.2 Construction Process Flow
The standard installation process for floor load-bearing support frames is as follows:
Site Survey → Base Treatment → Positioning and Layout → Base Plate Placement → Drilling and Anchoring → Column Installation → Crossbeam Assembly → Preliminary Leveling → Grounding Connection → Fine Leveling → Locking and Fastening → Load Pre-Test → Finished Product Protection → Acceptance and Handover
9.3 Base Treatment
Base Cleaning
Thoroughly remove dust, oil stains, laitance, and protrusions from the installation area floor, ensuring the floor is solid and clean. Loose floor surface layers must be removed, and depressed areas can be leveled with cement mortar.
Flatness Treatment
Check floor flatness with a 2m straightedge. If local elevation differences exceed 10mm, leveling treatment is required. Small protrusions should be ground flat with an angle grinder. Large depressed areas should be repaired and leveled with polymer cement mortar, cured until strength is achieved.
Moisture and Dust Protection
For basements or damp areas, it is recommended to apply moisture-proof primer and lay moisture-proof film. For high-cleanliness computer rooms, dust-proof floor paint can be applied to reduce dust generation.
Underground Utility Marking
Confirm the routing of water and electrical pipelines beneath the floor and clearly mark them on the floor with markers. Drilling at pipeline locations is strictly prohibited to avoid damaging existing utilities.
9.4 Positioning and Layout
Elevation Datum Line Determination
Calculate the design elevation of the support frame top surface based on the computer room finished floor elevation and equipment installation height requirements. Use a laser level to project the support frame top elevation control line on the surrounding walls as the leveling reference.
Grid Layout
According to the support frame layout in the construction drawings, mark the center points of support columns and the boundary lines of crossbeams on the floor. Use the computer room axis or walls as the reference for layout, first projecting main control lines, then detailed grid lines.
Accuracy Requirements
| Item | Tolerance |
|---|---|
| Column point position deviation | ≤±2 mm |
| Crossbeam boundary line straightness | ≤1 mm/m |
| Squareness deviation | ≤3 mm/10 m |
| Elevation datum line closure error | ≤±1 mm |
Verification and Recheck
After layout is complete, use a steel tape measure to recheck diagonal dimensions to confirm grid squareness. Cross-check positions against equipment drawings to ensure support frames precisely correspond to equipment bases, avoiding misalignment after installation.
9.5 Base Plate and Anchoring Installation
Base Plate Placement
Place the base plates according to the marked layout points, aligning the base plate center with the point mark. Adjust the base plate orientation so bolt holes are conveniently positioned for drilling. Ensure the base plate sits flat with no rocking.
Drilling Operations
Drill holes with an impact drill according to the base plate bolt hole positions. The drill bit diameter and hole depth must strictly match the expansion bolt specifications. For example, M10 expansion bolts correspond to a φ12 drill bit with a hole depth of 100 mm.
- Keep the drill bit perpendicular to the floor while drilling to avoid angled holes
- Use a vacuum cleaner simultaneously during drilling to minimize dust dispersion
- Hole position deviation must not exceed 2 mm; depth deviation ±5 mm
- Clean dust from holes after drilling, ensuring holes are clean and free of debris
Expansion Bolt Installation
Insert the expansion bolt into the drilled hole and gently tap it in with a hammer, ensuring the bolt sleeve is fully inserted into the hole with the surface flush with the floor. Then tighten the nut with a wrench to fully expand the expansion sleeve, creating a firm bond with the concrete hole wall.
- Bolt tightening torque: M8 = 15 N·m, M10 = 25 N·m, M12 = 35 N·m
- Bolts must be tight and plumb after fastening
- Pull-out sampling inspection is required for critical areas: 1 bolt tested per 100 bolts, with pull-out force not less than 15 kN
Chemical Anchor Installation (Optional Process)
- After drilling, thoroughly clean dust from holes with a dedicated brush and air blower, repeating at least 3 times
- Insert the chemical cartridge, then slowly drive the stud into the hole with a drill at low speed to thoroughly mix the chemical
- Allow to cure undisturbed. Proceed to next steps only after the chemical has fully cured (curing time per product instructions, approximately 30 minutes at room temperature)
- Do not touch the stud or apply any load before curing is complete
9.6 Support Column Installation
Pre-Installation of Adjusting Threaded Rod
First thread the lower locking nut onto the adjusting threaded rod, then pass the rod through the center hole of the base plate. Adjust the initial height of the rod to approximately 5-10 mm below the design elevation, reserving upward adjustment margin.
Column Installation
Align the support column with the threaded rod and rotate it onto the adjusting rod. Adjust the column height so the column top surface initially approaches the design elevation. Ensure the column remains vertical without tilting.
Initial Column Verticality Adjustment
Use a spirit level against the side of the column and adjust the threaded rod to make the column vertical, with verticality deviation controlled within 1‰. After all columns are installed, perform an overall inspection to ensure no obvious tilting.
9.7 Crossbeam System Assembly
Main Crossbeam Installation
Install the main crossbeams first. Place the main crossbeam on the top plate of the column, align the connection holes, insert connection bolts with conductive gaskets, and initially tighten the nuts without fully securing.
- Crossbeam placement direction should match the design; main crossbeams are arranged along the direction of equipment load
- The overhang distance of crossbeam ends beyond the columns should be uniform, with deviation ≤5 mm
- Conductive gaskets must be installed between metal contact surfaces to ensure electrical continuity
Secondary Crossbeam Installation
After main crossbeams are in place, install secondary crossbeams to form a grid frame. Connect secondary crossbeams to main crossbeams using right-angle connectors, installing them one by one in position, also initially tightening bolts.
Frame Alignment
After all crossbeams are installed, correct the overall dimensions, squareness, and straightness of the frame:
| Item | Tolerance |
|---|---|
| Diagonal dimension difference | ≤3 mm |
| Crossbeam straightness | ≤2 mm/m |
| Joint connections | Tight with no visible gaps |
| Crossbeam top surface initial levelness | Elevation difference ≤3 mm |
9.8 Overall Leveling
Reference Point Setting
Select the four corner columns as reference points. Use a laser level and adjustment nuts to precisely adjust the top surface heights of the four reference points to the design elevation, with error controlled within ±0.5 mm.
Overall Leveling
Using the four reference points as a reference, pull level lines or use a laser level to adjust the heights of intermediate columns one by one, bringing all crossbeam top surfaces to the same horizontal plane.
- Rotate the adjustment nut slowly while adjusting and measuring to avoid overshooting
- Height difference between the two ends of the same crossbeam should be ≤0.5 mm
- Height difference between adjacent column top surfaces should be ≤0.3 mm
- Overall height difference within a 2 m range should be ≤1 mm
Locking and Fastening
After leveling meets requirements, sequentially lock the upper and lower locking nuts. Maintain column verticality during locking to avoid height changes during the process. After all nuts are locked, re-verify levelness and make fine adjustments if any deviation exists.
Joint Bolt Tightening
After levelness is confirmed, tighten all crossbeam connection bolts to the design torque using a diagonal cross-tightening sequence to prevent frame deformation from uneven stress.
| Bolt Size | Tightening Torque |
|---|---|
| M8 | 15 N·m |
| M10 | 25 N·m |
| M12 | 40 N·m |
9.9 Grounding System Installation
Joint Conductivity Treatment
Check that conductive gaskets are properly installed at all bolted joints to ensure electrical continuity throughout the entire support frame. For areas where the galvanized layer is excessively thick and may affect conductivity, use sandpaper to remove the local galvanized layer to ensure good contact.
Ground Terminal Connection
Install grounding terminals at designed positions. Press the grounding conductor securely onto the grounding terminal with bolts at one end, and connect the other end to the computer room equipotential copper bar.
- Grounding conductor cross-sectional area ≥4 mm²; ≥6 mm² for critical areas
- Both ends of the conductor should be crimped with copper lugs and fastened securely with bolts
- Each independent support frame unit must have no fewer than 2 grounding points, providing redundancy
Anti-Static System Integration
If connection to the anti-static floor grounding system is required, attach one end of copper foil tape to the support frame crossbeam and the other end to the floor grounding copper foil grid using soldering or conductive adhesive, ensuring static discharge paths are clear.
Grounding Test
After grounding installation is complete, test the overall grounding resistance of the support frame with a ground resistance tester. The requirement is ≤4 Ω. Use a multimeter to test conductivity between nodes, with transition resistance ≤0.03 Ω. Any failed tests require investigation and rectification.
9.10 Load Pre-Test
Purpose of Pre-Test
Verify the actual load-bearing capacity and deformation of the support frame, eliminate initial clearances and plastic deformation, and ensure safety and stability after equipment is installed.
Pre-Test Method
Use sandbags, weights, or other heavy objects evenly distributed on the support frame. The pre-test load is 1.2 times the rated load, maintained for 24 hours.
- Loading is performed in stages: first apply 50% load and observe for 1 hour; then increase to 100% and observe for 2 hours; finally increase to 120% and maintain for 24 hours
- During loading, periodically measure support frame deformation and record settlement data
- Key observation points: deformation of columns and crossbeams, checking for loosening or abnormal noise at joints
Acceptance Criteria
After the 24-hour pre-test, measure total deformation before unloading and residual deformation after unloading:
| Item | Criterion |
|---|---|
| Maximum deflection | ≤1/1000 of span |
| Residual deformation | ≤0.25 mm |
| Joints | No loosening, no deformation, no weld cracking |
| Base plates | No displacement, no expansion bolt pull-out |
9.11 Finishing and Finished Product Protection
Surface Cleaning
Clean dust and oil stains from the support frame surface. Apply anti-rust paint to areas cut or drilled on site to ensure the anti-corrosion coating remains intact.
Nameplate and Label Installation
Secure the product nameplate in a visible position on the support frame, indicating product model, rated load, manufacturer, installation date, and other information. Post load-bearing warning labels, prohibiting use beyond rated load.
Finished Product Protection
Protect the completed support frame from damage. Stepping on the support frame, stacking heavy objects on it, and impacting it are strictly prohibited. When equipment is subsequently installed, lift and place it gently to avoid impact loads. Cover surrounding areas with protective film during nearby construction to prevent cement, paint, and other contaminants from damaging the galvanized layer.
9.12 Special Scenario Installation Points
9.12.1 Installation Under Anti-Static Floors
- Support frame height should match the anti-static floor support height, ensuring the support frame top surface is 1-2 mm lower than the floor support surface to avoid lifting the floor
- Support frame columns should avoid floor support positions, with layout coordinated with the floor grid
- Grounding system should be reliably connected to the floor grounding system to form a unified equipotential body
- Floor cutouts should be accurately positioned with neat edges, and cutout edges should be edge-sealed
9.12.2 Extra-High Support Frame Installation (Height >800 mm)
- Add horizontal tie beams and lateral diagonal bracing to enhance lateral stability
- Reduce column spacing appropriately and increase support density
- Erect temporary supports during installation to prevent toppling
- Strictly control column verticality with deviation ≤0.5‰
- Seismic verification is mandatory; add seismic tie rods if necessary
9.12.3 Welded Support Frame Installation
- Welders must hold valid certification; fire extinguishing equipment must be available on site
- Tack weld for positioning first, verify dimensions, then perform full welding
- Weld height must meet design requirements; welds must be full with no slag inclusion, porosity, or undercut defects
- After welding, remove weld slag and apply two coats of anti-rust paint plus one coat of finish paint to welded areas
- Fire prevention and arc flash protection measures must be implemented during welding
Wiring for floor load-bearing support frames primarily refers to electrical system wiring, with the core being equipotential grounding system wiring. Smart monitoring support frames also include sensor and environment monitoring system wiring. Wiring quality directly affects static discharge effectiveness and electrical safety, and must be strictly performed in accordance with specifications.
10.1 Wiring Construction Basis
| Standard | Description |
|---|---|
| GB 50169-2016 | Code for Construction and Acceptance of Earthing Installation of Electrical Equipment Installation Engineering |
| GB 50174-2017 | Code for Design of Data Centers |
| YD/T 2164-2010 | Environment Conditions of Communication Data Center Computer Room |
| — | Design drawings and product technical requirements |
10.2 Equipotential Grounding System Wiring
10.2.1 Wiring Material Requirements
Grounding Conductors
| Property | Specification |
|---|---|
| Material | Stranded copper conductor with insulation, copper purity ≥99.9% |
| Specification | General areas: BV-4 mm²; heavy equipment areas and core computer rooms: BV-6 mm² |
| Insulation | Flame-retardant PVC insulation, yellow-green dual color |
| Requirement | Conductor must be free of damage and oxidation, wire gauge matching nominal value |
Connection Terminals
| Component | Specification |
|---|---|
| Copper lug | Closed-barrel copper terminal, red copper material, tin-plated surface |
| Bolts | Brass or galvanized bolts, M6-M8 specification, with flat washers and spring washers |
| Conductive gasket | Red copper material, 0.5 mm thickness, oxidation layer removed from contact surfaces |
Copper Foil Tape
| Property | Specification |
|---|---|
| Material | T2 red copper foil |
| Specification | Width ≥20 mm, thickness ≥0.1 mm |
| Requirement | Surface free of oxidation and creases, good conductivity |
10.2.2 Wiring Process Requirements
Conductor End Termination
- Strip the insulation from the conductor end, length matching the copper lug barrel depth, without damaging wire strands
- Insert the wire strands into the copper lug and crimp firmly with a crimping tool, with no fewer than 2 crimp points
- After crimping, perform a pull test to ensure the conductor does not detach
- Heat-shrink tubing can be applied over the copper lug-to-conductor connection for insulation protection
Support Frame End Connection
- Locate the pre-installed grounding terminal bolt on the support frame and remove the nut
- Slide the copper lug onto the bolt, add flat washer and spring washer in sequence, and tighten the fastening nut
- Tightening torque: M6 bolts 8 N·m, M8 bolts 12 N·m
- Before connection, sand the bolt and support frame contact surfaces to remove galvanized layer and oxide film, ensuring good conductivity
- Each independent support frame unit must have at least 2 grounding points arranged diagonally
Grounding Bar End Connection
- Connect the other end of the grounding conductor to the computer room equipotential grounding copper bar
- Clean the copper bar connection area to ensure good contact
- Use bolts for fastening; wiring should be neat with clear labeling
- When multiple conductors connect to the same copper bar, arrange them in sequence without overlapping
Copper Foil Tape Connection
- Lay copper foil tape flat; overlap length at joints ≥50 mm
- Bond overlapping areas with conductive adhesive and compress with pressure strips
- Secure copper foil tape to support frame crossbeams with dedicated clips, ensuring tight contact
- Make smooth arc transitions at bends in the copper foil tape, avoiding breakage
10.2.3 Wiring Quality Requirements
| Item | Requirement |
|---|---|
| Conductivity | The entire support frame system must be electrically continuous; transition resistance between any two points ≤0.03 Ω, with no open circuits |
| Grounding resistance | Overall grounding resistance of the support frame system ≤4 Ω; ≤1 Ω when connected to a combined grounding system |
| Mechanical strength | Wiring firmly secured, withstanding 50 N pull force without loosening or detachment |
| Appearance | Wiring neat and aesthetically pleasing, straight and level, securely fastened, clearly labeled, no tangled or messy wiring |
10.3 Smart Monitoring System Wiring
Smart monitoring support frames are equipped with pressure sensors, displacement sensors, tilt sensors, etc., which need to be connected to the computer room environment monitoring system.
10.3.1 Sensor Wiring
Pressure Sensor
- Installed between the column and base plate; four-wire connection: power positive, power negative, signal positive, signal negative
- Signal wire uses shielded cable with shield grounded at one end only
- Connection terminals must be secure, with moisture and dust protection
- Sensor power supply: DC 24V
Displacement Sensor
- Installed at the bottom of the crossbeam for monitoring deflection deformation
- RS485 communication interface, Modbus protocol
- Communication line uses shielded twisted pair, wire gauge ≥0.5 mm²
- Bus length ≤1000 m; repeaters required for longer distances
Tilt Sensor
- Installed on the support frame structure to monitor overall tilt angle
- Power supply DC 12-24V, output 4-20 mA analog or digital signal
- Pay attention to positive/negative terminal distinction to avoid reverse connection damaging the device
10.3.2 Acquisition Terminal Wiring
- All sensor signal lines connect to the on-site data acquisition terminal
- Acquisition terminal power is provided by the computer room UPS supply to ensure operation during power outages
- Acquisition terminal connects to the environment monitoring system host via Ethernet or 485 bus
- Wiring should be labeled with sensor number, location, and type
10.3.3 Wiring Precautions
- Confirm supply voltage and polarity before wiring sensors; reverse connection is strictly prohibited
- Separate signal cables from power cables, with spacing ≥300 mm, to avoid electromagnetic interference
- Ground the shield at one end only; grounding at both ends is strictly prohibited as it creates ground loops
- Joints must be properly insulated and waterproofed; special protection is required in humid computer room environments
- After wiring is complete, commission each sensor one by one to ensure normal data acquisition
10.4 Wiring Testing and Acceptance
Continuity Test
Use a multimeter resistance range to measure continuity resistance between nodes, confirming there are no open circuits or poor contact issues.
Grounding Resistance Test
Use a ground resistance tester with the four-terminal method to measure system grounding resistance, confirming compliance with design requirements.
Insulation Test
Measure insulation between the grounding conductor and the ground to confirm there is no accidental grounding or short circuit.
Functional Test
Power on the smart system for testing, confirming all sensor data is uploaded normally and alarm functions operate correctly.
After support frame installation and wiring is complete, system commissioning must be performed to verify that all performance indicators meet design requirements, ensuring safety and reliability after equipment is installed. Commissioning is divided into four parts: leveling accuracy commissioning, load-bearing performance commissioning, grounding performance commissioning, and seismic performance commissioning.
11.1 Commissioning Preparation
Testing Instrument Preparation
Prepare laser level, feeler gauge, dial indicator, torque wrench, ground resistance tester, multimeter, tension gauge, and other testing tools. Confirm that instrument metrological calibration is valid and accuracy meets requirements.
Commissioning Personnel Preparation
Commissioning is performed by professional technical personnel who are familiar with product performance and commissioning methods and understand the acceptance standards for each indicator.
Record Form Preparation
Prepare commissioning record forms to document all test data, serving as part of the acceptance documentation.
Site Condition Confirmation
Confirm that support frame installation is fully complete, all bolts are tightened, the site is clean, and there are no obstacles affecting commissioning.
11.2 Leveling Accuracy Commissioning
11.2.1 Top Surface Levelness Commissioning
Reference Calibration
Use the computer room elevation control line as the reference. Project a horizontal plane with a laser level covering the entire support frame area.
Point-by-Point Inspection
Measure the top surface elevation of the support frame point by point on a grid basis, recording the deviation at each point. Inspection points include all column positions, crossbeam midpoints, and crossbeam endpoints.
Deviation Adjustment
For points with elevation deviation exceeding ±0.5 mm, loosen the locking nuts and finely adjust the adjusting threaded rod until the elevation meets requirements. Follow the principle of “lower high points, raise low points,” adjusting slowly to avoid overshooting.
Overall Re-Verification
After all adjustments are complete, perform another comprehensive inspection to confirm:
| Item | Tolerance |
|---|---|
| Height difference between adjacent support points | ≤0.3 mm |
| Single crossbeam deflection (midpoint vs. ends) | ≤0.5 mm |
| Overall height difference within 2 m range | ≤1 mm |
| Maximum height difference across entire area | ≤2 mm |
Locking
After levelness is achieved, tighten all locking nuts to specified torque. Monitor elevation changes throughout the locking process, correcting any shift promptly. After locking, re-verify levelness to confirm no spring-back.
11.2.2 Column Verticality Commissioning
Use a magnetic level to attach to the column side and measure verticality in two directions.
- Columns with verticality deviation exceeding 1‰ should be corrected by adjusting base plate shims or adjusting threaded rods
- Extra-high support frames must strictly control verticality with deviation ≤0.5‰, and verify that diagonal braces are evenly loaded
11.3 Load-Bearing Performance Commissioning
11.3.1 No-Load Stability Inspection
- Manually rock the support frame structure to check overall stability; there should be no obvious shaking or abnormal noise
- Check that all joint bolts are tight, with no gaps or relative displacement at joints
- Check that base plates are in firm contact with the floor, with no rocking or voids
11.3.2 Staged Loading Test
Loading Plan
Use sandbags and standard weights as loading materials, loading in stages at 30%, 60%, 100%, and 120% of rated load.
Deformation Monitoring
Place dial indicators at key points to monitor deflection deformation and settlement during loading. Monitoring points include:
- Main crossbeam mid-span position (monitoring deflection)
- Column base (monitoring settlement)
- Joint connections (monitoring relative displacement)
Loading Procedure
| Stage | Load | Duration | Monitoring |
|---|---|---|---|
| First | 30% rated load | 30 min | Record deformation data |
| Second | 60% rated load | 1 hour | Record data, check for abnormalities |
| Third | 100% rated load | 2 hours | Continuously observe deformation development |
| Fourth | 120% rated load (safety factor test) | 24 hours | Record final deformation |
Unloading Observation
Unload in stages, allowing 30 minutes after each stage for recording rebound deformation. Measure residual deformation after complete unloading.
11.3.3 Acceptance Criteria
| Item | Criterion |
|---|---|
| Maximum crossbeam deflection at rated load | ≤1/1000 of span |
| At 1.2x load | No plastic deformation, no joint loosening, no weld cracking |
| After complete unloading | Residual deformation ≤0.25 mm |
| Base plates | No displacement, no expansion bolt pull-out, no floor cracking |
11.4 Grounding Performance Commissioning
Continuity Performance Test
Use a multimeter low-resistance range to measure resistance between any two points on the support frame. Requirement: ≤0.03 Ω, confirming the entire frame is electrically continuous with no insulation breakpoints.
Grounding Resistance Test
Use a ground resistance tester with the four-terminal method to measure the grounding resistance of the support frame system:
| Application | Requirement |
|---|---|
| General computer rooms | ≤4 Ω |
| Class A data centers, telecommunication computer rooms | ≤1 Ω |
If the test fails, check the reliability of grounding point connections, increase the number of grounding points, or verify that the computer room main grounding system is functioning properly.
Static Discharge Test
Use a surface resistance tester to measure the resistance between the support frame surface and the grounding electrode. The value should be in the range of 10⁶-10⁹ Ω, ensuring static electricity can be safely discharged without creating a short circuit.
11.5 Seismic Performance Commissioning (Seismic Support Frames)
Joint Strength Inspection
Check the bolt torque at all seismic diagonal brace and tie rod connection joints to ensure they meet design values.
Lateral Stiffness Test
Apply horizontal force to the support frame and measure lateral displacement:
- Apply horizontal force equivalent to 5% of self-weight; lateral displacement should be ≤1/500 of height
- No residual deformation after unloading
Limit Device Inspection
Check the adjustment margin of equipment limit stops and seismic tie rods to ensure effective limitation of equipment displacement.
11.6 Smart Monitoring System Commissioning
Sensor Calibration
Perform zero-point calibration on pressure, displacement, and tilt sensors; set range and alarm thresholds.
Communication Test
Test communication between sensors, acquisition terminal, and environment monitoring system to verify normal operation, data transmission stability, and absence of packet loss or delay.
Alarm Function Test
Simulate overload, excessive deformation, excessive tilt, and other conditions to verify the system triggers alarms properly and alarm information is accurately pushed.
Data Recording Test
Verify the system properly stores historical data that can be queried and exported.
11.7 Commissioning Completion
- After all commissioning items are complete, organize commissioning records, fill out the commissioning report, and obtain signatures from all parties for confirmation
- Promptly rectify any issues found during commissioning, and re-commission after rectification
- After commissioning passes, apply anti-rust grease to all threaded areas for protection
- Clean the commissioning site, remove loading weights and tools, and ensure finished product protection
12.1 Transportation and Storage Precautions
Transportation Precautions
- Products should be properly packaged during transportation, with buffer materials between components to prevent impact and friction damage to the galvanized layer
- Stack neatly during loading with a stable center of gravity, securely lashed to prevent sliding and toppling during transport
- Threaded areas should be fitted with protective caps; slender components should have anti-bending measures to prevent compression deformation
- Rain and moisture protection measures should be implemented during transportation; exposure to rain or immersion is strictly prohibited to prevent premature corrosion
- Lift and place gently during loading and unloading; throwing, rolling, or dropping is strictly prohibited to prevent component deformation and coating detachment
Storage Precautions
- Storage site should be dry, well-ventilated, and free of corrosive gases; indoor warehouse is optimal
- Components should be sorted and stacked with clear labeling; support with wooden blocks, keeping at least 100 mm above ground to prevent moisture
- Stacking height should not be excessive to avoid compression deformation of bottom components; square tubes and channels should not be stacked higher than 1.5 m
- Conduct regular inspections during storage; treat any rust promptly. Bolts and accessories should be sealed for storage
- Storage together with acids, alkalis, or other corrosive materials is strictly prohibited; keep away from heat sources and open flames
12.2 Installation and Construction Precautions
Safety Construction Precautions
- Construction personnel must wear safety helmets; safety harnesses are required for high-altitude work; comply with on-site safety management regulations
- Check insulation before using power tools; temporary electrical installations must comply with safety regulations; unauthorized wiring is strictly prohibited
- Wear protective goggles when drilling with impact drills to prevent debris from entering eyes
- Hot work requires a hot work permit, fire extinguishing equipment, and a designated fire watch; confirm no fire hazards remain after work
- Multiple personnel should coordinate when moving heavy components, with unified command to prevent crushing injuries
- When working in operating computer rooms, strictly comply with computer room management regulations; touching operating equipment is strictly prohibited
Construction Quality Precautions
- Strictly construct according to drawings and specifications; unauthorized changes to design plans and component specifications are prohibited
- Confirm no underground utilities before drilling; penetrating floor slabs or damaging utilities is strictly prohibited
- Expansion bolts must be embedded in solid concrete layers; installation in leveling layers or insulation layers is strictly prohibited
- Double locking nuts must be tightened after leveling to prevent loosening under prolonged compression
- All bolts must be tightened to specified torque; missing, under-tightened, or over-tightened bolts are strictly prohibited
- On-site cut and welded areas must undergo anti-corrosion treatment with anti-rust paint
- Clean the site daily after construction, ensuring the work area is tidy
Installation Prohibitions
- Exceeding rated load or applying impact loads beyond design values on the support frame is strictly prohibited
- Arbitrary cutting or welding of primary load-bearing components and drilling holes in columns are strictly prohibited
- Hanging heavy objects from the support frame and using it as a lifting anchor point are strictly prohibited
- Removing diagonal braces, tie rods, or other reinforcing components is strictly prohibited
- Striking the galvanized layer with hard objects is strictly prohibited to avoid damaging the anti-corrosion coating
12.3 Operational Precautions
Load Usage Specifications
- Strictly use according to the rated load indicated on the nameplate; overloading is strictly prohibited
- Distribute equipment evenly to avoid excessive localized concentrated loads
- Handle equipment gently during placement; dropping from heights is strictly prohibited to avoid impact loads
- When increasing equipment weight later, re-verify load-bearing capacity and reinforce as necessary
Daily Usage Precautions
- Welding or gas cutting operations on the support frame are strictly prohibited, as high temperatures can damage components and the anti-corrosion coating
- Washing the support frame base directly with water is strictly prohibited to avoid corrosion from prolonged water accumulation
- Keep the support frame area dry and well-ventilated, avoiding prolonged exposure to high-humidity environments
- Covering or obscuring support frame identification plates is strictly prohibited
- Non-professional personnel are strictly prohibited from adjusting support frame height or disassembling components without authorization
Environmental Precautions
- Avoid contact with corrosive liquids such as acids and alkalis; wipe up spills promptly if accidental contact occurs
- In the event of water leakage in the computer room, drain promptly to avoid prolonged immersion of the support frame
- Regularly inspect the surrounding environment to prevent debris accumulation from affecting support frame loading and heat dissipation
12.4 Electrical Safety Precautions
- The support frame must be reliably grounded. It is strictly prohibited to disconnect the ground or have poor contact.
- It is strictly prohibited to lay high-voltage power cables on the support frame, and it is strictly prohibited to place strong-current wiring directly on the frame.
- When inspecting electrical equipment, take care to prevent short-circuit current from passing through the support frame.
- Regularly check that ground connections are secure and that ground resistance meets the required standards.
- After thunderstorms, check that the grounding system is intact and free of lightning damage.
12.5 Special Environment Precautions
High-Altitude Regions
In areas above 2,000 meters elevation, due to thin air and poor heat dissipation, pay attention to temperature rise in electrical components. Also consider seismic and wind load effects and appropriately increase the safety factor.
Coastal High-Humidity, High-Salt-Spray Regions
Dacromet or stainless steel materials are recommended. Regularly inspect anti-corrosion conditions and increase the frequency of anti-corrosion maintenance.
High Seismic Intensity Regions
Seismic-resistant support frames must be selected. Regularly inspect the connections of seismic components, and conduct a comprehensive structural inspection after an earthquake.
The ground load-bearing support frame is a steel structure product with an inherently very low failure rate. However, good maintenance can significantly extend its service life and ensure long-term operational safety. Maintenance is divided into four levels: daily inspection, monthly maintenance, quarterly maintenance, and annual overhaul.
13.1 Daily Inspection
- Frequency: Once per day, performed by equipment room operations personnel.
- Inspection content:
- Visual inspection: Observe whether the overall support frame has obvious deformation or tilting, and whether components have cracks.
- Abnormal noise inspection: Check for abnormal friction or impact sounds during equipment operation.
- Label inspection: Verify that nameplates and warning signs are intact and legible.
- Environmental inspection: Check for water accumulation, debris, or corrosive liquid contamination around the support frame.
- Grounding inspection: Check whether the ground conductor has fallen off or broken.
- Inspection records: Fill out the daily inspection record form. Report abnormalities promptly. Handle minor issues on-site; notify professional maintenance personnel for major issues.
13.2 Monthly Maintenance
- Frequency: Once per month, performed by maintenance technicians.
- Maintenance content:
- Bolt tightening check: Spot-check key connection bolts for looseness, focusing on beam connection bolts and base anchor bolts directly beneath equipment. Re-tighten to specified torque if loosening is found. The spot-check ratio must not be less than 10% of the total number of bolts.
- Levelness spot check: Spot-check levelness at key positions to confirm whether the support frame has settled or deformed. Spot-check points must be no fewer than 5% of the total points, with emphasis on heavy-load areas.
- Anti-corrosion visual inspection: Check the galvanized layer for rust or peeling, and check welded touch-up painted areas for paint peeling or rust recurrence. Address minor rust promptly by removing rust and repainting.
- Grounding check: Inspect ground terminals for looseness and oxidation, and clean oxides from contact surfaces. Test continuity to ensure proper grounding.
- Cleaning and dust removal: Clean dust and debris from the support frame surface to keep it clean and dry.
13.3 Quarterly Maintenance
- Frequency: Once per quarter, performed by professional maintenance personnel.
- Maintenance content:
- Comprehensive bolt re-tightening: Conduct a full inspection and re-tightening of all connection bolts to ensure torque meets requirements. For bolts in areas subject to prolonged vibration, add lock washers or apply thread-locking adhesive.
- Settlement and deformation observation: Conduct a comprehensive levelness and settlement measurement of all support frames, plot settlement curves, and analyze settlement trends. Compare with previous data; promptly investigate any abnormal settlement rate.
- Anti-corrosion maintenance: Conduct a comprehensive anti-corrosion inspection. Remove rust and repaint all rusted points. Apply anti-rust grease to threaded adjustment areas to ensure smooth adjustment. Check the base-to-floor contact area for water accumulation and rust; raise with shims if necessary.
- Grounding system testing: Test the system ground resistance, inspect all ground connection points, and address oxidation and loosening issues.
- Seismic component inspection: For seismic-resistant support frames, check whether diagonal braces, tie rods, and limiting devices are intact and connections are secure.
13.4 Annual Overhaul and Comprehensive Inspection
- Frequency: Once per year, performed by the manufacturer or a professional inspection agency.
- Inspection and maintenance content:
- Comprehensive structural safety inspection: Fully inspect all components for deformation and corrosion. Measure the wall thickness of key cross-sections to assess corrosion thinning. Conduct flaw detection on node welds (for welded support frames). Perform load re-verification to assess the safety margin under current equipment loads.
- Mechanical performance sampling test: Select representative points for load-bearing capacity sampling tests to verify structural performance degradation.
- Anchorage performance testing: Spot-test the pull-out resistance of expansion bolts, check anchoring reliability, and replace severely corroded bolts.
- Comprehensive system maintenance: Clean and reapply anti-rust grease to all threaded parts. Thoroughly remove rust from all corroded areas and apply anti-corrosion paint. Replace damaged fittings, seals, and vibration-damping pads. Tighten all bolts and replace aged spring washers.
- Intelligent system calibration: For smart monitoring support frames, calibrate sensors, verify data accuracy, and update alarm thresholds.
- Issuance of maintenance report: After inspection, issue an annual inspection and maintenance report assessing the support frame safety status, providing subsequent maintenance recommendations and service life assessment.
13.5 Common Damage Repair Methods
13.5.1 Galvanized Layer Rust Repair
1. Thoroughly remove rust from corroded areas using sandpaper or a wire brush until bare metal is exposed.
2. Wipe clean with a dry cloth to remove dust.
3. Apply one coat of zinc-rich primer; after drying, apply two coats of finish paint close in color to the original galvanized layer.
4. If corrosion is severe and component wall thickness has reduced by more than 10%, the component must be replaced.
13.5.2 Bolt Loosening Repair
1. Clean dust and oil from the bolt area.
2. Re-tighten to the specified torque using a torque wrench.
3. For bolts that repeatedly loosen, replace with new spring washers or apply thread-locking adhesive.
4. If bolts are stripped or seized due to corrosion, replace with new bolts of the same specification.
13.5.3 Support Frame Settlement/Deformation Repair
1. Measure the settlement and deformation amount and analyze the cause.
2. If caused by ground settlement, add stainless steel shims under the base to adjust the height.
3. If caused by component deformation: minor deformation can be straightened and reinforced; severe deformation requires component replacement.
4. If caused by excessive load, add support columns for reinforcement.
13.5.4 Poor Grounding Repair
1. Locate the poor-contact node, disassemble, and grind the contact surface to remove the oxide layer.
2. Re-tighten bolts and apply conductive paste.
3. Replace damaged ground conductors with new ones.
4. If ground resistance does not meet requirements, add additional ground points or inspect the main grounding system.
13.6 Maintenance Safety Precautions
- Overloading is strictly prohibited during maintenance. Disassembly of load-bearing components while equipment is in operation is strictly prohibited.
- When working at height, wear a safety harness and take proper safety precautions.
- When removing rust and painting, ensure adequate ventilation and wear personal protective equipment to avoid inhaling dust and paint mist.
- For electrical maintenance, cut off power before operation to prevent electric shock.
- After maintenance, conduct inspection and testing to confirm safety before restoring normal use.
14.1 Installation and Construction Common Issues
Problem 1: Rebar encountered during floor drilling; expansion bolts cannot be installed
- Phenomenon: Drill bit hits rebar during drilling; cannot penetrate deeper, or the hole is wasted.
- Cause analysis: The hole position happens to fall on slab rebar.
- Solutions:
1. Offset the hole 2–3 cm and re-drill to avoid the rebar.
2. If the base hole positions do not match, replace with an adjustable base with slotted holes, or enlarge the holes on site.
3. In rebar-dense areas, switch to chemical anchor bolts or use adhesive fixing methods.
4. During the design phase, avoid rebar-dense areas and optimize column point positions.
Problem 2: Soft floor substrate; insufficient expansion bolt anchoring force
- Phenomenon: Expansion bolts remain loose after tightening; pull-out resistance is insufficient.
- Cause analysis: Leveling layer is too thick, concrete strength is insufficient, or the substrate is sandy/loose.
- Solutions:
1. Use extended-length expansion bolts that penetrate the leveling layer into the solid concrete layer.
2. Switch to chemical anchor bolts for stronger anchoring force suitable for low-strength substrates.
3. Enlarge the base area and increase the number of anchor points to distribute the anchoring force.
4. For particularly soft substrates, perform local grouting reinforcement before installing the support frame.
Problem 3: Support frame rebounds after leveling; height is unstable
- Phenomenon: After leveling and locking, the height changes over time and levelness degrades.
- Cause analysis: Thread clearance, nuts not locked, ground compaction settlement.
- Solutions:
1. Use double-nut locking and add lock washers to ensure reliable locking.
2. Perform secondary leveling after pre-loading to eliminate initial settlement.
3. Clean thread areas and apply a small amount of grease to prevent false locking due to thread binding.
4. Add base plates on soft ground to increase contact area and reduce later settlement.
Problem 4: Large gaps at beam connections after installation; poor contact
- Phenomenon: Visible gaps at beam-to-column and beam-to-beam connections; frame shakes.
- Cause analysis: Component dimensional deviation, improper alignment during installation, deformed connectors.
- Solutions:
1. Adjust component positions and re-align to ensure tight fit.
2. For small gaps, add metal shims to fill.
3. For excessively large gaps or deformed components, replace with qualified components.
4. Use a rubber mallet to tap nodes into place during installation.
14.2 Performance Common Issues
Problem 5: Excessive deflection under load
- Phenomenon: Beam bends noticeably after loading, exceeding allowable specification values.
- Cause analysis: Beam section undersized, span too large, insufficient support points, overload.
- Solutions:
1. Verify actual load; overload use is strictly prohibited.
2. Add support columns at mid-span of beams to reduce span and increase load capacity.
3. Replace with larger-section beam profiles to enhance bending resistance.
4. Add secondary beams and tie connections to improve overall stiffness.
Problem 6: Abnormal noise and vibration during use
- Phenomenon: Support frame emits abnormal noise during equipment operation or has noticeable vibration.
- Cause analysis: Loose nodes, component resonance, poor contact, failed vibration damping.
- Solutions:
1. Fully tighten all connection bolts to eliminate looseness gaps.
2. Add rubber pads at contact areas for cushioning and vibration damping, eliminating hard-contact noise.
3. Adjust support spacing to avoid resonance frequency.
4. Install vibration isolators under equipment to isolate vibration transmission.
Problem 7: Ground resistance does not meet requirements
- Phenomenon: Measured ground resistance exceeds specification requirements.
- Cause analysis: Poor ground connections, oxidized nodes, insufficient ground points, main grounding system issues.
- Solutions:
1. Grind all ground connection points to remove oxide layers and re-tighten.
2. Increase the number of ground points and connect to the grounding system at multiple points.
3. Inspect the main ground copper bar and ground electrodes in the equipment room to rule out main system faults.
4. Apply conductive paste at connections to reduce contact resistance.
Problem 8: Deteriorating overall levelness; tilting occurs
- Phenomenon: After a period of use, local areas of the support frame settle and levelness exceeds tolerance.
- Cause analysis: Uneven ground settlement, loose bolts, component deformation, local overload.
- Solutions:
1. Conduct a comprehensive inspection to identify the settlement cause and address the ground substrate issue.
2. Re-level and lock all nuts.
3. Add shims at settled areas to restore levelness.
4. Add supports in overloaded areas to distribute loads.
14.3 Maintenance Common Issues
Problem 9: White rust and red rust on the galvanized layer
- Phenomenon: White powdery corrosion appears on the support frame surface; in severe cases, reddish-brown rust spots appear.
- Cause analysis: Excessive environmental humidity, poor ventilation, damaged galvanized layer, contact with corrosive substances.
- Solutions:
1. For minor white rust, wipe clean with a dry cloth and improve ventilation to reduce humidity.
2. For areas with red rust, thoroughly remove rust and apply zinc-rich primer plus finish paint.
3. In high-humidity corrosive environments, upgrade to Dacromet or stainless steel materials.
4. Avoid contact with acid/alkaline liquids and keep the environment dry and clean.
Problem 10: Adjustment screw rusted and seized; cannot be adjusted
- Phenomenon: Nuts cannot be turned when height adjustment is needed; threads are rusted and seized.
- Cause analysis: Long-term non-adjustment, water ingress and dampness, no rust-prevention treatment.
- Solutions:
1. Apply rust-penetrating lubricant and allow time for penetration before attempting to turn.
2. Tap the nut lightly with a wrench to loosen the rust layer.
3. If completely seized, cut off and replace with a new adjustment screw.
4. Apply anti-rust grease to threaded areas during regular maintenance to maintain lubrication and corrosion protection.
Problem 11: Severe expansion bolt corrosion
- Phenomenon: Rust water appears around floor expansion bolts; bolt shanks are corroded.
- Cause analysis: Damp floor, damaged bolt anti-corrosion coating.
- Solutions:
1. For minor corrosion, remove rust and apply touch-up anti-rust paint.
2. For severe corrosion, replace with new stainless steel expansion bolts.
3. Apply sealant around bolt holes to prevent water ingress.
4. In damp areas, directly use stainless steel bolts.
14.4 Other Common Issues
Problem 12: Support frame interferes with anti-static floor
- Phenomenon: Support frame pushes up the floor panels, or floor panels press unevenly on the support frame.
- Cause analysis: Height calculation deviation, incorrect installation elevation.
- Solutions:
1. Fine-tune support frame height so that the frame top is 1–2 mm lower than the floor support surface.
2. Grind local interference areas or shim up the floor support as appropriate.
3. Re-verify elevation and unify the datum.
Problem 13: Abnormal smart monitoring data
- Phenomenon: Sensor data jumps, is inaccurate, or no data.
- Cause analysis: Loose wiring, sensor failure, interference, power supply issues.
- Solutions:
1. Check wiring and power supply; rule out poor contact and power loss.
2. Check shielding and grounding to rule out electromagnetic interference.
3. Calibrate sensors; replace faulty sensors if necessary.
4. Check communication lines and acquisition terminals.
Q1: How to select the appropriate load-bearing support frame model?
A: Model selection is primarily based on three factors:
- Equipment weight: Calculate the total weight of each equipment unit, including self-weight, internal modules, cables, and other attached weights. Multiply by a safety factor of 1.2 and select the load rating from the specification table.
- Floor load: Understand the original design live load of the building floor and determine base area and support density based on the required load reduction ratio.
- Installation height: Determine the support frame height and adjustment travel based on the equipment room raised floor height and anti-static floor height.
If uncertain, provide equipment parameters and building structural information, and our technical personnel will perform professional selection and structural verification calculations.
Q2: Can the load-bearing support frame be placed directly on the anti-static floor?
A: No. The load-bearing support frame must be installed on the ground, transmitting loads directly to the building slab. If placed on the floor, loads are still transmitted through the floor supports, which does not achieve load distribution to the slab and may instead crush the anti-static floor. The correct approach is for the support frame to pass through the floor layer and rest directly on the ground slab, with the top connected to the equipment base.
Q3: Will installing a load-bearing support frame damage the building structure?
A: Normal installation will not damage the building structure. Expansion bolt holes have small diameters and shallow depths, only working in the concrete surface layer without damaging main slab reinforcement, and have virtually no impact on structural load capacity. Compared with reinforcement methods such as steel plate bonding or carbon fiber, the impact on the building structure is smaller. Before construction, rebar positions are confirmed to avoid drilling through main reinforcement.
Q4: Can the support frame be relocated and reused after installation?
A: Assembled bolted support frames can be completely disassembled and reused. During disassembly, bolts are unscrewed and components remain undamaged, allowing reinstallation at new locations. This is particularly suitable for equipment room relocation and layout adjustment scenarios. Welded support frames have fixed welded nodes; disassembly damages the components, so reuse is generally not recommended.
Q5: Can heavy cabinets be installed on ordinary office floors?
A: Ordinary office floors typically have a live load of 3.5 kN/m² (approximately 350 kg/m²). Placing heavy cabinets directly on them would definitely exceed the limit. By properly designing load-bearing support frames to distribute loads over a sufficient area, the equivalent uniform load can be reduced to within the allowable floor capacity, enabling heavy cabinet deployment. However, professional personnel must perform structural calculations and solution design to ensure structural safety.
Q6: Does the load-bearing support frame need grounding? Why?
A: Grounding is mandatory. There are three reasons:
- Static protection: Metal support frames easily accumulate static charge. Grounding allows timely discharge of static electricity, preventing damage to electronic equipment from electrostatic discharge.
- Equipotential requirements: All metal components in the equipment room must maintain equipotential potential to prevent safety issues caused by potential differences.
- Electrical safety: In the event of equipment leakage, grounding the support frame provides a short-circuit current path, triggering protective devices and ensuring personnel safety.
Q7: What is the maximum support frame height? Will it be unstable if too tall?
A: Standard products can reach heights of 1,000 mm, with custom versions up to 2,000 mm. The higher the height, the poorer the lateral stability. Therefore, ultra-tall support frames enhance stability through increased column sections, reduced spacing, and additional diagonal bracing and tie beams. As long as designed and installed per specifications, stability and safety are fully guaranteed. Ultra-tall support frames require specialized design and verification.
Q8: What is the warranty period? What is the service life?
A: The warranty period for this product is 2 years. During the warranty period, quality issues not caused by human damage are repaired or replaced free of charge. Under normal indoor conditions, the design service life of hot-dip galvanized material is no less than 20 years. Regular maintenance can further extend service life. Dacromet and stainless steel materials have even longer service lives.
Q9: How long does it take to install a support frame? Will it affect normal equipment room operation?
A: For a standard single-cabinet support frame, a skilled installation crew can complete it in half a day. Full-row or full-area installation depends on scale, generally 1–3 days. Assembled installation involves no open flames, minimal dust, and no noise, allowing partial construction in operating equipment rooms. With proper isolation and protection, normal equipment room operation is essentially unaffected.
Q10: Can people stand on the support frame? Can maintenance personnel step on it?
A: Maintenance personnel live loads have been considered in the design. Standing and operating within the rated load range is allowed. However, multiple people standing together in one area is strictly prohibited, as are jumping, impact loading, and stacking heavy objects exceeding the maintenance load. When performing maintenance, step on columns and beam positions, avoiding mid-span beam areas.
Q11: Can the support frame protect equipment from falling during an earthquake?
A: Standard support frames primarily address vertical load-bearing and have limited seismic resistance. In high seismic intensity regions, seismic-resistant load-bearing support frames are recommended. By incorporating diagonal braces, tie rods, and limiting devices, these frames effectively resist horizontal seismic forces, preventing equipment sliding and overturning, and meeting building seismic design code requirements.
Q12: Does the load-bearing support frame require annual inspection?
A: Annual comprehensive inspection is recommended. Especially for heavy-load areas and critical equipment rooms, annual inspection promptly identifies hidden hazards such as corrosion, loosening, and settlement, ensuring structural safety. For ordinary light-load areas, inspection every 2 years is acceptable.
Q13: If equipment weight increases later, can the existing support frame still be used?
A: It depends on the increase magnitude. If the increased weight remains within the rated load range, continued use is acceptable. If it exceeds the rated load but not by much, reinforcement upgrades such as adding support columns and secondary beams can be implemented. If the weight increase is substantial and far exceeds the original structural capacity, a higher-grade support frame must be replaced.
Q14: Do rubber pads need to be placed under the support frame base? What is their function?
A: This is an optional configuration with the following main functions:
- Vibration damping and noise reduction: Cushions vibration and reduces structural sound transmission.
- Anti-slip: Increases friction and prevents horizontal sliding of the support frame.
- Insulation: Blocks some stray currents and prevents electrochemical corrosion.
- Floor protection: Prevents the metal base from scratching the floor surface.
Q15: Which type of support frame is best for damp basement equipment rooms?
A: Basements have high humidity, and ordinary hot-dip galvanized frames are prone to white rust. Dacromet-coated support frames are recommended, with corrosion resistance 3–5 times that of ordinary hot-dip galvanizing and stronger moisture resistance. For environments with extreme humidity or condensation, 304 stainless steel material is recommended to completely solve the rust problem. At the same time, implement equipment room dehumidification to reduce environmental humidity.
Product acceptance is divided into four stages: factory acceptance, site entry acceptance, process acceptance, and completion acceptance. Each stage is strictly implemented in accordance with national standards and contract requirements to ensure full-process quality control of both product and installation quality.
16.1 Factory Acceptance
After production is completed, factory inspection is conducted before shipment by the manufacturer’s quality inspection department. Products may only leave the factory upon passing inspection.
16.1.1 Inspection Items
Visual Inspection
- Component surfaces are smooth, free of burrs, sharp edges, weld slag, and spatter.
- Galvanized layer is uniform and smooth, free of missed plating, peeling, blistering, and rust.
- No obvious deformation, bending, or impact damage on components.
- Threads are intact, free of stripping and cross-threading.
Dimensional Inspection
- Column length deviation: ±1 mm
- Beam length deviation: ±0.5 mm
- Base dimension deviation: ±0.5 mm
- Hole center distance deviation: ±0.3 mm
- Component straightness: ≤0.5‰
Performance Sampling Inspection
- Galvanized layer thickness test: Spot-check with a thickness gauge, conforming to standard requirements.
- Component hardness sampling: Key load-bearing components meet hardness requirements.
- Load testing: Each batch undergoes sampling load-bearing capacity testing to verify strength and deformation.
16.1.2 Factory Documentation
The following documents are delivered with the products upon acceptance:
- Product certificate of conformance
- Factory inspection report
- Product installation and operation manual
- Packing list
- Main material certification documents
16.2 Site Entry Acceptance
Upon delivery of products to the construction site, the construction unit, supervision unit, and contractor jointly perform site entry acceptance. Installation may proceed only after acceptance is passed.
16.2.1 Acceptance Content
Documentation Verification
- Verify that factory certificates, inspection reports, material certifications, and other documents are complete and valid.
- Verify that product models and specifications match the contract and drawings.
Visual and Quantity Acceptance
- Check component and accessory quantities against the packing list to confirm correctness.
- Inspect for damage, deformation, and coating peeling during transport.
- Check threads and holes for impact damage.
- Verify accessories are complete and specifications are compatible.
Sampling Re-inspection
- Perform sampling re-inspection of key dimensions and galvanized layer thickness. Non-conforming products shall be returned and are strictly prohibited from use.
16.2.2 Acceptance Records
Fill out material site entry acceptance records with signatures from all parties. Non-conforming products must be marked, stored separately, and removed from site within the specified time.
16.3 Process Acceptance
During construction, sub-item acceptance is performed for key processes. Non-conforming previous processes may not proceed to the next process.
16.3.1 Substrate Preparation Acceptance
- Floor strength and flatness meet requirements.
- Floor is clean, solid, free of sanding, hollowing, and cracking.
- Underground pipelines are clearly marked with no safety hazards.
16.3.2 Layout and Positioning Acceptance
- Point layout conforms to drawing requirements.
- Dimensional deviation, squareness, and elevation datum meet precision requirements.
- Positions correspond correctly to equipment locations with no misalignment.
16.3.3 Anchoring Installation Acceptance
- Drilling depth and diameter meet bolt requirements.
- Bolt tightening torque meets requirements; no looseness or tilting.
- Anchoring force sampling tests pass; no pull-out risk.
- Base is in close contact with the floor; no rocking.
16.3.4 Frame Assembly Acceptance
- Component models and specifications conform to design.
- Node connections are tight; bolts are complete and tightened.
- Frame dimensions and squareness meet precision requirements.
- Column verticality preliminarily meets requirements.
16.3.5 Leveling and Grounding Acceptance
- Levelness and elevation meet design precision requirements.
- All locking nuts are tightened; no looseness.
- Grounding system connections conform to specifications with good continuity.
- Ground resistance testing passes.
16.4 Completion Acceptance
After all support frame installation and commissioning are complete, overall completion acceptance is conducted, organized by the construction unit with participation from supervision, contractor, and design units.
16.4.1 Acceptance Basis
- GB 50462-2015 “Code for Construction and Acceptance of Data Center Infrastructure”
- GB 50205-2020 “Standard for Acceptance of Quality of Steel Structure Engineering Construction”
- Construction drawings, design changes, and technical consultation documents
- Product technical standards and contract requirements
16.4.2 Acceptance Items
Visual and Dimensional Acceptance
- Overall layout conforms to drawings; appearance is tidy and aesthetically pleasing.
- No component deformation, damage, or anti-corrosion coating damage.
- Identification nameplates are complete with accurate information.
- Cabling is neat; grounding is standardized.
Precision Index Acceptance
- Top surface elevation deviation: ±1 mm
- Top surface levelness: ≤1 mm/2 m
- Column verticality: ≤1‰
- Frame diagonal difference: ≤3 mm
Mechanical Performance Acceptance
- Preloading test passes; deflection and residual deformation conform to standards.
- All bolt tightening torques meet requirements; sampling pass rate is 100%.
- Anchoring is reliable; no loosening or displacement.
Electrical Performance Acceptance
- Ground resistance conforms to design requirements.
- System continuity is good; node transition resistance meets requirements.
- Intelligent monitoring system functions are normal.
Documentation Acceptance
- Completion documentation is complete, including:
- Construction start report and technical disclosure records
- Material site entry acceptance records and factory documentation
- Concealed works acceptance records
- Sub-item works acceptance records
- Commissioning records and preloading test records
- Ground resistance test records
- As-built drawings
- Acceptance reports
16.4.3 Acceptance Conclusion
Upon passing acceptance, all parties sign the completion acceptance report and the system is handed over to operations personnel for use. For non-conforming acceptance, a rectification notice is issued, and re-acceptance is performed after rectification is completed.
16.4.4 Acceptance Standard Comparison Table
| Acceptance Item | Standard Requirement | Inspection Method |
|---|---|---|
| Support frame top surface elevation | ±1 mm | Laser level measurement |
| Top surface levelness | ≤1 mm/2 m | 2 m straightedge + feeler gauge / laser level |
| Column verticality | ≤1‰ | Spirit level / theodolite |
| Beam deflection (rated load) | ≤1/1000 of span | Dial indicator measurement |
| Residual deformation | ≤0.25 mm | Dial indicator measurement after unloading |
| Bolt tightening torque | Conforms to design values | Torque wrench sampling |
| Ground resistance | ≤4 Ω (combined grounding ≤1 Ω) | Ground resistance tester |
| Galvanized layer thickness | ≥65 μm | Coating thickness gauge |
| Visual quality | No deformation, no rust, intact coating | Visual inspection |
I. Search Keyword Classification and Layout
1. Core Primary Keywords
Equipment room load-bearing support frame, ground load-bearing support frame, equipment room load distribution frame, equipment load-bearing base, floor load-bearing reinforcement support frame
2. High-Conversion Long-Tail Keywords
Equipment room ground load-bearing support frame installation, load-bearing support frame manufacturer, anti-static floor load-bearing support frame, cabinet load-bearing load distribution frame price, UPS battery cabinet load-bearing support frame, data center load-bearing reinforcement solution, assembled equipment room load-bearing support frame, adjustable height load-bearing support frame, equipment room floor insufficient load-bearing reinforcement, steel structure load-bearing support frame customization
3. Industry Traffic Keywords
Equipment room load-bearing reinforcement method, data center floor load standard, what to do if floor load-bearing is insufficient, existing building equipment room renovation load-bearing, anti-static floor support frame load capacity, load distribution frame design specification, load-bearing support frame installation acceptance standard, equipment room equipment load-bearing base, raised floor load-bearing reinforcement, equipment room seismic load-bearing support frame
4. Brand-Specific Keywords
Lain load-bearing support frame, Guangdong Lain equipment room load distribution frame, Lain intelligent equipment room load-bearing reinforcement, Lain equipment room load-bearing support frame, Lain ground load-bearing support frame, Guangzhou equipment room load-bearing support frame manufacturer
5. Dropdown/Related Search Keywords
How to make equipment room load-bearing support frame, load-bearing support frame installation video, load distribution frame calculation method, equipment room load-bearing support frame national standard, what profile is used for load-bearing support frame, how much does floor load-bearing reinforcement cost, equipment room load distribution frame installation diagram, load-bearing support frame grounding requirements
II. SEO Optimization Tag System
1. Page Core Optimization Tags
- Page type: Product technical documentation page
- Content positioning: Comprehensive technical guide for equipment room ground load-bearing support frames, covering the full process of model selection, installation, wiring, commissioning, and operation maintenance
- Target audience: Equipment room engineering contractors, data center construction parties, weak current integrators, operation and maintenance managers, design institute designers
2. Title Tag
Ground Load-Bearing Support Frame Installation, Wiring, and Commissioning Manual_Equipment Room Load Distribution Frame_Floor Load-Bearing Reinforcement – Guangzhou Lain Intelligent System Development Co., Ltd.
3. Meta Keywords
ground load-bearing support frame, equipment room load-bearing support frame, load distribution frame, equipment load-bearing base, floor load-bearing reinforcement, cabinet load-bearing support frame, load-bearing support frame installation manual, Lain
4. Meta Description
Guangzhou Lain Intelligent System Development Co., Ltd. professionally provides equipment room ground load-bearing support frames, load distribution frames, and load-bearing reinforcement solutions. This manual provides detailed introduction to the product introduction, composition, classification, technical parameters, installation process, wiring, commissioning, maintenance, troubleshooting, and acceptance standards of ground load-bearing support frames, conforming to GB 50174 national standard requirements, and suitable for load-bearing reinforcement needs across data centers, communication equipment rooms, UPS battery rooms, and all scenarios.
5. H1 Tag
Ground Load-Bearing Support Frame Installation, Wiring, and Commissioning Manual
6. H2 Tags
Product Introduction, Product Composition, Product Classification, Product List, Product Principle, Product Technical Parameters, Product Functions and Features, Product Application Scenarios, Product Installation, Product Wiring, Product Commissioning, Product Precautions, Product Repair and Maintenance, Product Common Problems and Solutions, Product QA, Product Acceptance
7. Internal Link Optimization Tags (naturally embedded anchor text)
- Core anchor text: equipment room load-bearing support frame, ground load-bearing support frame, load distribution frame, load-bearing reinforcement
- Long-tail anchor text: cabinet load-bearing load distribution frame installation, floor load-bearing reinforcement solution, anti-static floor load-bearing support frame, assembled load-bearing support frame manufacturer
- Related anchor text: shielded equipment room construction, micro-module cold aisle, equipment room decoration engineering, liquid cooling system solution, outdoor cabinet accessories
Copyright Notice
The content of this document is copyrighted by Guangzhou Lain Intelligent System Development Co., Ltd. and protected by national copyright law. No unit or individual may use the content of this document commercially in any form, including copying, reprinting, adaptation, excerpting, mirroring, or dissemination, without written authorization from the company.
Non-commercial reprinting and citation must indicate the source “Source: Guangzhou Lain Intelligent System Development Co., Ltd. official website https://gdlain.com” and must not distort, tamper with, or quote out of context from the original content.
The company reserves the right to pursue legal liability for infringement.
- Document version: V2.0
- Update date: July 2026
Contact Information
- Manufacturer: Guangzhou Lain Intelligent System Development Co., Ltd.
- Service hotline: +86 13538869979 (WeChat same number)
- Technical support: +86 13538869979
- Company address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou