Installation and Commissioning Manual for Industrial Special Explosion-Proof Containers

Table of Contents

Preface

This manual is developed for the full lifecycle of industrial special containers — specifically explosion-proof containers — covering installation, commissioning, acceptance inspection, and operation maintenance. It strictly complies with national explosion-proof electrical standards, container structural design specifications, and on-site construction safety regulations. It is applicable to the full range of explosion-proof container products manufactured by Guangzhou Lain Intelligent System Development Co., Ltd., including flameproof (d), increased safety (e), intrinsic safety (i), pressurized (p), and hybrid/composite explosion-proof container types.

As core industrial special equipment for high-risk explosion-proof scenarios, explosion-proof containers are widely used in petrochemical, oil and gas fields, mining, pharmaceutical, hazardous goods storage, and new energy storage sectors. The quality of installation and commissioning directly determines explosion-proof performance and operational safety. This manual details operational standards and technical parameters across the entire process — from pre-installation preparation, main structure construction, system commissioning, acceptance and delivery, to operation and maintenance support — providing construction units and end users with standardized, executable guidelines to ensure long-term stable operation after commissioning, meeting the requirements of Zone 0, Zone 1, and Zone 2 hazardous area classifications.

As a professional explosion-proof container manufacturer, Guangzhou Lain Intelligent System Development Co., Ltd. holds complete explosion-proof qualifications and production systems. All products have passed certification by the National Quality Supervision and Inspection Center for Explosion-Proof Electrical Products. We offer full-chain services including customization, OEM manufacturing, confidentiality protection, and ready-stock supply. For technical issues during installation and commissioning, please contact the technical support hotline at +86 13538869979, or service hotline +86 13538869979 (also available via WeChat). Company address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou. Official website: https://gdlain.com.

This manual is a controlled technical document. Unauthorized alteration or lending is strictly prohibited. Installation and commissioning work must be performed exclusively by qualified personnel holding explosion-proof construction certifications. Operation by unqualified personnel is strictly prohibited.

Chapter 1: Explosion-Proof Container Product Definition and Application Fields

1.1 Definition of Industrial Special Containers and Explosion-Proof Containers

Industrial special containers are specialized equipment carriers developed for specific industrial scenarios, distinguished from ordinary freight containers. They feature high structural strength, high functional integration, and strong environmental adaptability, capable of meeting diverse requirements such as equipment integration, personnel operations, material storage, and emergency command. Explosion-proof containers are a core subcategory of industrial special containers, defined as specialized container equipment that achieves explosion-proof performance inside the enclosure through structural design, material selection, and system configuration, enabling safe use in explosive hazardous environments containing flammable gases, vapors, or dusts.

Compared with ordinary containers, the core difference of explosion-proof containers lies in their full-system explosion-proof design: the container structure possesses flameproof and pressure-relief capabilities; all electrical components adopt explosion-proof rated elements; the ventilation system is equipped with flame arresters and explosion-proof treatment devices; and the overall system integrates anti-static, earthing protection, and gas detection interlock safety functions. This effectively isolates internal ignition sources such as electrical sparks and high-temperature surfaces from the external explosive environment, preventing explosion accidents.

Lain explosion-proof containers manufactured by Guangzhou Lain Intelligent System Development Co., Ltd. adopt a modular design philosophy and can be customized according to the customer’s on-site explosion-proof classification, functional requirements, and site conditions. Products range from small explosion-proof junction boxes to large explosion-proof control rooms and explosion-proof analyzer houses, covering all size specifications. The company is a core supplier in the domestic industrial special container sector.

1.2 Core Value and Industry Significance of Explosion-Proof Containers

In high-risk industries such as petroleum, chemical, and mining, explosive environments are prevalent, and conventional equipment and buildings cannot meet safe operation requirements. The core value of explosion-proof containers is reflected in the following dimensions:

Essential Safety Assurance: Through full-system explosion-proof design, ignition sources are eliminated from multiple dimensions including structure, electrical, ventilation, and earthing, significantly reducing the risk of explosion accidents and ensuring the safety of personnel and equipment.

Rapid Deployment Capability: As a prefabricated industrial special container, all production and pre-installation is completed at the factory. On-site work only requires hoisting into position and simple connection before commissioning. This reduces construction time by more than 80% compared with traditional explosion-proof plant buildings, making it particularly suitable for emergency projects and field operation scenarios.

Flexible Relocation and Reuse: With standardized container hoisting and transportation attributes, the unit can be relocated as a whole and reused across projects, significantly reducing secondary construction costs and improving asset utilization.

Strong Environmental Adaptability: Can withstand extreme field environments including high temperature, extreme cold, high humidity, high altitude, and strong sandstorms. The container body features anti-corrosion, waterproof, dustproof, and seismic performance, meeting the requirements of complex working conditions at oilfields, mines, and remote stations.

High Functional Integration: Can integrate multiple functions including power distribution, control, analysis, office, storage, and fire protection, achieving a “one-container-is-one-station” solution, reducing safety hazards and management costs associated with multi-system interface on site.

From an industry development perspective, explosion-proof containers are foundational equipment for safe production in high-risk industries and are the core carrier for implementing the “Safety First, Prevention Foremost” policy. With the standardized development of China’s chemical, energy, and mining industries, as well as upgraded safety requirements in emerging sectors such as new energy storage and hydrogen energy, the market demand for industrial special explosion-proof containers continues to grow, with technology evolving toward intelligent, integrated, and higher explosion-proof classifications.

1.3 Main Application Fields of Explosion-Proof Containers

1.3.1 Petrochemical Industry Applications

Petrochemical production areas contain large quantities of flammable gases such as alkanes and aromatics, making them typical Zone 1 and Zone 2 hazardous areas. Explosion-proof containers are core supporting equipment for chemical industrial parks. Main application scenarios include:

  • Explosion-proof on-site control rooms in production device areas, used for process parameter monitoring and on-site operation;
  • Explosion-proof power distribution rooms, providing explosion-proof power distribution for on-site pumps and instrumentation equipment;
  • Explosion-proof analyzer houses, integrating chromatographs, analyzers, and other precision detection equipment for real-time monitoring of material composition;
  • Explosion-proof spare parts storage cabinets, storing tools and spare parts in flammable and explosive areas.

Lain chemical explosion-proof containers are designed for corrosive chemical environments, using 304/316 stainless steel material or high-grade anti-corrosion coating, with explosion-proof ratings up to Ex d IIB T4/T6, meeting the explosion-proof requirements of most chemical media.

1.3.2 Oil and Gas Field Applications

Oilfield and gas field production sites are located in the field with harsh environments and high risks of crude oil and natural gas leakage, making them typical hazardous areas. Oilfield explosion-proof containers are mainly used for:

  • Explosion-proof electrical control rooms on drilling platforms and production stations, controlling drilling equipment and Christmas tree operation;
  • Explosion-proof metering stations, achieving precise oil and gas production metering and data acquisition;
  • Explosion-proof duty rooms, providing safe rest and office space for field personnel;
  • Explosion-proof material storage rooms, storing wellhead tools, protective equipment, and other materials.

Lain oilfield explosion-proof containers feature sandstorm resistance, low-temperature tolerance, and high-temperature resistance, and are equipped with pressurized explosion-proof systems. They can adapt to desert, Gobi, plateau, and other field environments, and have been widely applied in major domestic oilfield projects.

1.3.3 Mining Underground and Surface Station Applications

Mining environments contain explosive substances such as methane and coal dust, making them high-risk explosion-proof scenarios. Mining explosion-proof containers are mainly used in surface gas drainage stations, mineral processing plants, and areas around explosives warehouses, serving functions including explosion-proof power distribution, explosion-proof monitoring, and explosion-proof duty. Special underground scenarios can adopt mining-specific explosion-proof containers meeting coal safety certification requirements, enabling underground equipment control and personnel refuge.

1.3.4 Pharmaceutical and Fine Chemical Applications

Pharmaceutical and fine chemical production processes use large quantities of organic solvents such as ethanol, acetone, and toluene, creating volatile flammable gas environments. Explosion-proof containers are mainly used as explosion-proof batching rooms, explosion-proof reagent storage cabinets, and explosion-proof central control rooms, meeting both production process requirements and safety production regulations.

1.3.5 Warehousing, Logistics, and Dangerous Goods Transshipment Applications

Dangerous goods warehouses and port hazardous chemical transshipment areas require supporting explosion-proof workspaces. Hazardous goods explosion-proof containers can serve as explosion-proof inspection rooms, explosion-proof temporary storage cabinets, and explosion-proof monitoring rooms, meeting safety control requirements during hazardous chemical loading/unloading, inspection, and storage.

1.3.6 Power and New Energy Storage Applications

With the rapid development of the energy storage industry, explosion-proof safety of electrochemical energy storage power stations has become a core concern. Energy storage explosion-proof containers represent a new application direction for industrial special explosion-proof containers, used to house energy storage battery clusters, PCS (Power Conversion Systems), and power distribution equipment. Through explosion-proof design, gas detection, and fire-fighting interlock systems, they prevent explosion risks caused by battery thermal runaway. Additionally, hydrogen refueling stations widely adopt explosion-proof containers as hydrogen refueling control rooms and equipment compartments.

1.3.7 Military and Special Operations Applications

Scenarios such as military ammunition depots, special test sites, and field combat command require extremely high levels of explosion-proof performance, confidentiality, and mobility. Explosion-proof containers can be customized as explosion-proof command rooms and explosion-proof equipment depots, meeting the safety and confidentiality requirements of military special operations. Guangzhou Lain can provide military-grade confidential customization services, with all production processes strictly managed under confidentiality regulations.

1.4 Market Development and Technology Trends of Explosion-Proof Containers

China’s industrial special explosion-proof container market is currently in a phase of rapid growth, benefiting on one hand from safety renovation and upgrades in traditional chemical and energy industries, and on the other hand from new demand generated by emerging sectors such as new energy storage and hydrogen energy. From a technology development trend perspective, four main directions are emerging:

Higher Explosion-Proof Classification: Upgrading from conventional IIB to IIC classification, and from Zone 2 to Zone 1 or even Zone 0 applicability, meeting more stringent explosion-proof scenarios.

Intelligent Integration: Integrating IoT, edge computing, and remote monitoring technologies to achieve real-time monitoring and remote management of internal container environment, equipment status, and gas concentration, improving intelligent O&M levels.

Green and Energy-Efficient: Adopting high-efficiency explosion-proof air conditioning, waste heat recovery, and photovoltaic supporting technologies to reduce operating energy consumption, in line with dual-carbon development goals.

Modular Customization: Based on standardized container modules, achieving rapid functional combination and customization, shortening delivery cycles, and meeting personalized scenario requirements.

Guangzhou Lain Intelligent System Development Co., Ltd. closely follows industry technology trends, continuously investing in R&D and optimizing explosion-proof container product performance. We provide customers with one-stop services from solution design, manufacturing, installation and commissioning, to after-sales operation and maintenance.

Chapter 2: Explosion-Proof Container Classification and Structural Composition

2.1 Classification by Explosion-Proof Type

According to the GB 3836 series standards, explosion-proof electrical equipment is classified into multiple explosion-proof types. Based on the core explosion-proof principles adopted, explosion-proof containers are mainly classified into the following categories:

2.1.1 Flameproof Explosion-Proof Containers (Type d)

The core principle of flameproof explosion-proof containers is the “flameproof enclosure”: all electrical components that may produce arcs, sparks, or high temperatures are placed within a flameproof cavity. Even if an explosion occurs inside the cavity, the flame is extinguished through the gap of the flameproof joint surfaces, preventing the explosion from propagating to the external explosive environment.

Characteristics of flameproof explosion-proof containers:

  • High explosion-proof rating, usable in Zone 1 and Zone 2 hazardous areas, with some structures meeting edge scenarios of Zone 0;
  • Sturdy structure with strong impact resistance and explosion pressure resistance;
  • Relatively low maintenance requirements and wide adaptability;
  • Heavier container weight and relatively higher manufacturing costs.

Lain flameproof explosion-proof containers achieve explosion-proof ratings up to Ex d IIB T6 Gb / Ex tD A21 IP65 T80°C, simultaneously meeting both gas and dust explosion-proof requirements.

2.1.2 Increased Safety Explosion-Proof Containers (Type e)

The core principle of increased safety explosion-proof containers is “enhanced safety”: based on the premise that no arcs, sparks, or dangerous high temperatures are produced under normal operating conditions, the safety margin of equipment is further improved through measures such as upgrading insulation ratings, increasing electrical clearances, and optimizing heat dissipation design, preventing ignition sources under normal operation or foreseeable overload conditions.

Characteristics of increased safety explosion-proof containers:

  • Moderate explosion-proof rating, mainly used in Zone 2 hazardous areas, with some applicable to auxiliary equipment in Zone 1;
  • Relatively lightweight structure with lower cost than flameproof type;
  • Suitable for lighting, power distribution, terminal connection, and other equipment scenarios without obvious spark generation;
  • Higher requirements for cleanliness and tightening quality during installation and maintenance.

2.1.3 Intrinsic Safety Explosion-Proof Containers (Type i)

Intrinsic safety (intrinsically safe) type is based on the principle of limiting circuit energy so that electrical sparks and thermal effects produced under normal operation or specified fault conditions cannot ignite the corresponding explosive environment. All electrical circuits inside intrinsic safety explosion-proof containers are intrinsically safe circuits, making this one of the safest explosion-proof types.

Characteristics of intrinsic safety explosion-proof containers:

  • Highest safety rating, applicable to all zones: Zone 0, Zone 1, and Zone 2;
  • Small size and light weight, suitable for low-power scenarios such as detection instruments and communication equipment;
  • Can be maintained while energized, providing convenient O&M;
  • Only applicable to low-power equipment; cannot carry high-power distribution and power equipment.

2.1.4 Pressurized Explosion-Proof Containers (Type p)

The core principle of pressurized explosion-proof containers is “protective gas pressurization”: clean air or inert gas is introduced into the container to maintain internal pressure higher than the external environmental pressure, preventing external explosive gases from entering the container, thereby achieving explosion-proof protection.

Characteristics of pressurized explosion-proof containers:

  • Large explosion-proof space, suitable for large explosion-proof control rooms and analyzer houses;
  • Ordinary non-explosion-proof equipment can be installed inside, significantly reducing equipment costs;
  • Requires continuous gas supply and pressure monitoring, with a relatively complex system;
  • Requires purging before startup and stable positive pressure maintenance during operation.

Lain pressurized explosion-proof containers are equipped with fully automatic positive pressure control systems featuring under-pressure alarm, under-pressure interlock power-off, and automatic gas replenishment functions. The positive pressure value is stably maintained at 50–200 Pa, meeting the requirements of GB 3836.5.

2.1.5 Composite/Hybrid Explosion-Proof Containers

Composite explosion-proof containers adopt two or more explosion-proof types simultaneously. For example, the main container body uses pressurized type, local power circuits use flameproof type, and detection instruments use intrinsic safety type. Composite design balances explosion-proof performance, equipment compatibility, and cost control, and is currently the mainstream design approach for large industrial special explosion-proof containers.

2.2 Classification by Function and Purpose

2.2.1 Explosion-Proof Control Room Containers

Explosion-proof control room containers, also known as explosion-proof central control rooms, are primarily used for production monitoring and operational control within hazardous areas. They integrate industrial computers, displays, operator consoles, and communication equipment, supported by explosion-proof air conditioning, positive pressure systems, and lighting systems, providing a safe working environment for operators.

2.2.2 Explosion-Proof Power Distribution Containers

Explosion-proof power distribution containers are specifically designed for power distribution in hazardous areas. They house explosion-proof distribution cabinets, transformers, UPS power supplies, and other equipment, achieving power distribution, protection, and monitoring. They serve as core power nodes in chemical plants and oilfields.

2.2.3 Explosion-Proof Analyzer House Containers

Explosion-proof analyzer houses integrate online analysis instruments, sample pretreatment systems, carrier gas systems, and data acquisition systems for real-time online analysis of material composition during chemical and refining processes. They are key equipment for production process quality control. Analyzer houses have extremely high requirements for temperature and humidity stability, explosion-proof sealing, and vibration control.

2.2.4 Explosion-Proof Storage Containers

Explosion-proof storage containers are used to store tools, spare parts, reagents, and small equipment within explosive hazardous areas. They feature explosion-proof, fire-resistant, and anti-static functions, with some configured with explosion-proof shelving and explosion-proof ventilation systems.

2.2.5 Explosion-Proof Office Containers

Explosion-proof office containers provide office, duty, and rest space for field hazardous stations, equipped with office furniture, lighting, air conditioning, and communication facilities, balancing explosion-proof performance with personnel comfort.

2.2.6 Explosion-Proof Emergency Rescue Containers

Explosion-proof emergency rescue containers are equipped with emergency supplies, rescue equipment, and communication command systems. They can be rapidly deployed to accident sites as emergency command and rescue material support bases.

2.3 Main Structural Composition of Explosion-Proof Containers

A complete industrial special explosion-proof container consists of seven core systems that work together to ensure explosion-proof performance and functional realization.

2.3.1 Explosion-Proof Container Body Structure

The container body is the main load-bearing structure and the fundamental carrier of explosion-proof performance. Lain explosion-proof container bodies are manufactured from high-quality carbon structural steel or stainless steel plates, formed through bending, welding, and shaping. Main components include:

  • Main Frame: Formed from welded structural steel sections, providing high strength and rigidity to meet the mechanical requirements of hoisting, stacking, and transportation;
  • Wall Panels: Sandwich structure with outer steel plate and inner fire-resistant insulation layer, combining structural strength, thermal insulation, and fire resistance;
  • Roof and Floor: Roof features a sloped design to prevent water accumulation; floor uses checkered steel plate or anti-static flooring; bottom is configured with channel steel base beams for forklift handling and foundation fixing;
  • Flameproof Joint Surfaces: Door and cover plate joint surfaces of flameproof containers are machined to flameproof standards, with controlled flatness, gap, and width parameters to ensure flameproof performance;
  • Anti-Corrosion Treatment: Container surface undergoes multi-layer treatment including sandblasting/derusting, zinc-rich primer, intermediate coat, and fluorocarbon topcoat, with anti-corrosion life exceeding 15 years. 316 stainless steel material can be customized for coastal and high-corrosion areas.

2.3.2 Explosion-Proof Door and Window Systems

Explosion-proof doors and windows are passages for personnel and equipment access and represent potential weak points in explosion-proof sealing. They must meet the corresponding explosion-proof classification requirements.

  • Explosion-Proof Doors: Available in swing and sliding types, constructed with steel plate reinforced structure, equipped with explosion-proof sealing strips, explosion-proof locks, and door closers. Flameproof type doors also require machined flameproof joint surfaces;
  • Explosion-Proof Windows: Multi-layer composite explosion-proof glass with steel window frames, connected to the container body by welding or bolted sealed connections, capable of withstanding explosion impact without shattering or flying fragments;
  • Sealing System: Oil-resistant, aging-resistant, flame-retardant explosion-proof sealing strips ensure air tightness when doors and windows are closed.

2.3.3 Explosion-Proof Ventilation and Air Conditioning Systems

The ventilation and air conditioning system maintains the temperature, humidity, and air quality inside the container while meeting explosion-proof requirements, preventing it from becoming a pathway for explosion propagation.

  • Ventilation System: Composed of explosion-proof fans, ductwork, flame arresters, air filters, and pressure relief devices, achieving fresh air supply and exhaust air discharge. Both inlet and outlet are equipped with explosion-proof flame arresters to prevent flame propagation;
  • Explosion-Proof Air Conditioning: Uses fully explosion-proof certified air conditioning units with explosion-proof treated compressors, fans, and electrical controls, providing cooling, heating, and dehumidification functions;
  • Positive Pressure System: Dedicated system for pressurized explosion-proof containers, composed of positive pressure fans, pressure sensors, control units, and pressure relief valves, maintaining stable positive pressure inside the container.

2.3.4 Explosion-Proof Electrical System

The electrical system is the core functional system of the explosion-proof container and a key focus of explosion-proof control. All components must possess the corresponding explosion-proof ratings.

  • Power Distribution Units: Explosion-proof distribution boxes, explosion-proof circuit breakers, explosion-proof terminal blocks;
  • Cable Systems: Explosion-proof cables, explosion-proof conduit, explosion-proof junction boxes, explosion-proof cable glands;
  • Control Units: Explosion-proof PLCs, explosion-proof push buttons, explosion-proof switches, explosion-proof indicator lights;
  • Earthing System: Main earthing busbar, equipotential bonding terminals, earthing down conductors.

2.3.5 Explosion-Proof Earthing and Anti-Static System

The earthing and anti-static system is the fundamental defense line for eliminating static charges and ensuring electrical safety, extending throughout the entire container.

  • Main Earthing Network: Container body connected to the on-site earthing network, forming the main earthing circuit;
  • Equipotential Bonding: All metal components, equipment enclosures, and piping inside the container undergo equipotential bonding to eliminate potential differences;
  • Anti-Static Flooring: Anti-static flooring or anti-static floor coating is used, with surface resistance controlled within specification limits;
  • Static Discharge Device: Human body static discharge devices are installed at entrances to eliminate static charges carried by personnel.

2.3.6 Explosion-Proof Lighting and Communication Systems

  • Lighting System: All explosion-proof LED luminaires, equipped with emergency lighting power supplies, meeting both normal illumination and emergency evacuation lighting requirements;
  • Communication System: Explosion-proof telephones, explosion-proof switches, explosion-proof wireless APs, and explosion-proof broadcasting systems, enabling communication and data transmission both inside and outside the container.

2.3.7 Fire Protection and Gas Detection Systems

Safety monitoring and fire protection systems are proactive safety safeguards for explosion-proof containers.

  • Gas Detection System: Combustible gas detectors, toxic gas detectors, and alarm controllers that monitor gas concentrations inside the container in real time. When concentrations exceed limits, audible and visual alarms activate with interlocked exhaust and power-off functions;
  • Fire Protection System: Gas fire extinguishing devices, dry powder fire extinguishers, and emergency evacuation signage for rapid initial fire response;
  • Audible and Visual Alarm System: Explosion-proof audible and visual alarm devices providing both visual and audible alarm signals.

Chapter 3: Applicable Standards and Regulatory Basis

The design, production, installation, commissioning, and acceptance inspection of this explosion-proof container strictly comply with current national, industry, and enterprise standards. The main standards are as follows:

3.1 National Explosion-Proof Electrical Standard System

Standard Number Standard Title
GB 3836.1-2010 Explosive atmospheres – Part 1: Equipment – General requirements
GB 3836.2-2010 Explosive atmospheres – Part 2: Equipment protected by flameproof enclosures “d”
GB 3836.3-2010 Explosive atmospheres – Part 3: Equipment protected by increased safety “e”
GB 3836.4-2010 Explosive atmospheres – Part 4: Equipment protected by intrinsic safety “i”
GB 3836.5-2017 Explosive atmospheres – Part 5: Equipment protected by pressurized enclosures “p”
GB 3836.9-2014 Explosive atmospheres – Part 9: Equipment protected by encapsulation “m”
GB 12476.1-2013 Electrical apparatus for use in the presence of combustible dust – Part 1: General requirements
GB 50058-2014 Code for design of electrical installations in explosive atmospheres
GB 3836.15-2017 Explosive atmospheres – Part 15: Inspection and maintenance of electrical installations

3.2 Container Structural Design Standards

Standard Number Standard Title
GB/T 1413-2008 Series 1 freight containers – Classification, dimensions and ratings
GB/T 17770-1999 Freight containers – Air/surface (intermodal) general purpose containers – Specification and tests
GB 50017-2017 Standard for design of steel structures
GB 50205-2020 Standard for acceptance of construction quality of steel structures
GB/T 18290.2-2000 Solderless connections – Part 2: Crimped connections – Special requirements

3.3 Installation, Construction, and Acceptance Specifications

Standard Number Standard Title
GB 50303-2015 Code for acceptance of construction quality of building electrical engineering
GB 50243-2016 Code for acceptance of construction quality of ventilation and air conditioning works
GB 50166-2019 Code for construction and acceptance of fire alarm system
GB 50235-2010 Code for construction of industrial metallic piping engineering
AQ 3009-2007 Safety code for electrical installations in hazardous locations
SH/T 3526-2015 Construction and acceptance specification for explosion-proof electrical equipment in petrochemical industry

3.4 Safety Protection and Occupational Health Standards

Standard Number Standard Title
GB 50016-2014 (2018 Edition) Code for fire protection design of buildings
GB 12158-2006 General guideline for preventing electrostatic accidents
GB 50034-2013 Standard for architectural lighting design
GBZ 1-2010 Hygienic standards for the design of industrial enterprises
JGJ 59-2011 Standard for construction safety inspection

3.5 Guangzhou Lain Enterprise Standards and Technical Specifications

Based on national standards, Guangzhou Lain Intelligent System Development Co., Ltd. has established stricter internal enterprise control standards, including the “Explosion-Proof Container Production and Manufacturing Specification,” “Explosion-Proof Container Installation and Commissioning Operating Instructions,” and “Explosion-Proof Container Inspection and Acceptance Procedures,” ensuring product performance and installation quality exceed industry standards. All ex-factory products undergo complete in-house testing and are supplied with a full set of qualification documents, including explosion-proof certificates, factory inspection reports, and product certificates of conformity.

Chapter 4: Delivery Acceptance and Storage Management

4.1 Pre-Delivery Preparation

Explosion-proof containers are large industrial special equipment. Adequate preparation must be completed before delivery to ensure orderly unloading, acceptance inspection, and storage.

  • Confirm delivery information: Confirm delivery quantities, arrival time, transport vehicle dimensions, and container weight with the manufacturer in advance. Coordinate unloading equipment and personnel.
  • Site preparation: Clear the unloading area, ensuring the ground is solid and level, meeting the traffic and operation requirements of cranes and trucks. Plan temporary storage locations, avoiding blockage of fire lanes and construction access routes.
  • Personnel organization: Arrange delivery acceptance leaders, construction contractor representatives, and supervision representatives to jointly participate in acceptance, with clear responsibilities for each position.
  • Tools and documentation preparation: Prepare cranes, forklifts, tape measures, levels, unpacking tools, and acceptance record forms. Review the contract technical agreement and packing list in advance.

4.2 Delivery Unpacking and Acceptance Procedure

Delivery acceptance is the first checkpoint for quality control and must be strictly executed according to procedure. Acceptance records must be retained, and any issues found must be promptly reported to the manufacturer for resolution.

4.2.1 Visual Inspection

Before unloading, check whether the transport vehicle’s container shows any tilting, collision marks, or whether the seals are intact. If any abnormalities are found, take photos, record them, and contact logistics and the manufacturer.

After the container is unloaded, conduct a comprehensive visual inspection of the explosion-proof container exterior:

  • Check whether the container steel plates have dents, deformation, scratches, or rust;
  • Check whether explosion-proof doors and windows have damage or deformation, and whether sealing strips have detached;
  • Check whether lifting lugs and bottom beams show weld cracking or deformation;
  • Check whether container markings and explosion-proof labels are clear and complete;
  • Check whether the sealing of air inlet/outlet vents and cable entry points is intact, with no signs of water or dust ingress;
  • Check whether accessory packaging boxes are damaged or water-soaked, and verify the quantity of packaging boxes against the packing list.

4.2.2 Accessories and Documentation Inventory Check

Open accessory packaging boxes and check items one by one against the packing list, including:

  • Random accessories: Spare explosion-proof luminaires, spare sealing strips, special tools, fasteners, earthing terminals, etc.;
  • Separately shipped equipment: Explosion-proof fans, explosion-proof air conditioners, distribution boxes, gas detectors, and other components shipped separately;
  • Installation consumables: Explosion-proof sealant, explosion-proof packing material, spare cable glands, etc.

Check the appearance of each component for damage or deformation, and verify that specifications and models match the contract.

Inventory technical documentation. The following documents must be included:

  • Product certificate of conformity;
  • Explosion-proof certificate (including duplicate);
  • Factory inspection report;
  • Installation and operation manual;
  • Explosion-proof certificates and manuals for major components;
  • Packing list;
  • Foundation construction drawings, electrical schematic diagrams, wiring diagrams.

Record all findings during the inventory check. Missing, incorrect, or damaged items must be documented in detail, signed by all participating parties, and reported to the manufacturer for replacement or replenishment.

4.2.3 Verification of Explosion-Proof Certificates and Qualification Documents

Explosion-proof qualifications are the core compliance documents for explosion-proof containers and must be strictly verified:

  • Verify that the explosion-proof certificate number, product model, explosion-proof rating, and manufacturer information match the product nameplate;
  • Verify that the explosion-proof certificate is within its validity period and that the issuing authority possesses nationally recognized explosion-proof inspection qualifications;
  • Verify the explosion-proof certificates of major electrical components, ensuring all explosion-proof components have valid qualifications and that their explosion-proof ratings are not lower than the overall container explosion-proof rating;
  • Retain copies of all qualification documents as completion documentation and for safety supervision inspection purposes.

4.2.4 Acceptance Exception Handling Procedure

  • Minor appearance scratches or small defects that do not affect explosion-proof performance may be recorded and repaired on-site by the manufacturer;
  • For serious issues affecting explosion-proof performance — such as structural deformation, damage to flameproof surfaces, or missing/damaged core components — immediately halt acceptance, seal the product, take photographic evidence, issue a written acceptance objection, and contact the manufacturer to negotiate return/replacement or on-site rework solutions;
  • All abnormal situations must be documented in writing, signed by all parties involved in acceptance, and serve as the basis for subsequent processing.

4.3 On-Site Temporary Storage Requirements

If the explosion-proof container cannot be installed immediately upon delivery, it must be properly stored to prevent performance degradation due to improper storage.

4.3.1 Storage Environment Requirements

  • The storage site should be level, solid, dry, and well-drained, avoiding water accumulation that could soak the container bottom;
  • Indoor warehouse storage is preferred. For outdoor storage, cover with rainproof tarpaulin and raise the bottom with wooden sleepers no less than 200 mm to prevent ground water corrosion;
  • The storage area should be away from corrosive gases, dust sources, high-temperature heat sources, and open flames;
  • Operations such as sandblasting and welding that may damage the container are prohibited in the surrounding storage area.

4.3.2 Stacking and Protection Requirements

  • Explosion-proof containers should generally be stored in a single layer. If stacking is required, it must comply with container stacking strength requirements. Stacking height should not exceed 2 layers, with cushioning pads placed between layers;
  • Close all doors, windows, and ventilation openings, and seal cable entries to prevent rain, dust, and insects from entering the container;
  • For precision instruments and electrical equipment requiring long-term storage inside the container, place desiccant and regularly check for moisture;
  • Protect flameproof joint surfaces and sealing strips from impacts, scratches, oil contamination, and corrosive substances.

4.3.3 Inspection and Maintenance During Storage

  • Conduct inspections at least once per week, checking whether rainproof measures are intact and whether the container body shows rust or water ingress indications;
  • Inspect electrical equipment inside the container once per month, measuring insulation resistance. If moisture is found, perform drying treatment promptly;
  • For storage exceeding 6 months, inspect the container anti-corrosion coating and touch up paint on damaged areas; inspect sealing strips for aging and replace as needed;
  • Maintain storage inspection records and conduct a comprehensive re-inspection before installation.

Chapter 5: Installation Site Survey and Foundation Construction

5.1 Core Contents of Site Survey

A detailed site survey must be conducted before installing the explosion-proof container to understand site conditions, identify potential safety hazards, and provide a basis for foundation design, hoisting construction, and system interconnection. The survey shall be organized by the construction unit’s technical leader, with participation from the owner and supervision representatives. Manufacturer technical personnel should be present for guidance when necessary.

5.1.1 Site Terrain and Geological Condition Survey

  • Measure the elevation and dimensions of the installation site, confirm site flatness. Leveling work is required when the slope exceeds 5‰;
  • Survey geological conditions to determine soil bearing capacity. Concrete foundations must be placed on undisturbed soil. Soft soil layers require replacement and compaction treatment;
  • Identify the distribution of underground pipelines, cables, and utility trenches to avoid damaging underground facilities during foundation construction;
  • Confirm the surrounding drainage system to ensure no water accumulation around the foundation during rainy season, preventing foundation settlement.

5.1.2 Surrounding Environment and Hazardous Area Classification Confirmation

  • Confirm the hazardous area classification (Zone 0/Zone 1/Zone 2), gas group, and temperature class of the installation location, and verify that the explosion-proof rating of the container matches the site requirements;
  • Survey the locations of release sources and prevailing wind direction. The explosion-proof container should preferably be located upwind or crosswind of release sources to reduce the risk of explosive gas accumulation;
  • Confirm safe distances from surrounding buildings and structures, complying with fire protection and explosion-proof spacing requirements;
  • Check for strong vibration sources and strong electromagnetic interference sources in the vicinity that could affect precision equipment inside the container.

5.1.3 Utility Supply Condition Survey

  • Confirm the voltage level, capacity, and access point location of the on-site power supply, and calculate cable length and specifications;
  • Confirm the earthing network location and earthing resistance. The container’s main earthing point must be reliably connected to the plant’s main earthing network;
  • If water supply connection is required (for air conditioning condensate discharge, cleaning water), confirm the drainage connection point location and elevation;
  • Confirm communication, network, and fire alarm signal access points.

5.1.4 Hoisting and Transport Access Survey

  • Measure the width, height, and turning radius of the transport route from the unloading point to the installation point, confirming the container can pass through smoothly;
  • Check the ground bearing capacity of the access route to determine whether it can support crane and flatbed truck traffic. Weak road sections require steel plate reinforcement;
  • Confirm the crane working space at the installation point, checking whether the crane outrigger deployment area and boom rotation range are free of obstacles such as overhead power lines and pipelines;
  • Calculate the crane tonnage based on container weight and working radius to ensure safe hoisting.

5.2 Foundation Design and Construction Requirements

The foundation is the basis for stable operation of the explosion-proof container and must meet multiple requirements including bearing capacity, flatness, earthing, and waterproofing. Construction must be strictly performed per design drawings.

5.2.1 Concrete Foundation Design Specifications

  • Foundation type: Reinforced concrete strip foundation or integral raft foundation is generally adopted. Point-type foundations may be used for small containers. The specific type is determined by container size, weight, and geological conditions.
  • Bearing capacity requirements: The foundation soil bearing capacity characteristic value shall be no less than 120 kPa. Foundation concrete strength grade shall be no less than C30. Steel reinforcement shall be HRB400 grade.
  • Dimension requirements: The foundation plane dimensions shall extend no less than 100 mm beyond the container bottom beam on each side. The foundation top surface shall be no less than 150 mm above the outdoor ground level to prevent rainwater ingress. Foundation thickness shall be no less than 200 mm, with thickened foundations for heavy equipment containers.
  • Settlement requirements: Uniform settlement of the foundation shall not exceed 20 mm, and differential settlement shall not exceed 10 mm, preventing container deformation that could affect explosion-proof sealing performance.
  • Waterproofing requirements: The foundation top surface shall have a drainage slope of 1%–2%, with drainage channels around the perimeter. Waterproof sleeves shall be embedded in the foundation, and waterproof sealing shall be applied where cables pass through.

5.2.2 Foundation Leveling and Embedded Parts Installation

  • Before concrete pouring, embed anchor bolts or embedded steel plates according to the bolt hole positions of the container bottom beam. The positional deviation of embedded parts shall not exceed 5 mm;
  • Monitor the position of embedded parts throughout the concrete pouring process to prevent displacement during vibration;
  • Use a level instrument to level the foundation top surface, with flatness error not exceeding 2 mm per meter and 5 mm overall;
  • Perform surface finishing after initial concrete set, and water curing after final set. The curing period shall not be less than 7 days. Anti-freezing measures are required for winter construction;
  • Container installation may only proceed after the foundation strength reaches 75% or more of the design strength.

5.2.3 Foundation Earthing Network Construction

  • Lay the earthing network simultaneously with foundation construction. Earthing electrodes shall be galvanized angle steel or galvanized steel pipe, with vertical electrode length no less than 2.5 m and spacing no less than 5 m;
  • Earthing busbars shall be galvanized flat steel with welded connections, and weld points shall receive anti-corrosion treatment;
  • Reserve no less than 2 earthing outgoing terminals at positions corresponding to the container’s main earthing points, with clear identification of outgoing terminals;
  • Measure the earthing resistance after earthing network construction. The protective earthing resistance for electrical equipment in hazardous areas shall not exceed 4 Ω, and anti-static earthing resistance shall not exceed 100 Ω. If requirements are not met, additional earthing electrodes or resistance-reducing agents shall be added.

5.2.4 Foundation Acceptance Standards and Testing Methods

After foundation construction, organize a dedicated acceptance inspection covering:

  • Visual inspection: Foundation surface free of honeycombing, pitting, cracks, exposed reinforcement, with complete edges and corners;
  • Dimension verification: Verify foundation external dimensions, elevation, and embedded part positional deviations, conforming to design requirements;
  • Flatness testing: Use a 2 m straightedge and feeler gauge to test surface flatness, with deviation not exceeding 3 mm;
  • Strength testing: Review concrete test cube strength reports or perform on-site rebound testing to confirm strength compliance;
  • Earthing resistance testing: Use an earth resistance tester to measure earthing resistance, ensuring compliance with specification requirements;
  • After acceptance passes, fill in the foundation acceptance record before proceeding to the next process step.

5.3 On-Site Construction Condition Preparation

5.3.1 Construction Utility Arrangement

  • Construction power shall be drawn from the on-site temporary distribution box, equipped with residual current circuit breakers, implementing a “three-level distribution, two-level protection” system;
  • Construction power in hazardous areas must use explosion-proof temporary distribution boxes and cables. The use of non-explosion-proof electrical equipment is strictly prohibited;
  • Construction water shall be routed to near the work area, meeting the requirements for concrete curing, cleaning, and fire-fighting;
  • Temporary utilities and pipelines shall be arranged neatly, not obstructing hoisting or construction operations, with anti-crushing and anti-damage protection.

5.3.2 Construction Tools and Materials Preparation

  • Prepare all hoisting equipment, installation tools, and testing instruments per the installation plan. Check their performance and condition before site entry to ensure they are intact and functional;
  • Measuring instruments must be within their calibration validity period and bear qualified identification labels;
  • Installation consumables such as bolts, sealants, earthing cables, and explosion-proof packing materials shall be prepared in sufficient quantities, with specifications and models conforming to design requirements;
  • All construction tools and materials shall be sorted and stored neatly with identification labels. Outdoor storage requires rain and moisture protection.

5.3.3 Construction Personnel Qualifications and Safety Training

  • The project manager, technical leader, and safety officer must possess the corresponding qualifications and construction experience;
  • Special operations personnel including electricians, welders, and riggers must hold valid certificates within their validity period;
  • Personnel working in hazardous areas must undergo explosion-proof safety training, master the safety regulations for working in hazardous areas, and pass assessments before entering the site;
  • Technical and safety briefings must be conducted before construction, covering construction procedures, technical standards, safety risks, and prevention and control measures.

5.3.4 On-Site Safety Protection Facility Arrangement

  • Set up warning lines and safety signs around the construction area, prohibiting unrelated personnel from entering;
  • Erect scaffolding or operating platforms for work at heights, equipped with safety harness anchorage points;
  • Configure sufficient fire-fighting equipment. Water-based fire extinguishers are strictly prohibited in hazardous areas; dry powder or gas fire extinguishers shall be configured;
  • Set up emergency access routes, keep them unobstructed, and post emergency evacuation signs;
  • For hot work operations, apply for hot work permits in advance, implement fire prevention measures, and arrange fire watch personnel.

Chapter 6: Installation Tools and Consumables Preparation

6.1 Hoisting Equipment Selection and Inspection

Explosion-proof container hoisting is a large equipment lifting operation. Equipment selection must be rational and condition inspection strict to ensure hoisting safety.

  • Truck crane selection: Select crane tonnage based on container weight (typically 8–15 tonnes for 20-foot explosion-proof containers, 15–25 tonnes for 40-foot units), working radius, and hoisting height, with a safety factor reserve of no less than 1.2 times;
  • Sling selection: Use high-strength polyester lifting slings or wire ropes with a rated load of no less than 2 times the container weight. Lifting slings are preferred to avoid damaging the container paint finish;
  • Shackle selection: Use D-type shackles with rated loads matched to the slings;
  • Site inspection:
  • Verify the crane’s vehicle registration, annual inspection report, and operator certificates are complete and valid;
  • Inspect the crane’s hydraulic system, braking system, and limit devices for proper operation;
  • Inspect lifting slings and wire ropes for broken wires, wear, corrosion, and aging. Defective equipment is strictly prohibited from use;
  • Inspect shackles for cracks, deformation, and excessive pin wear.

6.2 Installation Special Tool List

6.2.1 Mechanical Installation Tools

  • Torque wrenches (socket type, preset type), standard wrenches, socket sets
  • Levels, theodolites, steel tape measures, feeler gauges, plumb bobs
  • Chain hoists, jacks, crowbars
  • Angle grinders, hand drills, impact drills
  • Welding machines, gas cutting equipment (for use outside hazardous areas)
  • Rust removal tools, paint brushes

6.2.2 Electrical Installation Tools

  • Wire strippers, crimping tools, cable cutters, electrician’s knives
  • Multimeters, clamp meters, insulation resistance testers (megohmmeters)
  • Soldering irons, heat guns
  • Conduit benders, pipe threading machines
  • Voltage testers, discharge rods

6.2.3 Explosion-Proof Special Tools

  • Explosion-proof wrenches, explosion-proof screwdrivers, explosion-proof hammers, and other copper-alloy non-sparking tools
  • Explosion-proof temporary lighting fixtures
  • Explosion-proof packing material compression installation tools
  • Special grinding tools for flameproof joint surfaces
  • Combustible gas detectors (for explosion testing before construction)

6.2.4 Testing Instruments and Gauges

  • Earth resistance testers
  • Insulation resistance testers
  • Digital multimeters
  • Anemometers, micromanometers (for positive pressure system commissioning)
  • Temperature and humidity meters
  • Sound level meters
  • Gas leak detectors

6.3 Installation Consumables Specifications and Selection

6.3.1 Sealing and Explosion-Proof Packing Materials

  • Explosion-proof sealant: Silicone or polyurethane type explosion-proof sealant with flame-retardant, aging-resistant, and insulating properties, used for container body gaps and cable entry sealing;
  • Explosion-proof packing material: Epoxy resin or polyester type explosion-proof packing material, used for filling and sealing inside explosion-proof junction boxes and cable entry devices;
  • Sealing strips: EPDM or neoprene flame-retardant sealing strips for door and window sealing, with Shore hardness and compression set conforming to standards;
  • Fire-stop putty: Organic fire-stop putty for fire sealing of cable wall penetration openings.

6.3.2 Fasteners and Connecting Components

  • Anchor bolts and connecting bolts shall be grade 8.8 high-strength galvanized bolts, supplied with flat washers, spring washers, and nuts;
  • Stainless steel containers shall use 304 stainless steel bolts to avoid galvanic corrosion;
  • Earthing connections shall use galvanized bolts with spring washers and flat washers to ensure reliable contact.

6.3.3 Earthing and Cable Materials

  • Earthing busbar: 40×4 mm galvanized flat steel; earthing down conductors: no less than 16 mm² stranded copper conductor with yellow-green insulation;
  • Equipotential bonding conductors: no less than 6 mm² stranded copper conductor;
  • Power cables: flame-retardant armored explosion-proof cables; control cables: shielded flame-retardant cables, with specifications conforming to design requirements;
  • Explosion-proof conduit: galvanized steel conduit or explosion-proof flexible conduit, with diameters matched to cable quantities.

6.3.4 Sealants and Fire Protection Materials

  • Anti-corrosion primer and topcoat for touch-up painting of installation welds and damaged areas;
  • Anti-rust grease for bolts and metal connecting surfaces;
  • Fire-stop pillows and fire barrier boards for fire sealing of cable shafts and openings;
  • Anti-static floor coating or conductive adhesive for floor anti-static treatment.

Chapter 7: Construction Organization and Safety Management

Note: This section is continued in Part 2 of the manual.

Chapter 7 Installation Construction Organization

7.1 Installation Construction Organizational Structure

To ensure the orderly development of explosion-proof container installation and commissioning work, a project construction organization system is established with clearly defined responsibilities for each position:

  • Project Manager: Overall responsibility for project schedule, quality, safety, and cost management; coordinates relationships between all parties.
  • Technical Director: Responsible for construction plan preparation, technical disclosure, technical problem resolution, and quality acceptance.
  • Safety Officer: Responsible for on-site safety management, safety inspections, hazard rectification, and safety education.
  • Construction Crew Leader: Responsible for on-site work organization, leading the crew to construct according to the plan.
  • Hoisting Operation Crew: Responsible for lifting operations, including crane operator, signal commander, and rigger.
  • Mechanical Installation Crew: Responsible for container positioning, structural component installation, door and window installation.
  • Electrical Installation Crew: Responsible for electrical system, grounding system, and communication system installation and commissioning.
  • Ventilation and Air Conditioning Crew: Responsible for ventilation, air conditioning, and positive pressure system installation and commissioning.
  • Manufacturer Technical Guidance: Guangzhou Lain dispatches on-site technical personnel to provide technical support and guide key processes.

7.2 Construction Schedule Preparation

Based on the overall project duration requirements, a detailed construction schedule is prepared, specifying the start and end times and responsible persons for each process. An example is as follows (using a standard 20-foot explosion-proof container as an example):

No. Process Name Duration Responsible Person
1 On-site survey and foundation construction 7 days Civil construction crew
2 Arrival acceptance and construction preparation 2 days Project Manager
3 Container hoisting and fixing 1 day Hoisting + Mechanical crew
4 Structural accessories and door/window commissioning 2 days Mechanical installation crew
5 Ventilation and air conditioning system installation 3 days Ventilation and AC crew
6 Electrical and grounding system installation 4 days Electrical installation crew
7 Fire protection and gas detection system installation 2 days Electrical installation crew
8 Individual system commissioning 2 days Each specialized crew
9 Overall integrated commissioning and performance testing 2 days Technical Director + Manufacturer
10 Acceptance and delivery 1 day Project Manager

The actual project schedule may be adjusted according to the number of containers and complexity. Buffer time should be reserved for key processes, and a work acceleration plan should be prepared.

7.3 Personnel Responsibility Division

Project Manager Responsibilities:

  • Overall responsibility for the project, ensuring schedule, quality, and safety objectives are achieved.
  • Organize the preparation of construction organization design and approve construction plans.
  • Coordinate relationships between the owner, supervision, manufacturer, and other parties.
  • Responsible for project resource allocation to ensure smooth construction progress.

Technical Director Responsibilities:

  • Prepare construction plans and work instructions, conduct technical disclosures.
  • Resolve technical issues during construction and guide on-site operations.
  • Responsible for construction quality inspection and organization of sub-item acceptance.
  • Prepare commissioning plans and organize system commissioning.
  • Compile completion documentation and participate in completion acceptance.

Safety Officer Responsibilities:

  • Implement safety management systems and conduct safety education and training.
  • Conduct daily safety inspections, investigate safety hazards, and supervise rectification.
  • Supervise special operation personnel to work with valid certificates and stop violations.
  • Handle work permits for hot work, temporary electricity use, etc.
  • Participate in safety accident investigation and handling.

7.4 On-Site Safety Management System

7.4.1 Safety Regulations for Work in Explosion-Proof Areas

  • Personnel entering explosion-proof areas must wear anti-static work clothes and anti-static shoes. Carrying fire sources or non-explosion-proof electronic devices is strictly prohibited.
  • Use of non-explosion-proof electrical equipment or tools within explosion-proof areas is strictly prohibited. Temporary electricity must use explosion-proof types.
  • Before work, the concentration of combustible gases in the work area must be tested. Work may only proceed when the concentration is below 10% of the lower explosion limit.
  • Striking or colliding with metal equipment is strictly prohibited to prevent spark generation.
  • Before opening an explosion-proof container, the power must be cut off, and lockout/tagout must be performed. The “power off, voltage verification, discharge, and tagging” procedure must be followed.

7.4.2 Working at Heights Safety Regulations

  • All work at a fall height of 2 m or more above the reference surface is classified as working at heights and requires a work-at-height permit.
  • Workers must wear safety belts, secured high and anchored low, with reliable anchorage points.
  • Tools used at heights must be secured with anti-drop lanyards. Throwing tools or materials up or down is strictly prohibited.
  • Work at outdoor heights must stop in weather conditions of Force 6 winds or above, thunderstorms, or heavy fog.
  • Scaffolding and work platforms must be inspected and accepted before use.

7.4.3 Hot Work Approval System

  • Hot work within explosion-proof areas requires a Level 1 hot work permit, approved by the safety management department.
  • Before hot work, surroundingcombustible materials must be cleared, and combustible gas concentration must be tested and found acceptable.
  • Sufficient fire-fighting equipment must be provided, and a dedicated fire watch person designated. After hot work, confirm no residual sparks before leaving.
  • Hot work at heights must adopt measures to prevent spark splashing, with fire-resistant blankets laid below.
  • Gas concentration must be re-tested before hot work each day. Hot work permits are valid for the day only.

7.4.4 Temporary Electricity Safety Management

  • Temporary electricity must follow the “one machine, one switch, one residual current device (RCD), one box” principle. The RCD operating current must not exceed 30 mA, with an operating time not exceeding 0.1 s.
  • Cables must be overhead or protected by conduit. Dragging on the ground or running over cables is strictly prohibited.
  • Distribution boxes must be locked and managed by a qualified electrician. Unauthorized wiring is strictly prohibited.
  • The main temporary power supply must be switched off at the end of each workday.
  • All temporary electricity within explosion-proof areas must use explosion-proof electrical equipment. Ordinary distribution boxes and sockets are strictly prohibited.

7.4.5 Emergency Rescue Plan

An emergency rescue plan must be prepared for possible accidents during installation and commissioning, including falls from heights, object strikes, electric shock, fire and explosion, and gas poisoning:

  • Establish an emergency response team, clearly defining the responsibilities of the team leader and members.
  • Equip with first aid kits, stretchers, respirators, fire extinguishers, and other emergency supplies.
  • Publish emergency contact numbers, including on-site supervisor, emergency medical 120, fire alarm 119, and manufacturer technical support at +86 13538869979.
  • Conduct emergency drills before construction to ensure personnel master the emergency response procedures.
  • In the event of an accident, immediately activate the plan, organize rescue, report to relevant departments, and protect the accident scene.

Chapter 8 Container Hoisting and Positioning Installation

8.1 Hoisting Plan Preparation and Approval

Explosion-proof container hoisting is classified as a high-risk sub-project. A dedicated hoisting plan must be prepared and approved by the construction unit’s technical director and the chief supervision engineer before implementation. Overweight or over-span hoisting operations also require expert review.

8.1.1 Lifting Point Design and Force Calculation

  • Lifting point location: Use the dedicated lifting lugs on the top of the container as lifting points. Welding temporary lifting points or slinging the container frame is strictly prohibited. Standard container lifting points are located at the four top corners; all four points must bear load simultaneously during lifting.
  • Force calculation: Calculate lifting lug strength and sling tension based on container dead weight, lifting angle, and dynamic load coefficient, ensuring a safety factor of not less than 5.
  • Lifting angle: The angle between the sling and the top surface of the container should not be less than 60°, and the minimum must not be less than 45°. When the angle is too small, a spreader beam must be used.
  • Center of gravity verification: Confirm the container center of gravity position to ensure the line connecting the lifting points passes through the center of gravity. The container must remain level during lifting to avoid tilting and slipping.

8.1.2 Hoisting Sling Selection and Inspection

  • Prioritize wide-width flexible lifting slings to avoid damaging the container anti-corrosion coating and structural corners. Install corner protectors at sharp edges to prevent sling cutting.
  • Sling rated load: Single sling rated load × quantity × angle factor ≥ Container weight × dynamic load factor (1.1).
  • Inspect slings before lifting: no broken wires, tears, wear, corrosion, or chemical damage; markings must be clear.
  • Shackle pins must be tightened, threads lubricated, and lateral loading is strictly prohibited.

8.1.3 Hoisting Operation Risk Assessment

Risk identification and prevention measures must be conducted before lifting:

Risk Prevention Measure
Risk 1: Crane overturning Fully extend outriggers, lay outrigger pads, verify ground bearing capacity, strictly prohibit overloading
Risk 2: Container slipping Sling inspection passed, four-point even load distribution, test lift to confirm balance
Risk 3: Collision with obstacles Clear obstacles before lifting, designate a dedicated signal commander, strictly prohibit standing under the lifted load
Risk 4: Contact with overhead power lines Maintain safe distance, assign dedicated monitor, power off if necessary
Risk 5: Lifting in high wind conditions Stop lifting in winds of Force 6 or above; postpone operations in strong winds

8.2 Hoisting Operation Procedure

8.2.1 Pre-Hoisting Safety Inspection

Before hoisting operations, the crane signal commander and safety officer jointly inspect and confirm the following:

  • Crane outriggers fully extended, securely padded, and crane body level within requirements.
  • Slings and shackles inspected and qualified, correctly rigged, and evenly loaded.
  • Hoisting area cordoned off with warning tape; non-essential personnel evacuated; no one under the load.
  • Communication between commander and crane operator is clear, with unified command signals.
  • Weather conditions meet operational requirements: no high winds, thunderstorms, or heavy fog.
  • No obstacles between the container and foundation; positioning marks are clear.

8.2.2 Test Lift Operating Specifications

  • After all inspections pass, command the operator to slowly raise the hook, lifting the container 100–200 mm off the ground, then stop.
  • Check for outrigger settlement, sling slippage, container levelness, and lifting lug deformation.
  • Hold for 3–5 minutes; only after confirming no abnormalities may the formal lift proceed.
  • If any abnormality is found during the test lift, slowly lower the load immediately, eliminate the hazard, and repeat the test lift.

8.2.3 Formal Hoisting and Positioning

  • After the test lift passes, command the crane to smoothly lift, rotate, and luff the container to directly above the foundation.
  • Maintain a uniform speed during hoisting. Sudden stops or turns are strictly prohibited to avoid large container swings.
  • When the container is lowered to 300 mm above the foundation surface, pause to adjust the container orientation and position, aligning anchor bolts and positioning lines.
  • Slowly lower the container, aligning all four corners with the bolts simultaneously, avoiding impact with bolts and foundation edges.
  • After the container is fully seated, inspect position deviation. The hook may only be released after requirements are met.

8.2.4 Hoisting Command Signal Specifications

  • Signal commanders must hold valid certificates and wear conspicuous identification.
  • Two-way radios are the preferred communication method, with hand signals as backup.
  • Command signals must be clear, accurate, and unified. The crane operator must strictly follow command instructions.
  • Any person may issue an emergency stop signal, and the operator must obey immediately.
  • The signal commander must supervise throughout the lifting process and is strictly prohibited from leaving their post.

8.3 Container Positioning and Leveling

8.3.1 Baseline Layout and Positioning

  • After foundation construction, mark the container installation centerline, edge lines, and anchor bolt hole centerlines on the foundation surface.
  • After the container is seated, verify the deviation between the container edge lines and baseline. The planar position deviation must not exceed 5 mm.
  • The container longitudinal and transverse centerline deviation from the design baseline must not exceed 10 mm.
  • If position deviation exceeds tolerance, use jacks or pry bars for fine adjustment. Using the crane to forcibly drag the container is strictly prohibited.

8.3.2 Container Levelness Adjustment

  • Use a level to measure elevations at the four corners of the container bottom beams.
  • Adjust levelness by adding or removing leveling shims between the foundation and bottom beams. Shims should be placed on both sides of anchor bolts, with no more than 3 shims per group.
  • Longitudinal and transverse levelness deviation must not exceed 1‰, with a total length deviation not exceeding 5 mm.
  • After levelness adjustment passes, tack-weld the shims together to prevent movement.

8.3.3 Container Verticality Inspection

  • Use a theodolite or plumb bob to measure the verticality of container columns.
  • Container verticality deviation must not exceed 1‰, with total height deviation not exceeding 10 mm.
  • Verticality exceeding tolerance is corrected by adjusting bottom shims. Forcibly pulling or pushing the container frame is strictly prohibited.

8.3.4 Temporary Fixing After Positioning

  • After positioning and leveling are complete, install anchor bolt nuts for temporary fixing.
  • Install temporary diagonal bracing at the four corners of the container to prevent shifting or tipping after hoisting.
  • Hoisting slings may only be removed after temporary fixing is complete.
  • If final fixing is not completed on the same day, temporary reinforcement and wind protection measures must be implemented.

8.4 Container and Foundation Fixed Connection

8.4.1 Embedded Plate Welding Fixation

When using embedded steel plates, the container bottom beams are welded to the embedded plates:

  • Before welding, clean oil and rust from the welding area to expose metallic luster.
  • Use continuous fillet welds. The weld leg height must meet design requirements, generally not less than 8 mm.
  • Weld in segments symmetrically to reduce welding deformation. Monitor container levelness during welding and adjust promptly if deformation exceeds tolerance.
  • Welding within explosion-proof areas requires a hot work permit, with fire and explosion prevention measures in place.
  • After welding, remove slag, apply primer and topcoat for anti-corrosion treatment.

8.4.2 Bolt Anchorage Installation

When anchor bolts are pre-embedded:

  • Clean bolt threads and apply anti-rust grease.
  • Install flat washers, spring washers, and nuts, tightening symmetrically and evenly.
  • Use a torque wrench to tighten to the design torque value, ensuring even force distribution across all bolts.
  • After tightening, the bolt thread should extend 2–3 threads beyond the nut. Apply anti-rust grease to the exposed portion.
  • For seismic requirements, install lock nuts or anti-loosening washers.

8.4.3 Strength Inspection After Fixation

  • After fixation is complete, inspect weld appearance for cracks, porosity, slag inclusion, incomplete fusion, and other defects.
  • Tap welds with a small hammer: a crisp sound indicates quality; a dull sound requires further inspection.
  • Check bolt torque values with a sampling rate of not less than 20%, all must pass.
  • Apply horizontal force to the container to check for loosening or shifting; the connection must be firm and reliable.

8.4.4 Anti-Corrosion Sealing Treatment

  • All welded areas, bolt heads, and damaged paint surfaces must be derusted and repainted with primer + topcoat matching the container color.
  • Fill gaps between the container bottom beams and foundation with waterproof sealant to prevent rain and moisture from entering underneath and causing corrosion.
  • Create a waterproof slope around the foundation perimeter to channel rainwater away and prevent prolonged water accumulation.
  • Apply conductive paste to grounding connection points to prevent increased contact resistance.

Chapter 9 Explosion-Proof Door and Explosion-Proof Window System Installation

9.1 Explosion-Proof Door Structure and Installation Requirements

The explosion-proof door is a key pressure-bearing and sealing component of the explosion-proof container. Its installation quality directly affects the overall explosion-proof performance and must strictly meet the following requirements:

  • The door frame and container door opening must fit tightly with uniform gaps, ensuring that the flameproof joint parameters conform to standards.
  • The door leaf must open and close flexibly, with the sealing strip uniformly compressed after closing and no air gaps.
  • Door locks, hinges, door closers, and other accessories must be firmly installed and operate reliably.
  • The joint surfaces of flameproof doors must be free of scratches and corrosion, with surface roughness meeting requirements.
  • After installation, the door leaf must have no sagging or deformation, and open/close action must be free of sticking.

9.2 Explosion-Proof Door Installation Procedure

9.2.1 Door Frame Positioning and Fixation

  • Clean burrs and weld slag around the door opening, measure the door opening dimensions, and verify against door frame dimensions.
  • Place the door frame into the opening, adjust position and verticality. Door frame verticality deviation must not exceed 1 mm/m.
  • Fix the door frame to the container by bolting or welding. Fixing point spacing must not exceed 500 mm, with fixing points required at all four corners.
  • When fixing by welding, weld in segments symmetrically to prevent frame deformation. When bolting, tighten bolts evenly.
  • After fixation, re-verify door frame dimensions and verticality, adjusting promptly if out of tolerance.

9.2.2 Door Leaf Installation and Commissioning

  • Before installation, check the door leaf for deformation, flameproof surface damage, and sealing strip integrity.
  • Install hinge pins and hang the door leaf onto the frame. Adjust hinge clearances to ensure uniform gaps between the door leaf and frame on all sides.
  • Test door leaf opening and closing: must be smooth, free of sticking, sagging, or rubbing.
  • Adjust the parallel alignment between the door leaf and frame; after closing, all sides must fit tightly.
  • Heavy door leaves require hinge bearing adjustment to ensure smooth rotation and reduced wear.

9.2.3 Sealing Strip Installation

  • Before applying the sealing strip, clean the frame sealing groove, removing oil and dust.
  • The strip must be applied as a continuous loop. At joints, use 45° miter cuts with firm adhesion; butt joints are strictly prohibited.
  • The strip must be firmly seated in the groove without bulging, twisting, or detachment.
  • After door closure, strip compression must be uniform; compression ratio controlled at 25%–30% to ensure sealing performance.
  • Regularly inspect the strip for aging. Replace promptly if cracking, hardening, or loss of elasticity is found.

9.2.4 Door Lock and Door Closer Installation

  • The explosion-proof lock must be firmly installed with the latch and lock box properly aligned and operating smoothly.
  • For locks with interlock function, adjust the interlock travel to ensure reliable interlock action.
  • The door closer installation position must meet design requirements, with adjustable closing speed and moderate closing force.
  • Install a sequential closer to ensure double doors close in the correct sequence.
  • After installation, conduct no fewer than 20 repeated open/close tests; all actions must function normally to pass.

9.3 Explosion-Proof Window Installation Procedure

9.3.1 Window Frame Fixation and Sealing

  • Clean the window opening and check dimensional deviation; correct if the deviation is excessive.
  • Place the window frame into the opening, adjust levelness and verticality; deviation must not exceed 1 mm/m.
  • Fix the window frame to the container by welding or bolting, with no fewer than 6 fixing points around the perimeter.
  • Fill the gap between the frame and wall with fire-resistant insulation material, and apply weather-resistant sealant on the outside.
  • After fixation, re-verify frame flatness; no deformation or warping.

9.3.2 Explosion-Proof Glass Installation

  • Before installation, inspect the explosion-proof glass for cracks, bubbles, and scratches; verify dimensions meet requirements.
  • Lay rubber support pads in the glass channel, leaving expansion gaps on all four sides of the glass to avoid rigid contact.
  • Install retaining strips to secure the glass firmly. Strip joints must be tight with no warping.
  • Apply sealant around the glass perimeter; the sealant bead must be smooth and continuous with no bubbles or gaps.
  • For operable explosion-proof windows, install hinges and locking devices, and commission the opening angle and closed position sealing.

9.3.3 Opening Mechanism Commissioning

  • Commission the opening angle of operable explosion-proof windows, generally not exceeding 90°, with limit devices installed.
  • Opening and closing must be smooth, free of sticking or abnormal noise, with good sealing after closure.
  • For windows with locking mechanisms, the sealing strip must compress evenly after locking, with no light gaps visible.
  • Hand-crank opening mechanisms must operate smoothly with reliable self-locking and no slipping.

9.4 Explosion-Proof Door and Window Performance Testing

After installation, perform performance testing on explosion-proof doors and windows:

  • Sealing test: Close doors/windows, spray soapy water on the outside, pressurize from the inside with ventilation, and observe for bubble leakage; alternatively, use the smoke method to detect leak points.
  • Opening/closing reliability test: Continuously open/close 50 times; no sticking, deformation, or fastener loosening.
  • Flameproof joint parameter test: Use a feeler gauge to measure joint gap for flameproof doors/windows, and a caliper to measure joint width, conforming to GB 3836.2 standard requirements.
  • Visual inspection: Surfaces free of damage, anti-corrosion coating intact, accessories complete, and markings clear.

Chapter 10 Ventilation and Explosion-Proof Air Conditioning System Installation

10.1 Explosion-Proof Ventilation System Principle and Composition

The function of the explosion-proof ventilation system is to ensure air circulation inside the container, exhaust harmful gases, and supply fresh air, while preventing external flames from entering the container through flame-arresting devices. It is a critical system for the safe operation of the explosion-proof container.

Main system components: Explosion-proof fresh air fan, explosion-proof exhaust fan, ventilation ducts, air filters, explosion-proof flame arresters, pressure relief valves, volume control dampers, and silencers.

Ventilation rate design standards:

  • Normal ventilation: air change rate not less than 6 times/hour.
  • Emergency ventilation: air change rate not less than 12 times/hour.
  • Positive pressure containers: fresh air required to maintain positive pressure + personnel fresh air, with personnel fresh air not less than 30 m³/(person·h).

10.2 Ventilation Duct Installation

10.2.1 Duct Prefabrication and Connection

  • Ducts are fabricated from galvanized steel sheet or stainless steel sheet, with thickness conforming to ventilation standards; high-pressure systems require thicker material.
  • Duct sections are joined by lock-forming or welding. Welded ducts must be free of burn-through, cracks, and missed welds.
  • For flange connections, use flame-retardant oil-resistant rubber gaskets, 3–5 mm thick. Gaskets must not protrude into the duct interior.
  • Duct joints must be tight, with flange bolts tightened evenly, extending 2–3 threads beyond the nuts.
  • After fabrication, conduct light leakage testing on ducts; medium and high-pressure systems require air leakage rate testing.

10.2.2 Duct Explosion-Proof Sealing Treatment

  • Apply sealant to all duct seams and flange connections to ensure airtightness.
  • Where ducts penetrate the container wall, install waterproof sleeves and seal gaps with fire-resistant sealant.
  • Use explosion-proof flexible connectors between ducts and fans/equipment to prevent vibration transmission.
  • Regulating dampers and fire dampers on ducts must have explosion-proof actuators, with sealed wiring connections.

10.2.3 Duct Support and Hanger Installation

  • Supports and hangers are fabricated from angle steel or channel steel with complete anti-corrosion treatment.
  • Support spacing conforms to standards: for horizontal ducts with diameter or long side less than 400 mm, spacing not exceeding 4 m; for greater than 400 mm, not exceeding 3 m. Vertical duct spacing not exceeding 4 m, with no fewer than 2 fixings per vertical riser.
  • Supports and hangers must be in firm contact with ducts and securely fixed. Welding to flanges is strictly prohibited.
  • Install anti-sway bracing on main ducts, with additional supports at bends and ends.

10.2.4 Duct Airtightness Testing

  • After installation, conduct light leakage testing: in a dark environment, introduce a light source into the duct and move it along interfaces for observation; no visible light leakage indicates a pass.
  • Medium and high-pressure systems require air leakage rate testing, with leakage conforming to GB 50243 standard requirements.
  • Explosion-proof duct systems have stricter air leakage requirements: leakage must be reduced by 20% compared to standard values.
  • Mark leak points, rectify, and re-test until passing.

10.3 Explosion-Proof Fan Installation

10.3.1 Fan Foundation Fixation

  • Fans are installed on vibration-isolating bases or vibration-isolating supports, with isolator models matched to fan weight.
  • Fan levelness deviation must not exceed 1‰, with coupling concentricity meeting requirements.
  • Fan bases are securely bolted to foundations with anti-loosening devices.
  • Fans installed outdoors must have rain shields, with motor sections protected against moisture.

10.3.2 Fan and Duct Connection

  • Fan inlet/outlet connections to ducts use flexible connectors, 150–300 mm in length, made of flame-retardant fireproof canvas or silicone fabric.
  • Flexible connectors must be of appropriate tightness; twisting or forced loading is strictly prohibited.
  • Install a fire damper or check valve at the fan outlet in the correct direction.
  • Duct weight must not be supported by the fan; ducts require separate supports and hangers.

10.3.3 Fan Electrical Wiring

  • Fan motors must be explosion-proof type, with cables introduced through explosion-proof cable glands in the terminal box.
  • Wiring must be secure, phase sequence correct, and grounding reliable.
  • Motor insulation resistance must not be less than 1 MΩ; wiring may only proceed after testing passes.
  • After wiring, tighten the explosion-proof terminal box cover to ensure flameproof performance.

10.4 Explosion-Proof Air Conditioning System Installation

The explosion-proof air conditioner provides a constant temperature and humidity environment inside the container, ensuring equipment and personnel comfort. All electrical components must be explosion-proof type, and installation must comply with explosion-proof standards.

10.4.1 Indoor Unit Installation

  • Indoor units may be wall-mounted or cabinet type. Installation position must avoid direct airflow onto personnel and be away from heat sources.
  • Wall mounting must be secure, levelness must meet requirements, and condensate drain slope must not be less than 5‰.
  • Leave a maintenance access space of not less than 300 mm between the indoor unit and container wall.
  • The indoor unit housing must be reliably grounded, with wiring introduced through explosion-proof flexible conduit.

10.4.2 Outdoor Unit Installation

  • Outdoor units are installed on the container roof or an outdoor foundation, which must be firm and level.
  • Leave sufficient heat dissipation space around the unit: not less than 300 mm on the air intake side and not less than 500 mm on the discharge side.
  • Outdoor units must be firmly fixed with vibration-isolating pads to reduce vibration and noise.
  • When multiple outdoor units are installed, maintain spacing to avoid airflow short-circuiting.

10.4.3 Refrigerant Piping Connection

  • Refrigerant pipes use copper tubing with wall thickness meeting pressure requirements. Pipe ends must be capped to prevent dust and moisture entry.
  • Pipe welding must use nitrogen-shielded welding to prevent internal oxidation of the copper tube.
  • Pipes must be installed level and plumb, with support spacing meeting requirements and protective sleeves at wall penetrations.
  • After pipe installation, perform blow-through cleaning, airtightness testing, and vacuum drying.
  • Wrap pipes with insulation, seal insulation joints tightly, and wrap with protective tape.

10.4.4 Condensate System Installation

  • Condensate pipes use PVC pipe or galvanized steel pipe with a slope of not less than 3‰.
  • Connect to the on-site drainage system. Connecting to the explosion-proof area sewage network is strictly prohibited.
  • Install a water seal at the condensate pan outlet to prevent odor backflow.
  • After installation, perform a water flow test; drainage must be smooth with no leaks.

10.4.5 System Pressure Holding and Leak Detection

  • After piping connections are complete, charge with nitrogen for pressure holding. The pressure value is determined by refrigerant type: R22 systems hold at 2.4 MPa; R410A systems hold at 4.0 MPa.
  • Hold pressure for 24 hours; a pressure drop not exceeding 0.02 MPa indicates a pass.
  • Check all weld joints and connections with soapy water; no bubble leakage is acceptable.
  • After pressure holding passes, evacuate to a vacuum of −0.1 MPa and maintain for 2 hours without rebound.

10.5 Fresh Air and Exhaust Explosion-Proof Treatment Device Installation

10.5.1 Explosion-Proof Flame Arrester Installation

  • Install explosion-proof flame arresters at both the fresh air inlet and exhaust outlet to prevent flame propagation through ducts.
  • The flow direction arrow on the flame arrester must match the airflow direction; reverse installation is strictly prohibited.
  • Connect flame arresters to ducts with flanges and ensure gasket sealing.
  • Installation position must facilitate removal for cleaning, with maintenance access space reserved.
  • Regularly inspect the arrester element; clean or replace promptly if blocked or damaged.

10.5.2 Gas Filtration Device Installation

  • Install primary and medium-efficiency filters at the fresh air inlet to purify intake air.
  • In dusty or corrosive gas environments, add activated carbon filters or chemical filters.
  • Filters must be firmly installed with tightly sealed frames to prevent bypass leakage.
  • Configure differential pressure gauges to monitor filter resistance, with alerts indicating when replacement is needed.

10.5.3 Pressure Relief Valve Installation and Commissioning

  • Positive pressure containers require pressure relief valves to maintain stable internal pressure and automatically relieve overpressure.
  • Install relief valves on the upper section of the container or on the exhaust side, with correct orientation.
  • Commission the relief valve opening pressure to match the positive pressure system, generally set at 150–200 Pa.
  • The relief valve must operate flexibly and seal tightly after closing with no leakage.

Chapter 11 Explosion-Proof Electrical System Installation

11.1 Explosion-Proof Electrical System Overview

The explosion-proof electrical system is the core functional system of the explosion-proof container and a key focus of explosion-proof safety control. All electrical equipment, components, and cables must meet the corresponding explosion-proof level requirements. Installation must strictly follow explosion-proof construction standards, and compromising explosion-proof performance is strictly prohibited.

System composition: Incoming line unit, explosion-proof distribution cabinet, explosion-proof lighting circuits, explosion-proof power circuits, explosion-proof control circuits, grounding protection system, and surge protection system.

Overall installation principles:

  • All electrical components must have valid explosion-proof certificates, with explosion-proof levels not lower than design requirements.
  • Electrical clearances and creepage distances must conform to the corresponding explosion-proof level standards.
  • All cable entry points must receive explosion-proof sealing treatment.
  • Wiring must be secure with good contact to prevent overheating.
  • Grounding must be reliable with complete equipotential bonding.

11.2 Cable Laying and Explosion-Proof Conduit Threading

11.2.1 Cable Selection and Inspection

  • Power cables use copper-core XLPE insulated PVC sheathed flame-retardant armored cables. Control cables use shielded flame-retardant cables.
  • Cable rated voltage must not be lower than the operating voltage, with insulation thickness meeting standards.
  • Inspect cables upon arrival for external damage, crushing, or moisture. Product certificates and inspection reports must be complete.
  • Test insulation resistance before laying: low-voltage power cables must have insulation resistance not less than 10 MΩ, control cables not less than 5 MΩ.

11.2.2 Cable Tray and Conduit Installation

  • Cable trays use galvanized or stainless steel trays with corrosion resistance meeting environmental requirements.
  • Trays must be installed level and plumb, with support spacing meeting standards, connections secure, and grounding reliable.
  • Conduit threading within explosion-proof areas uses galvanized steel pipe with threaded connections. Thread engagement must be not less than 5 threads, coated with conductive paste.
  • Install explosion-proof junction boxes at conduit bends and branches, and one every 30 m on straight runs.
  • Conduit-to-equipment connections use explosion-proof flexible conduits of matching length, without twisting or forced loading.

11.2.3 Explosion-Proof Junction Box Installation

  • Explosion-proof junction box specifications must match the conduit, with explosion-proof levels meeting area requirements.
  • Box nipples connect to conduit via threaded joints. After tightening, leave 2–3 threads exposed, coated with anti-rust grease.
  • Box covers must be tightened with intact sealing gaskets; no missing or damaged parts.
  • Junction boxes must be installed in accessible maintenance locations, avoiding water and dust accumulation.

11.2.4 Cable Laying Specifications

  • Before cable laying, clean debris from conduits and trays. Install protective bushings at conduit ends to prevent cable damage.
  • Pull cables at a uniform speed, strictly avoiding excessive force. Cable insulation must be free of damage.
  • Cables of different voltage levels and different circuits must be laid separately. Strong current and weak current separation distance must not be less than 300 mm.
  • Cable bending radius must not be less than 10 times the cable outer diameter, and not less than 15 times for armored cables.
  • Cables must be laid neatly and securely tied, with appropriate allowance at bends and terminations.

11.2.5 Cable Identification and Dressing

  • Install identification tags at both cable ends, bends, and branch points, indicating circuit number, model/specification, and start/end points.
  • Tags must have clear, waterproof, corrosion-resistant markings and be securely tied.
  • Cables inside cabinets must be neatly arranged, with organized wiring in cable ducts and allowance at terminal points.
  • Power, control, and communication cables should be arranged in separate layers to reduce interference.

11.3 Explosion-Proof Distribution Cabinet and Control Cabinet Installation

11.3.1 Cabinet Positioning and Fixation

  • Distribution cabinet installation positions must conform to design drawings, be convenient to operate, and accessible for maintenance.
  • Wall-mounted cabinets: bottom edge 1.2–1.5 m above floor. Floor-standing cabinets: base raised 100–200 mm above floor.
  • Cabinets must be securely fixed with verticality deviation not exceeding 1.5‰.
  • When multiple cabinets are installed side by side, gaps must be uniform and top surfaces level, with deviation not exceeding 2 mm.

11.3.2 Cabinet Grounding Connection

  • The cabinet housing must be reliably connected to the grounding trunk. Grounding bolts must be not smaller than M8, with spring washers.
  • A dedicated grounding busbar must be installed inside the cabinet, either insulated from or directly connected to the cabinet housing, per design.
  • Cabinet doors and openable parts must be connected to the cabinet grounding busbar using yellow-green stranded copper wire with cross-section not less than 4 mm².
  • Grounding connections must be secure with low contact resistance and clear markings.

11.3.3 Incoming/Outgoing Line Explosion-Proof Sealing Treatment

  • Cables entering/exiting cabinets use explosion-proof cable glands (cable clamping sealed fittings), with specifications matching cable outer diameter.
  • Glands must be tightened with uniform compression of sealing rings. Cables must be firmly clamped with good sealing.
  • When multi-core cables are introduced, separate the cores and seal with explosion-proof packing compound, filled full and compact.
  • Spare entry holes must be sealed with explosion-proof plugs; leaving them open is strictly prohibited.
  • Flameproof distribution cabinet joint surfaces must be clean, undamaged, coated with a thin layer of anti-rust grease, and bolts tightened evenly.

11.4 Explosion-Proof Switch and Pushbutton Installation

  • Explosion-proof switches and pushbuttons must be securely installed, in positions conforming to design, with operating height of 1.2–1.5 m.
  • Wiring must be correct, markings clear, and contacts making good contact.
  • Explosion-proof joint surfaces must be intact, sealing gaskets complete, and housings fully tightened.
  • For pushbuttons with indicator lights, the indicator voltage must match the circuit, and colors must conform to standards.

11.5 Explosion-Proof Terminal Blocks and Explosion-Proof Connectors Installation

  • Terminal blocks must be explosion-proof type, with insulation class and rated current meeting circuit requirements.
  • Wire stripping length must be appropriate, crimping secure, with no broken strands or loose connections.
  • Stranded conductors must use crimped cable lugs; direct insertion into terminals is strictly prohibited.
  • Explosion-proof connectors must have tight threaded connections, good sealing, and cables free of stress.

11.6 Electrical System Insulation and Continuity Testing

  • Insulation resistance test: Use a 500 V megger to test each circuit to ground and between phases. Low-voltage power circuits: not less than 0.5 MΩ. Control circuits: not less than 1 MΩ.
  • Continuity test: Test each circuit for proper continuity, correct wiring, and absence of short circuits or open circuits.
  • Phase sequence check: Three-phase power phase sequence must be correct, and motor rotation direction must meet requirements.
  • Ground resistance test: Equipment housing grounding resistance must not exceed 4 Ω.
  • Record all test results. Identify and rectify causes for non-compliant circuits, then re-test.

Chapter 12 Grounding and Anti-Static System Installation

12.1 Explosion-Proof Grounding System Design Requirements

The grounding system is the fundamental safeguard for explosion-proof electrical safety. It is divided into protective grounding, working grounding, anti-static grounding, and lightning protection grounding. Explosion-proof areas should use a shared grounding system with grounding resistance not exceeding 1 Ω.

Design principles:

  • All electrical equipment metal housings, metal conduits, and metal structural components must be reliably grounded.
  • Grounding trunks form a ring network with multiple connections to the main grounding grid.
  • Grounding connections use welding or bolted connections with reliable contact.
  • Equipotential bonding covers all areas, eliminating potential differences between metal components.

12.2 Container Main Grounding Installation

12.2.1 Ground Electrode Construction

  • Vertical ground electrodes use ∠50×50×5 mm galvanized angle steel or φ50 mm galvanized steel pipe, 2.5 m in length, driven vertically into the ground with the top 0.8 m below the ground surface.
  • Electrode spacing must not be less than 5 m, arranged along the foundation perimeter.
  • If driving is difficult, use the drilling resistance-reduction method and fill with resistance-reducing agent.
  • Ground electrodes are welded to the horizontal grounding busbar. Weld length must be 2 times the flat steel width, welded on three sides.

12.2.2 Grounding Busbar Installation

  • The horizontal grounding busbar uses 40×4 mm galvanized flat steel, buried at a depth of 0.8 m.
  • Flat steel lap welding: lap length not less than 2 times the width, welded on three sides.
  • Remove weld slag at welded joints and apply asphalt paint for anti-corrosion treatment.
  • Where the busbar emerges from the ground, protect with a sleeve and provide clear grounding markings.

12.2.3 Container and Grounding Grid Connection

  • The container must have no fewer than 2 main grounding terminals, each connected to the grounding grid outgoing conductors.
  • Grounding down conductors use stranded copper wire of not less than 25 mm² or 40×4 mm flat steel.
  • For bolted connections, configure spring washers, polish contact surfaces to a bright finish, and apply conductive paste.
  • After connection, test continuity; contact resistance must not exceed 0.03 Ω.

12.3 Equipment Anti-Static Grounding Installation

12.3.1 Equipotential Bonding of Metal Components

  • All metal pipes, racks, cabinets, and door/window frames inside the container must receive equipotential bonding.
  • Bonding conductors use stranded copper wire of not less than 6 mm² in yellow-green color.
  • At connection points, remove paint film and corrosion to expose metal surfaces, then tighten bolts.
  • Form an equipotential network; the potential difference between any two points must not exceed 1 V.

12.3.2 Equipment Housing Grounding

  • All electrical equipment and instrument housings must be individually grounded. Series grounding is strictly prohibited.
  • Grounding terminals must have clear markings, secure connections, and complete anti-loosening devices.
  • Mobile equipment uses anti-static grounding clamps, reliably connected during use.

12.3.3 Anti-Static Floor Installation and Grounding

  • Anti-static floor supports must be reliably connected to the ground, with each floor panel connected to the grounding system through conductive supports.
  • Floor surface resistance: 10⁶–10⁹ Ω; system resistance: 10⁴–10⁶ Ω.
  • No fewer than 2 grounding down conductors from the floor, connected to the equipotential grounding busbar.
  • After installation, test surface resistance and system resistance to ensure compliance.

12.4 Grounding Resistance Testing and Acceptance

12.4.1 Test Instruments and Methods

  • Use a ground resistance tester, tested by the three-point or four-point method.
  • Test electrode arrangement must be proper, with current and voltage electrodes at required distances from the ground electrode.
  • Clean the ground terminal contact surface before testing to ensure good contact.
  • Re-test under different weather conditions and seasons, taking the maximum value as the basis for judgment.

12.4.2 Acceptance Criteria

Grounding Type Acceptance Criteria
Shared grounding system ≤1 Ω
Electrical protective grounding ≤4 Ω
Anti-static grounding ≤100 Ω
Lightning protection grounding ≤10 Ω

12.4.3 Non-Conforming Rectification Plan

  • When grounding resistance exceeds limits, prioritize adding more ground electrodes and extending the grounding busbar.
  • For high soil resistivity areas, replace soil or apply resistance-reducing agent.
  • Inspect grounding connection points; re-treat corroded or loose connections.
  • Re-test after rectification until compliant.

Chapter 13 Lighting and Communication System Installation

13.1 Explosion-Proof Lighting System Installation

13.1.1 Explosion-Proof Luminaire Selection and Layout

  • All luminaires must be explosion-proof LED type, with explosion-proof levels matching the area and ingress protection rating not lower than IP65.
  • Normal lighting illuminance must not be less than 300 lx. Emergency lighting illuminance must not be less than 10% of normal lighting. Evacuation routes must not be less than 1 lx.
  • Luminaires must be evenly distributed to avoid glare, with focused lighting in operating areas.
  • Emergency lighting duration must not be less than 90 minutes.

13.1.2 Luminaire Fixation and Wiring

  • Ceiling-mounted or wall-mounted installation with no fewer than 2 fixing bolts, securely installed.
  • Luminaire wiring enters through explosion-proof glands with secure connections. Phase wire controlled by switch.
  • Luminaire housings must be reliably grounded.
  • After installation, adjust the illumination angle to ensure uniform illuminance.

13.1.3 Emergency Lighting System Installation

  • Emergency luminaires must have self-contained backup power, automatically activating upon power failure.
  • Evacuation exit signs are installed at the top of exits and on corridor walls, with spacing not exceeding 20 m.
  • Emergency lighting circuits are separately powered and must not share circuits with normal lighting.
  • Regularly test emergency discharge time to meet standard requirements.

13.1.4 Illuminance Testing

  • Use an illuminance meter to test illuminance at work surface height at various points.
  • Average illuminance must meet design requirements, with illuminance uniformity not less than 0.7.
  • Test emergency lighting after power interruption: lighting time and illuminance must meet requirements.

13.2 Explosion-Proof Communication System Installation

13.2.1 Explosion-Proof Telephone Installation

  • Explosion-proof telephones are installed in convenient operating positions, 1.2–1.5 m in height.
  • Telephone lines use shielded cables in separate conduits, avoiding sharing conduits with power cables.
  • Wiring must be secure, call quality clear, and free of noise.
  • Telephone housings must be reliably grounded.

13.2.2 Explosion-Proof Network Equipment Installation

  • Explosion-proof switches and routers are installed in explosion-proof cabinets or use fully explosion-proof models.
  • Network cables use shielded Cat.5e or Cat.6 cables, with the shield grounded at one end only.
  • Equipment power supply must be configured with explosion-proof power modules or UPS.
  • Test network transmission speed and stability to meet usage requirements.

13.2.3 Explosion-Proof Public Address System Installation

  • Explosion-proof speakers are evenly distributed with volume covering the entire area.
  • The broadcast host is installed in the control room with both manual and automatic trigger functions.
  • Integrate with fire alarm and gas alarm systems; automatically broadcast evacuation instructions upon alarm.
  • Test volume and sound quality; must be clear without noise, with emergency broadcast at highest priority.

13.2.4 Communication Signal Testing

  • Telephone call test: Clear voice, no dropped calls or noise.
  • Network test: Bandwidth, latency, and packet loss rate must meet requirements.
  • Broadcast test: Volume meets requirements, coverage without dead zones, and integration functions operate normally.

Chapter 14 Gas Detection and Fire Protection System Installation

14.1 Combustible/Toxic Gas Detection System Installation

The gas detection system serves as the “safety sentinel” of the explosion-proof container, monitoring combustible and toxic gas concentrations in real time, triggering alarms and interlocking protection when limits are exceeded. It is the core proactive explosion-proof system.

14.1.1 Gas Detector Selection and Placement

Selection principles: Select the corresponding sensor according to the detected gas type. Catalytic combustion or infrared types are commonly used for combustible gases; electrochemical types for toxic gases.

Placement principles:

  • For gases lighter than air (e.g., methane, hydrogen), install detectors at the top, not more than 300 mm from the ceiling.
  • For gases heavier than air (e.g., gasoline vapors, hydrogen sulfide), install detectors at the lower section, not more than 300 mm from the floor.
  • Add detectors near release sources, ventilation dead zones, cable trenches, and other areas prone to accumulation.
  • Detector coverage radius: not greater than 7.5 m for combustible gases, not greater than 2 m for toxic gases.

The quantity must meet standard requirements, and the alarm controller must be installed in a manned location.

14.1.2 Detector Installation and Wiring

  • Detectors must be securely fixed, oriented toward the direction to be detected, and avoid installation at air vents or dead corners.
  • Use shielded cables for wiring, with shield grounded and terminals secure.
  • Detector explosion-proof housings must be tightened, sealing gaskets intact, and cable glands sealed.
  • After installation, protect detector sensing heads from dust and oil contamination. Remove protective covers before commissioning.

14.1.3 Alarm Controller Installation

  • Wall-mounted installation with bottom edge at 1.5 m above floor for convenient operation.
  • Dual power supply: main power + backup battery, operating for not less than 8 hours after power failure.
  • Reliable grounding, with shield wires grounded separately.
  • Alarm signals output to the central control room and fire protection system for remote monitoring.

14.1.4 System Interlock Wiring

  • Level 1 alarm (low limit, 25% LEL): audible and visual alarm, interlocked to start exhaust fan.
  • Level 2 alarm (high limit, 50% LEL): audible and visual alarm, interlocked to cut off non-fire-protection power and start emergency exhaust.
  • Interlock relays must be explosion-proof type, correctly wired, with correct logic.
  • Interlock action delay time is adjustable to prevent false activation.

Chapter 14 Explosion-Proof Fire Protection System Installation

14.1 Gas Fire Extinguishing System Installation

Precision equipment areas shall use a heptafluoropropane (HFC-227ea) or IG541 inert gas fire extinguishing system:

  • Extinguishing agent storage cylinders are installed in a dedicated cylinder room, securely fixed, with normal pressure;
  • Nozzles are evenly arranged to ensure no dead zones in the protected area;
  • Selector valves and solenoid valves are explosion-proof treated, with sealed wiring;
  • System piping shall undergo an air tightness test, with pressure drop conforming to standards;
  • Interlocked with the fire alarm system, providing three activation modes: automatic, manual, and mechanical emergency.

14.2 Dry Powder Fire Extinguishing Device Installation

  • Suspended dry powder fire extinguishing devices are installed at the ceiling, with the protection range covering hazardous areas;
  • Temperature-activated or electrically controlled activation, with response time meeting requirements;
  • Devices are securely fixed, with periodic inspection of pressure and expiration date;
  • Interlocked with the alarm system, automatically activating after an alarm is triggered.

14.3 Fire Emergency Signage Installation

  • Safety exit signs are installed at the top of exits, clear and conspicuous;
  • Evacuation direction signs are arranged along corridors, pointing towards the nearest safety exit;
  • Fire extinguisher placement points are marked with signage, clearly visible and easily accessible;
  • Signage is photoluminescent or light-powered type, remaining identifiable after power failure.

14.4 Audible and Visual Alarm System Installation and Commissioning

  • Explosion-proof audible and visual alarms are installed at entrances/exits, corridors, and other conspicuous locations;
  • Alarm sound pressure level shall not be less than 110dB, flash frequency 1-2Hz, red flashing light;
  • Interlocked with gas alarm and fire alarm systems, triggering simultaneously upon alarm;
  • On-site testing of audible and visual effects, clearly discernible, covering the entire area.

Chapter 15 Installation of Internal Supporting Facilities

15.1 Explosion-Proof Workbench and Cabinet Installation

  • Workbenches are made of steel or stainless steel, with anti-static rubber pads laid on the work surface;
  • Workbenches and filing cabinets are placed stably, fixed to the floor or fitted with anti-tipping devices;
  • Metal cabinets are reliably grounded to eliminate static electricity;
  • Layout is reasonable, leaving operating and maintenance access aisles with a width not less than 800mm.

15.2 Explosion-Proof Socket and Distribution Terminal Installation

  • Explosion-proof sockets are installed at a height of 0.3-0.5m above the floor, equipped with switches and protective shutters;
  • Socket circuits are configured with residual current circuit breakers (RCD) with a tripping current of 30mA;
  • Socket wiring is correct, with phase, neutral, and ground wires correspondingly connected, and reliable grounding;
  • After installation, test phase sequence, grounding, and residual current protection functions.

15.3 Insulation and Anti-Static Floor Treatment

  • Original floor is ground and cleaned, coated with conductive primer;
  • Anti-static flooring is installed or anti-static floor paint is applied, with thickness conforming to the design;
  • Floor grounding copper strip grid is laid out, connected to the equipotential grounding busbar;
  • After construction, test surface resistance and system resistance, conforming to anti-static standards.

15.4 Label and Signage Installation

  • Product nameplates, explosion-proof markings, and warning signs are installed on the exterior of enclosures;
  • Safety operating procedures, emergency evacuation diagrams, and hazard notification signs are installed inside;
  • Electrical circuits, valves, and pipelines are labeled with name, number, and flow direction;
  • Hazardous areas are equipped with warning signs such as “No Fire” and “Explosion Hazard”.

15.5 Explosion-Proof Sealing and Gap Treatment

  • Panel seams, wall penetrations, and pipeline interface points are sealed with explosion-proof sealant;
  • Cable trays and conduit penetrations through walls are sealed with fire-stop putty;
  • Door and window gaps are inspected, with defective seals adjusted or gaskets replaced;
  • After all gap treatments, an air tightness check is performed with no obvious leakage.

Chapter 16 Pre-Commissioning Preparation and Inspection

16.1 Pre-Commissioning Visual and Installation Quality Inspection

Before system commissioning, a comprehensive inspection of the overall installation quality shall be conducted. Only after confirming that the installation is satisfactory may the commissioning phase proceed.

Structural visual inspection: Container body without deformation or damage, anti-corrosion coating intact, doors and windows open/close flexibly, good sealing;

System installation completeness inspection: All equipment, pipelines, and accessories for each system are fully installed with no omissions;

Connection reliability inspection: Bolts tightened, welding qualified, wiring secure, grounding reliable;

Sealing performance inspection: All interfaces and gaps are properly sealed with no open ends or missing seals;

Safety protection inspection: Rotating parts have protective guards in place, hazardous locations have warnings, and fire-fighting equipment is in position.

16.2 Commissioning Tools and Instrument Preparation

Before commissioning, prepare all required instruments and meters, confirming they are within the calibration validity period and in good working condition:

Category Instruments
Electrical Multimeter, clamp ammeter, megohmmeter, ground resistance tester, phase sequence meter
Ventilation & Air Conditioning Anemometer, micromanometer, thermohygrometer, sound level meter, refrigerant pressure gauge
Safety Combustible gas detector, static electricity tester, illuminance meter
General Stopwatch, tape measure, spirit level, two-way radios

16.3 Commissioning Personnel Qualification and Safety Requirements

  • Commissioning personnel possess relevant professional qualifications and are familiar with explosion-proof equipment performance and commissioning methods;
  • A safety briefing is conducted before commissioning, clarifying commissioning risks and prevention/control measures;
  • Commissioning in explosion-proof areas strictly complies with explosion-proof safety regulations, carrying combustible gas detectors;
  • Live electrical commissioning follows electrical safety procedures, with lockout/tagout and dedicated supervision;
  • At least two persons are required for commissioning operations; solo work is strictly prohibited.

16.4 Commissioning Plan Preparation and Approval

  • Before commissioning, a dedicated commissioning plan is prepared, specifying commissioning items, methods, procedures, acceptance criteria, and personnel assignments;
  • The plan is approved by the technical director; major commissioning projects require confirmation by the supervision engineer and owner;
  • Before commissioning, a plan briefing is conducted for participating personnel to familiarize them with procedures and standards;
  • Emergency response plans for commissioning are established to address abnormal situations that may occur during commissioning.

16.5 Commissioning Safety Protection Measures

  • Warning signs are set up in the commissioning area, prohibiting entry of unrelated personnel;
  • Before energizing equipment, verify voltage presence and confirm correct voltage level and reliable grounding;
  • Before commissioning rotating equipment, manually rotate to check for smooth rotation before energizing;
  • When commissioning gas alarm and fire protection systems, notify relevant personnel to avoid panic;
  • Emergency equipment is available; in case of abnormality, immediately stop the machine, disconnect power, and troubleshoot.

Chapter 17 Mechanical Structure System Commissioning

17.1 Container Structure Strength and Sealing Commissioning

17.1.1 Container Air Tightness Testing

Positive pressure method test: Close all doors, windows, and ventilation openings, seal all openings, and inflate compressed air into the container until the pressure rises to 50Pa;

After stabilization, record the pressure drop. Qualification criterion: pressure drop not greater than 10Pa within 30 minutes;

Use soapy water or smoke agent to detect leakage points, focusing on door frames, window frames, pipeline interfaces, and panel seams;

Mark leakage points, rectify and re-seal, then retest until qualified.

17.1.2 Structural Load Testing

  • Perform load sampling tests on the container floor, roof, and lifting lugs, applying 1.2 times the rated load and maintaining for 1 hour;
  • Check for permanent structural deformation, weld cracking, and bolt loosening;
  • Deflection test: maximum roof deflection not greater than 1/200 of the span, floor not greater than 1/300;
  • After unloading, the structure recovers well with no residual deformation, considered qualified.

17.1.3 Seismic Performance Verification

  • Perform calculation verification or simulated vibration testing according to the designed seismic fortification category;
  • Equipment fixing, pipeline connections, and cabinet installations are free from loosening or detachment;
  • Electrical connections are reliable, and explosion-proof performance is not affected;
  • Conforms to the requirements of GB 50011 Code for Seismic Design of Buildings.

17.2 Explosion-Proof Door and Window System Commissioning

17.2.1 Opening and Closing Flexibility Commissioning

  • Manually operate doors and windows 50 times, checking for jamming, abnormal noise, or sagging;
  • Adjust hinges, rollers, and tracks to ensure moderate operating force with no sticking;
  • Commission the door closer closing speed with two-stage speed adjustment, smooth closing without impact;
  • Door locks operate flexibly, with smooth latch extension/retraction and accurate alignment.

17.2.2 Sealing Performance Testing

  • After closing doors and windows, use feeler gauges to check sealing gaps, with no through gaps;
  • During container positive pressure testing, no obvious leakage around doors and windows;
  • Water spray test: spray the exterior for 15 minutes, with no water seepage or leakage on the interior;
  • Sealing gaskets are uniformly compressed with no localized over-tightening or looseness.

17.2.3 Door Lock and Interlock Function Commissioning

  • Door lock keys and handles operate smoothly, with normal deadbolt and unlock functions;
  • For doors with electromagnetic interlocks, commission the interlock logic: reliable unlock when energized, locked when de-energized;
  • During fire alarm interlock, access control automatically unlocks for evacuation;
  • Test repeatedly 20 times, all actions normal with no faults.

17.3 Ventilation System Stand-Alone Commissioning

17.3.1 Fan Operating Condition Inspection

  • Before energizing, manually rotate to check that the impeller has no sticking or friction and rotates freely;
  • Jog-start to check correct rotation direction and absence of abnormal noise;
  • Run for 30 minutes continuously, checking that motor current does not exceed the rated value and temperature rise is normal;
  • Check fan vibration; bearing vibration velocity not greater than 4.5mm/s;
  • Check bearing temperature: rolling bearings not exceeding 80°C, sliding bearings not exceeding 70°C.

17.3.2 Air Volume and Air Pressure Testing

  • Use an anemometer to measure air velocity at duct outlets or air supply openings, calculating air volume;
  • Use a micromanometer to test fan total pressure and static pressure, conforming to design parameters;
  • Adjust air valves to test air volume uniformity at each outlet, with deviation not greater than ±15% of the design value;
  • In emergency ventilation mode, air volume meets the air change rate requirement.

17.3.3 Ventilation System Noise Detection

  • Test noise levels at 1m from the fan, at a height of 1.2m;
  • Indoor working zone noise not greater than 65dB(A);
  • If noise exceeds the standard, inspect vibration dampers and silencers, rectify, and retest.

17.3.4 Flame Arrestor and Pressure Relief Function Testing

  • Flame arrestor ventilation resistance test: resistance value conforms to product parameters, not affecting air volume;
  • Pressure relief valve opening pressure test: adjust to the setpoint, automatically opening on overpressure and automatically closing after pressure recovery;
  • Simulate overpressure conditions; the pressure relief valve actuates sensitively with no sticking or leakage.

Chapter 18 Air Conditioning and Environmental Control System Commissioning

18.1 Explosion-Proof Air Conditioning System Commissioning

18.1.1 Cooling Mode Commissioning

  • Set to cooling mode, set temperature to 26°C, start the air conditioner;
  • Check that the compressor starts normally, runs smoothly, with no abnormal noise;
  • Test supply and return air temperatures; return air temperature gradually decreases, and the compressor cycles on/off normally after reaching the set temperature;
  • Run for 1 hour, test indoor temperature uniformity, temperature difference not greater than ±2°C;
  • Check refrigerant pressure and current, with no alarms or faults.

18.1.2 Heating Mode Commissioning

  • Switch to heating mode, set temperature to 20°C;
  • Check that the four-way valve reverses correctly, and supply air temperature gradually rises;
  • Run for 30 minutes, indoor temperature reaches the setpoint, stable operation;
  • Check that the defrost function works normally, with no cold air blowing indoors during defrosting.

18.1.3 Dehumidification and Humidification Function Commissioning

  • Enable dehumidification mode, run for 1 hour, test indoor humidity decrease, reaching the setpoint;
  • For air conditioners with humidification function, enable humidification; humidity rises and stabilizes, with no condensation dripping;
  • Temperature and humidity control accuracy: temperature ±1°C, humidity ±5%RH.

18.1.4 Temperature Control Accuracy Testing

  • Arrange multiple temperature and humidity measurement points indoors, recording temperature changes over 2 hours;
  • After stabilization, temperature fluctuation not greater than ±1°C, meeting control accuracy requirements;
  • Temperature difference between different zones not greater than 2°C, with good temperature uniformity.

18.1.5 System Energy Consumption Testing

  • Use a power meter to test air conditioner operating power and current;
  • Calculate cooling/heating energy efficiency ratio, conforming to product nameplate values;
  • Standby power consumption and auxiliary electric heating power conform to design.

18.2 Positive Pressure Explosion-Proof System Commissioning (for Positive Pressure Type)

18.2.1 Positive Pressure Supply System Commissioning

  • Start the positive pressure fan, check rotation direction, air volume, and operating noise are normal;
  • Purging mode: start the purging program, displace the air inside the container per the design time, with purging air volume meeting requirements;
  • After purging is completed, automatically switch to normal positive pressure mode.

18.2.2 Pressure Control and Stabilization Commissioning

  • Adjust supply air volume and pressure relief valves to stabilize internal positive pressure at 50-200Pa;
  • Real-time pressure monitoring via micromanometer, fluctuation range not greater than ±20Pa;
  • After door opening or exhaust disturbance, the system can quickly restore stable pressure;
  • Pressure controller actuates accurately, starting/stopping fans or adjusting dampers to maintain pressure.

18.2.3 Under-Pressure Alarm and Interlock Commissioning

  • Simulate pressure drop; when pressure drops below the lower limit setpoint (generally 30Pa), an audible and visual under-pressure alarm is triggered;
  • When pressure continues to drop to the interlock value (generally 20Pa), automatically cut off non-explosion-proof power inside the container;
  • After pressure returns to normal, manual reset is required to restore power, preventing accidental energization;
  • Test repeatedly 5 times; alarm and interlock actuation are accurate and reliable.

18.2.4 Ventilation Exchange and Purging Function Commissioning

  • Set the air exchange cycle; the system periodically exchanges air to ensure fresh air;
  • Automatic purging before startup; purging time is calculated based on container volume, ensuring complete displacement;
  • When purging is incomplete, the main power cannot be switched on, achieving forced purging interlock.

18.3 Temperature and Humidity Environmental Uniformity Testing

  • Arrange 9 measurement points evenly in the working area of the container, divided into upper, middle, and lower layers;
  • After the air conditioning system runs stably for 2 hours, record temperature and humidity at each point;
  • Calculate temperature uniformity: (maximum temperature – minimum temperature) / average temperature ≤ 2°C;
  • Humidity uniformity: maximum humidity – minimum humidity ≤ 10%RH.

Chapter 19 Electrical System Commissioning

19.1 Power Supply System Commissioning

19.1.1 Incoming Power Source Inspection

  • Before closing the switch, check incoming power voltage, frequency, and phase sequence to confirm compliance with equipment requirements;
  • Three-phase voltage deviation not greater than ±7%, frequency deviation ±0.2Hz;
  • Check that the parameter settings of incoming switches and protective devices are correct.

19.1.2 Power Distribution System Energization Testing

  • Energize level by level, main first then branch, high voltage first then low voltage;
  • Each level of switch operates normally with no tripping, abnormal noise, or odor;
  • Test that each outgoing circuit voltage is normal and phase sequence is correct;
  • Simulate overload and short-circuit faults; protective devices actuate accurately with tripping times conforming to settings.

19.1.3 Short-Circuit and Overload Protection Testing

  • Use test buttons to test circuit breaker short-circuit and overload protection functions, confirming normal operation;
  • Verify protection settings match the load, with no nuisance tripping or failure to trip;
  • Residual current circuit breaker (RCD) simulated leakage test: trips within 0.1s at 30mA.

19.1.4 Residual Current Protection Function Testing

  • Test socket circuit RCD via test button, confirming reliable tripping;
  • Test residual current operating current and operating time, conforming to regulations;
  • After RCD tripping, reset and re-energize only after the fault is cleared.

19.2 Lighting System Commissioning

  • Close each lighting circuit switch individually; all luminaires illuminate with no flickering or failure to light;
  • Test switch control logic, confirming correct circuit correspondence;
  • For emergency lighting, cut off the main power; emergency lights illuminate immediately, with duration meeting requirements;
  • Test illuminance values conforming to design requirements.

19.3 Communication and Surveillance System Commissioning

19.3.1 Network Communication Testing

  • Connect computers to the network, test ping values, bandwidth, and packet loss rate, conforming to requirements;
  • Devices on the LAN interconnect and share resources normally;
  • External network access test: normal access, network speed meeting requirements.

19.3.2 Telephone Voice Testing

  • Internal and external line call tests: clear voice, no noise or crossed lines;
  • Dialing, answering, and hang-up functions are normal, caller ID accurate;
  • Explosion-proof telephones have responsive keypads, with hands-free and handset calls functioning normally.

19.3.3 Video Surveillance Commissioning

  • Camera images are clear, night vision functions normal;
  • PTZ control is smooth; zoom, rotation, and preset position functions are normal;
  • Video recording and storage are normal; playback is clear with accurate timestamps;
  • Remote surveillance access is normal with smooth video.

19.3.4 Data Transmission Stability Testing

  • Run continuously for 24 hours, monitoring communication stability with no interruptions or packet loss;
  • Communication functions normally under interference conditions, with bit error rate meeting requirements;
  • Data upload/download rates are stable, meeting business requirements.

Chapter 20 Safety Protection System Commissioning

20.1 Grounding and Anti-Static System Testing

20.1.1 Ground Resistance Re-Testing

  • After system installation, use a ground resistance tester to re-test the main ground resistance;
  • Common grounding system: resistance ≤ 1Ω; independent protective grounding: ≤ 4Ω;
  • Conduct continuity testing at each equipment grounding point, with no open circuits or loose connections.

20.1.2 Equipotential Connection Testing

  • Test the potential difference between any two metal components, not greater than 1V;
  • Equipotential bonding conductors have good continuity, with contact resistance ≤ 0.03Ω;
  • All metal pipes, racks, and cabinets are connected to the equipotential network.

20.1.3 Anti-Static Performance Testing

Test Item Standard Value
Anti-static floor surface resistance 10⁶-10⁹Ω
Workbench surface anti-static resistance 10⁶-10⁸Ω
Human body static eliminator contact resistance 10⁵-10⁹Ω
Shoes, clothing anti-static performance Conforms to standards

20.2 Gas Detection System Commissioning

20.2.1 Detector Calibration and Adjustment

  • Use standard gas to calibrate detectors by introducing gas of standard concentration;
  • Adjust zero point and span; display value deviation from standard value not greater than ±5% FS;
  • Calibration cycle conforms to regulations; newly installed equipment must be calibrated on-site;
  • Record calibration data and retain calibration records.

20.2.2 Concentration Alarm Threshold Commissioning

  • Combustible gas low-limit alarm set at 25% LEL, high-limit alarm at 50% LEL;
  • Toxic gas alarm values set at 1/2 and 1× the occupational exposure limit;
  • Simulate introducing standard gas; alarm accurately triggers when the threshold is reached;
  • Alarm value deviation not greater than ±10% of the setpoint.

20.2.3 Audible and Visual Alarm Function Testing

  • Trigger an alarm; the audible and visual alarm device actuates immediately, sound pressure level meets standards, and the flashing light is clearly visible;
  • The alarm controller displays alarm location, concentration, and time, recording alarm events;
  • Silence and reset functions are normal; alarm records are queryable.

20.2.4 Interlocked Exhaust and Power-Off Function Commissioning

  • At low-limit alarm, automatically start exhaust fans, switching to emergency ventilation;
  • At high-limit alarm, automatically cut off non-fire-protection power and close air conditioning fresh air supply;
  • Interlocked action delay time conforms to settings, with no false interlocking;
  • After the alarm is cleared, manually reset to restore normal operation.

20.3 Fire Protection System Commissioning

20.3.1 Fire Extinguishing Device Activation Testing

  • Manually activate the fire extinguishing device; discharge is normal with coverage range meeting requirements;
  • In automatic mode, after fire alarm, delayed activation occurs, with audible/visual pre-alarm before discharge;
  • Mechanical emergency activation function works normally and can be manually operated during power failure;
  • After testing, refill and reset; check piping for leaks.

20.3.2 Fire Interlock Function Commissioning

  • After fire alarm trigger, interlock activation of audible/visual alarms, emergency lighting, and evacuation signage;
  • Interlock cut-off of non-fire-protection power, activation of smoke exhaust and fire extinguishing systems;
  • Interlock signals are uploaded to the fire control room with normal feedback;
  • Interlock logic is correct, with action sequencing conforming to design.

20.3.3 Emergency Evacuation Signage Testing

  • After power failure, evacuation signage illuminates immediately with brightness meeting standards;
  • Photoluminescent signage remains clearly visible in darkness with duration meeting requirements;
  • Evacuation direction indications are correct, pointing to safety exits.

Chapter 21 Overall Explosion-Proof Performance Comprehensive Commissioning

21.1 Explosion-Proof Sealing Performance Comprehensive Inspection

  • Inspect sealing of all explosion-proof joint surfaces, cable entry devices, junction boxes, and terminal boxes;
  • Flameproof joint gaps, widths, and surface roughness conform to GB 3836.2;
  • Cable entry devices have qualified clamping and sealing; cables are secure with no leakage paths;
  • Overall container positive pressure leakage rate conforms to explosion-proof standard requirements.

21.2 Explosion-Proof Electrical Clearance and Creepage Distance Verification

  • Open explosion-proof electrical equipment and measure electrical clearance and creepage distance between live parts and the enclosure;
  • Parameters under different voltage levels and pollution degrees conform to corresponding explosion-proof standards;
  • Insulation parts are intact with no cracks or tracking marks;
  • Terminal spacing is sufficient with no short-circuit risk.

21.3 Overall Explosion-Proof Level Compliance Verification

  • Verify the explosion-proof certificates of all explosion-proof components, with levels not lower than the overall design level;
  • Check that explosion-proof markings are correct and consistent with the actual explosion-proof type;
  • Verify that installation methods comply with explosion-proof requirements, with no installation defects that reduce the explosion-proof level;
  • Issue an explosion-proof performance compliance inspection report, confirming suitability for the corresponding hazardous area classification.

21.4 Extreme Condition Simulation Testing

Condition Requirement
High temperature At ambient temperature 40°C, run continuously for 8 hours; equipment surface temperature does not exceed the temperature class limit
Low temperature At low ambient temperature, equipment starts normally; sealing materials show no brittle cracking
High humidity At high humidity, insulation resistance meets standards; no condensation short-circuits
Vibration Simulating transport and operating vibration; fasteners remain tight, electrical connections reliable, explosion-proof performance unaffected

21.5 Continuous Operation Stability Testing

  • All systems operate continuously at full load for 72 hours;
  • Record operating parameters every 2 hours, including temperature, pressure, current, voltage, and gas concentration;
  • During the period, no fault shutdowns, no abnormal alarms, and no performance degradation;
  • After testing, all components show no abnormal wear, overheating, or loosening.

Chapter 22 Commissioning Records and Problem Rectification

22.1 Commissioning Record Requirements

  • Commissioning records are filled out simultaneously during the commissioning process, with true and accurate data; no retroactive filling allowed;
  • Record contents include: commissioning item, commissioning time, environmental conditions, instruments/equipment, commissioning data, qualification determination, and commissioning personnel;
  • After completion of each sub-item commissioning, signatures are obtained from the contractor, supervision engineer, and owner’s representative;
  • Commissioning records are organized and archived as completion materials and acceptance basis.

22.2 Common Commissioning Problems and Solutions

No. Problem Symptom Possible Cause Solution
1 Container positive pressure cannot be maintained, large leakage Poor door/window sealing, air leakage at pipeline interfaces Adjust door/window sealing gaskets, seal leakage points
2 Excessive fan vibration and noise Fan imbalance, failed vibration dampers, duct resonance Perform dynamic balancing, replace vibration pads, reinforce ducts
3 Poor air conditioning cooling performance Insufficient refrigerant, clogged filters, low airflow Replenish refrigerant, clean filters, adjust airflow
4 Gas detector false alarms Incorrect calibration, environmental interference, improper position Re-calibrate, avoid interference sources, adjust position
5 Ground resistance exceeds standard Insufficient ground electrodes, high soil resistivity Add ground electrodes, use grounding resistance reducing agents
6 Lighting fixture flickering Unstable voltage, loose wiring, fixture fault Check power supply, tighten wiring, replace fixtures

22.3 Retest Requirements After Rectification

  • Non-conforming commissioning items must be rectified, and re-commissioning performed after rectification;
  • Invite the supervision engineer and owner to witness re-testing, recording data before and after rectification;
  • Major problem rectification requires preparation of a rectification plan, implemented after approval;
  • All problems must be closed-loop before proceeding to the acceptance stage.

22.4 Commissioning Report Preparation

After all commissioning is completed, prepare a system commissioning report including:

  • Project overview, commissioning basis;
  • Commissioning organization and personnel;
  • Commissioning instruments and equipment;
  • Commissioning content and data for each system;
  • Commissioning problems and rectification status;
  • Commissioning conclusions;
  • Appendices: commissioning records, test reports.

Chapter 23 Acceptance Process and Reference Standards

23.1 Acceptance Stage Division

Explosion-proof container acceptance is divided into three stages; delivery for use is only permitted after each level of acceptance is passed:

Stage Description
Sub-item acceptance After each system installation is completed, sub-item engineering acceptance is conducted separately; only after passing may commissioning proceed
Pre-completion acceptance After all commissioning is completed, the contractor completes self-inspection and applies to the supervision unit to organize pre-acceptance
Final completion acceptance After pre-acceptance rectifications are completed, the owner organizes relevant units including design, construction, supervision, and manufacturer for formal final acceptance; where necessary, safety supervision and fire departments may be invited to participate

23.2 Standards and Specifications for Acceptance Basis

  • National and industry relevant construction quality acceptance specifications (see Chapter 3);
  • Design drawings, technical agreements, and contract requirements;
  • Explosion-proof certificates, product manuals, and factory inspection reports;
  • Construction process documentation, commissioning records, and test reports.

23.3 Acceptance Organization and Personnel Requirements

  • Final acceptance group: composed of representatives from the owner, supervision, design, construction, and manufacturer, with one group leader appointed;
  • Professional acceptance personnel possess relevant professional knowledge and acceptance experience;
  • Dedicated explosion-proof acceptance requires participation of personnel with professional explosion-proof qualifications;
  • Acceptance personnel remain objective and impartial, accepting according to standards, and signing acceptance opinions.

Chapter 24 Sub-Item Acceptance Content and Standards

24.1 Structure Installation Acceptance

Item Acceptance Standard
Container positioning Plan position deviation ≤ 10mm, elevation deviation ±10mm, levelness ≤ 1‰, verticality ≤ 1‰
Fixing and connections Welds full and free of defects; bolt torque meets requirements; anti-loosening devices complete
Door and window systems Flexible opening/closing, good sealing, accessories complete, explosion-proof parameters meet requirements
Exterior anti-corrosion Anti-corrosion coating intact, no obvious scratches or rust; touch-up paint color consistent
Foundation works Foundation dimensions, strength, and ground resistance conform to design; no visual defects

24.2 Electrical System Acceptance

Item Acceptance Standard
Cable laying Neat arrangement, clear marking, secure fixing, qualified insulation
Power distribution equipment Secure installation, correct wiring, reliable grounding, intact explosion-proof sealing
Lighting and communication All luminaires lit, illuminance meets standards, clear communication, normal functions
Grounding system Ground resistance meets standards, equipotential connections complete, clear marking
Protection functions Short-circuit, overload, and residual current protection actuate accurately with correct parameter settings

24.3 Ventilation and Air Conditioning System Acceptance

Item Acceptance Standard
Duct system Smooth installation, secure supports/hangers, qualified air tightness, intact insulation
Fan equipment Stable operation, air volume and pressure meet standards, noise meets requirements
Air conditioning system Normal cooling/heating, temperature and humidity control accuracy meets standards, stable operation
Positive pressure system Stable pressure, purging, alarm, and interlock functions normal
Flame arrest and pressure relief Flame arrestors and pressure relief valves correctly installed, reliable actuation

24.4 Safety Protection System Acceptance

Item Acceptance Standard
Gas detection Detector placement reasonable, calibration qualified, accurate alarms, normal interlocking
Fire protection system Extinguishing devices complete, interlock logic correct, emergency signage complete
Anti-static Floor, work surface, and human body discharge device resistance conforms to standards
Audible/visual alarm Sound pressure and flash meet standards, reliable triggering, comprehensive coverage

24.5 Explosion-Proof Performance Dedicated Acceptance

Item Acceptance Standard
Qualification verification All explosion-proof product certificates complete and valid; models match on-site equipment
Explosion-proof structure Flameproof joint surfaces, sealing structures, and entry devices conform to explosion-proof standards
Installation compliance Installation methods in explosion-proof areas conform to regulations; no defects reducing explosion-proof level
Overall performance Air tightness, temperature class, and explosion-proof level meet the requirements of the use area

Chapter 25 Completion Documentation Delivery

25.1 Completion Documentation List

After final acceptance, the contractor delivers a complete set of completion documents to the owner, including at minimum:

  • Completion report, acceptance certificate;
  • Construction organization design, construction plans, technical briefing records;
  • Product certificates, explosion-proof certificates, factory inspection reports, instruction manuals;
  • Material and equipment incoming inspection records;
  • Concealed works acceptance records, sub-item engineering acceptance records;
  • System commissioning records, commissioning reports, and test reports;
  • As-built drawings (including civil, electrical, ventilation, and fire protection);
  • Bill of quantities, engineering change orders;
  • Quality warranty certificate, after-sales service commitments.

25.2 As-Built Drawing Preparation

  • As-built drawings are prepared according to actual construction conditions, consistent with on-site conditions;
  • Equipment models, locations, pipeline routing, elevations, and interface parameters are marked;
  • Drawings are stamped with the as-built drawing stamp, signed by the draftsman and reviewer;
  • Provide one paper set and one electronic set; electronic format is CAD or PDF.

25.3 Qualification Documents and Test Reports

  • Copies of explosion-proof certificates for all explosion-proof products stamped with the manufacturer’s official seal;
  • Test reports for ground resistance, insulation resistance, air volume, and illuminance;
  • Verification certificates for special equipment and measuring instruments;
  • Copies of contractor qualifications and personnel qualification certificates.

25.4 Operation and Maintenance Manual Delivery

  • Deliver this installation and commissioning manual along with operation and maintenance manuals for each subsystem;
  • Clarify daily operation procedures, maintenance requirements, and safety precautions;
  • Provide manufacturer contact information for technical support and after-sales service.

Chapter 26 Personnel Training and Technical Briefing

26.1 Operation and Usage Training

  • Training target: operating personnel and management personnel of the user unit;
  • Training content:
  • Basic principles of the explosion-proof container, explosion-proof levels, and scope of application;
  • Startup, shutdown, and daily operation procedures for each system;
  • Identification and handling of control panel and alarm information;
  • Normal operating parameter ranges and observation methods;
  • Training method: theoretical explanation + on-site practical operation; personnel must pass assessment before taking up their posts;
  • Training records are issued after training and retained for future reference.

26.2 Daily Maintenance Training

  • Daily inspection content, frequency, and inspection methods;
  • Replacement methods for wearing parts, such as filters, sealing gaskets, and detector sensors;
  • Troubleshooting and handling of common minor faults;
  • Maintenance safety precautions and maintenance regulations for explosion-proof areas.

26.3 Safety Operation Standards Training

  • Safety management regulations for explosion-proof areas, personnel and equipment entry requirements;
  • Safety procedures for hot work, electrical use, and maintenance operations;
  • Electrostatic protection requirements, human body static discharge regulations;
  • Prohibited behaviors and their hazardous consequences.

26.4 Emergency Response Training

  • Emergency handling procedures for gas leaks, fires, and electrical faults;
  • Alarm, evacuation, self-rescue, and mutual rescue methods;
  • Usage of emergency equipment;
  • Emergency contact methods: manufacturer technical support +86 13538869979, service hotline +86 13538869979.

Chapter 27 Daily Maintenance System

27.1 Daily Inspection Content and Frequency

Daily inspections are conducted by the shift duty personnel, recording operating status:

  • Check the container exterior for damage or rust, and check that doors and windows are properly closed;
  • Check the air conditioning and ventilation systems for normal operating sounds and temperatures;
  • Check the gas alarm controller for alarms and normal readings;
  • Check lighting and communication systems are normal;
  • Record indoor temperature, humidity, voltage, current, and other operating parameters;
  • Report any abnormalities promptly and maintain inspection records.

27.2 Monthly Maintenance Content

A comprehensive monthly maintenance is conducted by professional maintenance personnel:

  • Clean dust inside and outside the container, remove debris, and maintain a clean environment;
  • Check for loose fasteners, especially at door/window, equipment, and pipeline connections;
  • Clean air conditioning filters and ventilation filters; replace if severely clogged;
  • Check grounding connections for loosening or rust;
  • Test emergency lighting and gas alarm functions;
  • Check sealing gaskets for aging or cracking; replace promptly;
  • Check fire extinguisher pressure and expiration dates to ensure readiness.

27.3 Quarterly Maintenance Content

In-depth maintenance is performed quarterly:

Item Description
Bearing lubrication Apply grease to fan and air conditioner motor bearings
Electrical connections Tighten all electrical terminal connections; check for loose connections and overheating
Gas detector calibration Calibrate zero point of gas detectors; perform span calibration when necessary
Interlock testing Test fire protection interlock and positive pressure interlock functions
Flameproof joint surfaces Inspect, clean, and apply anti-rust grease
Resistance measurement Measure ground resistance and insulation resistance; record data
Anti-corrosion coating Inspect coating; touch up paint on damaged areas

27.4 Annual Overhaul and Testing Content

A comprehensive annual overhaul and inspection is performed, which may be implemented by contacting manufacturer professionals:

  • Complete disassembly and cleaning of all systems, replacing aged wearing parts;
  • Comprehensive inspection of explosion-proof electrical equipment per GB 3836.15 requirements;
  • Full-scale calibration of gas detectors; replace sensors upon expiration;
  • Air conditioning refrigerant pressure check, replenish refrigerant, clean evaporator and condenser;
  • Comprehensive grounding system testing; rectify corroded and loose connection points;
  • Comprehensive container anti-corrosion coating inspection; large-area touch-up painting or re-spraying;
  • Issue annual maintenance inspection report, assessing equipment health status.

Chapter 28 Maintenance Points for Each System

28.1 Container Structure Maintenance

  • Regularly clean the container surface to avoid long-term attachment of corrosive substances;
  • Inspect the anti-corrosion coating annually; promptly touch up paint on scratches and damage;
  • In coastal and chemical corrosive areas, inspect anti-corrosion status semi-annually;
  • Regularly clean water and debris from the roof to prevent corrosion from standing water;
  • Prohibit unauthorized welding, drilling, or adding heavy objects on the container which may damage the structure and explosion-proof performance.

28.2 Explosion-Proof Door and Window Maintenance

  • Keep door/window tracks and hinges clean, regularly apply lubricating grease to ensure flexible opening and closing;
  • Check sealing gaskets monthly; clean oil stains promptly and replace aged or cracked gaskets;
  • Wipe flameproof joint surfaces regularly, applying a thin layer of anti-rust grease to prevent corrosion;
  • Check door locks and door closers regularly; adjust and repair if operating abnormally;
  • Prohibit forceful impact or prying of doors and windows to prevent deformation affecting explosion-proof sealing.

28.3 Ventilation and Air Conditioning System Maintenance

Component Maintenance Requirement
Filter replacement Primary filter: clean or replace every 1-3 months; medium filter: replace every 3-6 months
Fan maintenance Check bearings and belts annually; replace worn parts; test motor insulation
Air conditioner maintenance Clean evaporator and condenser annually; check refrigerant pressure; clear drain lines
Flame arrestor maintenance Check flame arrestor elements semi-annually; clean blockages; replace damaged units
Positive pressure system Calibrate pressure sensors monthly; test under-pressure interlock function

28.4 Electrical System Maintenance

  • Regularly remove dust, keeping electrical equipment clean and dry;
  • Tighten terminal connections to prevent loosening and overheating;
  • Measure insulation resistance and ground resistance annually; archive data;
  • Regularly inspect explosion-proof junction boxes and cable glands; tighten if loose; replace when sealing fails;
  • Prohibit unauthorized replacement of electrical components; when replacement is necessary, use products of the same explosion-proof level.

28.5 Grounding and Anti-Static System Maintenance

  • Check grounding terminals and equipotential connection points quarterly; treat rust promptly;
  • Re-measure ground resistance annually; rectify promptly if exceeding standards;
  • Regularly clean anti-static floors to avoid oil contamination and damage that affects anti-static performance;
  • Regularly test human body static discharge devices to ensure normal function;
  • Prohibit unauthorized removal of grounding connection wires.

28.6 Gas Detection and Fire Protection System Maintenance

Item Maintenance Requirement
Gas detectors Clean sensor heads monthly; calibrate annually; sensor service life 2-3 years; replace upon expiration
Alarm controller Regularly remove dust; check backup power discharge time
Fire extinguishing devices Check pressure and expiration date monthly; refill or replace upon expiration
Audible/visual alarms Test monthly to ensure normal function
Fire escape routes Keep unobstructed; ensure emergency signage is intact and clear

Chapter 29 Common Fault Diagnosis and Troubleshooting

29.1 Structural and Sealing Faults

Fault Symptom Cause Analysis Troubleshooting Method
Door/window air or water leakage Sealing gasket aged or detached, door/window deformed Replace sealing gaskets, correct door/window alignment
Container rust Anti-corrosion coating damaged, environmental corrosion Remove rust and touch up paint; increase anti-corrosion level in harsh environments
Door lock cannot open Lock rusted, misaligned Remove rust and lubricate; adjust latch position
Condensation inside container Insulation failure, insufficient ventilation Repair insulation; strengthen ventilation; enable dehumidification

29.2 Ventilation and Air Conditioning Faults

Fault Symptom Cause Analysis Troubleshooting Method
Fan does not start Power supply fault, motor burned out, protection tripped Check power supply and motor; reset protection; replace damaged parts
Insufficient air volume Clogged filters, air valve closed, belt slipping Clean filters, adjust air valves, tension or replace belts
Air conditioner not cooling Refrigerant leak, compressor fault, clogged filters Locate leak and recharge refrigerant, repair compressor, clean filters
Unstable positive pressure Large leakage, fan fault, inaccurate pressure sensor Seal leaks, repair fan, calibrate sensor
Excessive noise Fan vibration, duct resonance, loose fasteners Reinforce vibration dampers, tighten bolts, add silencers to ducts

29.3 Electrical System Faults

Fault Symptom Cause Analysis Troubleshooting Method
Switch tripping Short circuit, overload, leakage Identify fault point, clear short circuit/overload, address leakage
Lighting not working Lamp burned out, switch fault, open circuit Replace lamp, repair switch, restore circuit
Communication interruption Line fault, equipment fault, parameter error Check lines, restart equipment, correct parameters
Ground resistance exceeds standard Ground electrode corrosion, loose connection, dry soil Treat corrosion points, tighten connections, water or add resistance reducing agent

29.4 Safety System Faults

Fault Symptom Cause Analysis Troubleshooting Method
Detector false alarm Calibration drift, interfering gas present, improper position Re-calibrate, eliminate interference, adjust position
Detector does not alarm Sensor failed, line disconnected, controller fault Replace sensor, restore circuit, repair controller
Audible/visual alarm not working Line fault, speaker damaged Check lines, replace alarm device
Fire extinguishing device accidental discharge Controller fault, detector false alarm Repair controller, investigate alarm cause, refill

29.5 Explosion-Proof Performance Degradation Faults

  • Flameproof joint surface rust or scratches: polish with fine sandpaper, replace components when severely damaged, apply anti-rust grease;
  • Seal aging: regularly replace sealing gaskets and O-rings, using original manufacturer parts;
  • Cable entry device loosening: tighten to specified torque; replace glands when sealing fails;
  • Unauthorized modification damaging explosion-proof structure: immediately restore to original condition, have explosion-proof performance tested by professionals;
  • When explosion-proof performance anomalies occur, usage must be stopped immediately; contact the manufacturer for testing and repair; operation under faulty conditions is strictly prohibited.

Chapter 30 Spare Parts and After-Sales Service

30.1 Common Spare Parts List

To ensure continuous operation, it is recommended that the user unit stock the following common spare parts:

Category Items
Sealing Door/window sealing gaskets, explosion-proof sealant, cable gland sealing rings
Electrical Explosion-proof lamps, fuses, push buttons, spare relays
Consumables Air conditioning filters, ventilation filters, desiccant
Wearing parts Fan belts, bearings, door lock fittings, door closers
Safety Gas detector sensors, fire extinguisher refill agent

30.2 Spare Parts Procurement Channels

  • All original spare parts can be purchased from Guangdong Lain Intelligent System Development Co., Ltd., ensuring matching specifications and reliable quality;
  • Service hotline: +86 13538869979 (WeChat same number), technical support: +86 13538869979;
  • Common spare parts available from stock; custom parts manufactured on demand with short delivery cycles;
  • Use of non-original inferior spare parts is prohibited to prevent reduction of explosion-proof performance and safety incidents.

30.3 After-Sales Service System

Guangdong Lain has established a comprehensive after-sales service system, providing customers with full-lifecycle support:

Service Description
Warranty service Product warranty period of 1 year; free repair and replacement for non-artificial damage during warranty
Technical support 7×24 hour technical hotline, remote guidance to resolve issues; on-site service within 48 hours for complex problems
Regular follow-up Quarterly telephone follow-up, annual on-site inspection, proactive problem identification
Upgrade and renovation Explosion-proof container upgrade and renovation services available to improve performance and expand functions
Training services Customized operation, maintenance, and safety training available

30.4 Warranty Service Commitment

  • Warranty period commences from the date of final acceptance;
  • Quality problems during the warranty period: manufacturer provides free repair and parts replacement;
  • Response within 2 hours of fault reports; general problems resolved remotely; major problems reach site within 24 hours within the province and 48 hours outside the province;
  • After the warranty period ends, lifetime repair service is provided, charging only cost price;
  • Long-term provision of technical consultation, upgrade and renovation, and spare parts supply services.

Chapter 31 General Safety Operation Rules

31.1 Safety Management Regulations for Explosion-Proof Areas

  • The interior and surrounding area of the explosion-proof container are classified as explosive hazardous areas; hazardous area management regulations are strictly enforced;
  • Open flames are strictly prohibited in the area; carrying lighters, matches, non-explosion-proof mobile phones, and other ignition sources or non-explosion-proof electrical devices is prohibited;
  • Personnel entering must wear anti-static work clothing and anti-static shoes, and touch the human body static discharge device to eliminate static electricity;
  • Wearing shoes with metal nails or chemical fiber clothing in the explosion-proof area is strictly prohibited;
  • Unauthorized modification of explosion-proof structures and electrical equipment is strictly prohibited.

31.2 Personnel Entry Requirements

  • Operators must undergo safety training and pass assessment to be certified before taking up their posts;
  • Outside personnel must obtain approval to enter, be accompanied by internal personnel, and comply with safety regulations;
  • Persons under the influence of alcohol or in poor mental state are strictly prohibited from entering;
  • Minors are strictly prohibited from entering explosion-proof work areas.

31.3 Electrical Safety Regulations

  • Unauthorized wiring is strictly prohibited; use of non-explosion-proof electrical equipment is strictly prohibited;
  • Electrical equipment maintenance requires power shutdown, implementing the “Power Off, Verify De-energized, Discharge, Tag Out, Lock Out” procedure;
  • Opening explosion-proof electrical enclosures while energized is strictly prohibited;
  • Upon detecting electrical odor, smoke, or abnormal sound, immediately cut off power, stop the equipment, and investigate the fault;
  • Operating electrical switches and equipment with wet hands is prohibited.

31.4 Hot Work Operation Prohibitions

  • All unauthorized hot work operations are strictly prohibited in the explosion-proof area;
  • Hot work requires a hot work permit, implementation of safety measures, and verification of combustible gas concentration within acceptable levels;
  • Before hot work, clear surrounding combustibles, equip fire-fighting equipment, and arrange a fire watch person;
  • After hot work, check and confirm no residual fire before leaving;
  • Outdoor hot work is prohibited when wind force is above level 5.

Chapter 32 Emergency Management System

32.1 Emergency Plan Preparation

The user unit shall prepare a dedicated emergency plan for the explosion-proof container based on on-site conditions, including:

  • Emergency organization structure and responsibilities;
  • Risk identification and assessment;
  • Emergency handling procedures for various types of accidents;
  • Emergency materials and equipment;
  • Emergency contact methods;
  • Emergency evacuation routes and assembly points;
  • Emergency drill and training requirements.

32.2 Emergency Response for Common Scenarios

32.2.1 Gas Leak Emergency Response

  • Upon detecting a gas leak or gas alarm triggering, immediately stop operations and cut off non-fire-protection power;
  • Activate emergency exhaust ventilation to enhance air exchange;
  • Personnel evacuate upwind to a safe area and verify personnel count;
  • Call the emergency phone number, report the situation, and notify professionals for handling;
  • Switching electrical appliances and hot work at the scene are strictly prohibited to prevent sparks;
  • After leak handling, personnel may enter only after gas concentration is verified at acceptable levels.

32.2.2 Fire and Explosion Emergency Response

  • For incipient fires, immediately use fire extinguishers to fight the fire while pressing the manual alarm button;
  • If the fire cannot be controlled, immediately evacuate and close fire doors and explosion-proof doors;
  • Call 119 fire emergency number, stating location, media, and fire intensity;
  • Evacuate to an upwind safe area; elevator use is prohibited;
  • Injured personnel receive immediate first aid; call 120;
  • Cooperate with firefighters in rescue operations.

32.2.3 Electrical Fault Emergency Response

  • If electrical equipment smokes or catches fire, immediately cut off power and use dry powder or gas extinguishers to fight the fire;
  • Using water to fight electrical fires is strictly prohibited;
  • For electric shock, immediately cut off power or use an insulated object to separate the victim from the wire; provide on-site first aid;
  • Before the fault is cleared, restoring power is strictly prohibited;
  • Notify professional electricians to investigate and repair.

32.2.4 Personnel Injury Emergency Response

  • Upon personnel injury, immediately stop operations and move the injured person to a safe area;
  • For minor injuries, provide on-site bleeding control and bandaging; for serious injuries, immediately call 120;
  • If heartbeat and breathing have stopped, immediately perform CPR;
  • Protect the accident scene and report to relevant departments;
  • Cooperate with accident investigation and implement rectification measures.

32.3 Emergency Drill Requirements

  • Conduct at least one emergency drill every six months, covering gas leak and fire scenarios;
  • Prepare a drill plan before the drill, specifying objectives, procedures, and personnel assignments;
  • Conduct evaluation and summary after drills, analyzing shortcomings and revising the plan;
  • All on-duty personnel must participate in drills and master emergency skills;
  • Drill records and evaluation reports are archived for future reference.

Appendices

Appendix A: Standards and Specifications Number and Name

(Refer to Chapter 3: Implementation Standards and Specification Basis)

Appendix B: Explosion-Proof Level Description and Applicable Areas

Hazardous area classification:

Zone Definition
Zone 0 Places where explosive gas atmospheres are present continuously or for long periods
Zone 1 Places where explosive gas atmospheres are likely to occur in normal operation
Zone 2 Places where explosive gas atmospheres are unlikely to occur in normal operation, and if they do occur, they occur only occasionally and for short durations

Explosion-proof type applicable areas:

Type Applicable Zones
Intrinsically safe type ia Zone 0, Zone 1, Zone 2
Flameproof type d, increased safety type e, positive pressure type p Zone 1, Zone 2

Gas group: IIA, IIB, IIC — hazard level increases in that order;

Temperature class: T1-T6 — maximum surface temperature decreases in that order; T6 is the most stringent.

Appendix C: Common Tools and Instruments Calibration Requirements

  • Measuring instruments must be calibrated regularly per national verification regulations and marked with qualified labels;
  • Ground resistance testers, megohmmeters, and multimeters calibrated annually;
  • Combustible gas detectors calibrated annually;
  • Torque wrenches calibrated semi-annually;
  • Use of expired, uncalibrated, or defective instruments and tools is strictly prohibited.

Appendix D: Acceptance Record Form Templates

(Including foundation acceptance record, container installation acceptance record, electrical system acceptance record, ventilation/air conditioning acceptance record, safety system acceptance record, final completion acceptance certificate, etc.)

Appendix E: Maintenance Record Form Templates

(Including daily inspection records, monthly maintenance records, quarterly maintenance records, annual overhaul records, fault repair records, etc.)

Appendix F: Manufacturer Contact Information and Service System

  • Manufacturer: Guangdong Lain Intelligent System Development Co., Ltd. (KITOZER)
  • Service Hotline: +86 13538869979 (WeChat same number)
  • Technical Support: +86 13538869979
  • Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou City
  • Official Website: https://gdlain.com
  • Core Business: Explosion-proof container customization, OEM processing, confidential production, stock supply — one-stop service for research, development, production, installation, operation, and maintenance of the full series of industrial special containers.

Internal anchor text description:

  • Core anchor text: Explosion-proof Container (Explosion-proof Container)
  • Long-tail anchor text: Industrial special explosion-proof container installation and commissioning, explosion-proof container maintenance, explosion-proof container acceptance standards
  • Related anchor text: Explosion-proof container manufacturer, Guangdong Lain explosion-proof container, explosion-proof container specifications and parameters
Scroll to Top