Table of Contents
TogglePreface

This manual provides comprehensive, full-process technical documentation for condensate drainage systems used with precision air conditioners in data centers, communication base stations, industrial control centers, and similar environments. It covers product principles, structural composition, installation and construction, electrical wiring, system commissioning, operation and maintenance, troubleshooting, and acceptance and delivery. This manual is compiled in accordance with national and industry standards including the *Code for Design of Data Centers* (GB 50174-2017), *Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works* (GB 50243), and *Standard for Design of Building Water Supply and Drainage* (GB 50015). It applies to the full range of computer room air conditioning condensate drainage system products manufactured by Guangzhou Lain Intelligent System Development Co., Ltd., covering multiple categories including gravity self-flow type, power lift type, and integrated all-in-one systems.
This manual addresses the needs of design personnel, construction personnel, and operations and maintenance personnel, with clear quantitative specifications for critical processes, parameter thresholds, and safety regulations. Construction and maintenance personnel must strictly follow the requirements of this manual. Non-compliant operation may lead to risks such as poor drainage, condensation dripping, and overflow accidents, which may in turn affect the operational safety of electronic equipment in the computer room. The company reserves the right to upgrade and optimize product technical parameters and structural designs. If product changes result in discrepancies between this manual and the actual product, the technical documentation shipped with the product shall prevail. The latest version may also be obtained by contacting our technical support hotline.
Chapter 1: Product Introduction

1.1 System Definition
The computer room air conditioning condensate drainage system is a core auxiliary system for precision air conditioners, constant temperature and humidity units, and fresh air dehumidification equipment in computer rooms. It is responsible for the collection, conveyance, and compliant discharge of condensate formed on the evaporator surface during air conditioning operation. It is a critical protection system that ensures temperature and humidity stability in the computer room and prevents liquid water from intruding into equipment areas. The system collects condensate through water collection devices and conveys it to the building drainage network via piping systems using gravity self-flow or power lift methods. It is equipped with multiple protection mechanisms including anti-condensation, anti-clogging, anti-backflow, and overflow alarm functions, achieving safe, stable, and automated condensate discharge.
Computer rooms are high-grade electrical environments where electronic information equipment is highly sensitive to liquid water. The reliability of the condensate drainage system is directly related to computer room operational safety. According to industry statistics, approximately 65% of computer room water leakage incidents originate from condensate drainage system failures, including pipe blockages, insufficient slope, insulation failure, and pump malfunction. These may cause ceiling mold, slippery floors, or in severe cases, server short circuits, data loss, and significant economic losses. Therefore, a professional, standardized condensate drainage system is an irreplaceable and essential component of computer room infrastructure.
1.2 Industry Development Background
With the rapid development of the digital economy, the scale of data centers and computing computer rooms continues to expand. The load and operating hours of computer room air conditioning systems continue to increase, along with correspondingly higher requirements for condensate discharge volume and drainage system reliability. Early computer room condensate drainage systems often followed civil air conditioning drainage schemes, using simple PVC hoses connected to nearby floor drains, lacking standardized design and protective measures, resulting in frequent overflow, condensation, and blockage incidents.
With the implementation of industry standards such as GB 50174, computer room condensate drainage systems have progressively developed toward specialization, integration, and intelligence: piping materials have upgraded from ordinary hoses to rigid PVC-U, galvanized steel pipes, and even 304 stainless steel pipes; drainage methods have evolved from single gravity drainage to composite solutions combining gravity flow and lift; control functions have advanced from no monitoring to intelligent protection including liquid level monitoring, overflow alarms, and interlocked shutdown; construction processes have developed from rough installation to standardized procedures with precise slope control, full insulation, and sectional pressure testing.
Guangzhou Lain Intelligent System Development Co., Ltd. has deep expertise in the computer room infrastructure field. In response to the special safety requirements of computer room environments, the company has developed a full series of condensate drainage system products covering all scenarios from small edge computer rooms to large Class A data centers. The products feature core advantages including anti-clogging, anti-leakage, anti-condensation, high reliability, and ease of maintenance, and have been widely applied in computer room projects across government, finance, communications, internet, and industrial manufacturing sectors.
1.3 Design Standards
This product strictly complies with the following national and industry standards in design, production, construction, and acceptance:
*Code for Design of Data Centers* — GB 50174-2017
*Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works* — GB 50243-2016
*Standard for Design of Building Water Supply and Drainage* — GB 50015-2019
*Code for Acceptance of Construction Quality of Building Water Supply, Drainage and Heating Works* — GB 50242-2002
*Code for Acceptance of Construction Quality of Building Electrical Works* — GB 50303-2015
*Design Standard for Energy Efficiency of Public Buildings* — GB 50189-2015
*Code for Construction of Industrial Metal Piping Engineering* — GB 50235-2010
*Design Guide for Thermal Insulation of Equipment and Pipes* — GB/T 8175-2008
*Technical Requirements for Computer Room Environment Monitoring System* — YD/T 1821-2008
*Classification for Burning Behavior of Building Materials and Products* — GB 8624-2012
1.4 Product Scope of Application
This series of condensate drainage systems is compatible with various types of computer room air conditioning equipment, including but not limited to:
- Room-level precision air conditioners (air-cooled, water-cooled, chilled water type)
- In-row air conditioners / row-level cooling units
- Rack-level air conditioners / rear-door heat exchangers
- Constant temperature and humidity air conditioning units
- Fresh air dehumidification integrated machines
- Supporting terminal equipment for industrial chillers
Applicable environments include:
- Class A/B/C data center main computer rooms and auxiliary areas
- Communication base stations and carrier core computer rooms
- Power dispatch rooms and industrial control rooms
- Hospital clean computer rooms and laboratory constant temperature and humidity rooms
- Archives and museum warehouse constant temperature and humidity systems
- Financial data centers and disaster recovery center computer rooms
Chapter 2: Product Composition

The computer room air conditioning condensate drainage system consists of six functional units: the condensate collection unit, piping conveyance unit, power lift unit, detection and control unit, end treatment unit, and insulation protection unit. All units work cooperatively to complete full-process management and control of condensate from generation to discharge.
2.1 Condensate Collection Unit
The collection unit is the starting point of the system, responsible for receiving condensate generated by the air conditioner evaporator and performing initial filtration to prevent debris from entering the piping and causing blockages.
2.1.1 Built-in Drain Pan of Air Conditioner
The drain pan is installed directly below the evaporator and serves as the primary condensate collection device. Drain pans standard on precision air conditioners in computer rooms are typically made of 1.2mm thick cold-rolled steel sheet with electrostatic powder coating or 304 stainless steel. The pan depth shall be no less than 50mm, with raised edges to prevent condensate splashing and overflow. The pan bottom is set at a 2% slope toward the drain outlet to ensure complete water accumulation at the outlet with no residual water zones.
The inner surface of the drain pan is coated with a hydrophobic coating to reduce scale and algae adhesion. A removable stainless steel filter screen with 2mm apertures is installed at the drain outlet to filter dust, fibers, fin oxidation debris, and other foreign matter from the air, preventing pipe blockage. Some high-end models feature a built-in electric heating wire in the drain pan to prevent condensate freezing in low-temperature environments and ensure smooth winter drainage.
2.1.2 External Water Collection Tank
Power lift systems are equipped with an external water collection tank for temporary condensate storage, providing stable inlet conditions for the lift pump. The tank is injection-molded from food-grade PP or ABS engineering plastic, with capacities ranging from 1L to 10L, selected according to the air conditioner condensate volume. The tank is equipped with a water inlet, water outlet, overflow port, and inspection cover, with integrated multi-level liquid level detection electrodes and an inlet filter screen.
A sediment settling groove is provided at the tank bottom where debris accumulates, preventing it from being drawn into the pump and causing impeller wear. A scale line is marked on the tank side wall for intuitive visual monitoring of the water level by maintenance personnel. The inspection cover is fitted with a sealing gasket to prevent dust ingress and moisture vapor escape.
2.1.3 Collection Funnel and Flow Guide Device
When multiple air conditioners share a common discharge main pipe, a collection funnel is installed at the point where branch pipes join the main pipe to achieve indirect drainage and prevent odors and insects from the main pipe backing up into the air conditioner. The funnel is made of UPVC or stainless steel, with the upper opening larger than the branch pipe outer diameter and the lower opening connected to the main pipe by socket joint. A filter screen is installed inside the funnel for further debris filtration.
For air conditioning units operating under negative pressure conditions (such as horizontal air handling units where the fan is located downstream of the cooling coil), the drain pan is in a negative pressure zone. Specialized flow guide devices and water seal structures must be provided to prevent condensate from being held by negative pressure and unable to discharge.
2.2 Piping Conveyance Unit
The piping unit is the conveyance channel for condensate, consisting of main pipes, branch pipes, pipe fittings, and supports and hangers. Its construction quality directly determines drainage performance and service life.
2.2.1 Drainage Pipes
Pipes are classified into three categories by material, with different materials suited to different scenarios:
PVC-U Drain Pipe: The most commonly used pipe material, made of national standard rigid polyvinyl chloride, wall thickness ≥2.0mm, nominal pressure ≥0.6MPa. Advantages include smooth inner walls, low flow resistance, corrosion resistance, light weight, convenient construction, and moderate cost. Disadvantages include average rigidity, requiring denser supports and hangers for long-distance installation. Suitable for the vast majority of ordinary computer room scenarios, working temperature 0~60°C.
Hot-Dip Galvanized Steel Pipe: Made of high-quality carbon steel pipe with internal and external hot-dip galvanized anti-corrosion treatment, wall thickness ≥2.5mm. Advantages include high strength, good rigidity, impact resistance, and long service life. Disadvantages include susceptibility to internal scaling, heavy weight, difficult construction, and higher cost. Suitable for large data centers, industrial environments, and other scenarios with high pipe strength requirements.
304 Stainless Steel Pipe: Food-grade stainless steel material, wall thickness ≥1.5mm, internally and externally polished. Advantages include excellent corrosion resistance, smooth non-scaling inner walls, high hygiene grade, and service life exceeding 30 years. Disadvantages include high cost and demanding welding construction requirements. Suitable for medical clean computer rooms, food production workshops, highly corrosive industrial environments, and other special scenarios.
Pipe diameter specifications are matched to condensate volume. Common specifications include DN20, DN25, DN32, DN40, DN50, DN65, and DN80. Branch pipes generally use DN20~DN25. Horizontal main pipes are progressively enlarged according to the number of connected equipment units. Riser pipe diameters shall not be smaller than the corresponding horizontal main pipe.
2.2.2 Pipe Fittings
These include elbows, tees, couplings, reducers, traps, inspection ports, and cleanout ports, with materials corresponding to the pipes to ensure connection compatibility.
Elbows: Available as 45° elbows and 90° elbows. For drainage systems, 45° elbows are preferred to reduce flow resistance. When 90° elbows are necessary, large radius elbows shall be used to avoid right-angle sharp turns that may cause air locks and debris deposition.
Tees: Branch drain pipes shall join the main pipe using oblique tees (45° tees) in the direction of flow. Reverse flow connection is strictly prohibited. 90° straight tees shall only be used for vertical flow diversion.
Traps: U-shaped or P-shaped traps form a water seal to block odors and insect backflow. The water seal depth shall be no less than 50mm. Under negative pressure conditions, the water seal depth shall exceed 1.5 times the water column height corresponding to the negative pressure.
Inspection Ports / Cleanout Ports: Inspection ports shall be installed every 10m on horizontal pipe sections and on each floor on risers. Cleanout ports shall be installed at pipe turns and convergence points for convenient future pipe cleaning and maintenance. Inspection port covers are fitted with sealing gaskets to prevent water leakage and odor emission.
2.2.3 Supports and Hangers
Used to secure pipes and prevent sagging and deformation that would compromise the slope. Supports and hangers are made of hot-dip galvanized steel sections or PVC-specific pipe clips. Support and hanger spacing is determined by pipe material and diameter:
| Pipe Type | Horizontal Pipe Spacing | Vertical Pipe Spacing |
|---|---|---|
| PVC-U Pipe | ≤0.8m | ≤1.5m |
| Galvanized Steel Pipe | ≤1.2m | ≤2.0m |
| Stainless Steel Pipe | ≤1.0m | ≤1.8m |
Supports and hangers must be securely installed with tight contact with the pipe. Sleeves shall be installed where pipes pass through walls and floor slabs, and the sleeves shall be filled with fire-resistant sealing material. Rubber pads shall be placed between pipes and supports/hangers to avoid hard contact that may cause pipe wear and vibration noise.
2.3 Power Lift Unit
When the building structure cannot meet gravity drainage slope requirements, a power lift unit must be configured. The lift unit uses a water pump to raise condensate to a higher discharge point, enabling same-level or upward drainage.
2.3.1 Condensate Lift Pump
The core power component, using a centrifugal impeller structure. The motor is a fully enclosed induction motor with overheat protection. Classified by installation form into built-in and external types:
Built-in Lift Pump: Integrated inside the air conditioning unit, compact structure, small footprint, suitable for small precision air conditioners; head generally 3~5m, flow rate 100~300L/h.
External Lift Pump: Independently installed outside the air conditioner or in the ceiling, convenient for maintenance, capable of matching large flow and high head requirements; head 5~15m, flow rate 200~1000L/h, suitable for medium-large computer room air conditioners and scenarios with multiple units operating in parallel.
Classified by structure into integrated and split types:
Integrated Lift Pump: Water tank and pump integrated into one unit, simple installation, lower cost; suitable for single air conditioner drainage.
Split Lift Pump: Collection tank and pump arranged separately. The pump can be installed at a lower position, providing greater suction lift and flexible arrangement; suitable for scenarios with limited installation space and long drainage distances.
The pump impeller is made of wear-resistant engineering plastic. The mechanical seal is made of silicon carbide material. The waterproof rating is IP54 or above, enabling long-term stable operation in high-humidity environments. The motor insulation class is Class F, compatible with 220V/50Hz civil power supply and 380V industrial power supply.
2.3.2 Check Valve
Installed on the pump outlet pipe to prevent water in the pipe from flowing back into the tank when the pump stops, avoiding tank overflow. Spring-loaded check valves or swing check valves are used, made of PVC or brass, with diameter matching the pipe. Forward flow resistance is low, and reverse sealing is tight.
The check valve installation direction must match the water flow direction, with the arrow indicator pointing toward the discharge side. Both horizontal and vertical installation are acceptable; for vertical installation, the water flow direction must be upward.
2.3.3 Inlet Filter
A Y-type filter is installed at the front of the pump water inlet with a 40-mesh filter screen to filter impurities from the water, preventing impeller blockage and wear. The filter has a removable end cover for convenient periodic cleaning of the filter screen. During installation, the filter screen shall face downward to facilitate debris settling.
2.4 Detection and Control Unit
This unit achieves automated system operation and safety protection, consisting of liquid level detection elements, control modules, and alarm devices.
2.4.1 Liquid Level Detection Elements
Used to detect the water level in the collection tank or drain pan, controlling pump start/stop and overflow alarm. Common types include electrode-type liquid level switches and float-type liquid level switches.
Electrode-Type Liquid Level Switch: Uses water conductivity to detect liquid level, composed of multiple electrode probes of different lengths, corresponding to stop level, start level, and alarm level respectively. The electrodes are made of 304 stainless steel, corrosion-resistant, with no mechanical moving parts, high reliability, and long service life. This is the mainstream choice for computer room condensate systems.
Generally configured with four electrodes: common electrode, stop electrode (lowest water level), start electrode (normal high water level), and alarm electrode (overflow warning level). When the water level rises to the start electrode, the pump starts draining; when the water level drops to the stop electrode, the pump stops; when the water level exceeds the start electrode and reaches the alarm electrode, the overflow alarm is triggered.
Float-Type Liquid Level Switch: A float rises and falls with the water level, driving an internal magnetic reed switch to output switching signals. Advantages include simple structure, low cost, and no dependence on water conductivity. Disadvantages include mechanical moving parts that may jam after prolonged use. Suitable for scenarios with poor water quality and high debris content.
Float switches are available in single-point and multi-point types. Multi-point types can simultaneously achieve start/stop and alarm functions. During installation, they must be firmly secured to prevent the float from being entangled by debris.
2.4.2 Control Module
The control core of the system, receiving liquid level signals and outputting pump control and alarm signals. The module integrates a power circuit, signal processing circuit, and relay output circuit, with functions including pump start/stop logic control, delayed start/stop, overload protection, and fault alarm.
The control module is set with a start/stop dead band to avoid frequent pump start/stop caused by water level fluctuations, extending pump service life. A built-in overload protection relay automatically cuts off power when the pump is stalled or overcurrent occurs, protecting the motor. A dry contact alarm output is provided for connection to the computer room environment monitoring system for remote alarm.
Some high-end control modules support the RS485 communication interface, enabling upload of water level status, pump operating status, and fault information to the environmental monitoring platform for centralized monitoring and data analysis.
2.4.3 Alarm Device
An on-site audible and visual alarm that emits red flashing light and buzzer alerts upon overflow, reminding on-site maintenance personnel to respond promptly. The alarm is powered by DC24V or AC220V, with a sound level of ≥85dB, protection rating IP44, and is installed in a conspicuous location within the computer room.
The system also provides a passive dry contact alarm signal output supporting normally open/normally closed mode switching, which can interlock with air conditioning unit shutdown to prevent overflow accidents from escalating. It can also be connected to the environmental monitoring system for remote alarm via SMS, telephone call, or APP push notification.
2.5 End Treatment Unit
The discharge terminus of the condensate system, responsible for compliant discharge of conveyed condensate into the building drainage system, with anti-backflow and anti-odor functions.
2.5.1 Floor Drain / Collection Well
The final discharge point of condensate, preferably connected to a dedicated condensate floor drain or air conditioning computer room collection well. Direct connection to sewage risers is strictly prohibited. The floor drain shall be a self-closing type for clean rooms with a water seal structure of ≥50mm depth to prevent odor and insect backflow. The drain grate shall have a grid to block large particle debris.
Large computer rooms are equipped with dedicated collection wells. After condensate is discharged into the well, a submersible sewage pump lifts it to the outdoor pipe network. The collection well is equipped with high and low liquid level control and a standby pump in a one-duty-one-standby configuration with automatic fault switching.
2.5.2 Air Gap and Indirect Drainage Device
The condensate pipe outlet must not be inserted below the water surface of the discharge point. An air gap must be maintained to achieve indirect drainage and prevent sewage backflow. The air gap height shall be no less than 150mm and no less than 2.5 times the drainage pipe diameter.
Indirect drainage can be achieved using devices such as drainage funnels or drainage sockets. The funnel upper opening receives the condensate pipe outlet, and the lower opening connects to the floor drain or drainage channel, with an air break maintained in between.
2.5.3 Outdoor Splash Pad Device
When condensate is discharged directly outdoors, a splash pad or rain grate shall be installed at the outlet to prevent water flow from scouring the ground and causing soil erosion. The pipe outlet shall be bent downward to prevent rain, debris, and insects from entering the pipe. Outdoor pipes shall be insulated or heat-traced to prevent winter freezing.
2.6 Insulation Protection Unit
Preventing condensation and dripping on the outer pipe wall is a critical protection measure for computer room condensate systems. In computer rooms where ambient temperature is low and air humidity is high, when low-temperature condensate flows through the pipes, the pipe wall temperature falls below the air dew point temperature, and water vapor in the air condenses into water droplets on the pipe wall, which may drip onto equipment or the floor, creating safety hazards.
2.6.1 Insulation Material
B1-class flame-retardant closed-cell rubber-plastic insulation foam is used, complying with GB 8624 combustion performance requirements, with oxygen index ≥32% and self-extinguishing upon flame removal. The closed-cell ratio of the insulation foam is ≥92%, and the thermal conductivity is ≤0.034W/(m·K), providing excellent insulation performance. It also features good elasticity and water resistance, and moisture vapor cannot penetrate through.
Polyurethane insulation material may be used for low-temperature environments or large temperature differential scenarios, offering superior insulation performance. For clean room scenarios, insulation material with an outer aluminum foil cladding may be used for dust resistance and easy cleaning.
2.6.2 Insulation Thickness
Determined by calculation based on the water temperature inside the pipe and ambient temperature/humidity parameters. For standard computer room scenarios, the insulation layer thickness shall be no less than 10mm. For large-diameter pipes, high-humidity environments, and areas with poor ventilation in ceiling voids, the thickness shall be increased to 15~20mm.
All pipes, fittings, valves, and equipment interfaces must be fully insulated with no exposed areas. Insulation joints shall be bonded with specialized adhesive and then wrapped with insulation tape for sealing, eliminating cold bridge phenomena.
2.6.3 Protective Outer Shell
For exposed pipes or areas prone to impact, a PVC or galvanized steel protective outer shell shall be installed over the insulation layer to protect it from damage and improve aesthetics. Joints of the outer shell shall be sealed with sealant to prevent moisture ingress.
Chapter 3: Product Classification
Our condensate drainage systems are classified along multiple dimensions including power form, system structure, application grade, control method, and pipe material type, covering all scenario requirements.
3.1 Classification by Power Form
3.1.1 Gravity Self-Flow Condensate Drainage System
Relies on gravity to drive condensate flow, requiring no power equipment. This is the most basic and most reliable drainage form.
Working Principle: Uses the gravitational component force created by pipe slope to drive condensate from a higher point to a lower discharge point.
System Composition: Drain pan + filter screen + drainage piping + trap + end discharge point + insulation layer
Advantages: Simple structure, no electrical components, no noise, extremely low failure rate, low maintenance cost, long service life
Disadvantages: Depends on building elevation differences; requires sufficient installation space to maintain slope; cannot achieve upward drainage or long-distance horizontal drainage
Applicable Scenarios: Locations where the air conditioner is installed above the discharge point, ceiling space is sufficient, and drainage slope of at least 1% can be achieved; such as first-floor computer rooms and computer rooms on floors near drain risers.
3.1.2 Power Lift Condensate Drainage System
Uses a condensate lift pump to provide power, lifting condensate to the discharge point and overcoming the spatial limitations of gravity drainage.
Working Principle: Condensate collects in the collection tank. When the water level reaches the start threshold, the pump automatically starts and pressurizes the water, lifting it to the discharge pipe. When the water level drops to the stop threshold, the pump stops.
System Composition: Drain pan + collection tank + lift pump + liquid level controller + check valve + drainage piping + alarm device + insulation layer
Advantages: Not limited by slope requirements; supports same-level and upward drainage; flexible layout; saves ceiling space and reduces raised floor height requirements
Disadvantages: Contains electrical moving parts with a certain failure probability; requires periodic maintenance; produces slight operating noise
Applicable Scenarios: Locations where the air conditioner is below the discharge point, ceiling space is insufficient for slope, and same-level long-distance drainage is required; such as high-rise office building computer rooms, underground computer rooms, and mezzanine computer rooms.
3.1.3 Composite Condensate Drainage System
A combined gravity self-flow + power lift solution. Under normal conditions, drainage is achieved by gravity. Under extreme overflow conditions, the lift pump is activated to assist drainage, providing dual protection.
Working Principle: The primary path uses gravity drainage, with a lift pump and overflow level detection installed on a bypass. When gravity drainage is inadequate and the water level rises to the alarm value, the lift pump automatically starts to accelerate drainage.
Advantages: Extremely high reliability with dual redundancy; no energy consumption or wear during normal operation; long pump service life
Disadvantages: Complex system structure, higher cost
Applicable Scenarios: Class A data centers, core computer rooms, and other critical scenarios with extremely high drainage reliability requirements.
3.2 Classification by System Structure
3.2.1 Independent Drainage System
Each air conditioner is provided with a separate drainage pipe system with independent discharge, with no mutual interference.
Advantages: Failure of one unit does not affect other equipment; facilitates fault location; no cross-contamination risk
Disadvantages: Higher pipe material consumption, more piping runs, greater construction workload
Applicable Scenarios: Computer rooms with a small number of equipment units and dispersed layouts; dedicated drainage for core equipment with high safety levels.
3.2.2 Centralized Drainage System
Drainage branch pipes from multiple air conditioners converge into a single main pipe for centralized discharge to a common discharge point.
Advantages: Simple piping layout, lower pipe material consumption, higher construction efficiency; facilitates centralized maintenance
Disadvantages: Main pipe blockage affects all connected equipment; requires proper design of pipe diameter and slope to prevent backwater
Applicable Scenarios: Large computer rooms with dense equipment; modular data centers; scenarios with multiple air conditioners in the same area.
3.2.3 Zoned Drainage System
The computer room is divided into multiple zones, each with an independent drainage system and zoned centralized discharge.
Advantages: Balances reliability and economy; failure in one zone does not affect the whole; facilitates zoned management
Disadvantages: Increased system design complexity
Applicable Scenarios: Medium-large data centers, multi-room combined computer rooms; computer room clusters divided by functional zones.
3.3 Classification by Application Grade
3.3.1 Standard Type (Class C)
Meets basic drainage functions and complies with conventional computer room usage requirements.
Configuration: PVC-U pipes, standard liquid level control, basic insulation, local audible/visual alarm
Compliance Standard: Complies with GB 50174 Class C data center requirements
Applicable Scenarios: Small computer rooms, office computer rooms, general business computer rooms
3.3.2 Enhanced Type (Class B)
Upgraded material grades and reliability with multiple additional protections.
Configuration: Heavy-duty PVC or galvanized steel pipes, dual liquid level redundant detection, thickened insulation, overflow interlocked alarm, densified pipe inspection ports
Compliance Standard: Complies with GB 50174 Class B data center requirements
Applicable Scenarios: Medium data centers, communication computer rooms, enterprise core computer rooms
3.3.3 Flagship Type (Class A)
Highest-grade configuration with full redundancy design, meeting the stringent requirements of Class A data centers.
Configuration: 304 stainless steel pipes, dual pumps in one-duty-one-standby configuration, triple liquid level detection, intelligent control module, environmental monitoring system integration, full thickened insulation, leak detection cable provision
Compliance Standard: Complies with GB 50174 Class A data center requirements
Applicable Scenarios: Large Tier 3/Tier 4 data centers, financial core computer rooms, government cloud computer rooms, disaster recovery centers
3.4 Classification by Pipe Material Type
3.4.1 PVC-U Pipe System
The most common piping solution with outstanding cost-effectiveness.
Pipe Material: National standard PVC-U drainage pipe, solvent weld connection
Features: Fast construction, low cost, smooth inner walls, corrosion resistance
Applicable: The vast majority of conventional computer room scenarios
3.4.2 Galvanized Steel Pipe System
High-strength metal piping solution.
Pipe Material: Hot-dip galvanized steel pipe, threaded or grooved connection
Features: High strength, impact resistance, long service life, good fire resistance
Applicable: Large industrial computer rooms, high-grade data centers, impact-prone areas within ceiling voids
3.4.3 Stainless Steel Pipe System
Premium corrosion-resistant solution.
Pipe Material: 304/316 stainless steel pipe, welded or press-fit connection
Features: Ultimate corrosion resistance, non-scaling, high hygiene grade, extremely long service life
Applicable: Clean computer rooms, highly corrosive environments, medical/food industry computer rooms
3.5 Classification by Control Method
3.5.1 Float Control Type
Pump start/stop controlled by float switch. Simple structure, low cost.
Control Element: Float liquid level switch
Features: Simple structure, low water quality requirement, low cost
Applicable: General scenarios with average water quality; projects with limited budgets
3.5.2 Electrode Control Type
Pump start/stop controlled by electrode probes detecting liquid level. High reliability; this is the mainstream solution.
Control Element: Electrode-type liquid level sensor
Features: No mechanical parts, long service life, high sensitivity, precise multi-point level detection
Applicable: The majority of computer room scenarios, especially high-reliability projects
3.5.3 Intelligent Monitoring Type
Equipped with communication functionality for integration with environmental monitoring systems, enabling remote monitoring and management.
Control Element: Intelligent control module + liquid level sensor
Features: Observable status, recordable data, remote alarm, interlocked control
Applicable: Unattended computer rooms, centrally managed data centers, smart computer room projects
Chapter 4: Product List
4.1 Standard Configuration List (Gravity Self-Flow Type, DN25 System, Single Air Conditioner)
| No. | Component Name | Specification/Model | Material | Unit | Qty | Remarks |
|---|---|---|---|---|---|---|
| 1 | Drain pan filter screen | Φ20mm, 2mm aperture | 304 stainless steel | pcs | 1 | Installed at air conditioner drain pan outlet |
| 2 | PVC-U drain pipe | DN25, wall thickness 2.0mm | Rigid PVC | m | As required | Including 5% allowance |
| 3 | 45° elbow | DN25 | PVC-U | pcs | As required | For corners |
| 4 | 90° long radius elbow | DN25 | PVC-U | pcs | As required | Use when necessary |
| 5 | Coupling | DN25 | PVC-U | pcs | As required | Pipe connection |
| 6 | U-trap | DN25, 50mm water seal | PVC-U | pcs | 1 | At air conditioner outlet |
| 7 | Inspection port | DN25 | PVC-U | pcs | 1 | One per 10 meters |
| 8 | Pipe clip | DN25 | Galvanized + PVC lining | set | As required | Spacing 0.8m |
| 9 | Wall penetration sleeve | DN40 | PVC | pcs | As required | At wall penetration |
| 10 | Fire-resistant sealing putty | National standard | Organic fire-proof putty | pack | As required | Sleeve sealing |
| 11 | Rubber-plastic insulation foam | DN25, thickness 10mm, Class B1 | Closed-cell rubber-plastic | m | As required | Pipe insulation |
| 12 | Insulation tape | Width 50mm | Rubber-plastic specific | roll | As required | Joint sealing |
| 13 | PVC adhesive | 500ml | Special adhesive | bottle | As required | Pipe bonding |
| 14 | Drainage funnel | DN25 | PVC-U | pcs | 1 | End indirect drainage |
4.2 Standard Configuration List (Power Lift Type, DN25 System, Single Air Conditioner, 5m Head)
| No. | Component Name | Specification/Model | Material | Unit | Qty | Remarks |
|---|---|---|---|---|---|---|
| 1 | Collection tank | 3.8L capacity | PP engineering plastic | pcs | 1 | Including inlet filter screen |
| 2 | Condensate lift pump | Flow 300L/h, head 5m | Engineering plastic + copper motor | set | 1 | Built-in overheat protection |
| 3 | Electrode-type liquid level switch | 4 electrodes, high/low level + alarm | 304 stainless steel | set | 1 | Integrated in tank |
| 4 | Control module | AC220V input, relay output | Flame-retardant ABS housing | pcs | 1 | Including start/stop delay |
| 5 | Check valve | DN20 | PVC + rubber seal | pcs | 1 | At pump outlet |
| 6 | Y-type filter | DN20 | PVC, 40-mesh filter screen | pcs | 1 | At pump water inlet |
| 7 | Inlet hose | Φ20mm, length 1m | Corrosion-resistant PVC | pcs | 1 | From drain pan to tank |
| 8 | PVC-U drain pipe | DN25, wall thickness 2.0mm | Rigid PVC | m | As required | Post-pump piping |
| 9 | Pipe fittings | DN25 matching | PVC-U | batch | As required | Elbows, couplings, etc. |
| 10 | Pipe clips and supports | DN25 | Galvanized | set | As required | For pipe fixing |
| 11 | Rubber-plastic insulation foam | DN25, thickness 10mm, Class B1 | Closed-cell rubber-plastic | m | As required | Pipe + tank insulation |
| 12 | Audible/visual alarm | AC220V, 85dB | ABS housing | pcs | 1 | Overflow alarm |
| 13 | Electrical junction box | 86 type | PVC | pcs | 1 | Wiring protection |
| 14 | Control cable | RVV 3×1.5mm² | Copper core | m | As required | Power and signal |
| 15 | Installation hardware | Expansion bolts, cable ties, etc. | Galvanized steel | batch | 1 | Installation accessories |
4.3 Flagship Configuration List (For Class A Data Centers, DN50 Centralized Drainage System)
| No. | Component Name | Specification/Model | Material | Unit | Qty | Remarks |
|---|---|---|---|---|---|---|
| 1 | Main collection tank | 50L capacity | 304 stainless steel | pcs | 1 | With level scale |
| 2 | Condensate lift pump | Flow 2m³/h, head 10m | 304 stainless steel pump body | set | 2 | One duty, one standby |
| 3 | Level sensor | Ultrasonic level gauge, accuracy ±2mm | Anti-corrosion probe | set | 1 | Continuous level detection |
| 4 | Redundant electrode liquid level switch | 5-point | 316 stainless steel | set | 1 | Backup detection |
| 5 | Intelligent control box | PLC control, with RS485 communication | Cold-rolled steel, powder coated | set | 1 | Dual pump automatic switching |
| 6 | Check valve | DN50 | Brass | pcs | 2 | One at each pump outlet |
| 7 | Motorized ball valve | DN50 | Brass valve body | pcs | 2 | Automatic shutoff on fault |
| 8 | Stainless steel drain pipe | DN50, wall thickness 1.5mm | 304 stainless steel | m | As required | Main pipe |
| 9 | Stainless steel fittings | DN50 matching | 304 stainless steel | batch | As required | Elbows, tees, etc. |
| 10 | Pipe supports and hangers | Size 50 | Hot-dip galvanized channel steel | set | As required | Spacing 1.0m |
| 11 | Rubber-plastic insulation foam | DN50, thickness 20mm, Class B1 | Closed-cell rubber-plastic | m | As required | Thickened insulation |
| 12 | Insulation protective outer shell | DN50 | Galvanized steel sheet | m | As required | Protects insulation layer |
| 13 | Leak detection cable | Locating type, 10m | Sensing cable | pcs | 1 | Laid along piping |
| 14 | Leakage monitoring module | 485 communication | Industrial grade | pcs | 1 | Connected to environmental monitoring system |
| 15 | Audible/visual alarm | Industrial grade, 120dB | Explosion-proof housing | pcs | 2 | On-site + computer room entrance |
| 16 | Power distribution box | Independent circuit, with residual current protection | Cold-rolled steel | set | 1 | Dedicated power supply for system |
| 17 | Signal cable | RVSP 2×1.0mm² | Shielded copper core | m | As required | Communication signal |
| 18 | Power cable | YJV 3×2.5mm² | Copper core | m | As required | Main power supply |
4.4 Dedicated Construction Tool List
| No. | Tool Name | Specification | Purpose |
|---|---|---|---|
| 1 | Pipe cutter | PVC-specific | Cutting PVC pipes |
| 2 | Hacksaw | Hand saw | Cutting metal pipes |
| 3 | Chamfering tool | Matching pipe diameter | Pipe end chamfering |
| 4 | Level | Laser level / bubble level | Checking pipe slope |
| 5 | Tape measure | 5m / 30m | Dimension measurement |
| 6 | Wrench | Adjustable wrench / socket wrench | Tightening fittings |
| 7 | Electric drill | Impact drill | Drilling holes for supports and hangers |
| 8 | Multimeter | Digital multimeter | Electrical testing |
| 9 | Megohmmeter | 500V | Insulation resistance testing |
| 10 | Pressure test barrel | 10L | Water filling test |
| 11 | Test ball | 3/4 of pipe diameter | Ball passage test |
| 12 | Utility knife | Heavy duty | Cutting insulation foam |
| 13 | Brush | 1 inch | Applying PVC adhesive |
| 14 | Wire strippers | Electrician-specific | Wire stripping for connections |
| 15 | Voltage tester | Induction type | Live circuit detection |
4.5 Wear Parts and Consumables List
| No. | Name | Replacement Cycle | Remarks |
|---|---|---|---|
| 1 | Drain pan filter screen | 6 months | Clean or replace |
| 2 | Pump inlet filter screen | 12 months | Clean or replace |
| 3 | Float/electrode liquid level switch | 3 years | Periodic calibration; replace on failure |
| 4 | Pump mechanical seal | 2~3 years | Replace on leakage |
| 5 | Check valve sealing gasket | 3 years | Replace on seal failure |
| 6 | Insulation tape | 5 years | Replace on aging or detachment |
| 7 | Pipe bonding adhesive | 12-month shelf life | Purchase as needed |
Chapter 5: Product Working Principles
5.1 Condensate Generation Principle
When a computer room air conditioner operates in cooling mode, low-temperature low-pressure liquid refrigerant evaporates in the evaporator coil, absorbing heat and lowering the coil surface temperature below the air dew point. Humid air from the computer room flows across the evaporator coil driven by the fan. When water vapor in the air contacts the low-temperature coil surface, it condenses from gaseous state into liquid water droplets. This process is called condensation.
The condensed droplets slide down the fins under gravity and collect in the drain pan below, forming condensate. The condensate generation rate is directly related to parameters including air conditioner cooling capacity, relative air humidity, air temperature, and airflow rate. The calculation formula is as follows:
Condensate Volume Calculation Formula:
W = ρ × L × (d1 − d2) / 1000
Where:
- W: Condensate volume, in kg/h
- ρ: Air density, taken as 1.2kg/m³
- L: Air conditioner supply airflow rate, in m³/h
- d1: Inlet air moisture content, in g/kg
- d2: Outlet air moisture content, in g/kg
Under standard computer room conditions (temperature 24°C, relative humidity 50%), a precision air conditioner with 10kW cooling capacity produces approximately 3~5kg of condensate per hour. During high-humidity seasons or in high-humidity regions, the condensate volume may increase to 6~8kg/h. When designing the drainage system, the capacity must be selected with a 1.5x margin over the maximum condensate volume to ensure unobstructed drainage under extreme conditions.
5.2 Gravity Self-Flow System Working Principle
Gravity self-flow drainage is based on the gravity flow principle of fluid mechanics, relying on the gravitational potential energy generated by the elevation difference between the pipe inlet and outlet to drive water flow. The pipe maintains a continuous downward slope, causing water to flow continuously toward lower points under the gravitational component force, ultimately discharging from the end discharge point.
The key parameter for gravity flow drainage is the hydraulic slope, which is the elevation drop per unit pipe length. A larger slope results in faster water flow velocity and greater drainage capacity, but requires more vertical space. An excessively small slope results in slow water flow, making the pipe susceptible to debris deposition, and may even cause water accumulation and air locks.
For computer room condensate systems, the branch pipe slope is required to be ≥1% (i.e., 10mm drop per meter of pipe), and the main pipe slope is required to be ≥0.5%, ensuring turbulent flow with a certain self-cleaning capacity to prevent debris deposition. Additionally, local high points along the entire pipe run must be avoided to prevent air entrapment forming air locks that impede water flow.
For air conditioning units operating under negative pressure conditions where the drain pan is in the fan negative pressure zone, the air pressure at the condensate outlet is lower than atmospheric pressure. Under these conditions, simple gravity drainage may fail because the water flow is held by negative pressure and cannot discharge. Therefore, a U-trap must be installed, using the water column in the trap to form a water seal that offsets the negative pressure effect. The water seal height must be greater than the water column height corresponding to the negative pressure value, ensuring smooth condensate discharge while preventing air from being drawn back into the unit.
5.3 Power Lift System Working Principle
The power lift system uses a water pump to perform work on the condensate, converting electrical energy into the kinetic and potential energy of the water, enabling condensate to overcome gravity and pipe resistance to be conveyed from a lower point to a higher discharge point.
5.3.1 Pump Working Principle
Condensate lift pumps typically use centrifugal pumps. During operation, the motor drives the impeller to rotate at high speed. The water in the pump body rotates with the impeller and is thrown toward the impeller edge under centrifugal force, flowing through the volute casing channel to the outlet. Simultaneously, a vacuum is created at the center of the impeller, and water in the tank is drawn into the pump body through the inlet under atmospheric pressure, forming continuous water flow.
The core performance parameters of a pump are flow rate and head. Flow rate refers to the volume of water delivered per unit time, and head refers to the vertical height to which the pump can lift water. During selection, the total piping resistance must be calculated based on the actual discharge height, pipe length, and number of fittings to ensure that the pump rated head is greater than the sum of total resistance and lift height, and the rated flow rate is greater than the maximum condensate volume.
5.3.2 Automatic Control Principle
The system uses a liquid level sensor to detect the water level in the collection tank in real time, controlling automatic pump start/stop. The specific logic is as follows:
Standby State: When the air conditioner is not operating or the condensate volume is low, the water level in the tank is below the start level, and the pump remains in the stopped state.
Pump Start: As condensate continuously accumulates and the water level rises to the start level, the liquid level sensor sends a signal, the control module energizes the pump power supply, and the pump begins draining.
Pump Stop: Pump drainage lowers the water level. When the water level drops to the stop level, the liquid level sensor sends a stop signal, and the pump ceases operation.
Overflow Alarm: If the pump fails or the drainage flow rate is insufficient, the water level continues to rise to the alarm level. The system triggers an on-site audible/visual alarm and simultaneously outputs a dry contact signal to the environmental monitoring system. If necessary, the air conditioner is interlocked to shut down.
To avoid frequent pump start/stop caused by water level fluctuations, the control module is set with a start/stop dead band. The start level and stop level maintain a certain differential, typically 20~30mm, ensuring each pump run has a reasonable duration and extending motor service life.
5.4 Anti-Condensation Insulation Principle
The function of the insulation layer is to reduce heat exchange between the low-temperature water in the pipe and the outside air, keeping the outer pipe wall temperature above the air dew point temperature to prevent water vapor in the air from condensing on the pipe wall.
Heat transfer occurs through three mechanisms: conduction, convection, and radiation. Closed-cell rubber-plastic insulation material contains a large number of independent closed microscopic air bubbles. Air is a poor heat conductor and effectively blocks heat conduction. The closed-cell structure simultaneously prevents moisture vapor penetration, avoiding internal condensation and insulation failure within the insulation layer. The outer surface of the insulation layer has a small contact area with air, resulting in weak convective heat exchange.
By properly designing the insulation layer thickness, the cold loss at the pipe wall can be controlled within allowable limits, keeping the insulation layer outer surface temperature above the ambient dew point temperature, fundamentally eliminating condensation. The insulation layer thickness must be determined through thermal calculation based on the water temperature inside the pipe, ambient temperature and humidity, and the thermal conductivity of the insulation material, ensuring compliance with anti-condensation requirements.
5.5 Anti-Clogging Working Principle
The system reduces the risk of clogging through multi-stage filtration and water self-cleaning design:
Primary Filtration: A stainless steel strainer at the drain pan outlet filters large particles such as dust clumps, fin fragments, insect debris, etc.
Secondary Filtration: A filter screen at the collection tank inlet further filters fine impurities, while the sediment sump at the bottom of the tank settles heavy materials such as sand and sediment.
Tertiary Filtration: A Y-type strainer at the pump inlet protects the pump impeller from clogging and wear caused by debris.
Water Self-Cleaning: The piping maintains adequate slope and flow velocity, keeping the water in a turbulent state to carry away fine particles and prevent sedimentation; periodic high-flow flushing thoroughly removes algae and biofilm attached to pipe walls.
5.6 Anti-Backflow Working Principle
The system prevents backflow of sewage, odors, and insects through multiple structural safeguards:
Trap Water Seal: The U-shaped trap in the piping always retains a water column, forming a physical barrier that prevents odors and insects from the downstream pipeline from flowing back upward.
Indirect Drainage: An air gap is maintained between the terminal drain outlet and the drainage point. Condensate falls through the air into the drainage point without direct contact with sewage, completely preventing sewage backflow into the condensate piping.
Check Valve: A check valve at the lift pump outlet prevents water in the piping from flowing back into the tank when the pump is stopped, avoiding overflow.
Self-Closing Floor Drain: The terminal floor drain adopts a self-closing structure — opens when water is present and automatically closes when dry, providing dual protection against odors and backflow.
6.1 Piping System Technical Parameters
6.1.1 PVC-U Pipe Parameters
| Nominal Diameter | Outer Diameter | Wall Thickness | Theoretical Weight | Working Pressure | Recommended Flow Range | Applicable Cooling Capacity |
|---|---|---|---|---|---|---|
| DN20 | 25mm | 2.0mm | 0.17kg/m | ≥0.6MPa | 0~100L/h | ≤12kW |
| DN25 | 32mm | 2.0mm | 0.22kg/m | ≥0.6MPa | 50~200L/h | 10~25kW |
| DN32 | 40mm | 2.0mm | 0.28kg/m | ≥0.6MPa | 150~400L/h | 20~50kW |
| DN40 | 50mm | 2.4mm | 0.42kg/m | ≥0.6MPa | 300~800L/h | 40~100kW |
| DN50 | 63mm | 2.5mm | 0.55kg/m | ≥0.6MPa | 600~1500L/h | 80~200kW |
| DN65 | 75mm | 2.6mm | 0.71kg/m | ≥0.6MPa | 1200~2500L/h | 150~350kW |
| DN80 | 90mm | 3.0mm | 0.95kg/m | ≥0.6MPa | 2000~4000L/h | 300~600kW |
6.1.2 Galvanized Steel Pipe Parameters
| Nominal Diameter | Outer Diameter | Wall Thickness | Theoretical Weight | Working Pressure | Recommended Flow Range |
|---|---|---|---|---|---|
| DN20 | 26.9mm | 2.8mm | 1.66kg/m | ≥1.6MPa | 0~120L/h |
| DN25 | 33.7mm | 3.2mm | 2.42kg/m | ≥1.6MPa | 80~250L/h |
| DN32 | 42.4mm | 3.5mm | 3.36kg/m | ≥1.6MPa | 200~500L/h |
| DN40 | 48.3mm | 3.5mm | 3.87kg/m | ≥1.6MPa | 400~900L/h |
| DN50 | 60.3mm | 3.8mm | 5.29kg/m | ≥1.6MPa | 800~1800L/h |
6.1.3 304 Stainless Steel Pipe Parameters
| Nominal Diameter | Outer Diameter | Wall Thickness | Theoretical Weight | Working Pressure | Recommended Flow Range |
|---|---|---|---|---|---|
| DN25 | 32mm | 1.5mm | 1.13kg/m | ≥1.0MPa | 80~250L/h |
| DN32 | 42mm | 1.5mm | 1.50kg/m | ≥1.0MPa | 200~500L/h |
| DN40 | 48mm | 1.5mm | 1.72kg/m | ≥1.0MPa | 400~900L/h |
| DN50 | 57mm | 2.0mm | 2.71kg/m | ≥1.0MPa | 800~1800L/h |
6.2 Condensate Lift Pump Technical Parameters
6.2.1 Compact Built-In Lift Pump Series
| Model | Rated Flow | Rated Head | Power Supply | Power | Tank Volume | Noise | Application |
|---|---|---|---|---|---|---|---|
| LA-T03 | 120L/h | 3m | AC220V/50Hz | 8W | 0.8L | ≤28dB | Small cabinet AC below 5kW |
| LA-T05 | 200L/h | 5m | AC220V/50Hz | 12W | 1.2L | ≤30dB | Precision AC 5~12kW |
| LA-T08 | 300L/h | 8m | AC220V/50Hz | 18W | 1.5L | ≤32dB | Precision AC 12~25kW |
6.2.2 Medium External Lift Pump Series
| Model | Rated Flow | Rated Head | Power Supply | Power | Tank Volume | Noise | Application |
|---|---|---|---|---|---|---|---|
| LA-P10 | 360L/h | 10m | AC220V/50Hz | 25W | 3.8L | ≤35dB | Single unit 25~50kW AC |
| LA-P15 | 600L/h | 15m | AC220V/50Hz | 40W | 6L | ≤38dB | Single unit 50~100kW AC / multiple small units |
| LA-P20 | 1000L/h | 20m | AC220V/50Hz | 60W | 10L | ≤40dB | Centralized drainage for multiple AC units |
6.2.3 Large Industrial-Grade Lift Pump Series
| Model | Rated Flow | Rated Head | Power Supply | Power | Material | Protection Class | Application |
|---|---|---|---|---|---|---|---|
| LA-G20 | 2m³/h | 20m | AC220V/380V | 0.37kW | 304 Stainless Steel | IP55 | Centralized drainage for medium data centers |
| LA-G30 | 5m³/h | 30m | AC380V | 0.75kW | 304 Stainless Steel | IP55 | Centralized drainage for large data centers |
| LA-G50 | 10m³/h | 35m | AC380V | 1.5kW | Cast Iron + Stainless Steel | IP55 | Centralized condensate system for building clusters |
6.3 Control System Technical Parameters
6.3.1 Standard Control Module
- Power Supply: AC220V ±10%, 50Hz
- Power Consumption: Standby ≤2W, Operating ≤5W
- Level Input: 4-electrode type / float switch, dry contact
- Output Contact Capacity: 5A/AC220V (pump output), 3A/AC220V (alarm output)
- Start/Stop Differential: 20~50mm adjustable
- Start Delay: 3 seconds, anti-false-trigger
- Stop Delay: 10 seconds, to fully drain residual water in the pipe
- Overload Protection: Current threshold adjustable, trip time ≤5 seconds
- Operating Environment: Temperature 0~60°C, relative humidity ≤95% non-condensing
- Mounting: DIN rail mount or wall mount
6.3.2 Intelligent Monitoring Module
- Power Supply: DC24V/AC220V optional
- Level Detection: Supports 4~20mA analog level transmitter, accuracy ±1%
- Communication Interface: RS485, Modbus-RTU protocol
- Data Logging: Stores 30 days of operating data, exportable
- Alarm Functions: High/low level alarm, pump fault alarm, communication fault alarm
- Interlock Functions: Supports dual-pump rotation, automatic fault switchover, interlocked AC unit shutdown
- Display Interface: LED digital display showing real-time water level and operating status
- Operating Environment: Temperature -10~70°C, relative humidity ≤95% non-condensing
6.4 Insulation System Technical Parameters
- Insulation Material: B1 grade closed-cell rubber-plastic (NBR/PVC) foam
- Flammability Rating: GB 8624 Class B1, self-extinguishing upon flame removal, smoke density rating ≤75
- Thermal Conductivity: ≤0.034W/(m·K) (at 0°C)
- Closed Cell Rate: ≥92%
- Water Absorption: ≤1.0%
- Service Temperature Range: -40°C ~ 105°C
- Apparent Density: 60~80kg/m³
- Compression Rebound Rate: ≥70%
- Standard Thicknesses: 10mm, 15mm, 20mm, 25mm, 30mm
- Insulation Tape: Rubber-plastic specific pressure-sensitive adhesive tape, width 50mm, adhesion ≥1.0N/cm
6.5 Overall System Performance Parameters
- Design Service Life: PVC system ≥15 years, metal system ≥25 years
- Pump Mean Time Between Failures (MTBF): ≥30,000 hours
- System Leakage Rate: 0 (under qualified installation conditions)
- Drainage Response Time: Pump starts within 3 seconds after water level reaches the start value
- Alarm Response Time: Alarm triggered within 1 second under overflow condition
- Applicable Ambient Temperature: -10°C ~ 60°C
- Applicable Ambient Humidity: ≤95% RH non-condensing
- Seismic Rating: Grade 8
- Fire Resistance Rating: Overall system not lower than Class B1
7.1 Core Functions
7.1.1 Automatic Condensate Collection and Discharge
The system automatically collects all condensate generated by AC unit operation and delivers it steadily to the designated discharge point without manual intervention. Gravity systems rely on slope for continuous drainage; powered systems automatically start and stop via level control, ensuring no overflow risk in the drain pan or collection tank.
The system’s drainage capacity provides more than 1.5 times reserve margin, capable of handling extreme conditions such as high-humidity seasons and full-load operation. Even with a significant increase in condensate volume, smooth discharge is maintained without water accumulation or overflow.
7.1.2 Multi-Level Anti-Clogging Protection
The three-stage filtration system intercepts debris at the source, combined with the self-cleaning water flow created by proper pipe slope, effectively reducing the probability of clogging. Inspection ports and cleanout openings are provided at critical points, allowing rapid unclogging without extensive dismantling or modification.
The tank’s sediment sump design allows impurities to settle at the bottom without entering the pump or piping; regular opening of the access cover allows easy cleaning and maintenance.
7.1.3 Comprehensive Anti-Condensation Protection
All piping, fittings, and equipment connections receive complete insulation treatment with no cold bridge dead zones, ensuring no condensation or dripping on pipe surfaces under high-temperature, high-humidity conditions. The B1 grade flame-retardant insulation material also meets fire safety requirements, compliant with data center fire protection regulations.
Reinforced insulation design addresses extreme high-humidity conditions; even when summer relative humidity exceeds 90%, the outer surface of the insulation remains dry, eliminating the risk of dripping.
7.1.4 Backflow and Odor Isolation
The U-trap water seal + terminal air gap + self-closing floor drain provide triple protection, completely blocking odors, insects, and pathogens from the drainage network from backflowing into the equipment room, ensuring clean room air quality.
The check valve prevents return water in the piping after the lift pump stops, avoiding tank overflow and sewage backflow.
7.1.5 Overflow Safety Alarm
Multi-level level detection automatically triggers an alarm when water level rises abnormally. Local audible and visual alarms alert on-site personnel; dry contact signals can be connected to the equipment room environmental monitoring system (DCIM/BMS) to enable remote SMS, phone, and APP notifications.
High-specification systems support overflow-linked shutdown: when the water level reaches the danger threshold, the corresponding AC units are automatically shut down to prevent the overflow incident from escalating and to protect equipment room equipment.
7.2 Product Features
7.2.1 High-Reliability Design
- Gravity systems have no electrical moving parts; theoretical service life matches the building itself with near-zero failures.
- Powered systems use branded motors with built-in multi-level protection (overheat, overload, overcurrent), with MTBF exceeding 30,000 hours.
- Electrode-type level switches have no mechanical wear, strong anti-interference capability, and stable long-term operation.
- Pipe connections use specialized bonding/welding processes with excellent sealing performance, eliminating leakage risk.
- Flagship-grade products feature dual-pump duty/standby redundancy; failure of one pump does not affect system drainage.
7.2.2 Scenario-Based Adaptability
- Three major solution types — gravity, lift, and composite — accommodate different building structures and installation conditions.
- Pipe materials cover three categories: PVC, galvanized steel, and stainless steel, meeting different budget and environmental requirements.
- Full range of pipe diameters available, matching applications from single small AC units to large data center clusters.
- Control options range from basic to intelligent, adapting to various operation and maintenance modes including unattended and centralized monitoring.
- Customizable design provides specialized solutions for special scenarios such as negative-pressure units, low-temperature environments, and highly corrosive environments.
7.2.3 Convenient Maintenance Design
- All filter components are removable and cleanable without requiring tools.
- Inspection ports and transparent observation sections are provided at critical pipe points, enabling visual inspection of internal water flow without disassembly.
- Pumps feature quick-connect interfaces for easy replacement; complete unit replacement can be completed within ten minutes.
- Control modules feature clear status indicator lights and intuitive fault codes for rapid problem localization.
- Wear parts are standardized with strong interchangeability, making procurement and replacement convenient.
7.2.4 Energy Efficiency and Environmental Features
- Gravity systems consume zero energy with no operating costs.
- Powered systems use high-efficiency motors with extremely low energy consumption; annual power consumption of a single pump is less than 50 kWh.
- Automatic start/stop control ensures the pump does not operate when there is no water, avoiding wasted energy.
- Insulation materials are environmentally friendly and non-toxic, free of formaldehyde, halogens, and other harmful substances, compliant with RoHS standards.
- Condensate can be recycled for cooling tower makeup water, landscape irrigation, and other uses, conserving water resources.
7.2.5 Standardized Construction Processes
- All series components are manufactured to standard specifications with uniform dimensions and strong interchangeability.
- Standardized construction procedures with quantified parameters for slope, spacing, insulation thickness, etc., enabling effective construction quality control.
- Complete construction tools and auxiliary materials are provided, reducing preparation effort.
- Standardized acceptance procedures: three-step verification (water flow test, ball passage test, and full-water test) ensures delivery quality.
8.1 Data Center Equipment Rooms
Data centers are the most critical application scenario for condensate drainage systems. The dense concentration of servers, switches, and other IT equipment in equipment rooms means zero tolerance for water leakage.
Class A Data Centers: Flagship solution — stainless steel piping + dual-pump redundancy + intelligent monitoring + leak detection cable, with 20mm reinforced insulation throughout, zoned independent drainage, meeting high-reliability requirements. The system integrates with the DCIM platform for remote monitoring and alarm, with leak location accuracy up to 0.5 meters.
Class B/C Data Centers: Enhanced or standard solution — PVC or galvanized steel piping + single lift pump + level alarm, meeting conventional reliability requirements. Centralized drainage design reduces construction and maintenance costs.
Micro-Module Data Centers: In-row AC units are paired with integrated drainage systems; modules collect condensate and connect to a common header; leak detection rope is installed at the module base for dual protection.
8.2 Telecommunications Operator Equipment Rooms
Including operator core equipment rooms, base station rooms, transmission rooms, etc., with wide distribution of equipment and some rooms having restricted installation conditions.
Core Equipment Rooms: Centralized powered lift system — multiple switch-mode power supply and transmission equipment AC units share a common drainage main, with centralized alarm integrated into the network management system.
Base Station Rooms: Mostly small rooms using standard gravity drainage solutions with simple structure and low failure rates, suitable for unattended environments; some underground base stations use compact lift pump solutions.
Outdoor Cabinets: Paired with integrated condensate evaporation devices or lift discharge devices to solve outdoor drainage challenges; electric heat tracing for freeze protection in winter.
8.3 Enterprise-Grade Equipment Rooms
Including enterprise office building equipment rooms, school equipment rooms, hospital equipment rooms, government equipment rooms, etc., with medium scale, balancing reliability and cost.
Conventional Office Equipment Rooms: Standard gravity or basic lift solutions with PVC piping and local audible/visual alarm, meeting daily operational needs.
Hospital Clean Equipment Rooms: 304 stainless steel piping system with high sanitary standards, easy to clean and disinfect, preventing bacterial growth, compliant with medical cleanliness requirements.
Government Core Equipment Rooms: Enhanced solution — galvanized steel piping + redundant control + DCIM integration, meeting government information system security level requirements.
8.4 Industrial Control Equipment Rooms
Including factory DCS control rooms, power dispatch rooms, rail transit control centers, etc., with complex environments requiring high anti-interference and durability.
Industrial Factory Equipment Rooms: Galvanized steel piping system with impact resistance, dust tolerance, suitable for harsh industrial environments; reinforced filtration devices for dusty air.
Power Dispatch Equipment Rooms: High-reliability redundant design — dual power supply + dual pump backup, ensuring normal drainage under extreme conditions and stable operation of power dispatch systems.
Rail Transit Control Centers: Seismic-reinforced design with enhanced supports and hangers, meeting long-term stable operation requirements in rail transit vibration environments.
8.5 Special Environment Equipment Rooms
8.5.1 High-Altitude Equipment Rooms
At altitudes above 2000 meters, thinner air and reduced boiling point make pumps prone to cavitation. The system uses plateau-specific custom pumps with enlarged inlet pipe diameter, reduced suction lift, and cavitation suppression devices; pipe slope is appropriately increased to enhance drainage flow velocity.
Electrical components are derated with upgraded insulation ratings to adapt to low-pressure environments.
8.5.2 Low-Temperature Environment Equipment Rooms
In northern winter low-temperature regions, pipes are prone to freezing. Outdoor piping and piping in unheated areas are fitted with electric heat tracing systems combined with reinforced insulation to prevent freezing inside the pipes during winter; the drain pan and tank can be optionally equipped with electric heating to prevent freezing at low temperatures.
8.5.3 High-Corrosion Environment Equipment Rooms
For chemical plants, coastal salt-spray, and other corrosive environments. Piping and equipment use 316 stainless steel with anti-corrosion surface treatment; motors and electrical components receive anti-corrosion insulation treatment to extend service life.
8.5.4 Cleanroom Equipment Rooms
Supporting equipment rooms for pharmaceutical, electronics manufacturing, and other clean workshops. Piping is covered with smooth aluminum foil insulation jackets that do not accumulate dust and are easy to wipe; drainage system features sterile design with regular disinfection ports to prevent microbial growth.
8.6 Other Supporting Scenarios
Constant Temperature and Humidity Laboratories: High-precision AC units paired with drainage systems; stable drainage does not affect indoor temperature and humidity fluctuations.
Archives/Warehouses: Dehumidification equipment paired with drainage systems to maintain stable temperature and humidity in storage areas, protecting collection safety.
IDC Cooling Tower Makeup Water: Condensate recovery system collects and filters condensate for use as cooling tower makeup water, achieving water resource recycling.
Liquid-Cooled Equipment Room Auxiliary Drainage: Collection and discharge system for condensate and leak water from liquid cooling systems, equipped with leak detection and emergency drainage pumps.
9.1 Pre-Construction Preparation
9.1.1 Technical Preparation
- Review construction drawings and design documents; clarify pipe routing, slope requirements, equipment installation positions, and drainage point locations.
- Verify AC model and condensate volume; confirm system selection and pipe diameter match; recheck whether pipe slope and elevation difference meet requirements.
- Prepare construction plan defining construction sequence, personnel assignment, safety measures, and quality control points.
- Conduct technical and safety briefings for construction personnel, explaining construction specifications, operational key points, and acceptance standards.
- Perform on-site layout and positioning; mark pipe elevations, support/hanger positions, and wall penetration drilling locations; coordinate with decoration, electrical, and fire protection trades to confirm crossing points and avoid conflicts.
9.1.2 Material and Equipment Inspection
- Upon delivery of pipes, fittings, pumps, insulation materials, etc., check product certificates, test reports, and warranty documents; verify model, specification, and quantity.
- Pipe Appearance Inspection: Pipe wall smooth, free of bubbles, cracks, deformation; uniform color; metal pipes free of rust, dents, with intact galvanized layer.
- Fitting Inspection: Specifications match, interfaces tight, no damage, sealing rings intact.
- Pump Inspection: Appearance intact, impeller rotates freely without sticking; power-on jog test confirms correct rotation direction, no abnormal noise.
- Insulation Material Inspection: Uniform thickness, no damage, flame retardant rating meets requirements, test report attached.
- Electrical Accessory Inspection: Cable specifications conform to design, insulation layer intact; switches, terminals, and other accessories complete with matching specifications.
9.1.3 Tools and Site Preparation
- Prepare construction tools: pipe shears, hacksaws, electric drills, levels, tape measures, wrenches, multimeters, pressure testing tools, etc.; ensure tools are in good condition and measuring instruments are within calibration validity.
- Clean the construction site to ensure a tidy work area free of obstructions; erect scaffolding or ladders for high-altitude work and confirm they are secure.
- Connect temporary power supply with residual current circuit breaker installed, compliant with temporary electricity regulations; construction water supply ready.
- Organize material storage areas; store pipes by category to avoid crushing and deformation; keep insulation materials away from ignition sources with fire prevention measures in place.
9.1.4 Work Condition Confirmation
- AC main unit installed in position, drain pan position secured, elevation accurate.
- Building structural construction complete; wall and floor leveling finished; ceiling elevation determined.
- Wall and floor slab penetrations pre-formed or drilling conditions available.
- Drainage points (floor drains, collection wells) constructed and completed with elevations meeting design requirements.
- Site safety conditions confirmed: high-altitude work protection in place, hot work permits processed.
9.2 Overall Construction Process
1. Measurement and layout → 2. Support/hanger fabrication and installation → 3. Pipe prefabrication and cutting → 4. Pipe connection and laying → 5. Trap and fitting installation → 6. Equipment (pump, tank) installation → 7. Full-water test and water flow test → 8. Insulation work → 9. Electrical wiring → 10. System commissioning → 11. Acceptance and handover
9.3 Support and Hanger Installation
9.3.1 Support and Hanger Selection
- PVC Pipes: PVC pipe clips + galvanized expansion bolts; pipe clips lined with rubber pads to prevent pipe damage.
- Metal Pipes: Angle steel brackets + U-type pipe clamps; brackets treated with anti-corrosion coating; rubber gasket between clamp and pipe.
- Large-Diameter Pipes: Channel steel hangers secured to floor slabs or beams with expansion bolts; load capacity satisfies pipe full-water weight × 1.5 safety factor.
9.3.2 Installation Spacing Requirements
| Pipe Type | Horizontal Pipe Support Spacing | Vertical Pipe Support Spacing |
|---|---|---|
| PVC Pipe | ≤0.8m | ≤1.5m |
| Galvanized Steel Pipe | ≤1.2m | ≤2.0m |
| Stainless Steel Pipe | ≤1.0m | ≤1.8m |
- Additional supports/hangers required at pipe turns, equipment connections, and within 150mm on both sides of valves.
- Load-bearing support installed at the base of vertical risers to bear pipe self-weight and water weight, preventing pipe sagging.
9.3.3 Installation Specifications
- Drill holes according to marked positions; hole depth per expansion bolt requirements; clean dust from holes; insert expansion bolts and secure firmly.
- Install supports/hangers level with accurate elevation; supports in the same direction aligned in a straight line.
- Supports/hangers must not be installed at pipe connection points; maintain distance ≥50mm from connections.
- Since pipes require slope, adjust support heights according to slope requirements to ensure continuous and uniform pipe slope.
- Install one support on each side within 300mm of wall penetrations to prevent pipe movement from wearing the sleeve.
- After installation, perform pull-test sampling to verify load capacity and no loosening.
9.4 Pipe Installation
9.4.1 Pipe Cutting and Chamfering
- PVC Pipes: Cut with dedicated pipe shears; cut surface smooth and perpendicular to pipe axis; large diameters may use hacksaws, followed by deburring with a file.
- Metal Pipes: Cut with hacksaw or cutting machine; grind cut surfaces smooth, removing burrs and oxide layer.
- Chamfer pipe cut ends at an angle of 15°~30°, depth of 1/2~2/3 of wall thickness, facilitating insertion into fittings and preventing scraping of adhesive or sealing rings.
9.4.2 PVC Pipe Solvent Cement Connection
- Before bonding, wipe pipe outer surface and fitting inner surface clean — free of oil, dust, and moisture.
- Use a brush to apply dedicated PVC solvent cement evenly to the pipe outer wall and fitting inner wall; apply quickly, uniformly, and in appropriate quantity — no skipping or excessive application.
- Immediately after applying cement, insert the pipe into the fitting, rotate 1/4 turn to distribute the cement evenly; ensure insertion to full depth; maintain pressure for 30 seconds without loosening.
- Wipe away excess cement extruded from the joint; allow to cure. Curing time: no less than 30 minutes at 20°C; extend appropriately at lower temperatures.
- Bonded joints reach maximum strength after 24 hours; during curing, joints must not be subjected to load or water pressure testing.
9.4.3 Galvanized Steel Pipe Threaded Connection
- Thread the pipe; thread length must match the fitting; after threading, clean metal chips and check thread integrity — no broken or crossed threads.
- Wrap PTFE tape around threads or apply pipe joint compound; wrap clockwise with moderate tightness.
- Tighten the fitting with a pipe wrench; after tightening, 2~3 threads should remain exposed; clean excess PTFE tape.
- Apply anti-corrosion treatment at joints: coat exposed threads and damaged galvanized areas with rust-inhibitive paint.
9.4.4 Stainless Steel Pipe Welded / Press-Fit Connection
- Welded Connection: Use TIG (argon arc) welding; single-side welding with double-side weld formation; weld bead full and free of porosity, cracks, and slag inclusions; after welding, perform passivation treatment to remove weld discoloration and provide corrosion protection.
- Press-Fit Connection: Use dedicated pressing tools; confirm sealing ring is properly positioned; after pressing, perform pull-out test to confirm connection is secure.
9.4.5 Pipe Slope Control
- Pipe installation strictly follows design slope: branch pipe slope ≥1%, main pipe slope ≥0.5%; continuous downward slope throughout — no reverse slope, no flat sections, no local high points.
- Use a level to check slope at any time during installation; re-measure every 3 meters to ensure uniform slope.
- Maintain slope continuity at pipe turns and transitions; fittings must not cause local elevation.
- For long pipe runs, adjust support heights section by section, pulling a reference line to control overall slope.
9.4.6 Trap Installation
- A trap must be installed at the AC drain pan outlet. For negative-pressure units, the trap water seal height is calculated based on the unit’s negative pressure value and must not be less than 50mm.
- Install the trap vertically, not tilted, to ensure stable water seal depth.
- Provide a cleanout at the bottom of the trap for future unclogging.
- Before multiple AC unit branch pipes join the main pipe, each branch must have its own trap to avoid mutual interference.
9.4.7 Inspection Port and Cleanout Installation
- Install an inspection port every 10m on horizontal pipe runs; increase frequency at turns, confluences, and long straight sections.
- Install an inspection port at each floor on vertical risers, 1.0~1.2m above floor level.
- Orient inspection ports toward the side convenient for operation; covers fitted with sealing gaskets to ensure watertight closure.
- Install cleanouts at the lowest points of the piping system for sediment removal.
9.4.8 Wall and Floor Slab Penetration Treatment
- Install sleeves where pipes pass through walls or floor slabs. Sleeve diameter should be two sizes larger than the pipe; sleeve length matches wall/slab thickness.
- Fill the gap between sleeve and pipe with fire-resistant sealing compound, compact and void-free, meeting fire protection and leak prevention requirements.
- Floor slab sleeves protrude 50mm above the finished floor to prevent floor water from entering the sleeve.
- Secure sleeves firmly; they must not serve as pipe supports.
9.5 Powered Equipment Installation
9.5.1 Collection Tank Installation
- Install the tank at a position lower than the AC drain pan outlet to ensure condensate flows into the tank by gravity.
- Level the tank using a spirit level; tilting affects level detection accuracy.
- Secure the tank firmly with anti-vibration pads underneath to reduce vibration transmission.
- Connect the tank inlet to the AC condensate outlet, optionally with a flexible hose for vibration isolation; outlet connects to the pump inlet.
- Tank access cover faces upward with maintenance space reserved for easy opening and cleaning.
9.5.2 Lift Pump Installation
- Install the pump on a flat, secure base with anchor bolts; anti-vibration pads properly installed to reduce operating noise and vibration.
- Connect pump inlet to tank outlet with a Y-type strainer in between; arrow direction must align with water flow direction.
- Install a check valve and isolation valve at the pump outlet for convenient maintenance shutdown.
- Verify pump installation direction is correct: pump body arrow points toward the discharge direction; reverse installation is prohibited.
- For split-type pumps, installation height must be lower than the tank’s minimum water level to ensure suction lift requirements are met and avoid cavitation.
- Reserve maintenance space around the pump for easy disassembly and replacement.
9.6 Pipe Testing
After pipe installation and before insulation work, full-water test and water flow test must be performed to verify pipe sealing integrity and drainage performance.
9.6.1 Full-Water Test (Hydrostatic Leak Test)
- Seal the terminal drain outlet; fill the system from the highest point, expelling all air from the piping.
- Fill to full state; water level not less than 300mm above the highest point of the system.
- Let stand for 30 minutes; inspect all joints, fittings, and pipe walls for leakage.
- Acceptance criteria: no significant drop in water level and no joint leakage within 30 minutes. If leakage is found, mark the location, drain, repair, and retest.
- Document the test process, complete the test record form, and obtain signature confirmation from the supervisor or owner’s representative.
9.6.2 Water Flow Test
- After the full-water test passes, open the terminal seal and allow water to drain naturally.
- Continuously inject clean water from the highest point with a flow rate not less than 1.2 times the design maximum condensate volume.
- Acceptance criteria: smooth drainage, no water accumulation, no air lock, no overflow.
- Measure discharge flow rate; discharge volume not less than 70% of the injected volume is acceptable.
- For systems with multiple connected units, test with simultaneous water injection to check for backflow or overflow at confluences.
9.6.3 Ball Passage Test
- Perform ball passage test on main trunk pipes to verify internal unobstructed flow.
- Use a hard plastic ball with a diameter of 3/4 of the pipe’s internal diameter.
- Insert the ball at the pipe’s top end, flush it down with water; passing through and exiting at the terminal end constitutes a pass.
- 100% first-pass rate required. If the ball becomes stuck, locate the obstruction, clear it, and retest.
9.7 Insulation Work
Proceed with insulation layer installation after pipe tests pass.
9.7.1 Installation Requirements
- Pipe surfaces must be clean and dry, free of dust, oil, and moisture.
- Cut insulation tube sections neatly; bore to match pipe diameter; after fitting onto the pipe, joints must be tight.
- Pipe joints, elbows, tees, and valves require individual insulation wrapping with tight seams and no exposed areas.
- Stagger longitudinal seams of insulation; seams must not be positioned directly beneath the pipe.
- Insulation must adhere firmly — no hollow areas, detachment, or gaps.
9.7.2 Joint Treatment
- Apply dedicated insulation adhesive at insulation joints for tight bonding.
- Seal all joints with insulation tape wrapped spirally; tape overlap width not less than 20mm, wrapped smoothly without wrinkles.
- Insulation continues through wall penetrations; fill inside sleeves with insulation material to eliminate cold bridges.
- Equipment connections, pumps, and tanks receive complete insulation with no exposed metal parts.
9.7.3 Outer Protective Jacket (Optional)
- For exposed piping or applications requiring aesthetics, install metal or PVC protective jacketing over the insulation layer.
- Jacket seams must be tight with laps facing downward to prevent water ingress.
- Jacket securely fastened, smooth and aesthetically pleasing, free of deformation.
9.8 Terminal Drainage Point Installation
- The condensate pipe terminal must connect to a dedicated floor drain or drainage channel — direct connection to sewage piping is prohibited.
- Maintain an air gap between the pipe outlet and the drainage point water surface; gap height ≥150mm; the pipe outlet must not be submerged in water.
- When using a drain funnel transition, secure the funnel firmly; upper opening larger than the drain pipe; lower opening aligned with the floor drain center.
- Outdoor drain outlets should curve downward with insect screen installed to prevent rainwater, debris, and insect backflow.
- Floor drains should be self-closing water-seal type; check the water seal periodically to prevent drying out and failure.
10.1 Pre-Wiring Preparation
10.1.1 Electrical Safety Regulations
- Wiring work must be performed by a certified electrician in strict compliance with electrical safety operating procedures.
- Disconnect the main power supply before wiring; verify with a voltage tester that the circuit is de-energized. Live wiring is strictly prohibited.
- The power circuit must have a dedicated air switch and residual current circuit breaker (RCD) with a leakage trip current of 30mA and trip time ≤0.1s.
- All metal enclosures and piping must be reliably grounded; grounding resistance ≤4Ω.
- Cable installation complies with electrical codes; power and signal cables are routed separately to avoid interference; cables must be installed in conduit and never left exposed.
10.1.2 Material Inspection
- Verify cable specifications: power cables, control cables, and signal cables conform to design requirements with intact insulation layers.
- Inspect electrical components: control module, terminal blocks, air switch, alarm devices, etc., with correct models, intact appearance, and complete accessories.
- Prepare tools: wire strippers, crimping tools, multimeter, insulation resistance tester (megger), voltage tester, screwdrivers, cable ties, etc.
- Verify wiring diagram: cross-reference the product wiring diagram to confirm terminal definitions and avoid incorrect connections.
10.2 Cable Selection Specifications
| Purpose | Cable Type | Recommended Specification | Description |
|---|---|---|---|
| Pump power | RVV | 3×1.5mm² (≤0.5kW); 3×2.5mm² (0.5~1.5kW) | Copper conductor PVC insulated flexible cable |
| Control power | RVV | 2×1.0mm² | Control module power supply |
| Level signal | RVV | 4×0.75mm² | Electrode level signal cable |
| Alarm signal | RVV | 2×1.0mm² | Dry contact alarm output |
| Communication signal | RVSP | 2×1.0mm² | Shielded twisted pair, RS485 communication |
| Grounding | BVR | 1×2.5mm² | Yellow-green dual-color grounding wire |
10.3 Standard Powered Lift System Wiring
10.3.1 Power Supply Wiring
- Connect incoming power L (line), N (neutral), and PE (protective earth) to the control module’s power terminals.
- Install an air switch and RCD in series ahead of the power input as the system’s main disconnecting means.
- Connect pump power wires L, N, and PE to the control module’s pump output terminals; connect PE to the pump housing grounding terminal.
- Connect the audible/visual alarm device power wires to the control module’s alarm output terminals.
- All connections must use crimped ferrule terminals; insert into terminal blocks, tighten screws, and pull-test to verify secure connection.
10.3.2 Level Switch Wiring (Electrode Type)
Electrode-type level switches generally have four electrode wires corresponding to common, stop level, start level, and alarm level. Wiring is as follows:
- Common (COM): Connect to the control module’s common terminal.
- Stop Level (LOW): Connect to the control module’s low-level input.
- Start Level (HIGH): Connect to the control module’s high-level input.
- Alarm Level (ALARM): Connect to the control module’s alarm level input.
- Shield the cable with single-ended grounding to avoid interference; electrode wires must not be routed in the same conduit as power cables.
10.3.3 Alarm Output Wiring
- The control module provides a passive dry contact alarm output with three terminals: normally open (NO), normally closed (NC), and common (COM).
- Connect the local audible/visual alarm to the NO terminal: when the water level alarm triggers, the contact closes and energizes the alarm device.
- When connecting to the DCIM/BMS system, select NO or NC signal based on the system’s input type. NC (normally closed) is generally preferred, as a broken wire will also trigger the alarm (fail-safe).
- For interlocked AC shutdown, connect the alarm dry contact in series with the AC unit’s compressor control circuit to cut power to the AC unit upon overflow.
10.3.4 Grounding Wiring
- The system is equipped with a main grounding terminal. The pump housing, control cabinet housing, metal piping, and metal supports/hangers must all be cross-bonded with grounding conductors and connected to the main grounding terminal.
- The main grounding terminal connects to the equipment room grounding busbar; grounding resistance measured ≤4Ω.
- Grounding conductors use yellow-green dual-color wire with clear identification; must never be used as a neutral conductor.
10.4 Dual-Pump Redundant System Wiring
10.4.1 Duty/Standby Pump Control Logic
- Two pumps operate in duty/standby configuration: the primary pump runs under normal conditions; the standby pump automatically engages upon primary pump failure.
- Level signals are simultaneously input to both control circuits, with the primary pump circuit having priority response.
- Rotation function can be set to automatically alternate duty/standby pumps based on runtime, balancing the service life of both pumps.
- Highest-level alarm triggers when both pumps fail simultaneously or when water level remains excessively high.
10.4.2 Wiring Key Points
- Dual pumps use dual independent power supplies connected to different circuit breakers; loss of one circuit does not affect the other.
- Redundant level sensor configuration: if the primary sensor fails, the backup sensor automatically takes over.
- Manual/automatic selector switch provided in the control cabinet to allow manual single-pump operation during maintenance.
- Each pump circuit has independent overload and short-circuit protection; a fault trips only the affected pump without affecting the other.
10.5 Intelligent Monitoring System Wiring
10.5.1 Communication Wiring
- The intelligent control module connects to the DCIM/BMS system via RS485 bus using shielded twisted pair cable RVSP 2×1.0mm².
- The bus uses daisy-chain connection with 120Ω terminating resistor at each end to prevent signal reflection.
- Connect RS485 A and B lines correspondingly — reversed connections are prohibited; shield ground at one end only, grounding at the DCIM side.
- When communication distance exceeds 1000 meters, install an RS485 repeater to amplify the signal.
10.5.2 Leak Detection Cable Wiring
- Leak detection controller power supply: DC24V or AC220V.
- Connect both ends of the leak detection cable to the controller input terminals; lay the cable along the bottom of the piping and secure firmly.
- Keep the detection cable away from strong electromagnetic interference; do not route parallel to power cables.
- Connect the controller alarm output to the DCIM/BMS system for leak location alarms.
10.6 Wiring Workmanship Requirements
- Label both ends of all cables with tags indicating purpose and destination for future maintenance.
- Tighten terminal screws with moderate torque — sufficient for good contact without crushing the conductor strands.
- Multi-strand conductors must be terminated with crimped ferrules; direct insertion into terminals is prohibited.
- Route cables neatly with horizontal and vertical alignment; secure with cable ties at uniform spacing; leave service loops at bends to avoid strain.
- Separate power and signal cables with spacing ≥300mm; cross at right angles when intersection is unavoidable to minimize electromagnetic interference.
- After wiring, organize cable bundles neatly inside the control cabinet; secure with ties and replace the cover.
- Provide insulation protection for exposed live parts to prevent electric shock.
10.7 Post-Wiring Inspection
- Continuity Check: Use a multimeter’s continuity mode to verify each circuit’s continuity and correctness, checking for shorts, opens, or mis-wiring.
- Insulation Test: Use a 500V megger to measure insulation resistance between phase and neutral, phase and ground, and neutral and ground; insulation resistance ≥0.5MΩ is acceptable.
- Grounding Test: Measure system grounding resistance; ≤4Ω is acceptable.
- Visual Inspection: Wiring neat, labels clear, connections secure, no exposed conductors, protection in place.
- Complete the electrical wiring inspection record; energize and commission only after confirming all checks pass.
11.1 Pre-Commissioning Preparation
- Confirm pipe installation is complete; full-water test and water flow test passed; insulation work finished.
- Confirm electrical wiring is complete; insulation and grounding tests passed; power supply normal.
- Confirm AC equipment is installed and ready for commissioning.
- Prepare commissioning tools: multimeter, clamp-on ammeter, spirit level, measuring cup, stopwatch, thermometer, record book.
- Commissioning personnel must be familiar with system principles and operating procedures, with clear understanding of commissioning steps and safety precautions.
- Clean the site and eliminate safety hazards; set up warning signs in the commissioning area; unauthorized personnel must not enter.
11.2 Individual Component Commissioning
11.2.1 Pump Standalone Commissioning
- Disconnect the pump from the piping or confirm the piping is unobstructed.
- Jog the pump power to check motor rotation direction matches the label; if reversed, swap any two phase wires.
- Run the pump unloaded for 5 minutes, checking for abnormal noise or excessive vibration.
- Measure no-load current; should be within 30%~50% of rated current; three-phase current imbalance ≤5%.
- Check pump seals for leakage; mechanical seal leakage ≤3 drops/minute is considered normal.
- Test pump start/stop control: short the start signal, the pump should start immediately; disconnect the signal, the pump stops after the delay period.
11.2.2 Level Switch Commissioning
- Slowly fill water into the collection tank, observing whether signals at each level point trigger correctly.
- When the water level reaches the start level, the control module should output the pump start signal.
- When the water level drops to the stop level, the control module should output the pump stop signal.
- When the water level reaches the alarm level, the audible/visual alarm should trigger and the alarm output contacts should actuate.
- Record the actual water level heights at each trigger point; deviation from design values ≤±10mm.
- Repeat the test 3 times; accurate and reliable operation in all tests is acceptable.
11.2.3 Alarm Function Commissioning
- Simulate an overflow condition by raising the water level to the alarm line; verify the audible/visual alarm operates correctly with proper volume and flashing.
- Verify the DCIM/BMS system receives the alarm signal correctly with accurate alarm information.
- Test the interlocked shutdown function: after alarm triggers, the AC unit should shut down according to the programmed logic.
- Disconnect the level signal wire to test the broken-wire fault alarm function.
- Simulate pump overload to verify the overload protection actuates and the fault alarm triggers.
11.3 System Water Commissioning
11.3.1 Gravity System Water Commissioning
Slowly inject clean water into the air conditioner condensate drain pan, with the flow rate simulating the rated condensate water volume.
Observe the water level changes in the drain pan. It should rise steadily and then stabilize, with no rapid rise and no overflow.
Check whether the piping drainage is smooth, and whether the water discharge at the end drain outlet is continuous and uniform, with no air lock or splashing phenomena.
Check all piping joints, valves, and trap locations for any leakage.
Check the insulation layer surface for condensation. Use a temperature measuring instrument to measure the external surface temperature of the insulation layer, which should be higher than the ambient dew point temperature.
Continue water flow for 30 minutes. The system is deemed qualified if operation is stable with no overflow, no leakage, and no condensation.
11.3.2 Powered System Water Commissioning
Inject water into the water collection tank. When the water level reaches the start level, the water pump should automatically start draining.
Observe the pump operating status. Current, sound, and vibration should be normal, and drainage should be continuous and stable.
When the water level drops to the stop level, the pump should automatically stop. Record the single drainage duration and the start-stop interval.
Increase the water injection volume to 1.5 times the rated condensate water volume to test the system’s maximum drainage capacity. The water level should stabilize near the start level and must not exceed the alarm level.
Check the check valve function. After the pump stops, water in the piping should not flow backward, and the tank water level should not show obvious rebound.
Check the piping for vibration and noise. Support hangers should not be loose.
Continue operation for 2 hours. The system is deemed qualified if the pump starts and stops normally, with no fault alarms and no tank overflow.
11.4 Linkage Commissioning
11.4.1 Linkage with Air Conditioning Units
Start the air conditioning unit in cooling mode and run until stable operating conditions are reached. The evaporator begins to produce condensate water.
Observe the status of condensate water flowing into the drainage system. The drain pan should have no accumulated water or overflow.
The powered system should start and stop automatically with condensate water production. The logic should be normal with no frequent start-stop cycling.
After the air conditioning unit shuts down, the system should drain the remaining condensate water and then shut down automatically. There should be no residual water in the tank.
Simulate a drainage fault by artificially blocking the drain outlet. When the water level rises to the alarm value, the air conditioning unit should shut down for protection as set.
11.4.2 Linkage with Environmental Monitoring System (EMS)
The environmental monitoring system should display system operating status in real time: water level, pump operating status, fault alarms, etc.
Data refresh should be normal with a delay of ≤3 seconds. Data should be accurate.
When a fault alarm occurs, the environmental monitoring system should pop up alarm information and simultaneously push SMS and APP notifications.
Historical data storage should function normally, allowing query of water level curves, pump operating duration, fault records, etc.
Test remote control functions (if configured): remote start/stop of pumps, parameter settings, etc.
11.5 72-Hour Continuous Trial Operation
After the system commissioning passes, conduct a 72-hour continuous trial operation to verify long-term operational stability.
The air conditioning unit operates at full load, with the drainage system operating in synchronization.
Conduct inspections every 4 hours, recording water level, pump operating current, start-stop frequency, any leakage, any condensation, and other data.
During the trial operation, the system should have no faults, no alarms, no overflow, no leakage, and no abnormal condensation.
The cumulative pump operating time should meet design expectations, with no frequent start-stop cycling and no overheating.
After the trial operation concludes, comprehensively inspect the system status, clean the filter and any sediment in the water tank.
Complete the trial operation record. All parties sign for confirmation as the basis for acceptance.
11.6 Commissioning Precautions
The commissioning process must be strictly carried out step by step: single equipment before system, manual before automatic, advancing progressively.
During electrical commissioning, dedicated personnel must be on duty. If any abnormality occurs, cut off power immediately, troubleshoot the problem, and then continue.
During water injection commissioning, control the water injection speed to avoid overflow caused by excessive instantaneous flow.
Take proper protection when working at height. When commissioning high piping sections, use a ladder with dedicated personnel holding it steady.
Keep detailed records during the commissioning process, including parameters, time, phenomena, and corrective measures.
After commissioning is complete, restore the system to normal operating status and clean up site tools and debris.
12.1 Installation and Construction Safety Precautions
Construction personnel must wear safety helmets, work clothes, and protective footwear. When working at height, safety belts must be worn and high-altitude operation regulations followed.
Before using power tools, check that insulation is intact and power cords are not damaged. Temporary electrical connections must be equipped with residual current circuit breakers. Unauthorized wiring is strictly prohibited.
Wear protective goggles when cutting pipes to prevent debris from injuring eyes. PVC cutting debris should be cleaned up promptly to prevent slipping.
Maintain ventilation when applying PVC adhesive to avoid inhaling irritant gases. Keep adhesive away from fire sources and store in a cool, dry place.
When pressure testing pipes, increase pressure slowly. Never repair joints while under pressure. Set up warning signs in the test area and keep unrelated personnel away.
When working in suspended ceilings, wear anti-slip shoes and confirm the ceiling grid load-bearing capacity is reliable. Use 36V safety voltage for handheld lighting.
Hot work operations (welding, cutting) require a hot work permit, fire extinguishers on site, dedicated fire watch personnel, and confirmation that no fire hazards remain before leaving the site.
When moving heavy equipment (large pumps, water tanks), use unified command, handle with care, and prevent crushing injuries and equipment damage.
At the end of each construction day, turn off temporary power and clean up the site to eliminate safety hazards.
12.2 Electrical Wiring Safety Precautions
Electrical work must be performed by certified electricians, strictly following electrical safety regulations.
Power must be disconnected before wiring. Verify no voltage is present before commencing work. Hang a warning sign reading “Under Repair – Do Not Close Switch.”
The system must be reliably grounded, with grounding resistance meeting requirements. Never connect the ground wire to water pipes, gas pipes, or other piping.
The power circuit must be equipped with residual current protection devices. Test the effectiveness of residual current circuit breakers regularly.
Never insert or remove terminals or make connections while energized. In humid environments, strengthen insulation protection to avoid electric shock.
Cables must not have exposed conductors. Joints must be properly insulated. Avoid crushing, stepping on, or scratching cables.
Do not store debris inside the control cabinet. Maintain proper heat dissipation. Keep the cabinet door closed and locked to prevent unauthorized access.
Do not start-stop the pump motor frequently. The interval between two starts must be no less than 3 minutes to prevent motor overheating and burnout.
If electrical abnormalities are detected such as smoke, odor, or unusual noise, cut off power immediately and troubleshoot before resuming use.
12.3 Commissioning and Operation Safety Precautions
Dedicated personnel must be on duty at the commissioning site. In case of overflow, electrical leakage, or other abnormalities, stop the machine and cut off power immediately.
Do not leave the site without authorization during trial operation. Conduct regular inspections and keep records.
Do not remove protective covers or touch rotating parts while the pump is operating.
Do not touch live parts of electrode level switches with bare hands to prevent electric shock.
When simulating fault tests, prepare emergency measures to prevent actual overflow accidents.
When commissioning in a machine room, protect surrounding IT equipment. Do not splash water onto equipment. Prepare rags, mops, and other emergency items.
When the system alarms, investigate the cause promptly. Reset the alarm after clearing the fault. Do not bypass alarms to force system operation.
12.4 Daily Use Safety Precautions
Machine room operation and maintenance personnel should understand the system’s basic principles and emergency handling methods. Do not modify the system structure without authorization.
It is strictly prohibited to hang heavy objects on pipes or pumps, or to step on pipes.
It is strictly prohibited to block the drainage end. Do not throw debris into floor drains or collection wells.
Do not arbitrarily adjust the position of level switches or change control parameters. If adjustment is needed, professional personnel must perform the operation.
Regularly check the effectiveness of residual current circuit breakers and grounding devices to ensure electrical safety.
Pay attention to frost protection in low-temperature winter environments. When shutting down for extended periods, drain the water in the pipes to prevent freezing and cracking.
If system overflow occurs, immediately turn off the power supply of the corresponding air conditioner and drainage system, clean up the accumulated water, troubleshoot the fault, and strictly prohibit energizing before the water is completely dry.
If an electrical fault occurs, cut off power first, then contact professional personnel for repair. Do not disassemble electrical components yourself.
12.5 Transport and Storage Safety Precautions
Handle products with care during transport, avoiding severe collision and dropping to prevent damage to pumps, water tanks, and pipe fittings.
Electrical equipment must be protected against moisture, dust, and rain during transport and storage. Do not store outdoors.
PVC pipes should avoid direct sunlight and stay away from heat sources to prevent aging and deformation. Stacking height should not exceed 1.5 meters to prevent compression deformation.
Insulation materials must be kept away from fire and heat sources, stored in a cool, ventilated place, and comply with fire protection requirements.
For long-term storage of pumps, drain internal water and periodically energize for a few minutes of no-load operation to prevent motor moisture damage.
Product storage environment: temperature -10~40°C, relative humidity ≤80%, no corrosive gases, good ventilation.
13.1 Daily Inspection (Daily/Weekly)
13.1.1 Inspection Content
- Observe whether the air conditioner drain pan has accumulated water or overflow, and whether the drain outlet is blocked by debris.
- Listen for abnormal pump operating sounds, unusual noise, or excessive vibration.
- Check whether the control module indicator lights are normal and whether there are fault alarms.
- Check pipes and joints for leakage or dripping, and check the insulation layer for damage or condensation.
- Check whether the end drainage points drain smoothly and whether floor drains are blocked.
- Check the sound and light alarm status for any alarm indications.
13.1.2 Inspection Frequency
| Type | Frequency |
|---|---|
| Core machine room | 1 inspection per day |
| Ordinary machine room | 1 inspection per week |
| Unattended machine room | Remote monitoring via environmental monitoring system, check operating data daily |
13.1.3 Inspection Records
Fill in the inspection record form, recording inspection time, operating status, abnormal conditions, and corrective measures. Keep records archived.
13.2 Monthly Maintenance
- Clean the drain pan: Open the air conditioner maintenance panel, remove the drain pan filter screen, rinse clean; wipe the inner wall of the drain pan to remove dust, sludge, and algae.
- Check the water tank: Open the collection tank maintenance cover, clean sediment inside, rinse the inner wall; check the level electrodes for scaling and wipe clean with a soft cloth.
- Clean the filter: Disassemble the Y-type filter, remove the filter screen, rinse to remove impurities; check the filter screen for damage and replace if damaged.
- Pipe appearance inspection: Along the piping route, check the insulation layer for damage or detachment, joints for leakage, and support hangers for looseness.
- Electrical inspection: Tighten wiring terminals, check cables for aging or damage; test residual current circuit breaker operation.
- Functional test: Manually inject water to test pump start-stop and alarm functions.
- End point cleaning: Clean debris from drainage floor drains to ensure smooth drainage; check whether the water seal has dried up and replenish water to maintain an effective seal.
13.3 Quarterly Maintenance
- Deep pipe cleaning: Inject dedicated cleaning agent (neutral air conditioning cleaner) from the drain pan, soak for 30 minutes, then rinse with clean water to remove algae, biofilm, and scale from pipe walls.
- Ball passage test: Perform a ball passage test on main pipes to check pipe smoothness. If the ball does not pass smoothly, perform unclogging.
- Pump inspection: Check that the pump base is securely fixed and vibration dampers are not aged; measure pump operating current and compare with rated values to assess operating status.
- Insulation inspection: Comprehensively check insulation layer integrity and repair damaged areas; focus on pipe fittings, valves, and joints to eliminate cold bridges.
- Grounding test: Measure system grounding resistance to ensure ≤4Ω; check each grounding point for looseness or corrosion.
- Alarm linkage test: Test the overflow alarm and environmental monitoring linkage function to ensure the alarm channel is unobstructed.
13.4 Annual Major Overhaul
- System comprehensive flushing: Use a combination of high-pressure water flushing and chemical cleaning to thoroughly remove dirt, algae, and scale from pipe walls; after cleaning, drain wastewater and rinse repeatedly with clean water until the effluent is clear.
- Pump disassembly and maintenance: Disassemble the pump, check impeller wear (replace if severely worn), check the mechanical seal (replace seal if leaking), add grease to bearings (replace bearings if noisy), perform motor insulation testing (dry or repair if insulation is insufficient).
- Level sensor calibration: Remove level electrodes or floats, clean and descale; calibrate level trigger points; replace if error is excessive.
- Control module inspection: Clean dust inside the control cabinet, check the circuit board for corrosion or cold solder joints; test all functional parameters, calibrate clock and communication.
- Comprehensive pipe inspection: Check pipes for aging and corrosion. For PVC pipes, check for yellowing or embrittlement. For metal pipes, check for rust and wall thickness reduction. Replace damaged sections promptly.
- Support hanger reinforcement: Tighten all support hangers comprehensively, remove rust and repaint corroded areas; adjust pipe slope to ensure compliance.
- Insulation layer overall assessment: Check insulation layer aging. If insulation performance has degraded, replace entirely; replace aged insulation tape and reseal joints.
- Comprehensive electrical inspection: Cable insulation testing (replace aged cables); comprehensive testing of switches, terminals, and protective devices (replace failed components); overall electrical safety assessment.
- Performance testing: Full-load water flow test to verify system maximum drainage capacity, response time, alarm thresholds, and other performance indicators; assess system status.
- Documentation update: Organize maintenance records, update equipment ledger, record replaced components and parameter adjustments.
13.5 Wear Parts Replacement Standards
| Component | Standard Replacement Cycle | Replacement Criteria |
|---|---|---|
| Drain pan filter screen | 6 months | Damaged, clogged beyond cleaning, deformed |
| Pump inlet filter screen | 12 months | Damaged, mesh deformed, severely clogged |
| Level switch (electrode type) | 5 years | Detection failure, severely scaled beyond cleaning, corrosion fracture |
| Level switch (float type) | 3 years | Sticking, failure, seal failure with water ingress |
| Pump mechanical seal | 2-3 years | Leakage exceeding limits, abnormal noise, severe wear |
| Pump bearing | 3-5 years | Abnormal noise, excessive vibration, uneven rotation |
| Check valve | 5 years | Seal failure, backflow, sticking |
| Insulation material | 8-10 years | Aging, cracking, reduced insulation performance, condensation |
| Control module | 8-10 years | Functional failure, component aging, communication abnormality |
| Rubber-plastic insulation tape | 5 years | Detachment, aging, loss of adhesion |
13.6 Maintenance Safety Precautions
- Disconnect system power before maintenance work and hang warning signs to prevent accidental switch-on.
- Wear rubber gloves when cleaning water tanks and pipes to avoid contact with dirt and cleaning agents.
- Wear protective goggles and masks during chemical cleaning to prevent cleaning agents from splashing into eyes or being inhaled.
- Wear safety belts when performing maintenance at height. Keep tools in tool bags to prevent falling tool injuries.
- Disconnect power before pump disassembly. Confirm the impeller has completely stopped rotating before disassembly.
- Take waterproofing measures during maintenance to avoid water splashing onto electrical equipment and machine room IT equipment.
- After maintenance is complete, conduct a comprehensive check to confirm no tools are left inside equipment before energizing for testing.
- Record maintenance content and replaced components, and file them in the equipment archive.
14.1 Poor Drainage Faults
Fault 1: Drain pan water accumulation, slow drainage
Possible causes:
- Drain pan drain outlet filter screen blocked
- Trap sediment blockage
- Insufficient pipe slope, slow water flow velocity
- Air lock in the pipe hindering water flow
- Scale and algae buildup on inner pipe walls, reducing pipe diameter
- End drainage point blocked, causing poor drainage
Troubleshooting steps:
1. First check the drain pan drain outlet and remove the filter screen to see if it is blocked
2. Check the end drain outlet discharge condition to determine whether blockage is at the front or back end
3. Use a level to re-measure pipe slope to confirm compliance
4. Tap the pipe and listen to estimate the blockage location
5. Open the inspection port to view internal conditions
Solutions:
- Filter screen blocked: Remove, clean, or replace
- Trap blocked: Open the trap cleanout and remove debris
- Insufficient slope: Adjust support hanger heights to correct pipe slope
- Air lock: Install an air release valve at the highest point of the pipe to expel air
- Pipe scaling: Flush with pipe cleaning agent or use a drain unclogging tool
- End blockage: Clean debris from floor drains and collection wells, unclog the main drain pipe
Fault 2: Complete drainage failure, drain pan overflow
Possible causes:
- Complete pipe blockage, foreign object stuck
- Severe reverse slope in pipe, water cannot flow
- Trap dried out then sealed by air lock
- Winter pipe freezing, ice blockage
- Powered system pump completely failed
Troubleshooting steps:
1. Water injection test to observe whether the water level does not drop at all
2. Check from the end in reverse direction, progressively locating the blockage point
3. Check pipe routing for obvious reverse slope
4. Check for ice formation in low-temperature environments
Solutions:
- Complete blockage: Use a pipe unclogging machine or disassemble sections for cleaning
- Severe reverse slope: Re-correct the pipe routing to ensure proper slope
- Air lock seal: Inject water into the pipe to break through the air seal and restore the water seal
- Ice blockage: Use hot air or heat tracing to melt ice, then add insulation and heat tracing
- Pump failure: Troubleshoot per pump fault procedures
14.2 Leakage and Overflow Faults
Fault 3: Leakage at pipe joints
Possible causes:
- Uneven PVC adhesive application, poor bonding
- Insufficient Teflon tape wrapping on threaded joints, poor sealing
- Pinholes or cracks in welded joints
- Pipe squeezed by external force causing joint cracking
- Seal ring aging and deformation, seal failure
- Pipe vibration causing joint loosening
Troubleshooting steps:
1. Wipe dry the leaking area and observe the leak point location and seepage volume
2. Check joints for cracking or deformation
3. Gently shake the pipe to observe if seepage worsens
Solutions:
- PVC adhesive leakage: Drain and dry, reapply adhesive for bonding; replace the pipe section if severe
- Threaded joint leakage: Disassemble, rewrap with Teflon tape, and reinstall
- Weld leakage: Repair by re-welding or replace the fitting
- External force cracking: Repair the pipe, eliminate the source of external force
- Seal ring failure: Replace with a new seal ring
- Vibration loosening: Reinforce support hangers and add vibration damping pads
Fault 4: Condensation and dripping on the outer pipe wall
Possible causes:
- Insufficient insulation layer thickness, poor anti-condensation performance
- Insulation layer damaged or detached, pipe exposed
- Insulation joint cracks, cold bridge leakage
- Abnormal rise in ambient humidity beyond design range
- Pipe fittings and valves not insulated, cold bridge condensation
- Insulation material water ingress, insulation failure
Troubleshooting steps:
1. Check the insulation layer condition at the dripping location
2. Measure ambient temperature and humidity, calculate the dew point temperature
3. Check whether insulation at pipe fittings, joints, and support hangers is complete
4. Press the insulation layer to determine whether it has absorbed water
Solutions:
- Insufficient thickness: Add insulation layers or replace with higher-performance insulation material
- Damage/detachment: Repair damaged areas, re-adhere and secure
- Joint cracks: Reapply adhesive at joints, wrap with insulation tape for sealing
- Excessive humidity: Coordinate with machine room dehumidification to reduce ambient humidity
- Uninsulated fittings: Add insulation to valves, tees, flanges, and other parts
- Insulation water ingress: Remove water-soaked insulation, dry the pipe, and re-insulate
Fault 5: Collection tank overflow
Possible causes:
- Pump not started, control or power supply fault
- Insufficient pump head, cannot pump water out
- Pump impeller blocked, insufficient flow
- Check valve blocked, poor outlet flow
- Level switch failure, cannot trigger pump start
- Condensate water volume far exceeding design value, pump capacity insufficient
Troubleshooting steps:
1. Observe whether the pump is running, determine whether the pump is not turning or turning but not discharging
2. Check the water level and level switch position to determine whether the switch operates normally
3. Measure the pump power supply voltage to determine whether power supply is normal
4. Check outlet flow rate to determine drainage capacity
Solutions:
- Pump not starting: Troubleshoot per pump electrical fault procedures
- Insufficient head: Verify selection and replace with a higher-head pump
- Impeller blocked: Disassemble the pump to clear debris from the impeller
- Check valve blocked: Disassemble, clean, or replace the check valve
- Level switch failure: Clean electrodes or replace the level switch
- Excessive water volume: Recalculate condensate volume, add pumps or increase pipe diameter
14.3 Pump Faults
Fault 6: Pump completely does not start, no response
Possible causes:
- Power supply interrupted, circuit breaker tripped
- Control module failure, no output
- Level switch failure, no start signal
- Pump motor burned out, coil open circuit
- Loose or disconnected wiring
- Overload protection activated, not reset
Troubleshooting steps:
1. Check the power circuit breaker status for tripping
2. Use a multimeter to measure voltage at the pump input to determine if power is present
3. Short-circuit the level switch signal to test whether the pump starts
4. Measure motor coil resistance to determine if the circuit is open
5. Check wiring terminals for looseness or burn marks
Solutions:
- Circuit breaker tripped: Close the breaker; if it trips repeatedly, troubleshoot for short circuit faults
- Control module failure: Replace the control module
- Level switch failure: Repair or replace the level switch
- Motor burnout: Replace the pump motor or the entire pump
- Loose wiring: Re-tighten connections, crimp terminals
- Overload protection: Identify the overload cause and reset the protector
Fault 7: Abnormal noise and excessive vibration after pump starts
Possible causes:
- Pump air intake, cavitation noise
- Impeller blocked or wrapped with debris, dynamic balance disrupted
- Bearing wear, insufficient lubrication
- Loose fixing screws, base vibration
- Pump-pipe resonance
- Motor rotor scraping the stator
Troubleshooting steps:
1. Listen to the noise source to determine whether it comes from the motor or pump body
2. Observe whether the outlet water flow has air bubbles to determine air intake
3. Touch the pump body to check vibration status and base fixation
4. After power-off, rotate the impeller to check for sticking
Solutions:
- Air intake/cavitation: Check the suction pipe for air leaks, lower installation height, fully purge air from the pipe
- Impeller blockage: Disassemble and clear debris from the impeller
- Bearing failure: Replace bearings, apply grease
- Loose fixation: Tighten base screws, replace vibration damping pads
- Pipe resonance: Adjust support hanger spacing, add flexible vibration-damping connections
- Motor rotor scraping: Repair or replace the motor
Fault 8: Insufficient pump flow, slow drainage
Possible causes:
- Inlet filter blockage, poor water intake
- Impeller wear, reduced efficiency
- Insufficient speed, low voltage
- Reverse rotation
- Insufficient head, actual resistance exceeds design
- Discharge pipe blockage
Troubleshooting steps:
1. Check whether the inlet filter is blocked
2. Measure whether the power supply voltage is normal
3. Confirm whether the pump rotation direction is correct
4. Check whether the outlet valve and piping are unobstructed
Solutions:
- Filter blockage: Clean the filter screen
- Impeller wear: Replace the impeller or the entire pump
- Low voltage: Stabilize the power supply voltage
- Reverse rotation: Swap any two phase wires
- Insufficient head: Replace with a higher-head pump
- Discharge blockage: Unclog the discharge pipe
14.4 Alarm and Control Faults
Fault 9: Frequent false alarms
Possible causes:
- Level electrode scaling causing false conduction
- Large water level fluctuation, frequently touching the alarm line
- Improper control module parameter settings, excessive sensitivity
- Moisture in wiring, insulation degradation, signal interference
- Float switch sticking, false actuation
Troubleshooting steps:
1. Observe the actual water level to determine whether it truly reaches the alarm position
2. Check electrode surfaces for scale or algae
3. Check wiring for moisture damage
4. Check whether alarms trigger irregularly and frequently
Solutions:
- Electrode scaling: Clean electrode surfaces, soak in white vinegar to descale
- Water level fluctuation: Install a flow stabilizing plate in the tank to reduce fluctuation
- Improper parameters: Adjust control module alarm thresholds, increase hysteresis
- Wiring moisture: Dry the wiring, replace damaged cables, provide waterproofing
- Float sticking: Clean debris around the float, re-fix
Fault 10: Alarm does not trigger
Possible causes:
- Alarm device damaged
- Alarm circuit open circuit
- Level switch alarm electrode damaged
- Control module alarm output fault
- Alarm power supply not connected
Troubleshooting steps:
1. Manually short-circuit the alarm output terminal to test whether the alarm device works
2. Measure the alarm circuit continuity
3. Simulate high water level and measure whether the alarm electrode conducts
Solutions:
- Alarm device broken: Replace the sound and light alarm
- Circuit open circuit: Repair wiring
- Level switch broken: Replace the level switch
- Module fault: Repair or replace the control module
- Power supply issue: Connect the alarm power supply
14.5 Other Common Faults
Fault 11: Odor in pipes, mosquito breeding
Possible causes:
- Trap water seal dried out, losing its barrier function
- End directly connected to sewage pipe, no air gap
- Long-term water accumulation breeding bacteria and algae, producing odor
- Floor drain water seal failure, odor backflow
Solutions:
- Replenish water to the trap to restore the water seal; regularly replenish to prevent drying
- Rectify the end drainage to indirect drainage, maintaining an air gap
- Inject disinfectant into the pipe, clean the pipe, kill algae and bacteria
- Replace with self-closing floor drains, regularly replenish water to maintain the seal
Fault 12: Winter pipe freezing and cracking
Possible causes:
- Winter shutdown, water in pipes not drained
- Outdoor pipes without insulation and heat tracing
- Drain pan freezing in low-temperature environments, blocking the drain outlet
Solutions:
- Drain water from pipes during long-term shutdown; for short-term winter shutdown, maintain low-flow operation for freeze protection
- Install electric heat tracing + thickened insulation on outdoor pipes, with thermostat-controlled tracing
- Add electric heating to the drain pan, automatically activating during low temperatures for freeze protection
- For already-frozen pipes: Replace damaged sections and implement freeze protection measures
Basic Questions
Q1: Is insulation mandatory for the condensate drainage system?
A: Yes, insulation is mandatory in machine room scenarios. Because the condensate water temperature is lower than the machine room air dew point temperature, exposed pipes will cause condensation and dripping on the outer wall. Dripping onto electronic equipment can cause short circuits and damage. According to GB 50174-2017 “Data Center Design Specification,” water supply and drainage pipes in machine rooms must adopt anti-condensation measures. The insulation layer thickness should be calculated based on ambient temperature and humidity. For conventional machine rooms, it should not be less than 10mm, and should be thickened in high-humidity environments.
Q2: Which is more reliable: gravity drainage or lift pump drainage?
A: From a reliability perspective, gravity self-flow drainage is more reliable. Gravity systems have no electrical moving parts and rarely fail. Their service life matches the building’s lifespan. However, gravity drainage depends on building elevation differences and slope conditions, which many scenarios cannot satisfy. Lift pump drainage overcomes spatial limitations but carries a probability of electrical faults. For high-reliability applications, a composite solution of “gravity primary, lift backup” is recommended, balancing flexibility and reliability.
Q3: Can condensate pipes be directly connected to sewage pipes?
A: No. According to the “Standard for Design of Building Water Supply and Drainage” GB 50015, condensate water is classified as clean wastewater and must adopt indirect drainage. Direct connection with sewage pipes is strictly prohibited. It must be indirectly connected to floor drains or drainage channels through air gaps, drainage funnels, etc., to prevent sewage, odor, and pathogenic bacteria from flowing backward.
Q4: Why is a trap required at the air conditioner drain pan outlet?
A: There are two main functions: 1. Water seal for odor prevention, blocking odors and insects from the drainage pipe system from backflowing into the air conditioning unit and then entering the machine room through the supply air; 2. It is essential for negative pressure units. When the air conditioner fan is located downstream of the cooling coil, the drain pan is in a negative pressure zone. Without a trap water seal, condensate water would be held by negative pressure and unable to drain. Air could even be sucked in, blowing up water splashes. The trap water seal height must be greater than the water column height corresponding to the unit’s negative pressure, and not less than 50mm.
Selection Questions
Q5: How is the condensate pipe diameter determined?
A: The pipe diameter is determined by the maximum condensate water volume, which can be estimated from the air conditioner cooling capacity: each 10kW of cooling capacity corresponds to approximately 5kg/h of condensate water, corresponding to a branch pipe of DN20~DN25. When multiple units are combined, the total flow rate is summed and the table is consulted for selection. Slope and pipe length also need to be considered. For long-distance pipes, increase the pipe diameter by one grade. Standard selection reference: DN20 for single units of 5~12kW, DN25 for 12~25kW, DN32 for 25~50kW, progressively increasing after multiple units are combined.
Q6: How is the lift pump head selected?
A: The pump rated head must be greater than the sum of “vertical lift height + pipe friction loss + local resistance,” with a 1.2 times safety margin reserved. The vertical height is the vertical distance from the pump outlet to the highest drainage point. Friction loss is calculated based on pipe length and diameter, with approximately 0.5~1m head loss per 10 meters of pipe. Local resistance includes elbows, valves, and fittings, with each elbow approximately 0.2~0.5m head loss. For example: vertical lift of 3 meters, total pipe length of 20 meters, 5 elbows, total resistance is approximately 3+1+2=6m. A pump with a rated head of 8~10m is sufficient.
Q7: Is overflow alarm mandatory in machine rooms?
A: Recommended, and mandatory for core machine rooms. Electronic equipment in machine rooms is of high value and overflow accidents cause significant losses. An overflow alarm can alert at the first sign of abnormal water levels, preventing accident escalation. According to GB 50174, Class A data centers should be equipped with leak detection systems, and the condensate water area is a key monitoring location. The alarm can be integrated with the environmental monitoring system for remote notification, which is especially necessary for unattended machine rooms.
Installation Questions
Q8: What is the required slope for condensate pipes? Can they run level?
A: Code requires condensate branch pipe slope ≥1% (10mm drop per meter), and main pipe slope ≥0.5%. Completely level runs are not permitted. A level slope causes excessively slow water flow, sediment deposition, and eventual pipe blockage over time. It can also create air locks that obstruct drainage. If space constraints genuinely prevent slope installation, a powered lift solution should be adopted. Do not force level-slope gravity drainage.
Q9: Why can’t support hanger spacing be too large?
A: If support hanger spacing is too large, the pipe will sag and deform under its own weight, forming depressions in the middle. This causes localized water accumulation and slope failure, and can also cause joint cracking from stress. Different pipe materials have different rigidity and spacing requirements: PVC pipes have poor rigidity and spacing should not exceed 0.8 meters; galvanized steel pipes have good rigidity and spacing should not exceed 1.2 meters. Additional brackets should be installed at corners and joints.
Q10: Why is a sleeve required at wall penetrations?
A: Sleeves serve three functions: 1. Protecting the pipe from being squeezed and damaged during wall settlement or thermal expansion/contraction; 2. Facilitating repair and replacement since the pipe can be pulled out of the sleeve without destroying the wall; 3. Fire sealing, with fire-resistant putty filled between the sleeve and pipe to meet building fire protection requirements, preventing smoke and flames from spreading through the opening.
Operation and Maintenance Questions
Q11: How often should the condensate system be cleaned?
A: For conventional machine rooms, clean the filter screen quarterly and perform a deep pipe flush every six months. In high-humidity, dusty, or poor air quality environments, double the cleaning frequency. This is because pipes remain damp for long periods, readily breeding algae and biofilm while accumulating dust and sludge, eventually blocking the pipe. When cleaning, use a neutral air conditioning cleaner or diluted white vinegar, soak, and then rinse clean.
Q12: How long is the lift pump lifespan? Is it prone to failure?
A: Quality condensate lift pumps, under normal use and regular maintenance, can achieve an average service life of 5-8 years, with a mean time between failures (MTBF) exceeding 30,000 hours. Pumps are wear parts, but their failure rate is not inherently high. Most failures result from impeller blockage due to long-term neglect of cleaning, or motor burnout from overload. Regular filter cleaning and tank debris removal can significantly extend pump life.
Q13: What should be done when the trap water seal dries out?
A: When machine room air conditioners are shut down for extended periods, the water in the trap gradually evaporates and dries, losing the water seal function and allowing odor backflow. The solution is simple: if shutdown exceeds 1 month, periodically pour a cup of clean water into the drain pan to replenish the trap water seal; or install an automatic water replenishment device at the trap. Before resuming operation, replenish the water first, then start the air conditioner.
Q14: The insulation layer surface is slightly wet. Is this normal?
A: Not normal. Under normal conditions, the insulation layer outer surface should be dry. If the surface is damp or even dripping, it indicates insufficient insulation performance and condensation has already occurred. Possible causes are insulation layer too thin, joint cracking, insulation damage, or excessively high ambient humidity. Timely troubleshooting and treatment are needed, either repairing or thickening the insulation. Otherwise, prolonged dripping will damage ceilings and floors, and could even drip onto equipment.
Fault Questions
Q15: The air conditioner drips as soon as it starts. Is the drainage system broken?
A: Not necessarily. First check common causes: 1. The drain pan filter screen is blocked, causing slow drainage and overflow; 2. The air conditioner is not installed level, the drain pan is tilted, and water overflows from the lower side; 3. The evaporator fins are dirty and blocked, causing condensate to be blown out of the drain pan by the airflow; 4. Insulation failure causing condensation on the pipe or drain pan outer wall. If all the above are excluded, then check whether the drainage pipe is blocked. Most dripping problems are not caused by the pipe itself being broken, but by inadequate cleaning or minor installation issues.
Q16: What causes the pump to run continuously without stopping?
A: Three common causes: 1. Level switch failure, the stop electrode cannot break the circuit, continuously sending a start signal to the pump; 2. Check valve failure, water flows back from the pipe, the water level cannot drop, and the pump keeps working; 3. The condensate water volume is too large, the pump capacity is insufficient, and the water level cannot drop to the stop position. When troubleshooting, first check whether the water level truly cannot drop, then check the level switch and check valve.
Q17: How is a blocked pipe cleared?
A: Slight blockage: Pour pipe unclogging agent or white vinegar from the drain pan, soak for half an hour, then flush with large amounts of clean water; or use an air pump to blow air backward from the drain outlet. Moderate blockage: Use a soft spring unclogging tool inserted through the inspection port. Severe blockage: Locate the blockage point and disassemble the pipe for cleaning. Regular cleaning can prevent blockage. Try to avoid having to deal with severe blockage after it occurs.
Special Scenario Questions
Q18: Will condensate pipes freeze in northern winters?
A: Indoor machine room pipes generally will not freeze because machine room temperatures are typically maintained above 20°C year-round. However, outdoor sections and pipes in non-heated areas, when winter temperatures drop below 0°C, can have water freeze and expand inside the pipe, causing pipe cracking. Solutions: Outdoor pipes should have thickened insulation + electric heat tracing. Drain all water from pipes during long-term shutdowns. The drain pan can be optionally equipped with electric heating for freeze protection.
Q19: What should be noted when using lift pumps in high-altitude areas?
A: In high-altitude areas, low atmospheric pressure reduces the boiling point of water, making pumps prone to cavitation and reduced suction capacity. Considerations: 1. Install the pump as low as possible to reduce suction lift; 2. Increase the inlet pipe diameter to reduce inlet resistance; 3. Select high-altitude duty pumps with cavitation-optimized impellers; 4. Install more air release valves to promptly expel air from the pipe.
Q20: Can condensate water be recycled?
A: Yes. Air conditioner condensate water is distilled-water grade pure water with few impurities. It can be recycled for cooling tower make-up water, landscape irrigation, toilet flushing, floor cleaning, and other uses to conserve water resources. When recycling, filtration, disinfection, and storage devices should be installed to ensure water quality meets usage requirements. Large data centers can see substantial condensate recovery volumes with meaningful water conservation benefits.
16.1 Acceptance Basis
- “Data Center Design Specification” GB 50174-2017
- “Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works” GB 50243-2016
- “Code for Acceptance of Construction Quality of Building Water Supply, Drainage and Heating Works” GB 50242-2002
- “Code for Acceptance of Construction Quality of Building Electrical Works” GB 50303-2015
- Design and construction drawings, technical disclosure documents
- Technical requirements in this product manual
16.2 Acceptance Stage Division
16.2.1 Material Incoming Inspection
Pipes, fittings, pumps, insulation materials, electrical accessories, and other materials must be inspected upon arrival at the site. They may only be used after passing inspection.
Inspection content:
- Verify product model, specification, and quantity match the contract and design
- Check that product certificates, quality inspection reports, warranty documents, etc. are complete
- Visual inspection: pipes free from damage, deformation, and corrosion; insulation material thickness uniform without damage; pump appearance intact with complete accessories
- Key materials sampled and sent for testing, such as insulation material flame retardant performance, pipe wall thickness, etc.
Acceptance criteria: Complete documentation, intact appearance, parameters meeting requirements = qualified. Unqualified materials are strictly prohibited from use and must be immediately removed from site and replaced.
16.2.2 Concealed Works Acceptance
Acceptance of concealed works is conducted after pipe installation is complete, before insulation construction, and before ceiling panel sealing.
Inspection content:
- Pipe routing, elevation, and slope comply with design requirements
- Support hanger spacing and installation firmness comply with codes
- Trap, inspection port, and cleanout settings comply with requirements
- Pipe joint quality qualified, no leakage
- Wall and floor penetration sleeves meet requirements
- Water-filling test, water flow test, and ball passage test passed
- Grounding cross-connection meets electrical requirements
Acceptance criteria: All items comply with codes and design requirements, tests passed, concealed works acceptance record signed before proceeding to the next process.
16.2.3 Sub-Project Acceptance
After the system is fully installed and commissioned, conduct sub-project acceptance.
Inspection content:
- Pipe installation quality
- Equipment installation quality
- Insulation construction quality
- Electrical wiring quality
- System functional testing
- Appearance and labeling
Acceptance criteria: All sub-items comply with acceptance codes and system functions operate normally = qualified.
16.2.4 Final Acceptance
After the overall project is completed and the trial operation passes, conduct final acceptance.
Inspection content:
- Document review: as-built drawings, construction records, test records, commissioning records, material certificates, etc.
- On-site physical inspection: system appearance, installation quality, labeling and signage
- System performance spot checks: water flow test, alarm test, linkage test
- Review of 72-hour trial operation records
Acceptance criteria: Complete documentation, qualified physical inspection, stable operation, meeting design and usage requirements = sign the final acceptance report.
16.3 Main Control Item Acceptance Standards
| No. | Item | Acceptance Requirement | Inspection Method |
|---|---|---|---|
| 1 | Pipe, fitting, equipment quality | Model, specification, material comply with design and code requirements, quality certification documents complete | Document check, visual inspection |
| 2 | Pipe slope | Branch pipe ≥1%, main pipe ≥0.5%, no reverse slope, no local high points | Level measurement, string line measurement |
| 3 | Water-filling test | No leakage for 30 minutes, no obvious liquid level drop | On-site observation, timing |
| 4 | Water flow test | Smooth drainage, no water accumulation, no overflow, discharge volume ≥70% of injected volume | Water injection test, measurement |
| 5 | Trap water seal | Seal depth ≥50mm, negative pressure zones meet requirements | Measurement, calculation |
| 6 | Pump operation | Correct rotation direction, stable operation, no abnormal noise, current conforms to rated value | Energized test, clamp meter measurement |
| 7 | Level control | Start/stop levels accurate, reasonable hysteresis, no frequent start-stop | Water injection test |
| 8 | Overflow alarm | When water level reaches alarm value, sound and light alarm normal, signal output normal | Simulation test |
| 9 | Insulation resistance | Phase-to-phase and phase-to-ground insulation resistance ≥0.5MΩ | Megger measurement |
| 10 | Grounding | System reliably grounded, grounding resistance ≤4Ω | Ground resistance tester |
16.4 General Item Acceptance Standards
| No. | Item | Acceptance Requirement | Inspection Method |
|---|---|---|---|
| 1 | Support hanger installation | Spacing meets requirements, securely installed, neatly arranged, good corrosion protection | Measurement, visual inspection |
| 2 | Pipe joints | Firm bonding, full welds, standard threads, no leakage | Visual inspection |
| 3 | Inspection ports and cleanouts | Reasonable location, easy to operate, good sealing | Visual inspection, measurement |
| 4 | Sleeve installation | Sleeves at wall/floor penetrations, tightly sealed, correct height | Visual inspection, measurement |
| 5 | Insulation construction | Firmly adhered, tight joints, uniform thickness, no exposed areas, neat appearance | Visual inspection, measurement |
| 6 | End drainage | Indirect drainage, air gap ≥150mm, floor drain unobstructed | Visual inspection, measurement |
| 7 | Electrical wiring | Neat wiring, secure terminals, clear labeling, standard routing | Visual inspection |
| 8 | Appearance and labeling | Clean system, clear flow direction labels, complete equipment labels | Visual inspection |
| 9 | Noise | Pump operating noise ≤45dB (in machine room) | Sound level meter measurement |
| 10 | Condensation condition | No condensation or dripping on insulation outer surface | Visual inspection, temperature measurement |
16.5 Acceptance Documentation Checklist
- As-built drawings (system diagram, plan view, control schematic diagram)
- Design change and technical consultation records
- Material and equipment factory certificates, inspection reports, warranty documents
- Material incoming inspection records
- Concealed works acceptance records
- Water-filling test records, water flow test records, ball passage test records
- Electrical insulation test records, grounding resistance test records
- System commissioning records
- 72-hour continuous trial operation records
- Sub-project quality acceptance records
- Final acceptance report
- Product manual, warranty card
16.6 Handling of Failed Acceptance
- General defects found during acceptance: issue a rectification notice with a deadline for correction. Re-inspect after rectification.
- Main control item failure, or existence of major quality hazards: suspend work for rectification, re-organize acceptance after rectification is complete.
- If acceptance standards still cannot be met after rectification, acceptance will not be granted, and relevant responsibilities will be pursued.
- Incomplete acceptance documentation: supplement and improve before acceptance.
- Condensate water: Liquid water formed when water vapor condenses on a surface at a temperature below the dew point.
- Gravity flow: Fluid flow driven by gravitational force.
- Head: The vertical height to which a pump can lift water, measured in meters.
- Cavitation: When the pressure at the pump inlet is too low, water vaporizes to form bubbles that collapse and impact the impeller, causing pump damage and noise.
- Water seal: A measure using a certain height of static water pressure to resist pressure changes in the drainage pipe and prevent pipe gases from entering the room.
- Trap: A pipe fitting that forms a water seal, commonly U-shaped or P-shaped.
- Air lock: A phenomenon where accumulated air in the pipe obstructs water flow.
- Cold bridge: Locations where the insulation layer is discontinuous, allowing heat to transfer directly through solid conduction, resulting in locally low temperatures prone to condensation.
- Closed-cell rubber-plastic: Rubber-plastic insulation material with an internal structure of independent closed cells, providing good insulation and waterproofing performance.
- Dry contact: A passive switch with two states – closed and open. The two contacts have no polarity and can be interchanged.
I. Search Keyword Classification
1. Core Primary Keywords
Machine room air conditioner condensate drainage system, machine room condensate drainage system, precision air conditioner condensate system, machine room air conditioner drainage system
2. High-Conversion Long-Tail Keywords
Machine room air conditioner condensate drainage system installation, precision air conditioner condensate lift pump installation, machine room condensate system commissioning, data center condensate drainage solution, machine room air conditioner drainage pipe installation code, condensate drainage system acceptance standards, machine room air conditioner drainage system maintenance and repair
3. Industry Traffic Keywords
Air conditioner condensate drainage methods, how to drain machine room air conditioner condensate, precision air conditioner condensate pipe slope requirements, condensate lift pump working principle, machine room anti-condensation insulation practice, air conditioner condensate blockage clearing methods, data center water supply and drainage design code
4. Brand-Specific Keywords
KITOZER machine room condensate system, Guangdong Lain air conditioner drainage system, KITOZER intelligent machine room condensate discharge, LA series condensate lift pump, KITOZER machine room drainage system manufacturer
5. Dropdown/Related Search Keywords
Machine room air conditioner condensate drainage system installation and wiring, machine room air conditioner condensate system manual, precision air conditioner common faults, how to handle machine room air conditioner dripping, condensate system acceptance code, machine room air conditioner drainage slope standard, condensate lift pump wiring diagram
II. SEO Optimization Tag System
1. Page Core Optimization Tags
- Page topic: Machine room air conditioner condensate drainage system installation, wiring, and commissioning manual
- Core positioning: Full-process technical manual from a professional machine room infrastructure manufacturer, covering the complete lifecycle of installation, wiring, commissioning, and maintenance
- Target audience: Machine room contractors, O&M personnel, designers, procurement professionals
2. Title Tag
Machine Room Air Conditioner Condensate Drainage System Installation Wiring Commissioning Manual_Precision Air Conditioner Drainage System_Guangdong Lain Intelligent Machine Room
3. Meta Keywords
Machine room air conditioner condensate drainage system, precision air conditioner condensate system, condensate lift pump installation, machine room drainage system commissioning, condensate system acceptance, data center drainage design, Lain intelligent machine room
4. Meta Description
Guangdong Lain Intelligent Machine Room Equipment Co., Ltd. professionally provides machine room air conditioner condensate drainage systems, covering the full range of gravity flow and powered lift products. This manual provides detailed introduction to the condensate system’s product overview, system composition, principles, technical parameters, installation construction, electrical wiring, system commissioning, maintenance and repair, fault diagnosis, and acceptance specification, suitable for data centers, communication rooms, and all scenarios, ensuring safe and reliable machine room drainage.
5. H1 Tag
Machine Room Air Conditioner Condensate Drainage System Installation Wiring Commissioning Manual
6. H2 Tags
Product Introduction | Product Composition | Product Classification | Product List | Product Working Principle | Product Technical Parameters | Product Functions and Features | Product Application Scenarios | Product Installation Construction | Product Electrical Wiring | Product System Commissioning | Product Safety Precautions | Product Maintenance and Repair | Product Common Problems and Solutions | Product QA | Product Acceptance Specification
III. Internal Link Optimization Tags (Natural Anchor Text Placement)
1. Core Anchor Text
Machine room air conditioner condensate drainage system, precision air conditioner condensate lift pump, machine room drainage system, condensate pipe installation
2. Long-Tail Anchor Text
Machine room condensate system installation and commissioning, precision air conditioner drainage system acceptance standards, data center anti-condensation insulation construction, condensate lift pump wiring methods
3. Related Anchor Text
Machine room precision air conditioner, micro-module data center, machine room environmental monitoring system, machine room leak detection system
This document is copyrighted by Guangdong Lain Intelligent Machine Room Equipment Co., Ltd. and is protected by national copyright law.
Any unit or individual, without prior written authorization from the company, is prohibited from copying, reprinting, adapting, excerpting, disseminating, or commercially using this document in any form. The document contents may not be used for product promotion, proposal writing, training and teaching, or other commercial purposes.
When authorized to reprint or quote, the source “Guangdong Lain Intelligent Machine Room Equipment Co., Ltd.” and the original link must be indicated. The original content must not be altered, and the copyright notice must not be deleted or abridged.
The company reserves the right to pursue legal liability for infringing acts. If the content of this document is updated, no separate notice will be provided. The latest version shall prevail as officially released.
- Manufacturer: Guangdong Lain Intelligent Machine Room Equipment Co., Ltd.
- Service Hotline: +86 13538869979 (also on WeChat)
- Technical Support: +86 13538869979
- Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou
- Official Website: https://gdlain.com