TogglePreface

With the rapid development of the digital economy, equipment heat density in data centers, computing rooms, industrial control stations, and similar scenarios continues to rise. Single-cabinet power has grown rapidly from the traditional 3kW to 10kW, 20kW, and even above 50kW. Traditional air-cooling heat dissipation solutions can no longer meet the cooling requirements of high-density computing equipment, and suffer from shortcomings such as high energy consumption, high noise levels, and insufficient temperature control accuracy. Water-cooling heat dissipation technology, with its core advantages of high heat exchange efficiency, low energy consumption, precise temperature control, and strong environmental adaptability, has become the mainstream solution for a new generation of high-density computer room cooling.
As the core carrier of the liquid-cooling heat dissipation system, the stable operation of the integrated water-cooled cabinet is highly dependent on the reliability and compatibility of its water circulation system. The water circulation accessories for water-cooled cabinets constitute the core component set that forms the cabinet-level water-cooling circulation loop. They undertake critical functions such as refrigerant delivery, heat exchange, pressure regulation, water quality filtration, status monitoring, and safety protection, serving as the foundational support for ensuring continuous, efficient, and safe heat dissipation of water-cooled cabinets.
This manual has been jointly compiled by the Technology R&D Center and the Engineering Delivery Center of Guangzhou Lain Intelligent System Development Co., Ltd. It strictly follows national and industry standards including GB 50174 *Code for Design of Data Centers*, GB/T 37582 *Technical Requirements for Data Center Cooling*, and JB/T 8690 *Industrial Water Chillers*, and is written based on our company’s more than ten years of experience in computer room heat dissipation equipment R&D and engineering practice. The manual comprehensively covers the full lifecycle of the product, including product introduction, composition structure, list details, working principles, technical parameters, functional features, application scenarios, installation specifications, wiring standards, commissioning procedures, precautions, maintenance, troubleshooting, Q&A, and acceptance criteria. It aims to provide equipment installers, operations and maintenance personnel, and project management personnel with systematic and standardized operational guidance, ensuring the correct installation, standardized wiring, precise commissioning, and long-term stable operation of water-cooled cabinet water circulation accessories.
The content of this manual is compiled based on our company’s current technical level and product configuration. Due to continuous product iteration and upgrades, some parameters, structures, and procedures may be subject to minor adjustments. For actual operations, please refer to the product certificate of conformity, packing list, and the latest technical drawings supplied with the goods. If you have any technical questions, please contact our technical support team at any time for professional guidance.
Chapter 1 Product Introduction

1.1 Industry Development Background
Driven by the national “East Data, West Computing” strategy and the rapid development of the computing industry, China’s data center industry maintains a high-speed growth trend. High-density servers, GPU computing clusters, AI training servers, and other equipment are deployed at large scale, and the thermal load per cabinet is rising exponentially. Traditional air-cooling heat dissipation systems remove heat through air convection. Limited by physical characteristics such as low specific heat capacity of air and high duct resistance, when single-cabinet power exceeds 15kW, problems such as a sharp drop in cooling efficiency, frequent local hot spots, and persistently high PUE emerge, making them unable to meet the cooling requirements of next-generation computing infrastructure.
Liquid-cooling technology achieves heat transfer through direct or indirect heat exchange between liquid coolant and heat-generating components. Its heat exchange efficiency is hundreds of times that of air, effectively solving the high-density heat dissipation challenge while significantly reducing cooling system energy consumption, helping data centers achieve their “dual carbon” goals. Among these, the indirect water-cooling solution, due to its strong compatibility, low retrofitting cost, and high reliability, has become the mainstream choice for both existing computer room retrofits and new computer room construction. The integrated water-cooled cabinet is the core implementation form of the indirect water-cooling solution.
The heat dissipation performance and service life of the integrated water-cooled cabinet are directly related to the configuration quality, installation quality, and maintenance quality of the water circulation system. As the “vascular system” for coolant delivery, the selection, installation, and commissioning of water circulation system accessories directly determine the heat exchange efficiency, operational stability, and leakage risk of the entire water-cooling system. Some water circulation accessories on the market have issues such as mismatched parameters, poor sealing performance, simple control logic, and missing protection mechanisms, which can easily lead to insufficient flow, temperature runaway, pipeline leakage, equipment corrosion, and other faults, posing serious safety hazards to computer room operations.
Against this industry background, Guangzhou Lain Intelligent System Development Co., Ltd., leveraging years of R&D expertise in computer room environment monitoring and heat dissipation equipment, has launched a full series of standardized water-cooled cabinet water circulation accessories. Deeply optimized for cabinet-level water-cooling scenarios, these products feature core advantages including high compatibility, high reliability, high intelligence, and low leakage risk. They are seamlessly compatible with various brands of integrated water-cooled cabinets, providing stable and reliable water circulation support for high-density computer room heat dissipation systems.
1.2 Product Definition and Overview
Water-cooled cabinet water circulation accessories refer to the collective term for all functional components used in conjunction with integrated water-cooled cabinets to form a complete closed water circulation loop. Using deionized water or ethylene glycol aqueous solution as the coolant medium, the circulation power unit drives the coolant to circulate between the cabinet cold plates/heat exchange coils and the external cold source, continuously carrying away heat generated by equipment inside the cabinet to achieve precise temperature control.
This product series comprises complete cabinet-level water circulation system accessories, integrating seven core functional units: circulation power module, heat exchange module, water quality treatment module, pressure regulation module, status monitoring module, safety protection module, and intelligent control module. It achieves full functional coverage including coolant circulation, heat exchange, flow regulation, pressure stabilization, impurity filtration, leakage monitoring, and fault alarm. No additional piecemeal procurement of accessories is required — the complete water circulation system can be constructed by directly matching with the water-cooled cabinet.
The product adopts a modular design philosophy, with each functional unit independently packaged and interfaces standardized. It supports both complete procurement with integrated installation, and flexible selection of components based on project requirements, adapting to water-cooled cabinet cooling needs across different power levels, scenarios, and cold source conditions. All accessories have undergone strict pressure testing, sealing testing, aging testing, and salt spray testing, and can operate stably over the long term in computer room environments, with a design service life of no less than 10 years.
1.3 Product Development History
Guangzhou Lain Intelligent System Development Co., Ltd. began its strategic focus on liquid-cooling heat dissipation technology in 2018, establishing a professional R&D team to conduct water-cooling heat dissipation technology research, and is one of the earliest domestic manufacturers to venture into cabinet-level water-cooling system R&D.
In 2019, the first generation of cabinet water-cooling circulation components was launched, focusing on basic circulation functions, adapted to cooling scenarios below 10kW per cabinet, and achieving an initial breakthrough in replacing piecemeal custom parts with standardized accessories.
In 2020, the second generation product iteration was completed, adding a plate heat exchange module and intelligent control unit. Temperature control accuracy was improved to ±0.5°C, adapted power was increased to 30kW per cabinet, and IPX5 waterproof rating certification and CE electrical safety certification were obtained.
In 2022, the third generation full-function water-cooled cabinet water circulation accessory series was launched, integrating leakage monitoring, automatic water replenishment, variable frequency regulation, remote communication, and other functions. Adapted to the full power range of 10kW-80kW per cabinet, it formed a complete product matrix widely used in data centers, industrial control, scientific research laboratories, and other fields.
In 2025, comprehensive product upgrades and optimization were completed, including optimizing pipeline structure to reduce flow resistance, upgrading control algorithms to improve energy efficiency, and adding multiple water leakage protection mechanisms. The product’s energy efficiency ratio, reliability, and intelligence level were further improved, and customized accessory services were launched to meet non-standard requirements in special scenarios.
To date, our water-cooled cabinet water circulation accessories have served more than 300 liquid-cooling computer room projects, with over 10,000 units of supporting water-cooled cabinets. We have accumulated rich project implementation and maintenance experience, and product performance and reliability have been widely recognized by the market and customers.
1.4 Product Design Philosophy
1.4.1 Safety-First Design
The core risk of a water-cooling system is liquid leakage. This product series treats leak prevention, leak detection, and leak remediation as the design core. All pipeline connections adopt dual-seal structures, with water leakage sensors installed at key nodes. Pipeline materials are selected from high-strength corrosion-resistant materials with pressure-bearing capacity far exceeding the rated working pressure. The system is equipped with multiple pressure relief protection mechanisms to prevent pipeline rupture due to overpressure. The control logic includes a leakage-linked shutdown function — upon detection of a leak, the pump is immediately stopped and valves are closed, minimizing the impact of leakage.
1.4.2 High-Efficiency and Energy-Saving Design
Pipeline structure is optimized through fluid simulation to reduce system flow resistance and decrease wasted pump power. High-efficiency variable frequency circulation pumps automatically adjust flow rate and head according to real-time thermal load, achieving on-demand cooling. High heat exchange efficiency plate heat exchangers are selected to reduce heat exchange temperature difference and improve cold source utilization. The overall system energy efficiency ratio is improved by more than 15% compared to conventional industry solutions, effectively reducing computer room cooling energy consumption.
1.4.3 Modular and Standardized Design
All accessories adopt standardized interface design with unified pipe diameters, unified connection methods, and unified electrical terminals. Different model accessories are interchangeable and compatible. Each functional module is independently formed, requiring no on-site processing during installation. The system can be assembled by direct connection, significantly shortening construction periods while reducing on-site construction difficulty and the risk of human error.
1.4.4 Intelligent Operations and Maintenance Design
An intelligent controller is provided that monitors core parameters in real time, including system flow, pressure, temperature, liquid level, and conductivity. It supports local display and remote upload. Comprehensive fault self-diagnosis functions can accurately locate fault points and output alarm information. Seamless integration with computer room environment monitoring systems supports centralized monitoring and unattended operation, reducing operations and maintenance costs.
1.4.5 Full-Scenario Adaptation Design
The product supports multiple coolant media and adapts to different cold sources including normal-temperature chilled water, chilled water, and ethylene glycol antifreeze. It supports various installation methods including wall-mounted, floor-standing, and in-cabinet embedded, adapting to different computer room space conditions. Wide voltage design and wide temperature operation design accommodate different regional power supply conditions and ambient temperatures, meeting usage requirements in complex scenarios such as industrial, outdoor, and high-altitude environments.
1.5 Product Market Positioning
This series of water-cooled cabinet water circulation accessories is positioned as core supporting products for mid-to-high-end cabinet-level water-cooling systems, targeting customers with high requirements for cooling reliability, temperature control accuracy, and maintenance convenience. It primarily serves three major markets:
New High-Density Data Center Market: Providing standardized, high-reliability water circulation supporting solutions for integrated water-cooled cabinets in new high-density computer rooms such as AI computing rooms, high-performance computing rooms, and financial data rooms.
Existing Computer Room Retrofit Market: Providing water circulation accessory solutions with strong adaptability and minimal retrofit scope for converting traditional air-cooled computer rooms to water-cooled rooms. Computer room infrastructure requires no large-scale modification, enabling rapid cooling upgrades.
Special Industry Application Market: Providing customized water-cooling circulation support for special scenarios including industrial automation control cabinets, medical imaging equipment, scientific research and test equipment, and military classified computer rooms, meeting special environment and special indicator requirements.
With high reliability, high cost-effectiveness, and comprehensive technical services as its core competitiveness, the product is committed to providing customers with a full-process solution of “selection – installation – commissioning – operations and maintenance,” becoming a trustworthy accessory supplier and technical service provider in the water-cooling heat dissipation field.
1.6 Product Executive Standards
The design, production, inspection, installation, and acceptance of this product strictly follow the following national and industry standards:
| Standard | Title |
|---|---|
| GB 50174-2017 | Code for Design of Data Centers |
| GB/T 37582-2019 | Technical Requirements for Data Center Cooling |
| GB/T 39663-2020 | Technical Requirements for Liquid-Cooled Server Heat Dissipation Systems in Computer and Data Processing Rooms |
| JB/T 8690-2014 | Industrial Water Chillers |
| GB 50236-2011 | Code for Construction of Field Equipment and Industrial Pipeline Welding Engineering |
| GB 50235-2010 | Code for Construction of Industrial Metallic Piping Engineering |
| GB 50303-2015 | Code for Acceptance of Construction Quality of Building Electrical Engineering |
| GB/T 13306-2011 | Plates |
| GB 7251.1-2013 | Low-Voltage Switchgear and Controlgear Assemblies — Part 1: General Rules |
| YD/T 2165-2010 | Technical Requirements for Water-Cooled Air Conditioners in Telecommunication Rooms |
Chapter 2 Product Composition

The water-cooled cabinet water circulation accessory system consists of seven major functional modules: circulation power module, heat exchange module, water quality treatment module, pressure regulation and water replenishment module, status monitoring module, safety protection module, and intelligent control module. Each module is connected through pipelines and wiring to form a complete water circulation system. The following provides a detailed introduction to each module and its subordinate components.
2.1 Circulation Power Module
The circulation power module is the power core of the water circulation system, providing driving force for coolant flow, ensuring continuous circulation of coolant in the closed loop, and achieving continuous heat transfer. Core components include the circulation pump, pump base, vibration-damping connectors, inlet connection, and outlet connection.
2.1.1 Circulation Pump
This product series comes standard with a vertical centrifugal circulation pump; some high-flow models are equipped with horizontal multistage centrifugal pumps. It is the core power component of the system.
Structural Composition: Comprises pump body, impeller, motor, mechanical seal, bearings, inlet, outlet, and junction box.
Working Principle: The motor drives the impeller to rotate at high speed, causing water in the pump chamber to gain kinetic and pressure energy under centrifugal force, discharging from the outlet. Simultaneously, negative pressure is formed at the pump chamber inlet, drawing return water in, creating continuous circulation.
Material Characteristics: The pump body is made of 304 stainless steel, corrosion-resistant and not prone to scaling. The impeller is made of engineering plastic or stainless steel with excellent hydraulic performance. The mechanical seal uses silicon carbide-graphite material with good wear resistance and extremely low leakage rate.
Configuration Features: Standard variable frequency motor, supporting 0-100% speed regulation, dynamically adjusting flow and head according to system requirements. Motor protection class is IP54, insulation class is F, suitable for long-term operation in computer room environments. Some models are configured with a standby pump in a one-active-one-standby arrangement, automatically switching over in the event of a primary pump failure to ensure uninterrupted system operation.
2.1.2 Pump Supporting Components
Pump Base: Made of carbon steel with plastic spraying, used to secure the pump, increase operational stability, and reduce vibration transmission.
Vibration-Damping Connectors: Rubber flexible joints are configured at both pump inlet and outlet to absorb vibration generated during pump operation, preventing vibration transmission to pipelines that could cause loosening and noise amplification.
Reducer Adapters: Used to adapt the diameter difference between pump connections and main pipelines, made of 304 stainless steel with internal and external polishing to reduce flow resistance.
2.2 Heat Exchange Module
The heat exchange module is the core unit for heat exchange, responsible for transferring heat carried by cabinet-side return water to the external cold source side coolant, allowing the return water to cool down before re-entering the cabinet for heat absorption. The core component is the plate heat exchanger, with associated inlet/outlet connections, sealing gaskets, and mounting brackets.
2.2.1 Plate Heat Exchanger
This product series comes standard with brazed plate heat exchangers; high-capacity models are configured with gasketed (plate-and-frame) plate heat exchangers.
Structural Composition: Comprises a series of metal plates with specific corrugated shapes stacked and brazed together. Narrow channels are formed between plates, with two coolants flowing in counter-current directions through their respective channels, exchanging heat through the metal plates.
Working Principle: High-temperature side coolant (cabinet return water) enters from one side inlet of the heat exchanger, flows along the plate channels, transfers heat through the metal plates to the low-temperature coolant on the other side (external cold source water). The cooled coolant exits from the outlet and enters the cabinet-side circulation. The low-temperature coolant absorbs heat, its temperature rises, and exits from the cold source side outlet, carrying the heat away.
Material Characteristics: Plates are made of 304/316L stainless steel with high thermal conductivity and corrosion resistance. The brazing material is pure copper with good sealing performance and strong pressure-bearing capacity.
Configuration Features: Counter-current heat exchange design provides high heat exchange efficiency and large logarithmic mean temperature difference. The corrugated plate structure enhances turbulence and resists fouling. Compact size and light weight make it easy to install inside or alongside the cabinet.
2.2.2 Heat Exchanger Supporting Components
Mounting Brackets: Made of carbon steel with plastic spraying, used to secure the heat exchanger to the installation foundation, preventing displacement during operation.
Sealing Gaskets: Gasketed plate heat exchangers are equipped with nitrile rubber (NBR) or ethylene propylene diene monomer (EPDM) gaskets to ensure sealing performance between plates; they are replaceable and maintainable.
Connection Flanges/Union Joints: Standardized interfaces for rapid connection with pipelines on both sides, with reliable sealing.
2.3 Water Quality Treatment Module
The water quality treatment module ensures the cleanliness and water quality indicators of the circulating coolant, preventing impurities from blocking pipelines and cold plate channels, avoiding corrosion and scaling of metal pipelines, and extending system service life. Core components include Y-type strainers, precision filters, ion exchangers, and electronic water treatment devices.
2.3.1 Y-Type Strainer
Installed at the front end of the system water inlet, used to filter large particle impurities from the coolant. It serves as the system’s first filtration barrier.
Structural Composition: Comprises valve body, filter screen, drain port, and end cover, forming a Y shape overall.
Working Principle: Water enters from the inlet, and as it passes through the filter screen, impurities are intercepted on the outside of the screen. Clean water exits from the outlet. Periodically opening the drain port removes the impurities intercepted by the screen.
Material Characteristics: Valve body is made of 304 stainless steel; filter screen is stainless steel woven mesh. Filtration accuracy is typically 80-100 mesh, corrosion-resistant and easy to clean.
2.3.2 Precision Filter
Installed downstream of the Y-type strainer, used to filter smaller particle impurities, ensuring the cleanliness of water entering the cabinet cold plates.
Structural Composition: Comprises filter housing, filter cartridge, inlet/outlet ports, vent valve, and drain valve.
Working Principle: Water enters from the outside of the filter cartridge, passes through the micropores of the cartridge to remove fine impurities, and clean water exits from the center of the cartridge.
Configuration Features: Filtration accuracy up to 5μm, effectively intercepting fine sediment, rust, weld slag, and other impurities. The filter cartridge is made of polypropylene material with high dirt-holding capacity and easy replacement. The filter housing is made of 304 stainless steel with strong pressure-bearing capacity.
2.3.3 Ion Exchanger
Configured for scenarios with high water quality requirements, used to reduce the conductivity of circulating water and prevent electrochemical corrosion.
Structural Composition: Comprises tank body, cation exchange resin, inlet water distributor, outlet water collector, and regeneration connection.
Working Principle: As water flows through the ion exchange resin, calcium, magnesium, copper, and other ions in the water exchange with sodium ions on the resin, reducing water hardness and conductivity, and reducing scaling and corrosion risks.
Configuration Features: Compact tank design, suitable for cabinet-level system installation. Resin is regenerable and reusable, reducing operations and maintenance costs.
2.3.4 Electronic Water Treatment Device
Installed on the main return water pipeline, using high-frequency electromagnetic fields to change the molecular structure of water, providing anti-scaling, descaling, bacteriostatic, and corrosion-inhibiting effects.
Working Principle: High-frequency electric fields treat the water flow, altering the crystal structure of calcium and magnesium ions in the water from hard calcite to soft aragonite, which does not readily adhere to pipe walls to form scale. It also disrupts bacterial living environments, inhibiting microbial growth.
Configuration Features: No chemical agents required, environmentally friendly. Easy installation with no damage to pipelines. Low power consumption and low long-term operating costs.
2.4 Pressure Regulation and Water Replenishment Module
The pressure regulation and water replenishment module maintains system pressure stability, replenishes water lost through leakage and evaporation, absorbs volume expansion caused by coolant temperature changes, and prevents system overpressure or water shortage. Core components include expansion tanks, automatic water replenishment valves, water replenishment solenoid valves, manual water replenishment valves, pressure relief valves, and pressure regulating valves.
2.4.1 Expansion Tank
Used to accommodate volume expansion of water in the system due to temperature rise, stabilizing system pressure. It can also hold a small amount of replenishment water to maintain system liquid level.
Structural Composition: Closed expansion tanks comprise tank body, bladder, inflation port, pressure gauge, and inlet/outlet ports. Open expansion tanks comprise tank body, level gauge, overflow port, drain port, and water replenishment port. This product series comes standard with a closed diaphragm expansion tank.
Working Principle: When system water temperature rises, water volume expands, and excess water enters the expansion tank, compressing the bladder, causing system pressure to rise slowly. When water temperature drops, water volume contracts, the bladder rebounds, pressing water back into the system to maintain stable system pressure.
Material Characteristics: Tank body is made of carbon steel with plastic spraying; internal bladder is made of butyl rubber with good air-tightness and long service life.
Configuration Features: Compact size, suitable for wall-mounted or floor-standing installation. Pre-charged with nitrogen gas; pressure is preset before factory shipment and can be fine-tuned on-site according to system parameters.
2.4.2 Water Replenishment Components
Automatic Water Replenishment Valve: Integrates pressure reducing valve and check valve functions, connected to municipal water supply or softened water source. Automatically maintains minimum system pressure — when system pressure drops below the set value, it automatically opens for replenishment, and closes when the set pressure is reached.
Water Replenishment Solenoid Valve: Controlled by the controller, linked with the liquid level sensor. Automatically opens for replenishment when system liquid level is too low, and closes after liquid level returns to normal, achieving automated water replenishment.
Manual Water Replenishment Valve: Serves as a backup water replenishment channel, used for initial system filling and manual replenishment when the automatic replenishment system fails. Made of brass or stainless steel ball valve.
2.4.3 Pressure Regulation Components
Safety Valve (Pressure Relief Valve): System overpressure protection component. When system pressure exceeds the set safety value, the safety valve automatically opens to relieve pressure, and automatically closes after pressure returns to normal, preventing pipeline rupture due to overpressure. The set pressure is typically 1.1-1.2 times the system rated working pressure.
Pressure Regulating Valve: Installed on branch pipelines, used to regulate flow and pressure of each branch circuit, ensuring balanced flow in each cabinet circuit. Features graduated adjustment with high adjustment accuracy and a locking device to prevent accidental operation.
2.5 Status Monitoring Module
The status monitoring module collects various system operating parameters in real time, providing data support for the control system and providing operations and maintenance personnel with a basis for assessing operating status. Core components include temperature sensors, pressure sensors, flow sensors, liquid level sensors, conductivity sensors, and water leakage sensors.
2.5.1 Temperature Sensors
Used to monitor coolant temperature at key system nodes, including supply water temperature, return water temperature, and cold source side inlet/outlet temperatures. These are the core data sources for temperature control logic.
Type: Standard PT100 platinum resistance temperature detectors; some points are configured with NTC thermistors.
Installation Method: Insertion-type installation with temperature wells, allowing sensor removal and installation without stopping flow.
Accuracy Parameters: PT100 accuracy is Class A, ±0.15°C, measurement range -20°C to 120°C, meeting full temperature range monitoring requirements for computer room water-cooling scenarios.
2.5.2 Pressure Sensors
Used to monitor system supply pressure, return pressure, and differential pressure across filters, determining whether the system has abnormalities such as blockage, leakage, or overpressure.
Type: Standard diffusion silicon pressure transmitters, outputting 4-20mA analog signals.
Installation Method: Installed at pipeline pressure measurement points via threaded connections, with buffer tubes to mitigate water hammer impact.
Accuracy Parameters: Accuracy class 0.5, measurement range 0-1.6MPa, adapting to the pressure range of the vast majority of cabinet-level water-cooling systems.
2.5.3 Flow Sensors
Used to monitor system circulating water flow rate, determining pump operating status and pipeline blockage conditions. This is one of the core system operating parameters.
Type: Standard turbine flow meters or electromagnetic flow meters. Small-diameter systems use turbine type; large-diameter systems use electromagnetic type.
Working Principle: Turbine flow meters use water flow to rotate an impeller; rotation speed is proportional to flow rate, with pulse signals output through a signal coil. Electromagnetic flow meters are based on Faraday’s law of electromagnetic induction, measuring the velocity of conductive fluids.
Accuracy Parameters: Turbine flow meter accuracy ±1.0%; electromagnetic flow meter accuracy ±0.5%. Both can output pulse signals or 4-20mA analog signals.
2.5.4 Liquid Level Sensors
Used to monitor the liquid level in expansion tanks and water replenishment tanks, determining whether the system is short of water and linking with the water replenishment solenoid valve.
Type: Standard float-type liquid level switches; high-precision scenarios are configured with submersible level transmitters.
Function: Multiple alarm points can be set for high level, low level, and ultra-low level, enabling graded level monitoring and control.
2.5.5 Conductivity Sensors
Used to monitor the conductivity of circulating water, determining water quality changes and promptly detecting ion exchange resin failure or water contamination issues.
Measurement Principle: Electrodes measure the electrical conductivity of the aqueous solution, indirectly reflecting ion concentration in the water, assessing water cleanliness and corrosion risk.
Parameter Range: Measurement range 0-2000μS/cm, accuracy ±2% FS, with automatic temperature compensation.
2.5.6 Water Leakage Sensors
Used to monitor leakage conditions at key system nodes, serving as the core sensing components of the leakage protection system.
Type: Standard combination of rope-type water leakage sensors and point-type water leakage sensors.
Installation Locations: Deployed at points prone to leakage, including pump bases, beneath heat exchangers, at pipeline connections, and at cabinet bases.
Working Principle: When the leakage rope contacts water, its resistance changes; the controller detects the signal change and triggers a leakage alarm. Point-type sensors output switch signals upon liquid contact detection.
Sensitivity: Can detect leaks of 0.5ml or more, with response time less than 1 second, enabling early detection and early response to water leaks.
2.6 Safety Protection Module
The safety protection module executes protective actions when abnormal operating conditions occur in the system, preventing fault escalation and ensuring equipment and computer room safety. In addition to the aforementioned pressure safety valve, it also includes shut-off valves, check valves, motorized shut-off valves, automatic air vents, and drain valves.
2.6.1 Shut-Off Valves
Installed at key system nodes, used to isolate pipeline media during maintenance, facilitating component replacement and servicing.
Type: Stainless steel ball valves or globe valves with low switching torque and good sealing performance.
Configuration Locations: Shut-off valves are configured at pump inlet/outlet, heat exchanger inlet/outlet, filter upstream/downstream, and main pipeline inlet/outlet ends, enabling zone-based isolation.
2.6.2 Check Valves (Non-Return Valves)
Installed on the pump discharge side and water replenishment pipelines to prevent water backflow, avoiding water hammer impact on the impeller when the pump stops, and preventing backflow contamination of the system from the replenishment water side.
Type: Lift-type check valves or wafer-type check valves with low flow resistance and tight closure.
Material: Valve body 304 stainless steel; sealing surfaces rubber or PTFE material.
2.6.3 Motorized Shut-Off Valves
Controlled by the controller, linked with water leakage sensors and serious fault signals. When leakage or serious faults occur, they automatically cut off the inlet and outlet pipelines, limiting the scope of leakage and preventing fault escalation.
Type: Standard motorized ball valves with short shut-off time and reliable sealing.
Drive Method: Driven by electric actuators, powered by 24V DC or 220V AC, with open/closed position feedback signals.
2.6.4 Automatic Air Vents
Installed at the highest points of the system and local high points of pipelines, automatically discharging air from the system to prevent issues such as insufficient flow, reduced heat exchange efficiency, and pump cavitation caused by air locks.
Working Principle: Air in the system rises and accumulates in the air vent chamber, the water level drops, the float descends, and the exhaust port opens to discharge air. After air is fully discharged, the water level rises, the float ascends, and the exhaust port closes.
Material: Valve body brass or stainless steel; float made of high-temperature-resistant engineering plastic.
2.6.5 Drain Valves
Installed at the lowest points of the system, filter bottoms, and tank bottoms, used to periodically discharge wastewater, impurities, and sediment from the system.
Type: Ball valves or gate valves with nominal diameter DN15-DN25, meeting drain flow requirements.
2.7 Intelligent Control Module
The intelligent control module is the “brain” of the system, responsible for collecting signals from various sensors, running control logic, and outputting control commands to achieve automated system operation and intelligent management. Core components include the main controller, touchscreen display, operation buttons, indicator lights, communication module, power supply module, and relay output module.
2.7.1 Main Controller
Uses a PLC or dedicated microcontroller as the system’s control core.
Core Functions: Analog signal acquisition, digital signal acquisition, logic operation processing, relay control output, data storage, alarm handling, and communication interaction.
Configuration Features: Ample I/O points with reserved expansion interfaces. Programs can be customized and modified according to project requirements. Industrial-grade chips with strong anti-interference capability, suitable for computer room electromagnetic environments.
2.7.2 Human-Machine Interface Unit
Touchscreen Display: 7-inch color touchscreen displaying system operating parameters, operating status, and alarm information locally, supporting parameter settings, manual operation, and historical data query functions.
Operation Buttons and Indicator Lights: Configured with power, operation, alarm, and fault indicator lights, and physical buttons for start, stop, reset, and emergency stop, facilitating rapid on-site operation.
2.7.3 Communication and Power Supply Unit
Communication Module: Standard RS485 communication interface supporting Modbus-RTU protocol. Optional Ethernet and 4G modules support remote monitoring and data upload.
Power Supply Module: Wide voltage input, AC220V ±15%, 50Hz, with overvoltage, undervoltage, overload, and short-circuit protection, providing stable power to the controller, sensors, and actuators.
Relay Module: Multiple relay outputs for controlling pumps, solenoid valves, motorized valves, and other actuating devices, with contact capacity meeting load requirements.
2.8 Piping and Auxiliary Material Components
In addition to the above functional modules, the system also includes pipelines connecting each module and installation auxiliary materials, including main pipelines, branch pipelines, pipe joints, elbows, tees, flanges, pipe clamps, brackets, insulation material, sealant, and thread seal tape.
Pipeline Material: Standard 304 stainless steel pipe; PPR pipe or galvanized steel pipe may be selected for some scenarios. Pipe wall thickness meets pressure requirements; inner surface is smooth with low flow resistance.
Connection Fittings: Union joints, elbows, tees, and reducers are all made of 304 stainless steel with precision machining and flat sealing surfaces, ensuring connection sealing performance.
Installation Auxiliary Materials: Pipe clamps and brackets are made of carbon steel with plastic spraying, corrosion-resistant and durable. Insulation is made of rubber-plastic insulation material with 20-30mm thickness, reducing pipeline cooling loss and preventing external wall condensation.
Chapter 3 Product List
This chapter details the standard configuration list, optional accessory list, installation auxiliary material list, and special tool list for water-cooled cabinet water circulation accessories, facilitating arrival inspection and construction preparation. Configurations differ slightly by product model; the actual list is subject to the packing list shipped with the goods.
3.1 Standard Configuration List (Example: LA-SL-20 Single-Cabinet Water Circulation System)
| No. | Component Name | Model/Specification | Unit | Qty | Material/Parameters | Remarks |
|---|---|---|---|---|---|---|
| 1 | Variable Frequency Circulation Pump | LA-B25-20 | Set | 1 | 304 stainless steel pump body, power 0.75kW, flow 5m³/h, head 20m, IP54, Class F insulation | Vertical centrifugal pump with variable frequency motor |
| 2 | Plate Heat Exchanger | LA-BR-020 | Set | 1 | 304 stainless steel plates, brazed type, heat exchange area 2㎡, design pressure 1.6MPa | Suitable for 20kW heat exchange capacity |
| 3 | Y-Type Strainer | LA-Y-DN25 | Pc | 1 | 304 stainless steel valve body, 80-mesh stainless steel screen, DN25 female thread | Primary filtration at water inlet |
| 4 | Precision Filter | LA-JM-DN25 | Pc | 1 | 304 stainless steel filter housing, 5μm PP filter cartridge, DN25 connection | Secondary precision filtration |
| 5 | Closed Expansion Tank | LA-PZ-12 | Pc | 1 | Carbon steel tank body, butyl rubber diaphragm, volume 12L, pre-charge pressure 0.15MPa | Pressure stabilization and expansion |
| 6 | Automatic Water Replenishment Valve | LA-BS-DN15 | Pc | 1 | Brass valve body, pressure regulating range 0.1-0.6MPa, with check function | Automatic pressure-stabilized water replenishment |
| 7 | Manual Water Replenishment Ball Valve | Q11F-16P DN15 | Pc | 1 | 304 stainless steel, two-piece ball valve | Manual water replenishment backup |
| 8 | Safety Valve | A28W-16P DN15 | Pc | 1 | 304 stainless steel, set pressure 0.6MPa | Overpressure relief protection |
| 9 | Check Valve | H12W-16P DN25 | Pc | 1 | 304 stainless steel, vertical lift type | Prevents water backflow |
| 10 | Motorized Shut-Off Ball Valve | LA-DQ-DN25 | Pc | 2 | 304 stainless steel valve body, electric actuator, AC220V, with feedback | 1 each at inlet and outlet, leakage-linked shut-off |
| 11 | Automatic Air Vent | ZP-1 DN15 | Pc | 2 | Brass valve body, float type | Air venting at system high points |
| 12 | Supply Water Temperature Sensor | PT100 Class A | Pc | 1 | Platinum resistance, insertion depth 50mm, with well | Monitors supply water temperature |
| 13 | Return Water Temperature Sensor | PT100 Class A | Pc | 1 | Platinum resistance, insertion depth 50mm, with well | Monitors return water temperature |
| 14 | Pressure Sensor | LA-YL-01 | Pc | 2 | Diffusion silicon, 0-1MPa, 4-20mA output, accuracy class 0.5 | 1 each for supply and return water |
| 15 | Turbine Flow Meter | LA-LL-DN25 | Set | 1 | Turbine type, 0-10m³/h, pulse output, accuracy ±1% | Monitors circulation flow rate |
| 16 | Liquid Level Switch | LA-YW-02 | Pc | 1 | Float type, high/low dual-point level | Expansion tank liquid level monitoring |
| 17 | Water Leakage Sensor | LA-LS-rope type | Set | 1 | Rope type 3m + point type 2 pcs, with controller | Leakage monitoring at key points |
| 18 | Intelligent Control Cabinet | LA-KZ-20 | Set | 1 | Wall-mounted, 7-inch touchscreen, PLC controller, RS485 communication | System control core |
| 19 | Rubber Flexible Joint | KXT-DN25 | Pc | 2 | Nitrile rubber, carbon steel flange | Pump inlet/outlet vibration damping |
| 20 | Stainless Steel Ball Valve | Q11F-16P DN25 | Pc | 8 | 304 stainless steel, female thread | Shut-off at various nodes for maintenance |
| 21 | Main Pipeline | 304 stainless steel pipe DN25 | m | 8 | Wall thickness 2mm, internal/external polished | System main pipeline |
| 22 | Pipeline Fittings | DN25 union joints, elbows, tees | Batch | 1 | 304 stainless steel | Includes couplings, 90° elbows, tees, etc. |
| 23 | Pipeline Brackets | Adjustable pipe clamp brackets | Set | 6 | Carbon steel with plastic spraying | Securing pipelines |
| 24 | Rubber-Plastic Insulation | DN25, thickness 20mm | m | 8 | Closed-cell rubber-plastic, flame retardant Class B1 | Pipeline insulation and condensation prevention |
| 25 | Electrical Auxiliary Materials | Cables, terminals, cable trays | Batch | 1 | National standard cables | Wiring supporting materials |
3.2 Optional Accessory List
| No. | Component Name | Model/Specification | Unit | Applicable Scenario | Function Description |
|---|---|---|---|---|---|
| 1 | Standby Circulation Pump | Same as main pump model | Set | High reliability requirement scenarios | One active, one standby, automatic switchover, uninterrupted operation |
| 2 | Ion Exchanger | LA-LZ-05 | Set | High water quality requirement scenarios | Reduces water conductivity, prevents corrosion and scaling |
| 3 | Conductivity Sensor | LA-DD-01 | Pc | Water quality monitoring requirement scenarios | Real-time water conductivity monitoring, alarm on water quality exceedance |
| 4 | Electronic Water Treatment Device | LA-DZ-DN25 | Set | Scale-prone water quality scenarios | High-frequency anti-scaling, bacteriostatic, corrosion inhibition |
| 5 | Flow Regulating Valve | Graduated regulating valve | Pc | Multi-cabinet parallel scenarios | Regulates flow of each branch, balanced distribution |
| 6 | Water Replenishment Tank | 304 stainless steel, 50L | Pc | No municipal water supply scenarios | Stores replenishment water, used with automatic water replenishment valve |
| 7 | 4G Communication Module | LA-4G-01 | Set | No wired network scenarios | Remote data upload, mobile APP monitoring |
| 8 | Ethylene Glycol Addition Device | LA-TJ-01 | Set | Low-temperature environment scenarios | Automatic antifreeze proportioning, prevents winter freeze damage |
| 9 | Water Hammer Eliminator | LA-SC-DN25 | Pc | Water hammer-prone scenarios | Absorbs water hammer impact, protects pipelines |
| 10 | Differential Pressure Transmitter | LA-YC-01 | Pc | Filter status monitoring | Monitors filter differential pressure, prompts cleaning/replacement |
3.3 Multi-Cabinet Parallel System Expansion List (Example: 10 Cabinets)
When multiple integrated water-cooled cabinets share one main water circulation system, the following accessories must be added based on the standard configuration:
Main Circulation Pump: Upgraded to a high-flow model. Flow rate is selected based on single-cabinet flow × number of cabinets × 1.2 redundancy factor; head is selected based on most unfavorable loop resistance + in-cabinet resistance.
Plate Heat Exchanger: Heat exchange area is selected based on total heat exchange capacity. Total heat exchange capacity = single-cabinet thermal load × number of cabinets × 1.1 redundancy factor.
Main Pipeline: Main pipe diameter is upgraded based on total flow; branch pipes maintain single-cabinet diameters. Water distributors and water collectors are configured to achieve independent control of each branch.
Branch Valves and Instruments: Each cabinet branch is configured with shut-off valves, flow regulating valves, flow sensors, and temperature sensors, enabling independent monitoring and regulation of individual branches.
Expansion Tank: Volume is selected based on total water capacity. Total water capacity = pipeline water capacity + cabinet water capacity + component water capacity. Expansion tank volume ≥ 10% of total water capacity.
Control System: Upgrade main controller I/O points, add branch parameter acquisition and control functions, supporting independent start/stop of individual cabinets and centralized management.
3.4 Special Tool List for Installation
To ensure installation and construction quality, the following special tools must be available on site:
Pipeline Processing Tools: Stainless steel pipe cutter, chamfering tool, pipe bender, pipe threading machine, argon arc welding machine (for welded connections), hot melt tool (for PPR pipes).
Installation Tools: Adjustable wrenches, torque wrenches, hex key sets, screwdriver sets, pipe wrenches, rubber mallets, spirit levels, tape measures, marking pens.
Testing Tools: Pressure gauges, pressure test pumps, thermometers, flow meters, megger, multimeter, clamp ammeter, water testing device.
Auxiliary Tools: Safety harnesses, anti-slip gloves, safety goggles, flashlights, trash bins, cleaning cloths, thread seal tape, sealant, cable ties.
Chapter 4 Product Working Principles
4.1 Overall System Working Principle
The closed water circulation system formed by water-cooled cabinet water circulation accessories operates on the core principle of utilizing the physical properties of water — high specific heat capacity and high heat exchange efficiency — with water as the coolant medium. The circulation pump provides power, causing water to flow continuously in the closed loop, continuously carrying away heat generated by equipment inside the cabinet and transferring it to the external cold source, achieving stable temperature control within the cabinet.
The entire system is divided into two independent water circulation loops: the cabinet-side circulation loop (secondary side) and the cold source-side circulation loop (primary side). The two loops exchange heat through the plate heat exchanger without coming into contact, preventing impurities and water quality issues on the cold source side from affecting the cabinet-side system, while ensuring the cleanliness of cabinet-side water quality.
4.1.1 Cabinet-Side Circulation Loop Workflow
1. Cooled low-temperature chilled water flows out from the system supply water outlet and enters the internal heat exchange pipeline/cold plates of the integrated water-cooled cabinet.
2. The low-temperature water exchanges heat with the heat-generating equipment inside the cabinet, absorbing heat generated by the equipment. The water temperature rises, becoming high-temperature return water.
3. The high-temperature return water flows out from the cabinet, enters the Y-type strainer and precision filter through the return pipeline, where impurities in the water are filtered out.
4. The filtered return water enters the circulation pump inlet. The pump performs work on the water, increasing its pressure and kinetic energy.
5. The pressurized high-temperature return water enters the secondary-side channels of the plate heat exchanger, transferring heat through the metal plates to the low-temperature cold source water on the primary side.
6. The cooled water exits from the heat exchanger secondary-side outlet and is delivered back to the cabinet through the supply pipeline, completing one circulation cycle.
4.1.2 Cold Source-Side Circulation Loop Workflow
1. Low-temperature chilled water from chillers, cooling towers, or municipal cold water enters the primary-side inlet of the plate heat exchanger.
2. The low-temperature water flows through the plate channels, absorbing heat transferred from the secondary-side return water; the water temperature rises.
3. The warmed water exits from the heat exchanger primary-side outlet and returns to the cold source system for re-cooling, completing the cold source-side circulation.
The two loops flow in counter-current directions, maximizing the heat exchange temperature difference and enhancing heat exchange efficiency. The intelligent control system monitors supply/return water temperature, flow rate, pressure, and other parameters in real time, automatically adjusting pump speed and cold source-side flow according to cabinet thermal load changes, achieving precise temperature control and energy-saving operation.
4.2 Detailed Working Principles of Core Components
4.2.1 Working Principle of Centrifugal Pumps
A centrifugal water pump is a fluid machine that uses centrifugal force to transport liquids. Its working process is divided into three stages: energy input, energy conversion, and energy output.
Start-up and Air Evacuation Stage: Before the pump starts, the pump chamber must be completely filled with water and all air expelled; otherwise, the “air binding” phenomenon will occur, preventing normal water delivery.
Centrifugal Work Stage: The motor drives the impeller to rotate at high speed. The impeller blades drive the water in the pump chamber into circular motion. Under centrifugal force, the water moves toward the outer edge of the impeller, gaining kinetic energy and pressure energy. Both velocity and pressure increase simultaneously.
Discharge Stage: High-speed, high-pressure water flows out from the outer edge of the impeller into the volute-shaped pump casing. As the flow channel in the casing gradually expands, the water velocity decreases, and part of the kinetic energy is converted into pressure energy, finally discharging from the outlet at higher pressure.
Suction Stage: After the water at the impeller center is thrown toward the outer edge, a low-pressure vacuum zone forms at the impeller center. Under atmospheric pressure and system pressure, water from the inlet is forced into the pump chamber, replenishing the impeller center and achieving continuous water suction.
Variable-frequency pumps regulate motor speed by changing the power supply frequency to the motor. Speed changes directly affect the pump’s flow rate and head. According to the pump affinity laws, flow rate is proportional to speed, head is proportional to the square of speed, and power is proportional to the cube of speed. Therefore, reducing speed can significantly reduce pump power consumption, achieving energy-saving operation.
4.2.2 Working Principle of Plate Heat Exchangers
Plate heat exchangers belong to the recuperative type of heat exchangers, transferring heat between two fluids through a metal wall. Following the second law of thermodynamics, heat spontaneously transfers from the high-temperature fluid to the low-temperature fluid.
Heat Transfer Process: The high-temperature fluid and low-temperature fluid flow in adjacent plate channels in opposite directions (countercurrent flow). Heat from the high-temperature fluid is conducted through the plate wall to the low-temperature fluid.
Heat Transfer Enhancement Principle: The plate surfaces are pressed with herringbone corrugations. As fluid flows over the corrugations, the flow direction constantly changes, creating strong turbulence that disrupts the boundary layer and significantly increases the heat transfer coefficient. Additionally, the corrugated structure increases the heat transfer area, further improving heat transfer efficiency.
Countercurrent Advantage: With the two fluids flowing in opposite directions, a large temperature difference is maintained across the entire heat transfer surface, resulting in higher heat transfer efficiency. The cold fluid outlet temperature can approach the hot fluid inlet temperature, achieving better heat exchange completeness than parallel flow.
4.2.3 Pressure Stabilization Principle of Expansion Tanks
The closed expansion tank uses a compressible bladder to buffer system volume changes and maintain stable system pressure, operating based on Boyle’s Law (at constant temperature, the pressure of a fixed mass of gas is inversely proportional to its volume).
Initial Cold State: The system is filled with water at ambient temperature, and the system pressure is at the set static pressure. At this time, the bladder is at its initial volume, and the nitrogen pressure inside the bladder balances with the system water pressure.
Heating and Expansion Stage: After the system starts operating, the water temperature rises and the water volume expands. The excess water enters the expansion tank, compressing the bladder. The bladder volume decreases, the nitrogen pressure rises, and the system pressure slowly increases without exceeding the limit.
Cooling and Contraction Stage: When the system shuts down or the load decreases, the water temperature drops and the water volume contracts. The bladder rebounds under the nitrogen pressure, pushing the water in the tank back into the system to compensate for the volume reduction, maintaining stable system pressure and preventing negative pressure from drawing in air.
4.2.4 Working Principle of the Intelligent Control System
The intelligent control system uses a PLC controller as its core, employing a “acquisition-calculation-output-feedback” closed-loop control logic to achieve automated system operation.
Signal Acquisition Layer: Various sensors convert physical quantities such as temperature, pressure, flow rate, and liquid level into electrical signals (analog or digital), transmitting them to the controller’s input modules.
Logic Calculation Layer: The controller’s internal program processes the acquired signals according to preset control logic and parameter thresholds, determines the system operating status, and generates control commands.
Execution Output Layer: The controller transmits control commands through output modules to actuating devices (pump variable-frequency drives, solenoid valves, motorized valves, etc.), executing corresponding actions such as regulating pump speed, initiating water make-up, or closing valves.
Feedback and Correction: After actions are executed, the parameters sensed by the sensors change. The controller continuously adjusts control outputs based on the changed parameters, forming closed-loop control that stabilizes system parameters within the set range.
Alarm and Protection: When acquired parameters exceed normal thresholds, the controller triggers alarms, outputs audible and visual alarm signals, and uploads alarm information. In the event of serious faults, protective actions are executed directly, such as stopping pumps or closing valves.
4.3 Core Control Logic Principles
4.3.1 Temperature Control Logic
The system uses the cabinet return water temperature or supply water temperature as the control target, employing a PID regulation algorithm to control pump speed for precise temperature control.
1. Set Target Temperature: The user sets the target value for supply water temperature or return water temperature.
2. Deviation Calculation: The controller collects the actual temperature in real time, compares it with the set value, and calculates the temperature deviation.
3. PID Calculation: Based on the deviation value, proportional, integral, and derivative calculations are performed, outputting a frequency adjustment signal to the pump variable-frequency drive.
4. Speed Regulation: When the actual temperature is higher than the set value, the pump speed is increased to increase circulation flow and enhance heat exchange; when the actual temperature is lower than the set value, the pump speed is reduced to decrease circulation flow and lower energy consumption.
5. Steady-State Maintenance: Through PID closed-loop regulation, the actual temperature is stabilized near the set value, achieving control accuracy of ±0.5°C.
4.3.2 Pressure and Liquid Level Control Logic
Low-Pressure Make-up Logic: When the system pressure drops below the set lower limit or the liquid level falls below the low-level alarm, the controller opens the make-up solenoid valve to begin water replenishment; when pressure or liquid level recovers to the set value, the make-up solenoid valve closes to stop replenishment.
Overpressure Relief Logic: When the system pressure exceeds the safety valve set pressure, the safety valve mechanically opens to relieve pressure; it automatically closes when pressure recovers to the safe value. The controller simultaneously monitors the overpressure signal and triggers an overpressure alarm.
Water Shortage Protection Logic: When the liquid level falls below the ultra-low level or pressure drops below the protection threshold, the system is determined to be severely short of water. The pump is immediately stopped and a water shortage alarm is triggered, preventing pump dry-running damage.
4.3.3 Leakage Protection Logic
Leak Detection: Leak sensors monitor in real time and immediately transmit leak signals to the controller upon detection.
Tiered Response:
- Minor Leak: Triggers audible and visual alarm, uploads alarm information, and prompts O&M personnel to inspect.
- Serious Leak: Immediately stops the circulation pump, closes the inlet and outlet motorized shut-off valves, cuts off the system water source, triggers a serious alarm, and interfaces with the facility’s environment monitoring system (DCIM/BMS).
Fault Lockout: After leakage fault protection is triggered, manual troubleshooting and reset are required before the system can restart, preventing recurrent faults.
4.3.4 Pump Rotation and Standby Logic
Systems configured with one-operating/one-standby dual pumps are equipped with automatic rotation and fault switchover capabilities.
Timed Rotation: The system is set with a rotation cycle (e.g., 24 hours). Upon cycle expiration, the primary and standby pumps are automatically switched to avoid prolonged single-pump operation wear and extend overall service life.
Fault Switchover: When the operating pump experiences a fault (overload, water shortage, no flow), the controller immediately stops the faulty pump and starts the standby pump, simultaneously triggering a fault alarm to ensure uninterrupted system operation.
Manual Switchover: Local manual switching between primary and standby pumps is supported for maintenance and commissioning needs.
Chapter 5 Product Technical Parameters
This chapter details the technical parameters for each series of water-cooling cabinet water circulation accessories, as well as detailed parameters for each core component, providing data basis for selection, installation, and commissioning. The products are available in five standard models — LA-SL-10, LA-SL-20, LA-SL-30, LA-SL-50, and LA-SL-80 — respectively matching the cooling demands of 10kW, 20kW, 30kW, 50kW, and 80kW single-cabinet heat loads. Multi-cabinet parallel systems can be selected based on total power summation.
5.1 System Technical Parameters
| Parameter | LA-SL-10 | LA-SL-20 | LA-SL-30 | LA-SL-50 | LA-SL-80 | Unit |
|---|---|---|---|---|---|---|
| Compatible cabinet heat load | 10 | 20 | 30 | 50 | 80 | kW |
| Rated circulation flow rate | 2.5 | 5 | 7.5 | 12.5 | 20 | m³/h |
| Rated supply water pressure | 0.2-0.3 | 0.2-0.3 | 0.25-0.35 | 0.3-0.4 | 0.35-0.45 | MPa |
| System design pressure | 1.0 | 1.0 | 1.0 | 1.6 | 1.6 | MPa |
| Safety valve set pressure | 0.6 | 0.6 | 0.6 | 1.0 | 1.0 | MPa |
| Rated supply/return water temperature difference | 5 | 5 | 5 | 5 | 5 | °C |
| Temperature control accuracy | ±0.5 | ±0.5 | ±0.5 | ±0.5 | ±0.5 | °C |
| Supply water temperature adjustment range | 18-35 | 18-35 | 18-35 | 18-35 | 18-35 | °C |
| Cold source inlet water temperature | 7-25 | 7-25 | 7-25 | 7-25 | 7-25 | °C |
| Pump rated power | 0.37 | 0.75 | 1.1 | 2.2 | 3.0 | kW |
| Pump rated head | 16 | 20 | 24 | 28 | 32 | m |
| Heat exchanger heat transfer area | 1.0 | 2.0 | 3.0 | 5.0 | 8.0 | m² |
| Heat exchanger efficiency | ≥92% | ≥92% | ≥92% | ≥92% | ≥92% | – |
| Expansion tank volume | 8 | 12 | 16 | 24 | 36 | L |
| Total system water capacity | ≈15 | ≈25 | ≈35 | ≈60 | ≈90 | L |
| Filtration precision | 5 | 5 | 5 | 5 | 5 | μm |
| Rated supply voltage | AC 220V±15% | AC 220V±15% | AC 220V±15% | AC 380V±15% | AC 380V±15% | – |
| Rated frequency | 50 | 50 | 50 | 50 | 50 | Hz |
| Control method | Variable-frequency PID control | Variable-frequency PID control | Variable-frequency PID control | Variable-frequency PID control | Variable-frequency PID control | – |
| Communication protocol | Modbus-RTU | Modbus-RTU | Modbus-RTU | Modbus-RTU | Modbus-RTU | – |
| Ambient operating temperature | 5-40 | 5-40 | 5-40 | 5-40 | 5-40 | °C |
| Ambient relative humidity | ≤90% non-condensing | ≤90% non-condensing | ≤90% non-condensing | ≤90% non-condensing | ≤90% non-condensing | – |
| Noise level (at 1 m) | ≤50 | ≤52 | ≤55 | ≤60 | ≤62 | dB(A) |
| Design service life | ≥10 | ≥10 | ≥10 | ≥10 | ≥10 | years |
| Unit dimensions (W×D×H) | 400×300×1200 | 500×350×1400 | 550×400×1500 | 650×500×1600 | 700×550×1700 | mm |
| Unit weight | ≈45 | ≈70 | ≈95 | ≈150 | ≈210 | kg |
5.2 Circulation Pump Technical Parameters
5.2.1 Vertical Centrifugal Pump Parameters
| Model | Flow Range | Rated Head | Motor Power | Rated Speed | Port Size | Material | Protection Class | Insulation Class |
|---|---|---|---|---|---|---|---|---|
| LA-B20-16 | 0.5-3 m³/h | 16 m | 0.37 kW | 2900 rpm | DN20 | 304 stainless steel | IP54 | Class F |
| LA-B25-20 | 1-6 m³/h | 20 m | 0.75 kW | 2900 rpm | DN25 | 304 stainless steel | IP54 | Class F |
| LA-B32-24 | 2-10 m³/h | 24 m | 1.1 kW | 2900 rpm | DN32 | 304 stainless steel | IP54 | Class F |
| LA-B40-28 | 5-15 m³/h | 28 m | 2.2 kW | 2900 rpm | DN40 | 304 stainless steel | IP54 | Class F |
| LA-B50-32 | 10-25 m³/h | 32 m | 3.0 kW | 2900 rpm | DN50 | 304 stainless steel | IP54 | Class F |
| LA-B65-36 | 20-40 m³/h | 36 m | 5.5 kW | 2900 rpm | DN65 | 304 stainless steel | IP55 | Class F |
5.2.2 Pump Performance Notes
- The pump performance curve conforms to centrifugal pump characteristics: flow rate decreases as head increases, and increases as head decreases.
- Variable-frequency adjustment range: 20%-100% of rated speed. Below 20% speed, cooling performance decreases; long-term operation at such speeds is not recommended.
- Permissible medium temperature range for the pump: 0°C-110°C; with antifreeze coolant, operation down to -20°C is possible.
- Pump Net Positive Suction Head required (NPSHr) ≤ 2.5 m. Positive inlet pressure must be ensured during system installation to avoid cavitation.
- Mechanical seal service life ≥ 8,000 hours; under normal water quality conditions, continuous operation for more than 3 years is possible.
5.3 Plate Heat Exchanger Technical Parameters
5.3.1 Brazed Plate Heat Exchanger Parameters
| Model | Heat Transfer Area | Rated Heat Transfer Capacity | Design Pressure | Design Temperature | Port Size | Plate Material | Brazing Material |
|---|---|---|---|---|---|---|---|
| LA-BR-010 | 1.0 m² | 10 kW | 3.0 MPa | -196~225°C | DN20 | 304 stainless steel | Pure copper |
| LA-BR-020 | 2.0 m² | 20 kW | 3.0 MPa | -196~225°C | DN25 | 304 stainless steel | Pure copper |
| LA-BR-030 | 3.0 m² | 30 kW | 3.0 MPa | -196~225°C | DN25 | 304 stainless steel | Pure copper |
| LA-BR-050 | 5.0 m² | 50 kW | 3.0 MPa | -196~225°C | DN32 | 304 stainless steel | Pure copper |
| LA-BR-080 | 8.0 m² | 80 kW | 2.5 MPa | -196~225°C | DN40 | 304 stainless steel | Pure copper |
| LA-BR-120 | 12.0 m² | 120 kW | 2.5 MPa | -196~225°C | DN50 | 304 stainless steel | Pure copper |
5.3.2 Heat Exchanger Performance Notes
- Rated heat transfer capacity test conditions: primary side inlet water temperature 12°C, flow rate matched; secondary side inlet water temperature 30°C, rated flow rate, countercurrent heat exchange.
- Heat transfer coefficient: under water-to-water heat exchange conditions, overall heat transfer coefficient ≥ 3000 W/(m²·°C).
- Pressure drop: at rated flow rate, single-side pressure drop ≤ 0.05 MPa.
- 316L stainless steel plates are available as an option for media with higher corrosiveness.
- Gasketed (gasket-plate) heat exchangers support on-site disassembly and cleaning, suitable for scale-prone water quality scenarios.
5.4 Sensor Technical Parameters
5.4.1 Temperature Sensor (PT100 Class A)
- Measuring range: -50°C ~ +150°C
- Accuracy class: Class A, ±(0.15 + 0.002 |t|) °C
- Output signal: three-wire resistance signal
- Protective tube material: 304 stainless steel
- Insertion depth: 50 mm (customizable)
- Connection: M14x1.5 thread
- Response time: ≤ 3 s
5.4.2 Pressure Sensor
- Measuring range: 0-1 MPa / 0-1.6 MPa (optional)
- Accuracy class: 0.5
- Output signal: 4-20 mA, two-wire
- Supply voltage: DC 24V
- Overload capacity: 2x full scale
- Connection: G1/2 female thread
- Protection class: IP65
- Temperature compensation: -10°C ~ 80°C
5.4.3 Turbine Flow Meter
- Measuring range: 0.6-6 m³/h (DN25), 1-10 m³/h (DN32), 2-20 m³/h (DN40)
- Accuracy class: ±1.0%
- Output signal: pulse signal / 4-20 mA (optional)
- Supply voltage: DC 24V
- Working pressure: 1.6 MPa
- Medium temperature: -20°C ~ 120°C
- Connection: threaded connection
- Repeatability: ≤ 0.2%
5.4.4 Leak Sensor
- Detection method: cable-type electrode detection
- Response time: ≤ 1 s
- Detection sensitivity: capable of detecting 0.5 mL of accumulated water
- Output signal: digital (switch) signal
- Supply voltage: DC 12V/24V
- Leak cable length: standard 3 m, extendable up to 100 m
- Operating environment: temperature 0-60°C, humidity ≤ 95%
- Protection class: IP67 (detection end)
5.5 Intelligent Control Cabinet Technical Parameters
- Controller: Industrial-grade PLC, CPU main frequency 100 MHz, program memory capacity 128 K
- Inputs/Outputs:
- Analog inputs: 8 AI channels, 4-20 mA / PT100 configurable
- Digital inputs: 16 DI channels, dry contacts
- Relay outputs: 8 DO channels, contact rating 5 A / 250VAC
- Analog outputs: 2 AO channels, 4-20 mA
- Display: 7-inch full-color touch screen, resolution 800×480, resistive touch
- Communication interfaces: 1x RS485, 1x Ethernet (optional)
- Power supply: AC 220V±15%, 50 Hz
- Power consumption: ≤ 100 W
- Enclosure material: cold-rolled steel plate with plastic powder coating, thickness 1.5 mm
- Protection class: IP54
- Mounting: wall-mounted / floor-standing
- Dimensions: 500x400x200 mm (W×H×D, wall-mounted version)
- Operating environment: temperature 0-50°C, humidity ≤ 90% non-condensing
5.6 Material and Process Parameters
- Piping material: 304 stainless steel pipe, wall thickness 2.0-3.0 mm, conforming to GB/T 14976 standard
- Seal material: Nitrile rubber (NBR), applicable temperature -10°C ~ 120°C; EPDM rubber available as an option
- Welding process: TIG (argon arc) welding; weld seams undergo pickling and passivation treatment for excellent corrosion resistance
- Surface treatment: all carbon steel components are electrostatically powder coated, coating thickness 60-80 μm, adhesion class 1
- Pressure testing: all pressure-bearing components undergo a hydrostatic test at 1.5x design pressure before shipment, held for 30 minutes with no leakage
- Electrical testing: all electrical components undergo insulation resistance testing (≥ 2 MΩ) and dielectric withstand testing (2000V/1 min)
Chapter 6 Product Functions and Features
6.1 Core Functions
6.1.1 Closed-Loop Circulation Heat Exchange Function
The system forms a completely sealed water circulation loop. The coolant circulates and exchanges heat in a closed environment with no direct contact with outside air, effectively preventing dust, debris, and microorganisms from entering the system, reducing scaling and corrosion, and lowering make-up water frequency and water quality maintenance costs. The plate heat exchanger provides complete isolation between cold and hot sides — water quality fluctuations on the cold source side do not affect the cabinet-side system, ensuring safe water supply for precision cabinet equipment.
6.1.2 Variable-Frequency Precision Temperature Control Function
Using a variable-frequency pump with a PID temperature control algorithm, the system dynamically adjusts the circulation flow rate based on real-time cabinet heat load, achieving precise supply water temperature control of ±0.5°C and preventing temperature fluctuations from affecting equipment operational stability. The temperature control range of 18-35°C is continuously adjustable, allowing flexible settings according to the cooling requirements of different equipment, accommodating servers, industrial PCs, medical devices, and various other heat-generating equipment.
6.1.3 Multi-Stage Water Quality Purification Function
A two-stage filtration system consisting of a “Y-type coarse filter + precision fine filter” effectively intercepts welding slag, rust, sediment, and other impurities, achieving 5 μm filtration precision and preventing impurities from blocking the microchannels of cabinet cold plates. An optional ion exchanger and electronic water conditioner can further reduce water hardness and conductivity, inhibiting scaling and electrochemical corrosion, and extending overall system service life.
6.1.4 Automatic Pressure Stabilization and Make-up Water Function
A closed expansion tank and automatic make-up valve automatically absorb volume expansion and contraction caused by water temperature changes, maintaining stable system pressure. An automatic make-up water function is provided — when system pressure drops due to leakage or other causes, make-up water is automatically added without manual intervention. Water shortage protection is also included: in the event of severe water shortage, the pump automatically stops to prevent dry-running damage.
6.1.5 Multiple Safety Protection Functions
The system is equipped with comprehensive safety protection mechanisms covering all risk dimensions including pressure, temperature, flow, liquid level, leakage, and electrical:
- Pressure protection: automatic pressure relief on overpressure, automatic make-up on low pressure, automatic pump stop on water shortage
- Temperature protection: over-temperature alarm, automatic load shedding on over-temperature
- Flow protection: low flow alarm, automatic shutdown on flow interruption
- Leak protection: immediate alarm upon leak detection, automatic pump stop and valve closure for serious leaks
- Electrical protection: overcurrent, overload, short circuit, phase loss, and earth leakage protection
- Pump protection: overload protection, over-temperature protection, dry-run protection
6.1.6 Intelligent Monitoring and Alarm Function
All core operating parameters — temperature, pressure, flow rate, liquid level, conductivity, etc. — are monitored in real time and displayed in full on the local touch screen for at-a-glance visibility. Tiered alarm functions are provided: minor faults trigger audible and visual alerts; serious faults immediately trigger protection actions and upload alarm information. Historical data storage and query are supported, with up to 30 days of operating data and alarm records traceable for fault analysis and O&M management.
6.1.7 Remote Communication and Interlocking Function
Standard RS485 communication interface with Modbus-RTU standard protocol enables seamless integration into data center infrastructure monitoring systems (DCIM), building automation systems (BAS), and centralized monitoring and unified management platforms. Optional Ethernet and 4G communication modules support remote web-based and mobile app monitoring, allowing system operating status to be viewed anytime, anywhere, with alarm push notifications. The system can interlock with cold source equipment such as chillers and cooling towers for coordinated optimization of the entire cooling system.
6.1.8 Pump Redundancy Backup Function
High-reliability models are configured with one-operating/one-standby dual pumps. During normal operation, a single pump operates with timed automatic rotation to balance pump wear. When the operating pump fails, the standby pump automatically switches over within seconds, ensuring uninterrupted system operation and satisfying the 7×24-hour continuous cooling requirements of high-grade data centers.
6.2 Product Core Features
6.2.1 High Efficiency and Energy Saving, Reduced Operating Costs
- High-efficiency plate heat exchanger with heat exchange efficiency above 92%, high cold source utilization, and small temperature difference
- Variable-frequency pump adjusts flow rate on demand; significant energy savings under partial load — more than 30% energy savings compared to constant-flow systems
- Optimized piping design with low flow resistance and low parasitic pump power consumption; overall system energy efficiency is 15% higher than the industry average
- Closed-loop circulation with no evaporation losses, extremely low make-up water consumption, and water resource utilization close to 100%
6.2.2 Safe and Reliable, Reduced Leak Risk
- Full-system 304 stainless steel construction for corrosion resistance, high strength, and long service life, preventing pipe rust and leakage
- All connections use double-seal construction with 100% factory pressure testing; high sealing reliability
- Multi-point leak monitoring with second-level response for early detection and early resolution of leak faults
- Motorized shut-off valve interlock protection — rapid water source isolation upon leak detection, minimizing the impact of leakage and preventing spread to other cabinets
- Comprehensive pressure protection mechanisms prevent overpressure pipe rupture; system operating pressure always remains within the safe range
6.2.3 Modular Design, Fast and Efficient Installation
- All functional modules are factory-prefabricated and integration-tested; on-site installation only requires connecting inlet/outlet water pipes and power cables, reducing construction time by over 60%
- Standardized interfaces and universal components make subsequent maintenance and replacement convenient, with no custom fabrication required
- Compact footprint with wall-mounted, floor-standing, and in-cabinet mounting options; minimal space occupation, adaptable to different data center layouts
- Strong scalability — adding new cabinets only requires adding branch accessories without replacing the main system, enabling flexible capacity expansion
6.2.4 Intelligent O&M, Reduced Management Costs
- Fully automated operation with no dedicated attendant required; zero manual operations during normal operation
- Fault self-diagnosis function precisely locates fault points and provides handling recommendations, lowering the technical threshold for O&M personnel
- Remote monitoring capability — system status can be checked without visiting the site, reducing on-site inspection frequency
- Scheduled maintenance reminders automatically prompt filter replacement, water quality testing, and other maintenance items, preventing failures caused by overdue service
6.2.5 Low-Noise Operation, Improved Data Center Environment
- Pumps are equipped with vibration-damping bases and flexible connectors to effectively isolate vibration, reducing vibration noise and solid-borne sound transmission
- Variable-frequency pump noise is significantly reduced at low speeds — ≤ 52 dB at 1 m, far lower than air-cooled air conditioning noise
- No fan airflow noise; overall data center noise levels are significantly reduced, improving the working environment for O&M personnel
6.2.6 Broad Compatibility, Suitable for Multiple Scenarios
- Compatible with all brands of indirect water-cooled integrated cabinets; standard universal interfaces require no modification for integration
- Compatible with multiple cold sources: chillers, cooling towers, plate heat exchange stations, municipal chilled water, and other cold source systems
- Compatible with multiple coolant media: deionized water, softened water, ethylene glycol aqueous solutions, and more
- Wide voltage and wide temperature design, suitable for industrial, outdoor, plateau, and other complex environmental conditions
6.2.7 Green and Environmentally Friendly, Meeting Dual Carbon Goals
- Significantly reduces cooling system energy consumption and effectively lowers data center PUE, supporting the low-carbon goal of PUE ≤ 1.2 for data centers
- Closed-loop circulation with zero emissions, causing no water resource waste or pollution
- No refrigerants such as Freon required; no ozone depletion or greenhouse effect concerns
- All materials comply with RoHS environmental standards; the production and use processes are green and environmentally friendly
Chapter 7 Product Application Scenarios
As the core supporting components for cabinet-level water-cooled heat dissipation, water-cooled cabinet water circulation accessories are widely applied in various high-density heat dissipation scenarios. The following describes the main application scenarios and compatible solutions.
7.1 Data Centers and Computing Facilities
7.1.1 AI Computing Data Centers
AI training servers and GPU clusters can reach 30-80 kW per cabinet — traditional air cooling is completely inadequate, making water cooling the mainstream cooling solution. This product can support integrated water-cooled GPU cabinets, providing high-flow, high-stability water circulation support with precise supply water temperature control, ensuring full-load stable operation of GPUs while significantly reducing cooling energy consumption and improving the energy efficiency ratio of computing clusters.
7.1.2 Enterprise Data Centers
Data centers for financial, telecommunications, and internet enterprises typically have 10-20 kW per cabinet and place high demands on cooling reliability. This product can support standard water-cooled cabinets, replacing traditional in-row air conditioners to save data center space and reduce PUE, while featuring comprehensive leak protection mechanisms to ensure the safe operation of data equipment.
7.1.3 Edge Data Centers
Edge data centers typically have limited space and no professional data center environment, placing high demands on cooling equipment size, reliability, and intelligence. This product features an integrated design — compact, quick to install, and capable of unattended operation — making it a perfect fit for edge site deployment conditions and providing reliable cooling support for edge computing nodes.
7.1.4 High-Density Server Rooms
High-density blade server and storage server rooms have high thermal density and numerous local hotspots. Water cooling directly removes heat from the heat-generating components, eliminating local hotspots and improving server operating stability and service life. This product enables independent control per cabinet, flexibly accommodating heat load differences across cabinets.
7.2 Industrial Automation Field
7.2.1 Industrial Control Cabinet Cooling
PLC control cabinets, variable-frequency drive cabinets, and servo drive cabinets on automated factory production lines contain dense electronic components that generate significant heat. Factory environments are dusty and hot, making traditional fan cooling ineffective and prone to equipment failures. This product supports water-cooled industrial control cabinets, using a closed-loop water cooling circuit that isolates external dust and high temperatures, ensuring stable operation of industrial control equipment in harsh industrial environments and reducing failure rates.
7.2.2 CNC Machine Tool Cooling
The spindles, servo motors, and hydraulic systems of high-precision CNC machine tools generate substantial heat. Temperature increases cause thermal deformation, affecting machining accuracy. This product can support machine tool water cooling systems, precisely controlling coolant temperature, stabilizing machine operating temperature, reducing thermal deformation, and improving machining precision and tool service life.
7.2.3 Injection Molding Machines and Mold Cooling
In injection molding production, mold temperature directly affects product molding quality and production efficiency. This product provides precisely temperature-controlled cooling water, stabilizing mold temperature, improving injection-molded part surface quality, reducing defect rates, shortening molding cycles, and increasing production efficiency.
7.3 Medical and Scientific Research Fields
7.3.1 Medical Imaging Equipment Cooling
Large medical devices such as CT, MRI, DR, and linear accelerators generate enormous heat in their core components and require extremely high temperature stability — temperature fluctuations can affect imaging accuracy and equipment performance. This product offers ±0.5°C high-precision temperature control, ensuring constant temperature for critical equipment components, improving medical equipment operational stability and diagnostic accuracy.
7.3.2 Laboratory Analytical Instruments
Precision analytical instruments such as mass spectrometers, spectrometers, chromatographs, and electron microscopes have extremely high requirements for ambient temperature and self-cooling — even minor temperature fluctuations affect detection accuracy. This product provides high-precision constant-temperature cooling, ensuring stable temperatures for critical instrument components and improving detection result accuracy and repeatability.
7.3.3 Scientific Research Test Equipment
Materials testing equipment, environmental test chambers, laser equipment, vacuum coating equipment, and other research equipment require stable cooling systems to ensure test conditions. This product offers precise temperature control, stable operation, and customizable special parameters to meet the special cooling requirements of various scientific research tests.
7.4 New Energy and Power Fields
7.4.1 Energy Storage Inverters and Charging Pile Cooling
PCS inverters in energy storage stations and high-power DC charging piles have high power and concentrated heat generation, typically installed in harsh outdoor environments. This product features wide-temperature design and anti-corrosion design, adaptable to outdoor high and low temperature environments, providing reliable water cooling for high-power power electronics equipment and improving equipment operating life and reliability.
7.4.2 Power Control Cabinet Cooling
Relay protection cabinets, thyristor cabinets, and rectifier cabinets in substations and converter stations have extremely high operational reliability requirements — overheating faults are not permitted. This product’s high-reliability configuration with one-operating/one-standby redundant design ensures uninterrupted cooling system operation for power equipment, meeting the high availability requirements of the power industry.
7.5 Military and Classified Fields
Military data centers, classified data centers, command centers, and similar scenarios have extremely high requirements for equipment reliability, security, noise, and electromagnetic compatibility. This product features all-stainless-steel construction, rugged structure, strong anti-interference capability, low-noise operation, fanless design to reduce dust ingress, and an optional electromagnetic shielding version, meeting the special requirements of military and classified scenarios.
7.6 Other Application Scenarios
- Radio and Television: cooling for transmitters and broadcast servers, ensuring stable signal broadcasting
- Rail Transit: cooling for onboard control cabinets and signal cabinets, adapting to vibration and temperature variation environments in vehicles
- Building Intelligence: cooling for building automation equipment rooms and fire control room equipment
- Telecommunications Base Stations: cooling for 5G base station BBU rooms and core equipment rooms, reducing base station energy consumption
Chapter 8 Product Installation
8.1 Installation Construction Preparation
8.1.1 Personnel Preparation
- Installation must be performed by professional personnel qualified in plumbing and electrical installation. Construction personnel must be familiar with the product structure and installation requirements and have received product technical training.
- The construction team must designate a project manager, technical lead, and safety officer with clearly defined responsibilities.
- Special operation personnel (welders, electricians) must hold nationally recognized special operation certificates and work with proper certification.
- Technical and safety briefings must be conducted before construction, clarifying construction procedures, technical standards, and safety precautions.
8.1.2 Technical Preparation
- Review construction drawings, product manuals, and relevant codes and standards; verify that equipment models, specifications, and quantities conform to design requirements.
- Conduct on-site survey to confirm installation location, piping routes, power access points, and cold source interface positions; verify dimensional compatibility.
- Prepare a construction plan detailing schedule, personnel arrangements, tooling plan, quality control points, and safety assurance measures.
- Conduct technical briefing for construction personnel, explaining key process operation points and acceptance standards.
8.1.3 Site Preparation
- Clean the installation site — free of debris and standing water; the floor must be level, solid, and capable of supporting equipment weight.
- Reserve sufficient operating space at the installation location: ≥600 mm operating space in front of the equipment, ≥300 mm maintenance space on the sides, and ≥200 mm space above.
- For wall-mounted installation, confirm the wall load-bearing capacity. The wall must be a solid wall or load-bearing column; hollow walls require reinforced backing plates.
- On-site power supply and cold source interfaces must be pre-installed and conform to design parameter requirements.
- The site must have adequate lighting and ventilation to meet construction needs.
8.1.4 Equipment and Material Preparation
- Check the quantity, model, and specification of equipment and accessories against the packing list; inspect for transportation damage and verify that all accessories are complete.
- Verify that factory certificates of conformity, test reports, manuals, and other technical documents are complete.
- Prepare installation auxiliary materials including piping, fittings, insulation, sealing materials, and electrical materials — specifications must conform to requirements and quality must be certified.
- Prepare all construction tools in good condition; measuring instruments must be within their calibration validity period.
8.2 Pre-Installation Inspection
8.2.1 Equipment Appearance Inspection
- Inspect the main unit, pump, heat exchanger, control cabinet, and other components for dents, deformation, paint peeling, cracks, or other damage.
- Check that all port seals are intact, confirming no debris inside and no water ingress or moisture damage.
- Check that gauge glasses on pressure gauges, thermometers, and displays are intact, and that pointers and displays function normally.
- Check that valves operate smoothly without sticking.
8.2.2 Internal Integrity Inspection
- Open the control cabinet door and check that internal components are intact, terminals are securely tightened, and there is no looseness, detachment, or moisture damage.
- Check that pump motor wiring is secure and insulation is sound.
- Check that sensor connections are secure and cables are undamaged.
- Verify that internal component models and configurations match the purchase contract.
8.2.3 Installation Condition Confirmation
- Confirm the installation foundation levelness: level deviation ≤ 2 mm/m.
- Confirm installation ambient temperature is between 5-40°C, relative humidity ≤ 90%, no corrosive gases, and no strong electromagnetic interference.
- Confirm that power supply voltage and capacity meet equipment requirements and that the grounding system is reliable.
- Confirm that cold source supply water pressure and temperature meet system design requirements.
8.3 Main Unit Installation
8.3.1 Positioning and Layout Marking
- Based on design drawings and actual site conditions, determine the installation positions of the main unit, control cabinet, and piping. Snap layout reference lines using chalk lines.
- Mark mounting hole positions for wall-mounted equipment; mark base installation boundary lines for floor-standing equipment.
- Verify equipment dimensions against reserved space to ensure accurate installation positions and reasonable piping routes.
8.3.2 Base and Bracket Installation
- Floor-standing equipment: Place the equipment base on the reference position, level it with a spirit level, and secure it to the floor with expansion bolts. Vibration-damping pads may be installed between the base and floor to reduce vibration transmission.
- Wall-mounted equipment: Drill holes in the wall according to the marked positions, install expansion bolts, secure the mounting bracket to the wall, level and plumb the bracket, and tighten the bolts. Bracket load capacity must exceed 2x the equipment weight.
- Pipe supports: Install pipe supports according to the piping route. Support spacing must conform to code requirements: for horizontal pipes DN25-DN50, spacing 1.0-1.5 m; for vertical pipes, spacing 1.5-2.0 m. Supports must be securely installed with accurate positioning.
8.3.3 Main Unit Securing
- Hoist or move the main unit onto the installation base/bracket, aligning the mounting holes.
- Secure the equipment with bolts. Re-level and re-plumb; vertical deviation ≤ 3 mm/m.
- Pump installation must ensure the pump shaft is horizontal; motor shaft and pump shaft concentricity must meet requirements; coupling clearance must be uniform.
- Heat exchanger installation must maintain verticality; tilt angle must not exceed 5° to avoid affecting heat exchange performance and air venting.
8.4 Piping System Installation
8.4.1 General Piping Installation Requirements
- Piping must be installed horizontally level and vertically plumb, neatly arranged, aesthetically standard, and with slopes meeting requirements.
- Horizontal piping must have a slope of 0.2%-0.3%, sloping toward drain points. Air vent valves at high points and drain valves at low points.
- Pipe connections must be leak-tight and reliable; use PTFE tape or thread sealant for threaded connections; weld joints must be full and defect-free.
- Pipe openings must be temporarily capped during installation to prevent debris from entering the piping.
- Flexible connectors must be used for connections between piping and equipment to avoid stress and vibration transmission; forced alignment connections are strictly prohibited.
- Pipe penetrations through walls and floors must use sleeves. No joints are permitted inside sleeves; the space between pipe and sleeve must be sealed with non-combustible material.
8.4.2 Stainless Steel Pipe Threaded Connection Installation
- Cut pipe to design dimensions with square, even cuts. Remove burrs and flash, and chamfer the pipe ends.
- Use a threading machine to cut pipe threads. Threads must be regular with no broken or missing threads; thread accuracy must meet standards.
- Clean the thread surface. Wrap PTFE tape evenly on the external threads (clockwise direction) or apply thread sealant.
- Tighten fittings with pipe wrenches. Apply moderate force to avoid cracking from over-tightening or leaking from under-tightening.
- After connection, clean off excess PTFE tape and sealant, and apply identification marks.
8.4.3 Stainless Steel Pipe Welded Connection Installation
- Pipe cutting using plasma cutting or abrasive wheel cutting; cuts must be square and even. Remove oxidation layer and burrs; bevel preparation must meet welding requirements.
- Clean oil, grease, and scale from within 20 mm on both sides of the weld joint before welding, exposing bare metal.
- Use TIG (argon arc) welding. Select stainless steel filler wire matching the base material. Welding current should be appropriate to ensure full penetration.
- Weld seams must be uniformly formed with no cracks, porosity, slag inclusion, incomplete fusion, or other defects. Weld reinforcement height: 0.5-1.5 mm.
- After welding, perform pickling and passivation treatment on weld seams to enhance corrosion resistance; clean weld slag and spatter from weld surfaces.
8.4.4 Valve and Instrument Installation
- Before installation, check that valve models and specifications conform to design requirements. Perform visual inspection and verify smooth operation; important valves require hydrostatic testing.
- Valve installation orientation must be correct, with the body arrow aligned with medium flow direction; handles must be positioned for easy operation.
- Globe valves, ball valves, check valves, and safety valves installed at designed positions. Safety valves installed vertically with outlets routed to safe discharge locations.
- Temperature sensors installed on straight pipe sections with stable flow; insertion depth reaching the pipe centerline, avoiding elbows, valves, and other turbulent zones.
- Pressure sensors installed on straight pipe sections with pressure taps vertical upward or horizontal to avoid air accumulation. Install buffer tubes to mitigate water hammer impact.
- Flow meter installation requires straight run lengths: ≥10x pipe diameter upstream and ≥5x pipe diameter downstream to ensure measurement accuracy.
- Filter installation orientation must be correct with the drain port facing downward for convenient blowdown; install in locations accessible for disassembly and cleaning.
8.4.5 Expansion Tank Installation
- The closed expansion tank is installed on the system return water side, ahead of the pump suction inlet, at a position above the highest point of the system.
- Tank bracket must be securely installed; tank secured vertically. Connection piping must use union connections for convenient disassembly.
- The top of the tank is fitted with an air vent valve; the bottom with a drain valve. Liquid level sensor must be securely installed with well-sealed wiring.
- After installation, check the tank pre-charge pressure; adjust by charging or bleeding gas if it does not meet requirements.
8.4.6 Leak Monitoring System Installation
- Leak detection cable is laid flat along the floor in areas prone to leakage: under the pump base, below the heat exchanger, below pipe fittings, and at the cabinet base. The cable must be in close contact with the mounting surface.
- Point-type leak sensors are placed at critical leak risk points, securely fixed with the sensing surface facing downward and close to the floor.
- The leak controller is installed in a dry location that is convenient for observation, with secure wiring and proper waterproofing.
- Avoid sharp objects puncturing the leak detection cable; avoid strong electromagnetic interference; insulate all connections.
8.5 Piping Pressure Testing and Flushing
8.5.1 Piping Pressure Testing
- After piping installation is complete, perform a hydrostatic pressure test at 1.5x the system design pressure, with a minimum test pressure of 0.6 MPa.
- Before testing, close the equipment inlet/outlet valves to isolate pumps, heat exchangers, instruments, and other equipment to prevent overpressure damage.
- Fill the system with water, purge all air, and slowly raise the pressure in stages, inspecting at each stage. After confirming no abnormalities, raise to the test pressure.
- Hold the test pressure for 30 minutes. A pressure drop not exceeding 0.05 MPa with no leakage at any weld, connection, or valve is considered a pass.
- After passing the test, slowly release the pressure, drain the system water to an appropriate location, and clean the site.
8.5.2 Piping Flushing
- After the hydrostatic test passes, flush the piping to remove welding slag, rust, sediment, and other debris from the piping.
- Before flushing, remove precision filter cartridges, flow meters, and other precision components, replacing them with short pipe spools. Close equipment inlet/outlet to prevent debris from entering equipment.
- Use clean tap water for flushing. Flushing velocity must not be less than 1.5 m/s. Water enters from the system inlet and drains from the lowest point drain outlet.
- Flush continuously and periodically check the discharge water quality. Flushing is considered complete when the inlet and outlet water are consistent in transparency and color with no visible impurities.
- After flushing is complete, drain all flushing water from the system and reinstall the precision components and instruments.
8.6 Pipeline Insulation
After the pipeline pressure test and flushing pass, insulation construction shall be carried out. The purpose of insulation is to reduce cooling capacity loss and prevent condensation on the outer wall of the pipeline.
The insulation material shall be closed-cell rubber-plastic insulation cotton, with a flame retardant rating of Class B1, and a thickness meeting the design requirements (≥20mm).
Before insulation, clean the dust and oil stains on the pipeline surface to ensure the surface is dry and clean.
The insulation pipe sleeve is sleeved onto the pipeline, and the joints are bonded tightly with special adhesive, leaving no gaps; at elbows, tees, and valves, special insulation fittings shall be used and wrapped tightly.
Aluminum foil tape may be wrapped around the outside of the insulation layer to improve aesthetics and moisture resistance.
After the insulation construction is completed, the appearance shall be smooth and neat, without damage, cracks, or shedding. All metal surfaces shall be covered with no exposure.
8.7 Electrical Control Cabinet Installation
The control cabinet shall be installed in a dry, ventilated location that is convenient for operation. The wall-mounted installation height shall be 1.2-1.5m from the cabinet bottom to the floor; the floor-standing installation foundation shall be 100mm above the ground.
The control cabinet shall be fixed securely, with a verticality deviation ≤1.5‰, cabinet doors opening and closing flexibly, and reliable grounding.
The control cabinet shall be kept away from strong electromagnetic interference sources, and shall not be installed in locations with moisture, high temperature, excessive dust, or corrosive gases.
The wiring inside the cabinet shall be neat, with clear markings, firmly connected terminals, and sufficient reserved length for spare wires.
Proper cabinet sealing shall be provided to prevent dust and moisture from entering the cabinet.
8.8 Overall System Connection
After the pipeline pressure test and flushing pass, connect the host equipment to the pipeline interfaces, tighten the connecting bolts evenly and uniformly to avoid misalignment.
Connect the cooling source side pipelines, confirm that the interface direction is correct, and that the valve switch status is correct.
Connect the cabinet-side supply and return water pipelines, and make clear markings to distinguish between supply water and return water.
Check the initial status of all valves: service valves open; drain valves and air release valves closed.
After the electrical wiring is completed, perform an overall system appearance inspection to confirm that all connections are correct and no components are missing.
9.1 General Wiring Requirements
Electrical wiring must be carried out by licensed electricians, strictly complying with electrical safety operating procedures. Power shall be disconnected and verified before construction; live work is strictly prohibited.
All cables must comply with national standards, adopt copper core cables, with conductor cross-sections meeting the current-carrying capacity requirements, and voltage ratings matching the system voltage.
Before wiring, verify that the cable specifications, models, and quantities meet the design requirements, and check that the cable appearance is free of damage and the insulation is in good condition.
Terminal markings shall be clear, wire number sleeves shall be standardized, and markings at both ends shall be consistent to facilitate later maintenance.
Wiring shall be firm and reliable, terminal bolts tightened, with good contact and no loose or false connections; stranded wires shall be crimped with terminal lugs, and direct insertion is strictly prohibited.
The wiring inside the cabinet shall be neat, with strong-current and weak-current wires routed separately and avoiding crossing; cables shall be bundled into harnesses, routed horizontally and vertically, neat and standardized.
All exposed live parts shall be provided with insulation protection to prevent electric shock and short circuits.
The system grounding shall be reliable, with grounding resistance meeting requirements, ensuring personal and equipment safety.
9.2 Power Wiring
9.2.1 Main Power Wiring
System main power specifications: small power models — AC 220V single-phase three-wire system; large power models — AC 380V three-phase five-wire system.
The power incoming line shall be routed through the cable entry hole at the bottom of the control cabinet, with a protective grommet installed to prevent cable wear.
The power incoming line shall be connected to the upper terminals of the main power switch inside the control cabinet, with the L/N/PE markings correspondingly connected; the three-phase power phase sequence shall be correct.
The rated current of the main power switch shall meet the maximum load requirements of the system and provide overload and short-circuit protection functions.
Power incoming line conductor cross-section selection:
| Power Rating | Copper Core Cable Cross-Section |
|---|---|
| 0.75kW and below | 2.5mm² |
| 1.1-2.2kW | 4mm² |
| 3.0-5.5kW | 6mm² |
The power supply must be reliably grounded. The cross-sectional area of the protective earth (PE) conductor shall not be less than 1/2 of the phase conductor cross-sectional area, with grounding resistance ≤4Ω.
9.2.2 Control Power Wiring
Control power shall be provided by a switching power supply, with AC 220V input and DC 24V output, supplying power to sensors, actuators, and the controller.
The switching power supply input shall be connected to the lower terminals of the main power switch; the output terminals shall be connected with correct polarity — reverse connection is strictly prohibited.
The capacity of the switching power supply shall meet the total power requirements of all control loads, with 20% margin reserved.
A fuse or miniature circuit breaker shall be configured on the output side of the control power supply for short-circuit protection.
9.3 Pump Wiring
9.3.1 Fixed-Speed Pump Wiring
The pump motor cable shall be routed through the pump junction box. Verify the motor wiring diagram and confirm the wiring method (star/delta).
For three-phase motors, the three phase wires shall be connected to the contactor output terminals, and the PE wire to the grounding terminal; for single-phase motors, connect L, N, and PE.
The thermal relay shall be connected in series in the main circuit, with the setting current adjusted to the motor rated current value for overload protection.
After wiring is completed, manually rotate the pump to confirm flexible rotation without jamming; perform a jog test to confirm the rotation direction is correct, consistent with the pump direction arrow marking.
9.3.2 Variable-Frequency Pump Wiring
The VFD input side shall be connected to the main power supply, and the output side to the pump motor. Reverse connection is strictly prohibited (input and output must not be reversed).
The VFD grounding terminal shall be reliably grounded to reduce electromagnetic interference.
VFD control signals: the 4-20mA frequency adjustment signal output from the controller shall be connected to the VFD analog input terminal, with correct polarity.
The VFD running and fault feedback signals shall be connected to the controller digital input terminals for status feedback.
VFD parameters shall be set according to the pump nameplate parameters, including motor power, rated current, rated speed, acceleration/deceleration time, etc.
Motor cables and control cables shall be routed separately, avoiding parallel routing to reduce electromagnetic interference.
9.4 Sensor Wiring
9.4.1 Temperature Sensor Wiring (PT100)
PT100 shall adopt three-wire connection, with the three wires being power, signal, and compensation wires, correspondingly connected to the controller analog input terminals.
Shielded cable shall be used, with the shield layer grounded at one end only to reduce interference.
During wiring, verify the sensor lead wire colors and connect according to the wiring diagram to avoid incorrect connections causing abnormal temperature readings.
The sensor junction box shall be waterproof-sealed to prevent moisture ingress from affecting measurement accuracy.
9.4.2 Pressure/Level Transmitter Wiring
Two-wire transmitter wiring: DC 24V positive terminal to the transmitter positive terminal; the transmitter negative terminal to the controller analog input positive terminal; the analog input negative terminal to the DC 24V negative terminal, forming a loop.
Before wiring, confirm that the supply voltage matches the transmitter rated voltage; overvoltage supply is strictly prohibited.
The shield layer of shielded cable shall be grounded at one end only, and signal cables shall be kept away from power cables.
After wiring is completed, check the zero point and span to confirm that the measured value matches the actual value.
9.4.3 Flow Sensor Wiring
Pulse output type flow meter: power wires to DC 24V, pulse signal wire to the controller digital input terminal, and common terminal to the power supply negative terminal.
4-20mA output type flow meter: connect according to the two-wire transmitter wiring method.
The flow meter wiring shall be shielded to avoid electromagnetic interference causing inaccurate counting.
After wiring is completed, verify the flow coefficient parameters and set them into the controller.
9.4.4 Leak Detection Sensor Wiring
The leak controller power supply shall be DC 24V, with correct polarity.
Both ends of the leak detection cable shall be connected to the leak controller detection terminals. For extension, use dedicated extension cables with proper insulation at the joints.
The alarm output terminal shall be connected to the controller digital input to provide the leak signal.
The leak controller shall be reliably grounded to avoid false alarms.
9.5 Actuator Wiring
9.5.1 Solenoid Valve/Electric Valve Wiring
The solenoid valve coil voltage shall match the supply voltage — AC 220V or DC 24V — and be correspondingly connected to the controller relay output terminals.
Electric valve wiring: power terminals to the power supply; open/close control terminals to the controller outputs; open/close limit feedback terminals to the controller inputs.
During wiring, verify the valve body wiring diagram to avoid reverse connections causing incorrect operation.
The valve actuator shall be waterproof-protected to prevent water ingress from burning out the coil.
9.5.2 Alarm Device Wiring
The audible and visual alarm shall be connected to the controller alarm output terminals, with matching voltage ratings.
The alarm shall be installed in a location that is easy to see and hear, and firmly fixed.
Test the alarm function to confirm normal audible and visual operation.
9.6 Communication Wiring
RS485 communication cables shall be shielded twisted pair, with characteristic impedance of 120Ω and conductor cross-section ≥0.5mm².
The communication cable A/B terminals shall be connected correspondingly, with correct polarity; the shield layer shall be grounded at one end only, at the control cabinet side.
When the communication bus length exceeds 1000 meters, terminal matching resistors (120Ω) shall be installed at both ends.
Communication cables shall be kept away from power cables, avoiding parallel routing; when crossing, cross at right angles to reduce electromagnetic interference.
When multiple devices are connected in parallel for communication, use daisy-chain connection, avoiding star connection to ensure communication stability.
9.7 Grounding System Wiring
The system shall adopt a combined grounding method, where protective grounding, working grounding, and shield grounding share a common grounding electrode, with grounding resistance ≤4Ω.
The control cabinet enclosure shall be provided with a dedicated grounding terminal, reliably connected to the machine room grounding busbar with grounding cables. The grounding bolts shall be tightened with good contact.
All equipment metal enclosures, pipelines, and cable trays shall be reliably grounded to form equipotential bonding.
Shield layers of shielded cables shall be grounded at one end only, connected to the control cabinet grounding terminal.
After grounding construction is completed, measure the grounding resistance. The system may only be put into operation after the resistance meets requirements.
9.8 Wiring Inspection and Testing
9.8.1 Wiring Appearance Inspection
Check that all wiring is correct, with clear wire numbers consistent with the drawings.
Check that all terminals are tightened, with no loose or false connections.
Check that the wiring is neat, strong-current and weak-current wires are separated, and insulation protection is in place.
Check that grounding is reliable and markings are clear.
9.8.2 Insulation Resistance Test
Disconnect all electronic components, sensors, and the controller. Use a 500V megger to measure the main circuit-to-ground insulation resistance, which shall be ≥2MΩ.
Measure the control circuit-to-ground insulation resistance, which shall be ≥1MΩ.
If the insulation resistance fails, investigate and rectify the cause before powering on.
9.8.3 Pre-Power-On Check
Confirm that all switches are in the open (OFF) position and all loads are free of short circuits.
Verify that the power supply voltage is normal and consistent with the equipment rated voltage.
Confirm that no personnel are working on site, no debris is around the equipment, and conditions are ready for power-on.
Prepare emergency power-off measures to ensure immediate power cutoff in the event of abnormality.
After system installation and wiring are completed and pass inspection, commissioning may proceed. Commissioning must be carried out by professional technical personnel, strictly following the commissioning procedure step by step, with commissioning records kept. Commissioning is divided into six stages: pre-commissioning inspection, no-load commissioning, loaded commissioning, parameter tuning, functional testing, and trial operation.
10.1 Pre-Commissioning Inspection
10.1.1 Pipeline System Inspection
Check that all pipeline connections are secure and valve switching status is correct:
| Valve | Status |
|---|---|
| System main supply and return water valves | Open |
| Pump inlet and outlet valves | Open |
| Filter inlet and outlet valves | Open |
| Heat exchanger inlet and outlet valves | Open |
| All drain valves and air release valves | Closed |
| Valves before and after the makeup water valve | Open |
Check that the expansion tank pre-charge pressure meets the requirements, generally system static pressure + 0.05MPa.
Check that the safety valve set pressure is correct and the lead seal is intact.
Check that the pipeline insulation is intact, without damage or exposure.
Check that leak detection sensors are properly positioned and in normal condition.
Confirm that the cooling source side water supply is normal, with pressure and temperature meeting design requirements.
10.1.2 Electrical System Inspection
Check that all wiring is correct and secure, without looseness or misconnection.
Check that all circuit breakers and switches are in the open (OFF) position.
Check that the grounding system is reliable and grounding resistance meets requirements.
Measure the power supply voltage; voltage fluctuation shall be within ±10% of the rated value.
Check that the control cabinet interior is free of debris and moisture, and components are in good condition.
10.1.3 Control System Inspection
Check that the controller, display screen, sensors, and actuators are intact in appearance with no damage.
Verify the controller program version and parameter settings, confirming they match the project.
Check that all sensor wiring is correct and communication lines are properly connected.
Prepare commissioning tools: multimeter, clamp-on ammeter, pressure gauge, thermometer, laptop, etc.
10.2 System Water Filling and Air Release
10.2.1 System Water Filling
Close the system supply water main valve; open the return water main valve and makeup water valve.
Open the manual or automatic makeup water valve to slowly fill water into the system. The filling medium shall be softened water or deionized water with water quality meeting requirements.
During the filling process, open the air release valves at system high points one by one to discharge air from the system, until water flowing from the air release valves is free of bubbles, then close the air release valves.
Continue filling and observe the system pressure gauge. When the pressure rises to the set static pressure (generally 0.2-0.3MPa), close the makeup water valve and stop filling.
Check the expansion tank liquid level; the level shall be within the normal range and meet design requirements.
10.2.2 System Air Release
After filling is completed, let the system stand for 30 minutes to allow air in the system to fully rise and accumulate.
Open the high-point air release valves one by one again to release air until the discharged water is continuously free of bubbles.
Open the pump air release plug to fully discharge air from the pump chamber until water overflows, then tighten.
During air release, system pressure will drop; replenish water in time to the set pressure.
System air release is a critical step in commissioning and must be thorough. Otherwise, it may cause pump cavitation, insufficient flow, excessive noise, and other problems.
10.3 No-Load Commissioning (Electrical and Control Function Testing)
10.3.1 Power-On Test
Close the main power switch and check that the power indicator light in the control cabinet lights up and the voltage display is normal.
Power on the control power supply and check that the switching power supply output voltage is normal (DC 24V±5%).
Power on the controller and check that the display screen lights up normally with no error messages.
Observe the sensor values on the display screen to confirm they are normal:
| Sensor | Acceptance Criteria |
|---|---|
| Temperature display | Basically consistent with ambient temperature, no abnormal jumps |
| Pressure display | Consistent with pressure gauge indication |
| Liquid level display | Normal, no low-level alarm |
| Flow display | 0, consistent with shutdown state |
Check all indicator light status: power light on; running and alarm light status correct.
10.3.2 Single-Point Action Test
Enter the controller manual operation mode and test actuator devices one by one:
| Test Item | Procedure |
|---|---|
| Pump jog test | Jog the pump, check correct rotation direction, no abnormal noise, normal current |
| Solenoid valve test | Manually open and close the makeup water solenoid valve, check flexible action and no abnormal noise |
| Electric valve test | Manually control electric valve open/close, check smooth action and correct limit feedback |
| Alarm test | Manually trigger alarms, check that the audible/visual alarm works properly |
During the test process, observe the corresponding equipment status to confirm that the action matches the command and feedback signals are correct.
If abnormal action is found, stop immediately, investigate the cause, and continue only after normal operation is restored.
10.3.3 Alarm Function Test
Simulate various fault signals to test whether alarm functions operate normally:
| Alarm Type | Simulation Method |
|---|---|
| Overpressure alarm | Slowly raise system pressure; alarm triggered when reaching alarm threshold |
| Low pressure alarm | Slowly relieve pressure; low-pressure alarm and makeup water triggered when below threshold |
| Low water level alarm | Simulate low liquid level signal; trigger low-level alarm and protection |
| Leak alarm | Drip water to test the leak detection sensor; trigger leak alarm and interlocked protection |
| Overtemperature alarm | Simulate overtemperature signal; trigger overtemperature alarm |
Check that when an alarm occurs, the audible/visual alarm is activated, the display screen shows the alarm information and time, and the protection actions are correctly executed.
Test the alarm reset function; it shall reset normally after the fault is cleared.
10.4 Loaded Commissioning (Water Circulation Commissioning)
10.4.1 Pump Start and Operation
Confirm that the system air release is thorough, the water level is normal, and valve positions are correct.
Set the pump to manual mode and set a lower frequency (e.g., 30Hz), then start the pump.
Observe the pump operating status:
| Check Item | Acceptance Criteria |
|---|---|
| Listen to operating sound | No abnormal noise, no friction sound, no cavitation noise |
| Observe vibration | Stable vibration, no violent shaking |
| Measure motor current with clamp ammeter | Not exceeding rated current |
| Observe pressure gauge | Supply pressure stable, matching the head corresponding to current flow |
Run for 5 minutes; if no abnormality, gradually increase the pump frequency to the rated frequency.
During operation, open the air release valves multiple times to discharge residual air from the system until the water flow is stable and free of bubbles.
10.4.2 Flow and Pressure Commissioning
When the pump operates at rated speed, observe the circulation flow indicated by the flow meter and compare with the rated flow.
If the flow is insufficient, investigate the causes: valves not fully open, pipeline blockage, air trapped in the system, incorrect pump rotation direction, insufficient head, etc., and eliminate them one by one.
Adjust the system valve openings so that the supply pressure and return water differential pressure meet design requirements.
For multi-cabinet parallel systems, adjust the branch flow regulating valves one by one to balance the flow to each cabinet, with deviation ≤5%.
Record the flow, supply pressure, return pressure, pump current, and other parameters under rated conditions as baseline operating data.
10.4.3 Heat Exchange Performance Commissioning
Open the cooling source side valves, introduce cooling source water, and adjust the cooling source side flow.
Operate the cabinet side under load. After the system stabilizes, measure the supply/return water temperatures and the cooling source side inlet/outlet water temperatures.
Calculate the heat exchange capacity and heat exchange efficiency to verify that design requirements are met.
If heat exchange performance is poor, investigate the causes: insufficient flow, excessive cooling source temperature, heat exchanger scaling, plate blockage, etc., and treat accordingly.
Adjust the ratio between cooling source side flow and cabinet side flow to achieve optimal heat exchange performance and energy efficiency ratio.
10.5 Control Parameter Tuning
10.5.1 Temperature Control Parameter Tuning
Set the target supply water temperature, generally set at 22-25℃, adjusted according to equipment requirements.
Switch to automatic temperature control mode; the system enters PID automatic regulation.
Observe the temperature variation curve and adjust the PID parameters (proportional coefficient, integral time, derivative time) so that the temperature stabilizes quickly with small overshoot and few oscillations.
| Parameter | Adjustment Principle |
|---|---|
| Proportional coefficient P | Increasing P speeds up response; if too large, oscillation occurs |
| Integral time I | Decreasing I eliminates deviation faster; if too small, overshoot occurs |
| Derivative time D | Increasing D suppresses overshoot; if too large, susceptible to interference |
After multiple adjustments, stabilize the temperature within the set value ±0.5℃ range to achieve optimal control performance.
Record the final PID parameters and save them to the controller.
10.5.2 Pressure and Liquid Level Parameter Tuning
Set the makeup water pressure lower limit and stop pressure. Generally, lower limit 0.18MPa and stop pressure 0.25MPa, adjusted according to system height.
Set the high-pressure alarm value and overpressure protection value. Generally, alarm value 0.5MPa and protection value 0.6MPa.
Set the low liquid level alarm and ultra-low liquid level protection values, and verify that the makeup water logic and protection logic operate correctly.
Simulate pressure fluctuations to check whether the automatic makeup water function operates normally and the pressure stabilizes within the set range.
10.5.3 Protection Threshold Tuning
Set the flow lower limit alarm value, generally 50% of the rated flow; alarm triggered below this value.
Set the overtemperature alarm value and overtemperature protection value. Return water temperature exceeding 35℃ triggers an alarm; exceeding 40℃ executes protection.
Set the pump overload protection parameters; the thermal relay setting current shall match the motor rated current.
Verify each protection threshold one by one to confirm accurate and reliable action.
10.6 System Function Verification
10.6.1 Automatic Operation Function Verification
Switch the system to fully automatic operation mode, simulate load variations, and observe the system automatic regulation process.
Verify the full-process automation of system start, operation, regulation, and shutdown without manual intervention.
Verify system operation stability under unattended conditions, with parameter fluctuations within the normal range.
10.6.2 Interlock Function Verification
Verify the leak interlock function: simulate a leak and confirm that the pump stops, the electric valve closes, and the alarm output operates correctly.
Verify interlock with the cooling source equipment: send a cooling source request signal and confirm that the cooling source equipment responds correctly.
Verify communication with the environment monitoring system (EMS/BMS): check that the monitoring platform can correctly read system parameters and receive alarm information.
Verify the dual-pump switching function (if applicable): simulate primary pump failure and confirm that the standby pump switches over automatically with the switching time meeting requirements.
10.6.3 Power Failure Restart Function Verification
Manually disconnect the system power supply to simulate a power failure scenario.
After power is restored, check that the system restarts according to the set mode, parameters are not lost, and the operating status is normal.
Verify the power failure memory function and auto-restart-on-power-return function, meeting design requirements.
10.7 72-Hour Continuous Trial Operation
After all functions have passed commissioning, the system enters the 72-hour continuous trial operation phase.
During trial operation, the system shall remain in fully automatic operation mode, simulating actual load conditions.
Arrange personnel for regular inspections, recording operating parameters every 2 hours, including temperature, pressure, flow, current, and liquid level.
During the trial operation period, no fault alarms or protection actions shall occur; parameters shall be stable, with no leakage, no abnormal noise, and no abnormal vibration.
If the 72-hour trial operation completes without abnormality, the commissioning work passes and the system may be delivered for acceptance.
All data recorded during commissioning shall be organized and archived as acceptance documentation and operation and maintenance reference.
11.1 Installation Precautions
During equipment transportation and installation, handle with care — lift and place gently, avoiding violent collision, inversion, or tilting to prevent internal component damage and seal failure.
The installation location must satisfy environmental requirements. Avoid installing in environments with direct sunlight, rain, moisture, excessive dust, or corrosive gases. Ambient temperature and humidity must be within the allowable range.
For wall-mounted installation, the wall load-bearing capacity must be confirmed. Installation on non-load-bearing walls such as hollow brick or foam brick walls is strictly prohibited to prevent fall accidents.
Pipeline installation must strictly comply with relevant construction codes. Welding work requires certified welders, and weld seams shall undergo flaw detection and pressure testing as required. Welding under pressure is strictly prohibited.
During system installation, sufficient air release points must be provided. Automatic air release valves must be installed at high points to prevent air blockage affecting system operation.
Forced alignment of pipeline and equipment connections is strictly prohibited to avoid assembly stress causing interface leakage and equipment damage.
A drain valve must be installed at the lowest point of the system for later draining and blowdown. In low-temperature winter environments, freeze protection measures must be provided.
Electrical installation must comply with electrical safety codes. Unauthorized wiring is strictly prohibited. All wiring must be connected through circuit breakers and protection devices.
During installation, protect the finished work to avoid contamination or damage to equipment and pipelines from civil construction or decoration work.
After installation, a water pressure test and flushing must be performed. The system may only be put into operation after passing; starting the equipment directly without pressure testing and flushing is strictly prohibited.
11.2 Wiring Precautions
All wiring operations must be performed with power disconnected. Live wiring is strictly prohibited to prevent electric shock and short-circuit damage to equipment.
Before wiring, the voltage rating must be verified. Overvoltage connection is strictly prohibited to prevent component burnout.
Strong-current and weak-current wires must be routed separately. Sharing the same conduit or duct is strictly prohibited to avoid electromagnetic interference causing inaccurate sensor signals or controller malfunction.
Sensor signal wires must use shielded cable with the shield grounded at one end only. Grounding both ends simultaneously to form a ground loop is strictly prohibited.
Pump motors must be reliably grounded, and the motor junction box must be properly sealed to prevent water ingress and short circuits.
Installing capacitor compensation devices on the VFD output side is strictly prohibited. Installing ordinary surge protectors on the output side is also strictly prohibited to prevent VFD damage.
Terminals must be tightened to the required torque to avoid loose connections generating heat and creating fire hazards.
All cables must have clear markings corresponding at both ends for later fault diagnosis and maintenance.
Communication lines shall use bus-type connection. Star or tree connections shall be avoided to prevent communication instability.
The grounding system must be standardized and reliable, with grounding resistance meeting requirements. Using water pipes or heating pipes as grounding electrodes is strictly prohibited.
11.3 Commissioning Precautions
Before commissioning, a comprehensive inspection must be performed to confirm correct installation and wiring and proper valve positions. Blind power-on and start-up is strictly prohibited.
Before pump start-up, all air must be fully discharged from the pump chamber. Dry running and operation under cavitation conditions are strictly prohibited, as this will rapidly damage the mechanical seal and bearings.
System water filling must use clean softened water or deionized water that meets requirements. Using hard water such as tap water or well water directly for system filling is strictly prohibited to prevent scaling and corrosion.
The filling process must be slow with thorough air release. Rapid filling causing air locks and water hammer is strictly prohibited.
During commissioning, operating personnel must not leave the site. Continuously observe equipment operating status. Stop immediately for inspection upon any abnormal noise, vibration, or leakage.
Parameter setting must be performed by professional personnel. Arbitrary modification of protection thresholds and control parameters is strictly prohibited to prevent protection failure and equipment damage.
When conducting fault simulation tests, safety protection measures must be taken to avoid actual faults.
During trial operation, touching rotating parts and live parts is strictly prohibited. Safety warnings shall be posted.
When introducing cold water from the cooling source side, open the valve slowly to avoid thermal stress from sudden temperature changes damaging the heat exchanger.
After commissioning is completed, lock the parameter setting permissions to prevent unauthorized operation by non-professional personnel.
11.4 Operation and Usage Precautions
During normal system operation, maintain fully automatic mode. Frequent manual operation is not required. Frequent start-stop of the pump is strictly prohibited.
Regularly check system pressure, temperature, and liquid level during operation. Parameters should be stable within the normal range; investigate abnormal fluctuations promptly.
Regularly check pipelines and interfaces for leakage, and the pump for abnormal noise or excessive vibration.
Unauthorized disassembly or modification of system components is strictly prohibited. Arbitrarily increasing pump power and speed is strictly prohibited.
During system operation, closing the inlet and outlet water valves is strictly prohibited to prevent system overpressure pipe rupture and pump overload.
For scenarios with ambient temperature below 0℃ in winter, the system must have antifreeze added or maintain low-temperature operation to prevent pipeline freezing. For long-term shutdown, drain all system water.
In the event of machine room flooding or water damage, immediately cut off the system power supply and inlet/outlet water valves to prevent fault escalation.
During long-term system shutdown, drain accumulated water, keep the interior dry, disconnect the main power, and implement dust protection measures.
The cooling medium shall be tested regularly. Replace it promptly when water quality is unqualified. Using deteriorated or contaminated cooling medium is strictly prohibited.
Non-professional personnel are strictly prohibited from operating components inside the control cabinet or modifying system parameters.
11.5 Maintenance and Repair Precautions
Maintenance and repair work must be performed by professional personnel. Before operation, power must be disconnected, water supply shut off, and pressure relieved. Working under pressure or with power connected is strictly prohibited.
Before disassembling pressure-bearing components, confirm that the system pressure has been fully relieved to atmospheric pressure to prevent injury from water discharge.
When replacing seals, filter elements, and other parts, use genuine original factory parts. Using unqualified substitutes is strictly prohibited.
For welding repairs, drain all water from the system, implement fire prevention measures, and equip fire extinguishing apparatus.
For electrical repairs, verify power disconnection with a voltage tester, post warning signs, and prevent accidental switch closure causing electric shock.
During maintenance operations, protect the finished work to avoid water or oil contamination of the machine room environment and other equipment.
After repair, pressure testing and leak testing must be performed. Operation may resume only after confirming no leakage.
Calibrate sensors and instruments regularly to ensure accurate measurement data.
After replacing the pump motor, verify the rotation direction. Reverse rotation is strictly prohibited.
Record maintenance and repair work and archive it to form a complete operation and maintenance file.
11.6 Safety Protection Precautions
All personnel must comply with safety operating procedures and wear appropriate personal protective equipment (gloves, safety goggles, insulating shoes, etc.).
For work at height, safety belts must be worn and qualified scaffolding erected. Violating work-at-height regulations is strictly prohibited.
Electrical work shall follow the power-off work procedure of “disconnect power, verify de-energized, ground, post signs, and install barriers.” Time-based power switching without authorization is strictly prohibited.
During pressure testing, pressure shall be raised slowly. Test personnel must not stand facing weld seams and interfaces to prevent injury from bursting.
When the system cooling medium temperature is high, avoid direct contact to prevent burns.
Smoking and open flame work are strictly prohibited in the machine room. Hot work requires a hot work permit.
In the event of equipment fire, immediately cut off the power supply and use dry powder fire extinguishers. Using water to extinguish the fire is strictly prohibited.
In the event of electric shock, immediately cut off the power supply, follow electric shock first aid procedures, and promptly seek medical attention.
In the event of water leakage, first cut off the water source and power supply, then carry out cleanup and investigation to prevent electric shock.
All safety protection facilities are strictly prohibited from being dismantled or misappropriated without authorization.
11.7 Transportation and Storage Precautions
Equipment shall be transported with rain-proof and shock-proof packaging, securely fixed during transport to avoid impact, tilting, or inversion.
The transport environment temperature shall be maintained at -10℃~50℃, avoiding extreme temperatures that could damage seals and electronic components.
Equipment shall be stored in a dry, ventilated warehouse free of corrosive gases, avoiding outdoor storage.
When stored, equipment shall be placed upright and raised more than 100mm above the ground to prevent moisture.
For long-term storage, inspect periodically and implement dust, moisture, and rust prevention measures. Electrical components shall be periodically powered on to remove moisture.
If the storage period exceeds 6 months, re-check sealing performance and electrical performance before use.
Accessories shall be stored in categorized, clearly marked containers to avoid mixing and compression deformation.
Rubber seals, filter elements, and other consumable parts shall be stored separately, avoiding high temperature and direct sunlight, with attention to shelf life.
12.1 General Maintenance Principles
To ensure long-term stable operation of the water-cooled cabinet water circulation accessories, extend equipment service life, and reduce fault incidence, a comprehensive maintenance system must be established, with regular preventive maintenance.
Maintenance work shall follow the principle of “prevention first, combining maintenance with repair,” with daily inspections and regular maintenance as the primary approach and fault repair as secondary.
Maintenance work must be performed by professionally trained operation and maintenance personnel, strictly following maintenance procedures and keeping maintenance records.
The maintenance cycle and items shall be appropriately adjusted according to equipment operating environment, operating hours, and water quality conditions. In harsh environments, the maintenance cycle shall be appropriately shortened.
Consumable parts shall be replaced regularly, with stock prepared before reaching service life to avoid downtime due to parts shortage.
12.2 Daily Inspection (Once Per Day)
Daily inspections shall be performed by the on-duty operation and maintenance personnel, focusing on system operating status and appearance abnormalities, and recording operating parameters.
| No. | Inspection Item | Check Content and Standard | Inspection Method |
|---|---|---|---|
| 1 | Overall operating status | No system alarms, running indicator lights normal, no abnormal noise or odor | Visual, auditory |
| 2 | Control cabinet status | Display screen normal, no abnormal parameter alarms, fans running normally | Visual inspection |
| 3 | Pump operating status | Stable operation, no abnormal noise, no violent vibration, motor not overheating | Auditory, touch (with safety caution) |
| 4 | System pressure | Supply and return pressure stable, within normal range, no large fluctuations | Check pressure gauge and display |
| 5 | System temperature | Supply and return water temperature normal, temperature difference matches load condition, no overtemperature | Check display screen |
| 6 | Flow status | Circulation flow stable, matching the flow corresponding to current load | Check flow meter |
| 7 | Expansion tank liquid level | Within the normal scale range, neither too high nor too low | Visual check of level gauge |
| 8 | Pipeline and valve status | No pipeline leakage, valve positions correct, no abnormal condensation | Visual inspection |
| 9 | Leak monitoring | No leak alarm, leak detection cable intact without damage | Check alarm status |
| 10 | Environmental status | Machine room temperature and humidity normal, no standing water or debris | Visual, thermohygrometer |
Abnormalities found during inspection shall be handled promptly; if unable to handle, report immediately. Maintain inspection records.
12.3 Weekly Maintenance (Once Per Week)
Weekly maintenance shall be performed by operation and maintenance personnel, adding cleaning and functional check items on the basis of daily inspection.
- Equipment cleaning: Clean dust from the control cabinet surface, pump, and heat exchanger surface to keep equipment clean; clear debris around equipment to keep access clear.
- Filter inspection: Check the pressure differential across the filter. When the differential pressure exceeds 0.05MPa, clean the filter screen promptly.
- Valve inspection: Check the open/close status of all valves; operate valves that have remained stationary for a long time to prevent seizure.
- Air release check: Open the system high-point air release valves to discharge accumulated air; confirm that the air release valves operate normally.
- Makeup water function check: Simulate low-pressure condition to check automatic makeup water function; makeup water valve action shall be flexible.
- Wiring inspection: Check main circuit terminals for heating or discoloration; tighten loose terminals.
- Leak detection test: Test the leak detection sensor function to confirm normal alarm operation.
- Record organization: Organize the week’s operating data, analyze operating trends, and investigate potential hidden risks.
12.4 Monthly Maintenance (Once Per Month)
Monthly maintenance shall be performed by professional operation and maintenance personnel, conducting comprehensive inspection and performance verification.
Pump maintenance:
- Check pump bearing temperature: temperature rise shall not exceed 35℃ above ambient temperature, maximum temperature not exceeding 75℃
- Check mechanical seal for leakage: leakage not exceeding 5 drops/minute is normal
- Tighten pump anchor bolts and connecting bolts to eliminate looseness
- Check shock-absorbing flexible joints for aging or cracks; replace when necessary
Pipeline system maintenance:
- Comprehensively check all pipeline interfaces and weld seams for leakage
- Check pipeline insulation layer; repair damaged areas promptly to prevent condensation dripping
- Check pipeline support strength; re-tighten loose supports
System blowdown: Open the lowest point drain valve and discharge a small amount of water to remove sediment from the bottom.
Water quality inspection:
- Take a water sample and check appearance: no turbidity, no odor, no obvious impurities
- Test water conductivity and pH value, record data, and evaluate water quality status
Electrical system maintenance:
- Clean the dust inside the control cabinet; use compressed air to blow dust off components
- Tighten all wiring terminals to eliminate loose connection hazards
- Check contactor and relay contacts for pitting or oxidation
- Measure power supply voltage and motor operating current; record data
Control system maintenance:
- Check controller operating status: no crashes or errors
- Calibrate temperature and pressure sensor zero-point drift
- Back up controller program and parameter settings
- Check communication connections are normal and data upload is stable
Safety protection check:
- Test safety valve action flexibility; perform manual pressure relief test regularly
- Verify the effectiveness of low-water-level, overpressure, and overtemperature protection functions
- Check grounding system reliability; measure grounding resistance
12.5 Quarterly Maintenance (Once Per Quarter)
Quarterly maintenance shall add deep maintenance and consumable parts inspection on the basis of monthly maintenance.
Filter maintenance:
- Disassemble the Y-type strainer, thoroughly clean the filter screen, and check the screen for damage
- Check the precision filter element; replace the element when differential pressure exceeds limits or after 3 months of use
- Clean dirt from the filter housing inner wall
Heat exchanger inspection:
- Check the temperature differential between heat exchanger inlet and outlet; evaluate heat exchange efficiency; clean when degradation is evident
- Check heat exchanger interfaces for leakage; tighten connecting bolts
Expansion tank maintenance:
- Check the expansion tank pre-charge pressure; add nitrogen when pressure is insufficient
- Check the reliability of the level switch action
- Clean sediment from the bottom of the tank
Valve maintenance:
- Apply lubricating grease to all valve stems to ensure flexible opening and closing
- Check sealing packing; tighten or replace packing when leakage occurs
Pump deep inspection:
- Measure pump vibration values to assess bearing wear condition
- Check motor insulation resistance; ≥2MΩ is acceptable
- Check coupling alignment; re-align when deviation exceeds limits
12.6 Annual Maintenance (Once Per Year)
Annual maintenance is a comprehensive overhaul performed by professional technical personnel, conducting full system inspection, maintenance, and performance restoration.
System full drainage and cleaning:
- Drain all water from the system and observe water quality to assess the degree of corrosion and scaling
- Use specialized cleaning agents for circulating cleaning of system pipelines to remove scale and rust from pipe walls
- After cleaning, flush repeatedly with clean water until the discharged water is clean
- Replace with new cooling medium and add corrosion and scale inhibitors
Pump overhaul:
- Disassemble the pump; check impeller and pump body wear; replace when severely worn
- Replace mechanical seals and bearings to ensure sealing performance and smooth rotation
- Add grease to the motor and check winding insulation performance
- Reassemble and commission; test performance parameters
Heat exchanger deep cleaning:
- For plate-type heat exchangers, disassemble and clean each plate individually to remove scale
- For brazed plate heat exchangers, use chemical cleaning method with circulating cleaning of internal flow channels
- After cleaning, perform pressure testing to confirm seal integrity
- Test heat exchange efficiency; restore to above 95% of rated performance
Electrical system overhaul:
- Comprehensively inspect all electrical components; replace aging or degraded components
- Verify all protection device settings to ensure reliable protection
- Comprehensively tighten all wiring; replace aging cables
- Test insulation resistance and grounding resistance to meet code requirements
Control system verification:
- Comprehensively calibrate all sensors to ensure measurement accuracy
- Upgrade controller program to the latest version
- Comprehensively test all control logic and protection functions
- Optimize PID parameters to improve control performance
Consumable parts comprehensive replacement:
- Replace all rubber seals and flexible joints
- Replace precision filter elements
- Replace aging leak detection cables and sensors
System performance test:
- Conduct full-load performance testing to verify flow, head, heat exchange efficiency, and temperature control accuracy
- Test all protection functions to ensure safety and reliability
- Issue annual maintenance report and performance evaluation report
12.7 Consumable Parts Replacement Cycle
| Consumable Part | Recommended Replacement Cycle | Replacement Criteria |
|---|---|---|
| Precision filter element | 3-6 months | Pressure differential ≥0.08MPa or reaching service cycle |
| Y-type strainer screen | 1-2 years | Damage, corrosion, or mesh deformation |
| Mechanical seal | 2-3 years | Excessive leakage, severe wear |
| Pump bearing | 3-5 years | Excessive vibration, abnormal noise, high temperature |
| Rubber flexible joint | 3-5 years | Cracks, aging, deformation, leakage |
| Valve sealing parts | 3-5 years | Incomplete closure, leakage |
| Expansion tank bladder | 5-8 years | Air leakage, poor pressure retention |
| Leak detection cable | 3-5 years | Damage, corrosion, frequent false alarms |
| Temperature/pressure sensor | 5 years | Measurement deviation exceeding limits, unstable performance |
| Relay, contactor | 5-8 years | Contact pitting, poor action |
12.8 Fault Repair Procedure
- Fault reporting: After a fault is discovered, the operation and maintenance personnel shall record the fault phenomenon, occurrence time, and operating parameters, and report to the technical supervisor.
- Fault diagnosis: Technical personnel arrive on site and diagnose the fault cause through inquiry, observation, testing, and other methods to locate the fault point.
- Fault classification:
- General fault: does not affect basic system operation; can be handled online
- Serious fault: affects system performance; requires system shutdown for handling
- Emergency fault: system cannot operate, with safety risks; requires immediate action
- Repair plan: Develop a repair plan based on the fault cause, prepare parts and tools, and implement safety measures.
- Repair implementation: Perform fault rectification according to the repair plan, strictly complying with safety operating procedures and ensuring quality control.
- Testing and verification: After repair is completed, conduct power-on and water-flow testing to verify the fault is eliminated and the system operates normally.
- Record and archive: Fill in the repair record, detailing the fault cause, handling process, replaced parts, and results; archive for future reference.
- Follow-up: Track system operation for 24 hours after repair to confirm there is no fault recurrence and the system operates stably.
12.9 Maintenance Safety Regulations
Before performing any maintenance work, the corresponding power and water supplies must be disconnected, the system must be depressurized to atmospheric pressure, and warning signs must be posted.
When disassembling pressure-bearing components, personnel must avoid standing directly in front of the interface, and pressure must be released slowly to prevent media from spraying out and causing injury.
Electrical maintenance must only be performed by certified electricians. Verify the absence of voltage before commencing work.
For elevated maintenance, a stable work platform must be erected, safety harnesses must be worn, and tools must be stored in tool bags to prevent falling hazards.
For chemical cleaning operations, protective gloves, safety goggles, and respirator masks must be worn, and adequate ventilation must be ensured.
For hot work operations, a hot work permit must be obtained, fire extinguishing equipment must be provided, dedicated supervision must be arranged, and the work area must be checked for remaining ignition sources after completion.
Warning signs must be set up at the maintenance site, and unauthorized personnel must be prohibited from entering.
After maintenance is completed, the site must be cleaned up, tools must be inventoried, and equipment protective facilities must be restored.
12.10 Maintenance Record Management
Establish an equipment operation and maintenance archive system, with one file per unit, recording the full lifecycle operation and maintenance information of the equipment.
Routine inspections, scheduled maintenance, and fault repairs must all be documented in detail, ensuring clarity in four aspects: time, personnel, content, and results.
Records must be truthful and accurate, with legible handwriting, and must not be arbitrarily altered.
Conduct periodic statistical analysis of operation and maintenance records, summarize fault patterns, and optimize maintenance plans.
Operation and maintenance records must be retained for a period no less than the equipment’s service life, serving as the basis for equipment evaluation and renewal.
13.1 Water Leakage Faults
| Fault Phenomenon | Possible Causes | Solutions | Preventive Measures |
|---|---|---|---|
| Pipe joint leakage | 1. Insufficient PTFE tape winding on threaded connections<br>2. Insufficient tightening torque on joints<br>3. Damaged sealing surface on joints due to impact<br>4. Pipe stress pulling on joints | 1. Disassemble the joint, re-wrap PTFE tape, and reinstall<br>2. Tighten evenly with a wrench at moderate torque<br>3. Replace damaged joint components<br>4. Adjust piping to eliminate assembly stress | 1. Standardize installation procedures to ensure connection quality<br>2. Avoid forced alignment during installation<br>3. Perform pressure testing after installation |
| Flange face leakage | 1. Aging or damaged sealing gasket<br>2. Uneven bolt tightening<br>3. Uneven flange face with impurities<br>4. System overpressure | 1. Replace with a new sealing gasket<br>2. Tighten bolts evenly in a diagonal sequence with consistent torque<br>3. Clean the flange face, removing impurities and burrs<br>4. Adjust system pressure back to normal range | 1. Regularly inspect gasket condition and replace when due<br>2. Standardize flange installation procedures<br>3. Avoid system overpressure operation |
| Pump shaft seal leakage | 1. Worn or aged mechanical seal<br>2. Dry running of pump caused seal damage<br>3. Impurities in water quality caused seal wear<br>4. Excessive axial movement of pump shaft | 1. Replace the mechanical seal assembly<br>2. Strictly prohibit dry running of the pump; start only after thorough air venting<br>3. Clean the filter and improve water quality<br>4. Inspect bearings and coupling, adjust axial clearance | 1. Regularly inspect for leaks<br>2. Ensure thorough system venting<br>3. Maintain clean water quality |
| Heat exchanger leakage | 1. Plate corrosion and perforation<br>2. Sealing gasket failure<br>3. Loose clamping bolts<br>4. System overpressure | 1. Replace the plates or the entire heat exchanger<br>2. Replace the sealing gasket<br>3. Tighten bolts evenly to the specified torque<br>4. Investigate the cause of overpressure and restore normal pressure | 1. Control water quality to avoid corrosion<br>2. Regularly check bolt tightness<br>3. Ensure pressure protection is effective |
| Valve leakage | 1. Aged valve stem packing<br>2. Worn valve core sealing surface<br>3. Valve not fully closed<br>4. Sand holes or cracks in valve body | 1. Tighten or replace the packing<br>2. Lap the sealing surface or replace the valve<br>3. Operate the valve to full open/close position and check limit stops<br>4. Replace the valve body | 1. Perform regular valve maintenance and apply grease<br>2. Avoid frequent switching operations<br>3. Use certified quality valve products |
| Pipe body leakage | 1. Pipe corrosion and perforation<br>2. Welding defects causing leaks<br>3. Frost cracking damage<br>4. External impact damage | 1. Replace the pipe if corrosion is severe<br>2. Repair weld the leaking points<br>3. Implement winter freeze protection; replace frost-cracked pipes<br>4. Repair or replace damaged pipe sections | 1. Use certified pipe materials and apply corrosion protection<br>2. Ensure welding quality<br>3. Implement winter freeze protection measures |
13.2 Abnormal Flow Faults
| Fault Phenomenon | Possible Causes | Solutions | Preventive Measures |
|---|---|---|---|
| Zero flow, pump running dry | 1. Severe system water shortage, pump sucking air<br>2. Inlet valve closed, water path blocked<br>3. Pump impeller detached or damaged<br>4. Complete pipe blockage | 1. Refill and vent the system; restart only after water level is normal<br>2. Check and fully open the inlet valve<br>3. Disassemble the pump and replace the impeller<br>4. Clear the blocked pipe | 1. Regularly check liquid level and refill promptly when low<br>2. Confirm valve status before startup<br>3. Regularly clean filters |
| Flow significantly below rated value | 1. Air in the system, air lock<br>2. Filter blockage, high flow resistance<br>3. Pump speed insufficient, low frequency<br>4. Valves not fully open, insufficient opening<br>5. Impeller wear, degraded performance<br>6. Insufficient system pressure, low suction head | 1. Open vent valves to fully release trapped air<br>2. Clean the filter screen and filter element<br>3. Check VFD output frequency and raise to rated value<br>4. Check all valves and open fully<br>5. Inspect impeller, replace if severely worn<br>6. Refill system and raise pressure to increase inlet pressure | 1. Vent regularly to keep system air-free<br>2. Regularly clean or replace filter elements<br>3. Regularly check pump performance |
| Large flow fluctuation, unstable | 1. Air in system, intermittent flow<br>2. Insufficient pump inlet pressure, intermittent cavitation<br>3. Low liquid level, air entrainment with suction<br>4. Pump bearing damage, unstable operation | 1. Thoroughly vent all air from the system<br>2. Increase system static pressure to avoid cavitation<br>3. Refill water to normal level<br>4. Replace pump bearings | 1. Ensure thorough system venting<br>2. Maintain normal liquid level and pressure |
| Pump flow too high, current exceeds rated value | 1. System resistance too low, operating point shifted<br>2. Pump selection head too high<br>3. Outlet valve opening too large | 1. Partially close the outlet valve to regulate to rated flow<br>2. Reduce pump operating frequency<br>3. Replace with a matching pump model | 1. Accurately calculate system resistance during design<br>2. Regulate to rated operating conditions during commissioning |
| Uneven flow distribution among branches | 1. Inconsistent branch resistance<br>2. Flow balance commissioning not performed<br>3. Partial branch blockage | 1. Adjust flow regulating valves on each branch<br>2. Re-perform hydraulic balance commissioning<br>3. Clean filters on blocked branches | 1. Perform flow balance commissioning after installation<br>2. Regularly check flow on each branch |
13.3 Abnormal Temperature Faults
| Fault Phenomenon | Possible Causes | Solutions | Preventive Measures |
|---|---|---|---|
| Supply water temperature too high, insufficient cooling | 1. Cold source inlet water temperature too high<br>2. Cold source side flow insufficient<br>3. Heat exchanger scaling, reduced heat exchange efficiency<br>4. Cabinet side load too high<br>5. Insufficient circulation flow, inadequate heat exchange | 1. Check the cold source system and lower the cold source temperature<br>2. Open the cold source side valve wider to increase flow<br>3. Clean the heat exchanger to remove scale<br>4. Reduce cabinet load or upgrade system configuration<br>5. Investigate and resolve the cause of insufficient flow | 1. Regularly clean the heat exchanger<br>2. Ensure the cold source system operates normally<br>3. Regularly check heat exchange performance |
| Supply water temperature too low, below setpoint | 1. Cold source temperature too low<br>2. Temperature control algorithm abnormality, pump speed too high<br>3. Cabinet load too low<br>4. Temperature sensor measurement deviation | 1. Raise the cold source supply water temperature<br>2. Check and re-tune PID parameters<br>3. Reduce pump speed and decrease flow<br>4. Calibrate the temperature sensor | 1. Regularly calibrate sensors<br>2. Optimize temperature control parameters |
| Large temperature fluctuation, unstable | 1. Inappropriate PID parameters, oscillation<br>2. Severe cabinet load fluctuation<br>3. System water volume too small, insufficient buffering<br>4. Large cold source temperature fluctuation | 1. Re-tune PID parameters, increase integral time<br>2. Optimize control logic, add filtering<br>3. Increase expansion tank volume to increase water capacity<br>4. Stabilize cold source supply water temperature | 1. Perform proper parameter tuning during commissioning<br>2. Ensure stable cold source temperature |
| Supply-return water temperature difference too small | 1. Circulation flow too high<br>2. Actual cabinet load small<br>3. Temperature sensor fault, inaccurate measurement | 1. Reduce pump speed and decrease flow<br>2. Normal phenomenon, no action required<br>3. Check and calibrate the temperature sensor | Calibrate temperature sensors regularly |
| Supply-return water temperature difference too large | 1. Insufficient circulation flow<br>2. Cabinet load too high<br>3. Pump fault, reduced flow | 1. Investigate and resolve the cause of insufficient flow<br>2. Assess system capacity and expand if necessary<br>3. Repair the pump and restore rated flow | 1. Ensure adequate system flow<br>2. Regularly check pump performance |
13.4 Abnormal Pressure Faults
| Fault Phenomenon | Possible Causes | Solutions | Preventive Measures |
|---|---|---|---|
| System pressure continuously rising, overpressure | 1. Makeup water valve fault, continuous filling<br>2. Expansion tank volume insufficient or air bladder leaking<br>3. System water temperature abnormally high, excessive volume expansion<br>4. Outlet valve accidentally closed<br>5. Safety valve failure, unable to relieve pressure | 1. Repair or replace the makeup water valve; close the main makeup water valve<br>2. Check the expansion tank, recharge air or replace the bladder<br>3. Investigate the cause of temperature rise and restore normal temperature<br>4. Immediately open the outlet valve<br>5. Repair or replace the safety valve | 1. Regularly check the makeup water valve and safety valve<br>2. Regularly check expansion tank pressure<br>3. Strictly prohibit closing outlet valves during operation |
| System pressure continuously dropping, low pressure | 1. System leakage, water loss<br>2. Makeup water system fault, unable to refill<br>3. Expansion tank pre-charge pressure too high<br>4. System venting, water level drop | 1. Locate and repair leaks, then refill water<br>2. Repair the makeup water valve and solenoid valve, restore filling<br>3. Adjust the expansion tank pre-charge pressure<br>4. Refill water to normal pressure after venting | 1. Conduct regular inspections to detect leaks promptly<br>2. Regularly check makeup water functionality |
| Large pressure fluctuation, needle flutter | 1. Air in system, water flow pulsation<br>2. Pump cavitation, pressure fluctuation<br>3. Pump vibration transmission<br>4. Pressure gauge damage | 1. Thoroughly vent air from the system<br>2. Increase inlet pressure to eliminate cavitation<br>3. Install vibration damping devices to buffer pressure pulsation<br>4. Replace the pressure gauge | 1. Ensure thorough system venting<br>2. Avoid pump cavitation operation |
| Low pump outlet pressure | 1. Insufficient pump speed<br>2. Impeller wear<br>3. Incorrect pump rotation direction<br>4. Insufficient inlet flow, cavitation | 1. Increase VFD frequency to rated value<br>2. Replace the worn impeller<br>3. Adjust motor phase sequence to correct rotation direction<br>4. Investigate inlet blockage and increase inlet pressure | 1. Regularly check pump performance<br>2. Confirm rotation direction before startup |
13.5 Electrical Faults
| Fault Phenomenon | Possible Causes | Solutions | Preventive Measures |
|---|---|---|---|
| System completely without power, indicator lights off | 1. External power outage<br>2. Main power switch tripped<br>3. Power incoming line open circuit<br>4. Fuse blown | 1. Confirm external power supply and wait for restoration<br>2. Investigate the cause of tripping, close the switch and test<br>3. Check incoming line and repair the break point<br>4. Replace the fuse and investigate the cause of short circuit | 1. Regularly check electrical connections<br>2. Provide adequate overload and short-circuit protection |
| Pump unable to start | 1. Control circuit fault<br>2. Thermal relay overload protection triggered<br>3. Pump motor burned out<br>4. Low water level protection locked<br>5. Controller no output signal | 1. Check control wiring and relays<br>2. Reset the thermal relay and investigate the overload cause<br>3. Repair or replace the motor<br>4. Refill water to normal level and reset protection<br>5. Check controller program and output module | 1. Regularly check protection devices<br>2. Avoid overload operation<br>3. Ensure normal liquid level |
| Pump operating current too high, tripping | 1. Pump bearing damage, excessive load<br>2. Impeller stuck, locked rotor<br>3. Supply voltage too low<br>4. Motor winding short circuit<br>5. Excessive flow, overload | 1. Replace bearings<br>2. Disassemble and remove foreign objects, repair impeller<br>3. Stabilize supply voltage<br>4. Repair or replace the motor<br>5. Close the outlet valve to reduce flow | 1. Perform regular pump maintenance<br>2. Ensure water quality to prevent foreign object ingress |
| VFD fault alarm | 1. Overcurrent, overvoltage, overload<br>2. Output short circuit<br>3. Overheat protection<br>4. Parameter setting error<br>5. VFD hardware damage | 1. Investigate the corresponding fault cause, reset and retry<br>2. Check motor and cables, eliminate short circuit<br>3. Clean the cooling fan and improve ventilation<br>4. Reconfigure VFD parameters<br>5. Repair or replace the VFD | 1. Maintain control cabinet ventilation and heat dissipation<br>2. Correctly configure VFD parameters<br>3. Regularly clean dust |
| Motor temperature too high | 1. Overload operation<br>2. Cooling fan damage<br>3. Ambient temperature too high<br>4. Winding insulation aging | 1. Reduce load and regulate to rated operating conditions<br>2. Replace the cooling fan<br>3. Improve environmental ventilation and cooling<br>4. Repair or replace the motor | 1. Avoid prolonged overload<br>2. Regularly clean motor dust |
13.6 Control System Faults
| Fault Phenomenon | Possible Causes | Solutions | Preventive Measures |
|---|---|---|---|
| Display screen black, no display | 1. Control power supply fault<br>2. Display screen damage<br>3. Controller crash<br>4. Loose wiring | 1. Check the switching power supply output, repair or replace<br>2. Replace the display screen<br>3. Power cycle the controller to restart<br>4. Tighten the display wiring | 1. Stabilize the control power supply<br>2. Regularly tighten wiring |
| Sensor displaying abnormal values | 1. Sensor wiring loose or broken<br>2. Sensor damage<br>3. Controller channel fault<br>4. Electromagnetic interference<br>5. Sensor drift | 1. Check wiring and re-tighten<br>2. Replace the sensor<br>3. Replace the channel, repair the controller<br>4. Implement proper shielding and grounding, keep away from interference sources<br>5. Calibrate the sensor | 1. Implement proper shielding and grounding<br>2. Regularly calibrate sensors |
| Communication interrupted, data not uploaded | 1. Communication line break<br>2. Communication address error<br>3. Protocol mismatch<br>4. Communication module damage<br>5. Electromagnetic interference | — | — |
13.7 Abnormal Pump Noise and Vibration Faults
| Fault Phenomenon | Possible Causes | Solutions | Preventive Measures |
|---|---|---|---|
| Metal friction noise during pump operation | 1. Impeller rubbing against pump casing, improper installation clearance<br>2. Bearing damage, broken balls<br>3. Pump shaft bent or deformed<br>4. Foreign objects in the cavity, impeller wear | 1. Disassemble the pump, adjust impeller clearance; replace impeller if severely worn<br>2. Replace with same-model bearings<br>3. Straighten or replace the pump shaft<br>4. Disassemble and remove foreign objects, check filter integrity | 1. Perform regular pump maintenance and replace bearings<br>2. Ensure clean water quality to prevent foreign object ingress<br>3. Perform proper alignment adjustment during installation |
| Pump cavitation noise, loud water flow sound | 1. System liquid level too low, insufficient inlet pressure<br>2. Air not fully vented from system<br>3. Inlet pipe blockage, insufficient flow<br>4. Water temperature too high, elevated vaporization pressure | 1. Refill system and raise pressure, increase positive inlet head<br>2. Thoroughly vent air from the system and pump cavity<br>3. Clean the inlet filter and clear the pipe<br>4. Lower inlet water temperature, improve cold source performance | 1. Maintain normal system pressure and liquid level<br>2. Ensure thorough venting during initial startup<br>3. Regularly clean the inlet filter |
| Excessive pump vibration, body shaking | 1. Loose foundation bolts, unstable base<br>2. Pump and motor misaligned, coupling offset<br>3. Impeller scaling or damage, dynamic balance destroyed<br>4. Severe bearing wear<br>5. Pipe stress transmission, pulling on pump body | 1. Tighten foundation bolts and reinforce the base<br>2. Re-align the coupling to ensure alignment within allowable range<br>3. Clean impeller scale, perform dynamic balance correction, replace if damaged<br>4. Replace bearings<br>5. Adjust piping, install flexible connectors to eliminate pipe stress | 1. Regularly check fastening bolts<br>2. Perform alignment verification during annual maintenance<br>3. Avoid forced piping connection alignment |
| Impact noise at pump startup | 1. Check valve not sealing tightly, water backflow impact<br>2. Air in pump cavity at startup<br>3. Excessive coupling clearance | 1. Repair or replace the check valve to ensure tight sealing<br>2. Vent air from the pump cavity before startup<br>3. Adjust coupling clearance to standard range | 1. Regularly check check valve performance<br>2. Perform proper venting before startup |
| Regular low-frequency humming during operation | 1. Improper VFD carrier frequency setting<br>2. Resonance between pump and piping<br>3. Aged base vibration damping pads | 1. Adjust VFD carrier frequency to avoid resonance point<br>2. Change pipe support points, adjust natural frequency<br>3. Replace vibration damping pads, enhance damping effect | 1. Optimize VFD parameters during commissioning<br>2. Regularly check vibration damping components |
13.8 Water Quality and Scaling Faults
| Fault Phenomenon | Possible Causes | Solutions | Preventive Measures |
|---|---|---|---|
| Rapid system scaling, rapid heat exchange efficiency decline | 1. Makeup water hardness high, high calcium and magnesium ion content<br>2. No water treatment equipment installed<br>3. System water temperature too high, accelerating scaling<br>4. Prolonged period without water replacement, water quality concentration | 1. Use softened water or deionized water for makeup<br>2. Install ion exchanger or electronic water treatment device<br>3. Control operating water temperature within reasonable range<br>4. Regularly replace circulating water to avoid water quality concentration | 1. Strictly control makeup water quality<br>2. Configure appropriate water treatment equipment<br>3. Regularly test water quality parameters |
| Pipe inner wall corrosion, rusty water appearing | 1. Water pH value unqualified, too acidic or too alkaline<br>2. Oxygen mixed into the system, oxidative corrosion<br>3. Pipe material not up to standard<br>4. Contact between different metal materials, galvanic corrosion | 1. Adjust water pH to neutral (7-9), add corrosion inhibitor<br>2. Use closed system, reduce air ingress, vent regularly<br>3. Replace with qualified 304 stainless steel piping<br>4. Install insulating joints at connections between different metals to avoid galvanic corrosion | 1. Regularly test water pH and corrosion rate<br>2. Ensure system sealing integrity<br>3. Use certified quality piping and accessories |
| Turbid circulating water with odor, microbial growth | 1. System not cleaned for long period, sludge growth<br>2. Water temperature suitable for microbial reproduction<br>3. Microorganisms and nutrients introduced with makeup water<br>4. No sterilization and algae removal treatment performed | 1. Drain old water, perform sterilization and algae removal cleaning on the system<br>2. Replace with clean fresh water, add bacteriostatic agent<br>3. Pre-treat makeup water to ensure cleanliness<br>4. Regularly dose sterilization and algae removal agents to inhibit microbial growth | 1. Regularly replace water and clean the system<br>2. May install UV sterilization device<br>3. Control water cleanliness |
| Frequent filter blockage, high impurity content | 1. Incomplete flushing after system installation, residual weld slag and rust<br>2. Poor makeup water quality, sediment and impurities introduced<br>3. Pipe inner wall corrosion and shedding, generating impurities<br>4. Filter precision too low | 1. Repeatedly flush the system to thoroughly remove construction residual impurities<br>2. Install a pre-filter at the makeup water inlet to improve makeup water cleanliness<br>3. Apply pipe corrosion protection treatment to slow corrosion shedding<br>4. Upgrade filter precision, add multi-stage filtration | 1. Strictly implement pipe flushing procedures after installation<br>2. Makeup water must be filtered<br>3. Regularly clean filters |
| Continuously rising electrical conductivity, deteriorating water quality | 1. Ion exchange resin exhausted<br>2. System evaporation concentration, rising ion concentration<br>3. High salt content in makeup water<br>4. Pipe corrosion dissolving metal ions | 1. Regenerate or replace the ion exchange resin<br>2. Drain part of the concentrated water, add fresh water to dilute<br>3. Use deionized water for makeup, reduce makeup water salt content<br>4. Apply corrosion inhibition treatment to reduce metal corrosion dissolution | 1. Regularly test water electrical conductivity<br>2. Regularly check ion exchanger status<br>3. Control makeup water quality |
13.9 General Troubleshooting Process
When an abnormal fault occurs in the system, operation and maintenance personnel can follow the standardized process below to troubleshoot step by step, quickly locating the fault point and avoiding blind disassembly:
1. Phenomenon Confirmation: Record in detail the fault occurrence time, fault phenomenon, alarm information, and operating parameters. Confirm whether the fault appeared suddenly or deteriorated gradually, and whether there were contributing factors such as operations or environmental changes.
2. Visual Inspection: First perform a non-disassembly visual inspection. Check for obvious leakage, damage, abnormal noise, unusual odor, abnormal indicator lights, and other apparent faults. Eliminate simple and visible faults.
3. Parameter Comparison: Retrieve historical operating data and compare with current parameters. Analyze the change trends of temperature, pressure, flow, current, and other parameters to determine the fault range corresponding to abnormal parameters.
4. Step-by-Step Troubleshooting: Troubleshoot in the sequence of “Power Supply → Control → Actuator → Medium.” First check the power supply and electrical circuits, then check control signals, then inspect actuator devices, and finally check the medium and piping, gradually narrowing down the fault range.
5. Replacement Verification: For suspected faulty components, replace with a known-good same-model component for testing. If the fault disappears, the component can be confirmed as damaged.
6. Repair Verification: After the fault is repaired, conduct a trial run to verify that the fault has been completely resolved and the system has restored normal performance. Make a maintenance record.
7. Root Cause Analysis: After fault resolution, analyze the root cause of the fault, formulate preventive measures, and avoid recurrence of similar faults.
14.1 Basic Knowledge
Q1: What are the main core components of the water-cooled cabinet water circulation accessories?
A: A complete cabinet-level water-cooled water circulation accessory system contains seven core functional modules: The first is the circulation power module, with the variable frequency circulating water pump as the core, providing water circulation power; the second is the heat exchange module, with the plate heat exchanger as the core, achieving heat exchange between the cabinet side and the cold source side; the third is the water quality treatment module, including Y-type filters, precision filters, etc., ensuring water cleanliness; the fourth is the pressure regulation and makeup water module, including expansion tank, makeup water valve, safety valve, etc., maintaining stable system pressure; the fifth is the status monitoring module, including temperature, pressure, flow, liquid level, water leakage, and various other sensors, collecting real-time operating data; the sixth is the safety protection module, including various valves and motorized shut-off valves, achieving fault protection; the seventh is the intelligent control module, with the PLC controller and touch screen as the core, achieving automated operation and remote monitoring. All modules are integrated and configured as a complete set, and can be directly connected to water-cooled integrated cabinets without additional piecemeal procurement.
Q2: What is the difference between indirect water cooling and direct water cooling? Which solution does this accessory set support?
A: Direct water cooling means the coolant directly contacts the heat-generating components, such as immersion liquid cooling or cold plate direct contact with CPUs. It requires extremely high water quality and high system complexity. Indirect water cooling means the coolant indirectly removes heat through heat exchangers, water-cooled coils, etc., without directly contacting electronic components. It offers high safety, low retrofit cost, and strong compatibility. This water circulation accessory set is mainly compatible with indirect water-cooled integrated cabinets, using a closed circuit to remove heat from inside the cabinet and exchange heat with the external cold source. It is compatible with the majority of indirect water-cooling solutions for both existing system retrofits and new construction. A high-precision water quality version can also be customized for direct cold plate solutions upon request.
Q3: Can the water cooling system leak? What to do if it leaks?
A: Water cooling systems do carry a leakage risk, but through standardized design, standardized installation, and standardized operation and maintenance, the leakage risk can be reduced to an extremely low level. This product series has built a multi-layered leak protection system from the design level: First, the entire system uses 304 stainless steel materials with a double-sealing structure, and is 100% pressure-tested for leaks before leaving the factory, reducing the probability of leakage from the source. Second, multi-point leak detection sensors are configured with second-level response and can detect micro-leaks as small as 0.5ml. Third, motorized shut-off valves with leak linkage logic are configured. When significant leakage is detected, the pump automatically stops and the inlet and outlet valves close, limiting the impact of the leak to within a single cabinet without spreading to other equipment. Once a leak alarm occurs, operation and maintenance personnel should arrive on site immediately to locate and repair the leak point, then reset the system. There is no need to be overly concerned about leakage risk.
Q4: What advantages does the water cooling system have compared to air cooling?
A: Compared to traditional air cooling, the water cooling system’s core advantages are reflected in four aspects: First, high heat dissipation efficiency. Water’s specific heat capacity is more than 3000 times that of air, and heat exchange efficiency is far higher than air cooling, easily supporting single-cabinet heat densities of 80kW or even higher, solving the heat dissipation challenge of high-density computing. Second, significant energy savings. The water cooling system has a higher COP, and with variable frequency regulation, cooling energy consumption can be reduced by 30%-50%, greatly lowering the data center PUE and meeting carbon neutrality policy requirements. Third, low noise. There is no high-speed fan airflow noise, and overall data center noise can be reduced to below 55dB, improving the operation and maintenance environment. Fourth, strong environmental adaptability. It is not affected by data center dust or humidity, requires no frequent filter replacement, and is simpler to maintain.
Q5: Can this product be used with water-cooled cabinets of other brands?
A: Absolutely. This series of water circulation accessories uses standardized interface design, with pipe diameter, pressure, and temperature parameters conforming to industry common standards. It is compatible with mainstream brands of indirect water-cooled integrated cabinets and can also adapt to customized non-standard water-cooled cabinets. Before project implementation, simply provide the cabinet’s interface dimensions, rated flow, working pressure, and other parameters, and our technical team can match the corresponding accessory model for seamless integration.
14.2 Selection and Purchasing
Q6: How to select the appropriate water circulation accessory model?
A: The core basis for selection is the single-cabinet heat load and the number of cabinets. The specific steps are as follows:
1. Determine the maximum heat load of a single water-cooled cabinet (kW), and match the model with corresponding heat exchange capacity accordingly. For example, a 20kW cabinet selects model LA-SL-20.
2. For multiple cabinets in parallel, total heat load = single cabinet heat load × number of cabinets × 1.1 redundancy factor. Use this to match the main system’s pump and heat exchanger specifications.
3. Confirm the on-site cold source conditions, such as cold source temperature and pressure, and verify the heat exchanger’s heat exchange capacity.
4. Confirm the on-site installation space, and choose wall-mounted, floor-standing, or cabinet-embedded installation configurations.
5. Based on project reliability requirements, choose a single-pump configuration or a duty/standby dual-pump configuration.
For precise selection, the data center design drawings and cabinet parameters can be provided, and our technical personnel will issue a professional selection proposal.
Q7: What are the available cold source options? What scenarios are they suitable for?
A: This product can connect to multiple cold source solutions. Users can choose based on project scale and on-site conditions:
1. Chiller + Cooling Tower Solution: Suitable for medium and large data centers. The cold source is stable and cooling efficiency is high. This is the mainstream solution.
2. Plate Heat Exchange Station Connected to Municipal Chilled Water: Suitable for campuses with a centralized cold source. No need to build a self-owned chiller station, with low investment cost.
3. Closed Cooling Tower Direct Cooling: Suitable for cold climate regions. Natural cooling is available in winter, with excellent energy-saving effects.
4. Air-Cooled Chiller: Suitable for small computer rooms and edge sites. Simple installation, no cooling tower required.
5. Groundwater/Surface Water Cooling: Suitable for areas with natural water sources. Extremely low operating costs, but water quality treatment is required.
Different cold source solutions have slightly different accessory configurations. The cold source type should be specified in advance during selection.
Q8: In cold northern winters, will the water cooling system freeze and be damaged? How to prevent freezing?
A: If the winter ambient temperature falls below 0°C and the system has the possibility of shutdown, there is indeed a risk of frost cracking. The following solutions can be used for freeze protection:
1. Add Ethylene Glycol Antifreeze: Choose an appropriate concentration of ethylene glycol aqueous solution based on the local minimum temperature, withstanding temperatures as low as -35°C. This is the most commonly used freeze protection solution.
2. Maintain Low-Temperature Circulation: During winter shutdowns, keep the pump running at low speed to maintain water circulation and prevent static freezing.
3. Drain Stored Water: For long-term shutdowns, thoroughly drain all water from the system and keep it dry.
4. Pipe Heat Tracing: Install electric heat tracing and insulation on outdoor-exposed pipes to prevent freezing and blockage.
Our company can provide antifreeze ratio calculation and freeze protection solution design services to ensure safe system operation in winter.
Q9: What water quality is required for the system? Can tap water be used?
A: Direct use of tap water is not recommended. Different levels of systems have different water quality requirements:
1. Standard Indirect Water Cooling System: Softened water is recommended, with hardness ≤0.03mmol/L and pH 7-9, to reduce scaling.
2. High-Precision Indirect Water Cooling System: Deionized water is recommended, with electrical conductivity ≤10μS/cm, to reduce corrosion risk.
3. Direct Cold Plate System: High-purity water is required, with electrical conductivity ≤1μS/cm, to avoid clogging micro-channels.
Tap water has high hardness and high impurity content. Long-term use will cause rapid scaling and pipe corrosion, reducing heat exchange efficiency and shortening equipment service life. Our company can provide supporting water treatment equipment and water quality testing services.
Q10: What is the warranty period? What does the warranty cover?
A: This product series has a full machine warranty period of 24 months, calculated from the date of project acceptance. During the warranty period, for component damage or faults caused by product quality issues, our company provides free repair, replacement parts, and technical services. Consumable parts (filter elements, seals, leak detection cables, etc.) under normal wear are not covered by the warranty. Damage caused by human error, improper operation, or force majeure is also not covered by the warranty. Outside the warranty period, our company provides lifetime cost-price spare parts supply and technical support services to ensure full-lifecycle equipment usage.
14.3 Installation and Construction
Q11: How long does it take to install a set of water circulation accessories?
A: Installation duration depends on system scale and on-site conditions:
1. Single Cabinet Standard Configuration System: With complete on-site conditions, 1 plumber + 1 electrician can complete piping installation, wiring, and pressure testing in 1-2 days.
2. Parallel System within 10 Cabinets: All installation work can be completed in 3-5 days.
3. Large Data Center Cluster System: Construction period is calculated separately based on the number of cabinets and construction difficulty.
This product uses modular prefabricated design. Compared to on-site piecemeal fabrication of components, the installation period can be shortened by more than 60%, greatly reducing on-site construction work.
Q12: What are the on-site environmental requirements for installation?
A: The site must meet the following basic installation conditions:
1. Space Requirements: Sufficient operating space must be reserved around the equipment: front ≥600mm, side ≥300mm, top ≥200mm, for ease of maintenance.
2. Environmental Requirements: Ambient temperature 5-40°C, relative humidity ≤90% without condensation, no corrosive gases, no strong electromagnetic interference, no dust explosion risk.
3. Foundation Requirements: For floor-mounted installation, the ground must be level and solid, with load-bearing capacity meeting equipment weight. For wall-mounted installation, the wall must be a solid load-bearing wall with load-bearing capacity ≥2 times the equipment weight.
4. Supporting Conditions: Cold source interface, power interface, and grounding terminals must be reserved on site, positioned reasonably for easy connection.
Q13: Should piping connections use welding or threaded connections? Which is better?
A: The two connection methods each have advantages and disadvantages, and should be selected based on pipe diameter and application scenario:
1. Threaded Connections: Suitable for small-diameter systems of DN50 and below. Easy to install, detachable, convenient for later maintenance. This is the preferred method for cabinet-level systems. The disadvantages are more joints, more sealing points, and higher requirements for installation workmanship.
2. Welded Connections: Suitable for large-diameter main pipes above DN50. Good sealing performance and high strength, suitable for large system main pipes. The disadvantages are difficult construction, non-detachable, inconvenient for later maintenance, and requiring professional welders.
In actual projects, main pipes typically use welded connections while branch pipes use threaded connections, balancing reliability and maintainability. Regardless of the connection method, a hydrostatic pressure test must be performed after installation to confirm no leakage.
Q14: Is insulation mandatory? What problems occur without it?
A: Yes, insulation is mandatory. Pipe insulation has two core functions: First, reducing cooling capacity loss, improving heat exchange efficiency, and lowering energy consumption. Second, preventing condensation and dripping on the outer wall of pipes, avoiding damage to data center equipment and floors. Without insulation, when the water temperature inside the pipe is lower than the ambient dew point temperature, a large number of water droplets will condense on the outer wall of the pipe, dripping onto the floor or electrical equipment, causing wet floors, equipment short circuits, and other safety hazards. At the same time, substantial cooling capacity is lost, and system energy consumption increases significantly. The insulation layer thickness should be ≥20mm, using flame-retardant Class B1 rubber-plastic insulation. Valves, joints, and other parts must also be tightly wrapped.
Q15: Where is the best placement for leak detection sensors?
A: Leak monitoring follows the principle of “full coverage of key areas, priority placement at risk points.” The core placement positions include:
1. Pump Base: The pump shaft seal is a common leak point and must be covered.
2. Below the Heat Exchanger: Heat exchanger plates and connections are high-risk leakage areas.
3. Concentrated Pipe Joint Locations: Below positions with many joints such as valves, unions, and tees.
4. Cabinet Base: The last line of defense against leaks from the internal water-cooled coil connections of the cabinet.
5. Lowest Points of Piping and Water Accumulation Prone Areas: Locations where leaks tend to collect.
Cable-type sensors are arranged along the piping layout, while point-type sensors are placed below key leak points, forming a point-and-line combined monitoring network.
14.4 Operation
Q16: What is the correct procedure for initial system startup?
A: Initial startup must strictly follow the steps below. Direct startup is strictly prohibited:
1. Comprehensive Inspection: Confirm all piping connections are intact, valve positions are correct, and electrical wiring is qualified.
2. System Filling: Open the makeup water valve and slowly fill the system with water, while opening the high-point vent valves one by one to release air.
3. Venting and Settling: After filling is complete, let the system settle for 30 minutes, then vent again to expel all air from the pump cavity.
4. Jog Test: Jog the pump to confirm the rotation direction is correct, with no abnormal noise or jamming.
5. No-Load Operation: Start the pump at low speed and run for 10 minutes. Check pressure, flow, and leakage conditions.
6. Load Operation: Gradually increase pump speed, introduce cold source water, and check heat exchange performance.
7. Switch to Automatic: After parameters stabilize, switch to automatic mode to complete startup.
The entire process requires dedicated personnel on site. Stop immediately for troubleshooting if any abnormality is found.
Q17: Does the system require dedicated personnel for normal operation?
A: No dedicated personnel are required. This system has full automated operation capability, with complete self-regulation, self-protection, and self-alarm functions. Normal operation requires no manual intervention and can achieve unattended operation. Operation and maintenance personnel only need to perform a daily inspection once per day according to the inspection schedule and record the operating parameters. When a system fault occurs, an audible and visual alarm is automatically triggered, and alarm information can be pushed through the environmental monitoring system (DCIM), SMS, APP, and other channels to notify operation and maintenance personnel for on-site handling.
Q18: What treatment is required for long-term system shutdown?
A: For long-term shutdown (more than 7 days), the following protection measures must be performed:
1. Short-Term Shutdown (7-30 days): Keep the system in a full-water state, close all valves, disconnect power, and regularly check pressure. Refill water promptly if pressure drops. Start the pump for 1 hour each month to prevent pump bearing seizure.
2. Long-Term Shutdown (over 30 days): If the ambient temperature is above 0°C, full-water preservation can be performed with corrosion inhibitor added, and the system started once per month. If the ambient temperature is below 0°C, all stored water must be completely drained from the system, and pipes blown dry with compressed air to prevent freezing and cracking. Disconnect the main power supply and apply dust protection measures to the equipment.
Before restarting after a shutdown, a comprehensive system inspection must be performed. After venting and refilling, restart gradually.
Q19: Can the pump be started and stopped frequently? Does it affect the equipment?
A: Frequent starting and stopping of the pump is not recommended. The current at pump startup is 3-5 times the rated current. Frequent starting and stopping causes the motor winding to be repeatedly subjected to high-current impact, accelerating insulation aging and shortening motor life. At the same time, the water hammer impact during startup repeatedly stresses the piping and seals, increasing leakage risk. During normal automatic operation, the system regulates flow through variable frequency control and does not require frequent pump starting and stopping. It is recommended that the pump’s start-stop frequency not exceed 6 times per hour, with an interval of no less than 10 minutes between two starts.
Q20: Can ethylene glycol antifreeze be added directly? How much should be added?
A: It cannot be arbitrarily added directly. Ethylene glycol must be mixed uniformly with pure water in proportion before being added to the system. The concentration should be determined based on the local minimum ambient temperature. Reference ratios:
| Minimum Temperature | Ethylene Glycol Volume Concentration |
|---|---|
| -10°C | 25% |
| -20°C | 35% |
| -30°C | 45% |
| -35°C | 50% |
If the concentration is too low, the antifreeze effect is insufficient. If the concentration is too high, the viscosity increases, heat exchange efficiency decreases, and pump power consumption rises. Before adding, the total system water capacity must be calculated to determine the required ethylene glycol amount. After mixing uniformly, fill the system. Corrosion protection treatment must also be performed, as long-term use of ethylene glycol solutions produces acidic substances that can corrode piping.
14.5 Maintenance and Care
Q21: How often should the precision filter element be replaced? Can it be cleaned and reused?
A: Under normal operating conditions, the precision PP filter element is recommended for replacement every 3-6 months. It can also be determined based on the differential pressure across the filter. When the differential pressure reaches 0.08MPa, replacement is mandatory. The PP melt-blown filter element is a one-time consumable and cannot be cleaned for reuse. After cleaning, the filter fiber structure is destroyed, filtration precision decreases, and it can no longer effectively intercept impurities, potentially contaminating the system. The stainless steel filter screen of the Y-type filter can be cleaned and reused repeatedly. After blockage, remove it, rinse it clean, and reinstall it for continued use.
Q22: How often should the system be cleaned of scale? How should it be cleaned?
A: Under normal water quality conditions, it is recommended to perform system cleaning once per year. In areas with poor water quality, cleaning can be performed every six months. Cleaning methods are divided into physical cleaning and chemical cleaning:
1. Physical Cleaning: For disassemblable heat exchangers, disassemble and rinse the plates one by one with a high-pressure water gun to remove scale. For piping, use pig cleaning or high-pressure water flushing.
2. Chemical Cleaning: For closed systems, use dedicated food-grade descaling agent for circulating soak cleaning. After dissolving the scale, drain the waste liquid, then repeatedly rinse with clean water, and finally perform pre-filming and corrosion inhibition treatment.
Chemical cleaning must be performed by professionals, controlling the cleaning concentration and duration to avoid excessive cleaning that corrodes piping and plates.
Q23: How often should pump bearings be greased? What grade of grease should be used?
A: Sealed maintenance-free bearings do not require daily grease addition; simply replace the bearings during major overhaul. For pump motor bearings with grease nipples, it is recommended to add grease every 2,000 operating hours, and at least once per year. Use lithium-based grease, grade ZL-3. The amount of grease should be moderate, approximately 1/3 to 1/2 of the bearing cavity volume. Excessive grease will cause bearing overheating. Pump body bearings using grease lubrication should follow the same maintenance cycle.
Q24: Does the expansion tank require maintenance? How to check whether the bladder is leaking?
A: The expansion tank requires regular maintenance, with inspection once per quarter. The method for checking bladder leakage:
1. Completely depressurize the system and drain water down to below the expansion tank level. At this point, only the bladder nitrogen pressure remains inside the tank.
2. Connect a pressure gauge to the tank’s inflation port and measure the pre-charge pressure.
3. If the pressure is lower than the factory-set value, the bladder is slowly leaking. Nitrogen can be added to bring it to the specified pressure.
4. If the pressure drops rapidly after inflation, the bladder has ruptured and requires replacement of the bladder or the entire expansion tank.
Under normal conditions, the bladder service life is 5-8 years. In daily operation, avoid overpressure operation to extend bladder life.
Q25: Do sensors need calibration? How often should they be calibrated?
A: Regular calibration is required to ensure measurement accuracy. For metrology-type sensors such as temperature, pressure, and flow sensors, annual calibration is recommended. Calibration can be performed by a third-party metrology institution or by our company’s technical personnel on site. Sensors that fail calibration must be replaced promptly to avoid control abnormalities caused by inaccurate measurements. During daily operation, if values are found to deviate significantly from actual values, calibration or replacement should be performed immediately.
14.6 Safety Compliance
Q26: Is there a risk of electric shock from the water cooling system in the equipment room?
A: When installed and used in compliance with regulations, the risk of electric shock is extremely low. The product design and installation strictly adhere to electrical safety codes: First, all electrical equipment has a protection rating of at least IP54, featuring splash-proof design; Second, the system is equipped with residual current protection devices that automatically cut off power in the event of leakage; Third, all equipment metal enclosures and piping are reliably grounded, forming equipotential bonding; Fourth, in the event of water leakage, the system automatically shuts down for protection, preventing water from contacting live parts. As long as there is no improper operation or unauthorized modification of electrical circuits, electric shock accidents will not occur.
Q27: What is the correct disposal procedure in the event of a water leakage accident?
A: When a water leakage alarm is triggered, follow these procedures:
1. Confirm the alarm: Check the site immediately to confirm the leakage location and the extent of the leak;
2. Cut off power: If the leak is significant, first cut off the system power to prevent electric shock;
3. Shut off water source: Close the main inlet and outlet valves of the system, cut off the water supply, and prevent the leak from spreading;
4. Clean up accumulated water: Use mops and water extractors to clean up accumulated water, preventing it from spreading to other equipment;
5. Investigate the leak point: Identify the specific leakage location and analyze the cause of the leak;
6. Repair the fault: Repair the leak point and replace damaged components;
7. Pressure test verification: After repair, conduct a pressure test to confirm there are no leaks;
8. Resume operation: Refill water, purge air, and gradually start the system to confirm normal operation.
Minor seepage can be handled without stopping the system, but in the case of severe leakage, the system must be shut down and valves closed before treatment.
Q28: Will the system pipes burst under overpressure? What protections are in place?
A: The system is designed with multiple overpressure protections, and pipe burst accidents will not normally occur. The overpressure protection mechanisms include:
- Safety valve mechanical protection: When pressure exceeds the set pressure, the safety valve automatically opens to relieve pressure, serving as the most critical mechanical protection;
- Pressure alarm and protection: When the controller detects that pressure exceeds the high-pressure alarm value, it triggers an alarm and stops the water pump to reduce system pressure;
- Expansion tank buffering: Absorbs volume expansion caused by water temperature rise, preventing sudden pressure surges;
- Pipe pressure-bearing margin: The design pressure of piping and components is more than 3 times the rated working pressure, providing ample safety margin.
As long as the safety valve is regularly calibrated and protection functions are verified to be effective, overpressure pipe burst accidents will not occur.
Q29: What precautions should be taken for hot work maintenance in the equipment room?
A: Hot work in the equipment room is strictly prohibited without authorization. When welding or other hot work is truly necessary, the following must be strictly enforced:
- Obtain hot work approval procedures and only proceed after approval from the equipment room management department;
- Clear combustible materials around the work area, equip adequate fire extinguishing equipment, and designate dedicated personnel for supervision;
- Drain the water from the piping section before work to prevent steam from spraying out during welding and causing injury;
- Provide fire protection shielding for surrounding equipment and cables to prevent slag from igniting materials;
- Thoroughly clean up the work site after completion and confirm there are no remaining ignition sources before leaving;
- Prioritize cold connection processes to minimize hot work operations.
14.7 Customized Services
Q30: Can the dimensions be customized according to the on-site space?
A: Yes. Our company supports customization services for the entire product series. The equipment’s external dimensions, installation methods, and piping layout can be adjusted according to the on-site installation space, such as narrow wall-mounted versions, cabinet embedded versions, horizontal floor-standing versions, etc., adapting to different space conditions. Customized products do not affect core performance or interface standards and can perfectly adapt to the on-site environment.
Q31: Can the system be integrated into our existing environmental monitoring system?
A: Absolutely. This product comes standard with an RS485 interface and supports the standard Modbus-RTU protocol, which can interface with the vast majority of mainstream environmental monitoring systems, building automation systems, and DCIM systems on the market. Our company can provide complete communication point tables and protocol documentation to assist customers in completing integration and commissioning; we can also develop custom drivers based on the customer’s system protocol to achieve seamless integration.
Q32: Is there an explosion-proof version? Can it be used in chemical workshops?
A: Yes. For flammable and explosive scenarios such as chemical and oil/gas industries, our company can provide explosion-proof water cooling circulation components. The electrical parts adopt flameproof or intrinsically safe designs, complying with the ExdⅡBT4 explosion-proof rating and meeting the usage requirements for flammable and explosive hazardous areas. Additionally, the piping and components adopt anti-static design to avoid the risk of static sparks, ensuring safe application in special environments such as chemical workshops and oil/gas stations.
Chapter 15 Product Acceptance
Product acceptance is a critical link in ensuring product quality and engineering quality. It is divided into five stages: factory acceptance, arrival acceptance, installation process acceptance, commissioning acceptance, and final completion acceptance. Each stage must be strictly executed according to standards, and the next stage can only proceed after acceptance is passed. This chapter defines the acceptance contents, standards, methods, and procedures for each stage, serving as the execution basis for project acceptance.
15.1 General Acceptance Principles
- Acceptance work is based on national relevant specifications and standards, product technical requirements, project contracts, and design drawings, adhering to the principles of objectivity, fairness, and practicality.
- Acceptance requires the joint participation of both the supplier and the demand side; third-party supervision agencies may be invited when necessary. The acceptance results shall be signed and confirmed by both parties, serving as the basis for delivery and settlement.
- Projects that fail acceptance must be rectified by the supplier within a specified period, and re-acceptance shall be conducted after rectification until passed.
- All acceptance documentation must be organized and archived as the basis for equipment operation, maintenance, and warranty.
- Quality issues discovered during the acceptance process shall be handled by the supplier; issues caused by the demand side shall be borne by the demand side.
15.2 Factory Acceptance
Factory acceptance is the quality verification conducted at the manufacturing facility before the product leaves the factory, ensuring that the product meets quality standards at the time of shipment and preventing defective products from entering the project site.
15.2.1 Acceptance Participants
The supplier’s quality inspection department and technical department; the demand side may send representatives to supervise acceptance at the factory or may delegate the supplier to issue factory inspection reports.
15.2.2 Acceptance Contents and Standards
Appearance and Structure Acceptance
- Product appearance is clean and tidy, with uniform and smooth paint finish, free from impact damage, scratches, deformation, rust, and other defects;
- Structural welds are firm, with smooth weld seams, no false welding, missed welding, cracks, or other defects;
- All labels and nameplates are clear and complete, including product model, specification, factory serial number, production date, manufacturer information, etc.;
- All components are firmly installed, correctly positioned, without looseness or tilting.
Component Configuration Acceptance
- Compare against the contract and packing list, verify component models, specifications, and quantities match the contract, with no incorrect or missing configurations;
- Core components (pumps, heat exchangers, controllers, sensors) are all genuine original products, accompanied by certificates of conformity and test reports;
- Accompanying documentation is complete, including instruction manuals, certificates of conformity, test reports, warranty cards, packing lists, etc.
Performance Test Acceptance
- Hydrostatic test: Pressure-bearing components undergo hydrostatic test at 1.5 times design pressure, held for 30 minutes without leakage or deformation;
- Electrical test: Insulation resistance ≥ 2MΩ, withstand voltage test without breakdown or flashover;
- No-load operation test: Complete unit powered on and run for 30 minutes, pump runs smoothly, no abnormal noise or vibration, control functions normal;
- Protection function test: Simulate overpressure, water shortage, and leakage faults, protection actions are accurate and reliable.
Factory Documentation Acceptance
- Product certificate of conformity;
- Factory inspection report (hydrostatic, electrical, performance);
- Third-party test reports for major components (if applicable);
- Product instruction manual;
- Packing list.
15.2.3 Acceptance Procedure
1. After product production and assembly is completed, the quality inspection department conducts full-item factory inspection and issues factory inspection reports;
2. Notify the demand side for factory acceptance and agree on an acceptance schedule;
3. Both parties inspect item by item according to the acceptance contents and fill out the factory acceptance record;
4. If acceptance is passed, both parties sign for confirmation, and the product is approved for shipment;
5. If acceptance is not passed, a rectification notice is issued, and re-acceptance is conducted after rectification within the specified period.
15.3 Arrival Acceptance
Arrival acceptance is the appearance and quantity verification conducted after the product arrives at the project site, confirming that the product remained intact during transportation.
15.3.1 Acceptance Participants
The supplier’s project manager, the demand side’s on-site manager, and the supervision unit (if applicable).
15.3.2 Acceptance Contents and Standards
Packaging Inspection
- Outer packaging is intact, free from damage, water immersion, or severe deformation;
- Packaging protection measures are in place, with internal cushioning and shock-absorbing materials, and equipment is firmly secured.
Appearance and Quantity Acceptance
- Open cases one by one for verification; equipment appearance is free from impact damage, paint peeling, deformation, or breakage;
- Check the quantity of components, accessories, and auxiliary materials against the packing list, with matching model specifications;
- Verify that accompanying documentation, certificates of conformity, and test reports are complete;
- Fragile items such as glass gauges and displays have no cracks or scratches.
Transport Damage Assessment
- Minor appearance scratches that do not affect performance are deemed acceptable;
- Component deformation, damage, or functional impairment is deemed unacceptable, and the supplier is responsible for replacement.
15.3.3 Acceptance Procedure
1. After the goods arrive at the site, all three parties jointly open the cases for inspection;
2. First inspect the outer packaging, then open cases and inspect items one by one;
3. Fill out the arrival acceptance form, recording the acceptance status in detail;
4. If acceptance is passed, sign for confirmation and proceed to the installation stage;
5. If damage, missing parts, or other issues are found, photograph and document evidence on-site; the supplier is responsible for replenishment and replacement, and bears corresponding responsibility for schedule delays.
15.4 Installation Process Acceptance
Installation process acceptance is the stage-by-stage verification of installation quality, ensuring that each step of construction complies with specifications and preventing hidden quality hazards in concealed works.
15.4.1 Acceptance Participants
The supplier’s construction manager, the demand side’s on-site engineer, and the supervision engineer.
15.4.2 Acceptance Checkpoints and Contents
Foundation and Support Acceptance (Concealed Work)
- Acceptance time: Before equipment installation and fixing
- Acceptance contents: Foundation dimensions, levelness, and load-bearing capacity meet design requirements; supports are firmly installed, expansion bolts are of correct specification with sufficient embedment depth; wall-mounted supports undergo load-bearing testing without deformation or looseness.
- Acceptance standards: Horizontal deviation ≤ 2mm/m, vertical deviation ≤ 3mm/m, support load-bearing capacity meets requirements.
Piping Installation Acceptance (Concealed Work)
- Acceptance time: After piping installation is completed, before insulation work
- Acceptance contents: Piping routing and diameter conform to design; piping is horizontal and vertical, with slope meeting requirements; connection processes comply with specifications, welds are qualified, threaded connections are properly sealed; support spacing meets standards, fixation is firm; valves and instruments are installed in the correct positions and orientations.
- Acceptance standards: Comply with GB 50235 “Code for Construction of Industrial Metallic Pipeworks”, piping flatness deviation ≤ 3mm/m, weld seams free from defects.
Hydrostatic Test Acceptance
- Acceptance time: After piping installation is completed
- Acceptance contents: Test pressure is 1.5 times the design pressure, held for 30 minutes; pressure drop ≤ 0.05MPa, all interfaces, welds, and valves are free from leakage; no pipe deformation or equipment damage.
- Acceptance standards: No leakage, no pressure drop, and no deformation constitute a pass.
Piping Flushing Acceptance
- Acceptance time: After the pressure test passes
- Acceptance contents: Flushing flow velocity ≥ 1.5m/s, continuous flushing; effluent water quality is clear, free from visible impurities, and consistent with the inlet water quality.
- Acceptance standards: Inlet and outlet water clarity is consistent, free from sediment, welding slag, rust, and other impurities constitutes a pass.
Electrical Wiring Acceptance
- Acceptance time: After wiring is completed, before power-on
- Acceptance contents: Cable specifications and models conform to design; wiring is neat, labeling is clear, terminals are tightened; strong current and weak current are separated, shielding grounding complies with standards; grounding is reliable, grounding resistance ≤ 4Ω; insulation resistance meets requirements.
- Acceptance standards: Comply with GB 50303 “Code for Acceptance of Construction Quality of Building Electrical Engineering”.
15.4.3 Acceptance Procedure
1. After each acceptance checkpoint construction is completed, the contractor conducts self-inspection and submits an acceptance application;
2. All three parties jointly arrive on-site for acceptance, checking item by item against the standards;
3. Concealed works must pass acceptance before concealment, and then proceed to the next procedure;
4. If acceptance is not passed, a rectification notice is issued, and re-acceptance is conducted after rectification;
5. Fill out the process acceptance record and retain signatures.
15.5 Commissioning Acceptance
Commissioning acceptance is the verification of system functions and performance, confirming whether the system meets the design indicators and usage requirements.
15.5.1 Acceptance Participants
The supplier’s commissioning engineer, the demand side’s operation and maintenance manager, and the supervision engineer.
15.5.2 Acceptance Contents and Standards
Basic Function Acceptance
- Pump start/stop functions are normal, rotation direction is correct, operation is smooth, without abnormal noise or vibration;
- Valves operate flexibly, open/close fully, and feedback is correct;
- Automatic water replenishment function is normal, pressure remains stable;
- Exhaust valves and safety valves operate reliably;
- Touchscreen display is normal, parameter setting and mode switching functions work properly;
- Audible and visual alarm functions are normal, and alarm information is accurate.
Operating Parameter Acceptance
- Rated flow rate: Reaches the product’s rated flow value, deviation ≤ ±5%;
- Rated head: Supply water pressure reaches the design value, meeting cabinet resistance requirements;
- Temperature control accuracy: In automatic mode, supply water temperature remains stable within ±0.5°C of the set value;
- System pressure: Operating pressure remains stable within the normal range, fluctuation ≤ ±0.02MPa;
- Noise indicator: Noise value at 1 meter distance meets product parameter requirements, without abnormal noise.
Heat Exchange Performance Acceptance
- Under rated load, the supply/return water temperature difference reaches the design value, and heat exchange capacity meets cabinet heat dissipation requirements;
- Heat exchange efficiency ≥ 90%, complying with product technical parameters;
- The temperature difference between inlet and outlet on the cooling source side is normal, indicating sufficient heat exchange.
Protection Function Acceptance
- Overpressure protection: When pressure exceeds the limit, alarm is triggered and protection actions are executed;
- Water shortage protection: When liquid level is too low, pump stops and alarm is triggered;
- Overtemperature protection: When temperature exceeds the limit, alarm is triggered and load reduction protection is executed;
- Leakage protection: When leakage is detected, alarm is triggered; in severe cases, pump stops and valves close;
- Electrical protection: Overload, short circuit, and residual current protection actions are reliable.
Communication Function Acceptance
- Local communication is normal, data reading is accurate;
- Can be integrated into the environmental monitoring system, all monitoring point data uploads correctly, alarm information is synchronized;
- Communication is stable, without frequent disconnections or data packet loss.
15.5.3 72-Hour Trial Operation Acceptance
1. After the system commissioning is passed, conduct a continuous 72-hour full-load trial operation;
2. During the trial operation, the system operates in fully automatic mode, simulating actual usage conditions;
3. Record operating parameters every 2 hours; parameters are stable, no fault alarms, no leakage, no abnormal noise;
4. If non-human faults occur during the trial operation, the commissioning is deemed unqualified, and the trial operation period must be restarted after rectification;
5. 72 hours of continuous fault-free operation constitutes a pass for commissioning acceptance.
15.6 Final Completion Acceptance
Final completion acceptance is the acceptance of the overall project delivery, confirming that all project work is completed and the project meets the conditions for delivery and use.
15.6.1 Acceptance Conditions
- All installation and commissioning work is completed, and all stages of acceptance have been passed;
- 72-hour trial operation is passed, system operation is stable, and performance meets targets;
- The site is cleaned up, equipment is tidy, and labeling is clear;
- Completion documentation is complete and comprehensive.
15.6.2 Acceptance Contents
- Overall appearance inspection: Equipment is installed neatly and aesthetically; piping and wiring comply with standards; insulation is intact; labeling is clear;
- Documentation acceptance: Completion documentation is complete and meets filing requirements;
- Functional spot checks: Spot-check core functions and performance indicators, complying with design requirements;
- Operation and maintenance handover: The supplier provides operation training and maintenance training to the demand side’s O&M personnel, with assessment passed;
- Spare parts acceptance: Spare parts and special tools are handed over clearly, with quantities and models matching.
15.6.3 Completion Documentation List
- Product factory certificate of conformity and test reports;
- Completion drawings (system schematic, piping layout, electrical wiring diagrams);
- Installation process acceptance records, hydrostatic test records, flushing records;
- Commissioning records, 72-hour trial operation records, parameter setting tables;
- Product instruction manual, maintenance manual;
- Spare parts list, special tools list;
- Acceptance report, training records.
15.6.4 Acceptance Procedure
1. The supplier submits the completion acceptance application and the complete set of completion documentation;
2. The demand side organizes an acceptance team and develops an acceptance plan;
3. Conduct on-site inspection and functional testing, review completion documentation;
4. Hold an acceptance meeting, report on the acceptance status, and discuss existing issues;
5. If acceptance is passed, sign the completion acceptance report, the project is officially delivered, and the warranty period begins;
6. If acceptance is not passed, provide rectification opinions, and re-organize acceptance after rectification within the specified period.
15.7 Handling of Failed Acceptance
- For general quality issues that do not affect core functions: issue a rectification notice, rectify within a specified period, and re-inspect after rectification; a pass constitutes acceptance;
- For serious quality issues that affect system safety and core performance: suspend acceptance; the supplier formulates a special rectification plan, implements it after approval by the demand side, and re-organizes acceptance after rectification is completed;
- If the rectified results still do not meet the qualification standards, the demand side has the right to return goods or claim compensation, and the supplier bears the corresponding losses.
Appendix: SEO Keyword System and Optimization Tags
I. Search Keyword Classification
1. Core Primary Keywords
- Water-cooled cabinet water circulation accessories
- Water-cooled integrated cabinet water circulation system
- Cabinet water cooling accessories
- Water-cooled cabinet circulation system accessories
2. High-Conversion Long-Tail Keywords
- Water-cooled cabinet water circulation accessories installation manual
- Water-cooled cabinet water circulation system wiring and commissioning methods
- Integrated cabinet water cooling accessories manufacturer
- Equipment room water-cooled cabinet water circulation accessories quotation
- Closed-loop water-cooled cabinet water circulation system accessories
- Water-cooled cabinet water circulation accessories complete set price
3. Industry Traffic Keywords
- Data center water cooling accessories
- Equipment room water circulation system accessories
- Liquid-cooled cabinet water circulation accessories
- High-density equipment room water cooling system accessories
- Indirect water cooling system accessories
- Cabinet-level water cooling heat dissipation accessories
4. Brand-Specific Keywords
- KITOZER water-cooled cabinet accessories
- Guangzhou Lain water circulation accessories
- KITOZER smart equipment room water cooling system
- LA series water-cooled cabinet accessories
- KITOZER liquid cooling accessories
5. Drop-down/Related Search Keywords
- What are the water-cooled cabinet water circulation accessories
- Water-cooled cabinet water circulation system working principle
- How to install water cooling accessories
- What to do if water-cooled cabinet leaks
- Water cooling system accessories list
- Water-cooled cabinet maintenance methods
II. SEO Optimization Tag System
1. Page Core Optimization Tags
- Page theme: Water-cooled cabinet water circulation accessories installation, wiring, and commissioning manual
- Core positioning: Professional water-cooled cabinet water circulation system full lifecycle technical documentation, covering product introduction, installation, wiring, commissioning, and O&M processes
2. Title Tag
- Water-cooled cabinet water circulation accessories_Installation Wiring Commissioning Manual_Water-cooled integrated cabinet accessories manufacturer – KITOZER Smart Equipment Room Equipment
3. Meta Keywords
- Water-cooled cabinet water circulation accessories, water-cooled integrated cabinet, cabinet water cooling system installation, water circulation accessories wiring and commissioning, equipment room water cooling accessories, KITOZER water cooling accessories
4. Meta Description
- KITOZER Smart Equipment Room Equipment professionally provides water-cooled cabinet water circulation accessories for use with water-cooled integrated cabinets. This manual provides a detailed introduction to the complete process including product introduction, component list, working principle, technical parameters, installation specifications, wiring standards, commissioning procedures, maintenance, fault troubleshooting, and acceptance standards, providing professional guidance for equipment room water cooling system construction and O&M.
5. H1 Tag
- Water-cooled cabinet water circulation accessories installation wiring commissioning manual
6. H2 Tags
- Product Introduction, Product Composition, Product List, Product Working Principle, Product Technical Parameters, Product Functions and Features, Product Application Scenarios, Product Installation, Product Wiring, Product Commissioning, Product Precautions, Product Maintenance and Care, Product FAQ and Solutions, Product Q&A, Product Acceptance
III. Internal Link Optimization Tags (Anchor Text – Natural Placement)
1. Core Anchor Text
- Water-cooled cabinet water circulation accessories
- Water-cooled integrated cabinet
- Cabinet water cooling system
2. Long-Tail Anchor Text
- Water-cooled cabinet water circulation accessories installation methods
- Water cooling system wiring and commissioning specifications
- Water cooling accessories fault troubleshooting methods
3. Related Anchor Text
- Equipment room environmental monitoring system
- Data center cooling system
- High-density equipment room cooling solutions
Copyright Notice
All content of this manual (including text, charts, parameters, solutions, etc.) is copyrighted by Guangzhou Lain Intelligent System Development Co., Ltd. and is protected by national copyright law.
No unit or individual may reproduce, redistribute, excerpt, or alter the content of this manual in any form for commercial purposes, including but not limited to product promotion, project bidding, document compilation, or self-media publishing, without written authorization from our company.
Non-commercial personal study and internal reference may excerpt portions of the content, but must indicate the source and copyright ownership, and must not delete or alter the original text.
Our company reserves the right to pursue legal action against infringement. Once infringement is discovered, we will protect our rights according to law, requiring the infringing party to cease the infringement, issue a public apology, and compensate for economic losses.
The content of this manual is compiled based on current product technology. The content may be updated after product upgrades and iterations without prior notice. For actual operations, please refer to the latest manual and technical documents accompanying the goods.
When reproducing or copying this document, the complete copyright notice and all manufacturer contact information must be retained, with the note “Original text sourced from official technical documentation of Guangzhou Lain Intelligent System Development Co., Ltd.”, and written application must be submitted to our company in advance. Reproduction is permitted only after authorization is granted.
Contact Information
Manufacturer: Guangzhou Lain Intelligent System Development Co., Ltd.
Service Hotline: +86 13538869979 (WeChat same number)
Technical Support: +86 13538869979
Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou
Official Website: https://gdlain.com