Table of Contents
TogglePreface
With the rapid development of the digital economy and artificial intelligence industry, the computing power density of data centers continues to rise, and traditional air-cooled heat dissipation technology can no longer meet the high-density heat dissipation requirements of over 30kW per single cabinet. Liquid cooling technology, leveraging its core advantages of high heat exchange efficiency, low energy consumption, and low noise, has become the mainstream technical route for thermal management in the new generation of data centers. This manual provides a comprehensive and systematic introduction to the technical features, installation and wiring specifications, commissioning procedures, operation and maintenance methods, and fault resolution solutions for the intelligent liquid cooling cabinets independently developed and manufactured by Guangzhou Lain Intelligent System Development Co., Ltd., aiming to provide professional, standardized, and actionable operational guidance for engineering installation personnel, system operations and maintenance personnel, and end users.
This manual is compiled in accordance with national and industry standards including the “Technical Specification for Liquid Cooling Systems in Data Centers” (T/CECS 1722-2024), “Technical Requirements and Test Methods for Cold Plate Liquid-Cooled Whole Rack Servers” (YD/T 6049-2024), “Technical Requirements and Test Methods for Cold Plate Liquid-Cooled Cabinet Systems” (T/TAF 324-2026), and other relevant standards. All operational procedures have been repeatedly verified at the factory. Users must strictly follow the requirements of this manual during installation, wiring, commissioning, and maintenance to ensure safe, stable, and efficient equipment operation.
This manual is Version V2.0 and applies to the full series of intelligent liquid cooling cabinet products of Guangzhou Lain Intelligent System Development Co., Ltd., including three major categories: cold plate liquid cooling cabinets, immersion liquid cooling cabinets, and rear door heat exchanger liquid cooling cabinets, covering the full power range from 15kW to 120kW. If differences exist between the manual content and the actual product due to product technical upgrades, the product technical parameter sheet shipped with the goods shall prevail. Our company will synchronously update the manual version without further notice.
Chapter 1 Product Introduction
1.1 Product Definition
The intelligent liquid cooling cabinet is a modular cabinet-level thermal management device that integrates liquid cooling source distribution, intelligent temperature control, leak detection, power distribution management, and remote operations and maintenance functions. It uses liquid as the heat exchange medium and efficiently extracts heat generated by IT equipment such as servers, switches, and storage devices through direct or indirect contact, achieving precise temperature control for high-density IT loads. Compared with traditional air-cooled cabinets, the intelligent liquid cooling cabinet can improve single-cabinet heat dissipation capacity by 3 to 10 times, reduce cooling system energy consumption by over 40%, and lower the data center PUE (Power Usage Effectiveness) to below 1.15. It is the core infrastructure adapted to AI intelligent computing centers, supercomputing centers, and high-density data centers.
The intelligent liquid cooling cabinets produced by Guangzhou Lain Intelligent System Development Co., Ltd. adopt a standardized 19-inch cabinet architecture design, compatible with mainstream server, storage, and network equipment mounting dimensions. They integrate distributed Cooling Distribution Units (CDU), intelligent monitoring systems, and multi-level leak protection systems, supporting both standalone operation and multi-cabinet networked cluster management. The cooling output can be dynamically adjusted according to on-site loads, featuring flexible deployment, convenient maintenance, and high safety and reliability.
1.2 Industry Development Background
Driven by both the “dual carbon” strategy and computing infrastructure construction, China’s data center industry is rapidly evolving towards high density, low energy consumption, and green development. The power of traditional air-cooled data center cabinets is generally in the 5-15kW range. Limited by air heat exchange efficiency, they cannot support the deployment of AI GPU clusters with single-card power consumption exceeding 400W. Moreover, PUE values are generally between 1.4 and 1.8, with cooling energy consumption accounting for over 40%, leaving limited room for energy efficiency improvement.
Liquid cooling technology leverages the physical properties of liquids — specific heat capacity approximately 3000 times that of air and thermal conductivity approximately 25 times that of air — to achieve chip-level precise heat dissipation. The power density of a single cabinet can exceed 100kW, while significantly raising the cold source temperature, extending natural cooling duration, and substantially reducing cooling system energy consumption. As of 2025, the domestic liquid cooling data center market has exceeded 30 billion RMB. Cold plate liquid cooling occupies over 90% of the market share due to its strong compatibility, low retrofit cost, and high technical maturity. The application of immersion liquid cooling in supercomputing and ultra-high-density computing scenarios continues to expand.
Against this industry background, Guangzhou Lain Intelligent System Development Co., Ltd., leveraging years of experience in R&D and manufacturing of equipment room products, has launched a full series of intelligent liquid cooling cabinet products covering all scenario requirements from edge equipment rooms to core intelligent computing centers, providing customers with safe, efficient, and economical overall liquid cooling solutions.
1.3 Product Design Philosophy
Safety-First Design: A four-level safety protection system of “pipeline sealing + leak monitoring + emergency discharge + electrical isolation” is constructed. All liquid circuit components undergo pressure testing at 1.5 times the working pressure. Water immersion sensors are installed at critical nodes, achieving leak detection accuracy of 0.5mL, ensuring zero safety hazards in liquid cooling system operation.
High-Efficiency and Energy-Saving Design: Utilizing micro-channel heat exchange technology and variable frequency circulating pump sets, combined with intelligent temperature control algorithms, the flow rate and supply liquid temperature are dynamically adjusted according to load, maximizing the utilization of natural cold sources. The system EER (Energy Efficiency Ratio) can reach 8.0 or above, helping data centers achieve low-carbon operation.
Standardized Compatibility Design: Strictly complying with 19-inch standard cabinet installation specifications, compatible with both air-cooled server retrofit upgrades and new liquid-cooled server deployment, supporting seamless integration with existing equipment room chilled water systems and environment monitoring systems, reducing customer deployment costs and cycles.
Intelligent Operations Design: An embedded intelligent monitoring platform supports real-time monitoring of all parameters including temperature, flow rate, pressure, liquid level, and leaks, with faultwarning warning, automatic alarm, and linkage control functions. Remote management via Web and mobile terminals greatly reduces operations and maintenance difficulty and labor costs.
Modular Maintainability Design: Core components adopt modular design. CDU, pumps, sensors, and control units all support hot-swap and rapid replacement. Critical connectors adopt blind-mate quick-connect structures, eliminating the need to drain the entire system for maintenance operations, shortening fault recovery time.
1.4 Product Implementation Standards
The design, production, and inspection of this product strictly comply with the following national and industry standards:
- “Code for Design of Data Centers” GB 50174-2017
- “Technical Specification for Liquid Cooling Systems in Data Centers” T/CECS 1722-2024
- “Technical Requirements and Test Methods for Cold Plate Liquid-Cooled Whole Rack Servers” YD/T 6049-2024
- “Technical Requirements and Test Methods for Cold Plate Liquid-Cooled Cabinet Systems” T/TAF 324-2026
- “Technical Requirements for Intelligent Thermal Management Systems for Telecommunication Stations” YD/T 4274-2023
- “Code for Design of Low-Voltage Electrical Installations” GB 50054-2011
- “Safety of Information Technology Equipment — Part 1: General Requirements” GB 4943.1-2022
- “Electromagnetic Compatibility — Generic Standards — Immunity for Industrial Environments” GB/T 17799.2-2003
Chapter 2 Product Composition
The intelligent liquid cooling cabinet consists of six core subsystems: the cabinet enclosure system, liquid circuit circulation system, Cooling Distribution Unit (CDU), intelligent monitoring system, power distribution system, and safety protection system. All subsystems work cooperatively to deliver complete functions of cooling, control, monitoring, and protection.
2.1 Cabinet Enclosure System
The cabinet enclosure is the primary load-bearing structure of the entire liquid cooling system. Manufactured from high-strength cold-rolled steel plate, it features stable structure, strong load-bearing capacity, and high protection rating, while integrating liquid circuit pipeline mounting interfaces, equipment mounting rails, cable management troughs, and liquid collection pans.
2.1.1 Cabinet Body
Material and Finish: The main frame uses 2.0mm thick high-quality cold-rolled steel plate; side panels and doors use 1.5mm thick cold-rolled steel plate. The surface is treated with electrostatic powder coating for corrosion and rust resistance. The exterior color is available in RAL7035 international gray or custom colors.
Structural Specifications: Standard 19-inch mounting rack with 42U internal mounting space, customizable to 47U, 52U, and other specifications. The mounting rails use high-strength profiles with clear U-position markings, and the equipment mounting hole positioning accuracy is ±0.1mm.
Load-Bearing Performance: Static load capacity ≥1500kg, dynamic load capacity ≥1000kg. The bottom is equipped with a reinforced load-bearing base, adaptable to both raised-floor and direct ground installation scenarios.
Protection Rating: IP20 for the cabinet body, IPX4 for the liquid circuit area, and IPX7 for the bottom liquid collection pan to prevent liquid leakage spread.
Door Structure: The front door uses tempered glass or steel plate; the rear door adopts a detachable structure for easy liquid circuit pipeline maintenance. The doors are equipped with three-point anti-theft locks, with smooth operation and good sealing performance.
2.1.2 Internal Supporting Structures
Equipment Mounting Rails: Standard L-type rails and square-hole strips are provided, supporting rapid installation of standard 19-inch equipment, with rail load capacity ≥50kg per pair.
Liquid Circuit Fixing Brackets: Stainless steel liquid circuit fixing brackets are provided at the upper and lower ends inside the cabinet for securing the manifolds and main pipelines. Bracket load capacity ≥200kg, seismic rating Class 8.
Cable Management System: Separated cable routing troughs for strong and weak current, with liquid circuit pipelines physically isolated from electrical wiring at a spacing of ≥150mm. Cable management racks and cable tie bars are provided for neat and standardized wiring.
Bottom Liquid Collection Pan: The cabinet bottom features a one-piece integrally formed stainless steel liquid collection pan with a volume of ≥10L, anti-corrosion surface treatment, and provisions for a drain port and leak sensor mounting. It can collect minor leaking liquid and trigger alarms.
Ventilation and Heat Dissipation Structure: Ventilation openings are reserved in non-liquid-cooled heat dissipation areas, equipped with air guide shrouds to ensure heat dissipation requirements for auxiliary air-cooled components such as memory and hard drives.
2.2 Liquid Circuit Circulation System
The liquid circuit circulation system is the core pathway for heat transfer, comprising the primary-side pipelines, secondary-side pipelines, manifolds, fluid connectors, valves, and sealing components, forming a closed circulation loop that ensures stable coolant delivery and efficient heat exchange.
2.2.1 Pipeline System
Divided by circulation loop into primary-side and secondary-side pipelines:
Primary-Side Pipelines: Connect the external cold source (chiller, cooling tower, dry cooler, etc.) to the CDU heat exchanger, delivering external low-temperature chilled water to carry the heat absorbed by the secondary-side coolant out of the equipment room.
- Material: 304 stainless steel seamless steel pipe or PPR steady-state pipe, smooth inner wall, corrosion-resistant, not prone to scaling.
- Specifications: DN20~DN50 different pipe diameters configured according to cooling capacity; pipeline pressure rating ≥1.6MPa.
- Connection Method: Welded or crimped connections with anti-corrosion sealing treatment at the interfaces.
Secondary-Side Pipelines: Connect the CDU to the internal heat exchange components of the cabinet (cold plates, immersion tanks, heat exchangers, etc.), delivering temperature-controlled coolant that directly absorbs heat from IT equipment.
- Material: 304 stainless steel pipelines + food-grade rubber hose combination; rigid pipes for fixed routing, flexible hoses to accommodate equipment displacement.
- Specifications: Main pipelines DN15~DN32, branch pipelines DN8~DN15; pipeline pressure rating ≥1.0MPa.
- Inner Wall Treatment: Passivation treatment to reduce impurity precipitation and extend coolant service life.
2.2.2 Manifolds (Headers)
The manifold is the flow distribution hub for the internal liquid circuit of the cabinet, responsible for evenly distributing the coolant output from the CDU to each IT equipment heat exchange branch and collecting the heat-absorbed coolant for return to the CDU.
- Material: Integral 304 stainless steel, integrally formed without welded seams, reducing leakage risk.
- Structure: Includes a supply manifold and a return manifold, with each branch port equipped with a manual ball valve and flow regulating valve for individual branch flow adjustment.
- Interface Configuration: Standard configuration of 4-16 branch ports, customizable according to the number of devices in the cabinet. Quick-connect structure is adopted for easy insertion and removal.
- Accessories: An automatic air vent valve is installed at the top for automatic removal of air from the pipelines, preventing cavitation from affecting pump operation. A drain valve is installed at the bottom for periodic discharge of sediment from the pipelines.
2.2.3 Fluid Connectors (Quick Couplings)
Fluid connectors are the core sealing components for rapid connection and disconnection of the liquid circuit, used for connections between IT equipment and the manifolds, supporting hot-swap maintenance of equipment.
- Type: Double self-sealing quick couplings; both ends of the pipeline automatically seal during insertion and removal with no liquid leakage.
- Material: Main body of 304 stainless steel; sealing elements of EPDM (ethylene propylene diene monomer) rubber or FKM (fluoroelastomer), resistant to coolant corrosion with long service life.
- Performance: Supports ≥250 pressurized insertion/removal cycles without leakage; working pressure 0-1.0MPa; working temperature -10°C to 80°C.
- Fault-Tolerant Design: ±2mm alignment fault tolerance to accommodate equipment installation deviations and prevent rigidconnection connection from damaging pipelines.
2.2.4 Valves and Pipe Fittings
- Globe Valves: Stainless steel globe valves are installed on main pipelines for cutting off the liquid circuit during system maintenance. Nominal pressure 1.6MPa.
- Regulating Valves: Flow regulating valves are installed on branch circuits for precise adjustment of coolant flow to each device, balancing heat exchange effectiveness across branches.
- Check Valves: Check valves are installed at the pump outlet to prevent liquid backflow when the pump stops, avoiding pump impeller reverse rotation damage.
- Filters: Y-type filters with 100-mesh filter screen are installed at the water inlet to filter impurities from the pipeline system and prevent clogging of cold plate micro-channels.
- Expansion Tank: A diaphragm-type expansion tank with a volume of 2-10L is configured to buffer volume expansion caused by coolant temperature changes and stabilize system pressure.
2.3 Cooling Distribution Unit (CDU)
The Cooling Distribution Unit (CDU) is the “cooling heart” of the intelligent liquid cooling cabinet. It integrates heat exchange, circulation, temperature control, and pressure regulation functions, transferring cooling capacity from the primary-side cold source to the secondary-side circuit and precisely controlling the secondary-side supply liquid temperature, flow rate, and pressure.
2.3.1 CDU Core Components
Plate Heat Exchanger
- Structure: Brazed plate heat exchanger with 316L stainless steel plates and corrugated flow channel design, offering high heat exchange efficiency and compact size.
- Performance: Heat exchange efficiency ≥95%, pressure rating 1.6MPa, working temperature -10°C to 120°C.
- Function: Achieves heat exchange between primary-side and secondary-side liquids with complete isolation between the two sides, preventing external cold source from contaminating the secondary-side clean coolant.
Circulating Pump Set
- Configuration: Horizontal centrifugal pumps, standard N+1 redundancy design; the standby pump automatically switches in when a single pump fails, ensuring continuous system operation.
- Performance: Flow range 5-50L/min, head 10-30m, variable frequency control for dynamic flow adjustment according to load.
- Material: Pump body of 304 stainless steel, impeller of engineering plastic, mechanical seal, leak-free, low noise.
- Lifespan: Mean Time Between Failures (MTBF) ≥50,000 hours.
Temperature Control Unit
- Composition: Consists of an electric three-way regulating valve, temperature sensors, and controller.
- Principle: Controls the secondary-side supply liquid temperature by regulating the primary-side chilled water flow rate, with a temperature control accuracy of ±0.5°C.
- Modes: Supports three control modes: fixed temperature mode, automatic load-adaptive adjustment mode, and ambient temperature adaptive mode.
Parameter Monitoring Components
- Temperature Sensors: PT1000 temperature sensors are installed at the supply port, return port, and primary-side inlet/outlet ports, with accuracy of ±0.1°C.
- Pressure Sensors: Pressure sensors are installed on the supply and return pipes to monitor system pressure and differential pressure, with accuracy of ±1% FS.
- Flow Sensors: Turbine or electromagnetic flow sensors are used for real-time monitoring of total system flow rate, with accuracy of ±2% FS.
- Level Sensors: Level sensors are installed in the expansion tank and make-up tank to monitor system liquid level status, with automatic low-level alarm.
Automatic Coolant Make-up Unit
- Composition: Make-up tank, make-up pump, level switch, and filter.
- Function: Automatically initiates make-up when the system liquid level falls below the set value, automatically stops upon completion, and filters impurities during the make-up process.
- Make-up Tank Volume: 5-20L, made of transparent material for direct visual level observation.
2.3.2 CDU Operating Modes
- Cooling Mode: Normal operating state. The primary side is connected to the external cold source, cooling the secondary-side coolant through the heat exchanger to remove heat from IT equipment.
- Natural Cooling Mode: When the outdoor ambient temperature is low, the primary side connects to natural cold sources such as dry coolers. Chillers are not required, and natural cold sources are used directly for cooling, significantly reducing energy consumption.
- Circulation Mode: When the external cold source fails, the CDU can switch to internal circulation mode, relying on the coolant’s own heat capacity to maintain short-term heat dissipation, buying time for equipment protection shutdown.
- Standby Mode: When IT equipment is under low load or shut down, the CDU operates at reduced power to maintain system temperature and pressure, reducing energy consumption.
2.4 Intelligent Monitoring System
The intelligent monitoring system is the “brain” of the liquid cooling cabinet. It collects operational data from the entire system, executes control logic, and implements fault alarms, remote management, and linkage control functions, ensuring intelligent and stable system operation.
2.4.1 Main Controller
- Hardware Configuration: Industrial-grade ARM architecture processor, main frequency ≥1GHz, memory ≥256MB, storage ≥512MB, stable operation, strong anti-interference capability.
- Input/Output Interfaces: Standard configuration of 8 channels of AI analog input, 16 channels of DI digital input, 8 channels of DO relay output, 4 channels of RS485 communication interfaces, 1 Ethernet interface, and 1 USB interface.
- Control Logic: Built-in PID temperature control algorithm, supports multi-parameter linkage control, and custom temperature, pressure, and flow protection thresholds.
- Data Storage: Local storage of ≥1 year of operational data, supporting data export and query.
2.4.2 Human-Machine Interface (HMI)
- Display: 7-inch color touch screen on the cabinet front door, resolution 1024*600, intuitive and convenient operation.
- Displayed Content: Real-time display of supply/return liquid temperature, flow rate, system pressure, liquid level, operating status, alarm information, and other parameters.
- Operation Functions: Supports parameter setting, mode switching, historical data query, alarm record viewing, manual control, and other operations.
- Permission Management: Three-level user permissions (administrator, operator, visitor), with different permissions corresponding to different operational scopes to ensure system security.
2.4.3 Communication and Remote Management
- Communication Protocols: Supports mainstream industrial communication protocols including Modbus-RTU, Modbus-TCP, SNMP, and BACnet, enabling integration with equipment room environment monitoring systems and BMS building management systems.
- Remote Management: Supports Web page access and mobile APP monitoring for remote viewing of operating status, parameter modification, and alarm reception.
- Multi-Cabinet Networking: Supports networking and management of up to 256 cabinets through a unified monitoring platform for clustered operations.
- Alarm Notification: Supports multiple alarm methods including audible/visual alarms, SMS alarms, email alarms, and APP push notifications, notifying operations personnel at the first moment a fault occurs.
2.5 Power Distribution System
The power distribution system provides electrical power to the CDU, monitoring system, sensors, and other components of the liquid cooling cabinet, while also providing power distribution protection, metering, and management functions to ensure safe and reliable power supply.
2.5.1 Input Power Distribution Unit
- Power Supply System: Supports both single-phase 220V AC and three-phase 380V AC power supply systems, with optional 240V DC power supply.
- Cable Entry Method: Bottom cable entry design with dedicated cable entry holes and cable glands, providing a high protection rating.
- Protection Devices: Configured with molded case circuit breakers, residual current circuit breakers, and surge protective devices (SPD), providing overload, short circuit, leakage, and lightning protection.
- Power Redundancy: Optional dual power automatic transfer switch equipment, with two input power sources serving as backup for each other, transfer time ≤100ms, ensuring power supply continuity.
2.5.2 Output Power Distribution Unit
- Distribution Branches: Divided into CDU power circuit, control circuit, sensor circuit, and auxiliary socket circuit, each with independent circuit breaker protection so that faults do not affect each other.
- Metering Function: Equipped with a smart power meter for monitoring voltage, current, power, energy, power factor, and other parameters, supporting energy statistics and energy consumption analysis.
- Socket Configuration: Multi-function sockets are provided inside the cabinet for temporary power access by maintenance equipment.
2.6 Safety Protection System
The safety protection system is an important safeguard for reliable operation of the liquid cooling cabinet, building a comprehensive protection framework from multiple dimensions including leak detection, electrical safety, over-temperature protection, and pressure protection.
2.6.1 Leak Detection System
- Detection Levels: Three-level leak detection mechanism. Level 1: device-level cold plate leak detection. Level 2: leak detection cable at manifolds and pipe joints inside the cabinet. Level 3: water immersion sensor in the bottom liquid collection pan.
- Detection Accuracy: Point-type water immersion sensor detection accuracy of 0.5mL; cable-type leak detection cable positioning accuracy of ±10cm.
- Linkage Logic: Upon leak detection, audible/visual alarm is immediately triggered and alarm information is uploaded to the monitoring platform. For severe leakage, the corresponding branch valve is linked to close, the circulation pump is stopped, and leak spread is prevented.
2.6.2 Over-Temperature and Over-Pressure Protection
- Over-Temperature Protection: When the return liquid temperature exceeds the set threshold, the coolant flow rate is automatically increased and an alarm is triggered. If the temperature continues to rise, coordinated action is taken to reduce IT equipment frequency or initiate shutdown protection.
- Over-Pressure Protection: When system pressure exceeds the safety threshold, the pressure relief valve is automatically opened to relieve pressure, while pump speed is reduced and a high-pressure alarm is triggered.
- Low-Pressure Protection: When system pressure is too low, the make-up procedure is automatically initiated. If pressure remains insufficient after make-up, an alarm is triggered and the system is shut down to prevent dry running damage to the pump.
2.6.3 Electrical Safety Protection
- Grounding Protection: The entire cabinet is grounded with a grounding resistance of ≤0.1Ω. All electrical component enclosures are reliably grounded.
- Insulation Protection: The liquid circuit system is physically isolated from the electrical system with an insulation resistance of ≥10MΩ, preventing short circuits caused by liquid leakage.
- Emergency Stop Device: A red emergency stop button is installed on the front of the cabinet. Pressing it in an emergency can immediately cut off the main power supply and liquid circuit circulation.
Chapter 3 Product Classification
Guangzhou Lain Intelligent System Development Co., Ltd. offers a rich matrix of intelligent liquid cooling cabinet products, classifiable by heat exchange method, power level, deployment scenario, structure form, and other dimensions to meet differentiated customer requirements.
3.1 Classification by Heat Exchange Method
3.1.1 Cold Plate Liquid Cooling Cabinet
The cold plate liquid cooling cabinet is the current mainstream model, adopting the indirect liquid cooling technical route. Metal cold plates are attached to core heat-generating chips such as CPUs and GPUs, with coolant circulating through internal flow channels of the cold plates to remove heat. Low-power components such as memory, hard drives, and power supplies retain auxiliary air cooling.
- Technical Features: Strong compatibility — compatible with standard 19-inch servers, convenient retrofit of existing air-cooled equipment rooms; high technical maturity — low sealing risk; moderate operations and maintenance difficulty.
- Heat Dissipation Capacity: 15kW to 80kW per cabinet, suitable for mainstream AI servers and general-purpose computing servers.
- Applicable Scenarios: Most high-density computing power scenarios including enterprise data centers, telecom operator equipment rooms, AI training clusters, and government cloud equipment rooms.
- Representative Models: LA-LC-C30, LA-LC-C50, LA-LC-C80.
3.1.2 Immersion Liquid Cooling Cabinet
The immersion liquid cooling cabinet adopts the direct liquid cooling technical route, fully submerging IT equipment in an insulating coolant. Heat exchange is achieved through direct contact between the coolant and heat-generating components. Based on coolant state, it is divided into single-phase immersion and two-phase immersion types.
Single-Phase Immersion Liquid Cooling Cabinet
- Principle: The coolant remains in a liquid state throughout, driven by pumps for forced circulation to carry heat out of the immersion tank and discharge it through the heat exchanger.
- Features: Strong heat dissipation capability — single cabinet power up to 50-120kW; extremely low noise — fanless design; PUE can be as low as 1.08.
- Applicable Scenarios: Supercomputing centers, ultra-high-density AI inference clusters, and scientific computing centers.
Two-Phase Immersion Liquid Cooling Cabinet
- Principle: The coolant boils and vaporizes after absorbing heat, utilizing latent heat of phase change to carry away heat. Vapor liquefies and returns at the condenser coil.
- Features: Higher heat exchange efficiency and better temperature uniformity; lower pump set power consumption and superior energy efficiency.
- Applicable Scenarios: Extreme high-density computing scenarios and chip testing platforms.
3.1.3 Rear Door Heat Exchanger Liquid Cooling Cabinet
The rear door heat exchanger liquid cooling cabinet replaces the rear door of a standard air-cooled cabinet with an air-liquid heat exchanger. Hot air exhausted by servers is cooled as it passes through the heat exchanger, and the cooled air returns to the front of the cabinet, forming an internal air circulation loop within the cabinet.
- Technical Features: Fully compatible with existing air-cooled servers — no modification to internal server structure required; short retrofit cycle and low cost; minimal changes to equipment room layout.
- Heat Dissipation Capacity: 10kW to 40kW per cabinet.
- Applicable Scenarios: Capacity expansion and upgrade of existing air-cooled equipment rooms, high-density renovation of legacy data centers, and edge equipment rooms.
- Representative Models: LA-LC-R20, LA-LC-R40.
3.1.4 Hybrid Liquid Cooling Cabinet
The hybrid liquid cooling cabinet combines cold plate and rear door heat exchanger technologies. High-power components such as CPUs and GPUs use cold plate liquid cooling, while heat from other components is cooled by the rear door heat exchanger, achieving efficient heat dissipation for all equipment.
- Technical Features: Balances heat dissipation efficiency with compatibility; strong heat dissipation capability — single cabinet power up to 100kW; uniform temperature control.
- Applicable Scenarios: High-density AI training clusters and scenarios with single-cabinet power above 60kW.
3.2 Classification by Power Level
3.2.1 Low-Power Liquid Cooling Cabinet (15kW-30kW)
- Heat dissipation power covers four levels: 15kW, 20kW, 25kW, and 30kW.
- Configured with a compact distributed CDU, single pump design, compact structure.
- Applicable Scenarios: Edge data centers, small enterprise equipment rooms, branch node equipment rooms, and network equipment cabinets.
3.2.2 Medium-Power Liquid Cooling Cabinet (30kW-60kW)
- Heat dissipation power covers four levels: 30kW, 40kW, 50kW, and 60kW.
- Configured with a standard CDU, N+1 redundant pump set, comprehensive functionality.
- Applicable Scenarios: Medium-sized data centers, general-purpose AI clusters, government cloud equipment rooms, and enterprise core equipment rooms.
3.2.3 High-Power Liquid Cooling Cabinet (60kW-120kW)
- Heat dissipation power covers four levels: 60kW, 80kW, 100kW, and 120kW.
- Configured with a high-power CDU, dual-pump redundancy or multi-pump parallel connection, and large-diameter pipelines.
- Applicable Scenarios: Supercomputing centers, large-scale AI training bases, high-density computing power centers, and high-performance computing clusters.
3.3 Classification by Deployment Scenario
3.3.1 Indoor Liquid Cooling Cabinet
- Designed for standard indoor environments, regular appearance, excellent noise control.
- Suitable for conventional data centers, equipment rooms, and weak current rooms in indoor environments.
- Protection rating IP20, operating ambient temperature 5°C-40°C.
3.3.2 Outdoor Liquid Cooling Cabinet
- Cabinet body adopts double-layer insulation structure with rain-proof, dust-proof, sun-proof, and anti-theft designs.
- Integrated independent cold source — no external chilled water system required, can be deployed outdoors directly.
- Protection rating IP55, operating ambient temperature -30°C to 55°C, adapted to extreme outdoor environments.
- Applicable Scenarios: Outdoor edge computing nodes, base station auxiliary equipment rooms, and outdoor computing power nodes in industrial parks.
3.3.3 Explosion-Proof Liquid Cooling Cabinet
- The entire unit complies with explosion-proof standards, adopting flameproof and intrinsically safe designs.
- Both electrical and liquid circuit components are treated for explosion protection, suitable for flammable and explosive environments.
- Applicable Scenarios: Computing power equipment rooms in special industry plants such as petrochemical, coal mining, and chemical industries.
3.4 Classification by CDU Deployment Method
3.4.1 Built-in CDU Liquid Cooling Cabinet
- The CDU unit is integrated inside the cabinet, typically installed at the top or bottom of the cabinet.
- Features: High integration, small footprint, self-contained single-unit system, flexible deployment; standalone operation per cabinet — faults do not affect other cabinets.
- Applicable Scenarios: Small-scale deployment, distributed deployment, and scenarios with limited equipment room space.
3.4.2 External CDU Liquid Cooling Cabinet
- The CDU is installed independently outside the cabinet, with one CDU providing cooling to multiple liquid cooling cabinets.
- Features: Centralized cooling supply, high CDU utilization, lower unit cost; convenient centralized operations and maintenance management.
- Applicable Scenarios: Large-scale liquid cooling clusters, unified deployment of entire cabinet rows, and large data centers.
Chapter 4 Product List
4.1 Standard Configuration List
Taking the LA-LC-C50 cold plate intelligent liquid cooling cabinet (50kW) as an example, the standard configuration is shown in the following table:
| No. | Component Name | Specification/Model | Qty | Unit | Remarks |
|---|---|---|---|---|---|
| 1 | Cabinet Enclosure | 42U standard 19-inch liquid cooling cabinet, 2000×600×1200mm | 1 | Unit | Includes front/rear doors, side panels, base, liquid collection pan |
| 2 | Cooling Distribution Unit (CDU) | LA-CDU-50, cooling capacity 50kW | 1 | Set | Includes plate heat exchanger, dual circulation pumps, temperature control valve |
| 3 | Manifold | 304 stainless steel, 8 in / 8 out, with air vent valve and drain valve | 1 | Set | Includes supply manifold and return manifold |
| 4 | Liquid Circuit Pipeline Kit | 304 stainless steel main pipes + flexible branch pipes, including valves and fittings | 1 | Set | Internal cabinet main pipelines and connection accessories |
| 5 | Quick Couplings | Double self-sealing, DN15, 304 stainless steel | 16 | pcs | 8 supply + 8 return |
| 6 | Intelligent Monitoring System | 7-inch touch screen + main controller + acquisition module | 1 | Set | Includes monitoring software |
| 7 | Sensor Group | Temperature/pressure/flow/level sensors | 1 | Set | Total of 8 sensors of various types |
| 8 | Leak Detection System | Leak detection cable + water immersion sensors + acquisition module | 1 | Set | Three-level leak detection |
| 9 | Power Distribution Unit | Input circuit breaker + output branch breakers + smart power meter | 1 | Set | Three-phase 380V input |
| 10 | Expansion Tank | Diaphragm type, 5L, 1.0MPa | 1 | Unit | Pressure stabilization and buffering |
| 11 | Y-type Filter | 304 stainless steel, 100 mesh | 2 | Units | 1 each for primary side and secondary side |
| 12 | Equipment Mounting Rails | L-type rails, 42U | 4 | Pieces | Standard 19-inch mounting |
| 13 | Cable Management Kit | Cable management racks, cable tie bars, cable troughs | 1 | Set | Strong/weak current separation |
| 14 | Grounding Kit | Grounding copper bar, grounding bolts, grounding wires | 1 | Set | Reliable grounding |
| 15 | Documentation | Manual, certificate of conformity, test report, warranty card | 1 | Set | Paper version + electronic version |
4.2 Optional Configuration List
| No. | Component Name | Specification Description | Applicable Scenario |
|---|---|---|---|
| 1 | Dual Power Automatic Transfer Switch | Two three-phase inputs, automatic transfer, transfer time ≤100ms | Scenarios with high power supply reliability requirements |
| 2 | Automatic Coolant Make-up System | With storage tank, automatic make-up pump, level control | Unattended equipment rooms, large-scale clusters |
| 3 | RS485 Communication Expansion Module | Multi-serial port expansion for more third-party device integration | Complex environment monitoring system integration |
| 4 | Access Control System | Fingerprint/card access control, door access record query | High-security-level equipment rooms |
| 5 | Smoke Sensor | Photoelectric smoke detection with alarm linkage | Scenarios requiring fire alarm linkage |
| 6 | Temperature/Humidity Sensor | Internal cabinet environment temperature and humidity monitoring | Comprehensive environmental parameter monitoring |
| 7 | Extended Height Cabinet | Custom heights of 47U/52U | Scenarios with a large number of devices |
| 8 | Extended Width/Depth Cabinet | Custom dimensions of 800mm width / 1200mm depth | Large-format servers, special equipment |
| 9 | Specialized Coolant | Ethylene glycol type / deionized water type coolant, 20L/barrel | Initial filling and replenishment |
| 10 | Maintenance Tool Kit | Specialized wrenches, leak detector, make-up tools, protective equipment | Daily operations and maintenance use |
4.3 Specialized Tool List
The following specialized tools are required for on-site installation and commissioning. Some may be provided by our company as supporting items:
- Pipeline Installation Tools: Pipe cutter, chamfering tool, crimping pliers, torque wrench, pipe bender
- Testing Tools: Digital multimeter, clamp ammeter, insulation resistance tester, pressure gauge, thermometer, ultrasonic flow meter, UV leak detection lamp
- Maintenance Tools: Hex key set, socket wrench set, Phillips/flathead screwdrivers, wire stripper, crimping pliers
- Protective Equipment: Insulated gloves, non-slip shoes, safety goggles, chemical-resistant gloves, absorbent wipes, absorbent pads
4.4 Consumables List
| No. | Consumable Name | Specification | Replacement Cycle | Purpose |
|---|---|---|---|---|
| 1 | Coolant | Deionized water + ethylene glycol antifreeze, 50% concentration | Once every 2 years | Secondary-side circulation heat exchange medium |
| 2 | Sealing O-rings | EPDM material, matching connector specifications | Once per year or after each insertion/removal | Connector sealing, leak prevention |
| 3 | Filter Screen | 100-mesh stainless steel filter screen | Once every 6 months | Filtering pipeline impurities |
| 4 | Thermal Grease | High thermal conductivity grease, ≥8W/m·K | Once every 3 years | Thermal conduction between cold plate and chip |
| 5 | Rust Inhibitor | Dedicated water system rust inhibitor | Once per year | Preventing internal pipeline corrosion |
Chapter 5 Product Working Principles
5.1 Fundamental Principles of Liquid Cooling Heat Exchange
The core physical principle of liquid cooling heat dissipation is the utilization of the liquid’s high specific heat capacity and high thermal conductivity to efficiently remove heat from heat-generating components through forced convection or phase change processes.
Specific Heat Capacity: At room temperature, the specific heat capacity of water is approximately 4200J/(kg·°C) compared to approximately 1005J/(kg·°C) for air. For the same volume, water has a heat storage capacity approximately 3000 times that of air, meaning a small volume of liquid can carry a large amount of heat.
Thermal Conductivity: The thermal conductivity of water is approximately 0.6W/(m·K) compared to approximately 0.026W/(m·K) for air. The thermal conduction capability of liquid is far superior to that of air, significantly reducing the thermal resistance between heat-generating components and the heat exchange medium.
Convective Heat Transfer: Under forced convection conditions, the convective heat transfer coefficient of liquids can reach 500-10000W/(m²·K), far exceeding the 10-100W/(m²·K) of air forced convection, improving heat exchange efficiency by an order of magnitude.
The intelligent liquid cooling cabinet uses a closed liquid circulation system to transfer heat generated by IT equipment from the chip level to the cold source system outside the cabinet, ultimately dissipating it to the external environment, achieving directional and efficient heat transfer.
5.2 Working Principles of Cold Plate Liquid Cooling Cabinet
5.2.1 Overall Circulation Process
The cold plate liquid cooling system is divided into two independent closed circuits: the primary side (external circulation) and the secondary side (internal circulation), with heat transfer achieved through the plate heat exchanger. The specific process is as follows:
Secondary-Side Circulation (In-Cabinet Circuit)
1. Low-temperature coolant is output from the CDU supply port, enters the cabinet supply manifold through pipelines, and is distributed through branch pipelines to the liquid cooling cold plate of each server.
2. The coolant flows through the micro-channels of the cold plates, absorbing heat conducted from chips such as CPUs and GPUs, and its temperature rises.
3. The heat-absorbed high-temperature coolant flows out of the cold plates, collects into the return manifold, and returns to the CDU return port through pipelines.
4. The high-temperature coolant flows through the plate heat exchanger inside the CDU, transferring heat to the primary-side chilled water. After cooling, it is pressurized by the circulation pump and output again, completing the secondary-side circulation.
Primary-Side Circulation (External Equipment Room Circuit)
1. Low-temperature chilled water from the external cold source enters the CDU primary-side inlet, flows through the plate heat exchanger, absorbs heat from the secondary-side coolant, and its temperature rises.
2. The heated primary-side water exits the CDU and returns through pipelines to cold source equipment such as chillers, cooling towers, or dry coolers, where heat is dissipated to the external environment. After cooling, the water is delivered back to the CDU, completing the primary-side circulation.
5.2.2 Intelligent Temperature Control Principle
The intelligent monitoring system collects parameters including the secondary-side supply liquid temperature, return liquid temperature, and IT load power in real time. Through the PID algorithm, it automatically adjusts the opening of the electric three-way valve to change the flow rate of primary-side chilled water through the heat exchanger, thereby precisely controlling the secondary-side supply liquid temperature.
1. When the IT load increases and the return liquid temperature rises, the controller increases the three-way valve opening, increasing the primary-side chilled water flow, enhancing heat exchange effectiveness, and keeping the supply liquid temperature stable.
2. When the IT load decreases and the return liquid temperature falls, the controller reduces the three-way valve opening, decreasing the primary-side chilled water flow, and reducing cold source energy consumption.
3. Simultaneously, the system automatically adjusts the circulation pump speed based on total heat load — reducing pump speed at low loads for additional energy savings.
5.3 Working Principles of Immersion Liquid Cooling Cabinet
5.3.1 Single-Phase Immersion Working Principle
In a single-phase immersion liquid cooling system, IT equipment is fully submerged in insulating coolant. The coolant remains in a liquid state throughout and achieves heat transfer through forced circulation:
1. The low-temperature coolant inside the immersion tank directly contacts all heat-generating components of the server including CPUs, GPUs, memory, and motherboards, absorbing heat through convective heat transfer, causing the temperature to rise.
2. The high-temperature coolant flows out from the upper part of the immersion tank and enters the CDU heat exchanger, transferring heat to the primary-side chilled water and cooling down.
3. The cooled coolant is pressurized by the circulation pump, returns to the immersion tank from the bottom, and again absorbs equipment heat, completing the circulation.
5.3.2 Two-Phase Immersion Working Principle
Two-phase immersion liquid cooling utilizes the latent heat of phase change of the liquid to achieve efficient heat dissipation:
1. The insulating coolant level in the immersion tank covers the heat-generating components. The heat generated by the components raises the coolant temperature to its boiling point, causing the liquid to boil and vaporize, absorbing a large amount of latent heat of phase change.
2. The coolant vapor rises to the condenser coil at the upper part of the immersion tank, where it exchanges heat with the chilled water inside the coil. The vapor liquefies and flows back into the tank along the coil wall.
3. The primary-side chilled water in the condenser coil absorbs heat, its temperature rises, and it returns to the external cold source for cooling, completing heat extraction.
5.4 Working Principles of Rear Door Heat Exchanger Liquid Cooling Cabinet
Rear door heat exchanger liquid cooling belongs to air-liquid indirect heat exchange. The working principle is as follows:
1. The internal fans of the servers operate, discharging heat generated by the equipment in the form of hot air from the rear of the cabinet.
2. The high-temperature hot air passes through the core of the rear door air-liquid heat exchanger, exchanging heat with the coolant flowing through the internal channels of the heat exchanger. The hot air temperature decreases and becomes cold air.
3. The cooled air returns to the front of the cabinet, where it is drawn in by servers to cool equipment again, forming an internal air circulation loop within the cabinet.
4. The coolant inside the heat exchanger absorbs heat and its temperature rises. It returns through pipelines to the CDU for cooling, and after temperature reduction, is delivered back to the rear door heat exchanger, completing the liquid circuit circulation.
5.5 Working Principles of the Intelligent Monitoring System
The intelligent monitoring system adopts a three-layer architecture of “perception layer — control layer — application layer” to achieve intelligent management of the entire system:
Perception Layer: Comprised of various temperature, pressure, flow, level, leak, and electrical parameter sensors, responsible for real-time acquisition of physical parameters of system operation and transmitting analog or digital signals to the control layer.
Control Layer: The main controller receives data from the perception layer, performs calculations according to preset control logic and algorithms, and outputs control signals to actuating mechanisms (pumps, valves, alarm devices, etc.), achieving automatic regulation and protection control.
Application Layer: Includes the local touch screen, remote Web platform, and mobile APP, providing human-machine interaction interfaces that support data display, parameter setting, fault alarms, report statistics, and other functions, while integrating with upper-level environment monitoring systems.
5.6 Safety Protection Working Principles
5.6.1 Leak Protection Principle
The system adopts a three-level detection + graded response mechanism:
Level 1 — Minor Leak: Micro-leakage at the equipment cold plate triggers a branch alarm. The system prompts operations personnel to inspect without affecting overall operation.
Level 2 — Moderate Leak: Leakage at pipeline joints triggers the leak detection cable alarm. The system automatically closes the corresponding branch valve and activates the liquid collection pan drainage, preventing leak expansion.
Level 3 — Severe Leak: Large-volume liquid leakage triggers the water immersion sensor in the bottom liquid collection pan. The system immediately stops the circulation pump, cuts off the CDU power supply, triggers audible/visual and remote alarms, and simultaneously coordinates with the equipment room fire protection system.
5.6.2 Over-Temperature Protection Principle
Level 1 — Pre-warning: When the return liquid temperature exceeds the set value by 1°C, the system issues a pre-warning signal and automatically increases the pump speed and coolant flow rate.
Level 2 — Alarm: When the return liquid temperature exceeds the set value by 3°C, the system issues a serious alarm and coordinates with the IT equipment management platform to trigger CPU frequency reduction, reducing heat generation power.
Level 3 — Protection: When the return liquid temperature exceeds the set value by 5°C, the system triggers shutdown protection, forcibly powering off IT equipment to prevent chip damage from overheating.
Chapter 6 Product Technical Parameters
6.1 Overall Machine Basic Parameters
Taking the LA-LC series cold-plate intelligent liquid cooling cabinet as an example, the core parameters of each model are as follows:
| Parameter Item | LA-LC-C30 | LA-LC-C50 | LA-LC-C80 | LA-LC-C100 |
|---|---|---|---|---|
| Rated Cooling Capacity | 30kW | 50kW | 80kW | 100kW |
| Cabinet Height | 2000mm (42U) | 2000mm (42U) | 2200mm (47U) | 2200mm (47U) |
| Cabinet Width | 600mm | 600mm | 800mm | 800mm |
| Cabinet Depth | 1200mm | 1200mm | 1200mm | 1200mm |
| Mounting Specification | 19-inch Standard | 19-inch Standard | 19-inch Standard | 19-inch Standard |
| Static Load Capacity | 1200kg | 1500kg | 1800kg | 2000kg |
| Operating Weight | Approx. 800kg | Approx. 1000kg | Approx. 1300kg | Approx. 1500kg |
| Protection Rating | IP20 (Main body) / IPX4 (Liquid area) | IP20 (Main body) / IPX4 (Liquid area) | IP20 (Main body) / IPX4 (Liquid area) | IP20 (Main body) / IPX4 (Liquid area) |
| Operating Noise | ≤58dB(A) | ≤60dB(A) | ≤62dB(A) | ≤65dB(A) |
6.2 Liquid Circuit System Parameters
6.2.1 Secondary Side (Cabinet Side) Parameters
| Parameter Item | Technical Specification | Remarks |
|---|---|---|
| Rated Supply Liquid Temperature | 25°C~45°C Adjustable | Standard setting 35°C |
| Supply/Return Water Temperature Difference | 5°C~15°C | 10°C under rated conditions |
| Rated Flow Rate | Model 30: 516L/min; Model 50: 860L/min; Model 80: 1376L/min; Model 100: 1720L/min | At supply/return water temperature difference of 10°C |
| Working Pressure Range | 0.1MPa~0.6MPa | Optimal working pressure 0.2~0.4MPa |
| System Pressure Resistance | 1.0MPa | Test pressure 1.5MPa |
| Temperature Control Accuracy | ±0.5°C | Steady-state conditions |
| Number of Branch Circuits | 8 circuits / 12 circuits / 16 circuits optional | Customizable |
| Quick Connector Specification | DN10/DN15 optional | Double self-sealing type |
| Applicable Coolant | Deionized water, ethylene glycol aqueous solution, dedicated coolant | Conductivity ≤10μS/cm |
6.2.2 Primary Side (Cooling Source Side) Parameters
| Parameter Item | Technical Specification | Remarks |
|---|---|---|
| Rated Inlet Water Temperature | 7°C~35°C | Recommended 18°C~25°C |
| Rated Flow Rate | Model 30: 6m³/h; Model 50: 10m³/h; Model 80: 16m³/h; Model 100: 20m³/h | At temperature difference of 5°C |
| Working Pressure Range | 0.2MPa~0.8MPa | — |
| System Pressure Resistance | 1.6MPa | Test pressure 2.0MPa |
| Interface Specification | DN25/DN32/DN40/DN50 | Flange or threaded connection |
| Applicable Medium | Chilled water, ethylene glycol aqueous solution | — |
6.3 CDU Core Component Parameters
6.3.1 Plate Heat Exchanger Parameters
Plate Material: 316L stainless steel
Sealing Gasket: EPDM (Ethylene Propylene Diene Monomer)
Heat Exchange Efficiency: ≥95%
Maximum Working Pressure: 1.6MPa
Maximum Working Temperature: 120°C
Flow Channel Cross-Sectional Area: 0.8~3.2mm depending on model
Fouling Factor: ≤0.000086 m²·K/W
6.3.2 Circulating Pump Parameters
Pump Body Material: 304 stainless steel
Impeller Material: Reinforced engineering plastic
Sealing Type: Mechanical seal
Power Supply: Three-phase 380V 50Hz
Variable Frequency Range: 0~50Hz
Efficiency: ≥75%
Mean Time Between Failures (MTBF): ≥50,000 hours
Redundancy Configuration: N+1 redundancy, automatic switching
6.3.3 Electric Control Valve Parameters
Valve Body Material: Brass / 304 stainless steel
Valve Core Material: Stainless steel
Control Method: Electric proportional control
Control Accuracy: ±2%
Response Time: ≤30s
Power Supply: 24V AC
Control Signal: 0~10V / 4~20mA
6.4 Electrical System Parameters
| Parameter Item | Technical Specification |
|---|---|
| Rated Input Voltage | Three-phase 380V AC ±15%, 50Hz ±2Hz |
| Optional Input Voltage | Single-phase 220V AC, 240V DC |
| Rated Input Power | Model 30: 1.5kW; Model 50: 2.2kW; Model 80: 4kW; Model 100: 5.5kW |
| Insulation Class | Class B |
| Protection Rating | IP20 |
| Grounding Resistance | ≤0.1Ω |
| Insulation Resistance | ≥10MΩ |
| Surge Protection | Class III, nominal discharge current 20kA |
| Leakage Protection | 30mA tripping current |
6.5 Monitoring System Parameters
Processor: ARM Cortex-A9, main frequency 1GHz
Display: 7-inch TFT color LCD screen, touch operation
Analog Inputs: 8 channels, 4~20mA/PT1000
Digital Inputs: 16 channels, dry contacts
Relay Outputs: 8 channels, 5A 250V AC
Communication Interfaces: 1 Ethernet port, 2 RS485 ports, 1 USB port
Communication Protocols: Modbus-RTU, Modbus-TCP, SNMP
Data Storage: Local storage ≥12 months
Power Supply: 24V DC
Operating Temperature: -10°C~60°C
6.6 Sensor Accuracy Parameters
| Sensor Type | Measurement Range | Accuracy Class | Response Time |
|---|---|---|---|
| Temperature Sensor (PT1000) | -20°C~100°C | ±0.1°C | ≤1s |
| Pressure Sensor | 0~1.0MPa | ±0.5%FS | ≤500ms |
| Flow Sensor | 0~50L/min | ±1.5%FS | ≤2s |
| Liquid Level Sensor | 0~100% | ±2% | ≤1s |
| Water Leakage Sensor | Point type / Rope type | 0.5mL trigger | ≤100ms |
| Current Sensor | 0~50A | ±0.5% | ≤300ms |
6.7 Environmental Adaptability Parameters
| Parameter Item | Technical Specification |
|---|---|
| Operating Ambient Temperature | 5°C~40°C |
| Storage Ambient Temperature | -20°C~60°C |
| Operating Ambient Humidity | 20%~80%RH, non-condensing |
| Storage Ambient Humidity | 10%~90%RH, non-condensing |
| Altitude | ≤2000m (derating required above 2000m) |
| Seismic Resistance Level | Level 8 |
| Corrosion Level | G1 level (mild corrosive environment) |
Chapter 7 Product Functions and Features
7.1 Core Cooling Functions
High-Efficiency Heat Exchange Capability: Adopting micro-channel cold plate and brazed plate heat exchanger technology, the heat exchange efficiency is 5~10 times that of traditional air cooling. A single cabinet supports up to 120kW heat dissipation capacity, easily handling heat dissipation requirements for high-power AI GPU and CPU clusters.
Precise Temperature Control: Based on PID closed-loop control algorithm, the supply liquid temperature control accuracy can reach ±0.5°C, with minimal chip temperature fluctuation, ensuring stable operation of IT equipment and extending equipment service life.
Wide Temperature Range Operation: Secondary side supply liquid temperature is continuously adjustable from 25°C~45°C, and the primary side inlet water temperature supports up to 35°C, maximizing the utilization of natural cooling sources and reducing chiller operating time.
Dynamic Load Adaptation: The system can monitor heat load changes in real time and automatically adjust coolant flow rate and temperature. Temperature can be stably controlled even when the load fluctuates from 10% to 100%, adapting to business fluctuation scenarios.
7.2 Intelligent Control Functions
Multi-Mode Operation: Supports multiple operating modes including cooling mode, natural cooling mode, energy-saving mode, standby mode, and maintenance mode. The system can automatically switch modes based on ambient temperature and load conditions to achieve optimal energy efficiency.
Intelligent Energy Efficiency Optimization: Built-in energy efficiency optimization algorithm comprehensively considers cooling source side power consumption, pump group power consumption, and fan power consumption, dynamically adjusting operating parameters to achieve the lowest overall system PUE.
Automatic Liquid Replenishment and Pressure Stabilization: The system monitors liquid level and pressure in real time. When the liquid level is too low, it automatically initiates the replenishment procedure; when pressure is abnormal, it automatically adjusts pump speed and valve opening to maintain system pressure stability.
Fault Self-Diagnosis: The system has built-in fault diagnosis models that can automatically identify more than 20 fault types including sensor faults, pump faults, valve faults, and liquid leakage faults, accurately locating fault points and providing handling recommendations.
Scheduled Operation: Supports timed power on/off and timed switching of operating modes. Operating strategies can be preset according to business peak and off-peak periods, further reducing energy consumption.
7.3 Comprehensive Safety Protection Functions
Multi-Level Leakage Protection: A three-level leakage detection system is established at chip level, branch circuit level, and cabinet level. Leakage as small as 0.5mL can trigger an alarm. The graded linkage handling mechanism progresses layer by layer from early warning to shutdown protection, thoroughly eliminating liquid leakage safety hazards.
Full-Parameter Threshold Protection: Provides dozens of protection functions including over-temperature, low temperature, over-pressure, low pressure, overload, water shortage, and leakage protection. Any parameter abnormality can trigger timely alarms and protective measures, ensuring equipment and personnel safety.
Redundant Reliability Design: Core components adopt N+1 redundant configuration, with dual pumps serving as backups for each other and automatic seamless switching upon failure; optional dual power input with automatic switching ensures continuous system operation.
Electrical Safety Isolation: The liquid circuit system and electrical system are physically isolated, and the insulation design complies with national standards. Even if liquid leakage occurs, it will not cause electrical short circuit accidents.
Emergency Stop Function: The cabinet is equipped with a prominent emergency stop button. In emergency situations, all power output can be cut off at the press of a button to quickly terminate risks.
7.4 Convenient Operation and Maintenance Functions
Modular Design: Core components including CDU, water pumps, controllers, and sensors all adopt modular design, supporting rapid disassembly and replacement. Mean Time To Repair (MTTR) ≤30 minutes.
Quick Connector Design: The equipment liquid circuit connections use double self-sealing quick connectors with drip-free connection/disconnection. Equipment replacement does not require system draining, improving operation and maintenance efficiency by over 80%.
Visual Operation and Maintenance: The 7-inch touch screen intuitively displays all operating parameters and status information, with clear fault information. Simple and easy operation lowers the technical threshold for operation and maintenance personnel.
Remote Centralized Management: Supports Web and APP multi-terminal remote monitoring, allowing system status viewing, alarm reception, and remote parameter adjustment from anywhere at any time. No on-site duty required, significantly reducing operation and maintenance labor costs.
Data Statistical Analysis: The system automatically records operating data, energy consumption data, and alarm records, supporting generation of daily, monthly, and annual reports for energy consumption analysis and operation and maintenance management.
7.5 Compatibility and Scalability
Standard Architecture Compatibility: Strictly follows 19-inch standard cabinet specifications, compatible with mainstream brand servers, switches, and storage equipment installation. Existing air-cooled computer rooms can be smoothly upgraded and retrofitted.
Multi-Scenario Adaptation: Supports indoor, outdoor, explosion-proof, and other scenario-specific models, adapting to full-scenario deployment needs from edge nodes to core data centers.
Flexible Networking and Expansion: Supports single-cabinet standalone operation and multi-cabinet cluster networking. Expansion only requires adding cabinets and connecting to the main liquid circuit pipeline. Flexible deployment with on-demand expansion.
Third-Party System Integration: Supports mainstream environment monitoring protocols, seamlessly integrating with existing BMS and DCIM systems in the computer room, incorporating into the customer’s unified operation and maintenance platform.
7.6 Green and Energy-Saving Features
Ultra-Low PUE: The liquid cooling system can significantly increase supply water temperature and extend natural cooling duration. The overall computer room PUE can be reduced to below 1.15, while immersion solutions can achieve PUE as low as 1.05, saving 30%~50% energy compared to traditional air cooling.
Waste Heat Recovery and Utilization: The hot water discharged from the liquid cooling system has high temperature and good quality, which can be recovered for building heating, domestic hot water, industrial heating, and other scenarios, further improving energy utilization efficiency.
Low Noise Operation: The liquid cooling system replaces high-speed cooling fans, reducing cabinet operating noise to as low as 58dB(A), improving the computer room operation and maintenance environment without requiring additional noise treatment.
Environmentally Friendly Materials: All materials comply with RoHS environmental standards. Coolant is recyclable with no waste pollutant discharge, meeting green data center construction requirements.
Chapter 8 Product Application Scenarios
8.1 AI Intelligent Computing Centers
AI large model training and AI inference services require deployment of large numbers of high-power GPU servers, with single-cabinet power typically reaching 30~80kW, which traditional air cooling cannot support.
Solution Adaptation: Cold-plate liquid cooling cabinets or hybrid liquid cooling cabinets are recommended, with single-cabinet heat dissipation of 30~100kW, adapting to high-density deployment of 8-card and 16-card AI servers.
Customer Value: Supports high-density computing deployment and improves computing output per unit area of the computer room; low PUE reduces long-term operating costs; precise temperature control ensures stable full-load operation of GPUs over extended periods.
Typical Cases: AI enterprise training clusters, operator intelligent computing centers, cloud vendor AI computing nodes.
8.2 High-Performance Computing (HPC) Supercomputing Centers
Supercomputing centers undertake scientific computing, weather forecasting, gene sequencing, simulation, and other computing tasks with extremely high computing density and stringent heat dissipation reliability requirements.
Solution Adaptation: Immersion liquid cooling cabinets are recommended, with single-cabinet power of 50~120kW, providing ultimate heat dissipation capability and excellent temperature uniformity.
Customer Value: Breaks through the air-cooling power density ceiling, enabling ultra-high-density computing deployment; extremely low PUE reduces the massive electricity costs of supercomputing centers; fanless design improves equipment reliability and reduces fault downtime.
Typical Cases: National supercomputing centers, research institute computing centers, university high-performance computing platforms.
8.3 Enterprise Data Centers
Enterprise data centers carry core business systems with high reliability and availability requirements, while also facing energy-saving and carbon-reduction assessment pressure.
Solution Adaptation: Cold-plate liquid cooling cabinets or rear-door heat exchange liquid cooling cabinets are recommended, with power of 15~50kW, balancing compatibility and heat dissipation capability.
Customer Value: Compatible with existing IT equipment, low retrofitting cost; significantly reduces PUE to meet green and low-carbon requirements; stable and reliable operation ensures core business continuity.
Typical Cases: Financial data centers, enterprise headquarters computer rooms, government cloud data centers, medical data centers.
8.4 Edge Computing Nodes
Edge computer rooms are widely distributed, small in space, and have limited operation and maintenance conditions, requiring compact, reliable, and minimally attended computing facilities.
Solution Adaptation: Built-in CDU liquid cooling cabinets or outdoor liquid cooling cabinets are recommended, featuring high integration and self-contained systems without requiring complex computer room supporting infrastructure.
Customer Value: Complete single-cabinet system with rapid deployment and plug-and-use capability; high level of intelligence supporting unattended remote operation and maintenance; outdoor models can be installed directly outdoors, saving computer room construction costs.
Typical Cases: 5G edge computer rooms, industrial park edge nodes, transportation hub computing nodes, smart city edge sites.
8.5 Retrofit and Upgrading of Legacy Data Centers
Traditional air-cooled data centers face problems of insufficient power density and excessive energy consumption, with overall reconstruction being costly and time-consuming.
Solution Adaptation: Rear-door heat exchange liquid cooling cabinets are recommended, requiring no server modification. Direct replacement of the cabinet rear door can enhance heat dissipation capability.
Customer Value: Low retrofitting cost, short cycle, no impact on existing business operations; single-cabinet power can be increased from 10kW to 40kW, rapidly improving computer room carrying capacity; significantly reduces cooling energy consumption and extends data center service life.
Typical Cases: Operator traditional computer room retrofits, enterprise legacy computer room upgrades, park data center expansion.
8.6 Special Industry Application Scenarios
Petrochemical, coal mining and other flammable/explosive industries: Explosion-proof liquid cooling cabinets meet explosion-proof standards, enabling safe deployment of computing equipment in hazardous environments.
Military and classified computer rooms: Shielded liquid cooling cabinets integrate electromagnetic shielding functions with liquid cooling heat dissipation, meeting both confidentiality and heat dissipation requirements.
Communication base station supporting facilities: Outdoor integrated liquid cooling cabinets integrate base station equipment and heat dissipation systems, adapting to harsh outdoor environments with convenient deployment.
Chip testing and equipment burn-in rooms: High-power liquid cooling test cabinets provide precise temperature control, simulating different temperature environments to meet chip and equipment testing and burn-in requirements.
Chapter 9 Product Installation
9.1 Pre-Installation Preparation
9.1.1 Technical Preparation
Organize installation technical personnel to familiarize themselves with this manual, product construction drawings, and relevant technical standards, clarifying the installation process and quality requirements.
Survey the construction site, verify that the computer room layout, cabinet positioning, liquid circuit interface positions, power supply interface positions, and grounding terminal positions are consistent with the design.
Prepare a construction plan, clarifying construction schedule, personnel assignments, safety measures, and emergency response plans.
Conduct technical and safety briefings for construction personnel, ensuring all personnel master operating specifications and safety precautions.
9.1.2 Site Environmental Requirements
Floor Load-Bearing Capacity: The computer room floor load-bearing capacity must exceed the cabinet operating weight. Raised floor load-bearing capacity ≥1000kg/m². The floor must be level with a horizontal deviation ≤2mm/m.
Space Requirements:
- Cabinet front maintenance aisle width ≥1000mm, rear maintenance aisle width ≥800mm.
- Space between cabinet top and ceiling or duct bottom ≥500mm, facilitating pipeline connection and maintenance.
- Appropriate clearance reserved between side-by-side cabinets; multiple cabinets can be closely joined when installed together.
Environmental Requirements: Construction site temperature 5°C~35°C, humidity 20%~80%RH, non-condensing; no dust, corrosive gases, or flammable/explosive materials at the site.
Supporting Conditions:
- Primary side cooling source piping has been laid in place, with interfaces reserved near the cabinet, and pressure and temperature meeting product parameter requirements.
- Power supply circuits have been installed, with voltage and capacity meeting equipment rated requirements.
- Grounding system is complete, with grounding resistance ≤1Ω.
- Clean water source and drainage facilities available on site, facilitating system flushing and pressure testing.
9.1.3 Unpacking Inspection
After equipment arrival, unpack indoors in a dry, level area. Operate carefully during unpacking to avoid collision damage to the equipment.
Against the packing list, verify one by one the model, quantity, and specification of the cabinet main body, accessories, consumables, and documentation, checking consistency with the purchase contract.
Inspect the equipment appearance, confirming no deformation, paint chipping, corrosion on the cabinet body, no glass damage, no impact damage on pipe interfaces, and no damage to sealing surfaces.
Check whether the sealing plugs on liquid circuit interfaces are intact, with no signs of liquid leakage; check electrical components for looseness or damage.
If missing parts, damage, or model discrepancies are found, record the issues and take photos for documentation, promptly contacting the manufacturer for resolution.
After unpacking inspection acceptance, properly store the equipment and accessories to avoid loss or damage, awaiting installation.
9.1.4 Tools and Materials Preparation
Installation Tools: Forklift, manual hydraulic pallet truck, spirit level, torque wrench, socket wrench, screwdriver, pipe wrench, crimping pliers, pipe cutter, deburring tool, pipe bender, electric drill, impact drill, etc.
Inspection Tools: Multimeter, megohmmeter, clamp ammeter, pressure gauge, thermometer, tape measure, feeler gauge, spirit level, etc.
Installation Materials: Expansion bolts, anchor bolts, sealing tape, PTFE tape, stainless steel pipes, hoses, fittings, valves, cables, cable trays, cable ties, grounding copper wire, etc.
Protective Equipment: Safety helmets, insulated gloves, anti-slip shoes, safety goggles, work clothes, etc.
9.2 Cabinet Positioning and Securing
Mark the cabinet installation positions according to the computer room floor plan drawings, ensuring neat arrangement and compliance with cabling planning.
Use a hydraulic pallet truck to transport the cabinet to the installation position. Keep the cabinet upright during transport with a tilt angle not exceeding 15°. Horizontal placement or inversion of the cabinet is strictly prohibited.
Remove the transport fixing brackets at the cabinet bottom, adjust the adjustable support feet at the cabinet base, and use a spirit level to calibrate cabinet levelness and plumbness. Horizontal deviation ≤1mm/m, verticality deviation ≤1.5mm/m.
After cabinet positioning and calibration, secure it to the floor using anchor bolts, or reinforce the connection with the raised floor, ensuring the cabinet is stable and free from wobbling.
When installing multiple cabinets side by side, adjust the spacing between cabinets to be consistent, and connect cabinets using cabinet joining brackets to ensure overall neatness and firmness.
After cabinet securing is completed, re-check levelness and verticality. Once confirmed correct, clean up site debris.
9.3 Liquid Circuit System Installation
9.3.1 General Requirements for Pipeline Installation
Before pipeline installation, all pipe materials and fittings must be cleaned to remove internal wall oil, dust, and scale, ensuring the interior of the pipes is clean.
Pipe cutting uses dedicated pipe cutters, with flat cuts, free from burrs and deformation. After cutting, use a deburring tool to remove internal and external burrs from the pipe ends.
Pipe connections must strictly follow process requirements. Stainless steel pipe welding requires argon arc welding, ensuring good weld formation without porosity, slag inclusion, or cracks. Crimp connections require dedicated crimping tools with proper crimping.
Pipeline routing should be horizontal and vertical, neatly arranged, and firmly secured. Bracket spacing meets specification requirements: for horizontal pipes DN25 and below, spacing ≤1.5m; DN50 and below, spacing ≤2.0m; for vertical pipes, spacing ≤2.5m.
During pipeline installation, reserve appropriate allowance for thermal expansion and contraction. Long pipelines should be equipped with expansion joints or natural compensation bends.
Maintain safe distances between pipelines and electrical circuits and low-voltage circuits. Parallel spacing ≥150mm, crossing spacing ≥100mm.
All pipeline interfaces and valve positions should be accessible for operation and maintenance, avoiding obstruction.
9.3.2 Primary Side Pipeline Installation
Branch pipes should be taken from the computer room primary side cooling source main pipeline. After installing shut-off valves, Y-type strainers, pressure gauges, and thermometers, connect to the CDU primary side inlet and outlet ports.
Inlet and outlet port markings must be clear; reverse connection is strictly prohibited. Typically, the CDU primary side has bottom inlet and top outlet; specific arrangements should follow equipment markings.
Install automatic air vent valves at high points of the pipeline system and drain valves at low points, facilitating system air venting and drainage.
Pipelines must be firmly secured to avoid pipeline weight acting on CDU interfaces, which could cause stress damage to the interfaces.
After pipeline installation, conduct a separate hydrostatic test on the primary side pipeline at 1.5 times the working pressure, maintaining pressure for 30 minutes. Pressure drop ≤0.02MPa with no visible leakage is considered qualified.
9.3.3 Secondary Side Pipeline Installation
The internal manifolds (supply and return headers) inside the cabinet are pre-installed at the factory. On-site, only the main pipelines between the CDU and the manifolds need to be connected.
Connect the CDU supply liquid port to the supply header inlet, and the CDU return liquid port to the return header outlet. Pipeline markings must be clear, and reverse connection of supply and return pipelines is strictly prohibited.
Check the valve status of each branch circuit on the supply and return headers. All valves should be in the closed position before initial installation.
During pipeline installation, avoid forced alignment to prevent interface stress that could cause leakage risks. When connecting flexible hoses, reserve appropriate allowance to avoid tension.
All threaded connection points should be wrapped with PTFE tape or use sealing compound to ensure reliable sealing.
Internal cabinet pipelines should be secured on dedicated brackets, neatly arranged with clear markings, without affecting IT equipment installation and maintenance.
9.3.4 Leakage Detection System Installation
Install point-type water immersion sensors in the liquid collection tray at the cabinet bottom, with sensor probes fitted flush against the tray bottom and firmly secured.
Lay leakage detection rope along areas prone to leakage such as manifolds, pipe joints, and valves. The detection rope should be laid flat beneath potential leak points, secured flat and avoiding tangling.
The leakage detection module should be installed on the cabinet side wall at a position convenient for maintenance, with secure wiring and clear markings.
Connect the leakage detection system to the main controller and test the detection function. Simulate a leak to verify that the alarm is triggered correctly.
9.3.5 System Flushing and Pressure Testing
Pipeline Flushing
After pipeline installation, flush the secondary side system to remove impurities introduced during installation.
Disconnect precision components such as cold plates and use short connecting pipes to bridge the circuit. Start the circulating pump for circulation flushing, with a flushing duration of no less than 2 hours.
Periodically check the filter screens and clean out impurities until the discharged water is clear with no visible impurities, which is considered qualified.
After flushing is qualified, clean the filter screens and restore the system pipeline connections.
Hydrostatic Pressure Test
Inject clean coolant into the system and open air vent valves to exhaust all air from the system.
Use a manual pressure test pump to slowly increase pressure at a rate ≤0.1MPa/min until reaching the test pressure (1.5 times working pressure).
Maintain pressure for 12 hours. Check pressure drop within the first 10 minutes; pressure drop ≤0.03MPa. Then reduce to working pressure for visual inspection. No leakage at all interfaces, welds, and valves, and no pipeline deformation is considered qualified.
If leakage is found during the pressure test, immediately relieve pressure for handling. Repairing under pressure is strictly prohibited. After rectification, re-test.
After the pressure test is qualified, drain the test water and prepare for filling the formal coolant.
9.3.6 Coolant Filling
Select coolant that meets product requirements. Recommend the company’s dedicated coolant, or deionized water mixed with ethylene glycol meeting conductivity ≤10μS/cm (ethylene glycol concentration determined by minimum ambient temperature, typically 30%~50%).
Inject coolant into the system through the filling port. During filling, proceed slowly while opening air vent valves at high points to release air.
Stop filling when the expansion tank liquid level is within the normal scale range and system pressure reaches 0.2~0.3MPa.
Start the circulating pump at low speed for 5~10 minutes to expel residual air from the pipelines. Re-check liquid level and pressure, replenishing if insufficient.
Record the coolant model, concentration, and filling volume for archival purposes.
9.4 Electrical System Installation
9.4.1 General Requirements
Electrical installation must be performed by certified electricians, strictly complying with the “Code for Design of Low-Voltage Electrical Installations” and safety operating procedures.
Before installation, confirm that the power supply voltage, frequency, and phase count match the equipment rated requirements.
All electrical circuits should be neatly routed and firmly secured, with separation of high-voltage and low-voltage circuits to avoid interference.
Wiring must be firm and reliable, with no loose or false connections at terminals, and cable markings clear and accurate.
The entire installation process must be performed with power disconnected. Live work is strictly prohibited.
9.4.2 Main Power Supply Wiring
Route a dedicated power supply circuit from the computer room distribution cabinet. Cable cross-sectional area must meet the equipment rated current requirements with appropriate margin.
Cables enter through the bottom cable entry holes of the cabinet, secured with cable glands and sealed, with cable protection in place.
Connect to the upper terminals of the cabinet main input circuit breaker. Three-phase power phase sequence must be correct, with neutral and ground wires properly connected.
For dual-power models, connect the main and backup power circuits separately, confirming that the phase sequence of both power sources is consistent.
After wiring is completed, check wiring firmness and measure insulation resistance. Phase-to-phase and phase-to-ground insulation resistance ≥10MΩ is considered qualified.
9.4.3 Control and Sensor Wiring
Following the wiring diagram, connect CDU pumps, electric valves, sensors, and other components to the corresponding terminals on the main controller.
Temperature sensor and pressure sensor wiring should use shielded cables, with the shield layer grounded at one end to avoid signal interference.
Leakage sensor and alarm device wiring must be correct, with linkage logic conforming to design requirements.
Communication lines should be connected to the cabinet communication interface. When interfacing with environment monitoring systems, use shielded twisted pair cables.
All wiring terminals should be tightened to the required torque, with cable numbers clear and consistent with drawings.
9.4.4 Grounding System Connection
Connect the cabinet grounding copper bar to the computer room grounding busbar using dedicated grounding copper wire, with a cross-sectional area ≥16mm².
The cabinet body, CDU, electrical equipment enclosures, and metal pipelines should all be reliably grounded, forming a complete grounding network.
After grounding connections are completed, measure grounding resistance. Whole-machine grounding resistance ≤0.1Ω, and system grounding resistance ≤1Ω is considered qualified.
9.5 IT Equipment Liquid Cooling Connection
Install IT equipment onto cabinet rails, securing firmly, with equipment positions corresponding to the liquid cooling branch circuits.
Remove the dust caps from the manifold branch quick connectors and the equipment liquid cooling interfaces. Check that interface sealing surfaces are clean and undamaged.
Align the quick connectors and insert horizontally and smoothly. Confirm the locking buckle engages with a “click” sound, then gently pull to verify secure connection.
Following the sequence of supply water first, return water second, connect all equipment liquid cooling pipelines one by one.
After all connections are completed, slowly open the branch circuit valves and observe whether there is any leakage at the connection points. After confirming no leakage, fully open the valves.
After all branch circuits are connected, check system pressure. After confirming normal conditions, prepare for commissioning.
9.6 Post-Installation Inspection
After all installation work is completed, conduct a comprehensive inspection according to the following items. Only after confirming everything is correct can the commissioning phase begin:
- Cabinet is firmly secured, levelness and verticality meet requirements, no appearance damage.
- Liquid circuit system pipelines are correctly connected, markings are clear, valve open/close statuses are correct; system pressure is normal with no leakage.
- Coolant model, concentration, and liquid level meet requirements.
- Electrical system wiring is correct, insulation resistance and grounding resistance are qualified, protective devices are correctly configured.
- Sensors and detection devices are properly installed with correct wiring.
- Monitoring system hardware connections are complete, display screen functions normally.
- Site is cleaned up with no tools or debris left behind, and maintenance aisles are unobstructed.
Chapter 10 Product Wiring
10.1 General Wiring Specifications
Personnel Qualifications: All wiring operations must be performed by professionals with electrician certification, strictly following electrical safety operating procedures.
Power-off Operation: Before wiring, the upstream power supply must be disconnected, and voltage verification must confirm zero voltage before proceeding. Live wiring is strictly prohibited.
Cable Selection: Power cables, control cables, and communication cables must be selected according to rated current and signal type, meeting current-carrying capacity, voltage withstand, and shielding requirements.
Wire Number Marking: Both ends of all cables must be fitted with wire number sleeves. Wire numbers must match the wiring diagram, with clear and durable markings.
Wiring Workmanship: Terminal connections must be firm. Stranded wires should be tinned or use crimped terminals, with no false connections or excessive exposed copper. No more than 2 wires per terminal.
Cabling Standards: High-voltage and low-voltage circuits should be routed separately. AC and DC circuits should be separated. Power lines and signal lines should be separated with spacing ≥50mm. Cables should be neatly routed, tied and secured, without tension or stress.
Protection Requirements: Cable entry/exit points at the cabinet should be sealed with cable glands. Bends should have protection to prevent metal burrs from cutting cable insulation.
10.2 Main Power Circuit Wiring
10.2.1 Three-Phase 380V Power Supply Wiring
LA-LC series standard models adopt three-phase five-wire power supply (L1, L2, L3, N, PE). Wiring steps are as follows:
1. Connect the three-phase power lines L1, L2, L3 to the L1, L2, L3 terminals at the upper end of the main circuit breaker respectively.
2. Connect the neutral wire N to the corresponding terminal on the neutral bar.
3. Connect the protective ground wire PE to the corresponding terminal on the grounding copper bar.
4. Tighten the wiring terminals. Torque values are determined by cable cross-sectional area: 10mm² cable torque 2.5N·m, 16mm² cable torque 3.2N·m, 25mm² cable torque 4.0N·m.
5. After wiring is completed, verify phase sequence using a phase sequence meter to ensure correct three-phase phase sequence without phase sequence errors.
10.2.2 Dual Power Supply Switching Wiring
Wiring steps for models with optional dual power supply:
1. Connect the two three-phase power sources to the normal power source terminal and standby power source terminal of the automatic transfer switch respectively.
2. Connect the output terminal of the automatic transfer switch to the input terminal of the main circuit breaker.
3. Connect the neutral and ground wires of both power sources to the corresponding neutral bars and grounding bars.
4. Set the automatic transfer switch parameters to prioritize the main power source. When the main power source fails, automatically switch to the standby power source with a switching time ≤100ms.
5. Test the switching function by disconnecting the main power source to confirm the standby power source activates properly with correct phase and voltage.
10.3 CDU Power Circuit Wiring
10.3.1 Circulating Pump Wiring
The circulating pump is a three-phase asynchronous motor. Connect the three phase wires to the U, V, W terminals at the output end of the contactor respectively.
Connect the pump body protective ground wire to the grounding terminal.
For variable frequency drive models, connect the VFD output to the pump motor and the VFD input to the power supply.
After wiring is completed, perform a jog test of the pump rotation direction, confirming it matches the arrow direction on the label. If rotating in reverse, swap any two phase wires.
For dual-pump redundant models, connect the two pumps to two separate control circuits, serving as backups for each other.
10.3.2 Electric Control Valve Wiring
The electric valve actuator power supply is 24V AC, connected to the corresponding terminal on the control power supply.
Connect the control signal terminal (4~20mA or 0~10V) to the analog output terminal of the main controller.
Connect the valve position feedback signal terminal to the analog input terminal of the main controller.
Pay attention to positive and negative polarity during wiring. Reverse connection is strictly prohibited, as it may damage the actuator.
10.4 Sensor Circuit Wiring
10.4.1 Temperature Sensor (PT1000) Wiring
Use two-wire or three-wire connection. Three-wire connection eliminates lead resistance influence for higher accuracy.
Connect the sensor positive and negative terminals to the positive and negative terminals of the corresponding AI channel on the main controller. For three-wire connection, connect the compensation wire to the compensation terminal.
For long cable runs, use shielded cables with the shield layer grounded at one end at the controller.
After wiring is completed, measure the sensor resistance value. At room temperature, it should be approximately 1000Ω, confirming the sensor is normal.
10.4.2 Pressure/Flow Sensor Wiring
Sensor power supply is typically 24V DC. Connect the red wire to the positive power terminal and the black wire to the negative power terminal.
Connect the output signal (4~20mA) signal wire to the positive terminal of the AI input on the main controller, with the negative terminal common ground.
Pay attention to power supply polarity during wiring. Reverse connection may damage the sensor.
The sensor housing should be reliably grounded to reduce interference.
10.4.3 Leakage Sensor Wiring
Point-type water immersion sensors have switch output. Connect the two wires to the DI digital input terminals of the main controller.
For rope-type leakage detection controllers, connect the power supply to 24V DC, alarm output to DI terminals, and positioning signal to corresponding AI terminals.
Correctly connect the head and tail ends of the leakage detection rope, avoiding short circuits and open circuits.
After wiring is completed, touch the detection rope with a damp cloth to test whether the alarm triggers normally.
10.5 Monitoring and Communication Circuit Wiring
10.5.1 Touch Screen Wiring
The touch screen power supply is 24V DC, connected to the control power output terminal.
Connect the communication interface to the corresponding communication port on the main controller via network cable or RS485 cable.
After wiring is completed, power on and check whether communication between the touch screen and controller is normal and whether parameter display is synchronized.
10.5.2 Remote Communication Wiring
RS485 Communication: Use shielded twisted pair cable, connect A and B lines correspondingly, with the shield layer grounded at one end. Communication distance ≤1200m, daisy-chain connection, with 120Ω terminating resistors at both ends of the bus.
Ethernet Communication: Use standard network cable, connect to the computer room LAN, set correct IP address, subnet mask, and gateway, ensuring network connectivity with the monitoring host.
Dry Contact Alarm Output: Fault alarms, operating status, and other dry contact signals connect to the DI input terminals of the computer room environment monitoring system. Passive contacts with a capacity of 5A 250V AC.
10.6 Auxiliary Circuit Wiring
Audible and Visual Alarm Wiring: Alarm power supply 24V DC, connected to the controller DO output terminal. When an alarm occurs, the output power drives the alarm device.
Lighting and Socket Wiring: Auxiliary lighting and maintenance sockets inside the cabinet are powered by a separate branch circuit breaker. Wiring must be correct with reliable grounding.
Access Control, Smoke Detection, and Other Optional Component Wiring: Wire according to the corresponding product manual, connecting to the corresponding input/output terminals with correct linkage logic.
10.7 Post-Wiring Inspection and Testing
Continuity Check: Against the wiring diagram, verify one by one each cable connection position, ensuring no wrong or missing connections.
Insulation Test: Disconnect all low-voltage components, use a 500V megohmmeter to measure the insulation resistance of the power circuit. ≥10MΩ is considered qualified.
Grounding Check: Measure the continuity between all metal components and the grounding terminal, confirming reliable grounding with no false connections.
Pre-Power-On Confirmation: All circuit breakers are in the open position, all component wiring is correct, and no personnel are in contact with live parts at the site.
Chapter 11 Product Commissioning
Product commissioning is divided into four stages: single-machine commissioning, system integration testing, performance testing, and linkage testing. The process must be strictly followed in sequence, and the next stage can only proceed after the previous stage passes testing.
11.1 Pre-Commissioning Preparation
- Confirm all installation work is completed, installation inspection is qualified, and the site is cleaned up.
- Confirm the external cooling source system is operating normally, with supply water temperature, pressure, and flow meeting commissioning requirements.
- Confirm normal power supply with voltage and frequency within rated ranges.
- Confirm coolant is filled to the proper level, liquid level and pressure are normal, and system air venting is completed.
- Prepare commissioning record forms and assign dedicated personnel to record commissioning data.
- Commissioning personnel should be familiar with system principles, operating methods, and emergency handling procedures.
11.2 Electrical System Single-Machine Commissioning
Pre-Power-On Check: Re-confirm that all circuit breakers are in the open position and there are no short circuits at the load end.
Control Circuit Power-On: First close the control circuit breaker, check that the controller, touch screen, and sensor power supplies are normal, the display screen lights up, and there are no error messages.
Initial Parameter Setting: Set basic system parameters on the touch screen, including rated temperature, pressure thresholds, alarm thresholds, and communication parameters. Restore factory settings first, then configure according to site operating conditions.
Sensor Calibration: Against standard instruments, perform zero-point calibration and span calibration for temperature, pressure, and flow sensors, ensuring accurate detection data.
Actuator Testing:
- Manually test the electric control valve from 0% to 100% opening, observing smooth valve operation, accurate valve position feedback, and no jamming.
- Jog test the circulating pump to confirm correct rotation direction, smooth operation, no abnormal noise or vibration.
- Test the audible/visual alarm, indicator lights, and emergency stop button functions.
Protection Function Testing: Simulate overload, leakage, overvoltage, and other faults to verify protection devices operate correctly.
11.3 Liquid Circuit System Single-Machine Commissioning
Air Venting Operation:
- Open the air vent valves at system high points, start the circulating pump at low speed, and gradually exhaust air from the pipelines.
- Observe the air vent valves until no bubbles are discharged and continuous liquid flows out, then close the air vent valves.
- After running for 10 minutes, vent air again to ensure no residual air remains in the system.
- Check the expansion tank liquid level and replenish coolant to the normal range.
Flow and Pressure Commissioning:
- Gradually increase the pump speed, observe system pressure and flow changes, and record pressure and flow values at different frequencies.
- Adjust branch circuit valves to balance flow across all branches, with flow deviation ≤5%.
- Test system pressure stability. Under rated flow, pressure fluctuation ≤0.02MPa.
- Check all pipelines, fittings, and valves for leakage. If leakage is found, stop the machine immediately for handling.
Pump Redundancy Switching Test:
- Manually stop the main pump to verify the standby pump starts automatically with switching time ≤3s and no significant system pressure fluctuation.
- Test multiple switching cycles to confirm reliable switching logic without faults.
11.4 Temperature Control System Commissioning
Steady-State Temperature Control Test:
- Set the target supply liquid temperature to 35°C, allow the system to operate automatically, and observe the temperature change curve.
- After temperature stabilizes, run continuously for 30 minutes, record supply liquid temperature and return liquid temperature values, and calculate temperature control accuracy. Within ±0.5°C is considered qualified.
- Record primary side inlet/outlet water temperatures and flow, calculate heat exchange capacity, and verify rated cooling capacity is achieved.
Dynamic Response Test:
- Suddenly change the target temperature by 5°C, observe the system adjustment process, and record the time for temperature to reach the new steady state. Response time ≤5 minutes is considered qualified.
- Simulate load changes (by opening and closing some branch circuits), observe return liquid temperature changes and system adjustment effectiveness, verifying temperature stability under dynamic loading.
Operating Mode Switching Test:
- Test switching between cooling mode, energy-saving mode, and standby mode. Switching should be smooth with no pressure surge or sudden temperature changes.
- Verify that in automatic mode, the system’s logic for automatically switching operating modes based on ambient temperature and load is correct.
11.5 Safety Protection Function Commissioning
Leak Detection Protection Test
Simulate a minor leak to verify that the system triggers an audible and visual alarm, and that the display screen shows the leak location and alarm information.
Simulate a severe leak to verify that the system’s interlocking logic for automatically stopping the pump, closing valves, and uploading alarms operates correctly.
After clearing the leak, verify that the alarm reset function operates normally.
Over-Temperature Protection Test
Manually modify the temperature protection threshold to simulate return liquid over-temperature, and verify the system’s staged protection logic of alarm, frequency reduction, and shutdown.
After the temperature returns to normal, verify that the system automatically resumes operation.
Pressure Protection Test
Simulate excessive system pressure to verify the pressure relief valve action, pump speed reduction, and over-pressure alarm functions.
Simulate excessively low system pressure to verify the automatic liquid replenishment, low-pressure alarm, and shutdown protection functions.
Power Failure Protection Test
Suddenly cut off the main power supply and verify that the system suffers no abnormal damage, and that manual or automatic operation recovery is possible after power is restored.
For dual-power models, test primary/backup power switching to verify that the control system does not restart and operation status is not interrupted during the switching process.
11.6 IT Equipment Joint Commissioning
Start the IT equipment and gradually increase the load from 25%, 50%, 75% to 100% of rated load.
Maintain stable operation at each load level for 30 minutes, recording server chip temperature, supply/return liquid temperature, flow rate, and pressure data.
Verify that chip temperature is controlled within equipment requirements, temperature fluctuation is minimal, and equipment operates stably without frequency reduction or alarms.
Test rapid load variation scenarios to verify the response speed of the liquid cooling system temperature control and ensure it meets equipment heat dissipation requirements.
Test individual equipment insertion/removal to verify no dripping from quick connectors and that the system operates normally after insertion/removal.
11.7 Remote Monitoring Joint Commissioning
Configure network parameters and test remote web access to confirm successful login and real-time data viewing.
Test remote parameter modification and mode switching functions to verify that command execution is normal.
Test the alarm push function by simulating faults to verify that SMS, email, and APP alarms are received normally.
Test integration with the data center infrastructure monitoring (DCIM) system to confirm normal data upload and correct alarm interlocking.
Test multi-unit networking so that multiple cabinets can be centrally monitored and managed on the same platform.
11.8 72-Hour Full Load Trial Operation
After all commissioning items pass, conduct a 72-hour continuous full load trial operation as a prerequisite for final acceptance.
Run the system at full load with IT equipment at full capacity, with the liquid cooling system operating in automatic control mode.
Record operating data every 2 hours, including temperature, pressure, flow rate, voltage, current, power, and other parameters.
During the trial operation, the system must be fault-free, alarm-free, and leak-free, with all parameters stable within normal ranges.
After the trial operation, calculate system energy efficiency ratio, PUE, and other indicators; these must meet design requirements.
Compile commissioning records and trial operation data to form a commissioning report.
12.1 Transport and Storage Precautions
Transport Requirements
During transport, the equipment must be kept upright with an inclination angle not exceeding 15°. Inverting, laying horizontally, or rolling the equipment is strictly prohibited.
Secure and protect the equipment during transport to avoid collision and jolting, preventing pipe deformation and component loosening.
Transport environment temperature: -20°C to 60°C. Protect from rain and snow. In winter, take anti-freezing measures to prevent coolant from freezing and cracking pipes.
Use a forklift or crane for loading and unloading. Use designated lifting points when hoisting. Never pull directly on pipes, wiring terminals, or other components.
Storage Requirements
The equipment shall be stored in a dry, ventilated indoor warehouse free of corrosive gases, avoiding direct sunlight.
Storage environment temperature: -10°C to 40°C, humidity 20% to 80% RH, without condensation.
All liquid circuit interfaces shall be sealed with plugs to prevent dust and debris from entering the pipes.
For long-term storage (over 3 months), periodically inspect the appearance and energize for dehumidification to prevent moisture damage to electrical components.
Stacking height during storage shall not exceed 2 layers to avoid damage to the cabinet from excessive pressure.
12.2 Installation and Construction Precautions
Installation and construction must strictly follow the design drawings and the requirements in this manual. Unauthorized modification of system structure and component parameters is prohibited.
High-risk operations such as pipe welding and pressure testing shall be performed by certified personnel. Fire-fighting equipment and emergency supplies shall be available on site.
Protect sealing surfaces and quick connectors during installation to avoid impact and scratches, which could otherwise cause seal failure and leakage.
Strictly prevent debris, welding slag, dust, and other foreign matter from entering the liquid circuit system, as this may block the cold plate micro-channels, affecting heat dissipation and potentially damaging equipment.
Electrical wiring shall strictly comply with electrical safety codes. After wiring is complete, insulation and grounding must be measured and verified qualified before energizing.
Maintain a safe distance between the liquid circuit system and the electrical system. Water pipes must never be positioned directly above electrical equipment to prevent short circuits caused by leakage or dripping.
After installation, pressure testing and leak inspection must be performed. The system may only be put into service after confirming there is no leakage.
When construction ambient temperature is below 5°C in winter, take anti-freezing measures. Drain accumulated water promptly after pressure testing to prevent pipes from freezing and cracking.
12.3 Operation Precautions
Equipment operators must receive professional training, be familiar with equipment principles, operating procedures, and emergency handling methods, and hold relevant certification.
Before startup, check the power supply, cold source, liquid level, and pressure for normal conditions. Confirm there are no alarms before starting the system.
Strictly follow the startup and shutdown operating procedures. Frequent start/stop of the equipment is prohibited. The interval between pump starts/stops shall be ≥ 5 minutes.
Do not arbitrarily modify system parameters during operation. Adjustments, if required, shall be performed by professional personnel and properly recorded.
When the equipment is running, it is strictly prohibited to disassemble pipes, connectors, or valves, or to insert/remove quick connectors under pressure to prevent liquid spraying and injury.
Regularly inspect the operating status. If abnormal noise, vibration, or leakage is found, stop the equipment immediately for inspection and only resume operation after the fault is eliminated.
The data center ambient temperature shall not exceed 40°C and humidity shall not exceed 80% RH. Avoid direct sunlight on the cabinet.
Placing heavy objects on the cabinet is strictly prohibited. Do not block ventilation openings or maintenance access passages.
12.4 Safety Protection Precautions
Electrical Shock Protection
It is strictly prohibited to open electrical cabinet doors while energized. When performing maintenance, disconnect the upstream power supply and apply lockout/tagout procedures.
Periodically inspect the grounding system to ensure reliable grounding. Removing grounding devices is strictly prohibited.
Wear insulating gloves and use insulated tools when operating electrical components.
In case of electrical fire, first cut off the power supply, then use dry powder or CO2 fire extinguishers. Use of water is strictly prohibited.
Leak Protection
Regularly inspect the leak detection system functions to ensure normal operating status.
Equip the data center with emergency absorbent materials and drainage tools for use in the event of a leak.
Ethylene glycol coolant has a slight irritant effect on skin and eyes. Rinse immediately with clean water after contact. For large leaks, take protective measures to prevent slipping.
Standing or stepping on the liquid circuit system is strictly prohibited to prevent pipe damage and leakage.
Pressure Vessel Safety
The system working pressure shall not exceed the rated working pressure. Over-pressure operation is strictly prohibited.
Safety valves and pressure gauges shall be periodically calibrated to ensure accuracy and reliability. Blocking safety valves is strictly prohibited.
During pressure testing, increase pressure slowly and never exceed the rated pressure. Unrelated personnel are prohibited from remaining at the pressure test site.
12.5 Coolant Usage Precautions
Only coolants that meet product requirements shall be used. Using untreated water such as tap water or groundwater is strictly prohibited to prevent scaling, corrosion, and microbial growth.
The ethylene glycol coolant concentration shall be configured according to the ambient minimum temperature, ensuring the freezing point is at least 5°C below the ambient minimum temperature.
Coolants of different brands and models must not be mixed to prevent chemical reactions that may produce sediment or cause corrosion.
Periodically test the coolant. Replace it promptly when color darkening, turbidity, or unusual odor is observed.
Waste coolant disposal shall comply with environmental protection requirements. Arbitrary discharge is strictly prohibited.
When shutting down in winter, if ambient temperature is below 0°C, drain the coolant from the system or add sufficient antifreeze to prevent pipes and heat exchangers from freezing and cracking.
12.6 Maintenance and Repair Precautions
Equipment maintenance and repair shall strictly follow the procedures of power-off, pressure relief, and liquid drainage to ensure safe working conditions.
When replacing seals, connectors, and other accessories, only original factory parts of the same specification shall be used. Arbitrary substitution is strictly prohibited.
When disassembling pipes, prepare liquid collection measures to prevent residual liquid spillage. Seal pipe openings promptly after disassembly to prevent foreign matter entry.
When reassembling after maintenance, clean the sealing surfaces and install new sealing O-rings to ensure reliable sealing.
After repair work is complete, perform pressure testing and leak inspection before resuming operation.
Maintain maintenance records detailing the time, content, replaced components, operating status, and other relevant information.
13.1 Daily Inspection (Daily)
Daily routine inspections shall be performed by operations and maintenance personnel to promptly identify hidden hazards. Inspection items include:
Appearance and Environment Inspection: Cabinet appearance is intact, doors close properly; data center ambient temperature and humidity are within normal ranges.
Operating Status Inspection: Touchscreen display functions normally with no fault alarms; pump operates smoothly with no abnormal noise or vibration.
Parameter Inspection: Verify that supply/return liquid temperature, system pressure, flow rate, and liquid level parameters are all within normal ranges.
Leak Inspection: Check pipe joints, valves, and quick connectors for signs of leakage; verify no liquid accumulation in the drain pan.
Electrical Inspection: Distribution cabinet has no unusual odor or abnormal heating; indicator lights display normally.
Complete Inspection Records: Record inspection data and status, and report any abnormalities promptly for handling.
13.2 Monthly Maintenance
Perform comprehensive monthly maintenance, including:
Cleaning and Dust Removal: Clean dust from inside and outside the cabinet; wipe the display screen and cabinet doors; clean dust from inside the electrical cabinet to maintain good heat dissipation.
Pipe and Valve Inspection: Check that all pipes are securely fixed, valves operate flexibly without corrosion; check quick connectors for looseness or damage.
Filter Cleaning: Clean the Y-type filter strainer to remove impurities; check the strainer for damage.
Sensor Inspection: Check that sensors are securely installed with no loose wiring; compare displayed temperature and pressure with on-site gauges and calibrate if deviation is excessive.
Leak Detection System Test: Test the leak detection function; clean the detection cable and sensor probes to ensure detection sensitivity.
Grounding Inspection: Check grounding terminals for looseness or corrosion; measure grounding resistance for normal values.
Fastener Inspection: Tighten electrical terminals and pipe connections to prevent loosening.
13.3 Quarterly Maintenance
Perform deep maintenance quarterly, including:
Heat Exchanger Inspection and Cleaning: Check the differential pressure across the plate heat exchanger inlet and outlet. When differential pressure exceeds 20% of initial value, perform back-flushing to remove scaling and impurities.
Pump Maintenance: Check pump bearing temperature; temperature rise shall not exceed 40°C; replenish bearing grease; inspect mechanical seal for leakage.
Valve Maintenance: Perform full-stroke open/close testing on motorized valves and control valves; clean valve stem dust, apply anti-rust grease, and ensure flexible operation.
Expansion Tank Inspection: Check the pre-charge pressure of the expansion tank and replenish nitrogen if insufficient; inspect the bladder for damage.
Coolant Testing: Sample and test coolant conductivity, pH value, and concentration to assess coolant condition; replenish or replace as necessary.
Electrical Component Inspection: Check contactor and circuit breaker contacts for burn marks; check terminals for heating or discoloration; tighten high-current terminals.
Alarm Function Test: Simulate various faults to verify alarm functions and interlocking protection logic operate correctly.
13.4 Annual Maintenance
Perform comprehensive annual overhaul maintenance, including:
System Full Cleaning: Perform chemical cleaning of the entire liquid circuit system to remove internal scale and biological slime; flush thoroughly and replace with new coolant.
Heat Exchanger Deep Cleaning: Disassemble the plate heat exchanger, thoroughly clean the plates, inspect gasket aging status, and replace gaskets if severely aged.
Pump Overhaul: Disassemble the pump, inspect impeller and pump casing wear; replace mechanical seal and bearings; calibrate shaft alignment.
Sensor Full Calibration: Perform metrological calibration on all temperature, pressure, and flow sensors; issue calibration reports; replace unqualified sensors.
Electrical System Testing: Perform insulation resistance testing, grounding resistance testing, and harmonic testing; verify protection device trip settings.
Pipe Full Inspection: Inspect pipes for corrosion; perform pressure testing to verify system sealing performance; replace aged seals and flexible hoses.
Control System Upgrade: Check the monitoring system firmware version and upgrade if necessary; back up system configuration and historical data.
Performance Testing: Perform full-load performance testing to verify that cooling capacity, temperature control accuracy, energy efficiency, and other indicators meet requirements.
13.5 Common Component Replacement Methods
13.5.1 Filter Strainer Replacement
1. Close the shut-off valves before and after the filter to isolate the pipe section.
2. Slowly open the filter drain valve to relieve pressure and drain internal liquid.
3. Unscrew the filter end cap, remove the old strainer, and clean the filter cavity.
4. Install a new strainer of the same specification, verify the sealing gasket is intact, and tighten the end cap.
5. Close the drain valve, slowly open the inlet valve to vent air, then fully open both front and rear valves.
6. Check for leakage and confirm normal operation to complete the replacement.
13.5.2 Quick Connector Sealing O-Ring Replacement
1. Close the corresponding branch valve and disconnect the quick connector.
2. Remove the old sealing O-ring with tweezers and clean the connector seal groove.
3. Install a new O-ring of the same specification, ensuring it is flat and untwisted.
4. Reconnect the quick connector and confirm proper latching.
5. Slowly open the valve and check for leakage.
13.5.3 Temperature Sensor Replacement
1. Enter system settings and disable the corresponding sensor alarm to prevent false triggering.
2. Disconnect the sensor wiring and mark the wire numbers.
3. Unscrew the old sensor and clean the mounting hole threads.
4. Wrap thread seal tape around the new sensor threads, screw it into the mounting hole, and tighten with moderate torque.
5. Reconnect the wiring according to the marks and restore the alarm setting.
6. Observe whether the temperature display is normal and calibrate the zero-point deviation.
13.5.4 Circulating Pump Replacement (Redundant Models)
1. Confirm the standby pump is operating normally; close the valves before and after the faulty pump.
2. Disconnect power to the faulty pump and apply lockout/tagout procedures.
3. Open the pump casing drain valve and drain liquid from the pump.
4. Remove the flange bolts at the pump inlet and outlet and remove the old pump.
5. Clean the flange sealing surfaces and install a new sealing gasket.
6. Install the new pump and tighten flange bolts evenly in a diagonal pattern.
7. Connect the power wires and grounding wire.
8. Slowly open the inlet valve to vent air, then fully open the inlet and outlet valves.
9. Perform a jog test to confirm correct rotation direction, put into operation, and check for leakage and abnormal noise.
13.6 Long-Term Shutdown Maintenance
When the equipment is shut down for an extended period (over 1 month):
1. Drain the coolant from the system and dry the pipes with dry compressed air.
2. Cut off the main power supply, close all valves, and seal the pipe interfaces.
3. Clean the equipment inside and out, cover with a dust cover, and take moisture-proof measures.
4. Periodically (monthly) energize the equipment for 2 hours for dehumidification to prevent moisture damage to electrical components.
5. In winter, take anti-freezing measures to ensure the ambient temperature remains above 0°C.
6. Before recommissioning, perform a comprehensive inspection, pressure test, and commissioning in accordance with new equipment installation requirements before operation.
14.1 Common Liquid Circuit System Faults
| Fault Phenomenon | Possible Causes | Troubleshooting Steps | Solutions |
|---|---|---|---|
| System pressure continuously drops, liquid level decreases | 1. Pipe, joint, or valve leakage<br>2. Expansion tank pre-charge pressure insufficient<br>3. Safety valve relieving<br>4. Internal cold plate leakage | 1. Visually inspect all interfaces for leak traces<br>2. Check drain pan leak sensor for alarm<br>3. Check safety valve for liquid discharge<br>4. Test expansion tank pre-charge pressure | 1. Locate leak point, tighten joint or replace seal<br>2. Replenish nitrogen to expansion tank to specified pressure<br>3. Repair safety valve, adjust opening pressure<br>4. Replace leaking cold plate |
| System pressure too high | 1. Air not fully vented from system<br>2. Liquid expansion due to temperature rise<br>3. Outlet valve not fully open<br>4. Pipe blockage<br>5. Expansion tank bladder damaged | 1. Check high-point vent valves, vent and observe pressure change<br>2. Check for abnormal temperature rise<br>3. Check valve opening<br>4. Check filter for blockage<br>5. Test expansion tank pre-charge pressure | 1. Thoroughly vent air from system<br>2. Check temperature control system, lower supply liquid temperature<br>3. Fully open valves<br>4. Clean filter, clear blocked pipe<br>5. Replace expansion tank |
| Insufficient flow rate, poor cooling effect | 1. Pump speed insufficient<br>2. Pump rotation direction incorrect<br>3. Cavitation in system<br>4. Filter blockage<br>5. Cold plate channel blockage<br>6. Insufficient valve opening | 1. Check pump frequency and current<br>2. Confirm pump rotation direction matches label<br>3. Vent air and observe flow change<br>4. Check and clean filter<br>5. Test cold plate inlet/outlet differential pressure<br>6. Check control valve and branch valve openings | 1. Increase pump speed, check VFD parameters<br>2. Swap phase wires to correct rotation direction<br>3. Thoroughly vent air, check suction inlet for air leakage<br>4. Clean filter strainer<br>5. Clean or replace cold plate<br>6. Fully open valves, adjust flow to rated value |
| Supply liquid temperature too high, insufficient cooling | 1. Primary side inlet water temperature too high<br>2. Primary side flow insufficient<br>3. Heat exchanger fouled, reduced efficiency<br>4. Motorized control valve fault, insufficient opening<br>5. IT load exceeds design value<br>6. Temperature sensor inaccurate | 1. Measure primary side inlet water temperature<br>2. Check primary side flow and valve opening<br>3. Test heat exchanger inlet/outlet temperature difference and pressure drop<br>4. Check motorized valve opening matches command<br>5. Calculate actual heat load<br>6. Calibrate temperature sensor | 1. Lower external cold source supply water temperature<br>2. Increase primary side supply flow<br>3. Clean heat exchanger to remove scale<br>4. Repair or replace motorized control valve<br>5. Reduce load or upgrade cooling configuration<br>6. Calibrate or replace temperature sensor |
| Pump abnormal noise and excessive vibration | 1. Air ingestion, cavitation<br>2. Pump bearing damage<br>3. Impeller wear or foreign object stuck<br>4. Foundation bolts loose<br>5. Coupling misalignment<br>6. Pump body resonance | 1. Check outlet for bubbles, vent test<br>2. Listen to bearing area for sound, check temperature<br>3. Disassemble and inspect impeller<br>4. Tighten foundation bolts<br>5. Calibrate coupling alignment<br>6. Adjust speed to avoid resonance zone | 1. Thoroughly vent air, check suction inlet for air leak point<br>2. Replace bearings<br>3. Remove foreign objects, repair or replace impeller<br>4. Tighten fixing bolts<br>5. Re-calibrate alignment<br>6. Optimize operating parameters, add vibration dampers |
| Leak sensor false alarm | 1. Detection cable damp or condensation<br>2. Dust or impurities on detection cable surface<br>3. Sensor fault<br>4. Loose wiring, signal interference | 1. Check detection cable for dampness or condensation<br>2. Clean detection cable surface<br>3. Replace sensor for testing<br>4. Check wiring, measure signal | 1. Wipe detection cable dry, improve ambient humidity<br>2. Wipe detection cable with clean water, air dry before restoring<br>3. Replace faulty sensor<br>4. Tighten wiring, ground shield layer |
14.2 Common Electrical System Faults
| Fault Phenomenon | Possible Causes | Troubleshooting Steps | Solutions |
|---|---|---|---|
| Unit has no power, display screen does not illuminate | 1. External power outage<br>2. Main circuit breaker tripped<br>3. Input cable open circuit<br>4. Control power transformer fault<br>5. Emergency stop button pressed, not reset | 1. Check upstream power supply<br>2. Check main circuit breaker status<br>3. Measure input terminal voltage<br>4. Measure control power output<br>5. Check emergency stop button status | 1. Restore external power<br>2. Investigate trip cause, reset breaker<br>3. Repair or replace power cable<br>4. Replace control power supply<br>5. Rotate emergency stop button to reset |
| Pump fails to start | 1. Pump circuit breaker tripped<br>2. Contactor damaged<br>3. VFD fault<br>4. Thermal overload relay activated<br>5. Abnormal control signal<br>6. Pump motor burnt out | 1. Check branch breaker status<br>2. Check contactor engagement<br>3. View VFD fault code<br>4. Check if thermal relay has tripped<br>5. Measure control signal output<br>6. Measure motor winding insulation and resistance | 1. Investigate overload cause, reset breaker<br>2. Replace contactor<br>3. Troubleshoot VFD based on fault code<br>4. Reset thermal relay after cooling, check load<br>5. Check controller output, repair control circuit<br>6. Repair or replace pump motor |
| Temperature display abnormal, values fluctuating | 1. Sensor wiring loose<br>2. Sensor damaged<br>3. Signal interference<br>4. Controller channel fault | 1. Check sensor wiring terminals<br>2. Measure sensor resistance for normal range<br>3. Check shield grounding, keep away from power cables<br>4. Change channel for testing | 1. Tighten wiring terminals<br>2. Replace temperature sensor<br>3. Replace shielded cable, single-point grounding<br>4. Replace controller channel or controller |
| Communication interrupted, remote monitoring unavailable | 1. Network/communication cable disconnected<br>2. Network fault, IP conflict<br>3. Communication parameter settings incorrect<br>4. Controller communication port damaged<br>5. Firewall blocking | 1. Check communication cable connection<br>2. Ping test network connectivity<br>3. Verify IP address, baud rate and other parameters<br>4. Change communication port for testing<br>5. Check firewall and port settings | 1. Repair or replace communication cable<br>2. Troubleshoot network fault, modify IP to avoid conflict<br>3. Set communication parameters correctly<br>4. Replace communication module or controller<br>5. Open corresponding ports, add to whitelist |
| Circuit breaker trips frequently | 1. Load too large, overload<br>2. Line short circuit<br>3. Breaker aging, trip value drift<br>4. Leakage protection activated<br>5. Motor starting current too high | 1. Measure operating current, compare with rated value<br>2. Power off and measure line insulation resistance<br>3. Replace breaker for testing<br>4. Measure leakage current, check insulation<br>5. Check starting method, verify soft start | 1. Reduce load or install larger capacity breaker<br>2. Locate short circuit point, repair line<br>3. Replace with same specification breaker<br>4. Locate leakage point, restore insulation<br>5. Add soft start or VFD start |
14.3 Common Control System Faults
| Fault Phenomenon | Possible Causes | Troubleshooting Steps | Solutions |
|---|---|---|---|
| Touchscreen black screen, no display | 1. Control power supply fault<br>2. Touchscreen damaged<br>3. Ribbon cable loose<br>4. Brightness set to minimum | 1. Measure touchscreen supply voltage<br>2. Replace touchscreen for testing<br>3. Check internal ribbon cable connection<br>4. Try adjusting brightness | 1. Repair control power supply<br>2. Replace touchscreen<br>3. Reconnect ribbon cable<br>4. Restore brightness settings |
| Temperature control out of control, temperature fluctuating | 1. PID parameters set unreasonably<br>2. Temperature sensor detection lag<br>3. Motorized control valve stuck<br>4. System flow fluctuation significant<br>5. Load fluctuating drastically | 1. Check PID parameters, re-auto-tune<br>2. Check sensor installation position<br>3. Check motorized valve for smooth operation<br>4. Check pump speed stability<br>5. Observe load change patterns | 1. Re-tune PID parameters, optimize control logic<br>2. Adjust sensor installation position for accurate measurement<br>3. Repair motorized control valve, clean valve stem<br>4. Stabilize pump speed, check pressure |
| No alarm output | 1. Alarm threshold set too high<br>2. Alarm output terminal fault<br>3. Audible/visual alarm damaged<br>4. Alarm function disabled | 1. Check alarm threshold settings<br>2. Measure alarm output terminal signal<br>3. Power test the alarm directly<br>4. Check system settings for alarm enabled status | 1. Set alarm threshold reasonably<br>2. Repair output terminal or relay<br>3. Replace audible/visual alarm<br>4. Cancel disabling, enable alarm function |
| Parameter settings cannot be saved | 1. Controller storage chip fault<br>2. Insufficient operation permission<br>3. Incorrect setting procedure<br>4. System crash | 1. Test whether other parameters can be saved<br>2. Check logged-in user permissions<br>3. Operate correctly per manual<br>4. Restart controller for testing | 1. Repair or replace controller<br>2. Log in with administrator account<br>3. Set and confirm save following correct procedure<br>4. Restart system, restore factory settings |
14.4 General Principles for Fault Handling
Safety First: When handling faults, prioritize personnel safety. Cut off power and relieve pressure before working, and take protective measures.
Simple Before Complex: Troubleshoot in the order of visual inspection → parameter inspection → component testing → disassembly and repair. First investigate simple common causes, then proceed to deeper complex faults.
External Before Internal: First check external factors such as power supply, cold source, and environment, then investigate internal equipment components.
Static Before Dynamic: First perform static inspection with power off, then perform dynamic testing with power on to avoid expanding the fault.
Record and Trace: Keep records of all fault handling, including fault phenomenon, cause, handling method, and replaced components, to accumulate O&M experience.
Major Fault Escalation: For major faults that cannot be diagnosed or handled, promptly contact the manufacturer’s technical support. Do not blindly disassemble or repair.
15.1 Basic Knowledge
Q1: What advantages do liquid-cooled cabinets have over traditional air-cooled cabinets?
A: Liquid-cooled cabinets have core advantages in four areas: First, superior heat dissipation capability — a single cabinet supports up to 120kW, which is 5–10 times that of air cooling, suitable for high-density AI computing power. Second, high energy efficiency — data center PUE can be reduced below 1.15, saving over 30% energy compared to air cooling. Third, low noise — operating noise ≤ 60dB, improving the O&M environment. Fourth, high equipment reliability — chip temperatures are low with minimal fluctuation, extending IT equipment service life.
Q2: How to choose between cold plate and immersion liquid cooling?
A: Cold plate liquid cooling offers strong compatibility, directly adapting to standard servers with low retrofit costs, mature technology, and simple O&M — suitable for most data centers and AI cluster scenarios. Immersion liquid cooling provides higher heat dissipation density and lower PUE, but requires dedicated immersion servers, higher initial investment, and more complex O&M — suitable for supercomputing centers and extreme high-density computing scenarios. For existing data center retrofits, cold plate or rear-door heat exchange solutions are preferred.
Q3: Will liquid-cooled cabinets leak? Are they safe?
A: Liquid-cooled cabinets from reputable manufacturers undergo rigorous seal design and pressure testing; under normal operation, leakage will not occur. Our products adopt a three-level leak detection and protection system, with monitoring from chip level to cabinet level. Even trace leaks trigger alarms, supplemented by drain pans, emergency shut-off, and other protective measures. With proper installation and O&M, safety is guaranteed.
Q4: What coolant is used in liquid-cooled cabinets? Is it toxic?
A: The commonly used coolant is deionized water + ethylene glycol antifreeze; specialized fluorinated fluids are also available as an option. Ethylene glycol coolant is a low-toxicity substance with mild skin and eye irritation. Avoid direct contact and ingestion; under normal sealed operation, it poses no health hazard. Fluorinated fluids are insulating and non-toxic with higher safety, but at greater cost. All coolants meet environmental requirements and will not pollute the environment with standard use.
Q5: How many servers can one liquid-cooled cabinet accommodate?
A: This depends on individual server power and the cabinet cooling capacity. For example, a 50kW cold plate liquid-cooled cabinet with 5kW AI servers can hold 10 units; with 2kW general-purpose servers, it can hold 25 units. Cabinet U-space must also be considered — a 42U cabinet typically installs 10–20 servers.
15.2 Installation and Deployment
Q6: Can existing air-cooled data centers be converted to liquid cooling? Is the retrofit difficult?
A: Yes, conversion is possible with different retrofit levels: The simplest is the rear-door heat exchange solution, which directly replaces the cabinet rear door without modifying servers — short retrofit cycle and low cost. The next level is the cold plate solution, where server cold plates are replaced and the cabinet gains a liquid circuit system — slightly longer retrofit. If the data center already has a chilled water system, conversion becomes more convenient. A single cabinet retrofit typically takes 1–3 days without affecting other cabinets’ operation.
Q7: What data center facilities are required to support liquid-cooled cabinets?
A: A chilled water system (chiller + cooling tower/dry cooler) is required to provide the primary side cold source, along with the corresponding power distribution system, grounding system, and DCIM monitoring system. For built-in CDU models, only connection to the main chilled water header and power supply is needed; centralized CDU solutions require planning of the CDU room and main pipe routing.
Q8: Can liquid cooling pipes run under the raised floor? What precautions are needed?
A: Yes, pipes can run under the raised floor — a common pipe routing method in data centers. Points to note: Pipes must be properly fixed and supported to avoid deformation from stepping; interfaces should be located near maintenance access points; insulation should be provided to prevent condensation; leak detection cables should be installed for continuous monitoring; and safe distances from high-voltage power cables must be maintained.
Q9: Can liquid-cooled cabinets be used at high altitudes?
A: Yes, but with derating design. Above 2,000 meters altitude, thinner air reduces electrical component heat dissipation capability, requiring derated operation. Additionally, the coolant boiling point decreases, requiring corresponding adjustments to system pressure. Our company can provide altitude-customized models to ensure stable operation in plateau environments.
15.3 Operation and Maintenance
Q10: Is daily O&M of the liquid cooling system complex? Does it require dedicated personnel on-site?
A: Intelligent liquid-cooled cabinets are highly automated. Daily O&M mainly involves routine inspection of parameters and periodic filter cleaning — simple operations requiring no 24-hour dedicated staffing. The system supports remote monitoring with automatic alarm push. Ordinary data center O&M personnel can manage it after simple training; the additional workload compared to air-cooled systems is modest.
Q11: How often should coolant be replaced? Is replacement costly?
A: Under normal conditions, ethylene glycol coolant should be replaced every 2 years; with good water quality maintenance, this can be extended to 3 years. Replacement costs are not high — a single cabinet fill is approximately 50–100 liters, and the cost depends on the coolant type, constituting routine O&M expenditure.
Q12: Will coolant leak when servers are replaced or maintained?
A: No. The liquid cooling interfaces use double self-sealing quick connectors. When disconnected, both ends seal automatically — no dripping occurs after removal; when connected, flow resumes automatically. Server replacement does not cause leakage and is as simple as unplugging a network cable.
Q13: Is there a freeze risk during winter shutdown? How to prevent it?
A: If data center ambient temperature falls below 0°C, water in the pipes may freeze and crack equipment after shutdown. Anti-freezing measures: First, add ethylene glycol antifreeze with concentration configured according to the minimum temperature, ensuring the freezing point is below the ambient minimum; second, for long-term shutdown, drain the system liquid and blow dry with compressed air; third, maintain data center temperature above 0°C.
Q14: What should be done if the liquid cooling system scales up? How to clean it?
A: Using deionized water or dedicated coolant with periodic replacement effectively reduces scaling. If scaling has occurred, chemical cleaning can be used — circulate a dedicated descaling agent through the system, then flush thoroughly with clean water; plate heat exchangers can be disassembled for physical cleaning. Annual cleaning maintenance is recommended.
15.4 Technical Performance
Q15: What temperature control accuracy can liquid-cooled cabinets achieve?
A: Our intelligent liquid-cooled cabinets use PID closed-loop control with steady-state supply liquid temperature control accuracy of ±0.5°C. Chip temperature fluctuation can be controlled within ±1°C — significantly better than air-cooled systems, ensuring stable operation of high-performance chips.
Q16: How many cabinets can a single CDU support?
A: This depends on CDU cooling capacity and per-cabinet power. For example, a 100kW CDU can support 3 cabinets at 30kW each, or 2 cabinets at 50kW each. Centralized large CDUs can reach 500kW or more, supporting over a dozen cabinets. The specific configuration must be designed based on site conditions to ensure balanced flow and pressure to each cabinet.
Q17: Can waste heat from liquid cooling be recovered? How can it be utilized?
A: The liquid cooling system return water temperature is high (typically 30–45°C) with excellent heat quality, making it highly suitable for recovery. After temperature boosting with heat pumps, it can be used for building heating or domestic hot water supply, or directly for industrial process heating and agricultural greenhouse heating — further improving energy utilization and reducing carbon emissions.
Q18: How noisy are liquid-cooled cabinets? Can they be placed in office areas?
A: Cold plate liquid-cooled cabinets operate at approximately 58–62dB(A), over 10dB lower than ordinary air-cooled cabinets, comparable to normal office conversation. Immersion liquid cooling, having no fans, is even quieter at approximately 50dB. For office areas with moderate noise requirements, they can be installed; for strict requirements, soundproofing material can be added for further noise reduction.
15.5 After-Sales and Warranty
Q19: What is the warranty period? What does the warranty cover?
A: The complete machine warranty period is 12 months from the date of factory shipment. During the warranty period, quality issues not caused by human damage are repaired and parts replaced free of charge. Liquid circuit seals and wear parts are not covered by the lifetime warranty; normal wear-and-tear parts are replaced at the customer’s expense. Extended warranty services are available upon request.
Q20: How quickly can on-site support be provided for faults?
A: We provide 7×24-hour technical support services. After receiving a service request, we respond within 1 hour; on-site service within 24 hours in Guangdong Province, and within 48 hours in other domestic regions (remote areas excluded). Most faults can be resolved through remote guidance; major faults are handled by engineers dispatched to the site.
16.1 Acceptance Classification and Basis
16.1.1 Acceptance Classification
Intelligent liquid-cooled cabinet acceptance is divided into four stages: factory acceptance, on-site delivery acceptance, installation and commissioning acceptance, and completion acceptance. Each stage must be passed before proceeding to the next.
16.1.2 Acceptance Basis
- Purchase contract and technical agreement
- This product manual and product technical specification sheet
- “Technical Specification for Data Center Liquid Cooling Systems” T/CECS 1722-2024
- “Technical Requirements and Test Methods for Cold Plate Liquid-Cooled Cabinet Systems” T/TAF 324-2026
- Design and construction drawings and change documents
- Relevant national construction and acceptance specifications
16.2 Factory Acceptance
Factory acceptance is conducted at the production facility with participation from both the supplier and the purchaser. Acceptance items include:
Appearance and Structural Inspection: Cabinet appearance is smooth with no deformation, paint chipping, or rust; dimensions conform to drawings; doors open and close smoothly with intact locks; internal structural components are securely installed.
Component Configuration Verification: Against the configuration list, verify that the models, specifications, and quantities of the CDU, pumps, valves, sensors, monitoring system, and other components are consistent with the contract and are genuine original factory products.
Factory Performance Testing:
- Liquid circuit pressure test: 1.5 times working pressure held for 10 minutes with no leakage.
- Cooling performance test: Cooling capacity reaches ≥95% of rated value under rated conditions.
- Temperature control accuracy test: Steady-state control accuracy within ±0.5°C.
- Safety protection test: Leak, over-temperature, over-pressure, and other protection functions operate normally.
- Monitoring function test: Data display, parameter setting, and alarm functions operate normally.
Documentation Inspection: Product certificate of conformity, factory test report, manual, accessory list, and other documentation are complete.
After passing factory acceptance, both parties sign the factory acceptance report before the equipment is shipped.
16.3 On-Site Delivery Acceptance
Upon equipment arrival at the site, both parties jointly conduct delivery acceptance:
Outer Packaging Inspection: Check that the packaging is intact with no damage, water immersion, or impact marks; transport markings are clear.
Unpacking and Inventory: Against the packing list, verify the main unit, accessories, consumables, and documentation one by one; verify model, quantity, and specification.
Appearance Inspection: Check the equipment for transport damage; verify no deformation, damage, or leakage on the cabinet, pipes, glass, or electrical components.
Random Documentation Acceptance: Verify that the certificate of conformity, test report, manual, warranty card, and other documentation are complete.
Sign the delivery acceptance form upon passing; if damage, missing parts, or incorrect shipments are found, record the issues and the manufacturer shall arrange replacement or replenishment.
16.4 Installation and Commissioning Acceptance
After installation and commissioning are complete and the 72-hour trial operation has passed, conduct installation and commissioning acceptance:
16.4.1 Installation Quality Acceptance
Cabinet Installation: Cabinet position is correct and alignment is neat; levelness ≤ 1mm/m; verticality ≤ 1.5mm/m; secure fixation and reliable grounding.
Liquid Circuit Installation: Pipes are neatly routed and securely fixed; markings are clear with correct supply/return connections; valves are installed in correct positions and operate flexibly; welds and interfaces have no leakage; slope, venting, and drainage conform to specifications.
Electrical Installation: Wiring is neat with proper separation of power and signal cables; connections are secure with clear markings; insulation resistance and grounding resistance meet standards; protective devices are correctly configured.
Monitoring and Sensor Installation: Sensors are installed in correct positions and securely fixed; leak detection cable is laid out per specification; communication wiring is reliably connected.
Markings and Finished Product Protection: System markings are complete and clear; finished equipment is well protected with no damage or contamination.
16.4.2 Performance Indicator Acceptance
| Acceptance Item | Acceptance Standard | Test Method |
|---|---|---|
| System sealing integrity | No leakage at working pressure; pressure drop ≤ 0.03MPa over 12 hours | Close all branches, maintain system pressure, record pressure change, visually inspect for leakage |
| Rated cooling capacity | ≥ 95% of rated value | Measure supply/return liquid temperature difference and flow rate, calculate heat exchange capacity |
| Supply liquid temperature control accuracy | ±0.5°C | Steady-state operation for 30 minutes, record maximum and minimum supply liquid temperatures |
| System noise | ≤ rated value; ≤ 65dB(A) at 1 meter from cabinet | Measure with sound level meter at 1 meter from front, rear, left, and right of cabinet; take average |
| Flow uniformity | Branch flow deviation ≤ 5% | Measure each branch flow separately, calculate deviation rate |
| Grounding resistance | ≤ 0.1Ω | Measure with grounding resistance tester |
| Insulation resistance | ≥ 10MΩ | Measure power circuit with 500V megohmmeter |
16.4.3 Functional Acceptance
Operating Mode Switching: All operating mode switches function normally with smooth transitions and no impact.
Protection Functions: Over-temperature, over-pressure, leak, overload, and other protection actions are accurate with correct interlocking logic.
Redundancy Switching: Dual pump and dual power switching times meet requirements with no interruption during switching.
Monitoring Functions: Data display is accurate, parameter setting is effective, and historical data storage functions normally.
Remote Communication: Remote monitoring, alarm push, and data upload functions operate normally.
Leak Detection: 0.5mL of leakage triggers an alarm with accurate location identification.
16.4.4 Trial Operation Acceptance
1. Continuous 72-hour full-load operation with no faults, alarms, or leaks.
2. All operating parameters are stable and fluctuate within normal ranges.
3. IT equipment operates normally with chip temperatures meeting requirements and no overheating or frequency reduction.
4. Energy consumption indicators meet design requirements and PUE complies with agreed values.
16.5 Completion Acceptance
After the overall project is completed, completion acceptance is conducted as the final delivery acceptance:
Documentation Acceptance: Complete acceptance documentation is comprehensive and archived, including as-built drawings, installation records, commissioning records, test reports, acceptance records, product documentation, and operation training records.
On-Site Re-inspection: Conduct spot checks on key performance indicators to confirm satisfactory operating status.
Training Acceptance: Provide operation training to user O&M personnel and verify they pass assessment and possess independent O&M capability.
Issue Rectification: Any issues found during acceptance are rectified and pass re-inspection.
After all acceptance items pass, both parties sign the completion acceptance report, and the project is officially delivered, entering the warranty period.
16.6 Handling of Failed Acceptance Items
For general non-conforming items found during acceptance, issue a rectification notice specifying the rectification content and deadline. Re-conduct acceptance after rectification is complete.
For major quality issues that seriously affect performance, the equipment may be rejected, requiring the manufacturer to repair or replace.
For rectification that fails to meet requirements within the deadline, breach of contract liability shall be pursued in accordance with the contract agreement.
I. Search Keyword Classification
1. Core Primary Keywords
Smart liquid-cooled cabinet, liquid-cooled cabinet, cold plate liquid-cooled cabinet, immersion liquid-cooled cabinet, liquid-cooled server cabinet, data center liquid-cooled cabinet
2. High-Conversion Long-Tail Keywords
Smart liquid-cooled cabinet manufacturer, liquid-cooled cabinet factory, cold plate liquid-cooled cabinet price, immersion liquid-cooled cabinet cost, high-density liquid-cooled cabinet customization, data center liquid-cooled cabinet installation, liquid-cooled cabinet commissioning service, Guangdong liquid-cooled cabinet factory, Guangzhou liquid-cooled cabinet production, KITOZER liquid-cooled cabinet
3. Industry Traffic Keywords
Data center liquid cooling solutions, AI data center liquid cooling, high-density cabinet liquid cooling retrofit, liquid-cooled cabinet technical parameters, liquid-cooled cabinet working principle, liquid-cooled cabinet installation specification, liquid cooling system O&M, common liquid-cooled cabinet faults, liquid-cooled cabinet acceptance standards, data center PUE reduction solutions
4. Brand-Specific Keywords
Guangdong KITOZER liquid-cooled cabinet, KITOZER smart liquid-cooled cabinet, LA-LC liquid-cooled cabinet, KITOZER intelligent liquid-cooled cabinet, KITOZER cold plate liquid cooling, KITOZER immersion liquid cooling, KITOZER liquid-cooled cabinet factory, Guangzhou KITOZER liquid cooling equipment
5. Dropdown/Related Search Keywords
Liquid-cooled vs air-cooled cabinet differences, do liquid-cooled cabinets leak, what coolant is used in liquid-cooled cabinets, how to install and wire liquid-cooled cabinets, liquid-cooled cabinet commissioning steps, is liquid-cooled cabinet O&M difficult, liquid-cooled cabinet power density, liquid-cooled cabinet PUE value, liquid-cooled cabinet application scenarios, liquid-cooled cabinet selection guide
II. SEO Optimization Tag System
1. Title Tag
Smart Liquid-Cooled Cabinet_ Cold Plate/Immersion Liquid-Cooled Cabinet Manufacturer_ Installation, Wiring, and Commissioning Manual – Guangdong Lain Smart Data Center Equipment Co., Ltd.
2. Meta Keywords
Smart liquid-cooled cabinet, liquid-cooled cabinet manufacturer, cold plate liquid-cooled cabinet, immersion liquid-cooled cabinet, liquid-cooled cabinet installation and commissioning, data center liquid-cooled cabinet, Guangdong liquid-cooled cabinet manufacturer, KITOZER liquid-cooled cabinet
3. Meta Description
Guangdong Lain Smart Data Center Equipment Co., Ltd. professionally manufactures smart liquid-cooled cabinets, offering the full range of cold plate, immersion, and rear-door heat exchange liquid-cooled cabinet products covering the 15kW–120kW power range, suitable for AI computing centers, high-density data centers, and supercomputing centers. This manual provides comprehensive technical specifications including product introduction, principles and parameters, installation and wiring, commissioning and O&M, fault resolution, and acceptance standards. Factory direct sales with customization support. Service hotline: +86 13538869979.
4. H1 Tag
Smart Liquid-Cooled Cabinet Installation, Wiring, and Commissioning Manual
5. H2 Tags
Product Introduction, Product Composition, Product Classification, Product List, Product Working Principle, Product Technical Parameters, Product Functions and Features, Product Application Scenarios, Product Installation, Product Wiring, Product Commissioning, Product Precautions, Product Repair and Maintenance, Common Product Problems and Solutions, Product QA, Product Acceptance
6. Page Core Optimization Tags
Image ALT Tags: Smart liquid-cooled cabinet structure diagram, cold plate liquid cooling working principle diagram, liquid-cooled cabinet installation diagram, liquid-cooled cabinet wiring diagram
Strong Tags: Core keywords naturally bolded, including smart liquid-cooled cabinet, cold plate liquid-cooled cabinet, liquid-cooled cabinet manufacturer, etc.
III. Internal Link Optimization Tags (Natural Anchor Text Integration)
1. Core Anchor Text
Smart liquid-cooled cabinet, liquid-cooled cabinet, cold plate liquid-cooled cabinet, immersion liquid-cooled cabinet, liquid cooling system
2. Long-Tail Anchor Text
Smart liquid-cooled cabinet installation method, liquid-cooled cabinet wiring specification, liquid-cooled cabinet commissioning process, liquid-cooled cabinet repair and maintenance, high-density data center liquid cooling solution
3. Related Anchor Text
Shielding cabinet, outdoor smart cabinet, micro-module cold aisle, data center infrastructure monitoring system, precision air conditioning
This document is copyrighted by Guangdong Lain Smart Data Center Equipment Co., Ltd. and is protected by national copyright law. Any individual or organization may not reproduce, redistribute, adapt, excerpt, disseminate, or use this document for commercial purposes in any form without the company’s written authorization.
When reproducing or citing with authorization, the source must be credited as “Source: Guangdong Lain Smart Data Center Equipment Co., Ltd.,” and the original text must not be altered, abridged, or distorted in meaning.
The company reserves the right to pursue legal liability for infringement. If the content of this document is updated, no separate notice will be provided; the latest version published on the official website shall prevail.
Manufacturer: Guangdong Lain Smart Data Center Equipment Co., Ltd.
Service Hotline: +86 13538869979 (WeChat same number)
Technical Support: +86 13538869979
Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou
Official Website: https://gdlain.com