Manufacturer: Guangdong Lain Intelligent Computer Room Equipment Co., Ltd.
Document Version: V2.0
Release Date: July 2026
Applicable Models: LA-YL-XH Series Liquid Cooling Medium Circulation System (Compatible with LA-YL-JG Series Liquid Cooling Integrated Cabinets)
Table of Contents
TogglePreface

This manual is the official technical guidance document for the liquid cooling medium circulation system supporting the liquid cooling integrated cabinet, produced by Guangdong Lain Intelligent Computer Room Equipment Co., Ltd. (hereinafter referred to as “Lain Intelligent”). It specifies in detail the full-process technical requirements and operating specifications for the system, covering product familiarization, site acceptance inspection, installation and construction, electrical wiring, system commissioning, operation and maintenance, troubleshooting, and project acceptance.
This manual is compiled in accordance with national and industry standards including the *General Specification for Cold-plate Liquid Cooling Cabinets in Data Centers*, the *Technical Specification for Liquid Cooling Devices for Servers and Storage Equipment*, and the *Code for Design of Data Centers*. All operational procedures, technical parameters, and safety requirements have been repeatedly verified in the Lain Intelligent laboratory and validated through field engineering implementation, and may serve as the direct technical basis for project construction, supervision acceptance, and routine operation and maintenance.
All installation personnel, operation and maintenance personnel, and technical support staff must read this manual in full before commencing work, and strictly comply with the safety regulations and operational procedures contained herein. Improper operation may result in system leakage, heat exchange failure, equipment damage, or even personal injury accidents. Lain Intelligent assumes no warranty liability for equipment faults or property losses caused by failure to operate in accordance with this manual.
For technical support, please contact the Lain Intelligent official technical hotline: +86 13538869979; Business and service consultation: +86 13538869979 (WeChat same number).
Chapter 1 General Safety Regulations

1.1 Personal Safety Regulations
All on-site personnel must work with valid certifications: electricians must hold a valid low-voltage/high-voltage electrician operation certificate; pipeline welders must hold a welder qualification certificate for the corresponding material; personnel working at heights must hold a high-altitude work certificate.
The work site must be equipped with personal protective equipment including insulating gloves, safety goggles, cut-resistant gloves, anti-slip safety shoes, etc. Chemical-resistant gloves and safety goggles must be worn when handling coolant filling operations.
Electrical wiring operations must follow the “power off, verify no voltage, tag, and lock out” procedure. Live wiring is strictly prohibited. During system commissioning with live testing, two personnel must be present — one operator and one supervisor.
Smoking and open flames are strictly prohibited at the work site. Some coolant models are flammable (e.g., synthetic hydrocarbon immersion fluids). Appropriate types of fire extinguishing equipment must be available in the work area.
During system pressure testing, personnel must not stand directly in front of pipe joints, flanges, or valves to prevent personal injury from high-pressure spray.
Qualified lifting tools must be used for equipment hoisting and cabinet handling. Overloading is strictly prohibited, and no personnel shall stand beneath the lifting area.
1.2 Equipment Safety Regulations
Upon delivery, equipment must be stored in its original packaging. Storage environment temperature range: -10°C to 40°C, relative humidity ≤85%, free from corrosive gases, strong electromagnetic interference, and direct sunlight.
During handling, the equipment tilt angle must not exceed 30° to prevent seal fluid leakage from the circulation pump and displacement of the expansion tank diaphragm.
It is strictly prohibited to start the circulation pump without fluid in the system. Dry running will cause the mechanical seal to burn out from friction, which constitutes man-made damage and is not covered by warranty.
It is strictly prohibited to add coolant that does not match the specified model. Mixing different brands or types of coolant is prohibited to avoid chemical reactions that may cause corrosion, scaling, or blockage.
During system operation, it is strictly prohibited to disassemble pipes, joints, or valves without authorization, or to block heat dissipation vents or plug exhaust valves.
All parameter settings must be performed under the guidance of Lain Intelligent technical personnel. It is strictly prohibited to modify protection thresholds or bypass alarm signals without authorization.
1.3 Environmental Safety Regulations
The installation site must be equipped with a reliable grounding system with grounding resistance ≤1Ω. The equipment grounding terminal must be reliably connected to the machine room grounding grid.
The installation area must be equipped with leak detection and drainage facilities. The machine room floor must be waterproofed. It is recommended to configure a waterproof containment berm and leak detection cable beneath the cabinet.
The system operating environment must meet the design temperature and humidity requirements. Avoid prolonged operation in condensing environments. When necessary, enable the anti-condensation heating function.
Waste coolant must be disposed of in accordance with hazardous waste regulations by qualified units. It is strictly prohibited to pour coolant directly into drains or soil to avoid environmental pollution.
Chapter 2 Product Introduction

2.1 Product Definition and Positioning
The Lain LA-YL-XH Series Liquid Cooling Medium Circulation System is the core thermal management subsystem of the liquid cooling integrated cabinet. It is a cabinet-level closed-loop liquid cooling solution specifically designed for the heat dissipation requirements of high power density IT equipment, computing equipment, and industrial control equipment. The system uses coolant as the heat transfer medium, efficiently extracting heat generated by equipment heat-generating components through a closed loop and releasing it to an external cold source, achieving precise temperature control of the thermal load inside the cabinet.
The system integrates six major functional modules: circulation power, heat exchange regulation, filtration and purification, pressure compensation, intelligent monitoring, and safety protection. It is deeply integrated with the liquid cooling integrated cabinet, with pre-installation and factory testing completed before shipment. On-site, only external pipe connection and electrical wiring are required for rapid deployment, significantly reducing on-site construction difficulty and duration.
2.2 Industry Background and Technical Value
With the rapid popularization of AI computing power, high-performance computing, and high-density servers, the thermal load per cabinet has risen from the traditional 5–10kW to 30–100kW or even higher. Traditional air cooling technology has approached its heat dissipation limits, presenting issues such as high energy consumption, high noise, low temperature control accuracy, and inability to accommodate ultra-high-density computing equipment. Liquid cooling technology, leveraging the physical properties of high specific heat capacity and high thermal conductivity of liquid media, has become the mainstream technical approach for solving high-density heat dissipation challenges.
The Lain Intelligent liquid cooling medium circulation system is optimized for cabinet-level application scenarios and offers the following core advantages over centralized liquid cooling solutions:
Flexible Deployment: Independent circulation per cabinet, eliminating the need for large-scale machine room piping renovation; suitable for both retrofitting existing machine rooms and rapid deployment in new machine rooms.
Excellent Energy Efficiency: Utilizing variable frequency control and natural cold source linkage technology, the system’s energy efficiency ratio far exceeds that of traditional air cooling, helping data centers reduce PUE to below 1.15.
Safety and Reliability: Fully closed-loop design with multiple leak detection and protection mechanisms, eliminating the risk of coolant leakage; redundant design of critical components ensures continuous and stable system operation.
Intelligent Operation and Maintenance: Equipped with an IoT monitoring platform supporting remote parameter monitoring, fault alarming, energy efficiency analysis, and predictive maintenance, reducing operational complexity and costs.
Broad Compatibility: Supports multiple liquid cooling architectures including cold-plate, rear-door, and immersion types, compatible with X86 servers, GPU computing clusters, storage equipment, industrial control equipment, and various other loads.
2.3 Product Design Philosophy
Reliability First: All core components are manufactured to industrial-grade or higher specifications, having undergone continuous operation testing for over 10,000 hours. The system’s Mean Time Between Failures (MTBF) is ≥100,000 hours.
Modular Design: The pump set, filters, heat exchanger, and control unit all adopt modular structures, supporting online maintenance and rapid replacement to reduce fault downtime.
Standardized Adaptation: Strictly complies with industry-standard interface specifications, compatible with mainstream brand server cold plates and primary-side cold source systems, enabling rapid integration without custom modification.
Full Lifecycle Optimization: The entire process from installation, operation, maintenance to upgrade and replacement is considered to reduce total lifecycle costs and improve return on investment.
Green and Environmentally Friendly: Eco-friendly coolant is selected, and the low-energy operation design complies with the energy-saving and carbon-reduction requirements for data centers under China’s dual carbon policy.
2.4 Product Model Naming Convention
The Lain liquid cooling medium circulation system model uses a unified naming convention for users to quickly identify product specifications:
LA - YL - XH - □□□ - □ │ │ │ │ └── Temperature Control Type: 1=Cooling only, 2=Heating and cooling dual control │ │ │ └──────── Rated Heat Exchange Power, unit: kW │ │ └────────────── Product Series: XH=Circulation System │ └─────────────────── Technology Route: YL=Liquid Cooling └──────────────────────── Brand Abbreviation: LA=Lain
Example: LA-YL-XH-50-2 indicates a Lain liquid cooling series circulation system with a rated heat exchange power of 50kW and dual heating and cooling control.
2.5 Applicable Product Standards
The design, production, and inspection of this product comply with the following standard documents:
| Standard No. | Standard Name |
|---|---|
| GB/T 50174-2017 | Code for Design of Data Centers |
| GB/T 39663-2020 | Liquid cooling distribution unit for computer and data processing rooms |
| T/CESA 1249.2-2023 | Technical specification for liquid cooling devices for servers and storage equipment — Part 2: Connection systems |
| GB 50236-2011 | Code for construction of field equipment, industrial pipe welding engineering |
| GB 50303-2015 | Code for acceptance of quality of construction of building electrical engineering |
| GB/T 13306-2011 | Plates |
| JB/T 8690-2014 | Industrial pumps — Noise limits |
Chapter 3 Product Composition
The Lain LA-YL-XH Series Liquid Cooling Medium Circulation System is an integrated closed-loop circulation unit, composed of eight core subsystems that work collaboratively to achieve coolant circulation, temperature regulation, purification and filtration, pressure compensation, and status monitoring.
3.1 Circulation Power Subsystem
The circulation power subsystem provides the power source for coolant flow, delivering stable flow rate and head to the entire circulation loop — the “heart” of the system.
Main Circulation Pump
- Industrial-grade vertical/horizontal centrifugal pump with 304 stainless steel pump casing and closed impeller design for high efficiency and excellent anti-cavitation performance.
- Equipped with a permanent magnet variable frequency motor, supporting 0–100% stepless speed regulation, automatically adjusting flow rate based on load changes for energy-saving operation.
- Mechanical seal made of silicon carbide-graphite, compatible with water-based, ethylene glycol, and fluorinated fluids; long service life and low leakage risk.
- Standard configuration includes pump body temperature sensor and vibration sensor for real-time pump status monitoring and early warning in case of abnormality.
Standby Circulation Pump (standard on redundant models)
- Identical specifications to the main pump; duty/standby design with automatic switchover to the standby pump upon main pump failure, ensuring continuous system operation.
- Supports scheduled rotation function with configurable daily/weekly automatic switching between main and standby pumps to prevent component aging from single-pump prolonged operation.
Pump Inlet and Outlet Valves
- Y-type strainer and manual gate valve at the inlet; check valve and manual butterfly valve at the outlet.
- The check valve prevents coolant backflow during shutdown, avoiding pump reverse rotation damage; the gate/butterfly valves isolate piping for maintenance, enabling maintenance under pressure.
Inlet/Outlet Flexible Connections
- Rubber flexible joints at pump inlet and outlet to absorb pump operating vibration and prevent vibration transmission to piping, which could cause resonance and noise.
3.2 Heat Exchange Regulation Subsystem
The heat exchange regulation subsystem is responsible for regulating coolant temperature, cooling the high-temperature coolant after heat absorption to the set temperature — the core guarantee of system temperature control accuracy.
Plate Heat Exchanger
- Stainless steel brazed plate heat exchanger with 316L stainless steel plates; corrugated plate design provides high heat exchange efficiency, compact size, and light weight.
- Complete isolation between primary and secondary sides, preventing cross-contamination of media on both sides; pressure rating ≥1.6MPa, suitable for most machine room operating conditions.
- Removable/cleanable structure available (serviceable models); after long-term scaling, plates can be disassembled and cleaned to restore heat exchange performance.
Electric Control Valve
- Proportional-integral electric three-way or two-way control valve with high-precision stepper motor actuator; regulation accuracy ≤1%.
- Automatically regulates primary-side cold source flow based on secondary-side supply temperature, achieving precise supply temperature control with accuracy up to ±0.5°C.
Bypass Piping
- Supply/return bypass piping with bypass valve configured; under low-load conditions, a portion of return water directly mixes with supply water, avoiding temperature fluctuation caused by excessive heat exchanger cooling.
- Also serves system pressure relief and low-flow protection functions, preventing pump cavitation under low flow conditions.
PTC Electric Heater (standard on heating and cooling dual-control models)
- Insulated PTC ceramic heating element with water-electricity separation for safety and reliability; used to preheat coolant in low-temperature environments, preventing pump damage caused by excessive viscosity during cold starts.
- Equipped with over-temperature protection — automatic power-off when temperature exceeds threshold; supports multi-level power regulation.
3.3 Filtration and Purification Subsystem
The filtration and purification subsystem removes solid impurities, metal particles, and colloidal sediment from the coolant, protecting the circulation pump and cold plate micro-channels from blockage and extending system service life.
Main Line Filter
- Installed before the circulation pump inlet; stainless steel filter housing with high-precision pleated filter cartridge, filtration rating 10μm.
- Equipped with differential pressure transmitter for real-time monitoring of inlet/outlet pressure differential; automatic alarm when differential pressure exceeds 0.1MPa, indicating filter cartridge replacement is required.
- Drain valve at filter bottom for periodic discharge of accumulated sediment.
Branch Precision Filter (optional)
- For cold plate micro-channel applications, a 5μm precision filter is installed on the cabinet branch circuit to further filter fine particles and prevent micro-channel blockage.
Ion Exchange Tank (optional, for deionized water media)
- Contains cation exchange resin that continuously adsorbs metal ions from the coolant, maintaining low coolant conductivity and ensuring electrical safety.
- Equipped with conductivity sensor for real-time coolant conductivity monitoring; prompts resin replacement when limits are exceeded.
3.4 Pressure Compensation Subsystem
The pressure compensation subsystem buffers the volume expansion and contraction of coolant caused by temperature changes, maintaining system pressure stability and preventing overpressure or negative pressure air ingress.
Diaphragm Expansion Tank
- Carbon steel tank body with EPDM rubber diaphragm; gas chamber pre-charged with nitrogen, fully isolated from coolant with no corrosion risk.
- Tank volume selected based on total system water volume to ensure system pressure fluctuation remains within allowable range across the full temperature range.
- Equipped with pressure gauge and charging valve for real-time pressure observation and periodic nitrogen replenishment.
Automatic Water Make-up Valve
- Connected to external water supply (deionized water/antifreeze); automatically adds water when system pressure drops below the set value, maintaining system pressure stability.
- Built-in check valve and strainer to prevent media backflow and impurity ingress into the system.
Safety Valve
- Installed on the system high-pressure side; automatically opens to relieve pressure when system pressure exceeds the safety threshold, protecting piping and equipment from overpressure damage.
- Trip pressure adjustable based on system working pressure; factory-calibrated — field adjustment strictly prohibited.
Automatic Air Vent Valve
- Installed at the highest point of the system; automatically discharges air accumulated in the circulation loop, preventing air locks and cavitation.
- Float-type design; automatically seals after venting to prevent coolant overflow.
3.5 Piping and Connection Subsystem
The piping and connection subsystem serves as the coolant delivery channel, connecting all functional components to form a complete closed circulation loop.
Main Circuit Piping
- System internal main piping uses 304 stainless steel seamless steel pipe, wall thickness meets pressure requirements, interior passivated for corrosion resistance and scale resistance.
- Piping welded using argon arc welding process; welds subjected to penetration testing to ensure leak-free; pipe supports use anti-vibration design to reduce operating noise.
Quick Couplings
- External cabinet interfaces use self-sealing quick couplings that automatically seal upon insertion/removal, providing leak-free connection/disconnection for rapid cabinet integration and maintenance.
- Coupling material: 316 stainless steel; sealing ring: fluororubber, resistant to various coolant corrosions; insertion/removal service life ≥1000 cycles.
Valve Assemblies
- Includes main supply valve, main return valve, branch regulating valves, drain valves, and air vent valves for system isolation, flow regulation, and maintenance.
- Valve materials consistent with piping; reliable sealing, low operating torque, long service life.
Insulation Layer
- Low-temperature piping wrapped with rubber-plastic insulation ≥20mm thick, covered with aluminum foil protective layer to prevent surface condensation and minimize cooling capacity loss.
3.6 Status Detection Subsystem
The status detection subsystem consists of various sensors that collect system operating parameters in real time, providing data basis for the control system and enabling abnormal condition alarming.
Temperature Sensors
- Supply Water Temperature Sensor: Installed at the secondary side supply outlet, detecting coolant temperature supplied to the load — the core basis for temperature control.
- Return Water Temperature Sensor: Installed at the secondary side return inlet, detecting returning coolant temperature, used for calculating heat exchange capacity and load rate.
- Primary Side Inlet/Outlet Temperature Sensors: Monitor cold source operating conditions and determine whether the cold source is functioning normally.
- Pump Body Temperature Sensor: Monitors motor and mechanical seal temperature to prevent overheat damage.
- Ambient Temperature and Dew Point Sensor: Monitors machine room environmental temperature and humidity, calculates dew point temperature, and enables anti-condensation control.
Pressure/Differential Pressure Sensors
- Supply Pressure Sensor and Return Pressure Sensor: Monitor system supply and return pressure, calculate system differential pressure, and determine whether piping is blocked or leaking.
- Filter Differential Pressure Sensor: Monitors filter blockage level and prompts filter cartridge replacement.
- Expansion Tank Pressure Sensor: Monitors system static pressure and determines whether water make-up is needed.
Flow Sensor
- Electromagnetic flowmeter or turbine flowmeter installed on the secondary side main circuit, monitoring coolant circulation flow in real time with accuracy of ±0.5%.
- Supports low flow alarm; automatically triggers protection when flow is insufficient.
Level Sensor
- Installed in the expansion tank/fill tank to monitor coolant level; alarms and automatically makes up water when level is too low.
Leak Detection Sensors
- Leak detection cables and point-type leak sensors are arranged at leak-prone locations including cabinet bottom, pipe joints, and valves; immediate alarm and optional linked shutdown upon leak detection.
Conductivity Sensor (optional)
- Monitors coolant conductivity to assess coolant contamination level and ion concentration, ensuring electrical safety.
3.7 Intelligent Control Subsystem
The intelligent control subsystem is the “brain” of the entire circulation system, receiving sensor signals and regulating actuators through control algorithms to achieve fully automatic system operation and intelligent protection.
Main Controller
- Industrial-grade PLC controller with 7-inch color touchscreen display; user-friendly interface and intuitive operation.
- Built-in PID temperature control algorithm with fast response and high temperature control accuracy; supports multiple control mode switching.
- Strong expansion capability for integrating additional sensors and actuators; supports customized function development.
Human-Machine Interface (HMI)
- Touchscreen displays real-time operating parameters: supply/return temperature, pressure, flow rate, pump speed, valve opening, operating status, etc.
- Supports parameter settings, operating mode switching, historical data query, fault record query, and alarm threshold settings.
- Multi-level permission management with separation of ordinary operator and administrator permissions to prevent misoperation.
Communication Module
- Standard RS485 communication interface with Modbus-RTU protocol; optional Ethernet, 4G/5G modules with Modbus-TCP and MQTT protocol support.
- Can integrate with machine room DCIM (Data Center Infrastructure Management) systems and BAS (Building Automation Systems) for centralized monitoring and remote management.
Protection Logic
- Built-in multiple protection functions: over-temperature protection, low-temperature protection, over-pressure protection, low-pressure protection, low-flow protection, pump overload protection, leak protection, power-off memory, auto-restart upon power restoration, etc.
- Tiered fault alarming: general faults trigger alarms only without shutdown; serious faults trigger immediate shutdown protection to prevent fault escalation.
3.8 Cabinet Integration Subsystem
All components of the liquid cooling medium circulation system are integrated inside a standard cabinet, designed integrally with the IT cabinet for unified appearance and convenient deployment.
Cabinet Enclosure
- High-quality cold-rolled steel plate, thickness ≥1.5mm, surface electrostatic powder coating for corrosion and wear resistance; protection rating IP20.
- Cabinet dimensions compatible with standard 19-inch racks; color options include black, white, and gray to match the machine room overall style.
Mounting Racks
- Internal galvanized mounting rails and mounting plates; components firmly secured with rational layout and ample maintenance space reserved.
Cabling and Raceways
- Separation of high-voltage and low-voltage wiring; dedicated cable trays and cable tie bars for neat, standardized wiring that facilitates inspection.
Piping Layout
- Piping layout follows the principles of short routing and minimal elbows to reduce flow resistance and improve system energy efficiency.
Lighting and Maintenance Receptacle
- Interior configured with LED lighting and maintenance power receptacle for convenient routine maintenance and fault repair.
Chapter 4 Product Checklist
4.1 Main Equipment Checklist (Take LA-YL-XH-50-2 as an example)
| No. | Component Name | Specification/Model | Material | Unit | Qty | Remarks |
|---|---|---|---|---|---|---|
| 1 | Circulation system main cabinet | 600mm×1000mm×2000mm, standard 19-inch rack | Cold-rolled steel sheet, electrostatic powder coated | Set | 1 | Includes cabinet body, mounting rails, doors, door locks |
| 2 | Main circulation pump | Rated flow 15m³/h, head 20m, power 1.5kW, variable frequency | 304 stainless steel body, silicon carbide seal | Unit | 1 | Industrial centrifugal pump |
| 3 | Standby circulation pump | Rated flow 15m³/h, head 20m, power 1.5kW, variable frequency | 304 stainless steel body, silicon carbide seal | Unit | 1 | Duty/standby redundancy |
| 4 | Plate heat exchanger | Heat exchange power 50kW, primary/secondary side isolated | 316L stainless steel plates | Unit | 1 | Brazed type |
| 5 | Electric three-way control valve | DN40, proportional-integral type, regulation accuracy 1% | Brass body, stainless steel trim | Unit | 1 | For heating/cooling dual control |
| 6 | PTC electric heater | Power 3kW, multi-level regulation, over-temperature protection | Ceramic PTC, stainless steel housing | Unit | 1 | For low-temperature preheating |
| 7 | Diaphragm expansion tank | Volume 50L, pre-charge pressure 0.2MPa | Carbon steel body, EPDM diaphragm | Unit | 1 | Pressure compensation |
| 8 | Main line filter | DN40, filtration rating 10μm, with differential pressure switch | 304 stainless steel housing, PP filter cartridge | Piece | 1 | Pump inlet protection |
| 9 | Automatic water make-up valve | DN15, set pressure 0.15MPa, with check and strainer | Brass | Piece | 1 | Automatic make-up |
| 10 | Safety valve | DN20, trip pressure 0.6MPa | Brass | Piece | 1 | Over-pressure protection |
| 11 | Automatic air vent valve | DN15, float type | Brass | Piece | 2 | High-point venting |
| 12 | Supply water temperature sensor | PT100, Class A accuracy | Stainless steel housing | Unit | 1 | Secondary side supply |
| 13 | Return water temperature sensor | PT100, Class A accuracy | Stainless steel housing | Unit | 1 | Secondary side return |
| 14 | Pressure sensor | Range 0~1MPa, accuracy 0.5% | Stainless steel diffused silicon | Unit | 2 | One each for supply and return |
| 15 | Electromagnetic flowmeter | DN40, accuracy ±0.5% | 304 stainless steel | Unit | 1 | Flow monitoring |
| 16 | Leak sensor | Point type + 3m sensing cable | ABS housing | Set | 1 | Leak detection |
| 17 | PLC controller | Industrial grade, 32-point I/O | — | Set | 1 | Includes CPU, I/O modules |
| 18 | Touchscreen display | 7-inch color touch screen | — | Unit | 1 | Human-machine interface |
| 19 | Electrical control components | Circuit breakers, contactors, relays, terminals, etc. | — | Set | 1 | Includes electrical cabinet |
| 20 | Internal piping and valves | DN40 main piping, including gate valves, check valves, flexible connections, etc. | 304 stainless steel | Set | 1 | Pre-installed at factory |
| 21 | Insulation layer | Rubber-plastic insulation + aluminum foil | — | Set | 1 | Low-temperature piping insulation |
4.2 Random Accessories Checklist
| No. | Accessory Name | Specification | Unit | Qty | Purpose |
|---|---|---|---|---|---|
| 1 | Spare filter cartridge | 10μm, suitable for main filter | Piece | 2 | Filter replacement |
| 2 | Dedicated seal kit | Suitable for various joint and valve models | Pack | 1 | Seal replacement |
| 3 | Dedicated tools | Wrenches, screwdrivers, hex key set | Set | 1 | Installation and maintenance |
| 4 | Coolant | Lain dedicated coolant, 20L/barrel | Barrel | 2 | System filling (optional) |
| 5 | Leak detection test paper | Fluorescent detection type | Box | 1 | Leak point inspection |
| 6 | Grounding terminals and bolts | M8 copper terminals, bolts and washers | Set | 1 | Electrical grounding |
| 7 | Identification labels | Pipe labels, electrical labels | Set | 1 | System identification |
4.3 Included Documentation List
| No. | Document Name | Version | Copies | Remarks |
|---|---|---|---|---|
| 1 | Liquid cooling medium circulation system installation, wiring and commissioning manual | V2.0 | 1 | Paper + Electronic |
| 2 | Product certificate of conformity | — | 1 | Includes factory inspection report |
| 3 | Electrical schematic diagram | — | 1 | Paper version |
| 4 | Piping system diagram | — | 1 | Paper version |
| 5 | Component warranty card | — | 1 | Effective upon stamping |
| 6 | Packing list | — | 1 | Accompanying shipment |
4.4 Optional Accessories List
| No. | Accessory Name | Specification | Purpose |
|---|---|---|---|
| 1 | Branch precision filter | 5μm rating | Protect cold plate micro-channels |
| 2 | Ion exchange tank | 2L resin | Maintain deionized water conductivity |
| 3 | Conductivity sensor | 0~20μS/cm | Coolant conductivity monitoring |
| 4 | 4G communication module | Full network compatible | Remote wireless monitoring |
| 5 | Cloud monitoring platform license | 1 year / 3 years / perpetual | Remote O&M, data analysis |
| 6 | Quick coupling extension pipe | 1m / 2m / 5m | Pipe extension and connection |
| 7 | Waterproof containment berm | Matches cabinet dimensions | Leak containment protection |
| 8 | Spare pump seal kit | Suitable for corresponding pump model | Pump seal maintenance |
4.5 Receiving Inspection Instructions Upon Delivery
1. Upon equipment delivery, immediately check goods against the packing list, verifying that the main unit, accessories, and documentation are complete and that the appearance shows no transportation damage.
2. If missing, damaged, or mismatched items are found, immediately contact the logistics provider to issue a proof document and contact Lain Intelligent business personnel within 24 hours for resolution.
3. Verify the nameplate information on the equipment; confirm that the model, specification, and factory serial number are consistent with the contract.
4. After acceptance, properly store the equipment and accessories in a dry, ventilated indoor environment, avoiding moisture, impact, and direct sunlight.
Chapter 5 Product Operating Principle
5.1 Core Heat Exchange Principle
The physical foundation of liquid cooling is that the specific heat capacity and thermal conductivity of liquids are far higher than those of air. At room temperature, the specific heat capacity of water is approximately 4200 J/(kg·°C), more than four times that of air; the thermal conductivity is approximately 0.6 W/(m·K), more than 20 times that of air. This means that the same volume of liquid can carry much more heat with faster heat transfer rates. Therefore, liquid cooling systems can remove large amounts of heat with smaller volumes and lower flow rates, making them suitable for high-density heat dissipation scenarios.
The Lain liquid cooling medium circulation system adopts an indirect heat exchange closed-loop architecture. The entire system is divided into two independent circulation loops: the secondary-side (load-side) circulation loop and the primary-side (cold-source-side) circulation loop. The two loops exchange heat through the plate heat exchanger without direct contact, preventing impurities and corrosive substances from the cold source side from entering the load side and protecting IT equipment safety.
5.2 Secondary Side Circulation Workflow
The secondary side circulation is the loop directly connected to the cold plates/heat exchange components of the IT equipment inside the cabinet, and is the core control loop of this system. The workflow is as follows:
1. Pressurized Delivery: Low-temperature coolant is pressurized by the circulation pump, flows out from the pump outlet, passes through the filter for impurity removal, and is delivered through the supply main piping to the water distributor inside the cabinet.
2. Flow Distribution: The water distributor evenly distributes coolant to the cold plate branches of each server, with each branch valve adjustable to ensure sufficient coolant flow to every device.
3. Heat Absorption and Exchange: When coolant flows through the cold plates on the surface of heat-generating components such as CPUs and GPUs, it absorbs heat from the devices through convective heat exchange. The device temperature decreases while the coolant temperature rises.
4. Return Collection: The high-temperature coolant after heat absorption flows out from the cold plates, is collected by the water collector, and flows back through the return main piping to the circulation system main unit.
5. Cooling: The high-temperature return water enters the secondary side channels of the plate heat exchanger, where heat is exchanged with the low-temperature cold source on the primary side, reducing the coolant temperature to the set value.
6. Cycle Repetition: The cooled coolant re-enters the circulation pump inlet and begins the next cycle, continuously carrying heat away from the IT equipment.
During circulation, the expansion tank continuously compensates for coolant volume changes caused by temperature variations: when temperature rises, the coolant volume expands and excess fluid enters the expansion tank, compressing the gas chamber; when temperature drops, the coolant volume contracts and the nitrogen in the expansion tank pushes the diaphragm to press fluid back into the system, maintaining system pressure stability. The automatic air vent valve continuously discharges gas precipitated from the loop, preventing air locks and cavitation.
5.3 Primary Side Circulation Workflow
The primary side circulation is the cold source side loop, responsible for transferring heat from the secondary side to the external cold source system (such as cooling towers, chillers, dry coolers, etc.) and rejecting it to the outdoor environment. The workflow is as follows:
1. Primary-side low-temperature chilled water enters the circulation system’s primary side inlet from the external cold source system, passes through the electric control valve for flow regulation, and enters the primary side channels of the plate heat exchanger.
2. Inside the plate heat exchanger, the primary-side chilled water absorbs heat from the secondary-side high-temperature coolant and its temperature rises.
3. The heated primary-side return water flows out from the system’s primary side outlet, returns to the external cold source system, and is cooled by the cooling tower/chiller before circulating again.
4. The electric control valve automatically adjusts its opening based on the secondary side supply temperature: when the secondary side supply temperature is too high, the valve opens wider to increase primary-side chilled water flow and enhance heat exchange; when temperature is too low, the valve closes partially to reduce cooling capacity input and maintain temperature stability.
5.4 Intelligent Control Principle
The system employs a PID closed-loop control algorithm with the secondary side supply temperature as the control target and the electric control valve opening and circulation pump speed as control variables, achieving precise temperature control and energy-saving operation. The control logic is as follows:
Temperature Control Loop: Temperature sensors collect the secondary side supply temperature in real time and compare it with the set temperature value to calculate the deviation. The PID controller outputs control signals based on three parameters — deviation magnitude, deviation change rate, and cumulative deviation — to adjust the electric control valve opening, stabilizing the supply temperature near the set value with control accuracy of ±0.5°C.
Flow Control Loop: The flow sensor monitors the system total flow in real time, combined with the supply/return temperature difference to calculate the current actual heat exchange rate and load ratio. When load decreases, the variable frequency drive reduces the circulation pump speed, decreasing flow and reducing pump energy consumption; when load increases, the pump speed is increased to provide more flow and meet heat dissipation demand. Through variable frequency regulation, the system supports a wide load adaptation range of 20%~100%, significantly improving energy efficiency under partial loads.
Protection Control Logic: The controller continuously scans all sensor data; when parameters exceed the normal range, corresponding protection actions are executed based on fault level:
- Warning Level Faults (e.g., filter differential pressure slightly high, liquid level slightly low): Audible/visual and remote alarms triggered to notify O&M personnel, system continues operating.
- General Faults (e.g., temperature slightly high, pressure slightly high): Automatic adjustment of operating parameters to increase cooling output, alarm triggered simultaneously, continued observation.
- Serious Faults (e.g., leak detected, extremely low flow, pump overload, over-temperature): Immediate shutdown of the circulation pump, closure of relevant valves, emergency alarm triggered, and when necessary, coordinated IT equipment frequency reduction or shutdown to prevent equipment damage.
5.5 Special Operating Condition Principles
5.5.1 Low-Temperature Cold Start Condition
When the ambient temperature is too low and the coolant temperature is below the set cold-start temperature, the system activates the low-temperature protection mode:
- The circulation pump operates at minimum speed in low-speed mode, and the PTC electric heater turns on to slowly heat the coolant.
- After the coolant temperature rises above the safe start temperature and viscosity returns to the normal range, the pump speed is gradually increased to return to normal operation.
- This mode prevents pump overload and accelerated mechanical seal wear caused by excessive coolant viscosity at low temperatures, extending pump service life.
5.5.2 Free Cooling Condition
When the external ambient temperature is low and the primary-side cold source can provide sufficiently low-temperature cooling water, the system automatically switches to free cooling mode, shutting down the chiller compressor and relying solely on the cooling tower or dry cooler for cooling capacity, significantly reducing cooling energy consumption. During this time, the circulation system maintains normal secondary side circulation and temperature control without manual intervention.
5.5.3 Power Failure and Restoration Condition
The system has power-off memory functionality — all operating and setting parameters before power loss are automatically saved in the controller memory and are not lost. Upon power restoration, the system can be configured for either manual start or automatic start:
- Automatic Start Mode: After power restoration, the system automatically starts after a configurable delay (default 30 seconds), operating according to pre-power-loss parameters, suitable for unattended machine rooms.
- Manual Start Mode: After power restoration, the system remains in standby requiring manual confirmation to start, suitable for attended locations with high safety requirements.
5.5.4 Main/Standby Pump Switchover Condition
For models configured with redundant pump sets, the main pump operates during normal operation while the standby pump remains on standby. The system automatically switches to the standby pump under the following conditions:
- Main pump overload, over-temperature, or output fault signal.
- System flow continuously below threshold, indicating main pump failure.
- Scheduled rotation time reached.
The switchover process is smooth: the standby pump is started first, and the main pump is shut down only after the standby pump is operating stably, preventing system flow interruption and ensuring continuous heat dissipation for IT equipment.
Chapter 6 Product Technical Parameters
6.1 Overall Unit Performance Parameters (LA-YL-XH Series Common Parameters)
| Parameter Category | Parameter Item | Technical Specification | Remarks |
|---|---|---|---|
| Heat Exchange Performance | Rated heat exchange power | 20kW / 30kW / 50kW / 80kW / 100kW / 150kW | Multiple specifications, customizable |
| Temperature control range | 15°C ~ 45°C | Continuously adjustable | |
| Temperature control accuracy | ±0.5°C | Under steady-state conditions | |
| Supply/return temperature difference | 5°C ~ 10°C | 5°C at rated conditions | |
| Circulation Parameters | Rated flow rate | 6m³/h ~ 50m³/h | Corresponding to different power models |
| Rated head | 15m ~ 30m | High-head models customizable | |
| System working pressure | 0.15MPa ~ 0.4MPa | Normal operating range | |
| Maximum pressure rating | 1.0MPa | Factory hydrostatic test at 1.6MPa | |
| Electrical Parameters | Rated voltage | 380V±10%, three-phase five-wire, 50Hz | 220V single-phase available for low power |
| Total power | 2.5kW ~ 12kW | Including pumps, heating, control | |
| Control power supply | 24V DC | Safety extra-low voltage control | |
| Grounding requirement | Grounding resistance ≤1Ω | TN-S grounding system | |
| Environmental Adaptability | Operating ambient temperature | 5°C ~ 40°C | Storage temperature -10°C ~ 50°C |
| Operating ambient humidity | 20% ~ 85% RH | Non-condensing | |
| Altitude | ≤2000m | Derating required above 2000m | |
| Physical Parameters | Cabinet dimensions (W×D×H) | 600mm×1000mm×2000mm / 800mm×1200mm×2000mm | Standard 19-inch rack |
| Unit weight | 280kg ~ 650kg | Excluding coolant | |
| Protection rating | IP20 | Indoor type | |
| Reliability | Mean Time Between Failures (MTBF) | ≥100,000 hours | Industrial-grade design |
| Design service life | ≥15 years | Under normal maintenance conditions | |
| Noise | Operating noise | ≤55dB(A) | At 1 meter from equipment |
6.2 Core Component Technical Parameters
6.2.1 Circulation Pump Parameters
| Parameter Item | Technical Specification |
|---|---|
| Pump type | Vertical/horizontal centrifugal pump, closed impeller |
| Pump body material | 304 stainless steel |
| Impeller material | 304 stainless steel |
| Mechanical seal | Silicon carbide-graphite, spring-loaded |
| Motor type | Permanent magnet synchronous variable frequency motor, IP55 protection |
| Motor insulation class | Class F |
| Regulation range | 0~100% speed stepless regulation |
| Allowable media temperature | -10°C ~ 90°C |
| Maximum allowable working pressure | 1.0MPa |
| Bearing life | ≥40,000 hours |
6.2.2 Plate Heat Exchanger Parameters
| Parameter Item | Technical Specification |
|---|---|
| Type | Brazed plate heat exchanger (serviceable type optional) |
| Plate material | 316L stainless steel |
| Gasket material | Nitrile rubber / fluororubber |
| Maximum working pressure | 1.6MPa |
| Maximum working temperature | 150°C |
| Heat transfer coefficient | ≥3000 W/(m²·°C) |
| Pressure drop | ≤50kPa |
| Connection size | DN32 ~ DN100 |
6.2.3 Expansion Tank Parameters
| Parameter Item | Technical Specification |
|---|---|
| Type | Diaphragm-type pressure tank |
| Tank body material | Carbon steel, epoxy spray anti-corrosion coating |
| Diaphragm material | EPDM rubber |
| Pre-charge gas | Nitrogen |
| Working temperature range | -10°C ~ 90°C |
| Maximum working pressure | 1.0MPa |
| Volume series | 25L / 50L / 100L / 200L |
6.2.4 Sensor Parameters
| Sensor Type | Range | Accuracy | Output Signal |
|---|---|---|---|
| PT100 temperature sensor | -20°C~100°C | ±0.1°C (Class A) | Resistance signal |
| Pressure transmitter | 0~1MPa | ±0.5% FS | 4~20mA |
| Electromagnetic flowmeter | 0~50m³/h | ±0.5% | 4~20mA / RS485 |
| Conductivity sensor | 0~20μS/cm | ±2% | 4~20mA |
| Leak sensor | Point type / cable type | Detection sensitivity ≤1mL | Switch signal |
6.3 Coolant Technical Requirements
This system supports multiple coolant media. Different media have different applicable scenarios and parameter requirements, as follows:
6.3.1 Modified Deionized Water (Mainstream medium for cold-plate type)
| Parameter Item | Specification Requirement |
|---|---|
| Conductivity (25°C) | ≤5μS/cm |
| pH value (25°C) | 7.0 ~ 8.5 |
| Chloride ion content | ≤0.5mg/L |
| Total hardness | ≤0.02mmol/L |
| Suspended solids | No visible suspended solids |
| Bacteriostatic agent | Contains environmentally friendly corrosion inhibitor/bacteriostat |
| Freezing point | ≤0°C (antifreeze required for low-temperature environments) |
| Replacement period | 2 years |
6.3.2 Ethylene Glycol Aqueous Solution (Suitable for low-temperature environments)
| Parameter Item | Specification Requirement |
|---|---|
| Ethylene glycol concentration | 30% ~ 50% (selected based on freezing point requirements) |
| Base water quality | Deionized water |
| Corrosion inhibitor | Contains multi-metal corrosion inhibitors for copper, aluminum, stainless steel |
| Freezing point (40% concentration) | -25°C |
| Boiling point | ≥105°C |
| pH value | 7.5 ~ 9.0 |
| Replacement period | 2 years |
6.3.3 Electronic Fluorinated Fluid (For immersion-type/high-safety scenarios)
| Parameter Item | Specification Requirement |
|---|---|
| Dielectric strength | ≥40kV |
| Boiling point | 40°C ~ 60°C (depending on model) |
| Kinematic viscosity (25°C) | ≤1.5cSt |
| Surface tension | ≤18mN/m |
| Material compatibility | Compatible with the vast majority of electronic component materials |
| Environmental friendliness | ODP=0, low GWP |
| Replacement period | 5~8 years |
6.4 Interface Parameters
| Interface Type | Specification | Connection Method | Remarks |
|---|---|---|---|
| Secondary-side Water Supply Port | DN32 / DN40 / DN50 / DN65 | Flange / Quick Coupling | Connect to cabinet load side |
| Secondary-side Water Return Port | DN32 / DN40 / DN50 / DN65 | Flange / Quick Coupling | Connect to cabinet load side |
| Primary-side Water Inlet | DN25 / DN32 / DN40 / DN50 | Female Thread / Flange | Connect to external cooling source supply |
| Primary-side Water Return Port | DN25 / DN32 / DN40 / DN50 | Female Thread / Flange | Connect to external cooling source return |
| Water Make-up Port | DN15 | Male Thread | Connect to water make-up source |
| Drain Port | DN20 | Male Thread | Connect to drain pipe |
| Power Interface | Three-phase five-wire, 5-core terminal | Crimp terminal | 380V AC |
| Communication Interface | RJ45 / Terminal-type RS485 | Network cable / Shielded cable | Integration with environmental monitoring system |
| Dry Contact Alarm Output | Passive contact, 5A/250V AC | Terminal | Connect to external alarm system |
Chapter 7 Product Functions and Features
7.1 Core Functions
7.1.1 Fully Automatic Circulating Temperature Control Function
The system enables unattended fully automatic operation. After power-on, the circulation starts automatically according to set parameters, and the cooling capacity and flow rate are automatically adjusted based on load variations to maintain stable supply liquid temperature. Multiple temperature presets are supported, and temperature control strategies can be switched based on different time periods and load requirements to achieve energy-saving operation.
7.1.2 Variable Frequency Energy-Saving Function
The circulation pump adopts variable frequency speed control technology, dynamically adjusting the pump speed based on real-time thermal load, saving more than 30% energy compared with constant-speed pump systems. At low load, the pump operates at low speed while also reducing system noise; at high load, it automatically speeds up to ensure heat dissipation requirements. The electric regulating valve synchronously adjusts proportionally to achieve precise cooling capacity matching, avoiding energy waste caused by excessive cooling.
7.1.3 Multiple Safety Protection Functions
The system has built-in more than twenty safety protection mechanisms to comprehensively safeguard equipment and personnel safety:
- Pressure Protection: Automatic pressure relief on overpressure, automatic water make-up on low pressure, and alarm on abnormal pressure.
- Temperature Protection: Supply liquid over-temperature alarm and protection, low-temperature anti-freeze heating protection, and pump body over-temperature protection.
- Flow Protection: Low flow alarm and shutdown protection to prevent equipment overheating due to flow interruption.
- Leakage Protection: Full-point leakage monitoring; alarm triggered immediately upon leak detection, with optional interlocking shutdown and valve closure.
- Electrical Protection: Overload, short circuit, phase loss, undervoltage, overvoltage protection, and residual current protection.
- Anti-Condensation Protection: Real-time dew point temperature monitoring, automatic adjustment of supply liquid temperature to prevent condensation on pipe surfaces and equipment surfaces.
- Cavitation Protection: Pump speed limited at low liquid level and low pressure to prevent cavitation damage to the pump body.
7.1.4 Intelligent Monitoring and Alarm Functions
- Real-time display of all operating parameters, with historical data curve query support, data storage period ≥1 year.
- Tiered alarm mechanism: audible/visual alarm + remote communication alarm; alarm information includes fault code, fault description, and handling recommendations.
- Automatic fault recording with fault log export support for O&M analysis.
- Multiple alarm notification methods supported: SMS, email, platform push, etc. (requires optional cloud platform).
7.1.5 Redundant Backup Functions
- Pump set with one-in-use/one-standby redundancy, automatic fault switching to ensure continuous system operation.
- Optional dual power input; automatic switchover to the other power supply path upon failure of one path, ensuring higher power supply reliability.
- Optional dual communication links for the controller; automatic switchover to wireless communication upon wired communication failure to ensure uninterrupted monitoring.
7.1.6 Remote Operation and Maintenance Functions
- Supports integration with data center environmental monitoring systems for centralized monitoring and unified management.
- Optional KITOZER Intelligent Cloud Platform enables remote viewing of system operating status, receiving alarms, and remote parameter settings via PC or mobile devices.
- Supports predictive maintenance through big data analysis of component operating status, providing early warning of potential faults and reducing unplanned downtime.
7.2 Product Features
7.2.1 Highly Integrated, Rapid Deployment
All functional components are integrated within a standard cabinet and fully assembled, pressure-tested, and commissioned at the factory, delivered as a finished product. On-site work only requires primary-side cooling source connection, secondary-side load connection, power and communication wiring, enabling rapid commissioning. Installation time is reduced by more than 70% compared with distributed systems, making it especially suitable for rapidly deployed computing cluster projects.
7.2.2 Efficient Heat Exchange, Excellent Energy Efficiency
Adopts high-efficiency plate heat exchangers and optimized flow channel design, providing high heat exchange efficiency and low cooling capacity loss. Combined with variable frequency pumps and intelligent temperature control algorithms, the system’s annual comprehensive energy efficiency ratio is far superior to traditional air-cooled solutions. When combined with natural cooling source utilization, low PUE operation can be achieved, helping data centers meet energy-saving assessment requirements.
7.2.3 Safe and Reliable, Low Leakage Risk
- Fully closed circulation design with fewer pipe connection points and reliable sealing, significantly reducing leakage probability.
- All sealing components are made of high-quality media-resistant materials and have undergone long-term immersion testing, providing long service life.
- Multiple leak detection points cover all leakage-prone locations; even minor seepage can be detected, controlling leakage risk at its inception.
- Stable system pressure avoids impact on seals from pressure fluctuations, extending seal service life.
7.2.4 Broad Compatibility, Strong Adaptability
- Supports multiple liquid cooling architectures including cold plate, rear door, spray, and immersion cooling, adapting to different types of IT equipment.
- Standardized interfaces compatible with mainstream brand server, storage, and computing equipment liquid cooling interfaces without custom modification.
- Supports connection to multiple external cooling sources: chillers, cooling towers, dry coolers, closed cooling towers, etc., adapting to different data center cooling source conditions.
- Wide temperature control range with flexible settings based on equipment requirements, accommodating heat dissipation requirements of different heat-generating components such as CPUs, GPUs, and power devices.
7.2.5 Low-Noise Operation, Environmentally Friendly
- Pump body features low-noise design with vibration-damping base and flexible connections, minimizing vibration and noise.
- Piping incorporates sound attenuation treatment to prevent fluid noise transmission.
- Entire unit operating noise ≤55dB(A), far below air-cooled cabinet noise levels, improving data center O&M environment and reducing noise reduction costs.
7.2.6 Easy Maintenance, Low O&M Cost
- Modular design allows quick replacement of wearing parts without special tools.
- Filters, valves, and other maintenance components are positioned on the cabinet front with ample working space for routine maintenance.
- Rich system self-diagnosis functions provide accurate fault location, reducing the professional skill requirements for O&M personnel.
- Long coolant replacement intervals require minimal routine maintenance, resulting in low full-lifecycle O&M costs.
7.2.7 Green and Environmentally Friendly, Policy Compliant
- Uses environmentally friendly coolant with zero ozone depletion potential and low global warming potential.
- Low system energy consumption reduces carbon emissions, complying with dual-carbon policy and green data center construction requirements.
- All materials are recyclable with minimal environmental impact upon disposal.
Chapter 8 Product Application Scenarios
The KITOZER LA-YL-XH Series Liquid Cooling Medium Circulation System, featuring high-density heat dissipation, high energy efficiency, and high reliability, is widely used in heat dissipation scenarios for various high-power-density equipment. Typical application scenarios are as follows:
8.1 AI Intelligent Computing Centers
AI large model training and inference clusters commonly use multi-GPU servers with single-cabinet power reaching 50~100kW or even higher, which traditional air cooling cannot satisfy. This system provides stable and efficient liquid cooling for GPU computing clusters, supporting high-density deployment and reducing PUE, while also reducing data center noise and improving the O&M environment. Compatible with cold plate cooling solutions for mainstream GPUs including NVIDIA and AMD, supporting cluster-scale deployment of ten-thousand-card configurations.
8.2 High-Performance Computing (HPC) Centers
High-performance computing clusters in research institutes, meteorology, petroleum, finance, and other fields have high per-cabinet power density and extremely high requirements for temperature control accuracy and operational stability. This system’s high-precision temperature control ensures stable computing node temperatures, preventing temperature fluctuations from affecting computing accuracy and stability; redundant design ensures continuous system operation, meeting the demands of long-duration computing tasks.
8.3 Enterprise Data Centers
For heat dissipation requirements of enterprise core business servers, storage devices, and network equipment, this system can replace traditional precision air conditioning, significantly reducing cooling energy consumption and increasing data center power density, thereby increasing computing capacity without expanding data center floor area. The system’s high reliability ensures continuous operation of core business.
8.4 Existing Data Center Retrofitting
Many existing data centers are limited by their original air-cooling systems and cannot deploy high-power-density equipment. This system is a cabinet-level standalone solution that does not require large-scale renovation of data center infrastructure, ceiling, flooring, or the original air conditioning system. It enables rapid high-density upgrades, improves data center carrying capacity, extends data center service life, with low renovation cost and short duration.
8.5 Edge Data Centers
Edge facilities typically have limited space and O&M conditions, requiring high equipment integration, reliability, and unattended operation capability. This system’s integrated design has a small footprint, fully automatic operation, and remote monitoring support, making it highly suitable for edge data centers, base station facilities, and campus equipment rooms.
8.6 Industrial Control and Special Equipment Heat Dissipation
- Industrial VFDs and Servo Drives: High-power power electronic equipment generates substantial heat; liquid cooling effectively reduces device temperature, improving equipment reliability and service life.
- Laser Equipment: Laser generators and laser heads are temperature-sensitive; liquid cooling enables precise temperature control, ensuring stable laser output power.
- Medical Equipment: Heat dissipation and temperature control for CT, MRI, and high-energy medical equipment, meeting the high-precision and high-reliability requirements of medical devices.
- Energy Storage PCS (Power Conversion Systems): Heat dissipation for high-power PCS equipment in energy storage stations, improving system operational stability and safety.
- Charging Piles: Heat dissipation for high-power liquid-cooled ultra-fast charging piles, ensuring stable temperature of charging guns and modules.
8.7 Special Environment Facilities
- High-Altitude Facilities: At high altitudes, thin air significantly reduces air-cooling efficiency; liquid cooling is unaffected by altitude and maintains stable heat dissipation efficiency.
- High-Dust and High-Corrosion Environment Facilities: The closed liquid cooling system isolates internal components from ambient air, preventing dust and corrosive gases from entering equipment, improving equipment reliability.
- Noise-Sensitive Facilities: Such as office-area support equipment rooms or facilities near residential areas, where the low-noise characteristics of liquid cooling systems meet environmental requirements.
Chapter 9 Product Installation
9.1 Pre-Installation Preparation
9.1.1 Construction Technical Preparation
- Organize construction personnel to familiarize themselves with this manual, construction drawings, and design documents, clarifying construction scope, technical requirements, quality standards, and safety precautions.
- Conduct technical disclosure: the project technical leader explains construction procedures, key processes, and acceptance points to the construction crew, with written disclosure records signed for confirmation.
- Verify on-site conditions: confirm that facility floor load-bearing capacity, installation position dimensions, power supply capacity, cooling source interfaces, and grounding system meet design requirements; coordinate to resolve any deviations promptly.
- Prepare a construction schedule identifying time nodes and responsible persons for each process.
9.1.2 On-Site Environment Preparation
- Installation site cleaned and cleared of debris and standing water; floor level and meeting load-bearing requirements. Cabinet installation floor load-bearing capacity should be ≥1000kg/m²; structural reinforcement required if insufficient.
- Data center civil works, finishing, and flooring works completed; no drilling, cutting, or other dust-generating operations on walls or floors.
- Temporary power and water supply available on site to meet construction requirements.
- Warning signs installed in the installation area; non-construction personnel prohibited from entry.
- Fire-fighting equipment and emergency lighting available on site to meet safe construction requirements.
9.1.3 Tools and Instruments Preparation
All tools and instruments required for installation should be prepared in advance and verified calibrated, mainly including:
| Category | Tool/Instrument Name | Specification | Purpose |
|---|---|---|---|
| Handling Tools | Hydraulic forklift | 2 ton | Equipment handling |
| Manual hydraulic pallet truck | 3 ton | Short-distance movement | |
| Lifting sling | 3 ton | Lifting operation | |
| Installation Tools | Socket wrench set | 8~32mm | Bolt fastening |
| Adjustable wrench | 8″, 12″, 15″ | Valve and fitting installation | |
| Hex key set | Metric | Component installation | |
| Torque wrench | 5~50N·m | Bolt torque-controlled fastening | |
| Pipe wrench | 12″, 18″ | Pipe installation | |
| Chamfering tool | Matching pipe diameter | Hard pipe end preparation | |
| Pipe cutter | Matching pipe diameter | Pipe cutting | |
| Welding Tools | TIG welding machine | 315 type | Stainless steel pipe welding |
| Angle grinder | 100mm | Weld bead grinding | |
| Testing Instruments | Spirit level | Accuracy 0.02mm/m | Equipment levelness inspection |
| Pressure gauge | 0~1.6MPa, Class 1.6 | Pressure testing | |
| Multimeter | Digital type | Electrical inspection | |
| Insulation resistance tester | 500V/1000V | Insulation testing | |
| Ground resistance tester | Accuracy ±5% | Ground resistance testing | |
| Ultrasonic flowmeter | Portable type | Flow calibration | |
| Other Tools | Hand drill / Impact drill | — | Drilling operations |
| Tape measure, caliper, feeler gauge | — | Dimensional measurement | |
| Marker pen, cable ties, PTFE tape | — | Auxiliary operations | |
| Vacuum cleaner, cloths | — | Cleaning and dust removal |
9.1.4 Materials and Equipment Incoming Inspection
- Upon arrival, check equipment and materials against the packing list and material list, verifying model, specification, and quantity item by item, and inspecting appearance quality.
- Verify that factory certificates of conformity, inspection reports, manuals, and other technical documentation are complete.
- Perform visual inspection of key materials including pipes, valves, and seals for cracks, deformation, rust, and sand holes.
- After acceptance, complete incoming inspection records, process storage procedures, and store properly.
9.2 Equipment Positioning and Foundation Installation
9.2.1 Layout and Positioning
- Determine cabinet installation position according to construction drawings; mark installation reference lines and cabinet outline on the floor.
- Confirm maintenance clearances around the cabinet: front maintenance space ≥800mm, rear ≥600mm, sides ≥500mm, meeting operation and inspection requirements.
- Check for obstructions near the installation position to ensure smooth pipe and cable routing.
9.2.2 Base Frame Installation (Optional)
- For uneven floors or scenarios requiring elevated installation, install the cabinet base frame first. The base frame is fabricated from 10# channel steel, with dimensions matching the cabinet bottom.
- Place the base frame on the positioning lines; adjust levelness using a spirit level and shim plates to ensure base frame levelness deviation ≤0.5mm/m.
- After leveling, secure the base frame to the floor with expansion bolts, specification M12×100mm, with no fewer than 4 fixing points per base frame.
- Apply anti-corrosion treatment to the base frame with rust-inhibitive primer and finish paint in a color matching the cabinet.
9.2.3 Cabinet Placement and Fixation
- Use a hydraulic forklift to transport the cabinet to the installation position, maintaining stability during handling and avoiding severe vibration and tilting; tilt angle ≤30°.
- Remove the cabinet’s external packaging; inspect the cabinet exterior for impacts and deformation, check door operation and lock condition.
- Align the cabinet to the reference lines and place on the base frame or floor; inspect cabinet levelness and verticality with a spirit level:
- Levelness deviation ≤0.5mm/m
- Verticality deviation ≤1.5mm/m
- Adjust levelness and verticality using the cabinet’s adjustable leveling feet; lock the foot nuts after adjustment.
- When installing multiple cabinets side by side, the gap between adjacent cabinets ≤2mm, cabinet fronts flush, height difference ≤1mm. Inter-cabinet coupling bolts must be tightened securely, ensuring reliable overall connection.
- If floor fixation is required, secure with expansion bolts through the cabinet bottom mounting holes to prevent cabinet displacement.
9.2.4 Grounding Connection
- The cabinet top and bottom are each provided with a dedicated grounding terminal. Use yellow-green multiconductor copper ground wire of no less than 6mm² to connect reliably to the facility grounding busbar.
- The internal electrical control box grounding terminal, pump body grounding terminal, and pipe bonding jumpers must all be reliably connected to the cabinet grounding terminal, forming a complete grounding network.
- Test grounding resistance with a ground resistance tester; requirement: grounding resistance ≤1Ω. If non-compliant, inspect grounding connections and add ground electrodes if necessary.
- All grounding connections must be secure with bolts properly tightened and loosening prevention measures in place.
9.3 External Piping Installation
9.3.1 General Piping Installation Requirements
- Pipe material and specifications must conform to design requirements; 304 stainless steel seamless pipe is preferred; PPR pipe, copper pipe, etc., may also be used depending on operating conditions.
- Piping layout follows the principle of “shortest path, fewer elbows, level and plumb, neat and tidy,” minimizing pipe length and elbow count to reduce system flow resistance.
- Horizontal pipes must be installed with a slope of no less than 5‰, sloping toward the air vent or drain valve direction, ensuring system gas can be smoothly discharged through the air vent and impurities can settle at drain points.
- Pipe support spacing complies with code requirements: DN50 and below — support spacing ≤2m; DN50~DN100 — ≤3m. Additional supports required at bends and valves. Supports use corrosion-treated angle steel or pipe clamps, firmly fixed.
- Install rubber pads between pipes and supports to reduce vibration and noise and prevent galvanic corrosion.
- Seal pipe openings during installation to prevent debris and dust from entering the piping.
- Install sleeves where pipes pass through walls and floors; seal between sleeve and pipe with fire-resistant sealing material.
9.3.2 Stainless Steel Pipe Welding Installation
- Pipe cutting uses a dedicated pipe cutter or plasma cutting; cut ends must be smooth and free of burrs and deformation. After cutting, chamfer both inner and outer edges of pipe ends to remove burrs and sharp edges.
- Pipe welding uses TIG (argon arc) welding process; filler wire must be same-grade stainless steel as the pipe material. Weld beads must be uniform and neat, free of porosity, cracks, slag inclusion, and lack of fusion.
- Butt weld joints must be properly aligned; misalignment shall not exceed 10% of pipe wall thickness and no more than 1mm.
- After welding, perform pickling and passivation treatment on weld areas to remove weld scale and improve corrosion resistance.
- All welds undergo 100% visual inspection; critical welds undergo penetrant testing, meeting Class I weld standard.
9.3.3 Threaded and Flange Connections
- For threaded connections, clean thread surfaces, wrap with PTFE tape or apply sealant, and tighten with moderate force to avoid thread cracking from excessive force.
- For flange connections, flange faces must be flat and clean; gasket placed centered; bolts tightened evenly in a crisscross sequence; bolt threads protrude 2~3 threads beyond the nut.
- Flange gasket material must be compatible with the medium; EPDM or FKM (Viton) gaskets preferred; asbestos gaskets are strictly prohibited.
- After connection, flange faces must be parallel with uniform clearance, free of misalignment or distortion.
9.3.4 Valve and Accessory Installation
- Inspect valves before installation, test switch flexibility, and confirm no jamming or leakage. Important valves require individual hydrostatic testing before installation.
- Valve installation direction must match medium flow direction; handles positioned for convenient operation; inverted installation strictly prohibited.
- Air vents installed at the highest points of the system piping; drain valves installed at the lowest points for convenient air venting and draining.
- Filter installation direction correct, with filter screen facing the side convenient for removal and cleaning; installation position must reserve removal clearance.
- Flow meters, pressure sensors, and temperature sensors installed on straight pipe sections with sufficient straight pipe length before and after (10 pipe diameters upstream, 5 pipe diameters downstream) to ensure measurement accuracy.
9.3.5 Pipe Insulation
- Insulation work conducted after successful pipe pressure testing. Insulation thickness conforms to design requirements: supply liquid pipe insulation thickness ≥20mm, return pipe ≥15mm.
- Insulation material: closed-cell rubber-plastic (NBR/PVC) insulation, thermal conductivity ≤0.034W/(m·K), fire rating Class B1 or above.
- Insulation layers must be tightly joined with gaps bonded using dedicated adhesive; longitudinal seams of pipe shells staggered to avoid continuous seams.
- Valves, flanges, and elbows individually insulated to ensure no thermal bridges and no exposed surfaces.
- Wrap insulation exterior with aluminum foil tape or install aluminum sheet protective layer, neat and smooth, providing moisture protection.
9.3.6 Pipe Identification
- After piping installation, affix pipe identification labels indicating medium name, flow direction arrows, pipe diameter, and system name.
- Supply liquid pipes use blue identification; return liquid pipes use red identification; cooling source pipes use green identification.
- Install valve tags indicating valve number, name, and purpose for convenient O&M operation.
9.4 Internal Component Inspection and Fastening
- Open cabinet doors and inspect internal components for loosening, displacement, or damage sustained during transportation.
- Tighten fixing bolts of circulation pumps, heat exchangers, valves, filters, and pipe supports one by one to eliminate transportation loosening.
- Check all pipe joints, flanges, and valve connections for tightness; verify seals are intact.
- Check electrical component wiring for looseness; tighten terminal block screws one by one; inspect cables for crushing or damage.
- Check sensor probes for integrity and wiring security.
- Clean internal debris and dust from the cabinet, ensuring interior cleanliness and dryness.
9.5 Pipe Flushing and Pressure Testing
9.5.1 Pipe Flushing
- After piping installation, pipe flushing must be performed before formal liquid filling to remove weld slag, rust, dust, and other impurities from the pipes, preventing blockage of cold plates and filters.
- Disconnect the secondary-side connection to load equipment and short-circuit supply and return lines to form a temporary flushing loop. Remove fine filter elements and temporarily install coarse strainers.
- Inject clean deionized water into the system; after filling, start the circulation pump for circulating flushing.
- During flushing, periodically open the drain valve to discharge dirty water and replace flushing water until the discharge is clear with no visible impurities.
- Flushing duration no less than 24 hours; after flushing, verify discharge water turbidity and particle count meet standards.
- After flushing passes, drain the flushing water, clean filters, and install formal filter elements.
9.5.2 Hydrostatic Strength Test
- After flushing passes, fill the system with clean deionized water, vent all air from the system, and close all air vents.
- Use a manual test pump to increase pressure slowly at a rate of ≤0.1MPa/min.
- After reaching the test pressure (1.5 times the working pressure, and not less than 0.6MPa), stop pressurization and hold for 30 minutes.
- Inspect all welds, joints, flanges, valves, and component sealing surfaces; no leakage, no deformation, and no significant pressure drop constitutes a pass.
- If leakage is discovered during testing, immediately relieve pressure, address the issue, and retest. Repair under pressure is strictly prohibited.
9.5.3 Tightness Test
- After the strength test passes, reduce pressure to 1.25 times the working pressure for the tightness test.
- Hold pressure for 24 hours; record initial and final pressures.
- Pressure drop ≤0.03MPa with no leakage at any sealing point constitutes a pass.
- After the test passes, slowly relieve pressure, drain test water, and prepare for formal coolant filling.
9.6 Coolant Filling and Air Venting
9.6.1 Pre-Filling Inspection
- Confirm pressure test passed, system free of residual water and impurities.
- Confirm coolant type is correct, quality qualified, and within shelf life.
- Prepare filling tools: filling pump, funnel, hoses, drip tray, etc.
- Check all valve positions: main circuit valves fully open, bypass valve appropriately open, drain and blowdown valves closed, air vents open.
9.6.2 Filling Operation
- Slowly fill coolant through the system’s dedicated filling port; filling rate should not be excessive to avoid drawing in large amounts of air.
- During filling, monitor the expansion tank level while opening high-point air vents to release air; close air vents after steady liquid flow is observed.
- When the expansion tank level reaches the normal level mark (2/3 height), stop filling and seal the filling port.
- Jog-start the circulation pump for 5~10 seconds then stop, and open air vents again to release air. Repeat multiple times until air is essentially vented from the system.
- Recheck the expansion tank level and top up coolant if insufficient until the level is within the normal range.
9.6.3 System Air Venting
After initial filling, micro air bubbles may remain in the system and need to be gradually expelled through operational venting:
- Start the circulation pump at low speed and run continuously for 1~2 hours.
- Open high-point air vents every 30 minutes to release air.
- Monitor pressure and flow changes during operation; pressure fluctuations or unstable flow indicate residual gas in the system, requiring continued venting.
- Air venting is complete when system pressure is stable, flow is steady, and no significant air bubbles are discharged.
- After venting, reconfirm liquid level and top up to the normal level.
9.7 Installation Quality Acceptance Standards
After installation, perform itemized acceptance of installation quality according to the following standards:
- Cabinet Installation: Position correct, levelness and verticality compliant, securely fixed, grounding reliable, appearance intact.
- Piping Installation: Layout reasonable, level and plumb, slope compliant, supports secure, welds qualified, connections leak-free, identification clear.
- Valve and Accessory Installation: Position correct, orientation correct, smooth operation, proper sealing, convenient operation.
- Pressure Testing: Strength test and tightness test passed with complete records.
- Insulation Work: Insulation layer complete, thickness compliant, no thermal bridges, neat appearance.
- Grounding System: Grounding connections reliable, grounding resistance compliant.
- Cleanliness and Identification: Equipment and pipes clean, identification complete and standardized.
Chapter 10 Product Wiring
10.1 Pre-Wiring Preparation
10.1.1 Safety Preparation
- Confirm upstream power is disconnected, verify no voltage with a voltage tester, and hang a “DO NOT CLOSE — WORK IN PROGRESS” warning sign.
- Personnel must wear insulating gloves, insulating shoes, and other protective equipment.
- Prepare voltage testers, multimeters, and other testing tools; confirm tool insulation integrity.
- At least two personnel required on site: one operator and one safety observer.
10.1.2 Technical and Material Preparation
- Familiarize with electrical schematic diagrams and wiring diagrams; understand terminal functions, wiring requirements, and wire gauge requirements.
- Verify cable type, specification, and length conform to design requirements; cable appearance free of damage, crushing, or broken conductors.
- Prepare wiring tools: wire strippers, crimping pliers, screwdrivers, multimeter, insulating tape, cable ties, ferrule number tubes, etc.
- Prepare cable lugs, terminals, bolts, washers, and other auxiliary materials with specifications matching the cables.
10.2 Power Circuit Wiring
10.2.1 Main Power Wiring
- Main power uses three-phase five-wire system (380V AC, 50Hz), consisting of three phase conductors (L1, L2, L3) + neutral (N) + ground (PE).
- Power cable gauge selected according to total power: for units of 30kW and below, use 4×6mm²+1×4mm² copper cable; for 50~80kW units, use 4×10mm²+1×6mm² copper cable; for units above 100kW, calculate wire gauge based on actual power to ensure current-carrying capacity meets requirements.
- Route external power cables into the cabinet’s main power incoming terminals; connect to L1, L2, L3, and N terminals according to phase sequence; PE wire to the dedicated grounding terminal.
- Before wiring, verify supply voltage is normal and phase sequence is correct. A phase sequence meter can be used to check phase sequence; incorrect phase sequence will cause pump reverse rotation.
- Crimp cable lugs onto conductors and tighten bolts securely for good contact without loosening. Stranded conductors must be fitted with crimped terminals; direct insertion into terminal blocks is strictly prohibited.
- Install cable fixing glands at the power entry point to secure cables and prevent tension from pulling terminals loose.
10.2.2 Pump Power Wiring
- Circulation pump motor cables connect from the main circuit contactor output terminals to the motor terminals according to phase sequence.
- Variable frequency pumps must be connected to the VFD output terminals per VFD wiring requirements; connecting the VFD output to the power supply is strictly prohibited.
- Motor grounding terminals connected separately to the protective ground wire with reliable grounding.
- Main pump and standby pump wired separately; after wiring, clearly label to distinguish main and standby pumps.
- After wiring, jog-test motor rotation direction; rotation matching the label indicates correct direction; reverse rotation requires swapping any two phase conductors.
10.2.3 Heater and Actuator Wiring
- PTC heater power cables connect to dedicated contactor output terminals; for step-controlled power, wire each step separately.
- Heater must be reliably grounded with an over-temperature protection switch for automatic power cutoff upon over-temperature.
- Electric regulating valve actuator power cables and control cables connect to corresponding terminals, with correct polarity per the instruction manual.
- Solenoid valves, motorized valves, and other actuators: pay attention to voltage ratings and polarity; over-voltage wiring strictly prohibited.
10.2.4 Auxiliary Power Wiring
- Control circuit power, socket power, and lighting power are tapped from the downstream side of the main circuit breaker and supplied through miniature circuit breakers.
- For 220V circuits, distinguish between live and neutral conductors; switches must control the live conductor.
- Service sockets must have residual current protection to ensure electrical safety.
10.3 Low-Voltage Control Circuit Wiring
10.3.1 Sensor Wiring
- All sensor cables must use shielded cable with shield layer grounded at one end only to avoid electromagnetic interference.
- Temperature sensors (PT100) use three-core shielded cable connected to corresponding AI channels per terminal labels; compensating leads must match sensor type.
- Two-wire sensors such as pressure transmitters and flow meters: 24V DC supply positive terminal to power terminal, signal output to AI analog input terminal, negative terminal common ground.
- Switch-type sensors such as leak detectors and flow switches connect to DI digital input terminals; passive contacts connect directly, active contacts require attention to voltage levels.
- After sensor wiring, verify signal readings at the controller end and confirm values match actual conditions.
10.3.2 Controller and HMI Wiring
- PLC controller power connects to 24V DC power supply; observe correct polarity; reverse connection strictly prohibited.
- HMI connects to the PLC via communication cable, with connections per interface type and matching communication parameters.
- All IO terminal connections must be secure with clear ferrule number tube identification consistent with drawings.
- Controller grounding terminal connected separately to protective ground to improve anti-interference capability.
10.3.3 Alarm and Indicator Light Wiring
- Audible/visual alarm connects to DO output terminals; observe voltage rating and polarity.
- Cabinet panel indicator lights and buttons connect to corresponding terminals per wiring diagram with correct function labels.
- Remote dry contact alarm output connects to dedicated terminals; passive contacts; external connected equipment must not introduce high voltage.
10.4 Communication Circuit Wiring
10.4.1 RS485 Communication Wiring
- Use shielded twisted pair cable with characteristic impedance of 120Ω and conductor gauge ≥0.5mm².
- Install 120Ω termination resistors at both ends of the bus to reduce signal reflection.
- A and B lines must be connected correspondingly; polarity must not be reversed; shield layer grounded at one end only with grounding resistance ≤1Ω.
- When communication distance exceeds 1000 meters, repeaters must be added; device addresses on the bus must not be duplicated.
- After wiring, test communication functionality and verify stable data transmission and reception.
10.4.2 Ethernet Communication Wiring
- Use Category 5e or Category 6 shielded network cable, terminated with RJ45 connectors per T568B standard.
- Connect to a switch or directly to the environmental monitoring system; set IP addresses correctly and verify network connectivity.
- Network cables must avoid parallel routing with power cables; cross at right angles when necessary to reduce electromagnetic interference.
10.5 Grounding System Wiring
- A grounding copper busbar is provided within the cabinet; all components requiring grounding connect to this busbar via yellow-green ground wires.
- Motors, heaters, heat exchangers, pipes, and other metal components must all be reliably grounded to form equipotential bonding.
- The grounding copper busbar connects to the facility grounding grid using yellow-green copper cable of no less than 16mm², with secure connections.
- All grounding wire colors must be yellow-green dual-color; substitution with other colors is strictly prohibited.
- After wiring, test grounding resistance; must be ≤1Ω.
10.6 Wiring Workmanship Requirements
- Separate power and control wiring; different circuits routed in separate troughs with spacing ≥200mm to avoid interference.
- Cables routed neatly, level and plumb, with smooth arc transitions at bends; no sharp bends or crushing.
- Secure cables with cable ties every 300mm, evenly spaced, with moderate tightness.
- Both ends of all cables fitted with ferrule number tubes with clear, standardized, fade-resistant identification consistent with drawings.
- Reserve appropriate cable slack for maintenance; reserve length sufficient for 2~3 times re-termination at terminals.
- Cable insulation stripped at terminals should not exceed 2mm of exposed conductor; stranded conductors must be terminated with crimped terminals, free of burrs and broken strands.
- Cables at cabinet door hinges use cable chains or spiral wrap with movement allowance so doors do not stress cables when opened/closed.
10.7 Post-Wiring Inspection and Testing
10.7.1 Continuity and Insulation Testing
- Open all circuit breakers; use a multimeter in continuity mode to check each circuit for correct wiring, short circuits, and misconnections.
- Use a 500V insulation resistance tester to test insulation resistance of each circuit to ground:
- Power circuits insulation resistance ≥0.5MΩ
- Control circuits insulation resistance ≥0.5MΩ
- Low-voltage circuits insulation resistance ≥0.2MΩ
- If insulation is non-compliant, investigate the cause, retest after correction, and repeat until passing.
10.7.2 Phase Sequence and Voltage Testing
- Close the upstream power supply; test incoming terminal voltage; three-phase voltage balanced with deviation ≤5%.
- Test phase sequence correct and conforming to motor forward rotation requirements.
- Test neutral and ground conductor voltages normal with no cross-connection.
10.7.3 Standalone Power-On Testing
- With load-side breakers open, energize control power first; check the controller and HMI start normally with correct display.
- Test each sensor signal one by one; displayed values normal with no abnormal alarms.
- Manually test each actuator: valve open/close, pump start/stop, heater start/stop; operation normal with correct feedback.
- Test indicator lights, buttons, and audible/visual alarm functions.
- Test communication connections normal with stable data upload.
10.8 Wiring Safety Precautions
- All wiring work must be performed with power disconnected; energize wiring is strictly prohibited. If live testing is required, a dedicated safety observer must be present with proper insulation protection.
- Unauthorized modification of electrical circuits is strictly prohibited; enlarging fuse or circuit breaker ratings is strictly prohibited.
- Cable terminations must be secure; poor contact can cause heating, arcing, and fire.
- Shield layers may only be grounded at one end; grounding at both ends creates ground loop currents that actually increase interference.
- After wiring, clean debris from inside the cabinet, especially metal shavings, to prevent short circuits.
- All wiring must comply with electrical installation codes; unauthorized or disorderly wiring is strictly prohibited.
Chapter 11 Product Commissioning
After installation and wiring are completed and pass inspection, the system enters the commissioning phase. Commissioning is divided into five steps: stand-alone commissioning, no-load system integration testing, load integration testing, performance testing, and protection function testing. Steps must be performed sequentially, with progression to the next step only after the previous step passes.
11.1 Pre-Commissioning Preparation
- Confirm all installation work is complete, installation quality acceptance passed, pressure testing passed, and coolant filling and air venting completed.
- Confirm all electrical wiring is complete, insulation testing passed, and power supply, grounding, and communication connections are normal.
- Confirm all valves are in the correct positions: main circuit valves fully open, bypass valve appropriately open, drain and blowdown valves closed.
- Confirm expansion tank level is normal and system pressure is within the normal range.
- Confirm facility environment conditions meet operational requirements and the cooling source system can supply water normally.
- Commissioning personnel in place with clear division of responsibilities; prepare commissioning record forms, tools, and instruments.
- Develop commissioning emergency response procedures to promptly handle abnormal situations.
11.2 Stand-Alone Component Commissioning
11.2.1 Circulation Pump Stand-Alone Commissioning
- Disconnect the pump outlet valve, jog-start the pump, and check motor rotation direction is correct with no abnormal noise or vibration.
- After confirming rotation direction, run briefly for 1 minute and check motor current, temperature rise, vibration, and noise are normal.
- Slowly open the outlet valve, progressively increase pump speed to rated speed, and run for 15 minutes.
- Measure and record pump inlet/outlet pressure, flow rate, motor current, temperature, and vibration values.
- Check mechanical seal for leakage; slight seepage is acceptable (≤3 drops/minute); excessive leakage requires shutdown for repair.
- Commission the standby pump using the same procedure to ensure both pumps operate normally.
- Test main/standby pump switchover function; switchover smooth with no significant pressure fluctuation.
11.2.2 Electric Regulating Valve Commissioning
- Manually operate the controller to output 0%, 25%, 50%, 75%, and 100% opening signals; verify valve operation corresponds accordingly.
- Test valve full-open and full-close stroke times, conforming to product parameters.
- Check valve for jamming or abnormal noise; position feedback signals correct.
- Test valve regulation response in automatic mode; valve responds promptly and smoothly to temperature changes without oscillation.
11.2.3 Electric Heater Commissioning (Dual Cooling/Heating Control Models)
- In low-temperature environments or with simulated low-temperature signals, activate the heating function.
- Test each heater power stage outputs normally with current conforming to rated values.
- Test over-temperature protection function: automatic power cutoff and alarm activation when temperature exceeds threshold.
- Test heating temperature control effect; temperature stabilizes within the set range.
11.2.4 Sensor Calibration
- Temperature sensors: compare against a standard thermometer; calibrate if deviation exceeds allowable range.
- Pressure sensors: compare against a standard pressure gauge; calibrate zero point and span.
- Flow meters: compare against a portable ultrasonic flowmeter; deviation ≤±2% constitutes a pass.
- After calibration, record calibration data for all sensors and complete the calibration record form.
11.3 No-Load System Integration Testing
After all stand-alone commissioning passes, conduct no-load system integration testing to verify overall system operation logic and control functions.
- Secondary-side loop in closed circulation without load; set supply water temperature to 25℃.
- Start the system in automatic operation mode; observe the startup sequence is correct: air venting, pump start, valve regulation.
- Run continuously for 2 hours, recording supply/return water temperatures, pressures, flow rates, pump speed, valve opening, and motor current at 30-minute intervals.
- Observe temperature control effect: after stabilization, fluctuation range should be within ±0.5℃, with smooth control and no overshoot or oscillation.
- Change the set temperature and observe system response speed; adjustment process smooth with rapid stabilization at the new set point.
- Change pump speed settings and observe flow and pressure changes; adjustment smooth without abnormalities.
- Check for leakage, abnormal noise, and vibration; all components operate smoothly.
- Test HMI functions: parameter display, parameter setting, history query, fault query, and permission management all function correctly.
11.4 Load Integration Testing
After no-load integration testing passes, progressively connect loads for loaded commissioning.
11.4.1 Low Load Testing
- Connect 10%~30% of rated load; power on some IT equipment.
- System operates automatically; observe temperature, flow, and pressure changes after load increase and whether system adjustment is timely.
- Run for 1 hour, record all parameters, and verify temperature control accuracy and operational stability under low load.
- Check flow distribution uniformity across branches and effectiveness of branch valve regulation.
11.4.2 Medium Load Testing
- Progressively increase load to 50%~70% of rated load.
- Observe system adjustment process; supply liquid temperature remains stable without significant fluctuation.
- Monitor supply/return temperature differential; calculate actual heat exchange capacity and compare against theoretical values to verify heat exchange capability.
- Run for 2 hours; system operates stably with no abnormal alarms.
11.4.3 Full Load Testing
- Power on all loads to reach rated thermal load.
- System operates at full load; record supply/return water temperature, pressure, flow, temperature differential, pump speed, valve opening, and cooling source parameters under rated conditions.
- Verify system heat exchange capacity meets design requirements; supply water temperature remains stable at the set value under full load.
- Check flow and temperature at the most unfavorable points in the system meet requirements with no localized overheating.
- Run continuously for 4 hours; system operates without faults, leakage, and with stable parameters.
11.5 Protection Function Testing
After the system operates normally, test each protection function item by item to verify protection logic is correct and reliable.
11.5.1 Temperature Protection Testing
- Simulate supply water over-temperature: modify the temperature alarm threshold, artificially raise temperature, and observe whether over-temperature alarm triggers and protection actions are correct.
- Simulate low-temperature protection: simulate low-temperature signal and observe whether low-temperature alarm and heating function activate.
- Test pump body over-temperature protection: simulate pump body over-temperature and observe whether alarm and shutdown protection are activated.
11.5.2 Pressure Protection Testing
- Simulate system overpressure: slowly raise system pressure; when the overpressure threshold is reached, verify the safety valve pops and the alarm triggers.
- Simulate system low pressure: close the water make-up valve to simulate pressure drop; observe whether low-pressure alarm and automatic water make-up activate.
- When pressure falls below the protection threshold, verify system shutdown protection engages.
11.5.3 Flow Protection Testing
- Partially close the outlet valve to simulate flow reduction; alarm triggers when flow falls below the alarm threshold.
- Continue closing the valve; when flow falls below the shutdown threshold, system automatically shuts down for protection.
- Restore valve opening; system can be manually reset and restarted.
11.5.4 Leakage Protection Testing
- Drip a small amount of water on the leak sensor to simulate leakage; observe whether the leakage alarm triggers immediately.
- Test the leakage interlocking shutdown function (with prior confirmation that the load permits shutdown); for severe leakage, the system automatically stops pumps and closes valves.
11.5.5 Electrical Protection Testing
- Test overload protection: artificially increase load or simulate overload; verify circuit breaker/thermal relay operation.
- Test phase loss protection: disconnect one phase; verify system alarms and shuts down.
- Test residual current protection: simulate leakage; verify residual current protective device operates.
11.5.6 Power Outage and Power Restoration Testing
- With the system operating normally, disconnect power; system shuts down smoothly without abnormalities.
- After 5 minutes, restore power and test whether automatic restart-on-power function executes per settings.
- Verify power-off memory function: parameter settings and fault records are not lost.
11.6 Performance Parameter Testing and Verification
11.6.1 Temperature Control Accuracy Test
After the system has been operating stably at full load, continuously record supply water temperature data for 1 hour, calculate the temperature fluctuation range, and verify whether the design accuracy of ±0.5°C is achieved.
11.6.2 Heat Exchange Capacity Test
Record the flow rate and supply/return water temperature difference under rated operating conditions, and calculate the actual heat exchange rate using the following formula:
Heat Exchange Rate Q (kW) = Flow Rate (m³/h) × Temperature Difference (°C) × Specific Heat Capacity (kJ/(kg·°C)) × Density (kg/m³) / 3600
Verify that the actual heat exchange rate is not less than the rated heat exchange power.
11.6.3 Energy Efficiency Test
Test the total input power of the system under rated operating conditions, calculate the system Energy Efficiency Ratio (EER) = Heat Exchange Rate / Input Power, and verify the energy efficiency indicators. Test the energy efficiency under partial load conditions to verify the variable frequency energy-saving effect.
11.6.4 Noise Test
Use a sound level meter to test operating noise at a distance of 1 meter from the front of the cabinet and at a height of 1.5 meters. After background noise correction, a noise value of ≤55 dB(A) qualifies as passing.
11.7 Commissioning Wrap-up Work
After all commissioning tests have passed, organize the commissioning records, fill out the commissioning report, and obtain signatures from all parties for confirmation.
Perform final optimization of system parameters, set optimal operating parameters, and save the parameter settings.
Set reasonable alarm thresholds and protection parameters to suit actual site operating conditions.
Clean up the commissioning site, remove debris and wastewater, and keep equipment and environment clean.
Provide preliminary operating training to maintenance personnel, covering basic operations, daily inspection key points, and emergency handling methods.
11.8 Commissioning Safety Precautions
During the commissioning process, personnel are strictly prohibited from contacting live parts and high-temperature components.
During pressure testing and pressurized operation, never stand directly facing joints or valves to prevent injury from fluid ejection.
Fault testing must be conducted within controllable limits to avoid equipment damage.
When shutting down for maintenance, power must be disconnected and pressure released before any operations.
If abnormal sounds, odors, leaks, overtemperature, or overpressure occur during commissioning, stop the machine immediately for inspection, and only resume after the fault has been eliminated.
It is strictly prohibited to modify protection parameters or disable protection functions without authorization.
12.1 Installation Precautions
The equipment must be installed in a well-ventilated, dry indoor location, avoiding direct sunlight, rain, and corrosive gas exposure.
Sufficient maintenance space must be reserved at the installation location to facilitate component replacement and servicing. It is strictly prohibited to install the equipment flush against walls or obstacles.
Piping installation must include proper slopes and air release valves. Horizontal installation without slope is strictly prohibited; otherwise, accumulated air cannot be discharged from the system, leading to air locks, poor heat exchange efficiency, and pump cavitation.
Pipe welding must be performed by certified welders. After welding, pickling and passivation treatment and pressure testing must be carried out. Welding by uncertified personnel and commissioning without pressure testing are strictly prohibited.
The piping system must be flushed before initial use. Directly filling and operating without flushing is strictly prohibited to prevent welding slag and impurities from clogging the cold plate micro-channels.
Only the specified coolant type must be used. Mixing different types of coolant is strictly prohibited. Untreated water such as tap water or groundwater must not be directly used for filling.
Electrical wiring must be performed by certified electricians, strictly following electrical codes. Unauthorized or improper wiring connections are strictly prohibited.
Grounding must be reliable with compliant grounding resistance. Operation without grounding is strictly prohibited to prevent electric shock hazards.
12.2 Operating Precautions
Before system startup, the liquid level, pressure, and valve status must be checked and confirmed normal before starting. Starting with insufficient liquid is strictly prohibited to prevent pump dry-running damage.
During system startup, start the circulation pump first, then turn on the cold source; during shutdown, stop the cold source first, then stop the circulation pump.
Conduct regular inspections during operation, observing parameters such as temperature, pressure, flow rate, and liquid level, and handle any abnormalities promptly.
Unauthorized modification of system parameters is strictly prohibited, especially protection thresholds and pump protection parameters. If adjustments are needed, contact the manufacturer’s technical personnel.
Closing the inlet and outlet valves while the system is running is strictly prohibited to prevent pressure buildup and equipment damage.
When shutting down in low-temperature environments, anti-freeze measures must be taken, such as draining the coolant from the system or maintaining low-temperature circulation to prevent pipes and heat exchangers from freezing and cracking.
When the ambient humidity in the equipment room is high, check for condensation on pipe surfaces. If necessary, raise the supply liquid temperature or thicken the insulation layer to prevent condensed water from dripping and damaging electrical equipment.
For extended system shutdown, drain the coolant completely and purge with nitrogen gas for protection against internal corrosion.
12.3 Maintenance Precautions
Maintenance work must only be performed after shutdown, power disconnection, and pressure release. Servicing under pressure or with power connected is strictly prohibited.
When replacing accessories such as filter cartridges and seals, only genuine original parts must be used. Using unqualified substitutes is strictly prohibited to prevent leaks and damage.
Coolant refills must use the same model and brand. Mixing different brands or types of coolant is strictly prohibited.
When disassembling pipes and components, prepare liquid collection containers to prevent coolant spillage from damaging other equipment.
When performing welding repairs, drain nearby coolant and take fire prevention measures to prevent igniting the coolant.
Calibrate sensors regularly to ensure accurate monitoring data and avoid false alarms or missed alarms.
After maintenance work is completed, pressure testing and trial operation must be performed. Normal operation may only resume after confirming no leaks and proper functioning.
Maintain detailed maintenance records, documenting maintenance time, content, replaced parts, and operating parameters, to form a complete operation and maintenance archive.
12.4 Safety Precautions
Smoking and open flames are strictly prohibited near the equipment. Fire-fighting equipment must be provided. Some coolants are flammable media, requiring special attention to fire prevention.
Electrical cabinets and control boxes must not be operated with doors open to prevent dust and moisture ingress and to prevent personnel from accidentally contacting live parts.
Operating equipment or touching switches and buttons with wet hands is strictly prohibited to prevent electric shock.
In case of electrical fire, first disconnect the power supply, then use dry powder or carbon dioxide fire extinguishers. Using water to extinguish electrical fires is strictly prohibited.
In case of major coolant leakage, stop the machine and disconnect power immediately, close upstream and downstream valves, organize personnel for cleanup, and prevent liquid from entering electrical areas. Leaked liquid must be disposed of as hazardous waste and must not be discharged arbitrarily.
If skin comes into contact with coolant, rinse promptly with clean water. If accidentally splashed into eyes, immediately rinse with plenty of clean water and seek medical attention.
Children and unauthorized personnel are strictly prohibited from touching the equipment to prevent accidents caused by improper operation.
12.5 Other Precautions
During the warranty period, unauthorized disassembly or modification of the equipment is strictly prohibited; doing so will void the warranty.
If a system fault occurs that the maintenance personnel cannot resolve, contact the manufacturer’s technical support promptly. Do not blindly disassemble or repair.
When relocating or moving the equipment, professional personnel must perform the operation with proper protection to avoid component damage.
Regularly pay attention to the manufacturer’s technical bulletins and promptly perform firmware upgrades and functional optimization.
Establish a sound operation and maintenance management system, clearly define job responsibilities, and conduct regular operation and maintenance training and emergency drills.
To ensure long-term stable and reliable operation of the liquid cooling medium circulation system and extend equipment service life, a regular maintenance system must be established, carrying out daily inspections, regular maintenance, and annual overhauls according to plan.
13.1 Maintenance Cycle Overview
| Maintenance Level | Cycle | Main Content | Executing Personnel |
|---|---|---|---|
| Daily Inspection | Daily/Weekly | Appearance, parameters, status checks | Data center maintenance personnel |
| First-Level Maintenance | Monthly | Cleaning, tightening, consumable parts inspection | Maintenance engineer |
| Second-Level Maintenance | Quarterly | Filter replacement, valve maintenance, calibration checks | Professional maintenance personnel |
| Third-Level Maintenance | Annual | Comprehensive inspection, deep cleaning, performance testing, consumable parts replacement | Manufacturer after-sales engineer |
| Major Overhaul | Every 3~5 years | Seal replacement, pump body maintenance, heat exchanger cleaning, anti-corrosion treatment | Manufacturer professional team |
13.2 Daily Inspection Procedures
13.2.1 Daily Inspection Content
Appearance Inspection:
- Cabinet appearance intact, doors close properly, no abnormal sounds or odors.
- No leaks at pipes, valves, and joints; no liquid accumulation on the floor.
- Insulation layer intact, no peeling, damage, or condensation.
Parameter Inspection:
- Check supply/return water temperature, pressure, and flow rate via the touchscreen; values should be within normal range with no large fluctuations.
- Check circulation pump operating status; current and speed normal, no overload alarms.
- Check valve openings and operating mode are normal.
- Check for alarm messages; record and handle any alarms promptly.
Liquid Level Inspection:
- Check the expansion tank liquid level gauge; level within normal scale range, no significant drop.
- If the liquid level drops too quickly, investigate for possible leaks.
Environmental Inspection:
- Equipment room temperature and humidity normal, no condensation risk.
- No debris blocking around equipment, good ventilation.
13.2.2 Weekly Inspection Content
Based on daily inspections, add the following:
- Filter Differential Pressure Check: Check the filter differential pressure reading to determine the degree of clogging; prepare for replacement in advance when approaching the alarm value.
- Pump Body Inspection: Listen for pump operating sounds — no abnormal noise; touch the pump housing — temperature normal, not noticeably hot.
- Valve Inspection: Check that common valve positions are correct, no external leakage.
- Electrical Inspection: Check inside the electrical cabinet for odors or heat; circuit breakers and contactors show no abnormal temperature rise.
- Leak Detection: Check the leak sensor status and test the alarm function is normal.
- Record Organization: Compile weekly operating data, analyze operating trends, and anticipate potential problems.
13.3 Monthly First-Level Maintenance
Cleaning Work:
- Clean the cabinet exterior surfaces and touchscreen surface to keep them clean and dust-free.
- Use a vacuum cleaner to clean dust inside the cabinet, especially at electrical components and cooling fans.
- Clean the area around the equipment to keep access clear.
Tightening Inspection:
- Tighten electrical terminal strip screws to eliminate loose connection heating hazards.
- Inspect pipe supports and component mounting bolts; tighten any loose parts.
- Check grounding connections to ensure they are secure and reliable.
Valve Maintenance:
- Operate manual valves open/closed several times to prevent valve stem seizure from rust.
- Apply a small amount of lubricating grease to valve stems to maintain smooth operation.
Seal Inspection:
- Check all sealing points for signs of leakage, especially pump seals, valve packing, and flange gaskets.
- Handle minor leaks promptly; replace seals as needed.
Functional Testing:
- Test audible/visual alarms, indicator lights, and buttons for proper function.
- Test the primary/backup pump switching function to ensure the backup pump is operational.
- Check communication connections are normal and data upload is stable.
Record Archiving: Fill in maintenance records and archive them.
13.4 Quarterly Second-Level Maintenance
Filter Maintenance:
- Replace the main line filter cartridge and clean impurities inside the filter housing.
- Check filter cartridge clogging condition and analyze system contamination level.
- Calibrate the differential pressure sensor to ensure accurate detection.
Air Release and Refilling:
- Manually operate air release valves at system high points to discharge accumulated gas.
- Check the expansion tank pre-charge pressure; replenish with nitrogen if insufficient.
- Refill coolant to normal level.
Pump Set Maintenance:
- Check pump mechanical seal leakage; replace seals if leakage exceeds limits.
- Check pump vibration isolation base and flexible connections; replace if aged or damaged.
- Test motor insulation resistance; must meet requirements.
- Clean motor heat sink fins to ensure good heat dissipation.
Heat Exchanger Inspection:
- Check heat exchanger inlet/outlet temperature difference to assess heat exchange efficiency; if the difference is too large, evaluate whether cleaning is required.
- Check heat exchanger sealing surfaces for leaks.
Sensor Calibration:
- Compare and calibrate temperature, pressure, and flow sensors; recalibrate those with significant deviation.
- Check sensor wiring and tighten loose terminals.
Electrical Maintenance:
- Thoroughly tighten all wiring terminals in the electrical circuits.
- Clean variable frequency drive (VFD) and PLC cooling fan filters.
- Check circuit breaker and contactor contacts for burning or oxidation.
- Test the leakage protection function is normal.
13.5 Annual Third-Level Maintenance
Annual maintenance is performed by the manufacturer’s professional engineers, conducting a comprehensive in-depth maintenance of the system to ensure stable operation for the next year.
Comprehensive System Inspection:
- Comprehensive inspection of the entire system’s appearance, piping, valves, and components; document and address any defects.
- Recheck pressure tests to verify system sealing integrity.
- Comprehensive insulation layer inspection; repair damaged sections.
Circulation Pump Deep Maintenance:
- Disassemble the pump body, inspect impeller and pump chamber wear; replace if severely worn.
- Replace mechanical seals and O-rings to ensure reliable sealing.
- Apply grease to bearings; replace worn bearings.
- Maintain motor front and rear bearings; test motor performance.
Heat Exchanger Cleaning:
- Based on the degree of fouling, use chemical cleaning or physical cleaning methods to clean the heat exchanger.
- After cleaning, test heat exchange efficiency; must be restored to above 95% of the design value.
Comprehensive Valve Maintenance:
- Disassemble and inspect all electric valves and solenoid valves, clean valve cores, and replace seals.
- Perform actuator lubrication maintenance and calibrate travel.
- Replace packing on manual valves and lubricate valve stems.
Coolant Testing and Replacement:
- Extract coolant samples for laboratory analysis; test pH value, electrical conductivity, ion concentration, and impurity content.
- If indicators exceed limits, replace all coolant and clean system piping.
- Check the deionized water system’s ion exchange resin; replace if expired.
Electrical System Deep Maintenance:
- Clean and dust all electrical components; inspect for aging.
- Polish or replace contactor and relay contacts.
- Optimize VFD parameters; test capacitor capacitance.
- Upgrade controller firmware; optimize control logic.
Performance Retesting:
- After maintenance completion, perform system performance testing to verify heat exchange capacity, temperature control accuracy, and energy efficiency indicators.
- Retest all protection functions to ensure reliable protection.
Report Issuance:
- Issue an annual maintenance report documenting maintenance contents, replaced components, test data, and operational assessment.
- Provide recommendations for the next year’s operation and improvement measures.
13.6 Periodic Major Overhaul
After 3~5 years of system operation, perform a comprehensive major overhaul to restore system performance and extend service life.
- Full System Disassembly and Cleaning: Disassemble all piping, heat exchangers, pump bodies, and valves; thoroughly clean internal fouling, corrosion products, and biological slime.
- Replace All Consumable Parts: Replace all seals, O-rings, gaskets, diaphragms, and bearings.
- Pump Body Overhaul: Replace wear parts, perform performance testing; replace the entire pump if it fails to meet requirements.
- Heat Exchanger Overhaul: For plate-type heat exchangers, replace sealing gaskets, inspect plate corrosion; replace plates with severe corrosion.
- Pipe Anti-Corrosion Treatment: Perform passivation anti-corrosion treatment on pipe inner walls; derust and repaint outer walls.
- Electrical Upgrade: Replace aged electrical components; upgrade and optimize the control system.
- Complete Machine Performance Testing: After overhaul, perform comprehensive performance testing according to new machine standards; all indicators must reach over 90% of new machine performance.
13.7 Common Component Replacement Methods
13.7.1 Filter Cartridge Replacement
1. Close the valves before and after the filter, open the drain valve at the bottom of the filter, and drain the internal coolant.
2. Unscrew the filter top cover, remove the old cartridge, and clean impurities inside the filter housing.
3. Inspect the O-ring seal; replace if aged, apply a small amount of silicone grease.
4. Install the new cartridge, ensuring correct orientation, and tighten the top cover.
5. Close the drain valve, slowly open the inlet valve to fill and vent air, then open the outlet valve to resume operation.
6. Check for leaks and verify the differential pressure reading is normal.
13.7.2 Expansion Tank Pre-charge Pressure Adjustment
1. Depressurize the system, close the valve on the expansion tank side, and confirm there is no pressure in the tank.
2. Use a pressure gauge to test the nitrogen pre-charge pressure in the tank; it should normally be approximately 70% of the system working pressure.
3. If pressure is insufficient, charge with a nitrogen cylinder to the specified value; if pressure is too high, release some gas appropriately.
4. After adjustment, replace the valve cap, open the system valve, and resume operation.
13.7.3 Temperature Sensor Replacement
1. Shut down the system, disconnect the sensor wiring, and mark wire numbers.
2. Unscrew the old sensor and clean the threads of the mounting hole.
3. Apply thermal conductive silicone grease to the new sensor probe, screw into the mounting hole, and tighten securely.
4. Reconnect the wiring according to the markings, restore power, and verify the temperature reading is normal.
13.8 Maintenance Safety Regulations
All maintenance operations must implement the power-off, voltage verification, and tagging procedures. Working on live equipment is strictly prohibited.
Before servicing pressurized components, pressure must be released and confirmed to be zero before disassembly.
Safety harnesses must be worn when working at heights, and qualified tools must be used.
When performing chemical cleaning operations, wear protective equipment, ensure adequate ventilation, and prevent chemical burns.
Replaced waste filter cartridges, waste coolant, and waste grease must be disposed of according to hazardous waste regulations and must not be discarded arbitrarily.
After maintenance, a trial run inspection must be performed; leave the site only after confirming no problems.
Keep detailed records for every maintenance session to establish a complete equipment lifecycle file.
14.1 Leakage Faults
14.1.1 Pipe Joint Leakage
Fault Phenomenon: Coolant seeps from pipe threaded joints or quick couplings; liquid accumulation marks on the floor.
Cause:
- Joint threads not tightened sufficiently, or insufficient Teflon tape wrapping.
- Seal ring aged, damaged, or scratched during installation.
- Excessive pipe stress; joint subjected to external force.
- System overpressure causing seal failure.
Solution:
- For minor leaks, first tighten the joint and observe whether the leak stops.
- If tightening is ineffective, shut down, release pressure, disassemble the joint, inspect the seal ring, and replace if damaged.
- Re-wrap Teflon tape on threads and tighten to the specified torque.
- Inspect pipe supports to eliminate pipe stress; add supports where necessary.
- Check system pressure; if overpressure, investigate the cause of excessive pressure.
Preventive Measures: Standardize installation procedures, use quality seals, conduct regular inspections to detect and handle issues promptly.
14.1.2 Pump Mechanical Seal Leakage
Fault Phenomenon: Coolant drips at the pump shaft seal, flowing in a stream in severe cases.
Cause:
- Mechanical seal normal wear, reaching service life.
- System liquid shortage causing dry running, burning the seal faces.
- Coolant contains abrasive particles, wearing the seal faces.
- Severe pump cavitation impacting the seal faces.
- Large pump shaft vibration causing poor seal face contact.
Solution:
- Minor leakage (≤3 drops/minute) is considered normal; continue observation.
- If leakage exceeds the limit, shut down and replace the mechanical seal assembly.
- Check system liquid level and air release to prevent cavitation and dry running.
- Check the filter to ensure effective filtration and prevent impurities from entering the pump.
- Check pump alignment and vibration isolation to reduce vibration.
Preventive Measures: Dry running operation is strictly prohibited; replace filter cartridges regularly; avoid long-term pump cavitation operation.
14.1.3 Heat Exchanger Internal Leakage
Fault Phenomenon: Primary and secondary side media mix together; secondary side coolant level abnormally rises or changes color; electrical conductivity becomes abnormal.
Cause:
- Heat exchanger plate corrosion perforation.
- Plate sealing gasket aged and failed.
- System overpressure causing plate deformation and cracking.
Solution:
- Shut down immediately, isolate the heat exchanger to prevent contamination spread.
- For plate-type heat exchangers, disassemble and inspect, replace damaged plates and sealing gaskets.
- Brazed plate heat exchangers require complete replacement.
- Clean both side piping and replace contaminated coolant.
- Investigate the cause of overpressure and adjust system pressure.
Preventive Measures: Control coolant quality to prevent corrosion; strictly prohibit overpressure operation; regularly test medium composition.
14.2 Flow and Pressure Faults
14.2.1 Insufficient System Flow
Fault Phenomenon: Flow meter reading below normal value; supply/return temperature difference increases; equipment temperature runs high.
Cause:
- Filter clogged, flow resistance increased.
- Pipe valve opening insufficient or accidentally closed.
- Circulation pump speed too low; VFD parameter settings incorrect.
- Severe air accumulation in the system, forming air locks.
- Pump impeller worn or blocked, output reduced.
- Cold plate/heat exchange component blocked, branch circuit resistance increased.
Solution:
- Check filter differential pressure; replace cartridge if clogged.
- Check all valve openings to ensure fully open.
- Check VFD output frequency and pump speed; adjust to correct parameters.
- Perform system air release; open high-point air release valves; if necessary, start/stop the pump multiple times to assist air discharge.
- Disassemble and inspect the pump body, clean debris from the impeller; replace impeller if severely worn.
- Investigate branch circuit blockages; check flow in each circuit; clean clogged cold plates.
Preventive Measures: Replace filter cartridges regularly; fully flush piping during initial installation; perform regular air release.
14.2.2 Excessive System Pressure
Fault Phenomenon: System pressure continuously rises beyond the normal range; safety valve trips.
Cause:
- Expansion tank undersized or pre-charge pressure insufficient to accommodate thermal expansion.
- Make-up water valve fault, continuous refilling causing overpressure.
- System outlet valve accidentally closed, causing pressure buildup.
- Rapid temperature rise causing rapid coolant expansion.
- Primary side pressure too high, transferring through the heat exchanger.
Solution:
- Immediately open the drain valve to release pressure appropriately; check whether the outlet valve is fully open.
- Check expansion tank pre-charge pressure; replenish nitrogen if insufficient; replace with a larger tank if undersized.
- Inspect the automatic make-up valve; close the manual make-up valve and replace the valve if faulty.
- Control the temperature rise rate to avoid sudden temperature spikes.
- Check primary side pressure; adjust the cold source side pressure if too high.
Preventive Measures: Regularly check expansion tank pressure and make-up valve status; strictly prohibit closing outlet valves during operation.
14.2.3 Low System Pressure
Fault Phenomenon: System pressure continuously drops below normal working pressure; low pressure alarm triggered.
Cause:
- System has leak points; coolant slowly escaping.
- Automatic make-up valve fault, unable to refill automatically.
- Expansion tank pre-charge pressure too high; insufficient liquid volume in the system.
- Temperature decrease causing coolant volume contraction.
- Excessive liquid discharged during air release.
Solution:
- Conduct comprehensive leak investigation; locate and repair all leaks.
- Manually refill coolant to normal level; check whether the make-up valve is blocked or damaged; replace if faulty.
- Adjust expansion tank pre-charge pressure to the correct value.
- Pressure decrease due to temperature drop is normal; restored after automatic make-up.
- Monitor liquid level during air release and refill promptly.
Preventive Measures: Conduct regular inspections for leaks; regularly check make-up valve function; ensure correct expansion tank parameters.
14.2.4 Large Pressure Fluctuation
Fault Phenomenon: Pressure gauge pointer swings significantly; unstable flow rate; abnormal pump noise.
Cause:
- Large amount of air in the system; gas-liquid mixing causes pressure fluctuation.
- Insufficient liquid level at pump inlet, causing cavitation.
- Unstable pump speed; VFD malfunction.
- Loose pipe supports causing pipe vibration.
Solution:
- Thoroughly perform system air release to discharge all accumulated gas.
- Refill coolant, increase inlet pressure to eliminate cavitation.
- Check the VFD and motor; troubleshoot speed fluctuation faults.
- Tighten pipe supports; add vibration dampening measures.
Preventive Measures: Fully vent air during initial operation; perform regular manual air release; maintain normal liquid level.
14.3 Temperature Faults
14.3.1 Supply Water Temperature Too High, Insufficient Cooling
Fault Phenomenon: Supply water temperature higher than set value and cannot be reduced; load equipment temperature high.
Cause:
- Primary side cold source temperature too high; insufficient cooling capacity.
- Electric regulating valve opening insufficient or stuck; insufficient cold source water flow.
- Heat exchanger fouled and blocked; heat exchange efficiency decreased.
- Insufficient system flow; heat exchange capacity insufficient.
- Load exceeds system rated heat exchange power.
- Temperature sensor fault; display deviation.
Solution:
- Check primary side inlet water temperature; if too high, coordinate with cold source side to lower supply temperature.
- Check electric regulating valve opening; test with manual full-open; if stuck, disassemble and clean or replace the actuator.
- Check heat exchanger temperature difference; if fouled, clean the heat exchanger.
- Investigate the cause of insufficient flow and increase system flow rate.
- Verify actual load; if overloaded, add cold source capacity or upgrade the system.
- Calibrate temperature sensors; replace if faulty.
Preventive Measures: Clean heat exchanger regularly; regularly maintain regulating valves; ensure cold source supply water parameters meet requirements.
14.3.2 Supply Water Temperature Too Low, Large Temperature Fluctuation
Fault Phenomenon: Supply water temperature below set value, frequent fluctuation, unstable control.
Cause:
- Primary side cold source temperature too low; excessive cooling capacity.
- Electric regulating valve poor regulation performance; severe overshoot.
- PID parameters set unreasonably; regulation oscillation.
- Bypass valve opening too small; over-regulation at low load.
- Temperature sensor improperly installed; detection lag.
Solution:
- Appropriately raise primary side supply temperature to reduce cooling input.
- Re-tune PID parameters; optimize the regulation curve.
- Appropriately increase the bypass valve opening to add return water mixing and stabilize temperature.
- Check the regulating valve core; replace if severely worn.
- Optimize sensor installation position to ensure accurate and timely detection.
Preventive Measures: Optimize PID parameters during commissioning; reasonably use bypass at low loads.
14.3.3 Supply/Return Temperature Difference Too Small
Fault Phenomenon: Supply/return temperature difference far below design value; high flow rate but low heat exchange.
Cause:
- Actual load small; low heat exchange rate.
- Poor contact between cold plate and components; poor heat transfer.
- Flow rate too high, exceeding load demand.
- Temperature sensor detection deviation.
Solution:
- Low load is a normal phenomenon; reduce pump speed for energy saving.
- Check cold plate installation; reapply thermal conductive silicone grease; tighten evenly.
- Appropriately reduce pump speed to decrease flow rate, increase temperature difference, and improve energy efficiency.
- Calibrate temperature sensors.
Preventive Measures: The variable frequency system automatically adjusts flow based on load for optimal temperature difference operation.
14.4 Pump Set Faults
14.4.1 Water Pump Fails to Start
Fault Phenomenon: Pump does not rotate after start signal; no sound or buzzing sound.
Cause:
- Power not connected; circuit breaker tripped.
- Contactor or relay damaged or wiring loose.
- VFD fault or protection activated.
- Motor burned out; winding open circuit or short circuit.
- Pump impeller seized; rusted after long shutdown or blocked by foreign objects.
- Thermal relay overload protection activated without reset.
Solution:
- Check power supply and circuit breaker; investigate and reset after tripping.
- Check control circuit; replace damaged contactors/relays; tighten wiring.
- Check VFD fault code and handle according to fault indications.
- Use a multimeter to test motor windings; repair or replace the motor if burned out.
- Manually turn the shaft to check for seizure; if seized, disassemble the pump body, remove foreign objects, and apply anti-rust lubrication.
- Reset the thermal relay; investigate the cause of overload.
Preventive Measures: Regularly check electrical connections; periodically rotate the shaft during long shutdowns; avoid overload operation.
14.4.2 Loud Pump Operating Noise and Excessive Vibration
Fault Phenomenon: Abnormal noise during pump operation; significant body vibration; pipe resonance.
Cause:
- System cavitation; bubble collapse inside the pump produces noise.
- Impeller wear or dynamic balance destruction; increased vibration.
- Pump and motor misalignment; large coupling deviation.
- Loose base fixing; aged vibration dampening pads.
- Bearing damage; lack of grease or wear.
- Pipe resonance; fluid pulsation causing pipe vibration.
Solution:
- Investigate cavitation causes; release air, refill liquid, increase inlet pressure.
- Disassemble and inspect the impeller; replace if severely worn; redo dynamic balancing.
- Re-align the pump and motor coaxiality within allowable deviation.
- Tighten base bolts; replace aged vibration dampening pads.
- Replace bearings; apply grease.
- Add pipe supports; install silencers or flexible connections to eliminate resonance.
Preventive Measures: Avoid cavitation operation; regularly maintain bearings; ensure installation alignment accuracy.
14.4.3 Pump Overload Tripping
Fault Phenomenon: Excessive current during pump operation; thermal relay or circuit breaker trips.
Cause:
- Medium temperature too low; viscosity too high, increasing load.
- Flow rate too high, exceeding pump rated operating conditions.
- Impeller seized or bearing damaged; excessive mechanical load.
- Motor running with phase loss.
- Supply voltage too low; current increases.
- Motor winding inter-turn short circuit.
Solution:
- In low-temperature environments, preheat the medium first, then increase speed after temperature rises.
- Close the outlet valve to reduce flow to rated range.
- Disassemble the pump body; remove foreign objects; replace damaged bearings.
- Check power supply and wiring; eliminate phase loss faults.
- Check supply voltage; rectify power supply if voltage is too low.
- Test motor windings; repair or replace the motor if short-circuited.
Preventive Measures: Avoid over-flow operation; gradually increase speed at low temperatures; regularly check electrical conditions.
14.5 Control and Alarm Faults
14.5.1 Touchscreen No Display
Fault Phenomenon: Touchscreen black screen after system power-up; no display.
Cause:
- 24V control power supply fault; no output.
- Touchscreen power wiring loose.
- Touchscreen itself damaged.
- Fuse blown.
Solution:
- Use a multimeter to test 24V power output; replace the power module if no output.
- Tighten touchscreen power wiring.
- If power is normal and still no display, replace the touchscreen.
- Check the fuse; replace with same specification if blown, and investigate the cause of the short circuit.
Preventive Measures: Provide stable power supply; avoid voltage surges; regularly check wiring.
14.5.2 Abnormal Sensor Display
Fault Phenomenon: Temperature, pressure, or flow readings inaccurate, jumping, or no display.
Cause:
- Sensor wiring loose or poor contact.
- Sensor damaged or drifted.
- Signal affected by electromagnetic interference.
- Analog input channel fault.
- Probe fouled or blocked; inaccurate detection.
Solution:
- Check wiring, tighten terminals, ensure good contact.
- Calibrate sensors; replace if deviation is too large.
- Check shielded wire grounding; keep away from high-power lines; eliminate interference.
- Replace the PLC input channel to determine if the channel is damaged.
- Clean sensor probe fouling and impurities.
Preventive Measures: Standardize wiring layout; separate high and low voltage lines; calibrate sensors regularly.
14.5.3 False Alarms or No Alarms
Fault Phenomenon: Frequent alarms when parameters are normal, or no alarm when a fault occurs.
Cause:
- Alarm threshold settings unreasonable.
- Sensor inaccurate detection; numerical deviation.
- Controller program fault.
- Alarm output circuit fault.
Solution:
- Reset reasonable alarm thresholds and delays.
- Calibrate or replace sensors.
- Restart the controller, upgrade firmware; if program fault, re-download the program.
- Check the alarm output circuit; replace damaged components.
Preventive Measures: Set alarm parameters reasonably; regularly test alarm functions.
14.6 Coolant Quality Faults
14.6.1 Coolant Discolored and Turbid
Fault Phenomenon: Coolant color darkens, becomes turbid, with suspended matter or odor.
Cause:
- Pipe corrosion in the system, producing metal ions and oxides.
- Microbial growth producing biological slime.
- Impurities entering the system, contaminating the coolant.
- Coolant expired; additives depleted.
Solution:
- Take samples for testing to confirm contamination level.
- For light contamination, replace the filter cartridge and strengthen filtration.
- For severe contamination, drain all coolant, clean system piping, and refill with new liquid.
- Add corrosion inhibitors and biocides to restore coolant performance.
Preventive Measures: Use qualified coolant; regularly test coolant quality; replace coolant on schedule.
14.6.2 Conductivity Exceeds Limits (Deionized Water System)
Fault Phenomenon: Conductivity continuously rises, exceeding the safety threshold.
Cause:
- Ion exchange resin exhausted.
- System corrosion producing metal ions.
- Make-up water quality unqualified, introducing ions.
- Primary side water leaking into secondary side.
Solution:
- Replace the ion exchange resin.
- Investigate corrosion causes; add corrosion inhibitors.
- Ensure make-up water is qualified deionized water.
- Check for heat exchanger internal leakage; repair the heat exchanger if leaking.
Preventive Measures: Monitor conductivity regularly; replace resin on schedule; ensure make-up water quality.
15.1 Basic Knowledge
Q1: What are the advantages of the liquid cooling system compared to air cooling systems?
A: Compared to traditional air cooling, the core advantages of the liquid cooling system are: ① Strong heat dissipation capability, supporting high-density loads of over 100kW per single cabinet; ② High energy efficiency, with PUE reduced to below 1.15, saving over 30% energy; ③ Low noise, with operating noise ≤55dB, improving the equipment room environment; ④ High temperature control accuracy, within ±0.5°C, ensuring stable equipment operation; ⑤ Unaffected by altitude, dust, and other environmental factors, with stronger adaptability.
Q2: What types of coolant does this system support?
A: This system supports modified deionized water, ethylene glycol water solutions, electronic fluorinated fluids, synthetic hydrocarbon coolants, and other media. Different media correspond to different seal and material configurations. Please specify the coolant type when ordering. Users are not recommended to change media types on their own; contact the manufacturer for evaluation and modification if a change is needed.
Q3: How long is the system service life?
A: Under normal maintenance and standard usage, the system design service life is ≥15 years. Consumable parts such as seals, filter cartridges, and bearings require regular replacement. Core components such as pump bodies, heat exchangers, and controllers have a service life of 8~10 years or more.
Q4: Will the system leak? Is it safe?
A: This system features a fully closed loop design and undergoes strict pressure testing before leaving the factory. Under normal operation, the risk of leakage is extremely low. The system is also equipped with multiple leak detection protections, allowing even minor seepage to be detected and alarmed promptly. With standardized installation and regular maintenance, leakage accidents can be effectively prevented. Compared to open-loop liquid cooling solutions, safety is significantly improved.
15.2 Installation and Deployment
Q1: Does installing this system require modifying the equipment room?
A: This system is a cabinet-level integrated product that is self-contained and does not require large-scale modification of the equipment room. On-site requirements are only a power interface, a primary side cold source interface, and a liquid cooling interface for connecting to the load. It is highly suitable for retrofitting existing equipment rooms without affecting the original air conditioning and layout.
Q2: How long is the installation cycle?
A: For a single system, from equipment positioning to installation and wiring completion takes approximately 1~2 days; pipe flushing, pressure testing, and commissioning take approximately 2~3 days; the overall installation and commissioning cycle is 3~5 days. Parallel construction of multiple systems can shorten the cycle. The specific cycle depends on project scale and site conditions.
Q3: Are there floor load-bearing requirements for the equipment room?
A: A single system weighs approximately 300~700kg when fully filled with liquid. The installation floor load-bearing capacity must be ≥1000kg/m². For standard raised-floor equipment rooms, it is recommended to install above load-bearing beams or perform load-bearing reinforcement.
Q4: Can it be used together with the existing air cooling system?
A: Yes. The liquid cooling system primarily handles heat dissipation for high-heat components such as CPUs and GPUs, while components like memory and hard drives can retain the original air cooling as auxiliary cooling, forming a hybrid cooling solution with higher safety redundancy.
15.3 Operation
Q1: Does the system require dedicated personnel on duty?
A: The system supports fully automatic unattended operation with comprehensive automatic control and protection functions. No dedicated personnel are required for normal operation. Only routine daily inspections by maintenance personnel are needed. With the optional remote monitoring platform, remote management can be achieved, further reducing on-site staffing requirements.
Q2: What happens during a power outage?
A: The system features power-loss memory and automatic restart upon power restoration. After a power outage, the system automatically shuts down. Upon power restoration, it can be set to automatically start and operate according to pre-outage parameters without manual operation. It can also be set to manual start mode, selectable based on site requirements.
Q3: Will it freeze in cold winter environments?
A: If ethylene glycol antifreeze is used, depending on concentration, it can withstand low temperatures from -10°C to -45°C without freezing. If deionized water is used, the liquid must be drained during shutdown in low-temperature environments, or low-temperature circulation must be maintained to prevent freezing damage. The system is equipped with a low-temperature heating function that can automatically preheat, avoiding cold-start damage.
Q4: Can the system be remotely controlled?
A: The system comes standard with an RS485 communication interface supporting the Modbus protocol, which can be connected to the equipment room’s environment monitoring system (DCIM) for remote monitoring. With the optional cloud platform module, parameters can be viewed remotely via computer or mobile phone APP, alarms can be received, and parameters can be set remotely — very convenient.
15.4 Maintenance
Q1: Is daily maintenance troublesome? Does it require professional personnel?
A: Daily inspection operations are simple, and ordinary data center maintenance personnel can handle them after brief training. Quarterly and annual maintenance is recommended to be performed by professionals. The manufacturer can provide after-sales maintenance services or train the user’s maintenance personnel. Overall maintenance workload is far less than that of precision air conditioning systems for air cooling.
Q2: How often should the coolant be changed?
A: Different media have different replacement cycles: modified deionized water is recommended for replacement every 2 years; ethylene glycol water solutions are recommended for replacement every 2 years; electronic fluorinated fluids have a longer service life, recommended for testing and replacement every 5~8 years. Replacement timing can be determined based on coolant test results.
Q3: How often should the filter cartridge be replaced?
A: Under normal operating conditions, the main line filter cartridge should be replaced every 3 months. If the system is relatively clean and the differential pressure rises slowly, the interval can be appropriately extended; if the environment is poor with more impurities, the replacement cycle should be shortened. Use the differential pressure alarm value as a reference; the cartridge must be replaced when the differential pressure reaches 0.1MPa.
Q4: How long is the warranty period, and what does the warranty cover?
A: The complete machine carries a 1-year warranty, and core components carry a 2-year warranty. Non-artificial damage during the warranty period is repaired or replaced free of charge. Consumable parts (filter cartridges, seals, etc.) are considered wear items and are not covered by the warranty. After the warranty period, maintenance agreements can be signed to enjoy regular maintenance and on-site repair services.
15.5 Fault Emergency Response
Q1: What should be done if a leak occurs?
A: Upon discovering a leak, follow these steps: ① Immediately press the emergency stop button to halt system operation; ② Close the system inlet and outlet valves to isolate the coolant circuit; ③ Disconnect equipment power; ④ Locate the leak point, use a catch pan to contain leaking liquid and prevent spread; ⑤ Contact manufacturer technical personnel for repair; ⑥ Clean up the leaked liquid at the site and dispose of waste liquid according to regulations.
Q2: What should be done when the system alarms?
A: First, check the fault code and fault description on the touchscreen, and perform initial troubleshooting based on the prompts. General alarms (such as filter clogging, low liquid level) can continue operation while arranging prompt handling; serious alarms (such as overtemperature, leakage, extremely low flow) will trigger automatic system shutdown. After troubleshooting and resolving the fault, manually reset and restart. If unable to handle, contact the manufacturer’s technical support promptly.
Q3: Will a pump failure affect equipment operation?
A: For models configured with 1+1 redundant pumps, if the primary pump fails, the system will automatically switch to the backup pump without interrupting cooling, and IT equipment operation will not be affected. For single-pump models, pump failure will cause system shutdown, and prompt repair is required. For applications requiring high reliability, redundant pump configurations are recommended.
Q4: Can the system still operate if the cold source fails?
A: If the primary side cold source fails, the secondary side circulation can continue to operate, but the coolant temperature will gradually rise. The system will issue an overtemperature alarm and perform shutdown protection when the temperature reaches the protection threshold. Short-duration cold source interruptions can be sustained by the system’s thermal capacity for a period; long-duration cold source failures require shutting down IT equipment to prevent overheating damage.
15.6 Customization and Expansion
Q1: Can the dimensions and power be customized according to our cabinet?
A: Yes. KITOZER supports a full range of customization. Customized design can be provided based on user cabinet dimensions, power loads, interface types, and special functional requirements to meet personalized needs across different scenarios.
Q2: Can the power be upgraded in the future?
A: The system features a modular design. Within a certain range, power upgrades can be achieved by replacing the pump set and heat exchanger. The specific upgrade space needs to be evaluated based on the model. It is recommended to reserve some margin during selection.
Q3: Can it be integrated into our existing environment monitoring system?
A: Yes. The system supports multiple standard communication protocols including Modbus-RTU, Modbus-TCP, and SNMP, and can seamlessly integrate with mainstream brand environment monitoring systems and DCIM platforms. Custom protocol development for integration can also be provided based on the user’s system.
16.1 Acceptance Basis
The acceptance of this system strictly follows the following documents and standards:
- Purchase contract and technical agreement
- This installation, wiring, and commissioning manual
- GB/T 39663-2020 “Liquid cooling distribution unit for computer and data processing room”
- T/CESA 1249.2-2023 “Technical specification for liquid cooling devices for servers and storage equipment”
- GB 50303-2015 “Code for acceptance of quality of construction of electrical engineering in building”
- GB 50236-2011 “Specification for construction of field equipment and industrial pipe welding engineering”
16.2 Acceptance Stage Division
Acceptance work is divided into three stages: incoming inspection acceptance, sub-project engineering acceptance, and completion acceptance.
16.2.1 Incoming Inspection Acceptance
After equipment and materials arrive, the construction party, supervision party, contractor party, and supplier party jointly conduct the incoming inspection acceptance:
- Appearance Inspection: Equipment packaging intact, no damage or moisture; equipment appearance free of collisions, deformation, paint peeling, or rust.
- Quantity Verification: Check against the packing list item by item — host unit, accessories, auxiliary materials, and documentation — verify model, specification, and quantity; confirm complete.
- Documentation Verification: Product certificate, factory inspection report, manual, warranty card, and other technical documents complete and valid.
- Performance Spot Check: Key components can undergo power-on spot checks to confirm basic functions are normal.
After passing acceptance, sign the “Equipment Incoming Inspection Acceptance Form” before proceeding to the installation stage.
16.2.2 Sub-Project Engineering Acceptance
During the installation and construction process, key sub-project engineering items undergo staged acceptance. The next sub-project may only proceed after the previous one has passed acceptance:
- Cabinet Installation Acceptance: Verify cabinet positioning, levelness, verticality, fixing, and grounding; fill in the “Cabinet Installation Acceptance Record.”
- Pipe Installation Acceptance: Verify pipe layout, slope, welding, supports, and valve installation; fill in the “Pipe Installation Acceptance Record.”
- Pressure Test Acceptance: Witness the strength test and tightness test throughout; pressure drop and leakage conditions must meet requirements; fill in the “Pipe Pressure Test Record.”
- Electrical Wiring Acceptance: Verify wiring workmanship, insulation test, grounding test, and phase sequence check; fill in the “Electrical Installation Acceptance Record.”
- Insulation and Labeling Acceptance: Verify insulation layer thickness, quality, and pipe labeling; fill in the “Insulation and Labeling Acceptance Record.”
16.2.3 Completion Acceptance
After system installation and commissioning is complete and the continuous 72-hour full-load trial run has passed, the overall completion acceptance is performed.
16.3 Acceptance Check Content and Standards
16.3.1 Documentation Acceptance
As-built documentation must be complete, comprehensive, and bound into volumes, including:
- As-built drawings: system diagrams, floor plans, electrical schematic diagrams, piping diagrams.
- Equipment documentation: certificates of conformity, instruction manuals, test reports, warranty cards.
- Construction records: installation records, welding records, pressure test records, insulation test records, commissioning records.
- Acceptance records: sub-item acceptance records, trial operation records.
- Operation and maintenance manuals: operation guide, maintenance manual, troubleshooting manual.
- Others: change orders, engineering consultations, material certificates of conformity, etc.
16.3.2 Appearance and Installation Quality Acceptance
- Equipment installed in correct positions, neatly and aesthetically arranged, and firmly secured.
- Piping runs horizontally and vertically true, supports secure, slopes meet requirements, and markings are clear and complete.
- Valves and instruments installed upright, with correct operating directions, and easily accessible for maintenance.
- Insulation layer complete and aesthetically pleasing, free from damage, thermal bridges, or condensation.
- Electrical wiring neat and standardized, with clear markings and reliable grounding.
- Equipment surfaces clean, free from stains or dust; site left clean and tidy.
16.3.3 Performance Indicator Acceptance
- Heat exchange capacity: Under rated load, the system’s actual heat exchange rate must be ≥ the rated heat exchange power.
- Temperature control accuracy: During steady-state operation, the secondary side supply water temperature fluctuation must be ≤ ±0.5°C.
- Flow rate and pressure: Under rated conditions, flow rate and pressure must reach design values and meet load requirements.
- Energy efficiency indicators: System energy efficiency ratio must reach the design value, with energy-saving effects conforming to the agreement.
- Noise indicator: Noise level at 1 meter from the equipment must be ≤ 55 dB(A).
- Continuous operation: 72 hours of continuous full-load operation without faults, leaks, or parameter instability.
16.3.4 Functional Acceptance
- Automatic control function: System operates normally in fully automatic mode, with correct start/stop logic and stable temperature control.
- Variable frequency adjustment function: Pump variable frequency adjustment operates normally, with flow rate automatically adapting to load changes.
- Primary/standby switching function: Redundant pump switching operates normally, with no interruption during the switching process.
- Protection functions: Over-temperature, over-pressure, low flow, liquid leak, overload, and other protection functions must operate accurately and reliably, with timely alarms.
- Communication function: Data upload operates normally, remote monitoring is stable, and protocols are compatible.
- Human-machine interface function: Touchscreen operation is smooth, displays are accurate, and parameter setting and history query functions operate normally.
16.3.5 Safety Acceptance
- Grounding system is reliable, with grounding resistance ≤ 1Ω.
- Electrical insulation is qualified, with no risk of electric leakage.
- Safety protection devices are complete, with emergency stop and alarm functions operating normally.
- Leak detection and protection measures are in place.
- Warning signs are complete, and safety passages are unobstructed.
16.4 72-Hour Full-Load Trial Operation
Before acceptance, a 72-hour continuous full-load trial operation must be conducted to simulate actual operating conditions.
During the trial operation, the system operates in automatic mode carrying all rated loads.
Personnel shall be arranged for shift duty, recording operating parameters every 2 hours, including temperature, pressure, flow rate, current, voltage, etc.
If a fault occurs during the trial operation, the timer restarts after the fault is repaired, until 72 consecutive hours of fault-free operation are achieved.
After the trial operation concludes, compile the trial operation data and issue the “72-Hour Trial Operation Report.”
16.5 Acceptance Procedure
After the construction contractor completes all installation, commissioning, and internal inspection to a qualified standard, it submits the completion acceptance application and as-built documentation.
The construction owner and supervision unit review the documentation; once the documentation is complete, the acceptance is organized.
The acceptance team inspects and tests item by item according to the acceptance content, filling out acceptance record forms.
After all items pass, all parties sign the “Completion Acceptance Certificate,” and the system is officially handed over for use.
If issues are found during acceptance, a rectification notice is issued, the construction contractor rectifies within the specified deadline, and re-inspection is conducted after rectification is completed.
After acceptance passes, the warranty period begins, and the manufacturer provides warranty services as promised.
16.6 Example Acceptance Form
Liquid Cooling Medium Circulation System Completion Acceptance Form
| Project Name | Acceptance Date | ||
|---|---|---|---|
| Equipment Model | Equipment Serial No. |
<table>
<tr>
<th>No.</th>
<th>Acceptance Item</th>
<th>Acceptance Content and Standard</th>
<th>Acceptance Result</th>
</tr>
<tr>
<td>1</td>
<td>Documentation Acceptance</td>
<td>As-built documentation complete, comprehensive, and accurate</td>
<td></td>
</tr>
<tr>
<td>2</td>
<td>Appearance & Installation</td>
<td>Equipment installed securely and neatly, piping standardized, markings clear</td>
<td></td>
</tr>
<tr>
<td>3</td>
<td>Heat Exchange Capacity</td>
<td>Rated heat exchange capacity reaches design value</td>
<td></td>
</tr>
<tr>
<td>4</td>
<td>Temperature Control Accuracy</td>
<td>Supply water temperature fluctuation ≤ ±0.5°C</td>
<td></td>
</tr>
<tr>
<td>5</td>
<td>Operational Stability</td>
<td>72 hours of continuous operation without faults</td>
<td></td>
</tr>
<tr>
<td>6</td>
<td>Protection Functions</td>
<td>All protection actions accurate, alarms normal</td>
<td></td>
</tr>
<tr>
<td>7</td>
<td>Electrical Safety</td>
<td>Insulation qualified, grounding resistance ≤ 1Ω</td>
<td></td>
</tr>
<tr>
<td>8</td>
<td>Noise Indicator</td>
<td>≤ 55 dB(A)</td>
<td></td>
</tr>
<tr>
<td>9</td>
<td>Communication Function</td>
<td>Environmental monitoring integration normal, data stable</td>
<td></td>
</tr>
<tr>
<td>10</td>
<td>Leak Inspection</td>
<td>No leaks throughout the entire system</td>
<td></td>
</tr>
</table>
| Acceptance Conclusion | ||
|---|---|---|
| Construction Owner | Signature: | Seal: |
| Supervision Unit | Signature: | Seal: |
| Construction Unit | Signature: | Seal: |
| Supply Unit | Signature: | Seal: |
Appendix
Appendix A Fault Code Table
| Fault Code | Fault Name | Fault Level | Handling Recommendation |
|---|---|---|---|
| E001 | Supply Water Over-temperature | Severe | Check cold source, heat exchanger, flow rate; reset after cooling |
| E002 | Return Water Over-temperature | General | Check if load is excessive; increase cooling capacity |
| E003 | Supply Water Low Temperature | General | Check heating function; raise set temperature |
| E004 | System Over-pressure | Severe | Check water make-up valve, expansion tank; reset after pressure relief |
| E005 | System Low Pressure | General | Check for leaks; replenish coolant |
| E006 | Flow Rate Too Low | Severe | Check valves, filters, pump; reset after troubleshooting |
| E007 | Pump Overload | Severe | Check pump body, power supply; reset and retry |
| E008 | Leak Alarm | Emergency | Stop immediately; investigate leak point |
| E009 | Sensor Fault | General | Check sensor wiring; replace sensor |
| E010 | Power Phase Loss | Severe | Check three-phase power supply |
Appendix B Common Parameter Reference Table
| Parameter Name | Default Value | Adjustment Range | Remarks |
|---|---|---|---|
| Supply Water Set Temperature | 25°C | 15~45°C | Adjust according to load |
| Over-temperature Alarm Threshold | 32°C | 25~50°C | |
| Over-pressure Alarm Threshold | 0.45 MPa | 0.3~0.8 MPa | |
| Low Pressure Alarm Threshold | 0.1 MPa | 0.05~0.2 MPa | |
| Low Flow Alarm Threshold | 30% of rated flow | 10%~50% | |
| Pump Start Delay | 10 seconds | 5~60 seconds | |
| Power-on Auto Start | Enabled | Enabled/Disabled |
Appendix C Periodic Maintenance Schedule
| Maintenance Item | Period | Responsible Person | Recording Requirements |
|---|---|---|---|
| Daily Inspection | Daily | Operation & Maintenance Technician | Fill in inspection record form |
| Filter Element Replacement | 3 months | Operation & Maintenance Engineer | Record replacement time and pressure differential |
| System Air Venting | Monthly | Operation & Maintenance Engineer | Record venting status |
| Expansion Tank Pressure Check | Quarterly | Operation & Maintenance Engineer | Record nitrogen pressure |
| Sensor Calibration | Annually | Metrology Personnel | Issue calibration record |
| Coolant Testing | Semi-annually | Third Party | Issue test report |
| Annual Maintenance | Annually | Manufacturer Engineer | Issue annual maintenance report |
SEO Optimization System
I. Search Keyword Category Distribution
1. Core Primary Keywords
Liquid cooling medium circulation system, liquid-cooled integrated cabinet, cabinet liquid cooling system, liquid cooling circulation system, closed-loop liquid cooling system
2. High-Conversion Long-Tail Keywords
Liquid cooling medium circulation system installation manual, liquid-cooled cabinet wiring and commissioning guide, integrated liquid cooling system manufacturer, data center liquid cooling circulation system quotation, cold plate liquid cooling circulation system, liquid cooling system installation and commissioning service, high-density cabinet liquid cooling solution, liquid cooling medium circulation system maintenance
3. Industry Traffic Keywords
Data center liquid cooling system, IDC data center liquid cooling retrofit, computing cluster liquid cooling heat dissipation, server liquid cooling circulation system, industrial liquid cooling system, cabinet-level liquid cooling solution, liquid cooling system working principle, liquid cooling system technical parameters
4. Brand Exclusive Keywords
KITOZER liquid cooling medium circulation system, Guangdong KITOZER liquid-cooled cabinet, KITOZER smart data center liquid cooling, LA-YL-XH liquid cooling system, KITOZER liquid cooling installation and commissioning, Guangzhou liquid cooling equipment manufacturer
5. Dropdown/Related Search Keywords
Liquid cooling medium circulation system composition, how to install and wire a liquid cooling system, common liquid cooling system fault handling, liquid cooling system maintenance cycle, liquid cooling system acceptance standard, liquid cooling circulation system schematic diagram, liquid cooling system pressure test specification, what to do if liquid cooling system leaks
II. SEO Optimization Tag System
1. Page Core Optimization Tags
- Page Topic: Liquid Cooling Medium Circulation System Installation, Wiring, and Commissioning Manual
- Core Semantics: Full-process technical guidance for the circulation system supporting liquid-cooled integrated cabinets
- Content Attributes: Technical manual, installation guide, operation and maintenance handbook
2. Title Tag
Liquid Cooling Medium Circulation System Installation, Wiring, and Commissioning Manual_Liquid-Cooled Integrated Cabinet – KITOZER Guangzhou Lain Intelligent System Development Co., Ltd.
3. Meta Keywords
Liquid cooling medium circulation system, liquid-cooled integrated cabinet, liquid cooling system installation, liquid cooling wiring and commissioning, liquid cooling system manual, cabinet liquid cooling circulation, KITOZER liquid cooling system, data center liquid cooling
4. Meta Description
Official liquid cooling medium circulation system installation, wiring, and commissioning manual from KITOZER Guangzhou Lain Intelligent System Development Co., Ltd., detailing the product introduction, system composition principles, technical parameters, installation steps, wiring specifications, commissioning methods, maintenance, and fault