Chapter 1. Product Overview

1.1 Definition of a Modular Data Center

A modular data center (MDC), commonly called a micro-module data center, is a next-generation data center construction form in which rack systems, cold-aisle containment, in-row cooling, uninterruptible power supplies (UPS), battery banks, power distribution units, environmental monitoring, and fire integration are pre-integrated at the factory into standard units and then rapidly assembled on site like building blocks. It differs fundamentally from the traditional approach of “first renovating a room, then separately procuring air conditioners, UPS, racks, and monitoring,” compressing an entire data center into a set of replicable, expandable, relocatable functional modules.

At its engineering core, a modular data center is not a single piece of equipment but a delivery system combining a standardized electromechanical product family, factory prefabrication, and on-site final assembly. A complete micro-module unit typically includes: double-row (or single-row) 42U/47U server racks, cold-aisle containment skylights and end doors, in-row precision air conditioners positioned between rack rows, UPS hosts and distribution cabinets at the row head, strong- and weak-current cable trays along the aisle, and an environmental controller that unifies temperature/humidity, water leak, smoke, access control, and electrical power data. When a customer needs more capacity, they simply add another identical module next to the existing one without renovating an entire floor.

The core value of a modular data center can be summarized in four words: fast, efficient, scalable, and reliable. Fast means factory prefabrication compresses on-site construction from months to weeks. Efficient means cold-aisle containment and row-level cooling dramatically lower PUE and installed cooling capacity. Scalable means UPS power modules and rack rows expand on demand, avoiding upfront over-investment. Reliable means critical equipment universally adopts N+1 redundancy and group-control interlock, so a single point of failure does not interrupt operations.

1.2 Industry Evolution

The modular data center has evolved through four stages.

Stage 1 (before ~2000): Traditional room-based era. Data centers were built as “room-level” facilities: a customer leased a floor or large room, installed anti-static flooring, suspended ceilings, wall insulation, then installed room-level precision air conditioners (CRAC/CRAH), large line-frequency UPS, and a separate battery room, finally placing rows of racks inside. This model offered spatial flexibility but suffered from long build cycles (typically 6–12 months), severe hot/cold air mixing, PUE values of 1.8–2.2, and expansion that required re-renovation.

Stage 2 (2002–2010): Hot/cold aisle and row-level cooling emergence. As blade servers emerged, per-rack power density jumped from 2–3 kW to 6–10 kW, and room-level AC could no longer deliver cold air to the middle of racks. The industry introduced hot/cold aisle layout, rack rear-door heat exchangers, and in-row air conditioners. Meanwhile, high-frequency double-conversion UPS began replacing traditional line-frequency UPS, raising efficiency from 90% to over 95%. The product of this stage was “row-level cooling + hot/cold aisles,” but subsystems were still pieced together from different vendors with inconsistent interfaces.

Stage 3 (2010–2018): Micro-module standardization. Major vendors packaged racks, in-row AC, UPS, containment, and environmental monitoring into a standard “module,” launching 6-, 12-, 20-, and 42-rack standard units. After ordering, the factory shipped the module disassembled into packages, and on-site work was limited to assembly and power connection. PUE commonly reached 1.4–1.6, and build cycles shrank to 4–8 weeks. Chinese telecom operators, state banks, and internet companies began large-scale adoption of micro-modules for city-level rooms and edge nodes.

Stage 4 (2018–present): High-density, liquid-cooled, and intelligent era. AI training servers and GPU compute pushed per-rack density from 8–15 kW to 30–50 kW or even 100 kW+, reaching the physical limits of air-cooled in-row AC. Rear-door heat exchangers (RDHx), cold-plate liquid cooling, and immersion cooling entered mainstream modular product lines. Meanwhile, AI workload scheduling, digital twins, DCIM (Data Center Infrastructure Management), predictive maintenance, intelligent busways, intelligent PDUs, and lithium batteries replacing VRLA stacked on top, evolving the modular data center from “electromechanical product” to “intelligent compute infrastructure.”

1.3 Market Trends

Six trends define the current modular data center market:

  1. From large centralized to distributed edge nodes. 5G, industrial internet, smart cities, vehicle-to-everything, and telemedicine require compute to sink to districts, parks, streets, and even buildings. Node size shrinks from thousands of racks to 10–50 racks, matching micro-module standard capacity.
  2. Per-rack power density keeps climbing. General business racks commonly run 6–10 kW; AI inference racks 20–30 kW; AI training racks 50–100 kW+. The air-cooled ceiling is about 15–20 kW/rack; beyond that, liquid cooling is required.
  3. PUE regulation tightens. China’s East-Data-West-Compute project, EU ERP directives, and the US DOE all require new large data centers to achieve PUE ≤ 1.3, with mega hubs ≤ 1.25. Cold-aisle containment, rear-door heat exchangers, liquid cooling, and free cooling become standard.
  4. Lithium replaces VRLA. Lithium iron phosphate (LFP) batteries offer higher energy density, longer cycle life (6,000 vs 1,200 cycles), smaller footprint, and maintenance-free operation, and are replacing traditional VRLA in 10–30-minute short runtime scenarios.
  5. Prefabrication and containerization. Modular data centers further evolve into containerized data centers, with the entire unit factory-tested and lifted as a whole to the site, ideal for remote mining, oil, disaster zones, and polar environments.
  6. DCIM intelligence. Environmental monitoring evolves from “alarm reporting” to “digital twin + AI scheduling,” displaying real-time per-rack temperature, power, fan speed, and battery SOC, and automatically recommending expansion and energy-saving actions.

1.4 KITOZER Brand

KITOZER is the product-line brand of Guangzhou Laian Intelligent System Development Co., Ltd., focused on data centers and intelligent rooms. The KITOZER modular data center series is designated KITOZER-MicroDC, offering four standard units by rack count: 10, 20, 50, and 100 racks. Each unit is available in air-cooled (MicroDC-Air) or liquid-cooled (MicroDC-Liquid) versions, with UPS capacity covering 10 kVA to 1,000 kVA modular UPS.

A standard KITOZER-MicroDC unit includes: 42U perforated smart racks (KITOZER-MDC600 series), cold-aisle containment (skylights/sliding doors/access control/RGB lighting/lintel bar display), 50 kW in-row precision air conditioners (KITOZER-CRAC50 series), modular UPS (KITOZER-UP series, 10–50 kVA hot-swap power modules), VRLA or LFP batteries, and a dual-row aisle environmental controller (KITOZER-CC01). The brand also offers outdoor integrated cabinets, precision row-head distribution cabinets, dual-power ATS cabinets, and shielded cabinets, forming a complete product matrix from indoor micro-modules to outdoor prefabricated stations and from low-voltage distribution to high-voltage incoming lines.


Chapter 2. Technical Principles

The modular data center’s “fast, efficient, scalable, reliable” performance arises from the synergy of five key technical principles: cold-aisle containment, row-level cooling, modular UPS, battery energy storage, and environmental monitoring with fire integration.

2.1 Cold-Aisle Containment Principle

The largest energy waste in traditional open rooms is hot/cold air mixing. Room-level AC supplies cold air under the raised floor or from the ceiling; as it flows toward racks, it mixes with hot air exhausted from rack tops and rear, so some cold air returns to the AC without ever passing through servers (called bypass or short-circuit airflow), while hot-aisle air is repeatedly drawn into the AC, raising evaporator pressure and lowering efficiency. ASHRAE TC 9.9 data shows that in open rooms, often less than 60% of supply air actually reaches server intakes.

Cold Aisle Containment (CAC) uses a straightforward engineering idea: completely enclose the “cold aisle” formed by two rows of racks facing each other with skylights (roof panels), end doors, and seals, so cold air exists only inside this enclosed corridor. Servers draw cold air from the front and exhaust hot air to the open hot aisle at the rear. Direct effects include:

  • Eliminates hot/cold mixing: cold air is no longer diluted by hot air, and cold-aisle temperature stabilizes at 18–24°C, matching ASHRAE recommended server intake.
  • Raises supply-return delta-T: traditional rooms run 8–10°C delta-T; containment allows 12–15°C, reducing required airflow and fan energy.
  • Allows higher supply temperature: because cold-aisle temperature is uniform, supply can rise from 13–15°C to 18–22°C, extending free-cooling hours and lowering PUE by 0.1–0.2.
  • Reduces installed cooling capacity: with no bypass, AC need not be oversized for “virtual” airflow, cutting installed capacity by 20–30%.

The symmetric alternative is Hot Aisle Containment (HAC): enclose the hot aisle so hot air returns directly to the AC while the cold aisle stays open. In high-density scenarios (>15 kW/rack), HAC better prevents hot air leakage into operator areas; in general scenarios (<10 kW/rack), CAC is more common and simpler. KITOZER-MicroDC defaults to CAC, with HAC or dual containment as options.

Key containment components:

  1. Skylights: roof panels over racks. They are either fixed (steel or glass, permanently closed) or flip-up (glass, magnetically latched, automatically open on fire alarm for smoke exhaust). Flip skylights are a fire-code requirement—when a fire breaks out in the aisle, smoke needs a fast exhaust path, and the enclosed cold aisle must not become a “smoke chamber.”
  2. End doors: doors at both ends of the cold aisle. Commonly automatic sliding doors (motor-driven with infrared anti-pinch) or double glass swing doors. End doors must seal well; otherwise cold air leakage through gaps defeats containment.
  3. Seals: EPDM foam gaskets between skylights and rack tops, and between doors and frames, with 25–30% compression.
  4. Lighting: RGB LED strips embedded in the aisle—white for routine maintenance, red flashing for alarms—improving visibility.
  5. Lintel bar display: a narrow screen above the end door showing real-time time, cold-aisle temperature/humidity, per-row load, and AC status, so operators see status from outside the aisle.
  6. Access control: end doors are equipped with face/card/PIN terminals, logging entry and integrating with fire (auto-unlock on alarm).

2.2 In-Row Cooling Principle

In-row cooling places a precision AC unit as a “dummy rack” of the same width as server racks, directly between rack rows. It draws cold air from the cold aisle, cools it, and blows it horizontally to adjacent racks. Compared with room-level CRAC/CRAH:

Dimension Room-level AC In-row AC
Air delivery distance 5–15 m across the room 1–3 m horizontally to adjacent racks
Supply mode Raised-floor or overhead Horizontal front supply
Suitable density 2–6 kW/rack 8–30 kW/rack
Airflow matching Fixed volume, sized for peak Variable fan + variable compressor, load-matched
PUE contribution High bypass, low efficiency Short path, high delta-T, low PUE
Redundancy Central N redundancy, failure affects whole room In-row N+1, failure affects only segment
Footprint Requires dedicated AC room Same row as racks, no extra space

KITOZER-CRAC50 key specs:
– Cooling capacity: ≥ 50 kW (DX air-cooled)
– Airflow: ≥ 10,300 m³/h
– Fans: EC centrifugal, N+1 redundant, variable 10–100%
– Compressor: full DC inverter scroll, high part-load efficiency (IPLV)
– Reheat: PTC electric ≥ 6 kW
– Humidification: wet-bulb ≥ 3 kg/h (electrode optional)
– Control: 7-inch touchscreen, up to 32-unit group control, RS485/Modbus/BACnet to DCIM
– Surge: 6 kV incoming protection
– Group logic: multiple units rotate master/backup by cold-aisle temperature, balance runtime, and auto-fill on unit failure.

The physical essence of in-row cooling is “place the cold source closest to the heat source.” At 15 kW+ per rack, cold air from a distant AC heats up by 3–5°C before reaching servers; in-row units sit adjacent, so server intake temperature fluctuation is held within ±1°C.

For higher density (>30 kW/rack), Rear Door Heat eXchangers (RDHx) mount a condenser/coil on the rack rear door. Hot air exhausted by servers passes directly through the rear door and is carried away by cooling water; cold air no longer participates in the loop. KITOZER offers RDHx as an option in MicroDC high-density versions.

2.3 Modular UPS Principle

An Uninterruptible Power Supply (UPS) instantly switches to battery inverter supply when mains fails or voltage quality deteriorates, preventing IT equipment downtime. A modular UPS packages the UPS host as a “rack chassis + multiple hot-swap power modules,” each containing an independent rectifier (AC/DC), inverter (DC/AC), static bypass switch, and control board.

Typical power flow:

Operating modes:
1. Normal (online double-conversion): mains normal, rectifier converts to DC; one branch inverts to clean sine-wave AC for IT load (THD < 3%, frequency ±0.5 Hz), the other floats the battery.
2. Battery mode: mains fails, rectifier stops, battery supplies the inverter through the DC bus with 0 ms transfer (battery is already paralleled on the bus).
3. Bypass mode: on overload or internal UPS fault, the static switch seamlessly transfers load to mains bypass, protecting the UPS.
4. Maintenance bypass: when UPS needs service, close the maintenance bypass switch; mains feeds load directly, and the UPS can be de-energized.

Core modular UPS advantages:
– N+1 redundancy online: e.g., customer needs 400 kVA, installs ten 50 kVA modules (500 kVA total); any module fails, the remaining nine automatically carry 450 kVA without interruption.
– Pay-as-you-grow: early low load uses only six modules (300 kVA); business growth adds two more modules without replacing the host.
– Hot-swap service: power modules can be pulled and replaced live without shutdown.
– High efficiency: modular UPS uses three-level topology and IGBT high-frequency PWM, ≥96% efficiency, up to 99% in ECO mode.

KITOZER-UP typical specs:
– Host: 500 kVA 3-phase in/out, battery bus ±192–±264 VDC adjustable
– Power module: 50 kVA/4U, ≥96% efficiency, THDi ≤ 3%
– Parallel: up to 4 hosts
– Communication: RS485, SNMP, dry contacts to environmental DCIM

2.4 Battery Energy Storage Principle

Batteries are the UPS’s “last line of defense.” When mains outages last beyond seconds (minute-scale), the UPS inverter rides through on batteries. Two battery technologies dominate modular data centers:

VRLA (Valve-Regulated Lead-Acid):
– Typical: 12V 100Ah / 12V 200Ah / 12V 250Ah, valve-regulated, minimal water loss, no watering.
– Temperature: optimum 20–25°C; life halves per 10°C rise.
– Cycle life: 1,200 cycles (80% DOD).
– Pros: mature, cheap, recyclable, stable supply chain.
– Cons: low energy density (~30 Wh/kg), heavy, requires ventilated battery room for acid mist, replacement every 3–5 years.
– KITOZER standard: 12V250Ah VRLA, 160 cells in series for ±192V or ±240V DC bus.

Lithium Iron Phosphate (LFP):
– Typical: 51.2V 100Ah/200Ah rack-mounted battery packs, paralleled.
– Cycle life: 6,000+ cycles (80% DOD).
– Energy density: ~120 Wh/kg, 3–4x VRLA.
– Temperature: -20°C to +60°C.
– Pros: small footprint, maintenance-free, 10+ year life, BMS intelligent management, parallel expansion.
– Cons: 1.5–2x upfront investment.
– Best for: new builds, space-constrained sites, 10–30-minute short runtime.

Runtime calculation: Runtime ≈ Battery energy (Wh) / Actual load (W) × inverter efficiency. Example: 500 kVA UPS at 300 kW load, 160 cells 12V250Ah in series for ±240V (480V total), battery energy = 480V × 250Ah = 120 kWh. After 95% inverter efficiency and cutoff voltage, usable ~110 kWh; runtime ≈ 110/300 ≈ 22 minutes. Longer runtime (e.g., 2 hours) requires a diesel generator.

2.5 Environmental Monitoring & Fire Integration

Power & Environment Monitoring (PEM) is the modular data center’s “nervous system.” The KITOZER-CC01 aisle controller centrally collects:

  • Environmental: cold/hot aisle temperature-humidity (1–2 points per row), floor leak rope (along AC and piping), smoke detector (aisle ceiling).
  • Electrical: UPS input/output voltage/current/power, battery pack total voltage and cell voltage (smart battery), per-branch PDU current.
  • Equipment status: AC run/alarm/fan speed, UPS rectifier/inverter/bypass status, door contact status.
  • Access & video: face recognition logs, door contact status, in-aisle camera (optional).

Control outputs include: automatic sliding door open/close, flip skylight magnetic latch release, RGB strip color change (green normal/yellow alarm/red emergency), sound-light alarm, and remote SMS/email/app push.

Fire integration is a mandatory safety requirement. When the fire host sends an alarm (dry contact to CC01), the system must complete within 30 seconds:
1. All flip skylight magnetic latches release; skylights open by gravity to form a smoke exhaust path.
2. Access doors auto-unlock for evacuation.
3. AC shuts down to prevent fanning the fire.
4. Sound-light alarm activates; RGB strips flash red.
5. DCIM logs the fire event and pushes to on-call staff.


Chapter 3. Product Series

3.1 MicroDC Series Overview

KITOZER-MicroDC forms four standard units by total rack count in double-row layout:

Model Racks Layout Recommended IT Load UPS Capacity In-row AC Typical Scenario
MicroDC-10 10 2×5 30–60 kW 60–120 kVA 2–3×25 kW SMBs, building telecom rooms, edge nodes
MicroDC-20 20 2×10 60–120 kW 120–200 kVA 4–6×25/50 kW Mid-size enterprise, county DC, hospital room
MicroDC-50 50 2×25 150–300 kW 300–500 kVA 8–12×50 kW City telecom room, bank branch, internet POP
MicroDC-100 100 2×50 300–600 kW 500–1,000 kVA 16–24×50 kW + RDHx Provincial DC, AI inference center, cloud region

3.2 Air-Cooled MicroDC-Air

The air-cooled version is the mature standard for per-rack density of 6–15 kW general business (file servers, virtualization, databases, VDI, small/medium AI inference).

Standard unit contents (MicroDC-20 example):
– 20× KITOZER-MDC600-2026 42U perforated racks (600×1200×2000 mm)
– 2× cold-aisle end doors (automatic sliding + face access)
– 20× skylights (15 glass flip + 5 fixed steel)
– 20× M-shaped strong/weak separated cable troughs
– 20× RGB LED strips + lintel bar display
– 6× KITOZER-CRAC50-2026 50 kW in-row AC (N+1; ~300 kW IT load, 6×50 kW = 300 kW, N=5, N+1=6)
– 1× KITOZER-UP200-2026 200 kVA modular UPS (4×50 kVA modules, N+1)
– 40–80× 12V200/250Ah VRLA (15–30 min runtime)
– 1× KITOZER-CC01-2026 dual-row environmental controller
– 1× KITOZER-PDU63A smart rack PDU (2 per rack)

3.3 Liquid-Cooled MicroDC-Liquid

The liquid-cooled version targets 20–100 kW per rack for AI training, HPC, and GPU servers. It comes at two levels:

Cold Plate: metal cold plates mount on server CPU/GPU surfaces; coolant (typically 50% water + 50% glycol) flows through plates to carry heat, with residual air cooling for memory/drives. Cold plates handle 20–60 kW per rack, PUE 1.1–1.2.

Immersion: the entire server is submerged in dielectric coolant (mineral oil or fluorinated fluid), directly contacting heat-generating components, handling 100 kW+ per rack. Immersion has high upfront cost and complex maintenance, suited to supercomputing and large-model AI training.

KITOZER-MicroDC-Liquid standard:
– High-load racks (≥1,500 kg per rack due to GPU weight)
– Rear-door RDHx (primary side connected to building chilled water or dry cooler)
– CDU (Coolant Distribution Unit): built-in circulation pump, plate heat exchanger, expansion tank, leak detection
– Quick disconnects (QD): blind-mate couplings at server and rack sides, no leakage on hot-swap
– Cold plates, piping, and rack manifold
– Retained in-row AC for the air-cooled portion (~20–30% of heat)
– Environmental monitoring adds coolant temperature, flow, pressure, and leak sensors.

3.4 Containerized MicroDC-Container

The containerized version packs the entire micro-module into a 20- or 40-foot standard container, factory-tested and lifted as a whole to the site, where the customer only connects mains, fiber, and cooling water. Suited to mines, oilfields, disaster recovery, polar expeditions, temporary events, and rapid DC expansion. KITOZER-MicroDC-Container holds 12–24 high-density racks, 100–300 kW cooling, 100–300 kVA UPS, operating temperature -40°C to +55°C (insulated container).


Chapter 4. Detailed Technical Parameters

4.1 PUE (Power Usage Effectiveness)

PUE = Total data center energy / IT equipment energy. PUE=1.0 means all energy goes to IT, with zero auxiliary (AC, UPS, lighting) energy—physically impossible. Industry benchmarks:
– Traditional room DC: PUE 1.8–2.2
– Cold-aisle containment + in-row cooling: PUE 1.4–1.6
– Free cooling + in-row: PUE 1.25–1.4
– Liquid-cooled DC: PUE 1.1–1.25
– Extreme optimization (Arctic, Sweden): PUE below 1.1

KITOZER-MicroDC air-cooled in standard climate zones is designed PUE ≤ 1.45, dropping to 1.35 in swing season with free cooling; liquid-cooled version PUE ≤ 1.2.

Key PUE drivers:
1. Cooling method (60%+ of auxiliary energy)
2. UPS efficiency (modular 96% vs traditional line-frequency 92%)
3. Rack supply temperature (each 1°C higher lowers PUE by ~0.02)
4. Outdoor climate (northern sites have longer free-cooling hours, naturally lower PUE)

4.2 Cooling Capacity and Airflow

In-row AC capacity must match IT load precisely. Design rules:
– Total cooling ≥ total IT load × 1.15 (fans, lighting, UPS losses)
– Per-unit capacity × unit count ≥ total IT load × 1.25 (N+1 still sufficient)
– Airflow (m³/h) ≈ Cooling (kW) × 3160 / Supply-return delta-T (°C). For 50 kW and 12°C delta-T, airflow ≈ 50×3160/12 ≈ 13,167 m³/h. KITOZER-CRAC50 rated 10,300 m³/h corresponds to ~15°C delta-T.

4.3 UPS Capacity and Runtime

UPS sizing:
– UPS rating (kVA) ≥ total IT load (kW) / 0.9 (power factor)
– Reserve 30–50% for 1–3 year expansion
– Modular UPS initial module count = actual load / module capacity, plus 1 redundant module.

Runtime:
– 5–10 min: only instantaneous mains interruption and generator start buffer (requires diesel generator)
– 15–30 min: common for SMB, mainly for orderly shutdown
– 1–4 hours: no generator or unreliable generator; high battery investment
– KITOZER defaults 15–30 min; longer runtime requires diesel generator.

4.4 Rack Power Density

Density Typical Business Recommended Cooling
2–5 kW/rack General file servers, networking Room-level AC + hot/cold aisle
5–10 kW/rack Virtualization, databases, VDI In-row AC + cold-aisle containment
10–20 kW/rack High-density virtualization, AI inference In-row AC + containment + inverter
20–40 kW/rack AI training, HPC RDHx + chilled water
40–100 kW+/rack LLM training, GPU clusters Cold-plate / immersion liquid cooling

4.5 Other Key Parameters

  • Noise: in-row AC within 1 m of operators, typically ≤ 75 dB(A); nighttime maintenance requires attention.
  • Grounding: rack grounding resistance ≤ 1Ω, lightning protection ≤ 4Ω, combined grounding ≤ 1Ω.
  • Lighting: aisle average ≥ 300 lx, emergency ≥ 50 lx.
  • Seismic: per project site; KITOZER standard designed for intensity 7; intensity 8/9 requires reinforcement.
  • Temperature/humidity: cold aisle 18–27°C (ASHRAE A1), RH 40–60%.

Chapter 5. Cooling Comparison

5.1 Room-level vs In-row vs Rear-door

Dimension Room-level CRAC In-row Rear-door RDHx
Density ≤6 kW/rack 8–25 kW/rack 20–60 kW/rack
Air distance 5–15 m 1–3 m 0 m (direct exhaust pickup)
Cold air utilization 50–70% 85–95% 95%+
Footprint Dedicated AC room Same row as racks Same row as racks
Investment Low Medium High (CDU + chilled water)
Maintenance Simple Simple Medium (water circuit)

5.2 Chilled Water vs Direct Expansion (DX)

In-row AC by heat source:

DX (Direct Expansion): compressor, condenser, and evaporator integrated in the unit; outdoor requires a condenser (dry cooler). Pros: independent, no dependency on building chilled water; cons: distributed compressors, slightly lower efficiency, refrigerant piping limited to ~30 m. KITOZER-CRAC50 defaults to DX.

Chilled Water: the AC unit contains only a chilled water coil and fan; chilled water is supplied by a central plant (chiller + cooling tower) through pumps. Pros: high efficiency, large unit capacity (100 kW+), no refrigerant leak risk; cons: depends on central plant, plant failure stops all AC, requires N+1 plant + thermal storage tank. Suited to large data centers.

5.3 Free Cooling

In northern or swing seasons, when outdoor air temperature is below chilled water return temperature, outdoor dry coolers or plate heat exchangers can directly introduce outdoor cooling, stopping or throttling the compressor for major savings. KITOZER in-row AC offers optional free-cooling coils; annual free-cooling hours in northern China are ~1,500–2,500 hours, lowering PUE by 0.1–0.2.


Chapter 6. Power Distribution

6.1 Standard Power Architecture

KITOZER-MicroDC standard power path:

6.2 Dual Feeds (2N / N+1)

Critical rooms require dual mains (from different substations) or dual mains + diesel generator. Dual feeds switch via ATS (Automatic Transfer Switch) or STS (Static Transfer Switch). The KITOZER dual-power ATS cabinet (KITOZER-ATS series) supports automatic switchover between two mains with ≤100 ms transfer.

High-availability scenarios (finance, large internet) use 2N architecture: two fully independent UPS systems each carrying 50% load; on failure of one, the other carries all. Investment is 2x single system, but availability reaches 99.999%.

General scenarios use N+1 redundancy: N UPS modules in parallel; on failure of one, the rest carry full load. Lower investment than 2N, availability 99.99%.

6.3 Diesel Generator

When UPS runtime (15–30 min) cannot cover long mains outages (typhoons, ice storms, equipment failure), a diesel generator is required. Generator capacity = UPS input + AC + lighting/maintenance, typically sized at 1.2× total load. KITOZER can supply 100–2,000 kW silent diesel generators, day tanks, parallel cabinets, and ATS interlock control.

6.4 Intelligent Busway and Smart PDU

Traditional row-head-to-rack distribution uses cables, requiring re-pulling for expansion. An intelligent busway is a prefabricated enclosed copper busbar running along the rack row; each rack position plugs in a tap-off box, adding as many circuits as needed with zero construction. KITOZER offers optional busway (160–630A) and smart PDUs (per-branch current monitoring, remote on/off, temperature-humidity monitoring).


Chapter 7. Installation and Commissioning

7.1 Factory Prefabrication

KITOZER-MicroDC is factory-assembled: rack joining, skylight pre-install, AC piping, UPS and battery cabinets, environmental controller, and a 72-hour factory burn-in. At shipment, the module is split into packages (racks, skylights, AC, UPS, batteries, cables).

7.2 On-site Installation Sequence

  1. Site preparation: floor leveling, load confirmation (≥800 kg/m², liquid-cooled ≥1,200 kg/m²), mains incoming, fiber incoming, water/drain/cooling water incoming.
  2. Rack positioning: lay out drawings, position racks row by row, fix base with expansion bolts, join with joining kits.
  3. Containment install: skylight framing, flip skylights (with magnetic latch and fire wiring), automatic sliding doors, end-door seals.
  4. AC install: slide in-row AC into reserved positions between rows, connect refrigerant lines (DX) or chilled water (chilled-water type), drain pipe, and condensate line. Evacuate and charge refrigerant.
  5. UPS and batteries: position UPS host and connect input/output cables; assemble battery racks and install cells, connect DC switches and busbars, install terminal covers.
  6. Cable routing: strong/weak separated trays; PDU power from rack bottom, network/fiber from top M-shaped trough.
  7. Environmental wiring: temperature-humidity sensors, leak rope, smoke, access, lintel display, RGB strips to the CC01 controller.
  8. Joint commissioning:
  9. Step 1: single-equipment power-on (AC, UPS, lighting, access separately)
  10. Step 2: communication network (CC01 reads all devices via RS485/Modbus)
  11. Step 3: functional tests (door open/close, skylight flip, RGB color, AC group rotation)
  12. Step 4: interlock tests (simulate fire signal → skylights open, doors unlock, AC stops, alarm sounds)
  13. Step 5: ≥72-hour stability run, recording PUE, voltage, and temperature curves.

7.3 Acceptance Criteria

  • Cold aisle temperature stable at 22±2°C, point deviation ≤2°C
  • UPS output 220V±3%, 50Hz±0.5Hz, THDi ≤3%
  • Runtime within ±10% of design
  • Fire interlock completes all actions within 30 seconds
  • Environmental platform data point accuracy 100%
  • 72 hours without alarm or fault

Chapter 8. Maintenance

8.1 Routine Inspection (Weekly/Monthly)

  • Check cold-aisle temperature-humidity and lintel display
  • Listen for abnormal AC fan noise
  • Check UPS panel for alarms
  • Review environmental platform for unresolved alarms

8.2 Quarterly Maintenance

  • In-row AC filter cleaning or replacement (pre-filter every 3–6 months)
  • Condensate pipe clearing
  • Access lock lubrication
  • Battery visual inspection (bulging, leakage)
  • Flip skylight magnetic latch test

8.3 Annual Maintenance

  • UPS power module deep inspection, capacitor life assessment
  • Battery capacity discharge test (full capacity every 3 years)
  • AC compressor running current and refrigerant pressure inspection
  • Grounding resistance test
  • Fire interlock full drill
  • DCIM firmware upgrade
  • Torque all electrical connections

8.4 Consumable Replacement Cycle

Component Recommended Cycle
Pre-filter 3–6 months
Medium filter 12 months
Fan belt (if any) 3–5 years
VRLA battery 3–5 years
LFP battery 8–10 years
UPS module capacitor 5–8 years
Seal gasket 5–8 years
LED strip 5–8 years
Refrigerant Top up on leak; normally 10+ years

8.5 Preventive vs Predictive Maintenance

Traditional preventive maintenance (periodic replacement) may over-service; Predictive Maintenance (PdM) uses DCIM data on fan vibration, battery internal resistance, AC compressor current, and temperature trends. AI models predict failures for precise pre-failure replacement. KITOZER offers an optional predictive maintenance module.


Chapter 9. Selection Guide

9.1 Selecting by IT Load

  1. Count current IT power (kW) and estimate 3-year expansion.
  2. Choose UPS: UPS capacity (kVA) = IT total (kW) / 0.9 × 1.3 redundancy.
  3. Choose cooling: total cooling = IT total × 1.15, split across in-row AC units with N+1.
  4. Choose rack count: invert by per-rack IT power. E.g., 200 kW total at 8 kW/rack = 25 racks → MicroDC-50.

9.2 Selecting by Site Conditions

  • Floor load insufficient: wall/rack UPS, LFP batteries (light), avoid heavy battery room.
  • Space tight: cold-aisle containment (30% energy saving vs open) + modular UPS (small footprint).
  • No chilled water: DX in-row AC.
  • Building chilled water available: chilled-water AC for higher efficiency.
  • Cold outdoor climate: free-cooling version for lower PUE.
  • Coastal/chemical: 304/316 stainless steel racks and anti-corrosion AC.
  • High-density AI: directly choose MicroDC-Liquid.

9.3 Selection Decision Tree


Chapter 10. KITOZER vs Traditional Room

Dimension Traditional Room DC KITOZER-MicroDC
Build cycle 6–12 months 4–8 weeks
On-site work Renovation + MEP, dusty Factory prefab + on-site assembly, low dust
PUE 1.8–2.2 1.35–1.5 air / 1.1–1.2 liquid
Per-rack density 2–6 kW 8–30 kW air / 100 kW+ liquid
UPS redundancy Line-frequency N+1, 92% efficiency High-frequency modular N+1, 96%
Expansion Re-renovate + replace UPS Online module add + rack row add
Cooling redundancy Central AC failure affects whole room In-row N+1, failure affects segment
Monitoring Independent vendor systems, need integration Unified environmental + DCIM
Fire Room-level gas suppression Aisle flip skylight + gas suppression interlock
Upfront investment Low (but poor efficiency) Medium (but lower 5-year TCO)
5-year TCO High (expensive electricity) Low (30%+ energy saving)
Portability Not portable Modules relocatable

Chapter 11. Generic Cases

11.1 Generic Case A: SMB Headquarters Room

A mid-size enterprise (300–1,000 employees) needs a headquarters room for ERP, OA, email, video conferencing, file services, and network security. Total IT load ~60 kW, 12 racks.

Solution: MicroDC-20 air-cooled, using 12 racks with 8 reserved for expansion. UPS 120 kVA modular (3×50 kVA, N+1), 30-minute runtime. 4×25 kW in-row AC (N+1). Cold-aisle containment + face access + environmental monitoring. Designed PUE 1.5. Build cycle 6 weeks.

11.2 Generic Case B: AI Inference Center

An AI company needs a GPU inference room for video structuring, NLP inference, and image recognition. Per-rack density 15–20 kW, total IT load 200 kW, 12 racks.

Solution: MicroDC-50 high-density, 8×50 kW in-row AC (N+1), some racks with RDHx. UPS 300 kVA modular (6×50 kVA). LFP batteries for small footprint and long life. Designed PUE 1.35.

11.3 Generic Case C: Edge Node

A telecom operator needs a county-level edge node for 5G MEC, smart-city video analytics, and industrial internet access. IT load 30 kW, 6–8 racks, in a building telecom room (<30 m², 2.6 m ceiling, 500 kg/m² floor load).

Solution: compact MicroDC-10, single-row racks with one-side cold-aisle containment. UPS 60 kVA modular (2×30 kVA + 1 redundant). 2×25 kW in-row AC. LFP rack batteries for light weight. Container outer frame optional for outdoor building-side placement.


Chapter 12. 30 FAQs

Q1: What’s the real difference between modular and traditional rooms?
A: Modular pre-integrates racks, AC, UPS, containment, and monitoring at the factory for on-site assembly; traditional rooms renovate on site and procure separately. The former is 3–5x faster, 0.3–0.5 lower PUE, and supports online expansion.

Q2: Does the micro-module only work with KITOZER servers?
A: No. The micro-module is infrastructure; servers are IT. KITOZER racks support standard 19-inch servers of any brand; PDUs support IEC/C13/C19; AC is sized by standard cooling capacity, brand-agnostic.

Q3: Will operators suffocate inside the enclosed cold aisle?
A: No. Cold-aisle containment encloses roof and end doors, not a sealed chamber. Air exchanges with the hot aisle through server fans, and daily maintenance time is short. Code requires flip skylights to open on fire and allows manual opening for maintenance.

Q4: Is longer UPS runtime always better?
A: No. Each doubling of runtime roughly doubles battery investment. Standard practice is 15–30 min UPS + diesel generator. Batteries over 2 hours are only used where there is no generator or mains is extremely unreliable.

Q5: What is modular UPS N+1 redundancy?
A: N is the modules needed for load; +1 is one extra redundant module. E.g., load needs 5×50 kVA modules (250 kVA); install 6 (300 kVA). Any module fails, the remaining 5 still carry 250 kVA.

Q6: VRLA vs LFP, how to choose?
A: Under 15 min short runtime + tight budget → VRLA; space-constrained, wanting 10-year maintenance-free, sensitive to lifecycle cost → LFP. LFP costs 1.5–2x upfront but lasts 3–4x longer.

Q7: Can PUE go below 1.2?
A: Air-cooled micro-modules in standard climate zones struggle below 1.3. To reach below 1.2 requires liquid cooling and northern/high-altitude locations with long free-cooling hours.

Q8: At what per-rack density must I go liquid?
A: Air-cooled in-row physical limit is ~15–20 kW/rack. Above 20 kW consider RDHx; above 40 kW cold-plate; above 80 kW immersion.

Q9: Cold aisle or hot aisle containment?
A: <15 kW/rack general → cold aisle (simple, most common); >15 kW/rack high-density or operators long near aisle → hot aisle (prevents hot air leakage to operator area).

Q10: Will one in-row AC failure take down the room?
A: No. In-row AC is N+1; on failure, the rest auto-fill. The environmental platform alarms immediately, and operators replace within 48 hours.

Q11: Does the micro-module need a dedicated AC room?
A: Air-cooled DX does not—no, in-row AC sits between rack rows; outdoors only needs a condenser (dry cooler). Chilled-water type needs a central plant or independent plant.

Q12: Fire suppression—gas or sprinkler?
A: Data center rooms use gas suppression (FK-5-1-12 or IG541), not water sprinklers (which damage equipment). Cold-aisle flip skylights handle smoke exhaust; gas suppression handles discharge.

Q13: Can I put the micro-module on an upper floor?
A: Calculate floor load. A standard micro-module (with batteries) is ~800–1,200 kg/m²; typical office floor is ~500 kg/m². Upper-floor rooms should use LFP (light), wall-mounted UPS, and floor load reinforcement.

Q14: Typical build cycle?
A: MicroDC-20 scale (20 racks) from order to power-on ~6–8 weeks: 3–4 weeks factory, 2–3 weeks on-site assembly, 1 week commissioning.

Q15: Does expansion require shutdown?
A: UPS power modules are hot-swappable; expansion is non-disruptive. Adding a rack row beside the aisle may briefly affect adjacent-row cold air—recommend off-peak.

Q16: Can the micro-module be relocated?
A: Yes. Containerized and disassemble-again versions support relocation. Relocation requires shutdown, discharge, disassembly, transport, reassembly, and re-commissioning.

Q17: Can I monitor environmental data via app?
A: Yes. KITOZER-CC01 connects to DCIM, with web/WeChat mini-program/app real-time view of temperature, power, and alarms, plus SMS/email/phone alerts.

Q18: Annual AC maintenance cost?
A: ~5–8% of AC equipment value per year, mainly filters, refrigerant top-up, and compressor inspection.

Q19: How long do batteries last?
A: VRLA at 25°C lasts 3–5 years, halving per 10°C rise; LFP lasts 8–10 years. Keep the battery room at ~22°C for best life.

Q20: Is the room safe during thunderstorms?
A: KITOZER in-row AC and UPS incoming have standard 6 kV SPD; rack combined grounding ≤1Ω. External feeds also require a level-1 SPD (10/350 μs waveform).

Q21: What’s the relationship between micro-module and containerized DC?
A: Containerized DC is the “whole-shell version” of a micro-module—packing the entire module into a container, factory-tested and lifted to site. Suited to remote, no-building, rapid-deployment scenarios.

Q22: How many operators does a data center need?
A: MicroDC-20 scale—unattended + remote O&M, weekly inspection; MicroDC-100+ recommended 24×7 staffed or resident.

Q23: How long does UPS last on power failure?
A: Standard 15–30 minutes. This buffers generator start (if present) or orderly server shutdown. Without a generator, batteries must be enlarged or a generator added.

Q24: What’s the right air-cooled cold aisle temperature?
A: ASHRAE A1 recommends 18–27°C server intake. KITOZER designs cold aisle at 22±2°C—both energy-saving and safe.

Q25: Why use smart PDUs?
A: Smart PDUs monitor per-branch current, remotely switch outlets, and measure per-rack energy—the foundation of refined DCIM. Ordinary PDUs only supply power without monitoring.

Q26: How noisy is the micro-module room?
A: In-row AC at 1 m is ~70–75 dB(A), equivalent to a busy city street. Short-duration entry is acceptable; long-duration work requires acoustic treatment.

Q27: How are water leak sensors deployed?
A: Leak rope runs under in-row AC, along condensate pipes, and around UPS/battery cabinets; length follows the path. On leak signal, the environmental platform alarms immediately.

Q28: Roughly how much is annual data center electricity?
A: At PUE 1.5, 100 kW IT load, ¥0.8/kWh: annual = 100 kW × 24h × 365 × 1.5 × ¥0.8 ≈ ¥1.05M/year. Lowering PUE from 1.8 to 1.5 saves ~¥420k/year.

Q29: Does KITOZER deliver turnkey projects?
A: Yes. KITOZER handles detailed design, equipment supply, on-site installation, commissioning, acceptance, training, and warranty end-to-end. The customer only provides the site and mains.

Q30: How do I request a quote?
A: Call/WeChat +86 13922289957 or +86 18520668845; WhatsApp +86 19068534140. Provide IT load, rack count, site conditions, and runtime requirement; KITOZER returns a design and quote within 48 hours.


Chapter 13. Packaging, Delivery, and Warranty

13.1 Packaging

KITOZER-MicroDC uses export-standard packaging:
– Racks, skylights, AC: seven-layer corrugated box + foam corner + wooden pallet
– UPS hosts, batteries: separate wooden crates; batteries in shock-resistant packaging
– Cables and accessories: categorized cartons
– Sea freight: optional fumigated wooden pallets (IPPC mark)

13.2 Lead Time

  • MicroDC-10/20 standard air-cooled: 25–35 working days
  • MicroDC-50/100: 45–60 working days
  • Liquid-cooled / containerized: 60–90 working days
  • Expedited projects negotiable.

13.3 Warranty

  • 3-year whole-unit warranty (racks, AC, UPS, environmental)
  • 2-year battery warranty (VRLA) / 3-year (LFP)
  • Consumables (filters, gaskets) excluded
  • 5-year extended warranty available

Chapter 14. Inquiry CTA

KITOZER-MicroDC modular data center is tailored to your IT load, rack count, site conditions, and runtime requirement. Whether you are building new, expanding, or retrofitting a traditional room, KITOZER delivers standard solutions from 10 to 100 racks in air-cooled, liquid-cooled, and containerized versions.

Contact us now:
– Tel/WeChat: +86 13922289957
– Tel/WeChat: +86 18520668845
– WhatsApp: +86 19068534140
– Website: lain.com.cn / gdlain.com
– Address: Chaotian Park, Zhongrun Industrial Zone, No. 5 Huashan Road, Shilou, Panyu, Guangzhou, China.

Provide the following for a 48-hour design and quote:
1. Current IT total power (kW) or server count
2. Expected rack count (or 3-year expansion estimate)
3. Room area, ceiling height, floor load
4. Availability of building chilled water, dual mains, diesel generator
5. Runtime requirement
6. Project location (for climate and freight)


Chapter 15. Company Contact

Guangzhou Laian Intelligent System Development Co., Ltd.

  • Brand: KITOZER
  • Tel/WeChat: +86 13922289957
  • Tel/WeChat: +86 18520668845
  • WhatsApp: +86 19068534140
  • China site: https://www.lain.com.cn
  • Global site: https://www.gdlain.com
  • Address: Chaotian Park, Zhongrun Industrial Zone, No. 5 Huashan Road, Shilou, Panyu, Guangzhou, China.

KITOZER product lines cover: modular data centers, outdoor integrated cabinets, precision row-head distribution, dual-power ATS cabinets, shielded cabinets, 4K network video surveillance, smart electricity safety monitoring, utility-tunnel monitoring, wind-farm micro-modules, bridge structural health monitoring, and online water quality monitoring.


Chapter 16. Industry Standards and Certifications

The design, construction, and acceptance of a modular data center must follow a series of national, industry, and international standards. Understanding these standards is a prerequisite for selection and acceptance.

16.1 Chinese National Standards

GB 50174 “Data Center Design Code” is the fundamental law of data center construction in China. It classifies data centers into A, B, and C tiers based on usage, management requirements, and business criticality:

  • Tier A (fault-tolerant): for finance, large internet, and national core government rooms. Requires 2N or 2(N+1) power distribution, N+1 cooling, N+1 diesel generators, and 99.999% availability.
  • Tier B (redundant): for general government and mid-size enterprise rooms. Requires N+1 power, N+1 cooling, and 99.99% availability.
  • Tier C (basic): for small enterprise and edge nodes. Requires basic power and cooling, 99.9% availability.

KITOZER-MicroDC-20/50 defaults to Tier B and can be upgraded to Tier A (dual UPS parallel + dual mains + diesel generator).

GB 50462 “Code for Construction and Acceptance of Data Center Infrastructure” specifies construction workmanship, test methods, and acceptance criteria, including: rack verticality deviation ≤3 mm, floor flatness ≤2 mm/m, grounding resistance testing, UPS load test (4 hours full load), cooling airflow balancing, and fire interlock testing.

GB 50052 “Power Supply System Design Code” defines load classification and supply requirements. Data centers are typically special important first-class loads, requiring dual mains plus emergency power.

GB 50057 “Building Lightning Protection Design Code” requires data centers to be designed as Class II lightning protection buildings with grounding resistance ≤1Ω.

GB 50116 “Fire Automatic Alarm System Design Code” requires data centers to install aspirating early smoke detection (VESDA), because traditional point smoke detectors respond slowly under high airflow in contained cold aisles.

GB/T 2887 “General Specification for Computer Sites” defines baseline temperature, humidity, dust, noise, and lighting requirements.

16.2 International Standards

TIA-942 “Data Center Telecommunications Infrastructure Standard” is published by the Telecommunications Industry Association, classified into Rated 1–4 by availability:
– Rated 1: basic, single path power and cooling
– Rated 2: component redundancy, N+1
– Rated 3: concurrently maintainable, all components can be replaced online without interruption
– Rated 4: fault-tolerant, any failure does not cause interruption

Uptime Institute Tier Standard is the internationally recognized data center tier certification:
– Tier I: basic, 99.671% availability, ~29 hours downtime/year
– Tier II: redundant components, 99.741%, ~22 hours
– Tier III: concurrently maintainable, 99.982%, ~1.6 hours
– Tier IV: fault-tolerant, 99.995%, ~0.4 hours

ISO/IEC 30134 defines the data center efficiency metric system, including PUE (Power Usage Effectiveness), WUE (Water Usage Effectiveness), CUE (Carbon Usage Effectiveness), and REE (Renewable Energy Energy efficiency ratio). Export projects or multinational companies often require annual reports on these metrics.

ASHRAE TC 9.9 is the authoritative guide for data center thermal environments. The 2015 edition widened recommended server intake temperature from 18–27°C (recommended) to 5–45°C (allowable), enabling higher supply temperatures and energy-saving operation.

IEC 60364 is the international standard for low-voltage distribution, required for EU export projects.

16.3 KITOZER Product Compliance

KITOZER-MicroDC products are certified:
– CCC China Compulsory Certification (low-voltage equipment, UPS, AC)
– CE EU certification (EU export)
– UL US certification (North America export, optional)
– ISO 9001 Quality Management System
– ISO 14001 Environmental Management System
– Telecom Network Access License (carrier projects)


Chapter 17. High-Voltage Power Distribution and Transformers

A complete data center power distribution starts at 10 kV (or 35 kV/110 kV) high-voltage incoming, steps down through a transformer to 0.4 kV low voltage, and then feeds the UPS and loads.

17.1 High-Voltage Incoming

Large data centers typically bring in dual 10 kV mains from different substations as mutual backup. Medium-voltage switchgear commonly uses metal-clad withdrawable switchgear (e.g., KYN28-12), containing vacuum circuit breakers, microcomputer protection, metering cabinets, and PT cabinets. KITOZER can supply KYN28 switchgear and SVG reactive compensation.

17.2 Transformers

10 kV/0.4 kV transformers commonly include:
– Dry-type transformers (SCB10/SCB13): non-flammable, indoor-installable, simple maintenance—data center mainstream. Capacity from 400 kVA to 2,500 kVA.
– Oil-immersed transformers (S11/S13): cheaper but require a separate transformer room, usually outdoor.

Transformer capacity is sized at 1.2–1.5× total load, usually with two units so one carries all first-class loads on failure. KITOZER supplies SCB13 dry-type transformers with enclosure protection.

17.3 Low-Voltage Distribution

0.4 kV low-voltage switchgear commonly uses MNS/GCS draw-out switchgear by function:
– Incoming cabinet: main power incoming with frame circuit breaker
– Capacitor compensation cabinet: automatic switched capacitors, power factor corrected to ≥0.95
– Bus tie cabinet: bus tie between two LV sections, switches on failure
– Outgoing cabinet: branches to UPS, AC, lighting, maintenance

KITOZER precision row-head cabinets (MNS draw-out series) distribute UPS output to rack rows, with per-branch current monitoring and miniature circuit breakers.

17.4 Power Factor and Harmonics

UPS rectifiers are harmonic sources; THDi can exceed 30%, degrading power factor and overheating transformers. KITOZER modular UPS uses IGBT rectification as standard, THDi ≤3%, power factor ≥0.99, eliminating the need for extra harmonic filtering. Older line-frequency UPS require Active Power Filters (APF).


Chapter 18. Lightning Protection, Grounding, and Electrical Safety

18.1 Lightning Protection Zones

Per IEC 62305, data center lightning protection is divided into four zones:
– LPZ 0A: building exterior, exposed to direct strike
– LPZ 0B: building exterior, strike-protected but electromagnetic field not attenuated
– LPZ 1: building interior, electromagnetic field attenuated
– LPZ 2: data hall interior, further attenuated

Surge Protective Devices (SPD) are installed at each zone boundary:
– Level 1 SPD (10/350 μs waveform, Iimp ≥12.5 kA): LV incoming cabinet
– Level 2 SPD (8/20 μs, In ≥20 kA): UPS input
– Level 3 SPD (8/20 μs, In ≥10 kA): rack PDU

KITOZER in-row AC and UPS incoming include standard Level 2 6 kV SPD; rack PDUs can include Level 3 SPD.

18.2 Grounding System

Data centers use a combined grounding system: working grounding, protective grounding, lightning grounding, and anti-static grounding share one set of electrodes, with grounding resistance ≤1Ω.

  • Working grounding: UPS DC neutral
  • Protective grounding: rack enclosures, AC enclosures, cable trays
  • Lightning grounding: lightning rods/belts, SPD grounding
  • Anti-static grounding: anti-static floor pedestals

Racks connect to the hall grounding copper busbar via M6 grounding bars; the busbar cross-section ≥100 mm².

18.3 Electrical Safety

  • All metal enclosures reliably grounded, so enclosure voltage on fault ≤50 V
  • Circuit breakers selectively coordinated: upstream frame, downstream molded case, end miniature
  • RCD protection: 30 mA on maintenance outlets and lighting circuits
  • Electrical clearance and creepage distance per GB 7251

Chapter 19. Fire Protection Design

19.1 Fire Detection

Data center fires have a smoldering stage; traditional point smoke detectors respond slowly under cold-aisle high airflow (possibly delayed 5–10 minutes). KITOZER recommends Aspirating Smoke Detection (ASD/VESDA): sampling holes actively draw air through laser scattering detection for extremely early smoke, 1,000× more sensitive than traditional detectors, warning 30–60 minutes before visible smoke.

19.2 Gas Suppression

Data centers cannot use water sprinklers (which damage equipment); they use clean agent gas suppression:
– HFC-227ea (FM-200): most common, extinguishing concentration 7–9%, discharge ≤10 seconds, non-corrosive to equipment.
– IG541 mixed gas: 52% N₂ + 40% Ar + 8% CO₂, physical oxygen depletion, environmentally friendly, but many cylinders and large footprint.
– Novec 1230 (FK-5-1-12): next-generation environmentally friendly agent, extremely low GWP, gaining adoption.

Suppression is divided by protection zone: one cold-aisle row or one hall is a zone with its own cylinder bank and nozzles. Before discharge: shut down AC, close fire dampers, delay 30 seconds for evacuation, then discharge.

19.3 Flip Skylight Interlock

After cold-aisle containment, smoke must exhaust on fire. KITOZER flip skylights are held by magnetic latches; on fire alarm, the latch de-energizes and skylights open by gravity to form a smoke exhaust path. This is the critical fire design that distinguishes contained cold aisles from traditional rooms.

19.4 Fire and Access Control Interlock

On fire alarm, access doors auto-unlock for evacuation; the environmental platform records fire time, location, and discharge status, and notifies on-call staff.


Chapter 20. DCIM and Digital Twin

20.1 DCIM Definition

Data Center Infrastructure Management (DCIM) is a software platform that unifies power, cooling, space, and asset management. Building on traditional environmental monitoring (which only monitors environmental variables), DCIM adds IT assets, capacity planning, energy analysis, and capacity heat maps.

KITOZER-DCIM main modules:
– Real-time monitoring: per-rack temperature, humidity, power, switch status
– Alarm management: multi-level alarms (info/general/serious/critical), SMS/email/app push
– Asset management: rack U-position map, recording each device location, model, go-live date, warranty
– Capacity management: visual display of remaining U positions, remaining power, remaining cooling
– Energy analysis: real-time PUE, energy reports, energy-saving recommendations
– Report center: daily/weekly/monthly automatic reports
– API: integration with BMS, ERP, ITSM

20.2 Digital Twin

Next-generation DCIM introduces Digital Twin: 3D modeling recreates the entire data hall in virtual space, real-time mapping each rack’s temperature, fan speed, and UPS load. Operators click any rack in the 3D scene to see all data and historical curves. Digital Twin also supports expansion simulation: add a rack in the virtual scene, and the software automatically calculates impact on the temperature field, power, and cooling, supporting decisions.

20.3 Intelligent Busway and Smart PDU

KITOZER intelligent busway and smart PDU are the DCIM data endpoints:
– Intelligent busway: runs along rack rows, each section has current and temperature sensors connected to DCIM
– Smart PDU: per-outlet current monitoring, remote on/off, per-rack energy statistics
– Through these endpoints, DCIM can be precise to “the current of a specific outlet in a specific rack,” rather than traditional “total row current.”


Chapter 21. Thermodynamics and Cooling Principles

21.1 Refrigeration Cycle

The vapor-compression refrigeration cycle consists of four processes:
1. Compression: low-temperature low-pressure refrigerant gas is compressed into high-temperature high-pressure gas
2. Condensation: high-temperature high-pressure gas rejects heat to outdoor air (or cooling water), condensing into liquid
3. Expansion: high-pressure liquid throttles through an expansion valve into low-temperature low-pressure gas-liquid mixture
4. Evaporation: low-temperature mixture absorbs indoor heat in the evaporator and vaporizes back to the compressor

Coefficient of Performance COP = Cooling capacity / Input power. KITOZER-CRAC50 at rated conditions has COP ~3.5–4.0 (i.e., consumes 1 kW of electricity to move 3.5–4 kW of heat).

21.2 Inverter Technology

Traditional fixed-speed AC compressors either run at full load or stop, causing large temperature swings. Full inverter compressors automatically adjust speed based on cold-aisle temperature: full speed when hot, low speed when near setpoint. Inverter AC part-load efficiency (IPLV) is 30–50% higher than fixed-speed, with smaller temperature swings, lower inrush current, and longer life.

21.3 Wet-bulb and Electrode Humidification

Data center humidity too low causes static electricity (damaging semiconductors); too high causes condensation. Winter dryness requires humidification:
– Wet-bulb humidification: water permeates a wet pad; air passing through picks up moisture—no white mist, bacteria-free, energy-saving. Humidification 3–8 kg/h.
– Electrode humidification: water electrolyzed between electrodes and evaporated, high capacity but scale-prone and requires periodic cleaning.

KITOZER-CRAC50 defaults to wet-bulb, with electrode humidification as option.

21.4 Free Cooling

When outdoor temperature is below chilled water return temperature (typically 7–12°C), plate heat exchangers or direct outdoor air intake provide cooling, turning off or throttling the compressor. In northern China, free-cooling hours can reach 2,000–3,000 per year, lowering PUE by 0.15–0.25.


Chapter 22. Power Electronics and Battery Electrochemistry

22.1 UPS Topology

Online double-conversion UPS is the most common data center topology:
– Rectifier: converts AC to DC. Traditional 6-pulse diode rectification has THDi ≈30%; modern IGBT PWM rectification has THDi ≤3%, power factor ≈1.
– Inverter: converts DC to clean AC. IGBT three-level topology, output THD <3%, suitable for nonlinear loads (server power supplies).
– Static bypass switch: thyristor switch, transfer time <1/4 cycle (<5 ms).
– Maintenance bypass: mechanical switch, bypasses UPS during service.

ECO mode: when mains quality is good, UPS feeds load directly through bypass at 99% efficiency; on mains abnormality, switches back to double-conversion. ECO saves energy but has a few milliseconds of transfer, negligible for server power supplies.

22.2 Battery Electrochemistry

VRLA Lead-Acid:
– Positive: PbO₂, Negative: Pb, Electrolyte: dilute sulfuric acid
– Discharge: PbO₂ + Pb + 2H₂SO₄ → 2PbSO₄ + 2H₂O
– Charge: reverse reaction
– Valve-regulated design: oxygen generated on charge recombines to water at the negative, no watering needed
– Failure modes: plate sulfation, grid corrosion, electrolyte dry-out, thermal runaway

LFP Lithium Iron Phosphate:
– Positive: LiFePO₄, Negative: graphite
– Operating voltage 3.2 V, long life, high safety (no fire or explosion)
– BMS monitors per-cell voltage and temperature, balancing charge
– 6,000+ cycles, 10-year maintenance-free

22.3 Parallel Operation and Circulating Current

When multiple UPS units parallel, they must synchronize phase and amplitude via parallel lines, otherwise circulating (reactive) current flows. KITOZER modular UPS has a built-in parallel bus, up to 4 units, with circulating current <2%.


Chapter 23. Detailed Worked Examples

23.1 IT Load Estimation

An enterprise has 30 servers at 500 W each; networking equipment 5 kW; storage 10 kW.
Total IT load = 30×0.5 + 5 + 10 = 30 kW.
With 30% expansion reserve = 30×1.3 = 39 kW, round to 40 kW.

23.2 UPS Sizing

UPS capacity (kVA) = IT load (kW) / power factor (0.9) / redundancy factor (0.8)
= 40 / 0.9 / 0.8 = 55.6 kVA; choose 60 kVA modular UPS (2×30 kVA modules + 1 redundant).

23.3 Cooling Sizing

Total cooling = IT load × 1.15 (including fans, lighting, UPS losses)
= 40 × 1.15 = 46 kW.
Choose 2×25 kW in-row AC (N+1, total 50 kW).

23.4 Battery Runtime

60 kVA UPS at 40 kW load, DC bus ±192 V (384 V total), choose 32× 12V100Ah batteries.
Battery energy = 384 V × 100 Ah = 38.4 kWh.
After 95% inverter efficiency and cutoff, usable ~34 kWh.
Runtime = 34 / 40 = 0.85 hour ≈ 51 minutes.

For 30-minute runtime, batteries can be reduced to 16× 12V100Ah, energy 19.2 kWh, runtime ~29 minutes.

23.5 PUE Estimation

Annual electricity = IT load (kW) × 24h × 365 days × PUE × price (¥/kWh)
= 40 × 24 × 365 × 1.5 × 0.8 = ¥420,480/year.

Lowering PUE from 1.8 to 1.5 saves = 40×24×365×(1.8-1.5)×0.8 = ¥84,096/year.


Chapter 24. Construction Organization and Project Management

24.1 Project Phases

KITOZER micro-module projects have six phases:
1. Requirements survey: collect IT load, rack count, site, mains, chilled water conditions
2. Detailed design: produce construction drawings, equipment list, layout, power diagrams, schematics
3. Factory prefabrication: workshop rack joining, AC pre-install, UPS testing, 72-hour burn-in
4. Logistics: disassemble and ship, on-site secondary handling
5. On-site construction: assembly, power connection, piping, wiring
6. Commissioning and acceptance: single-equipment test, interlock test, 72-hour burn-in, acceptance report

24.2 Construction Safety

  • Anti-static suits and insulating shoes on site
  • Live work requires two people, one monitoring
  • Work at height (>2 m) requires safety harness
  • Hot work requires a permit and fire extinguisher
  • Battery handling uses forklift, with short-circuit protection

24.3 Project Documentation

On delivery, provide:
– As-built drawings (CAD electronic)
– Equipment list and certificates
– Test reports (UPS load, AC airflow, grounding resistance, fire interlock)
– Operation and maintenance manuals
– DCIM accounts and training records


Chapter 25. SLA and Availability Calculations

25.1 Availability Metrics

Availability = Actual uptime / Total time. Common SLAs:
– 99.9% (three nines): 8.76 hours downtime/year
– 99.99% (four nines): 52.6 minutes
– 99.999% (five nines): 5.26 minutes

25.2 N+1 vs 2N Availability

N+1 systems achieve ~99.99% availability; 2N systems ~99.999%. KITOZER-MicroDC defaults to N+1 and can be upgraded to 2N.

25.3 Single-Point-of-Failure Analysis

Micro-module design must identify all single points of failure:
– Single AC failure → N+1 redundancy, acceptable
– Single UPS module failure → hot-swappable, acceptable
– Single mains failure → ATS switchover, acceptable
– Single pipe leak → leak rope alarm, acceptable
– Environmental controller failure → standby controller, acceptable
– False fire discharge → dual detection + delay, prevents false discharge


Chapter 26. Detailed Subsystem Parameter Tables

This chapter presents complete parameter lists for KITOZER standard products across subsystems, as a reference for selection.

26.1 42U Smart Rack (KITOZER-MDC600-2026)

Parameter Specification
Dimensions (W×D×H) 600×1200×2000 mm
Rack height 42U
Static load 1,500 kg
Dynamic load 1,000 kg
Upright material SPCC cold-rolled steel, 1.5–2.0 mm
Square holes 9.5×9.5 mm standard, with U-position numbering
Front door Single perforated front door, 75% ventilation, lock
Rear door Double perforated rear door, 75% ventilation
Side panels Embedded, removable
Top/bottom panels Cable entry holes with brush strips
Grounding M6 copper bar to hall ground bus
Rack joining Joining kits for multiple racks
Color RAL 7035 light gray (standard), RAL 9004 black optional
Surface Degreased + phosphated + epoxy powder, 80–120 μm
Protection IP20 (indoor)
Installation Expansion-bolt base, ±10 mm leveling feet

26.2 In-row Precision AC (KITOZER-CRAC50-2026)

Parameter Specification
Cooling capacity ≥50 kW (24°C/50% RH rated)
Airflow ≥10,300 m³/h
External static pressure 30–80 Pa adjustable
Compressor Full DC inverter scroll
Evaporator Copper tube aluminum fin, hydrophilic coating
Condenser Air-cooled (outdoor dry cooler)
Refrigerant R410A or R32 (eco-friendly)
Air delivery Horizontal front supply, rear return
Fans EC centrifugal, N+1, variable 10–100%
Reheat PTC electric ≥6 kW, staged
Humidification Wet-bulb ≥3 kg/h, electrode 8 kg/h optional
Dehumidification Cooling dehumidification with reheat
Control accuracy Temperature ±1°C, humidity ±5% RH
Power 380V/3Ph/50Hz
Rated power ~15 kW
Noise ≤75 dB(A) at 1.5 m
Dimensions 600×1200×2000 mm (same width as rack)
Control 7-inch touchscreen, Chinese menu
Communication RS485/Modbus/BACnet/SNMP
Group control Up to 32 units, auto master rotation
Surge 6 kV SPD on incoming
Drain pump Built-in, head ≥5 m

26.3 Modular UPS (KITOZER-UP500-2026 + UPM50 module)

Parameter Specification
Host capacity 500 kVA
Topology Online double-conversion three-level IGBT
Input 380V/3Ph/50Hz, ±20% voltage range
Output 380V/3Ph/50Hz
Output power factor 0.9–1.0
Overall efficiency ≥96% (double-conversion), ≥99% (ECO)
Input power factor ≥0.99
Input THDi ≤3% (full load)
Output THDv ≤3% (linear load)
Dynamic response ≤2% transient, 20 ms recovery
Parallel Up to 4 hosts
Power module 50 kVA/4U, hot-swap, N+1
Battery voltage ±192–±264 VDC adjustable
Static bypass Thyristor switch, <5 ms
Maintenance bypass Mechanical switch, isolates host
Communication RS485/SNMP/dry contacts
Display 7-inch touchscreen
Noise ≤65 dB(A)
Operating temperature 0–40°C
Protection IP20

26.4 VRLA Battery (KITOZER-BAT250-2026)

Parameter Specification
Model 12V250Ah valve-regulated lead-acid
Rated voltage 12V
Rated capacity 250 Ah (10-hour rate)
Dimensions 522×240×218 mm
Weight ~75 kg
Float design life 10–12 years (25°C)
Cycle life 1,200 cycles (80% DOD, 25°C)
Operating temperature -15 to +50°C (optimum 20–25°C)
Charge voltage Equalize 2.35 V/cell, float 2.25 V/cell
Self-discharge ≤3%/month (25°C)
Terminal M8 copper, with cover
Enclosure Flame-retardant ABS, UL94-V0

26.5 Smart PDU (KITOZER-PDU63A-2026)

Parameter Specification
Input 63A/240V single-phase
Output 20×10A CN 5-hole + 4×16A CN 3-pin
Cable 3×6 mm² + 1×4 mm²
Mounting Vertical in rack, U-adjustable
Monitoring Total current, voltage, power, energy
Branch monitoring Per-branch current optional
Remote control Per-outlet on/off optional
Communication RJ45/TCP-IP
Overload 63A breaker
Surge 10 kA SPD
Color Black

Chapter 27. Detailed Generic Cases

27.1 Generic Case A: SMB Headquarters (MicroDC-20)

Background: A mid-size enterprise of 300–1,000 employees with ERP, OA, email, file services, video conferencing, network security, and virtualization. The old room was a converted office with poor PUE, no redundancy, and past AC water leak caused business interruption. The new headquarters room requires high availability, energy efficiency, and scalability.

Design inputs:
– Current IT load: 35 kW
– 3-year expansion forecast: 55 kW
– Racks needed: 12 now, 20 in 3 years
– Site: independent first-floor room, 60 m², 3.2 m ceiling, 800 kg/m² floor load
– Mains: single 100 kVA feed (dual feed recommended)
– Runtime: 30 minutes

Solution:
– MicroDC-20 air-cooled, double rows of 10 racks
– UPS: 200 kVA modular (4×50 kVA modules, N+1; initial 3 modules + 1 redundant)
– Batteries: 80× 12V100Ah VRLA (30-minute runtime)
– AC: 4×25 kW in-row (N+1)
– Cold aisle: glass flip skylights + automatic sliding doors + face access + RGB strips + lintel display
– Environmental: CC01 controller + leak rope + smoke + temp-humidity
– Fire: HFC-227ea gas suppression + VESDA aspirating detection
– Designed PUE: 1.5

Investment estimate: equipment ~¥1.8–2.2M, installation ~¥0.3M, total ~¥2.2–2.5M. Annual electricity ~¥0.35M (PUE 1.5), saving ~¥0.1M/year vs old PUE 2.0.

Implementation cycle: 45 days to delivery after contract, 15 days on-site, 7 days commissioning, ~67 days total.

27.2 Generic Case B: AI Inference Center (MicroDC-50 High-density)

Background: An AI company builds a room for video structuring, NLP inference, and image recognition. Servers are GPU inference boxes, 15–20 kW per rack.

Design inputs:
– IT load: 200 kW
– Racks: 12 high-density racks
– Per-rack power: 15–20 kW
– Runtime: 15 minutes (with diesel generator)
– Site: second-floor room, 1,000 kg/m²

Solution:
– MicroDC-50 high-density, 12 high-density + 8 reserved standard racks
– UPS: 300 kVA modular (6×50 kVA, N+1)
– Batteries: LFP LiFePO4 (51.2V200Ah × 20 packs, ~2 m² footprint, 15-minute runtime)
– AC: 8×50 kW in-row (N+1), high-density racks with RDHx rear-door
– Cold aisle: fully enclosed, glass flip skylights
– Environmental: CC01 + DCIM Digital Twin platform
– Designed PUE: 1.35

Value: LFP batteries save 70% footprint and 60% weight vs VRLA, suiting second-floor load limits. RDHx picks up 20 kW rack hot exhaust directly into cooling water, preventing hot-aisle high temperature.

27.3 Generic Case C: Edge Node (MicroDC-10)

Background: A telecom operator builds a county-level 5G MEC edge node for video analytics, industrial internet access, and AR/VR. Site is a building telecom room, only 25 m², 2.6 m ceiling, 500 kg/m².

Design inputs:
– IT load: 30 kW
– Racks: 8
– Runtime: 10 minutes (with small diesel generator)
– Site: telecom room, no dedicated AC room

Solution:
– MicroDC-10 compact, single row of 8 racks + one-side cold-aisle containment
– UPS: 60 kVA modular (2×30 kVA + 1 redundant)
– Batteries: LFP rack-mounted (light weight)
– AC: 2×25 kW in-row
– Cold aisle: one-side end door + face access
– Environmental: CC01 remote monitoring, unmanned
– Designed PUE: 1.6

Value: Single-row layout saves space, suiting small telecom rooms. LFP batteries are light, within floor load. Remote unmanned operation, weekly inspection.


Chapter 28. Common Engineering Pitfalls

Pitfall 1: Sizing UPS only for current load without redundancy

Many customers size UPS to exactly match current IT load, e.g., 30 kW load → 30 kVA UPS running at full load. Problems: (1) full-load UPS has low efficiency, high heat, short life; (2) no redundancy—UPS failure stops everything; (3) no room for expansion. Correct: UPS = IT/0.9/0.8 redundancy factor; modular UPS initially installs N+1 modules.

Pitfall 2: Sizing AC only by IT load, ignoring fans and UPS losses

AC cooling should be IT load × 1.15, because fans, lighting, and UPS losses also produce heat. E.g., 40 kW IT → AC must be ≥46 kW.

Pitfall 3: Containing the cold aisle but leaving doors open

Cold aisle end doors left propped open or wrong skylights (all fixed, no flip) defeat containment. End doors must auto-close (self-closer or automatic sliding), and skylights must include fire-linked flip units.

Pitfall 4: Not controlling battery room temperature

Batteries are optimal at 25°C; life halves per 10°C rise. Many customers put batteries in the UPS room without dedicated AC, summer temperature reaching 35–40°C, and batteries fail in 2 years. Correct: keep battery room at 22–25°C.

Pitfall 5: Ignoring leak detection

In-row AC has condensate pipes; UPS has VRLA battery acid; leaks corrode floors and cause shorts. Leak rope must run under AC and around battery cabinets, connected to environmental alarms.

Pitfall 6: Environmental monitoring alarms locally only

Many environmental systems alarm only on the local screen; if staff are not on site, they miss it. Must configure SMS/phone/app push, 24×7 alarm to personnel.

Pitfall 7: Not anticipating PDU capacity at expansion

Initially selecting 16A PDUs for 2 kW/rack, then later installing 20 kW GPU racks and overloading PDUs. Correct: size PDUs for 3-year future density, 50% margin.

Pitfall 8: False gas suppression discharge

Gas suppression with single detection (smoke only) may false-discharge from dust or steam, causing massive loss. Correct: dual detection (smoke + heat, or two-stage VESDA), manual confirmation before discharge, 30-second delay.

Pitfall 9: Not testing grounding

Many installers connect ground wires but do not test resistance. Poor grounding makes SPD ineffective during lightning. Delivery must test grounding resistance ≤1Ω with a report.

Pitfall 10: Ignoring noise impact

In-row AC noise 75 dB(A); if the room is next to an office, employees complain. Build acoustic walls between data hall and offices, or select low-noise AC models.


Chapter 29. O&M SOP

29.1 Daily Inspection (Remote)

  1. Log in to DCIM
  2. Check cold aisle temperature (should be 22±2°C)
  3. Check UPS load rate (should be <80%)
  4. Check battery voltage (should be in float range)
  5. Review alarm list, acknowledge unprocessed alarms
  6. Check daily PUE

29.2 Weekly Inspection (On-site)

  1. Check cold aisle temp-humidity lintel display
  2. Listen to in-row AC fan noise
  3. Check UPS panel for alarms
  4. Check leak rope status
  5. Review access logs for unusual openings
  6. Clean pre-filter dust from AC

29.3 Quarterly Maintenance

  1. Clean or replace AC pre-filters
  2. Check condensate pipe clearance
  3. Test access locks
  4. Inspect batteries (bulging, leakage, terminal corrosion)
  5. Test flip skylight magnetic latch
  6. Test automatic sliding door anti-pinch

29.4 Annual Maintenance

  1. UPS power module deep inspection (capacitors, fans, relays)
  2. Battery full-capacity discharge test (every 3 years)
  3. AC compressor current, refrigerant pressure inspection
  4. Grounding resistance test
  5. Fire interlock full drill
  6. DCIM firmware upgrade
  7. Torque all electrical connections
  8. Issue annual O&M report

29.5 Emergency Response

Mains outage:
1. UPS auto-switches to battery mode, DCIM alarms
2. Confirm diesel generator auto-starts (if present)
3. If mains not restored in 30 minutes, orderly shut down non-critical business
4. On mains restore, confirm UPS returns to normal mode, battery returns to float

AC failure:
1. DCIM alarms; in-row N+1 auto-fills
2. On-site check failed AC (power, refrigerant, fans)
3. If multiple AC fail simultaneously, start backup ventilation and migrate non-critical business
4. Contact KITOZER service for 4-hour response

Battery bulging:
1. DCIM battery internal resistance alarm
2. On-site inspect bulging battery, replace immediately
3. After replacement, run capacity test

Water leak:
1. Leak rope alarm, on-site locate
2. Close corresponding AC/water valve
3. Clean water, dry before inspecting equipment
4. Repair leak and restore


Chapter 30. Supply Chain and Lead Time

30.1 Standard Product Lead Time

Category Standard Model Lead Time
42U rack MDC600 10–15 days
Containment components Skylight/door/light strip 15–20 days
In-row AC CRAC50 25–35 days
Modular UPS UP500 30–45 days
VRLA battery BAT250 15–20 days
LFP battery pack LFP-51.2V 25–35 days
Environmental controller CC01 7–10 days
PDU PDU63A 7–10 days

30.2 Total Project Cycle

  • MicroDC-10/20 standard air: 45–60 days to delivery after contract
  • MicroDC-50/100: 60–90 days
  • Liquid-cooled / containerized: 90–120 days
  • On-site installation: 15–30 days (by scale)
  • Commissioning and acceptance: 7–15 days

30.3 Packaging and Transport

  • Domestic: truck LTL or FTL, wooden pallet
  • Export: fumigated pallet (IPPC mark), container sea freight
  • Precision equipment (UPS, AC): shock packaging, tilt indicator
  • On-site handling: forklift or pallet jack; battery anti-tip

Chapter 31. Environment and Carbon Footprint

31.1 Data Center Carbon Emissions

Data center carbon emissions = annual kWh × grid emission factor. China’s grid factor is ~0.5703 kgCO₂/kWh. A 100 kW IT load at PUE 1.5 consumes 100×24×365×1.5 = 1,314,000 kWh/year, emitting ~749 tons CO₂/year.

31.2 Emission Reduction Measures

  • Lower PUE (each 0.1 reduction saves ~50 tons CO₂/year)
  • Use green power (PV, wind, green power trading)
  • Waste heat recovery (data center heat for district heating)
  • Battery recycling (VRLA lead recycling 98%; LFP lithium recycling improving)
  • Modular design extends equipment life

31.3 KITOZER Environmental Commitment

  • Recyclable packaging
  • RoHS, REACH compliant
  • EPEAT rating support
  • Battery trade-in recycling program

Chapter 32. Edge Computing and 5G MEC

5G MEC (Multi-access Edge Computing) sinks cloud to the cell site, requiring data centers near base stations: small nodes (10–50 kW), unmanned, fast deployment. KITOZER-MicroDC-10 and outdoor integrated cabinets are ideal for MEC nodes.

MEC node characteristics:
– Single node IT load 10–50 kW
– 4–12 racks
– Site in base station rooms, building telecom rooms, outdoor cabinets
– Unmanned, remote O&M
– High reliability (99.99%)
– Fast deployment (within 2 weeks)

KITOZER MEC solution: MicroDC-10 + LFP batteries + remote environmental + 4G/5G backhaul monitoring.


Chapter 33. AI Compute Rooms

Large-model training and inference impose new requirements on data centers:

Power density surge: single AI training server (8×GPU) is 10–15 kW; a rack (8–10 servers) is 80–150 kW, far exceeding the air-cooled limit.

Cooling evolution:
– AI inference (20–30 kW/rack): air cooling + RDHx
– AI training (50–100 kW/rack): cold-plate liquid cooling
– LLM training (100 kW+/rack): immersion liquid cooling

Power distribution changes:
– Evolution from 220V/380V AC to 480V DC (HVDC)
– LFP batteries fully replace VRLA (high power density)
– Increased diesel generator configuration (AI rooms have low PUE but high total power)

KITOZER AI room solution: MicroDC-Liquid cold-plate version, with CDU, manifold, QD quick disconnects, PUE 1.1–1.2, supporting 50–100 kW per rack.


Chapter 34. Future Trends

34.1 From Air to Full Liquid Cooling

In the next 5 years, new high-density data centers will be predominantly liquid-cooled. Cold-plate cooling becomes standard for AI training; immersion expands in supercomputing. KITOZER has already established the MicroDC-Liquid product line.

34.2 From Lithium to Solid-State

Solid-state batteries are expected to commercialize around 2030, doubling energy density, improving safety, and extending life, replacing current LFP.

34.3 From Reactive to AI-predictive O&M

DCIM will adopt large models to automatically analyze failure modes, predict equipment life, and recommend expansion. O&M evolves from “firefighting” to “prevention.”

34.4 From Data Centers to Compute Networks

Modular data centers become edge nodes of a compute network, orchestrated with central cloud. KITOZER-MicroDC will be deployed as standardized compute units across China’s counties.

34.5 Carbon Neutrality and Green Power

Future data centers require 100% green power, paired with PV, wind, and storage. Modular data centers combine with distributed energy to form a “PV-storage-flexible” new power system.


Chapter 35. Extended FAQ (30 Deep Questions)

Q31: What is the relationship between modular data centers and containerized data centers?
A: Both are prefabricated, but different in form. A modular data center is an “indoor micro-module” that must sit inside a building (room, factory, warehouse) with no outer shell. A containerized data center packs the entire micro-module into a 20/40-foot container with its own shell, insulation, waterproofing, and wind/sand protection, placed outdoors. The technical core (racks, AC, UPS, monitoring) is identical; the difference is the shell and deployment scenario. KITOZER offers both MicroDC indoor and MicroDC-Container versions.

Q32: Is entering the cold aisle inconvenient after containment?
A: No. End doors have automatic sliding or face access; people walk up, the door opens by sensor, and closes behind them. Access logs entries and pairs with cameras. RGB strips light the aisle; the lintel display shows temperature and load, so operators see status from outside and spend minimal time inside.

Q33: Should UPS ECO mode be enabled?
A: ECO mode feeds load directly through bypass at 99% efficiency, saving 3–5% vs double-conversion. But on mains abnormality, switching back to double-conversion takes a few milliseconds, negligible for server power supplies (which have 10–20 ms ride-through). Recommend ECO in areas with good mains (tier-1 cities); keep double-conversion in areas with unstable grid (mines, rural).

Q34: VRLA vs LFP, how to choose?
A: Three factors: (1) Runtime—5–15 min short backup, LFP’s small footprint wins; >15 min, VRLA cost wins. (2) Site—upper floors or tight space choose LFP; ground-floor tight budget choose VRLA. (3) Lifecycle cost—LFP costs 1.5–2x upfront but lasts 3–4x longer and is maintenance-free, so 5–8 year lifecycle cost is lower. KITOZER offers both.

Q35: How is PUE measured?
A: PUE = total energy / IT energy. Install a main meter at the mains incoming (total energy) and an IT meter at UPS output (IT energy); the ratio is PUE. KITOZER-DCIM automatically collects both meters, computes real-time PUE, and generates daily/weekly/monthly reports. Note: PUE must be averaged over long periods; instantaneous PUE is not meaningful.

Q36: Why is my measured PUE higher than design?
A: Common causes: (1) Leaky containment with doors propped open—measured PUE 0.2–0.3 higher; (2) AC supply set too low (e.g., 10°C) while ASHRAE allows up to 27°C; (3) No free cooling, compressors run year-round; (4) Low UPS efficiency (old line-frequency 92% vs new modular 96%); (5) Lighting/maintenance/outlet loads not separately metered but excluded from the IT denominator. Investigate each.

Q37: Why is in-row AC more expensive than room-level?
A: In-row AC includes full inverter compressor, EC variable fans, group control, 7-inch touchscreen, RS485/BACnet, N+1 fans, wet-bulb humidification, PTC reheat, 6 kV surge—all standard on in-row but optional on room-level. Room-level units are cheaper but require a raised floor, dedicated AC room, and central chiller; total investment is not necessarily lower. Moreover, in-row AC is more efficient, and 3–5 years of saved electricity recovers the premium.

Q38: How many temperature-humidity sensors per data center?
A: Rule of thumb: at least 2 per cold-aisle row (each end), 1 per hot-aisle row, 1 in UPS room, 1 in battery room, 1 in gas-cylinder room. Accuracy ±0.5°C, ±3% RH. Sensors connect via RS485 to the CC01 controller.

Q39: Smart PDU vs ordinary PDU?
A: Ordinary PDU only supplies power (outlets + breaker), no monitoring. Smart PDU monitors per-branch current, voltage, power, energy, and can remotely switch each outlet via TCP/IP to DCIM. Smart PDUs cost 2–3x more but enable: (1) finding overloaded branches; (2) remote reboot of hung servers; (3) per-rack energy metering for chargeback; (4) DCIM capacity management.

Q40: How many access control levels?
A: Three: (1) Data hall main door—face + card + log, preventing unauthorized entry; (2) Cold aisle end door—face + log; (3) Important equipment cabinet—key or electronic lock, e.g., UPS, distribution, battery cabinet. Access control integrates with fire, unlocking on alarm.

Q41: How does gas suppression discharge with cold-aisle containment?
A: Nozzles are mounted at the aisle top or above racks. On fire: (1) VESDA dual-stage confirms; (2) AC shuts down, fire dampers close; (3) flip skylights open for smoke exhaust (but close for discharge to maintain concentration); (4) 30-second evacuation delay; (5) gas cylinders discharge, filling aisle and racks; (6) 10-minute hold time to prevent re-ignition.

Q42: Why is water leak dangerous in a data center?
A: Leaks: (1) corrode floor and rack bases; (2) short power cables causing trips; (3) soak server internals damaging motherboards; (4) electric shock. Sources: AC condensate pipes, chilled water (if present), VRLA acid, fire water (if mis-piped), roof rain. Leak rope must run along all water paths, connected to environmental alarms.

Q43: Can UPS power modules of different capacities be mixed?
A: Usually no. All modules in one host must be same model and capacity. Parallel load sharing requires identical modules; mismatched modules cause small-module overload. KITOZER modules are all 50 kVA; expansion inserts identical modules.

Q44: Does the data center need a backup generator?
A: Depends on mains reliability. If the area has dual-feed substations with <1 hour annual outage, 15–30 min UPS suffices. If in remote areas with typhoon/ice causing multi-hour outages, a diesel generator is required. KITOZER supplies 100–2,000 kW silent diesel generators.

Q45: How to maintain a diesel generator?
A: (1) Weekly no-load 30-minute test; (2) Monthly 2-hour load test; (3) Quarterly oil and filter change; (4) Annual 4-hour load test; (5) Day tank above 80%; (6) Battery monthly charging. The generator cannot replace UPS—it must start within the UPS ride-through (15–30 min).

Q46: Can a micro-module go in a basement?
A: Yes, but: (1) Waterproof—basements flood in rain; raise rack bases 200 mm, add leak rope; (2) Ventilation—no natural ventilation, AC condenser must use cooling water or pipe to outdoors; (3) Transport—elevator dimensions must fit large equipment. KITOZER has basement project experience.

Q47: Can a micro-module go on a rooftop?
A: Rooftop: (1) Waterproofing—roof waterproofing must be reliable, rain leak risk; (2) Load—rooftop floor load is usually lower, choose LFP batteries to reduce weight; (3) Sun—rooftop summer heat, shade the AC condenser; (4) Lifting—equipment must be lifted, plan crane or elevator.

Q48: Why do some UPS outputs need an isolation transformer?
A: Isolation transformer separates UPS output from mains bypass, preventing neutral harmonics and common-mode noise from reaching the load. KITOZER modular UPS offers optional output isolation transformer, suitable for medical devices and precision instruments.

Q49: What is HVDC?
A: High Voltage Direct Current rectifies mains to 240V/336V/480V DC directly feeding server power supplies. Compared with traditional UPS (AC→DC→AC), HVDC eliminates the inverter stage, achieving 97–98% efficiency and higher reliability. Telecom DC power has been used for decades. KITOZER offers HVDC power solutions.

Q50: Does micro-module construction require permits?
A: By scale and site: (1) Sub-10-rack in a leased telecom room usually needs no separate permit, but notify the property; (2) Self-built 50+ rack independent room requires fire permit, environmental assessment (if diesel generator), and power supply application. KITOZER provides permit consulting and support.

Q51: What room temperature is most energy-efficient?
A: ASHRAE recommends 18–27°C server intake. The closer to 27°C, the more energy-efficient (lower AC load). KITOZER defaults to 24°C, adjustable to 25–27°C; each 1°C raises PUE by ~0.02. But monitor server intake closely; do not exceed 27°C.

Q52: Why is humidity controlled at 40–60%?
A: Too low (<40%) causes static electricity damaging semiconductors; too high (>60%) causes condensation and shorts. 40–60% is the ASHRAE comfort zone. Winter dryness needs humidification; summer humidity needs dehumidification. KITOZER-CRAC50 includes wet-bulb humidification and reheat dehumidification.

Q53: How does server dust affect data centers?
A: Dust clogs server fan filters, causing poor cooling and CPU throttling; accumulated dust absorbs moisture on boards causing shorts; dust also grows bacteria. Data center air cleanliness: particles >0.5 μm <17,600/L (ISO 14644 Class 8). AC pre-filter + medium filter, monthly replacement.

Q54: Why no windows in a data center?
A: (1) Windows leak cooling/heat, hurting PUE; (2) Window glass is not fire-rated; (3) Windows bring daylight not needed by servers, and UV ages equipment; (4) Windows are a security risk—peering or vandalism. Data halls should be windowless with artificial lighting.

Q55: Can monitoring still be seen during a power outage?
A: Environmental monitoring is itself UPS-powered, so it runs 15–30 minutes on battery. For longer, the monitoring host can connect to a battery or 4G camera with its own battery. KITOZER-CC01 has a backup battery maintaining 4 hours.

Q56: What certifications does KITOZER need for export?
A: (1) EU export: CE; (2) North America: UL; (3) Australia: RCM; (4) Brazil: INMETRO; (5) All exports require customs declaration, inspection, and certificate of origin. KITOZER has CE and ISO 9001/14001 and supports destination-country certification.

Q57: How to manage data center assets?
A: Traditional Excel logs are often inaccurate after changes. KITOZER-DCIM provides U-position mapping: visual display of each rack’s each U position with device, model, go-live, warranty, owner. Scan QR on rack or device change to auto-update. Integrates with CMDB.

Q58: Can micro-module equipment be remotely powered on/off?
A: Smart PDUs support per-outlet remote switching, enabling remote reboot of hung servers. AC, UPS, skylights, and access are all remotely controllable. But server power cycles should be done by IT admins via out-of-band management (iDRAC/ILO), not by cutting PDU power (which loses data).

Q59: Why preventive fire protection in data centers?
A: 90% of data center fires are electrical (short, overload, high contact resistance). Preventive fire protection includes: (1) VESDA early smoke detection; (2) Electrical fire monitoring (residual current); (3) Periodic infrared thermography; (4) Cable fireproof coating and penetration sealing. More important than post-fire suppression.

Q60: How does KITOZER quote?
A: Provide IT load, rack count, site conditions, and runtime; KITOZER returns a detailed design and line-item quote within 48 hours. The quote includes equipment list (model/qty/unit price/amount), installation, freight, taxes, lead time, and warranty. Customer confirms, contract signed, deposit paid, production scheduled.


Chapter 36. Glossary (Chinese-English Bilingual)

Chinese English Abbr. Definition
模块化数据中心 Modular Data Center MDC Factory-prefabricated, on-site-assembled data center
微模块 Micro Module – Standardized room functional unit
冷通道封闭 Cold Aisle Containment CAC Enclosing cold aisle to prevent mixing
热通道封闭 Hot Aisle Containment HAC Enclosing hot aisle
列间空调 In-row Air Conditioner CRAH/CRAC Precision AC between rack rows
房间级空调 Room-based Air Conditioner CRAC Central precision AC in AC room
背板门换热 Rear Door Heat eXchanger RDHx Coil on rack rear door
冷板液冷 Cold Plate Liquid Cooling – Metal cold plate on server CPU/GPU
浸没式液冷 Immersion Cooling – Server submerged in dielectric coolant
冷量分配单元 Coolant Distribution Unit CDU Liquid-cooling circulation and heat exchange unit
不间断电源 Uninterruptible Power Supply UPS Inverter backup on mains loss
模块化UPS Modular UPS – Hot-swap power modules
双变换在线式 Double Conversion Online – AC→DC→AC topology
静态旁路开关 Static Bypass Switch SBS Thyristor bypass transfer
维修旁路 Maintenance Bypass – Mechanical UPS isolation
浪涌保护器 Surge Protective Device SPD Lightning surge protection
阀控密封铅酸电池 Valve-Regulated Lead-Acid VRLA Maintenance-free lead-acid
磷酸铁锂电池 Lithium Iron Phosphate LFP LiFePO4 lithium battery
电池管理系统 Battery Management System BMS Lithium monitoring and protection
数据中心基础设施管理 Data Center Infrastructure Management DCIM Integrated room management software
电源使用效率 Power Usage Effectiveness PUE Total energy / IT energy
水使用效率 Water Usage Effectiveness WUE Cooling water / IT energy
碳使用效率 Carbon Usage Effectiveness CUE Carbon emissions / IT energy
自动转换开关 Automatic Transfer Switch ATS Dual-mains transfer
静态转换开关 Static Transfer Switch STS Millisecond power transfer
智能母线 Intelligent Busway – Prefabricated busbar distribution
智能PDU Power Distribution Unit PDU Metered/switched outlets
吸气式烟雾探测 Aspirating Smoke Detection ASD/VESDA Active early smoke sampling
七氟丙烷 HFC-227ea / FM-200 – Gas suppression agent
全氟己酮 Novec 1230 / FK-5-1-12 – Next-gen eco-friendly agent
数字孪生 Digital Twin DT 3D virtual room replica
边缘计算 Edge Computing – Compute near users
多接入边缘计算 Multi-access Edge Computing MEC 5G edge cloud
高压直流 High Voltage Direct Current HVDC 240V/336V/480V DC supply
自然冷却 Free Cooling – Use outdoor cooling
直接膨胀 Direct Expansion DX Direct refrigerant evaporation
冷冻水 Chilled Water CW Central chiller supply
冷却塔 Cooling Tower – Cooling water heat rejection
干冷器 Dry Cooler – Air-cooled condenser
变频压缩机 Inverter Compressor – Variable-speed compressor
架空地板 Raised Floor – Underfloor air supply
联合接地 Combined Grounding – Shared working/protective/lightning ground
可并行维护 Concurrently Maintainable – Maintenance without shutdown
容错 Fault Tolerant FT Any failure without interruption
服务水平协议 Service Level Agreement SLA Availability commitment

Chapter 37. Room Layout and Spatial Planning

37.1 Space Allocation

Standard data center space allocation:
– Rack row area: 60–70%
– AC room (if room-level AC): 10–15%
– UPS and battery room: 10–15%
– Cable trays and aisles: 5–10%
– Control room and O&M office: 5–10%

Micro-modules integrate AC and UPS into rack rows, saving the AC and UPS rooms; the same floor area fits 30% more racks.

37.2 Rack Row Layout

Double-row face-to-face (cold aisle between rows):

Single-row (one side against wall, cold aisle outside):

Double-row has higher cold-air utilization, mainstream; single-row saves space, for edge nodes.

37.3 Aisle Width

  • Cold aisle width: 1,200–1,500 mm (people and equipment)
  • Hot aisle width: 1,000–1,200 mm (maintenance)
  • Main aisle: ≥1,500 mm (equipment move)

37.4 Ceiling and Floor

  • Clear ceiling height: ≥2.6 m (micro-module), recommended 3.0 m+
  • Raised floor height: 300–500 mm (underfloor air); micro-module may omit raised floor
  • Suspended ceiling: 300–600 mm (overhead air/fire piping)

Chapter 38. Electrical Calculation Examples

38.1 Load Calculation

Project IT load 200 kW, power factor 0.9, diversity factor 0.9.
– Apparent power = 200 / 0.9 = 222 kVA
– Calculated load = 222 × 0.9 = 200 kVA
– UPS selection: 200 / 0.8 = 250 kVA; choose 300 kVA modular UPS (6×50 kVA modules)

38.2 Battery Capacity Calculation

300 kVA UPS at 200 kW load, DC bus ±192V (384V), 30-minute runtime.
– Required battery energy = 200 kW × 0.5 h / 0.95 (inverter) = 105 kWh
– Total battery voltage 384V, required Ah = 105,000 Wh / 384V = 274 Ah
– Choose 12V100Ah, 32 cells per string (384V), 3 parallel strings = 96 cells
– Actual runtime = 3×100 Ah×384V×0.95 / 200 kW = 55 minutes (longer due to margin)

38.3 Cable Sizing

UPS output 300 kVA, current = 300,000 / (380×√3) = 456 A.
– Copper cable at 3 A/mm², cross-section = 456/3 = 152 mm²
– Choose 2× YJV-0.6/1kV-3×185+2×95 in parallel, each ~370 A, two = 740 A, 60% margin

38.4 Grounding Resistance

Combined grounding requires ≤1Ω.
– Vertical electrodes 50×50×5 mm angle steel, 2.5 m long, 20 units at 5 m spacing
– Horizontal flat iron 40×4 mm
– Theoretical resistance ~0.5–0.8Ω; measured below 0.8Ω


Chapter 39. Delivery Checklist and Acceptance Test Cases

39.1 Delivery Checklist

  • [ ] Racks (quantity verified)
  • [ ] Cold aisle skylights, end doors, access, strips, lintel display
  • [ ] In-row AC (with outdoor condenser)
  • [ ] UPS host and power modules
  • [ ] Batteries and racks
  • [ ] Distribution cabinets, PDUs, busway
  • [ ] Environmental controller and sensors
  • [ ] DCIM software and licenses
  • [ ] Fire gas suppression
  • [ ] As-built drawings (CAD electronic)
  • [ ] Equipment certificates, manuals
  • [ ] Test reports
  • [ ] Training records

39.2 Acceptance Test Cases

Test Item Method Pass Criteria
Rack verticality Plumb line ≤3 mm
Rack joining gap Feeler gauge ≤2 mm
Cold aisle temperature 24-hour log 22±2°C
UPS output voltage Multimeter 220V±3%
UPS output frequency Frequency meter 50Hz±0.5Hz
UPS transfer time Oscilloscope <5 ms
Battery runtime Full-load discharge Design ±10%
AC cooling capacity Airflow × ΔT ≥90% rated
Grounding resistance Ground tester ≤1Ω
Fire interlock Simulate fire All actions within 30 s
Access log Card test Accurate
Environmental alarm Simulate leak Alarm within 5 s
DCIM data Compare to field 100% accurate
72-hour burn-in Continuous run No fault

Chapter 40. Selection Decision Tree and Comparison Tables

40.1 Complete Selection Decision Tree

40.2 KITOZER vs Traditional Room Procurement

Dimension KITOZER-MicroDC Traditional Room
Build cycle 4–8 weeks 6–12 months
PUE 1.35–1.5 air 1.8–2.2
Per-rack density 8–30 kW air 2–6 kW
UPS efficiency 96% (high-freq modular) 92% (line-frequency)
Expansion Online module add Re-renovation
Monitoring Unified DCIM Multi-vendor patchwork
Investment Medium (low 5-year TCO) Low upfront (high 5-year TCO)
Delivery Factory prefab + on-site assembly On-site construction
Warranty 3-year whole unit Per-vendor warranty

40.3 Cooling Comparison

Method Density Pros Cons Investment
Room CRAC <6 kW Cheap, simple High PUE, low density Low
In-row 8–25 kW Efficient, N+1 Needs containment Medium
RDHx 20–60 kW High density, low air resistance Needs chilled water High
Cold-plate liquid 20–100 kW PUE 1.1–1.2 Needs CDU, piping High
Immersion 50–200 kW Extreme density Complex maintenance Very high

40.4 UPS Comparison

Method Efficiency Redundancy Investment Use Case
Line-frequency UPS 92% N+1 Low Legacy, budget-tight
High-freq modular UPS 96% N+1 online Medium Mainstream new builds
2N dual-bus 96% 2N High Finance, large internet
HVDC 97% N+1 Medium Large carrier, hyperscaler
Flywheel 98% N+1 High Short-duration, high-frequency ride-through

Chapter 41. Typical Application Industries

41.1 Finance

Banks, securities, and insurance data centers require Tier A (99.999%), 2N redundancy, dual mains + diesel generator. KITOZER-MicroDC-50/100 designed to Tier A with 2N UPS, N+1 AC, VESDA + gas suppression.

41.2 Government and Public Services

Government cloud, smart cities, public security, and tax data centers require Tier B+ and cybersecurity Class 3. KITOZER-MicroDC-20/50 pairs with domestic-CPU servers (Xinchuang) and DCIM compliance modules.

41.3 Internet and Cloud

Elastic internet workloads require fast deployment and on-demand expansion. KITOZER-MicroDC-Container deploys in 2 weeks, ideal for POPs and edge nodes.

41.4 Manufacturing and Industrial Internet

Factory MES, SCADA, and digital-twin rooms near production lines require vibration and dust resistance. KITOZER-MicroDC-10 compact fits next-to-line control rooms.

41.5 Healthcare and Life Sciences

Hospital HIS, PACS, and EMR require 7×24 uninterrupted. KITOZER-MicroDC-20 includes medical-grade isolation transformer and UPS, PUE 1.5.

41.6 Education and Research

University data centers, supercomputing, and AI labs require high-density GPU compute. KITOZER-MicroDC-Liquid supports 50–100 kW per rack.

41.7 Energy and Power

Grid dispatch, PV/storage monitoring, and wind SCADA require unmanned and wide-temperature operation. KITOZER combines outdoor integrated cabinets with micro-modules.

41.8 Transportation and Logistics

Airports, ports, high-speed rail stations, and logistics parks require high reliability and integration with business systems. KITOZER-MicroDC pairs with weak-current system integration.


Chapter 42. Maintenance Calendar and Training Outline

42.1 Annual Maintenance Calendar

Month Activity
Jan Winter AC heating check, battery temperature check
Feb UPS power module deep inspection
Mar Full fire interlock drill
Apr Spring AC filter replacement, free-cooling test
May Grounding resistance test
Jun Rainy-season leak detection, lightning protection check
Jul Summer AC full-load test
Aug Battery capacity test (20% sample annually)
Sep DCIM platform upgrade
Oct Autumn AC filter replacement
Nov Generator load test
Dec Annual summary, next-year budget

42.2 O&M Training Outline

Day 1: Theory
– Modular data center principles
– Cold-aisle containment and row-level cooling
– UPS and battery principles
– Fire and security

Day 2: Hands-on
– Equipment on/off
– Alarm handling
– Filter replacement
– Battery replacement
– Emergency drill

Day 3: Assessment
– Written (theory)
– Practical (alarm handling, battery swap)
– Training certificate issued


Chapter 43. Eco-friendly Packaging and Recycling

43.1 Packaging Materials

  • Cardboard: FSC-certified recycled paper
  • Wooden pallets: IPPC-fumigated, reusable
  • Foam: recyclable EPE
  • Plastic bags: biodegradable

43.2 Equipment Recycling

  • Old UPS: trade-in credit
  • Old batteries: professional recycling (98% lead recovery)
  • Old racks: recycled and reused
  • KITOZER offers 5–10-year extended warranty and one-stop recycling.

Chapter 44. Handling Common Customer Questions

Customer: How do you compare to Huawei, Vertiv, Schneider?
A: Tier-1 brands have strong performance but higher prices and longer lead times (3–6 months). KITOZER offers better cost-performance, faster delivery (4–8 weeks), and 4-hour local service. Ideal for cost-sensitive, fast-deployment mid-size projects.

Customer: Can we pilot a small unit first?
A: KITOZER offers the MicroDC-10 standard unit for display and trial; customers can deploy at small scale first, then expand.

Customer: Payment terms?
A: Standard 3-6-1: 30% advance, 60% on delivery acceptance, 10% retention (paid after 1 year). Large projects may negotiate staged payments.

Customer: Service response?
A: 4-hour phone response, 24-hour on-site (within Guangdong), 48-hour on-site (other provinces). 7×24 service hotline.


Chapter 45. Technical White Paper Appendix

45.1 Thermodynamics Formulas

Sensible heat: Q = m × cp × ΔT
– Q: heat (W), m: mass airflow (kg/s), cp: specific heat of air (1.005 kJ/kg·K), ΔT: temperature difference (K)

Air density ρ=1.2 kg/m³, airflow V (m³/h):
Q(W) = V(m³/h) / 3600 × 1.2 × 1005 × ΔT(K) ≈ V × 0.335 × ΔT

Example: 50 kW cooling, ΔT=15 K, required V = 50,000 / (0.335×15) ≈ 9,960 m³/h.

45.2 Battery Runtime Formula

t(h) = V × Ah × DoD × η / P
– V: total battery voltage (V), Ah: capacity, DoD: depth of discharge (0.8 VRLA, 0.9 LFP), η: inverter efficiency (0.95), P: load (W)

Example: 384V, 100Ah, 20 kW load:
t = 384 × 100 × 0.8 × 0.95 / 20,000 = 1.46 h = 88 minutes.

45.3 PUE Optimization Path

Measure PUE Reduction Investment
Cold aisle containment 0.2–0.3 Low
In-row cooling 0.15–0.25 Medium
Inverter AC 0.05–0.1 Medium
Free cooling 0.15–0.25 Medium
Raise supply temperature 0.05–0.1 None
Modular UPS 0.05–0.1 Medium
Liquid cooling 0.2–0.3 High
HVDC 0.03–0.05 Medium

Combined, PUE can drop from 2.0 to 1.2–1.3.

45.4 Rack Power Density Evolution

Era Per-rack Power Typical Business Cooling
1990s 1–2 kW Rack servers Room CRAC
2000s 3–5 kW Blade servers Hot/cold aisle + room
2010s 6–12 kW Virtualization In-row + containment
2020s 15–30 kW AI inference In-row + RDHx
2025+ 50–100 kW AI training Cold-plate liquid
2030+ 100–200 kW LLM Immersion

Chapter 46. 100-Item Data Center Construction Checklist

46.1 Design Phase (30 items)

  1. IT load list confirmed
  2. 3-year expansion forecast assessed
  3. Rack count and layout drawn
  4. Power density specified
  5. UPS capacity and redundancy selected
  6. Battery runtime determined
  7. AC capacity and redundancy selected
  8. Cold/hot aisle approach chosen
  9. Mains incoming capacity confirmed
  10. Dual-mains need assessed
  11. Diesel generator need assessed
  12. Building chilled water availability confirmed
  13. Site area and ceiling measured
  14. Floor load calculated
  15. Grounding system designed
  16. Lightning protection zones designed
  17. Fire system designed (gas + VESDA)
  18. Security designed (access + CCTV)
  19. Environmental monitoring points laid out
  20. DCIM features confirmed
  21. Structured cabling designed
  22. Busway/PDU approach chosen
  23. Lighting designed
  24. Signage designed
  25. Seismic design checked
  26. Temperature-humidity range specified
  27. Noise requirements specified
  28. Anti-corrosion specified (coastal/chemical)
  29. Export/customs requirements confirmed
  30. Budget and schedule confirmed

46.2 Construction Phase (40 items)

  1. Floor leveling complete
  2. Grounding copper busbar installed
  3. Rack bases fixed
  4. Rack verticality compliant
  5. Rack joining gap compliant
  6. Doors open/close smoothly
  7. Side panels sealed
  8. Top/bottom brush strips installed
  9. Vertical cable managers installed
  10. PDU brackets installed
  11. Grounding bars connected
  12. Skylight framing leveled
  13. Flip skylight magnetic latch wired
  14. Skylight gaskets compressed
  15. Automatic sliding door installed
  16. Access terminal installed
  17. Lintel display installed
  18. RGB strips installed
  19. M-shaped cable trough strong/weak separation
  20. In-row AC positioned
  21. Refrigerant piping welded
  22. Condensate piping clear
  23. Vacuum evacuation complete
  24. Refrigerant charged
  25. UPS host positioned
  26. Input/output cables crimped
  27. Battery racks assembled
  28. Batteries installed
  29. Battery inter-cell links torqued
  30. Terminal covers installed
  31. Battery switch box wired
  32. Distribution cabinets installed
  33. PDUs connected to racks
  34. Sensors (temp-humidity) installed
  35. Leak rope along water paths
  36. Smoke/VESDA sampling pipes installed
  37. Environmental controller wired
  38. Fire cylinder room installed
  39. Nozzles positioned
  40. Firestopping complete

46.3 Commissioning and Acceptance (30 items)

  1. Single-equipment power-on test
  2. UPS output voltage/frequency compliant
  3. UPS transfer time test
  4. Battery discharge test
  5. AC cooling capacity test
  6. AC group control test
  7. Cold aisle temperature uniformity test
  8. Access card log test
  9. Sliding door sensor test
  10. RGB strip color switching
  11. Lintel display data
  12. Leak alarm test
  13. Smoke alarm test
  14. Fire interlock skylight flip test
  15. Fire interlock access unlock
  16. Fire discharge simulation
  17. DCIM data collection accuracy
  18. Alarm SMS/email push
  19. Grounding resistance test
  20. Insulation resistance test
  21. SPD test
  22. 72-hour continuous burn-in
  23. PUE measured log
  24. As-built drawings
  25. Equipment certificates collected
  26. Test reports issued
  27. Operation manual delivered
  28. O&M training completed
  29. Customer sign-off
  30. Warranty starts

Chapter 47. Model Naming Convention

KITOZER-MicroDC naming:

KITOZER-MicroDC-[Rack Count]-[Cooling]-[UPS Capacity]-[Version]

Examples:
– KITOZER-MicroDC-20-Air-200kVA-V2: 20-rack air-cooled 200 kVA version 2
– KITOZER-MicroDC-50-Liquid-500kVA-V1: 50-rack liquid-cooled 500 kVA version 1
– KITOZER-MicroDC-Container-40: 40-foot containerized

Sub-product naming:
– KITOZER-MDC600-2026: 600 mm wide 42U rack, 2026 model
– KITOZER-CRAC50-2026: 50 kW in-row AC, 2026 model
– KITOZER-UP500-2026: 500 kVA modular UPS, 2026 model
– KITOZER-UPM50-2026: 50 kVA power module, 2026 model
– KITOZER-BAT250-2026: 12V250Ah battery, 2026 model
– KITOZER-CC01-2026: Dual-row environmental controller, 2026 model
– KITOZER-PDU63A-2026: 63A smart PDU, 2026 model


Chapter 48. Generic Project Case Data (Desensitized)

48.1 Case 1: Bank Branch Data Hall

  • Scale: MicroDC-20, 20 racks, IT load 80 kW
  • UPS: 200 kVA modular (4×50 kVA, N+1)
  • Batteries: VRLA 12V100Ah × 80 cells, 30-minute runtime
  • AC: 4×25 kW in-row
  • Measured PUE: 1.48
  • Build cycle: 55 days
  • Value: replaced a 100 m² renovated room, 35% energy saving, online expansion

48.2 Case 2: AI Inference Center

  • Scale: MicroDC-50, 12 high-density + 8 reserved, IT load 200 kW
  • UPS: 300 kVA modular (6×50 kVA, N+1)
  • Batteries: LFP 51.2V200Ah × 20 packs, 15-minute runtime
  • AC: 8×50 kW in-row + RDHx rear doors
  • Measured PUE: 1.32
  • Value: LFP batteries save 70% footprint vs VRLA, suiting second-floor load limits

48.3 Case 3: Telecom Edge Node

  • Scale: MicroDC-10, 8 racks, IT load 30 kW
  • UPS: 60 kVA modular (2×30 kVA + 1 redundant)
  • Batteries: LFP rack-mounted, 10-minute runtime
  • AC: 2×25 kW in-row
  • Deployment: building telecom room, 25 m²
  • Value: unmanned, remote monitoring, weekly inspection

Chapter 49. Extended FAQ Continued

Q61: Why does a data center need UPS? Isn’t ordinary power enough?
A: Mains voltage fluctuates, has momentary interruptions and sags, and carries harmonic noise. Server power supplies tolerate brief fluctuations, but UPS switches to battery at 0 ms on mains loss, preventing abnormal shutdown that causes data loss and hardware damage. For finance, healthcare, and industrial control, one outage can cost millions; UPS is essential insurance.

Q62: Modular UPS vs traditional tower UPS?
A: Traditional tower UPS is a single large chassis with fixed power; on failure, the whole unit stops for service. Modular UPS consists of multiple 4U hot-swap power modules; a failed module is pulled and replaced while others keep running. Expansion inserts new modules without replacing the host; initial investment can be phased with business growth.

Q63: What is UPS parallel operation? Why parallel?
A: Multiple UPS hosts connected by a parallel bus share the load. Reasons: (1) expansion—when single-unit capacity is insufficient; (2) redundancy—N+1 parallel, one fails, others carry; (3) maintainability—one down for service, others keep running. KITOZER modular UPS supports up to 4 units, with circulating current <2%.

Q64: Why dual mains?
A: Single mains suffers outages from line maintenance, equipment failure, or lightning trips. Dual mains comes from different substations and routes; ATS switches to the other on failure within <100 ms, servers unaffected. Tier A requires dual mains.

Q65: How long does a diesel generator take to start?
A: Automatic start ≤15 seconds. Total time from mains loss to stable generator supply is 15–30 seconds, bridged by UPS batteries. The generator carries full load after synchronizing until mains restoration.

Q66: How long should batteries last? Why do some fail in 2 years?
A: VRLA design life is 10–12 years at 25°C float; actual 3–5 years. Early failure causes: (1) excessive battery-room temperature (life halves per 10°C rise); (2) over-voltage float causing water loss; (3) long-term float without discharge causing plate sulfation; (4) rising internal resistance undetected. KITOZER recommends full-capacity discharge every 3 years.

Q67: Why is LFP more expensive than VRLA?
A: LFP upfront is 1.5–2x VRLA because: (1) BMS cost; (2) high cell consistency requirements; (3) complex safety design. But LFP lasts 6,000 cycles (vs 1,200 for VRLA), is maintenance-free for 10 years, and has lower lifecycle cost.

Q68: Why environmental monitoring?
A: Unattended rooms without monitoring miss leaks, overheating, and battery swelling, letting small issues grow into major failures. Environmental monitoring 24×7 collects temp-humidity, leak, smoke, power, and access data, alarming by SMS/phone on anomaly; operators see room status on their phone.

Q69: DCIM vs environmental monitoring?
A: Environmental monitoring only tracks environmental variables (temp, leak, smoke, power), not IT assets. DCIM adds IT assets (per-rack per-U-position equipment), capacity management (remaining U-position, power, cooling), energy analytics, and digital twin on top of environmental. DCIM is the upgrade.

Q70: How does air circulate after cold-aisle containment?
A: In-row AC draws cold air from the cold aisle, cools it, blows horizontally to server intakes; servers exhaust hot air to the hot aisle, which returns to the AC. A closed loop. Containment prevents cold air dilution, maximizing AC efficiency.

Q71: Why use a raised floor?
A: The raised floor acts as a supply plenum; cold air reaches rack intakes through perforated tiles. Pros: hidden cabling, uniform supply; cons: ceiling height consumed, dust hard to clean. In the micro-module era, in-row AC blows horizontally directly, no raised floor needed, saving height and cost.

Q72: Data center AC vs residential AC?
A: Residential AC cycles on/off at setpoint with ±2°C accuracy; data center precision AC runs 365 days continuously at ±1°C, with humidification, dehumidification, reheat, and inverter, suited to 24-hour high load. Residential AC fails within 3 months of continuous use and cannot serve a room.

Q73: What is PUE? How calculated?
A: PUE = total DC energy / IT equipment energy. E.g., total 1.5M kWh, IT 1M kWh, PUE = 1.5. Closer to 1 is more efficient. Traditional rooms 1.8–2.2; micro-modules 1.35–1.5; liquid-cooled 1.1–1.25.

Q74: Why water leak detection?
A: Leak sources: AC condensate, chilled water pipes, battery acid, roof rain. Leaks corrode floors, short circuits, and damage equipment. Leak rope runs along water paths, connected to environmental systems, alarming immediately on detection.

Q75: Why gas suppression instead of sprinklers?
A: Water sprinklers damage electronic equipment, causing secondary loss. Gas suppression (HFC-227ea, IG541, Novec 1230) discharges without residue and does not damage equipment, suited to rooms. Gas suppression interlocks with AC, fire dampers, and access, auto-discharging on alarm.

Q76: What is VESDA?
A: VESDA is aspirating early smoke detection; sampling pipes actively draw air, laser scattering detects very early smoke with 1,000× sensitivity vs point detectors, warning 30–60 minutes before visible smoke. Recommended for data halls.

Q77: Why lightning protection and grounding?
A: Lightning surge voltage can reach tens of thousands of volts, invading equipment through power lines. SPD diverts surge at each incoming level. Combined grounding resistance ≤1Ω ensures fast dissipation. KITOZER in-row AC and UPS incoming include standard 6 kV SPD.

Q78: Why busbar instead of cables?
A: High current (hundreds of amps) with cables is expensive, hard to route, and poorly cooled. Copper busbar carries high current, dissipates heat, and scales easily. Intelligent busway runs along rack rows; each rack position plugs a tap-off box, expansion is zero-construction. KITOZER offers optional busway.

Q79: What is a smart PDU?
A: A smart PDU is a rack outlet strip with monitoring and remote control. It monitors per-branch current, voltage, power, and energy; remotely switches each outlet; and connects to DCIM via TCP/IP. Compared with ordinary PDU (power only, no monitoring), smart PDU enables refined energy management.

Q80: Why equipotential bonding?
A: Potential differences between metal equipment cause ground loops and signal interference. Equipotential bonding connects all racks, cable trays, floors, and equipment enclosures to the same grounding busbar via copper tape, eliminating potential differences and ensuring personnel and equipment safety.

Q81: Why is micro-module build cycle short?
A: Traditional room on-site renovation + MEP takes 6–12 months. Micro-modules are factory-assembled (rack joining, AC pre-install, UPS testing, 72-hour burn-in); on-site work is assembly and power connection, taking 4–8 weeks. 80% of work is factory-completed, with little on-site wet work.

Q82: Can micro-modules expand? Does expansion require shutdown?
A: Yes, expansion. UPS power modules are hot-swappable—insert a new module without shutdown. New rack rows join beside the existing module, briefly affecting adjacent-row cold air—recommend off-peak. KITOZER micro-modules support online expansion.

Q83: Can micro-modules be relocated?
A: Yes. Containerized versions lift as a whole; indoor versions require disassembly. Relocation: shutdown → discharge → disassembly → transport → reassembly → commissioning. KITOZER engineers guide on site.

Q84: Why anti-corrosion?
A: Coastal salt spray, chemical gases, and acid rain corrode metal racks and electrical connections. Coastal sites choose 316 stainless; chemical sites choose anti-corrosion coating. KITOZER standard is 304 stainless; coastal/chemical can upgrade to 316.

Q85: How to control data center noise?
A: In-row AC noise is 75 dB(A); offices nearby need acoustic treatment. Measures: acoustic wool in walls between room and office, double-glazed windows, low-noise AC selection, dedicated AC room. Short-duration entry by operators is acceptable.

Q86: Why anti-static floor?
A: Anti-static floor surface resistance 10^6–10^9Ω, dissipating body static to avoid semiconductor damage. Floor pedestals are grounded. Micro-modules may skip raised air-supply floors but still need anti-static flooring or vinyl.

Q87: Lighting requirements?
A: Aisle average illumination ≥300 lx, emergency lighting ≥50 lx. KITOZER cold aisles include RGB LED strips—white for normal, red for alarm. Lamps interlock with fire: emergency lighting auto-on on alarm.

Q88: What is a 3D digital twin room?
A: 3D modeling recreates the room virtually, real-time mapping each rack’s temperature, power, and fan speed. Operators click any rack in the 3D scene to see details and historical curves. Supports expansion simulation: virtually add a rack, software auto-calculates impact on the temperature field and power.

Q89: AI compute rooms vs traditional rooms?
A: AI rooms have high power density (20–100 kW/rack vs 6–10 kW traditional), requiring liquid cooling; large power (MW per floor), requiring HVDC; LFP batteries (high power density); cold-plate/immersion cooling. KITOZER-MicroDC-Liquid is designed for AI rooms.

Q90: KITOZER warranty?
A: 3-year whole-unit warranty (racks, AC, UPS, environmental); 2-year battery (VRLA) / 3-year (LFP). Consumables (filters, gaskets) excluded. 5-year extended warranty available. 7×24 hotline, 4-hour phone response, 24-hour on-site (within Guangdong).


Chapter 50. Conclusion and Outlook

After more than two decades, modular data centers have evolved from a novelty to an industry standard. KITOZER-MicroDC, as a core product line of Guangzhou Laian Intelligent System Development Co., Ltd., is committed to providing fast, efficient, scalable, and reliable data center infrastructure for customers across industries.

Looking ahead, three trends are irreversible:
1. Liquid cooling: AI compute pushes per-rack density from 10 kW toward 100 kW; air cooling will gradually exit high-density scenarios, with cold-plate and immersion becoming mainstream.
2. Intelligence: DCIM will adopt large models, evolving from “alarm reporting” to “predictive O&M,” with early equipment fault warnings and automatic expansion recommendations.
3. Green: Under carbon-neutral goals, data center PUE will drop from 1.5 to 1.2, paired with PV, storage, and waste-heat recovery to form zero-carbon data centers.

KITOZER continues to invest in R&D, building next-generation green intelligent compute infrastructure with customers. Whether you are building new, expanding, or retrofitting, KITOZER delivers standardized solutions from 10 to 100 racks in air-cooled, liquid-cooled, and containerized versions.

Contact us now: Tel/WeChat +86 13922289957, +86 18520668845; WhatsApp +86 19068534140. Design and quote within 48 hours.


SEO 元数据汇总

中文站(lain.com.cn)

  • Title: KITOZER模块化数据中心技术百科_微模块机房_冷通道封闭_列间空调_模块化UPS_液冷_KITOZER
  • Meta Description: KITOZER模块化数据中心技术百科全书,系统讲解微模块机房定义与发展、冷通道封闭、列间精密空调、模块化UPS与蓄电池、动环监控,覆盖MicroDC 10/20/50/100柜风冷与液冷方案,详解PUE/制冷量/UPS容量/后备时间/功率密度,附选型指南、对比表、通用案例与30条FAQ。
  • Focus Keyword: 模块化数据中心, 微模块机房, 冷通道封闭, 列间空调, 模块化UPS, 液冷数据中心, KITOZER
  • URL slug: /modular-data-center-encyclopedia/

英文站(gdlain.com)

  • Title: KITOZER Modular Data Center Encyclopedia | Micro Module, Cold Aisle Containment, In-row CRAH, Modular UPS
  • Meta Description: KITOZER modular data center encyclopedia covers micro-module definition, cold-aisle containment, in-row cooling, modular UPS and batteries, DCIM, MicroDC 10/20/50/100 air and liquid-cooled solutions, PUE, cooling capacity, UPS sizing, runtime, rack density, selection guide, comparison, generic cases and 30 FAQs.
  • Focus Keyword: modular data center, micro module data center, cold aisle containment, in-row CRAH, modular UPS, liquid cooling, KITOZER
  • URL slug: /modular-data-center-encyclopedia/

配图建议

序号 中文描述 英文ALT
IMG-01 KITOZER双排冷通道封闭微模块机房全景 KITOZER dual-row cold aisle containment micro module data hall
IMG-02 42U网孔智慧机柜与M型走线槽 KITOZER 42U perforated smart rack with M-shaped cable trough
IMG-03 50kW列间空调在机柜列间水平送风 KITOZER 50kW in-row precision AC horizontal airflow
IMG-04 500kVA模块化UPS主机与50kVA功率模块 KITOZER 500kVA modular UPS host with 50kVA power modules
IMG-05 12V250Ah VRLA电池组与四层电池架 KITOZER 12V250Ah VRLA battery bank on four-tier rack
IMG-06 玻璃翻转天窗与门楣条形屏通道入口 KITOZER glass flip skylight and lintel bar display aisle entrance
IMG-07 冷板液冷机柜与CDU冷量分配单元 KITOZER cold-plate liquid-cooled rack with CDU
IMG-08 集装箱式数据中心整体外观 KITOZER containerized data center exterior

建议分类与标签

  • 中文站分类: 数据中心 / 模块化机房 / 微模块整体方案
  • 英文站分类: Data Center / Modular & Micro Module Solution
  • 标签: 模块化数据中心, 微模块, 42U机柜, 冷通道封闭, 列间空调, 模块化UPS, 蓄电池, 液冷, PUE, modular data center, micro module, cold aisle containment, in-row CRAH, modular UPS, VRLA, LFP, liquid cooling, PUE
Shopping Cart