Manufacturer: Guangzhou Lain Intelligent System Development Co., Ltd.
Document Version: V2.0
Release Date: July 2026
Table of Contents
TogglePreface
With the rapid development of the digital economy, the demand for computing power from AI computing, high-performance computing, cloud computing, and other services continues to rise. The power consumption of a single server has grown rapidly from a few hundred watts in traditional designs to several kilowatts, and the power density of a single cabinet has exceeded 30 kW and even reached 100 kW. Traditional air-cooling heat dissipation technologies can no longer meet the heat dissipation requirements of high-density computing scenarios, while also facing industry pain points such as high energy consumption, high noise levels, and frequent localized hot spots.
As a new-generation liquid-cooling heat dissipation infrastructure, the open water-cooled integrated cabinet uses water as the primary cooling medium. Through an open-loop heat exchange path, it efficiently removes heat generated by IT equipment from the data center. It offers core advantages including high heat dissipation efficiency, low energy consumption, flexible deployment, and convenient operation and maintenance. It is the core solution to the heat dissipation challenges of high-power-density data centers.
This manual covers the open water-cooled integrated cabinet developed and manufactured by Guangzhou Lain Intelligent System Development Co., Ltd., providing comprehensive coverage of the full lifecycle including product introduction, structural composition, technical parameters, installation specifications, wiring standards, commissioning procedures, operation and maintenance, fault troubleshooting, and acceptance criteria. It is designed to provide professional, standardized, and actionable operating guidance for equipment installers, operations and maintenance engineers, and data center management personnel, ensuring safe, stable, and efficient equipment operation.
This manual is compiled based on current national and industry standards. If product technology is upgraded or standards are updated, the content will be revised accordingly without prior notice. Equipment operation must be performed by qualified professionals who strictly follow the specifications in this manual. The manufacturer assumes no liability for equipment damage or safety incidents caused by improper operation.
Chapter 1 Product Introduction
1.1 Industry Development Background
Driven by the dual carbon policy, PUE (Power Usage Effectiveness) management indicators for data centers have become increasingly stringent. The PUE of traditional air-cooled data centers is generally above 1.4, with some older facilities exceeding 1.8. Energy costs account for more than 40% of the total lifecycle cost of a data center. Energy conservation and carbon reduction have become core requirements for data center construction.
Liquid cooling technology, with its heat exchange efficiency far exceeding that of air cooling, has become the mainstream development direction for data center heat dissipation technology. Among these, water cooling technology uses water as the cooling medium, which features high specific heat capacity, high heat transfer coefficient, and low acquisition cost, making it the most mature commercially applied liquid cooling technology route. Open water cooling systems, due to their simple structure, low deployment cost, and low maintenance difficulty, are widely used in scenarios such as small and medium-sized data centers, edge computing nodes, and modular data centers.
Guangzhou Lain Intelligent System Development Co., Ltd. hasdeeply cultivateded the fields of data center cooling and intelligent cabinets for many years. Combining industry needs with technical accumulation, the company independently developed the open water-cooled integrated cabinet product series, integrating the cabinet body, water-cooling circulation module, power distribution module, and environment monitoring module into one unit. This achieves factory prefabrication and rapid on-site deployment, significantly shortening project construction cycles and reducing overall construction costs.
1.2 Product Definition
The open water-cooled integrated cabinet is a standardized cabinet product integrating a water-cooling heat dissipation system, power supply and distribution system, and intelligent monitoring system. It adopts an open water circulation heat dissipation architecture, where cooling water has direct or indirect contact exchange with the outside atmosphere. Through heat exchange forms such as cold plates, coil pipes, or spray cooling, it absorbs heat generated by IT equipment operation inside the cabinet. The heated cooling water is cooled by an external cold source and then circulated back, continuously maintaining the internal cabinet temperature within the allowable range for equipment.
Compared with closed water cooling systems, the circulation piping of open water cooling systems is connected to the atmosphere, requiring no pressure-bearing sealed design. The system structure is simpler, investment costs are lower, and maintenance operations are more convenient. Compared with traditional air-cooled cabinets, heat dissipation efficiency is improved by 3-5 times, supporting a maximum power density of up to 120 kW per cabinet, while significantly reducing data center air conditioning energy consumption. PUE can be reduced to below 1.15.
1.3 Product Positioning
The Lain open water-cooled integrated cabinet is positioned as standardized heat dissipation infrastructure for high-density computing scenarios. Targeting medium and high power density data center requirements, it covers the full power range from 10 kW to 120 kW, balancing heat dissipation performance, construction cost, and operational convenience. It can be deployed independently as a standalone computing unit or connected in parallel in multiple cabinets to form a large-scale liquid-cooled data center, adapting to computing construction needs of different scales.
The product adopts a modular design philosophy. Core components are standardized universal parts, supporting on-demand configuration and expansion. It is compatible with mainstream brands of servers, switches, storage devices, and other IT equipment, as well as existing data center cold source systems. No large-scale renovation of the data center is required, making it suitable for two core scenarios: upgrading existing data centers and rapid deployment of new data centers.
1.4 Design Philosophy
1.4.1 Safety and Reliability Priority
Product design takes safe operation as the first principle. The water circuit system features multiple leak prevention designs, configured with full-point leak detection and emergency water shutoff mechanisms. The electrical system complies with national low-voltage distribution specifications, equipped with overload, short-circuit, and leakage protection. The structural design meets seismic, load-bearing, and fire protection standards, ensuring equipment and data safety.
1.4.2 High Efficiency and Energy Saving
The water circuit flow path design is optimized to reduce system flow resistance and pump power consumption. High-efficiency heat exchange structures are adopted to improve heat exchange efficiency and maximize the utilization of natural cold sources. The intelligent temperature control system dynamically adjusts water flow and cold source output based on load, achieving on-demand cooling and reducing ineffective energy consumption.
1.4.3 Convenient Operation and Maintenance
Standardized quick-connect fittings are used, requiring no professional welding tools for pipeline connections. Core components are front-mounted, allowing maintenance without removing IT equipment. The monitoring system has fault self-diagnosis and positioning functions, reducing maintenance difficulty. Wear parts are designed with universal specifications for convenient spare parts acquisition and replacement.
1.4.4 Combination of Standardization and Customization
The main structure and core components adopt standardized design, ensuring product consistency and delivery cycles. At the same time, customized adjustments are supported based on customer site conditions, equipment types, and power requirements, including cabinet dimensions, interface specifications, power distribution parameters, and monitoring functions, to meet personalized scenario needs.
1.5 Applicable Standards and Specifications
The design, production, and inspection of this product strictly follow the following national and industry standards:
- GB/T 39663-2020 “Technical Requirements for Cold Plate Liquid Cooling Systems in Data Centers”
- GB 50174-2017 “Data Center Design Specification”
- GB 7251.1-2013 “Low-Voltage Switchgear and Controlgear Assemblies – Part 1: General Rules”
- GB/T 19001-2016 “Quality Management Systems – Requirements”
- GB/T 24001-2016 “Environmental Management Systems – Requirements”
- T/CIE 093-2021 “Technical Specification for Data Center Liquid Cooling Systems”
- YD/T 2165-2020 “Integrated Cabinet for Telecommunications”
- GB 50236-2011 “Specification for Construction of Field Equipment, Industrial Pipeline Welding Engineering”
- GB 50303-2015 “Code for Acceptance of Construction Quality of Building Electrical Engineering”
Chapter 2 Product Composition
The Lain open water-cooled integrated cabinet adopts an integrated design, consisting of five core systems: the cabinet body system, open water-cooling circulation system, power supply and distribution system, intelligent monitoring system, and auxiliary support system. All systems work in coordination to achieve full-function operation of cabinet cooling, power supply, and monitoring.
2.1 Cabinet Body System
The cabinet body serves as the carrier for equipment installation and system integration. It is manufactured from high-strength steel, featuring high load-bearing capacity, high protection, and easy expansion. It mainly includes the following components:
2.1.1 Cabinet Frame
Manufactured from high-quality cold-rolled steel plate formed by bending. Main frame thickness ≥2.0mm; side panels and door panels thickness ≥1.5mm. The surface undergoes acid washing, phosphating, and electrostatic powder coating for excellent anti-corrosion and anti-rust performance. Standard cabinet heights: 42U/47U/52U optional; widths: 600mm/800mm optional; depths: 1000mm/1200mm/1400mm optional. Custom dimensions are available upon request.
The cabinet adopts a modular spliced structure. Front and rear doors are double-open tempered glass doors or steel plate doors with anti-theft locks. Left and right side panels are detachable for cabinet grouping installation and side maintenance. The bottom is equipped with cable entry holes and water leak drainage channels. The top can be optionally equipped with a top cover and cable trough.
2.1.2 Internal Mounting Components
- Mounting Rails: Four high-strength mounting rails with U-position markings. Supports both square-hole and round-hole mounting patterns, compatible with standard 19-inch IT equipment installation. Rails are adjustable in front-to-back position to accommodate equipment of different depths.
- Shelves: Optional fixed shelves and sliding shelves, load-bearing capacity ≥80kg each, used for installing non-rack-mounted equipment such as switches and storage devices.
- Cable Management: Vertical and horizontal cable managers with separate routing for power and signal cables, ensuring neat and standardized cable organization.
- Load-Bearing Base: Reinforced base at the cabinet bottom, supporting forklift handling and expansion bolt fixation, distributing cabinet weight and adapting to floors of different load-bearing ratings.
2.1.3 Sealing and Protection Structure
The cabinet adopts a semi-enclosed sealing design. Front and rear doors are equipped with sealing rubber strips to reduce mixing of hot and cold air and improve heat dissipation efficiency. The cabinet bottom is equipped with a waterproof coaming and drainage guide structure. In the event of minor water leakage, water can be concentrated and directed to leak detection points, avoiding spread to IT equipment areas. The cabinet protection rating reaches IP20, meeting indoor data center usage requirements.
2.2 Open Water-Cooling Circulation System
The open water-cooling circulation system is the core functional system of the product, responsible for heat absorption, transfer, and discharge. It adopts an open circulation architecture and mainly consists of the heat exchange module, circulating water pump module, piping distribution module, water make-up and drainage module, and water treatment module.
2.2.1 Heat Exchange Module
The heat exchange module is the core component for heat exchange. This product adopts a dual architecture of cold plate heat exchange + cabinet-level air-liquid heat exchange, which can be flexibly configured based on equipment type:
- Server Cold Plates: Directly attach to server CPUs, GPUs, and other core heat-generating components. High thermal conductivity interface materials reduce thermal resistance and transfer component heat directly to the cooling water. Configured for high-power computing nodes.
- Cabinet-Level Air-Liquid Heat Exchanger: Installed at the rear or top of the cabinet. Hot air inside the cabinet passes through the heat exchanger fins and exchanges heat with the cooling water. The cooled air returns to the front of the cabinet, forming an internal air circulation path. Suitable for general IT equipment that cannot be fitted with cold plates.
- External Heat Exchange Unit: Open cooling tower or dry cooler. The heated circulating water exchanges heat with air in the external heat exchange unit, and after cooling, returns to the cabinet. This serves as the cold source end of the open system.
2.2.2 Circulating Water Pump Module
The circulating water pump provides power for water circulation. It adopts a one-active-one-standby redundant design. When one pump fails, the standby pump automatically switches over to ensure continuous system operation.
- Pump Type: Vertical/horizontal stainless steel centrifugal pump. Wetted parts use 304/316L stainless steel material for corrosion and rust resistance, suitable for cooling water quality requirements.
- Pump Drive: Standard variable frequency drive, capable of dynamically adjusting speed based on cabinet load and temperature, with a speed adjustment range of 0-100% for energy-efficient operation.
- Pump Parameters: Flow range 2-30m³/h, head range 10-60m. Selected to match cabinet power and piping resistance.
2.2.3 Piping Distribution Module
The piping distribution module is responsible for the delivery, distribution, and collection of cooling water, ensuring uniform flow to each heat exchange unit.
- Main Supply and Return Piping: 304 stainless steel seamless pipe or PPR steady-state pipe. Main pipe diameter DN25-DN100 optional, matched to total flow rate.
- Water Collector/Distributor: Stainless steel construction with built-in flow regulating valves and flow meters. Each branch circuit flow rate can be independently adjusted to ensure uniform heat exchange across all equipment.
- Quick Couplings: Self-sealing quick-connect couplings with built-in shutoff valves. Automatically seal upon connection/disconnection with no cooling water leakage. Suitable for rapid equipment removal and installation and maintenance.
- Valve Components: Include butterfly valves, ball valves, check valves, safety valves, and air vent valves, providing functions such as pipe circuit on/off, flow regulation, pressure protection, and automatic air venting.
2.2.4 Water Make-up and Drainage Module
Open systems experience certain water evaporation and loss. The water make-up module is used to maintain system water level and volume balance.
- Make-up Water Tank: Open make-up water tank, open to the atmosphere, 304 stainless steel construction, volume 50-500L optional. Equipped with a built-in liquid level sensor that automatically triggers water make-up at low level.
- Make-up Water Solenoid Valve: Connected to municipal water supply or softened water system. Automatically opens and closes based on liquid level signals to achieve automatic water make-up.
- Drain Valve: The system bottom is equipped with blowdown valves and drain valves for system blowdown, water replacement, and maintenance drainage.
2.2.5 Water Treatment Module
Open system cooling water contacts air and is prone to scale, algae growth, and corrosion. The water treatment module ensures stable water quality and extends system life.
- Water Filters: Y-type filter and precision filter combination, filtering impurities from the water to prevent blockage of piping and heat exchange channels.
- Electronic Water Treatment Unit: Installed on the main pipeline. Through electromagnetic field action, prevents scale formation while also providing certain sterilization and algae-removal effects.
- Chemical Dosing Device: Optional fully automatic chemical dosing device, periodically adding corrosion inhibitors, scale inhibitors, and biocides to maintain water quality indicators within the acceptable range.
2.3 Power Supply and Distribution System
The power supply and distribution system provides stable and reliable power to IT equipment, the water-cooling system, and the monitoring system inside the cabinet. It is integrated within the cabinet and has comprehensive protection and metering functions.
2.3.1 Main Input Power Distribution Unit
- Input Circuit Breaker: Molded case circuit breaker with overload, short-circuit, and undervoltage protection functions. Rated current 63A-400A optional, configured based on total cabinet power.
- Surge Protection Module: Class C/D power surge protective device, suppressing surge voltages to protect downstream equipment from lightning strikes and grid surges.
- Energy Metering: Multi-function power meter, real-time monitoring of voltage, current, power, energy, power factor, and other parameters. Supports remote data transmission.
2.3.2 IT Equipment Power Distribution Unit
- Rack-Mounted PDU: Installed on cabinet mounting rails. Available in basic and intelligent types. Output socket quantity: 10-30 sockets optional. Supports GB standard 10A, 16A, IEC C13, C19, and various other socket specifications.
- Branch Circuit Protection: Each output branch circuit is equipped with a miniature circuit breaker for independent protection. A single branch fault does not affect the operation of other equipment.
- Busbar Power Distribution: High-power models can be optionally configured with busbar trunking power distribution, offering high current-carrying capacity, flexible installation, and hot-swappable tap-off boxes.
2.3.3 Water-Cooling System Power Distribution Unit
Independent power supply circuit for the water-cooling system, including pump power supply circuit, valve power supply circuit, and heat exchange fan power supply circuit. Each circuit is equipped with an independent circuit breaker and contactor, uniformly controlled by the monitoring system.
2.3.4 Grounding and Equipotential System
The cabinet is equipped with a dedicated grounding copper busbar. The cabinet frame, power distribution units, metal piping, and equipment enclosures are all reliably connected to the grounding copper busbar, which is ultimately connected to the data center grounding system. Grounding resistance ≤4Ω, ensuring electrical safety.
2.4 Intelligent Monitoring System
The intelligent monitoring system achieves real-time monitoring, automatic control, fault alarm, and remote management of the entire cabinet system. It is the core of intelligent cabinet operation.
2.4.1 Main Controller
Adopts PLC or industrial-grade ARM controller with stable and reliable operation and multi-protocol communication support. It serves as the core of the entire monitoring system. The controller collects data from various sensors, executes control strategies according to preset logic, and uploads data to the environment monitoring platform.
2.4.2 Sensor Group
- Temperature Sensors: PT100 platinum resistance temperature sensors, accuracy ±0.1℃. Installed at supply/return water pipes, cabinet air inlet, air outlet, cold plate surfaces, and other locations to monitor full-path temperatures.
- Pressure Sensors: Diffused silicon pressure sensors, accuracy ±0.5%FS. Installed on supply/return main pipes to monitor system pressure and determine pipe blockage or leakage.
- Flow Sensors: Turbine or electromagnetic flow sensors, measuring main pipe and branch circuit water flow rates to monitor circulation status.
- Liquid Level Sensors: Submersible or float-type liquid level sensors, installed in the make-up water tank to monitor water level.
- Leak Detection Sensors: Positioning-type leak detection cable combined with point-type leak sensors, deployed at the cabinet bottom, pipe joints, valves, and other leak-prone locations. Accuracy up to ±1cm.
- Humidity Sensors: Monitor internal cabinet air humidity to prevent condensation.
2.4.3 Human-Machine Interface Unit
The cabinet front door is equipped with a 7-inch color touchscreen display with a Chinese-language operating interface. It provides real-time viewing of system operating parameters, equipment status, and fault alarm information, and supports parameter settings, manual control, and historical data query.
2.4.4 Communication and Remote Management
- Communication Interfaces: Standard RS485 and Ethernet interfaces, supporting Modbus-RTU, Modbus-TCP, SNMP, and other standard communication protocols. Can be integrated into the data center environment monitoring system.
- Remote Management: Supports Web and mobile remote access. Real-time viewing of operating status and alarm information. Enables unattended operation and maintenance.
- Alarm Functions: Supports audible/visual alarm, SMS alarm, email alarm, and other alarm methods. Immediately notifies operations personnel in the event of a fault.
2.5 Auxiliary Support System
2.5.1 Emergency Air-Cooling Backup System
Standard emergency air-cooling module. When the water-cooling system fails and shuts down, the emergency air-cooling fans automatically start to maintain basic equipment heat dissipation, buying time for repairs and preventing equipment shutdown due to overheating.
2.5.2 Fire Protection Support
The cabinet has reserved installation positions for smoke detectors and heat detectors, which can be connected to the data center fire protection system. Cabinet-level gas fire suppression devices are optional for rapid local fire extinguishing.
2.5.3 Lighting System
LED lighting is installed inside the cabinet. The lights automatically turn on when the door opens and turn off when the door closes, facilitating equipment installation and maintenance operations.
Chapter 3 Product List
3.1 Standard Configuration List
Taking the LA-SW-42U-30kW standard model as an example, the standard configuration is as follows:
| No. | Component Name | Specification/Model | Qty | Unit | Remarks |
|---|---|---|---|---|---|
| 1 | Cabinet body | 42U, 600×1200×2000mm, cold-rolled steel, powder coated | 1 | Unit | Includes front/rear doors, side panels, base |
| 2 | Mounting rails | 19-inch standard, square hole, galvanized | 4 | Pcs | With U-position markings |
| 3 | Air-liquid heat exchanger | 30kW heat exchange capacity, copper tube aluminum fin | 1 | Set | Installed at cabinet rear |
| 4 | Circulating water pump | Stainless steel centrifugal pump, 10m³/h, 20m head, 0.75kW | 2 | Units | One active, one standby |
| 5 | Variable frequency control cabinet | Pump VFD control, includes contactor, protector | 1 | Set | Integrated at cabinet side |
| 6 | Water collector/distributor | 304 stainless steel, 6 circuits, with flow regulating valves | 1 | Set | One set each for supply and return |
| 7 | Make-up water tank | 304 stainless steel, 100L, with level switch | 1 | Pc | Open design |
| 8 | Make-up water solenoid valve | DN20, brass material, 220V supply | 1 | Pc | Automatic water make-up |
| 9 | Y-type filter | DN32, 304 stainless steel, 80 mesh screen | 2 | Pcs | One each for supply and return |
| 10 | Electronic water treatment unit | DN32, high-frequency electromagnetic field type | 1 | Unit | Anti-scaling and anti-corrosion |
| 11 | Valve set | Ball valve, check valve, air vent valve, safety valve | 1 | Set | Includes matching fittings |
| 12 | Main water piping | 304 stainless steel pipe, DN32 | 1 | Set | Factory pre-fabricated inside cabinet |
| 13 | Rack-mounted PDU | 24 outlets, 10A GB + 16A GB, intelligent metering type | 2 | Pcs | One on each side (left and right) |
| 14 | Main input circuit breaker | Molded case circuit breaker, 100A, 3P | 1 | Pc | Main input protection |
| 15 | Grounding copper busbar | 30×3mm copper, length 500mm | 1 | Pcs | With grounding terminals |
| 16 | Monitoring controller | Industrial PLC, 7-inch touchscreen | 1 | Set | Includes control program |
| 17 | Temperature sensor | PT100, Class A accuracy | 4 | Pcs | Supply/return water, inlet/outlet air each |
| 18 | Pressure sensor | 0-1.6MPa, 4-20mA output | 2 | Pcs | One each for supply and return |
| 19 | Flow sensor | Turbine type, 0-15m³/h | 1 | Pc | Supply main pipe |
| 20 | Leak detection system | Positioning leak detection cable 3m + controller | 1 | Set | Deployed at cabinet bottom |
| 21 | Emergency air-cooling module | Axial fan, air volume 1200m³/h | 2 | Units | Redundant backup |
| 22 | LED lighting | 12W, door-operated switch | 2 | Pcs | One front, one rear |
| 23 | Cabinet door lock | Three-point anti-theft lock | 2 | Sets | Front and rear doors |
| 24 | Random accessories | Expansion bolts, wrenches, sealing rings, manual | 1 | Set | For installation and maintenance |
3.2 Optional Accessory List
| No. | Accessory Name | Specification Description | Applicable Scenario |
|---|---|---|---|
| 1 | Server cold plate kit | Compatible with mainstream CPU/GPU models, includes cold plate, thermal pad, hoses | High-power computing nodes |
| 2 | Precision chemical dosing device | Fully automatic dosing, corrosion/scale inhibitor + biocide dual chemical tanks | Areas with poor water quality |
| 3 | Busbar power distribution system | 630A busbar trunking, hot-swappable tap-off boxes | Single cabinet power ≥60kW |
| 4 | Cabinet-level gas fire suppression | Heptafluoropropane fire suppression device, automatic activation | High security level data centers |
| 5 | 485 communication gateway | Supports multi-protocol conversion, integration with third-party environment monitoring systems | Unified monitoring platform projects |
| 6 | Cabinet grouping connectors | Fixing components for parallel cabinet installation | Multi-cabinet grouping deployment |
| 7 | Cabinet base elevation | 100mm/200mm elevated base | Underfloor cabling scenarios |
| 8 | Top cable trough | Separate routing trough for power and signal cables | Overhead cabling data centers |
| 9 | External cooling water tank | 500L/1000L open water tank | Scenarios without centralized cold source |
| 10 | Dry cooler unit | Air-cooled chiller, open circulation | Projects without cooling towers |
3.3 Specialized Tool List
The following specialized tools are required for equipment installation and commissioning. Some are provided by the manufacturer, and some must be prepared on site:
Manufacturer-Provided Specialized Tools:
- Specialized torque wrench (for pipe fitting tightening)
- Pipe flaring tool
- Leak detection test pen
- Dedicated commissioning data cable
- Water quality test kit
Tools to Be Prepared On Site:
- Impact drill, hand drill
- Adjustable wrench, open-end wrench, hex key set
- Wire stripper, crimping tool, electrician’s knife
- Multimeter, megohmmeter, clamp ammeter
- Level, tape measure, plumb line
- Pressure test pump, hose clamp pliers
- Lint-free cloth, isopropyl alcohol, sealant
- Safety helmet, insulated gloves, protective goggles, and other PPE
3.4 Unpacking and Acceptance Requirements
After equipment arrives, unpacking and acceptance must be performed jointly by the manufacturer’s technical personnel and the customer. Check each component’s model, quantity, and appearance against the packing list one by one.
- Check the equipment appearance for collision damage, deformation, paint peeling, glass component damage, and any moisture or water ingress marks on sealed packaging.
- Check electrical components for moisture damage and corrosion, and check wiring terminals for looseness or detachment.
- Check that all accompanying documents are complete, including this manual, product certificate of conformity, quality inspection report, warranty card, electrical schematic diagram, and piping schematic diagram.
- After acceptance is confirmed without issues, both parties sign for confirmation. If missing parts, damage, or other issues are found, record them on site and contact the manufacturer for resolution.
Chapter 4 Product Working Principle
4.1 Basic Principles of the Open Water Cooling System
The core characteristic of an open water cooling system is that the circulating cooling water is directly connected to the atmosphere. System pressure is primarily determined by pump head and position head, with no sealed pressure-bearing structure. The entire heat dissipation process is divided into three core stages: heat absorption, heat transfer, and heat rejection, forming a complete open circulation loop.
4.1.1 Heat Absorption Stage
Inside the cabinet, heat generated by IT equipment operation is transferred to the cooling water through two paths:
Direct Contact Heat Exchange: For servers equipped with cold plates, heat from heat-generating components such as CPUs and GPUs is transferred through thermal grease/thermal pads to the cold plate base. The cooling water flowing at high speed through the internal channels of the cold plate carries away the heat through convective heat exchange. This is the most efficient heat exchange method with the lowest thermal resistance.
Indirect Air Heat Exchange: For general IT equipment, hot air inside the cabinet flows through the fin gaps of the air-liquid heat exchanger driven by fans. Heat is transferred to the cooling water inside the heat exchanger. The cooled air returns to the front of the cabinet, where it absorbs equipment heat again, forming an internal air circulation loop within the cabinet.
The two heat exchange methods can be configured independently or in combination, adapting to different types of IT equipment configurations.
4.1.2 Heat Transfer Stage
After absorbing heat and rising in temperature, the cooling water flows out of the cabinet along the supply piping, driven by the circulating water pump, and is delivered to the external cold source equipment. The water collector/distributor and regulating valves in the piping system ensure uniform flow distribution to each branch circuit. Filters remove impurities from the water, protecting heat exchange equipment and pumps.
The supply piping of an open system does not need to withstand high pressure. Requirements for pipe material and connection techniques are relatively lower. Various pipe materials can be used, including stainless steel pipe, galvanized steel pipe, and PPR pipe. Construction difficulty and cost are lower than those of closed systems.
4.1.3 Heat Rejection Stage
The heated cooling water enters the external open cold source equipment. Common types include open cooling towers, evaporative air coolers, and dry coolers:
Open Cooling Tower: Cooling water is sprayed down from the top of the tower and directly contacts the flowing air. A portion of the water evaporates, absorbing latent heat of vaporization, and the majority of the cooling water is cooled. The cooled water falls into the collection basin at the tower bottom and is returned to the cabinet by pump. This is the most typical open heat exchange form, with high heat exchange efficiency and outlet water temperature approaching the wet bulb temperature.
Dry Cooler: Cooling water flows through sealed coil pipes. Air blows over the pipe surface for heat exchange. Water does not directly contact air. This is an indirect heat exchange form within an open system, which can reduce water losses and water quality contamination. It is suitable for areas with high water quality requirements or water scarcity.
After cooling through heat rejection, the cooling water is transported back to the cabinet through the return piping, entering the next heat absorption cycle. This process repeats continuously, discharging heat from inside the cabinet to the outdoor environment.
4.2 Water Balance and Make-up Principle
During open cooling tower operation, three types of water losses occur: evaporation loss, wind drift loss, and blowdown loss. The system water level will gradually decrease. The make-up water tank has built-in high and low level sensors. When the water level drops to the low level, the make-up water solenoid valve automatically opens, admitting softened water or municipal water for make-up. When the water level rises to the high level, the solenoid valve automatically closes, maintaining system water balance.
Under normal operating conditions, the daily make-up water volume is approximately 1%-3% of the circulating water volume, varying with ambient temperature, humidity, and load rate. The system has an ultra-low level alarm. When a make-up failure causes the water level to continue dropping, an alarm is triggered and the pump automatically stops to prevent dry-running damage to the pump.
4.3 Intelligent Temperature Control Principle
The monitoring system collects real-time temperature data through supply/return water temperature sensors and in-cabinet temperature sensors. Using a PID closed-loop control algorithm, it dynamically adjusts the system cooling output to achieve precise temperature control:
- When the temperature inside the cabinet rises, the controller outputs a signal to increase pump speed, increasing circulating water flow, while simultaneously increasing the external cold source fan speed to lower the return water temperature and enhance heat dissipation capability.
- When the temperature inside the cabinet drops and load is low, pump and fan speeds are reduced to decrease system energy consumption, achieving energy-efficient operation.
- In winter or low-temperature environments, when the natural cold source alone can meet heat dissipation requirements, compression refrigeration can be shut off, relying solely on dry cooler or cooling tower natural cooling to maximize energy savings.
- The system can be set with temperature thresholds. When temperature exceeds the alarm threshold, an audible/visual alarm is triggered. When it exceeds the shutdown threshold, IT equipment frequency reduction or shutdown protection is automatically triggered to prevent equipment damage from overheating.
4.4 Safety Protection Principle
The system is equipped with multiple safety protection mechanisms to ensure operational safety:
- Pressure Protection: When system pressure exceeds the safety valve setpoint, the safety valve automatically opens to relieve pressure, preventing pipe rupture. When pressure is too low, an alarm is triggered, indicating a pipe leak.
- Flow Protection: When the flow sensor detects water flow below the set threshold, an alarm is triggered and the standby pump is automatically started. If flow still does not recover, the emergency air-cooling is activated and an alarm is raised.
- Leak Protection: When the leak sensor detects water leakage, an immediate audible/visual alarm is raised while the inlet solenoid valve and corresponding branch circuit valves are automatically closed. In the event of severe leakage, the pump can be stopped and the system shut down to prevent leak spread.
- Electrical Protection: The power distribution system has overload, short-circuit, leakage, undervoltage, and overvoltage protection. In the event of a fault, the corresponding circuit power is automatically cut off to prevent electrical accidents.
- Freeze Protection: In low-temperature environments, when the water temperature falls below the freeze protection threshold, the pump automatically starts low-speed circulation or electric heating is activated to prevent pipe freezing.
4.5 Comparison Between Open and Closed Systems
| Comparison Dimension | Open Water-Cooled Integrated Cabinet | Closed Water-Cooled Integrated Cabinet |
|---|---|---|
| System Structure | Simple structure, fewer components, high integration | Complex structure, includes plate heat exchanger, expansion tank, etc., more components |
| Construction Cost | Low, 20%-30% lower than closed systems | High, pressure-bearing components and sealing requirements are demanding |
| Heat Exchange Efficiency | High, direct evaporative heat exchange, low outlet water temperature | Slightly lower, secondary heat exchange introduces thermal resistance |
| Water Quality Requirement | Higher, contact with air makes scaling and biological growth more likely | Lower, closed system maintains stable water quality |
| Maintenance Difficulty | Medium, requires periodic water treatment and make-up | Lower, closed system has longer maintenance intervals |
| Applicable Scenarios | Medium/small data centers, edge nodes, budget-constrained projects | Large data centers, high-reliability scenarios |
| System Pressure | Low, primarily pump head | High, system pressure rating 0.6-1.0MPa |
Chapter 5 Product Technical Parameters
5.1 General Cabinet Parameters
| Parameter Item | Technical Specification | Remarks |
|---|---|---|
| Cabinet height | 42U/47U/52U optional | Standard 19-inch mounting space |
| Cabinet width | 600mm/800mm optional | 800mm width for high-power models |
| Cabinet depth | 1000mm/1200mm/1400mm optional | 1200mm is the standard model |
| Overall load capacity | Static ≥1500kg, dynamic ≥1000kg | High load-bearing version available up to 2000kg |
| Protection rating | IP20 | Indoor use type |
| Operating ambient temperature | 5℃-40℃ | Storage temperature -20℃-60℃ |
| Operating ambient humidity | 20%-80%RH, non-condensing | |
| Altitude | ≤2000m | Derating required above 2000m |
| Noise level | ≤55dB(A) | Measured at 1m distance from cabinet |
| Design service life | ≥15 years | Under normal maintenance conditions |
| Enclosure material | High-quality cold-rolled steel plate, electrostatic powder coating | Color options: RAL7035, RAL9004 |
5.2 Water Cooling System Parameters
5.2.1 Parameters for Different Power Models
| Model | Rated Cooling Capacity | Circulating Water Flow | Pump Power | Supply/Return Water ΔT | Rated Supply Water Temperature |
|---|---|---|---|---|---|
| LA-SW-10kW | 10kW | 2m³/h | 0.37kW | 5℃ | 18-22℃ |
| LA-SW-20kW | 20kW | 3.5m³/h | 0.55kW | 5℃ | 18-22℃ |
| LA-SW-30kW | 30kW | 5m³/h | 0.75kW | 5℃ | 18-22℃ |
| LA-SW-50kW | 50kW | 8.6m³/h | 1.5kW | 5℃ | 18-22℃ |
| LA-SW-80kW | 80kW | 13.8m³/h | 2.2kW | 5℃ | 18-22℃ |
| LA-SW-120kW | 120kW | 20.6m³/h | 4kW | 5℃ | 18-22℃ |
5.2.2 Detailed Water Circuit System Parameters
- System Type: Open circulation system
- Heat Exchange Form: Air-liquid heat exchange + optional cold plate heat exchange
- Pump Type: Stainless steel centrifugal pump, one active one standby redundancy
- Pump Variable Frequency Range: 0-100% stepless speed regulation
- System Design Pressure: 0.3MPa
- Safety Valve Opening Pressure: 0.25MPa
- Pipe Material: 304 stainless steel pipe / PPR steady-state pipe
- Connection Specifications: DN20-DN100 flange/threaded connection, quick couplings optional
- Filter Accuracy: 80 mesh Y-type filter + 40 mesh precision filter
- Make-up Water Tank Volume: 50L/100L/200L/500L optional
- Make-up Water Pressure: 0.1-0.4MPa
- Water Quality Requirements:
- Resistivity: ≥0.5MΩ·cm
- pH value: 7.0-9.0
- Hardness: ≤100mg/L (as CaCO₃)
- Turbidity: ≤5NTU
- Chloride ion content: ≤100mg/L
5.3 Power Supply and Distribution System Parameters
| Parameter Item | Technical Specification | Remarks |
|---|---|---|
| Rated input voltage | 380V/220V AC, three-phase five-wire | 220V single-phase available as custom |
| Rated frequency | 50Hz | 60Hz available as custom |
| Voltage fluctuation range | ±15% | |
| Input current range | 63A-400A | Matched based on power rating |
| Insulation resistance | ≥1MΩ | Tested with 500V megohmmeter |
| Power frequency withstand voltage | 2000V/1min, no breakdown or flashover | |
| Grounding resistance | ≤4Ω | |
| PDU output specifications | GB standard 10A/16A, IEC C13/C19 | Custom combinations available |
| Surge protection level | Class C power surge protection | Response time ≤25ns |
| Metering accuracy | Voltage/current ±0.5%, energy ±1% |
5.4 Monitoring System Parameters
- Controller: Industrial-grade PLC, 32-bit processor, memory 128M
- Display: 7-inch color resistive/capacitive touchscreen, resolution 800×480
- Temperature Measurement Range: -20℃-100℃, accuracy ±0.1℃
- Pressure Measurement Range: 0-1.6MPa, accuracy ±0.5%FS
- Flow Measurement Range: 0-30m³/h, accuracy ±1%FS
- Leak Detection Accuracy: ±1cm, response time ≤1s
- Data Storage: Local storage of ≥1 year of historical data
- Communication Interfaces: RS485 ×2, Ethernet ×1
- Supported Protocols: Modbus-RTU, Modbus-TCP, SNMP, BACnet
- Alarm Methods: Local audible/visual alarm, SMS alarm, email alarm
- Power Supply: 24V DC
5.5 Performance Parameters
- Maximum IT Load Supported per Cabinet: 120kW
- Temperature Uniformity Inside Cabinet: ≤±2℃
- Temperature Control Accuracy: ±1℃
- System COP: ≥4.0 (at rated conditions)
- Supporting Data Center PUE: ≤1.15 (when using natural cold source)
- Leak Detection Response Time: ≤1s
- Pump Fault Switching Time: ≤2s
- Emergency Air-Cooling Start-up Time: ≤5s
Chapter 6 Product Functions and Features
6.1 Core Heat Dissipation Functions
6.1.1 Ultra-High Density Heat Dissipation Capability
Using water-cooling heat dissipation technology, heat exchange efficiency is 3-5 times that of traditional air cooling. A single cabinet can support a maximum power density of up to 120kW, easily handling the heat dissipation needs of high-power equipment such as AI servers and GPU computing clusters. It solves the localized hot spot problems that traditional air cooling cannot address, ensuring stable equipment operation under high load.
6.1.2 Precise Temperature Control
Using a PID intelligent temperature control algorithm combined with variable frequency pumps and variable frequency fans, the cooling output is dynamically adjusted based on IT load. Temperature control accuracy inside the cabinet can reach ±1℃, avoiding the impact of temperature fluctuations on equipment lifespan and providing a stable operating environment for IT equipment.
6.1.3 Dual Heat Dissipation Backup
A dual heat dissipation architecture with water cooling as the primary method and air cooling as backup. When the water-cooling system fails, the emergency air-cooling system can automatically start within 5 seconds to maintain basic equipment heat dissipation, buying sufficient time for fault diagnosis and repair, preventing equipment shutdown from overheating, and improving system reliability.
6.2 Energy Saving Features
6.2.1 Significant Reduction in Cooling Energy Consumption
The water-cooling system has high heat exchange efficiency, and the energy consumption for delivering the same cooling capacity is far lower than that of air-cooling systems. At the same time, natural cold sources can be fully utilized, achieving free cooling in spring, autumn, and winter, significantly reducing the operating time of compression refrigeration. The overall data center PUE can be reduced to below 1.15, saving more than 30% of energy compared with traditional air-cooled data centers.
6.2.2 Variable Frequency Intelligent Energy Saving
Pumps and fans both use variable frequency drives, dynamically adjusting output power based on actual load requirements to avoid ineffective energy consumption from full-load operation. The system can automatically adjust operating modes based on outdoor temperature, maximizing the use of natural cold sources and achieving optimal energy efficiency under all operating conditions.
6.2.3 Low Noise Operation
The water-cooling system has no high-speed cooling fans. Internal cabinet noise mainly comes from the low-speed circulating water pump, with operating noise ≤55dB(A), far lower than the 70dB-plus noise level of air-cooled cabinets at the same power rating. This improves the data center operations environment and is suitable for scenarios with noise requirements such as office data centers and edge sites.
6.3 High Reliability Design
6.3.1 Core Component Redundancy
Pumps adopt a one-active-one-standby redundant design. When the primary pump fails, the standby pump automatically switches over seamlessly without affecting cooling operation. The power distribution system offers optional dual-input automatic switching. The monitoring system has a watchdog function with automatic restart on system hang, providing all-around protection for continuous system operation.
6.3.2 Multiple Safety Protections
The system has more than ten safety protection mechanisms including pressure protection, flow protection, temperature protection, liquid level protection, leak protection, electrical protection, and freeze protection, covering all risk points across water circuits, electrical circuits, and equipment. In the event of a fault, protection actions are automatically executed to prevent fault escalation and ensure equipment and data safety.
6.3.3 High-Quality Component Selection
Core components are selected from well-known domestic and international brands. Pumps are selected from brands such as Nanfang Pump Industry and Grundfos. Electrical components are selected from brands such as Schneider and CHINT. Sensors use imported brand chips. Product quality and reliability are ensured at the source, reducing fault probability.
6.4 Convenient Operation and Maintenance Features
6.4.1 Integrated Design
The cabinet, water-cooling, power distribution, and monitoring systems are all factory prefabricated and integrated. Individual testing is completed before shipment. Installation on site only requires connecting the inlet/outlet water pipes and power cables. This significantly reduces on-site construction work, shortens installation time, and reduces construction difficulty and quality risks.
6.4.2 Standardized Quick-Connect Design
Piping uses standardized self-sealing quick couplings. Connection and disconnection require no tools, and no water leaks during connection/disconnection. Equipment replacement and maintenance are convenient. Core components adopt modular design, supporting rapid replacement without requiring professional tools, reducing the technical requirements for operations and maintenance personnel.
6.4.3 Intelligent Fault Diagnosis
The monitoring system has fault self-diagnosis function, automatically locating the fault position and fault cause, displaying fault codes and handling recommendations on the screen, while pushing alarm information to operations and maintenance personnel. This significantly reduces fault diagnosis time and improves operational efficiency.
6.4.4 Remote Operation and Maintenance Management
Supports Web and mobile remote access. Operations and maintenance personnel can view system operating status, historical data, and alarm information without visiting the site. Remote operations such as parameter adjustment and firmware upgrades can be performed, enabling unattended operation and reducing labor costs.
6.5 Flexible Adaptation Features
6.5.1 Multi-Scenario Adaptation
Compatible with multiple water-cooling heat exchange forms including cold plate type, air-liquid type, and spray type. Compatible with X86 servers, ARM servers, AI accelerator cards, switches, storage devices, and various other IT equipment, meeting heat dissipation needs of different business scenarios.
6.5.2 Flexible Deployment Methods
Supports multiple deployment methods including single-cabinet standalone deployment, multi-cabinet grouping, and container data center integrated deployment. Suitable for both overall planning of new data centers and local high-density area retrofits of existing data centers, without requiring large-scale modifications to the entire data center.
6.5.3 Customized Expansion
Supports multi-dimensional customization of cabinet dimensions, power ratings, interface specifications, power distribution solutions, and monitoring functions. Can be flexibly adjusted based on customer site conditions and business needs to meet personalized project requirements.
6.6 Green and Environmental Features
6.6.1 Low Carbon and Emission Reduction
Significantly reduces data center cooling energy consumption and carbon emissions, in compliance with the dual carbon policy requirements. Helps customers achieve green data center construction goals and meet PUE indicator assessment requirements.
6.6.2 Water-Saving Design
Optional dry cooler indirect heat exchange solution significantly reduces water evaporation losses, saving more than 70% of water compared with traditional cooling towers. Suitable for areas with water scarcity.
6.6.3 Environmentally Friendly Materials
All materials used in the product, including steel and plastics, comply with RoHS environmental standards. The production process uses environmentally friendly powder coating technology with no hazardous substance emissions. Products can be recycled and reused after disposal.
The KITOZER open-loop water-cooled integrated cabinet, leveraging its advantages of efficient heat dissipation, energy savings, low consumption, and flexible deployment, is widely applied in various high power-density computing scenarios. Core application scenarios are as follows:
7.1 AI Computing Power Data Centers
With the explosive growth of large model training and inference services, the power consumption of a single AI server generally reaches 1–5 kW, and per-cabinet power density can reach 50–100 kW. Traditional air cooling is completely unable to meet heat dissipation requirements. The open-loop water-cooled integrated cabinet can provide direct cold-plate-level heat dissipation for AI GPU servers, efficiently removing the massive heat generated by GPUs under high-load operation, ensuring the stable and full-load operation of the computing cluster, while significantly reducing cooling energy consumption and lowering AI computing operating costs.
Typical applications: Artificial intelligence computing centers, large model training bases, intelligent computing centers, AI inference data centers.
7.2 High-Performance Computing (HPC) Centers
High-performance computing clusters are widely used in scientific research institutes, meteorological forecasting, aerospace, automotive R&D, gene sequencing, and other fields. They feature high computing node density, high power consumption, and long operating times, requiring extremely high heat dissipation reliability. The high heat dissipation capability and high-reliability design of the open-loop water-cooled integrated cabinet can meet the heat dissipation needs of HPC clusters operating at full load for extended periods, while precise temperature control improves computational stability and extends equipment service life.
Typical applications: National supercomputing centers, university high-performance computing platforms, enterprise R&D simulation platforms, meteorological forecasting computing centers.
7.3 Cloud Computing and IDC Data Centers
Traditional IDC data center cabinets generally have a power of 5–10 kW per cabinet, which cannot meet the hosting requirements of high-power servers. By deploying open-loop water-cooled integrated cabinets, cabinet power density can be rapidly increased, creating high-density hosting zones, meeting the high-power computing hosting needs of premium customers, and enhancing the output value per unit area and competitiveness of the data center. Additionally, the open-loop system has low retrofit costs and short implementation cycles, making it very suitable for upgrading existing IDC data centers.
Typical applications: Third-party IDC data centers, telecom operator data centers, enterprise private cloud data centers.
7.4 Edge Computing Nodes
Edge computing sites are deployed close to the user side and often have limited space, incomplete supporting facilities, and poor maintenance conditions, requiring high integration, reliability, and maintainability of equipment. The open-loop water-cooled integrated cabinet features an integrated design, with a complete water cooling, power distribution, and monitoring system built in. It requires no dedicated data center air conditioning and can be directly deployed in ordinary indoor environments, enabling rapid deployment of edge computing power nodes, while its low-noise and easy-maintenance characteristics suit the operating conditions of edge sites.
Typical applications: 5G edge data centers, industrial edge computing stations, smart city edge nodes, campus computing power centers.
7.5 Industrial Control Equipment Rooms
Industrial control equipment rooms in manufacturing, mining, electric power, chemical, and other industries often have higher ambient temperatures and significant dust content. Traditional air-cooled cabinets tend to accumulate dust, have poor heat dissipation, and suffer from high equipment failure rates. The open-loop water-cooled integrated cabinet uses a closed water-cooling circulation with internal air recirculation within the cabinet, effectively isolating external dust, while its strong heat dissipation capability enables stable operation in high-temperature environments, making it suitable for harsh industrial environments.
Typical applications: Factory industrial control rooms, mining dispatch rooms, power substation equipment rooms, chemical process control rooms.
7.6 Modular and Container Data Centers
Modular data centers and container data centers pursue rapid deployment and plug-and-play operation. The open-loop water-cooled integrated cabinet, as a standardized computing power unit, can be directly integrated into modular equipment rooms and containers, with factory prefabrication and on-site assembly, significantly shortening construction cycles. Additionally, the water-cooling heat dissipation solution is more compact than air-cooling solutions, offering higher space utilization.
Typical applications: Container data centers, prefabricated modular equipment rooms, emergency mobile computing power centers, temporary computing power deployment.
7.7 Financial and Government/Enterprise Data Centers
Data centers in the banking, government, and central state-owned enterprise sectors have high requirements for reliability, security, and energy consumption indicators. The multiple redundant designs, high-security protection, and low PUE of the open-loop water-cooled integrated cabinet meet the high standards of these customers, while its low-noise characteristics improve the environmental experience of office equipment rooms.
Typical applications: Bank data centers, securities trading rooms, government cloud data centers, central SOE headquarters equipment rooms.
7.8 Special Scenario Applications
High-density storage rooms: High-density storage equipment generates significant heat and is temperature-sensitive. Water cooling provides a stable low-temperature environment, reducing disk failure rates and extending storage media service life.
Telecommunications core equipment rooms: As the power density of 5G core network equipment and transmission equipment increases, the water-cooling solution can resolve localized overheating issues in equipment rooms, improving telecommunications network reliability.
University and research laboratories: The heat dissipation requirements of computing clusters and experimental equipment in university laboratories are diverse. The water-cooling cabinet offers flexible adaptation, while its low noise does not affect the laboratory environment.
8.1 Pre-Installation Preparation
8.1.1 Technical Preparation
Organize installation technical personnel to become familiar with this manual, product drawings, design plans, and other technical documents, and clarify installation requirements, process flow, and quality standards.
Conduct on-site technical disclosure, confirming the installation location, piping routing, power incoming line position, grounding system, and other key information, and verify that on-site conditions are consistent with the design plan.
Prepare an installation construction plan, clarifying personnel assignments, schedule, safety measures, and emergency response plans, to ensure the installation work proceeds in an orderly manner.
8.1.2 Site Preparation
The installation site must be clean, dry, free from corrosive gases, and free from strong electromagnetic interference, and located away from flammable and explosive materials.
The floor must be level and solid, and the floor load-bearing capacity must meet the full-load weight requirements of the cabinet. If the floor load-bearing capacity is insufficient, reinforcement must be carried out in advance. Specific load-bearing requirements: 30 kW model ≥ 1000 kg/m², 120 kW model ≥ 2000 kg/m².
Adequate maintenance space must be reserved at the cabinet installation location: front ≥ 1000 mm, rear ≥ 800 mm, side ≥ 600 mm, and top ≥ 500 mm reserved for piping and cable routing.
The equipment room must be equipped with a qualified grounding system, with grounding resistance ≤ 4 Ω and clearly identified grounding terminal positions.
On-site power supplies must be routed and in place, with power capacity and voltage levels meeting equipment requirements, and stable power supply.
The chilled water supply and return piping must be routed to near the cabinet, with matching interface specifications, and supply water pressure and temperature meeting design requirements.
8.1.3 Tools and Materials Preparation
Prepare installation tools and test instruments according to the tool list in Chapter 3, ensuring tools are in good condition and measuring instruments are within their calibration validity period.
Prepare auxiliary installation materials, including expansion bolts, sealing tape, thread seal tape, cable ties, wire number sleeves, insulating tape, and anti-rust paint.
Check delivered equipment and accessories, verifying correct models, correct quantities, and intact appearance, and prepare for installation.
8.1.4 Safety Preparation
Construction personnel must wear safety helmets, insulating gloves, protective shoes, and other personal protective equipment. Safety belts must be worn when working at heights.
On-site construction power usage must comply with safety regulations. Temporary power supply must be equipped with residual current circuit breakers, and unauthorized wiring is prohibited.
Develop a dedicated plan for moving large items to prevent equipment damage due to impact and personnel injury.
Fire-fighting equipment must be available on site, and fire prevention measures must be implemented.
8.2 Unpacking and Equipment Positioning
8.2.1 Unpacking Inspection
After the equipment is transported to the site, place it near the installation location and unpack it on a level, solid floor.
Use dedicated tools for unpacking. Avoid violent hammering to prevent damage to internal components.
Check the main unit, accessories, attachments, and technical documents one by one against the packing list, and inspect the appearance for transportation damage, moisture, or water ingress.
Complete an unpacking acceptance record with signatures from both parties. If there is any damage or missing parts, contact the manufacturer promptly for handling.
8.2.2 Equipment Handling and Positioning
Cabinet handling can be performed using a forklift or manual labor. When using a forklift, insert the forks into the base of the cabinet bottom, and lift smoothly. Tilting more than 15° is prohibited.
For manual handling, multiple personnel should cooperate, with the lifting points on the main load-bearing beams of the cabinet frame. Pulling door panels, side panels, or other weak components is prohibited.
Move the cabinet to the predetermined installation position, and make preliminary position adjustments to ensure the clearances from other cabinets and walls meet requirements.
8.2.3 Leveling Calibration and Securing
Place a level on the top frame of the cabinet and adjust the adjustable support feet at the cabinet bottom so that the cabinet levelness deviation is ≤ 1 mm/m and verticality deviation is ≤ 1.5 mm/m.
When installing multiple cabinets side by side, first adjust the levelness and verticality of the first cabinet, then install adjacent cabinets in sequence, connecting and securing them with cabinet-joining connectors to ensure neat cabinet alignment and uniform gaps.
After the cabinet is adjusted into position, secure the cabinet base to the floor using expansion bolts, with no fewer than 4 fixing points, to ensure the cabinet will not shift or tip over.
For scenarios with high seismic requirements, the cabinet top must also be secured to the equipment room ceiling steel beams or seismic bracing, meeting seismic fortification requirements.
8.3 Water System Installation
8.3.1 General Requirements for Piping Installation
Before piping installation, check the specifications, material, and quality of pipe materials and fittings to ensure they meet design requirements, and that pipe inner walls are clean, free from debris, corrosion, and cracks.
Piping routing must be carried out according to the design drawings, running horizontally and vertically, neatly arranged, firmly secured, avoiding crossings, and reserving thermal expansion allowance.
Pipe connections must be secure and reliably sealed without leakage, and connection processes must comply with the corresponding pipe material construction specifications.
Dust protection must be implemented during piping installation, with open ends temporarily plugged to prevent debris from entering the pipes.
Pipe support spacing must comply with code requirements: for stainless steel pipes, horizontal support spacing ≤ 1.5 m and vertical support spacing ≤ 2 m.
8.3.2 Main Piping Installation
Route the cabinet supply and return water pipes from the data center chilled water main pipes, along the floor or suspended ceiling, to the cabinet location.
304 stainless steel piping should be welded by argon arc welding. Welds must be full and uniform, free from porosity, cracks, slag inclusions, and other defects. After welding, remove welding slag and perform passivation treatment.
PPR piping should be joined by thermal fusion, with fusion temperature and time in accordance with pipe material process requirements. After joining, allow natural cooling. Forced correction is prohibited.
Install a drain valve at the lowest point of the piping system and an automatic air vent at the highest point to ensure smooth system venting and drainage.
The supply and return water pipes should be labeled to indicate water flow direction and medium name, and the pipe surfaces should be insulated to prevent condensation and cooling capacity loss.
8.3.3 Cabinet Internal Piping Connections
Check the cabinet internal prefabricated piping for looseness or damage, and check the sealing surfaces of interfaces for scratches or contaminants.
Connect the external supply and return water pipes to the reserved cabinet interfaces, adding sealing gaskets or using thread seal tape at the interfaces, and tighten with a torque wrench to the specified torque. Forced over-tightening is prohibited.
Connect the water distributor/header to each heat exchange branch piping, and adjust branch valves to the fully open position.
Install the makeup water piping, connecting the makeup water interface to the data center softened water system, and install a filter and valve.
Connect the drain piping, routing the drain valve and overflow valve outlets to the data center floor drain or drainage system.
8.3.4 Cold Plate and Branch Piping Installation
Server cold plate installation must be performed with the server powered off. First remove the server’s original heat sink.
Clean the CPU and GPU surfaces, and apply thermal grease evenly or attach thermal pads with appropriate thickness, free from air bubbles and contaminants.
Align the cold plate with the mounting holes and tighten the mounting screws evenly to ensure the cold plate is in close contact with the heat-generating components with uniform pressure.
Use flexible hoses to connect the cold plates to the cabinet water distributor/header. The hose bending radius must be ≥ 5 times the hose diameter, avoiding sharp bends.
When connecting quick couplings, align the interface and insert smoothly. A “click” sound indicates proper connection. Gently pull to confirm it will not detach.
8.3.5 Hydrostatic Pressure Test and Piping Flushing
After piping installation is complete, perform a hydrostatic pressure test. The test pressure is 1.5 times the system working pressure, and not less than 0.3 MPa.
Pressurization should be carried out slowly. After reaching the test pressure, maintain the pressure for 12 hours. A pressure drop of ≤ 0.03 MPa is considered acceptable. At the same time, check all interfaces and welds for leakage and deformation.
After the hydrostatic pressure test passes, perform piping flushing using clean softened water at a flow velocity of not less than 1.5 m/s for circulating flushing, until the water quality at the outlet is consistent with the inlet and free from impurities and turbidity, which is considered qualified.
During flushing, the filter blowdown valve may be opened periodically for blowdown. After flushing is complete, clean the filter screens.
8.4 Electrical System Installation
8.4.1 Power Distribution Wiring Installation
Route the incoming power cable through the cable entry hole at the cabinet bottom or top, and install cable grommets at the entry holes to prevent cable wear.
Connect the main power cable to the incoming terminals of the cabinet main input circuit breaker. Verify the phase sequence L1, L2, L3, N, PE, ensure correct phase sequence and secure connections, with tightening torque in accordance with code requirements.
Cable cross-sections must meet rated current-carrying capacity requirements. Stranded copper wires must be terminated with crimp terminals. Direct twisted connections are prohibited.
Internal cabinet power distribution wiring should be routed along the cable management panel. Power and signal cables must be routed separately with spacing ≥ 50 mm. Cables must be neatly bundled and clearly labeled.
Install the PDU on the cabinet mounting rail at a suitable height for convenient equipment plug-in. Connect the PDU input cable to the output terminals of the corresponding branch circuit breaker.
8.4.2 Grounding System Installation
Connect the cabinet grounding copper busbar to the data center grounding busbar using a multi-strand copper cable with cross-section ≥ 16 mm², ensuring a secure and reliable connection.
All metal components inside the cabinet, equipment enclosures, and electrical mounting plates must be reliably grounded. Grounding connection points must be free from rust and paint, ensuring good conductivity.
Metal water pipes must be bonded (equipotential connection) and connected to the cabinet grounding system to prevent static electricity accumulation.
After installation, use a ground resistance tester to measure the system grounding resistance. It must be ≤ 4 Ω. If it does not meet the requirement, corrective action must be taken.
8.4.3 Insulation Test
After electrical installation is complete, disconnect all loads, open the circuit breakers, and use a 500 V megohmmeter to test the insulation resistance between phases and between phase and ground.
The main circuit insulation resistance must be ≥ 1 MΩ, and the secondary control circuit insulation resistance must be ≥ 0.5 MΩ to be qualified.
If the insulation test fails, troubleshoot section by section to identify the cause, and only proceed to the next step after the fault is eliminated.
8.5 Monitoring and Sensor Installation
8.5.1 Sensor Installation
Temperature sensors: Pipe-type temperature sensors are installed on the main supply and return water pipes, inserted into the pipe interior with good sealing and no water leakage; in-cabinet temperature sensors are suspended at the cabinet air inlet and outlet, avoiding direct sunlight and direct contact with equipment.
Pressure sensors: Install vertically on straight sections of piping, with straight pipe length before and after of ≥ 5 times the pipe diameter, to avoid eddy currents affecting measurement accuracy. Sealing at the interface must be leak-free.
Flow sensors: Install on horizontal straight pipe sections, with straight pipe length meeting the requirements of 10D upstream and 5D downstream (D is the pipe diameter). The fluid direction must match the marked direction.
Leak detection cable: Route along the weir at the cabinet bottom, avoiding sharp edges and corners, securely fixed, with waterproofing at joints. The controller is installed in a position convenient for observation.
Level sensors: Install vertically in the makeup water tank, securely fixed, with smooth liquid level float movement and no sticking.
8.5.2 Communication Wiring Installation
Sensor signal wires should use shielded twisted pair cables, with single-ended grounding of the shield layer to avoid electromagnetic interference.
Communication cables and power cables must be routed separately. Running them in the same conduit or trough is prohibited. When crossing, they should cross at right angles to reduce interference.
Connect network cables and RS485 buses to the corresponding interfaces on the monitoring controller, with correct wire sequence and secure connections.
If integration with the data center dynamic environment monitoring system (DCIM/environmental monitoring system) is required, connect through a communication gateway, configure the corresponding communication parameters, and ensure normal data upload.
8.5.3 Human-Machine Interface (HMI) Unit Installation
Mount the touchscreen display at the reserved position on the cabinet front door, securely fixed with neat wiring.
Install the audible and visual alarm (sound and light annunciator) on top of the cabinet, ensuring the alarm sound and light are clearly visible.
After installation, power on and check that the display operates normally and the touchscreen responds sensitively.
8.6 Auxiliary Component Installation
Shelf and cable management installation: Install corresponding shelves and cable management panels according to the IT equipment installation plan, horizontally and securely, at accurate positions.
Emergency air-cooling module check: Check that the emergency fan is securely fixed, wiring is correct, and manually rotate the fan blades to ensure no sticking.
Lighting system installation: Debug the door switch so it operates normally — door opens, light turns on; door closes, light turns off — with sufficient illumination.
Door lock debugging: The front and rear door locks should open and close smoothly, latches should be properly seated, and anti-theft functions should operate normally.
8.7 Installation Quality Inspection
After installation is complete, perform a self-inspection of installation quality according to the following items. Only after all items pass can the commissioning phase begin:
Cabinet installation: Accurate position, levelness and verticality meeting requirements, securely fastened, no appearance damage.
Water system: Pipes neatly arranged, securely fixed, clearly labeled, hydrostatic pressure test passed, no leakage, insulation intact.
Electrical system: Wiring correct and secure, phase sequence correct, insulation resistance qualified, grounding reliable, labels clear.
Monitoring system: Sensors installed at correct positions, wiring secure, communication wiring connections normal.
Safety protection: All protective covers installed in place, rotating parts have protection, hazardous areas have warning signs.
Site cleanup: Installation debris cleaned up, equipment surfaces wiped clean, no clutter on site.
9.1 General Wiring Specifications
9.1.1 Wiring Safety Requirements
Wiring work must be performed by a certified electrician, strictly following electrical safety operating procedures, with power disconnected. Live wiring is strictly prohibited.
Before work begins, confirm that the power supply is disconnected, and hang a “Work in Progress – Do Not Close” warning sign. Arrange dedicated personnel to stand guard when necessary.
Use insulated tools and wear insulating gloves. Do not operate electrical equipment with wet hands.
After wiring is completed, carefully inspect to confirm that there are no short circuits, incorrect connections, or loose connections before powering on for testing.
9.1.2 Cable Selection Requirements
Power cables should be copper-core PVC insulated cables with a rated voltage of not less than 0.6/1 kV, with current-carrying capacity meeting the rated current requirements of the circuit, and with some margin reserved.
Control and signal cables should be shielded copper-core cables with a rated voltage of not less than 300/500 V, conductor size ≥ 0.75 mm². Analog signals should use twisted shielded cables.
Grounding cables should be yellow-green two-color multi-strand copper flexible wire, with cross-section meeting code requirements.
Cables must be free from damage, aging, and broken conductors, with good insulation performance.
9.1.3 Wiring Process Requirements
Cable stripping length should be moderate, just sufficient to fully insert into the terminal, without exposing excessive copper wire or clamping the insulation layer.
Multi-strand copper wires must be terminated with crimp terminals (cold-pressed terminals). Terminal specifications must match the wire size, with secure crimping and no loosening.
Terminal tightening torque must comply with standards: M3 terminals 0.5–0.6 N·m, M4 terminals 0.8–1.0 N·m, M5 terminals 1.2–1.5 N·m, M6 terminals 1.8–2.2 N·m, to prevent loosening or screw breakage.
No more than 2 wires per terminal. Wires of different sizes must not be connected to the same terminal.
All cable ends must be fitted with wire number sleeves. Wire numbers must be clear and accurate, consistent with the schematic diagram, for convenient maintenance.
Wiring should be neat and tidy, with power and signal wires separated, securely bundled, routed horizontally and vertically, without crossed or chaotic wiring.
Cables in moving parts should have sufficient allowance and use flexible cables to prevent breakage from frequent movement.
9.2 Main Power Circuit Wiring
9.2.1 Three-Phase Input Wiring
Confirm that the external input power supply is three-phase five-wire 380 V/220 V AC, with voltage fluctuation within the allowable range.
Connect the three-phase live wires L1, L2, L3 to the L1, L2, L3 terminals on the upper side of the main circuit breaker respectively, connect the neutral wire N to the N terminal, and connect the protective earth wire PE to the grounding terminal block.
Verify the phase sequence using a phase sequence meter to ensure correct phase sequence. Incorrect phase sequence will cause the water pump to reverse and heat dissipation failure.
Connect the lower side of the main circuit breaker to the surge protector input, energy meter, and each branch circuit breaker.
High-current terminals should be coated with conductive grease to reduce contact resistance and prevent overheating.
9.2.2 Water Pump Circuit Wiring
Connect the three-phase wires of the main pump and standby pump motors to the output terminals of the corresponding contactors. The motor housing grounding terminal must be reliably grounded.
For variable frequency drive (VFD) models, connect the pump motor to the VFD output terminals. Connection to the input terminals is strictly prohibited. Connect the VFD input to the main circuit power supply.
After motor wiring is complete, first perform a jog test to check the motor rotation direction. It must match the marked direction. If reversed, swap any two phases of the wiring.
Adjust the thermal relay setting value to the motor rated current value to achieve overload protection.
9.2.3 PDU Power Distribution Circuit Wiring
Each PDU corresponds to one branch circuit breaker. Connect the live wire and neutral wire to the circuit breaker output terminals and the neutral busbar respectively.
Connect the communication wire of the smart PDU to the monitoring controller communication interface, with the communication wire shield layer grounded.
Reliably connect the PDU grounding terminal to the cabinet grounding copper busbar.
After wiring is complete, test that each outlet is energized normally and the phase is correct.
9.2.4 Auxiliary Power Circuit Wiring
Connect the power supply for auxiliary equipment such as fans, solenoid valves, and lighting to the output terminals of the corresponding control circuit contactors.
For single-phase equipment, pay attention to the distinction between the neutral wire and the live wire. Reversed connections that cause equipment damage are prohibited.
Each auxiliary circuit should be protected by an independent circuit breaker.
9.3 Control Circuit Wiring
9.3.1 Controller Power Supply Wiring
The monitoring controller operating power supply is 24 V DC, supplied by a switching power supply. The switching power supply input is connected to 220 V AC power.
Connect the L and N terminals of the switching power supply to 220 V AC, and PE to ground. Connect the output +24 V and GND to the controller power terminals. Reverse connection of positive and negative poles is strictly prohibited.
Adjust the switching power supply output voltage to 24 V ± 0.5 V to ensure stable power supply.
9.3.2 Digital Input Wiring
For switch-type signals such as level switches, flow switches, leak alarms, and door magnetic switches, connect one end to the controller DI common terminal and the other end to the corresponding DI input terminal.
Passive contact signals can be directly connected. For active signals, pay attention to voltage level matching. High voltage intrusion that damages the controller is prohibited.
Connect the shield layer of shielded cables to the controller grounding terminal.
9.3.3 Analog Input Wiring
For 4–20 mA analog signals from temperature, pressure, and flow sensors, use two-wire wiring. The sensor +24 V power is supplied by the controller. Connect the signal output to the AI input terminal, with the negative terminal sharing a common ground.
Analog signal cables should use twisted shielded cables, shielded throughout, with single-point grounding, to avoid common-mode interference.
After wiring is complete, calibration can be performed using a standard signal source to ensure measurement accuracy.
9.3.4 Control Output Wiring
For loads such as contactors, solenoid valves, and indicator lights, connect one end to the power supply and the other end to the controller DO output terminal, controlling on/off through relay contacts.
Inductive loads must have a freewheeling diode or surge absorber connected in parallel to prevent back-EMF from damaging the controller contacts.
High-power loads should be switched through an intermediate relay. Directly connecting controller contacts to high-current loads is prohibited.
9.4 Communication and Grounding Wiring
9.4.1 RS485 Communication Wiring
The RS485 bus should use shielded twisted pair cable. Connect the A and B lines correspondingly. Reversal of positive and negative polarity is not permitted.
Install a 120 Ω terminal resistor at both ends of the bus. Intermediate nodes do not require terminal resistors, reducing signal reflection.
The shield layer should be grounded at one end, with grounding resistance ≤ 4 Ω. If the communication distance exceeds 1000 m, add a repeater.
Multiple devices should be connected in a daisy-chain (daisy chain/series). Star connections are prohibited to avoid communication faults.
9.4.2 Ethernet Wiring
Use standard Cat 5e or Cat 6 network cables, with the T568B wire sequence: orange-white, orange, green-white, blue, blue-white, green, brown-white, brown.
Crimp RJ45 connectors on both ends of the cable and test with a cable tester that all 8 conductors are continuous with no open circuits, short circuits, or crosstalk.
Connect to a switch or router, and configure the IP address, subnet mask, and gateway to ensure network connectivity.
9.4.3 Equipotential Grounding Wiring
The cabinet interior is equipped with a main grounding copper busbar. All grounding branches connect to the main busbar, using a single-point grounding method.
The cabinet frame, door panels, and side panels are connected to the grounding copper busbar through grounding jumper wires, with jumper wire cross-section ≥ 4 mm².
All electrical equipment metal enclosures, metal piping, and metal cable trays must be reliably grounded.
Series grounding in the grounding system is strictly prohibited. Each must be independently routed to the ground main.
The entire grounding system ultimately connects to the data center grounding grid at a single point, forming a complete equipotential system.
9.5 Wiring Inspection and Testing
9.5.1 Continuity Check
Against the electrical schematic diagram, check the wiring at both ends of each cable one by one to ensure wire numbers correspond, wiring is correct, and there are no incorrect or missed connections.
Open all circuit breakers and use a multimeter in continuity mode to test each circuit, confirming no short circuits or ground faults.
Test the operation of each switch contact to ensure reliable on/off operation.
9.5.2 Insulation Resistance Test
Main circuit: With all loads disconnected, use a 500 V megohmmeter to test phase-to-phase and phase-to-ground insulation resistance. ≥ 1 MΩ is qualified.
Control circuit: Test with a 500 V megohmmeter. Insulation resistance ≥ 0.5 MΩ is qualified.
During testing, disconnect low-voltage equipment and sensors to prevent high voltage from damaging electronic components.
9.5.3 Polarity and Phase Sequence Test
Before energizing DC circuits, use a multimeter to test the voltage polarity, confirming the positive and negative are correct, to prevent reverse connection from burning out equipment.
Test three-phase motor rotation direction with a jog test. If the rotation direction is wrong, swap two phases of the wiring.
Perform a phase sequence test on the three-phase power supply to ensure positive phase sequence.
9.5.4 Labeling
Apply identification labels to all circuits, indicating circuit name, number, and rated current.
Wire numbers at both ends of cables must be clear, with clear routing identification.
An electrical schematic diagram should be posted inside the distribution cabinet for convenient future maintenance and repair.
After equipment installation and wiring are complete and pass inspection, the commissioning phase begins. Commissioning is divided into five stages: pre-energization inspection, individual component commissioning, system no-load commissioning, system loaded commissioning, and performance optimization. Proceed strictly step by step according to the process. Bypassing stages is prohibited to ensure equipment and personnel safety.
10.1 Preparation Before Commissioning
Establish a commissioning team, clarify the team leader and responsibilities of each position. Commissioning personnel must be familiar with equipment principles, operating methods, and safety precautions.
Prepare commissioning tools and instruments, including multimeter, clamp meter, thermometer, pressure gauge, flow meter, water quality test kit, and record book.
Confirm that on-site water and electricity supply are normal, voltage, water pressure, and water quality meet requirements, and the grounding system is qualified.
Clean the commissioning site, evacuate unnecessary personnel, and set up safety warning signs.
Develop emergency response plans and prepare emergency tools and spare parts to address sudden faults.
10.2 Comprehensive Pre-Energization Inspection
10.2.1 Mechanical Structure Inspection
Check that the cabinet is securely fixed and all screws are tight.
Check the protective covers of rotating components such as water pumps and fans are intact. Manually rotate to verify smooth operation with no sticking or abnormal noise.
Check the status of all valves: main supply water valve and main return water valve open, air vent valves open, drain valves closed.
Check the makeup water tank for debris and verify the water level is within the normal range.
Check pipe supports for secure fastening, looseness, or deformation.
10.2.2 Water System Inspection
Confirm all pipe connections are correct, well-sealed, and free from signs of leakage.
Confirm all filters are installed in place with clean screens.
Confirm the setting values of safety valves and pressure relief valves are correct and operate flexibly.
Confirm the chilled water source system can supply water normally, with supply water temperature and pressure meeting requirements.
10.2.3 Electrical System Inspection
Confirm all circuit breakers are in the open position with no short circuit hazards.
Re-verify wiring correctness, focusing on power phase sequence, grounding connections, and control circuit wiring.
Confirm all electrical components are securely fixed and terminal connections are tight.
Confirm controller and sensor wiring are correct, with no risk of short circuits or reverse connections.
10.2.4 Monitoring System Inspection
Confirm the controller program has been flashed with default factory parameters.
Confirm all sensor wiring is correct, with measurement ranges and parameters matching.
Confirm alarm devices are installed in place and function normally.
10.3 Individual Component Commissioning
10.3.1 Power Distribution System Commissioning
Close the main input circuit breaker and measure the input voltage. Three-phase voltage should be balanced with deviation ≤ 2%, within rated voltage ±10%.
Close each branch circuit breaker in sequence and check that the corresponding circuit voltage is normal, with no tripping, abnormal noise, or odor.
Test the surge protector and residual current circuit breaker (RCD/residual current device) operation to verify normal, reliable protection functions.
Test the energy meter display, confirming voltage, current, and power data are accurate.
10.3.2 Water Pump Standalone Commissioning
Manually jog the water pump and observe the motor rotation direction. It must match the marked arrow direction. If reversed, swap the phase sequence.
Start the pump and run for 5 minutes. Check the pump operating sound for abnormal noise or excessive vibration.
Measure the pump operating current. It should be within the rated current range, with balanced three-phase current.
Test pump start/stop control, and verify manual/automatic switching functions operate normally.
Test the standby pump switching function. Simulate a main pump failure; the standby pump should start automatically within 2 seconds.
For VFD pumps, test the variable frequency adjustment function. Vary the frequency from low to high, and verify the pump speed changes smoothly, current changes accordingly, with no abnormalities.
10.3.3 Fan and Valve Commissioning
Start the emergency air-cooling fan, check correct rotation direction, normal airflow, stable operation with no abnormal noise.
Test the makeup water solenoid valve: energize to open, de-energize to close, with flexible action, no sticking, and no leakage after closing.
Test the electric regulating valve: smooth adjustment from 0–100% opening, with feedback signal consistent with valve opening.
Test all valve switching actions, verifying markings match actual status.
10.3.4 Monitoring System Standalone Commissioning
Power on the monitoring controller and check the display starts normally, without screen distortion or black screens.
Check displayed values of temperature, pressure, flow, level, and other sensors one by one, comparing to actual on-site values. Deviations should be within the accuracy range. Sensors with large deviations should be calibrated.
Test digital input signals by triggering level switches, leak sensors, etc. The controller should correctly display status changes.
Test control output functions by manually operating pump, fan, and solenoid valve start/stop. Corresponding equipment should respond correctly, with accurate status feedback.
Test the audible and visual alarm function by simulating faults. The alarm sound should be loud and the light flashing clearly visible.
Test communication functions by connecting to a computer or the dynamic environment monitoring system. Data upload should be normal with no packet loss or interruption.
10.4 System No-Load Commissioning
10.4.1 System Water Filling and Venting
Open the makeup water valve and slowly fill the system with water, while opening all high-point air vent valves for venting.
During filling, monitor the makeup water tank level, keeping the level stable. Close the air vent valves only after all vent valves discharge continuous water without air bubbles.
After the system is filled with water, start the pump at low speed for 10 minutes, repeatedly opening air vent valves to vent until all air in the system is completely expelled.
After venting is complete, adjust the system pressure to the normal working pressure, and maintain the makeup water tank level at the normal level.
10.4.2 Water Circulation Test
Start the main pump and run the system at full circulation for 2 hours.
Monitor system pressure, flow, and temperature throughout the process. Parameters should be stable with no significant fluctuations.
Check all pipes, joints, valves, and equipment for leakage. If leakage is found, stop the pump immediately for handling.
Check pump operating current, temperature, and vibration, all within normal ranges.
Test the flow adjustment function by adjusting branch valves. The corresponding branch flow should change accordingly, with sensitive adjustment.
Test the system pressure protection function by simulating overpressure. The safety valve should open normally for pressure relief.
10.4.3 Automatic Control Logic Commissioning
Set temperature control parameters: target temperature, alarm temperature, and shutdown temperature thresholds.
Simulate temperature changes to verify temperature control logic: as temperature rises, pump speed increases and fan speed increases; as temperature decreases, speeds decrease, consistent with PID regulation logic.
Test level control: simulate low level — the makeup water valve should open automatically for filling; reaching high level — automatically close; very low level — trigger alarm and stop the pump.
Test leak protection: simulate a leak — the system should immediately trigger the audible and visual alarm, automatically close the inlet valve, and for severe leaks, interlock pump shutdown.
Test fault switching logic: simulate faults such as main pump failure or low flow. The standby pump should automatically engage, and the emergency air cooling should start automatically.
Test interlocking control: interlock test with the external chilled water source system, automatically adjusting the chilled water source output based on return water temperature.
10.5 System Loaded Commissioning
10.5.1 Low-Load Commissioning
Turn on some IT equipment, at approximately 30% load rate, with the system in automatic operation.
Monitor cabinet inlet and outlet air temperatures and equipment surface temperatures. Temperatures should gradually stabilize within the set range.
Monitor supply/return water temperature, flow, and pressure. The system should automatically adjust operating status with stable parameters.
Check the cabinet interior for condensation. Humidity should be within the normal range.
Run continuously for 4 hours, recording all operating parameters. The system should operate stably with no alarms.
10.5.2 Half-Load Commissioning
Increase IT equipment load to 50% and continue operation.
Observe the system heat dissipation effect. The maximum temperature inside the cabinet must not exceed the equipment allowable value, with good temperature uniformity.
Monitor pump and fan operating frequencies, which should automatically increase as load rises, with operating current within the rated range.
Check pipes for leakage and equipment for abnormal vibration and noise.
Run continuously for 8 hours, recording parameter trends. The system should be stable and reliable.
10.5.3 Full-Load Commissioning
Turn on all IT equipment, with the load reaching 100% of rated power, and the system operating at full load.
Monitor temperatures at each point in the cabinet. The maximum temperature must not exceed the equipment operating limit, with no local hot spots.
Monitor system cooling capacity and supply/return water temperature differential, reaching rated design parameters.
Monitor pumps and fans operating at rated conditions, with normal current, vibration, and temperature.
Test the system’s ultimate heat dissipation capability. Even at the maximum ambient temperature, equipment normal operating temperatures must be maintained.
Run continuously at full load for 72 hours, recording operating parameters every 2 hours. No faults, no alarms, and stable performance qualify the loaded commissioning as passed.
10.6 Performance Optimization and Parameter Tuning
10.6.1 PID Parameter Tuning
Based on actual on-site load and environmental conditions, optimize PID control parameters by adjusting the proportional coefficient, integral time, and derivative time to make temperature control more stable, with smaller overshoot, faster response speed, and to avoid frequent start/stop and oscillation.
10.6.2 Flow Balance Commissioning
Adjust the flow regulating valves on each branch so that the flow of each branch meets design requirements, achieving uniform heat dissipation across all equipment, avoiding some equipment overheating while others overcool, and optimizing overall heat dissipation efficiency.
10.6.3 Energy Saving Optimization
Based on on-site load patterns, set time-based temperature control strategies. During nighttime low-load periods, appropriately raise the set temperature to reduce system energy consumption. Set up sleep mode — when the load is extremely low, operate a single pump at low speed to maximize energy savings.
10.6.4 Alarm Threshold Optimization
Based on actual on-site operating data, optimize alarm thresholds to both ensure safety and avoid false alarms, improving the operation and maintenance experience.
10.7 Commissioning Completion Work
After commissioning is complete, organize all commissioning records into a commissioning report, documenting the commissioning process, parameter settings, test results, existing issues, and rectification measures.
Save the final operating parameters to the controller and back up the parameter file.
Clean up the commissioning site, organizing tools and remaining materials.
Provide on-site operational training to the customer’s operations and maintenance personnel, covering daily operations, precautions, and basic fault handling.
Both parties sign to confirm the commissioning has passed, and the equipment enters the trial operation phase.
11.1 Installation Safety Precautions
Equipment installation must be performed by professionals in accordance with this manual. Unauthorized installation or modification by non-professionals is prohibited, as this may cause equipment damage and safety accidents, and will not be covered by the warranty.
During equipment handling and installation, avoid severe vibration, collision, and tilting. Turning the equipment upside down or placing it on its side is prohibited, to prevent internal component displacement and damage.
The installation site must meet load-bearing requirements. Installation on floors with insufficient load-bearing capacity is prohibited, to prevent collapse risk.
The water system must undergo a hydrostatic pressure test. Only after passing can it be put into operation. Operating with water without pressure testing is prohibited to avoid water leakage accidents.
Electrical installation must comply with national electrical safety codes. Grounding must be reliable. Operating without grounding is prohibited to prevent electric shock risk.
During installation operations, strictly comply with safety regulations for work at heights, hot work (welding/cutting), and electrical work, and implement safety protection measures.
11.2 Operating Precautions
Equipment operators must receive professional training and be familiar with equipment operating methods and safety precautions, strictly following operating procedures.
Before starting, check the water level, valve status, and power status. Only after confirming normal conditions can the equipment be started. Operating with existing faults is prohibited.
During system operation, unauthorized disassembly of pipes, valves, and electrical components is prohibited, and unauthorized modification of control parameters is prohibited.
If abnormal noise, vibration, odor, water leakage, or other abnormal conditions are found during operation, stop the equipment immediately for inspection. Only after the fault is eliminated can operation resume.
Frequent start/stop of the water pump is prohibited. The interval between start/stop operations must be no less than 5 minutes, to prevent motor overheating damage from frequent starting.
When the system is shut down for extended periods, drain the water from the piping, especially in winter low-temperature environments, to prevent pipe freezing and cracking.
When the equipment room ambient temperature is below 5°C or above 40°C, corresponding measures should be taken. Operation beyond environmental conditions is prohibited.
The ventilation openings at the front and rear of the cabinet must not be blocked. Maintain air circulation, and do not stack debris on the cabinet.
11.3 Water Quality Management Precautions
The open-loop system has high requirements for water quality. Softened water or deionized water meeting requirements must be used. Direct use of untreated tap water or well water is prohibited, to prevent scaling and corrosion.
Regularly test water quality indicators, including pH value, hardness, conductivity, and turbidity. Treat promptly when water quality exceeds standards.
Regularly add corrosion and scale inhibitors and biocides to maintain water quality stability and prevent scale, bacteria, and algae growth.
Regularly clean filters to prevent impurities from clogging pipes and heat exchangers.
Perform a system cleaning and water change at least once per year to keep the system interior clean.
Adding unidentified chemical agents to the system is prohibited, to prevent damage to pipes and components.
11.4 Maintenance and Repair Precautions
Maintenance and repair must be performed with the power off, water supply off, and pressure released, with warning signs posted to prevent accidental switching and accidental water opening.
Before disassembling pipe components, first drain the water from the corresponding pipe section, to prevent water spray from wetting electrical equipment.
During electrical maintenance, verify the absence of voltage, use insulated tools, and prevent electric shock.
Replacement parts must be original factory genuine parts. Using unqualified substitute parts is prohibited, as this may affect performance and safety.
When removing or installing cold plates, protect the cold plate surface from impact and deformation. When replacing thermal interface materials, apply evenly to ensure heat exchange performance.
When replacing seals, clean the sealing surfaces, select seal rings with matching specifications and materials, and install them properly to prevent seal failure and water leakage.
After maintenance is complete, conduct a comprehensive inspection to confirm everything is correct, then gradually restore water and power for trial operation. Normal operation can resume only after everything passes.
Maintenance work should be documented in records, including maintenance time, content, replaced parts, and operating status, forming an operation and maintenance archive.
11.5 Safety Protection Precautions
The safety protection devices equipped on the system should be regularly calibrated to ensure sensitivity and reliability. Unauthorized bypassing or removal of protection devices is prohibited.
The leak detection system should be regularly tested to ensure timely alarm upon water leakage. Disabling the leak alarm function is prohibited.
The equipment room should be equipped with appropriate fire-fighting equipment. Flammable and explosive materials must not be stacked near the equipment.
Placing any unspecified items inside the cabinet is prohibited, especially liquids, flammable materials, and metal debris.
In the event of a water leakage accident, immediately cut off the power supply and the inlet valve, and organize drainage and emergency repair, preventing water from contacting electrical equipment and causing short circuits or electric shock.
In the event of an electrical fire, first cut off the power supply, then use gas or dry powder fire extinguishers. Using water to extinguish electrical fires is prohibited.
11.6 Winter Freeze Protection Precautions
In regions where ambient temperature drops below 0°C in winter, the equipment room must be equipped with heating measures to ensure the ambient temperature is maintained above 5°C, preventing pipe freezing and cracking.
If the equipment is shut down for extended periods and the equipment room has no heating, all water in the system must be completely drained, including water in pipes, pumps, heat exchangers, and water tanks. If necessary, purge with compressed air.
For short-term shutdown, a low-temperature freeze protection mode can be set, with the pump circulating at low speed to keep water flowing and prevent freezing.
Outdoor pipes must be insulated and heat-traced, with electric heat tracing and insulation layers installed, to prevent freezing and blockage of outdoor pipes.
Before winter arrives, conduct a comprehensive system inspection and make freeze protection preparations to eliminate hidden hazards.
To ensure the long-term stable and reliable operation of the open-loop water-cooled integrated cabinet, extend equipment service life, and reduce failure probability, a comprehensive maintenance system must be established with regular preventive maintenance. This chapter specifies the content and standards for daily inspections, monthly maintenance, quarterly maintenance, and annual maintenance, as well as the process requirements for fault repair.
12.1 General Maintenance Principles
Equipment maintenance follows the principle of “prevention first, regular inspection, and equal emphasis on maintenance and repair.” Preventive maintenance enables timely detection and elimination of hidden hazards, reducing the occurrence of failures.
Maintenance work shall be performed by trained professional operations personnel, strictly following standard procedures, with maintenance records properly maintained.
Safety operating procedures shall be strictly observed during maintenance to ensure personnel and equipment safety.
Wear parts shall be replaced periodically, and necessary spare parts shall be stocked to ensure timely replacement in the event of failure.
Establish equipment operation and maintenance archives, recording in detail operation, maintenance, failure, and component replacement information to achieve full lifecycle management.
12.2 Daily Inspection (1 time per day)
Daily inspections are performed by equipment room operations personnel, focusing on equipment operating status and obvious abnormalities, as follows:
Overall Status Inspection
- Check the cabinet exterior for abnormalities; verify side panels and doors are intact; check for signs of water leakage.
- Listen for equipment operating sounds; check pumps and fans for abnormal noise or rattling; verify vibration is normal.
- Check for unusual odors, such as burning or musty smells.
Monitoring Parameter Inspection
- Check operating parameters displayed on the touchscreen, including supply/return water temperature, pressure, flow rate, in-cabinet temperature and humidity, and liquid level, to verify they are within normal ranges.
- Check for alarm messages and whether fault indicator lights are illuminated.
- Record key operating parameters to form an operation log.
Water System Inspection
- Check the makeup water tank level, ensuring it is within the normal scale range; investigate the water makeup system promptly if the level is too low.
- Check visible piping, joints, and valves for leakage or dripping.
- Check pump operating status for overheating or abnormal vibration.
Electrical System Inspection
- Check the distribution cabinet for abnormal sounds or odors; verify circuit breaker status is normal with no tripping.
- Check indicator lights and displays for normal operation.
Environmental Inspection
- Check the equipment room ambient temperature and humidity, ensuring they are within the allowable range for the equipment.
- Check the equipment room for water leakage or water accumulation hazards.
If abnormalities are found during daily inspection, they shall be handled promptly; if they cannot be resolved on-site, report immediately and contact manufacturer technical support.
12.3 Monthly Maintenance (1 time per month)
Monthly maintenance is performed by professional operations personnel, conducting more in-depth inspections and cleaning based on daily inspections, as follows:
12.3.1 Water System Maintenance
- Inspect the interior of the makeup water tank, removing debris and sediment to maintain water quality.
- Clean the Y-type filter screen; remove the screen and rinse with clean water; replace promptly if damaged.
- Check all valves for flexible operation without sticking; check valve stems for corrosion; apply anti-rust grease.
- Check pipe insulation for damage or detachment; repair promptly to prevent condensation.
- Check pipe supports and clamps for looseness; tighten promptly.
- Test the leak detection function by simulating a leak to confirm the alarm operates normally.
- Sample water quality to test pH value and conductivity; record data; treat abnormal water quality promptly.
12.3.2 Electrical System Maintenance
- Tighten all wiring terminals, with emphasis on high-current loop terminals, to prevent loosening and overheating.
- Clean dust from electrical components using dry compressed air; keep clean and dry.
- Check circuit breaker and contactor contacts for pitting; verify flexible and reliable operation.
- Check grounding connections for looseness; test ground resistance to ensure reliable grounding.
- Check surge protection device status; verify failure indicators operate normally; replace damaged units promptly.
- Test emergency lighting and alarm devices for proper function.
12.3.3 Equipment Body Maintenance
- Clean dust and stains from the inside and outside surfaces of the cabinet to maintain a neat appearance.
- Check door locks and hinges; apply lubricating oil; ensure flexible opening and closing.
- Clean debris from the cabinet base; keep dry and clean.
- Check cabinet sealing strips for aging or detachment; ensure proper sealing.
12.3.4 Monitoring System Maintenance
- Verify sensor data against on-site instruments; calibrate sensors with excessive deviation.
- Back up controller parameters and historical data.
- Check communication connections are normal and data upload is stable.
- Clean the display screen surface; ensure responsive operation without lag.
12.4 Quarterly Maintenance (1 time every 3 months)
Quarterly maintenance is intermediate-level maintenance involving in-depth inspection and servicing of core components, as follows:
12.4.1 Pump Maintenance
- Check pump seals for leakage; replace mechanical seals that leak beyond the drip standard.
- Check pump bearing temperature; during operation, bearing temperature should be ≤70°C; if temperature rise exceeds 40°C, inspect bearing lubrication.
- Test pump insulation resistance; motor winding insulation should be ≥5MΩ; perform drying treatment if damp.
- Check pump coupling elastomers for wear; verify proper alignment.
- For variable-frequency pumps, clean dust from the inverter cooling fan and heat sink to ensure proper heat dissipation.
12.4.2 Heat Exchanger Maintenance
- Check air-liquid heat exchanger fins for dust accumulation or deformation; blow clean with compressed air or rinse with clean water if heavily soiled to maintain heat exchange efficiency.
- Check heat exchanger piping for corrosion or leakage; handle any hazards found promptly.
- For cold plate heat exchange loops, check flow balance across branches; adjust branches with large flow deviations.
12.4.3 Water Treatment Maintenance
- Conduct comprehensive testing of system water quality, including hardness, turbidity, chloride ion content, total iron, and algae/bacterial content.
- Add water treatment chemicals based on water quality conditions to bring water quality within acceptable ranges.
- Check the electronic water conditioner for proper working status and function.
- If a chemical dosing device is installed, check the chemical tank level, replenish chemicals, and verify the dosing pump operates normally.
12.4.4 Safety Protection Verification
- Verify pressure switches and safety valves for accurate setpoints and reliable operation.
- Verify temperature, pressure, and flow sensor accuracy; calibrate or replace sensors out of tolerance.
- Test all protection functions, including over-temperature protection, low-pressure protection, overload protection, and leak protection, ensuring sensitivity and reliability.
- Test automatic changeover of the standby pump; changeover time must meet requirements.
12.5 Annual Maintenance (1 time per year)
Annual maintenance is comprehensive overhaul maintenance involving full disassembly inspection, cleaning, and replacement of wear parts across the entire system to restore equipment performance. It is recommended that this be performed by manufacturer’s professional after-sales personnel.
12.5.1 Comprehensive Water System Cleaning
- Drain all old cooling water from the system.
- Circulate specialized cleaning agents through the system piping, heat exchangers, and water tank to remove scale, rust, and biological slime.
- After cleaning, rinse repeatedly with clean water until the effluent is clear and pH is neutral.
- Perform pre-film treatment to form a protective film on the inner walls of the piping, enhancing corrosion and scale resistance.
- Refill with new qualified cooling water, add water treatment chemicals, and adjust water quality to standard.
12.5.2 Core Component Overhaul
- Pump overhaul: Disassemble the pump, inspect impeller, pump body, and shaft for wear; replace bearings, mechanical seals, sealing rings, and other wear parts; after reassembly, test performance to meet factory specifications.
- Valve overhaul: Disassemble key valves, inspect valve core and sealing surfaces for wear; replace seals and packing; grind sealing surfaces; ensure flexible operation and reliable sealing.
- Heat exchanger deep cleaning: Disassemble the heat exchanger, thoroughly clean heat exchange tubes and fins to remove stubborn scale and dirt; inspect heat exchange tubes for corrosion or perforation; perform pressure testing for leaks.
12.5.3 Comprehensive Electrical System Overhaul
- Perform comprehensive dust removal and cleaning on all electrical components; check for aging and replace severely aged components.
- Verify all protection device setpoints to ensure accurate protection parameters.
- Tighten all wiring terminals comprehensively; replace aged cables.
- Test overall system insulation performance to meet standard requirements.
- Upgrade controller firmware to the latest version and optimize control programs.
12.5.4 Structural and Seal Replacement
- Replace all piping interface sealing rings and valve seals to eliminate leakage hazards.
- Replace aged cabinet sealing strips to ensure sealing performance.
- Check cabinet structure for corrosion or deformation; perform rust removal and touch-up painting.
- Tighten all structural connection bolts and reinforce pipe supports.
12.5.5 Comprehensive Performance Testing
- After maintenance is completed, conduct comprehensive system performance testing, including cooling capacity, temperature control accuracy, energy consumption, and noise indicators.
- Conduct a 72-hour full-load operation test to verify system stability.
- Issue an annual maintenance and performance test report.
12.6 Fault Repair Procedures
12.6.1 Fault Reporting
- When equipment failure occurs, operations personnel shall first record fault symptoms, alarm codes, and operating parameters, and preserve the fault scene.
- Simple faults may be handled per the troubleshooting methods in this manual; if they cannot be resolved, contact the manufacturer’s after-sales department promptly to report for repair.
- When reporting, provide equipment model, serial number, fault symptoms, operating environment, and other information to facilitate rapid diagnosis by technical personnel.
12.6.2 Fault Handling Principles
- Safety First: When handling faults, prioritize personnel safety and equipment safety, and prevent fault escalation.
- Restore Before Repair: Prioritize restoring equipment operation to minimize business interruption time; perform complete repair during business idle periods.
- Simple Before Complex: First troubleshoot simple and common causes, then progressively investigate complex causes to improve troubleshooting efficiency.
- Treat Both Symptoms and Root Causes: Not only eliminate the current fault but also identify the root cause and take preventive measures to avoid recurrence.
12.6.3 On-Site Repair Requirements
- After repair personnel arrive on site, first understand the fault situation, formulate a repair plan, and confirm safety measures are in place.
- Perform repair work after power-off, water shut-off, and pressure release; post warning signs.
- Use genuine original accessories for replacement; use of inferior accessories is prohibited.
- Maintain proper records throughout the repair process, documenting replaced components and repair procedures in detail.
- After repair completion, conduct water-on and power-on trial operation to confirm the fault is eliminated and equipment operates normally.
- Explain the fault cause and preventive measures to operations personnel, fill out the repair report, and obtain signatures from both parties.
12.7 Recommended Wear Parts and Spare Parts
To ensure operation and maintenance efficiency, customers are recommended to stock the following common wear parts:
| Spare Part Name | Recommended Stock Quantity | Replacement Cycle |
|---|---|---|
| O-ring seals (various specifications) | Several | 1-2 years |
| Filter screen | 2 pcs | 6 months |
| Pump mechanical seal | 1 set | 2 years |
| Temperature sensor | 2 pcs | 3 years |
| Pressure sensor | 1 pc | 3 years |
| AC contactor | 1 pc | 3 years |
| Quick-connect fittings | 2 pcs | As needed |
| Thermal grease/thermal pad | Several | As needed |
13.1 Common Water System Faults
Fault 1: System Water Leakage
Fault Symptoms: Water accumulation at the cabinet base, leak sensor alarm, system pressure drop, liquid level drop.
Possible Causes:
- Loose pipe joints, failed seals
- Aged or damaged sealing rings
- Pipe corrosion, cracking at weld joints
- Valve stem leakage
- Pump mechanical seal damage
- Cold plate or heat exchanger leakage
- Excessive system pressure causing rupture
Solutions:
1. Immediately stop the pump, close the inlet valve, and cut off power to the corresponding circuit to prevent leak escalation.
2. Locate the leak point based on leak alarm positioning and visual inspection.
3. Loose joints: Re-tighten with a torque wrench to the specified torque; be careful not to overtighten and damage threads.
4. Damaged sealing rings: Drain the corresponding pipe section, replace with identical specification sealing rings, clean sealing surfaces, and reinstall.
5. Cracking at pipe weld seams: Perform weld repair or replace the pipe section; conduct pressure testing after welding.
6. Valve leakage: Replace valve packing or replace the complete valve.
7. Pump mechanical seal leakage: Replace the pump mechanical seal; replace the complete pump assembly in severe cases.
8. Heat exchanger/cold plate leakage: Replace the damaged heat exchange component; restore service after passing pressure testing.
9. Excessive pressure: Check whether the safety valve has failed; adjust system pressure to normal range.
10. After repair, conduct pressure testing to confirm no leakage before restoring system operation.
Fault 2: Insufficient System Flow
Fault Symptoms: Flow reading below normal value, excessive supply/return water temperature differential, poor cabinet heat dissipation, rising temperature.
Possible Causes:
- Pump running in reverse, insufficient head and flow
- Pump impeller worn or blocked, degraded performance
- Air in the system causing air lock and reduced flow
- Filter blockage causing increased flow resistance
- Piping valves not fully open or valve core detached
- Pipe scaling and blockage reducing flow passage diameter
- Makeup water tank level too low, pump drawing air
- Branch valve opening too small, insufficient total flow
Solutions:
1. Check pump rotation direction; if reversed, swap any two phase wires.
2. Open system high-point vent valves and vent repeatedly to fully remove air from the system.
3. Check makeup water tank level and replenish cooling water to normal level.
4. Check all valves to ensure they are fully open; replace valves with detached cores.
5. Dismantle and clean filters; clean debris from filter screens.
6. Adjust branch valves to ensure sufficient total flow and reasonable distribution across branches.
7. If flow remains insufficient after the above, disassemble the pump to inspect the impeller, clear blockages, or replace worn impellers.
8. For pipes with severe scaling, perform system acid cleaning to remove scale.
Fault 3: Abnormal System Pressure
Fault Symptoms: System pressure too high or too low, pressure alarm.
Possible Causes — Pressure Too High:
- Return water valve not fully open, pipe blockage
- Air not fully vented from system
- Safety valve failed, not relieving overpressure
- Pump oversized, excessive head
- Water volume expansion due to temperature rise
Solutions — Pressure Too High:
1. Fully open the return water valve and investigate pipe blockage points.
2. Thoroughly vent air from the system.
3. Verify the safety valve; replace if failed.
4. Partially close the pump discharge valve to regulate, or reduce pump speed.
5. Open systems generally have stable pressure; pressure fluctuations from temperature are normal; if excessively high, check expansion space.
Possible Causes — Pressure Too Low:
- System leakage, insufficient water volume
- Makeup water tank level too low
- Makeup water system failure, unable to replenish
- Pump suction side blockage, insufficient supply
- Pressure gauge damaged, incorrect reading
Solutions — Pressure Too Low:
1. Investigate leak points and repair leaks.
2. Check makeup water tank level and replenish cooling water.
3. Check the makeup water solenoid valve and level switch; replace if faulty.
4. Clean the inlet-side filter and piping to ensure unobstructed water intake.
5. Calibrate or replace the pressure gauge.
Fault 4: Deteriorating Cooling Water Quality
Fault Symptoms: Turbid water color, unpleasant odor, scaling, algae growth.
Possible Causes:
- Substandard makeup water quality, high hardness, high impurity content
- Open system exposure to air, allowing dust and debris entry
- Prolonged periods without water change, concentrated water quality
- Water treatment chemicals not dosed regularly
- Water treatment equipment failure
Solutions:
1. Improve makeup water quality; install a water softening unit.
2. Cover the makeup water tank to prevent debris from falling in.
3. Perform regular blowdown and water changes to maintain fresh water quality.
4. Regularly dose corrosion/scale inhibitors and bactericides/algaecides.
5. Repair the electronic water conditioner and dosing device to restore water treatment function.
6. For severely deteriorated water quality, drain the system, thoroughly clean, and refill with fresh water.
13.2 Common Electrical System Faults
Fault 1: Equipment Cannot Be Powered On, Main Switch Trips
Fault Symptoms: Main circuit breaker trips immediately upon closing; power cannot be supplied.
Possible Causes:
- Short circuit on power supply side
- Short circuit or ground fault in main circuit cables
- Short circuit on load side, such as motor burnout
- Circuit breaker itself faulty
- Leakage protection triggered; there is current leakage
Solutions:
1. Open all branch switches, then close the main breaker; if it still trips, the fault is in the main incoming line or main switch — inspect the incoming line and replace the breaker.
2. After the main breaker is normal, close branch switches one by one; troubleshoot whichever branch causes tripping.
3. Use a multimeter and megger to trace short circuit and leakage points; repair insulation faults.
4. For motor burnout, disassemble and repair or replace the motor.
5. Check leakage points, repair insulation, and eliminate leakage faults.
Fault 2: Pump Cannot Start
Fault Symptoms: Pump start signal given, pump does not rotate, no sound or humming sound.
Possible Causes:
- Power not connected, circuit breaker tripped
- Control circuit fault, damaged contactor or relay
- Thermal overload relay tripped and not reset
- Motor burned out, winding open or short circuit
- Pump impeller seized, motor stalled
- Inverter fault, no output
- Liquid level too low, interlock protection prevents starting
Solutions:
1. Check power supply and circuit breaker; identify the cause of tripping before resetting.
2. Check the control circuit; replace damaged contactors and relays.
3. For thermal relay tripping, allow the motor to cool before resetting; identify the cause of overload.
4. Manually rotate the pump shaft to check for seizure; disassemble to remove foreign objects and repair the impeller if seized.
5. For motor damage, repair or replace the motor.
6. For inverter faults, check the fault code; repair or replace the inverter.
7. For low liquid level, replenish cooling water to normal level; the protection will automatically release.
Fault 3: Excessive Pump Operating Current
Fault Symptoms: Pump operating current exceeds rated value, severe heating, frequent overload tripping.
Possible Causes:
- Pump bearing damage, high rotational resistance
- Impeller worn or blocked with foreign objects, increased load
- Motor rotor rubbing against stator
- Supply voltage too low
- Three-phase voltage imbalance, single-phase operation
- Pump flow too high, operating beyond design conditions
- Mechanical seal too tight
Solutions:
1. Check supply voltage; three-phase voltage balance should be within allowable range.
2. Check bearings; replace if damaged; apply grease.
3. Disassemble the pump; clean foreign objects from the impeller; replace worn impellers.
4. For rotor rubbing, repair the motor and adjust the air gap.
5. Partially close the discharge valve to reduce flow to rated conditions.
6. Adjust mechanical seal compression to avoid excessive tightness.
Fault 4: Monitoring System No Display, Black Screen
Fault Symptoms: Touchscreen not illuminated, controller not working.
Possible Causes:
- 24V switching power supply fault, no output
- Power wiring loose or disconnected
- Controller hardware damage
- Display screen damaged
- Fuse blown
Solutions:
1. Check whether input power is normal and whether the fuse is blown; replace blown fuses with the same specification.
2. Measure the switching power supply output voltage; replace the power supply if there is no output.
3. Check wiring terminals; re-tighten loose connections.
4. If still not working with normal power supply, replace the controller or display screen.
13.3 Common Cooling Performance Faults
Fault 1: Excessive In-Cabinet Temperature, Poor Heat Dissipation
Fault Symptoms: High IT equipment temperature, high cabinet outlet air temperature, over-temperature alarm.
Possible Causes:
- Insufficient circulating water flow, unable to remove heat
- Supply water temperature too high, insufficient cooling source capacity
- Heat exchanger scaling and dust accumulation, reduced heat exchange efficiency
- Pump failure, poor water circulation
- Poor cabinet sealing, severe air leakage causing cold/hot air mixing
- IT load exceeding design value
- Temperature sensor fault, inaccurate reading
- Improper temperature control parameter settings, insufficient cooling output
Solutions:
1. Check water flow; troubleshoot per the insufficient flow fault procedure to restore normal flow.
2. Check supply water temperature; if too high, investigate the external cooling source system and reduce supply water temperature.
3. Clean the heat exchanger to remove scale and dust and restore heat exchange performance.
4. Check pump operating status; repair faults promptly.
5. Check cabinet sealing; repair damaged sealing strips, close maintenance doors, and reduce air leakage.
6. Verify IT load; for loads exceeding design, expand capacity or reduce load.
7. Calibrate temperature sensors; replace those displaying incorrect values.
8. Optimize temperature control parameters; increase cooling output setpoints.
Fault 2: Condensation Inside Cabinet
Fault Symptoms: Condensation droplets on cabinet interior walls and equipment surfaces.
Possible Causes:
- Supply water temperature too low, below dew point temperature
- Equipment room ambient humidity too high
- Poor cabinet sealing allowing external humid air to enter
- Frequent system start/stop causing large temperature fluctuations
- Rapid temperature rise during startup in low-temperature environments
Solutions:
1. Raise the supply water temperature setpoint to above the ambient dew point temperature.
2. Activate dehumidification equipment in the equipment room to reduce ambient humidity.
3. Strengthen cabinet sealing to reduce external air ingress.
4. Optimize control logic to reduce frequent system start/stop and maintain stable temperature.
5. In low-temperature environments, warm up slowly during startup and gradually increase load.
6. For existing condensation, shut down first, wipe dry, and drive out moisture by warming before resuming operation.
13.4 Common Monitoring and Alarm Faults
Fault 1: Inaccurate Sensor Readings
Fault Symptoms: Temperature, pressure, and flow readings deviate significantly from actual values.
Possible Causes:
- Sensor calibration drift
- Incorrect sensor installation location
- Poor signal line contact, high interference
- Sensor damage
- Incorrect controller range parameter settings
Solutions:
1. Check controller parameter settings; ensure range matches sensor specifications.
2. Check installation location against installation specifications to avoid measurement errors.
3. Check wiring; tighten terminals, ensure proper shield grounding, and eliminate interference.
4. Calibrate sensors with standard instruments; adjust calibration coefficients for large deviations.
5. Replace damaged sensors with identical specification sensors.
Fault 2: False Alarms or No Alarms
Fault Symptoms: Frequent false alarms during normal operation, or no alarm during faults.
Possible Causes:
- Unreasonable alarm threshold settings
- Large sensor signal fluctuations
- Alarm device damage
- Alarm function disabled
- Controller program fault
Solutions:
1. Adjust alarm thresholds; set reasonable alarm hysteresis to avoid false alarms from fluctuations.
2. Investigate the cause of sensor signal fluctuations; add filtering.
3. Test alarm devices; replace if damaged.
4. Check alarm settings and enable the corresponding alarm functions.
5. Restart the controller; reprogram if the program is faulty.
14.1 Basic Concepts
Q1: What is an open-loop liquid-cooled integrated cabinet? What is the difference compared to traditional cabinets?
A: An open-loop liquid-cooled integrated cabinet is an integrated cabinet product that combines a liquid cooling system, power supply and distribution system, and intelligent monitoring system. It adopts an open-loop water circulation architecture, using water as the cooling medium to remove heat from IT equipment. Compared to traditional air-cooled cabinets, heat dissipation efficiency is improved by 3-5 times, supporting higher power density, lower operating noise, reduced cooling energy consumption, and significantly lower data center PUE.
Q2: Which is better, open-loop or closed-loop liquid cooling? How do I choose?
A: Neither has an absolute advantage; they suit different application scenarios. Open-loop systems have a simple structure, lower cost, and easy maintenance, making them suitable for small and medium-sized equipment rooms, edge nodes, and projects with limited budgets. Closed-loop systems operate in a sealed environment with stable water quality and high reliability, making them suitable for large data centers and scenarios requiring high reliability. The choice should be made based on project scale, budget, maintenance capability, and reliability requirements.
Q3: Will the open-loop liquid cooling leak? Will a leak burn the servers?
A: Any liquid cooling system carries a leakage risk, but this product reduces the probability and impact of leakage through multiple design measures: first, high-quality seals and standardized connection processes reduce the probability of leakage; second, a full-point leak detection system provides second-level alarm response; third, leak-linked protection automatically shuts off water and stops pumps; fourth, the cabinet base has a drainage containment system that collects leakage centrally without direct contact with equipment; fifth, all water circuit interfaces are located at the bottom of the cabinet while IT equipment is positioned above, so minor leaks do not contact electrical equipment. With proper installation and maintenance, leakage risk is controllable.
Q4: What kind of water does the open-loop liquid-cooled cabinet need? Can tap water be used?
A: Direct use of tap water is not recommended. The open-loop system has water quality requirements; softened water or deionized water is recommended, with hardness ≤100mg/L, to reduce scaling and corrosion. Tap water has high hardness, and long-term use will cause scaling that blocks piping and heat exchangers, reducing heat dissipation efficiency and shortening equipment life. If tap water must be used, a water treatment device must be installed, and regular chemical dosing maintenance must be performed.
Q5: Does this system consume a lot of electricity? Is it more energy-efficient than air cooling?
A: The system’s own power consumption mainly comes from pumps and fans, which is far lower than precision air conditioners of equivalent cooling capacity. Overall, liquid cooling solutions reduce data center cooling energy consumption by 30%-50% compared to traditional air cooling. PUE can be reduced from above 1.5 to approximately 1.15. Long-term electricity savings are substantial, with the additional investment typically recovered within 2-3 years.
14.2 Installation and Deployment
Q1: What are the requirements for installing an open-loop liquid-cooled cabinet in an equipment room?
A: Main requirements include: floor load-bearing capacity to support the cabinet’s fully loaded weight; a qualified grounding system in the equipment room; suitable cooling source water supply and drainage conditions; power supply of corresponding capacity; sufficient maintenance space reserved; and ambient temperature and humidity within the equipment’s allowable range. Ordinary equipment rooms can be installed with simple modifications without large-scale civil works.
Q2: Can an existing air-cooled equipment room be retrofitted with these liquid-cooled cabinets?
A: Absolutely. This product features integrated design and can be deployed directly in existing equipment rooms as an independent unit. Simply connect the cooling source water pipes and power supply for operation, with no need to modify the existing air conditioning system. It is highly suitable for high-density area upgrades in existing data centers.
Q3: How long does it take to install one cabinet?
A: Cabinet body installation for a single unit can be completed in half a day. Including pipe connection, electrical wiring, and commissioning, the overall installation can be operational within 1-2 days. Multi-cabinet installation time extends according to quantity. This significantly shortens the construction period compared to traditional data center builds.
Q4: How is the cooling source provided? Is a cooling tower mandatory?
A: The cooling source can be provided in multiple ways: if the equipment room has a centralized chilled water system, connect directly to the existing chilled water supply; if no centralized cooling source exists, supporting equipment such as open cooling towers, dry coolers, or air-cooled chillers can be used. A cooling tower is not mandatory. In northern regions, dry coolers can fully utilize natural cold sources for greater energy and water savings. Dry cooler solutions are also recommended for water-scarce regions.
Q5: Should piping run overhead or underfloor? Which is better?
A: Both are acceptable; the choice depends on equipment room conditions. Overhead routing is aesthetically pleasing and does not affect the floor, making it suitable for overhead cabling equipment rooms. Underfloor routing is simpler to construct with lower cost, suitable for underfloor cabling or raised-floor equipment rooms. Whichever method is used, proper fixation and leak prevention measures must be implemented.
14.3 Operation and Maintenance
Q1: Is daily maintenance complicated? Do I need specialized liquid cooling maintenance personnel?
A: Daily maintenance is not complicated. Ordinary equipment room operations personnel can handle it after simple training. Daily tasks mainly involve checking parameters, inspecting for leaks, and periodically cleaning filters — all simple operations. In-depth maintenance is recommended to be performed by professionals, and the manufacturer also provides after-sales operation and maintenance services.
Q2: How often does the water need to be changed? Is maintenance cost high?
A: Under normal water quality maintenance conditions, the cooling water only needs to be changed once per year, with system cleaning performed at the same time. Daily maintenance only requires regular chemical dosing and filter cleaning, with very low consumable costs. Overall maintenance costs are lower than air-cooled air conditioning systems, with no large wear-prone components such as compressors, resulting in longer service life.
Q3: Will it freeze in winter? Can it be used in northern regions?
A: If the equipment room has heating and the temperature remains above 5°C, freezing will not occur. For winter shutdown in northern regions, drain accumulated water and provide insulation and heat tracing for outdoor piping. If the equipment room has no heating and the system will be shut down for extended periods, all water must be drained from the system to prevent freezing and cracking. With proper anti-freeze measures, normal use in northern regions is entirely feasible.
Q4: What if the pump fails? Will the servers overheat and go down?
A: Pumps are designed with N+1 redundancy. When the primary pump fails, the standby pump automatically switches over within 2 seconds without interrupting heat dissipation. Additionally, an emergency air-cooled backup is provided. In extreme cases where both pumps fail, the emergency air-liquid cooling automatically starts to maintain basic heat dissipation, providing ample time for repair without causing immediate server overheating and shutdown.
Q5: Is the system noisy? Will it affect the office environment?
A: Operating noise is ≤55dB(A), equivalent to normal office background noise, much lower than air-cooled cabinets of equivalent power. It can be placed next to office areas without noticeable noise impact, making it highly suitable for noise-sensitive scenarios.
14.4 Performance and Compatibility
Q1: What is the maximum server power supported?
A: The full product series covers 10kW-120kW per cabinet power range, supporting up to 120kW of IT load, which can accommodate full deployment of the highest-power AI GPU servers currently available. Higher power ratings can be customized.
Q2: Which server brands are supported? Can ordinary servers be converted to liquid cooling?
A: All mainstream standard 19-inch rack-mount servers are compatible. For cold plate solutions, the server must be compatible with the corresponding cold plate interface; mainstream brands have corresponding liquid-cooled server models available. For ordinary servers, the cabinet-level air-liquid hybrid cooling solution can be used without modifying the server itself — simply install and operate.
Q3: Is the U-space the same as ordinary cabinets? Can standard IT equipment be installed?
A: Standard 19-inch installation space with U-position specifications fully consistent with ordinary cabinets. All standard rack-mount equipment can be installed. Liquid cooling piping does not occupy IT installation space and does not affect equipment installation.
Q4: What is the temperature control accuracy? Are temperature fluctuations large?
A: Using PID intelligent temperature control, temperature control accuracy reaches ±1°C with minimal temperature fluctuation, providing a highly stable operating environment for IT equipment, which is beneficial for extending equipment life and improving operational stability.
Q5: Can it integrate with our existing environment monitoring system?
A: Yes. The product supports standard communication protocols including Modbus, SNMP, and BACnet, enabling seamless integration with mainstream environment monitoring platforms for unified management.
14.5 Safety and Warranty
Q1: What safety certifications does the product have? What is the warranty period?
A: The product has passed ISO9001 quality management system certification, 3C certification, and CE certification, complying with relevant national standards. The complete unit carries a 1-year warranty, core components carry a 2-year warranty, and lifetime technical support and repair services are provided. Extended warranty services are available for purchase.
Q2: Will damage caused by leakage be compensated?
A: Where leakage results from the product’s own quality issues under standard installation and use, the manufacturer bears corresponding responsibility. Leakage caused by unauthorized modification, non-compliant operation, or improper maintenance is not covered under warranty. It is recommended that projects purchase corresponding property insurance to further mitigate risk.
Q3: Are there fire safety hazards?
A: The liquid cooling system itself is flame-retardant and has no refrigerant leakage risk, making it safer than air-cooled air conditioners. The product complies with data center fire protection codes and can be equipped with cabinet-level gas fire suppression systems, ensuring fire safety.
Q4: What is the equipment service life?
A: Under normal maintenance conditions, the design service life is ≥15 years. Core components such as pumps and heat exchangers can last over 10 years. With periodic replacement of wear parts, long-term stable operation is achievable, with a longer service life than traditional precision air conditioners.
Q5: What after-sales services does the manufacturer provide?
A: Full-process services include a 7×24-hour technical support hotline, on-site installation guidance, commissioning training, periodic inspections, fault repair, spare parts supply, firmware upgrades, and operation and maintenance training, ensuring long-term stable equipment operation.
Product acceptance is divided into four stages: factory acceptance, on-site delivery acceptance, installation and commissioning acceptance, and completion acceptance. Each stage must pass before proceeding to the next, ensuring product quality and engineering quality meet requirements.
15.1 Factory Acceptance
Factory acceptance is conducted at the manufacturer’s factory after production is completed. Customers may send representatives to participate.
15.1.1 Acceptance Contents
Appearance and Structure Inspection
- Check the cabinet exterior is smooth, free of deformation, paint chipping, and scratches, with uniform powder coating.
- Check structural dimensions meet design requirements, with accurate mounting hole positions.
- Check door locks, hinges, shelves, and other accessories function normally.
Component Configuration Verification
- Against the configuration list, verify the brand, model, specification, and quantity of all components, conforming to contract and technical requirements.
- Check that certificate of conformity and test reports for core components are complete.
Factory Testing
- Electrical performance testing: insulation resistance, withstand voltage test, and ground resistance test all pass.
- Water circuit testing: hydrostatic pressure test passes with no leakage.
- No-load operation testing: pumps, fans, and monitoring system operate normally with accurate parameters.
- Protection function testing: all safety protection functions are sensitive and reliable.
Documentation Inspection
- Check that product certificates of conformity, quality inspection reports, manuals, drawings, and other technical documents are complete.
15.1.2 Acceptance Standards
- No appearance defects; dimensions conform to drawing requirements
- Configuration consistent with contract; all components are genuine qualified products
- All performance tests meet technical parameter specifications
- All protection functions are normal and effective
- Technical documents are complete and accurate
15.1.3 Acceptance Conclusion
Upon passing acceptance, both parties sign the factory acceptance report, and the equipment is approved for shipment. If acceptance fails, the manufacturer shall rectify and re-inspect until passing.
15.2 On-Site Delivery Acceptance
After equipment arrives at the project site, delivery acceptance is conducted to confirm no damage or missing parts occurred during transportation.
15.2.1 Acceptance Contents
- Check whether the external packaging is intact, with no damage, moisture exposure, or impact marks.
- Open the box and inspect the equipment exterior for bumps, deformation, paint chipping, or damage.
- Against the packing list, verify equipment, accessories, spare parts, and technical documents are all present.
- Check the equipment for water ingress, moisture exposure, or corrosion marks.
- Check electrical components and precision components for damage.
15.2.2 Acceptance Standards
- External packaging intact, no obvious damage
- Equipment exterior intact, no transportation damage
- Components, accessories, and documents complete and consistent with the packing list
- Equipment free of moisture exposure, corrosion, or water ingress
15.2.3 Exception Handling
If damage, missing parts, or moisture exposure are found, take photos and record on-site immediately, with both parties signing confirmation. The manufacturer shall arrange for replacement or replenishment. Damage caused by transportation shall be claimed against the logistics carrier.
15.3 Installation and Commissioning Acceptance
After equipment installation and commissioning are completed and a 72-hour full-load trial operation passes, installation and commissioning acceptance is conducted.
15.3.1 Installation Quality Acceptance
Cabinet Installation
- Cabinet position and arrangement conform to design drawings
- Levelness ≤1mm/m, verticality ≤1.5mm/m
- Firmly fixed, expansion bolts complete with no loosening
- Uniform gaps between joined cabinets, neat and aesthetically pleasing
Water Circuit Installation
- Piping routing is logical, level and plumb, firmly fixed
- No leakage at joints or welds; hydrostatic pressure test passes
- Valve markings clear, flexible operation
- Insulation intact, no condensation
- Piping identification complete with clear flow direction
Electrical Installation
- Wiring neat and secure, correct phase sequence
- Insulation resistance and ground resistance tests pass
- Cable identification clear, power and signal cables separated
- Lightning protection and grounding comply with specifications
Monitoring and Sensor Installation
- Sensors installed in correct positions, firmly fixed
- Communication lines connected properly, free of interference
- Display screen and alarm devices properly installed
15.3.2 Performance Indicator Acceptance
Cooling Performance
- During full-load operation, in-cabinet temperature remains stable within set range, temperature control accuracy ±1°C
- Supply/return water temperature differential conforms to design value; cooling capacity reaches rated specification
- No local hot spots in cabinet; temperature uniformity ≤±2°C
- IT equipment surface temperature within allowable range
System Energy Efficiency
- System COP reaches design value
- Pump and fan operating currents within rated range
- Variable frequency regulation functions normally; energy savings meet expectations
Safety Protection Functions
- Over-temperature, over-pressure, low-flow, and leak protection functions trigger normally with accurate operation
- Pump fault changeover time ≤2s
- Leak alarm response time ≤1s
- Emergency air cooling starts normally
Monitoring and Communication
- All sensor data displays accurately, with errors within accuracy range
- Local monitoring functions complete, smooth operation
- Remote communication normal, stable data upload
- Alarm methods comprehensive, timely notification delivery
15.3.3 Trial Operation Acceptance
Continuous 72-hour full-load trial operation with no faults, no alarms, stable performance, and all parameters normal qualifies as a passing trial operation. During the trial operation, record operating data every 2 hours to form a trial operation record.
15.4 Completion Acceptance
After the overall project is completed, all equipment acceptance passes, and documentation transfer is complete, final completion acceptance is conducted.
15.4.1 Acceptance Documentation Transfer
Complete completion documentation must be transferred prior to acceptance, including:
- Product certificates of conformity and factory test reports
- As-built installation drawings (piping diagrams, electrical diagrams, layout drawings)
- Installation records, commissioning records, trial operation records
- Test and inspection reports (hydrostatic pressure tests, insulation tests, performance tests, etc.)
- Operating manuals and maintenance manuals
- Spare parts list and tool list
- Acceptance reports, change orders, and other engineering documents
15.4.2 Acceptance Process
1. The contractor submits the completion acceptance application and complete documentation set.
2. The acceptance team reviews the documentation; after verifying completeness and qualification, organizes on-site acceptance.
3. Spot-check equipment operating status and installation quality on-site; re-verify key performance indicators.
4. Conduct operational assessment of operations personnel to confirm mastery of basic operations and emergency handling.
5. The acceptance team discusses and forms an acceptance opinion; issues are given a rectification deadline, with re-inspection after rectification.
6. Upon full compliance, sign the completion acceptance report; the project is officially delivered and enters the warranty period.
15.5 Acceptance Reference Standards
- GB 50174-2017 “Data Center Design Specification”
- GB 50236-2011 “Code for Construction of Field Equipment and Industrial Pipe Welding Engineering”
- GB 50303-2015 “Code for Acceptance of Construction Quality of Building Electrical Engineering”
- GB/T 39663-2020 “Technical Requirements for Cold Plate Liquid Cooling Systems for Data Centers”
- T/CIE 093-2021 “Technical Specification for Liquid Cooling Systems in Data Centers”
- Project contract, technical agreement, design drawings
- Technical parameter requirements in this product manual
Appendix A Electrical Schematic Diagrams
(Detailed main circuit diagrams, control circuit diagrams, and terminal connection diagrams are attached here. Due to text format limitations, high-definition drawings are provided in the printed manual.)
Appendix B Piping System Diagrams
(System water circuit schematic diagrams, cabinet piping layout diagrams, and interface dimension drawings are attached here. High-definition drawings are provided in the printed manual.)
Appendix C Fault Code Table
| Fault Code | Fault Name | Fault Cause | Recommended Action |
|---|---|---|---|
| E01 | Supply water temperature too high | Insufficient cooling source, low flow, high load | Check cooling source system, investigate flow, reduce load |
| E02 | System pressure too low | Water leakage, insufficient water, pump failure | Replenish water, check for leaks, inspect pump |
| E03 | System pressure too high | Valve blockage, poor venting | Open valves, vent air, check safety valve |
| E04 | Flow too low | Pump failure, blockage, insufficient water | Check pump, clean filter, replenish water |
| E05 | Leak alarm | System water leakage | Shut off water and power, investigate leak point |
| E06 | Pump overload | Pump seizure, low voltage, bearing damage | Check pump, investigate power supply, replace bearings |
| E07 | Liquid level too low | Makeup system failure, water leakage | Check makeup system, investigate leaks and replenish |
| E08 | Communication fault | Line break, address error | Check cables, verify addresses |
Appendix D Common Parameters Quick Reference Table
(Omitted; parameter tables can be printed according to specific models.)
I. Search Keyword Classification
1. Core Primary Keywords
Open-loop liquid-cooled integrated cabinet, liquid-cooled integrated cabinet, open-loop liquid-cooled cabinet, data center liquid-cooled cabinet, high-density liquid-cooled cabinet
2. High-Conversion Long-Tail Keywords
Open-loop liquid-cooled integrated cabinet manufacturer, open-loop liquid-cooled cabinet installation and commissioning, liquid-cooled integrated cabinet technical parameters, KITOZER liquid-cooled cabinet price, high-density server liquid-cooled cabinet, data center open-loop liquid-cooled cabinet, data center liquid-cooling retrofit integrated cabinet, industrial liquid-cooled cabinet customization, 120kW liquid-cooled cabinet, cold plate liquid-cooled integrated cabinet
3. Industry Traffic Keywords
Data center liquid cooling cabinet, data center liquid cooling solution, high-power cabinet heat dissipation, liquid-cooled integrated cabinet, IDC data center liquid cooling retrofit, computing power data center liquid cooling equipment, edge computing liquid-cooled cabinet, modular liquid-cooled cabinet, air-liquid hybrid liquid-cooled cabinet, open-loop circulation liquid cooling system
4. Brand-Specific Keywords
KITOZER liquid-cooled integrated cabinet, Guangdong KITOZER open-loop liquid-cooled cabinet, KITOZER smart data center liquid cooling equipment, LA-SW series liquid-cooled cabinet, KITOZER liquid cooling cabinet manufacturer
5. Dropdown/Related Search Keywords
How to install open-loop liquid-cooled integrated cabinet, what to do if open-loop liquid-cooled cabinet leaks, advantages and disadvantages of liquid-cooled integrated cabinet, difference between open-loop and closed-loop liquid-cooled cabinets, integrated liquid-cooled cabinet maintenance, liquid-cooled cabinet wiring method, liquid-cooled cabinet commissioning steps, liquid-cooled cabinet acceptance standards, integrated liquid-cooled cabinet application scenarios, liquid-cooled cabinet maintenance methods
II. SEO Optimization Tag System
1. Core Page Optimization Tags
- Page Topic: Open-loop liquid-cooled integrated cabinet installation, wiring, and commissioning manual
- Core Positioning: Professional open-loop liquid-cooled integrated cabinet full-lifecycle technical documentation, covering installation, wiring, commissioning, and maintenance processes
- Target Audience: Data center operations engineers, data center builders, system integrators, IT equipment procurement personnel
2. Title Tag
Open-loop Liquid-Cooled Integrated Cabinet Installation Wiring Commissioning Manual_KITOZER Liquid-Cooled Cabinet Technical Handbook-Guangdong KITOZER Intelligent Data Center Equipment Co., Ltd.
3. Meta Keywords
open-loop liquid-cooled integrated cabinet, liquid-cooled integrated cabinet, open-loop liquid-cooled cabinet, liquid-cooled cabinet installation, liquid-cooled cabinet commissioning, liquid-cooled cabinet wiring, KITOZER liquid-cooled cabinet, high-density liquid-cooled cabinet, data center liquid cooling cabinet, data center liquid cooling retrofit
4. Meta Description
Guangdong KITOZER Intelligent Data Center Equipment Co., Ltd. professionally provides open-loop liquid-cooled integrated cabinets. This manual provides full-process technical content covering product introduction, principles, parameters, installation, wiring, commissioning, maintenance, fault troubleshooting, and acceptance standards for liquid-cooled integrated cabinets. Supporting 10-120kW power range, suitable for AI computing, HPC, data centers, and other high-density heat dissipation scenarios. Service hotline: +86 13538869979.
5. H1 Tag
Open-Loop Liquid-Cooled Integrated Cabinet Installation Wiring and Commissioning Manual
6. H2 Tags
Product Introduction, Product Composition, Product List, Product Working Principles, Product Technical Parameters, Product Functions and Features, Product Application Scenarios, Product Installation, Product Wiring, Product Commissioning, Product Precautions, Product Repair and Maintenance, Common Product Problems and Solutions, Product Q&A, Product Acceptance
7. Internal Link Optimization Tags (Natural anchor text placement)
- Core Anchor Text: open-loop liquid-cooled integrated cabinet, liquid-cooled integrated cabinet, open-loop liquid-cooled cabinet
- Long-Tail Anchor Text: open-loop liquid-cooled integrated cabinet installation, liquid-cooled cabinet commissioning methods, high-density server liquid-cooled cabinet, data center open-loop liquid cooling solution
- Related Anchor Text: liquid-cooled integrated cabinet, data center liquid cooling equipment, modular integrated cabinet, KITOZER intelligent data center equipment
The copyright of this document belongs to Guangdong KITOZER Intelligent Data Center Equipment Co., Ltd. and is protected by national copyright law.
No unit or individual may copy, reprint, adapt, excerpt, distribute, or commercially use this document, in whole or in part, without the written authorization of the Company.
For reprinting or citation of this document content, the source must be credited as “Source: Guangdong KITOZER Intelligent Data Center Equipment Co., Ltd.,” and the original content must not be altered or used for commercial purposes.
Violators of the above statement will be held legally liable by the Company.
This document is subject to technical upgrades and revisions without prior notice. The latest version shall prevail.
- Manufacturer: Guangdong KITOZER Intelligent Data Center Equipment Co., Ltd. (Guangzhou Lain Intelligent System Development Co., Ltd.)
- Service Hotline: +86 13538869979 (WeChat same number)
- Technical Support: +86 13538869979
- Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou
- Official Website: https://gdlain.com