Outdoor Energy Storage Container Installation & Commissioning Manual

Table of Contents

SEO Optimization Tag System

Page Core Optimization Tags

Title Tag: Outdoor Energy Storage Container Installation & Commissioning Manual_Energy Storage Container Construction & Acceptance Specification – Guangzhou Lain Intelligent Machine Room Equipment Co., Ltd.

Meta Keywords: outdoor energy storage container, energy storage container installation & commissioning, containerized energy storage power station installation guide, commercial & industrial energy storage container commissioning standard, Guangdong Lain energy storage container, energy storage container construction plan, energy storage container acceptance specification, energy storage container wiring requirements

Meta Description: Guangzhou Lain Intelligent System Development Co., Ltd. releases the full version of the Outdoor Energy Storage Container Installation & Commissioning Manual, detailing the complete process of on-site hoisting, electrical wiring, system joint commissioning, safety acceptance, and operation & maintenance for energy storage containers. Lain Intelligent is dedicated to containerized energy storage system integration, providing full-process technical support. Service Hotline: +86 13538869979.

H1 Tag: Outdoor Energy Storage Container Installation & Commissioning Manual

H2 Tags:

  • Outdoor Energy Storage Container Product Overview and Technical Parameters
  • Pre-Installation Preparation Work for Outdoor Energy Storage Containers
  • On-Site Installation Construction Process for Outdoor Energy Storage Containers
  • Electrical System Wiring and Cabling Specification for Outdoor Energy Storage Containers
  • System Commissioning and Trial Operation Plan for Outdoor Energy Storage Containers
  • Installation Quality Acceptance Standards for Outdoor Energy Storage Containers
  • Routine Operation, Maintenance, and Fault Troubleshooting for Outdoor Energy Storage Containers
  • Guangdong Lain Energy Storage Container After-Sales Service and Technical Support

Internal Link Optimized Anchor Text (Natural Placement)

Core Anchor Text: outdoor energy storage container, energy storage container installation & commissioning

Long-tail Anchor Text: outdoor energy storage container installation steps, energy storage container commissioning methods, containerized energy storage power station construction process, energy storage container grounding specification

Related Anchor Text: energy storage container system integration, commercial & industrial energy storage solutions, energy storage container safety operation & maintenance, containerized data center

Manufacturer: Guangzhou Lain Intelligent System Development Co., Ltd.

Service Hotline: +86 13538869979 (WeChat: same number)

Technical Support: +86 13538869979

Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou City

Official Website: https://gdlain.com

Version: V2.0

Release Date: July 2026

Preface

With the continuous advancement of the dual-carbon goals, new energy power generation has grown rapidly, and the power system’s demand for energy storage devices continues to rise. As a highly integrated, modular, and rapidly deployable energy storage solution, the outdoor energy storage container is widely applied in scenarios such as commercial and industrial peak-valley arbitrage, new energy co-located storage, grid peak shaving and frequency regulation, backup power supply, and off-grid power supply. Guangzhou Lain Intelligent System Development Co., Ltd. has been deeply engaged in the fields of intelligent machine rooms and energy storage integration for many years. The Lain outdoor energy storage container, independently developed and produced, offers core advantages including high safety, high reliability, high integration, easy deployment, and easy maintenance. Products cover 20-foot standard cabinets, 40-foot standard cabinets, and customized energy storage enclosures, meeting energy storage needs across various capacities and application scenarios.

This manual provides detailed standardized specifications for the entire process of installation, commissioning, acceptance, and operation & maintenance of Guangdong Lain outdoor energy storage containers. It is intended to provide construction units, operation & maintenance units, and owners with standardized operational basis, ensuring safe, stable, and efficient operation of the energy storage container system. All construction and commissioning personnel must carefully read this manual and strictly follow the specification requirements during operation. Non-compliant operation may result in equipment damage, personal injury, and safety accidents.

This manual is compiled in accordance with national and industry standards including *GB/T 36276 Lithium Ion Batteries for Electric Energy Storage*, *GB/T 34120 Technical Specification for Power Conversion System of Electrochemical Energy Storage System*, *GB 51048 Design Code for Electrochemical Energy Storage Power Station*, *GB 50303 Code for Acceptance of Construction Quality of Building Electrical Engineering*, among others. If relevant standards are updated, the latest version of the standards shall prevail.

Chapter 1 Outdoor Energy Storage Container Product Overview and Technical Parameters

1.1 Definition and Application Scenarios of Outdoor Energy Storage Containers

1.1.1 Product Definition

An outdoor energy storage container is an integrated energy storage device that integrates core equipment including battery modules, Power Conversion System (PCS), Battery Management System (BMS), temperature control system, fire protection system, monitoring system, and power distribution system within a standard container enclosure. It features factory prefabrication, rapid on-site deployment, convenient mobility, and strong environmental adaptability. Compared with traditional fixed energy storage power stations, containerized energy storage power stations can significantly shorten the on-site construction period, reduce site modification requirements, and offer the advantages of relocatability and reusability. It is currently the mainstream application form in the field of electrochemical energy storage.

The outdoor energy storage container manufactured by Guangzhou Lain Intelligent System Development Co., Ltd. adopts a standardized industrial design philosophy. All core equipment undergoes installation, wiring, and pre-commissioning within the factory. Before shipment, it passes strict functional testing and aging verification. On-site work only requires container positioning, external cable connection, and system joint commissioning before operation, effectively reducing on-site construction difficulty and quality risks.

1.1.2 Core Application Scenarios

Commercial and Industrial Energy Storage Scenario

Applied to large electricity consumers such as industrial parks, commercial complexes, data centers, hospitals, and schools, achieving electricity cost reduction and improved power supply reliability through peak-valley price arbitrage, demand management, and backup power functions. Lain commercial and industrial energy storage containers can be configured with 0.5C-1C charge/discharge rates, supporting 2 charge/discharge cycles per day, adapting to the peak-valley electricity price arbitrage profit model in most regions.

New Energy Co-located Storage Scenario

Deployed alongside photovoltaic and wind power generation stations to smooth new energy output fluctuations, enhance grid absorption capacity, and participate in grid ancillary services. Outdoor energy storage containers can be directly deployed at new energy power station sites without requiring new buildings, enabling rapid response to new energy co-located storage policy requirements.

Grid-Side Energy Storage Scenario

Applied at substations and distribution network nodes, providing ancillary services such as peak shaving, frequency regulation, voltage regulation, and black start, thereby enhancing grid stability and power supply quality. Containerized energy storage power stations support modular expansion, allowing flexible capacity configuration based on grid requirements.

Off-Grid and Microgrid Scenario

Applied in remote areas, islands, mines, field operation camps, and other regions without grid coverage, building independent microgrids in conjunction with new energy generation to provide stable power supply. Outdoor energy storage containers feature strong environmental adaptability and can operate stably under harsh conditions including high temperature, extreme cold, high humidity, and high altitude.

Emergency Backup Power Scenario

Serving as backup power for critical loads, enabling rapid power switching during grid outages to ensure uninterrupted operation of key loads. Applicable to important facilities such as communication base stations, hospital operating rooms, data centers, and emergency command centers.

1.2 Core Features of Guangdong Lain Outdoor Energy Storage Containers

1.2.1 Highly Integrated Consolidated Design

The Lain outdoor energy storage container adopts an integrated design philosophy, deeply integrating five core subsystems—battery system, electrical system, temperature control system, fire protection system, and monitoring system—within a standard container enclosure. More than 90% of assembly and commissioning work is completed within the factory. On-site, only external power and communication cable connections are required before operation, significantly shortening the on-site construction period. Typically, the on-site installation and commissioning period for a single energy storage container can be controlled within 7-15 days.

The internal container layout adopts a modular zoned design, divided into three independent functional areas: battery compartment, electrical compartment, and equipment compartment. Each area is separated by fire-resistant partition panels, ensuring rational equipment layout, sufficient maintenance space, and physical isolation to enhance safety levels. The in-container equipment layout follows ergonomic design principles, with adequate operation and maintenance access reserved for later O&M inspections.

1.2.2 Multi-Layer Safety Protection System

Safety is the core indicator of an energy storage system. Guangdong Lain energy storage containers establish a five-level safety protection system spanning “cell level – module level – cluster level – system level – container level,” comprehensively safeguarding system operation safety.

Cell Level: High-safety-grade lithium iron phosphate (LiFePOâ‚„) cells are selected, featuring basic protection functions including overcharge, over-discharge, over-temperature, and short-circuit protection. Cells pass rigorous safety tests including nail penetration, crush, and thermal abuse.

Module Level: Each battery module is equipped with an independent fuse, temperature sensors, and voltage acquisition units, enabling precise monitoring and fault isolation of individual cells.

Cluster Level: Each battery cluster is equipped with a high-voltage box containing circuit breakers, fuses, pre-charge circuits, and insulation monitoring modules, enabling rapid fault disconnection at the cluster level.

System Level: The BMS (Battery Management System) and PCS (Power Conversion System) operate with interlocked protection, featuring multiple protection logic functions including overvoltage, undervoltage, overcurrent, over-temperature, and insulation fault, with rapid shutdown upon fault occurrence.

Container Level: The container enclosure uses fire-retardant materials and is equipped with a heptafluoropropane (FM200) gas fire suppression system and combustible gas detection system, featuring triple detection through smoke, heat, and combustible gas sensors. Abnormal conditions trigger automatic alarm and fire suppression activation. The container is also equipped with explosion-proof pressure relief design, enabling rapid pressure release under extreme conditions to reduce risk.

1.2.3 Strong Environmental Adaptability

Outdoor energy storage containers are deployed directly in outdoor environments and must withstand complex and variable climatic conditions. Lain energy storage containers use high-strength cold-rolled steel plate construction. The surface undergoes triple anti-corrosion treatment: pickling and phosphating, electrostatic spraying, and fluorocarbon topcoat, achieving C5-level anti-corrosion rating, suitable for coastal high salt spray and industrial high-corrosion environments. The container protection rating reaches IP54, providing good waterproof and dustproof performance, enabling stable operation under severe weather conditions such as heavy rain and sandstorms.

The temperature control system employs a precision intelligent temperature control scheme, automatically adjusting cooling/heating power based on in-container temperature to maintain the battery operating environment within the optimal range of 20°C-30°C. The system can adapt to an ambient temperature range of -30°C to +55°C, meeting outdoor deployment requirements for the vast majority of regions nationwide. High-altitude-specific equipment can be custom-configured for high-altitude regions to ensure stable operation above 4,000 meters.

1.2.4 Intelligent Monitoring and Operation & Maintenance

The system is equipped with an intelligent Energy Management System (EMS), featuring dual monitoring capabilities through local monitoring and remote cloud platform. It can collect real-time operational data from the battery system, PCS system, temperature control system, and fire protection system, enabling real-time monitoring and historical storage of parameters including voltage, current, temperature, SOC, SOH, and alarm information. Multiple access methods are supported including web portal, mobile APP, and WeChat mini-program, allowing O&M personnel to view system operation status anytime, anywhere.

The system features intelligent alarm functionality with support for multi-level alarm threshold settings. Faults trigger notifications through multiple channels including SMS, phone call, and APP push. The system also features fault self-diagnosis capability, automatically locating fault positions and causes, significantly improving O&M efficiency and reducing O&M costs. Remote parameter configuration, remote upgrades, and remote start/stop control are supported, enabling most O&M operations without on-site visits.

1.2.5 Flexible Configuration and Scalability

Guangdong Lain outdoor energy storage containers offer standardized product series and customized services. Standard products cover two major series: 20-foot cabinets (1MWh-2MWh) and 40-foot cabinets (3MWh-5MWh). Customized energy storage container products with different capacities, voltage levels, and functional configurations can also be manufactured per customer requirements. Multiple containers support parallel expansion, enabling construction of energy storage power stations from several MWh to hundred-MWh levels. Expansion only requires adding new cabinets and connecting communication and power buses, offering convenient construction and low expansion costs.

The system supports multiple operating modes including grid-connected, off-grid, and grid-connected/off-grid switching, adapting to functional requirements of different application scenarios. It is also compatible with multiple power sources including photovoltaic, wind power, and diesel generators, enabling construction of multi-energy complementary microgrid systems.

1.3 System Composition of Outdoor Energy Storage Containers

The Guangdong Lain outdoor energy storage container system comprises eight major subsystems: container structure system, battery energy storage system, power conversion system, battery management system, power distribution system, temperature control system, fire protection system, and monitoring & energy management system. All subsystems work cooperatively to ensure the safe and stable operation of the energy storage system.

1.3.1 Container Structure System

The container structure serves as the carrier and protective enclosure of the energy storage container. It adopts standard marine container dimensions with characteristics including high structural strength, convenient hoisting and transportation, and excellent sealing and protection performance.

Container Body

The container body is fabricated from Q235B high-strength cold-rolled steel plate with a thickness of no less than 2mm. The overall structural strength meets marine transportation, road transportation, and hoisting requirements, capable of withstanding seismic intensity of 8 degrees. The container frame uses a shaped steel welded structure with reinforced cross beams at the base, capable of bearing equipment weight and hoisting forces.

The container surface undergoes multiple anti-corrosion treatment processes: first, overall pickling and phosphating to remove surface oil and rust; then, epoxy zinc-rich primer coating to enhance anti-corrosion adhesion; followed by epoxy micaceous iron oxide intermediate coating to increase anti-corrosion thickness; and finally, fluorocarbon topcoat to enhance weather resistance and appearance. Total paint film thickness is no less than 120μm, with an anti-corrosion service life of no less than 15 years.

Compartment Zoning

The interior uses fire-resistant rock wool sandwich panels for functional zoning, typically divided into two main areas: battery compartment and electrical compartment. Large-capacity cabinets may add an independent equipment compartment.

Battery Compartment: Used for installing battery clusters and battery management system related equipment. This is the core energy storage area of the energy storage container, occupying approximately 70% of the internal container space. Independent temperature control and fire protection systems are installed within the battery compartment to strictly control temperature and safety conditions.

Electrical Compartment: Used for installing electrical equipment including the Power Conversion System (PCS), AC distribution cabinet, DC distribution cabinet, and energy management cabinet. This is the energy conversion and control area of the energy storage system. Fire-resistant partition walls and fire doors are installed between the electrical compartment and battery compartment to achieve electrical isolation.

Equipment Compartment: Some customized cabinets feature an independent equipment compartment for installing auxiliary equipment including temperature control main units, fire suppression cylinders, and UPS power supplies, further improving space utilization and safety.

Doors and Access Ways

Double-leaf access maintenance doors are installed at both ends of the container. Each single door measures no less than 900mm × 2000mm, meeting equipment entry/exit and personnel passage requirements. Door construction uses steel plate of the same material as the container body, equipped with three-point locking mechanisms and sealing gaskets, providing good sealing performance when closed. Observation windows with tempered fire-resistant glass are installed on doors, enabling viewing of the basic in-container conditions without opening the doors.

Maintenance side doors are installed on container sides as needed for routine O&M inspections. In-container access aisle widths are no less than 800mm, meeting personnel passage and equipment handling requirements. The floor is covered with anti-slip insulated rubber matting to enhance O&M safety.

Ventilation and Protection Structures

Air inlet and outlet vents are installed on the container, working with the temperature control system to achieve in-container air circulation. Vents are equipped with dust filter screens and rainproof louvers to prevent rainwater, sand, and insects from entering the container. Filter screens feature a removable and washable design for easy routine maintenance and replacement.

Cable entry openings are provided at the container base, equipped with waterproof sealed cable glands. After cable connection, sealing treatment is applied to prevent moisture and rodent entry. The container roof features drainage slopes to prevent water accumulation and leakage. No heavy objects are permitted on the roof.

Standard hoisting corner castings are installed at the four corners of the container, conforming to ISO container hoisting standards and compatible with universal container hoisting equipment. The base features standard container bottom rails, compatible with container transport vehicles and fixed foundation installation.

1.3.2 Battery Energy Storage System

The battery energy storage system is the core energy storage unit of the outdoor energy storage container, responsible for the storage and release of electrical energy. The current mainstream technology uses lithium iron phosphate (LiFePOâ‚„) lithium-ion batteries, offering advantages including high safety performance, long cycle life, and moderate energy density.

Cell Selection

All Guangdong Lain outdoor energy storage containers use Grade-A lithium iron phosphate cells. Cells comply with GB/T 36276 standard requirements and have passed safety testing and certification by national authoritative institutions. Cell nominal voltage is 3.2V, with capacities covering multiple specifications including 50Ah, 100Ah, 200Ah, and 280Ah, flexibly selectable based on system capacity requirements.

Key Cell Performance Parameters:

Parameter Value
Nominal Voltage 3.2V
Operating Voltage Range 2.5V – 3.65V
Nominal Capacity 50Ah – 280Ah (selectable)
Cycle Life ≥ 6,000 cycles (1C charge/discharge, 80% DOD, 25°C ambient)
Operating Temperature Range Charge: -10°C ~ 55°C; Discharge: -20°C ~ 60°C
Safety Performance Passes nail penetration, crush, hot box, overcharge, and over-discharge safety tests; no fire, no explosion

Battery Module

Multiple cells are combined in series and parallel configurations to form battery modules. Modules feature unified mechanical structure and electrical interfaces for batch production and maintenance convenience. Modules use aluminum alloy enclosures, providing good heat dissipation performance and mechanical strength.

Each module is equipped with an independent acquisition and protection unit, capable of real-time acquisition of voltage and temperature for each individual cell, with cell balancing functionality. Modules have built-in fuses that rapidly isolate faults in the event of internal short-circuit faults, preventing fault propagation.

Standard Module Specification: 16 series × 1 parallel, nominal voltage 51.2V, capacity 100Ah-280Ah (selectable), module capacity 5.12kWh – 14.336kWh.

Battery Cluster

Multiple battery modules are connected in series to form battery clusters, raising the system voltage level to meet high-voltage DC input requirements. Each battery cluster is equipped with an independent high-voltage distribution box (cluster-level management unit) containing DC circuit breakers, fuses, pre-charge resistors, relays, insulation monitoring modules, and current sensors.

DC Circuit Breaker: Provides on/off control of the battery cluster with overcurrent and short-circuit protection functions; automatically trips upon fault.

Fuse: Secondary short-circuit protection that rapidly fuses to interrupt the fault circuit if the circuit breaker fails.

Pre-charge Circuit: During system startup, the bus capacitor is charged through the pre-charge resistor first, avoiding large inrush current damage to equipment at the moment of switch closure.

Insulation Monitoring Module: Real-time monitoring of DC bus insulation resistance to ground. When insulation resistance drops below the threshold, an alarm is triggered and shutdown occurs to prevent electric shock risk.

Current Sensor: Real-time acquisition of battery cluster charge/discharge current, providing current data to the BMS for SOC calculation and overcurrent protection.

Standard Battery Cluster Configuration: Typically composed of 7-15 modules in series, nominal voltage 358.4V – 768V. The mainstream configuration uses 15 series modules with a nominal voltage of 768V. Capacity corresponds to module capacity, with single-cluster capacity of 76.8kWh – 215kWh. A single 20-foot energy storage container can be configured with 8-12 battery clusters, total capacity 1MWh – 2.5MWh; a 40-foot cabinet can be configured with 16-24 battery clusters, total capacity 3MWh – 5MWh.

1.3.3 Power Conversion System (PCS)

The Power Conversion System (PCS) is the core equipment connecting the battery DC system and the AC grid, responsible for bidirectional conversion between DC and AC power. During charging, AC power from the grid is converted to DC power to charge the batteries; during discharging, DC power from the batteries is converted to AC power fed into the grid or supplied to loads.

PCS Operating Principle and Topology

The PCS configured in Lain energy storage containers adopts three-phase two-level or three-level topology structures, implementing bidirectional energy conversion based on IGBT power devices, using SPWM pulse width modulation technology to control output voltage and frequency. The system is equipped with LCL filter circuits to effectively reduce output current harmonics, meeting grid power quality requirements.

The PCS features four-quadrant operation capability, enabling independent regulation of active power and reactive power. In addition to charge/discharge functions, it also provides reactive power compensation and harmonic treatment functions, improving grid power quality.

PCS Core Functions

Function Description
Bidirectional Charge/Discharge Control Supports multiple charge/discharge modes including constant current, constant voltage, and constant power; automatically adjusts charge/discharge power per BMS commands
Grid Synchronization Automatically tracks grid voltage, frequency, and phase in grid-connected mode; seamless grid connection with inrush current less than 10% of rated current
Off-Grid Inversion Independently constructs AC bus in off-grid mode, outputting stable three-phase AC power to supply loads
Grid-Connected/Off-Grid Switching Supports seamless switching between grid-connected and off-grid modes with switching time less than 20ms, ensuring uninterrupted power supply to critical loads
Protection Functions Multiple protection functions including overvoltage, undervoltage, overcurrent, over-temperature, short-circuit, islanding, and insulation fault; rapid shutdown and alarm reporting upon fault
Communication Functions Supports multiple communication interfaces including RS485, CAN, and Ethernet; communicates with BMS and EMS monitoring systems, uploading operational data and receiving control commands

PCS Technical Parameters

Using the mainstream 500kW PCS as an example, core parameters are as follows:

Parameter Value
Rated Power 500kW
DC Side Voltage Range 500V – 850V
AC Side Rated Voltage 380V / 400V (three-phase, four-wire)
Rated Frequency 50Hz
Efficiency Maximum efficiency ≥ 98.5%; overall efficiency ≥ 97.5%
Power Factor 0.9 leading ~ 0.9 lagging (adjustable)
Current Harmonic Distortion Rate ≤ 3% (at rated load)
Protection Rating IP20 (indoor installation type) / IP54 (outdoor installation type)
Cooling Method Air-cooled / liquid-cooled (optional)
Operating Ambient Temperature -20°C ~ +50°C

A single energy storage container can be configured with one or multiple PCS units, matched and selected based on system capacity and discharge rate. For example, a 1MWh/0.5C system is configured with a 500kW PCS, and a 2MWh/1C system is configured with a 2MW PCS.

1.3.4 Battery Management System (BMS)

The Battery Management System (BMS) is the “brain” of the battery system, responsible for core functions including battery status monitoring, safety protection, balancing control, and SOC estimation, ensuring safe, stable, and efficient battery operation.

BMS Architecture

The Lain energy storage system adopts a three-level BMS architecture: Cell Acquisition Unit (BMU) – Cluster Management Unit (BCU) – System Management Unit (BAU), with hierarchical management and high reliability.

Cell Acquisition Unit (BMU): Installed in each battery module, responsible for acquiring voltage and temperature data of individual cells, executing cell balancing functions, and communicating with the cluster management unit via CAN bus.

Cluster Management Unit (BCU): Installed in the high-voltage box of each battery cluster, responsible for acquiring entire-cluster current, total voltage, and insulation resistance, receiving cell data uploaded by BMUs, executing cluster-level protection logic, and communicating with the system management unit.

System Management Unit (BAU): Installed in the electrical compartment control cabinet, responsible for aggregating data from all battery clusters, calculating overall system SOC and SOH, executing system-level protection strategies, interacting with PCS and EMS systems, uploading battery system data, and receiving charge/discharge commands.

BMS Core Functions

Data Acquisition Function: Real-time acquisition of voltage and temperature of all cells, plus battery cluster total voltage, total current, and insulation resistance. Acquisition accuracy meets national standard requirements: voltage acquisition accuracy ±5mV, temperature acquisition accuracy ±1°C.

SOC Estimation Function: Uses a composite algorithm combining ampere-hour integration, open-circuit voltage correction, and Kalman filtering for accurate estimation of battery remaining capacity. SOC estimation accuracy ≤ ±5%.

SOH Estimation Function: Estimates battery state of health by recording parameters including cycle count, charge/discharge capacity, and internal resistance changes, providing a basis for battery life assessment.

Balancing Management Function: Offers both active balancing and passive balancing options. Maximum balancing current reaches 5A, effectively reducing voltage differences between cells, improving overall battery pack capacity utilization and cycle life.

Safety Protection Function: Multiple protection functions including overvoltage protection, undervoltage protection, overcurrent protection, over-temperature protection, low-temperature protection, insulation fault protection, and short-circuit protection. Protection actions are classified into three levels—Level 1 Alarm, Level 2 Alarm, and Level 3 Shutdown—based on fault severity, with graded protection actions executed accordingly.

Fault Diagnosis Function: Automatically diagnoses various battery system faults, locates faulty cells and fault positions, records fault occurrence time and parameters, facilitating O&M troubleshooting.

Data Storage Function: Stores at least 1 year of historical operating data and fault records, supporting data export and analysis.

1.3.5 Power Distribution System

The power distribution system is responsible for energy distribution, on/off control, and protection of the energy storage system, primarily consisting of the DC distribution cabinet, AC distribution cabinet, and lightning protection & grounding devices.

DC Distribution Cabinet

The DC distribution cabinet is installed between the battery compartment and the PCS, responsible for aggregating DC outputs from multiple battery clusters and uniformly connecting to the PCS DC side. The cabinet contains DC circuit breakers, fuses, DC surge protectors, current and voltage sensors, and other devices, implementing on/off control, short-circuit protection, lightning protection, and status monitoring of DC circuits.

The DC distribution cabinet features per-cluster management capability. Each battery cluster corresponds to an independent input circuit with individual on/off control, facilitating separate cluster maintenance and inspection. Insulation monitoring devices are installed within the cabinet to monitor DC bus insulation status to ground in real time.

AC Distribution Cabinet

The AC distribution cabinet is installed between the PCS AC side and the grid/loads, responsible for aggregation, distribution, and grid connection of PCS output power. The cabinet contains AC circuit breakers, contactors, fuses, AC surge protectors, energy metering meters, current and voltage sensors, and other devices.

Grid-connected distribution cabinets are equipped with grid-connection circuit breakers featuring undervoltage trip and overcurrent protection functions, meeting grid connection requirements. Multi-function energy meters are installed within the cabinet to meter charge/discharge energy, supporting peak-valley time-of-use metering, providing a basis for electricity bill settlement.

Lightning Protection and Grounding System

The energy storage container is equipped with a comprehensive lightning protection and grounding system, including power lightning protection, signal lightning protection, and grounding devices. Power lightning protection is configured with Class B + Class C two-stage surge protective devices, installed at the AC incoming line side and DC bus side respectively, effectively withstanding lightning surges and switching overvoltages. Signal lightning protection is installed at the incoming side of communication lines, protecting monitoring equipment and communication interfaces.

A dedicated grounding busbar is installed in the container. All equipment metal enclosures, cabinets, cable trays, and cable shielding layers must be reliably grounded. Grounding resistance meets specification requirements with power-frequency grounding resistance ≤ 4Ω.

1.3.6 Temperature Control System

The temperature control system regulates in-container temperature to ensure batteries and electrical equipment operate in a suitable temperature environment. It is a key system for ensuring battery life and safety. Common temperature control solutions for outdoor energy storage containers are divided into air-cooled temperature control and liquid-cooled temperature control.

Air-Cooled Temperature Control System

The air-cooled temperature control system consists of industrial air conditioning units, ventilation fans, air ducts, temperature sensors, and controllers, achieving in-container temperature regulation through air convection.

Industrial Air Conditioning: Uses dedicated energy storage air conditioning units with cooling, heating, and dehumidification functions, automatically adjusting operating mode and power based on in-container temperature. Units use high-reliability compressors, adapt to wide temperature operating environments, and feature remote monitoring capability.

Ventilation Fans: Configured with intake fans and exhaust fans. When ambient temperature is suitable, natural ventilation cooling is used to reduce air conditioning energy consumption. Fans are equipped with filter screens to ensure clean intake air.

Temperature Control Logic: Multiple temperature sensors are deployed at different positions in the battery compartment to monitor in-container temperature and battery surface temperature in real time. Cooling is activated when in-container temperature exceeds 30°C; heating is activated when below 10°C; ventilation mode is activated when temperature is in the 15°C-25°C range with suitable ambient temperature. Temperature control accuracy: ±2°C.

The air-cooled system offers advantages of simple structure, convenient maintenance, and lower cost, suitable for scenarios with moderate ambient temperatures and lower battery charge/discharge rates.

Liquid-Cooled Temperature Control System

The liquid-cooled temperature control system consists of a chiller unit, coolant distribution unit, cold plates, circulation piping, temperature sensors, and controllers. It removes heat generated by batteries through coolant circulation, achieving higher temperature control accuracy and more uniform heat dissipation.

Chiller Unit: Provides constant-temperature coolant with cooling and heating functions, enabling precise control of coolant inlet and outlet temperatures.

Cold Plates: Installed at the bottom or side of battery modules, in close contact with modules, removing battery heat through heat exchange.

Coolant: Uses environmentally friendly antifreeze with characteristics including freeze resistance, corrosion resistance, and good thermal conductivity.

Control Logic: Real-time monitoring of battery temperature and coolant temperature, automatically adjusting chiller unit power and coolant flow rate to ensure temperature difference between battery cells ≤ 3°C, with battery operating temperature stabilized at approximately 25°C.

The liquid-cooled system offers advantages of high heat dissipation efficiency, good temperature uniformity, and high temperature control accuracy, suitable for energy storage scenarios with high-rate charge/discharge, large capacity, and high-temperature environments.

1.3.7 Fire Protection System

The fire protection system is the last line of defense for energy storage container safety protection, used for detecting and extinguishing incipient fires within the container to prevent accident escalation. Lain energy storage containers adopt an integrated “detection + alarm + suppression” fire protection solution.

Detection System

Multiple detection devices are configured within the container for early warning of fires and hazardous gases:

Smoke Detector: Uses photoelectric smoke detectors installed at the container ceiling, detecting smoke generated during incipient fire stages with high sensitivity and fast response.

Heat Detector: Uses differential/fixed-temperature heat detectors monitoring abnormal temperature rise within the container, assisting in fire status determination.

Combustible Gas Detector: Detects combustible gases including carbon monoxide and hydrogen generated during battery thermal runaway, providing early warning before fire occurrence.

Flame Detector: Certain high-safety-grade configurations include infrared flame detectors for rapid open flame detection.

Alarm System

The fire control unit receives detection signals and triggers alarms in a graded manner:

Level 1 Early Warning: Combustible gas concentration reaches the early warning threshold; audible and visual alarm is triggered and uploaded to the monitoring system, prompting O&M personnel to inspect.

Level 2 Fire Alarm: Smoke or heat detectors trigger a fire alarm; intense audible and visual alarm is activated, interlocked shutdown of air conditioning and ventilation fans, cutting of non-fire-related power within the container, and simultaneous upload of fire alarm signals to the monitoring platform and the owner’s fire protection system.

Level 3 Fire Suppression: Upon confirmed fire, the suppression device is automatically or manually activated to extinguish the fire.

Suppression System

The mainstream solution uses heptafluoropropane (FM200) gas fire suppression systems. Some scenarios use aerosol suppression or water-based suppression systems.

Heptafluoropropane (FM200) Suppression System: Composed of heptafluoropropane cylinders, actuating valves, piping, and nozzles. Upon activation, heptafluoropropane gas is released to rapidly extinguish fire through chemical inhibition. It offers high suppression efficiency, no secondary damage to equipment, and excellent insulation properties, making it suitable for electrical equipment fires. The system features three activation methods: automatic activation, manual activation, and mechanical emergency activation.

Aerosol Suppression System: Uses hot aerosol suppression devices that generate aerosol extinguishant upon activation. Fast suppression speed, no high-pressure cylinders required, simple maintenance, suitable for small-space fire suppression.

Explosion-Proof Pressure Relief Device: Explosion-proof pressure relief openings are installed on the container. When in-container pressure rises, they automatically open for pressure relief, preventing container explosion or deformation.

1.3.8 Monitoring and Energy Management System (EMS)

The Energy Management System (EMS) is the master control center of the energy storage system, responsible for system-wide data acquisition, operation monitoring, energy dispatch, fault management, and report statistics.

System Architecture

The EMS adopts a layered distributed architecture, divided into field layer, control layer, and application layer:

Field Layer: Various sensors and smart devices, responsible for data acquisition and execution of control commands.

Control Layer: Local monitoring host, responsible for on-site data aggregation, logic control, and local human-machine interaction.

Application Layer: Cloud platform servers, responsible for data storage, remote access, big data analysis, and multi-site management.

Core Functions

Real-Time Monitoring: Displays system topology diagrams in graphical interface, real-time display of equipment operating status and key parameters, including battery SOC, charge/discharge power, voltage, current, temperature, and alarm information, with data refresh period ≤ 1 second.

Energy Dispatch: Supports multiple operating strategies including scheduled charge/discharge, peak-valley arbitrage, demand management, output smoothing, and frequency/voltage regulation. Automatically controls charge/discharge power and timing per preset strategies. Supports switching between manual control and automatic control modes.

Alarm Management: Multi-level alarm functionality with customizable alarm thresholds and alarm levels. Real-time pop-up alerts upon alarm occurrence, supporting multiple alarm notification methods including audible/visual alarms, SMS notifications, and APP push. Automatically records all alarm information, queryable by time, level, and type for historical alarms.

Report Statistics: Automatically generates daily, weekly, monthly, and annual operating reports, including charge/discharge energy, cycle count, electricity revenue, equipment operating hours, and fault statistics. Supports report export and printing.

Permission Management: Multi-level user permission management; different users have different operating permissions, ensuring system operation security.

Remote Operation & Maintenance: Supports remote access, remote parameter configuration, remote program upgrade, and remote fault diagnosis, significantly reducing O&M costs and improving response speed.

Communication Methods

Local Communication: CAN bus, RS485 bus, and Ethernet communication between devices.

Remote Communication: Supports multiple remote communication methods including Ethernet, 4G/5G, and WiFi, selectable based on on-site network conditions.

1.4 Standard Product Technical Parameter Tables

1.4.1 20-foot Standard Outdoor Energy Storage Container Parameters

Item Parameter Specification Remarks
Container Dimensions (L×W×H) 6058mm×2438mm×2896mm Standard 20-foot shipping container
Container Protection Rating IP54 Outdoor type
Corrosion Protection Rating C5-M Suitable for coastal high salt-spray environments
Rated Energy Storage Capacity 1MWh / 1.5MWh / 2MWh Optional
Rated Power 500kW / 1MW 0.5C/1C optional
Battery Type Lithium Iron Phosphate (LFP) Battery —
DC Rated Voltage 768V 15-series module configuration
AC Output Voltage 380V Three-phase Four-wire —
System Efficiency ≥90% AC-AC comprehensive efficiency
Cycle Life ≥6000 cycles 80% DOD, 25℃
Operating Ambient Temperature -30℃~+55℃ —
Temperature Control Method Forced air cooling / Liquid cooling optional —
Fire Suppression Method Heptafluoropropane gas fire extinguishing —
Protection Rating IP54 —
Weight Approx. 18-25 tons Varies with capacity
Design Service Life ≥15 years —

1.4.2 40-foot Standard Outdoor Energy Storage Container Parameters

Item Parameter Specification Remarks
Container Dimensions (L×W×H) 12192mm×2438mm×2896mm Standard 40-foot shipping container
Container Protection Rating IP54 Outdoor type
Corrosion Protection Rating C5-M Suitable for coastal high salt-spray environments
Rated Energy Storage Capacity 3MWh / 4MWh / 5MWh Optional
Rated Power 1.5MW / 2.5MW 0.5C/1C optional
Battery Type Lithium Iron Phosphate (LFP) Battery —
DC Rated Voltage 768V / 1500V Optional
AC Output Voltage 380V / 10kV LV/ HV grid connection optional
System Efficiency ≥90% AC-AC comprehensive efficiency
Cycle Life ≥6000 cycles 80% DOD, 25℃
Operating Ambient Temperature -30℃~+55℃ —
Temperature Control Method Forced air cooling / Liquid cooling optional —
Fire Suppression Method Heptafluoropropane gas fire extinguishing + combustible gas detection —
Weight Approx. 35-50 tons Varies with capacity
Design Service Life ≥15 years —

1.5 Applicable Standards and Specifications

The design, production, installation, commissioning, and acceptance of this outdoor energy storage container strictly comply with the following national and industry standards:

  • GB/T 36276-2018 “Lithium-ion Batteries for Electric Energy Storage”
  • GB/T 34120-2017 “Technical Specification for Power Converter System of Electrochemical Energy Storage System”
  • GB/T 34131-2017 “Technical Requirements for Battery Management System of Electric Energy Storage”
  • GB 51048-2014 “Code for Design of Electrochemical Energy Storage Power Station”
  • GB 50303-2015 “Code for Acceptance of Construction Quality of Building Electrical Engineering”
  • GB 50168-2018 “Code for Construction and Acceptance of Cable Lines in Electrical Installation Engineering”
  • GB 50169-2016 “Code for Construction and Acceptance of Earthing Device in Electrical Installation Engineering”
  • GB 50261-2017 “Code for Construction and Acceptance of Automatic Sprinkler Fire Extinguishing System”
  • GB 50370-2005 “Code for Design of Gas Fire Extinguishing Systems”
  • GB/T 14285-2006 “Technical Code for Relay Protection and Safety Automatic Devices”
  • GB 50057-2010 “Code for Design Protection of Structures against Lightning”
  • DL/T 1812-2018 “Code for Operation and Maintenance of Electrochemical Energy Storage Power Station”
  • NB/T 10394-2020 “Acceptance Code for Electrochemical Energy Storage Power Station”
  • T/CNESA 1201-2018 “Technical Specification for Prefabricated Cabin Type Lithium-ion Battery Energy Storage System”

The installation and commissioning of an outdoor energy storage container is a systematic project involving multiple specialized trades including hoisting operations, electrical construction, equipment installation, and system commissioning. Adequate preparatory work must be completed before construction to ensure a safe, orderly, and efficient construction process. Guangzhou Lain Intelligent System Development Co., Ltd. recommends that all construction units complete the five major aspects of preparation — organization, technology, site, materials, and safety — before project commencement. Construction shall not commence without completing the preparatory work.

2.1 Construction Organization Preparation

2.1.1 Project Organization Structure Establishment

For each energy storage container installation project, the construction unit shall establish a dedicated project department, define the staffing and division of responsibilities for each position, and implement the project manager responsibility system. The core positions of the project department shall include at least the project manager, technical director, safety director, and quality director. Each specialized construction crew shall be assigned a corresponding crew leader.

Project Manager

The project manager is the primary person responsible for the project, with overall responsibility for project schedule, quality, safety, cost, and coordination. Main responsibilities include:

  • Establishing the project management team and defining the division of responsibilities for each position;
  • Organizing the preparation of the project construction organization design and special construction plans;
  • Formulating the project construction schedule, coordinating the arrival of personnel, equipment, and materials;
  • Coordinating relationships with the owner, supervision engineer, manufacturer, local authorities, and other parties;
  • Responsible for overall project production safety management, implementing safety management systems;
  • Organizing project self-inspection, pre-acceptance, and completion acceptance;
  • Responsible for the compilation and archiving of project construction documents.

The project manager shall hold a Class II or above Registered Constructor qualification in mechanical and electrical engineering, with more than 3 years of experience in energy storage or electrical project management, and be familiar with the installation and commissioning processes and relevant specifications and standards for energy storage containers.

Technical Director

The technical director is responsible for all technical management work of the project, ensuring that the construction process complies with specifications and design requirements. Main responsibilities include:

  • Participating in the preparation of construction organization design and special plans, responsible for reviewing technical plans;
  • Organizing construction drawing review and technical disclosure sessions;
  • Resolving technical difficulties during construction, approving technical changes;
  • Guiding on-site construction personnel to construct in accordance with specifications and drawings;
  • Responsible for the preparation, review, and archiving of construction technical documents;
  • Participating in quality acceptance and fault diagnosis work.

The technical director shall hold an intermediate or above Electrical Engineer title, with technical management experience in energy storage systems or electrical engineering construction.

Safety Director (Full-time Safety Officer)

The safety director is responsible for the daily management of project production safety and must hold a valid safety officer certificate (Class C Safety Officer Certificate). Main responsibilities include:

  • Implementing production safety management systems, conducting safety education and training, and safety technical disclosures;
  • Conducting daily on-site safety inspections, identifying safety hazards, and supervising rectification;
  • Supervising construction personnel in the correct use of safety protective equipment;
  • Providing side-station supervision for hazardous operations and handling work permits;
  • Participating in safety accident investigations and handling;
  • Responsible for the compilation and archiving of safety documents.

Quality Director

The quality director is responsible for project construction quality management and inspection work. Main responsibilities include:

  • Formulating quality inspection plans, defining quality control points;
  • Conducting quality inspection of incoming materials and equipment;
  • Performing quality inspections and acceptance for each construction process; the previous process shall not proceed to the next process if unqualified;
  • Participating in concealed works acceptance, sub-division works acceptance, and completion acceptance;
  • Responsible for tracking rectification and verification of quality issues;
  • Responsible for the compilation and archiving of quality acceptance documents.

Specialized Construction Personnel Configuration

Construction personnel shall be allocated according to project scale, including at least the following trades:

  • Rigger: Responsible for container hoisting operations; must hold a hoisting operation certificate and have experience in large equipment lifting;
  • Electrician: Responsible for electrical wiring, grounding construction, insulation testing, etc.; must hold a low-voltage/high-voltage electrician certificate with high-voltage electrical construction experience;
  • Installer: Responsible for equipment installation, pipeline connection, container fixing, etc.;
  • Commissioning Engineer: Responsible for system commissioning and trial operation; must have energy storage system commissioning experience;
  • General Laborer: Assists various specialized trades in completing auxiliary work.

For a single 20-foot energy storage container installation project, the recommended personnel configuration is: 1 project manager, 1 technical director, 1 safety officer, 2 riggers, 2 high-voltage electricians, 4 installers, 1 commissioning engineer, and 3 general laborers, totaling 15 personnel. For multi-unit projects, personnel may be increased or decreased as appropriate.

2.1.2 Construction Management System Establishment

The project department shall establish and improve various management systems to ensure the standardized operation of the project:

  • Technical Disclosure System: Implement three-level technical disclosure, i.e., the project technical director discloses to construction crew leaders, and crew leaders disclose to construction personnel, ensuring that every construction worker understands the construction requirements, technical standards, and safety precautions.
  • Safety Management System: Including safety education and training system, safety inspection system, hazardous operation approval system, safety reward and punishment system, etc.
  • Quality Inspection System: Implement the three-inspection system — self-inspection, mutual inspection, and handover inspection. Each process must pass inspection before proceeding to the next process.
  • Schedule Management System: Formulate a detailed construction schedule, verify daily completion status, adjust resource allocation in a timely manner, and ensure completion on schedule.
  • Equipment and Materials Management System: Establish incoming acceptance, storage, requisition, and return ledgers for equipment and materials to ensure accounts match actual inventory and prevent damage and loss.
  • Site Civilized Construction System: Standardize on-site material stacking, construction power, and construction water management; keep the site clean and achieve “work completed, site cleaned.”

2.2 Technical Preparation Work

2.2.1 Construction Drawing Review

Before commencement, the project manager shall organize technical personnel and construction crew leaders to familiarize themselves with the construction drawings and this installation manual. The manufacturer’s technical support personnel shall conduct the drawing review and technical disclosure. The drawing review shall focus on the following key items:

  • Foundation drawings: Verify whether foundation dimensions, embedded part positions, elevations, and load-bearing requirements match the container dimensions; check whether the grounding reservation points are reasonably positioned.
  • Electrical system drawings: Verify DC and AC circuit wiring diagrams; confirm cable models, specifications, routing, and terminal numbers; verify that protection settings comply with requirements.
  • System schematic diagrams: Familiarize with the overall system architecture, connection relationships between equipment, control logic, and protection principles.
  • Equipment layout drawings: Verify the installation positions of in-container equipment, aisle dimensions, and operation and maintenance space.
  • Interface drawings: Confirm the positions and specifications of external power access points and communication access points; verify that interface parameters match.
  • Fire protection and temperature control drawings: Verify the routing and installation requirements of fire protection piping and ventilation ducting.

Issues found during drawing review shall be reported in writing to the design institute or manufacturer in a timely manner. Construction may only proceed after the issues are clarified and formal change documents are issued. Modifying design drawings without authorization is strictly prohibited. The review process shall produce a drawing review record signed by all participating parties, serving as both construction basis and completion documentation.

2.2.2 Construction Plan Preparation

The project department shall prepare a special construction plan based on project characteristics, which shall be reviewed and approved by the construction unit’s technical director and submitted to the supervision engineer and owner for review and approval before implementation. For hazardous operations such as hoisting operations, high-voltage operations, and hot work, separate special safety construction plans shall be prepared.

The construction organization design and special plans shall include at least the following:

  • Project overview: Project background, construction scale, number and capacity of energy storage containers, construction scope, and schedule requirements.
  • Compilation basis: Relevant national standards, industry specifications, design drawings, manufacturer manuals, etc.
  • Construction deployment: Project organization structure, personnel allocation, construction zoning, construction sequence, and schedule plan.
  • Main construction methods: Construction methods and operational key points for each process, including foundation construction, container hoisting, equipment installation, electrical wiring, and system commissioning.
  • Quality assurance measures: Quality control point settings, inspection standards, and preventive measures for common quality defects.
  • Safety assurance measures: Hazard source identification, safety protection measures, and emergency rescue plans.
  • Civilized construction and environmental protection measures.
  • Construction machinery and materials plan.

For large-scale energy storage power station projects where multiple outdoor energy storage containers are constructed simultaneously, a general layout plan shall also be prepared, with reasonable planning of equipment stacking areas, material storage areas, temporary construction power, and temporary access roads to avoid interference from cross-operations.

2.2.3 Technical Disclosure

Full personnel technical disclosure must be conducted before construction. The disclosure content shall be comprehensive and detailed to ensure that every construction worker masters the operational key points and safety requirements. Technical disclosure is divided into three levels:

Level 1: Project-level Disclosure

Conducted by the project manager and technical director to all management personnel and crew leaders. Main content includes: overall project situation, construction organization design, overall schedule plan, quality objectives, safety objectives, main construction plans, major hazard sources and prevention measures, and coordination procedures between all parties.

Level 2: Crew-level Disclosure

Conducted by each specialized crew leader to the construction personnel of their crew. Main content includes: the construction scope of the crew, specific construction methods, operational procedures, quality standards, process interface requirements, safety precautions, and hazard point prevention measures.

Level 3: Pre-task Disclosure

Before daily work, the crew leader conducts a pre-shift disclosure for the day’s work content, clarifying the day’s work tasks, division of labor, operational key points, and safety precautions, and checking the condition of construction personnel and the wearing of protective equipment.

All technical disclosures shall be documented in writing, signed by both the disclosing party and the receiving party. Disclosure records shall be filed in the project archives. Personnel who have not received disclosure shall not be allowed to work on site.

2.3 Site Survey and Site Preparation

2.3.1 On-site Environment Survey

Before equipment arrival, the technical director and safety officer shall conduct a detailed survey of the installation site to confirm whether on-site conditions meet construction requirements. Survey contents include:

  • Site basic conditions: Measure site dimensions to confirm whether they meet the space requirements for container placement and hoisting operations. At least 1.5 meters of operation and maintenance aisle shall be reserved around the container, and an operating radius of no less than 10 meters shall be reserved on the hoisting operation side to meet crane outrigger and lifting operation requirements.
  • Site load-bearing conditions: Verify the ground load-bearing capacity of the site. The fully loaded weight of an energy storage container can reach 20-50 tons. The foundation ground load-bearing capacity shall meet design requirements to avoid settlement. The ground in the hoisting operation area shall be solid, and load-bearing verification shall be performed at crane outrigger positions. Steel plates shall be laid for reinforcement when necessary.
  • Transportation route conditions: Check the transportation vehicle route, confirming whether road width, height clearances, turning radius, and bridge load-bearing capacity meet the requirements for large container transport vehicles. Check for obstacles such as overhead power lines, trees, and height limit gantries along the route. If the route does not meet requirements, clearing, widening, or reinforcement shall be carried out in advance.
  • Surrounding environment conditions: Survey whether there are flammable or explosive sites, corrosive gas sources, or strong electromagnetic interference sources in the vicinity, and confirm compliance with the deployment environmental requirements for energy storage containers. Confirm surrounding drainage conditions to avoid water accumulation flooding the container base.
  • Power access conditions: Verify the grid access point location, voltage level, and capacity margin; confirm the configuration of grid-connection interface devices.
  • Communication access conditions: Confirm whether Ethernet, 4G/5G signals are available on site to meet remote monitoring system communication requirements.
  • Temporary construction conditions: Confirm temporary construction power and water connection points, and confirm on-site office and material storage areas.

2.3.2 Site Foundation Requirements

Outdoor energy storage containers must be installed on dedicated concrete foundations. Direct placement on dirt ground or ordinary asphalt pavement is strictly prohibited. The foundation shall be designed by a qualified design institute and meet load-bearing, seismic, waterproofing, and grounding requirements.

Foundation Types

Two foundation types are commonly used: strip foundations and integral raft foundations:

  • Strip foundation: Concrete strip foundations are placed along the two main load-bearing beams at the bottom of the container. Simple construction and low cost; suitable for sites with good geological conditions.
  • Integral raft foundation: A monolithic reinforced concrete raft slab is cast. The foundation has good integrity, uniform load distribution, and strong anti-settlement capability; suitable for sites with poor geological conditions and large-capacity energy storage containers.

Foundation Technical Requirements

  • Concrete strength grade shall not be lower than C30, with double-layer bidirectional rebar configured inside the foundation. Rebar specifications and spacing shall comply with design requirements.
  • Foundation surface flatness deviation shall not exceed 5mm/m, and overall elevation deviation shall not exceed ±10mm.
  • Drainage slopes and drainage channels shall be provided around the foundation, with a slope of no less than 3‰, to ensure timely rainwater drainage and no water accumulation around the foundation.
  • The foundation shall be raised no less than 200mm above ground level to prevent ground water from seeping into the container base.
  • Embedded anchor bolts or embedded steel plates shall be provided in the foundation, with position deviation not exceeding ±5mm. Embedded parts shall be treated with anti-corrosion coating.
  • Grounding flat steel lead-out points shall be reserved in the foundation, with no fewer than 2 lead-out points, reliably connected to the grounding grid.
  • The foundation seismic fortification intensity shall not be lower than local seismic fortification requirements.

Foundation Acceptance

After foundation construction is completed, curing shall be carried out until the design strength is reached (typically 28 days of curing) before container installation. Foundation acceptance shall be organized before installation, including: foundation dimensions, elevation, flatness, embedded part positions, grounding resistance, and appearance quality. Only after acceptance is passed and the acceptance record is signed may the next step of construction proceed.

2.3.3 Temporary Construction Facilities Setup

Necessary temporary facilities shall be set up based on site conditions:

  • Temporary construction power: Connect temporary construction power from the site power distribution point, configure three-level distribution with two-level protection. Distribution boxes shall comply with safety specifications and meet the power demands of construction machinery and lighting.
  • Material and equipment storage area: Set up dedicated equipment and material storage areas with rainproof, moisture-proof, and anti-theft measures. Precision electrical equipment shall be stored in dry, ventilated locations, protected from sun and rain.
  • Safety warning facilities: Set up barricades and warning signs in the construction area. Prominent safety warning signs shall be placed in hazardous areas, and warning lights shall be installed at night.
  • Fire protection facilities: Configure sufficient fire extinguishers, fire sand, and other firefighting equipment on site to meet construction site fire safety requirements.

2.4 Equipment and Material Incoming Acceptance

2.4.1 Equipment Incoming Acceptance

After the outdoor energy storage container and supporting equipment arrive at the site, joint unpacking inspection shall be conducted by four parties: the owner, supervision engineer, construction unit, and manufacturer. Acceptance shall be signed only after passing inspection.

Acceptance Procedure

1. Check the delivery note against the purchase contract to confirm that equipment models, quantities, and specifications match the contract.

2. Check whether the external packaging of the container and equipment is intact, with no signs of collision, damage, or rain exposure.

3. Open the packaging and inspect the equipment appearance for deformation, paint peeling, or rust; check for damaged or missing components.

4. Verify that random technical documents such as factory certificates, test reports, instruction manuals, and factory test records are complete.

5. Verify that equipment nameplate parameters match design requirements.

6. Document the acceptance process with records and photographic evidence. Report any issues found to the manufacturer for handling in a timely manner.

Container Appearance Acceptance Key Points

  • Container dimensions comply with design requirements; no obvious deformation, dents, or scratches overall.
  • Surface paint film is intact, no peeling, runs, or color difference; anti-corrosion coating has no damage.
  • Doors open and close smoothly, locks are intact, and sealing strips show no detachment or cracking.
  • Vents and louvers are intact; filter screens are complete and undamaged.
  • Lifting corner castings are intact with no deformation or cracks.
  • Container markings and nameplates are clear and complete, including product name, model, capacity, factory serial number, production date, and manufacturer information.

Internal Equipment Acceptance Key Points

  • Equipment layout inside the container matches the drawings, with no displacement, looseness, or detachment.
  • All equipment appearance is intact, no collision damage; terminal connections are not loose.
  • Cables are neatly bundled with clear markings, no damage or exposed conductors.
  • Random spare parts and special tools are complete and consistent with the packing list.

If equipment damage, shortages, or parameter discrepancies are found during acceptance, records and photographs shall be taken. The manufacturer shall be responsible for replacement or replenishment. Installation shall not proceed until the issues are resolved. After acceptance is passed, an equipment incoming acceptance record shall be signed by all parties.

2.4.2 Construction Materials Incoming Acceptance

Materials required for construction, including cables, cable trays, grounding materials, fasteners, and sealing materials, shall undergo quality acceptance upon arrival:

  • Check whether material models, specifications, and quantities match the material list.
  • Inspect material appearance quality: cable insulation layers have no damage, cable trays have no deformation with intact galvanized coating, and fasteners have no rust.
  • Verify that factory certificates, quality test reports, and material certification documents are complete and valid.
  • Conduct sampling and third-party testing for critical materials such as high-voltage cables and grounding flat steel to ensure performance meets standard requirements.
  • Non-conforming materials are strictly prohibited from use and shall be promptly removed from site.

2.4.3 Construction Machinery and Instruments Preparation

Configure the corresponding construction machinery and testing instruments according to the construction plan. Check equipment condition before entering the site to ensure performance is intact. Measuring instruments shall be within their calibration validity period.

  • Hoisting and transport machinery: Truck crane, forklift, wire ropes, shackles, lifting slings, leveling instruments, jacks, etc.
  • Installation machinery: Welding machine, cutting machine, impact drill, wrenches, torque wrench, crimping pliers, wire strippers, handheld drill, etc.
  • Electrical testing instruments: Multimeter, clamp ammeter, insulation resistance tester, ground resistance tester, loop resistance tester, phase sequence meter, power quality analyzer, etc.
  • Safety protective equipment: Safety helmet, safety harness, insulated shoes, insulated gloves, gas mask, protective goggles, warning tape, emergency first aid kit, etc.
  • Other tools: Two-way radios, tape measure, spirit level, marker pens, cable ties, etc.

All construction machinery and instruments shall be logged in a ledger, with regular maintenance to ensure normal operation during construction.

2.5 Safety Protection Preparation

2.5.1 Safety Education and Training

All personnel entering the construction site must undergo three-level safety education and training, and may only begin work after passing assessment. Training contents include:

  • Safety production laws, regulations, and company safety management systems;
  • Project construction site hazard sources and prevention measures;
  • Safety operating procedures for each trade;
  • Safety requirements for hazardous operations such as work at heights, hoisting operations, electrical operations, and hot work;
  • Correct usage methods of safety protective equipment;
  • Emergency response and self-rescue/mutual-rescue knowledge;
  • Energy storage system safety precautions and battery safety protection knowledge.

Special operation personnel such as electricians, riggers, and welders must hold valid certificates within their validity period. Working without certification is strictly prohibited.

2.5.2 Hazard Source Identification and Prevention

Before commencement, the safety director shall organize hazard source identification for the entire construction process and formulate special prevention measures for major hazard sources. The main hazard sources and prevention measures for energy storage container installation are as follows:

Hazard Source Risk Level Prevention Measures
Hoisting operation overturning, falling objects Major Prepare special hoisting plan; solidly support crane outriggers; set up warning zone in hoisting area; dedicated signal person; no personnel under suspended loads; inspect slings and rigging before lifting
High-voltage electric shock Major Implement lockout/tagout procedures (power off, voltage verification, grounding, tagging); dedicated supervision for high-voltage operations; use certified insulated tools; operators hold valid certificates
Fall from height Significant Wear safety harness for work at heights; erect qualified scaffolding; install guardrails at openings and edges; prevent tools and materials from falling
Battery short circuit causing fire Significant Use insulated tools for battery operations; strictly prohibit short circuiting positive and negative terminals; wear protective equipment; configure firefighting equipment on site
Hot work fire Significant Obtain hot work permit; clear combustible materials in the vicinity; dedicated supervision; configure fire extinguishing equipment; verify no ignition sources remains after work
Mechanical injury General Operate machinery correctly; wear protective equipment; ensure equipment guards are intact; prohibit unauthorized operations

2.5.3 Emergency Response Plan Preparation

The project department shall prepare a production safety accident emergency response plan, establishing emergency handling procedures for possible accidents such as hoisting injuries, electric shock, fire, and falls from height; defining the emergency organization structure and personnel responsibilities; and equipping emergency supplies.

The emergency response plan shall primarily include:

  • Emergency organization structure and personnel responsibilities;
  • Accident reporting procedures and contact information;
  • Emergency handling measures for various types of accidents;
  • Emergency supplies and equipment list;
  • Emergency evacuation routes and assembly points;
  • Contact information for nearby hospitals, fire departments, and emergency services.

Emergency drills shall be organized before commencement to ensure construction personnel are familiar with emergency procedures and handling methods.

The on-site installation and construction of the outdoor energy storage container follows the principle of “foundation first, then equipment; exterior first, then interior; mechanical first, then electrical.” The construction process sequence is: foundation re-survey and embedded part treatment, container hoisting and positioning, container fixing and sealing treatment, internal equipment installation and calibration, and auxiliary facility installation. Each process must pass quality inspection before proceeding to the next process.

3.1 Foundation Re-survey and Pre-construction Preparation

3.1.1 Foundation Re-survey

Before container hoisting, surveyors shall conduct a comprehensive re-survey of the concrete foundation to confirm that foundation parameters meet installation requirements:

  • Elevation re-survey: Use a level to measure the foundation surface elevation, taking multiple measurement points and averaging. The overall foundation elevation deviation shall not exceed ±10mm, and the elevation difference between the two ends of the same foundation shall not exceed 5mm. If the elevation deviation exceeds the limit, high-strength grouting material shall be used for leveling.
  • Flatness re-survey: Use a 2-meter straightedge with a feeler gauge to measure the foundation surface flatness. The flatness deviation shall not exceed 3mm per meter, and the overall flatness deviation shall not exceed 5mm. Raised areas on the surface shall be ground smooth, and recessed areas shall be repaired with leveling mortar.
  • Embedded part position re-survey: Based on the container anchor bolt hole position drawings, measure the positions of embedded anchor bolts or embedded steel plates. The position deviation in both longitudinal and transverse directions shall not exceed ±5mm, and the embedded part elevation deviation shall not exceed ±3mm. If the position deviation exceeds the limit, correction or re-fabrication of the embedded parts shall be carried out.
  • Grounding lead-out point inspection: Check whether the position and quantity of reserved grounding flat steel lead-out points in the foundation comply with design requirements. The lap length of the lead-out flat steel shall meet welding requirements.
  • Foundation appearance inspection: Check the foundation surface for quality defects such as cracks, honeycombing, surface voids, or exposed rebar. Defects shall be repaired per specification requirements. Foundation drainage facilities around the perimeter shall be intact with no water accumulation.

After the re-survey is completed, a foundation re-survey record shall be issued and signed by the supervision engineer for acceptance. Hoisting operations may proceed only after the foundation is confirmed qualified.

3.1.2 Pre-hoisting Preparation Work

  • Hoisting plan confirmation: Before hoisting operations, reconfirm that the hoisting plan has been approved. The crane operator, signal person, and riggers shall all hold valid certificates with clear division of labor.
  • Crane and rigging inspection: Check that the truck crane is in good condition, with no faults in outriggers, hook, wire ropes, or hydraulic system. The crane’s rated lifting capacity shall meet hoisting requirements. Inspect wire ropes, slings, shackles, and other rigging for integrity — no broken wires, wear, or corrosion — with rated loads meeting the hoisting weight requirements and valid certificates.
  • Hoisting area clearance: Clear obstacles in the hoisting operation area. Level and compact the ground at crane outrigger positions. Place sleepers or steel plates under outriggers to increase the bearing area and prevent ground settlement during hoisting.
  • Warning zone setup: Set up warning tape and warning signs within the hoisting operation radius. Assign dedicated personnel to guard the area. Unauthorized personnel are strictly prohibited from entering the hoisting area.
  • Container inspection: Recheck the container appearance for damage. Confirm that internal equipment has not shifted or loosened. Close and lock the container doors. Confirm that the container lifting points are intact and clear debris from the lifting points.
  • Technical disclosure: Conduct a special safety technical disclosure for all personnel participating in hoisting operations before lifting, clarifying command signals, hoisting procedures, and precautions.
  • Weather confirmation: Hoisting operations shall be conducted only under favorable weather conditions. Hoisting is prohibited during severe weather such as winds of Force 6 or above, heavy rain, or heavy fog.

3.2 Container Hoisting and Positioning Operations

The hoisting of an outdoor energy storage container is a large equipment lifting operation. Safety regulations for hoisting operations must be strictly observed, and operations shall be performed by certified professional personnel to ensure a safe and stable hoisting process.

3.2.1 Rigging Installation

Select appropriate rigging based on the container weight and lifting point positions. Priority shall be given to using a container-specific spreader beam with four-corner lifting to ensure uniform horizontal force on the container. When no special spreader beam is available, four equal-length wire ropes may be used, each connected to the standard lifting corner castings at the four corners of the container.

Protective corner pads shall be placed at contact points between wire ropes and container edges to prevent the wire ropes from being cut by sharp edges and to protect the container paint from damage.

After rigging is connected, the hoisting signal person shall check that all lifting points are evenly loaded, wire ropes show no twisting, and shackles are fully tightened.

Slowly lift the hook. Once the wire ropes are slightly tensioned, stop lifting and recheck that all lifting point connections are secure and the container is balanced without tilting. Only after confirmation may formal lifting proceed.

3.2.2 Hoisting Operation

The hoisting signal person issues the lifting command, and the crane slowly raises the hook, lifting the container approximately 200-300mm above the ground before stopping.

Hover check: Observe the container balance condition, check the rigging load condition, and check for crane outrigger settlement. Only after confirming no abnormalities may lifting continue.

The hoisting process shall remain stable with uniform speed, avoiding sudden stops or starts. The lifting height shall clear obstacles above the foundation by at least 500mm.

Dedicated personnel shall direct the hoisting process. The crane operator shall strictly follow command signals. Standard hand signals combined with two-way radios shall be used, with unified radio channels and clear signals.

Personnel are strictly prohibited from standing under the container or within the hoisting radius. All personnel shall evacuate to safe areas.

3.2.3 Positioning and Initial Alignment

After the container is hoisted to directly above the foundation, lower it slowly. Stop lowering at approximately 100mm above the foundation surface, and manually assist in aligning the anchor bolts with the mounting holes.

After aligning the holes, lower the container slowly. The landing process shall remain stable to avoid impact on the foundation.

After the container is fully seated, perform a preliminary check of the container position. Adjust the container’s longitudinal and transverse position so that the container centerline coincides with the foundation centerline, with position deviation not exceeding 10mm.

Use a spirit level to measure the levelness of the container top and bottom. Use jacks for fine adjustment of both the transverse and longitudinal levelness. The deviation shall not exceed 2mm/m, and the overall levelness deviation shall not exceed 5mm.

After initial alignment is completed, re-check the container position and levelness. Only after confirmation may the next fixing operation proceed.

3.3 Container Fixing and Sealing Treatment

3.3.1 Anchor Bolt Fixing

If embedded anchor bolts are used, insert the anchor bolts after the container is seated, place washers and nuts, and tighten the nuts evenly in a diagonal alternating sequence to avoid container deformation from single-side loading.

Use a torque wrench for tightening. The tightening torque is determined by the bolt specification: M20 bolts are approximately 280N·m, M24 bolts are approximately 460N·m. Refer to design requirements for specific values.

If embedded steel plate welding is used for fixing, weld the container bottom base to the embedded steel plates. Use intermittent welding with a weld height of no less than 6mm. After welding, remove welding slag and apply anti-rust primer and finishing paint for corrosion protection.

After fixing is completed, re-measure the container levelness and position deviation. If there are changes, readjust to ensure compliance with accuracy requirements.

Fill anchor bolt holes and gaps with waterproof sealant to prevent rainwater ingress. Apply anti-rust grease to exposed bolt portions and install protective caps.

3.3.2 Container Bottom Sealing and Waterproofing Treatment

1. Clean the gap between the container bottom and the foundation, removing debris and dust.

2. Fill the bottom of the gap with foam backing rod, with a filling depth of approximately 2/3 of the gap width.

3. Apply neutral silicone structural weatherproof sealant. The sealant shall be continuous, full, and uniform — free of bubbles and breaks — with the surface smoothed and trimmed to ensure a tight seal.

4. Create a waterproof slope at the bottom perimeter of the container using cement mortar, sloping outward at no less than 5%, to prevent water accumulation from seeping along the container base.

Avoid touching or exposing the sealant to water before curing. After curing, inspect the sealing quality and apply additional sealant to any cracks or gaps found.

3.3.3 Container Appearance Restoration and Markings

Inspect the container surface for paint damage or scratches that may have occurred during hoisting. Repair any damage using paint of the same color to ensure intact appearance.

Post safety warning signs at prominent positions on the container, including “CAUTION: Electric Shock,” “Flammable and Explosive,” “Authorized Personnel Only,” and “Fire Extinguisher Location” signs.

Post equipment identification plates and operating status identification signs.

3.4 Internal Equipment Installation and Calibration

The core equipment inside Guangzhou Lain outdoor energy storage containers has been factory-installed and secured. During transportation, equipment may shift or loosen. Comprehensive on-site inspection and calibration are required. Some accessories shipped separately for assembly require on-site installation.

3.4.1 Battery Rack Installation and Calibration

1. Open the battery compartment door and ventilate for 10 minutes before entering. Check the compartment for unusual odors or abnormalities.

2. Check whether the fixing bolts of each battery rack are loose. If loose, tighten to the specified torque.

3. Check whether battery modules have shifted or suffered collision damage, and whether the copper busbars between modules are loose or deformed.

4. Check that the battery rack high-voltage box is securely installed, with internal circuit breakers and fuses properly installed and wiring secure.

For battery racks assembled on site, install according to the following steps:

  • Install the battery frame: Secure the battery frame to the mounting beams at the container base. Adjust the frame verticality and levelness — verticality deviation shall not exceed 1‰, and levelness deviation shall not exceed 2mm/m. Tighten all connecting bolts and apply anti-loosening treatment.
  • Install battery modules: Install battery modules layer by layer from bottom to top. Handle with care, avoiding collisions. Place modules level, with locating pins accurately engaging the locating holes. After installation, check that each layer of modules is horizontally aligned without tilting.
  • Connect inter-module busbars: Use insulated tools to connect the copper busbars between modules. Wipe the busbar contact surfaces clean and apply conductive grease. Tighten bolts to the specified torque to ensure good contact. During connection, prevent short circuits between positive and negative terminals. Tools are strictly prohibited from simultaneously contacting both positive and negative terminals.
  • Install BMU sensing wires: Connect the BMU sensing wires to the sensing terminals of each module, ensuring secure insertion and clear wire number markings. Neatly organize and bundle the sensing wires along the wiring duct.
  • Install the high-voltage box: Secure the battery cluster high-voltage box to the end of the battery frame, connecting the battery cluster total positive and total negative busbars. Tightening torque shall meet requirements.
  • Insulation test: After a single battery rack installation is completed, use an insulation resistance tester to measure the insulation resistance of the positive and negative terminals to ground. A resistance value of no less than 1MΩ is considered qualified.

3.4.2 PCS and Distribution Cabinet Installation and Calibration

1. Check whether the PCS equipment mounting base bolts are tightened and whether the equipment has shifted or tilted. Adjust the PCS levelness and verticality — verticality deviation shall not exceed 1.5‰.

2. Check that the distribution cabinet is securely installed, cabinet doors open and close smoothly, and internal components show no loosening or detachment.

3. Check that equipment ground connections are reliable, with grounding terminals connected securely to the container grounding busbar and contact resistance meeting requirements.

4. Check that equipment ventilation openings are unobstructed and heat dissipation channels are clear.

For PCS equipment installed on site, follow these steps:

1. Equipment positioning: Move the PCS to the installation position and align it with the base mounting holes. Place it level.

2. Equipment fixing: Tighten the mounting bolts and adjust levelness and verticality.

3. Vibration isolation: Install vibration isolation pads between the equipment and base to reduce operating vibration and noise.

4. Ground connection: Connect the equipment protective grounding wire.

5. Appearance inspection: Check that the equipment appearance has no damage and that panels and displays are intact.

3.4.3 Temperature Control System Installation and Calibration

1. Check that the air conditioning unit is securely installed with no loose bolts and that unit levelness meets requirements.

2. Check that duct connections are tight, with no air leaks or detachment, and that duct fixing brackets are secure.

3. Check that temperature sensor installation positions are correct and securely fixed, with probes in good contact with the measured surface.

4. Check that fans are securely installed, blades show no deformation, and rotation is flexible without jamming.

5. For liquid cooling systems, check that piping connections are secure with no leaks, coolant levels are normal, and circulation pumps are securely installed.

6. Clean air conditioning filters and vent openings of debris to ensure smooth ventilation.

3.4.4 Fire Suppression System Installation and Calibration

1. Check that the heptafluoropropane cylinder is securely fixed, pressure indication is in the normal green zone, and cylinder labels are intact.

2. Check that fire protection piping connections are secure, nozzle installation directions are correct, and nozzles are unobstructed.

3. Check that smoke detectors, heat detectors, and combustible gas detectors are securely installed, correctly positioned, and intact in appearance.

4. Check that the fire controller is securely installed, wiring is not loose, and audible and visual alarms are intact.

5. Check that the manual emergency start button is correctly positioned with the protective cover intact.

6. Check that the pressure relief vent is correctly installed and the relief valve plate is intact.

3.4.5 Monitoring System Installation and Calibration

1. Check that the monitoring host, switches, communication gateways, and other equipment are securely installed with no loose wiring.

2. Check that touchscreens and displays are securely installed and display correctly.

3. Check that cameras are correctly positioned with viewing angles covering key areas and clear images.

4. Check that communication lines are reliably connected with clear markings.

3.5 Auxiliary Facility Installation

3.5.1 Ladder and Platform Installation

If the container height is significant, external maintenance ladders and top access platforms shall be installed:

  • Ladders shall be fabricated from galvanized steel for good corrosion resistance and installed at the container end or side.
  • Ladders shall be bolted to the container with secure fixing. Ladder verticality deviation shall not exceed 5‰.
  • Ladder width shall not be less than 400mm, with step spacing of 300mm. Safety hoops shall be installed to enhance safety.
  • Top access platforms shall be equipped with protective guardrails at a height of no less than 1200mm, with anti-slip surface treatment.
  • After ladder and platform installation, load testing shall be conducted to meet safety requirements.

3.5.2 Outdoor Markings and Protective Facilities

  • Install safety fencing around the container perimeter, with a height of no less than 1200mm, and hang safety warning signs.
  • Install fire lane markings to ensure unobstructed access.
  • Install water-retaining curbs and drainage channels around the container perimeter to complete the drainage system.
  • Install outdoor lighting to meet nighttime operation and maintenance illumination requirements.

Electrical system wiring is the core process in outdoor energy storage container installation. Wiring quality directly affects the safety and reliability of system operation. All electrical work shall be performed by certified electricians, strictly following electrical construction specifications and the requirements of this manual, ensuring accurate wiring, standardized workmanship, and good insulation.

4.1 General Electrical Wiring Requirements

4.1.1 Basic Construction Principles

  • Drawings-based construction principle: Strictly construct according to design drawings and manufacturer wiring diagrams. Unauthorized changes to wiring methods and cable specifications are prohibited. If changes are required, formal design change documents shall be issued.
  • Safety first principle: Strictly implement electrical safety operating procedures. Live-line work must be approved and reliable protective measures taken. Live-line wiring is strictly prohibited in principle.
  • Workmanship standardization principle: Wiring workmanship shall comply with specification requirements, achieving neatness, firmness, aesthetic quality, and clear markings.
  • Quality inspection principle: After each wiring section is completed, insulation testing, continuity testing, and phase sequence checks must be performed. The next step may proceed only after passing inspection.

4.1.2 Pre-wiring Preparation

1. Familiarize with electrical schematics, wiring diagrams, and terminal diagrams to understand the functions and cable specifications of each circuit.

2. Check whether cable models, specifications, and lengths comply with design requirements. Cable appearance shall show no damage, and insulation layers shall be intact.

3. Prepare wiring tools and testing instruments, including crimping pliers, wire strippers, torque wrench, multimeter, and insulation resistance tester. Tool insulation shall be intact.

4. Clear debris from the wiring area, keep it dry and tidy, and implement fire prevention measures.

5. Confirm that all equipment is in a de-energized state, with all circuit breakers in the open position, and post “DO NOT CLOSE — WORK IN PROGRESS” warning signs.

4.1.3 Cable Marking Requirements

All cables shall have clear wire number markings at both ends. Marking content shall include circuit number, starting point, and ending point. Use dedicated number ferrules or labels with clear, durable printing.

  • High-voltage power cables: Mark circuit name, phase sequence, and number.
  • Low-voltage power cables: Mark circuit number and wire number.
  • Control and communication cables: Mark signal name and terminal number.

Marking direction shall be consistent for easy identification by operation and maintenance personnel.

4.2 DC System Wiring

The DC system connects the battery racks to the PCS DC side. It is a high-voltage DC circuit with voltages reaching hundreds or even thousands of volts. Strict insulation protection must be maintained during wiring to prevent short circuits and electric shock.

4.2.1 DC Cable Selection and Laying

Cable selection: DC power cables shall use flame-retardant XLPE insulated power cables with a voltage rating of no less than 1.5 times the system maximum voltage. Cable current-carrying capacity shall meet the maximum operating current requirements of the circuit, with appropriate margin.

Cable laying:

  • DC cables shall be laid along dedicated DC cable trays made of fire-retardant material with reliable grounding.
  • Avoid crossing and twisting during cable laying. The bending radius shall not be less than 15 times the cable outer diameter.
  • Fire-stopping sealing shall be installed where cables pass through partitions and walls, using fire-stop putty for sealing.
  • Reserve appropriate slack during cable laying for wiring and maintenance convenience. The reserved length shall be approximately 0.5-1m.
  • Positive and negative cables shall be laid separately or distinguished by color coding — positive red, negative black — with clear phase markings.

4.2.2 DC Wiring Workmanship

Cable end termination:

1. Strip the insulation at the cable end. The stripping length shall match the terminal size without damaging the conductors.

2. Straighten the conductors and crimp copper terminals of the corresponding size. Crimping shall be firm with indentation depth meeting requirements.

3. After crimping, slide heat-shrink tubing of the corresponding color over the terminal and heat to shrink, protecting the end.

4. Wipe terminal contact surfaces clean and apply conductive grease to reduce contact resistance.

Battery rack side connection:

1. Connect the battery rack end first, then the PCS end. The PCS side shall remain disconnected throughout the wiring process.

2. Use insulated tools during wiring, operating with one hand to prevent short circuits between positive and negative terminals.

3. Connect the negative terminal first, then the positive terminal. Insert terminals fully and tighten connecting bolts to the specified torque.

4. After connection is complete, check for firm connection, no looseness, and proper insulation protection.

5. Each battery rack shall be connected to the corresponding circuit in the DC distribution cabinet, with circuit numbers corresponding one-to-one with battery rack numbers.

PCS side connection:

1. Confirm that all circuit breakers in the DC distribution cabinet are in the open position. Verify no voltage before wiring.

2. Connect the DC bus positive and negative terminals to the corresponding PCS DC input terminals with accurate phase sequence.

3. Bolts shall be tightened to the manufacturer’s specified torque. High-current terminals shall be tightened using a torque wrench.

4. After wiring is complete, check that the phase sequence is correct, connections are firm, and insulation distances meet requirements.

4.2.3 DC System Insulation Testing

1. After all DC wiring is complete, open all battery rack circuit breakers and PCS DC switches to make each circuit independent.

2. Use a 1000V insulation resistance tester to measure the insulation resistance of positive-to-ground, negative-to-ground, and positive-to-negative for each circuit.

3. Insulation resistance shall not be less than 1MΩ, with a polarization index greater than 1.3.

4. If insulation resistance is unqualified, troubleshoot section by section, eliminate the fault, and re-test until qualified.

5. Record test results and file them in the construction archives.

4.3 AC System Wiring

The AC system connects the PCS AC side to the grid/load, including low-voltage AC circuits and high-voltage AC circuits, and serves as the channel for power output.

4.3.1 AC Cable Selection and Laying

Cable Selection:

AC power cables shall adopt flame-retardant XLPE insulated power cables with a voltage rating of 0.6/1kV (low voltage) or corresponding high-voltage ratings. The cable ampacity shall meet the rated current requirements with an appropriate margin.

Cable Laying:

  • AC cables shall be laid along dedicated AC cable trays, separated by layers from DC cables and communication cables to avoid electromagnetic interference.
  • Three-phase cables shall be distinguished by color: A phase yellow, B phase green, C phase red, neutral blue, and ground yellow-green.
  • Cable bending radius shall comply with code requirements, and avoid twisting or kinking during laying.
  • Waterproof cable glands shall be used at cable entry/exit points to prevent rainwater ingress.
  • Cables laid outdoors shall be protected by conduits or adopt armored cables with pressure resistance, waterproofing, and corrosion resistance.

4.3.2 AC Wiring Procedure

Terminal Handling:

Same as DC wiring requirements: cable cores shall be crimped with terminal lugs, contact surfaces shall be cleaned and polished, and conductive paste applied.

PCS Side Wiring:

  • Confirm the PCS is in a de-energized state and verify no voltage.
  • Connect A, B, C three-phase wires and neutral wire to the PCS AC output terminals respectively in correct phase sequence, and connect the ground wire to the protective earth terminal.
  • Tighten bolts to specified torque to ensure good contact.
  • Check phase sequence correctness, secure connections, and sufficient phase-to-phase insulation distance.

Grid-Tie Cabinet Side Wiring:

  • Confirm the upstream power supply on the grid side is disconnected and verify no voltage.
  • Connect the PCS output cables to the corresponding incoming circuits of the AC distribution cabinet, ensuring phase sequence matches the grid side.
  • Verify accurate wiring for energy meters and current transformers, and reliable grounding of secondary circuits.
  • Ensure proper wiring of surge protective devices (SPDs) and reliable grounding of their earth terminals.

4.3.3 AC System Testing

  • Insulation Test: Disconnect all AC switches, use a 1000V insulation resistance tester to measure insulation resistance between each phase and ground, between phases, and between neutral and ground. A resistance of not less than 0.5MΩ is acceptable.
  • Phase Sequence Check: After grid-side power is supplied, use a phase sequence meter to verify the grid side phase sequence is positive. Ensure the PCS side phase sequence matches the grid side.
  • Continuity Test: Use a multimeter in continuity mode to check that each circuit is correctly connected, with no open circuits or short circuits.
  • Ground Resistance Test: Measure the protective earth resistance. The value must meet design requirements, typically ≤4Ω.

4.4 Control and Communication System Wiring

4.4.1 Control Circuit Wiring

Cable Selection:

Control circuits shall adopt multi-core shielded control cables with core cross-section not less than 0.75mm². The shield layer shall be reliably grounded.

Wiring Requirements:

  • Control cables shall be laid along dedicated control cable trays, kept away from power cables to avoid electromagnetic interference.
  • Terminal block connections shall use pin-type or fork-type terminals; each terminal shall accommodate no more than two wires.
  • The stripped length of cable cores shall be appropriate, connections secure, with no burrs or looseness.
  • The shield layer shall be single-ended grounded to the control ground. Insulation treatment shall be applied at the shield cut positions.
  • Wire markers shall be clear and accurate, matching the corresponding terminal numbers.

Secondary Circuit Inspection:

  • Check that each control circuit wiring matches the schematic diagram and the logic is correct.
  • Test the insulation resistance of control circuits; resistance shall be not less than 1MΩ.
  • Perform continuity tests to confirm the circuits are properly open/closed.

4.4.2 Communication Circuit Wiring

Cable Selection:

  • CAN bus and RS485 bus shall adopt shielded twisted pair cables with characteristic impedance of 120Ω.
  • Ethernet communication shall use Category 5e or Category 6 network cables; for outdoor applications, use waterproof armored fiber optic cables.

Wiring Requirements:

  • Communication cables shall be laid separately, maintaining a distance of at least 30cm from power cables. When crossing, cross at right angles.
  • For bus-type communication, terminator resistors shall be installed at both ends with matching resistance values.
  • Network cables shall be crimped to the T568B standard with correct wire sequence and secure crimping.
  • Fiber optic splicing shall use a dedicated fusion splicer; splice loss must meet requirements, and both ends shall be labeled.
  • The shield layer of communication cables shall be single-ended reliably grounded.
  • At the entry point of outdoor communication lines, install signal surge protection devices (SPDs) with reliable grounding.

Communication Testing:

  • Test network cables with a network cable tester for continuity and wire sequence, confirming no miswiring or breaks.
  • Test fiber optic link loss with an optical power meter, ensuring within allowable range.
  • After energizing equipment, test communication status to confirm normal data transmission.

4.5 Grounding System Construction

The grounding system is an important foundation for ensuring electrical safety and stable equipment operation. The grounding system of the energy storage container includes working grounding, protective grounding, lightning protection grounding, and anti-static grounding, and it is recommended to adopt a common grounding grid.

4.5.1 Technical Requirements for Grounding System

  • The common grounding grid resistance shall be ≤4Ω. In areas with high soil resistivity, resistance reduction measures may be taken, and the requirement can be relaxed to ≤10Ω, provided that the minimum equipment requirements are met.
  • The container shall be equipped with a main grounding busbar. All grounding branches shall be connected to the main busbar, which shall be made of galvanized flat steel or copper busbar with dimensions not less than 40×4mm.
  • The metal enclosures of all electrical equipment, container steel structure, cable trays, pipes, and cable shields shall be reliably grounded.
  • Grounding main conductors shall adopt galvanized flat steel or stranded copper wires; grounding electrodes shall adopt galvanized angle steel or copper-clad steel grounding rods.
  • Grounding connections shall be made by welding or bolted connections. The lap length of welding shall comply with code requirements. For bolted connections, contact surfaces shall be cleaned and tightened reliably.

4.5.2 Grounding Grid Construction

Grounding Electrode Installation:

  • Excavate grounding trenches along the foundation perimeter. Trench depth shall be not less than 0.8m, width 0.4m.
  • Grounding electrodes shall adopt ∠50×50×5mm galvanized angle steel, length 2.5m, driven vertically into the ground, with the top end 0.8m below the surface.
  • The spacing between grounding electrodes shall not be less than 5m. The quantity is determined based on grounding resistance requirements, typically not less than 4 rods.

Grounding Busbar Laying:

  • The grounding busbar shall adopt 40×4mm galvanized flat steel, laid horizontally in the trench, and welded to each grounding electrode.
  • The lap length of flat steel shall not be less than 2 times the width of the flat steel, with welding on three sides. Weld seams shall be full and free of cold welds.
  • Remove welding slag from welded joints and apply bituminous paint for anti-corrosion treatment.

Riser Connection:

  • Lead out grounding risers from the grounding busbar to connect to the container main grounding busbar.
  • The riser shall be connected to the container by bolting, with contact surfaces cleaned and securely tightened.
  • There shall be no fewer than 2 the riser lead-out points, forming a ring grounding to improve reliability.

4.5.3 Equipment Grounding Connection

Protective Grounding:

  • Each electrical equipment metal enclosure shall have a separate grounding wire connected to the grounding busbar. Series grounding is strictly prohibited.
  • The grounding wire shall adopt yellow-green insulated multi-strand copper flexible wire with cross-section not less than 1/2 of the equipment power phase wire cross-section, and shall not be less than 2.5mm².
  • Add spring washers at grounding terminals, tighten firmly to ensure anti-loosening reliability.

Working Grounding:

  • The neutral point of the AC system and the working ground of the DC system shall be reliably grounded as per design requirements.
  • When working grounding and protective grounding share the same grounding grid, the grounding resistance shall meet the minimum value requirement.

Lightning Protection Grounding:

  • The container top shall be equipped with an air termination strip or air termination rod, reliably connected to the grounding grid through down conductors.
  • The grounding terminals of power SPDs and signal SPDs shall be connected to the grounding busbar as close as possible. Grounding wires shall be short and straight, with length not exceeding 0.5m.

Anti-Static Grounding:

  • Anti-static grounding terminals shall be provided inside the battery compartment. Operation and maintenance personnel must discharge static before entering.
  • Metal pipes and racks in explosive or flammable areas shall be equipped with anti-static grounding.

4.5.4 Grounding Resistance Test

  • After the grounding system construction is completed, use a grounding resistance tester to measure the grounding resistance value.
  • Use the three-probe or four-probe method, taking measurements at different positions of the grounding grid and using the average value.
  • The grounding resistance value shall meet design requirements; typically ≤4Ω is acceptable.
  • If the resistance does not meet the requirement, adopt resistance reduction measures such as increasing the number of grounding electrodes, replacing resistance-reducing agents, or extending the grounding busbar, until the value is satisfactory.
  • Record the test results and sign the grounding resistance test record.

4.6 Wiring Process and Fire Proofing

4.6.1 Cable Tray and Conduit Laying

  • Cable trays shall be installed horizontally and vertically straight, securely fixed. Support spacing shall comply with code requirements: 1.5-2m for horizontal supports and 2m for vertical supports.
  • Bonding jumpers shall be installed at tray connections to ensure electrical continuity, and the entire tray system shall be reliably grounded.
  • When cables pass through conduits, protective bushings shall be installed at the conduit openings to prevent damage to cable insulation. The total number of cables in a single conduit shall not exceed 40% of the conduit cross-sectional area.
  • Cables inside trays shall be laid neatly, with different voltage levels and different functions separated or partitioned.
  • Cables shall be secured with ties at intervals of 1.5-2m, with additional fixed points at bends and terminals.

4.6.2 Fire Proofing

  • Openings where cables pass through fire walls, floors, or container walls must be fire-stopped.
  • Use fire-resistant putty, fire-stop pillows, fire-stop boards, and other fire-stop materials. The sealing shall be tight with no gaps.
  • Reserve appropriate cable slack on both sides of the fire-stop to facilitate maintenance.
  • After completion, inspect the fire-stop quality to ensure fire protection performance meets requirements.

4.6.3 Cable Labeling and Management

  • All cables shall have nameplates at both ends, bends, and branch points, indicating cable number, specification, and start/end points.
  • Cables inside cabinets shall be bound neatly, horizontally and vertically straight, with minimal crossings, for a neat and standard appearance.
  • Power cables and control cables shall be bound separately, with spacing meeting anti-interference requirements.
  • Surplus cables shall be coiled neatly and fixed; they shall not be randomly stacked.

Chapter 5 Commissioning and Trial Operation of Outdoor Energy Storage Container Systems

System commissioning is a critical step to verify the functions and performance of the outdoor energy storage container. It must be carried out after all installation work is completed and inspections pass. Commissioning shall be performed by professional commissioning engineers, strictly following the step-by-step process: first individual units, then the entire system; first no-load, then loaded; first low voltage, then high voltage, ensuring a safe and orderly commissioning process. Guangzhou Lain Intelligent System Development Co., Ltd. can provide professional technical support and guide on-site commissioning work.

5.1 Pre-Commissioning Preparations and Inspections

5.1.1 Prerequisites for Commissioning

  • Container installation, electrical wiring, and grounding construction are all completed; each sub-project has passed acceptance inspection, and documentation is complete.
  • The site is clean, free of debris, with adequate ventilation and lighting, meeting commissioning conditions.
  • Commissioning personnel are familiar with system principles, equipment manuals, and commissioning plans, and hold valid certificates for the relevant work.
  • Commissioning instruments and tools are fully prepared, including multimeters, clamp meters, oscilloscopes, power quality analyzers, insulation testers, etc., with calibration certificates.
  • Safety protective equipment and fire-fighting equipment are fully available, and emergency exits are unobstructed.
  • Grid connection conditions are satisfied; grid voltage and frequency are normal.
  • All equipment is in a de-energized state, and all circuit breakers and switches are in the OFF position.

5.1.2 Visual and Wiring Inspections

Before commissioning, perform a comprehensive visual and wiring inspection to eliminate obvious fault risks:

Visual Inspection:

  • All equipment is intact externally, with no collision damage, corrosion, or paint loss.
  • Equipment is securely mounted, with no looseness or tilting.
  • The interior of the container is clean, with no debris, tools, or metal objects left behind.
  • Ventilation openings and heat dissipation vents are unobstructed; passageways are clear.
  • Doors and locks are intact and seals are normal.

Wiring Inspection:

  • All power circuits and control circuits are correctly wired and consistent with drawings.
  • Terminal blocks are tight and secure; large-current terminal torque meets requirements.
  • Cable labels are clear and accurate; phase color markings are correct.
  • Insulation distances meet requirements; there are no exposed live parts.
  • All grounding connections are complete and reliable.
  • All secondary circuits are correctly wired; terminal block connections are secure.

Switch State Inspection:

  • Confirm that all circuit breakers, disconnectors, and fuses are in the OFF position.
  • Confirm that all control switches are in the stop position.
  • Confirm that emergency stop buttons are in the reset position.

5.1.3 Insulation and Grounding Inspections

DC System Insulation Inspection:

  • Open all battery cluster switches, PCS DC switches, and DC distribution cabinet main switches.
  • Use a 1000V insulation tester to measure the insulation resistance of the DC bus positive and negative poles to ground. Resistance shall be ≥1MΩ.
  • Measure the insulation resistance of each battery cluster’s positive and negative poles to ground. Resistance shall be ≥1MΩ.

AC System Insulation Inspection:

  • Open all AC switches, including PCS AC switches, grid-tie switches, and load switches.
  • Use a 1000V insulation tester to measure the insulation resistance of each phase to ground and between phases on the AC bus. For low-voltage systems, resistance shall be ≥0.5MΩ.

Control Circuit Insulation Inspection:

  • Disconnect the control power supply, measure the insulation resistance of control circuits to ground. Resistance shall be ≥1MΩ.

Grounding Resistance Inspection:

  • Re-measure the total system grounding resistance to ensure it meets design requirements (≤4Ω).
  • Check that all equipment grounding is continuous and free of open circuits.

Power-on commissioning is permitted only after all inspections pass. If any inspection fails, power-on is strictly prohibited.

5.2 Individual Auxiliary System Commissioning

5.2.1 Temperature Control System Commissioning

Pre-power Inspection:

Check that the air conditioning power wiring is correct, fans and compressors are firmly mounted, air ducts are unobstructed, and filters are clean.

Power-on Test:

  • Close the temperature control system power switch; check that the controller power supply is normal and the display screen lights up.
  • Set temperature parameters: cooling set point 30°C, heating set point 10°C.
  • Manually start cooling mode; check that compressor and fans start normally, run smoothly, and produce no abnormal noise. Measure the outlet air temperature to confirm cooling effect.
  • Manually start heating mode; check that heating devices operate normally and outlet air temperature rises.
  • Manually start ventilation mode; check that ventilation fans rotate in the correct direction and air volume is normal.

Automatic Control Test:

  • Simulate temperature signals and change the container temperature to verify automatic start/stop. The system shall automatically start cooling when temperature exceeds the set point and automatically start heating when below the set point.
  • Test the accuracy of temperature sensors by comparing displayed temperature with actual temperature. Error ≤±1°C.
  • Test high/low temperature alarm functions by simulating over-temperature conditions to verify alarm output is normal.

Interlock Test:

Test communication between the temperature control system and BMS/EMS. Temperature data can be uploaded normally, and remote start/stop and parameter setting commands can be received.

Record the operating parameters of the temperature control system and confirm all functions are normal.

5.2.2 Fire Protection System Commissioning

Fire protection system commissioning must be carried out under the guidance of factory professionals. Starting the fire suppression device without authorization is strictly prohibited.

Detection System Commissioning:

  • Power on the fire alarm controller; check that system self-test is normal with no fault alarms.
  • Use simulated smoke to test smoke detectors. Detectors shall activate, the controller shall receive fire signals, and trigger audible and visual alarms.
  • Use a heat gun to test heat detectors; alarm function shall be normal.
  • Use standard calibration gas to test combustible gas detectors. Concentration display shall be accurate, and pre-alarm and alarm thresholds shall operate correctly.

Alarm Function Commissioning:

  • Test level 1 pre-alarm: when combustible gas concentration reaches the pre-alarm value, the controller shall issue a pre-alarm signal and upload it to the monitoring system.
  • Test level 2 fire alarm: when smoke or heat detectors activate, the controller shall trigger the fire alarm audible and visual alarm, interlock to shut down air conditioning and fans, cut off non-fire power supply, and output the fire alarm signal to the EMS.
  • Test manual alarm: press the manual alarm button to trigger the fire alarm.

Fire Suppression System Interlock Test:

  • Conduct a simulated interlock test without releasing extinguishing agent. Verify that after fire alarm triggers, the fire suppression device start signal is output normally, and the solenoid valve operates correctly (may test by removing the solenoid coil).
  • Test manual emergency start and emergency stop functions; operations must be accurate and reliable.
  • Check that gas cylinder pressure is normal and within the green working range.

Communication Test:

Test communication between the fire system and monitoring system. All alarm signals and equipment status shall be uploaded to the EMS platform in real time.

After commissioning is completed, restore the system to normal.

5.2.3 Monitoring and Energy Management System (EMS) Individual Commissioning

The Monitoring and Energy Management System is the “command center” of the outdoor energy storage container. It assumes the core functions of full-system data acquisition, status display, strategy scheduling, fault alarm, and operation and maintenance management. The commissioning quality of the EMS directly determines the intelligent operation level and O&M efficiency of the energy storage system. The EMS system independently developed by Guangzhou Lain Intelligent System Development Co., Ltd. (KITOZER) is compatible with the full series of outdoor energy storage container products, supports multi-terminal access and multi-site centralized management. Commissioning must strictly follow the manufacturer’s operation manual.

Pre-power Hardware Inspection

Commissioning personnel shall first conduct a comprehensive hardware check of the EMS system to ensure hardware installation and wiring comply with specifications:

  • Check that monitoring hosts, industrial switches, communication gateways, touch screens, data acquisition devices, etc., are firmly installed, free of looseness or impact damage, and that nameplate parameters match the design.
  • Check that device power wiring polarity is correct, voltage rating matches, and ground wires are reliably connected to the grounding busbar. Grounding resistance meets requirements.
  • Check that all communication cables are connected properly. Ethernet ports, CAN interfaces, and RS485 interfaces are securely plugged in, wire sequence and labels correspond accurately, with no loose or wrong connections.
  • Check that outdoor communication antennas are securely installed, with no obstruction in the signal reception direction. The 4G/5G module SIM card is installed correctly, and the service plan is active.
  • Clean debris inside the monitoring cabinet, ensure that cooling vents are unobstructed, and the cabinet temperature and humidity meet equipment operating requirements.

System Power-on Self-test

After confirming the hardware inspection is correct, power on in order of “peripheral devices first, core hosts later”:

  • First close the monitoring system main power switch. Check that the UPS power starts normally, output voltage is stable within 220V±5%, and the DC backup switching function works properly.
  • Successively power on switches, communication gateways, acquisition devices, and other peripherals. Observe device indicator lights: power indicators are solid on, operation indicators blink, and no fault alarm indicators stay on.
  • Power on the monitoring host and touch screen, wait for system startup. Check that the operating system loads normally with no errors, blue screens, or freezes.
  • Start the EMS monitoring software and perform system self-test. Verify that all background services, including database service, communication service, Web service, and alarm service, run normally with no abnormal service stops.
  • Check that the touch screen responds sensitively, screen transitions are smooth, and there are no lags, offsets, or touch malfunction issues.

Basic Function Commissioning

After the system starts, verify the basic functions of the EMS item by item:

  • Topology Diagram Display: Check that the one-line topology diagram is accurately drawn, device icons match the actual configuration, and real-time device operating status and key parameters are displayed. Data refresh cycle shall not exceed 1 second, and displayed values shall be accurate with no jumps.
  • Data Acquisition: Check data upload from each subsystem one by one, including battery system voltage, current, SOC, temperature; PCS operating power, voltage, current; temperature control system temperature and operating status; fire system alarm status, etc. Ensure that all measurement point data is fully acquired with no missing or dropped packets.
  • Curve Query: Test historical data curve generation. Query historical trend curves for voltage, current, power, SOC, and other parameters over time intervals. Curves shall be smooth, data points correspond accurately, and zoom and export functions are supported.
  • Report Generation: Test automatic generation of daily, weekly, monthly, and yearly operation reports. Report content shall include core indicators such as charge/discharge energy, electricity revenue, cycle count, equipment utilization rate, and fault statistics. Data calculations must be accurate, and reports support Excel export and printing.
  • Event Log: Test automatic storage of operation records, alarm records, and fault records. Records shall include occurrence time, event type, detailed description, and operator information. Records must be tamper-proof and stored for a period not less than 1 year.

Alarm and Interlock Function Commissioning

Alarm functions are crucial for safe system operation, and alarm logic and interlocking actions shall be verified level by level:

  • Threshold Setting: Set parameter thresholds in the system for level 1 pre-alarm, level 2 alarm, and level 3 shutdown, covering common fault types such as overvoltage, undervoltage, overcurrent, overtemperature, SOC too high/low, and insulation abnormality.
  • Alarm Trigger Test: Trigger alarms at each level by simulating signals or modifying parameters. Verify that the system accurately identifies the fault level, displays corresponding color pop-up prompts, and simultaneously triggers on-site audible and visual alarms.
  • Alarm Notification Test: Verify that SMS alarm, APP push alarm, and email alarm functions are normal. Alarm messages shall be pushed to designated O&M personnel accounts within 10 seconds, and notification content shall include fault location, fault type, and handling recommendations.
  • Interlock Control Test: Test the automatic shutdown interlock logic for level 3 faults. When a serious fault is triggered, the system shall automatically send shutdown commands to the PCS and BMS, cut off the charge/discharge circuit, and initiate corresponding protection actions. Response time shall not exceed 200ms.
  • Alarm Acknowledgment and Reset: Test alarm acknowledgment and manual reset functions. After the fault is cleared, the alarm can be reset and the system returns to normal operation. Historical alarm records shall be retained completely.

Control and Scheduling Function Commissioning

Verify the core control functions of the energy storage system item by item to ensure accurate execution of scheduling commands:

  • Manual Control: Perform manual start/stop, manual power setting, and manual charge/discharge mode setting from the monitoring interface. Verify commands are accurately sent to the corresponding equipment, equipment responds correctly, with no delay, no refusal, and no misoperation.
  • Scheduled Charge/Discharge: Set multi-time-period scheduled charge/discharge strategies, specifying charge/discharge power and target SOC for different periods. Verify the system automatically switches operating states on time, and power control accuracy meets design requirements.
  • Demand Management: Simulate load power exceeding the set demand threshold. Verify the system automatically starts discharge to supplement power and suppress maximum demand. The demand control deviation shall not exceed 2% of rated power.
  • Smooth Output: Simulate fluctuations in renewable energy output. Verify the system automatically adjusts charge/discharge power to smooth output power fluctuations. The smoothed power fluctuation rate shall meet design specifications.
  • Authority Management: Set three user levels: administrator, operator, and visitor. Verify that different accounts have different operation permissions after login. Accounts without authorization cannot execute control operations, ensuring system operation security.

Communication and Remote Access Commissioning

  • Local Communication Test: Verify that a computer on the local area network can access the monitoring system via the Web interface. Pages load normally, operations respond smoothly, with no access delays or data synchronization issues.
  • Remote Communication Test: Access the public network via 4G/5G or Ethernet. Verify the remote cloud platform can receive on-site data normally, and the remote access interface is consistent with the local interface. Synchronization delay shall not exceed 3 seconds.
  • Mobile Access Test: Verify the mobile APP and WeChat mini-program can log in normally to view system operating status and receive alarm push notifications. Mobile functions shall be consistent with Web functions.
  • Multi-System Interface Test: If integration with the owner’s energy management platform or grid dispatch platform is required, data integration shall be carried out according to the agreed communication protocol. Verify data upload is accurate, command delivery is smooth, and integration requirements are met.

After the EMS individual commissioning is completed, save all parameter configuration files, export commissioning records, and confirm that all functional indicators meet design requirements before proceeding to subsequent system integration commissioning.

5.2.4 Individual Commissioning of Power Distribution and Lightning Protection/Grounding Systems

The power distribution system serves as the carrier for power transmission and distribution, while the lightning protection and grounding system is an important safeguard for equipment and personnel safety. Both must be individually commissioned before the system is energized to ensure reliable circuit continuity, effective protection, and grounding system performance.

DC Distribution Cabinet Commissioning

  • Appearance and Mechanism Inspection: Check that circuit breakers, fuses, and disconnectors inside the cabinet have models and specifications matching the design, with no damage, and that operating mechanisms are flexible and reliable, with clear open/close position indicators.
  • Switching Test: Manually operate the circuit breakers for each circuit to verify smooth open/close actions, no sticking or tripping failure. Auxiliary contacts operate synchronously with main contacts, and signal feedback is accurate.
  • Protective Settings Calibration: Verify that DC circuit breaker rated currents and short-circuit breaking capacities meet design requirements. Verify overcurrent trip settings are accurately calibrated. Simulated overcurrent faults shall cause reliable tripping.
  • Insulation Monitoring Device Commissioning: Power on the insulation monitoring device and check self-test is normal. It shall accurately display the insulation resistance of the DC bus to ground. When simulating a ground fault, the device shall issue a ground alarm within the specified time and locate the fault branch.
  • Metering Device Calibration: Check that DC current and voltage sensor wiring is correct, and displayed values deviate from actual measured values by no more than 0.5%. Metering accuracy meets requirements.

AC Distribution Cabinet Commissioning

  • Circuit Breaker Mechanism Test: Check that the incoming breaker, outgoing breakers, and grid-tie breaker operating mechanisms are flexible, open/close positions are accurate, and energy storage mechanisms work normally, with no failure to open or close.
  • Protection Device Calibration: Perform setting calibration for microprocessor-based protection devices. Input simulated values for overcurrent, instantaneous overcurrent, undervoltage, overvoltage, etc., to verify protection action logic is correct. Action time and setting errors are within allowable ranges, and action signals can be accurately uploaded to the monitoring system.
  • Energy Metering Device Calibration: Check that the multi-function energy meter wiring is correct, voltage, current, power, and energy displays are accurate, errors meet metering accuracy requirements, and the device supports multiple rates (peak, flat, valley). Communication for metering data upload is normal.
  • Interlock Function Test: Verify the interlock logic between the grid-tie breaker and the upstream grid switch to prevent reverse power feeding, meeting grid safety requirements. Test cabinet door interlocks with live circuits: the breaker cannot close when the door is open, ensuring O&M safety.
  • Capacitor Compensation Device Commissioning (if configured): Check that the reactive power compensation controller operates normally and can automatically switch capacitor banks based on power factor. Switching logic shall be correct with no over-compensation or under-compensation. After compensation, power factor shall not be less than 0.95.

Lightning Protection and Grounding System Test

  • Power SPD Test: Check that Class B and Class C power surge protective devices (SPDs) are securely installed, correctly wired, and the status indication window shows green (normal), with no failure or damage. Use an SPD tester to measure the varistor voltage and leakage current of the SPDs. Parameters shall comply with product standards, and deterioration is within the allowable range.
  • Signal SPD Test: Check that signal and control signal SPDs are correctly installed, interfaces match, and grounding terminals are reliably grounded as close as possible. Test that the signal path is normal, with no excessive attenuation or open circuits.
  • Ground Continuity Test: Use a ground continuity tester to measure the continuity resistance between all equipment metal enclosures, container, cable trays, pipes, and the main grounding busbar. Resistance shall not exceed 0.1Ω, ensuring all exposed conductive parts are reliably grounded with no open ground points.
  • Ground Resistance Re-measurement: Use the four-probe method to re-measure the common grounding grid resistance of the entire energy storage system. Confirm the resistance does not exceed 4Ω. In high soil resistivity areas, it may be relaxed to not more than 10Ω after design confirmation, while meeting the minimum grounding requirements of all equipment.
  • Equipotential Bonding Check: Check that the equipotential bonding network in the battery compartment and electrical compartment is complete, all metal components are equipotential-bonded, and transition resistance meets code requirements.

After all individual auxiliary system commissioning is completed, organize commissioning records for each subsystem and form individual commissioning reports. Only after these reports are signed by the commissioning leader and technical leader may proceed with core equipment individual commissioning and system integration commissioning.

5.3 Battery Management System (BMS) Unit Commissioning

The Battery Management System is the core control unit of the outdoor energy storage container battery system, undertaking key functions such as cell state monitoring, safety protection, balancing control, and SOC/SOH estimation. It is the core system for ensuring battery safety and extending battery life. The Lain outdoor energy storage container adopts a three-level distributed BMS architecture. Commissioning must follow the principle of “from bottom to top, from cell to system,” verifying functions and performance level by level.

5.3.1 Pre-energization Inspection and Insulation Verification

Circuit Integrity Inspection

  • Check each battery module’s BMU acquisition wiring harness for secure insertion, ensuring acquisition terminals are not loose or detached, wire sequence corresponds accurately to numbering, with no mis-connection or reverse-connection situations.
  • Check that CAN communication lines between the cluster-level BCU and each module BMU are properly connected, termination resistors are correctly installed, and the communication cable shield layer is reliably grounded at a single point.
  • Check that the system-level BAU master control unit communication lines to each cluster BCU are properly connected, power supply wiring polarity is correct, and voltage levels match.
  • Check that current sensors, insulation monitoring modules, and voltage acquisition modules inside the high-voltage box are correctly wired, and that transformer ratios are consistent with system settings.
  • Check that BMS communication interfaces with PCS and EMS are correctly wired and communication protocols match.

Insulation Safety Verification

  • Confirm all battery cluster circuit breakers are in the open position, all high-voltage circuits are de-energized, and “Do Not Close” warning signs are posted.
  • Use a 1000V insulation resistance tester to measure the total positive-to-ground and total negative-to-ground insulation resistance of each battery cluster, confirming insulation resistance values are not less than 1MΩ, with no ground short-circuit hazards.
  • Measure insulation resistance between the BMS acquisition circuit and high-voltage circuits to ensure reliable isolation between strong and weak current, with no risk of high voltage penetrating into low-voltage control circuits.

5.3.2 Bottom-level Acquisition Unit (BMU) Commissioning

Energization and Self-test

  • Energize the BMU low-voltage auxiliary power supply, observe the module BMU indicator light status; the power light should be solidly lit, the operation light should be flashing, with no fault alarm light remaining illuminated.
  • Review BMU self-test results, confirming all acquisition channels are normal, with no channel faults or acquisition chip fault alarms.
  • Check that each BMU’s address code is correct, corresponding one-to-one with the module numbers within the battery cluster, with no duplicate or incorrect addresses.

Voltage Acquisition Accuracy Verification

  • Use a high-precision multimeter to measure the actual voltage of individual cells and compare with the voltage values displayed by the BMU acquisition.
  • Randomly sample no less than 10% of cells per cluster for accuracy verification; voltage acquisition error not greater than ±5mV is considered qualified.
  • If error exceeds the standard, check acquisition line contact conditions and perform acquisition calibration if necessary.
  • Verify total voltage acquisition accuracy by measuring module total voltage against BMU displayed total voltage; error not greater than ±0.1%.

Temperature Acquisition Accuracy Verification

  • Use a high-precision contact thermometer to measure the actual temperature at the temperature sensor locations within the module and compare with BMU displayed temperatures.
  • Temperature acquisition error not greater than ±1°C is considered qualified; at least 2 temperature measurement points must be sampled per module.
  • Simulate an over-temperature environment to verify the high-temperature alarm function operates correctly, with alarm thresholds consistent with set values.

Cell Balancing Function Test

  • Active balancing BMS: Set the balancing activation differential voltage threshold, artificially create voltage differences between cells; after reaching the threshold, verify the balancing circuit activates automatically, balancing current reaches the design value, and cell voltage differences gradually decrease.
  • Passive balancing BMS: Simulate a high-voltage cell, verify the corresponding balancing resistor activates and generates heat, cell voltage slowly decreases, and balancing function operates normally.
  • Test the balancing stop logic; when cell voltage difference falls below the stop threshold, the balancing function should automatically shut off.

5.3.3 Cluster-level Management Unit (BCU) Commissioning

Data Aggregation Function Verification

  • Energize the BCU power supply, check that the BCU communicates normally with all BMUs in its cluster, can completely acquire all cell voltage and temperature data, with no data packet loss or missing data.
  • Verify that battery cluster total voltage and total current real-time displays are accurate, with errors from actual measured values within the allowable range.
  • Check the SOC estimation function; cluster-level SOC calculation should be accurate, with jump amplitude not greater than 1%.

Cluster-level Protection Function Verification

  • Overvoltage protection: Gradually raise the cluster total voltage; when reaching the overvoltage alarm threshold, a level-1 alarm triggers; when reaching the overvoltage protection value, shutdown protection triggers; operating voltage deviation from set values not greater than ±0.5%.
  • Undervoltage protection: Gradually lower the cluster total voltage; when reaching the undervoltage alarm threshold, an alarm triggers; when reaching the undervoltage protection value, shutdown protection triggers; operation must be accurate.
  • Overcurrent protection: Simulate charge/discharge overcurrent; when reaching the overcurrent setpoint, protection activates, with operating time meeting design requirements.
  • Insulation fault protection: Simulate a DC bus ground fault; when insulation resistance falls below the threshold, the BCU accurately issues an insulation alarm; upon serious insulation faults, shutdown triggers.
  • Overtemperature/undertemperature protection: Simulate excessively high/low battery temperatures, verify graded alarm and protection operation logic is correct, with temperature thresholds consistent with settings.

Pre-charge Function Test

  • Simulate the system startup process, verify the BCU first closes the pre-charge relay, charges the bus capacitance through the pre-charge resistor; when bus voltage reaches above 90% of the battery cluster voltage, close the main relay and disconnect the pre-charge circuit; the pre-charge process should be complete and smooth.
  • Test pre-charge timeout protection by simulating a pre-charge failure scenario; verify automatic disconnection and fault reporting after pre-charge timeout to prevent equipment damage.

5.3.4 System-level Management Unit (BAU) Commissioning

System Data Aggregation

  • Energize the BAU master control power supply, check communication with all battery cluster BCUs is normal, can aggregate operating data of all cells and clusters in the entire cabinet, with complete data and no missing entries.
  • Verify system-level parameters are calculated accurately and displayed correctly: total voltage, total current, total SOC, average temperature, highest/lowest voltage, highest/lowest temperature, etc.
  • Test the SOH estimation function; the system should accurately calculate the entire cabinet’s battery health status, with estimation deviation not greater than ±5%.

System-level Protection Logic Verification

  • Verify the system-level graded protection strategy: on single-cluster fault, only the faulty cluster is isolated while other clusters continue normal operation; on serious systemic faults, full-station shutdown protection executes; protection grading logic must be clear and operation reliable.
  • Test fault location functionality; upon cell voltage abnormality, temperature abnormality, or other faults, the system should accurately locate the specific cluster number, module number, and cell number, with high-light display on the monitoring interface for rapid troubleshooting.

External Interface Function Commissioning

  • PCS communication commissioning: Verify CAN/Ethernet communication between BMS and PCS is normal; the system can send battery maximum allowable charge/discharge power, SOC, fault status, and other information to the PCS in real time, can receive PCS operating status information, with communication delay not greater than 100ms.
  • EMS communication commissioning: Verify BMS data can be completely uploaded to the EMS monitoring platform, all measurement point data is consistent with BMS local display, and alarm information is synchronized and uploaded.
  • Test the charge/discharge power limiting logic: When battery SOC approaches full charge, empty, or temperature approaches thresholds, the BMS automatically reduces the maximum allowable charge/discharge power, the PCS follows the power limit, and the protection logic linkage operates correctly.

After BMS unit commissioning is complete, save all parameter configurations and calibration data, generate the BMS commissioning report, and confirm all protection settings and alarm thresholds comply with design and battery specification requirements before proceeding to PCS commissioning and loaded joint commissioning.

5.4 Energy Storage Converter (PCS) Unit Commissioning

The energy storage converter is the core equipment for bidirectional AC/DC energy conversion. Its commissioning quality directly determines the system’s power conversion efficiency, power quality, and operational stability. The PCS commonly used in outdoor energy storage containers is a three-phase bidirectional grid-connected converter. Commissioning must strictly follow the manufacturer’s technical manual and proceed step by step while ensuring personnel and equipment safety.

5.4.1 Comprehensive Pre-energization Inspection

Mechanical and Visual Inspection

  • Check the PCS cabinet is firmly installed, with levelness and verticality conforming to installation specifications; cabinet doors open and close smoothly, and locks are intact.
  • Check core components inside the cabinet—IGBT modules, reactors, capacitors, transformers—are firmly installed with no loosening, displacement, impact damage, or loose wiring terminals.
  • Check the cooling system is intact: for air-cooled models, fan blades have no deformation and air ducts have no blockage; for liquid-cooled models, piping has no leakage and coolant level is normal.
  • Clean debris from inside the cabinet, confirming no leftover tools, metal shavings, or dust that could cause short circuits after energization.

Electrical Circuit Inspection

  • Verify DC-side and AC-side wiring phase sequence is correct, polarity is correct, terminals are tightened to specified torque, with no loose connections.
  • Check control circuit and auxiliary power supply circuit wiring is correct, voltage levels match, with no mis-connections or short circuits.
  • Check all circuit breakers and disconnecting switches are in the open position, and the grounding switch has been pulled open (if applicable).
  • Check PCS grounding is reliable, cabinet protective grounding is firmly connected to the ground busbar, and ground resistance meets requirements.

Insulation Performance Test

  • Disconnect all external connections on both DC and AC sides of the PCS to ensure circuit independence.
  • DC side: Use a 1000V insulation resistance tester to measure DC positive/negative to ground and positive-to-negative insulation resistance; resistance values must not be less than 2MΩ.
  • AC side: Use a 1000V insulation resistance tester to measure AC three-phase to ground and phase-to-phase insulation resistance; resistance values must not be less than 2MΩ.
  • Control circuit: Measure control circuit to ground insulation resistance; resistance value must not be less than 1MΩ.
  • Energization is strictly prohibited if insulation tests fail; the cause must be identified and corrected before proceeding.

5.4.2 No-load Energization and Parameter Configuration

Auxiliary Power Supply Energization Self-test

  • Energize only the PCS auxiliary control power supply, keeping the main power circuit switch open.
  • Observe the control system startup, display screen illumination, and system entry into the self-test process.
  • Check self-test results, confirming no hardware faults, communication faults, or power supply fault alarms; all circuit boards operate normally.
  • Check fans and cooling system operate normally under no-load conditions with no abnormal noise or stalling, and speed is controllable.

Parameter Configuration and Calibration

  • Input PCS rated parameters according to system design requirements, including DC voltage range, AC rated voltage, rated power, rated frequency, and other basic parameters.
  • Configure protection settings, including AC/DC side overvoltage, undervoltage, overcurrent, overtemperature, frequency protection settings, consistent with system design.
  • Configure communication parameters: set communication addresses, protocols, and baud rates with BMS and EMS to ensure communication compatibility.
  • Calibrate voltage and current sampling accuracy; use high-precision instruments to calibrate AC/DC voltage and current acquisition channels, ensuring sampling error not greater than ±0.2%.
  • Save the parameter configuration file and back up parameters to prevent parameter loss.

5.4.3 Protection Function Testing

DC Side Protection Verification

  • Simulate DC overvoltage and DC undervoltage faults; verify the PCS alarms accurately and shuts down, with operating voltage deviation from set values within the allowable range.
  • Simulate DC overcurrent and DC short-circuit faults; verify the PCS quickly blocks pulses and triggers protection, fault current is limited to a safe range, with no component damage.
  • Test DC insulation monitoring linkage; after receiving the BMS insulation fault signal, the PCS can execute shutdown protection according to set logic.

AC Side Protection Verification

  • Overvoltage/undervoltage protection: Simulate grid voltage increase/decrease; when exceeding protection thresholds, the PCS accurately triggers grid overvoltage/undervoltage alarms; when exceeding the allowable range, reliably disconnects from the grid; operating values comply with GB/T 34120 standard requirements.
  • Overfrequency/underfrequency protection: Simulate grid frequency deviation; when exceeding the frequency protection range, the PCS disconnects from the grid within the specified time, meeting grid interconnection technical requirements.
  • Anti-islanding protection: Simulate grid power loss forming an island; verify the PCS can detect the islanding state within the specified time and stop grid-connected output; islanding detection time complies with national standard requirements.
  • Short-circuit protection: Simulate an AC-side short-circuit fault; the PCS quickly blocks output, short-circuit current is limited to within 1.5 times rated current, reliably protecting equipment.

Equipment Self-protection Verification

  • Overtemperature protection: Simulate temperature rise of key components such as IGBT and reactors; when reaching the alarm threshold, an alarm is issued; when reaching the protection value, power derating or shutdown automatically executes; protection logic is correct.
  • Fan fault protection: Simulate cooling fan failure; verify the system issues a timely alarm, and after temperature rise, executes derating or shutdown protection.
  • Emergency stop test: Press the PCS local emergency stop button; verify the system immediately blocks pulses and disconnects the main circuit, with rapid and reliable shutdown response.

5.4.4 Off-grid Mode No-load Commissioning

For PCS units with grid-connected/off-grid capability, off-grid mode no-load commissioning must be performed first to verify inverter output performance:

  • Confirm the AC side is disconnected from the grid and in no-load state; the DC side can be connected to a simulated DC power supply or low-voltage DC signal.
  • Set the PCS to off-grid operating mode and start inverter output.
  • Measure output three-phase voltage; verify voltage is stable within 380V±2% range, with three-phase voltage unbalance less than 2%.
  • Measure output frequency; stable at 50Hz±0.2Hz, with frequency deviation meeting requirements.
  • Use a power quality analyzer to measure output waveform; sine wave quality should be good, with total harmonic distortion (THD) less than 3%, meeting power quality requirements.
  • Test off-grid voltage regulation and frequency regulation functions; regulation command response must be accurate.
  • Test off-grid overload capability: 1.1 times rated load for continuous operation, 1.5 times rated load for 1 minute, meeting design specifications.

5.4.5 Grid-connected Synchronization Performance Commissioning

  • Confirm grid-side voltage and frequency are normal and meet grid connection conditions.
  • Start PCS grid-connected mode and execute the grid synchronization process.
  • Observe the synchronization process; the PCS automatically tracks grid voltage amplitude, phase, and frequency; after synchronization is complete, smoothly close the grid-connected switch; grid connection inrush current should be less than 10% of rated current, with no obvious impact.
  • Observe no-load operation status after grid connection; PCS output power approaches 0, reactive power can be adjusted according to set values, operation is stable with no oscillation.
  • Test reactive power regulation function; continuously regulate reactive power within the range of 0.9 leading to 0.9 lagging; regulation should be smooth and accurate, meeting grid reactive power support requirements.

After PCS unit commissioning is complete, record all commissioning data and parameter configurations, confirm all performance indicators comply with national standards and design requirements, and form the PCS unit commissioning report to prepare for system joint commissioning.

5.5 System Joint Commissioning

System joint commissioning is conducted on the basis of all subsystem unit commissioning being qualified, linking all subsystems—battery system, PCS, BMS, EMS, temperature control, fire protection—to operate together, verifying the system’s overall collaborative working capability, charge/discharge performance, protection logic, and operating strategies. It is the core commissioning stage before the outdoor energy storage container is put into operation. Lain energy storage container system joint commissioning must follow the principle of “low voltage to high voltage, no-load to light load, light load to full load,” progressing step by step to ensure safety.

5.5.1 Pre-commissioning Prerequisites

Before system joint commissioning begins, the following conditions must all be confirmed as satisfied:

  • All subsystem unit commissioning is qualified, commissioning records are complete, and sign-off procedures are fully completed.
  • All high-voltage circuit insulation tests are qualified, grounding system acceptance is complete, and ground resistance meets standards.
  • Site environment meets operating requirements: cabin is clean with no debris, ventilation and lighting are good, fire-fighting equipment is in place, and emergency exits are clear.
  • Commissioning personnel have clear division of responsibilities with unified command; personnel at all positions are familiar with commissioning procedures and emergency response plans.
  • Grid access conditions are in place, grid voltage and frequency are stable within the allowable range, and grid connection procedures are complete.
  • Battery system SOC is within the safe range of 30%-70%, and battery temperature is within the normal operating temperature range.
  • All protection settings have been configured according to design requirements and protection functions are verified effective.
  • Fire protection system is in normal alert status, and temperature control system can operate normally.

5.5.2 DC System Joint Commissioning

DC Busbar Energization

  • Confirm all PCS DC switches are in the open position and all battery cluster circuit breakers are in the open position.
  • Select one battery cluster as the first to be energized; close that cluster’s battery circuit breaker, check the BCU operates normally, cluster voltage displays accurately, with no abnormal alarms.
  • Observe the DC bus voltage gradually rising to that cluster’s battery voltage, confirming no short circuit or abnormal grounding on the DC bus.
  • Close the remaining battery cluster circuit breakers sequentially; observe for 30 seconds after closing each cluster to confirm no system abnormalities, DC bus voltage is stable, and current has no abnormal fluctuations.
  • After all battery clusters are closed, check BMS system data is normal, all clusters have consistent operating status, with no circulating current or voltage abnormalities.

BMS and PCS DC Linkage

  • Close the PCS DC side switch; check the PCS DC side voltage display is consistent with the BMS total voltage, with error within the allowable range.
  • Verify BMS and PCS communication is normal; the PCS can receive the maximum allowable charge/discharge power, SOC, fault status, and other information issued by the BMS in real time.
  • Test power limit linkage: Manually set a BMS power limit value; verify the PCS output power automatically follows the limit value and does not exceed the allowable power; linkage response time not greater than 200ms.
  • Test fault linkage: Simulate a battery cluster level-1 alarm; verify the PCS automatically derates operation after receiving the alarm signal; simulate a level-2 serious fault; verify the PCS immediately shuts down, disconnects the DC circuit, and protection action is accurate.

5.5.3 Grid-connected Mode Charge/Discharge Joint Commissioning

Grid-connected No-load Operation

  • Confirm the AC side grid-connected switch is in the open position and the PCS is in standby state.
  • Issue the grid connection command; the PCS executes synchronous grid connection, smoothly closes the grid-connected switch, with no impact or tripping during the grid connection process.
  • Observe no-load operation status after grid connection: PCS active power approaches 0, reactive power is 0 or operates per set values, DC voltage is stable, battery system has no abnormal current, and operation is stable.
  • Continue no-load operation for 30 minutes, record operating data, and confirm no abnormal temperature rise, abnormal noise, or alarms on any equipment.

Low Power Charging Test

  • Set charging power to 10% of rated power and start charging mode.
  • Observe charging current rising smoothly, battery SOC increasing slowly, and charging voltage and current within normal ranges.
  • Check BMS data acquisition is normal, PCS charge/discharge control accuracy meets requirements, with power error not greater than ±1% of rated power.
  • Check temperature control system operates normally, with battery and PCS temperature rise within reasonable ranges.
  • Continue low power charging for 15 minutes; after no abnormalities, gradually increase charging power to 30% and 50% of rated power.

Rated Power Charging Test

  • Gradually increase charging power to 100% of rated charging power and maintain rated power continuous charging.
  • Monitor the highest cell voltage and highest temperature to ensure alarm thresholds are not reached.
  • Test the charging constant current/constant voltage phase transition function: When battery voltage approaches the upper limit, automatically switch from constant current to constant voltage charging, with current gradually decreasing; the transition process must be smooth with no impact.
  • Measure charging efficiency by calculating AC-DC conversion efficiency; overall efficiency must meet design specifications.
  • Test the SOC full-charge shutdown logic: When SOC reaches 100% or cell voltage reaches the upper limit, the BMS issues a full-charge signal, the PCS gradually reduces charging power to 0 and stops charging; shutdown process must be smooth.

Discharge Function Test

  • After battery charging to above 80% SOC, switch to discharge mode.
  • Gradually increase discharge power from low power, testing sequentially at 20%, 50%, and 100% of rated discharge power.
  • Observe that voltage and current change smoothly during discharge, with no oscillation or sudden changes, and battery SOC decreases uniformly.
  • Test continuous discharge at rated power, monitoring lowest battery voltage and lowest temperature to ensure they remain within normal ranges.
  • Measure discharge efficiency by calculating DC-AC conversion efficiency; system overall efficiency must meet design requirements.
  • Test the low SOC shutdown logic: When SOC falls to the set lower limit or cell voltage reaches the lower limit, the PCS gradually reduces discharge power to 0 and stops discharging to protect the battery from over-discharge.

Power Step and Dynamic Response Test

  • Test power step response: At rated power, suddenly change the power command from 100% to 0, then from 0 to 100%; verify the PCS power response is fast, overshoot is small, settling time is short, and dynamic performance meets requirements.
  • Test continuous power regulation: Smoothly regulate charge/discharge power continuously within the 0-100% range; verify power tracking is accurate with no stalling or sudden changes.

5.5.4 Grid-connected/Off-grid Seamless Transition Joint Commissioning

For outdoor energy storage containers equipped with grid-connected/off-grid transition capability, transition performance must be verified to ensure uninterrupted power supply to critical loads:

Grid-connected to Off-grid Test

  • System is in grid-connected loaded operation state at 50% load rate.
  • Simulate grid power loss; test the PCS automatically detects the grid fault and rapidly switches to off-grid inverter mode.
  • Measure load-side voltage interruption time during the transition; ensure it is less than 20ms, achieving seamless transition without load equipment being affected by power interruption.
  • After off-grid operation begins, output voltage and frequency must be stable, and loads operate normally.

Off-grid to Grid-connected Test

  • System is in off-grid loaded operation state; simulate grid power restoration.
  • Test the PCS automatically detects grid voltage, executes synchronization adjustment; when voltage, phase, and frequency are synchronized, automatically close the grid-connected switch and switch to grid-connected mode.
  • Transition process must be smooth with no inrush current, and no impact on loads or the grid.
  • Repeat the transition test multiple times to verify transition function is stable and reliable, with 100% success rate.

5.5.5 Full-system Integrated Protection Joint Commissioning

Battery Fault Integrated Protection

  • Simulate a single cell overvoltage fault: Upon level-1 alarm, the system issues an alarm and automatically reduces power; upon reaching the protection value, the system automatically shuts down and isolates the corresponding battery cluster, preventing fault propagation.
  • Simulate a battery overtemperature fault: Verify graded alarm, derating, and shutdown protection logic; simultaneously, the temperature control system automatically increases cooling power for coordinated temperature reduction.
  • Simulate an insulation ground fault: The system immediately issues an alarm and shuts down to prevent electric shock and fault expansion.

Electrical Fault Integrated Protection

  • Simulate an AC side short-circuit fault: The PCS rapidly executes protection shutdown; simultaneously, the AC circuit breaker trips, the battery-side circuit breaker opens, and the fault is reliably isolated.
  • Simulate a DC side short circuit: BMS and PCS trigger protection simultaneously, rapidly cutting off the fault circuit to prevent battery short-circuit and fire.

Fire Protection Integrated Protection

  • Simulate a fire alarm signal; verify the system automatically executes the shutdown procedure: immediately stop charge/discharge, disconnect AC/DC main switches, shut down temperature control and ventilation systems, activate audible and visual alarms, and upload the fire alarm signal to the monitoring platform.
  • Test the fire emergency stop button function: After pressing, the entire station executes emergency shutdown, all high-voltage circuits are de-energized, and action is reliable.

Emergency Stop Test

  • Press the local emergency stop button; verify the entire system immediately executes emergency shutdown, all power circuits are cut off, equipment enters a safe state, and shutdown response time is not greater than 100ms.
  • Test remote emergency stop function: Issue an emergency stop command from the EMS monitoring platform; the system accurately executes the shutdown action.

5.5.6 Energy Management Strategy Joint Commissioning

Peak-valley Arbitrage Strategy Test

  • Set typical peak/valley electricity price periods and charge/discharge strategies; simulate a complete operating cycle; verify the system automatically starts charging and discharging on schedule, with power and target SOC control accurate, completely executing the peak-valley arbitrage logic.
  • Calculate simulated revenue and compare with theoretical revenue; strategy execution accuracy must not be less than 98%.

Demand Management Strategy Test

  • Simulate load power changes; when total load power approaches the set demand threshold, the energy storage system automatically discharges to supplement, suppressing peak power and ensuring maximum demand is controlled within the set value.
  • Test demand response speed and control accuracy to meet commercial and industrial user demand management requirements.

Multi-strategy Priority Test

  • Set multiple operating strategies simultaneously; verify the system executes according to priority, with clear strategy transition logic, no conflicts, and no disorder.
  • Test manual intervention priority: Manual commands can override automatic strategies, prioritizing manual operation.

After system joint commissioning is complete, organize all joint commissioning data, form the system joint commissioning report, and confirm all system functions and performance indicators meet design requirements and are ready for trial operation.

5.6 System Trial Operation

After system joint commissioning passes, the continuous trial operation phase begins. Long-duration loaded operation is used to verify the outdoor energy storage container’s long-term operational stability, reliability, and consistency, exposing potential hidden hazards and laying the foundation for formal commercial operation. KITOZER recommends an outdoor energy storage container trial operation period of not less than 72 hours; important projects may be extended to 168 hours (7 days).

5.6.1 Trial Operation Prerequisites

  • All system joint commissioning is qualified, all discovered issues have been rectified and re-inspected successfully.
  • All protection settings and operating parameters have been optimized to optimal state, with complete parameter backups.
  • Trial operation plan has been prepared and approved; trial operation organizational structure, personnel division, record requirements, and emergency plans are clearly defined.
  • Grid conditions are stable and load conditions are available to meet continuous charge/discharge trial operation requirements.
  • Monitoring system operates normally, can completely record all operating data, and data storage capacity is sufficient.
  • Operations and maintenance personnel have been trained and are familiar with system operation and emergency handling procedures.

5.6.2 Trial Operation Plan Development

A detailed trial operation plan must be developed before trial operation begins, with main contents including:

  • Trial operation period and schedule: Define trial operation start/end times and phased operation arrangements.
  • Trial operation operating modes: Determine charge/discharge cycle system, such as 1 charge/1 discharge or 2 charges/2 discharges per day, charge/discharge depth, and power settings.
  • Monitoring content and frequency: Define parameters requiring monitoring and recording frequency; record once per hour during normal operation, with increased frequency during critical phases.
  • Inspection system: Develop inspection routes, inspection content, and inspection frequency; define inspection personnel and responsibilities.
  • Abnormal handling procedures: Define fault grading and handling procedures, including shutdown and reporting procedures for serious faults.
  • Acceptance criteria: Define trial operation qualification criteria, including availability rate, fault rate, and performance indicators.

5.6.3 Trial Operation Core Content

Continuous Charge/Discharge Cycle Test

  • Execute continuous charge/discharge cycles according to the cycle system set in the trial operation plan, with charge/discharge depth of 80% DOD and rated power operation.
  • After each complete charge/discharge cycle, record key data: charge/discharge energy, charge/discharge efficiency, cycle count, and battery temperature rise.
  • Monitor cell voltage consistency; cell voltage difference must remain within a reasonable range during cycling, with no obvious trend toward increased dispersion.
  • Test system continuous operation capability: System availability rate must not be less than 99% during the 72-hour trial operation, with no unscheduled shutdowns.

Rated Conditions Stability Test

  • Maintain rated charge/discharge power for extended operation and monitor each equipment’s operating status:
Equipment Monitoring Item Standard
Battery system Maximum cell temperature Not exceeding 35°C
Battery system Maximum temperature difference between cells Not exceeding 5°C
Battery system Abnormal alarms None
PCS equipment Maximum IGBT temperature Not exceeding 70°C
PCS equipment Reactor temperature Normal
PCS equipment Fan operation Stable, no abnormal noise
PCS equipment Overheating None
Temperature control system Cabin temperature Stable at 25°C±3°C
Temperature control system AC start/stop Normal
Temperature control system Temperature control accuracy Within specification
Distribution equipment Breaker, busbar, cable temperature rise No abnormal temperature rise
Distribution equipment Contact point temperature Not exceeding 70°C
  • Monitor power quality; harmonic content and power factor during grid-connected operation must meet grid requirements.

Extreme Condition Verification Testing

  • High SOC condition: Charge battery to above 90% SOC, maintain low-power float charging; verify battery management and voltage control stability, with no overcharge risk.
  • Low SOC condition: Discharge battery to below 10% SOC; verify undervoltage protection and discharge control, with no over-discharge risk.
  • Ambient temperature condition: If site ambient temperature approaches design limit temperatures, verify system operation capability under high/low temperature environments; the temperature control system must ensure equipment operating temperatures remain within normal ranges.

Unattended Operation Test

  • Set automatic operation strategy; system enters unattended mode for continuous operation of more than 24 hours.
  • Verify the system can automatically execute charge/discharge strategies, automatically handle general alarms, and automatically upload operating data without manual intervention.
  • Test automatic fault alarm function; when abnormalities occur, notifications can be promptly pushed to operations and maintenance personnel.

5.6.4 Trial Operation Inspection and Recording

Inspection Content

During the trial operation period, perform scheduled inspections with the following content:

Inspection Area Inspection Items
Container exterior Door seals intact, no abnormal noise or odor, no standing water or debris nearby
Battery compartment No battery module swelling, leakage, or odor; uniform temperature distribution; no loose or overheating connections
Electrical compartment PCS and distribution cabinet operation without abnormal noise or odor; indicator lights normal; no breaker tripping; no cable overheating
Temperature control system AC and fans operating normally; supply air temperature normal; filters not blocked
Fire protection system Controller operating normally, no alarms; gas cylinder pressure normal; detector indicator lights normal
Monitoring system Data display normal, no abnormal alarms, communication connections normal

Data Recording

  • Record core system operating data once per hour, including: total voltage, total current, SOC, highest/lowest cell voltage, highest/lowest temperature, charge/discharge power, cabin temperature, and ambient temperature.
  • Daily statistics: charge/discharge energy, cycle count, equipment operating hours, alarm count, and availability rate.
  • Detailed records of abnormal events: occurrence time, phenomenon, handling process, and handling results.

5.6.5 Trial Operation Issue Rectification and Acceptance

  • General issues and minor alarms discovered during trial operation should be recorded and uniformly rectified/optimized after trial operation ends.
  • For serious faults affecting system safety, immediately shut down for troubleshooting; after rectification is complete, restart the trial operation time calculation.
  • After trial operation ends, compile all trial operation data and records and prepare the trial operation report.
  • The owner, supervision unit, construction unit, and manufacturer jointly conduct trial operation acceptance, verifying against the trial operation plan and acceptance criteria; confirm stable system operation, performance up to standard, complete functionality, and no major outstanding issues; then judge trial operation as qualified.
  • After trial operation passes, the system can be formally put into commercial operation and enters the warranty period.

Chapter 6: Outdoor Energy Storage Container Installation Quality Acceptance Standards

Outdoor energy storage container installation quality acceptance is the key link for controlling project quality and ensuring safe system operation. Acceptance work must strictly follow national standards, design drawings, and the requirements of this manual, adhering to the principle of “seeking truth from facts, data as the basis, item-by-item verification” to ensure objective, accurate, and traceable acceptance results. KITOZER can cooperate with the owner and supervision unit to complete the full-process acceptance work, providing technical support and documentation support.

6.1 Acceptance Classification and Acceptance Basis

6.1.1 Acceptance Level Classification

Referring to the “Unified Standard for Construction Quality Acceptance of Building Engineering” and electrochemical energy storage power station acceptance specifications, the outdoor energy storage container installation project is divided into three acceptance levels: itemized works, divisional works, and unit works, with level-by-level acceptance and level-by-level signature:

  • Itemized works acceptance: Conducted for a single construction process, such as foundation works, container installation, electrical wiring, grounding construction, and equipment installation. Each process is accepted immediately upon completion; unqualified preceding processes cannot proceed to subsequent processes.
  • Divisional works acceptance: On the basis of all itemized works being qualified, conduct acceptance of the entire installation project, commissioning project, and other divisions, confirming the overall quality of the divisional works is qualified.
  • Completion acceptance: On the basis of all divisional works acceptance being qualified, system trial operation passing, and completion documentation being complete, conduct overall project completion acceptance; after acceptance passes, formally deliver for use.

6.1.2 Main Acceptance Basis

  • National and industry standards/specifications: GB 51048 “Code for Design of Electrochemical Energy Storage Power Stations,” GB 50303 “Code for Acceptance of Construction Quality of Building Electrical Installation Engineering,” GB 50168 “Standard for Construction and Acceptance of Cable Lines in Electrical Equipment Installation Engineering,” GB 50169 “Code for Construction and Acceptance of Grounding Devices in Electrical Equipment Installation Engineering,” NB/T 10394 “Acceptance Code for Electrochemical Energy Storage Power Stations,” T/CNESA 1201 “Technical Specification for Prefabricated Cabin Type Lithium-ion Battery Energy Storage Systems,” etc.
  • Design documents: Construction drawings, design specifications, design changes, technical consultations, and other formal design documents.
  • Contract documents: Quality standards and technical requirements agreed in procurement contracts, construction contracts, and technical agreements.
  • Manufacturer documentation: This installation and commissioning manual, equipment factory certificate of conformity, factory test reports, equipment technical manuals, etc.
  • Construction documentation: Construction records, test records, commissioning records, concealed works acceptance records, and other process documentation.

6.2 Itemized Works Quality Acceptance

6.2.1 Foundation Works Acceptance

Foundation works acceptance is a concealed works acceptance that must be completed before container installation. Acceptance content and qualification criteria are as follows:

Foundation Dimensions and Elevation

Inspection Item Acceptance Standard
Foundation exterior dimension deviation Not greater than ±20mm
Foundation centerline vs. design centerline deviation Not greater than 10mm
Foundation top elevation deviation Not greater than ±10mm
Elevation difference between two ends of same foundation Not greater than 5mm
Foundation surface flatness (2m straightedge) Deviation not greater than 3mm/m
Overall flatness deviation Not greater than 5mm
Embedded part position deviation Not greater than ±5mm
Embedded part elevation deviation Not greater than ±3mm

Concrete Quality

  • Concrete strength reaches design requirements, with concrete test block strength inspection report available; strength grade not lower than C30.
  • Foundation surface has no obvious cracks, honeycombing, pitting, exposed reinforcement, or holes; general defects must be repaired per specification.
  • Foundation settlement observation data meets requirements, with no uneven settlement.

Waterproofing and Drainage

  • Drainage slope around foundation not less than 3‰, drainage channels unobstructed, no water accumulation risk.
  • Foundation raised above ground not less than 200mm, with no water infiltration path at the bottom.
  • Waterproof sealing at embedded parts and pipe penetration points is properly executed with no leakage points.

Grounding Reservation

  • Number of grounding exit points not less than 2, positioned per design requirements.
  • Grounding flat steel specifications meet design, and exit length meets lap joint requirements.
  • Grounding exit points are reliably connected to the grounding grid with good continuity.

After acceptance passes, sign the “Concealed Works Acceptance Record” and “Foundation Itemized Works Acceptance Record” with confirmation signatures from all parties.

6.2.2 Container Installation Works Acceptance

Container Position and Levelness

Inspection Item Acceptance Standard
Container longitudinal/transverse centerline vs. foundation centerline deviation Not greater than 10mm
Container longitudinal levelness deviation Not greater than 2mm/m
Container overall longitudinal deviation Not greater than 5mm
Container transverse levelness deviation Not greater than 2mm/m
Container overall transverse deviation Not greater than 3mm

Fixation and Sealing

  • Anchor bolt tightening torque meets design requirements, anti-loosening devices complete, bolts exposed 2-3 threads.
  • Welded fixation: weld height and length meet requirements, welds full and free of false welding, anti-corrosion treatment properly applied.
  • Container bottom gap sealing is continuous and full, with no cracking or bubbles, and waterproofing performance is good.
  • Container perimeter waterproof slope is intact and drainage is smooth.

Appearance and Accessories

  • Container exterior is intact with no deformation, dents, paint peeling, or rust; paint surface uniform and aesthetically pleasing.
  • Doors open and close smoothly, sealing strips are intact, and after closing, sealing is tight; locks and hinges function properly.
  • Ventilation louvers and filter screens are intact with no damage or blockage.
  • Ladders, platforms, nameplates, and other accessories are firmly installed, correctly positioned, and fully functional.

6.2.3 Electrical Wiring Works Acceptance

Cable Laying

Inspection Item Acceptance Standard
Cable model, specification, quantity Consistent with design, no wrong use
Cable laying Neat, securely tied, no twisting, compression, or damage; bending radius per specification
Power, control, communication cables Layered separation with spacing meeting anti-interference requirements
Cable identification Clear, complete, accurate; identification at both ends and bends
Fireproof sealing at pipe/board penetrations Tight and compliant with fire protection requirements

Wiring Quality

  • Wiring terminal crimping is firm, conductor core undamaged, contact surfaces properly prepared, and conductive grease evenly applied.
  • Bolted connections tightened to specified torque with contact resistance meeting requirements.
  • Phase sequence and polarity correctly connected, with no mis-connections or reverse connections.
  • Cabinet interior wiring neat and orderly, horizontally and vertically aligned, with no crossed or chaotic wiring.
  • Exposed live parts have insulation distances meeting safety specifications with adequate protection.

Insulation Performance

Circuit Insulation Resistance Requirement
DC power circuit ≥1MΩ
AC power circuit ≥0.5MΩ
Control circuit ≥1MΩ
  • Insulation test records complete with authentic data.

6.2.4 Grounding Works Acceptance

Grounding Grid Construction Quality

  • Ground electrode specifications, quantity, burial depth, and spacing meet design requirements.
  • Ground busbar specifications meet requirements; lap weld lengths comply with specifications (flat steel lap not less than 2 times width, welded on three sides).
  • Anti-corrosion treatment at weld points properly applied with no omissions.
  • Grounding backfill soil is compacted with no stones or construction waste.

Equipment Grounding

  • All electrical equipment metal enclosures are individually grounded with no series grounding.
  • Grounding conductor specifications meet requirements with clear yellow-green dual-color identification.
  • Grounding terminals are firmly connected, anti-loosening measures complete, and contact resistance qualified.
  • Equipotential bonding is complete with all metal components reliably bonded.

Ground Resistance

Item Requirement
Shared grounding grid ground resistance ≤4Ω; after design confirmation, may meet minimum requirements for special areas
Test method Correct
Test records Complete
Test instruments Within calibration validity period

6.2.5 Equipment Installation Works Acceptance

Battery System Installation

  • Battery rack installation is firm with verticality and levelness meeting specifications.
  • Battery modules installed neatly, securely fixed, free of impact damage, with clear labeling.
  • Connection copper busbars flat and bright, connections tightened, and insulation protection in place.
  • High-voltage box firmly installed with complete internal components and neat wiring.

PCS and Distribution Cabinet Installation

Inspection Item Acceptance Standard
Equipment installation position Correct per design
Fixation Firm
Verticality deviation ≤1.5‰
Equipment appearance Intact, no damage, no loose or detached components
Equipment grounding Reliable, clear labels
Cabinet doors Open/close smoothly, locks intact, proper sealing

Auxiliary Equipment Installation

  • Temperature control equipment, fire protection equipment, and monitoring equipment installed at correct positions and firmly fixed.
  • Piping and line connections meet specifications, with no leakage or loosening.
  • Detectors and sensors installed at positions meeting design requirements with correct detection angles.

6.3 Divisional Works Quality Acceptance

6.3.1 Installation Divisional Works Acceptance

On the basis of all itemized works acceptance being qualified, conduct installation divisional works acceptance:

  • Verify all itemized works acceptance records are complete, signatures complete, and all qualified.
  • Verify quality control documentation is complete, including material/equipment certificates of conformity, test reports, construction records, and test records.
  • Conduct on-site sampling inspection of installation quality, focusing on wiring quality, grounding quality, and equipment fixation; sampling results must meet specification requirements.
  • Verify aesthetic quality: overall layout neat and orderly, workmanship standard.
  • Form the “Divisional Works Quality Acceptance Record” with all parties signing to confirm the installation divisional works is qualified.

6.3.2 Commissioning and Trial Operation Divisional Works Acceptance

After system commissioning and trial operation are complete, conduct commissioning and trial operation divisional works acceptance:

  • Verify unit commissioning and joint commissioning records are complete with complete data, and all performance indicators meet standards.
  • Verify trial operation records are complete, trial operation period meets requirements, system operated stably during trial operation, and availability rate meets standards.
  • Verify all issues discovered during commissioning have been rectified with re-inspection records.
  • Verify protection settings and operating parameters comply with design and grid requirements.
  • Verify system functions are complete, meeting all functional requirements agreed in the contract.
  • Form the commissioning and trial operation divisional works acceptance conclusion, confirming commissioning quality is qualified.

6.4 Completion Acceptance

6.4.1 Completion Acceptance Prerequisites

  • All divisional works acceptance is qualified, with quality meeting standards and contract requirements.
  • System trial operation is qualified with performance indicators meeting design requirements.
  • Completion documentation is compiled, classified, and archived—complete and comprehensive.
  • Site is cleaned up, site cleared after work completion, equipment is tidy, and delivery conditions are met.
  • Operations and maintenance personnel training is complete, with capability for independent operation and routine maintenance.
  • Grid interconnection procedures are complete, meeting formal grid-connected operation requirements.

6.4.2 Completion Acceptance Organization and Process

  • Acceptance application: After the construction unit completes all work, submit a completion acceptance application to the owner and supervision unit, along with the full set of completion documentation.
  • Documentation pre-review: The supervision unit pre-reviews completion documentation; after documentation is complete and qualified, organize formal acceptance.
  • Form acceptance team: Form an acceptance team with representatives from the owner, supervision, design, construction, and equipment manufacturer, with clear acceptance division of responsibilities.
  • Site inspection: The acceptance team conducts on-site physical inspection, verifying equipment installation quality, appearance, operating status, and spot-checking key performance parameters.
  • Documentation review: The acceptance team reviews the full set of completion documentation, verifying completeness, authenticity, and standardization.
  • Functional spot testing: As needed, spot-test core system functions such as charge/discharge function, alarm function, and grid/off-grid transition function to verify functionality is effective.
  • Issue summary and rectification: The acceptance team summarizes discovered issues, issues rectification opinions, responsible units rectify within the specified period, and conduct re-inspection after rectification.
  • Acceptance opinion signing: After all issues are rectified to qualification, the acceptance team jointly signs the “Completion Acceptance Certificate,” judging the project as qualified and formally delivering for use.

6.4.3 Completion Acceptance Qualification Criteria

  • All project content is fully completed, conforming to design drawings and contract scope.
  • All itemized and divisional works acceptance is qualified, with project quality conforming to national specifications and industry standards.
  • System performance and functions meet design requirements and technical agreement provisions, with trial operation meeting standards.
  • Completion documentation is complete, accurate, and standardized, meeting archiving requirements.
  • No major quality issues or safety hazards; general issues have been rectified to qualification.

6.5 Completion Documentation List

Outdoor energy storage container project completion documentation must be complete, standardized, and provided in multiple copies to meet the owner’s archiving and operations/maintenance needs. Main contents include:

  • Project management documentation: Commencement report, construction organization design, technical disclosure records, drawing review records, design changes, engineering consultations, construction logs, completion report, completion acceptance certificate.
  • Equipment and material documentation: Equipment/material lists, factory certificates of conformity, factory inspection reports, commodity inspection certificates (for imported equipment), equipment manuals, spare parts lists, and special tool lists.
  • Construction record documentation: Foundation construction records, concealed works acceptance records, container installation records, equipment installation records, cable laying records, wiring construction records, grounding construction records, and welding construction records.
  • Testing and commissioning documentation: Insulation resistance test records, ground resistance test records, circuit resistance test records, phase sequence inspection records, unit commissioning reports, system joint commissioning reports, trial operation reports, and protection setting sheets.
  • Quality acceptance documentation: Itemized works acceptance records, divisional works acceptance records, quality inspection batch records, and quality accident handling records.
  • Completion drawings: Completion general layout plan, electrical completion drawings, grounding completion drawings, fire protection completion drawings, and monitoring system completion drawings.
  • Other documentation: Grid interconnection agreements, grid acceptance documents, training records, operation and maintenance manuals, and after-sales service commitments.

Chapter 7: Outdoor Energy Storage Container Daily Operation & Maintenance and Fault Troubleshooting

Outdoor energy storage containers operate outdoors for extended periods and are affected by environmental temperature, humidity, sand/dust, and other factors. A normalized operation and maintenance management mechanism must be established. Through standardized daily inspections, regular maintenance, and professional fault troubleshooting, system safety, stability, and efficient operation are ensured, extending equipment service life. KITOZER can provide full life-cycle operation and maintenance services and technical support to ensure long-term reliable operation of energy storage containers.

Chapter 7 Operations & Maintenance Management

7.1 General Principles of Operations & Maintenance Management

7.1.1 Basic O&M Principles

  • Safety First Principle: All O&M operations must strictly comply with electrical safety regulations. Implement the procedures of power outage, voltage verification, grounding, and tagging/locking. Strictly prohibit operating against regulations to ensure personnel and equipment safety.
  • Prevention First Principle: Combine routine inspections with scheduled maintenance. Identify and eliminate potential hazards in advance, prevent fault escalation, and reduce unscheduled downtime.
  • Standardized Operation Principle: Strictly operate according to the O&M manual and manufacturer’s instructions. Do not arbitrarily alter equipment parameters, disassemble core components, or change system wiring without authorization.
  • Recording and Traceability Principle: All O&M operations, fault handling, and parameter changes must be recorded in detail, forming a complete O&M archive for traceability and analysis.
  • Professional Division of Labor Principle: Specialized work such as high-voltage operations, battery maintenance, and fire protection maintenance must be performed by qualified professionals with appropriate certifications. Uncertified operation is strictly prohibited.

7.1.2 O&M Personnel Requirements

  • O&M personnel must undergo professional training, be familiar with energy storage system principles, equipment structure, and operational procedures, and master safety operation regulations and emergency response methods. They may only take up their posts after passing the assessment.
  • Special operation personnel such as high-voltage electricians and fire protection maintenance staff must hold nationally recognized special operation certificates within their validity period.
  • O&M personnel must be proficient in monitoring system operations, able to view operating status, analyze operational data, and handle general alarms through the monitoring platform.
  • O&M personnel must be equipped with qualified safety protective equipment and specialized tools. They must discharge static electricity and wear insulating protective gear before entering the battery compartment.

7.1.3 O&M Safety Precautions

  • Before entering the energy storage container, first observe the exterior for any abnormalities. After opening the door, ventilate for no less than 10 minutes. Only after confirming there is no odor or accumulation of combustible gases inside may personnel enter.
  • Open flames and smoking are strictly prohibited inside the battery compartment. Carrying flammable or explosive items into the compartment is strictly forbidden.
  • High-voltage operations must be performed by two people: one operator and one supervisor. Use qualified insulating tools, and wear insulating shoes and insulating gloves.
  • When the battery system is energized, it is strictly forbidden to touch both the positive and negative terminals simultaneously, and it is forbidden to touch the positive terminal with metal tools to prevent short circuits.
  • In the event of battery electrolyte leakage, swelling, smoke, or other abnormal conditions, immediately stop the machine, cut off power, evacuate personnel, and contact manufacturer professionals for handling. Self-disassembly of batteries is strictly prohibited.
  • Fire protection system maintenance must be performed by professionals. Unauthorized activation of fire suppression devices is strictly prohibited, and touching fire suppression gas cylinders and activation pipelines without authorization is forbidden.

7.2 Routine Inspection and O&M

Routine inspection is the fundamental work for timely detection of equipment abnormalities and prevention of faults. It is divided into two frequencies: daily inspection and weekly inspection.

7.2.1 Daily Inspection (at least once per day)

External Container Inspection

  • Check that the container exterior is intact, with no deformation, damage, or corrosion. Check that surrounding areas are free of debris accumulation and standing water.
  • Check that the container doors close tightly, locks are intact, and there are no signs of tampering.
  • Check that ventilation louvers are not blocked or clogged with debris, and that rain shields are intact.
  • Check that surrounding security facilities are intact and warning signage is clear and complete.

Remote Inspection via Monitoring System

  • Log in to the EMS monitoring platform to view the overall system operating status and check for alarm information.
  • View key battery system parameters: total voltage, total current, SOC, maximum cell voltage, minimum cell voltage, maximum temperature, minimum temperature. Parameters must be within normal ranges.
  • View PCS operating status: charging/discharging power, AC/DC voltage and current. Operation must be stable without fluctuations.
  • View temperature control system status: internal compartment temperature, air conditioning operating status. Temperature must remain stable within a reasonable range.
  • View fire protection system status: no fire alarms, no faults, detectors working normally.
  • View the day’s charging/discharging energy and operation duration. Verify execution of operating strategies.
  • View historical alarm records, confirm all alarms have been handled, and no unresolved abnormalities remain.

Key On-site Inspection Points

Method Check Items
Listen Approach the container and listen for internal operating sounds. No abnormal noise, unusual friction sounds, or discharge sounds.
Smell Detect any burning odor, electrolyte odor, or other abnormal smells.
Touch Touch the container door panels. No abnormal high temperature; temperature should be uniform.

7.2.2 Weekly Inspection (once per week)

Based on daily inspections, perform an internal compartment inspection once per week:

Battery Compartment Inspection

  • Check battery module appearance is intact: no swelling, no electrolyte leakage, no deformation. Labels must be clear.
  • Check battery connection copper busbars: no loosening, no overheating, no oxidation or discoloration. Bolts must be properly tightened.
  • Check battery racks are firm and secure: no loosening or corrosion.
  • Check high-voltage box circuit breaker status: normal, no overheating, no abnormal noise.
  • Check BMU acquisition wiring connections: firmly plugged, no detachment or damage.
  • Check internal compartment temperature uniformity: no local overheating areas.
  • Clean dust inside the compartment and maintain environmental cleanliness.

Electrical Compartment Inspection

  • Check that PCS operates smoothly: no abnormal noise, no unusual odor, no abnormal vibration. Indicator light status must be normal.
  • Check power distribution cabinet circuit breakers and switches: normal status. Wiring terminals: no overheating. Cables: no aging.
  • Check that energy meters and protection devices display normally with no abnormal parameters.
  • Check surge protector status indicators: normal, no failure.
  • Check cabinet interior cleanliness: no dust or debris, heat dissipation air ducts unobstructed.

Auxiliary System Inspection

  • Check air conditioning operates normally: cooling/heating effect is good, outlet air temperature is normal, filters are clean.
  • Check fans operate smoothly: no abnormal noise, correct rotation direction.
  • Check fire protection controller operates normally: no fault alarms, gas cylinder pressure in the green zone.
  • Check smoke detectors, heat detectors, and combustible gas detectors: indicator lights flashing normally, no dust accumulation obscuring the surface.
  • Check monitoring equipment and communication equipment operate normally with stable communication connections.

After completing the weekly inspection, fill in the “Weekly Inspection Record Form”, documenting any problems discovered during inspection and their handling status.

7.3 Scheduled Maintenance

Scheduled maintenance is key to ensuring long-term reliable equipment operation. It is divided into four levels: monthly, quarterly, semi-annual, and annual, with different maintenance content and depth corresponding to each level.

7.3.1 Monthly Maintenance

Cleaning and Maintenance

  • Clean the air conditioning intake filters and ventilation opening filters. Increase cleaning frequency in dusty areas to ensure smooth ventilation.
  • Wipe dust from equipment surfaces inside the compartment to keep equipment clean and prevent dust accumulation from affecting heat dissipation.
  • Clear debris and weeds around the container exterior, keeping drainage channels unobstructed.

Tightening Checks

  • Check container doors, hinges, and locks. Tighten loose screws and apply lubricating oil to ensure smooth opening and closing.
  • Check ladder and platform connection bolts; tighten any loose parts.
  • Check cable bundling and securing; organize any loose cables.

Functional Checks

  • Test the emergency stop button function, verify reliable operation, and reset after testing.
  • Test audible and visual alarm devices to confirm normal operation.
  • Check that monitoring system data storage is normal and hard disk capacity is sufficient.
  • Verify the system clock to ensure accurate time.

7.3.2 Quarterly Maintenance

Electrical Connection Inspection

  • Use an infrared thermometer to measure temperatures at major electrical connection points, including battery busbar connection points, breaker terminals, busbar connections, and PCS wiring terminals. Temperature must not exceed 70°C, and temperature difference must not exceed 15K. If hot spots are found, immediately cut off power, tighten, and handle accordingly.
  • Check DC and AC busbar connection tightness. Re-tighten critical parts according to specified torque.

Temperature Control System Maintenance

  • Check air conditioning refrigerant pressure; recharge refrigerant if insufficient.
  • Clean air conditioning condenser and evaporator fins to improve heat exchange efficiency.
  • Check temperature sensor calibration; calibrate if temperature deviation is too large.
  • Check condensate drain piping to ensure smooth drainage without blockage or leakage.

Grounding System Inspection

  • Check grounding connection points for loosening or corrosion. Treat corroded areas and tighten bolts.
  • Test grounding continuity of key equipment to ensure reliable grounding.

7.3.3 Semi-annual Maintenance

Insulation Performance Testing

  • After system power-off, measure insulation resistance of DC and AC power circuits. Compare with historical data; insulation resistance should show no significant decline.
  • Measure insulation resistance of control circuits to ensure proper isolation between strong current and weak current systems.
  • Test the DC system insulation monitoring device function; simulate grounding faults to verify alarm functionality.

Battery System Special Inspection

  • Verify the accuracy of BMS collected data. Spot-check cell voltages and temperatures, calibrate acquisition channels with significant deviations.
  • Check battery module consistency, analyze cell voltage dispersion, and perform balancing maintenance on modules with excessive voltage differences.
  • Check battery cluster fuses and circuit breakers to ensure protection functions are intact.
  • Record battery system SOH changes and assess battery health status.

Fire Protection System Maintenance

  • Clean dust from the surface of all fire detectors to ensure detection sensitivity.
  • Test detector functions; simulate test smoke detectors, heat detectors, and combustible gas detectors to verify alarm and linkage functions are normal.
  • Check fire suppression gas cylinder pressure; recharge promptly if insufficient.
  • Check piping and nozzles for blockage or leakage.
  • Test manual alarm buttons and emergency start/stop buttons to confirm normal function.

7.3.4 Annual Maintenance (Comprehensive Maintenance)

Annual maintenance is deep maintenance, recommended to be performed by manufacturer professionals. It involves a comprehensive inspection of system status to ensure stable operation for the coming year:

Battery System Deep Maintenance

  • Full detection of all cell voltages and temperatures, with comprehensive assessment of battery consistency and health status.
  • Perform full-system balancing maintenance to optimize cell voltage differences and improve available capacity of battery packs.
  • Calibrate BMS SOC estimation accuracy to improve SOC accuracy.
  • Inspect internal components of battery cluster high-voltage boxes; replace aging components.
  • Perform battery capacity testing to assess actual available capacity and degradation, and issue a battery health assessment report.

PCS Deep Maintenance

  • Clean dust from inside the PCS, clean radiators and air ducts to improve heat dissipation.
  • Check the status of core components including IGBTs, capacitors, and reactors; assess aging degree.
  • Calibrate voltage and current sampling accuracy to ensure accurate metering and control.
  • Upgrade PCS control program to the latest version to optimize operating performance.
  • Comprehensively test protection functions to verify accurate protection settings and reliable operation.

EMS System Maintenance

  • Back up system data and configuration parameters to prevent data loss.
  • Clean redundant database data to optimize system operating speed.
  • Upgrade monitoring system software versions to fix known issues and add functional optimizations.
  • Check communication link stability and optimize communication parameters.
  • Check UPS power batteries, test backup power supply duration, and replace aging batteries.

Overall Performance Testing

  • Perform rated power charge/discharge tests to check actual system efficiency, power accuracy, and power quality.
  • Test grid-connected/off-grid switching, emergency stop, and other core functions to ensure reliable operation.
  • Verify the execution effect of energy management strategies and optimize strategy parameters.
  • Issue an annual O&M inspection report with system health assessment and optimization recommendations.

Safety Protection Inspection

  • Comprehensively test grounding grid resistance to ensure compliance with requirements.
  • Test surge protector performance; replace degraded surge protection devices.
  • Inspect all insulation components and protective components; replace aging or damaged parts.
  • Assess the overall safety level and propose safety improvement recommendations.

7.4 Common Fault Troubleshooting and Handling

Various faults may occur during the operation of outdoor energy storage containers. O&M personnel must master troubleshooting methods and emergency handling measures for common faults, enabling rapid location and rapid resolution to minimize fault impact. The following are common faults and their handling methods. For faults involving high voltage and core components, contact manufacturer professionals for handling. Unauthorized disassembly and repair is strictly prohibited.

7.4.1 Common Battery System Faults

Fault Phenomenon Possible Causes Handling Methods
Cell overvoltage alarm Poor cell consistency, individual cells reaching high voltage first during charging; BMS acquisition deviation; excessive charging power 1. Stop charging, verify actual cell voltage to confirm true overvoltage; 2. If acquisition deviation, calibrate BMS acquisition; 3. Perform balancing maintenance for large cell voltage differences; 4. Reduce charging power and observe changes
Cell undervoltage alarm Inconsistent cell capacity degradation, some cells reaching low voltage first during discharge; cell micro-short circuit with high self-discharge; acquisition deviation 1. Stop discharging, measure actual cell voltage; 2. Individually recharge and balance low-voltage cells; 3. If self-discharge is abnormal, contact manufacturer to assess replacement; 4. Calibrate acquisition channels
Battery over-temperature alarm Excessive ambient temperature; temperature control system fault; excessively high charge/discharge C-rate; increased cell internal resistance causing heat generation 1. Reduce charge/discharge power or shut down for cooling; 2. Check temperature control system operating status, troubleshoot air conditioning faults; 3. Clean ventilation air ducts to ensure heat dissipation; 4. If high temperature persists, investigate internal cell faults
Low insulation resistance alarm Insulation damage somewhere on the DC busbar; wet or dusty wiring terminals; degraded acquisition circuit insulation; damaged cables 1. Shut down and inspect grounding points section by section, focusing on wet and high-wear areas; 2. Clean dust and moisture from wiring terminals; 3. Replace damaged cables; 4. Re-test insulation after fault elimination
Battery cluster communication interruption Loose or disconnected communication cables; BCU/BMU failure; auxiliary power supply fault; address conflict 1. Check communication cable connections, re-plug; 2. Check auxiliary power supply; 3. Verify no duplicate device addresses; 4. Replace faulty communication modules

7.4.2 Common PCS Faults

Fault Phenomenon Possible Causes Handling Methods
Grid connection failure Abnormal grid voltage/frequency; grid connection contactor fault; synchronization control abnormality; incorrect grid phase sequence 1. Check whether grid parameters are within the allowable grid connection range; 2. Check grid connection contactor status and wiring; 3. Restart PCS and retry grid connection; 4. Verify phase sequence correctness for grid connection
Charge/discharge power cannot increase BMS power limiting; DC voltage too low; abnormal AC voltage; IGBT fault derating; incorrect parameter settings 1. Check BMS maximum allowable charge/discharge power to confirm whether battery side is limiting; 2. Check whether DC bus voltage is within operating range; 3. Verify whether grid voltage is normal; 4. Check whether power parameter settings are correct
Overcurrent trip Excessive sudden load change; internal short circuit; abnormal current sampling; protection settings too low 1. Cut off power and check circuit for short circuit points; 2. Check whether current sampling is normal; 3. Verify whether protection settings are reasonable; 4. Reduce power and test gradually to identify the fault point
Overtemperature shutdown Cooling fan failure; severe dust accumulation on heat sink; excessive ambient temperature; prolonged overload operation 1. Check cooling fan operating status, replace faulty fans; 2. Clean dust from heat sinks; 3. Reduce operating power and restart after temperature drops; 4. Improve temperature control effectiveness inside the compartment
Communication fault Communication cable disconnected; incorrect communication address; protocol mismatch; damaged communication interface 1. Check communication cable connections; 2. Verify communication address, baud rate, and protocol settings; 3. Replace communication interface for testing; 4. Restart communication gateway and equipment

7.4.3 Common Temperature Control System Faults

Fault Phenomenon Possible Causes Handling Methods
Excessive internal compartment temperature Insufficient air conditioning refrigerant; air conditioning compressor fault; blocked filters reducing airflow; ambient temperature exceeding design value 1. Clean intake filters; 2. Check air conditioning operating current and pressure, recharge refrigerant; 3. Troubleshoot compressor faults, contact maintenance; 4. Reduce charge/discharge power to reduce heat generation
Air conditioning fails to start Power supply fault; temperature control sensor fault; controller fault; compressor overload protection 1. Check whether air conditioning power supply is normal; 2. Measure temperature sensor resistance to determine if damaged; 3. Reset overload protection and restart air conditioning; 4. Replace faulty controller or sensor
Uneven temperature inside compartment Air duct design issues; fan failure; partial outlet blockage 1. Check all fans operate normally; 2. Clear blockages from air outlets; 3. Adjust air duct flow guides to optimize airflow distribution
Water leakage/condensation Blocked condensate drain pipe; air conditioning temperature set too low; excessive humidity inside compartment 1. Clear the condensate drain pipe; 2. Appropriately raise the air conditioning set temperature; 3. Enable dehumidification function to reduce internal compartment humidity

7.4.4 Common Monitoring System Faults

Fault Phenomenon Possible Causes Handling Methods
Data not refreshing Communication interruption; acquisition equipment fault; monitoring software crash; network fault 1. Check local communication connections and equipment status; 2. Restart monitoring software and acquisition gateway; 3. Check network connection and communication links; 4. Verify device addresses and protocols
Remote access failure Site network interruption; public IP address change; server fault; firewall blocking 1. Check site 4G/broadband network status; 2. Verify remote access address and port; 3. Check cloud platform server status; 4. Troubleshoot firewall and security policies
False alarm reporting Sensor fault; unreasonable threshold settings; electromagnetic interference 1. Calibrate or replace faulty sensors; 2. Reasonably adjust alarm thresholds; 3. Check shielding and grounding to eliminate interference sources
Abnormal report data Data jump in acquisition; database anomaly; statistical logic error 1. Verify whether raw data is normal; 2. Repair database anomalies; 3. Contact manufacturer to optimize report statistics logic

7.4.5 General Principles for Fault Handling

  • Safety Priority: When handling faults, first ensure personnel safety. For high-voltage faults, cut off power first, verify power-off status, apply grounding, and tag/lock before troubleshooting.
  • Outside Before Inside: First troubleshoot external factors such as external wiring, power supply, and environment, then investigate internal equipment faults.
  • Simple Before Complex: First handle simple, easily detectable fault points, then progressively investigate complex causes.
  • Complete Records: Record fault phenomena, occurrence time, troubleshooting process, and handling results in detail to accumulate fault experience.
  • Major Fault Reporting: In the event of serious accidents such as battery smoke, fire, short circuit explosion, or major electrical faults, immediately activate the emergency response plan, evacuate personnel, and report to relevant departments and the manufacturer. Blind handling is strictly prohibited.

7.5 Key Points for Battery System Specialized O&M

The battery system is the core asset of the outdoor energy storage container. Its health status directly determines the system’s value and service life, and it must be managed as a key focus of O&M.

Operating Condition Management

  • Avoid prolonged full charge and full discharge cycles. Maintain daily operating SOC in the 10% to 90% range to extend cycle life.
  • Control charge/discharge C-rates. Avoid prolonged over-rate operation; derate when operating in high-temperature environments.
  • During prolonged idle periods, maintain SOC at 50% to 60% and perform a supplemental charge every 3 months to prevent battery over-discharge.

Consistency Management

  • Regularly analyze cell voltage and temperature data, tracking cell dispersion trends.
  • Regularly perform balancing maintenance to maintain cell consistency and improve overall pack capacity utilization.
  • Focused monitoring on cell clusters with severe degradation or poor consistency; perform cell replacement and regrouping when necessary.

Lifespan Assessment

  • Establish a battery lifespan archive, recording cumulative charge/discharge energy, cycle count, and operating temperature ranges.
  • Conduct an annual capacity test to assess actual available capacity and SOH.
  • Predict remaining life based on degradation patterns; plan battery replacement and echelon utilization strategies in advance.

Safety Management

  • Strictly prohibit unauthorized disassembly of battery modules, alteration of battery wiring, or short circuiting of battery positive and negative terminals.
  • Flammable, explosive, and corrosive materials are strictly prohibited inside the battery compartment. Unauthorized hot work operations are strictly prohibited.
  • Equip dedicated battery fire extinguishing equipment. O&M personnel must master battery fire emergency response procedures.
  • Retired batteries must be handed over to qualified organizations for recycling and disposal in accordance with regulations. Indiscriminate disposal is strictly prohibited.

Chapter 8 After-sales Service and Technical Support for Guangdong Lain Energy Storage Containers

Guangdong Lain Smart Equipment Room Co., Ltd. consistently adheres to the business philosophy of “Quality First, Service Above All,” providing full lifecycle technical support and after-sales service guarantees for every outdoor energy storage container product, ensuring customers invest with confidence and operate with peace of mind. Lain Smart has established a nationwide service network equipped with a professional technical service team, capable of responding quickly to customer needs and providing efficient, professional, and attentive service.

8.1 Warranty Service Commitment

8.1.1 Warranty Period

  • The complete outdoor energy storage container system carries a warranty period of 1 year, commencing from the date of project completion and acceptance.
  • Battery cells carry a warranty period of 5 years, with a commitment that capacity retention rate will not be less than 80% within 5 years. Specific terms are subject to the battery manufacturer’s warranty clauses.
  • Core components such as PCS, BMS, and air conditioning have a warranty period no less than the manufacturer’s standard warranty, and no less than 1 year.
  • Extended warranty services are available based on customer needs to extend warranty coverage and provide longer-term protection.

8.1.2 Warranty Scope

During the warranty period, equipment faults and damage caused by product design, manufacturing, material, or process defects will be repaired or replaced free of charge by our company, with labor and parts costs waived.

The following situations are not covered by the free warranty scope:

  • Damage caused by improper human operation, operation against regulations, or unauthorized disassembly or modification.
  • Faults caused by failure to perform O&M in accordance with the instruction manual, or by operating environments exceeding design specifications.
  • Damage caused by force majeure events such as natural disasters, accidents, or third-party vandalism.
  • Normal wear and replacement of wearing parts and consumables.
  • Faults caused by repair or modification performed by non-our-company personnel.

8.1.3 Warranty Service Response

  • The service hotline remains available 7×24 hours throughout the year, 365 days, for customer fault reporting and technical consultation at any time.
  • Upon receiving a fault report, provide telephone technical response within 1 hour, guiding customers to troubleshoot and handle general faults.
  • For on-site service needs: engineers will arrive at the site within 24 hours in the Pearl River Delta region, within 48 hours in other domestic regions, with extended times for remote areas depending on travel distance.
  • General fault on-site handling time does not exceed 48 hours. For major faults, solutions will be developed as soon as possible to minimize downtime.

8.2 Technical Support Services

8.2.1 Full-process Technical Services

Guangdong Lain Smart Equipment Room Co., Ltd. provides full-process technical support from project pre-planning to post-operation maintenance:

  • Preliminary Solution Support: Provide technical consultation including energy storage system solution design, capacity configuration, revenue estimation, and site selection recommendations, tailoring the optimal outdoor energy storage container solution for each customer.
  • Installation and Commissioning Guidance: Assign professional technical engineers to guide on-site installation and commissioning, control construction quality, and ensure the system is delivered in compliance with specifications.
  • Grid Connection Technical Support: Assist customers in completing grid connection applications, grid connection testing, and grid acceptance, providing technical documentation and technical coordination.
  • Operational Technical Support: During and after the warranty period, continue to provide operational technical guidance, answer O&M questions, optimize operating strategies, and enhance project returns.

8.2.2 Remote Technical Support

  • Leveraging the remote monitoring platform, remote assistance can be provided to customers for fault troubleshooting, data analysis, and parameter optimization, quickly resolving most software and parameter-related issues.
  • Provide multiple technical consultation channels including telephone, WeChat, and email, with professional engineers available to answer technical questions at any time.
  • Regularly push O&M knowledge, industry policies, software upgrades, and other information to help customers improve their O&M capabilities.

8.2.3 On-site Technical Services

  • Provide on-site technical services including installation guidance, commissioning guidance, and acceptance coordination.
  • Provide on-site handling services such as fault repair, equipment replacement, and system upgrades.
  • Provide preventive services including regular inspections, annual maintenance, and performance testing.
  • Provide value-added services such as customized technical retrofits, capacity expansion, and functional upgrades.

8.3 O&M Training Services

To ensure customer O&M personnel can independently and standardly operate and manage the energy storage system, Guangdong Lain Smart Equipment Room Co., Ltd. provides free professional O&M training services.

8.3.1 Training Content

  • Basic Theory Training: Energy storage system operating principles, subsystem function introductions, equipment structure and performance parameters, and relevant standards and specifications.
  • Operational Skills Training: Monitoring system operations, charge/discharge control, operating strategy configuration, routine inspection procedures, and regular parameter viewing and adjustment.
  • Safety O&M Training: Electrical safety knowledge, battery safety protection, fire emergency response, high-voltage operation standards, and precautions for hazardous operations.
  • Fault Handling Training: Common fault identification, troubleshooting methods, emergency handling procedures, simple fault handling, and reporting procedures for major faults.
  • O&M Management Training: O&M system establishment, O&M ledger management, lifespan assessment methods, and revenue optimization techniques.

8.3.2 Training Formats

  • On-site Training: During the project commissioning and delivery phase, hands-on training is conducted at the project site, explaining while operating on actual equipment for intuitive training results.
  • Centralized Training: Based on customer needs, systematic centralized training can be organized at our factory or training base for O&M personnel.
  • Online Training: Online video courses and training materials are provided for convenient learning and refresher training at any time.
  • An assessment is conducted after training completion. Those who pass will be issued a training completion certificate, ensuring trainees have independent O&M capabilities.

8.4 Upgrade, Retrofit, and Value-added Services

8.4.1 System Upgrade Services

  • Software Upgrades: Continuously optimize BMS, PCS, and EMS system software with regular upgrade version releases. Customers can upgrade for free to improve system performance and functionality.
  • Hardware Upgrades: Based on technological developments and customer needs, provide hardware upgrade and retrofit services, such as upgrading to higher-efficiency PCS units, adding balancing functions, or upgrading fire protection systems.

8.4.2 Capacity Expansion and Retrofit Services

  • Capacity Expansion: Support energy storage system capacity expansion through adding new storage containers or in-cabinet expansion to meet customers’ growing energy storage needs.
  • Functional Retrofits: Functional retrofits can be performed based on application scenario changes, such as adding grid-connected/off-grid functionality, adding microgrid control functions, or adapting to new energy integration.
  • Life Extension Retrofits: For energy storage systems in operation for many years, provide life extension retrofit services including battery balancing, cell replacement, and system optimization to extend system service life.

8.4.3 Fully Managed O&M Services

For customers without a professional O&M team, fully managed O&M services are available. Our professional team handles daily inspections, scheduled maintenance, fault handling, and operational optimization of the system. Customers do not need to staff dedicated O&M personnel, and can enjoy worry-free fully managed services ensuring high system availability.

8.5 Service Contact Information

All outdoor energy storage container products from Guangdong Lain Smart Equipment Room Co., Ltd. enjoy unified after-sales service guarantees. For any technical consultation, fault reporting, or business cooperation needs, please contact us through the following channels:

Item Details
Manufacturer Guangdong Lain Smart Equipment Room Co., Ltd.
Service Hotline +86 13538869979 (also available via WeChat)
Technical Support +86 13538869979
Company Address Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou City
Official Website https://gdlain.com

This manual’s final interpretation rights belong to Guangdong Lain Smart Equipment Room Co., Ltd. Product technical upgrades and manual updates are subject to change without prior notice. Please contact the manufacturer for the latest version.

Shopping Cart