ToggleDon’t Walk Away Until You’ve Checked Everything
A new rack install looks done, but small mistakes cause outages later. Run through this 20-point checklist before signing off.
Checklist
- Rack is level (front-to-back and side-to-side).
- Rack bolted to floor (or wall-mounted bracket secured).
- All cage nuts installed, no missing screws.
- Equipment mounted at correct U positions, rails aligned.
- All screws torqued to 2.5 Nm (finger-tight plus quarter turn).
- Power cables plugged into PDU, labeled both ends.
- Network cables plugged into correct switch ports, labeled.
- Ground wire connected from rack to earth point.
- Ground resistance tested (under 1 ohm).
- Blank panels fill all empty U-slots.
- Cable management: vertical and horizontal managers used.
- Cable ties secure but not over-tightened.
- Fan units spinning, no unusual noise.
- Temperature/humidity sensor installed and reading correctly.
- UPS powered on, battery charging, self-test passed.
- Door closes and seals properly; lock works.
- All labels applied: equipment, ports, U-positions.
- Monitoring system sees all devices (SNMP ping OK).
- Alert thresholds set (temp high, humidity high, door open).
- Documentation updated: rack inventory, cable schedule, IP list.