Don’t Walk Away Until All 20 Are Done
After rack assembly, equipment installation, and cable termination, run through this checklist. Each item takes 30 seconds. Skipping one costs hours later.
- Rack is level (front-to-back, left-to-right).
- Leveling feet touch the floor; casters are off the ground.
- Rack bolted to the floor (where required).
- All cage nuts installed and tight.
- Equipment mounted with M6 screws, all 4 corners.
- Blank panels fill every empty U position.
- Cables routed neatly, no pinches or kinks.
- Cable arms flex freely.
- Labels on both ends of every cable.
- PDU mounted securely, load under 80%.
- Ground wire connected to PE busbar.
- Fan tray running, airflow bottom-to-top.
- Temperature sensor reading correct value.
- Door closes and locks smoothly.
- Side panels installed and clipped.
- Top/bottom cable glands sealed.
- Power cords plugged into correct PDU outlets.
- Network cables punched down correctly.
- Equipment LEDs green (no alarms).
- Maintenance kit left on-site (spare screws, blanks, labels).