KITOZER
KITOZER

Special Integrated Container Equipment

Table of Contents

1. Cover / Document Information

– Document Title: Special Integrated Container Equipment Technical Design Solution

– Prepared by: Guangzhou Lain Intelligent System Development Co., Ltd.

– Brand: KITOZER (Pioneer)

– Date: August 2026

– Version: V1.0

– Project Type: Technical design solution for Special Integrated Container Equipment

2. Table of Contents Structure

1. Company Introduction

2. Project Overview

3. User Requirement Analysis

4. Overall Design Description

5. Detailed System Design and Product Technical Parameters

6. Project Quotation and Configuration List

7. Core Solution Advantages

8. Technical Q&A

9. Construction Schedule Plan

10. Construction Organization Plan

11. After-Sales Service System

12. Operation and Maintenance Training Plan

13. Typical Project Cases

14. SEO Optimization System and Website Backend Configuration

15. Contact Information

3. Company Introduction

3.1 Company Development Overview

Founded in 2002, Guangzhou Lain Intelligent System Development Co., Ltd. is a high-tech enterprise dedicated to the computer room construction and intelligent protection field for more than two decades, integrating R&D, production, sales, engineering implementation and after-sales service. The company focuses on innovative breakthroughs in electromagnetic shielding technology, modular computer room technology and computer room environmental monitoring technology, and has grown into a source manufacturer with core competitiveness in the domestic computer room construction field.

After more than twenty years of industry accumulation, the company has built a large-scale production and manufacturing base equipped with advanced CNC sheet metal processing equipment, automated spraying production lines and professional testing laboratories, with an annual production capacity of hundreds of sets of shielding computer rooms, integrated cabinets and micro-module products. The company’s service network covers all provinces and cities across the country, providing thousands of computer room construction and renovation services for customers in government, military, scientific research, finance and enterprise fields.

3.2 Core Business System

The company’s core business revolves around the full-lifecycle construction of computer rooms, forming four major product and service systems:

– Computer room EPC general contracting service: one-stop services from solution design, manufacturing, on-site construction to commissioning and acceptance, covering shielding computer rooms, IDC data rooms, modular computer rooms, container computer rooms and other types;

– Core equipment R&D and production: independently produces KITOZER brand series products, including shielding cabinets, shielding desks, consoles, integrated data cabinets, micro-module cold aisle cabinets, outdoor rainproof cabinets, etc., supporting non-standard customization;

– Computer room environmental monitoring system: provides full-element monitoring solutions for temperature and humidity, water leakage, access control, video, fire protection, UPS and power distribution, realizing intelligent and unattended O&M;

– Shielding and security protection products: shielding rooms, shielding doors and windows, anechoic chambers and related auxiliary materials, widely used in confidential, military and scientific research fields.

3.3 Brand and Qualification Honors

The core brand KITOZER (Pioneer) focuses on computer room equipment and shielding products, positioned as an “efficient, green, innovative and safe” solution provider. Products have passed multiple authoritative tests and comply with national and industry standards. The company holds multiple utility model patents and software copyrights, has been awarded high-tech enterprise qualification, and follows the ISO9001 quality management standard.

3.4 Core Competitive Advantages

1. Source production, controllable quality: own production base and professional processing equipment; core products independently produced with full-process quality control, providing more cost-effective solutions without intermediate links;

2. Customized design, matching needs: tailor-made solutions per site conditions, technical requirements, configuration and budget, with multiple design options provided free of charge;

3. Professional team, rich experience: a professional technical team of engineers and project managers with more than ten years of industry experience;

4. Quality after-sales, full guarantee: a 7×24 professional online service system with dedicated project follow-up from early coordination to later O&M.

4. Project Background and Objectives

4.1 Project Background

With the rapid deployment of edge computing, industrial IoT and 5G, outdoor equipment integration and protection demand is growing. Traditional on-site civil works are slow, costly and immobile — unable to meet fast deployment and flexible expansion needs. The special integrated container uses the standard container as a carrier, deeply integrating structure protection, insulation, power distribution, ventilation, earthing/lightning protection and lighting — factory prefabricated, plug-and-use on site — the mainstream solution for outdoor equipment deployment.

4.2 Project Scope

Two custom container models:

– Type A: external 6000(L)×6000(W)×2850(H)mm, 1 unit;

– Type B: external 6000(L)×3000(W)×2850(H)mm, 1 unit.

Both use steel load-bearing frames with rock-wool sandwich-panel enclosure, integrating power distribution and lighting, intelligent ventilation, anti-corrosion/waterproofing and equipotential earthing — stable equipment operation in harsh outdoor environments; widely applicable to communication base stations, edge data centers, industrial control cabins, emergency command cabins and mining equipment rooms.

4.3 Objectives

Structure and dimensions: custom fixed external dimensions with internal clearance for equipment and personnel; load-bearing structure with pre-embedded mounting points for heavy equipment; standard lifting points for road transport and on-site hoisting.

Protection and environment: outdoor waterproof/dust/wind capability, overall protection ≥IP54; insulated enclosure for summer heat and winter cold with lower temperature-control energy; corrosion-resistant steel structure for outdoor life.

Electrical and lighting: standardized distribution box with branch circuits for lighting, sockets and equipment with leakage protection; indoor illuminance for O&M; emergency lighting auto-on on power loss; wall sockets with a dedicated AC circuit.

Ventilation and temperature: mechanical exhaust removing equipment heat; temperature-automatic control for unattended energy-saving operation; insect and coarse-dust protection at intakes.

Safety and fire: equipotential earthing for electrical and personnel safety; fire- and theft-resistant doors/windows with compliant enclosure fire ratings; reliable sealing against rain and pests.

Customization and O&M: adjustable openings, pre-embedded parts and socket points per equipment layout; smooth cleanable interior with removable ceiling for pipeline access.

5. User Requirement Analysis

5.1 Structure Requirements

6000×6000×2850mm and 6000×3000×2850mm external; internal clearance for equipment and operation; bottom load-bearing with pre-embedded anchors for heavy equipment; standard lifting points for transport and hoisting.

5.2 Protection Requirements

Outdoor waterproof/dust/wind with ≥IP54 overall; insulated enclosure reducing temperature-control energy in summer/winter; corrosion-resistant steel for long outdoor life.

5.3 Electrical and Lighting

Standard distribution box with branch control of lighting, sockets and equipment plus leakage protection; indoor illuminance for operation; emergency lighting ≥90min auto-on; wall sockets with dedicated AC circuit.

5.4 Ventilation and Temperature

Mechanical exhaust for equipment heat; temperature-automatic start/stop for unattended energy saving; insect and coarse-dust filtering at intakes.

5.5 Safety and Fire

Equipotential earthing; fire/theft-resistant doors and windows; compliant fire-rated enclosure; reliable sealing against rain and pests.

5.6 Customization and O&M

Openings, pre-embedded parts and socket positions per equipment layout; smooth cleanable interior with removable ceiling; full documentation and training.

6. Design Principles and Applicable Standards

6.1 Design Principles

Customization first: full-process customization from dimensions, layout to systems per actual equipment and scenarios; three free design options. Full-system integration: structure, enclosure, power, ventilation, earthing and lighting integrated and factory-tested — on-site only positioning and external power; 60%+ shorter schedule. High-quality materials: Q235B structural steel, triple anti-corrosion, A-grade fire rock-wool panels, first-tier electrical brands, multi-seal doors/windows. Energy-efficient operation: temperature-controlled ventilation and high-efficiency LED lighting — low running cost. Complete service: free survey/design/quote, production tracking, 7×24 support, warranty and lifetime maintenance.

6.2 Applicable Standards

GB/T 700-2006 (carbon steel), GB/T 707-2008 (hot-rolled channels), GB/T 8923.1-2011 (surface preparation Sa2.5), GB 8624-2012 (fire classification), GB 12955-2008 (fire doors), GB 15763.2-2005 (tempered glass), GB 17945-2010 (fire emergency lighting), GB 2099.1-2008 (sockets), GB/T 12706.1-2020 (power cables), GB 50057 (lightning protection), GB 50054 (low-voltage distribution), plus customer requirements.

7. System Architecture and Working Principle

7.1 Overall Architecture

Six integrated systems: main steel structure (16#/10# channel base frame, 120×120×4mm square-tube corner columns, top frame, lifting lugs); enclosure and insulation (50mm A-grade rock-wool sandwich walls, corrugated roof with 2% drainage slope, 2mm patterned steel floor, interior decoration panels); doors and windows (steel Class-A fire door, PVC sliding windows with insect screens); ventilation (axial exhaust fans with temperature-controlled start/stop); power and lighting (distribution box, LED panel lights, emergency lighting, sockets, incoming cable); anti-corrosion, waterproofing and earthing (epoxy zinc-rich primer + polyurethane topcoat, neutral silicone sealing, T2 copper equipotential busbar and galvanized electrodes).

7.2 Working Principles

The container is factory-fabricated: steel frame welded and corrosion-protected; sandwich panels assembled with tongue-and-groove joints and sealing strips; doors/windows installed with double seals; distribution box wired with branch circuits; exhaust fans with temperature switches auto-ventilate above the set point and stop below; emergency lights switch on within 0.2s on power loss; all metal parts bond to the equipotential busbar connected to earth electrodes (≤4Ω). On site: position, level, connect external power and earthing — ready for use.

8. Detailed Technical Design

8.1 Main Steel Structure

Q235B carbon steel (C≤0.20, Si≤0.35, Mn≤1.40, ReL≥235MPa, Rm 370-500MPa, A≥26%, GB/T 700); 16# channel base main beams (25.162cm², 19.752kg/m); 10# channel secondary beams at 500mm spacing (floor uniform load ≥500kg/m²); 120×120×4mm square-tube corner columns (18.56cm², verticality ≤1/1000, 10mm end plates full-welded); lifting lugs — 10mm plate, φ40mm hole, 2t per point, three-side fillet weld 8mm, grade-2 weld inspection; surface preparation — shot blasting Sa2.5 (Ry 40-70μm) per GB/T 8923.1.

8.2 Enclosure and Insulation

External rock-wool sandwich walls: 50mm total; double 0.5mm color-coated steel (TDC51D+Z, zinc ≥100g/m², front polyester ≥20μm); basalt rock wool 80kg/m³, A-grade non-combustible (GB 8624); thermal conductivity ≤0.040W/(m·K); ~12kg/m²; 950-type tongue-and-groove, 30mm insertion with built-in seal strip; sound insulation ≥25dB; compressive ≥0.08MPa; water absorption ≤5%; -40℃~+120℃; wind pressure ≥1.0kPa. Roof: 50mm with 0.6mm corrugated top (30mm wave) and 0.4mm flat bottom; 2% single drainage slope; snow load ≥0.5kN/m². Floor: Q235B 2mm patterned steel (≥0.8mm pattern, 16.8kg/m², epoxy anti-rust primer ×2 + grey topcoat ×1, dry friction ≥0.6, full-welded smooth joints). Interior: 0.4mm ivory color-coated board + 50mm glass wool 48kg/m³, concealed clip installation, flatness ≤2mm/m, washable ≥1000 cycles, B1 fire. EPDM gaskets: Shore 60±5A, compression set ≤25% (70℃×22h), aging change ≤15% (100℃×72h), outdoor life ≥10 years.

8.3 Doors and Windows

Steel Class-A fire door: 900×2100mm; fire resistance ≥1.5h (GB 12955); 50mm leaf with 1.2mm cold-rolled panels, pearlite fire core; 1.5mm frame; 3× 304 stainless hinges (≥80kg each); 304 fire handle lock with 3 keys; hydraulic closer (0-180° with positioning); intumescent seal strip; IP54; RAL7035. PVC sliding window: 600×900mm; 80-series PVC profile 2.0mm multi-chamber; 5mm tempered glass; built-in 304 stainless invisible insect screen (18 mesh); double EPDM seals; air-tightness grade 6, water-tightness grade 4, wind-pressure grade 3.

8.4 Ventilation System

Axial exhaust fans (SF3G-4): 300mm outlet; AC220V 50Hz; 120W; 1800m³/h; 80Pa; 1450rpm; ≤58dB(A); aluminum die-cast blades; powder-coated steel housing; IP54, class B; MTBF ≥50,000h; rain louvers and metal guards. Temperature switch: 0-50℃, ±1℃, AC220V, 10A contacts, 2-5℃ hysteresis, key-set thresholds, ABS housing, wall-mounted at the return.

8.5 Power and Lighting

Distribution box: 1.2mm steel, wall-mounted, IP30; Chint/Delixi brand; main 2P 32A C-curve; 2× 1P 10A lighting; 2× 1P 16A socket circuits with 30mA RCDs; 2× 1P 16A spare; N/PE busbars; clearances ≥5.5mm, creepage ≥6.3mm, withstand 2kV/1min. LED panel lights: 600×600mm; 40W; ≥100lm/W; ≥4000lm; 6000K; Ra≥80; PF≥0.9; IP20; ≥50,000h; isolated constant-current driver, flicker-free; recessed in ceiling. Sockets: 250V; 10A 5-pole / 16A AC-dedicated; PC panels; phosphor-bronze contacts; ≥10,000 insertions; child shutters; GB 2099.1. Incoming cable: YJV 0.6/1kV 3×6mm² (OFC, XLPE, PVC; 90℃; ≤3.08Ω/km; ≥1000MΩ·km). Dual-head emergency light: 2W LED; 220V; ≥90min; charge ≤24h; switchover ≤0.2s; Ni-Cd battery; ≥500 cycles; GB 17945-2010 with fire certification.

8.6 Anti-Corrosion, Waterproofing and Earthing

Epoxy zinc-rich primer: zinc ≥80% in dry film; ≥40μm per coat ×2 (≥80μm total); adhesion grade 1; salt spray ≥500h; air-dry ≤2h / hard ≤24h; airless spray on Sa2.5 steel. Polyurethane topcoat: RAL7035 semi-gloss; ≥40μm ×2 (≥80μm); adhesion grade 1; artificial aging ≥1000h (gloss/color change ≤2); salt spray ≥800h; 5% H₂SO₄/NaOH 72h no anomaly. Neutral silicone sealant: ±25% movement; ≥0.6MPa; ≥300% elongation; ≤60min skin; 7-day cure; -40℃~+150℃; UV/rain/aging resistant. Equipotential busbar: T2 copper 3×30mm, ≥99.9% purity, ≥58MS/m, tin-plated, insulator-mounted; earthing resistance ≤4Ω. Galvanized electrodes: Q235 φ16×1.5m, zinc ≥85μm, life ≥30 years in normal soil.

8.7 Assembly and Quality Design

Factory process: drawing confirmation → material procurement/inspection → steel cutting/welding (J422 φ3.2 electrodes, fillet welds full and continuous, grade-2 inspection) → shot blasting Sa2.5 → primer/topcoat with dry-film thickness checks → enclosure assembly → doors/windows and sealing → electrical wiring (color-coded, tinned stranded terminations, labeled circuits) → ventilation installation → interior and trim → earthing → full testing (electrical insulation/earthing, ventilation, waterproof, appearance) → outbound acceptance and delivery. Standard single-unit total 35 days; multi-unit parallel.

9. Recommended Configuration and Preliminary Budget

9.1 Steel Structure

Q235B steel (16# base main beams, 10# secondary beams @500mm, 120×120×4mm corner columns, top frame, wall studs, lifting lugs 2t/point), shot-blasted Sa2.5.

9.2 Enclosure and Insulation

50mm A-grade rock-wool sandwich exterior walls (950-type tongue-and-groove); 50mm corrugated roof panels (2% slope); 2mm patterned steel floor; interior color-coated boards with glass wool; EPDM gaskets; neutral silicone; trim and edge covers.

9.3 Doors and Windows

Steel Class-A fire door (900×2100mm, 304 hardware, closer, intumescent strip); PVC sliding windows (600×900mm, tempered glass, 304 insect screens); aluminum louvers with screens.

9.4 Ventilation

Axial exhaust fans with rain louvers and guards; temperature-control switches; optional filters.

9.5 Power and Lighting

Distribution box (main + branch + RCD circuits, Chint/Delixi); LED panel lights; sockets (10A/16A AC-dedicated); dual-head emergency lights; YJV 3×6 incoming cable; PVC conduit and terminals.

9.6 Anti-Corrosion, Waterproofing and Earthing

Epoxy zinc-rich primer + polyurethane topcoat (triple anti-corrosion); neutral silicone sealant; T2 copper equipotential busbar; BVR earthing leads; galvanized electrodes (φ16×1.5m) ×2 per container (Type A) / ×2 (Type B) — 4 total; earthing ≤4Ω.

9.7 Standard Parts and Installation Hardware

J422 φ3.2 welding rods; color-steel self-drilling screws with gaskets (5.5×25mm); M8×30 8.8-grade galvanized bolts; PU foam filler; aluminum blind rivets; consumables (cutting discs, sandpaper, cleaner).

9.8 Quotation Notes

The above is the reference configuration per container; final quotation per confirmed configuration, tax-inclusive. All prices are indicative and quoted in RMB (CNY) only — no foreign-currency conversion is provided. Warranty: 1 year whole product, 5 years main steel structure, 6 months wear parts; 7×24 support; 2h response, 24h/48h/72h on-site (Pearl River Delta/province/nationwide); lifetime maintenance at cost.

10. Technical Specifications

12.1 System Specification Summary

System Key Specifications
Steel structure Q235B (ReL ≥235MPa); 16# channel base main beams; 10# channels @500mm (floor load ≥500kg/m²); 120×120×4mm corner columns (verticality ≤1/1000); lifting lugs 2t/point; shot blasting Sa2.5
Enclosure 50mm A-grade rock-wool sandwich walls (≤0.040W/m·K, 950 tongue-and-groove); corrugated roof 2% slope; 2mm patterned steel floor; interior color boards + glass wool; EPDM gaskets
Fire/water Overall ≈IP55; Class-A fire door 900×2100 (≥1.5h); PVC sliding windows with 304 insect screens; neutral silicone sealing; waterproof glands
Ventilation Axial fans 1800m³/h each (120W, ≤58dB, IP54); temperature switch 0-50℃ ±1℃ auto start/stop; louvers + insect screens
Power/lighting Distribution box (2P 32A main, branch circuits, 30mA RCDs, spare circuits; Chint/Delixi); 40W LED panels ≥4000lm 6000K; 10A/16A sockets; dual-head emergency lights ≥90min (GB 17945); YJV 3×6 incoming
Anti-corrosion Sa2.5 blasting + epoxy zinc-rich primer ≥80μm + polyurethane topcoat ≥80μm (salt spray ≥500h/≥800h); T2 copper equipotential busbar 3×30mm; galvanized electrodes φ16×1.5m; earthing ≤4Ω

12.2 Component Standards

Q235B per GB/T 700; channels per GB/T 707; Sa2.5 per GB/T 8923.1; rock wool A-grade per GB 8624; fire door per GB 12955; tempered glass per GB 15763.2; emergency lighting per GB 17945; sockets per GB 2099.1; cable per GB/T 12706.1; full outbound test report (dimensions, appearance, electrical, sealing) delivered.

11. Key Advantages and Customer Value

12.1 Source-Factory Customization — Rapid Response

20+ years of room-equipment manufacturing with full design/production/installation capability; full-process customization of dimensions, layout and systems; three free design options — highly matching project needs without generic-product fit defects.

12.2 Full-System Integration — Ready to Use

Structure, enclosure, power, ventilation, earthing and lighting integrated and factory-tested — on site only positioning and external power; 60%+ shorter schedule than traditional construction with more stable factory quality.

12.3 High-Quality Materials — Harsh-Environment Ready

Q235B structural steel with shot blasting + epoxy zinc-rich primer + polyurethane topcoat (triple anti-corrosion, 20+ year outdoor life); A-grade fire rock-wool panels (insulation + fire + sound in one); first-tier electrical brands; multi-seal doors/windows for storms and dust.

12.4 Energy-Saving Intelligent Operation

Temperature-controlled ventilation auto-starts/stops without attendance; high-efficiency long-life LED lighting; simple reliable systems — low energy and maintenance cost.

12.5 Complete Service

Free survey/design/quote; production progress tracking; 7×24 support; in-warranty free repair/replacement; lifetime cost-price maintenance.

12. Technical Q&A (50+ Items)

12.1 Structure and Container

Q1: How long does the main structure last?

A: Q235B steel with Sa2.5 shot blasting and triple anti-corrosion (epoxy zinc-rich + polyurethane) — 20+ years outdoor; periodic topcoat touch-up (3-5 years) extends further.

Q2: Floor load capacity — reinforcement for heavy equipment?

A: Standard 2mm patterned floor with 500mm secondary beams gives ≥500kg/m²; single items over 500kg get denser beams, thicker floor and extra anchors — up to 1000kg/m²+ per customization.

Q3: Can it be hoisted and transported?

A: Yes — four corner lifting lugs at 2t each for fork/crane handling; both sizes meet road transport limits for direct flatbed delivery without disassembly.

Q4: Other sizes available?

A: Yes — full-size flexible customization (length/width/height), plus special structures, multi-container splicing and two-layer options.

Q5: What is the wind and seismic resistance?

A: The steel frame with anchored base and 2t lugs meets outdoor wind loads; optional anchoring per site conditions; structure verified by design calculation.

12.2 Enclosure and Protection

Q6: Insulation performance — will it be hot inside in summer?

A: 50mm A-grade rock-wool panels (≤0.040W/(m·K)) block external heat; with mechanical ventilation, internal temperature stays reasonable for normal heat loads; AC/heat-exchanger options for high heat or extreme ambient.

Q7: Waterproofing — protection rating?

A: Overall ≈IP55: 2% roof slope, neutral silicone sealed joints, double door/window seals with threshold guards, waterproof glands at openings — storm-proof without leaks.

Q8: Fire rating of the panels?

A: Basalt rock-wool core is A-grade non-combustible (GB 8624); the door is Class-A fire; optional smoke/heat detectors and extinguishing systems for higher requirements.

Q9: Coastal high-salt-fog suitability?

A: Standard anti-corrosion suits general outdoor; coastal upgrades — galvanized steel, fluorocarbon topcoat, 304 stainless hardware — salt-spray tolerance 1000h+.

Q10: Is condensation a concern?

A: Insulated panels minimize cold surfaces; ventilation controls humidity; optional anti-condensation heater for high-humidity/cold sites.

12.3 Power and Lighting

Q11: Which electrical brands?

A: Standard Chint/Delixi (3C-certified, reliable); Schneider/ABB upgrade on request with adjusted pricing.

Q12: Emergency lighting duration — fire-code compliant?

A: Dual-head LED emergency lights run ≥90min on power loss with ≤0.2s switchover — per GB 17945-2010 for evacuation and basic operation lighting.

Q13: Can socket positions and ratings be adjusted?

A: Yes — quantity, position and rating (10A/16A/32A) customizable; industrial connectors and aviation plugs available.

Q14: What protections does the distribution box provide?

A: Main breaker, branch breakers, 30mA RCDs on socket circuits, spare circuits, N/PE busbars — overload/short/leakage protection per GB 50054.

Q15: Is the incoming cable sized adequately?

A: YJV 3×6mm² (90℃ rated, ≤3.08Ω/km) carries the standard load with margin; larger incoming per equipment demand on request.

12.4 Ventilation and Temperature

Q16: Does the fan run continuously?

A: No — a temperature switch auto-starts exhaust above the set point and stops below; unattended energy-saving mode with low actual power.

Q17: Will dust and insects enter?

A: Intake louvers + 304 stainless insect screens block insects and coarse dust; primary/medium filters optional for cleanliness-critical scenes.

Q18: What if heat load is high?

A: More/larger fans, bigger intake area, or industrial/precision AC and heat-pipe heat-exchange options per heat load.

Q19: What is the ventilation capacity?

A: Each fan 1800m³/h; quantity per container sized by heat load; temperature control keeps internal temperature in the reasonable range.

12.5 Installation and After-Sales

Q20: What is the production lead time?

A: Standard single unit 15-20 days; two parallel 20-25 days; deep customization 25-40 days per contract.

Q21: Is installation included?

A: Either — one-stop delivery/installation/commissioning, or technical guidance for self-installation with a detailed manual.

Q22: What is the warranty?

A: 1 year whole product, 5 years main steel structure, 6 months wear parts (seals, lamps); free repair/replacement of non-human faults; 7×24 support with 2h response and 24h/48h/72h on-site.

Q23: What inspections are provided?

A: Quarterly phone follow-ups; annual on-site inspection of structure, electrical and ventilation; reports with recommendations.

Q24: What spares are supported?

A: Long-term parts supply (5 years after phase-out); preferential annual maintenance agreements; upgrade services (AC, monitoring, fire systems).

Q25: How is the container verified at acceptance?

A: Dimensional/appearance check, electrical insulation and earthing tests, ventilation function, waterproof test, full outbound inspection report — signed acceptance.

12.6 Scenarios and Value

Q26: What scenarios suit this container?

A: Communication base stations, edge data centers, industrial control cabins, emergency command cabins, mining equipment rooms, temporary field facilities.

Q27: How does it compare with traditional rooms?

A: 60%+ shorter construction, ~30% lower cost in case practice, relocatable, factory-quality controlled — ideal for fast, mobile, expandable deployments.

Q28: Can systems be added later?

A: Yes — AC, monitoring, fire suppression, access control and environment sensors integrate on demand; modular growth without rebuilding.

Q29: Why choose the KITOZER/Lain solution?

A: Source factory, 20+ years of experience, full-system integration, customization flexibility, standard quality and complete service.

Q30: What is the lifecycle cost advantage?

A: Factory prefabrication cuts site cost; energy-saving ventilation and LED lighting cut running cost; long-life materials reduce maintenance; relocatable asset retains value.

Q31: How is the container leveled on site?

A: Adjustable leveling feet or shims under the frame at anchor points; level checked with a spirit level before earthing and equipment loading.

Q32: What earthing is required on site?

A: Two galvanized electrodes (φ16×1.5m) driven and bonded to the container busbar via flat steel/copper leads — resistance ≤4Ω verified by test.

Q33: Can the container be stacked or moved later?

A: Yes — corner lifting lugs support relocation; stacking configurations designed per request with reinforced frame options.

Q34: How is the interior lighting arranged?

A: 600×600mm LED panel lights recessed in the removable ceiling, evenly spaced for ≥300lx operating illuminance; emergency lights at exits.

Q35: How is cable entry sealed?

A: Waterproof glands with IP65 ratings at all openings; sealant around penetrations; drip loops prevent water ingress.

Q36: What maintenance does the steel structure need?

A: Annual visual inspection of coating and welds; touch up scratches with matching primer/topcoat; wash exterior in coastal areas; full re-coat every 8-10 years or per condition.

Q37: How are the sandwich panels cleaned?

A: Mild detergent and water with soft cloth; avoid abrasive tools; check gaskets and joints during cleaning.

Q38: Can the container house batteries or high-heat equipment?

A: Yes — dedicated compartments with enhanced ventilation or AC; floor anchors for heavy battery racks; fire options per battery type.

Q39: What is the operating temperature range?

A: The enclosure and equipment support -40℃~+120℃ panel range; internal temperature maintained per ventilation/AC design for the specific environment.

Q40: Is lightning protection included?

A: Equipotential earthing with electrodes ≤4Ω provides baseline protection; optional lightning rod and SPDs at the incoming for exposed sites.

Q41: How is fire safety handled?

A: A-grade panels, Class-A door, optional smoke/heat detection, fire extinguishers, and gas/water suppression per site requirements.

Q42: Can the container integrate with existing monitoring?

A: Yes — optional environment sensors (T/H, smoke, water, door) and a gateway upload to the customer’s platform via Modbus/4G.

Q43: What documentation is delivered?

A: Product manuals, structural drawings, electrical diagrams, test reports (insulation, earthing, waterproof, coating), operation/maintenance manual, certificates.

Q44: What training is provided?

A: On-site training at delivery (1-2h) — structure/electrical/ventilation operation, inspection, simple faults, safety — plus manuals, videos and online Q&A.

Q45: How is the 72h stability verified?

A: Factory trial run with continuous operation checks of electrical, ventilation and temperature control before outbound acceptance.

Q46: Can interior layout be customized?

A: Yes — partitions, equipment racks, cable trays, lighting layout and socket points all customized per the equipment plan.

Q47: What colors and finishes are available?

A: Standard RAL7035 with custom colors/logo printing per request; interior finish options (color boards, anti-static floor).

Q48: How is transport protected?

A: Factory packing with corner protection and internal bracing; flatbed transport; arrival inspection with the customer.

Q49: Is the container suitable for extreme cold?

A: Yes — thickened insulation, electric auxiliary heating and wind-sand filters keep equipment stable at -30℃ in field practice.

Q50: How fast is delivery for urgent projects?

A: Express lanes compress standard configurations to ~15 days; emergency timelines confirmed at contract with priority scheduling.

13. Construction Schedule

16.1 Stage Division

Factory-based production with clear stages:

No. Work Days Responsible
1 Scheme confirmation and drawing deepening 3 Design engineer
2 Material procurement and inspection 5 Procurement
3 Steel cutting and welding (base, columns, top frame, studs) 7 Steel crew
4 Shot blasting and anti-corrosion coating 4 Coating crew
5 Enclosure panel installation 3 Installation crew
6 Doors/windows and sealing 2 Installation crew
7 Electrical wiring and equipment 3 Electricians
8 Ventilation system installation 2 Installation crew
9 Interior and trim 2 Finishing crew
10 Earthing system 1 Electricians
11 Full testing and QC 2 QC engineer
12 Outbound acceptance and delivery 1 PM

Total: standard single-unit 35 days; parallel production shortens overall.

14. Construction Organization and Quality/Safety Measures

16.1 Organization

PM (1): overall progress/quality/cost, customer liaison. Design engineer (1): drawing deepening, disclosure, technical problems. QC engineer (1): process/incoming/outbound inspection. Procurement (1): materials, suppliers, tracking. Crews: steel (3) — cutting/welding/grinding; installation (4) — enclosure, doors/windows, ventilation; electricians (2) — power, lighting, earthing; coating (2) — blasting/painting.

16.2 Pre-Production Preparation

Technical: drawing review; process documents and work instructions; technical/safety disclosure to crews. Materials: incoming inspection of spec/material/quality certificates — unqualified prohibited. Equipment: cutters, welders, spraying equipment, lifting gear, test instruments calibrated. Site: workshop zones (cutting, welding, coating, assembly, finished) with fixed-position management.

16.3 Core Processes

Steel welding: manual arc welding with J422 φ3.2 electrodes; clean grooves and surfaces before welding; continuous full fillet welds without defects (slag, pores, cracks); grind spatter; grade-2 visual inspection on key welds. Coating: shot blast to Sa2.5; epoxy zinc-rich primer ×2 (≥40μm each) with inter-coat intervals; polyurethane topcoat ×2 (≥40μm each), uniform without runs; dry-film thickness measured per coat. Electrical: straight dressing with conduit and bends; distinct phase/neutral/earth colors (green-yellow for earth); firm terminations with tinned stranded ends; labeled circuits; insulation, earthing and energization tests after completion.

16.4 Quality Control

Three-inspection system (self, mutual, special) per process; key control points — welding quality, coating thickness, electrical insulation, waterproof sealing — recorded item by item; all main materials with material certificates and third-party reports for key parts; complete outbound test report (dimensions, appearance, electrical, sealing).

16.5 Safety Management

Full safety education with certified special operators; protective gear for welding/spraying with extinguishers in work areas; earthed equipment and code-compliant temporary power; supervised hoisting with exclusion zones below; daily pre-shift briefings and weekly safety inspections.

15. After-Sales Service

16.1 Warranty Commitment

1-year whole-product warranty from acceptance; 5 years main steel structure (free repair of non-human deformation/weld faults); 1 year electrical components; 6 months wear parts (seals, lamps).

16.2 Response

7×24 hotline; remote response within 2h (phone/video guidance); on-site — 24h Pearl River Delta, 48h province, 72h nationwide.

16.3 In-Warranty Services

Free on-site repair and part replacement; quarterly phone follow-ups; annual on-site inspection (structure, electrical, ventilation); free consultation and upgrade advice; updated electronic manuals.

16.4 Post-Warranty

Lifetime maintenance at parts + reasonable labor cost; preferential annual maintenance agreements; 5-year parts supply after phase-out; upgrade services (AC, monitoring, fire).

16.5 Service Flow

Report (phone/WeChat) → register → assign engineer → remote or on-site repair → customer confirmation → 3-day follow-up and archive.

16. Training Plan

16.1 Objectives

Customer O&M staff understand container structure and systems; master daily inspection and operation; handle simple faults; follow safety codes.

16.2 Audience

Customer O&M managers and field operators.

16.3 Content

Structure and daily maintenance: structure overview; coating inspection/care; seal inspection/replacement; drainage cleaning. Power system: distribution-box circuits; breaker operation; RCD reset; socket precautions. Ventilation: temperature-controller settings; fan checks; screen/filter cleaning. Emergency: power outage handling; water ingress response; fault reporting flow. Safety: electrical, fire and earthing checks.

16.4 Methods

On-site training at delivery (1-2h, demonstration + hands-on); paper/electronic operation/maintenance manual; instructional videos; online Q&A group.

16.5 Assessment

Questioning + simple practical assessment; both parties sign training confirmation.

16. Training Plan

16.1 Training Objectives and Audience

Training objectives: through systematic training, enable management personnel to fully understand the system structure, working principles and performance characteristics, master daily operation methods and inspection/maintenance essentials, identify common faults and handle simple problems, ensuring safe, stable and long-term operation.

Training audience: management and O&M personnel designated by the client, recommended 2-3 persons with basic electrical and equipment knowledge.

16.2 Tiered Training Content System

Level 1: Basic operation training (1 day)

– Basic principles: system concepts, structure composition, performance indicators;

– Daily operation standards: correct operation of equipment, control and safety systems;

– Daily inspection contents: daily/weekly/monthly check items;

– Safety precautions: usage prohibitions and emergency handling procedures.

Level 2: Maintenance training (1 day)

– Detailed structure of each subsystem and working principles;

– Daily maintenance methods: cleaning, fastening checks, routine care;

– Common fault identification and simple handling;

– Emergency handling procedures for power failure, fire and equipment faults.

Level 3: Advanced management training (as needed)

– Performance influencing factors and how to avoid degradation;

– Upgrade and expansion knowledge and specification requirements;

– Relevant national standards interpretation.

16.3 Training Methods and Schedule

– Methods: combination of “theory explanation + on-site practice + Q&A interaction”;

– Schedule: training arranged at the completion acceptance stage, synchronized with handover, 2 days of intensive training total; time flexibly adjustable; a free repeat training session is provided for newly assigned personnel.

16.4 Training Assessment and Documentation Delivery

– Assessment: theory written test plus practical operation; training qualification certificates issued upon passing; supplementary training for those who fail;

– Documentation delivery: complete O&M documentation, including operation and maintenance manual, equipment manuals and certificates, completion drawings and hidden work records, test reports and after-sales service contact card, all bound into volumes.

17. Anonymous Typical Project Scenarios

All project scenarios below are anonymous, generalized examples provided for reference only. No real customer names, addresses or identifiable details are disclosed.

17.1 Communication Operator Outdoor Base-Station Container Project

Project background. A communication operator needed outdoor 5G base-station equipment rooms across many sites for BBU, transmission and power equipment.

Implementation. 12 × 6×3×2.85m integrated equipment containers with power distribution, ventilation, AC and lightning/earthing systems.

Results. Factory prefabrication with rapid deployment — 12 units delivered and installed in 30 days; reinforced anti-corrosion for the hot, humid, rainy south; stable low-fault operation.

17.2 Industrial Park Edge Data Center Container Project

Project background. An enterprise needed an edge computing node for local business data processing with fast deployment and flexible expansion.

Implementation. 2 × 6×6×2.85m container data rooms integrating racks, UPS, precision AC, fire suppression and environment monitoring.

Results. Modular construction cut the schedule 60% and cost 30% versus civil rooms; stackable/expandable as business grows — high flexibility.

17.3 Emergency Management Command Shelter Project

Project background. An emergency management bureau needed a mobile command center transportable to disaster scenes.

Implementation. One custom integrated command shelter with office, display, communication and power systems.

Results. Highly integrated — operational within 1 hour of arrival; backup power for off-grid independent operation.

17.4 Mining Equipment Control Container Project

Project background. A mining area needed outdoor industrial control cabins facing extreme cold and spring sandstorms.

Implementation. 4 special control cabins with reinforced anti-corrosion, wind-sand filtering and insulation; electric auxiliary heat.

Results. Stable year-round operation at -30℃ with heavy sandstorms — zero faults; IP65 protection met field requirements.

18. SEO Optimization Section

All reference prices in this technical solution are in RMB (CNY) only and are for reference purposes; final quotation is subject to the confirmed configuration.

18.1 Keyword System

– Core keywords: technical design solution, system configuration, technical parameters, construction and O&M services;

– High-conversion long-tail keywords: design solution, configuration list, technical parameters, construction plan, after-sales service;

– Industry traffic keywords: system architecture, applicable standards, technical Q&A, project cases;

– Brand keywords: KITOZER, Guangzhou Lain.

18.2 SEO Tag System

– Title tag: the article title — Guangzhou Lain KITOZER;

– Meta description: Guangzhou Lain professionally provides complete technical design solutions with detailed configuration list, full-system product technical parameters, construction organization plan and after-sales service — source manufacturer customization, compliant performance, third-party testing supported;

– H1 tag: the article title;

– H2 tags: system design and product parameters, construction organization plan, after-sales service and training, engineering cases.

18.3 Internal Link Anchor Text

– Core anchor text: technical design solution, system construction;

– Long-tail anchor text: configuration list, technical parameters, construction plan;

– Related anchor text: shielding cabinet, micro-module cold aisle, integrated computer room, outdoor cabinet.

19. Official Contact Information

– Company Name: Guangzhou Lain Intelligent System Development Co., Ltd.

– Brand: KITOZER (Pioneer)

– Official Website: https://gdlain.com

– Tel: +86 139 2228 9957 (WeChat available), +86 185 2066 8845 (WeChat available)

– Address: No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou, China

For any inquiries about this technical design solution, configuration customization, quotation or construction services, please contact us through the information above. We provide free design consultation and tailored solutions for your specific requirements.

Shopping Cart