Meta Keywords: Container data center, prefabricated container data center, standard container data center, container data center installation and commissioning, prefabricated container data center construction plan, container data center installation manual, modular container data center commissioning guide, containerized data center, modular data center, prefabricated cabin data center, outdoor container data center, Lain container data center, Guangdong Lain prefabricated data center, KITOZER container data center
Meta Description: Guangdong Lain Intelligent Data Center provides a complete installation and commissioning manual for standard prefabricated container data centers, covering the full-system construction, commissioning, and acceptance procedures for hoisting and positioning, power supply and distribution, cooling, fire protection, and environmental monitoring. Service Hotline: +86 13538869979; Technical Support: +86 13538869979.
H1 Tag: Standard Prefabricated Container Data Center Installation and Commissioning Manual
H2 Tags: Product Overview, Construction Preparation, Transportation and Hoisting, Foundation Positioning, Cabin Assembly, Power Supply and Distribution System, Cooling System, Fire Protection System, Environmental Monitoring (Dynamics & Environment Monitoring), Integrated Cabling, Grounding and Lightning Protection, System Integration Commissioning, Acceptance Specifications, Operation and Maintenance, Fault Handling, Safety Regulations
Internal Link Optimization Tags (Natural Anchor Text Placement)
Core Anchor Text: Container data center, prefabricated container data center, standard container data center
Long-tail Anchor Text: Container data center installation and commissioning methods, prefabricated container data center construction specifications, container data center commissioning procedures
Related Anchor Text: Modular data center, outdoor data center construction, prefabricated cabin installation solutions
Manufacturer Information
Manufacturer: Guangdong Lain Intelligent Data Center Equipment Co., Ltd.
Service Hotline: +86 13538869979 (WeChat same number)
Technical Support: +86 13538869979
Company Address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou City
Official Website: https://gdlain.com
Preface
This manual is compiled in accordance with national and industry standards including GB/T 36448-2018 “General Specification for Containerized Data Center Rooms,” GB 50462-2024 “Standard for Construction and Acceptance of Data Center Infrastructure,” GB 50174-2017 “Code for Design of Data Centers,” and other relevant national and industry standards. It is applicable to the on-site installation, commissioning, acceptance, and operation and maintenance guidance for the full series of standard prefabricated container data center products manufactured by Guangdong Lain Intelligent Data Center Equipment Co., Ltd.
As a new-generation modular data center solution, the prefabricated container data center adopts a construction model featuring factory prefabrication and rapid on-site deployment. Infrastructure systems including power supply and distribution, cooling, fire protection, monitoring, and integrated cabling are highly integrated within a standard container cabin. Compared with traditional data center construction, the construction cycle is reduced by more than 70%. It is widely applicable in scenarios such as carrier base stations, edge computing nodes, enterprise temporary data centers, emergency command centers, and supporting data centers for outdoor energy storage stations.
This manual provides a detailed elaboration of the full-process technical requirements and operational specifications from construction preparation, transportation and hoisting, foundation positioning, installation and commissioning of each subsystem, to final acceptance and handover. It also incorporates daily operation and maintenance, fault diagnosis and handling, and safety operation procedures, serving as the core technical document guiding the implementation, operation, and maintenance of container data center projects.
All installation and commissioning work must be performed by qualified professional technical personnel. During construction, applicable national safety production laws and regulations as well as the operational procedures specified in this manual must be strictly observed. For special working conditions not covered in this manual, please contact the Guangdong Lain Intelligent Data Center technical support department promptly for specialized technical guidance.
Chapter 1 Product Overview

1.1 Product Definition and Features
A standard prefabricated container data center is an integrated data center product built upon standard marine shipping containers. The cabin structure modification, thermal insulation treatment, interior finishing, and integration and commissioning of all electromechanical systems are completed at the factory. The complete unit is then transported to the project site, where only external interface connections are required before it can be put into operation.
Core Features:
- Factory Prefabrication: More than 85% of construction work is completed at the factory. On-site work requires only hoisting and positioning, external pipeline connection, and system integration commissioning, significantly shortening the on-site construction period.
- Rapid Deployment: Standard single-cabin products can be delivered and put into service within 7 days of arrival on site. Multi-cabin parallel projects can complete overall deployment within 15 days.
- High Integration: Integrates complete data center infrastructure systems including power supply and distribution, UPS, precision air conditioning, fire protection, environmental monitoring (Dynamics & Environment Monitoring), and integrated cabling.
- Scenario Adaptability: Capable of withstanding extreme ambient temperatures from -40°C to +55°C, with windproof, rainproof, dustproof, anti-corrosion, and seismic protection capabilities.
- Flexible Expansion: Utilizes standardized modular design, enabling multi-cabin parallel expansion based on business requirements and supporting phased construction.
- Mobility and Convenience: Can be hoisted and relocated as a complete unit, suitable for temporary deployment, disaster recovery centers, and other applications requiring flexible relocation.
1.2 Product Classification
Classification by Function and Purpose:
- IT Equipment Container Data Center: Primarily used for housing server, switch, storage, and other IT equipment, configured with complete data center infrastructure.
- Power Distribution Container Data Center: Independent power supply and distribution module, built-in high-voltage distribution cabinets, transformers, low-voltage distribution cabinets, UPS systems, etc.
- Cooling Container Data Center: Independent cooling module, built-in precision air conditioners, chillers, cooling towers, and other cooling equipment.
- Hybrid Container Data Center: Simultaneously integrates IT equipment areas and supporting electromechanical equipment areas, suitable for small and medium-scale data centers.
- Special Function Container Data Center: Including customized products such as shielded data centers, command center data centers, and energy storage supporting data centers.
Classification by Specification and Dimensions:
- 20-foot Standard Type: External dimensions 6058mm × 2438mm × 2896mm; internal usable space approximately 5.8m × 2.2m × 2.4m.
- 40-foot Standard Type: External dimensions 12192mm × 2438mm × 2896mm; internal usable space approximately 11.9m × 2.2m × 2.4m.
- 40-foot High-Cube Type: External dimensions 12192mm × 2438mm × 3124mm; internal clear height up to 2.6m.
- Customized Wide Type: Width expandable to 3000mm~3500mm, improving internal space utilization.
Classification by Protection Rating:
- Standard Outdoor Type: IP55 protection rating, suitable for general outdoor environments.
- High Protection Type: IP65 protection rating, suitable for harsh environments such as dusty, high-humidity, and coastal high-salt-spray conditions.
- Explosion-Proof Type: Compliant with Ex explosion-proof standards, suitable for flammable and explosive locations such as petroleum, chemical, and coal mining facilities.
1.3 System Composition
A standard prefabricated container data center consists of the following eight major systems:
- Cabin Structure System: Container main frame, thermal insulation layer, interior finishing, doors and windows, anti-static flooring, etc.
- Power Supply and Distribution System: Utility power input distribution cabinets, UPS uninterruptible power supply, battery banks, rack-mounted PDUs, busways, etc.
- Cooling and Air Conditioning System: Precision air conditioners, fresh air system, airflow organization devices, cold/hot aisle containment, etc.
- Fire Protection System: Fire detection alarms, gas fire suppression devices, emergency lighting, evacuation signage, etc.
- Environmental Monitoring System (Dynamics & Environment Monitoring): Environmental monitoring, equipment monitoring, security monitoring, remote management platform, etc.
- Integrated Cabling System: Network cabinets, fiber optic patch panels, copper cabling, cable trays and conduits, etc.
- Grounding and Lightning Protection System: Surge protectors, grounding copper busbars, equipotential bonding, grounding electrodes, etc.
- Electromagnetic Shielding System (Optional): Shielding steel plates, waveguide windows, filter connectors, shielding doors, etc.
1.4 Main Technical Parameters
1.4.1 Cabin Structure Parameters
| Parameter | Value |
|---|---|
| Main Frame Material | Q235B high-quality carbon structural steel |
| Frame Welding Process | CO2 gas shielded welding, compliant with GB 50661-2011 |
| Rust Removal Grade | Sa2.5 grade, compliant with GB/T 8923 |
| Anti-Corrosion Coating | Zinc-rich primer + epoxy intermediate coat + polyurethane topcoat, total thickness ≥240μm |
| Insulation Layer Material | Centrifugal glass wool / rock wool, thermal conductivity ≤0.040W/(m·K) |
| Insulation Layer Thickness | Roof panel 120mm, side wall 100mm, floor panel 80mm |
| Interior Wall Surface | Color steel plate / galvanized steel plate, thickness ≥0.6mm |
| Anti-Static Flooring | All-steel anti-static flooring, load capacity ≥1000kg/m², system resistance 10⁶~10⁹Ω |
| Protection Rating | IP55 (standard type) / IP65 (high protection type) |
| Seismic Rating | Intensity 8, compliant with GB 50011 |
| Design Service Life | 25 years |
1.4.2 Environmental Parameters
| Parameter | Value |
|---|---|
| Operating Ambient Temperature | -40°C ~ +55°C |
| Storage Ambient Temperature | -55°C ~ +70°C |
| Relative Humidity | 5% ~ 95% (non-condensing) |
| Altitude | ≤3000m (derating required above 3000m) |
| Internal Operating Temperature | 18°C ~ 27°C (Class A data center standard) |
| Internal Relative Humidity | 40% ~ 70% |
| Cleanliness | Class A, airborne particles >0.5μm ≤18000 particles/liter |
| Noise Level | ≤75dB(A) at 1m outside the cabin; ≤65dB(A) in internal working area |
1.4.3 Electrical Parameters
| Parameter | Value |
|---|---|
| Rated Input Voltage | 380V/220V AC, three-phase five-wire system |
| Rated Frequency | 50Hz |
| Voltage Fluctuation Range | ±15% |
| UPS Backup Time | Standard configuration 15 minutes, expandable upon request |
| Grounding Resistance | ≤4Ω |
| Insulation Resistance | ≥2MΩ |
| Dielectric Strength | 2000V AC, no breakdown for 1 minute |
1.5 Applicable Standards
The design, production, installation, and acceptance of this product strictly comply with the following standards and specifications:
- GB/T 36448-2018 “General Specification for Containerized Data Center Rooms”
- GB 50174-2017 “Code for Design of Data Centers”
- GB 50462-2024 “Standard for Construction and Acceptance of Data Center Infrastructure”
- GB 50011-2010 “Code for Seismic Design of Buildings” (2016 Edition)
- GB 50017-2017 “Standard for Design of Steel Structures”
- GB 50052-2009 “Code for Design of Power Supply and Distribution Systems”
- GB 50116-2013 “Code for Design of Automatic Fire Alarm System”
- GB 50370-2005 “Code for Design of Gas Fire Extinguishing Systems”
- GB 50343-2012 “Technical Code for Protection of Building Electronic Information System Against Lightning”
- GB/T 2887-2011 “General Specification for Computer Field”
- GB/T 9361-2011 “Safety Requirements for Computer Field”
- JGJ/T 251-2011 “Technical Specification for Anti-Corrosion of Building Steel Structures”
Chapter 2 Construction Preparation

2.1 Technical Preparation
2.1.1 Drawing Review and Technical Disclosure
- Prior to construction, the construction organization, supervision unit, construction unit, and manufacturer must jointly conduct a drawing review to verify consistency between construction drawings and actual site conditions.
- Key drawings requiring priority review include the container data center floor plan, foundation construction drawings, external interface location drawings, and pipeline routing drawings.
- The manufacturer’s technical manager must provide detailed technical disclosure to on-site construction personnel, clarifying the installation and commissioning process, key technical parameters, quality control points, and safety precautions.
- Technical disclosure must be documented in writing, signed and confirmed by all participants, and archived.
- For special project requirements, a dedicated construction plan must be prepared and approved by the supervision unit before implementation.
2.1.2 Construction Plan Preparation
The dedicated construction plan shall include the following:
- Project overview and compilation basis
- Construction organization structure and personnel allocation
- Construction schedule plan and duration guarantee measures
- Main construction procedures and technical requirements
- Quality assurance system and quality control points
- Safety production and civilized construction measures
- Emergency response plan and risk control measures
- Equipment and material delivery schedule
- Acceptance standards and acceptance procedures
2.1.3 Standards and Specifications Preparation
The construction site shall be equipped with complete relevant standards and specification documents, mainly including:
- Applicable national and industry construction acceptance specifications
- Product factory inspection reports and certificates of conformity
- Installation and operation manuals for each subsystem equipment
- Specialized technical documents provided by the manufacturer
2.2 Site Preparation
2.2.1 Site Selection Requirements
- Terrain and Geological Requirements: The site shall be flat with solid geology, avoiding low-lying areas prone to water accumulation, landslide zones, and debris flow prone areas.
- Surrounding Environment Requirements: Stay clear of flammable and explosive locations, strong electromagnetic interference sources, and strong corrosive gas sources. Maintain adequate safety fire separation distances from surrounding buildings.
- Transportation Condition Requirements: Satisfy passage requirements for large transport vehicles and working space requirements for lifting equipment.
- Utility Interface Requirements: Municipal utility interfaces including power, water supply and drainage, and communication fiber optics shall be available nearby.
- Flood Prevention Requirements: The site elevation shall be at least 0.5m above the local 50-year flood level.
2.2.2 Site Leveling and Clearing
- Remove all obstacles, weeds, and debris from the construction area.
- Level and compact the site, with a compaction coefficient of not less than 0.93.
- Set up temporary drainage ditches around the site perimeter to ensure smooth drainage and no standing water.
- Plan functional areas including equipment storage area, material storage area, construction work area, and temporary office area.
- Set up temporary fencing and safety warning signs, implementing enclosed construction management.
2.2.3 External Interface Preparation
- Power Interface: Utility power incoming cables shall be laid and in place, with sufficient wiring margin reserved. Power supply capacity shall meet design requirements.
- Communication Interface: Communication fiber optic cables/cables shall be routed to the vicinity of the container data center, with sufficient access length reserved.
- Water Supply and Drainage Interface: If external water supply and drainage connection is required, pipelines shall be laid to the designated interface locations.
- Grounding Interface: The on-site grounding grid shall be completed, with grounding resistance tested and qualified. Grounding lead-out terminals shall be reserved.
2.3 Personnel Preparation
2.3.1 Construction Organization Structure
| Position | Quantity | Responsibility |
|---|---|---|
| Project Chief Commander | 1 | Overall project coordination and management |
| Technical Manager | 1 | Technical guidance and quality control |
| Construction Team Leader | 1 | On-site construction organization and personnel management |
| Crane Operators | 2 | Certified, responsible for hoisting operations |
| Electrical Engineers | 2 | Power supply and distribution system installation and commissioning |
| Refrigeration Engineers | 2 | Air conditioning and cooling system installation and commissioning |
| Fire Protection Engineer | 1 | Fire protection system installation and commissioning |
| Low-Voltage/ELV Engineers | 2 | Monitoring and integrated cabling systems |
| Welders | 2 | Certified, responsible for welding operations |
| General Laborers | 4~6 | Auxiliary operations |
2.3.2 Personnel Qualification Requirements
- Special operation personnel (crane operators, welders, electricians, and aerial work personnel) must hold valid special operation certificates recognized by the state.
- Professional technical personnel shall possess corresponding professional technical titles or job qualification certificates.
- All construction personnel must undergo safety training and technical disclosure, and only those who pass assessment are permitted to work.
- Manufacturer’s on-site technical support personnel shall possess corresponding product commissioning qualifications and extensive on-site experience.
2.4 Tool and Equipment Preparation
2.4.1 Hoisting and Transportation Tools
- Mobile crane (selected based on container weight: not less than 25 tons for 20-foot cabins, not less than 50 tons for 40-foot cabins)
- Flatbed transport trailer
- Dedicated lifting shackles, slings, wire ropes
- Spirit level, theodolite
- Hydraulic jacks, pry bars
2.4.2 Electrical Construction Tools
- Multimeter, clamp ammeter, megger (insulation resistance tester), grounding resistance tester
- Crimping pliers, wire strippers, electrician tool kit
- Hand drill, rotary hammer drill, angle grinder
- Torque wrench
- Cable reel stands, pulleys
2.4.3 Piping Construction Tools
- Threading machine, pipe cutting machine, pipe bender
- Pipe wrenches, wrenches, screwdriver sets
- Pressure test pump, vacuum pump
- Refrigerant charging machine
- Leak detector
2.4.4 Testing and Commissioning Instruments
- Temperature and humidity data logger
- Anemometer, differential pressure gauge
- Particle counter
- Noise meter
- Power quality analyzer
- Infrared thermal imaging camera
2.4.5 Safety Protective Equipment
- Safety helmets, safety harnesses, safety shoes
- Insulating gloves, insulating boots
- Protective goggles, dust masks
- Fire extinguishers, first aid kit
- Night construction lighting equipment
2.5 Material and Equipment Incoming Inspection
2.5.1 Incoming Inspection Procedure
- Upon arrival of equipment and materials at the site, joint inspection shall be conducted by the construction organization, supervision unit, construction unit, and supplier.
- Verify that the model, specification, and quantity of equipment and materials match the packing list.
- Inspect the equipment appearance for damage, including transportation damage, denting/deformation, moisture ingress, or water damage.
- Verify that product certificates of conformity, inspection reports, instruction manuals, and other technical documents are complete.
- Conduct sample unpacking inspection on critical equipment and preliminary performance checks on important components.
- Sign the incoming inspection record after acceptance. Non-conforming products shall be returned or replaced promptly.
2.5.2 On-Site Storage Requirements
- Equipment shall be stored on a flat, dry, well-ventilated site, protected from direct sunlight and rain.
- Precision electrical equipment shall be stored indoors or under a rain shelter.
- Equipment stacking height shall comply with product requirements to prevent crushing and deformation.
- Fragile parts and spare parts shall be stored separately by category with clear labeling.
- Fire-fighting equipment and hazardous materials shall be stored separately, compliant with safety management regulations.
Chapter 3 Transportation, Unloading, and Hoisting

3.1 Transportation Requirements
3.1.1 Pre-Transportation Preparation
- Confirm the transportation route, and verify that bridges, culverts, height limits, and width limits along the route satisfy transportation requirements.
- Handle relevant oversize/overweight transportation approval procedures (if required).
- Secure the container data center for transportation, with secondary fastening of internal equipment to prevent displacement during transit.
- Ensure doors and windows are firmly locked, and all openings are sealed and protected.
- The transport vehicle shall be a flatbed trailer of suitable tonnage, with a flat bed surface and reliable tie-down points.
3.1.2 Transportation Process Requirements
- Travel Speed: Ordinary roads ≤60km/h, expressways ≤80km/h; reduce speed on rough road sections.
- During transit, stop periodically for inspection, checking for loosened lashings and abnormal equipment conditions.
- In rainy or snowy weather, take waterproofing and moisture-proofing measures to prevent equipment from getting damp.
- Loading and unloading operations shall be performed during daylight hours. Night operations require adequate lighting.
- Avoid hard acceleration, hard braking, and sharp turns during transportation to prevent equipment sliding and collision.
3.2 Unloading and Hoisting Operations
3.2.1 Pre-Hoisting Inspection
- Inspect the performance condition of the hoisting equipment, ensuring the crane outriggers are stable and the ground bearing capacity meets requirements.
- Inspect hoisting tools, wire ropes, shackles, and other rigging to confirm no defects such as damage, broken wires, or deformation, and that the rated load meets hoisting requirements.
- Confirm the container lifting point locations. Standard containers use the four top corner castings as lifting points. Lifting from any other part is strictly prohibited.
- Clear the hoisting work area, set up a warning zone, and prohibit unauthorized personnel from entering.
- Designate a hoisting director to unify command signals. All operating personnel shall be familiar with the hoisting plan.
3.2.2 Hoisting Operation Specifications
- Hoisting rigging shall be securely connected to the container corner castings, with uniform load distribution across all four lifting points.
- Test Lift: Lift the container to a height of 200~300mm above the ground, hold for 3~5 minutes. Inspect the stability of the rigging, slings, and crane. Only after confirming no abnormalities may lifting continue.
- Lifting and lowering shall be smooth and slow, avoiding large swings and impacts.
- A dedicated person shall monitor the hoisting process at all times. Operations shall be stopped immediately upon detecting any abnormality.
- Outdoor hoisting operations are prohibited when wind force exceeds Force 6.
- Aerial workers must wear safety harnesses and tool bags. Throwing objects from height is strictly prohibited.
3.2.3 Unloading and Positioning
- Pause when the container is lowered to approximately 100mm above the foundation. Adjust its position to align with the foundation positioning lines.
- Lower slowly while observing the positioning on all sides to ensure accurate positioning.
- After the container is fully seated, check whether the forces at the four corners are uniform and whether there is any suspension/hollow condition.
- Remove the hoisting rigging and clean up the work area.
3.3 Hoisting Safety Precautions
- Hoisting operations must be directed and operated by certified crane operators. Uncertified operation is strictly prohibited.
- It is strictly prohibited for personnel to stand within the hoisting radius or to pass through or remain beneath suspended loads.
- Overloading hoists and angled pulling/lifting are strictly prohibited.
- Equipment inspection and adjustment are prohibited during hoisting operations.
- Hoisting operations shall be halted in adverse weather conditions such as heavy fog, thunderstorms, or strong winds.
- After hoisting operations are completed, retract the crane outriggers and organize the hoisting tools.
Chapter 4 Foundation Construction, Positioning, and Leveling
4.1 Foundation Design Requirements
4.1.1 Foundation Types
Standard prefabricated container data centers typically adopt the following foundation forms:
- Reinforced Concrete Strip Foundation: Suitable for sites with general geological conditions; strip foundations are set along the bottom perimeter of the container.
- Reinforced Concrete Raft Foundation: Suitable for poor geological conditions or high load conditions, providing uniform overall load distribution.
- Steel Structure Platform Foundation: Suitable for elevated installation requirements or uneven sites; fabricated using structural steel welding.
- Precast Concrete Pier Foundation: Suitable for temporary deployment scenarios; easy to install and reusable.
4.1.2 Foundation Technical Parameters
| Parameter | Requirement |
|---|---|
| Bearing Capacity | Foundation ground bearing capacity not less than 100kN/m²; increase accordingly for multi-cabin stacking or heavy-load equipment |
| Dimensional Requirements | Foundation plan dimensions shall extend 200~300mm beyond the container external dimensions on each side |
| Elevation Requirements | Foundation top elevation shall be not less than 300mm above the outdoor ground level to prevent rainwater backflow |
| Flatness Requirements | Foundation top surface flatness deviation ≤3mm/m; total length deviation ≤5mm |
| Embedded Parts Requirements | Embedded anchor bolts or embedded steel plates in the foundation; position deviation ≤2mm |
4.1.3 Foundation Construction Requirements
- Geological investigation shall be conducted prior to foundation construction, with foundation depth and type determined based on the geological report.
- Reinforcement bar specifications, spacing, and concrete cover thickness shall comply with design requirements, with secure binding.
- Concrete grade not lower than C30, thoroughly vibrated and compacted, with a curing period of not less than 7 days.
- Embedded parts shall be accurately positioned and securely fixed, and must not shift during concrete pouring.
- The foundation surface shall be smooth, free from honeycombing, surface voids, cracks, exposed reinforcement, and other defects.
- Drainage ditches and apron slopes shall be provided around the foundation perimeter to ensure smooth drainage.
4.2 Positioning and Leveling
4.2.1 Setting Out Lines
- Based on construction drawings, mark the container installation positioning lines and centerlines on the foundation top surface.
- Mark the positions of anchor bolt holes or embedded steel plates.
- Recheck positioning dimensions; deviations shall be controlled within allowable tolerances.
4.2.2 Positioning Adjustment
- After the container is lifted into place, roughly align it with the positioning lines.
- Use hydraulic jacks for fine adjustment so that the container edge lines completely coincide with the positioning lines.
- Adjust gradually and incrementally, avoiding excessive single adjustment amounts.
- For multi-cabin parallel installation, ensure adjacent cabins are aligned with uniform gaps.
4.2.3 Leveling
- Use a precision spirit level to measure the elevations at the four corners of the container.
- Adjust horizontal leveling through the use of base shims or adjustable support feet.
- Leveling Standard: Longitudinal levelness deviation ≤2mm/m, total length ≤5mm; transverse levelness deviation ≤1.5mm/m, total width ≤3mm.
- After leveling is completed, all support feet or shims shall bear uniform load with no suspension condition.
- After levelness inspection passes, tighten the anchor bolts to securely connect the container to the foundation.
4.3 Fixing and Sealing
4.3.1 Bottom Fixing
- When securing with embedded anchor bolts, the bolt specification shall not be less than M20, with tightening torque complying with design requirements.
- When securing by welding, the weld height shall not be less than 8mm, with full fillet welding. Anti-corrosion treatment shall be applied after welding.
- Number of Fixing Points: Not less than 6 points for 20-foot containers; not less than 8 points for 40-foot containers.
- After fixing is complete, conduct pull-out force spot checks to ensure connection strength meets requirements.
4.3.2 Bottom Sealing
- Seal the gap between the container bottom and the foundation using weather-resistant sealant.
- Clean dust and debris from the contact surfaces before sealing to ensure firm adhesion.
- The sealant shall be continuous and uniform, free from breaks and bubbles, with a smooth surface.
- Waterproofing baffles may be installed on the exterior side to further enhance waterproof performance.
Chapter 5 Cabin Assembly and Sealing
5.1 Multi-Cabin Assembly Requirements
5.1.1 Assembly Forms
- Horizontal Assembly: Containers arranged side by side along the width direction to expand the internal width of the data center.
- Longitudinal Assembly: Containers connected end-to-end along the length direction to extend the internal length of the data center.
- Stacked Assembly: Containers stacked vertically to save floor space.
- Mixed Assembly: Simultaneously employing horizontal, longitudinal, and stacked assembly methods to form a large-scale container data center cluster.
5.1.2 Assembly Accuracy Requirements
| Parameter | Tolerance |
|---|---|
| Gap between adjacent cabin mating surfaces | ≤5mm |
| Height difference between adjacent cabins | ≤3mm |
| Cabin alignment deviation | ≤3mm/m |
| Overall straightness deviation after assembly | ≤8mm |
5.2 Assembly Construction Procedure
5.2.1 Pre-Assembly Preparation
- Clean dust, oil, and debris from the mating end surfaces.
- Inspect sealing strips for damage or aging.
- Prepare assembly connectors, sealing materials, and fastening tools.
- Apply continuous sealing strips to the mating end surfaces, with strip joints made at 45° bevel joints.
5.2.2 Assembly Operations
- Use hydraulic jacks or traction devices to slowly bring the two cabins together.
- Observe alignment at all times during the mating process and promptly correct any deviations.
- After the two cabins are joined, install the assembly fasteners and tighten gradually and uniformly.
- Tightening sequence shall proceed symmetrically from the center outward to prevent localized stress concentration.
- After assembly is completed, recheck overall dimensions and accuracy.
5.2.3 Internal Passageway Opening
- If a connecting door needs to be opened in the cabin wall, use a factory-prefabricated standard door opening module.
- Structural reinforcement shall be applied around the opening to ensure the structural strength of the cabin is not compromised.
- Apply sealing treatment around the door opening and install a fire-rated sealing door.
- Install a threshold at the door opening to prevent water intrusion.
5.3 Sealing Treatment
5.3.1 External Sealing
- Seal the exterior side of assembly joints with weather-resistant silicone sealant.
- Sealant width not less than 20mm, thickness not less than 3mm.
- Apply painter’s tape before sealing to ensure straight and neat sealant lines.
- Trim the sealant before it skin-dries to remove excess material.
5.3.2 Internal Sealing
- Install decorative cover plates on the interior side of assembly joints to conceal joint gaps.
- Fill between the cover plates and the cabin wall with fire-resistant thermal insulation material.
- All gaps shall be fire-stopped to meet fire compartmentation requirements.
- Proper transition treatment at floor joint locations to ensure the anti-static flooring remains flat and continuous.
5.3.3 Waterproof Testing
- After assembly sealing is completed, conduct a water spray test.
- Use a high-pressure water gun to spray the assembly joints for not less than 30 minutes continuously.
- Inspect the interior side for any water seepage or leakage.
- If leakage is found, identify the cause and re-perform sealing treatment until it passes.
Chapter 6 Power Supply and Distribution System Installation and Commissioning
6.1 System Overview
The power supply and distribution system of the prefabricated container data center adopts a dual utility power input + UPS uninterruptible power supply architecture, comprising high-voltage distribution (optional), transformer (optional), low-voltage incoming cabinet, UPS distribution cabinet, battery banks, rack PDUs, lighting distribution, and other components, providing stable and reliable power to all IT equipment and electromechanical equipment within the data center.
The system design complies with GB 50052-2009 “Code for Design of Power Supply and Distribution Systems,” featuring comprehensive protection functions including overload, short circuit, leakage, overvoltage, and undervoltage protection. It is also equipped with energy metering and power monitoring modules for real-time monitoring and management of the power supply system.
6.2 Main Equipment Installation
6.2.1 Distribution Cabinet Installation
- Before positioning the distribution cabinet, check that the base steel channel is installed straight and level with reliable grounding.
- Hoist or transport the distribution cabinet to the installation position, and adjust for levelness and verticality.
- Verticality deviation ≤1.5‰, panel surface flatness deviation ≤2mm, gap between adjacent cabinets ≤2mm.
- Secure the distribution cabinet to the base steel channel using bolted connections or welding.
- Check internal components: circuit breakers, contactors, relays, and other components shall match the design in model and specification, with intact appearance and secure wiring.
- Distribution cabinet labeling shall be clear, circuit numbers accurate, and the correspondence relationship clear.
6.2.2 UPS Main Unit Installation
- The UPS main unit shall be installed in a well-ventilated location that is convenient for operation and maintenance.
- Install anti-vibration pads at the equipment base to reduce operating noise and vibration.
- Maintenance clearances around the main unit: front ≥800mm, sides ≥600mm, rear ≥600mm.
- The UPS main unit shall be reliably grounded with grounding resistance meeting requirements.
- Check that internal UPS modules are securely seated, and fan blades and heat sinks are free of dust accumulation.
- The cables connecting the battery bank to the UPS main unit shall comply with design specifications, with voltage drop meeting standards.
6.2.3 Battery Bank Installation
- The battery rack shall be installed firmly, with levelness meeting requirements and anti-corrosion treatment applied.
- Battery appearance inspection: housing free from cracks, deformation, and leakage; terminals free from oxidation.
- Batteries shall be placed in sequence according to positive/negative polarity, with correct polarity connections.
- Battery connecting bars shall be tightened, with torque meeting manufacturer requirements. Apply conductive grease to terminals.
- Measure and record the total voltage of the battery bank and individual cell voltages; deviations shall be within allowable range.
- The battery room shall be well ventilated, with ambient temperature ideally controlled at 20°C~25°C.
- Temperature sensors shall be installed on the battery bank and connected to the environmental monitoring system.
6.2.4 PDU and Busway Installation
- Rack PDUs shall be installed on the rear vertical rails of the cabinet at a height convenient for operation.
- PDUs shall be securely fixed with correct input/output wiring and clear phase labeling.
- The busway shall be installed straight and level, with support bracket spacing meeting requirements and reliable connections.
- Plug-in boxes shall make good contact with the busway, with smooth insertion/withdrawal and reliable locking mechanisms.
- The busway shall be properly grounded, with total grounding resistance along the full length ≤0.1Ω.
6.3 Cable Laying and Wiring
6.3.1 Cable Laying Requirements
- Cable specifications, models, and voltage ratings shall comply with design requirements, with complete product certificates of conformity and inspection reports.
- Insulation resistance testing shall be conducted before cable laying; low-voltage cable insulation resistance ≥10MΩ.
- Cables shall be laid along cable trays or through conduits, neatly arranged and securely tied.
- Cable bending radius shall comply with code requirements: armored cables ≥12 times cable diameter, non-armored cables ≥6 times.
- Sufficient slack shall be left at both cable ends, typically 1.5~2m.
- Cable tags shall be clearly labeled with the starting point, end point, model, and specification.
- Power cables and weak-current (signal) cables shall be laid separately, with spacing complying with code requirements to avoid electromagnetic interference.
6.3.2 Wiring Requirements
- Verify circuit numbers before wiring to ensure correct connections.
- Wire terminals shall be crimped securely with uniform tinning. Stranded wires are strictly prohibited from being inserted directly into terminals.
- Terminal connections to equipment shall be tightened with torque meeting requirements.
- Phase sequence correctness: phase A yellow, phase B green, phase C red, neutral light blue, ground yellow/green bicolor.
- Wiring inside cabinets shall be neat and orderly, with secure cable bundling and clear numbering.
- All cable entry points shall be fire-stopped and waterproof-sealed.
6.4 System Commissioning
6.4.1 Pre-Energization Inspection
- Verify that all switches are in the OFF position.
- Re-verify wiring correctness, with emphasis on phase sequence and neutral/ground conductors.
- Measure insulation resistance of each circuit to confirm no short circuit or ground fault.
- Verify that the grounding system connections are reliable and grounding resistance has passed testing.
- Clean debris from inside the distribution cabinets, confirming no tools or wire offcuts are left behind.
- Inspect the equipment surrounding environment to ensure good ventilation and no flammable or explosive materials.
6.4.2 Utility Power Incoming Circuit Commissioning
- Measure the utility input voltage, frequency, and phase sequence to confirm compliance with requirements.
- Close the utility power incoming switch and check the voltage and current indications on the incoming cabinet.
- Close circuit breakers level by level, checking whether the voltage of each distribution circuit is normal.
- Test the leakage protection, overload protection, and short-circuit protection functions for proper operation.
- Dual utility power transfer test: simulate a power failure on one utility feed and verify the ATS transfer action is reliable and the switching time meets requirements.
- Record the no-load voltage and current data of each circuit.
6.4.3 UPS System Commissioning
- Power on the UPS main unit and perform self-test, checking the display for normal operation and absence of fault alarms.
- Set UPS operating parameters: output voltage, frequency, battery low-voltage alarm value, charging parameters, etc.
- Utility mode operation test: check the UPS output voltage, frequency, and waveform.
- Battery mode test: disconnect utility input, verify automatic UPS transfer to battery power, measure output parameters, and record switching time.
- Bypass mode test: test the UPS transfer to bypass and return to normal mode functions.
- Parallel operation test (if applicable): check load sharing among the parallel system, with circulating current within the allowable range.
- Battery charge/discharge test: perform constant current charging test, checking charging current and voltage; perform discharge test, recording discharge time and individual cell voltage changes.
- Load testing: gradually increase load, testing UPS operating status at 25%, 50%, 75%, and 100% load.
6.4.4 Lighting and Socket Circuit Commissioning
- Lighting circuit energization test: check that all luminaires illuminate normally and switch controls operate correctly.
- Emergency lighting test: disconnect the normal lighting power supply, verify the emergency lighting automatically illuminates with duration meeting requirements.
- Maintenance sockets and general sockets energization test: measure socket voltage, phase sequence, and grounding.
- Test the socket leakage protection function for reliable operation.
6.5 Quality Acceptance Standards
- Distribution cabinet installation verticality and flatness comply with code requirements.
- Cables laid neatly, with clear labeling, correct and secure wiring.
- System insulation resistance and grounding resistance meet standards.
- Dual utility power transfer is reliable, with transfer time meeting design requirements.
- All UPS performance indicators meet requirements, with output voltage stability ≤±1%.
- Battery bank individual cell voltage deviation ≤±2%.
- All protection functions operate accurately and reliably.
- Energy metering devices are accurate, with errors within the allowable range.
Chapter 7 Cooling and Air Conditioning System Installation and Commissioning
7.1 System Overview
The cooling system of the prefabricated container data center utilizes dedicated precision air conditioning units for data centers, providing a stable and reliable operating environment for IT equipment through precise temperature and humidity control. Depending on the cooling method, the system can be configured as air-cooled precision air conditioning, water-cooled precision air conditioning, heat pipe rear-door cooling, or liquid cooling.
The standard configuration adopts an N+1 redundancy design. When a single air conditioning unit fails, the remaining units can handle the total cooling load, ensuring the data center temperature does not exceed limits. The system features automatic start/stop, automatic temperature adjustment, automatic fault transfer, and other functions, and is connected to the environmental monitoring system for remote monitoring and management.
7.2 Main Equipment Installation
7.2.1 Indoor Unit Installation
- Before positioning the precision air conditioning indoor unit, check that the foundation is level and the load-bearing capacity meets requirements.
- Install anti-vibration pads at the equipment base, with pad thickness and hardness complying with design requirements.
- Align and level the equipment, with verticality deviation ≤2‰.
- Secure the equipment firmly to the floor, with no visible shaking or abnormal noise during operation.
- Maintenance space requirements: front ≥1000mm, both sides ≥600mm, rear ≥800mm.
- Check that the fan, compressor, evaporator, filters, and other components are intact and free from transportation damage.
7.2.2 Outdoor Unit Installation
- The outdoor unit shall be installed in a well-ventilated location away from heat sources and obstructions, ensuring unobstructed air intake and exhaust.
- The outdoor unit foundation shall be not less than 300mm above ground, with a level and firm base.
- Equipment shall be installed level with an inclination of ≤3°.
- When multiple outdoor units are installed side by side, the spacing shall be ≥500mm to ensure effective heat dissipation.
- Outdoor units shall be securely fixed with wind-resistant fastening devices installed.
- The orientation of the outdoor unit shall avoid the prevailing summer wind direction blowing directly onto the condenser.
7.2.3 Air Duct and Air Outlet Installation
- Air duct material shall be galvanized steel sheet, with thickness complying with code requirements.
- Air duct connections shall use flanged or lock-form connections with tight sealing, and air leakage shall comply with standards.
- Air duct support hanger spacing shall comply with code requirements, installed securely.
- Supply and return air outlet positions shall be consistent with the airflow organization design, with flat and aesthetically pleasing installation.
- Cold/hot aisle containment devices shall be installed tightly to reduce cooling loss.
- Damper actuators shall operate flexibly, with proper open/close positioning, and accurate feedback signals.
7.3 Refrigerant Piping Installation
7.3.1 Piping Material Requirements
- Refrigerant copper pipes shall be high-quality seamless copper tubes, with clean and dry inner walls, free from oxidation and oil contamination.
- Copper pipe specifications and wall thickness shall meet design pressure requirements.
- Insulation material shall be Class B1 flame-retardant rubber-plastic insulation pipe, with thickness meeting design requirements.
- Support hangers, pipe clamps, and other accessories shall be treated with anti-corrosion treatment.
7.3.2 Piping Installation Requirements
- Piping routing shall comply with the design, with straight horizontal and vertical runs, neatly arranged and aesthetically pleasing.
- Copper pipe cutting shall use a dedicated pipe cutter, with smooth and burr-free cut ends.
- Copper pipe welding shall use brazing process. Nitrogen gas protection shall be applied during welding to prevent inner wall oxidation.
- Pipe slope requirements: discharge pipes slope toward the condenser; liquid pipes slope toward the indoor unit.
- Piping shall be securely fixed, with support hanger spacing complying with code requirements.
- Sleeves shall be installed where pipes pass through walls, with gaps sealed using fire-resistant materials.
- After piping installation is complete, perform blow-through to remove debris and oxide scale from the pipes.
7.3.3 Piping Pressure Testing and Leak Checking
- Pneumatic pressure test: Charge the system with dry nitrogen. Test pressure shall comply with design requirements (R22 system: high-pressure side 2.4MPa, low-pressure side 1.6MPa).
- Hold pressure for 24 hours; a pressure drop of ≤0.02MPa is considered acceptable.
- Conduct meticulous leak checking using an electronic leak detector or soapy water, focusing on weld joints, connections, and valves.
- After leak checking passes, evacuate the system to a vacuum of ≤-0.1MPa, holding for 2 hours without rebound.
- Charge refrigerant according to the design quantity, weighing the refrigerant cylinder before charging.
7.4 Water Piping Installation (Water-Cooled Type)
7.4.1 Piping Installation Requirements
- Pipe material and specifications shall comply with design; typically galvanized steel pipe or seamless steel pipe.
- Pipe connections: galvanized steel pipe shall use threaded or grooved connections; seamless steel pipe shall use welded connections.
- Pipe slope shall comply with requirements, with air vents at the highest points and drain valves at the lowest points.
- Pipe support hangers shall be installed securely, with spacing complying with code requirements.
- After pipe installation, perform hydrostatic testing. Test pressure shall be 1.5 times the working pressure, held for 30 minutes without leakage.
- Flush the pipes until the discharge water is clear and free of impurities.
7.4.2 Pipe Insulation
- Insulation work shall be performed after the pipe pressure test passes.
- Insulation material shall be Class B1 flame-retardant rubber-plastic insulation material, with thickness complying with design.
- Insulation joints shall be tight with firm adhesion, free from cracking and detachment.
- Valves, flanges, and other components shall be insulated separately for ease of maintenance.
- The outer surface of the insulation layer shall be smooth and aesthetically pleasing, with proper labeling.
7.5 System Commissioning
7.5.1 Pre-Commissioning Inspection
- Check that air conditioning equipment is securely installed with all accessories present.
- Check that refrigerant piping and water piping connections are correct and free from leakage.
- Check that electrical wiring is correct and grounding is reliable.
- Check that air filters are properly installed, clean, and intact.
- Check that condensate drain piping is unobstructed.
- Check that fans and compressors rotate freely without obstruction.
- Confirm that the supply voltage and frequency meet equipment requirements.
7.5.2 Single-Unit Trial Operation
- Fan independent trial run: Start the fan, check correct rotation direction, smooth operation, and absence of abnormal noise.
- Measure fan current, speed, and airflow, which shall comply with design requirements.
- Electric heater trial run (if applicable): check proper electric heating operation and reliable over-temperature protection.
- Humidifier trial run (if applicable): check normal humidification function and accurate water level control.
- Compressor trial run: Start the compressor, check rotation direction, sound, and oil pressure for normal operation.
- Single-unit trial operation time shall not be less than 2 hours, with operating parameters recorded.
7.5.3 System Integration Commissioning
- Set the air conditioner temperature and humidity set points; verify that temperature and humidity sensor calibration is accurate.
- Cooling mode test: Observe compressor start/stop control, with temperature regulation accuracy reaching ±1°C.
- Heating mode test: Check heating function and temperature control accuracy.
- Humidification mode test: Check humidification function and humidity control accuracy reaching ±5%RH.
- Dehumidification mode test: Check dehumidification function operates normally.
- Fan speed control test: Check the fan operates normally at different speed levels.
- Test high/low pressure protection, overload protection, anti-freeze protection, and other safety protection functions.
- Multi-unit coordinated test: Test main/standby unit transfer, rotating operation, and load sharing functions.
7.5.4 Performance Testing
- Temperature uniformity test: Place temperature and humidity measurement points at different locations in the data center. After 2 hours of full-load operation, the temperature deviation at each point shall be ≤2°C.
- Cooling capacity test: Use the enthalpy difference method or heat balance method to test the actual cooling capacity, which shall reach more than 95% of the nameplate rated value.
- Airflow organization test: Measure the rack inlet air temperature and outlet air temperature; the cold/hot aisle temperature difference shall comply with design.
- N+1 redundancy test: With one air conditioning unit shut down, the remaining units shall maintain operation with the data center temperature rise within the allowable range.
- Noise test: Measure noise levels inside and outside the data center, which shall comply with design indicators.
- Condensation test: Operate under high-humidity conditions; inspect equipment surfaces and piping for condensation.
7.6 Condensate Water System
The slope of the condensate drain pipe shall be ≥1%, sloping toward the drain outlet.
The water seal height of the trap shall comply with design requirements to prevent odor backflow.
The drain pipe shall be connected to the machine room water collection pan or the outdoor drainage system.
Leak detection sensors shall be installed and connected to the environment and power monitoring (EPMS) system.
The drainage system shall be inspected regularly to prevent clogging and overflow.
Chapter 8 Fire Protection System Installation and Commissioning
8.1 System Overview
The fire protection system of the prefabricated container machine room adopts a combined solution of an automatic fire alarm system and a gas fire suppression system, featuring early fire detection, automatic alarm, automatic/manual fire suppression, and linkage control functions. The system complies with the requirements of GB 50116-2013 “Code for Design of Automatic Fire Alarm System” and GB 50370-2005 “Code for Design of Gas Fire Suppression Systems.”
The commonly used extinguishing agent is heptafluoropropane (HFC-227ea) or IG541 mixed gas, featuring high fire-extinguishing efficiency, no residue, and no damage to equipment. The system provides three activation methods: automatic, electrical manual, and mechanical emergency manual, ensuring fire suppression reliability.
8.2 Automatic Fire Alarm System Installation
8.2.1 Detector Installation
- Smoke detectors: installed on the machine room ceiling, with a spacing of ≤15m and a distance from walls of ≤7.5m
- Heat detectors: installed on the ceiling or above equipment, with a spacing of ≤10m and a distance from walls of ≤5m
- Detectors shall be firmly installed, with correct base wiring, and the confirmation lamp oriented for easy observation
- The distance between detectors and air conditioning supply air outlets shall be ≥1.5m, and the distance from perforated supply air ceiling openings shall be ≥0.5m
- The horizontal distance from detectors to walls and beam edges shall be ≥0.5m, and there shall be no obstructions within 0.5m around detectors
8.2.2 Alarm Controller Installation
- The fire alarm controller shall be installed on a wall convenient for operation, with the bottom edge 1.3~1.5m above the floor
- The controller shall be firmly installed, with a verticality deviation of ≤3‰
- The main power supply of the controller shall be directly connected to the fire protection power supply; the use of plug connections is strictly prohibited
- The controller shall be reliably grounded, with a grounding resistance of ≤4Ω
- Wiring inside the controller shall be neat, terminal numbers clearly marked, and bundling secure
8.2.3 Manual Alarm Buttons and Audible/Visual Alarm Devices
- Manual fire alarm buttons shall be installed at entrances/exits, with the bottom edge 1.3~1.5m above the floor
- Buttons shall be firmly installed, clearly visible, and easy to identify
- Audible/visual alarm devices shall be installed above the door or in prominent positions, with an alarm sound level of ≥60dB
- Emergency start/stop buttons shall be installed outside the fire suppression protection zone door, easy to operate and clearly labeled
8.3 Gas Fire Suppression System Installation
8.3.1 Extinguishing Agent Storage Cylinder Installation
- The cylinder room shall be located in a dedicated area with an ambient temperature of 0℃~50℃, dry and well-ventilated
- Cylinder racks shall be firmly installed, and cylinders securely fixed
- Cylinder weighing devices shall be accurately installed to enable real-time monitoring of extinguishing agent leakage
- Cylinder nameplates shall be legible, with filling quantity and pressure conforming to design requirements
- The spacing between cylinders shall facilitate operation and maintenance, with a front operating distance of ≥1.0m
8.3.2 Piping Network and Nozzle Installation
- Fire suppression piping shall use seamless steel pipes with internal and external galvanized treatment
- Pipe connections shall use flange connections or threaded connections, with tight sealing
- Pipe support and hanger spacing shall comply with applicable codes, with secure installation
- Nozzle models and specifications shall conform to the design, with accurate installation direction and position
- After piping installation, pneumatic pressure strength tests and air tightness tests shall be conducted
- Piping shall be cleaned and purged free of debris and oil contamination
8.3.3 Selector Valves and Check Valves
- Selector valves shall be installed in the cylinder room, with operating handles positioned for convenient operation
- Valve flow direction indicators shall be consistent with the medium flow direction
- Pneumatic piping connections shall be correct with no air leakage
- Check valves shall be installed in the correct direction, with flexible and reliable operation
8.4 System Commissioning
8.4.1 Pre-Commissioning Inspection
- Verify that the system equipment models, specifications, and quantities conform to design requirements
- Verify that all circuit connections are correct and terminals are secure
- Verify that the piping network is correctly installed and pressure tests have passed
- Verify that the extinguishing agent filling quantity and filling pressure comply with requirements
- Verify that all labels and nameplates are complete and legible
8.4.2 Fire Alarm System Commissioning
- Power on the alarm controller for self-diagnosis, and verify that all functional modules operate normally
- Conduct simulated fire tests on each detector; the detector shall report alarm accurately and the controller shall display the correct location
- Manual alarm button test: press the button, and the controller shall receive the alarm signal
- Fault test: simulate detector faults and line faults; the controller shall issue fault alarms
- Isolation function test: test detector isolation and de-isolation functions
- Recording function test: verify event recording functions for alarms, faults, and operations
- Linkage logic programming: write linkage control programs according to design requirements
8.4.3 Gas Fire Suppression System Commissioning
- Simulated discharge test: use nitrogen or compressed air for simulated discharge testing
- Automatic activation test: simulate a fire signal; the system shall automatically activate after the set delay period, with normal discharge action
- Manual activation test: operate the emergency start button; the system shall immediately activate discharge
- Emergency stop test: press the emergency stop button during the delay period; the system shall terminate activation
- Linkage function test: upon gas suppression activation, air conditioning and fresh air systems shall automatically shut down, fire dampers shall close, non-fire power shall be cut off, and audible/visual alarms shall activate
- During discharge testing, measure nozzle discharge time and piping network pressure to verify compliance with design requirements
- After testing, reset the system and verify that all components return to normal
8.4.4 Emergency Lighting and Evacuation Signs
- Emergency lighting fixtures shall be installed in compliant positions and shall automatically illuminate upon power failure
- Evacuation sign indicators shall be correctly installed with clear directional indications
- Emergency lighting duration shall be ≥30 minutes
- Minimum floor illuminance shall be ≥1.0lx
8.5 Fire Protection Linkage Testing
- Simulate a fire incident and verify that fire detector alarms, audible/visual alarm activation, air conditioning shutdown, fresh air system closure, non-fire power disconnection, and gas suppression delayed activation are correctly executed in logical sequence
- Verify that the signal interface between the fire protection system and the EPMS system is normal, and that alarm information can be uploaded to the monitoring platform
- Test fire telephone call quality to ensure fire communication is unobstructed
- All linkage tests shall be documented in detail
Chapter 9 Environment and Power Monitoring System Installation and Commissioning
9.1 System Overview
The machine room environment and power monitoring system (EPMS) is the intelligent management core of the containerized machine room. Through various sensors and acquisition devices, it provides comprehensive real-time monitoring of power distribution, UPS, batteries, air conditioning, temperature and humidity, water leakage, smoke, access control, and video surveillance within the machine room, enabling data collection, status display, abnormal alarm, historical records, and remote management functions.
The system adopts a layered distributed architecture consisting of the on-site acquisition layer, transmission layer, and monitoring management layer. It supports local monitoring and remote Web access, can connect to higher-level centralized monitoring platforms, and enables unattended management.
9.2 Main Equipment Installation
9.2.1 Monitoring Host Installation
- The EPMS host shall be installed in a standard rack and securely fixed
- The host shall be powered by UPS to ensure normal operation during power failure
- The host shall be reliably grounded with strong anti-interference capability
- Wiring between the host and each acquisition module and sensor shall be correct
- Network interfaces shall be properly connected with correct IP address configuration
9.2.2 Environmental Sensor Installation
- Temperature and humidity sensors: evenly distributed in the machine room at key locations including the cabinet air intake side, cold/hot aisles, and air conditioning return air outlets, installed at a height of 1.8~2.0m
- Water leak detection sensors: arranged around air conditioning units, beneath water pipes, and inside the machine room door threshold; positioning-type leak detection cables shall be laid along areas prone to leakage
- Smoke detectors: shared with or independently configured from the fire protection system, installed on the ceiling
- Infrared detectors: installed near entrances/exits to monitor personnel intrusion
- All sensors shall be firmly installed at accurate locations to facilitate data collection
9.2.3 Power Equipment Acquisition
- Power distribution cabinet monitoring: install power meters and current transformers to monitor voltage, current, power, and electrical energy parameters
- UPS monitoring: connect to the monitoring system through the UPS intelligent communication interface to monitor UPS operating status, parameters, and alarms
- Battery monitoring: install battery monitoring modules to monitor individual cell voltage, total voltage, internal resistance, and temperature
- Air conditioning monitoring: connect through the air conditioning communication interface to monitor operating status, temperature and humidity, and fault alarms
- All acquisition equipment shall be correctly wired with matched communication protocols
9.2.4 Security System Installation
- Access control system: install access control controllers and card readers at machine room doors, supporting card swipe and password entry methods
- Video surveillance: install network cameras covering the main areas of the machine room with clear image quality
- Camera installation: proper angle, secure fixing, and unobstructed field of view
- Network video recorders shall be installed in racks, with storage capacity meeting video retention requirements
9.3 Cabling and Wiring
- Sensor signal lines shall use shielded cables to reduce electromagnetic interference
- All cables shall be routed through conduit or along cable trays, neatly arranged with clear labeling
- Power and low-voltage cables shall be routed separately with spacing complying with applicable codes
- Terminal connections shall be crimped securely, with the shield layer grounded at one end only
- Both ends of all cables shall be permanently labeled for easy maintenance and inspection
9.4 System Commissioning
9.4.1 Hardware Commissioning
- Power on the monitoring system and verify that the status indicators of each device are normal
- Verify that communication with each acquisition module is normal and no devices are offline
- Verify one by one that sensor data acquisition is accurate and values are reasonable
- Verify that access control card readers, door locks, and exit buttons operate normally
- Verify video surveillance image quality, PTZ control, and recording functions
9.4.2 Software Commissioning
- Install the monitoring system software and configure system parameters
- Add all monitored devices and configure device addresses and communication parameters
- Create the machine room floor plan monitoring view, visually displaying equipment locations and status
- Set alarm thresholds: temperature upper/lower limits, humidity upper/lower limits, voltage upper/lower limits, current upper limit, etc.
- Set alarm notification methods: local audible/visual alarm, SMS alarm, email alarm, popup alarm, etc.
- Configure user permissions and set up operator accounts at different authority levels
- Configure historical data storage policies and report generation functions
9.4.3 Functional Testing
- Data acquisition test: verify that all monitored parameters have accurate ranges and normal refresh rates
- Alarm function test: simulate various alarm conditions to verify accurate alarm triggering and timely notification
- High-temperature alarm: use a heat gun to simulate high temperature and verify system alarm
- Water leak alarm: drip water to simulate leakage and verify leak alarm and location detection
- Access control alarm: test unauthorized entry and door magnetic alarm
- Equipment fault alarm: simulate equipment failure and verify alarm reporting
- Linkage function test:
- High-temperature linkage: automatically increase air conditioning cooling capacity when temperature exceeds limits
- Water leak linkage: automatically close corresponding water pipe valves upon leakage
- Fire linkage: automatically unlock access control and start video recording upon fire alarm
- Remote access test: access the monitoring platform via LAN/Internet to verify normal functionality
- Data recording test: verify historical data storage, query, curve display, and report export functions
- Power interruption continuity test: disconnect mains power; the system shall continue normal operation under UPS power with no data loss
9.5 System Integration Commissioning
- Integrate and commission the EPMS with the power distribution, cooling, fire protection, and other subsystems to ensure normal data exchange
- Verify that all alarm points are fully configured with no omissions
- Verify the alarm escalation mechanism; different alarm levels shall correspond to different handling procedures
- Test system stability with continuous operation for 72 hours without abnormalities
Chapter 10 Structured Cabling System Installation and Commissioning
10.1 System Overview
The structured cabling system is the information transmission infrastructure of the containerized machine room. It adopts a structured cabling design supporting data, voice, video, and other applications to meet the network connection requirements of IT equipment. The system consists of the work area subsystem, horizontal subsystem, administration subsystem, and equipment room subsystem.
The standard configuration adopts Category 6 unshielded/shielded cabling supporting Gigabit Ethernet transmission, upgradeable to 10-Gigabit. Fiber optic cabling adopts OM3/OM4 10-Gigabit multimode fiber or single-mode fiber to meet high-speed backbone transmission requirements.
10.2 Cabinet and Rack Installation
- Network cabinets and server cabinets shall be positioned and installed according to the floor plan layout
- Cabinets shall be fixed to floor supports beneath the anti-static flooring, with secure stability
- Cabinet verticality deviation shall be ≤1‰; the gap between adjacent cabinets shall be ≤2mm, with flush panel alignment
- Cabinets shall be reliably grounded with grounding resistance meeting requirements
- Cabinet labeling shall be clear with accurate numbering
- Cable managers, patch panels, switches, and other equipment shall be installed inside cabinets with a rational layout
10.3 Cable Installation
10.3.1 Twisted Pair Cable Installation
- Category 6 twisted pair cable specifications and models shall conform to design requirements, with performance meeting the TIA/EIA 568-C.2 standard
- Inspect cables for intact appearance before installation, free of damage or kinks
- Cables shall be routed along cable trays or under the floor, neatly arranged with uniform bundling spacing
- Cable bend radius shall be ≥8 times the cable diameter, avoiding 90° right-angle bends
- Horizontal cabling length shall not exceed 90m, with total channel length not exceeding 100m
- Sufficient cable length shall be reserved at both ends: 1~1.5m reserved at the cabinet end and 0.3~0.5m at the work area end
- Cables shall be labeled with consistent numbering at both ends
- Keep distance from strong current interference sources, with spacing from power cables complying with applicable codes
10.3.2 Fiber Optic Cable Installation
- Fiber optic specifications and models shall conform to design requirements, with accurate single-mode/multimode type and fiber count
- Tension during fiber optic cable installation shall be controlled within allowable limits to avoid over-stretching
- Fiber optic cable bend radius shall be ≥15 times the cable diameter, and ≥20 times during construction
- Fiber optic cables shall be protected when routed through conduit to avoid scratching the outer sheath
- Sufficient slack shall be reserved at both ends of fiber optic cables for splicing and maintenance
- Fiber optic cables shall be labeled with fiber count, routing, and sequence numbers
10.4 Termination and Installation
10.4.1 Patch Panel Termination
- Category 6 patch panels shall be installed in standard U positions in the cabinet and firmly fixed
- Cable termination shall follow the T568A or T568B wiring sequence, with a uniform standard
- Termination workmanship shall meet requirements, with proper punch-down and good contact
- The untwisting length of twisted pairs shall meet Category 6 standards to reduce crosstalk
- Patch panel labels shall be clear, indicating port numbers and corresponding outlet locations
- Cable management shall be neat with aesthetically pleasing bundling, and patch cord insertion/removal shall be smooth
10.4.2 Fiber Optic Splicing
- Fiber optic splicing shall be performed by professional personnel using high-precision fusion splicers
- Fiber end faces shall be prepared flat and clean before splicing
- Splicing loss shall be ≤0.3dB per splice, with average loss ≤0.15dB
- Splice points shall be protected with heat-shrink sleeves, with neat fiber coil storage
- Fiber optic patch panels shall be securely installed with couplers properly seated
- Fiber optic patch cords shall be clearly labeled, with appropriate length and compliant bend radius
10.5 System Testing
10.5.1 Twisted Pair Testing
- Use a Category 6 cable certification tester for full performance testing
- Test parameters include: wire map, length, attenuation, near-end crosstalk (NEXT), attenuation-to-crosstalk ratio (ACR), return loss, delay, and delay skew
- All parameters shall meet Category 6 standard requirements
- Points that fail testing shall be investigated, re-terminated, or the cable replaced
- Generate test reports as acceptance documentation
10.5.2 Fiber Optic Testing
- Use an optical time-domain reflectometer (OTDR) to test fiber link loss and length
- Use an optical power meter and light source to test end-to-end attenuation
- Multimode fiber attenuation at 850nm wavelength ≤3.5dB/km, at 1300nm ≤1.5dB/km
- Single-mode fiber attenuation at 1310nm wavelength ≤0.4dB/km, at 1550nm ≤0.3dB/km
- Verify that splice point and connector losses are within allowable ranges
- Generate fiber optic test reports
10.6 Network Equipment Commissioning
- Switches, routers, and other network equipment shall be rack-mounted and securely fixed
- Power on equipment for self-diagnosis and verify normal operating status
- Configure equipment parameters according to design: IP addresses, VLAN partitioning, port configuration, routing configuration, etc.
- Conduct network connectivity tests to verify normal network connectivity at all points
- Conduct bandwidth and performance tests to verify design requirements are met
- Configure network security policies, including access control and port security
Chapter 11 Grounding and Lightning Protection System
11.1 System Overview
The grounding and lightning protection system is a critical system for ensuring electrical safety and stable equipment operation in the containerized machine room. It includes lightning protection, AC working grounding, safety protection grounding, DC working grounding, and anti-static grounding. A combined grounding method is adopted, sharing a common grounding electrode, with a grounding resistance of ≤4Ω.
The system design follows GB 50343-2012 “Technical Code for Protection of Electronic Information System Against Lightning.” Multi-level lightning protection is provided to effectively protect equipment from lightning overvoltage and switching overvoltage damage.
11.2 Grounding System Installation
11.2.1 Grounding Electrode Construction
- Grounding electrodes shall use galvanized angle steel or galvanized steel pipe, 2.5m in length, driven vertically into the ground
- The spacing between grounding electrodes shall be ≥5m, with the quantity determined by grounding resistance requirements
- Electrodes shall be connected with galvanized flat steel, welded securely
- Weld joints shall receive anti-corrosion treatment with asphalt paint coating
- After the grounding grid construction is completed, measure the grounding resistance to meet the ≤4Ω requirement
- If the grounding resistance does not meet requirements, measures such as adding electrodes, replacing soil, or adding resistance-reducing agents shall be adopted
11.2.2 Indoor Grounding System
- A ring-type grounding copper busbar shall be installed in the machine room, using 30×3mm or 40×4mm copper busbar
- The grounding copper busbar shall be installed along the walls around the machine room at a height of 0.3m, firmly fixed
- Busbar connections shall use tin-plated bolted connections, with tin-plated contact surfaces to ensure good conductivity
- All equipment metal housings, cabinets, racks, metal cable trays, and metal pipes shall be reliably grounded
- Anti-static floor supports shall be reliably connected to the grounding system
- Grounding down conductors shall use multi-strand copper core cables, routed from the indoor grounding busbar to the outdoor grounding grid
- Each cabinet shall have an independent grounding wire; daisy-chain grounding is prohibited
11.3 Lightning Protection System Installation
11.3.1 Power Supply Lightning Protection
- Level 1 protection: install a Class B power surge protective device (SPD) at the mains power incoming point, with a discharge capacity of ≥60kA
- Level 2 protection: install a Class C SPD at the UPS input or in the power distribution cabinet, with a discharge capacity of ≥40kA
- Level 3 protection: install a Class D SPD at the front end of critical equipment, with a discharge capacity of ≥20kA
- SPDs shall be firmly installed with correct wiring; phase, neutral, and ground conductors shall be correctly matched
- SPD grounding wires shall be as short and straight as possible, with a length of ≤0.5m
- SPDs shall be equipped with failure indicators and remote signaling contacts connected to the EPMS
11.3.2 Signal Lightning Protection
- Network signal SPDs shall be installed at network cable entry points
- The metallic strength member of communication fiber optic cables shall be reliably grounded
- Control lines and signal lines shall be fitted with appropriate signal SPDs as required
- Signal SPDs shall be installed at the equipment line input end, connected in series
- SPDs shall be reliably grounded with grounding resistance meeting requirements
11.3.3 Equipotential Bonding
- All metal components, equipment housings, pipelines, and shields in the machine room shall be equipotentially bonded
- Metal pipes entering/exiting the machine room and cable metal sheaths shall be connected to the grounding system at the entry point
- The container metal enclosure shall be reliably connected to the grounding system at multiple points
- Different grounding systems shall be connected through equipotential bonding devices to prevent potential difference back-strike
11.4 System Testing
- Grounding resistance test: use a ground resistance tester to measure the combined grounding resistance; ≤4Ω is acceptable
- Equipotential test: measure the potential difference between different metal components; ≤0.1V is acceptable
- SPD performance test: verify SPD status indicators are normal, and use an SPD tester to verify performance
- Insulation test: insulation resistance between live parts and grounded parts shall be ≥2MΩ
- All test data shall be recorded and archived as acceptance documentation
Chapter 12 Electromagnetic Shielding System (Optional)
12.1 System Overview
For containerized machine rooms with electromagnetic protection requirements, an electromagnetic shielding system is configured to effectively suppress external electromagnetic interference while preventing internal information electromagnetic leakage. Shielding effectiveness is classified as Class C (≥60dB), Class B (≥80dB), and Class A (≥100dB) based on requirements.
The shielding system consists of a shielding enclosure, shielding door, ventilation waveguide windows, power filters, signal filters, and waveguide tubes, forming a continuous and complete electromagnetic shielding space.
12.2 Shielding Enclosure Installation
- The shielding enclosure shall use high-quality cold-rolled steel plates with welded or modular construction
- Steel plate welding shall use continuous full welding, with smooth weld seams free of porosity and cold welding
- All joints shall receive conductive treatment to ensure electrical continuity
- The shielding enclosure shall be electrically insulated from the container body
- The inner surface of the shielding enclosure shall receive anti-corrosion treatment; the outer surface may receive decorative treatment
12.3 Shielding Components Installation
12.3.1 Shielding Door
- The shielding door shall adopt a knife-edge or leaf-spring type structure, with flexible opening/closing and reliable sealing
- The door frame shall be securely welded to the shielding enclosure, with good contact surface conductivity
- Conductive spring fingers around the door leaf shall be complete with uniform contact pressure
- The door locking mechanism shall be reliable, with stable shielding performance after locking
- The shielding door shall be properly grounded
12.3.2 Ventilation Waveguide Windows
- Ventilation waveguide windows shall adopt honeycomb-type waveguide structures, with ventilation volume and shielding effectiveness meeting design requirements
- Waveguide windows shall be fully welded to the shielding enclosure around the perimeter with no conductive gaps
- Waveguide window surfaces shall receive anti-corrosion treatment
- Dust filter screens shall be installed on the outside of waveguide windows
12.3.3 Filters
- Power filters shall be installed on the shielding wall, with input on the non-shielded side and output on the shielded side
- Filter flanges shall have good contact with the shielding body with conductive sealing
- Filter input and output cables shall be routed separately to avoid coupling
- Signal filters shall be selected based on signal type, with installation methods similar to power filters
- Filter housings shall be reliably grounded
12.3.4 Waveguide Tubes
- Waveguide tubes shall be installed where fiber optic cables, air conditioning piping, etc., penetrate the shielding enclosure
- Waveguide tubes shall be welded and sealed to the shielding enclosure
- The length-to-diameter ratio of waveguide tubes shall meet cutoff waveguide requirements
- Cables inside the tubes shall receive shielding treatment
12.4 Shielding Effectiveness Testing
- After installation of the shielding system is complete, shielding effectiveness testing shall be conducted
- Tests shall be performed at different frequency points per applicable standards, including magnetic field, electric field, and plane wave
- Test points shall cover all areas of the shielded room, including corners, doors, windows, wall penetrations, and other weak points
- Test results shall meet the design shielding level requirements
- If results fail, leak points shall be identified and corrected until compliance is achieved
Chapter 13 System Integration Commissioning and Overall Testing
13.1 Pre-Integration Preparation
- Standalone commissioning of all subsystems shall be completed and acceptance criteria met
- All equipment shall be in normal standby status
- A detailed integration commissioning plan and test schedule shall be developed
- Test instruments, tools, and record forms shall be prepared
- Technical personnel of all disciplines shall be in place with clearly defined responsibilities
- Site safety measures and emergency response plans shall be confirmed in place
13.2 System Linkage Commissioning
13.2.1 Power Distribution and Subsystem Linkage
- Simulate mains power interruption; the UPS shall automatically switch to battery power. Verify that air conditioning, monitoring, fire protection, and other systems operate normally
- Simulate mains power restoration; the UPS shall switch back to mains mode with all systems operating normally
- Test UPS overload and fault transfer to bypass, verifying the operating status of all systems
- Test power distribution system protection operations, verifying correct coordination between upstream and downstream protection devices
- Verify power management functions and accurate energy metering for each circuit
13.2.2 Cooling and Environmental System Linkage
- Set different ambient temperature conditions to test automatic air conditioning regulation
- Test air conditioning linkage with temperature and humidity sensors; control accuracy shall meet requirements
- Test that when one air conditioning unit fails, the standby unit automatically starts and takes over the load
- Test filter clogging alarms and automatic fan speed regulation
- Test high-temperature alarms linked with forced cooling of air conditioning
13.2.3 Fire Protection and Subsystem Linkage
- Simulate a fire alarm and verify that the following linkage actions execute in sequence:
- Audible/visual alarm activation
- Air conditioning and fresh air systems automatically shut down
- Non-fire power supply automatically disconnected
- Access control system automatically unlocks
- Video surveillance automatically starts recording
- Gas fire suppression activates with delay
- Test fire alarm signal upload to the EPMS platform, ensuring accurate and timely alarm information
- Test system reset and restoration procedures after fire suppression
13.2.4 EPMS Comprehensive Linkage
- Verify comprehensive monitoring coverage of all subsystems by the EPMS
- Test classified alarm processing and notification mechanisms
- Test remote control functions: remote on/off of air conditioning, remote switching of UPS operating modes, etc.
- Test the accuracy and timeliness of linkage strategy execution
- Test big data analysis and energy consumption statistics functions
13.3 Overall Performance Testing
13.3.1 Full Load Operation Test
- Use dummy loads to simulate full IT equipment load at 100% load rate
- Operate continuously for 72 hours, monitoring changes in various parameters
- Monitoring items include:
- Temperature and humidity changes in each machine room area
- Power distribution system voltage, current, power, and temperature rise
- Air conditioning system operating parameters and cooling effectiveness
- Operating status of all equipment and presence of abnormal alarms
- PUE calculation and energy consumption analysis
- The test passes if all systems operate stably throughout the test period with no fault shutdowns
13.3.2 Environmental Parameter Testing
- Temperature uniformity: arrange 9 or more measurement points in the machine room; temperature deviation at full load shall be ≤2℃
- Humidity uniformity: relative humidity deviation shall be ≤5%RH
- Cleanliness testing: use a particle counter; 0.5μm particle count shall be ≤18,000 particles/liter
- Noise testing: ≤65dB(A) in the machine room work area; ≤75dB(A) at 1m outside the machine room
- Static voltage testing: static voltage inside the machine room shall be ≤100V
13.3.3 Reliability Testing
- Dual power supply transfer test: perform 10 mains power transfer operations; IT load shall experience zero interruption during transfers
- N+1 redundancy test: with a single air conditioning unit or single UPS fault, the system shall still meet full-load operation requirements
- Continuous operation test: 72-hour full-load continuous operation without abnormalities
- Fault recovery test: simulate fault clearance and verify automatic system recovery functions
13.4 PUE Testing and Energy Efficiency Evaluation
- Measure total machine room power consumption and IT equipment power consumption
- Calculate power usage effectiveness: PUE = Total Energy Consumption / IT Equipment Energy Consumption
- PUE testing at different load rates: 25%, 50%, 75%, and 100% load
- Analyze energy consumption composition and evaluate energy-saving effectiveness
- Provide optimization recommendations to further improve energy efficiency
Chapter 14 Acceptance Specifications and Delivery
14.1 Acceptance Basis
- GB/T 36448-2018 “General Specification for Container Data Centers”
- GB 50462-2024 “Standard for Construction and Acceptance of Data Center Infrastructure”
- GB 50174-2017 “Code for Design of Data Centers”
- Project design drawings and technical agreements
- Product factory inspection standards
- Relevant requirements of this installation and commissioning manual
14.2 Acceptance Organization
- Acceptance shall be organized by the construction unit, with the participation of the supervision unit, construction unit, and equipment supplier
- An acceptance team shall be formed with clearly defined responsibilities for each member
- The construction unit shall submit complete completion documentation before acceptance
- An acceptance plan shall be developed, determining the acceptance items, methods, and standards
14.3 Acceptance Content
14.3.1 Appearance and Structure Acceptance
- The container body shall be intact with no deformation, impact damage, corrosion, or coating peeling
- Doors and windows shall open/close flexibly with good sealing
- Interior finishes shall be flat, aesthetically pleasing, free of damage and stains
- Anti-static flooring shall be laid flat with uniform gaps and no warping
- Equipment shall be installed neatly and securely with clear labeling
- Cables shall be routed neatly, bundled aesthetically, and completely labeled
- All types of labels and nameplates shall be complete, clear, and standardized
14.3.2 Subsystem Functional Acceptance
Power distribution system:
- Dual mains power transfer operates normally with reliable ATS operation
- All UPS functions are normal with transfer time meeting requirements
- Battery capacity meets targets with discharge time meeting design requirements
- All distribution circuits operate normally with reliable protection functions
- Grounding resistance and insulation resistance meet requirements
Cooling system:
- Air conditioning cooling, heating, humidification, and dehumidification functions operate normally
- Temperature and humidity control accuracy meets requirements
- N+1 redundancy transfer operates normally
- Airflow distribution is rational with uniform machine room temperature
- Condensate drainage is unobstructed with no leakage
Fire protection system:
- Fire detectors provide accurate alarms
- Gas fire suppression system operates reliably
- Linkage logic is correct
- Emergency lighting and evacuation signs operate normally
EPMS:
- All monitored parameters have accurate ranges
- Alarm functions are comprehensive with timely notification
- Linkage control is accurate
- Remote access operates normally
- Data recording and reporting functions are complete
Structured cabling system:
- All cabling tests pass
- Network connectivity is good
- Transmission performance meets requirements
- Labeling is complete and clear
Grounding and lightning protection system:
- Grounding resistance ≤4Ω
- All levels of SPDs are correctly installed
- Equipotential bonding is reliable
14.3.3 Overall Performance Acceptance
- 72-hour full-load operation test passes
- Environmental parameters meet Class A data center standards
- System redundancy functions verified
- PUE meets design requirements
- Safety protection performance meets requirements
14.4 Acceptance Procedure
- Construction unit self-inspection: upon completion of construction, the construction unit shall conduct a comprehensive self-inspection and rectify non-compliant items
- Factory acceptance: the manufacturer shall conduct factory acceptance and on-site commissioning acceptance
- Pre-completion acceptance: the supervision unit shall organize pre-acceptance and issue rectification opinions
- Formal acceptance: the construction unit shall organize formal completion acceptance
- After acceptance passes, sign the acceptance report and complete handover procedures
- If acceptance fails, rectify within a specified period and re-accept
14.5 Completion Documentation Delivery
Upon successful acceptance, the following completion documentation shall be delivered to the construction unit:
- Completion acceptance report
- As-built drawings (including floor plan, system diagrams, wiring diagrams, etc.)
- Equipment list and packing lists
- Product certificates of conformity and factory inspection reports
- System test records and commissioning reports for each system
- Concealed works acceptance records
- Material and equipment incoming inspection records
- Design change and engineering negotiation records
- Equipment user manuals and maintenance handbooks
- Spare parts list and special tools
- Training records
14.6 Personnel Training
- Manufacturer technical personnel shall conduct operational training for the owner’s operations and maintenance personnel
- Training content includes: system principles, equipment operation, daily inspection, maintenance, and common fault handling
- Training methods: theoretical instruction + on-site practical operation
- Assessment shall be conducted after training to ensure operations and maintenance personnel master basic operation and maintenance skills
- Training materials and operation manuals shall be provided
Chapter 15 Daily Operation and Maintenance
15.1 Operation and Maintenance Management System
15.1.1 Personnel Configuration
- A single-container machine room may be configured with 1 part-time operations and maintenance (O&M) personnel; multi-container clusters shall be configured with a dedicated O&M team
- O&M personnel shall receive professional training and be familiar with the principles and operation of all machine room systems
- A 7×24 hour duty system shall be established; when critical systems are unattended, reliance shall be placed on remote monitoring
- Regular O&M skills training and emergency drills shall be conducted
15.1.2 Management System
- Machine room access management system
- Daily inspection system
- Equipment maintenance system
- Duty and shift handover system
- Fault handling and emergency response plan
- Safety management system
- Archive and documentation management system
15.2 Daily Inspection
15.2.1 Daily Inspection
- View the operating status and alarm information of all equipment through the EPMS
- Check whether the machine room temperature and humidity are within the normal range
- Check UPS input/output voltage, current, and battery voltage
- Check air conditioning operating status for any alarms
- Check power distribution cabinets for abnormal heating or noise
- Verify the fire protection system status is normal
- Check water leak detection, access control, and video surveillance are normal
- Fill in the daily inspection record
15.2.2 Weekly Inspection
- Conduct on-site inspection of equipment operation, listening for abnormal sounds
- Check air conditioning filter cleanliness and clean when necessary
- Check battery appearance for electrolyte leakage or swelling
- Check all connection points for heating or oxidation
- Check machine room cleanliness and clean when necessary
- Verify fire suppression cylinder pressure is normal
- Test emergency lighting functions
- Compile weekly alarm records and analyze abnormal conditions
15.2.3 Monthly Inspection
- Measure battery cell voltages and record data
- Check grounding system connections
- Check SPD status indicators
- Clean dust from equipment surfaces
- Check cable labels for completeness and clarity
- Check door/window sealing and waterproofing
- Test access control and security system functions
- Conduct spot checks of system alarm functions
15.2.4 Quarterly Maintenance
- UPS battery discharge test (deep discharge of 30%)
- Deep cleaning of air conditioning systems, including evaporator and condenser coils
- Check air conditioning refrigerant pressure and replenish when necessary
- Check and tighten fasteners in power distribution cabinets
- Infrared temperature measurement of cable connections
- Fire protection system functional testing
- Grounding resistance testing
- Comprehensive EPMS inspection and calibration
15.2.5 Annual Maintenance
- Comprehensive UPS inspection and maintenance
- Battery capacity testing
- Air conditioning system overhaul, replacement of consumable parts
- Power distribution system outage maintenance, comprehensive cleaning and tightening
- Comprehensive fire protection system testing, extinguishing agent weighing inspection
- Comprehensive lightning protection system testing
- Shielding effectiveness testing (if installed)
- Overall performance testing and energy efficiency evaluation
15.3 Key Equipment Maintenance
15.3.1 UPS Maintenance
- Keep the UPS operating environment clean and dry, with an optimal temperature of 20~25℃
- Clean dust from the UPS interior regularly to maintain proper heat dissipation
- Conduct regular battery charge/discharge maintenance to extend battery life
- Avoid prolonged full-load operation of the UPS; a load rate of 50%~70% is recommended
- Regularly inspect and replace fans and other wear parts
- Regularly upgrade UPS firmware
15.3.2 Battery Maintenance
- Control battery ambient temperature at 20~25℃, avoiding high-temperature environments
- Keep battery surfaces clean and dry
- Regularly measure cell voltages and internal resistance to assess battery status
- Perform an equalizing charge every 3 months
- Conduct an annual capacity check discharge test
- Replace degraded batteries promptly to avoid affecting the entire bank
- Battery service life is generally 3~5 years; replace promptly upon expiration
15.3.3 Precision Air Conditioning Maintenance
- Air filters shall be cleaned or replaced regularly, generally every 1~3 months
- Evaporator and condenser coils shall be cleaned regularly to maintain heat exchange efficiency
- Regularly check refrigerant pressure and replenish any leakage
- Fan bearings shall be lubricated regularly
- Humidifier tanks shall be cleaned and descaled regularly
- Condensate drain lines shall be cleared regularly
- Temperature and humidity sensors shall be calibrated regularly
15.3.4 Fire Protection System Maintenance
- Check fire detector operating status monthly
- Check extinguishing agent cylinder pressure monthly
- Conduct manual alarm tests quarterly
- Conduct system simulated discharge tests annually
- Regularly inspect piping for corrosion or blockage
- Replace extinguishing agent promptly upon expiration of service life
15.4 Consumables and Spare Parts Management
- Establish an inventory of wear parts and consumables with clear replacement cycles
- Maintain reasonable stock levels of common spare parts to ensure rapid fault repair
- Main consumables include: air filters, humidifier tanks, fire suppression gas, batteries, fuses, etc.
- Maintain incoming/outgoing spare parts registration and conduct regular inventory counts
- Establish spare parts supply assurance mechanisms with suppliers
15.5 Archive Management
- Establish equipment ledgers recording equipment models, parameters, installation dates, and maintenance records
- Properly preserve all technical documentation, drawings, and manuals
- File inspection records, maintenance records, and fault records by category
- Regularly analyze operational data to optimize O&M strategies
- Digitally back up all archives for easy query and management
Chapter 16 Common Fault Troubleshooting and Handling
16.1 Common Power Distribution System Faults
16.1.1 UPS Faults
| Fault Phenomenon | Possible Cause | Handling Method |
|---|---|---|
| UPS cannot power on | Mains power not connected; DC fuse blown; power button faulty; control board faulty | Check mains input; check and replace fuse; check button; contact manufacturer for repair |
| Bypass output normal, inverter has no output | Inverter fault; driver board fault; output short-circuit protection | Check output load for short circuit; restart UPS; contact manufacturer for repair |
| Short battery mode runtime | Battery aging with insufficient capacity; battery not fully charged; excessive load | Check battery capacity; perform charging; reduce non-essential loads |
| Frequent UPS alarms | Large mains voltage fluctuations; large load fluctuations; fan fault; excessive temperature | Check mains quality; check load conditions; clean cooling system |
| Unbalanced current sharing in parallel system | Parallel communication failure; inconsistent parameter settings; one UPS unit faulty | Check parallel cables; calibrate parameters; repair faulty unit |
16.1.2 Distribution Faults
- Circuit breaker tripping: check for overload, short circuit, or leakage; reclose after fault clearance
- Poor contact heating: power off and tighten terminal connections, polish oxidized contact surfaces
- Phase sequence error: adjust input phase sequence
- Residual current device nuisance tripping: check line insulation, eliminate leakage points; replace aged protective devices
16.2 Common Cooling System Faults
16.2.1 Air Conditioning Not Cooling
- Power failure: check power supply, switch, and fuses
- Compressor not starting: check contactors, thermal protectors, and compressor motor
- Refrigerant leakage: check and repair leaks, replenish refrigerant
- Filter clogged: clean or replace filters
- Fan failure: check fan motor, capacitor, and belt
- Temperature sensor failure: replace sensor
- High-pressure protection: clean condenser, check fan speed, check for excessive refrigerant
16.2.2 Excessive Air Conditioning Noise
- Fan bearing wear: replace bearings
- Fan impeller dust accumulation causing imbalance: clean impeller and perform dynamic balancing
- Piping resonance: reinforce piping, add anti-vibration pads
- Compressor abnormal sound: check compressor mounting pads and internal valve plates
- Airflow whistling: adjust ducting to reduce airflow resistance
16.2.3 Water Leakage Faults
- Condensate drain blockage: clear the drain pipe, clean the collection pan
- Pipe joint leakage: tighten fittings, replace sealing gaskets
- Condensation due to poor insulation: repair insulation layer
- Humidifier leakage: check water level switches, replace aged seals
16.3 Common Fire Protection System Faults
- Detector false alarm: clean the detector, check for dust or moisture interference in the environment
- System fault indication: check for open or short circuits in wiring, and equipment faults
- Gas suppression accidental discharge: check linkage logic, inspect and repair solenoid valves
- Insufficient cylinder pressure: check for leakage and replenish extinguishing agent
- Audible/visual alarm not sounding: check wiring, fuses, and the alarm device itself
16.4 Common EPMS Faults
- Monitoring host offline: check power supply, network, and host faults
- Abnormal sensor data: check sensor wiring, calibrate, or replace sensors
- Alarm notification not received: check alarm settings and SMS/email gateway configuration
- Video has no image: check camera power, network, and camera faults
- Access control cannot open: check card readers, controllers, door locks, and permission settings
16.5 Fault Handling Principles
- Safety before repair: fault handling shall first ensure the safety of personnel and equipment
- External before internal: check external causes first, then disassemble equipment internals
- Power off before repair: electrical equipment repair must be performed with power disconnected
- Reset before troubleshooting: for software faults, first attempt restart/reset
- Backup before primary: when backup equipment is available, switch to backup first, then repair the faulty equipment
- Major faults shall be reported immediately, and emergency response plans activated
- After fault handling, records shall be made, causes analyzed, and preventive measures developed
Chapter 17 Safety Operating Procedures
17.1 General Safety Regulations
- All personnel entering the machine room must comply with the machine room safety management system
- Smoking is strictly prohibited in the machine room; carrying flammable and explosive materials is prohibited
- Working under the influence of alcohol or in a fatigued state is strictly prohibited
- Special operations must be performed by certified personnel; unlicensed operation is strictly prohibited
- Before work, check that tools and equipment are in good condition and safety protective equipment is fully worn
- Safety warning signs shall be set up in work areas; non-operating personnel are prohibited from entering
- At the end of each workday, cut off temporary power, clean up the site, and eliminate safety hazards
- In the event of a safety incident, report it immediately and activate emergency rescue procedures
17.2 Electrical Safety Regulations
- Electrical work must be performed by two or more persons, with one operator and one observer
- Power-off operations must strictly follow the “power off, verify de-energized, ground, tag out” procedure
- Live work must use insulated tools and insulated protective equipment
- Operating electrical equipment with wet hands is strictly prohibited
- Storing debris in power distribution cabinets and boxes is strictly prohibited
- Regularly inspect insulation of electrical lines and equipment; replace aged or damaged items promptly
- Outdoor electrical work is prohibited during thunderstorm weather
17.3 Work at Height Safety Regulations
- Work at height (above 2 meters) requires wearing a safety harness, with the lanyard secured above and used at a short length
- Tools for work at height shall be placed in tool bags; throwing tools or materials is strictly prohibited
- A warning zone shall be set up below work at height areas, prohibiting pedestrian passage
- Ladder work requires a dedicated person to hold the ladder, with a ladder angle of 60°~70° preferred
- Work at height shall be suspended during strong winds, rain/snow, heavy fog, and other severe weather
- Walking or working on unprotected structural members is strictly prohibited
17.4 Hot Work Safety Regulations
- Hot work such as welding and cutting requires a hot work permit approval procedure
- Before work, clear the area of flammable and explosive materials and equip fire extinguishing equipment
- A dedicated person shall monitor for fire during hot work, and inspect afterwards to confirm no residual ignition sources
- Pressure vessels and piping must be depressurized and purged before hot work
- Hot work in confined spaces requires adequate ventilation and combustible gas concentration testing
- Hot work in no-open-flame zones is strictly prohibited
17.5 Fire Protection Management Regulations
- Machine room fire protection facilities shall be inspected regularly to ensure they remain intact and effective
- Covering or moving fire protection equipment is strictly prohibited
- Evacuation routes shall remain unobstructed; storing debris is strictly prohibited
- Familiarize with fire extinguisher usage methods and evacuation routes
- Personnel are strictly prohibited from entering gas suppression zones after activation; entry is permitted only after ventilation
- Upon discovering a fire, report it immediately and activate the fire emergency plan
17.6 Emergency Handling
- Electric shock first aid: immediately cut off the power supply, or use an insulating object to separate the victim from the power source; perform rescue breathing and chest compressions; transport to medical facility
- Fire emergency: report the fire immediately, cut off power, use appropriate fire extinguishers, and evacuate in an orderly manner
- Fall from height: stop operations, provide first aid to the injured, avoid unnecessary movement, contact emergency services
- Water leak emergency: shut off the water source, relocate water-threatened equipment, drain and clean up, locate and repair the leak
- Power outage emergency: UPS supplies core equipment, activate emergency lighting, identify the cause of the outage and handle accordingly
Chapter 18 After-Sales Service and Technical Support
18.1 Warranty Service
- The standard warranty period for this product is 1 year. The warranty period for core components (compressors, UPS power modules, batteries) follows manufacturer standards
- Equipment faults caused by non-human factors during the warranty period shall be repaired or replaced free of charge
- The warranty period commences from the date of project completion acceptance
- Free technical support and system upgrade services are provided during the warranty period
18.2 Technical Support Services
- Service hotline: +86 13538869979 (also available on WeChat)
- Technical support: +86 13538869979
- Service hours: 7×24 hour all-day technical support
- Telephone support: response within 30 minutes of fault reporting, providing telephone technical guidance
- Remote support: remote assistance can be used for system commissioning and fault troubleshooting
- On-site service: for faults that cannot be resolved by telephone or remote means, technical engineers shall arrive on site within 48 hours (extended appropriately for remote areas)
- Regular follow-up: quarterly telephone follow-up during the warranty period, and annual on-site inspection
18.3 Value-Added Services
- Extended warranty: extended warranty services are available to extend equipment protection coverage
- O&M outsourcing: professional machine room O&M outsourcing services provided by a dedicated team for daily operations and maintenance
- Upgrades and retrofits: system expansion, equipment upgrades, and technical renovation services
- Technical consulting: data center planning and design, solution optimization, and other technical consulting services
- Training services: in-depth technical training to enhance customer O&M personnel skills
18.4 Contact Us
- Manufacturer: Guangdong Lain Intelligent Equipment Co., Ltd.
- Service hotline: +86 13538869979 (also available on WeChat)
- Technical support: +86 13538869979
- Company address: Zhongrun Industrial Park, No. 5 Huashan Road, Shilou Town, Panyu District, Guangzhou
- Official website: https://gdlain.com
Guangdong Lain Intelligent Equipment Co., Ltd. specializes in the R&D, production, and installation services of prefabricated container machine rooms, modular data centers, and intelligent shielded machine rooms. With rich industry experience and a professional technical team, the company is committed to providing customers with high-quality, high-efficiency, and high-reliability complete machine room solutions.
Prepared by: Guangdong Lain Intelligent Equipment Co., Ltd.
Version: V2.0
Release date: July 2026