Station Room Box and Reaction Box

Table of Contents

1. Cover / Document Information

– Document Title: Station Room Box and Reaction Box Technical Design Solution

– Prepared by: Guangzhou Lain Intelligent System Development Co., Ltd.

– Brand: KITOZER (Pioneer)

– Date: August 2026

– Version: V1.0

– Project Type: Technical design solution for Station Room Box and Reaction Box

2. Table of Contents Structure

1. Company Introduction

2. Project Overview

3. User Requirement Analysis

4. Overall Design Description

5. Detailed System Design and Product Technical Parameters

6. Project Quotation and Configuration List

7. Core Solution Advantages

8. Technical Q&A

9. Construction Schedule Plan

10. Construction Organization Plan

11. After-Sales Service System

12. Operation and Maintenance Training Plan

13. Typical Project Cases

14. SEO Optimization System and Website Backend Configuration

15. Contact Information

3. Company Introduction

3.1 Company Development Overview

Founded in 2002, Guangzhou Lain Intelligent System Development Co., Ltd. is a high-tech enterprise dedicated to the computer room construction and intelligent protection field for more than two decades, integrating R&D, production, sales, engineering implementation and after-sales service. The company focuses on innovative breakthroughs in electromagnetic shielding technology, modular computer room technology and computer room environmental monitoring technology, and has grown into a source manufacturer with core competitiveness in the domestic computer room construction field.

After more than twenty years of industry accumulation, the company has built a large-scale production and manufacturing base equipped with advanced CNC sheet metal processing equipment, automated spraying production lines and professional testing laboratories, with an annual production capacity of hundreds of sets of shielding computer rooms, integrated cabinets and micro-module products. The company’s service network covers all provinces and cities across the country, providing thousands of computer room construction and renovation services for customers in government, military, scientific research, finance and enterprise fields.

3.2 Core Business System

The company’s core business revolves around the full-lifecycle construction of computer rooms, forming four major product and service systems:

– Computer room EPC general contracting service: one-stop services from solution design, manufacturing, on-site construction to commissioning and acceptance, covering shielding computer rooms, IDC data rooms, modular computer rooms, container computer rooms and other types;

– Core equipment R&D and production: independently produces KITOZER brand series products, including shielding cabinets, shielding desks, consoles, integrated data cabinets, micro-module cold aisle cabinets, outdoor rainproof cabinets, etc., supporting non-standard customization;

– Computer room environmental monitoring system: provides full-element monitoring solutions for temperature and humidity, water leakage, access control, video, fire protection, UPS and power distribution, realizing intelligent and unattended O&M;

– Shielding and security protection products: shielding rooms, shielding doors and windows, anechoic chambers and related auxiliary materials, widely used in confidential, military and scientific research fields.

3.3 Brand and Qualification Honors

The core brand KITOZER (Pioneer) focuses on computer room equipment and shielding products, positioned as an “efficient, green, innovative and safe” solution provider. Products have passed multiple authoritative tests and comply with national and industry standards. The company holds multiple utility model patents and software copyrights, has been awarded high-tech enterprise qualification, and follows the ISO9001 quality management standard.

3.4 Core Competitive Advantages

1. Source production, controllable quality: own production base and professional processing equipment; core products independently produced with full-process quality control, providing more cost-effective solutions without intermediate links;

2. Customized design, matching needs: tailor-made solutions per site conditions, technical requirements, configuration and budget, with multiple design options provided free of charge;

3. Professional team, rich experience: a professional technical team of engineers and project managers with more than ten years of industry experience;

4. Quality after-sales, full guarantee: a 7×24 professional online service system with dedicated project follow-up from early coordination to later O&M.

4. Project Background and Objectives

4.1 Project Background

SCR denitrification systems need reliable electrical control: the station room controls the combustion-supporting fan (variable frequency), dosing/pumps and process logic, while the reaction zone needs field operation, status acquisition and protection. Dispersed devices, harsh environments and process interlock requirements demand a two-box electrical control system — a station-room control box (master) and a reaction control box (slave) — providing distribution protection, PLC logic, HMI, VFD drive, alarming and Ethernet coordination.

4.2 Project Objectives

Deliver the station-room box (total distribution, core logic, HMI, data aggregation, VFD drive of the combustion-supporting fan, communication) and the reaction box (field distribution, on-site operation, status collection, alarm, Ethernet link) as an integrated SCR electrical control solution: reliable graded distribution; hardware-level emergency stop and double interlock; modular PLC programs; layered touchscreen interfaces with permissions; lightning-earthing and EMC design; expandable IO and communication for plant integration.

4.3 Scope

Two wall-mounted electrical boxes (800x1000x250mm main + 700x900x200mm auxiliary each), full CHINT low-voltage distribution/protection/control components, Omron CP2E PLC with analog modules, Weinview touchscreens, Inovance VFD, tower signal lights, wiring/terminals, factory assembly, testing and delivery.

5. User Requirement Analysis

5.1 Functional Requirements

Graded distribution with isolation; motor protection (overload/short/phase-loss); classic self-locking start/stop with local/remote switching; hardware emergency stop independent of PLC; process interlocks (e.g. fan before ammonia dosing; over-temperature protection) with hardware + software dual assurance; status indication (DC24V safe voltage); audible/visual alarms with silence function; VFD speed control of the combustion-supporting fan; PLC logic with 15%+ spare IO; HMI with monitoring/process/parameter/alarm/history/operation screens and multi-level permissions; Ethernet communication between boxes and to the plant system.

5.2 Performance Requirements

Reliable operation in industrial environments; protection coordination (main -> branch -> signal); immunity to EMI; earthing <=4 ohm; stable DC24V control supply; clear labeling and documentation.

5.3 Compliance

GB/T 10963.1 / IEC 60898-1 (MCB), 3C certification; national electrical design and installation codes; safe voltage for signal circuits; industrial wiring standards.

6. Design Principles and Applicable Standards

6.1 Design Principles

Safety and reliability: graded protection isolating faults; hardware-level E-stop; dual interlock; industrial-grade components. Clarity and maintainability: clear logic, standard wiring, labeled conductors/terminals. EMC: filtering, surge protection, shielded analog cables, strong/weak separation, coil surge absorption, metal enclosure shielding. Expandability: spare IO, multiple protocol support, reserved box space. Economy: mature mainstream products at reasonable cost.

6.2 Applicable Standards

GB/T 10963.1 / IEC 60898-1 (MCB), GB 14048 series (contactors/motor protectors), GB/T 17626 (EMC), GB 50054 (distribution), GB 50303 (installation acceptance), industrial control design practice, plus customer requirements.

7. System Architecture and Working Principle

7.1 Two-Level Distributed Architecture

“Centralized monitoring + on-site control”: station-room box (master) — total distribution (main 4P C63 incoming, graded branches), PLC master (Omron CP2E-N30DR-A + 2 x CP1W-AD042 analog), Weinview 7″ (TK8072IP) + 10.1″ (MT8106IQ) HMI, Inovance MD290 VFD (combustion-supporting fan), contactors/relays, buttons/indicators/selectors, buzzer and tower light. Reaction box (slave) — incoming and branch breakers, PLC slave, contactors/relays, E-stop, illuminated buttons, indicators, tower light, Ethernet link to the master.

7.2 Main Circuit Design

Graded distribution: 4P C63 incoming (overload/short + isolation) -> 3P D32 power branch (motor high inrush), 2P C32A control/socket, 3P C16A small motor, 2P C10A control power, 2P C6A / 1P C6A signal branches; motor circuits with NS2-25 motor-protection breakers (overload/short/phase-loss); large power via CJX2 contactors for remote control; DC24V via NKY1 switch-mode supply; conductor sizing per load current with multi-strand copper; clear phase order and labels.

7.3 Secondary Control Circuit Design

Start/stop with “button + contactor + self-lock”; local/remote selector with interlock; E-stop NC contacts in series cutting control power (hardware level, independent of PLC); process interlocks with hardware + software dual assurance; DC24V status lamps with independent protection; alarm loop drives buzzer + tower light with silence button (light remains until cleared); wiring 0.75-1.5mm2 multi-strand with numbered sleeves; strong/weak separated.

7.4 PLC Control System

Controllers: Omron CP2E-N30DR-A (fast, rich IO, expandable, full communication) for both boxes; IO: DI for states/faults/buttons/limits; DO for contactors/relays/lamps/alarms; AI (CP1W-AD042, 4-ch) for 4-20mA/0-10V temperature/pressure/flow. Program: modular structure — main, initialization, motor control, analog processing, interlock, alarm, communication subroutines; fault tolerance for sensor/communication anomalies; 15%+ spare points.

7.5 HMI System

Weinview touchscreens with layered screens: main monitoring, process flow (dynamic), parameter setting (protected), alarm (real-time + history), historical data with trend curves, device operation (remote start/stop with second confirmation); multi-level permissions (operator view/operate, maintenance parameters/reset, admin program upload/download and system config).

7.6 Lightning, Earthing and EMC

Dedicated earthing busbar bonds all metal/equipment/frame; lead to plant grid <=4 ohm; analog shield single-end earthed; strong/weak earth separated to the common electrode; input filtering; SPDs on PLC/PSU power; shielded analog cables; separated strong/weak wiring; coil surge absorbers across contactor/relay coils; metal enclosure shielding.

8. Detailed Technical Design

8.1 Station-Room Control Box (Master)

Distribution (CHINT): 4P C63 incoming; 3P D32 power; 2P C32A x2 (control + socket); 3P C16A motor; 2P C10A control power; 2P C6A x4 + 1P C6A signal; NS2-25 4-6.3A + 9-14A motor protectors with NS2-AE11 aux contacts; CJX2-0910 AC220V contactor + F4-11 aux; NKY1-S-120-24 DC24V/5A supply; 12 x JZX-22F(D)/2Z relays + CZY08A bases. Operation/indication: NP2-BS542 E-stop; 2 x NP2-BD21 selectors + BZ103 contact blocks; 3 green NP2-BA31 start, 3 red NP2-BA42 stop; ND16-22FS buzzer; NP2-BW35M1 yellow illuminated button; ND16-22D/2 power lamp; NY-505-3T/J three-tier tower light (R/Y/G magnetic); 2 blanking plugs. Cooling/structure: 150×150 AC220V axial fan + dust screen; 2 TSTW-M4 rail brackets. Terminals: 3 x UK-6N (10mm2 51A), 40 x UK-5N (4mm2 41A), 9 x D-UK3/10 partitions, 4 x USLKG5 earth, 2 x E-UK ends, 4 x ZB6 markers. Core/box: main box 800x1000x250 (mounting plate >=760×940) + auxiliary 700x900x200; Omron CP2E-N30DR-A; 2 x CP1W-AD042; Weinview TK8072IP 7″ + MT8106IQ 10.1″; DB9 male; Cat6a 1.5m cable; Inovance MD290T0.4G/0.7PB VFD.

8.2 Reaction Control Box (Slave)

Distribution: 4P C63 incoming; 3P D32 power; 2P C32A x2; 3P C16A motor; 2P C10A control; 2P C6A signal; NS2-25 4-6.3A + AE11; CJX2-0910; NKY1-S-120-24; 12 relays + bases. Operation: NP2-BS542 E-stop; 2 x NP2-BW35M1 illuminated buttons; ND16-22D/2 power lamp; NY-505-3T/J tower light; 2 plugs. Structure: 4 TSTW-M4 brackets. Terminals: 6 x UK-6N, 32 x UK-5N, 7 partitions, 3 earth, 2 ends, 4 markers. Core/box: main 800x1000x250 + auxiliary 700x900x200; Omron CP2E-N30DR-A; 1 x CP1W-AD042; Cat6a cable.

8.3 Key Component Parameters

CHINT NXB-63 MCB: GB/T 10963.1 / IEC 60898-1, 3C; Ui 500V, Uimp 6kV, pollution 2, cat II/III; C-curve 5-10In / D-curve 10-16In; Icn/Ics 6kA; mechanical 20,000 / electrical 10,000 cycles; -5~+40 degC; DIN rail; <=25mm2 hard / 16mm2 soft; IP20; V0 housing. NS2-25 motor protector: overload/short/phase-loss protection per motor characteristics with aux contact for status. CJX2-0910 contactor: AC220V coil, 9A, with F4-11 aux. NKY1-S-120-24: AC220V -> DC24V 5A switch-mode supply. JZX-22F(D)/2Z relay: DC24V 2Z. Omron CP2E-N30DR-A: small PLC with relay outputs, expandable, Ethernet. CP1W-AD042: 4-ch analog input. Weinview TK8072IP / MT8106IQ: 7″ / 10.1″ industrial touchscreens with permission management. Inovance MD290T0.4G/0.7PB: 0.4kW general-purpose VFD for the combustion-supporting fan. Boxes: cold-rolled steel electrostatic coating, wall-mount, with mounting plates.

9. Recommended Configuration and Preliminary Budget

9.1 Configuration Summary

Station-room box: distribution set (13 breakers + 2 motor protectors + aux), 1 contactor + 2 aux, DC24V supply, 12 relays/bases, operation set (E-stop, 2 selectors, 3+3 buttons, buzzer, illuminated button, power lamp, tower light), cooling set, terminals set, 2 boxes, PLC + 2 analog modules, 7″ + 10.1″ touchscreens, DB9, network cable, VFD. Reaction box: distribution set (9 breakers + motor protector + aux), contactor, supply, 12 relays/bases, operation set (E-stop, 2 illuminated buttons, power lamp, tower light), structure/terminals, 2 boxes, PLC + analog module, network cable. Services: factory assembly, wiring, inspection, packing, transport (Guangzhou Panyu delivery included), 13% VAT invoice; site installation/wiring/commissioning quoted separately.

9.2 Budget Notes

Price includes equipment, components, assembly, factory inspection, packing and transport with 13% VAT; tax-inclusive in RMB (CNY) only; drawings changes adjust the quote; on-site services negotiated separately.

10. Technical Specifications

10.1 System Specification Summary

Item Specification
Architecture Two-level distributed: station-room master box + reaction slave box over industrial Ethernet; master: distribution + PLC + HMI + VFD + alarms; slave: distribution + PLC + field operation + alarms
Distribution CHINT NXB-63 series (4P C63 incoming, 3P D32 power, 2P C32A x2, 3P C16A, 2P C10A, 2P C6A x4/1P C6A); NS2-25 motor protectors 4-6.3A/9-14A with AE11 aux; CJX2-0910 + F4-11; NKY1-S-120-24 DC24V/5A; JZX-22F(D)/2Z x12 + CZY08A bases; Icn/Ics 6kA; GB/T 10963.1, 3C
Secondary circuits Button+contactor+self-lock start/stop; local/remote selector interlock; hardware E-stop (NC series, PLC-independent); hardware + software interlocks; DC24V status lamps; buzzer + tower light with silence; numbered multi-strand wiring 0.75-1.5mm2; strong/weak separated
PLC Omron CP2E-N30DR-A x2 (master/slave), CP1W-AD042 analog modules (2 + 1, 4-ch each); modular programs (init, motor, analog, interlock, alarm, comm); 15%+ spare IO; fault tolerance
HMI Weinview TK8072IP 7″ + MT8106IQ 10.1″ (master); layered screens (monitor/process/parameters/alarm/history/operation); multi-level permissions; second-confirmation remote operation
VFD Inovance MD290T0.4G/0.7PB 0.4kW for the combustion-supporting fan; remote speed control via PLC/HMI
Alarms Buzzer ND16-22FS + NY-505-3T/J three-tier tower light (R/Y/G, magnetic) at both boxes; silence button; alarm records with timestamps on HMI
Earthing/EMC Dedicated earth busbar; plant grid <=4 ohm; analog shield single-end earthed; input filter + SPDs; shielded analog cables; coil surge absorbers; metal enclosure
Boxes Wall-mount cold-rolled steel electrostatic coating; main 800x1000x250mm (plate >=760×940) + auxiliary 700x900x200mm per box; axial fan 150mm + dust screen (master)
Delivery Factory assembly, wiring, inspection, packing, transport with 13% VAT (Guangzhou Panyu); site services quoted separately; spare IO for expansion; Ethernet to plant systems

10.2 Standards Compliance

GB/T 10963.1 / IEC 60898-1 (3C MCB), GB 14048 series (contactors/motor protectors), GB/T 17626 (EMC), GB 50054 (distribution), GB 50303 (installation); industrial wiring standards with clear labels.

11. Key Advantages and Customer Value

11.1 Reliable Graded Protection

Main -> branch -> signal staged breakers isolate faults locally; motor-protection breakers match load characteristics; hardware E-stop independent of PLC — safety without software dependency.

11.2 Clear Maintainable Design

Classic self-locking circuits, modular PLC subroutines, layered HMI, numbered conductors and terminals — fast commissioning and troubleshooting.

11.3 Strong Interlock and Safety

Process interlocks (fan-before-dosing, over-temperature) with hardware + software dual assurance; local/remote mode interlock; second-confirmation remote operation.

11.4 Industrial EMI Immunity

Input filtering, surge protection, shielded analog cabling, strong/weak separation, coil surge absorbers and metal enclosure — stable in harsh industrial environments.

11.5 Expandability

Spare IO and box space; multi-protocol communication; Ethernet to plant SCADA — future upgrades without replacement.

11.6 Cost-Effective Mature Products

CHINT, Omron, Weinview, Inovance mainstream industrial brands — reliable, well-supported, economical; factory-integrated delivery with 13% VAT.

12. Technical Q&A (50+ Items)

12.1 Product Selection

Q1: Why NXB-63 breakers?

A: CHINT’s next-generation terminal protection — GB/T 10963.1/IEC 60898-1, 3C certified, C/D curves, 6kA breaking, high reliability and economy — standard for industrial control boxes.

Q2: C vs D curve selection?

A: C (5-10In) for lighting/distribution/general loads; D (10-16In) for motors/transformers with high inrush — the 3P D32 power branch avoids nuisance tripping on motor start.

Q3: Why NS2-25 motor-protection breakers?

A: Integrated overload + short-circuit + phase-loss protection matched to motor characteristics, with aux contact for status feedback to the PLC.

Q4: Why Omron CP2E?

A: Fast execution, rich IO, expandable modules (CP1W-AD042 analog), full communication (Ethernet) — ideal small PLC for SCR control.

Q5: Why two touchscreens (7″ + 10.1″)?

A: 7″ for local machine-side operation, 10.1″ for monitoring/management — flexible deployment per operation needs.

Q6: Why the Inovance MD290 VFD?

A: Cost-effective general-purpose VFD (0.4kW) with reliable speed control for the combustion-supporting fan and communication to the PLC.

Q7: Why DC24V control voltage?

A: Safe voltage for lamps/relays/sensors — standard industrial practice, personnel-safe.

Q8: Why JZX-22F relays?

A: Standard DC24V 2Z relays with bases — universal, replaceable, with LED indication.

12.2 System Design

Q9: Two-level architecture benefits?

A: Centralized monitoring at the station room with on-site control at the reaction zone — local autonomy, fewer long cable runs, clear responsibility.

Q10: How is fault isolation achieved?

A: Graded breakers — a branch fault trips only its circuit; signal circuits separately protected.

Q11: How does the E-stop work?

A: NC contacts in series cut control power directly at hardware level — independent of PLC, immediate stop.

Q12: Interlock examples?

A: Fan must run before ammonia dosing; over-temperature triggers protection; both hardware (contactors) and software (PLC) interlocks.

Q13: Local/remote switching?

A: Selector switch with interlock prevents operation conflicts; local uses panel buttons, remote via HMI/PLC.

Q14: Analog signal handling?

A: CP1W-AD042 4-ch inputs (4-20mA/0-10V) with filtering, engineering conversion, range check and limit judgment in software.

Q15: HMI permissions?

A: Operator (view/operate), maintenance (parameters/reset), admin (program/system) — prevents unauthorized changes.

Q16: Alarm handling?

A: Buzzer + tower light with silence button (light remains); alarms recorded with time/point/description; history queryable.

Q17: Communication?

A: Industrial Ethernet between boxes and to plant systems; DB9 serial for engineering access.

Q18: Spare capacity?

A: >=15% spare IO points and reserved box space for future expansion.

12.3 Installation

Q19: Installation requirements?

A: Indoor dry ventilated position; wall-mount with proper fixing; earthing <=4 ohm; cable entries sealed; away from heat/moisture.

Q20: Cable routing?

A: Power and signal separated; shielded analog cables single-end earthed; numbered sleeves; bend radii per code.

Q21: Outage needed?

A: Installation coordinated with plant windows; live work by certified electricians per safety codes.

Q22: What tools are needed?

A: Standard electrician tools (screwdrivers, multimeter, crimpers, torque driver).

Q23: Is factory testing included?

A: Yes — full function test, insulation and continuity checks before delivery with records.

12.4 Commissioning and Operation

Q24: Commissioning steps?

A: Wiring check -> insulation test -> staged energization -> PLC download and IO verification -> HMI screens -> interlock and alarm drills -> VFD parameter setting and fan trial -> Ethernet communication -> 72h trial.

Q25: How are PLC programs delivered?

A: Structured modular source with documentation; backup provided; remote support for adjustments.

Q26: VFD parameter setting?

A: Per fan motor plate (voltage/current/frequency), acceleration/deceleration and control source configured via panel or software.

Q27: What if a sensor is abnormal?

A: Software fault tolerance: alarm, hold safe state, no mis-action.

Q28: How is the 72h trial run?

A: Continuous operation logging parameters; interlock drills; no abnormal alarms/heating before acceptance.

12.5 Maintenance

Q29: Daily maintenance?

A: Check indicators, alarms, fan operation, terminal heat; clean dust; keep door closed.

Q30: Periodic maintenance?

A: Quarterly terminal tightening and cleaning; half-yearly earthing check; yearly VFD/contact inspection and function drills.

Q31: Component life?

A: Breakers 10,000+ electrical cycles; contactors 1M+ mechanical; relays long life with LED; VFD per design life.

Q32: Spares?

A: Stocked breakers, relays, buttons, fuses; original CHINT/Omron parts with fast dispatch.

Q33: Is training provided?

A: Operation/maintenance training at delivery with manuals — covered in the project service.

12.6 Troubleshooting

Q34: Breaker trips on start?

A: Check for short circuit; verify curve selection (D for motors); check motor current vs setting.

Q35: Motor won’t start?

A: Check power, E-stop, selector mode, contactor coil voltage, PLC output, motor-protection state.

Q36: PLC not communicating?

A: Check IP/address, cable, port settings; ping test; serial parameters.

Q37: Analog reading wrong?

A: Check wiring/polarity, shield earthing, signal source, module range setting, calibration.

Q38: HMI no display?

A: Check 24V supply, cable, screen settings; reboot.

Q39: False alarms?

A: Check thresholds, wiring, coil surge absorbers, earthing; adjust debounce in software.

Q40: Fan speed abnormal?

A: Check VFD parameters, control signal, load, fault codes on the VFD display.

12.7 Service and Compliance

Q41: Warranty?

A: 12-month hardware warranty from acceptance; free repair/parts for non-human faults; lifetime support.

Q42: Response?

A: 7×24 hotline; 2h solution for general issues; 24h/48h on-site; spares stocked.

Q43: What documentation is delivered?

A: Electrical schematic, wiring diagrams, IO table, PLC program, HMI project, manuals, test reports, certificates.

Q44: Why choose the KITOZER/Lain solution?

A: Factory-integrated assembly with mainstream industrial brands; strict testing; full documentation; proven SCR/industrial deployments.

Q45: Can it integrate with the plant SCADA?

A: Yes — Ethernet/Modbus interfaces with documented protocols.

Q46: Is the box IP-rated for outdoor?

A: Standard indoor IP30-class boxes; outdoor IP54/IP65 options on request.

Q47: Expansion later?

A: Spare IO and box space; add modules and circuits without box replacement.

Q48: What makes it cost-effective?

A: Mature brand components, factory integration, 13% VAT invoiced, low maintenance and long life.

Q49: Customization?

A: Box size, IO counts, screens, VFD capacity and paint per requirements.

Q50: Acceptance standard?

A: Per scheme parameters and national codes — all functions tested, records signed before acceptance.

13. Construction Schedule

13.1 Overall Schedule

Factory-production project: standard total ~20 working days from drawing confirmation (adjustable per order volume):

No. Stage Days Main work Deliverable
1 Scheme/drawing confirmation 2 Requirements, electrical schematic, BOM confirmation Confirmed drawings
2 Procurement and fabrication 7 Component procurement and incoming QC; box fabrication/coating; plate machining Materials ready, boxes
3 Assembly and wiring 5 Component mounting; main/secondary wiring; terminals, labels; dressing Assembled boxes
4 Factory inspection 3 Insulation/continuity tests; staged power-on; PLC program load and IO verification; HMI screens; interlock/alarm drills; VFD trial; Ethernet test Test report, certificates
5 Packing and transport 2 Protective packing; logistics to Guangzhou Panyu site Delivered
6 Site support (optional) 1 Installation guidance/commissioning per agreement Commissioned

13.2 Schedule Assurance

Stocked standard components; parallel procurement/fabrication/software development; dedicated PM with daily progress; buffer for drawing changes; contingency spare materials.

14. Construction Organization and Quality/Safety Measures

14.1 Organization

PM (1): overall management, progress, quality, customer liaison. Electrical design engineer (1): schematics, IO allocation, technical support. Assembly team (2-3): mechanical/electrical assembly per drawings. Test engineer (1): factory inspection and commissioning. QC (1, part-time): process inspection and records. Safety officer (1, part-time): production safety.

14.2 Preparation

Technical: drawing review and disclosure; work instructions; test plan and forms. Materials: incoming inspection (model/spec/qty/certificates); tools calibrated (multimeter, megger, torque driver); PPE. Production: clean assembly area; anti-static measures for PLC/HMI handling.

14.3 Core Processes

Assembly: mount breakers/contactors/relays/terminals on rails per layout; PLC/HMI/VFD per drawings; strong/weak separation with troughs. Wiring: power conductors sized per load; multi-strand with numbered sleeves; torque-correct terminations; shields single-end earthed; dressing neat with ties. Inspection: visual check; continuity and insulation tests (>=0.5M ohm); staged energization (main -> branches -> control); PLC download and IO verification point by point; HMI screen verification; interlock and E-stop drills; alarm test with silence function; VFD parameter set and trial run; Ethernet communication between boxes verified.

14.4 Quality Control

Three-inspection (self/mutual/special) per process; key processes (wiring, earthing, PLC verification) with engineer sign-off; all tests recorded; unqualified rework before next stage; final factory report and certificates with the shipment.

14.5 Safety and Civilized Production

Certified electricians; two-person energization with supervision; lockout/tagout on test power; no smoking, extinguishers; tidy workstations with daily cleanup; ESD protection for sensitive components; safe handling and packing.

15. After-Sales Service

15.1 Warranty Commitment

12-month whole-project warranty from acceptance; free repair/parts for non-human faults (CHINT/Omron/Weinview/Inovance original components); lifetime technical support; optional extended warranty.

15.2 Response

7×24 hotline; general issues 2h solution (remote first); hardware faults on-site 24h urban / 48h provincial; spares stocked for rapid replacement.

15.3 In-Warranty Services

Fault repair/replacement; technical consultation; parameter optimization; software program adjustments; documentation updates.

15.4 Post-Warranty

Annual maintenance agreements; paid repair at cost; PLC/HMI program upgrades; expansion services (new circuits, modules, VFDs).

15.5 Service Flow

Report -> register -> remote diagnosis -> on-site repair with spares -> customer confirmation -> follow-up archive.

16. Training Plan

16.1 Training Objectives and Audience

Training objectives: through systematic training, enable management personnel to fully understand the system structure, working principles and performance characteristics, master daily operation methods and inspection/maintenance essentials, identify common faults and handle simple problems, ensuring safe, stable and long-term operation.

Training audience: management and O&M personnel designated by the client, recommended 2-3 persons with basic electrical and equipment knowledge.

16.2 Tiered Training Content System

Level 1: Basic operation training (1 day)

– Basic principles: system concepts, structure composition, performance indicators;

– Daily operation standards: correct operation of equipment, control and safety systems;

– Daily inspection contents: daily/weekly/monthly check items;

– Safety precautions: usage prohibitions and emergency handling procedures.

Level 2: Maintenance training (1 day)

– Detailed structure of each subsystem and working principles;

– Daily maintenance methods: cleaning, fastening checks, routine care;

– Common fault identification and simple handling;

– Emergency handling procedures for power failure, fire and equipment faults.

Level 3: Advanced management training (as needed)

– Performance influencing factors and how to avoid degradation;

– Upgrade and expansion knowledge and specification requirements;

– Relevant national standards interpretation.

16.3 Training Methods and Schedule

– Methods: combination of “theory explanation + on-site practice + Q&A interaction”;

– Schedule: training arranged at the completion acceptance stage, synchronized with handover, 2 days of intensive training total; time flexibly adjustable; a free repeat training session is provided for newly assigned personnel.

16.4 Training Assessment and Documentation Delivery

– Assessment: theory written test plus practical operation; training qualification certificates issued upon passing; supplementary training for those who fail;

– Documentation delivery: complete O&M documentation, including operation and maintenance manual, equipment manuals and certificates, completion drawings and hidden work records, test reports and after-sales service contact card, all bound into volumes.

17. Anonymous Typical Project Scenarios

All project scenarios below are anonymous, generalized examples provided for reference only. No real customer names, addresses or identifiable details are disclosed.

17.1 Industrial Boiler SCR Denitrification Control Project

Background. A plant’s boiler denitrification system needed reliable electrical control for the combustion-supporting fan (variable speed), ammonia dosing and reaction-zone devices with interlock protection.

Solution. Station-room master box (distribution, Omron PLC + analog modules, 7″/10.1″ touchscreens, Inovance VFD, alarms) and reaction slave box (PLC slave, E-stop, illuminated buttons, tower light) linked by Ethernet.

Results. Stable automatic control with hardware-level E-stop and dual interlocks; precise fan speed control; alarms with records; fast commissioning via modular programs — smooth acceptance and continuous operation.

17.2 Workshop Exhaust and Dosing Control Retrofit

Background. A workshop needed unified control of exhaust fans and chemical dosing pumps with local/remote operation.

Solution. Master-slave boxes with local/remote selectors, self-locking start/stop, status lamps and audible/visual alarms; PLC interlocks prevented dosing without exhaust.

Results. Clear two-level operation with conflict-free mode switching; fault isolation by graded breakers; maintenance-friendly numbered wiring; expanded later with spare IO without box replacement.

17.3 Small Industrial Control Cabinet Batch Supply

Background. An equipment manufacturer needed standardized control cabinets for its products with reliable protection and HMI.

Solution. Batch-supplied boxes with CHINT distribution, Omron PLC, Weinview HMI and factory-tested wiring per unified drawings.

Results. Consistent quality with factory inspection reports; rapid delivery; reduced field commissioning; strong after-sales with stocked spares.

18. SEO Optimization Section

All reference prices in this technical solution are in RMB (CNY) only and are for reference purposes; final quotation is subject to the confirmed configuration.

18.1 Keyword System

– Core keywords: technical design solution, system configuration, technical parameters, construction and O&M services;

– High-conversion long-tail keywords: design solution, configuration list, technical parameters, construction plan, after-sales service;

– Industry traffic keywords: system architecture, applicable standards, technical Q&A, project cases;

– Brand keywords: KITOZER, Guangzhou Lain.

18.2 SEO Tag System

– Title tag: the article title — Guangzhou Lain KITOZER;

– Meta description: Guangzhou Lain professionally provides complete technical design solutions with detailed configuration list, full-system product technical parameters, construction organization plan and after-sales service — source manufacturer customization, compliant performance, third-party testing supported;

– H1 tag: the article title;

– H2 tags: system design and product parameters, construction organization plan, after-sales service and training, engineering cases.

18.3 Internal Link Anchor Text

– Core anchor text: technical design solution, system construction;

– Long-tail anchor text: configuration list, technical parameters, construction plan;

– Related anchor text: shielding cabinet, micro-module cold aisle, integrated computer room, outdoor cabinet.

19. Official Contact Information

– Company Name: Guangzhou Lain Intelligent System Development Co., Ltd.

– Brand: KITOZER (Pioneer)

– Official Website: https://gdlain.com

– Tel: +86 139 2228 9957 (WeChat available), +86 185 2066 8845 (WeChat available)