Cold Aisle Containment Installation: Day-by-Day Field Report

A real-world KITOZER cold aisle containment deployment at a 42-rack data hall. This is what actually happens on site, day by day, and what to watch for.

Day 1: Site Survey and Layout Marking

Measure the existing rack rows. Check floor tile spacing – the containment profiles must align with tile joints for clean cable routing. Mark the ceiling height. KITOZER containment works with ceiling heights from 2600mm to 3200mm.

Day 2: Profile Mounting

Install the aluminum uprights on each end rack. Level them. The sliding ceiling tiles mount between the uprights. Fire-rated tiles auto-open at 68C and must connect to the building fire alarm signal.

Day 3: End Doors and Ceiling

Install automatic sliding doors at aisle ends. These open on approach and close within 5 seconds. Run power from the rack PDU. Test the fire alarm interlock – doors must fully open on alarm.

Day 4: Air Sealing and Testing

Seal gaps between racks with brush strips. Block all unused U positions with blanking panels. Run the CRAC units and verify cold aisle temperature stays at 18-22C while hot aisle runs at 35-38C. The PUE improvement should be measurable within the first 24 hours.

Typical project duration: 2-4 days per row. Contact +86 13922289957 for KITOZER containment installation planning and on-site support.