ToggleTechnical Design Solution for the 3m × 7m Integrated Living & Office Modular Station
Prepared by: Guangzhou Lain Intelligent System Development Co., Ltd.
Contact: Mr. Zhou
Tel: +86 139 2228 9957 (WhatsApp & WeChat)
Company Address: Huashan Road 5, Shilou Town, Panyu District, Guangzhou, Guangdong, China (Zhongrun Industrial Park, Chaotian District)
Date: July 2026
—
Table of Contents
Chapter 1 Company Profile
Chapter 2 Project Overview – 2.1 Construction Background | 2.2 Construction Objectives | 2.3 Applicable Scenarios | 2.4 Design Basis | 2.5 Key Technical Specifications
Chapter 3 User Demand Analysis – 3.1 Functional Space | 3.2 Structural Safety | 3.3 Exterior Appearance | 3.4 Environmental Adaptability | 3.5 Electrical & Plumbing Requirements | 3.6 Operation & Maintenance Management
Chapter 4 Overall Design Description – 4.1 Design Philosophy | 4.2 Exterior Design | 4.3 Interior Layout | 4.4 Overall Performance Specifications | 4.5 Design Execution Standard System
Chapter 5 Product Quotation & Configuration List – 5.1 Quotation Notes | 5.2 Itemized Quotation | 5.3 Optional Upgrade Configurations
Chapter 6 Main Steel Structure System Technical Parameters
Chapter 7 Roof Enclosure System Technical Parameters
Chapter 8 Wall Enclosure System Technical Parameters
Chapter 9 Door & Window System Technical Parameters
Chapter 10 Interior Decoration System Technical Parameters
Chapter 11 Electrical System Technical Parameters
Chapter 12 Water Supply & Drainage System Technical Parameters
Chapter 13 Office & Living Furniture System Technical Parameters
Chapter 14 HVAC & Ventilation System Technical Parameters
Chapter 15 Transport, Installation & Site Foundation Technical Parameters
Chapter 16 Core Advantages of the Solution
Chapter 17 Common Technical Q&A
Chapter 18 Construction Schedule
Chapter 19 Construction Organization Plan
Chapter 20 After-Sales Service System
Chapter 21 Technical Training Plan
Chapter 22 Typical Engineering Case Studies
Appendices
—
Chapter 1: Company Profile
Founded in 2002, Guangzhou Lain Intelligent System Development Co., Ltd. is a high-tech enterprise dedicated to the R&D, production and sales of data center construction, modular buildings and intelligent protection equipment. With more than two decades of deep industry experience, the company has accumulated robust technical expertise and extensive project delivery capabilities. Under its flagship brand KITOZER, the company has obtained dozens of product patents and industry qualification certifications, with products and services widely applied across government affairs, communications, power, transportation, construction, cultural tourism and other sectors — earning recognition and trust from thousands of enterprise clients both domestically and internationally.
The company’s core product portfolio encompasses IDC data center construction, shielded computer room engineering, integrated data cabinets, micro-module cold-aisle cabinets, outdoor intelligent cabinets, shielded cabinets, shielded desks, and console systems. The company has also expanded into integrated modular buildings, outdoor duty stations, and containerized equipment rooms, forming a full-industry-chain service capability covering “Equipment R&D – Manufacturing – Engineering Implementation – After-Sales Operations & Maintenance.”
The company operates a modern production base equipped with CNC bending machines, laser cutting machines, automatic spraying lines, hot-dip galvanizing production lines and other specialized manufacturing equipment. A rigorous quality control system ensures all products pass third-party authority inspections and comply with national and industry standards. Adhering to the product philosophy of “Efficient, Green, Innovative, Safe, Convenient,” the company provides customized solutions tailored to diverse customer scenarios, offers multiple free design proposals for client selection, and assigns dedicated personnel to track project progress throughout the entire process, ensuring efficient project delivery.
On the service front, the company has established a 24-hour professional online service system that rapidly responds to customer inquiries and after-sales needs, providing end-to-end services from solution design, manufacturing, transportation and installation, to operation & maintenance training. With over 20 years of professional manufacturing experience, flexible customization capabilities and project-confirmed pricing advantages, Guangzhou Lain has become a highly influential supplier of data center equipment and modular buildings in South China, continuously delivering high-quality, high-reliability products and services to customers across all industries.
—
Chapter 2: Project Overview
2.1 Construction Background
As China accelerates infrastructure construction, expands industrial parks, improves outdoor public services and strengthens emergency response system development, the market demand for temporary, movable, fully functional integrated office-living spaces continues to grow. Traditional brick-and-mortar temporary buildings suffer from prolonged construction cycles, excessive construction waste, non-reusability, poor site adaptability and high comprehensive costs — no longer able to meet today’s demands for efficiency, low-carbon and flexible construction.
Meanwhile, modular integrated buildings — characterized by factory prefabrication, on-site assembly and relocatable reuse — have become the preferred solution for temporary office and accommodation scenarios. However, most modular houses on the market suffer from single-function design, crude structures, poor thermal insulation and waterproofing, and incomplete configurations, making them unable to simultaneously meet the dual requirements of office and residential use, nor adapt to complex outdoor climatic conditions.
Against this backdrop, Guangzhou Lain Intelligent System Development Co., Ltd. has leveraged over 20 years of experience in data center construction and modular equipment production to launch the standardized 3m × 7m Integrated Living & Office Modular Station. Targeting the core needs of outdoor duty, construction site offices, park gatehouses and scenic area services, this product achieves full integration of structure, enclosure, electrical & plumbing, interior decoration, furniture and HVAC — delivering a safe, comfortable, convenient and cost-effective integrated space solution.
2.2 Construction Objectives
This project aims to develop a standardized, highly reliable, fully integrated 3m × 7m living-office modular station achieving the following core objectives:
- Complete Functionality: Simultaneously meets the daily office and living needs of 2–3 persons, equipped with an independent washbasin area, power and data systems, HVAC system and storage furniture — move-in ready with no additional equipment procurement required.
- Structural Safety: The overall structure adopts a hot-dip galvanized steel frame, strictly designed in accordance with national building load codes, with wind resistance, seismic resistance and compression resistance capable of adapting to various complex outdoor environments. The main structure has a designed service life of more than 15 years.
- Standardized Appearance: Strictly matches the classic blue-white-gray color scheme — ocean-blue flat roof with parapet edging, off-white upper wall, light gray lower wall, accented by a dark gray decorative waistband — presenting a neat, stable appearance compatible with the visual requirements of various parks, municipal and construction sites.
- Efficient Delivery: Factory prefabrication rate exceeds 95%; on-site work is limited to foundation preparation, assembly and commissioning. A single unit can be installed and delivered within 3 days, dramatically shortening project lead times.
- Green & Low-Carbon: Utilizes recyclable building materials; construction involves no wet work and generates minimal construction waste. The product can be relocated and reused in its entirety, with lifecycle carbon emissions far lower than traditional buildings, in line with green development principles.
- Convenient O&M: All systems employ universal, mature components. Daily maintenance is simple, fault diagnosis is convenient, spare parts are readily available, and long-term operation and maintenance costs remain low.
2.3 Applicable Scenarios
This 3m × 7m integrated living-office station offers exceptional versatility and can be widely deployed across various outdoor temporary office and accommodation scenarios, including but not limited to:
- Construction Site Scenarios: Project department temporary offices, management dormitories, guard rooms, and worker rest areas — rapidly establishing on-site temporary facilities to meet accelerated project timelines.
- Industrial Park Scenarios: Park entrance guard posts, patrol personnel duty stations, temporary offices and material storage rooms — enhancing park security and management efficiency.
- Municipal & Transportation Scenarios: Road administration duty stations, sanitation worker rest stations, traffic duty posts and road maintenance sites — improving the working environment for outdoor frontline personnel.
- Scenic & Cultural Tourism Scenarios: Tourist service points, security duty rooms, equipment operation rooms and temporary ticketing stations — enhancing scenic area service capabilities and emergency response readiness.
- Power & Communication Scenarios: Duty rest rooms and supporting office spaces for substations and communication base station operations personnel — meeting the duty requirements of remote sites.
- Mining & Oilfield Scenarios: Temporary office and accommodation points at field mining and oilfield operation sites — adapting to complex field environments.
- Emergency Response Scenarios: Disaster relief temporary resettlement points, epidemic prevention checkpoints, emergency command posts and temporary medical points — enabling rapid deployment to meet urgent response needs.
2.4 Design Basis
This solution is designed in strict compliance with current national standards, specifications and procedures. The primary design bases include:
| Standard | Designation |
| ———- | ————- |
| Load Code for the Design of Building Structures | GB 50009-2012 (2012 edition) |
| Standard for Design of Steel Structures | GB 50017-2017 |
| Cold-Formed Steel Sections | GB/T 6728-2017 |
| Metallic Coatings — Hot-Dip Galvanized Coatings on Fabricated Iron and Steel Articles — Specifications and Test Methods | GB/T 13912-2002 |
| Metal-Faced Sandwich Panels for Building Insulation | GB/T 23932-2009 |
| Plastic Windows for Buildings | GB/T 28887-2012 |
| Code for Fire Protection Design of Buildings | GB 50016-2014 (2018 edition) |
| Standard for Electrical Design of Civil Buildings | GB 51348-2019 |
| Standard for Design of Building Water Supply and Drainage | GB 50015-2019 |
| Code for Design of Building Ground | GB 50037-2013 |
| Code for Acceptance of Construction Quality of Ventilation and Air-Conditioning Engineering | GB 50243-2016 |
| Technical Standard for Modular Buildings | JGJ/T 492-2018 |
| Technical Code for Safety of Temporary Electricity Application at Construction Sites | JGJ 46-2005 |
| Client-provided exterior reference drawings and functional requirement specifications | — |
2.5 Key Technical Specifications
| Specification Category | Core Parameters |
| ———————— | —————– |
| External Dimensions | Length 7000mm × Width 3000mm × External Height 2900mm (incl. roof parapet) |
| Interior Clear Height | 2700mm |
| Interior Usable Area | Approx. 21㎡ |
| Designed Service Life | Main structure ≥ 15 years; enclosure system ≥ 10 years |
| Seismic Fortification Intensity | 7 degrees (0.10g) |
| Wind Resistance Rating | Grade 10 (basic wind pressure 0.55kN/㎡) |
| Roof Live Load | 0.5kN/㎡ |
| Floor Uniform Live Load | 2.0kN/㎡ |
| Wall Heat Transfer Coefficient | ≤ 0.73W/(㎡·K) |
| Airborne Sound Insulation | Walls ≥ 30dB; doors & windows ≥ 25dB |
| Fire Resistance Rating | B1 class by default; upgradable to Class A non-combustible |
| Electrical Rated Voltage | 220V/50Hz |
| Design Total Electrical Load | 5kW |
| Water Supply Pressure Requirement | ≥ 0.1MPa |
| Drainage Connection | φ50mm standard interface |
—
Chapter 3: User Demand Analysis
3.1 Functional Space Requirements
Based on the positioning of application scenarios, this station must simultaneously accommodate both office and living functions, supporting routine use by 2–3 persons. Specific space requirements are as follows:
- Office Area Requirements: At least 2 standard office workstations equipped with desks, chairs and filing cabinets to support daily office work, document storage and equipment placement. Ample power outlets and network interfaces should be reserved on walls to support simultaneous operation of computers, printers, surveillance equipment and other office devices. Lighting brightness must meet office task requirements, with uniform illumination and no glare.
- Rest Area Requirements: At least 2 fixed beds and 1 backup bed to support shift rest and temporary overnight accommodation. Equipped with a locker for storing personal clothing and daily necessities. The rest area should provide independent privacy, separated from the office area by a partition to prevent mutual interference. Lighting should be zone-controlled to support low-illumination needs during rest.
- Washbasin Area Requirements: A pedestal washbasin with a hot/cold water faucet for daily washing and cleaning needs. A floor drain with odor trap should be provided for floor cleaning drainage. Water supply and drainage piping should be concealed for a clean appearance.
- Storage Space Requirements: A multi-tiered storage system comprising filing cabinets, lockers and under-bed space, separately storing office documents, personal belongings and tools/materials — clearly categorized and easily accessible.
3.2 Structural Safety Requirements
The product is primarily used in outdoor open-air environments and must provide reliable structural safety performance, meeting the following requirements:
- The overall structure must withstand self-weight, wind/snow loads and occupant activity loads, with no deformation or collapse risk under extreme weather conditions, providing sufficient safety margins.
- The steel structure main body must possess excellent anti-corrosion and rust-prevention performance, adapting to high-humidity southern climates, coastal salt spray, industrial corrosion and various other outdoor environments, avoiding short-term rust that could compromise structural lifespan.
- Enclosure panels must have sufficient strength and rigidity to withstand general external impact without deformation or damage, while preventing rainwater infiltration.
- Foundation design must accommodate various site conditions including general hardened ground, concrete ground and bare soil ground, with convenient installation, ensuring the building remains level and stable without settlement or tilting risk.
- Basic seismic resistance must be provided, with no structural damage at 7-degree fortification intensity, ensuring occupant safety.
3.3 Exterior Appearance Requirements
With reference to standardized municipal and park styles, the exterior must meet the following requirements:
- Overall form should be square and concise, with straight lines and stable, coordinated colors, conforming to public building visual standards.
- The roof adopts an ocean-blue flat design with parapet edging, forming a regular top border that visually enhances the building’s three-dimensional quality.
- The walls adopt a two-tone horizontal scheme: light gray lower section for dirt resistance and easy cleaning, off-white upper section for brightness and openness, with a dark gray decorative waistband serving as a smooth transition between the two.
- Doors and windows adopt a white color system with flat, transparent glass; frames connect tightly to the walls with uniform gaps.
- The overall exterior should have no exposed screws or messy piping, with neat edge trims and uniform joints, presenting a clean, unified visual effect compatible with various standardized parks and municipal scenarios.
3.4 Environmental Adaptability Requirements
The product must adapt to outdoor environments across most regions of China, providing excellent environmental adaptability:
- Temperature Adaptability: Normal operation at ambient temperatures from -10℃ to 45℃; with the HVAC system, comfortable interior temperatures are maintained. The enclosure structure provides excellent thermal insulation, reducing the impact of external temperatures on the interior.
- Rain & Water Infiltration Protection: The roof, walls, doors and windows all feature comprehensive waterproof sealing designs capable of withstanding heavy rainstorms without leakage or seepage. Drainage systems are unobstructed, allowing rapid removal of roof accumulation.
- Wind Uplift Resistance: The overall structure is securely anchored to the foundation, and enclosure panels are reliably connected to the framing. No damage or panel uplift risk under grade-10 winds.
- Moisture & Mold Resistance: Walls and floors feature moisture-resistant designs, preventing interior condensation and mold growth during southern plum rain seasons, ensuring a healthy living and working environment.
- Mosquito & Insect Protection: Doors and windows are equipped with screens, and gaps are tightly sealed to effectively block outdoor mosquitoes and insects from entering.
3.5 Electrical, Water Supply & Drainage Requirements
- Electrical Requirements: Operational with standard 220V mains power connection. The entire unit is equipped with ample lighting and outlet points, with segregated power and data wiring, and features leakage, overload and short-circuit protection. A dedicated air-conditioning circuit is reserved for high-power equipment. Network outlets cover both office and rest areas, supporting internet access and equipment connectivity.
- Water Supply & Drainage Requirements: The water supply system is operational upon connection to municipal water or storage equipment; drainage can discharge into municipal networks or temporary collection pits. The system features leak-proof, clog-proof and odor-trap functionality with rational piping layout — no odor or blockage during routine use.
3.6 Operation & Maintenance Management Requirements
- All product components adopt universal standardized specifications, enabling rapid replacement after damage with low maintenance costs. Common minor faults can be handled without specialist personnel.
- Daily maintenance is simple, requiring only periodic cleaning and inspection of sealants and fasteners — no frequent professional maintenance required, reducing long-term O&M costs.
- The product supports integral lifting and relocation. When the site changes, the unit can be reused, reducing secondary construction investment. Dismantling and reassembly are convenient, and transport is straightforward.
- Configurations can be flexibly upgraded based on usage requirements — such as upgrading to fire-resistant panels, adding furniture points, or expanding the low-voltage system — adapting to different stage-specific needs.
—
Chapter 4: Overall Design Description
4.1 Design Philosophy
This solution adheres to the design philosophy of “Standardization, Integration, Human-Centered Design, and High Reliability.” With factory prefabrication at its core, all systems — structure, enclosure, electrical & plumbing, interior decoration and furniture — are pre-manufactured and pre-installed at the factory, requiring only simple on-site assembly for delivery. Within the limited 21㎡ space, scientific functional zoning and humanized detailing achieve the integration of office, living and washroom functions, while strictly ensuring structural safety, environmental comfort and long-term durability — delivering a benchmark-grade modular station product that balances practicality and cost-efficiency.
The design process adheres to the principles of “Safety First, Function Priority, Details Win.” All structural designs undergo rigorous mechanical verification; all configurations are set based on actual usage requirements; and all details consider the reliability and convenience of long-term use — ensuring the product not only looks neat but also possesses solid inherent quality, capable of adapting to long-term use in various complex outdoor environments.
4.2 Overall Exterior Design
This product strictly matches the reference drawing styling, adopting a classic flat-roof box design with the following specific details:
- Roof Section: Flat-roof design with 200mm-high ocean-blue parapet edging around the perimeter, forming a regular border visual effect. The roof surface is finished with ocean-blue color-coated steel sheet — flat, smooth, combining waterproofing and decorative functions. Parapet corners are joined at 45°, with uniform gaps sealed with sealant for a seamless appearance.
- Wall Section: Horizontal three-band color scheme: the bottom 1000mm height is light gray color-coated steel sheet — dirt-resistant and easy to clean; the middle features a 150mm-wide dark gray decorative waistband to enhance the elevation’s layered appearance; above the waistband to the ceiling is off-white color-coated steel sheet — bright and luminous, enhancing interior daylighting.
- Door & Window Section: The main entrance door is positioned on one side of the 7m-long elevation — a white hinged door with observation window (300mm × 600mm), combining daylighting and security functions. The 7m-long elevation is fitted with two 1200mm × 1200mm double-sliding windows; the 3m side elevation features one same-spec sliding window — all with white frames, symmetrically arranged, providing ample natural light.
- Detail Finishing: Wall external/internal corners and upper/lower edges are wrapped with dedicated edge trim profiles with uniform joints and straight lines. All exposed screws are concealed — the overall appearance features no protruding components, presenting a clean, generous and consistent texture.
4.3 Interior Layout Design
Based on the 7m × 3m interior dimensions, the layout follows a “front office, rear rest, side washroom” scheme with clear functional zoning, smooth traffic flow and maximized space utilization.
- Space Division: Along the 3m width direction, a 50mm-thick interior partition wall is positioned approximately 4m from the entrance door, dividing the space into two zones: the front is the office area (approx. 4m depth, approx. 12㎡); the rear is the rest area (approx. 3m depth, approx. 9㎡). The partition features an 800mm-wide interior door connecting both zones.
- Office Area Layout: On one side adjacent to the entry, two 1200mm × 600mm office desks are arranged side-by-side along the side wall, paired with 3 office chairs, forming two standard workstations. A steel filing cabinet is placed against the opposite wall for storing office documents and supplies. Four 10A five-hole outlets and 2 network outlets are mounted on the walls to support office equipment power and connectivity. Two LED ceiling lights provide ample office illumination.
- Rest Area Layout: A 1.2m-wide double-layer steel bunk bed is positioned along the side wall, accommodating 2 persons. A folding single bed storage space is reserved at the corner; when unfolded, it accommodates a 3rd person for temporary accommodation. A two-door locker is placed against the opposite wall for storing personal clothing and daily necessities. The washbasin area is set in the inner corner of the rest area, equipped with a pedestal washbasin and odor-trap floor drain. Two LED ceiling lights are independently switched. Wall outlets include four 10A five-hole outlets, 2 network outlets and 1 16A air-conditioning outlet.
- Traffic Flow Design: The entrance door leads directly into the office area; the rest area and washroom are accessible through the partition door. Each zone operates without interference, with smooth passage and no wasted space. The interior main passage width is ≥ 800mm, meeting normal pedestrian flow and furniture movement requirements.
4.4 Overall Performance Specifications
- Structural Performance: The main frame adopts a Q235B hot-dip galvanized steel structure, with bolted + self-tapping screw dual connections at nodes. Structural strength meets 7-degree seismic fortification requirements, withstands grade-10 wind loads, the roof accommodates 0.5kN/㎡ live loads, and the floor accommodates 2.0kN/㎡ uniformly distributed live loads — providing ample overall structural safety margins.
- Thermal Performance: The enclosure structure adopts 50mm-thick EPS sandwich panels plus a roof fiberglass insulation reinforcement layer, achieving an overall heat transfer coefficient of ≤ 0.6W/(㎡·K). Excellent thermal insulation performance — effectively blocks solar radiant heat in summer and reduces interior heat loss in winter, significantly reducing air-conditioning energy consumption.
- Waterproof Performance: The roof features a triple waterproof design of tongue-and-groove interlocking + weather-resistant sealant + gutter drainage. Walls utilize tongue-and-groove joining + sealant waterproofing. Doors and windows employ multiple sealing strips. Overall waterproof rating reaches Class III and above per GB/T 21086-2007, withstanding heavy rainstorms without leakage.
- Sound Insulation Performance: Wall airborne sound insulation ≥ 30dB; door/window sound insulation ≥ 25dB — effectively isolating outdoor traffic noise and wind/rain sounds, ensuring a quiet office and rest environment.
- Fire Resistance Performance: Default configuration uses EPS sandwich panels with an overall fire rating of B1 (flame-retardant). For higher fire protection requirements, upgrades to rock wool sandwich panels achieve Class A non-combustible rating, meeting fire safety requirements of various premises.
- Environmental Performance: All building materials comply with national environmental standards. Interior formaldehyde emission meets E1 requirements with no irritating odor — ready for occupancy immediately after delivery, requiring no air-out period.
4.5 Design Execution Standard System
This solution establishes a full-process standard system covering design, production, installation and acceptance, ensuring consistent and controllable product quality:
- Structural Design Standards: Strictly implements the Standard for Design of Steel Structures, Cold-Formed Steel Sections and Load Code for the Design of Building Structures — all member selections subject to mechanical verification to ensure reliable structural safety.
- Enclosure Material Standards: Implements Metal-Faced Sandwich Panels for Building Insulation and Prepainted Steel Sheets and Strips — full-process inspection from raw material intake to finished product dispatch ensures panel performance and appearance quality.
- Electrical & Plumbing Design Standards: Follows the Standard for Electrical Design of Civil Buildings and Standard for Design of Building Water Supply and Drainage — standardized wiring, rational piping and comprehensive safety protection.
- Construction & Acceptance Standards: Construction and acceptance follow the Standard for Acceptance of Construction Quality of Steel Structures, Standard for Acceptance of Construction Quality of Decoration Engineering and Technical Standard for Modular Buildings — each process must pass inspection before proceeding to the next.
—
Chapter 5: Product Quotation & Configuration List
5.1 Quotation Notes
- This quotation covers the standard configuration price for the 3m × 7m Integrated Living & Office Modular Station, including all materials and installation costs for the main structure, enclosure system, door & window system, interior decoration, electrical system, water supply & drainage system, furniture system and HVAC system.
- The quotation is exclusive of tax and transportation. A 10% tax point applies for special VAT invoices, or 3% for regular invoices. Transportation costs are calculated based on actual project location, shipped freight collect.
- Site foundation costs are included in the quotation, covering standard 100mm-thick C20 concrete ground construction. Special site requirements are subject to separate calculation.
- The product can be customized and upgraded based on customer requirements — such as upgrading to Class A fire-resistant rock wool panels, increasing the number of air conditioners, upgrading door/window specifications, or adjusting the interior layout — with upgrade costs calculated separately.
- Warranty: Main steel structure: 2-year warranty; other systems: 1-year warranty. Air-conditioning equipment follows the manufacturer’s national warranty policy.
—
Chapter 6: Main Steel Structure System Technical Parameters
6.1 System Overview
The main structure adopts a Q235B hot-dip galvanized steel frame system, forming a complete load-bearing skeleton comprising four corner load-bearing columns, bottom-frame longitudinal main beams, bottom-frame transverse secondary beams, top-frame longitudinal main beams, top-frame transverse purlins, and wall vertical/horizontal studs. All structural components are mechanically connected using high-strength bolts combined with self-tapping screws for dual-redundancy fastening, ensuring the structural system’s integrity, stability and safety.
The design follows the Standard for Design of Steel Structures (GB 50017-2017) and the Load Code for the Design of Building Structures (GB 50009-2012), with all load conditions verified through rigorous structural calculations. The structural frame is engineered for:
- Seismic fortification intensity of 7 degrees (0.10g)
- Wind resistance to Grade 10 (basic wind pressure 0.55kN/㎡)
- Roof live load of 0.5kN/㎡
- Floor uniform live load of 2.0kN/㎡(continued)
6.2 Corner Load-Bearing Columns
| Parameter | Specification |
| ———– | ————— |
| Component designation | Corner load-bearing column |
| Section type | Square steel tube |
| Standard designation | GB/T 6728-2017 (Cold-Formed Steel Sections) |
| Section dimensions | 100mm × 100mm |
| Wall thickness | 3.0mm |
| Material grade | Q235B |
| Surface treatment | Hot-dip galvanized (GB/T 13912-2002) |
| Quantity per unit | 4 columns |
| Connection method | Bottom: bolted connection to bottom-frame beams; Top: bolted connection to top-frame beams |
6.3 Bottom-Frame Longitudinal Main Beams
| Parameter | Specification |
| ———– | ————— |
| Component designation | Bottom-frame longitudinal main beam |
| Section type | Cold-formed C-channel steel |
| Section dimensions | 180mm × 60mm × 20mm |
| Wall thickness | 2.5mm |
| Material grade | Q235B |
| Surface treatment | Hot-dip galvanized (GB/T 13912-2002) |
| Quantity per unit | 2 beams (length 7000mm) |
| Function | Primary bottom-frame load distribution members transferring floor loads to corner columns |
6.4 Bottom-Frame Transverse Secondary Beams
| Parameter | Specification |
| ———– | ————— |
| Component designation | Bottom-frame transverse secondary beam |
| Section type | Cold-formed C-channel steel |
| Section dimensions | 120mm × 50mm × 15mm |
| Wall thickness | 2.0mm |
| Material grade | Q235B |
| Surface treatment | Hot-dip galvanized (GB/T 13912-2002) |
| Quantity per unit | 6 beams (spanning 3000mm width) |
| Function | Secondary floor support members; support the floor base panels and transfer floor loads to longitudinal main beams |
6.5 Top-Frame Longitudinal Main Beams
| Parameter | Specification |
| ———– | ————— |
| Component designation | Top-frame longitudinal main beam |
| Section type | Cold-formed C-channel steel |
| Section dimensions | 180mm × 60mm × 20mm |
| Wall thickness | 2.5mm |
| Material grade | Q235B |
| Surface treatment | Hot-dip galvanized (GB/T 13912-2002) |
| Quantity per unit | 2 beams (length 7000mm) |
| Function | Primary roof load-bearing members transferring roof loads to corner columns |
6.6 Top-Frame Transverse Purlins
| Parameter | Specification |
| ———– | ————— |
| Component designation | Top-frame transverse purlin |
| Section type | Cold-formed C-channel steel |
| Section dimensions | 120mm × 50mm × 15mm |
| Wall thickness | 2.0mm |
| Material grade | Q235B |
| Surface treatment | Hot-dip galvanized (GB/T 13912-2002) |
| Spacing | ≤ 600mm |
| Function | Roof panel support members; support roof sandwich panels and transfer roof loads to longitudinal main beams |
6.7 Wall Vertical Studs
| Parameter | Specification |
| ———– | ————— |
| Component designation | Wall vertical stud |
| Section type | Cold-formed C-channel steel |
| Section dimensions | 80mm × 40mm × 12mm |
| Wall thickness | 1.5mm |
| Material grade | Q235B |
| Surface treatment | Hot-dip galvanized (GB/T 13912-2002) |
| Spacing | ≤ 600mm |
| Function | Main vertical framing members of wall panels; support wall panels and transfer wind loads and self-weight to the main frame |
6.8 Wall Horizontal Studs
| Parameter | Specification |
| ———– | ————— |
| Component designation | Wall horizontal stud |
| Section type | Cold-formed C-channel steel |
| Section dimensions | 60mm × 30mm × 10mm |
| Wall thickness | 1.5mm |
| Material grade | Q235B |
| Surface treatment | Hot-dip galvanized (GB/T 13912-2002) |
| Function | Horizontal stiffening members; provide additional rigidity and support for wall panel fixing |
6.9 Complete Connection Hardware
| Component | Specification | Material / Standard |
| ———– | ————– | ——————— |
| High-strength hex bolts (main frame) | M12 × 35mm, Grade 8.8 | High-strength carbon steel, zinc-plated |
| High-strength hex bolts (secondary frame) | M10 × 30mm, Grade 8.8 | High-strength carbon steel, zinc-plated |
| Self-tapping screws (panel fixing) | ST5.5 × 25mm / ST5.5 × 19mm | Carbon steel, zinc-plated |
| Self-tapping screws (frame connection) | ST6.3 × 30mm | Carbon steel, zinc-plated |
| Seismic anchor bolts (foundation) | M12 × 120mm expansion anchor bolts | Carbon steel, zinc-plated |
| Galvanized angle brackets | 50mm × 50mm × 3mm / lengths as required | Q235B hot-dip galvanized |
6.10 Anti-Corrosion Treatment Specification
The steel structure adopts a double-layer anti-corrosion system to ensure long-term structural durability in outdoor environments:
- Hot-Dip Galvanizing: All structural steel members undergo hot-dip galvanizing in accordance with GB/T 13912-2002 (Metallic Coatings — Hot-Dip Galvanized Coatings on Fabricated Iron and Steel Articles). Average zinc coating thickness: ≥ 85μm, providing 15+ years of sacrificial protection against atmospheric corrosion, including coastal salt spray environments.
- Touch-Up Coating: All cut ends, drill holes and weld areas are touched up with zinc-rich anti-corrosion paint after installation, ensuring complete coverage of the galvanized layer at all connection points.
Application Environment Adaptability:
| Environment | Suitability |
| ————- | ————- |
| General inland atmosphere | Excellent — 20+ years service life |
| High humidity / coastal areas | Good — 15+ years service life |
| Industrial atmospheric zones | Good — 15+ years service life with periodic touch-up |
6.11 Structural Mechanics Verification
The main structural frame has been verified by professional structural calculation software in accordance with GB 50009-2012 and GB 50017-2017. Key verification results:
| Verification Item | Limit Requirement | Calculated Value | Result |
| ——————- | ——————- | —————— | ——– |
| Corner column axial compression ratio | ≤ 0.80 | 0.42 | Pass |
| Corner column overall stability | ≤ 215 MPa | 118.6 MPa | Pass |
| Top-frame main beam deflection | ≤ L/250 | L/412 | Pass |
| Bottom-frame main beam deflection | ≤ L/250 | L/468 | Pass |
| Wall stud wind load deflection | ≤ L/200 | L/326 | Pass |
| Frame lateral displacement (wind) | ≤ H/300 | H/512 | Pass |
| Overall structural safety margin | — | 1.85× | Pass |
Note: All calculations configured with 7-degree seismic fortification intensity (0.10g) and Grade-10 wind basic pressure (0.55kN/㎡).
6.12 Steel Structure Processing & Acceptance Standards
- Processing Standards: Steel members are cut, drilled and formed using precision CNC equipment, ensuring dimensional accuracy of ±2mm. All connection holes are precisely positioned with matching accuracy per design drawings.
- Welding Quality: All welds are executed following the Code for Acceptance of Construction Quality of Steel Structures (GB 50205-2001), with full-penetration welds at critical nodes. Weld surfaces must be smooth, free of porosity, slag inclusion and undercut defects.
- Galvanizing Quality: Galvanized coatings must be uniform, continuous, and free of bare spots, bubbles, roughness and other defects as required by GB/T 13912-2002. Coating adhesion is verified using the hammer test.
- Assembly Acceptance: Pre-assembly is performed at the factory before dispatch. Overall dimension tolerances: length ± 5mm, width ± 3mm, height ± 3mm; diagonal difference ≤ 5mm; surface flatness ≤ 3mm/m.
- Inspection Certificate: Each structure is factory-inspected and supplied with a quality certificate and inspection report.
—
Chapter 7: Roof Enclosure System Technical Parameters
7.1 System Overview
The roof enclosure system adopts a 50mm-thick metal-faced EPS sandwich panel solution with complete waterproofing, thermal insulation and drainage provisions. The system includes roof sandwich panels, 200mm-high parapet edging, waterproof sealant, PVC drainage gutters, PVC downpipes with rain hoppers, and a thermal insulation reinforcement layer. The roof is designed with a triple waterproof defense: tongue-and-groove panel interlocking, weather-resistant sealant, and positive slope drainage through gutters.
7.2 Roof Sandwich Panel
| Parameter | Specification |
| ———– | ————— |
| Panel type | Metal-faced EPS sandwich panel |
| Standard | GB/T 23932-2009 (Metal-Faced Sandwich Panels for Building Insulation) |
| Core material | EPS (expanded polystyrene), density ≥ 16kg/m³ |
| Core thickness | 50mm |
| Face sheet (outer) | 0.5mm thick color-coated steel sheet, ocean blue (Roof color) |
| Face sheet (inner) | 0.4mm thick color-coated steel sheet, white |
| Panel width | 950mm (effective coverage width) |
| Panel length | Custom cut to fit roof dimensions |
| Joint type | Tongue-and-groove (shiplap) interlocking |
| Thermal conductivity (core) | ≤ 0.041 W/(m·K) |
| Panel weight | Approx. 12kg/㎡ |
7.3 Roof Parapet Edging
| Parameter | Specification |
| ———– | ————— |
| Component | Roof parapet edge trim |
| Height | 200mm |
| Material | 0.5mm color-coated steel sheet |
| Color | Ocean blue |
| Corner treatment | 45° mitered joints with sealant sealing |
| Function | Provides a clean roof border appearance; serves as perimeter water barrier directing runoff toward gutters |
7.4 Roof Waterproof Sealant
| Parameter | Specification |
| ———– | ————— |
| Type | Single-component neutral silicone weather-resistant sealant |
| Color | White / matching body colors |
| Application thickness | ≥ 6mm bead |
| Joint coverage | All panel joints, parapet connections, roof penetrations |
| Service temperature range | -40℃ to +150℃ |
| Key performance | Excellent UV resistance, weather resistance, ±25% joint movement capability |
7.5 PVC Drainage Gutter
| Parameter | Specification |
| ———– | ————— |
| Material | PVC (polyvinyl chloride), UV-stabilized |
| Color | White |
| Width | 100mm |
| Depth | 80mm |
| Thickness | 3.0mm |
| Length | Custom cut to roof edge |
| Slope requirement | ≥ 0.5% toward downpipe outlets |
| Connection | Solvent-welded joints |
7.6 PVC Downpipe & Rain Hopper
| Parameter | Specification |
| ———– | ————— |
| Downpipe material | PVC |
| Downpipe diameter | φ75mm |
| Rain hopper type | PVC 90° square hopper |
| Fixing method | Downpipe clamps at ≤ 1500mm intervals |
| Quantity per unit | 2 downpipes fitted to roof corners (long side) |
| Discharge capacity | ≥ 4.5 L/s per downpipe (exceeds local heavy rain requirements) |
7.7 Roof Insulation Reinforcement Layer
| Parameter | Specification |
| ———– | ————— |
| Material | Aluminum foil-faced glass fiber wool |
| Thickness | 30mm |
| Density | ≥ 32kg/m³ |
| Thermal conductivity | ≤ 0.038 W/(m·K) |
| Location | Between top-frame purlins, below roof panels |
| Function | Supplementary insulation; eliminates thermal bridges at purlin locations; improves overall roof U-value |
7.8 Roof Waterproof Construction Detail
The roof system is designed with a triple waterproof defense line:
- First Defense — Panel Interlocking: Roof sandwich panels utilize tongue-and-groove joints creating a mechanical water barrier. Panels are installed with transverse overlap direction opposite to prevailing wind direction.
- Second Defense — Sealant System: All panel longitudinal and transverse joints are sealed with neutral silicone weather-resistant sealant, forming a continuous elastic waterproof membrane.
- Third Defense — Positive Drainage: The roof incorporates a minimum 2% slope toward the gutter line. Water flows to the PVC gutter and is rapidly discharged through downpipes. The parapet edge trim provides a perimeter barrier preventing water ingress at edges.
Critical detail points:
- All roof-to-wall junctions are flashed with profiled metal flashings, sealed with sealant at both upper and lower edges.
- Panel joints at the parapet perimeter are additionally reinforced with capping profiles.
- All fasteners penetrating the roof surface are fitted with sealing washers.
7.9 Roof Thermal Performance Calculation
| Parameter | Value |
| ———– | ——- |
| EPS core thermal conductivity | 0.041 W/(m·K) |
| Glass wool reinforcement layer thermal conductivity | 0.038 W/(m·K) |
| Roof system combined heat transfer coefficient (U-value) | ≤ 0.5 W/(㎡·K) |
| Compare with standard brick-concrete roof (U ≈ 2.0 W/㎡K) | 75% reduction in heat loss/gain |
| Summer indoor ceiling surface temperature reduction vs. uninsulated roof | ≥ 8℃ |
| Winter indoor heat loss reduction | ≥ 60% |
7.10 Roof Wind Load Verification
Per GB 50009-2012, the roof system wind load verification is as follows:
| Verification Item | Requirement | Calculated Value | Result |
| ——————- | ————- | —————— | ——– |
| Roof panel wind uplift resistance per fixing | ≥ 1.5 × wind uplift load | 1.86 × | Pass |
| Purlin fixing pull-out resistance | ≥ 1.5 × uplift transfer load | 1.72 × | Pass |
| Panel-to-frame screw shear capacity | Safe against wind load | Compliant | Pass |
| Parapet wind pressure resistance | No deformation at 0.55kN/㎡ | Compliant | Pass |
Result: Roof system provides a safety margin of ≥ 1.5 against Grade-10 wind uplift forces.
—
Chapter 8: Wall Enclosure System Technical Parameters
8.1 System Overview
The wall enclosure adopts a 50mm-thick metal-faced EPS sandwich panel system with a two-tone color scheme. The wall system comprises lower wall panels (light gray), upper wall panels (off-white), a decorative waistband (dark gray) at mid-height, interior partition panels, and dedicated edge trim profiles. The system provides thermal insulation, sound insulation, waterproofing, fire resistance and wind load resistance as a complete building envelope.
8.2 Lower Wall Panels (External)
| Parameter | Specification |
| ———– | ————— |
| Panel type | Metal-faced EPS sandwich panel |
| Panel height | 1000mm |
| Outer face sheet | 0.5mm color-coated steel sheet — Light gray |
| Inner face sheet | 0.4mm color-coated steel sheet — White |
| Core thickness | 50mm EPS (density ≥ 16kg/m³) |
| Function | Lower wall cladding; dirt-resistant, easy-clean surface |
8.3 Upper Wall Panels (External)
| Parameter | Specification |
| ———– | ————— |
| Panel type | Metal-faced EPS sandwich panel |
| Panel height | From waistband to ceiling (approx. 1700mm) |
| Outer face sheet | 0.5mm color-coated steel sheet — Off-white |
| Inner face sheet | 0.4mm color-coated steel sheet — White |
| Core thickness | 50mm EPS (density ≥ 16kg/m³) |
| Function | Upper wall cladding; bright appearance enhancing interior daylighting |
8.4 Decorative Waistband (Mid-height)
| Parameter | Specification |
| ———– | ————— |
| Component | Prefabricated metal waistband trim |
| Width | 150mm |
| Material | 0.5mm color-coated steel sheet |
| Color | Dark gray |
| Profile | Factory-pressed with return edges for stiffness |
| Function | Visual transition between upper and lower wall panels; covers horizontal panel joint |
8.5 Interior Partition Panels
| Parameter | Specification |
| ———– | ————— |
| Panel type | Metal-faced EPS sandwich panel |
| Panel thickness | 50mm |
| Face sheets | 0.4mm color-coated steel, both sides white |
| Core material | EPS (density ≥ 16kg/m³) |
| Panel dimensions | 3000mm (width) × 2700mm (height), with 800mm door opening |
| Partition quantity | 1 panel width |
| Function | Divides office and rest zones; provides thermal and acoustic separation |
8.6 Wall Edge Trim Components
| Component | Specification | Function |
| ———– | ————— | ———- |
| External corner trim | 0.5mm color-coated steel, matched colors | Wraps external wall corners; prevents exposed edges; provides clean finish |
| Internal corner trim | 0.4mm color-coated steel, white | Covers interior corner joints |
| Base trim | 0.4mm color-coated steel, white | Covers wall-to-floor junction; allows easy cleaning |
| Ceiling junction trim | 0.4mm color-coated steel, white | Covers wall-to-ceiling junction |
| Coping trim | 0.5mm color-coated steel, wall color | Caps wall top edges; connects to roof flashing |
8.7 Wall Thermal Performance Analysis
| Parameter | Value |
| ———– | ——- |
| EPS core thermal conductivity | 0.041 W/(m·K) |
| Wall heat transfer coefficient (U-value) | ≤ 0.65 W/(㎡·K) |
| Thermal transmittance improvement vs. uninsulated single-skin wall | ≥ 70% improvement |
| Summer heat gain reduction | ≥ 65% |
| Winter heat loss reduction | ≥ 60% |
8.8 Wall Sound Insulation Performance
| Parameter | Value |
| ———– | ——- |
| Wall airborne sound insulation index (Rw) | ≥ 30dB |
| Interior partition sound insulation | ≥ 28dB |
| Sound reduction performance | Reduces normal conversation (60dB) to barely audible level (≤ 30dB) |
| Test standard | GB/T 50121-2005 (Standard for Sound Insulation Design of Building) |
8.9 Wall Fire Resistance Performance
| Parameter | Value (Default) | Value (Upgrade Option) |
| ———– | —————— | ———————— |
| Core material | EPS (expanded polystyrene) | Rock wool |
| Fire rating | B1 (flame-retardant) | A (non-combustible) |
| Fire resistance time | ≥ 15 minutes | ≥ 1 hour (per GB/T 9978.1) |
| Smoke production | Low | Negligible |
8.10 Wall Wind Pressure & Deformation Resistance
| Parameter | Value |
| ———– | ——- |
| Design wind pressure resistance | 0.55kN/㎡ (Grade 10 wind) — verified safe |
| Panel deflection under design wind load | ≤ L/200 (max 6mm for 1200mm stud spacing) |
| Panel-to-frame screw pull-out resistance | ≥ 1.5 × calculated wind suction load |
| Impact resistance | Withstands 50kg soft body impact without panel damage |
| Service temperature range | -30℃ to +80℃ continuous use |
—
Chapter 9: Door & Window System Technical Parameters
9.1 System Overview
The door and window system comprises the main entrance door, double-sliding glass windows, interior partition door and corresponding sealing hardware. All doors and windows are factory-fabricated, pre-hung and pre-sealed at factory for rapid on-site installation. The system provides daylighting, ventilation, security, sound insulation and thermal insulation functions.
9.2 Main Entrance Door
| Parameter | Specification |
| ———– | ————— |
| Door type | Single-leaf steel hinged door with observation window |
| Door dimensions | 900mm (width) × 2100mm (height) |
| Door leaf | 0.5mm color-coated steel sheet, white, with EPS insulation core |
| Frame | 1.5mm thick galvanized steel frame |
| Observation window | 300mm × 600mm, 5mm toughened glass |
| Hardware | Heavy-duty hinges ×3, mortise lock with latch, internal handle + external handle without key (internal locking) |
| Weather sealing | Full-perimeter EPDM sealing strips |
| Color | White |
9.3 Double-Sliding Glass Windows
| Parameter | Specification |
| ———– | ————— |
| Window type | Double-slider aluminum alloy sliding window |
| Window dimensions | 1200mm × 1200mm (2 on 7m elevation) |
| Additional window | 1200mm × 1200mm (1 on 3m side elevation) |
| Frame material | Aluminum alloy, powder-coated white |
| Glass | 4mm + 9A + 4mm hollow insulating glass |
| Sliding sashes | Both sashes sliding horizontally, internal stacked |
| Screen | Fiberglass mosquito screen on one sash |
| Locking | Crank-type window lock with locking arms |
| Water drainage | Concealed drainage holes in lower frame |
| Weather stripping | Nylon brush seals on sliding interfaces |
9.4 Interior Partition Door
| Parameter | Specification |
| ———– | ————— |
| Door type | Single-leaf flush interior door |
| Door dimensions | 800mm (width) × 2000mm (height) |
| Door leaf | 40mm thick honeycomb core flush door, white laminate finish |
| Frame | 45mm × 90mm engineered wood frame, white |
| Hardware | Hinges ×2, privacy latch lock |
| Color | White |
9.5 Door & Window Sealing Kit
| Component | Specification |
| ———– | ————— |
| Door perimeter seal | EPDM (ethylene-propylene-diene monomer) rubber sealing strip |
| Window frame seal | Neutral silicone sealant around exterior frame |
| Window sliding seal | Nylon brush pile weather-stripping |
| Structural fixings | 30mm self-tapping screws at ≤ 300mm spacing |
| Exterior junction seal | Weather-resistant sealant at all frame-to-wall junctions |
9.6 Water Tightness & Air Permeability Performance
| Parameter | Value |
| ———– | ——- |
| Water tightness (windows) | Class 3 or above per GB/T 7106-2019 |
| Air permeability (windows) | Class 6 per GB/T 7106-2019 |
| Water tightness (door) | Class 3 or above per GB/T 7106-2019 |
| Air permeability (door) | Class 4 per GB/T 7106-2019 |
| Frame-to-wall air leakage | Zero — fully sealed with sealant |
| Rain resistance | Withstands heavy rainstorm (≥ 100mm/h) with no water ingress |
9.7 Door & Window Sound Insulation & Thermal Performance
| Parameter | Door Value | Window Value |
| ———– | ———— | ————– |
| Sound insulation | ≥ 25dB | ≥ 25dB |
| Heat transfer coefficient (U-value) | ≤ 2.5 W/(㎡·K) | ≤ 2.8 W/(㎡·K) |
| Glass type | 5mm tempered | 4+9A+4 hollow insulating |
| Condensation resistance | No condensation on interior surfaces at outdoor -10℃ / indoor 20℃ / RH 50% |
9.8 Door & Window Hardware Durability Performance
| Test Item | Requirement | Standard |
| ———– | ————- | ———- |
| Sliding window durability cycle | ≥ 30,000 cycles without deformation or failure | GB/T 32223-2015 |
| Door hinge durability | ≥ 200,000 open/close cycles | JG/T 125-2007 |
| Window lock mechanism endurance | ≥ 10,000 operations | JG/T 125-2007 |
| Sealant accelerated aging | No cracking or peeling after 500h UV + heat aging | GB/T 16422.3-2022 |
| Hardware corrosion resistance | Salt spray test ≥ 100h without red rust | GB/T 10125-2021 |
—
Chapter 10: Interior Decoration System Technical Parameters
10.1 System Overview
The interior decoration system covers floor base panels, PVC floor covering, ceiling system, cove base trims and all interior finishes. The design prioritizes durability, easy cleaning, environmental safety and visual comfort indoors.
10.2 Floor Base Panels
| Parameter | Specification |
| ———– | ————— |
| Material | 18mm-thick high-density moisture-resistant particleboard (OSB or particle board) |
| Standard | GB/T 4897-2015 (Particleboard) |
| Size | 2440mm × 1220mm panels, custom cut |
| Fixing | Self-tapping screws to bottom-frame secondary beams at ≤ 300mm spacing |
| Surface treatment | Sanded smooth, dust-sealed |
| Moisture resistance | Board edges sealed with moisture-resistant sealant |
| Load capacity | Supports concentrated loads ≥ 300kg without visible deflection |
10.3 PVC Floor Covering
| Parameter | Specification |
| ———– | ————— |
| Type | Homogeneous PVC commercial flooring |
| Thickness | 2.0mm (total) with wear layer |
| Wear layer thickness | ≥ 0.35mm |
| Width | 2000mm (roll) |
| Color | Light wood-grain texture |
| Installation | Full-surface adhesive bonding to base panels, heat-welded seams |
| Slip resistance | R9 (suitable for normal dry/wet conditions) |
| Abrasion resistance | Class T (heavy commercial use) |
| Indentation resistance | ≤ 0.35mm after 1h, 500N load (per GB/T 11982.1-2015) |
10.4 Ceiling System
| Parameter | Specification |
| ———– | ————— |
| Ceiling type | Pre-painted steel coil ceiling (flat) |
| Material | 0.4mm color-coated steel sheet, white |
| Installation | Screw-fixed to top-frame purlins through furring channels |
| Ceiling height | 2700mm clear |
| Finish | Gloss level ≥ 70% (reflective), easy-clean surface |
| Joint treatment | Concealed joints with white filler or snap-on joint trims |
10.5 Cove Base Trim
| Parameter | Specification |
| ———– | ————— |
| Material | PVC cove base |
| Height | 80mm |
| Color | White |
| Installation | Adhesive-mounted around floor perimeter |
| Function | Covers floor-to-wall junction; provides clean, washable edge |
10.6 Interior Environmental Performance
| Parameter | Limit Value | Test Standard |
| ———– | ————- | ————— |
| Indoor formaldehyde emission | ≤ 0.08mg/m³ (meets E1) | GB/T 18883-2022 |
| TVOC concentration | ≤ 0.60mg/m³ | GB/T 18883-2022 |
| Benzene emission | ≤ 0.11mg/m³ | GB/T 18883-2022 |
| Indoor odor | No irritating odor on delivery | Visual/olfactory inspection |
| Ready-to-occupy | Immediate after installation — no air-out period required | — |
10.7 Fire & Abrasion Performance of Interior Finishes
| Item | Performance Requirement | Standard |
| —— | ———————— | ———- |
| Floor covering fire rating | B1 (flame-retardant), smoke density ≤ 75% | GB 8624-2012 |
| Ceiling panel fire rating | A (non-combustible steel surface) | GB 8624-2012 |
| Interior wall surface fire rating | B1 (flame-retardant) | GB 8624-2012 |
| Floor covering abrasion | Class T — withstands 20,000+ cycles | GB/T 11982.1-2015 |
10.8 Interior Lighting Environment & Spatial Comfort Design
| Parameter | Value |
| ———– | ——- |
| Office area maintained illuminance | ≥ 300 lux at desktop level |
| Rest area maintained illuminance | ≥ 100 lux at floor level |
| Uniformity of illumination (office) | ≥ 0.7 |
| Color rendering index (CRI) | ≥ 80 |
| Glare rating | UGR ≤ 19 (office area) |
| Interior wall color reflectivity | ≥ 0.75 (white upper walls) |
| Interior space volume per person | ≥ 7m³/person (for 3-person occupancy) |
| Natural daylighting (window area / floor area ratio) | ≥ 1/6 |
—
Chapter 11: Electrical System Technical Parameters
11.1 System Overview
The electrical system is designed per the Standard for Electrical Design of Civil Buildings (GB 51348-2019), providing complete power distribution, lighting, socket outlets, network/data connectivity, and safety protection. The system is factory pre-wired and tested, requiring only external connection at site. Power and data (weak current) wiring are physically separated to prevent electromagnetic interference.
11.2 Main Distribution Box
| Parameter | Specification |
| ———– | ————— |
| Type | Wall-mounted metal enclosure |
| Rated voltage | 220V / 50Hz |
| Incoming capacity | 5kW |
| Main breaker | 32A/2P residual current operated circuit breaker (RCBO) with overload and short-circuit protection |
| Branch circuits | 4 circuits total as follows |
| — Lighting circuit | 1 × C10A RCBO |
| — General sockets circuit | 1 × C16A RCBO |
| — Socket + air conditioning circuit | 1 × C20A RCBO |
| — Reserved circuit | 1 × C16A RCBO |
| Leakage protection sensitivity | 30mA, trip time ≤ 0.1s (all socket circuits and general circuits) |
| Enclosure protection rating | IP30 (indoor installation) |
| Busbar configuration | Copper busbar, tinned |
| Enclosure material | Cold-rolled steel, powder-coated |
11.3 LED Ceiling Lights
| Parameter | Specification |
| ———– | ————— |
| Type | LED ceiling panel light |
| Rated power | 24W per unit |
| Luminous flux | ≥ 2400 lm |
| Efficacy | ≥ 100 lm/W |
| Color temperature | 4000K (neutral white) |
| CRI | ≥ 80 |
| Rated life | ≥ 30,000 hours |
| Quantity per unit | 4 (2 in office area, 2 in rest area) |
| Installation | Surface-mounted on ceiling, quick-connect wiring |
11.4 10A Five-Hole Socket Outlets
| Parameter | Specification |
| ———– | ————— |
| Rating | 10A / 250V AC |
| Configuration | 2P+3P universal five-hole |
| Standard | GB/T 1002-2008 |
| Quantity per unit | 8 total (4 in office area, 4 in rest area) |
| Safety feature | Integrated safety shutters (child-proof) |
| Terminal type | Screw-clamp terminals, suitable for 2.5mm² conductors |
11.5 16A Air-Conditioner Socket Outlet
| Parameter | Specification |
| ———– | ————— |
| Rating | 16A / 250V AC |
| Standard | GB/T 1002-2008 (16A three-pin) |
| Quantity per unit | 1 (positioned in rest area for AC unit) |
| Dedicated circuit | C20A RCBO from distribution box, 4mm² copper conductor |
11.6 Lighting Switches
| Parameter | Specification |
| ———– | ————— |
| Rating | 10A / 250V AC |
| Type | Rocker switch, white |
| Quantity per unit | 4 (2 for office lights, 2 for rest lights) |
| Special feature | Rest area switches dual-controlled for convenient access |
11.7 Network / Data Sockets
| Parameter | Specification |
| ———– | ————— |
| Type | RJ45 Cat6 shielded modular jack |
| Standard | TIA/EIA-568.2-D |
| Bandwidth | 250MHz |
| Quantity per unit | 4 (2 in office area, 2 in rest area) |
| Data cabling | Cat6 UTP solid copper, run to wall-mounted junction/termination box |
11.8 Full-House Wiring Kit
| Parameter | Power Wiring | Data Wiring |
| ———– | ————- | ————- |
| Conductor type | BV single-core copper cable | Cat6 UTP |
| Wire gauge (lighting) | 2.5mm² | — |
| Wire gauge (sockets) | 2.5mm² | — |
| Wire gauge (AC circuit) | 4.0mm² | — |
| Wire gauge (main feed) | 6.0mm² | — |
| Conduit | PVC conduit (φ20 / φ25) | PVC conduit (φ20) |
| Color coding | Live: Red/Brown; Neutral: Blue; Earth: Yellow-Green | Blue/Slate jacket |
| Routing | Separate conduits from data wiring (≥ 300mm separation) | — |
11.9 Outdoor Waterproof Inlet Box
| Parameter | Specification |
| ———– | ————— |
| Type | IP66 outdoor weatherproof junction/connection box |
| Material | UV-stabilized ABS / polycarbonate |
| Ratings | IP66 ingress protection, 10A / 250V |
| Connection | External cable entry via IP68 cable gland; internal connection to main distribution box |
| Application point | External wall, near building service corner |
11.10 Electrical Safety Protection Design
Protection Layers:
- Residual Current Protection: All socket circuits and general-purpose circuits protected by 30mA RCD/RCBO — operates within 0.1s of leakage fault.
- Overload & Short-Circuit Protection: All circuits individually protected by MCB/RCBO at correct ratings.
- Earth Bonding: All exposed metal parts (frames, enclosures) are bonded to earth via dedicated earth conductor. Earth resistance ≤ 4Ω as verified at commissioning.
- Insulation: All live parts double-insulated per class II requirements; wiring insulation voltage rating 450/750V.
- Mechanical Protection: All cables protected within PVC conduit throughout; junction boxes are enclosed and secured.
11.11 Electrical Load Calculation & Cable Sizing Verification
| Load Category | Quantity | Unit Power | Total Load |
| ————— | ———- | ———– | ———— |
| LED ceiling lights | 4 | 24W | 96W |
| 10A socket outlets (general) | 8 | 500W (max simultaneous) | 1000W |
| 16A AC outlet (AC unit) | 1 | 1500W | 1500W |
| Office equipment (est.) | — | 800W | 800W |
| Total design load | — | — | ≤ 3.5kW |
| Design capacity | — | — | 5kW (30% margin) |
| Cable Verification | Requirement | Calculated | Result |
| ——————– | ————- | ———— | ——– |
| Main feed 6mm² copper current capacity | ≥ 32A | 47A | Pass |
| AC circuit 4mm² copper current capacity | ≥ 20A | 38A | Pass |
| Socket circuit 2.5mm² current capacity | ≥ 16A | 27A | Pass |
| Voltage drop at design load (whole circuit) | ≤ 5% | 1.8% | Pass |
11.12 Earthing & Lightning Protection Design
| Item | Design Detail |
| —— | ————— |
| Earthing system type | TN-S (separate PE conductor throughout) |
| Earthing electrode | Provided by site foundation or supplied grounding rod (L1200 × 16mm copper-clad steel) when required |
| Earth resistance requirement | ≤ 4Ω |
| Lightning protection approach | Building is a movable unit — no fixed lightning rod by design. In areas with high lightning density, site-supplied lightning rod + down conductor + earth electrode recommended |
| Equipotential bonding | All metal exterior components (roof panels, wall panels, frames) are interconnected and bonded to earth |
| SPD (surge protection) | Type 3 surge protective device fitted within main distribution box as standard |
—
Chapter 12: Water Supply & Drainage System Technical Parameters
12.1 System Overview
The water supply and drainage system is designed per the Standard for Design of Building Water Supply and Drainage (GB 50015-2019). The system includes cold water supply piping from external connection point to the washbasin, and drainage piping from the washbasin and floor drain to the external discharge point. All piping is concealed within wall/floor cavities for a clean appearance.
12.2 Water Supply Piping
| Parameter | Specification |
| ———– | ————— |
| Material | PPR (polypropylene random copolymer) pipe |
| Standard | GB/T 18742-2017 (Polypropylene (PP) Piping Systems) |
| Cold water pipe diameter | DN20 (inlet) / DN15 (to faucet) |
| Pipe rating | PN1.6MPa |
| Working temperature range | 5℃ – 95℃ |
| Connection method | Heat-fusion welded joints |
| Installation | Concealed within wall cavity/floor cavity |
| Supply point | 1 × pedestal washbasin with dual-connection for hot/cold faucet |
12.3 Drainage Piping
| Parameter | Specification |
| ———– | ————— |
| Material | PVC-U (unplasticized polyvinyl chloride) |
| Standard | GB/T 5836.1-2018 (Unplasticized Poly(Vinyl Chloride) (PVC-U) Pipes for Soil and Waste Discharge) |
| Main drain diameter | DN50 |
| Connection method | Solvent cement joints |
| Slope requirement | ≥ 1% (toward external outlet) |
| External connection | DN50 flexible adapter for site connection |
| Venting | Internal trap vents through anti-siphon valve on washbasin drain |
12.4 Pedestal Washbasin
| Parameter | Specification |
| ———– | ————— |
| Type | White ceramic pedestal washbasin |
| Dimensions | Approx. 560mm (W) × 450mm (D) |
| Faucet type | Single-lever chrome faucet, dual water supply connections |
| Water supply connection | DN15 flexible braided hoses to shut-off valve |
| Drain connection | DN32 basin waste with trap |
| Overflow | Built-in overflow channel |
| Mounting | Pedestal floor-standing |
12.5 Main Water Supply Shut-Off Valve
| Parameter | Specification |
| ———– | ————— |
| Type | Brass ball valve |
| Connection size | DN20 |
| Working pressure | 1.6MPa |
| Application point | Inlet side, just inside building; accessible access panel |
| Function | Emergency shut-off and isolation for system maintenance |
12.6 Odor-Trap Floor Drain
| Parameter | Specification |
| ———– | ————— |
| Type | Stainless steel floor drain with deep-seal water trap |
| Trap seal depth | ≥ 50mm |
| Drain opening | 100mm × 100mm |
| Material | 304 stainless steel cover, ABS body with PVC-U extension |
| Water seal function | Prevents sewer gas backflow into interior |
| Cleaning access | Removable grate with sediment basket |
12.7 Water Supply System Hydraulic Calculation
| Parameter | Value |
| ———– | ——- |
| Design flow rate (peak) | 0.15 L/s |
| Inlet pressure requirement | ≥ 0.1MPa (as per Chapter 2 specification) |
| Pipe friction loss (DN20 at 0.15 L/s) | ≤ 0.02 MPa over 10m run |
| Available pressure at highest fixture | ≥ 0.02MPa (sufficient for faucet operation) |
| Flow rate at faucet (at 0.1MPa inlet) | ≥ 6 L/min |
| Verification result | Water supply meets peak demand with 2× margin |
12.8 Drainage System Flow Capacity Verification
| Parameter | Value |
| ———– | ——- |
| Drainage design flow (washbasin + floor drain simultaneous) | 0.3 L/s (conservative) |
| DN50 PVC-U drain capacity at 1% slope (full bore) | ≥ 1.2 L/s |
| System capacity utilization | 25% — 80% capacity reserve |
| Verification result | Drainage system has exceptional capacity margin; no blockage risk under normal use |
12.9 Freeze Protection & Leak Prevention Design
| Item | Design Measure |
| —— | —————- |
| Freeze protection | Recommended site measures: drain-back valve on external supply, insulation wrap on exposed piping (site-provided in severe cold regions); PPR pipe tolerant to brief freezing without rupture |
| Leak prevention | All joints heat-fusion welded (water supply) — no threaded joints in concealed zones; full water test at factory (1.0MPa for 30 min) and after installation (0.8MPa for 30 min) |
| Condensation prevention | Cold pipe insulated with closed-cell rubber foam ≥ 9mm in warm/humid climates |
| Flood prevention | Floor drain at lowest point of washroom area; overflow protection via basin overflow channel |
12.10 Water System Hygiene Performance
| Parameter | Value |
| ———– | ——- |
| Piping material hygiene compliance | GB/T 17219-2001 (Hygienic standard for drinking water pipes) — complies |
| Water stagnation prevention | System flushed and sanitized before delivery; all pipe ends capped/sealed during transit |
| Inlet strainer | 60-mesh stainless steel strainer fitted at shut-off valve inlet |
| Surface cleanliness | All concealed pipes inaccessible — exposed sections finished flush & clean |
| System disinfection | System disinfected with chlorinated water (≥ 50mg/L) for 30 min before commissioning |
—
Chapter 13: Office & Living Furniture System Technical Parameters
13.1 System Overview
The furniture system is factory-supplied and installed, providing complete office and living functionality. All furniture is designed to commercial/industrial standards with environmental safety compliance, appropriate load capacity and durable construction suitable for daily use in outdoor field conditions.
13.2 Double-Layer Steel Bunk Bed
| Parameter | Specification |
| ———– | ————— |
| Configuration | Double-layer bunk bed |
| External dimensions | 2000mm (L) × 1200mm (W) × 1800mm (H) |
| Frame material | Cold-rolled steel square tube ≥ 40mm × 40mm × 1.5mm |
| Guardrail | 30mm × 30mm × 1.2mm steel tube, full-length upper guardrail |
| Ladder | Integrated welded steel ladder, anti-slip treads |
| Bed slats | 5 slats per level, 18mm particleboard, recessed frame support |
| Load capacity per level | ≥ 300kg uniformly distributed |
| Surface treatment | Electrostatic powder coating, scratch-resistant |
| Finish color | White |
| Assembled stability | Rocking test: ≤ 5mm displacement |
| Standard | GB/T 3325-2017 (Metal furniture) |
13.3 Folding Single Bed
| Parameter | Specification |
| ———– | ————— |
| Type | Foldable single bed |
| Unfolded dimensions | 1900mm (L) × 800mm (W) × 350mm (H) |
| Frame material | 20mm × 20mm × 1.0mm steel tube |
| Bed surface | Woven fabric/vinyl sling |
| Folded dimensions | Approx. 1900mm (L) × 800mm (W) × 120mm (thick) |
| Load capacity | ≥ 150kg |
| Storage | Stored in dedicated wall-mounted rack in rest area |
| Finished surface | Powder-coated steel frame |
13.4 Staff Office Desk
| Parameter | Specification |
| ———– | ————— |
| Configuration | Single-person desk |
| Desk top dimensions | 1200mm (W) × 600mm (D) × 750mm (H) |
| Desk top material | 25mm thickened particleboard with laminated finish |
| Frame material | 1.2mm cold-rolled steel legs, powder-coated |
| Edge treatment | PVC edge banding, heat-sealed |
| Load capacity (desk top) | ≥ 100kg uniformly distributed |
| Storage | 2 pull-out drawers, 1 file drawer (selected desk) |
| Cable management | Integrated cable tray/grommet on selected desks |
| Finish color | White top / gray frame |
| Quantity | 2 units |
13.5 Office Chair
| Parameter | Specification |
| ———– | ————— |
| Type | Swivel office chair with armrests |
| Seat material | High-density foam (≥ 45kg/m³), PU upholstery |
| Backrest | High-back ergonomic mesh/foam |
| Adjustment | Seat height adjustable (gas lift), tilt-lock backrest |
| Base | Five-star nylon/PU caster base |
| Load capacity | ≥ 150kg |
| Standard | BIFMA / GB/T 3325-2017 compliance |
| Quantity | 3 units |
13.6 Steel Filing Cabinet
| Parameter | Specification |
| ———– | ————— |
| Configuration | Two-door lockable filing cabinet |
| Dimensions | 900mm (W) × 400mm (D) × 1850mm (H) |
| Material | 0.8mm cold-rolled steel plate |
| Interior | 3 fixed shelves, adjustable |
| Finish | Electrostatic powder coating, scratch-resistant |
| Locking | Central locking mechanism, 2 keys |
| Load capacity per shelf | ≥ 50kg |
| Finish color | White |
| Standard | GB/T 3325-2017 |
| Quantity | 1 unit |
13.7 Two-Door Locker
| Parameter | Specification |
| ———– | ————— |
| Configuration | Two-door individual locker |
| Dimensions | 800mm (W) × 500mm (D) × 1850mm (H) |
| Material | 0.8mm cold-rolled steel plate |
| Interior | Each compartment: 2 shelves, 1 clothing hanging rod |
| Ventilation | Louvered vents in doors |
| Locking | Individual cam locks, 1 key per compartment |
| Finish | Electrostatic powder coating |
| Finish color | White |
| Standard | GB/T 3325-2017 |
| Quantity | 1 unit (2 compartments) |
13.8 Furniture Environmental & Safety Standards
| Parameter | Requirement | Standard |
| ———– | ————- | ———- |
| Formaldehyde emission (board products) | ≤ 0.05mg/m³ (E1) | GB 18580-2017 |
| VOC content (laminates, finishes) | Compliant with limits | GB 18584-2001 |
| Heavy metal content (finishes) | Within limits (Pb, Cd, Cr, Hg) | GB 18584-2001 |
| Edge sharpness | All exposed edges rounded or edge-banded | GB 28007-2011 |
| Stability | No tipping under lateral 20kg top-load test | GB/T 3325-2017 |
| Load safety factor | 1.5× rated load without permanent deformation | GB/T 3325-2017 |
13.9 Furniture Load & Durability Test Specifications
| Test Item | Requirement | Standard |
| ———– | ————- | ———- |
| Desk top static load | 100kg for 24h, no permanent deformation > 1mm | GB/T 3325-2017 |
| Bunk bed load test | 300kg per level for 24h, deflection ≤ 10mm, no permanent deformation | Factory test |
| Locker/File cabinet load | 50kg per shelf, door operation normal after test | GB/T 3325-2017 |
| Chair dynamic fatigue | 100,000 cycles seat height adjustment; 50,000 cycles rocking test | BIFMA X5.1 |
| Surface abrasion resistance | ≥ 500 cycles abrasion test without exposing substrate | GB/T 4893.8-2023 |
| Humidity/temperature cycling | No delamination, blistering or warping after 72h damp-heat cycle | GB/T 4893.1-2021 |
—
Chapter 14: HVAC & Ventilation System Technical Parameters
14.1 System Overview
The HVAC and ventilation system comprises one wall-mounted split air conditioner for cooling/heating, one louvered exhaust fan for positive ventilation, and natural ventilation openings via windows. The system is engineered to maintain comfortable indoor temperatures across outdoor ambient conditions from -10℃ to 45℃, with controlled indoor humidity and fresh air exchange.
14.2 Wall-Mounted Split Air Conditioner
| Parameter | Specification |
| ———– | ————— |
| Type | Wall-mounted split heat pump |
| Cooling capacity | 3500W (1.5 HP class) |
| Heating capacity | 4200W (heat pump) |
| Inverter | Yes — DC inverter compressor |
| Energy efficiency rating | ≥ Level 1 (SEER / HSPF high efficiency) |
| Rated power consumption (cooling) | Approx. 1050W |
| Rated power consumption (heating) | Approx. 1250W |
| Power supply | 220V / 50Hz, dedicated 16A circuit |
| Indoor unit dimensions | Approx. 900mm × 300mm × 200mm |
| Outdoor unit dimensions | Approx. 800mm × 550mm × 300mm |
| Refrigerant | R32 (GWP = 675, ozone-friendly) |
| Operating ambient range | -15℃ to +50℃ (cooling); -20℃ to +24℃ (heating) |
| Airflow volume | 650 – 800 m³/h (high speed) |
| Noise level (indoor) | ≤ 38dB(A) (low speed) |
| Noise level (outdoor) | ≤ 52dB(A) |
| Installation | Indoor unit high-mounted on rest area wall; outdoor unit on external wall bracket or freestanding base |
| Standard | GB/T 7725-2004; GB 21455-2019 (energy efficiency) |
| Warranty | Per manufacturer national warranty policy |
14.3 Louvered Exhaust Fan
| Parameter | Specification |
| ———– | ————— |
| Type | Wall-mounted louvered exhaust fan |
| Blade diameter | 250mm |
| Airflow capacity | ≥ 720 m³/h |
| Power consumption | ≤ 35W |
| Noise level | ≤ 45dB(A) |
| Installation location | External wall, upper wall area (office zone) |
| Control | Manual switch, 3-speed (selected models) |
| Backdraft shutter | Integrated gravity louver prevents backdraft |
14.4 Indoor Thermal Comfort Calculation
| Design Condition | Cooling Mode | Heating Mode |
| —————— | ————– | ————– |
| Outdoor temperature | 35℃ (design) | 0℃ (design) |
| Indoor setpoint | 26℃ | 20℃ |
| Indoor relative humidity | 40–60% | 30–50% |
| Cooling load estimate | 3.1kW (calculated) | Heating load estimate: 3.5kW |
| Installed capacity | 3.5kW | 4.2kW |
| Capacity margin | 13% margin | 20% margin |
| Verification result | Passes comfort requirement | Passes comfort requirement |
14.5 Ventilation Rate Design Verification
| Parameter | Value |
| ———– | ——- |
| Interior volume | 21㎡ × 2.7m = 56.7m³ |
| Required air changes per hour (occupancy) | ≥ 10 ACH (intermittent) / ≥ 3 ACH (continuous) |
| Exhaust fan capacity | 720 m³/h = 12.7 ACH |
| Natural ventilation (windows open) | Up to 15 ACH (cross-ventilation) |
| Verification result | Ventilation capacity exceeds 10 ACH requirement with 27% margin |
| COâ‚‚ concentration (3 occupants, 10 ACH) | Maintains below 800ppm in continuous use |
14.6 System Energy Efficiency Analysis
| Item | Performance |
| —— | ————- |
| Enthalpy load reduction via insulation | ≥ 60% heat transfer blocked through envelope |
| Inverter AC partial-load efficiency | Higher seasonal efficiency vs. fixed-speed units |
| Combined energy consumption estimate (cooling season 6 months, 12h/day) | Approx. 1,200 – 1,500 kWh/year |
| Energy cost saving compared with masonry building | ≥ 25% annually |
| Standby power consumption | ≤ 1W (inverter standby) |
14.7 Equipment Noise Control Specifications
| Source | Noise Limit | Control Measure |
| ——– | ————- | —————– |
| AC indoor unit | ≤ 38dB(A) | Low-noise fan design; high mounting position |
| AC outdoor unit | ≤ 52dB(A) | Installed on vibration-isolating pads; away from bedroom head area |
| Exhaust fan | ≤ 45dB(A) | Balanced impeller; low-speed setting for continuous night operation |
| Interior background noise (all systems off) | ≤ 30dB(A) | Envelope sound insulation ≥ 30dB |
—
Chapter 15: Transport, Installation & Site Foundation Technical Parameters
15.1 Sealing & Fixing Accessory Materials
| Component | Specification |
| ———– | ————— |
| Butyl sealing tape | 20mm × 2mm roll, used at panel joints |
| Neutral silicone sealant | Weather-resistant, UV-stable, color-matched |
| EPDM sealing strips | 10mm × 5mm, for door/window perimeter |
| Expansion anchor bolts | M12 × 120mm, for foundation fixing |
| Waterproofing membrane (base) | Self-adhesive modified bitumen membrane, 2mm thick, laid under bottom frame |
| Sealing washers | EPDM-backed washers for all roof-penetrating screws |
| Pu foam sealant | Expansion foam for gap filling (concealed areas only) |
15.2 Professional Installation & Construction Standards
| Stage | Standard / Requirement |
| ——- | ———————— |
| Site preparation | Per JGJ/T 492-2018 (Technical Standard for Modular Buildings) |
| Foundation checking | Concrete level tolerance: ± 5mm / 3m straight edge; corners within ± 3mm level |
| Unit positioning | Positioning tolerance: ± 10mm from design plan; orientation per drawings |
| Leveling | Leveling via shims at base connections, then anchor bolt installation |
| Structure assembly | Bolted connections tightened to specified torque; self-tapping screws at ≤ 300mm spacing |
| Panel installation | Vertical surface tolerance: 2mm/3m; panel joints ≤ 2mm gap |
| Sealing | Sealant applied continuously — no missed or cut joints |
| Electrical termination | Per GB 51348-2019; all connections tight; polarity verified |
| Plumbing connection | Per GB 50015-2019; all joints watertight; system pressure tested |
| Final inspection | Per Chapter 15.6 acceptance process |
15.3 Whole-Unit Transportation Plan & Requirements
| Item | Requirement |
| —— | ————- |
| Transport mode | Standard 17.5m flatbed truck (4.2m usable width) |
| Loading configuration | Single unit per truck (7000mm length fits within 17.5m bed) |
| Lifting equipment (loading/unloading) | 20-ton crane or forklift (rated ≥ 8 tons) |
| Lifting method | 4-point sling lifting at designated corner lifting points |
| Transit bracing | Internal bracing at door and window openings; furniture secured; loose parts packed separately |
| Waterproof wrapping | Full-body waterproof canvas/sheet wrap during transit |
| Road requirements | Standard highway clearance; entry road recommended ≥ 7.5m driveway width |
| Transport tilt limit | ≤ 5° during transit (road gradient) |
| Offloading at site | Crane or hydraulic tailgate; ground bearing capacity ≥ 80kN/m² for crane outriggers |
15.4 Site Concrete Ground Foundation Parameters
| Parameter | Specification |
| ———– | ————— |
| Foundation type | Reinforced concrete slab on grade |
| Concrete grade | C20 (minimum) |
| Slab thickness | 100mm (standard) / 150mm (recommended for permanent installations) |
| Reinforcement | φ8@200mm × 200mm welded wire mesh (at mid-slab) |
| Slab dimensions | 7000mm (length) × 3000mm (width) + 200mm perimeter overhang = 7400mm × 3400mm |
| Pre-formed anchor positions | 4 corner anchor positions at 7000mm × 3000mm centers, tolerance ± 10mm |
| Surface tolerance | ± 5mm per 3m straight edge; slope not exceeding 0.3% toward drainage |
| Concrete curing | Minimum 7 days before load application |
| Sub-grade compaction | ≥ 95% standard proctor density |
| Frost protection (cold regions) | Sub-base below frost depth or 150mm compacted gravel base (site design as required) |
| Standard reference | GB 50007-2011 (Code for Design of Building Foundation) |
15.5 Foundation Bearing Capacity Verification
| Parameter | Value |
| ———– | ——- |
| Total structural weight (unloaded) | Approx. 4.5 tons |
| Foundation contact area | 7.0m × 3.0m = 21㎡ |
| Average unit pressure (unloaded) | ≈ 21.4 kN/㎡ |
| Design bearing capacity (C20 slab on compacted ground) | ≥ 100 kN/㎡ |
| Capacity utilization | 21% — substantial safety margin (Factor of Safety ≥ 4.5) |
| Wind overturning moment check | Worst-case Grade-10 wind (0.55kN/㎡) — overturning safety factor ≥ 2.1 (anchored) |
15.6 Installation Acceptance Standards & Process
| Acceptance Stage | Inspection Items | Standard |
| —————— | —————— | ———- |
| Stage 1 — Foundation | Concrete grade, surface level, anchor positions | Level tolerance ± 5mm/3m; anchors within ± 10mm |
| Stage 2 — Structure | Frame verticality, connections, tightness | Verticality ± 4mm total; bolts torqued to spec |
| Stage 3 — Enclosure | Panel joints, alignment, sealant coverage | Joints ≤ 2mm; sealant continuous & uniform |
| Stage 4 — Doors & Windows | Open/close function, gap uniformity, water tightness | Smooth operation; gaps uniform within 2mm |
| Stage 5 — Electrical | Continuity, insulation resistance, RCBO operation | Insulation ≥ 0.5MΩ; RCD trip test at 30mA |
| Stage 6 — Plumbing | Pressure test, flow, drainage, no leaks | 0.8MPa 30min no drop; drain no-block |
| Stage 7 — HVAC | AC operation, heating/cooling, exhaust fan operation | AC reaches setpoint at 1.5h; exhaust air flow ≥ 720m³/h |
| Final Acceptance | Full documentation, key handover, client sign-off | Completed checklist & acceptance certificate |
—
Chapter 16: Core Advantages of the Solution
16.1 Integrated Factory-Prefabrication Advantage
With a factory prefabrication rate exceeding 95%, all structural, enclosure, electrical, plumbing, decoration and furniture systems are manufactured, pre-assembled and quality-tested at our Guangzhou production base. This eliminates most on-site labor, ensuring consistent quality control, reduced weather dependency, and the elimination of multi-trade coordination issues on site. Result: higher quality, faster delivery, lower risk.
16.2 Structural Safety & Reliability Advantage
The Q235B hot-dip galvanized steel structure is engineered and tested to withstand Grade-10 winds and 7-degree seismic events, with a designed service life of 15+ years for the main structure. The dual anti-corrosion system (hot-dip galvanizing + touch-up coating) ensures long-term structural integrity across diverse climates — from humid coastal areas to arid inland regions. This is a robust, industrialized system backed by 20+ years of manufacturing heritage.
16.3 Rapid Deployment Advantage
From factory delivery to full operational status: 3 days. The unit arrives as a complete system — simply place on the prepared foundation, connect power and water, and move in. This is a genuine turnkey solution that eliminates construction site delays, making it ideal for time-critical projects across the USA, Europe, Southeast Asia, the Middle East and Africa.
16.4 All-Scenario Environmental Adaptability
Engineered to perform reliably in ambient temperatures ranging from -10℃ to +45℃, the unit handles heavy rain, wind, humidity and heat through its triple waterproof defense, high-performance insulation, anti-condensation detailing and versatile HVAC system. Whether deployed in tropical Southeast Asia, Middle East desert heat, or cold European winters, the unit maintains a comfortable, dry and protected interior environment.
16.5 Energy-Efficient Insulation Advantage
The 50mm insulated sandwich panel envelope, reinforced roof insulation layer and triple-sealed door/window system achieve an overall envelope U-value of ≤ 0.6W/(㎡·K) — approximately 75% better than typical temporary structures. This translates directly to lower HVAC energy consumption, reduced operating costs and a smaller carbon footprint — a meaningful sustainability contribution for ESG-conscious organizations.
16.6 Full-Function Integration Advantage
Unlike conventional modular units that ship as empty shells, our station arrives complete with office furniture, beds, lockers, air conditioning, water supply, drainage and interior decoration — literally “plug and live.” Procurement teams save significant time and cost by receiving one fully integrated product rather than sourcing multiple suppliers for fit-out items.
16.7 Full-Lifecycle Cost Control Advantage
Consider the total cost of ownership across years of operation: factory-precision manufacturing reduces maintenance frequency; universal components reduce spare-part costs; energy-efficient envelope reduces utility bills; and the unit’s relocatability eliminates repeat construction costs when sites change. The result is a lower total cost of ownership than traditional construction or low-grade alternatives.
16.8 Relocatable & Reusable Advantage
The unit is designed for repeated integral relocation. When the project site changes, the unit is simply disconnected from utilities, crane-loaded onto a flatbed, transported to the new site, and reinstalled on a new foundation — typically within 1–2 days. This asset retains residual value over multiple deployments, making it an investment rather than an expense. KITOZER as your direct manufacturer supports you across the entire asset lifecycle.
—
Chapter 17: Common Technical Q&A
17.1 General Knowledge Q&A
Q1: What is the overall size and weight of this unit?
A: External dimensions are 7000mm × 3000mm × 2900mm (L × W × H incl. parapet). Total structural weight is approximately 4.5 tons (unloaded).
Q2: How many people can this unit accommodate?
A: Designed for 2–3 people. Two fixed beds in the rest area plus one folding bed provide accommodation for up to 3 persons. The office area seats 2–3 persons simultaneously.
Q3: Does the unit arrive fully furnished?
A: Yes. The standard configuration includes office desks, chairs, filing cabinet, locker, bunk bed, folding bed, air conditioner, LED lighting, electrical system, water supply & drainage system, and complete interior decoration — truly move-in ready.
17.2 Structural Safety Q&A
Q1: What is the structural service life?
A: Main steel structure ≥ 15 years; enclosure system ≥ 10 years. With routine maintenance (touch-up paint, sealant replacement), service life can be extended beyond these periods.
Q2: Can it withstand typhoons and earthquakes?
A: Yes. The structure is designed and verified to withstand Grade-10 wind loads (basic wind pressure 0.55kN/㎡) and seismic intensity of 7 degrees (0.10g). The steel frame’s ductility and bolted connections allow controlled energy dissipation during seismic events.
Q3: What happens if the site ground is not perfectly level?
A: The bottom frame can be shimmed and grouted during installation to achieve level. Maximum allowable leveling adjustment is ± 30mm via shims before anchoring.
17.3 Enclosure Performance Q&A
Q1: Will the roof leak during heavy rain?
A: No. The roof system incorporates a triple waterproofing defense: tongue-and-groove panel interlocking, continuous weather-resistant sealant, and positive slope drainage to gutter and downpipe system. The system is tested against heavy rain conditions.
Q2: Is the unit insulated for extreme heat or cold?
A: Yes. The 50mm EPS sandwich panels plus roof reinforcement layer achieve a heat transfer coefficient of ≤ 0.6W/(㎡·K) — comparable to permanent building insulation levels. Combined with the inverter air conditioner, comfortable indoor temperatures are maintained from -10℃ to +45℃ outdoors.
Q3: Will there be condensation inside during humid weather?
A: No — by design. The envelope’s high insulation value keeps interior surfaces above dew point. Additionally, the exhaust fan can be operated to actively control indoor humidity in extreme humid conditions.
17.4 Electrical & Plumbing Configuration Q&A
Q1: What power supply is required?
A: Standard single-phase 220V/50Hz supply, with a design load of 5kW. A dedicated 10mm² (or 6mm² per local code) incoming cable is recommended. Our system is factory-pre-wired internally; only external connection is required.
Q2: What water supply is needed?
A: A mains water connection (≥ 0.1MPa pressure) via standard DN20 connection, or connection to a pressure tank/storage water system. The entire internal system comes pre-plumbed.
Q3: Can the unit work without external water supply?
A: Yes — with a site-supplied water tank and small pressure pump connected to the inlet. Our team can advise on the appropriate configuration for your site.
17.5 Functional Layout Q&A
Q1: Can the interior layout be customized?
A: Yes. As the manufacturer, we can adjust the interior partition position, furniture configuration and electrical/plumbing point locations to suit your specific requirements. Lead time for customization varies based on complexity.
Q2: Is there enough space for both office and bedroom use?
A: The 21㎡ usable area is divided into approximately 12㎡ office area and 9㎡ rest area, providing comfortable space for both functions. The layout is optimized to avoid “cramped” feeling while maximizing utility.
17.6 Procurement & Delivery Q&A
Q1: What is the production lead time?
A: Standard units: 15–20 working days from order confirmation and drawing approval. Customized units: 25–35 working days depending on modification scope.
Q2: How is the unit shipped?
A: By standard 17.5m flatbed truck, one unit per truck. For overseas projects, units ship in breakbulk or containerized format (disassembled into sub-assemblies) as required by logistics constraints.
Q3: Can you supply for overseas projects?
A: Absolutely. Guangzhou Lain / KITOZER exports across Southeast Asia, the Middle East, Africa, Europe, the USA and global markets. We have extensive experience in export packaging, sea-freight logistics and overseas installation support.
17.7 After-Sales & Maintenance Q&A
Q1: What warranty is provided?
A: Main steel structure: 2 years. Other systems: 1 year. Air-conditioning equipment: per manufacturer policy. See Chapter 20 for complete warranty terms.
Q2: How do I get spare parts?
A: All components use universal standard specifications. Spare parts can be ordered directly from us or sourced locally from standard suppliers. See Chapter 20 for more details.
Q3: What maintenance is needed?
A: Minimal. Annual inspection of sealants and roof fixings, periodic cleaning of gutters and air-conditioner filters, and general cleaning. Full maintenance guide provided at handover.
—
Chapter 18: Construction Schedule
18.1 Overall Construction Duration Planning
| Phase | Duration | Description |
| ——- | ———- | ————- |
| Factory prefabrication | 15–20 working days | Structure fabrication, panel installation, factory pre-assembly, internal systems installation, quality inspection |
| Transport & delivery | 1–5 days (domestic) / port-dependent (overseas) | Loading, transport from Guangzhou factory to project site |
| Site installation | 3 days | Foundation prep (day 1), structure & systems installation (day 2), commissioning & handover (day 3) |
| Total turnaround (domestic) | Approx. 19–28 days | From order confirmation to operational handover |
18.2 Factory Prefabrication Phase Schedule
| Day | Activity |
| —– | ———- |
| Day 1–2 | Steel structure cutting, drilling, forming |
| Day 3–4 | Structure assembly & welding, hot-dip galvanizing process |
| Day 5–7 | Frame assembly, roof & wall panel installation |
| Day 8–10 | Door & window installation, interior partition |
| Day 11–12 | Electrical system installation & wiring |
| Day 13 | Plumbing system installation |
| Day 14–15 | Interior decoration completion (flooring, ceiling) |
| Day 16–17 | Furniture installation, equipment mounting |
| Day 18 | Full-system testing, quality inspection |
| Day 19–20 | Cleaning, packaging, load-out |
18.3 Transport Phase Schedule (Domestic)
| Day | Activity |
| —– | ———- |
| Day 1 | Loading at factory, securing cargo |
| Day 2–4 | Highway transport to project site (varies by distance) |
| Day 5 | Offloading at site, positioning on foundation |
18.4 Site Installation Phase Schedule
| Day | Activity |
| —– | ———- |
| Day 1 (AM) | Site survey, foundation inspection, base waterproofing membrane installation |
| Day 1 (PM) | Unit offloading into position, leveling, anchor bolt fixing |
| Day 2 (AM) | Electrical external connection, plumbing external connection |
| Day 2 (PM) | Sealant application (exterior), final joint cosmetic treatment |
| Day 3 (AM) | Full-system commissioning (electrical, plumbing, HVAC function tests) |
| Day 3 (PM) | Final inspection, client walkthrough, documentation handover |
18.5 Key Milestone Management Plan
| Milestone | Target Date | Control Method |
| ———– | ————- | —————- |
| Drawing approval | Day 0 | Client sign-off on dimension/layout drawings |
| Structure completion | Day 4–5 of production | Factory QC inspection, photo documentation |
| Pre-shipment inspection | Day 18–19 | Client QC approval before shipment |
| Site handover | Day 3 of site work | Signed acceptance certificate |
18.6 Schedule Assurance Measures
- Dedicated production line: Standard units are produced on dedicated lines with dedicated crews.
- Material inventory: Long-lead materials (steel, panels, AC units) held in stock to eliminate procurement delays.
- Parallel operations: Overlapping production activities (e.g., electrical wiring concurrent with wall panel installation).
- Regular reporting: Weekly production progress reports with photos to client/EPC.
- Contingency capacity: Backup production crew capacity ± 20% to recover from any delays.
18.7 Delay Contingency Plan
| Risk | Impact | Mitigation |
| —— | ——– | ———— |
| Steel material delay | Production start delay | Stock inventory & alternative supplier agreements |
| Transport delay (weather, road) | Delivery delay | Advance dispatch; flexible shipping alternatives |
| Site foundation not ready | Installation delay | Pre-installation site survey; modular unit staged at factory until site ready |
| Extreme weather during installation | 1–2 day delay | Covered waterproofing plan, flexible crew scheduling |
| Force majeure events | Project-wide delay | Commercial terms with force majeure clause (per contract standard terms) |
—
Chapter 19: Construction Organization Plan
19.1 Project Organization Structure
The project team is structured to ensure clear accountability and efficient coordination:
“`
Project Manager (1)
├── Production Coordinator (1) — Factory production scheduling & quality
├── Logistics Coordinator (1) — Transport & delivery arrangement
├── Site Installation Supervisor (1) — On-site installation & commissioning
│ ├── Installation Crew (3–4 persons) — Structure, enclosure, interior
│ ├── Electrical Technician (1) — Power & data wiring completion
│ └── Plumbing Technician (1) — Water supply & drainage completion
└── QC / Acceptance Engineer (1) — Quality inspections at factory & site
“`
19.2 Pre-Construction Preparation
| Task | Requirement |
| —— | ————- |
| Site survey | Confirm delivery access, crane positioning, ground bearing capacity |
| Client coordination | Confirm utilities connection points (power, water, drainage) |
| Document approval | Final drawing approval from client before production starts |
| Team mobilization | Assign project manager, confirm crew availability |
| Tooling & equipment | Site tools: crane (client-sourced or as specified), hand tools, power tools, leveling equipment |
| Permits | Confirm any local permits required for temporary structures |
19.3 Main Steel Structure Installation Process
| Step | Procedure |
| —— | ———– |
| 1 | Position bottom frame on foundation — check level and anchor positions |
| 2 | Fix bottom Frame to foundation via anchor bolts (M12 × 120mm expansion) at all 4 corners |
| 3 | Erect four corner columns — bolt to bottom frame corner gussets |
| 4 | Install top-frame longitudinal beams — bolt to column tops |
| 5 | Install top-frame transverse purlins — bolt/self-tap to longitudinal beams |
| 6 | Install wall vertical & horizontal studs at marked positions |
| 7 | Verify frame verticality (≤ ± 4mm), tighten all bolted connections to specified torque |
| 8 | Apply touch-up zinc-rich paint at all connection points |
19.4 Enclosure System Installation Process
| Step | Procedure |
| —— | ———– |
| 1 | Lay self-adhesive waterproofing membrane at base before wall installation |
| 2 | Install lower wall panels (light gray): align with frame, screw-fix with sealing washers |
| 3 | Install decorative waistband panel across mid-height line |
| 4 | Install upper wall panels (off-white): screw-fix to wall studs |
| 5 | Install external/internal corner trims and edge trims |
| 6 | Seal all panel joints with neutral silicone sealant — continuous bead, tooled flush |
| 7 | Install roof insulation reinforcement layer between purlins |
| 8 | Install roof panels (ocean blue): screw-fix with sealing washers, interlock joints |
| 9 | Install parapet edge trims (45° mitered corners), seal all joints |
| 10 | Install gutter, downpipes and rain hoppers ensuring slope toward outlets |
19.5 Door & Window Installation Process
| Step | Procedure |
| —— | ———– |
| 1 | Position door/window frames into prepared openings |
| 2 | Shim and level frames — check square and vertical (within ± 2mm) |
| 3 | Fix frames to wall studs with self-tapping screws at ≤ 300mm spacing |
| 4 | Apply EPDM sealing strips around door/window perimeters |
| 5 | Hang door leaves / install sliding sashes — check smooth operation |
| 6 | Apply exterior sealant around all frame-to-wall junctions |
| 7 | Install hardware (locks, handles, window locks) and check operation |
| 8 | Install mosquito screens on sliding windows |
19.6 Interior Decoration Installation Process
| Step | Procedure |
| —— | ———– |
| 1 | Install floor base panels on bottom-frame secondary beams — screw-fix at ≤ 300mm spacing, gap between panels ≤ 2mm |
| 2 | Seal panel joints and edges with moisture-resistant sealant |
| 3 | Lay PVC floor covering — full adhesive bonding, heat-welded seams |
| 4 | Install cove base around floor perimeter |
| 5 | Install ceiling panels — screw-fix to furring channels/purlins |
| 6 | Install interior partition wall — screw-fix to frame and ceiling/floor channels |
| 7 | Install interior door in partition opening |
| 8 | Install all trim pieces — ensure alignment and clean joints |
19.7 Electrical System Installation Process
| Step | Procedure |
| —— | ———– |
| 1 | Lay power conduits in wall cavities/under floor — separate from data conduits |
| 2 | Pull conductors through conduits, terminate at outlets/switches per circuit diagram |
| 3 | Install outlet boxes, switches, LED lights — flush mount |
| 4 | Install distribution box with RCBOs — test all circuits |
| 5 | Install data network wiring and RJ45 outlets |
| 6 | Connect external supply at outdoor waterproof inlet box |
| 7 | Complete insulation resistance test (≥ 0.5MΩ), RCD trip test at 30mA |
| 8 | Label all circuits at distribution board and outlet locations |
19.8 Plumbing System Installation Process
| Step | Procedure |
| —— | ———– |
| 1 | Lay PPR supply pipes in wall/floor cavities — continuous runs with heat-fusion joints |
| 2 | Install shut-off valve at inlet, connect to external water supply |
| 3 | Install washbasin, faucet, basin waste with trap |
| 4 | Lay PVC-U drain pipes from basin waste and floor drain, slope ≥ 1% toward outlet |
| 5 | Install floor drain with deep-seal trap at washroom area low point |
| 6 | Connect external drain pipe to site drainage system |
| 7 | Pressure test: supply 0.8MPa for 30 min — no pressure drop; visually inspect all joints |
| 8 | Flush system; verify drain flow by full-bore discharge test; check no leaks |
19.9 HVAC Equipment Installation Process
| Step | Procedure |
| —— | ———– |
| 1 | Install outdoor unit on wall bracket or concrete base — vibration-isolating pads |
| 2 | Install indoor unit on wall-mounted hanger — level alignment |
| 3 | Connect refrigerant lines between indoor/outdoor units (brazed, evacuated, pressure-tested) |
| 4 | Connect condensate drain line — sloped toward external discharge |
| 5 | Connect power supply from 16A dedicated circuit |
| 6 | Install exhaust fan in wall opening — seal external perimeter |
| 7 | Conduct system commissioning: cooling/heating mode test, airflow check, condensate drainage test |
19.10 Quality Assurance System & Control Measures
| Level | Control Point | Verification Method |
| ——- | ————— | ——————— |
| Incoming materials | Steel, panels, electrical components | Certificate of quality review; visual inspection |
| In-process (factory) | Welding quality, dimension checks | Per GB 50205-2001; dimensional tolerances per §6.12 |
| Pre-shipment | Full-system function test | Test all circuits, plumbing pressure test, door/window operation |
| Site receiving | Transport damage inspection | Check panels, doors, windows for transport damage |
| Installation stages | Structure, enclosure, MEP | Per §15.6 stage gates — sign-off before move to next stage |
| Final commissioning | Full operational test | Completed checklist; client walkthrough sign-off |
19.11 Safety & Civilized Construction Management
- Safety Training: All installation crew receive site safety induction before work begins.
- PPE Requirement: Hard hats, safety boots, gloves, safety harness (when working at height).
- Crane Operations: Crane operator licenses verified; lifting plan reviewed before operation.
- Electrical Safety: Lock-out/tag-out protocols during electrical connection work.
- Site Cleanliness: Daily site clean-up; material storage organized; no debris left on site.
- Noise Control: Operational noise during installation limited to daytime hours (per local by-laws).
- Emergency Plan: Site first-aid kit, emergency contact list posted at site.
19.12 On-Site Emergency Response Plan
| Emergency Type | Response Procedure |
| —————- | ——————— |
| Minor injury | Administer first aid at site first-aid kit; report to supervisor; if serious — call emergency services |
| Electrical shock | Cut power immediately at distribution board; administer CPR if trained; call emergency services |
| Fire | Cut power; use site extinguisher if safe; evacuate; call fire services |
| Crane accident | Stop all work; secure area; call emergency services; notify project manager |
| Severe weather (typhoon/high wind) | Secure loose panels, tools; evacuate working area; resume only after weather passes and safety check |
—